2026-10-29 - Municipal Facilities Optimization Committee
Summary
- Minutes: July 9, 2026 approved 4-0; September 9, 2026 approved 3-0 with one abstention. Two Vertex invoices of $2,623 each were approved 4-0.
- Architect amendment: the HKT Architects mechanical, electrical and plumbing amendment raised the contract from $96,500 to $104,200 (+$7,700), paid from funds already appropriated; approved unanimously.
- Vice chair: Steve Walsh was elected unanimously (name as heard; not present).
- DPW South Street facility: the recommended option is a new 29,325 sq ft administration and fleet maintenance building, keeping the existing 32,085 sq ft garage as cold storage and demolishing the water department building. Estimated cost: $26 million base less about $1.1 million in value engineering, plus $6.2 million soft costs, roughly $31.2 million total, against about $46 million for the failed 2025 project. Value engineering included simplified HVAC ($500,000), a smaller generator ($200,000) and a reduced equipment allowance ($150,000); pricing reflects tariffs, diesel at $6.50 and escalation. No formal vote; consensus to take the option to a Select Board workshop, with a committee vote before any formal request.
- Schedule if approved at town meeting and ballot in May: design resumes then, construction starts at the end of 2027, runs through most of 2028, and closes out in early 2029.
- Amended from the originally posted October 28 date.
Issues discussed
People
Speakers were heard by first name only (committee chair, project staff, the architect and construction manager teams), so none are linked.
Auto-captions: some terms and names were garbled; the fuel canopy savings item was unclear and is left out.
Agenda
Items as listed above.
Sources
- Agenda: https://www.shrewsburyma.gov/AgendaCenter/ViewFile/Agenda/_10292026-5597
- Video: https://www.youtube.com/watch?v=Iyldz3wf55w
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:02Good evening. This is the Municipal
00:04Facilities Optimization Committee
00:05meeting October 29th, 2026. We just have
00:09a little preliminary business to get to
00:10before we get to the main part of the
00:14meeting. Um, we have a quorum. So, this
00:15meeting is called to order and we have
00:17the minutes from July 9th and September
00:199th. I think that we can take those as
00:21one item. Um, any questions, concerns on
00:25the meeting minutes?
00:26>> I need to abstain from September. That's
00:27the only
00:28>> Okay. Anything else? Any comments or
00:31questions? No. We have a motion to
00:32approve.
00:34>> Yes.
00:35>> We have a motion and a second to approve
00:37the meeting minutes from July 9th and
00:38September 9th, 2026. All those in favor
00:41signify by saying I. I.
00:43>> Opposed? So voted.
00:464 July and 3 to zero for September with
00:51one abstension.
00:53Okay. We have a couple bills to pay. We
00:56have Vertex
00:57Company again. And I think we can take
00:59these as one item. Fertex companies for
01:02dated 8:31 2026 and 9:30 2026 both in
01:07the amount of $2,623.
01:10Any questions on those bills?
01:14There being none, do we have a motion to
01:16approve?
01:18>> Second. We have a motion and a second to
01:20approve the the uh bills for Vert.Ex
01:22Company 8312026
01:25and 9:30 2026
01:27for the amount of $2,623
01:30each. All those in favor signify by
01:32saying I
01:34>> I opposed. So voted unanimously four to
01:37zero.
01:38>> Item number four, review and act to
01:41authorize an amendment to the agreement
01:42with HKT architects for additional MEP
01:45services.
01:47John, do you want to talk that through?
01:49>> Sure. Um, we have uh we originally got a
01:54proposal from HKT, as you're aware, to
01:57uh extend uh the work on the project.
01:59And that initial proposal was for
02:01$96,500.
02:03And what ended up happening subsequently
02:06is we said, "Hey, um there was some
02:10discussion about the MEP systems, right?
02:12And how much we should uh how much we
02:15should include or not include for the
02:18MEP. Um the MEP had not been included in
02:21the original uh in the original
02:23amendment. Um so that the final the the
02:26965 increased to and I sent you the
02:30wrong one, Keith.
02:32One second here.
02:36The full final amount instead of 96,500
02:41increased to
02:46104200.
02:49So an additional
02:54>> not going to
02:55>> 77
02:56>> 7700
03:00>> correct. So, an additional 7,700 to
03:03HKT's contract. So, um would be looking
03:06just to get that that additional amount
03:09um increased
03:11or that total amount increased to cover
03:13the 7700 total.
03:19>> I just have one question.
03:20>> Sure.
03:21>> Was that the 7,700 included in that
03:24first allocation that we did at town
03:26meeting?
03:27>> Yes, this all all the funds are within
03:29Okay. So much they've been appropriated.
03:31Yep.
03:31>> Okay.
03:31>> Yep.
03:32>> Yep.
03:32>> That's all I need to know.
03:35>> Anything else?
03:36>> So, with that approval, we'll get the
03:37amendment to to the town for signature.
03:40>> Sure.
03:40>> Sure.
03:42Any other questions, discussion? Do we
03:44have a motion
03:46to approve
03:49to amend the agreement with HKT
03:51architects for additional MEP services
03:54from 96,500
03:56to $104,200?
04:03>> Motion to approve.
04:05>> We have a motion. Do we have a second?
04:07>> Okay. All those in favor signify by
04:08saying I. I. Opposed. So voted
04:11unanimously. Thank you everybody.
04:14>> Thank you.
04:15>> And item number five, we have gone two
04:17meetings now without a vice chair.
04:20Fortunately, the chair has been here,
04:23but I think it's time to elect a vice
04:25chair.
04:26Um, so I have spoken Steve Walsh reach
04:30when he heard about this Steve Walsh
04:31reached out to me and he's interested in
04:32filling that role. So I would like to
04:35nominate him to be the vice chair. Do we
04:39have any other nominations to consider?
04:42deep.
04:43>> No.
04:44>> Any discussion around that?
04:48>> There being none, do we have a motion to
04:51select Steve Walsh as the vice chair for
04:54the mun municipal facilities
04:55optimization committee?
04:57>> So moved.
04:58>> Second.
04:59>> Second.
05:00>> All those in favor signify by saying I.
05:03I. So voted unanimously.
05:05Congratulations, Steve, if you're
05:06listening. [laughter]
05:09Item number six, we have an update from
05:12the design designer architect.
05:14>> Who is taking that?
05:15>> Is me.
05:16>> All right.
05:17>> And there's really not a lot to update.
05:19We've basically been on kind of a
05:21holding pattern while we've been going
05:22through the cost estimate for the
05:24redesign facility and working with
05:27Fontaine Brothers to go through the PE
05:29options and to analyze how we can reduce
05:31the cost from the initial estimate that
05:34was done on the redesign.
05:36Any questions around that?
05:38>> No, I just want to say that um you know
05:41the project team obviously has done a
05:42ton of work over the summer. Um our
05:46staffs have been involved also with
05:48them. Um estimates were done initial
05:51estimates were done last week or so. Um,
05:54and I would I will tell you that in the
05:56past six or seven working days, there's
05:59been a ton of work by this team um to
06:01really dive into the VE um and reducing
06:06the cost of the project. Um, and when we
06:10get into this the, you know, the next
06:13presentation here, you'll see all the
06:14work that was done to get us where we're
06:17at.
06:19>> Okay,
06:20any questions? Any other questions,
06:22comments?
06:24concerns. There being none, we'll move
06:26on. Item number seven, we have an update
06:29from the construction manager. Who's
06:30going to take that?
06:31>> I'll take you guys through the
06:33>> All right, John.
06:34>> Um, with some side commentary by
06:37Fontaine as we go.
