2026-10-29 - Municipal Facilities Optimization Committee

Summary

  • Minutes: July 9, 2026 approved 4-0; September 9, 2026 approved 3-0 with one abstention. Two Vertex invoices of $2,623 each were approved 4-0.
  • Architect amendment: the HKT Architects mechanical, electrical and plumbing amendment raised the contract from $96,500 to $104,200 (+$7,700), paid from funds already appropriated; approved unanimously.
  • Vice chair: Steve Walsh was elected unanimously (name as heard; not present).
  • DPW South Street facility: the recommended option is a new 29,325 sq ft administration and fleet maintenance building, keeping the existing 32,085 sq ft garage as cold storage and demolishing the water department building. Estimated cost: $26 million base less about $1.1 million in value engineering, plus $6.2 million soft costs, roughly $31.2 million total, against about $46 million for the failed 2025 project. Value engineering included simplified HVAC ($500,000), a smaller generator ($200,000) and a reduced equipment allowance ($150,000); pricing reflects tariffs, diesel at $6.50 and escalation. No formal vote; consensus to take the option to a Select Board workshop, with a committee vote before any formal request.
  • Schedule if approved at town meeting and ballot in May: design resumes then, construction starts at the end of 2027, runs through most of 2028, and closes out in early 2029.
  • Amended from the originally posted October 28 date.

Issues discussed

People

Speakers were heard by first name only (committee chair, project staff, the architect and construction manager teams), so none are linked.

Auto-captions: some terms and names were garbled; the fuel canopy savings item was unclear and is left out.

Agenda

Items as listed above.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:02Good evening. This is the Municipal

00:04Facilities Optimization Committee

00:05meeting October 29th, 2026. We just have

00:09a little preliminary business to get to

00:10before we get to the main part of the

00:14meeting. Um, we have a quorum. So, this

00:15meeting is called to order and we have

00:17the minutes from July 9th and September

00:199th. I think that we can take those as

00:21one item. Um, any questions, concerns on

00:25the meeting minutes?

00:26>> I need to abstain from September. That's

00:27the only

00:28>> Okay. Anything else? Any comments or

00:31questions? No. We have a motion to

00:32approve.

00:34>> Yes.

00:35>> We have a motion and a second to approve

00:37the meeting minutes from July 9th and

00:38September 9th, 2026. All those in favor

00:41signify by saying I. I.

00:43>> Opposed? So voted.

00:464 July and 3 to zero for September with

00:51one abstension.

00:53Okay. We have a couple bills to pay. We

00:56have Vertex

00:57Company again. And I think we can take

00:59these as one item. Fertex companies for

01:02dated 8:31 2026 and 9:30 2026 both in

01:07the amount of $2,623.

01:10Any questions on those bills?

01:14There being none, do we have a motion to

01:16approve?

01:18>> Second. We have a motion and a second to

01:20approve the the uh bills for Vert.Ex

01:22Company 8312026

01:25and 9:30 2026

01:27for the amount of $2,623

01:30each. All those in favor signify by

01:32saying I

01:34>> I opposed. So voted unanimously four to

01:37zero.

01:38>> Item number four, review and act to

01:41authorize an amendment to the agreement

01:42with HKT architects for additional MEP

01:45services.

01:47John, do you want to talk that through?

01:49>> Sure. Um, we have uh we originally got a

01:54proposal from HKT, as you're aware, to

01:57uh extend uh the work on the project.

01:59And that initial proposal was for

02:01$96,500.

02:03And what ended up happening subsequently

02:06is we said, "Hey, um there was some

02:10discussion about the MEP systems, right?

02:12And how much we should uh how much we

02:15should include or not include for the

02:18MEP. Um the MEP had not been included in

02:21the original uh in the original

02:23amendment. Um so that the final the the

02:26965 increased to and I sent you the

02:30wrong one, Keith.

02:32One second here.

02:36The full final amount instead of 96,500

02:41increased to

02:46104200.

02:49So an additional

02:54>> not going to

02:55>> 77

02:56>> 7700

03:00>> correct. So, an additional 7,700 to

03:03HKT's contract. So, um would be looking

03:06just to get that that additional amount

03:09um increased

03:11or that total amount increased to cover

03:13the 7700 total.

03:19>> I just have one question.

03:20>> Sure.

03:21>> Was that the 7,700 included in that

03:24first allocation that we did at town

03:26meeting?

03:27>> Yes, this all all the funds are within

03:29Okay. So much they've been appropriated.

03:31Yep.

03:31>> Okay.

03:31>> Yep.

03:32>> Yep.

03:32>> That's all I need to know.

03:35>> Anything else?

03:36>> So, with that approval, we'll get the

03:37amendment to to the town for signature.

03:40>> Sure.

03:40>> Sure.

03:42Any other questions, discussion? Do we

03:44have a motion

03:46to approve

03:49to amend the agreement with HKT

03:51architects for additional MEP services

03:54from 96,500

03:56to $104,200?

04:03>> Motion to approve.

04:05>> We have a motion. Do we have a second?

04:07>> Okay. All those in favor signify by

04:08saying I. I. Opposed. So voted

04:11unanimously. Thank you everybody.

04:14>> Thank you.

04:15>> And item number five, we have gone two

04:17meetings now without a vice chair.

04:20Fortunately, the chair has been here,

04:23but I think it's time to elect a vice

04:25chair.

04:26Um, so I have spoken Steve Walsh reach

04:30when he heard about this Steve Walsh

04:31reached out to me and he's interested in

04:32filling that role. So I would like to

04:35nominate him to be the vice chair. Do we

04:39have any other nominations to consider?

04:42deep.

04:43>> No.

04:44>> Any discussion around that?

04:48>> There being none, do we have a motion to

04:51select Steve Walsh as the vice chair for

04:54the mun municipal facilities

04:55optimization committee?

04:57>> So moved.

04:58>> Second.

04:59>> Second.

05:00>> All those in favor signify by saying I.

05:03I. So voted unanimously.

05:05Congratulations, Steve, if you're

05:06listening. [laughter]

05:09Item number six, we have an update from

05:12the design designer architect.

05:14>> Who is taking that?

05:15>> Is me.

05:16>> All right.

05:17>> And there's really not a lot to update.

05:19We've basically been on kind of a

05:21holding pattern while we've been going

05:22through the cost estimate for the

05:24redesign facility and working with

05:27Fontaine Brothers to go through the PE

05:29options and to analyze how we can reduce

05:31the cost from the initial estimate that

05:34was done on the redesign.

05:36Any questions around that?

05:38>> No, I just want to say that um you know

05:41the project team obviously has done a

05:42ton of work over the summer. Um our

05:46staffs have been involved also with

05:48them. Um estimates were done initial

05:51estimates were done last week or so. Um,

05:54and I would I will tell you that in the

05:56past six or seven working days, there's

05:59been a ton of work by this team um to

06:01really dive into the VE um and reducing

06:06the cost of the project. Um, and when we

06:10get into this the, you know, the next

06:13presentation here, you'll see all the

06:14work that was done to get us where we're

06:17at.

06:19>> Okay,

06:20any questions? Any other questions,

06:22comments?

06:24concerns. There being none, we'll move

06:26on. Item number seven, we have an update

06:29from the construction manager. Who's

06:30going to take that?

06:31>> I'll take you guys through the

06:33>> All right, John.

06:34>> Um, with some side commentary by

06:37Fontaine as we go.

