2026-09-09 - Municipal Facilities Optimization Committee
Summary
Written from the auto-generated captions; names and numbers may be misheard.
- Quorum present. Minutes were deferred to the next meeting. The committee approved a $2,623 bill from Vertex Companies, 3-0.
- The consultants compared renovating the existing water and sewer garage at 207 South Street with the new-build plan. The roof and a corner are structurally poor, and repairs beyond about 30% of assessed value would trigger full code upgrades (accessibility, life safety, structural, energy).
- The 2025 design for the South Street site was about 65,000 square feet at $473 per square foot, roughly $30.7 million; the budget taken to Town Meeting was about $35.5 million including Town Hall work. A rough renovation estimate came to about $434 per square foot, and fixing the two existing buildings would still leave a gap of about 9,000 to 11,000 square feet, ending within about $100,000 of the 2025 total.
- Presenters stressed these are rough order-of-magnitude figures with design contingency, and that construction costs have been rising roughly 5% a year. Tariff exposure is not included.
- One member said $30 million is too high to pass and asked for something nearer $25 million. Presenters answered that a cut means cutting program (offices, vehicle storage), not just price per foot. A full estimate with a reconciled second estimate is due around October 22, then a presentation to the Select Board, tentatively the November 24 meeting.
- The chair said the exercise convinced them to keep moving toward the new, more prefabricated design rather than renovating; the rest of the committee was described as in agreement.
- The architect presented the layout: an administration building (common room that splits in two for the two voting precincts, offices, locker rooms, fleet maintenance, shops, wash bay) and a separate vehicle storage building for 71 vehicles. The recycling center is designed in-house and fits on the same site; the salt shed stays.
- Three exterior options were shown (vertical banding, wedge color blocking, and a perforated metal screen on the South Street face to be priced as an alternate). DPW managers liked the layout; some had concerns about screen maintenance. Roof monitors for daylight are required by code.
- Item six on the agenda was skipped and moved to the next meeting. The next meeting was set for Wednesday, October 28 at 6 PM.
Issues discussed
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:01[clears throat] Good evening. This is
00:02the September 9th, 2026 meeting of the
00:05Municipal Facilities Optimization
00:06Committee. We do have a quorum. So, I
00:08call this meeting to order.
00:11Uh, first on the agenda, which we are
00:12going to put off because they're not
00:14ready, is to review and approve the
00:15meeting minutes. Those are not prepared
00:17right now. So, we'll put those to the
00:18next meeting. Item number three is to
00:21review and approve bills. We have one
00:23bill from Vertex Companies for $2,623.
00:29Any questions or comments on this bill?
00:34We have a motion to approve.
00:37>> I second.
00:38>> We have a motion and a second to approve
00:40the bill from Vertex Companies in the
00:43amount of $2,623.
00:45All those in favor signify by saying I.
00:48>> I. Opposed. So voted. Three to zero.
00:52>> Thank you.
00:54>> Appreciate that.
00:54>> Our pleasure.
00:55>> You get the chair.
00:57Item number four, discuss the potential
00:59reuse of the existing water and sewer
01:01garage at 207 South Street. So, we have
01:04Paul from HKT Architects. I think we'll
01:06be presenting. Welcome, Paul.
01:08>> No, not yet. I'm sorry.
01:10>> Ryan Ryan and I are going to run through
01:12>> That's fine.
01:13>> Where where we were based after the last
01:16meeting because some of the questions
01:17that came up about the water department.
01:19So,
01:19>> take it away, John.
01:20>> Yeah, sure. So we went back and just to
01:23reook at you know if you look back the
01:26information is two years old right some
01:27of the the original work that HKA that's
01:31not confusing that HKA did on the
01:34project and you know when going back
01:37through the information you know when we
01:39separated um you know we had gotten some
01:42draft information there had been
01:44PowerPoint presentations but when you
01:46dig back through it and you look at
01:47their memos there's a couple of couple
01:49of things that are striking So the
01:52uh most important so the water
01:56department building when it was
01:58reviewed, you know, the report talked
02:00about a roof that was in pretty rough
02:03shape and structurally not just not just
02:06roofing. Also talked about the um one of
02:10the corners of the building being
02:12structurally deficient and needing to be
02:14needing to be rebuilt. But all of that
02:17needs to also be taken in tandem with um
02:20you know the programmatic needs. But
02:22let's stay on let's keep stay away from
02:24program for a second. when looking at
02:26the building, you know, I think it's
02:28important and I think and Ryan will talk
02:30about costs in a second is that that
02:33building is in such shape that once you
02:37start to develop it and start to do any
02:40repairs to it, you very quickly are
02:42going to exceed the assessed value of
02:45the building. And you don't call what
02:48that value is, but once you hit 30%.
02:52You then have to bring the building up
02:53to code all current codes, right? So
02:56your 1950s something building then needs
02:58to be made accessible life safety. This
03:02is the tricky the structural code,
03:03right? And bring that building up to,
03:05you know, whatever steel needs to be in
03:07the ceiling and the walls and all that
03:08stuff. So what trends from there is a
03:12repair that costs
03:16almost almost as much at per square
03:18foot. And again, I'll defer to Ryan on
03:20that. Just to repair a building that
03:24then
03:25doesn't meet the programmatic needs of
03:28the growing department that you have,
03:30you know, fast forward 70 years from
03:31when it was originally put together. So
03:34you really need to look at those two
03:36things together. In the end, you know,
03:38you've got
03:40needs, the needs drive the program, the
03:42program drives the square footage,
03:43right? So, at the end of the day, you
03:46know, the bays and those sorts of things
03:48don't work anymore. So, that's how this
03:51all kind of came into, you know, when
03:54HKA looked at it and they just said,
03:57"No, this it's not there's nothing
03:59useful there because the cost to bring
04:01it forward would be as expensive." Uh,
04:05you know, I'll go to Ryan for a minute
04:07just to talk about the breakdown of cost
04:08and I know there's a handout on the
04:10table. Um,
04:11>> did you get that or not?