06:38>> Okay. Um so if you direct your attention
06:41to the presentation I believe it was in
06:44your folders but um this what we wanted
06:46to do is basically very high level of
06:50the chronology of the project and then
06:52the summary of the costs and where those
06:56have played out uh some things that have
06:58impacted those some things we're looking
07:00at to try and offset those and then
07:02ultimately move you know provide a
07:05recommendation for the you know the most
07:07cost-effective solution that still helps
07:10address some of the issues at the DPW
07:13that we have today. Um, next slide,
07:15please. So, a little bit for the
07:17timeline. Um, taking you through very,
07:19you know, for anybody who's just picking
07:21this up for the first time. As you may
07:23or may not be aware, in 2024, there was
07:26the initial push with this project. Um,
07:28moved forward with a different architect
07:30for a project that was an addition
07:32renovation. It was basically a new
07:35administrative building tied to the
07:37existing DPW garage, but literally tied
07:40to it. So, new construction um tied to
07:42the existing building. Um that design
07:45got through schematic through schematic.
07:48Um and after schematic, the decision was
07:50made by the town to move ahead with a
07:53new designer. um the initial designer,
07:56the contract wasn't renewed,
07:58uh brought HKT in to um to to develop
08:01that design and help us get to the 2024
08:05town meeting and ballot votes. Um they
08:08did that. Um we had numbers, went to the
08:10town meeting, passed a town meeting, but
08:12failed at the ballot. So after that that
08:15initial um stoppage of the project
08:18really a lot of time went by and you
08:20know there had been work going on behind
08:22the scenes you know in town hall to try
08:24to figure out what to do next and in the
08:26spring of 26 the committee came back
08:29Keith came back to us and said okay we
08:31want to look at using the remaining
08:33funding to try to come up with a new
08:35approach for the project. Um what then
08:38happened was a design cheret across the
08:40way in the select board chambers really
08:42was HKT Fontaine Vertex and the town
08:46really trying to rethink
08:48the approach of the project again when
08:51HKT first came in they were really
08:52taking that initial design and trying to
08:54figure out okay what can we do with that
08:56instead rethought it and said you know
08:58what there's a way to do this you know
09:00let's go with two new buildings don't
09:03reuse anything and again there had been
09:05some looking at the you know a relook at
09:08the existing buildings and saying look
09:09there you know especially the water
09:11department building nothing there to
09:14save but let's you know let's let's do
09:16an approach where we you know redo the
09:18whole thing um next slide Keith the SD
09:22for that was completed for pricing and
09:24that first pricing that came in was was
09:27higher than expected so what can we do
09:30all right so let's still go with two
09:32separate buildings we'll do a new
09:34administration building but then
09:36renovate the existing DPW garage really
09:40um roof systems that sort of thing and
09:44look and see what happens. Uh in
09:46addition to that the team worked on
09:48[clears throat] a series of value
09:49engineering
09:51um value engineering items to try and
09:54pull that pricing down as well and give
09:57some relief valves. That pricing came
10:00back still what the folks felt was too
10:03high. So, we said, "Okay, final pivot
10:06here. Let's go with the new
10:08administration building and fleet
10:09maintenance and do zero work on the
10:12existing DPW garage. Truly use the
10:15existing building just for uh for
10:18storage. There would still be the need
10:20potentially for a roof on that building,
10:22but we can address that roof either out
10:24of contingency for the project or
10:27ultimately for out of the a capital
10:29budget from the town at some point down
10:31the way." And that was the
10:33recommendation that we bring to you
10:35tonight. A little bit about the costs.
10:39Um, basically what we did is tried to
10:41show you the four different iterations
10:43of the building. Oh, my little macros
10:46didn't pop up in Google. Um, the top
10:49building, the top item is a new and a
10:52rena. The allnew project is two would
10:56have been two new buildings. The green
10:59box talks about a new and a a rena. And
11:03the final box in blue at the bottom is
11:06just one new building, no renovation at
11:08all. Um pricing [clears throat] of the
11:11initial project from that failed was
11:14escalated forward to the same time
11:16period as now. So if you look back and
11:18go, wait a minute, that wasn't the
11:19number we voted on. No, it wasn't. What
11:21we did is brought it forward so that
11:22we're comparing four options to today.
11:26And again, the gray one isn't even on
11:27the table, but it's there for reference.
11:30Um, pricing includes current market
11:33conditions as they're known today. So,
11:35things that we know about for tariffs
11:37and all the news you've heard about
11:38that, $6.50 diesel is included in all of
11:43that, as well as escalation, moving
11:45moving that forward. And then, as
11:48applicable, we've got the VE taken out
11:50of this as well. So you heard me mention
11:53one and a half million for VE if and
11:56then in the suggested option at the
11:58bottom only 1.1 the difference is
12:00because 400,000 of that VE was suggested
12:04to the scope of a building we aren't
12:06doing anymore right so we would it's not
12:08one a.5 million of ve it's only 1.1 so
12:12the approach we took for this was the
12:14construction numbers all came from
12:15Fontaine and there's some very detailed
12:17backup for all of those subtract the VE
12:21and then add soft costs. Right? So at
12:23this point you know rather you know
12:25again with a design that is only you
12:27know is just inching its way towards you
12:30know schematic at this point for soft
12:32costs the cost for the designer for the
12:34OPM for furniture fixtures equipment and
12:37contingency we are just using a
12:39multiplier. Um, the reason why the
12:42multipliers are different is that you'll
12:44notice that in each of those options, we
12:46use 30% when there's a renovation
12:48involved and 25% when there is a a new
12:52project. The reason for that is is
12:55included in that 30% is a 10%
12:58contingency for unknowns on when you
13:01have a uh a building that you're
13:03renovating and only 5% when it's new.
13:06when it's a newer building, there's less
13:08problems, there's less surprises because
13:10you're just literally just scraping the
13:12old building and taking it down. So you
13:14it's it's you don't need to carry as
13:16much contingency. So basically that, you
13:19know, we're looking at a project right
13:21now that is a 26 million base
13:24construction cost minus a million inve
13:27gets you to 25. Uh soft costs of 6.2.
13:32Those added together is a roughly a
13:34$31.2 2 million project.
13:38Next slide, Keith.
13:40>> I know you can't see this. Um, we can
13:42pull up some VE logs, but some of the,
13:46you know, some of the items that we're
13:48talking about, you know, in the 1.1
13:50million dollar savings in VE, you had um
13:53some grading um grading associated with
13:56the recycling center for a couple
13:58hundred thousand, removing the fuel
14:01station canopy for 100,000, reducing the
14:04equipment allowance [clears throat]
14:05um built into the construction contract
14:07for 150,000. Remove the high density
14:11storage for 60,000.
14:13Simplify the HVAC in the fleet
14:15maintenance building for half a million
14:17dollars. Replacing vehicular concrete
14:20aprons at overhead doors with HDMA
14:2325,000.
14:25Downsize the generator and utilize the
14:27existing generator to provide power for
14:29the existing DPW building and reducing
14:32the generator size from 750 kows to 400.
14:36That's a $200,000 savings. and then
14:38removing the brine tank utilities from
14:40the project of another 23,000. So in
14:43discussing all of those with Keith and
14:45Keith with his staff, that is the
14:47savings of of 1.1 million. Now you say
14:51YveV, the reality is is that when the
14:53pricing came in, there wasn't time to
14:55change the design to then do an estimate
14:58that reflected the outcome, you know,
15:00the incorporation of that VE into the
15:03design yet. So with a yes, that's where
15:05we go forward. We won't talk about VE
15:08anymore. We'll incorporate those
15:09changes, have a new baseline of the $25
15:14million project, and if as the project
15:16proceeds, we hit, you know, oh wait,
15:19costs have gone up again, we'd have to
15:22ve other things, right? But at this
15:24point, we would accept the stuff that's
15:26in here and move ahead with with that
15:28project. Um
15:31so the rec next like the recommended
15:33solution um construct the new
15:36administration building the existing DPW
15:39garage excuse me becomes cold storage.