06:38>> Okay. Um so if you direct your attention

06:41to the presentation I believe it was in

06:44your folders but um this what we wanted

06:46to do is basically very high level of

06:50the chronology of the project and then

06:52the summary of the costs and where those

06:56have played out uh some things that have

06:58impacted those some things we're looking

07:00at to try and offset those and then

07:02ultimately move you know provide a

07:05recommendation for the you know the most

07:07cost-effective solution that still helps

07:10address some of the issues at the DPW

07:13that we have today. Um, next slide,

07:15please. So, a little bit for the

07:17timeline. Um, taking you through very,

07:19you know, for anybody who's just picking

07:21this up for the first time. As you may

07:23or may not be aware, in 2024, there was

07:26the initial push with this project. Um,

07:28moved forward with a different architect

07:30for a project that was an addition

07:32renovation. It was basically a new

07:35administrative building tied to the

07:37existing DPW garage, but literally tied

07:40to it. So, new construction um tied to

07:42the existing building. Um that design

07:45got through schematic through schematic.

07:48Um and after schematic, the decision was

07:50made by the town to move ahead with a

07:53new designer. um the initial designer,

07:56the contract wasn't renewed,

07:58uh brought HKT in to um to to develop

08:01that design and help us get to the 2024

08:05town meeting and ballot votes. Um they

08:08did that. Um we had numbers, went to the

08:10town meeting, passed a town meeting, but

08:12failed at the ballot. So after that that

08:15initial um stoppage of the project

08:18really a lot of time went by and you

08:20know there had been work going on behind

08:22the scenes you know in town hall to try

08:24to figure out what to do next and in the

08:26spring of 26 the committee came back

08:29Keith came back to us and said okay we

08:31want to look at using the remaining

08:33funding to try to come up with a new

08:35approach for the project. Um what then

08:38happened was a design cheret across the

08:40way in the select board chambers really

08:42was HKT Fontaine Vertex and the town

08:46really trying to rethink

08:48the approach of the project again when

08:51HKT first came in they were really

08:52taking that initial design and trying to

08:54figure out okay what can we do with that

08:56instead rethought it and said you know

08:58what there's a way to do this you know

09:00let's go with two new buildings don't

09:03reuse anything and again there had been

09:05some looking at the you know a relook at

09:08the existing buildings and saying look

09:09there you know especially the water

09:11department building nothing there to

09:14save but let's you know let's let's do

09:16an approach where we you know redo the

09:18whole thing um next slide Keith the SD

09:22for that was completed for pricing and

09:24that first pricing that came in was was

09:27higher than expected so what can we do

09:30all right so let's still go with two

09:32separate buildings we'll do a new

09:34administration building but then

09:36renovate the existing DPW garage really

09:40um roof systems that sort of thing and

09:44look and see what happens. Uh in

09:46addition to that the team worked on

09:48[clears throat] a series of value

09:49engineering

09:51um value engineering items to try and

09:54pull that pricing down as well and give

09:57some relief valves. That pricing came

10:00back still what the folks felt was too

10:03high. So, we said, "Okay, final pivot

10:06here. Let's go with the new

10:08administration building and fleet

10:09maintenance and do zero work on the

10:12existing DPW garage. Truly use the

10:15existing building just for uh for

10:18storage. There would still be the need

10:20potentially for a roof on that building,

10:22but we can address that roof either out

10:24of contingency for the project or

10:27ultimately for out of the a capital

10:29budget from the town at some point down

10:31the way." And that was the

10:33recommendation that we bring to you

10:35tonight. A little bit about the costs.

10:39Um, basically what we did is tried to

10:41show you the four different iterations

10:43of the building. Oh, my little macros

10:46didn't pop up in Google. Um, the top

10:49building, the top item is a new and a

10:52rena. The allnew project is two would

10:56have been two new buildings. The green

10:59box talks about a new and a a rena. And

11:03the final box in blue at the bottom is

11:06just one new building, no renovation at

11:08all. Um pricing [clears throat] of the

11:11initial project from that failed was

11:14escalated forward to the same time

11:16period as now. So if you look back and

11:18go, wait a minute, that wasn't the

11:19number we voted on. No, it wasn't. What

11:21we did is brought it forward so that

11:22we're comparing four options to today.

11:26And again, the gray one isn't even on

11:27the table, but it's there for reference.

11:30Um, pricing includes current market

11:33conditions as they're known today. So,

11:35things that we know about for tariffs

11:37and all the news you've heard about

11:38that, $6.50 diesel is included in all of

11:43that, as well as escalation, moving

11:45moving that forward. And then, as

11:48applicable, we've got the VE taken out

11:50of this as well. So you heard me mention

11:53one and a half million for VE if and

11:56then in the suggested option at the

11:58bottom only 1.1 the difference is

12:00because 400,000 of that VE was suggested

12:04to the scope of a building we aren't

12:06doing anymore right so we would it's not

12:08one a.5 million of ve it's only 1.1 so

12:12the approach we took for this was the

12:14construction numbers all came from

12:15Fontaine and there's some very detailed

12:17backup for all of those subtract the VE

12:21and then add soft costs. Right? So at

12:23this point you know rather you know

12:25again with a design that is only you

12:27know is just inching its way towards you

12:30know schematic at this point for soft

12:32costs the cost for the designer for the

12:34OPM for furniture fixtures equipment and

12:37contingency we are just using a

12:39multiplier. Um, the reason why the

12:42multipliers are different is that you'll

12:44notice that in each of those options, we

12:46use 30% when there's a renovation

12:48involved and 25% when there is a a new

12:52project. The reason for that is is

12:55included in that 30% is a 10%

12:58contingency for unknowns on when you

13:01have a uh a building that you're

13:03renovating and only 5% when it's new.

13:06when it's a newer building, there's less

13:08problems, there's less surprises because

13:10you're just literally just scraping the

13:12old building and taking it down. So you

13:14it's it's you don't need to carry as

13:16much contingency. So basically that, you

13:19know, we're looking at a project right

13:21now that is a 26 million base

13:24construction cost minus a million inve

13:27gets you to 25. Uh soft costs of 6.2.

13:32Those added together is a roughly a

13:34$31.2 2 million project.

13:38Next slide, Keith.

13:40>> I know you can't see this. Um, we can

13:42pull up some VE logs, but some of the,

13:46you know, some of the items that we're

13:48talking about, you know, in the 1.1

13:50million dollar savings in VE, you had um

13:53some grading um grading associated with

13:56the recycling center for a couple

13:58hundred thousand, removing the fuel

14:01station canopy for 100,000, reducing the

14:04equipment allowance [clears throat]

14:05um built into the construction contract

14:07for 150,000. Remove the high density

14:11storage for 60,000.

14:13Simplify the HVAC in the fleet

14:15maintenance building for half a million

14:17dollars. Replacing vehicular concrete

14:20aprons at overhead doors with HDMA

14:2325,000.

14:25Downsize the generator and utilize the

14:27existing generator to provide power for

14:29the existing DPW building and reducing

14:32the generator size from 750 kows to 400.

14:36That's a $200,000 savings. and then

14:38removing the brine tank utilities from

14:40the project of another 23,000. So in

14:43discussing all of those with Keith and

14:45Keith with his staff, that is the

14:47savings of of 1.1 million. Now you say

14:51YveV, the reality is is that when the

14:53pricing came in, there wasn't time to

14:55change the design to then do an estimate

14:58that reflected the outcome, you know,

15:00the incorporation of that VE into the

15:03design yet. So with a yes, that's where

15:05we go forward. We won't talk about VE

15:08anymore. We'll incorporate those

15:09changes, have a new baseline of the $25

15:14million project, and if as the project

15:16proceeds, we hit, you know, oh wait,

15:19costs have gone up again, we'd have to

15:22ve other things, right? But at this

15:24point, we would accept the stuff that's

15:26in here and move ahead with with that

15:28project. Um

15:31so the rec next like the recommended

15:33solution um construct the new

15:36administration building the existing DPW

15:39garage excuse me becomes cold storage.