04:13>> What is it?
04:13>> Did you get this?
04:14>> Yeah, there is one.
04:16>> You got one? Yeah. Okay.
04:17>> Okay. Good.
04:18>> Yeah. So, uh, the breakdown I've
04:20provided on the table is is essentially
04:22summarizing um all of the numerical
04:25values that Keith included in the um
04:30in the summary that he provided. So just
04:32a quick highlevel review the budget that
04:36we brought to town meeting and then the
04:38subsequent town vote in total was you
04:41know approximately $35.5 million for
04:44both the town hall and the DPW
04:46renovation of that. Um one of the uh
04:50value engineer items we had was a four
04:52mill a $4 million deduct to remove the
04:55town hall renovation portion of that.
04:57So, uh, when you consider the scope that
04:59was included for the DPW South Street
05:03site, um, DPW and water sewer, we had a
05:06gross square footage of 65,020 ft at a,
05:11uh, dollar uh, per square foot cost of
05:14$473
05:16for a total cost of, uh, $30.7 million.
05:21Um, you know, following up on the
05:23discussions from the previous committee
05:25meeting, um, my team looked at what, you
05:28know, a rough order of magnitude cost
05:30would be to bring the existing water
05:33sewer garage up to code um, and, you
05:38know, just get the basic function of
05:40that building to meet the standards that
05:42we would expect um, for today. So, we
05:45provided a breakdown of that overall
05:47cost. Again, that was just based on, you
05:49know, our understanding of the existing
05:51building, based on the pictures that
05:54were taken early on, some of the um
05:57narratives that were provided and then
05:59just our, you know, our market research
06:02on, you know, H uh HVAC, fire, electric,
06:06um as well as just, you know, taking
06:08some um assumptions on that
06:10>> and that was the breakdown that was in
06:12your packet. So, correct the documents.
06:14So at that cost, we got a uh the for the
06:19existing 20,000 foot building, we had a
06:22dollar per square foot cost for the
06:24renovation of that building of $434,
06:27which is $40 a square foot less than
06:31what the 60% um design that was uh
06:35shown. But to kind of give a, you know,
06:38a global picture of what the renovation
06:40of that building looked like, we wanted
06:42to kind of, you know, lay out a plan of
06:45what we would have to do to the rest of
06:48that site to get the usage that we need
06:52or that the town needs out of that. So,
06:54of the 65,000 square ft that was part of
06:58the 60% design, 35,000 of it was the DPW
07:03renovation. That's without the addition
07:06for the uh offices or the um water sewer
07:10off the north side of the building. So
07:12using the $473
07:15of the 60% design that would be $16
07:18million
07:20plus with the two existing buildings, we
07:23had a shortfall of 9,000 square ft of
07:26programming from the previous design
07:28that we had a gap there. So that's kind
07:30of what had been previously discussed.
07:32Do we renovate the two buildings and
07:34then add a small third building? And
07:37that could be for the town staff that
07:40are currently on the second floor of the
07:41town hall or some more equipment storage
07:44for equipment that's oversized that
07:46can't fit in the existing water sewer
07:48garage. Um, so we used that 9,000 square
07:52ft. Assumed because we weren't
07:54optimizing the uh the building into one
07:57new building that you would have, you
07:59know, some ex inefficiency factor. we we
08:02ended up carrying 20% as you know a
08:05reasonable assumption for that point. um
08:08it at the same, you know, new
08:11construction cost that we carried uh in
08:13the 2025 budget. And we came up with a
08:16total cost for renovating the two
08:18buildings on the South Street site, plus
08:22net adding the square footage we need to
08:24to get to the same square footage as was
08:26previously proposed. and we end up
08:29within a $100,000 of cost between what
08:32we had shown in 2025 and what a full
08:36renovation of the existing buildings
08:38would look like. Um, so again, I think,
08:42you know, uh, we've kind of already
08:45brushed on like the the the optimization
08:48and the lack that of that that there
08:50would be with just the full renovation.
08:53Um, I think probably, you know, Keith or
08:56John would be able to speak to that more
08:58elegantly just from a perspective.
08:59>> And just just to be clear, too, the the
09:022025 design, those numbers, that was a
09:07that was not a pre-fabricated metal
09:10building.
09:11>> That was a full
09:12>> fullon structural virtual steel block or
09:15brick. Okay. So, it's important to note
09:18that, you know, the changes that we're
09:21looking at are meant to make a more
09:26cost-effective building, but essentially
09:28we're trying to also mitigate, we're
09:31trying to keep the project in the same
09:32ballpark.
09:33>> Yep.
09:34>> While we've still had three years of
09:36escalation, right? So that that's the
09:38good work of HKT, you know, coming up
09:41with a, you know, what's up on the
09:43screen to be more prefab, more um just
09:47more cost effective because if you were
09:49trying to price the 20 original 2025
09:53design right now, it wouldn't be 30
09:54million anymore. It would be, you know,
09:57something plus plus probably
10:01555% a year, right? for right now.