15:41No additional work on the building at
15:43this time and you can the the plan
15:47reflects the new building. The red
15:49rectangle is really what's there right
15:52now. So that would stay. And again, as I
15:54mentioned earlier, we'd contemplate roof
15:56replacement on the existing garage
15:58either as part of bid savings if
16:00successful or a future DPW capital
16:03budget item. Neither, you know, does
16:04neither item that either approach
16:07doesn't need to be discussed now. But
16:09the the point is, you know, the it's a
16:12do nothing solution for the uh existing
16:15DPW garage as of today.
16:18>> So, I will stop and
16:20>> there was one there was one more slide
16:22about schedule too. Sorry.
16:23>> It's okay.
16:24>> Thank you. Uh schedule. What does that
16:26do to our schedule? So again, all of
16:29this discussion tonight is in
16:31preparation for presentation to select
16:34board and getting this project hopefully
16:37on in front of uh the voters in May. If
16:42with a successful town meeting and
16:44ballot vote in May, we jump right back
16:46into
16:48um you know pre precon and design,
16:51right? I mean the project isn't designed
16:53yet with the goal of moving forward um
16:56with construction at the end of 27. And
17:00just to be clear, one of the things, you
17:02know, how does the cost drop? You know,
17:04we were using conventional construction
17:06originally and moved towards all
17:08pre-fabricated metal buildings um for
17:11the project um for the admin building.
17:14So, you know, even those prefab metal
17:17buildings, those costs have gone up as
17:19well. So we saved by going with that
17:22type of pre-engineered construction but
17:25yet even that as a building block has
17:28increased in cost. So um so again to be
17:31clear the admin building is not you know
17:35fully stick built from the ground up. It
17:37is it is built with a pre-engineered
17:38system. Um very typical for lots of DPW
17:43facilities and other municipal utility
17:46facilities these days. that that would
17:48be the uh framework framework of that
17:50building. So, we'd be looking at
17:52construction through the majority of
17:542028
17:56um with a close out and turnover in the
17:58beginning the beginning of 29.
18:02Now, I'll turn it over to you for
18:04questions.
18:04>> Questions?
18:05>> You didn't Sorry. Go ahead.
18:06>> Go ahead. Go ahead.
18:07>> So, you didn't mention about the seaw
18:08water bes
18:10can see what will do with the sea and
18:13water building. Um, so the the the water
18:17building would come down. Like that's
18:19that building goes, the existing garage
18:22stays of the two buildings. I think it's
18:24pretty clear that the garage is in
18:26better shape than the than the water
18:28department building. So um so yeah, that
18:31and we would need to get rid of that to
18:32build the to build the new the new
18:34admin.
18:35>> And what are the like connection between
18:37the admin admin and the DPW? They're
18:40going to connect no connection. So, as
18:43you can see right here, just as the um
18:46in the last presentation, they would be
18:48two separate buildings. They would
18:49remain two separate buildings. Um the
18:52front left, that's the recycling center.
18:55The new building is at the top of the
18:57top of the picture with the the black
19:00that's highlighted is aprons, right? Um
19:02outside of the building. Similarly, the
19:05existing U garage, which is the red
19:08rectangle, that is what stay would stay.
19:11Obviously the design HKT really this
19:14happened in the last as Keith said in
19:16the last seven days. We've done a all of
19:18this kind of back and forth. So the site
19:21hasn't been you know finalized yet. This
19:24is still very even it's less than
19:27schematic right now really. the the new
19:30admin building is in good shape
19:31schematic wise, but the site would needs
19:34a you know needs another look at um a
19:38hard look at to see about traffic flow
19:40and parking and all of those things
19:42which you know had been set into a new
19:44had been moving forward in a new design
19:46which now um isn't you know we would
19:50suggest isn't on the table at this time
19:52>> and if I would suggest too right so
19:56reducing it to the one building work
19:58still needs all of our program needs.
20:00Like we still have the administrative
20:02space to move all of our staff there. Um
20:05we still will have the new fleet
20:07maintenance area. Um then shops for all
20:09of the individual departments in that
20:11administration building. We still have
20:12our large um conference area that we can
20:17still use for voting. U those sort of
20:19things. So, very little has changed on
20:21the administration building um
20:25uh since the last uh presentation other
20:29than some of the PE items that we've
20:30changed like originally the whole
20:32building was air conditioned. Uh we
20:34removed the air conditioning from the
20:36entire um shop and fleet maintenance
20:39area. That's a half a million dollar
20:41savings that was in the VE items. Um so
20:45that was one I one piece and that
20:46literally you know we would um we we
20:50feel that the current DPW building
20:53although it's you know 50 years old we
20:56we still believe it's um in good enough
20:59condition that we can continue to use
21:00that for cold for cold storage. Um it
21:03has a lot of good equipment in it. So, a
21:05lot of the equipment and fixtures like
21:07the truck lifts, compressors, things
21:09like that, we can relocate to um the
21:12administration building or the new
21:14building, which is why we also reduce
21:16the FFN for some of the
21:18>> [snorts]
21:18>> um equipment and and in throughout the
21:21budget. So, a lot of stuff we've talked
21:23through. um it still meets our program
21:26you know it's not all new but we also I
21:28also think or we think that [snorts] um
21:31it's you know closer to a number that
21:34the community can u get behind us on
21:38>> so what is actually you change like when
21:40you came in the July June or July that
21:43time
21:44>> and that time like you came the the same
21:46size what is the that size of this
21:48building right now so what actually we
21:50are g gaining what we are basically
21:53missing Yeah.
21:54>> So, great question. So, the admin
21:56building remains at
22:00uh the new admin building remains at
22:0229,325
22:05square ft and the
22:10uh
22:12existing DPW garage is 32,085.
22:20So that difference compared to the two
22:23new buildings is a to it's a total
22:25difference of when we came here before
22:28it was 64,633
22:31and now we're down to 61,410.
22:38So we've lost 3200 square ft in program
22:42size,
22:44but the admin building remains the same.
22:47The loss is in the the difference
22:49between the red rectangle and the
22:51square, right? So that you you've lost
22:53that square footage in what would have
22:54been a new garage that would have been
22:563,000 square feet bigger.
23:01>> And optimized for vehicle
23:03[clears throat] storage,
23:04>> right? Right. Your existing garage isn't
23:07optimized. you're going to, you know,
23:09whereas the new garage you would pull in
23:11and have nicely aligned spaces, it's
23:13going to be more, hey, move this in,
23:15move this out. We don't need this piece
23:18of equipment, bury it in the back.
23:19Right? There'll be more um hopscotching
23:22that the staff will have to do to make
23:24that to make the existing building work
23:26for indoor storage.
23:28>> Is there room for all the vehicles?
23:31>> No. No.
23:32>> No. Um, we'll we'll be we we will be
23:35close, but the way the the way the
23:37highway garage is configured now. Um,
23:40there would definitely be some jockeying
23:42to get um all the equipment in there, I
23:45don't think we could. um we would have
23:48to live with some equipment probably
23:50being outside and maybe that would be
23:52something that we use less or older
23:54equipment um or not emergency vehicles
23:58that we
23:59>> Mhm.