15:41No additional work on the building at

15:43this time and you can the the plan

15:47reflects the new building. The red

15:49rectangle is really what's there right

15:52now. So that would stay. And again, as I

15:54mentioned earlier, we'd contemplate roof

15:56replacement on the existing garage

15:58either as part of bid savings if

16:00successful or a future DPW capital

16:03budget item. Neither, you know, does

16:04neither item that either approach

16:07doesn't need to be discussed now. But

16:09the the point is, you know, the it's a

16:12do nothing solution for the uh existing

16:15DPW garage as of today.

16:18>> So, I will stop and

16:20>> there was one there was one more slide

16:22about schedule too. Sorry.

16:23>> It's okay.

16:24>> Thank you. Uh schedule. What does that

16:26do to our schedule? So again, all of

16:29this discussion tonight is in

16:31preparation for presentation to select

16:34board and getting this project hopefully

16:37on in front of uh the voters in May. If

16:42with a successful town meeting and

16:44ballot vote in May, we jump right back

16:46into

16:48um you know pre precon and design,

16:51right? I mean the project isn't designed

16:53yet with the goal of moving forward um

16:56with construction at the end of 27. And

17:00just to be clear, one of the things, you

17:02know, how does the cost drop? You know,

17:04we were using conventional construction

17:06originally and moved towards all

17:08pre-fabricated metal buildings um for

17:11the project um for the admin building.

17:14So, you know, even those prefab metal

17:17buildings, those costs have gone up as

17:19well. So we saved by going with that

17:22type of pre-engineered construction but

17:25yet even that as a building block has

17:28increased in cost. So um so again to be

17:31clear the admin building is not you know

17:35fully stick built from the ground up. It

17:37is it is built with a pre-engineered

17:38system. Um very typical for lots of DPW

17:43facilities and other municipal utility

17:46facilities these days. that that would

17:48be the uh framework framework of that

17:50building. So, we'd be looking at

17:52construction through the majority of

17:542028

17:56um with a close out and turnover in the

17:58beginning the beginning of 29.

18:02Now, I'll turn it over to you for

18:04questions.

18:04>> Questions?

18:05>> You didn't Sorry. Go ahead.

18:06>> Go ahead. Go ahead.

18:07>> So, you didn't mention about the seaw

18:08water bes

18:10can see what will do with the sea and

18:13water building. Um, so the the the water

18:17building would come down. Like that's

18:19that building goes, the existing garage

18:22stays of the two buildings. I think it's

18:24pretty clear that the garage is in

18:26better shape than the than the water

18:28department building. So um so yeah, that

18:31and we would need to get rid of that to

18:32build the to build the new the new

18:34admin.

18:35>> And what are the like connection between

18:37the admin admin and the DPW? They're

18:40going to connect no connection. So, as

18:43you can see right here, just as the um

18:46in the last presentation, they would be

18:48two separate buildings. They would

18:49remain two separate buildings. Um the

18:52front left, that's the recycling center.

18:55The new building is at the top of the

18:57top of the picture with the the black

19:00that's highlighted is aprons, right? Um

19:02outside of the building. Similarly, the

19:05existing U garage, which is the red

19:08rectangle, that is what stay would stay.

19:11Obviously the design HKT really this

19:14happened in the last as Keith said in

19:16the last seven days. We've done a all of

19:18this kind of back and forth. So the site

19:21hasn't been you know finalized yet. This

19:24is still very even it's less than

19:27schematic right now really. the the new

19:30admin building is in good shape

19:31schematic wise, but the site would needs

19:34a you know needs another look at um a

19:38hard look at to see about traffic flow

19:40and parking and all of those things

19:42which you know had been set into a new

19:44had been moving forward in a new design

19:46which now um isn't you know we would

19:50suggest isn't on the table at this time

19:52>> and if I would suggest too right so

19:56reducing it to the one building work

19:58still needs all of our program needs.

20:00Like we still have the administrative

20:02space to move all of our staff there. Um

20:05we still will have the new fleet

20:07maintenance area. Um then shops for all

20:09of the individual departments in that

20:11administration building. We still have

20:12our large um conference area that we can

20:17still use for voting. U those sort of

20:19things. So, very little has changed on

20:21the administration building um

20:25uh since the last uh presentation other

20:29than some of the PE items that we've

20:30changed like originally the whole

20:32building was air conditioned. Uh we

20:34removed the air conditioning from the

20:36entire um shop and fleet maintenance

20:39area. That's a half a million dollar

20:41savings that was in the VE items. Um so

20:45that was one I one piece and that

20:46literally you know we would um we we

20:50feel that the current DPW building

20:53although it's you know 50 years old we

20:56we still believe it's um in good enough

20:59condition that we can continue to use

21:00that for cold for cold storage. Um it

21:03has a lot of good equipment in it. So, a

21:05lot of the equipment and fixtures like

21:07the truck lifts, compressors, things

21:09like that, we can relocate to um the

21:12administration building or the new

21:14building, which is why we also reduce

21:16the FFN for some of the

21:18>> [snorts]

21:18>> um equipment and and in throughout the

21:21budget. So, a lot of stuff we've talked

21:23through. um it still meets our program

21:26you know it's not all new but we also I

21:28also think or we think that [snorts] um

21:31it's you know closer to a number that

21:34the community can u get behind us on

21:38>> so what is actually you change like when

21:40you came in the July June or July that

21:43time

21:44>> and that time like you came the the same

21:46size what is the that size of this

21:48building right now so what actually we

21:50are g gaining what we are basically

21:53missing Yeah.

21:54>> So, great question. So, the admin

21:56building remains at

22:00uh the new admin building remains at

22:0229,325

22:05square ft and the

22:10uh

22:12existing DPW garage is 32,085.

22:20So that difference compared to the two

22:23new buildings is a to it's a total

22:25difference of when we came here before

22:28it was 64,633

22:31and now we're down to 61,410.

22:38So we've lost 3200 square ft in program

22:42size,

22:44but the admin building remains the same.

22:47The loss is in the the difference

22:49between the red rectangle and the

22:51square, right? So that you you've lost

22:53that square footage in what would have

22:54been a new garage that would have been

22:563,000 square feet bigger.

23:01>> And optimized for vehicle

23:03[clears throat] storage,

23:04>> right? Right. Your existing garage isn't

23:07optimized. you're going to, you know,

23:09whereas the new garage you would pull in

23:11and have nicely aligned spaces, it's

23:13going to be more, hey, move this in,

23:15move this out. We don't need this piece

23:18of equipment, bury it in the back.

23:19Right? There'll be more um hopscotching

23:22that the staff will have to do to make

23:24that to make the existing building work

23:26for indoor storage.

23:28>> Is there room for all the vehicles?

23:31>> No. No.

23:32>> No. Um, we'll we'll be we we will be

23:35close, but the way the the way the

23:37highway garage is configured now. Um,

23:40there would definitely be some jockeying

23:42to get um all the equipment in there, I

23:45don't think we could. um we would have

23:48to live with some equipment probably

23:50being outside and maybe that would be

23:52something that we use less or older

23:54equipment um or not emergency vehicles

23:58that we

23:59>> Mhm.