10:03Again, tariffs and all that stuff, we're
10:07not talking about those right now. We're
10:08just talking about what we've seen
10:10happen with with costs. It's been it's
10:13quieted after the jumps of 22 and 23,
10:15which again we had in the 25 number.
10:18It's thankfully has at least it's at
10:21least leveled, you know. Um but again,
10:24we you know, the process moving forward
10:27would be to continue to, you know, make
10:30the design as efficient as possible. um
10:33you know trying to price in some
10:37contingency to protect us a little bit
10:41>> but not you know again all the tariffs
10:43so far have
10:45they haven't really been successful
10:47right so we've heard but this is the
10:49closest we've had I've actually started
10:51to see actual customs paperwork which is
10:55the closest I've ever seen with any of
10:57this discussion but still no real proof
10:59of payment from folks I don't know what
11:02what you guys are seeing, but we're as
11:04close as we're as close to actually
11:06getting hit with those as we as we ever
11:09have. But then the question is is if
11:10they go to court and get shot down,
11:13>> then what happens?
11:13>> Then what happens, right? So my fear for
11:15any client is pay it. How do we get it
11:18back? You know, once it's paid and it
11:20goes into that black hole of subs and
11:22suppliers, you know, is it ever getting,
11:25you know, and suddenly it gets found to
11:27be,
11:29you know, doesn't stand up in court. How
11:30do I get Shrewsburg their money back?
11:32So, all of these numbers are devoid of
11:35any discussion on that, but it's
11:36certainly something that this group will
11:38be thinking about over the coming months
11:41as it plays out.
11:42>> We need tariff insurance of some sort.
11:44>> Yeah. Oh, great. Just what we just what
11:46we need another insurance product,
11:48right?
11:49>> So, John and or Ryan on this 8.77
11:52million total construction cost, I'm
11:54assuming that these costs are based on
11:56everything going almost perfectly.
12:00Yeah, I mean again this is a rough order
12:02of magnitude just based on what our
12:04current knowledge is, you know, without
12:06a heavy input from the design team. Um,
12:10so we just wanted to give the group a
12:12sense of, you know, what our initial
12:14thought would be.
12:17>> And you would also I mean there's
12:19>> there's some there's some contingencies
12:21in here which I like because you
12:24>> you haven't cracked a wall open, right?
12:26you haven't found a sin hiding in the
12:28building
12:29>> the contingencies
12:30>> hiding under the building
12:31>> they align with what we had shown in the
12:3360% too so similar to any CM project as
12:37you go along you know you go from your
12:3960% to your 90% okay we have more
12:42certainty of you know what the design is
12:44what we're doing we would then you know
12:46based on the budget constraints modify
12:48those
12:48>> and that's really important so when you
12:49look at this breakdown that Ryan did
12:51that 777
12:53it's not a it's not an outside of the
12:57number contingency. It's that the plan
12:59wasn't developed yet. And as the plan
13:01gets developed,
13:02>> more of these categories up above get
13:05more money in them and this design
13:07contingency reduces down to zero. I you
13:10know, so just want to be be clear on
13:12that. This isn't fat by a million
13:14dollars. This is
13:15>> there's design that was never done. This
13:17is a here's what I've read. Here's what
13:19they read in the narrative. Here's what
13:20they you know by walking and seeing it
13:23trying to put you know put a number to
13:24it. So
13:26>> thank you.
13:28>> So I have a question like on the this
13:301100 square foot is it pre-fabricated?
13:35>> No. Is it prefabricated? Is that what
13:38the question is?
13:38>> Like last time you guys came with the
13:39proposal of
13:41>> No, it's regular.
13:42>> Yeah, it's all custom steel and
13:45masonary. It's not nothing like this
13:48current plan which is what we went right
13:51pre. The goal is to try to get when this
13:56design is finalized to still be in the
14:00same ballpark of that 30 million
14:02although we've encountered three years
14:04of escalation. So we're trading off some
14:10building types for other building types
14:12which are very, you know, tried and true
14:14for this type of this type of building.
14:16But just the the light gauge metal
14:18framing and whatnot that's used for that
14:20to clear some of those spans is much
14:23more effect cost effective than full-on
14:25structural steel for you know which is
14:28what you know which is what these
14:30numbers these numbers had.
14:33And you're saying something 9,000 I
14:35didn't get that 9,000. What is the
14:37difference that?
14:38>> So if you look if you look at the full
14:40renovation section the the 20,200 of the
14:45water sewer and the DPW renovation at
14:4835,000 the sum of that.
14:51>> So this right?
14:53>> Yeah. So the these are the existing
14:55>> it's this one here.
14:56>> Okay.
14:57>> Yeah. These are the existing square
14:58footages of the buildings if you were to
15:00renovate them. This was the programming
15:02of the all the new project. So if you
15:05just fixed what you had and just fixed
15:07what you had, you'd still be short by,
15:11>> you know, 9,000 square ft. So we put a
15:14little bit of a contingency on it. So
15:15that's what you'd still have to build in
15:18order to fit the program into two just
15:21repaired buildings. You would need
15:23another 10,000 11,000 foot something out
15:26there. And again, and the inefficiency
15:28he's talking about is that hadn't really
15:30been designed, right? So, where do you
15:32put it? How does it affect the other
15:34buildings? And that was that was one of
15:36the problems with the other plan was
15:38that trying to attach to that
15:41>> that old building.