23:59>> you know
24:00>> and with with that is there is there a
24:03plan to remove the office areas to
24:05increase the storage?
24:07>> Well, we could only do that with if
24:09funds allowed throughout the project. So
24:11if we if we
24:14came into bid savings then and and we
24:17could have I think our first priority
24:19for that building would be put a roof on
24:20it.
24:21>> Um and then if there was any
24:23opportunities to remove a wall here or
24:25there then we would consider that but um
24:28at this time that's not on the table.
24:31>> Okay.
24:33The hope I think is that with the moving
24:35forward
24:37as we you know with if the citizenry
24:40says yeah go for it is that in the time
24:43that this thing is designed
24:45>> hopefully you know gas doesn't stay
24:48diesel doesn't like the reality is is
24:50that you've got a bunch of site work
24:52site work runs on diesel everything that
24:54gets shipped here comes on diesel
24:55anything plastic has petroleum in it so
24:58you're really seeing a bit of a a bump
25:01right now you
25:02um you know construction costs and
25:05tariffs, you know, who knows what's
25:07going to happen with those, but the
25:08market is reflecting those right now. So
25:11if you say how much the it's really hard
25:13to pull that apart, right? Because you
25:16don't have a completed design right now.
25:18When these guys go to market, they're
25:19going to market with a square footage.
25:21Yeah. And an idea, right? And someone is
25:23saying, "Okay, if you can't show me more
25:25much more than an idea, here's my
25:28price." Right. So, you know, I feel good
25:31that we have a CM because we're not
25:33doing this with a third party estimator.
25:35We're doing this with people who are
25:36picking up the phone and doing this
25:37every day. But even those prefab metal
25:40buildings, these guys are building with
25:42those right now for EastN's DPW and
25:45they're talking to that vendor and it's
25:46that vendor that's giving them the
25:47pricing.
25:48>> And that vendor is saying, "No, those
25:50prices you bought that ad have gone have
25:53gone up."
25:54>> So, any we can't speak to what will go
25:56up and what will come down, right? We
25:58just can speak to this [clears throat]
25:59is where we are right now. And if we
26:01hold those numbers and say nothing else
26:03changes, we take those numbers and we
26:06escalate those up to okay a year from
26:08now when we bid and somebody holding
26:11that number through halfway through
26:12construction. And so that's what
26:14Fontaine has covered in these numbers.
26:16>> Okay.
26:17>> Very good. So there any probability to
26:20reduce the so cost because you don't
26:22know like after 6 months after the
26:24election like D the price can go down
26:26all those [clears throat] it c there
26:29certainly could be changes and listen we
26:31would all hope that there would be right
26:33could also go the other way right so I
26:35think the idea is to give if the if the
26:39committee supports it to give Keith
26:41enough information to say look we looked
26:43at this thing now four different ways
26:46this is clearly the most cost it's it's
26:49the most cost-effective solution to deal
26:52with fleet maintenance to deal with
26:54administration
26:56but we won't you know the reality is is
26:58because of the funding that was left
27:00there's not much more work this group
27:01can do between now and town meeting you
27:05know can they do can we look at taking
27:07the design and you know a little bit
27:09more sight to understand you know how
27:12traffic flows and things like that sure
27:14but at the end of the day we've gotten
27:17kind of to we're almost as far as we can
27:19go. Maybe there's a little more we can
27:21do if there's any remaining funds but
27:23not enough to advance the design far
27:25enough to say,
27:28you know, here this is a significant
27:30change that could drop this number. I
27:32think we've cut the program that we can
27:34at this point by going with the existing
27:37building. Um, as you can see the design
27:40from HKT, it's a pretty simple rectangle
27:44at this point. you know, one little bump
27:46out on one end. Um,
27:49you know, I can't I don't know if you
27:51guys any any thoughts on it's a pretty
27:54utilitarian kind of approach at this
27:56point.
27:57>> Yeah, it's pretty um pretty simple
27:59layout for as far as the admin and um
28:02but we would challenge that too to the
28:04next next level as we're going through
28:06things. Is there pushes and pulls that
28:08can make it even more cost effective?
28:11I guess yeah to that end right we would
28:13continue with an approved project it's
28:17still the goal of this I believe this
28:19committee to do it as cost-effectively
28:21as possible right so if we you know if
28:24this if the town says yes you would then
28:27do another estimate when that SD design
28:30gets design development and you might
28:32even do one more design as that design
28:34development set gets to construction
28:36documents so another two stopping points
28:38in that subsequent
28:42[snorts] seven to nine months after town
28:45meeting to say, "Okay, are we still are
28:47we holding? Are we holding?" And if
28:48we're saving, hey, great. Like, that's
28:50that's great news. And that's just money
28:52you don't have to borrow. This approach
28:54here for this project now is much more
28:56like what you would have to do for an
28:58MSBA school project. it is asking for a
29:01commitment to the number when it's just
29:04at SD and then having to live within
29:06that number for the next, you know, for
29:09the next year of design and the actual
29:11bidding and then for the year year and a
29:13half of construction. You know, when
29:15you're doing that with MSBA, you're
29:16committing for a school number for the
29:18coming four to five years, right? So,
29:20it's it's really the same approach um
29:23based [clears throat] on the the cards
29:25we're dealt right now and the funds
29:26available and where we are and and town
29:29meeting timing.
29:31>> So, with this new proposal of just
29:34keeping the old DPW building, where's I
29:37think I recall fleet going to the very
29:40right side or eastern side of the new
29:42building.
29:42>> Yeah, correct.
29:43>> So, does fleet remain in the
29:45>> fleet will still going to be moved?
29:46still move
29:47>> and there'll be extra space for
29:49>> correct
29:50garages there like those three bays.
29:52>> Okay. um there and I think you know the
29:55the
29:56like I said that building is a
29:58pre-engineered building and if like I
29:59said if there's savings you know um in
30:03the future you know maybe there's an
30:04opportunity to take a wall down and
30:06>> yeah one or two walls in those areas
30:09>> and look and I think we can certainly
30:10come back to you all with you know after
30:15the elections and in the spring as we're
30:17getting you know it's not like we're not
30:19going to talk to you between now and
30:20town meeting right if if we're seeing
30:22things in the market, you know, that's
30:24why we have a CM on board to say, hey,
30:26guess what? We have started to see some
30:28relief in the pricing for such and such.
30:31But for the discussions that need to
30:33take place now to get this on the, you
30:35know, to get this on the warrant or
30:39consideration for a warrant, these are
30:41the numbers we're at. But that doesn't
30:43mean that that couldn't shift between
30:46now and, you know, now and coming up to
30:48town meeting. So which one you are
30:50suggesting the construction code cost
30:52can reduce or like sub cost can reduce
30:56which are talking about the entire
30:58construction cost will be bid out like
31:01to subcontractors
31:03a year and a half from now or two years
31:05from now. So none of those construction
31:07costs are committed to any contractors.
31:09They're just our current estimate based
31:11on market conditions of what we believe
31:13the cost will be based on input. But
31:15each one of the subtrades bid will bring
31:18the bids to the you know the group and
31:20we'll choose the lowest responsible
31:22biders. So that whole number gets
31:23assembled as the design gets progressed
31:26so that the biders can give their most
31:28competitive pricing based on the
31:29finalized design. So all those costs are
31:32able to you know basically be at market
31:36at the time that we're able to buy them.