23:59>> you know

24:00>> and with with that is there is there a

24:03plan to remove the office areas to

24:05increase the storage?

24:07>> Well, we could only do that with if

24:09funds allowed throughout the project. So

24:11if we if we

24:14came into bid savings then and and we

24:17could have I think our first priority

24:19for that building would be put a roof on

24:20it.

24:21>> Um and then if there was any

24:23opportunities to remove a wall here or

24:25there then we would consider that but um

24:28at this time that's not on the table.

24:31>> Okay.

24:33The hope I think is that with the moving

24:35forward

24:37as we you know with if the citizenry

24:40says yeah go for it is that in the time

24:43that this thing is designed

24:45>> hopefully you know gas doesn't stay

24:48diesel doesn't like the reality is is

24:50that you've got a bunch of site work

24:52site work runs on diesel everything that

24:54gets shipped here comes on diesel

24:55anything plastic has petroleum in it so

24:58you're really seeing a bit of a a bump

25:01right now you

25:02um you know construction costs and

25:05tariffs, you know, who knows what's

25:07going to happen with those, but the

25:08market is reflecting those right now. So

25:11if you say how much the it's really hard

25:13to pull that apart, right? Because you

25:16don't have a completed design right now.

25:18When these guys go to market, they're

25:19going to market with a square footage.

25:21Yeah. And an idea, right? And someone is

25:23saying, "Okay, if you can't show me more

25:25much more than an idea, here's my

25:28price." Right. So, you know, I feel good

25:31that we have a CM because we're not

25:33doing this with a third party estimator.

25:35We're doing this with people who are

25:36picking up the phone and doing this

25:37every day. But even those prefab metal

25:40buildings, these guys are building with

25:42those right now for EastN's DPW and

25:45they're talking to that vendor and it's

25:46that vendor that's giving them the

25:47pricing.

25:48>> And that vendor is saying, "No, those

25:50prices you bought that ad have gone have

25:53gone up."

25:54>> So, any we can't speak to what will go

25:56up and what will come down, right? We

25:58just can speak to this [clears throat]

25:59is where we are right now. And if we

26:01hold those numbers and say nothing else

26:03changes, we take those numbers and we

26:06escalate those up to okay a year from

26:08now when we bid and somebody holding

26:11that number through halfway through

26:12construction. And so that's what

26:14Fontaine has covered in these numbers.

26:16>> Okay.

26:17>> Very good. So there any probability to

26:20reduce the so cost because you don't

26:22know like after 6 months after the

26:24election like D the price can go down

26:26all those [clears throat] it c there

26:29certainly could be changes and listen we

26:31would all hope that there would be right

26:33could also go the other way right so I

26:35think the idea is to give if the if the

26:39committee supports it to give Keith

26:41enough information to say look we looked

26:43at this thing now four different ways

26:46this is clearly the most cost it's it's

26:49the most cost-effective solution to deal

26:52with fleet maintenance to deal with

26:54administration

26:56but we won't you know the reality is is

26:58because of the funding that was left

27:00there's not much more work this group

27:01can do between now and town meeting you

27:05know can they do can we look at taking

27:07the design and you know a little bit

27:09more sight to understand you know how

27:12traffic flows and things like that sure

27:14but at the end of the day we've gotten

27:17kind of to we're almost as far as we can

27:19go. Maybe there's a little more we can

27:21do if there's any remaining funds but

27:23not enough to advance the design far

27:25enough to say,

27:28you know, here this is a significant

27:30change that could drop this number. I

27:32think we've cut the program that we can

27:34at this point by going with the existing

27:37building. Um, as you can see the design

27:40from HKT, it's a pretty simple rectangle

27:44at this point. you know, one little bump

27:46out on one end. Um,

27:49you know, I can't I don't know if you

27:51guys any any thoughts on it's a pretty

27:54utilitarian kind of approach at this

27:56point.

27:57>> Yeah, it's pretty um pretty simple

27:59layout for as far as the admin and um

28:02but we would challenge that too to the

28:04next next level as we're going through

28:06things. Is there pushes and pulls that

28:08can make it even more cost effective?

28:11I guess yeah to that end right we would

28:13continue with an approved project it's

28:17still the goal of this I believe this

28:19committee to do it as cost-effectively

28:21as possible right so if we you know if

28:24this if the town says yes you would then

28:27do another estimate when that SD design

28:30gets design development and you might

28:32even do one more design as that design

28:34development set gets to construction

28:36documents so another two stopping points

28:38in that subsequent

28:42[snorts] seven to nine months after town

28:45meeting to say, "Okay, are we still are

28:47we holding? Are we holding?" And if

28:48we're saving, hey, great. Like, that's

28:50that's great news. And that's just money

28:52you don't have to borrow. This approach

28:54here for this project now is much more

28:56like what you would have to do for an

28:58MSBA school project. it is asking for a

29:01commitment to the number when it's just

29:04at SD and then having to live within

29:06that number for the next, you know, for

29:09the next year of design and the actual

29:11bidding and then for the year year and a

29:13half of construction. You know, when

29:15you're doing that with MSBA, you're

29:16committing for a school number for the

29:18coming four to five years, right? So,

29:20it's it's really the same approach um

29:23based [clears throat] on the the cards

29:25we're dealt right now and the funds

29:26available and where we are and and town

29:29meeting timing.

29:31>> So, with this new proposal of just

29:34keeping the old DPW building, where's I

29:37think I recall fleet going to the very

29:40right side or eastern side of the new

29:42building.

29:42>> Yeah, correct.

29:43>> So, does fleet remain in the

29:45>> fleet will still going to be moved?

29:46still move

29:47>> and there'll be extra space for

29:49>> correct

29:50garages there like those three bays.

29:52>> Okay. um there and I think you know the

29:55the

29:56like I said that building is a

29:58pre-engineered building and if like I

29:59said if there's savings you know um in

30:03the future you know maybe there's an

30:04opportunity to take a wall down and

30:06>> yeah one or two walls in those areas

30:09>> and look and I think we can certainly

30:10come back to you all with you know after

30:15the elections and in the spring as we're

30:17getting you know it's not like we're not

30:19going to talk to you between now and

30:20town meeting right if if we're seeing

30:22things in the market, you know, that's

30:24why we have a CM on board to say, hey,

30:26guess what? We have started to see some

30:28relief in the pricing for such and such.

30:31But for the discussions that need to

30:33take place now to get this on the, you

30:35know, to get this on the warrant or

30:39consideration for a warrant, these are

30:41the numbers we're at. But that doesn't

30:43mean that that couldn't shift between

30:46now and, you know, now and coming up to

30:48town meeting. So which one you are

30:50suggesting the construction code cost

30:52can reduce or like sub cost can reduce

30:56which are talking about the entire

30:58construction cost will be bid out like

31:01to subcontractors

31:03a year and a half from now or two years

31:05from now. So none of those construction

31:07costs are committed to any contractors.

31:09They're just our current estimate based

31:11on market conditions of what we believe

31:13the cost will be based on input. But

31:15each one of the subtrades bid will bring

31:18the bids to the you know the group and

31:20we'll choose the lowest responsible

31:22biders. So that whole number gets

31:23assembled as the design gets progressed

31:26so that the biders can give their most

31:28competitive pricing based on the

31:29finalized design. So all those costs are

31:32able to you know basically be at market

31:36at the time that we're able to buy them.