15:43[clears throat] It's it was creating
15:45more cost and impact to the job whether
15:48by time or phasing than just
15:51>> scrape the earth and wiping
15:53>> you know and that's also not that's it's
15:56big numbers right but if you're adding
15:59>> you know another building then you also
16:01have to add facilities for staff in
16:03those buildings whether it's restrooms
16:05locker rooms showers like that sort of
16:07thing so like said that's not a huge
16:09number but like that's another savings
16:11of having reducing the the buildings
16:14because
16:15>> shared facilities,
16:15>> you know, share shared facilities for
16:17all um makes a big difference.
16:19>> It's also redundancy, too. I mean, if we
16:21can do it in one building,
16:24>> you're avoiding the redundancies of
16:25having two or three buildings.
16:28>> Yeah.
16:28>> Yeah. Then you're just beating fixture
16:30counts by code as opposed to
16:33>> multiple multiple locations.
16:47What if we going to use the fabricated
16:50here? What will be the cost? Do you know
16:52that any?
16:54>> I think we're if if that's the we're get
16:58we're getting to that. I would say
16:59another we we're looking at octo the end
17:03of October for doing an full-on
17:05estimate. Yeah.
17:06>> And having that first number. um you
17:09know we so specifically I'm hoping it's
17:12right around the same right around the
17:15same right for for the entire entire
17:17facility but again the they'll have to
17:20you know go go to the marketplace and
17:23see you know see what it looks like see
17:25what the impact if there's been any
17:26impact of tariffs that sort of stuff we
17:29probably want to try to call that out if
17:31we could so that we can identify it we
17:33don't want to show a
17:35>> a number that's over inflated Yeah,
17:38>> you know, we don't we don't want to talk
17:39those numbers out until we actually know
17:41exactly what they are cuz that was a
17:42mistake.
17:43>> So, John, just for um
17:45>> clarification, the work between now and
17:47October, would that get us from 60% to
17:50what number? Design phase?
17:52>> So, it's actually
17:54>> it's more like conceptual or schematic
17:56design.
17:59>> It's more like what you're used to
18:01seeing when you do an MSBA school in the
18:03town, right? It's it's coming up you
18:06know you've got your conceptual working
18:08towards schematic you know scope and
18:11budget you know what you're what the
18:13scope is you know the program
18:15>> and putting a number on it then and
18:17projecting that number out
18:19>> okay
18:19>> to the midpoint of construction. So
18:21>> then we go from okay
18:22>> then we go from there. So it'll be a
18:23little more just like you would do at a
18:25school. you know, you're you're couching
18:27it a little bit more with escalation and
18:29contingency
18:30>> because it is, you know, they haven't
18:32had the time
18:33>> to, you know, from since we said go
18:35again, you know, to develop.
18:36>> I just needed to jog my memory from 3
18:38years ago as to where we were getting
18:40to.
18:41>> Yeah. And we'll utilize that budget
18:44number to go to the community. Yes. for
18:46the ask and then at that point if if the
18:49we get a favorable vote then HKT will
18:52move forward to get and this group has
18:54to live with it like we would like you
18:56would
18:56>> with the when you eventually do it with
18:58the high school
18:59>> whatever that number is
19:00>> that's the number
19:01>> that's the number can't go up
19:03>> and the advantage is this time that
19:05it'll be both Fontaine and HKT's third
19:09party estimator that will be looking at
19:10it go through a reconciliation so it's
19:14it appear I believe that didn't occur
19:16the first time around. So we will have
19:18>> so we'll have two estimates
19:19>> two estimates those will get reconciled
19:21so you know there will be a higher level
19:24of looking forward to that
19:26>> conference.
19:27>> Oh you we'll save you from that pain.
19:29We'll just bring you the results.
19:32>> It's like it's like a usually usually
19:34like a 4-hour meeting. So
19:36>> it's like a unless you want.
19:38>> It's like a family holiday.
19:39>> Unless you want to.
19:41>> Good.
19:42>> All right. So no I'm in I'm in a good
19:43place. So because [clears throat] still
19:4630 like million is the still a big
19:48number.
19:49>> Yeah.
19:50>> Um
19:51we are looking for something like 25
19:53million or something and can you suggest
19:57like where we can like this is quite
20:002,000 is going to reduce it like if you
20:02want to meet like same 65,000
20:05you can have 9,000. [snorts]
20:07See that that becomes a so if you don't
20:10agree with the program the DPW has
20:12that's a program discussion right so you
20:15need that's a discussion between you
20:17know Keith to say what am I cutting out
20:19of the program he the whole I think the
20:23whole charge in the beginning was to say
20:24okay what do we have for space and what
20:26do we what do we need for space you know
20:31that number of 65,000 has been the
20:34program for 2 years right so the issue
20:36is is if you want to reduce that by 10
20:38to 15%. Whose office isn't going to be
20:41there? Which trucks aren't going to be
20:43inside? That's the type of discussion
20:45that's moving towards right and and the
20:48just just cutting
20:5110,000 square or
20:55to shoot at a number like that.
20:58This is a big wide open building. It's
21:00more square footage than you think
21:03because the square footage is the
21:05expensive things stay. The bathroom, the
21:08HVAC systems, right? All of those
21:10components stay and you're losing big
21:13chunks of big wide open space. It's not
21:16like this is a 65,000t office building
21:18or a school where your cost per square
21:21foot of removing something. You still
21:24don't get the utility of 473 a square
21:26foot for every one you take off. you get
21:28some reduced value. It's worse in a
21:31building like this because the spaces
21:32are so big. So if the
21:36you know that's a I don't know how this
21:39group wants to handle that kind of that
21:41kind of request.