31:39>> Okay. So the design at this point like
31:42the the idea you came with those two
31:45building looking good but still the
31:48price wise little higher side. So as I
31:51think
31:53>> yeah at this point you're cutting square
31:54footage. So if you if the price needs to
31:57come down you're taking away bays or
31:59you're taking away office space and
32:01there's people who can't be in that
32:02building. So this committee needs to
32:04make a recommendation based on
32:07you know the market the pricing is where
32:10it is right now and yeah it's reflecting
32:12some stressors on the market right now.
32:15Um
32:16the only way to make that number go
32:18lower
32:19>> the space what you both side like how
32:21much you can help in the soft cost or
32:23construction code
32:25>> if because you guys getting the project
32:27so well again the soft costs at this
32:30point are just it's a factor right now
32:32it's it's 25%
32:33>> I wouldn't go lower at this point I'm
32:34not going to go lower than 25% and
32:36that's not me that's just if if me is an
32:38OPM to you a job at this point I would
32:41not in the end do costs end up coming in
32:44around. Could they come in at 22 or 23%.
32:48Sure. I'm not going to cut it to 22 or
32:5023% now because we don't know in that
32:53number, as an example, is 4% for
32:55equipment. The cost of, as an example,
32:58anything we need that's a computer right
33:00now. I just authorized a server at a
33:03town on the Southshore that a year and a
33:06half ago was 50,000. It was $125,000
33:10to buy that server. So those decisions
33:13about what else is in the building were
33:16not far enough yet, right? So to be able
33:19to say, "Yeah, look, I can think those
33:21soft costs can come in at 24%." Right?
33:24None of that is bought. That includes
33:26their fees, our fees, our fees are tied
33:29to duration, you know, okay, we think we
33:31know what the duration is, FFNE, and
33:33also then contingency, right? uh that
33:35money that if you need it, you know, you
33:39know, you you have it there to spend.
33:41The last thing I want to do before we
33:43even have a project that's approved is
33:46to say, okay, we can carry a 4%
33:48contingency because that 1% it's real
33:52money. So, you know, I think the the
33:55committee has to know that the team is
33:57committed to, you know, look at we've
34:01seen this go from a se 60s something,000
34:04square foot all all new program down to
34:0829,000 square feet, you know, and if if
34:12we can do it more cost-effectively,
34:15you know, we're going to do it. And
34:16that's what, you know, to Shane's point,
34:18we continue to test and ask questions
34:21right along the way to see if we're
34:22doing it as as economically as possible.
34:25But for right now, you know, that number
34:28is at at 31.2 million. If you wanted to
34:31round it to 31, that's it. I can't I
34:35can't suggest anything
34:38rounder or more than that because we're
34:40just we don't have enough detail to base
34:43it on yet. We're just throwing darts,
34:45you know, we're just throwing darts at
34:47things otherwise. So, you know, if 31
34:50>> Do you want to speak to like the makeup?
34:52You know, the vast majority of the
34:53number obviously is in the construction
34:55side of things. Shane and Ryan are
34:57deeply involved in how we put it
34:59together and
35:00>> our our fees as the builder like within
35:03that number are essentially fixed. Like
35:05we have percentages for our insurance,
35:07our fees. So talk about how the number
35:08is constructed and how we'll make sure
35:10that that number ultimately is as
35:12competitive as it can be.
35:14>> Yeah. So I when based on the original
35:17design, we went out to market and got
35:18feedback from subcontractors based on
35:21what they're seeing for pricing on all
35:23of this stuff. That's fed into the
35:24direct costs that we that we have.
35:28Also built into that construction cost
35:30um is a 10% design contingency which at
35:33the stage of the project right now
35:35there's a lot to be worked through those
35:36details um as well as a 6 and a half%
35:39escalation
35:41um from now till um the project start or
35:44halfway through construction um looking
35:47at it as a 4 and a half% escalation um
35:50you're over
35:52um
35:54>> so if the escalation if the market
35:56conditions improve
35:57>> Yep. you know that number will happen.
35:59>> The important thing to understand with
36:01the way that this contract will be
36:03procured is we're essentially acting as
36:05like your agent to procure all those
36:07subtrades. So the negotiations with the
36:10subs of, you know, hey, three concrete
36:12bids and how do we make sure we get the
36:14best one and can we get a best and final
36:16to get some savings like those would all
36:18happen post vote and we'd essentially be
36:21you know conducting those transparently
36:24on behalf of the town to drive down
36:26costs as much as possible will work. No,
36:28I understand because all of you are
36:30working for a long time with us and uh
36:33you can see if you get you getting this
36:35project you are going to for two years
36:37like how many year going to complete?
36:38Two year almost two year right?
36:40>> Mhm.
36:40>> Yeah. It's it's it'll be
36:41>> two year you are getting the two years.
36:43Yeah. Project getting the job
36:45everywhere. So we have to come up with
36:48some right number so that way we can
36:51work it and
36:52>> down also this way if you reduce the
36:54good price whatever that you can do it.
36:58>> uh that way you can get the project that
36:59why it will go in the there in the town
37:01meeting it pass and then go to the town
37:04resident they will say no
37:06>> and I we don't want to second time to
37:08happen like that
37:09>> so you guys to help us to get a good
37:13amount number so that way we can easily
37:15say and we can say residents this is the
37:17right number and this is the size we are
37:19getting and u some you know sometime you
37:23are not getting the bigger number but
37:25you still getting the some profit or
37:26some because All of you I know working
37:28I'm a businessman too. I understand
37:30without proper no one work but uh still
37:33uh
37:35think like this way.
37:36>> Oh we totally are
37:37>> because otherwise at the last time if
37:39you have good number something you will
37:41get the project and now you have to
37:43complete it%.
37:44>> I think it's important to note too that
37:46what
37:47>> that the number that
37:50>> go sorry
37:53>> no I'm sorry John.
37:54>> No it's okay. No no no. So looking at
37:56the blue down below, I think it's
37:58important to note that the you know
38:00something like contingency what we're
38:03again we are asking for you know what
38:05the MFA will ultimately be asking for
38:08the select board is to support a warrant
38:10article that goes in and says this is
38:14the most we will spend. You aren't
38:16committing to spending that right now.
38:18you are committing to spending
38:22um you know again an a you know an
38:25amendment for these guys for
38:26pre-construction an amendment to get
38:28started for to to develop the design for
38:31us to walk that through you're not to
38:33Dave's point you're not buying
38:34construction for a year from now and
38:36when we do hopefully the market
38:38conditions will improve and if they
38:40haven't in that year we will have had
38:42many meetings in this room to figure out
38:45okay what are the relief valves you know
38:48that we can do to help to help drop that
38:51drop that price. Um I think you know to
38:55the earlier comments like at this point
38:58you've really you've driven that program
39:01down to a point where below this you are
39:05now not you're already not getting some
39:07storage. Keith can work with the storage
39:10and the team can work with the storage.
39:12If you go below the 29,000 you're really
39:15starting to car stuff up. I think that
39:18what we what we hope is that we see some
39:21relief in the marketplace. We see the
39:24pricing of prefab metal buildings coming
39:26down. To your point, we could start
39:28seeing changes as early as next week,
39:31depending on what happens election wise.
39:33Who knows, right? So far, all the tariff
39:35stuff that we've talked about for years,
39:39we haven't paid one on a job yet, right?