31:39>> Okay. So the design at this point like

31:42the the idea you came with those two

31:45building looking good but still the

31:48price wise little higher side. So as I

31:51think

31:53>> yeah at this point you're cutting square

31:54footage. So if you if the price needs to

31:57come down you're taking away bays or

31:59you're taking away office space and

32:01there's people who can't be in that

32:02building. So this committee needs to

32:04make a recommendation based on

32:07you know the market the pricing is where

32:10it is right now and yeah it's reflecting

32:12some stressors on the market right now.

32:15Um

32:16the only way to make that number go

32:18lower

32:19>> the space what you both side like how

32:21much you can help in the soft cost or

32:23construction code

32:25>> if because you guys getting the project

32:27so well again the soft costs at this

32:30point are just it's a factor right now

32:32it's it's 25%

32:33>> I wouldn't go lower at this point I'm

32:34not going to go lower than 25% and

32:36that's not me that's just if if me is an

32:38OPM to you a job at this point I would

32:41not in the end do costs end up coming in

32:44around. Could they come in at 22 or 23%.

32:48Sure. I'm not going to cut it to 22 or

32:5023% now because we don't know in that

32:53number, as an example, is 4% for

32:55equipment. The cost of, as an example,

32:58anything we need that's a computer right

33:00now. I just authorized a server at a

33:03town on the Southshore that a year and a

33:06half ago was 50,000. It was $125,000

33:10to buy that server. So those decisions

33:13about what else is in the building were

33:16not far enough yet, right? So to be able

33:19to say, "Yeah, look, I can think those

33:21soft costs can come in at 24%." Right?

33:24None of that is bought. That includes

33:26their fees, our fees, our fees are tied

33:29to duration, you know, okay, we think we

33:31know what the duration is, FFNE, and

33:33also then contingency, right? uh that

33:35money that if you need it, you know, you

33:39know, you you have it there to spend.

33:41The last thing I want to do before we

33:43even have a project that's approved is

33:46to say, okay, we can carry a 4%

33:48contingency because that 1% it's real

33:52money. So, you know, I think the the

33:55committee has to know that the team is

33:57committed to, you know, look at we've

34:01seen this go from a se 60s something,000

34:04square foot all all new program down to

34:0829,000 square feet, you know, and if if

34:12we can do it more cost-effectively,

34:15you know, we're going to do it. And

34:16that's what, you know, to Shane's point,

34:18we continue to test and ask questions

34:21right along the way to see if we're

34:22doing it as as economically as possible.

34:25But for right now, you know, that number

34:28is at at 31.2 million. If you wanted to

34:31round it to 31, that's it. I can't I

34:35can't suggest anything

34:38rounder or more than that because we're

34:40just we don't have enough detail to base

34:43it on yet. We're just throwing darts,

34:45you know, we're just throwing darts at

34:47things otherwise. So, you know, if 31

34:50>> Do you want to speak to like the makeup?

34:52You know, the vast majority of the

34:53number obviously is in the construction

34:55side of things. Shane and Ryan are

34:57deeply involved in how we put it

34:59together and

35:00>> our our fees as the builder like within

35:03that number are essentially fixed. Like

35:05we have percentages for our insurance,

35:07our fees. So talk about how the number

35:08is constructed and how we'll make sure

35:10that that number ultimately is as

35:12competitive as it can be.

35:14>> Yeah. So I when based on the original

35:17design, we went out to market and got

35:18feedback from subcontractors based on

35:21what they're seeing for pricing on all

35:23of this stuff. That's fed into the

35:24direct costs that we that we have.

35:28Also built into that construction cost

35:30um is a 10% design contingency which at

35:33the stage of the project right now

35:35there's a lot to be worked through those

35:36details um as well as a 6 and a half%

35:39escalation

35:41um from now till um the project start or

35:44halfway through construction um looking

35:47at it as a 4 and a half% escalation um

35:50you're over

35:52um

35:54>> so if the escalation if the market

35:56conditions improve

35:57>> Yep. you know that number will happen.

35:59>> The important thing to understand with

36:01the way that this contract will be

36:03procured is we're essentially acting as

36:05like your agent to procure all those

36:07subtrades. So the negotiations with the

36:10subs of, you know, hey, three concrete

36:12bids and how do we make sure we get the

36:14best one and can we get a best and final

36:16to get some savings like those would all

36:18happen post vote and we'd essentially be

36:21you know conducting those transparently

36:24on behalf of the town to drive down

36:26costs as much as possible will work. No,

36:28I understand because all of you are

36:30working for a long time with us and uh

36:33you can see if you get you getting this

36:35project you are going to for two years

36:37like how many year going to complete?

36:38Two year almost two year right?

36:40>> Mhm.

36:40>> Yeah. It's it's it'll be

36:41>> two year you are getting the two years.

36:43Yeah. Project getting the job

36:45everywhere. So we have to come up with

36:48some right number so that way we can

36:51work it and

36:52>> down also this way if you reduce the

36:54good price whatever that you can do it.

36:57M

36:58>> uh that way you can get the project that

36:59why it will go in the there in the town

37:01meeting it pass and then go to the town

37:04resident they will say no

37:06>> and I we don't want to second time to

37:08happen like that

37:09>> so you guys to help us to get a good

37:13amount number so that way we can easily

37:15say and we can say residents this is the

37:17right number and this is the size we are

37:19getting and u some you know sometime you

37:23are not getting the bigger number but

37:25you still getting the some profit or

37:26some because All of you I know working

37:28I'm a businessman too. I understand

37:30without proper no one work but uh still

37:33uh

37:35think like this way.

37:36>> Oh we totally are

37:37>> because otherwise at the last time if

37:39you have good number something you will

37:41get the project and now you have to

37:43complete it%.

37:44>> I think it's important to note too that

37:46what

37:47>> that the number that

37:50>> go sorry

37:53>> no I'm sorry John.

37:54>> No it's okay. No no no. So looking at

37:56the blue down below, I think it's

37:58important to note that the you know

38:00something like contingency what we're

38:03again we are asking for you know what

38:05the MFA will ultimately be asking for

38:08the select board is to support a warrant

38:10article that goes in and says this is

38:14the most we will spend. You aren't

38:16committing to spending that right now.

38:18you are committing to spending

38:22um you know again an a you know an

38:25amendment for these guys for

38:26pre-construction an amendment to get

38:28started for to to develop the design for

38:31us to walk that through you're not to

38:33Dave's point you're not buying

38:34construction for a year from now and

38:36when we do hopefully the market

38:38conditions will improve and if they

38:40haven't in that year we will have had

38:42many meetings in this room to figure out

38:45okay what are the relief valves you know

38:48that we can do to help to help drop that

38:51drop that price. Um I think you know to

38:55the earlier comments like at this point

38:58you've really you've driven that program

39:01down to a point where below this you are

39:05now not you're already not getting some

39:07storage. Keith can work with the storage

39:10and the team can work with the storage.

39:12If you go below the 29,000 you're really

39:15starting to car stuff up. I think that

39:18what we what we hope is that we see some

39:21relief in the marketplace. We see the

39:24pricing of prefab metal buildings coming

39:26down. To your point, we could start

39:28seeing changes as early as next week,

39:31depending on what happens election wise.

39:33Who knows, right? So far, all the tariff

39:35stuff that we've talked about for years,

39:39we haven't paid one on a job yet, right?