21:42>> I think I think the way the process
21:43would work is like so we get through
21:46this October through the estimate and
21:48the reconciliation and see what that
21:50number is right and then
21:52>> come up with ideas. That's when the
21:55select board as a group would decide if
21:57that number can be brought to the
22:00residents. If they decide as a group
22:02that that's number has to be less, then
22:05we go back to the drawing board and we
22:07take figure out what programming we take
22:09out of it.
22:10>> Yeah.
22:10>> So, so we we build it out to meet all
22:13needs to to needs that we're asking for
22:17and then if the select board decides
22:19that Yeah. Okay.
22:20>> No, I I feel like as for my
22:2430 million is still high for town
22:26because now I'm telling it's not going
22:28to pass. We have to come around five
22:31million less 25 then we can work on
22:34that. So how we are going to do that
22:36without losing the space and see here
22:39like last time you came with the
22:40fabricated and this time prefabricated
22:43and you are didn't add the
22:45pre-fabricated this time. We want that
22:47like job so we can
22:48>> right but but understand that the
22:50difference between the prefabricated
22:52savings is being offset by construction
22:55costs going up 5% every year. The longer
22:57you wait if you wait two more years 25%
23:01of your increase is just from waiting.
23:04So the longer you wait you you can't
23:06your your 30 million use that number
23:09every year gets you less and less and
23:11less and less and less. Right? So that's
23:13the that's the the trick here. So, it's
23:16finding that right balance between
23:18>> a budget that will pass cuz right, you
23:21don't want you don't want to get to a
23:22point where people say no,
23:23>> right?
23:24>> Again, there's been some good some good
23:27thought and some good alternatives that
23:29have been brought up. So, it's what's
23:30finding that right that right
23:32connection.
23:33>> This is just construction. Is this just
23:34construction cost or was this was this
23:37the to this was total budget?
23:38>> This was not
23:41>> just construction. Right. So the the
23:44other piece that there are other costs
23:46that will go into that
23:47>> my perception like in 11,000 square ft²
23:50if you use prefabricate definitely you
23:52can save some money there.
23:54>> Yes.
23:55>> So but yeah not right you didn't put
23:57right now but you can think about that
23:59also other option.
24:02>> Yeah I think I think that's just we just
24:04have to get through the process to see
24:05what the savings is.
24:06>> Yeah and under and again understand that
24:08this is just this is just construction.
24:10That's a good Right. So on top of that
24:12you have soft costs you have
24:15>> I mean FFN in something like this isn't
24:17huge because it's a lot of
24:19>> storage but it's not it's not zero right
24:23or you know it's the decision of are you
24:25taking all the old furniture with you or
24:26you know all of those things which we
24:28haven't gotten that far yet but all of
24:30that will be in the number we put
24:32together
24:32>> after the October estimate to say okay
24:35here's where we are now and okay what do
24:38we do now
24:38>> and then we'll present in November to
24:40the board and based on the programming
24:43>> program I'm giving you the like as per
24:45like what I think
24:47>> of course
24:47>> number will come around 25 going to pass
24:50like residency this number is a good and
24:53we are using the existing existing
24:55properties renovating them not like
24:58throwing something new we're not
25:00building anything
25:01>> and that's good idea like reuse it any
25:03longer
25:06>> okay yeah just I mean for perspective if
25:09you took
25:11Uh um if you cut, you know, 25% of that
25:16473, say you went to a prefab building
25:20and whatever whatever way we were able
25:22to minimize the cost and you dropped
25:24that cost just for round numbers to $350
25:27a square foot, the cost for that
25:29building would still be just under $4
25:31million. So you would still like even if
25:35we were able to say renovate renovate
25:37and you know go with the cheapest
25:39possible option which I don't even know
25:40if you could build an it would likely be
25:43office heavy than that for 350 you would
25:46still you know we'd be saving a million
25:49just you know a million and a half just
25:51under that. So it's like we're we don't
25:54want to chase this too much. This was
25:55just trying to give a high level sum.
25:57>> Yeah. No I think that Keith's point is
25:59is is is right on. let's
26:02>> move with this, take those comments, you
26:04know, and and again, we're nowhere close
26:06to saying this is the job, right? So,
26:09this is just the this is just the next
26:11step.
26:11>> The other thing I also noticed for for
26:14renovation also you still like 434 that
26:18like looks higher. New you are charging
26:20473 but for just like how many dollar
26:24less? $40 less.
26:26>> Yeah.
26:27Well, but he in the packet that Keith
26:30sent out, you've got his breakdown.
26:32>> Yeah. It comes with, you know, it's
26:34that is the biggest misnomer with
26:36renovation is is that while we're
26:39renovating so much of what if you have
26:42to repair so much of what you have and
26:45bring that up to code,
26:48it it's not always the cheapest option
26:50and it's not always if it is the least
26:54expensive option, it's always not by
26:56much. We see this on every job because
26:58people leave out the code upgrade piece
27:01of that. There are things that you just
27:04can't quote just fix. There's things you
27:06have to fully upgrade because of the age
27:08of the building. So, if you take a look
27:10at this the sheet that Keith sent, this
27:13is the breakdown and what drives that
27:15434. It's not a
27:18you know, it always it seems like it
27:20always comes out close in the end
27:23because with aged buildings, there's so
27:25much to do. Renovating something newer.