39:41That doesn't mean it won't eventually
39:43they won't start to stick but the market
39:46is reflecting that those are there right
39:47now and you know we have to we have to
39:51share th that with you and you know
39:53acknowledge [clears throat] that it's
39:54part it's part of the job. I mean we all
39:57expected I think to see pricing that
40:00would have been lower than this and in
40:02the last few months it has really it's
40:05really taken a turn in the wrong
40:06direction for right now. Doesn't mean it
40:08can't go back the other way but I mean
40:10and I don't know if Yeah, I just wanted
40:12to say, you know, Anad, like I I don't
40:14disagree with you, right? Like we we we
40:16worked really hard to make sure that
40:18what we're bringing to the residents is
40:20the best value for the project. Um like
40:24I can't stress enough how much work
40:26these people have put in for us to get
40:28there. Um, but also to your point, like
40:32I don't we we don't want to bring them a
40:34low number just to bring them a low
40:35number and then not be able to do the
40:37project because if you recall that is
40:39somewhat what happened the first time
40:41around, right? We came in with an
40:43estimate that was low and then it turned
40:44then we brought our construction manager
40:45on and said no no no this is the real
40:47number and that didn't work well at all.
40:50So, we worked really hard to try to to
40:54really dive in and make sure that we're
40:56giving the community the best we could
40:58possibly get because we don't want we
41:00certainly DPW certainly does not want
41:01this to fail and I know this committee
41:03doesn't want it to fail either. Um, but
41:05I think it it would be [clears throat]
41:06very hard for us to go in front of the
41:09board or in front of the town and
41:12[clears throat]
41:13and and say we'll get you a lower
41:15number. Um, but I am also confident that
41:18this team, if it does move forward, is
41:20going to work really hard to make to to
41:23to help us with that. And Fontaine has
41:26done that for us on the past at least
41:29the past three projects that they've
41:30worked on with us between the library,
41:33be school, and the police station. Um,
41:36they they've always um done a good job
41:38for us and, you know, we've had
41:41significant return on our money to the
41:43point where we didn't have to borrow. So
41:45that's why I'm saying that we have a
41:46pretty good relation being the so many
41:48project and the future project also
41:49coming.
41:50>> Uh but sometime you know one project you
41:53are not getting but you definitely have
41:55other project where you have more
41:56chances to because your reputation your
41:59work your quality your connection which
42:01you are building with us. Mhm.
42:03>> So on that basis still I'm saying like
42:06there some number is little high uh
42:08maybe you can reduce some uh
42:12[clears throat]
42:12>> yeah I in us putting this number
42:14together
42:17the like the fontine control portions of
42:20this um were essentially like procured
42:24in a competitive environment when we
42:26went through the process in the first
42:27place. I don't recall where the fe
42:28proposals were, but I believe we're, you
42:30know, competitive. We're less than than
42:32others in the market. And I think that
42:36um we also can control and I think that
42:39we've reduced our our staffing
42:41associated with this by bringing the
42:43duration down. So there have been
42:45savings that are baked into this number.
42:47Um and absolutely and from our
42:49perspective you know town's been an
42:50awesome partner for us and we recognize
42:52that the only way you know that this
42:55project moves forward and becomes a
42:56project for us that we generate any fee
42:59on is if it's you know able to be
43:01supported successful and when we're
43:03presenting this number it will all be
43:05shaken out and procured later the
43:07contingency will be well managed we
43:09return money at the end of each of these
43:10projects in town and I think to Keith's
43:13point what we want to make sure we
43:15balance is being able to deliver a
43:18number that's going to be the most
43:20competitive so that the the boat can
43:23find support
43:24>> while also making sure that we're
43:26careful that it's a number that with
43:28everything going on in the world we feel
43:30two 3 years from now the project will be
43:32able to be complete within because all
43:34that procurement that needs to happen
43:36for all the subtrades is obviously
43:38outside of our ability to pinpoint and
43:40lock people in right now. Um but we
43:43absolutely you know want to be good
43:44partners to the town and are happy to
43:47you know but we reduce
43:48>> yeah look at one more time like the
43:49number
43:50>> then everything looks good to me all of
43:53us are like we are okay with that but
43:55look at the number one more time
43:57whatever you can uh do on the certain
43:59extent
44:00>> definitely help for town and you will
44:02get more project because you are
44:03building a good reputation people know
44:05that like sometime town doesn't have the
44:07good amount of the money and you are
44:10helping that situation
44:12Y.
44:14>> So from my perspective, what I see here
44:15is we started with a project that failed
44:18in 2025. It's now projected out to $46
44:21million. Through the diligence and the
44:24hard work of the working group and the
44:25committee, we were keeping virtually all
44:29of the programming in this project and
44:31we've reduced the cost by 30 to 33% from
44:3646 to $31 million.
44:39That's to me a good and that's to me a
44:42good number. And I think it would be
44:43shortsighted of this committee and the
44:46working team to go to the select board
44:50or the town meeting with a with a
44:53virtually madeup number that's lower
44:56just to say that it could be passed by
44:58the select board or brought to town
45:00meeting and then we can't deliver on it.
45:02To me, that makes no sense at all. So,
45:05I'm comfortable with the work that's
45:07been done this far, and I'd be happy to
45:09bring that $ 31.2 million forward.
45:13That's my opinion. We've got a, you
45:15know, a one-third reduction in cost with
45:18the same programming. That's not easy to
45:21do in today's world.
45:24>> But I understand, but they are going to
45:25look at one more time and then they can
45:27come up with
45:28>> they constantly look at the numbers.
45:30Listen, I will just tell you that the
45:32the value that we were all brought back
45:34at, we have spent well in excess of the
45:37value of what because of the
45:41relationship. I think
45:42>> he will look at something,
45:43>> right? But we haven't just to be clear,
45:44we haven't even
45:46>> the the point of what's next. We nobody
45:50is contracted for any of that yet. So,
45:52we will absolutely look at all of that.
45:54I'll be looking at their contract. I'll
45:56be looking at their contract. I'll be
45:57looking at our durations. Yes, we will
45:59do that. But we can't do that today to
46:02drop that 312 to a lower number because
46:06if I take it out a little bit of him, a
46:08little bit of her and a little bit of
46:10us, but then the FFN doubles, I'm going
46:13to be coming back to you and saying,
46:14"Well, we we changed the number to 30.5
46:17to do that tonight." But FFN just went
46:20through the roof. So understand that the
46:23the approach of doing this as a group as
46:26a 25% markup is to basically say there
46:30are multiple spokes in the wheel but
46:33we'll contribute to that that we won't
46:35really price until
46:38until May until May of after May of next
46:40year. Right? We'll we'll do more work on
46:43it.
46:43>> All right. And we will yes we will look
46:45at it. We understand our relationship,
46:47but please understand that these guys
46:49just in what they've done in the last
46:51week have done what we asked them to do
46:53once three times already. They've done
46:56three estimates for the price of one.
46:58And there nobody's complaining and
46:59nobody's asking for extra money. They've
47:01got three representatives here tonight.
47:04They are they are a partner of the town
47:07of Shrewsbury and and we'll you know we
47:09will and we will all continue to be.
47:10It's our second job with you. It's their
47:13fourth, fifth. It's a it's a it's a lot,
47:16right? So, we want to see this built. We
47:18don't we don't participate in these
47:20meetings to just get to town meeting and
47:22then have it blow up. We want to
47:24actually build you guys build you
47:26something to help solve problems. That's
47:28the part that we love doing. So, yes, we
47:31will absolutely continue to work on this
47:34and you know, you'll you'll you'll get
47:36our best our best deal. That's you know,
47:39I think that's I think that's pretty
47:40clear from from everyone at the table.
47:43So what would you like when we throw
47:45numbers up the public it gets in Yep. So
47:48is that a GM I saw in the in the
47:51narrative you have this number but then
47:53you say you're going to develop a GMP
47:55later on down the road. Yes. So what
47:57what is this number GMBB?