39:41That doesn't mean it won't eventually

39:43they won't start to stick but the market

39:46is reflecting that those are there right

39:47now and you know we have to we have to

39:51share th that with you and you know

39:53acknowledge [clears throat] that it's

39:54part it's part of the job. I mean we all

39:57expected I think to see pricing that

40:00would have been lower than this and in

40:02the last few months it has really it's

40:05really taken a turn in the wrong

40:06direction for right now. Doesn't mean it

40:08can't go back the other way but I mean

40:10and I don't know if Yeah, I just wanted

40:12to say, you know, Anad, like I I don't

40:14disagree with you, right? Like we we we

40:16worked really hard to make sure that

40:18what we're bringing to the residents is

40:20the best value for the project. Um like

40:24I can't stress enough how much work

40:26these people have put in for us to get

40:28there. Um, but also to your point, like

40:32I don't we we don't want to bring them a

40:34low number just to bring them a low

40:35number and then not be able to do the

40:37project because if you recall that is

40:39somewhat what happened the first time

40:41around, right? We came in with an

40:43estimate that was low and then it turned

40:44then we brought our construction manager

40:45on and said no no no this is the real

40:47number and that didn't work well at all.

40:50So, we worked really hard to try to to

40:54really dive in and make sure that we're

40:56giving the community the best we could

40:58possibly get because we don't want we

41:00certainly DPW certainly does not want

41:01this to fail and I know this committee

41:03doesn't want it to fail either. Um, but

41:05I think it it would be [clears throat]

41:06very hard for us to go in front of the

41:09board or in front of the town and

41:12[clears throat]

41:13and and say we'll get you a lower

41:15number. Um, but I am also confident that

41:18this team, if it does move forward, is

41:20going to work really hard to make to to

41:23to help us with that. And Fontaine has

41:26done that for us on the past at least

41:29the past three projects that they've

41:30worked on with us between the library,

41:33be school, and the police station. Um,

41:36they they've always um done a good job

41:38for us and, you know, we've had

41:41significant return on our money to the

41:43point where we didn't have to borrow. So

41:45that's why I'm saying that we have a

41:46pretty good relation being the so many

41:48project and the future project also

41:49coming.

41:50>> Uh but sometime you know one project you

41:53are not getting but you definitely have

41:55other project where you have more

41:56chances to because your reputation your

41:59work your quality your connection which

42:01you are building with us. Mhm.

42:03>> So on that basis still I'm saying like

42:06there some number is little high uh

42:08maybe you can reduce some uh

42:12[clears throat]

42:12>> yeah I in us putting this number

42:14together

42:17the like the fontine control portions of

42:20this um were essentially like procured

42:24in a competitive environment when we

42:26went through the process in the first

42:27place. I don't recall where the fe

42:28proposals were, but I believe we're, you

42:30know, competitive. We're less than than

42:32others in the market. And I think that

42:36um we also can control and I think that

42:39we've reduced our our staffing

42:41associated with this by bringing the

42:43duration down. So there have been

42:45savings that are baked into this number.

42:47Um and absolutely and from our

42:49perspective you know town's been an

42:50awesome partner for us and we recognize

42:52that the only way you know that this

42:55project moves forward and becomes a

42:56project for us that we generate any fee

42:59on is if it's you know able to be

43:01supported successful and when we're

43:03presenting this number it will all be

43:05shaken out and procured later the

43:07contingency will be well managed we

43:09return money at the end of each of these

43:10projects in town and I think to Keith's

43:13point what we want to make sure we

43:15balance is being able to deliver a

43:18number that's going to be the most

43:20competitive so that the the boat can

43:23find support

43:24>> while also making sure that we're

43:26careful that it's a number that with

43:28everything going on in the world we feel

43:30two 3 years from now the project will be

43:32able to be complete within because all

43:34that procurement that needs to happen

43:36for all the subtrades is obviously

43:38outside of our ability to pinpoint and

43:40lock people in right now. Um but we

43:43absolutely you know want to be good

43:44partners to the town and are happy to

43:47you know but we reduce

43:48>> yeah look at one more time like the

43:49number

43:50>> then everything looks good to me all of

43:53us are like we are okay with that but

43:55look at the number one more time

43:57whatever you can uh do on the certain

43:59extent

44:00>> definitely help for town and you will

44:02get more project because you are

44:03building a good reputation people know

44:05that like sometime town doesn't have the

44:07good amount of the money and you are

44:10helping that situation

44:12Y.

44:14>> So from my perspective, what I see here

44:15is we started with a project that failed

44:18in 2025. It's now projected out to $46

44:21million. Through the diligence and the

44:24hard work of the working group and the

44:25committee, we were keeping virtually all

44:29of the programming in this project and

44:31we've reduced the cost by 30 to 33% from

44:3646 to $31 million.

44:39That's to me a good and that's to me a

44:42good number. And I think it would be

44:43shortsighted of this committee and the

44:46working team to go to the select board

44:50or the town meeting with a with a

44:53virtually madeup number that's lower

44:56just to say that it could be passed by

44:58the select board or brought to town

45:00meeting and then we can't deliver on it.

45:02To me, that makes no sense at all. So,

45:05I'm comfortable with the work that's

45:07been done this far, and I'd be happy to

45:09bring that $ 31.2 million forward.

45:13That's my opinion. We've got a, you

45:15know, a one-third reduction in cost with

45:18the same programming. That's not easy to

45:21do in today's world.

45:24>> But I understand, but they are going to

45:25look at one more time and then they can

45:27come up with

45:28>> they constantly look at the numbers.

45:30Listen, I will just tell you that the

45:32the value that we were all brought back

45:34at, we have spent well in excess of the

45:37value of what because of the

45:41relationship. I think

45:42>> he will look at something,

45:43>> right? But we haven't just to be clear,

45:44we haven't even

45:46>> the the point of what's next. We nobody

45:50is contracted for any of that yet. So,

45:52we will absolutely look at all of that.

45:54I'll be looking at their contract. I'll

45:56be looking at their contract. I'll be

45:57looking at our durations. Yes, we will

45:59do that. But we can't do that today to

46:02drop that 312 to a lower number because

46:06if I take it out a little bit of him, a

46:08little bit of her and a little bit of

46:10us, but then the FFN doubles, I'm going

46:13to be coming back to you and saying,

46:14"Well, we we changed the number to 30.5

46:17to do that tonight." But FFN just went

46:20through the roof. So understand that the

46:23the approach of doing this as a group as

46:26a 25% markup is to basically say there

46:30are multiple spokes in the wheel but

46:33we'll contribute to that that we won't

46:35really price until

46:38until May until May of after May of next

46:40year. Right? We'll we'll do more work on

46:43it.

46:43>> All right. And we will yes we will look

46:45at it. We understand our relationship,

46:47but please understand that these guys

46:49just in what they've done in the last

46:51week have done what we asked them to do

46:53once three times already. They've done

46:56three estimates for the price of one.

46:58And there nobody's complaining and

46:59nobody's asking for extra money. They've

47:01got three representatives here tonight.

47:04They are they are a partner of the town

47:07of Shrewsbury and and we'll you know we

47:09will and we will all continue to be.

47:10It's our second job with you. It's their

47:13fourth, fifth. It's a it's a it's a lot,

47:16right? So, we want to see this built. We

47:18don't we don't participate in these

47:20meetings to just get to town meeting and

47:22then have it blow up. We want to

47:24actually build you guys build you

47:26something to help solve problems. That's

47:28the part that we love doing. So, yes, we

47:31will absolutely continue to work on this

47:34and you know, you'll you'll you'll get

47:36our best our best deal. That's you know,

47:39I think that's I think that's pretty

47:40clear from from everyone at the table.

47:43So what would you like when we throw

47:45numbers up the public it gets in Yep. So

47:48is that a GM I saw in the in the

47:51narrative you have this number but then

47:53you say you're going to develop a GMP

47:55later on down the road. Yes. So what

47:57what is this number GMBB?