27:27Sure. Right. But something that's older
27:30can be, you know,
27:32>> can really can really.
27:33>> It's not the stairs that's driving this
27:35number.
27:35>> No, [laughter]
27:37no, no. It's lots it's lots. It's it's
27:39death by a thousand cuts, right? It
27:41really it's it's all the divisions of
27:44work, right?
27:45>> The breakdown.
27:45>> People think about the aesthetics that
27:47they see renovation also. You talking
27:49the same rate of same rate for new
27:51construction and same rate for
27:53renovation.
27:56Yeah, that's what Yes, that's what they
27:57carried. Yeah. Again, you have to
28:00understand that the that the
28:03they priced what was on the drawings
28:05last, you know, last time and this is
28:08>> there should be some difference like
28:10there should be different when you
28:11already have existing infrastructure,
28:13you have to make it up to date with that
28:15or
28:16>> sure but at the end of the day
28:17>> the price I can't see any difference
28:19like new new construction and renovating
28:21the existing construction they totally
28:24>> sure but at the end of the day if you
28:25took $40 off of all these prices it's
28:27still a $27 million ion dollar job, not
28:2930, right? It's not it's 10, it's going
28:32to come down 10%. So, yes, but in the
28:35end, understand that it also wasn't
28:38they made some assumptions based on a
28:42renovation that wasn't designed on
28:45buildings that weren't fully, you know,
28:47there was no design. You know, this
28:48number at the top was a set of 60%
28:51building plans, right? Plan specs, the
28:53whole nine yards that drove a number.
28:56This this lower half of the sheet is
28:59really about a rough idea if I renovate
29:02it. Right? So you you it's a fine point,
29:06but they had a reason after they looked
29:07at it internally.
29:09Okay, it's not 4473, it's 434, right? If
29:13you dropped all of it by $40, you know,
29:16yeah, you'd save 1.6 million. So we'd be
29:18at it'd be a million dollar difference.
29:20a million and a half dollar difference
29:21is a million and a half enough to use an
29:24old building and have it not meet your
29:26programmatic needs. So that's the
29:29>> the point is is we're looking at very
29:31specific numbers that were obtained
29:34>> 3 years
29:35>> but without the specificity of a
29:38detailed set of draws in in reality
29:41these numbers should be 8.700
29:4416 million straight and 5.300
29:48because by giving them
29:50>> dollar values to the single digit we
29:53give the idea this 30.7 7
29:58>> is way more specific
30:00>> than this 30.8.
30:02>> And so we could have discussions about
30:04it could be 31, it could be 32, it could
30:06be 27. All of those are true depending
30:09on what the actual details of what we
30:12actually do for scope, right? What we
30:14design.
30:15>> So John, I have a question on the um and
30:18I'm going to carry this exercise a
30:19little bit farther just so a little more
30:21clarification. The numbers that are
30:23used, the 473 number for cost per square
30:26foot, those were the numbers that were
30:27driven three years ago, right? Three
30:30years.
30:30>> Well, 20 in the March 2020,
30:32>> the rena number
30:34>> and in 2025, so year and a half, two
30:36years ago. So, it's with an except you
30:38were talking about 5% a year increase on
30:40construction costs. So, that would that
30:42473 is probably closer
30:45>> by next year.
30:47>> So, did you price did you look at these
30:49for right for right now? Was that 473 in
30:52today dollars?
30:53>> I would have to ask Shane. I'm not sure.
30:56I It may It may have been a direct poll
30:58from our estimate.
30:59>> That's my point. So I guess my point is
31:01that that cost is probably if those are
31:03from 2023 or even 2025,
31:06>> it was 2020. It would have been
31:07>> going to be higher than that. So So the
31:09del So the delta between the 434 and the
31:12473 is actually going to be greater.
31:14>> But even
31:16uh could be Yeah. But also too remember
31:20up above you're using a 473
31:24from 2025 itself. So even if you took
31:27that the you know the cost to do that
31:29building from two years ago
31:32>> you know
31:33>> or year and a half ago is no longer 473.
31:37It's 473 * 1.075
31:41do 18 months. That's my point. So it's
31:42not 30 anymore. It's 30 something. So it
31:44it makes renovation of anything even
31:46less of an option in my opinion
31:49>> if these numbers are newer.
31:53Yeah. Look, the numbers are clo I think
31:54the exercise that Fontaine was trying to
31:57show is that
31:59>> the numbers are close.
32:00>> Yeah.
32:01>> And what you can't see in comparison of
32:03numbers is the program.
32:06>> What you're going to see on the screen
32:07that they've been working on is a heck
32:09of a lot better than if you just made
32:12what you had
32:14better. And again, that last 11,000
32:16square feet, what is that? Where do you
32:19put it? Where do you drop it on the
32:20build? You know, there
32:22there was no design thought to that. It
32:25was just them saying, "We're 11, you're
32:2711,000 ft short of this 65,000
32:31>> square feet number." Yeah. So, to to
32:33point,
32:34>> yeah, if you get to a point where you've
32:35got to cut program to fit into a budget,
32:39the discussion of where you would cut it
32:41hasn't even happened yet. Right. right?
32:43You know, do you vehicle storage
32:45building cut it in half? Like, who
32:46knows? Like, that'll that's the stuff
32:48we'll have to talk about next. But until
32:50we had a
32:51>> plan that everybody bought in on
32:54>> at least roughly,
32:56>> that's where I'm trying to get to.