47:59>> No it's a great question. So if you look
48:00at the construction number right at 261
48:03and you take away the VE let's round
48:05that out at 25 million. Now right now
48:07you we would be looking at a GMP at 25
48:10million or less. Okay,
48:11>> that is the that's the goal here. That
48:13because that's what we're saying. If
48:15we're all telling you this is the number
48:17and we're committing to it, fast forward
48:19to a year and a half from now or even a
48:22little bit more, you would be or excuse
48:24me, a year from now, we'd be looking for
48:27a GMP from these guys at 25 or less
48:30because you will have committed to that
48:32number and the citizens will have voted
48:33it
48:34>> six months from now and then we have to
48:36live with it,
48:37>> you know, for the duration.
48:39>> I understand fully on board. I just want
48:40the public to understand
48:42>> that that that number um you you know
48:45that that this is this project is what
48:47I'm hearing is that won't exceed
48:49>> from this stat this number right here
48:52the GMP won't be higher than 31.
48:54>> Yeah. Look, I I mean what I would say
48:56though is that if 312 is the number,
48:58look, if suddenly the cost of steel went
49:01through the roof and you have to make a
49:02decision to do
49:04>> $400,000 less of furniture in the
49:07building and maybe reuse all the old
49:09stuff
49:10>> and their GMP goes up to 25.4 because
49:12that's what we need to do it,
49:14>> right? What we're saying is we're
49:16committing to that 312
49:19>> again. And those other things are all
49:21all up and down, but we will make the
49:23decisions to stay within that 312
49:26because we have to
49:27>> have to because we can't go back to the
49:28town meeting and go
49:31>> h kidding. We need 400,000 more. Like we
49:33know that's the we we do not do that. We
49:37we [clears throat]
49:38>> that is the
49:39>> that never
49:41>> doesn't work.
49:42>> It doesn't work. So we don't do it. It's
49:43not even in our
49:45>> in our brain. Yeah. I think at that
49:46point if something like that were to
49:48happen, that's where we'd utilize the we
49:50we'd decide what we wanted to do and
49:52possibly use the
49:53>> the owners the owner's contingency.
49:55>> Yes.
49:56>> Um and you you kind of
49:59>> Yeah. No, it's a great it's a great
50:00point. And listen, we we also too
50:03realize that, you know, this was a
50:05deadline to get Keith to appoint to get
50:08this committee to a point to make a
50:10recommendation. There can be certainly
50:12other public meetings, information
50:15sessions to the select board where we
50:17don't just show you one blue box. We
50:19show you kind of a breakout of here's
50:22how it's built. Here's what a GMP is
50:24kind of
50:25>> ed a little more education about where
50:27we're going. Um but this is the you know
50:31this is where we are right now today. Um
50:34and hopefully it's you know enough
50:37information to um to make a decision and
50:40again pursue it like you would pursue
50:43you know the high this is essentially
50:45the way you would do the high school
50:46project
50:48>> and I just had a couple of questions on
50:49the value engineer.
50:50>> Absolutely.
50:51>> Um just to make sure that we're not
50:53removing something that's you know that
50:56doesn't make sense to remove for
50:57instance the one that grabbed me was the
50:59fuel station canopy. Can you explain
51:01what that is? That to protect people
51:03from when they're
51:04>> That's that's actually I saw it
51:05deferred.
51:06>> That was an idea.
51:07>> So that's no longer talked about.
51:10>> We would like to have that in.
51:11>> Just saw deferred and I wanted to know
51:12what that meant.
51:13>> That was on a list that we all agreed
51:16we'd like to keep that one in for now.
51:18And that that could be another lever of
51:20>> Yeah. The other ones are in there.
51:21That's right.
51:21>> And and the masonry backup wall. Is that
51:23was that the connector? Is that the wall
51:25that was we were going to put on or what
51:27is that that to be determined evaluated
51:29or
51:30>> that's around the new admin building.
51:32It's kind of right right now the um
51:34details are showing a masonry backup
51:37wall. We think we could investigate that
51:39more to potentially extend the
51:41foundation wall.
51:42>> Um but there's a little bit more
51:43studying of the um energy modeling to
51:46make sure that that would work. But we
51:48think that that could be an additional
51:50value engineering that we would pursue.
51:52>> Yeah. I mean the downsizing of the
51:54generator that makes sense because if
51:55you don't need it you don't need it. Um
51:58but the brine tank what does that mean
52:00Keith is that
52:01>> so current currently inside um so we so
52:04we have a Brian programs
52:07>> um so that system lives inside the
52:10existing highway garage. Um, initially
52:14when we worked through this new
52:16conceptual plan, we were going to move
52:17that brine system well out next to the
52:21um, salt shed and create an enclosure
52:24for it there. Um, but since we're not
52:27going to rebuild a new building, build a
52:30new building for this that we would just
52:32leave the Brian system where it is.
52:33>> Weren't we going to add some capacity to
52:36it? Another tank?
52:37>> Um, we did that about two years ago.
52:39>> That was already done.
52:40>> That was already done. Yeah. So this is
52:41just this isn't removing our capability.
52:44It's just removing what we would need to
52:45build out.
52:46>> It's removing it from the new building.
52:47>> I'm good with that. Okay.
52:50>> Okay. That was all and just that you
52:52know the other one was the coding on the
52:54aprons just not that that's something
52:56things like that you if you can defer it
52:59if it if it's because you have to
53:00consider if it makes sense to doing
53:02doing it while you're doing
53:03construction,
53:04>> right?
53:04>> You know, things might cost more after.
53:06>> And so we talk about AP. We we did have
53:08that conversation specifically about
53:09moving that out, right? and and um you
53:14know we think we still we need we
53:16certainly think we need the concrete
53:17aprons in front of the fleet maintenance
53:19garage but we wouldn't necessarily need
53:20them at the wash bay or at the at the at
53:23the um shops in the back. Um, so it was
53:27that was kind that was just a
53:28>> and that's that value there was to keep
53:31them at fleet because we you know we
53:32discussed that originally maybe taking
53:34them all out but the need for definitely
53:37um keeping them at fleet maintenance.
53:39>> This was just to code them too. The HDMA
53:41is just a a coating on top, right? That
53:44wasn't a full pull out replacement, was
53:45it?
53:46>> Um no. So that that is referring to the
53:48there's a concrete apron in front of
53:51instead of it being um asphalt.
53:53>> Oh, it's by now. It's It's shown to be
53:55concrete. Yeah. Now,
53:57>> right. Right. I thought it was pushing.
53:59I was Can they add some
54:01>> to the current building?
54:02>> Yeah.
54:03>> So So we're not talking about the
54:04current building. We're actually talking
54:04about the administration building.
54:06>> Oh, okay. The new door.
54:07>> The new fleet garages would like
54:09originally there were concrete aprons at
54:10all the overhead doors for that building
54:12and we backed that off to just the fleet
54:14doors only. And then last one, uh, would
54:18FA would I assume this project be with
54:20the elimination of disruption to the DPW
54:23building would create less phasing? Did
54:25that factor into any of this value?
54:28>> It factored into their GC's that were
54:31added into the project, right? Because
54:33the phasing, extended duration, the
54:35duration got shorter. So when the
54:36duration got shorter, their portion of
54:38the of the markup got shorter because
54:41you're on the job for less months,
54:42right? So yes. So all of those things
54:45squeezed reflected into the total.