47:59>> No it's a great question. So if you look

48:00at the construction number right at 261

48:03and you take away the VE let's round

48:05that out at 25 million. Now right now

48:07you we would be looking at a GMP at 25

48:10million or less. Okay,

48:11>> that is the that's the goal here. That

48:13because that's what we're saying. If

48:15we're all telling you this is the number

48:17and we're committing to it, fast forward

48:19to a year and a half from now or even a

48:22little bit more, you would be or excuse

48:24me, a year from now, we'd be looking for

48:27a GMP from these guys at 25 or less

48:30because you will have committed to that

48:32number and the citizens will have voted

48:33it

48:34>> six months from now and then we have to

48:36live with it,

48:37>> you know, for the duration.

48:39>> I understand fully on board. I just want

48:40the public to understand

48:42>> that that that number um you you know

48:45that that this is this project is what

48:47I'm hearing is that won't exceed

48:49>> from this stat this number right here

48:52the GMP won't be higher than 31.

48:54>> Yeah. Look, I I mean what I would say

48:56though is that if 312 is the number,

48:58look, if suddenly the cost of steel went

49:01through the roof and you have to make a

49:02decision to do

49:04>> $400,000 less of furniture in the

49:07building and maybe reuse all the old

49:09stuff

49:10>> and their GMP goes up to 25.4 because

49:12that's what we need to do it,

49:14>> right? What we're saying is we're

49:16committing to that 312

49:19>> again. And those other things are all

49:21all up and down, but we will make the

49:23decisions to stay within that 312

49:26because we have to

49:27>> have to because we can't go back to the

49:28town meeting and go

49:31>> h kidding. We need 400,000 more. Like we

49:33know that's the we we do not do that. We

49:37we [clears throat]

49:38>> that is the

49:39>> that never

49:41>> doesn't work.

49:42>> It doesn't work. So we don't do it. It's

49:43not even in our

49:45>> in our brain. Yeah. I think at that

49:46point if something like that were to

49:48happen, that's where we'd utilize the we

49:50we'd decide what we wanted to do and

49:52possibly use the

49:53>> the owners the owner's contingency.

49:55>> Yes.

49:56>> Um and you you kind of

49:59>> Yeah. No, it's a great it's a great

50:00point. And listen, we we also too

50:03realize that, you know, this was a

50:05deadline to get Keith to appoint to get

50:08this committee to a point to make a

50:10recommendation. There can be certainly

50:12other public meetings, information

50:15sessions to the select board where we

50:17don't just show you one blue box. We

50:19show you kind of a breakout of here's

50:22how it's built. Here's what a GMP is

50:24kind of

50:25>> ed a little more education about where

50:27we're going. Um but this is the you know

50:31this is where we are right now today. Um

50:34and hopefully it's you know enough

50:37information to um to make a decision and

50:40again pursue it like you would pursue

50:43you know the high this is essentially

50:45the way you would do the high school

50:46project

50:48>> and I just had a couple of questions on

50:49the value engineer.

50:50>> Absolutely.

50:51>> Um just to make sure that we're not

50:53removing something that's you know that

50:56doesn't make sense to remove for

50:57instance the one that grabbed me was the

50:59fuel station canopy. Can you explain

51:01what that is? That to protect people

51:03from when they're

51:04>> That's that's actually I saw it

51:05deferred.

51:06>> That was an idea.

51:07>> So that's no longer talked about.

51:10>> We would like to have that in.

51:11>> Just saw deferred and I wanted to know

51:12what that meant.

51:13>> That was on a list that we all agreed

51:16we'd like to keep that one in for now.

51:18And that that could be another lever of

51:20>> Yeah. The other ones are in there.

51:21That's right.

51:21>> And and the masonry backup wall. Is that

51:23was that the connector? Is that the wall

51:25that was we were going to put on or what

51:27is that that to be determined evaluated

51:29or

51:30>> that's around the new admin building.

51:32It's kind of right right now the um

51:34details are showing a masonry backup

51:37wall. We think we could investigate that

51:39more to potentially extend the

51:41foundation wall.

51:42>> Um but there's a little bit more

51:43studying of the um energy modeling to

51:46make sure that that would work. But we

51:48think that that could be an additional

51:50value engineering that we would pursue.

51:52>> Yeah. I mean the downsizing of the

51:54generator that makes sense because if

51:55you don't need it you don't need it. Um

51:58but the brine tank what does that mean

52:00Keith is that

52:01>> so current currently inside um so we so

52:04we have a Brian programs

52:07>> um so that system lives inside the

52:10existing highway garage. Um, initially

52:14when we worked through this new

52:16conceptual plan, we were going to move

52:17that brine system well out next to the

52:21um, salt shed and create an enclosure

52:24for it there. Um, but since we're not

52:27going to rebuild a new building, build a

52:30new building for this that we would just

52:32leave the Brian system where it is.

52:33>> Weren't we going to add some capacity to

52:36it? Another tank?

52:37>> Um, we did that about two years ago.

52:39>> That was already done.

52:40>> That was already done. Yeah. So this is

52:41just this isn't removing our capability.

52:44It's just removing what we would need to

52:45build out.

52:46>> It's removing it from the new building.

52:47>> I'm good with that. Okay.

52:50>> Okay. That was all and just that you

52:52know the other one was the coding on the

52:54aprons just not that that's something

52:56things like that you if you can defer it

52:59if it if it's because you have to

53:00consider if it makes sense to doing

53:02doing it while you're doing

53:03construction,

53:04>> right?

53:04>> You know, things might cost more after.

53:06>> And so we talk about AP. We we did have

53:08that conversation specifically about

53:09moving that out, right? and and um you

53:14know we think we still we need we

53:16certainly think we need the concrete

53:17aprons in front of the fleet maintenance

53:19garage but we wouldn't necessarily need

53:20them at the wash bay or at the at the at

53:23the um shops in the back. Um, so it was

53:27that was kind that was just a

53:28>> and that's that value there was to keep

53:31them at fleet because we you know we

53:32discussed that originally maybe taking

53:34them all out but the need for definitely

53:37um keeping them at fleet maintenance.

53:39>> This was just to code them too. The HDMA

53:41is just a a coating on top, right? That

53:44wasn't a full pull out replacement, was

53:45it?

53:46>> Um no. So that that is referring to the

53:48there's a concrete apron in front of

53:51instead of it being um asphalt.

53:53>> Oh, it's by now. It's It's shown to be

53:55concrete. Yeah. Now,

53:57>> right. Right. I thought it was pushing.

53:59I was Can they add some

54:01>> to the current building?

54:02>> Yeah.

54:03>> So So we're not talking about the

54:04current building. We're actually talking

54:04about the administration building.

54:06>> Oh, okay. The new door.

54:07>> The new fleet garages would like

54:09originally there were concrete aprons at

54:10all the overhead doors for that building

54:12and we backed that off to just the fleet

54:14doors only. And then last one, uh, would

54:18FA would I assume this project be with

54:20the elimination of disruption to the DPW

54:23building would create less phasing? Did

54:25that factor into any of this value?

54:28>> It factored into their GC's that were

54:31added into the project, right? Because

54:33the phasing, extended duration, the

54:35duration got shorter. So when the

54:36duration got shorter, their portion of

54:38the of the markup got shorter because

54:41you're on the job for less months,

54:42right? So yes. So all of those things

54:45squeezed reflected into the total.