32:57>> You've got to start because then you
32:59start throwing price darts at it and
33:01suddenly
33:03>> you're talking about specificity that
33:05doesn't exist yet, but we're trying to
33:06get there. So I think what this was to
33:08try to talk about was that
33:11yeah the water department building
33:15would be almost as expensive as the as
33:18the new build
33:19>> then even if this is let's say these are
33:21all 2025 numbers.
33:23>> Um and I'm not surprised that it's not
33:26only off by a few dollars. I have this
33:28discussion
33:29all the time on school projects where
33:32the cost of renovation
33:35is all is often very close to the cost
33:38of new because all of those code
33:40required triggers force you to do things
33:43that you don't see. They're all above
33:45the ceiling and at the end of the day
33:46then you still have to make the building
33:48look better for the workers or for the
33:50students or whatever the subject right
33:52>> wherever the tenant is. But you spend a
33:54lot of money on systems that are old and
33:58past their useful life. And the only way
34:00to get to them is to tear down ceilings
34:02and to tear down walls that you then
34:04have to put back. So you get no no
34:06increased value.
34:07>> It's like a car
34:08>> from a program.
34:08>> You can keep fixing a car forever at a
34:11certain cost, but eventually it's going
34:12to have to be replaced.
34:13>> Oh, true. And then you've also got the
34:16energy code, too. We didn't mention
34:17that. So it's not just structural. the
34:18new energy code that the state has. It's
34:21it gets harder and harder to meet the
34:23codes
34:24with older construction, right? Just
34:26because, you know, windows aren't
34:29windows are now largely double and
34:31triple pain when you put them in. I
34:33appreciate I appreciate the exercise you
34:35went through and it it opened my eyes a
34:37little bit to really convince me that I
34:39think moving forward with a prefab as
34:42opposed to a renovation. I'm very
34:44comfortable going in that direction as
34:46opposed to renovating
34:48>> and and we'll have the rest of the
34:50committee feels the same way.
34:52>> We'll end up and we'll have again within
34:55you know six weeks we'll we'll start to
34:58have those numbers back, right? Is that
34:59what we we talking about? We talked
35:01about reconciling on like the 22nd of
35:03October,
35:04>> somewhere that third week of October.
35:06So, we'd be ready to have a discussion,
35:09>> you know, start, you know, show you the
35:11reconciled numbers probably the
35:12following week and then talk about,
35:15okay,
35:16>> what do we think we need to do in
35:17preparation for the select board
35:18November,
35:19>> you know, and if that number is and
35:21folks are, you know, who knows what the
35:23who knows what the market's going to do.
35:25>> Are you comfortable moving in that
35:26direction?
35:27>> Yeah. Can I this? So you you see this
35:30rate uh the rate like we put a for
35:34renovated DPW also 473 y
35:36>> and DPW building is better condition
35:38than the water and sever building but
35:42you still like put the rate so the rate
35:44discre discrepancy there I don't know
35:47who put that one
35:48>> it should be different that building
35:51still needs to be renovated and
35:52>> brought renovated
35:53>> no no what he's saying is if water's
35:56worse why is the DPW number showing
35:59So the rate discrepancy is there. So it
36:01come with the right numbers. The number
36:02is not right. Somebody copy copy cut and
36:05paste. So number is not right.
36:09>> Well the 20
36:10>> Oh no but the DPW rena required the Oh
36:13you were attaching
36:15>> you were attaching the new building to
36:16the to the re building the existing.
36:19That's what that's what jacked up the
36:20cost.
36:20>> That's right.
36:21>> That's why that was more expensive.
36:23>> That's right. It wasn't a pure
36:26>> just renovate it. It was you were going
36:28to be attaching
36:30this extra 11,000 square ft if I'm
36:33correct
36:34>> with the second floor
36:35>> with
36:35>> to a building that structurally couldn't
36:38handle it. That's what drove the DPW
36:40cost higher. Yeah.
36:41>> Because you you couldn't bolt you
36:43weren't going to bolt that extra
36:44building to the water and sewer. You
36:46were going to bolt it to the DPW. Took a
36:49while. Two years, right? Um you were
36:50going to bolt that to the backside of
36:52DPW. I remember Fontaine saying at one
36:55meeting that people didn't understand
36:57how much work that actually was to try
37:00to save the DPW building to scab onto
37:04it. Like one of those walls was going to
37:06completely deteriorate if they tried to
37:10touch it. So they were going to spend
37:11extra money to try to save it so that
37:14you could make that connection. That's
37:15why. So it's the condition of the
37:18building itself. So, it's not it's not
37:21that you're renovating it. It's that you
37:23are renovating and attaching something
37:25to it. So, yes, if you were going to not
37:28do this 11,000 square ft, yes, you
37:31probably could do that 35,000 square ft
37:34for less, but because you were going to
37:37attach to it, that's what drove drove
37:39the number higher, if that makes sense.
37:42So, it's not a wrong number. It's that
37:44given the fact that you were going to do
37:46an additional renovation to it to add to
37:49add program
37:50>> you could put the whole we could put the
37:52whole building all 66907
37:55at 434 [music]
37:57and you end up changing it by $2.5
38:00million and that 470 that 474 it's not
38:05completely 2025 or 2026 pricing too. So
38:08you end up at 18 months of inflation and
38:13we're not we're not far off. We I think
38:16you know the purpose of this exercise
38:17was to show that the in our eyes was
38:20that the water sewer garage renovation a
38:22full renovation doesn't get us to a $20
38:24million project with the snap of
38:27fingers. I think was what our intent was
38:30if that makes sense.