54:47>> Oh, I just didn't see it on the calendar
54:50memory, but I thought
54:51>> Yeah, the calendar was longer because
54:52then it was another like six or seven
54:55months then the close out. So the job
54:57the job did did shorten. The other thing
55:00too to remember about about um cost
55:03valves is that you know for something
55:05that like is on the VE list that you
55:09know
55:10maybe you really wish you don't want to
55:12ve something that you really might want
55:14later or or I say want need later we can
55:17do an alternate an add alternate right
55:19so as an example if this committee says
55:22you know what Keith I know you you know
55:24pretend we had taken the canopy out and
55:26you had said I really think you should
55:28have it well we could say, you know
55:29what, let's leave it out and then we can
55:31put a an ad alternate. So on bid day, we
55:34can see, yeah, we've been tracking it at
55:36100, but if the market says it's 50
55:38because okay, maybe we buy it, right? So
55:41similarly, if there are some things that
55:42if the number is looking tight, you
55:45know, we're going to have to identify
55:46possibly some deduct
55:48>> or we're going to have HKT take
55:50something out of the job and add it as
55:51an ad so that you know, you only do it
55:55if you have the money to do it, right?
55:57So again that's all that's months away
56:00but we will that is another cost um cost
56:04relief you know mechanism so we can you
56:08know make sure that we're staying at the
56:09number or lower right all the way
56:11across.
56:12>> You know there's nothing better than
56:14giving you good good uh good news on bid
56:17day but we also don't want to be so
56:19conservative that you take something out
56:22that you really need it that you really
56:24that really is part of this project.
56:26Right. So
56:28>> try to find try to find try to find that
56:30balance throughout the process for you
56:31guys.
56:32>> And again, this is exactly why we do
56:34this process, the construction manager
56:37at risk format,
56:38>> because it it it gets rid of those
56:40variables where if if there are sudden
56:43cost overruns and again I always go back
56:45to the Doerty High project. The day they
56:48crack around on that, it was $30 million
56:51over budget
56:52>> that they didn't foresee. And that was a
56:54design fit and build project.
56:57>> So I think we're heading in the right
57:00direction.
57:01>> They're in the room. [laughter]
57:05>> This is where you say don't do that.
57:07>> I'm not saying it was there. I'm not I'm
57:08not laying fault. I think the fault is
57:10in the process, right? Like that this
57:13before we've bought anything, before
57:14we've committed any of these costs,
57:16right? We're giving, you know, the
57:18chance to change the program, realign,
57:20think through all those things, but
57:22we're also able to bring feedback from
57:24the market. Right.
57:25>> Right. And, you know, it's also a number
57:27with our relationship in town and our
57:29history in town that each of the
57:31projects that we've done, the number
57:32that we've,
57:33>> you know, put forward as part of the
57:35committee has ultimately been a number
57:37that we've been able to deliver the
57:38projects inside of. So we are
57:40incentivized like to keep the
57:41relationship to deliver reliable numbers
57:43and to you know then deliver savings as
57:46we go through the project.
57:48>> I was blaming the city for picking them
57:50up process. [laughter]
57:53>> The architect's not going to either. So
57:59>> so when you're going to like as you
58:00mentioned like when you're going to send
58:02this one you have to remove 266 as you
58:05mentioned nowaday and then later you're
58:08going to work on that.
58:09We will all the way through.
58:11>> Listen, the the decision is up to the
58:12committee, right? If you if you take
58:14that out, you're just taking money out
58:16of your contingency right now. But if
58:17the committee feels a number a round
58:19number of 31 million is better than
58:2131.2, that's your decision.
58:24>> You mentioned like, I can take off this
58:26amount.
58:26>> No, no, no. I'm not saying my No, no.
58:28I'm saying if you want to reduce that
58:30from the budget, we can find that. I I
58:33haven't calculated my fee for this job
58:34and I my boss would kill me if he told
58:36me to take $200,000 out of our fee. I'm
58:40just saying from a budget standpoint, we
58:42can get to a round number if that is an
58:44easier number to talk about. I don't
58:46know what our budget is for this job
58:48yet, but it's Yeah, I'm I No, I'm just
58:52saying from an overall standpoint, if
58:54you need that number to be a round
58:56number, fine. Make the soft cost 0.245%.
59:01It's Yeah, it's it's
59:04Yeah, we we we are not at the point of
59:08negotiating amendments to contracts for
59:11jobs that aren't approved yet. We can't
59:13we can't do that. So,
59:20anything else?
59:22>> To vote if that's the next agenda.
59:26>> That brings us that moves us forward to
59:28item number eight. discuss the meeting
59:30schedule and potential select board
59:32presentation in November.
59:35>> Are we so
59:37>> at that point?
59:38>> We are not. So I have we have a meeting
59:40with the select board on uh Monday
59:43evening. It's a workshop. Um we're
59:45discussing this project along with um
59:49future financial obligations u financial
59:52modeling um and [clears throat] be part
59:54of that and uh my hope is come out of
59:56that meeting with a um decision on the
1:00:00from the board on what they want our
1:00:04next steps to be which could be uh
1:00:06presentation to them um or something
1:00:10different.
1:00:12And at that point that now would be the
1:00:14point when we would give our
1:00:16recommendation
1:00:18um
1:00:20our voters recommendation to move
1:00:22forward um also in public setting.
1:00:26>> Mhm.
1:00:27>> Patrick, do we need a a vote to bring
1:00:29this to the select board for the
1:00:30November meeting or
1:00:31>> um presented?
1:00:32>> We do not need a vote this evening um if
1:00:36we have a general agreement for me to
1:00:37present it as it's been presented. Yes.
1:00:39a workshop and then but prior to any
1:00:43public meeting with the select board to
1:00:46actually request something then we would
1:00:48come back as a
1:00:48>> right
1:00:49>> as a committee.
1:00:50>> Yep.
1:00:50>> Um to vote.
1:00:53>> So we're okay presenting it as it's
1:00:55>> I thought I saw that that we had to vote
1:00:56to send it to the
1:00:58>> good
1:00:58>> to check for but if not that's fine.
1:01:00>> Okay.
1:01:01>> They're presenting. Okay.
1:01:02>> Yeah.
1:01:03>> Yeah. Very good. So, gen generally
1:01:06speaking, we're getting the measure of
1:01:07this committee this evening. We'll get
1:01:08the measure of the select board.
1:01:10>> I appreciate all the work that was done.
1:01:12I know it was a lot. Um, and to get from
1:01:15where we were to where we are now, I
1:01:17think is phenomenal. So, thank you.
1:01:20>> I guess one, have we talked to the PPW
1:01:22staff? Have they been involved with
1:01:23this?
1:01:24>> Staff have been involved with this over
1:01:26the summer, I guess. Um, and they we've
1:01:30done some ton of ton of work as this
1:01:32team has over the past week, but I may
1:01:34I've had one-on- ones with most
1:01:36>> so they know about kind of so we know
1:01:38where we're at.
1:01:38>> Okay.
1:01:40>> Do you anticipate another meeting? Do
1:01:42you have an idea? [clears throat]
1:01:45>> So, I don't think we can set a date on a
1:01:46meeting now. Um, I would like to get
1:01:48through Monday evening and uh work with
1:01:51the board, understand what they want to
1:01:53do before schedule for public
1:01:54conversation.
1:01:55>> Okay. Very good.
1:01:58Any other business?
1:02:00>> None.
1:02:02>> There being none, do we have a motion to
1:02:04adjurnn?
1:02:05>> So moved.
1:02:06>> Second.
1:02:06>> We have a motion and a second to
1:02:07adjurnn. All those in favor signify by
1:02:09saying I. I. Thank you everybody. Thank
1:02:11you very much.
```*