54:47>> Oh, I just didn't see it on the calendar

54:50memory, but I thought

54:51>> Yeah, the calendar was longer because

54:52then it was another like six or seven

54:55months then the close out. So the job

54:57the job did did shorten. The other thing

55:00too to remember about about um cost

55:03valves is that you know for something

55:05that like is on the VE list that you

55:09know

55:10maybe you really wish you don't want to

55:12ve something that you really might want

55:14later or or I say want need later we can

55:17do an alternate an add alternate right

55:19so as an example if this committee says

55:22you know what Keith I know you you know

55:24pretend we had taken the canopy out and

55:26you had said I really think you should

55:28have it well we could say, you know

55:29what, let's leave it out and then we can

55:31put a an ad alternate. So on bid day, we

55:34can see, yeah, we've been tracking it at

55:36100, but if the market says it's 50

55:38because okay, maybe we buy it, right? So

55:41similarly, if there are some things that

55:42if the number is looking tight, you

55:45know, we're going to have to identify

55:46possibly some deduct

55:48>> or we're going to have HKT take

55:50something out of the job and add it as

55:51an ad so that you know, you only do it

55:55if you have the money to do it, right?

55:57So again that's all that's months away

56:00but we will that is another cost um cost

56:04relief you know mechanism so we can you

56:08know make sure that we're staying at the

56:09number or lower right all the way

56:11across.

56:12>> You know there's nothing better than

56:14giving you good good uh good news on bid

56:17day but we also don't want to be so

56:19conservative that you take something out

56:22that you really need it that you really

56:24that really is part of this project.

56:26Right. So

56:28>> try to find try to find try to find that

56:30balance throughout the process for you

56:31guys.

56:32>> And again, this is exactly why we do

56:34this process, the construction manager

56:37at risk format,

56:38>> because it it it gets rid of those

56:40variables where if if there are sudden

56:43cost overruns and again I always go back

56:45to the Doerty High project. The day they

56:48crack around on that, it was $30 million

56:51over budget

56:52>> that they didn't foresee. And that was a

56:54design fit and build project.

56:57>> So I think we're heading in the right

57:00direction.

57:01>> They're in the room. [laughter]

57:05>> This is where you say don't do that.

57:07>> I'm not saying it was there. I'm not I'm

57:08not laying fault. I think the fault is

57:10in the process, right? Like that this

57:13before we've bought anything, before

57:14we've committed any of these costs,

57:16right? We're giving, you know, the

57:18chance to change the program, realign,

57:20think through all those things, but

57:22we're also able to bring feedback from

57:24the market. Right.

57:25>> Right. And, you know, it's also a number

57:27with our relationship in town and our

57:29history in town that each of the

57:31projects that we've done, the number

57:32that we've,

57:33>> you know, put forward as part of the

57:35committee has ultimately been a number

57:37that we've been able to deliver the

57:38projects inside of. So we are

57:40incentivized like to keep the

57:41relationship to deliver reliable numbers

57:43and to you know then deliver savings as

57:46we go through the project.

57:48>> I was blaming the city for picking them

57:50up process. [laughter]

57:53>> The architect's not going to either. So

57:59>> so when you're going to like as you

58:00mentioned like when you're going to send

58:02this one you have to remove 266 as you

58:05mentioned nowaday and then later you're

58:08going to work on that.

58:09We will all the way through.

58:11>> Listen, the the decision is up to the

58:12committee, right? If you if you take

58:14that out, you're just taking money out

58:16of your contingency right now. But if

58:17the committee feels a number a round

58:19number of 31 million is better than

58:2131.2, that's your decision.

58:24>> You mentioned like, I can take off this

58:26amount.

58:26>> No, no, no. I'm not saying my No, no.

58:28I'm saying if you want to reduce that

58:30from the budget, we can find that. I I

58:33haven't calculated my fee for this job

58:34and I my boss would kill me if he told

58:36me to take $200,000 out of our fee. I'm

58:40just saying from a budget standpoint, we

58:42can get to a round number if that is an

58:44easier number to talk about. I don't

58:46know what our budget is for this job

58:48yet, but it's Yeah, I'm I No, I'm just

58:52saying from an overall standpoint, if

58:54you need that number to be a round

58:56number, fine. Make the soft cost 0.245%.

59:01It's Yeah, it's it's

59:04Yeah, we we we are not at the point of

59:08negotiating amendments to contracts for

59:11jobs that aren't approved yet. We can't

59:13we can't do that. So,

59:20anything else?

59:22>> To vote if that's the next agenda.

59:26>> That brings us that moves us forward to

59:28item number eight. discuss the meeting

59:30schedule and potential select board

59:32presentation in November.

59:35>> Are we so

59:37>> at that point?

59:38>> We are not. So I have we have a meeting

59:40with the select board on uh Monday

59:43evening. It's a workshop. Um we're

59:45discussing this project along with um

59:49future financial obligations u financial

59:52modeling um and [clears throat] be part

59:54of that and uh my hope is come out of

59:56that meeting with a um decision on the

1:00:00from the board on what they want our

1:00:04next steps to be which could be uh

1:00:06presentation to them um or something

1:00:10different.

1:00:12And at that point that now would be the

1:00:14point when we would give our

1:00:16recommendation

1:00:18um

1:00:20our voters recommendation to move

1:00:22forward um also in public setting.

1:00:26>> Mhm.

1:00:27>> Patrick, do we need a a vote to bring

1:00:29this to the select board for the

1:00:30November meeting or

1:00:31>> um presented?

1:00:32>> We do not need a vote this evening um if

1:00:36we have a general agreement for me to

1:00:37present it as it's been presented. Yes.

1:00:39a workshop and then but prior to any

1:00:43public meeting with the select board to

1:00:46actually request something then we would

1:00:48come back as a

1:00:48>> right

1:00:49>> as a committee.

1:00:50>> Yep.

1:00:50>> Um to vote.

1:00:53>> So we're okay presenting it as it's

1:00:55>> I thought I saw that that we had to vote

1:00:56to send it to the

1:00:58>> good

1:00:58>> to check for but if not that's fine.

1:01:00>> Okay.

1:01:01>> They're presenting. Okay.

1:01:02>> Yeah.

1:01:03>> Yeah. Very good. So, gen generally

1:01:06speaking, we're getting the measure of

1:01:07this committee this evening. We'll get

1:01:08the measure of the select board.

1:01:10>> I appreciate all the work that was done.

1:01:12I know it was a lot. Um, and to get from

1:01:15where we were to where we are now, I

1:01:17think is phenomenal. So, thank you.

1:01:20>> I guess one, have we talked to the PPW

1:01:22staff? Have they been involved with

1:01:23this?

1:01:24>> Staff have been involved with this over

1:01:26the summer, I guess. Um, and they we've

1:01:30done some ton of ton of work as this

1:01:32team has over the past week, but I may

1:01:34I've had one-on- ones with most

1:01:36>> so they know about kind of so we know

1:01:38where we're at.

1:01:38>> Okay.

1:01:40>> Do you anticipate another meeting? Do

1:01:42you have an idea? [clears throat]

1:01:45>> So, I don't think we can set a date on a

1:01:46meeting now. Um, I would like to get

1:01:48through Monday evening and uh work with

1:01:51the board, understand what they want to

1:01:53do before schedule for public

1:01:54conversation.

1:01:55>> Okay. Very good.

1:01:58Any other business?

1:02:00>> None.

1:02:02>> There being none, do we have a motion to

1:02:04adjurnn?

1:02:05>> So moved.

1:02:06>> Second.

1:02:06>> We have a motion and a second to

1:02:07adjurnn. All those in favor signify by

1:02:09saying I. I. Thank you everybody. Thank

1:02:11you very much.

```*