38:36We have more work to do.
38:37>> Mhm.
38:38>> We have more work to do.
38:39>> Yeah.
38:46>> So, where are we now?
38:49>> Well, I think we have to get my opinion,
38:51I think we I think we just have to get
38:52through the estimate process and then
38:55>> see what those numbers are and then work
38:57through the program to see if we have to
38:59reduce it from there.
39:00>> Yep.
39:04Should we move on?
39:07All right. So, that would bring us to
39:09Paul for the
39:11>> Thank you. The sectional design portion.
39:15Okay. I'm not sure how far back um I
39:20should go and trying to update
39:22everybody, but I will
39:25give you a quick summary on what we've
39:28done so far. So this is the proposed
39:31reworking of the site and we did this in
39:35a sharet process as everybody been
39:37hearing all of how we got to this
39:40layout. So the idea is to take down the
39:44existing building here build the new
39:46administration building and then once
39:48that's done work on the vehicle storage
39:51building. sort of a phasing but using
39:53the same the same site. The existing
39:56salt shed would stay and this new
39:58recycling center that's currently being
40:00designed is being fit onto the site as
40:02well. Um the parking the vehicular
40:05circulation [snorts]
40:08main entry would be there. The vehicles
40:10could move around the site and use the
40:12existing driveways there. This driveway
40:14would serve the recycling center and it
40:17would be enclosed and separated from the
40:20public parking here that would be
40:21accessing the administration building.
40:24Um, all of the traffic back in this
40:25portion of the site would all just be
40:27DPW staff. The public would be back
40:29there. Um, there is parking here and
40:32here. And then there are a few parking
40:35spaces here for city vehicles that would
40:37stop by the administration building to
40:38pick up parts, things like that for
40:40vehicle maintenance. And then I think at
40:43some point we'll have to coordinate with
40:45the design of the recycling center to
40:46provide an access here so we can access
40:49from the yard. Um and the fueling
40:51station it's current this is an older
40:53plan that's currently showed here. We've
40:54moved it already up to there. So those
40:57are the two main buildings that we're
40:59dealing with for that.
41:01>> And then just so everybody's aware the
41:03recycling center is being designed and
41:06developed by our our engineering
41:08department in house. That's part of the
41:10Swiffer program. Um, but HKT is so HKT
41:15is generally keeping that blank because
41:16we have a sharp design in place for
41:18that.
41:20I'm going to show you plans for two
41:23buildings. So, this is the
41:25administration building. The parking lot
41:27is on to the left side of the building
41:30there. The lower drawing is the first
41:32floor
41:38and the entry would be in that lower
41:41left corner.
41:46This is the common area and at the
41:48moment we still have the partition that
41:50would divide it into two spaces if
41:52that's needed. This is would be used for
41:55voting and community events. They'd
41:57[clears throat] enter in off the lobby
41:59and then from this lobby you'd also
42:01access the offices for the DPW. We put
42:05the conference room here so it can be
42:06used either by the office or for other
42:09events as well. It's directly accessed
42:11from the lobby. Uh we've got private
42:14offices around the perimeter of the
42:15building and then the open office with
42:17workstations in the middle and then a
42:20meeting room, couple of meeting rooms, a
42:22quiet room or lactation room,
42:24highdensity storage and a work coffee
42:26room and a small coffee point here for
42:28meetings that may happen in house there.
42:32And then off the lobby, we have two
42:33public restrooms.
42:35Off this back secure hallway, we've got
42:38staff restrooms and janitors. And then
42:41this kitchen would serve the office area
42:43and can be accessed through that hallway
42:46at the back.
42:48And then as you come down the hallway,
42:50we've got the locker rooms. The locker
42:52rooms themselves would be unisex. All
42:54the showers, we have four shower rooms
42:56there would be unisex as well. Off the
42:59locker rooms, we have a men's bunk room
43:01with 32 beds and a women's bunk room
43:04with eight beds.
43:06And then on this side of the plan, we've
43:09got the um superintendent and dispatch
43:13area, the highway foreman and war room,
43:15the park superintendent, water and sewer
43:17offices, and a records office there.
43:20And then this is actually an opening, so
43:22you can walk through this hallway to
43:24access fleet maintenance and the
43:27offices. And as you start heading
43:29towards the east side of the building,
43:32there is a decon and laundry area and
43:34that's accessible from the yard. It can
43:37also access directly into the locker
43:38rooms.
43:40And then the southern portion of the
43:42building [clears throat] is fleet
43:45maintenance. Let me maneuver over there.
43:49And the upper portion of the plan is the
43:52shops for water, sewer, highway, and
43:55parks. And then fleet makes this all
43:57down here. And then the wash bay is a
44:00drive-thru bay at the far end of the
44:02building.
44:05And then the upper floor
44:09is primarily just mezzanines
44:12and mechanical areas. So accessing it
44:15from fleet maintenance, there's a stair
44:16going up here. There's a mezzanine for
44:19storage there. The mechanical space is
44:21over the storage room that's below. And
44:24then the water sewer mezzanine is above
44:26the uh welding shop and the
44:28decontamination and laundry area. And
44:31then in the wash bay, there's also a
44:32mezzanine over the equipment room there.
44:44And then this is the vehicle storage
44:47building.
44:53We presented three options to the DPW
44:55team and this was the one that they
44:57picked that accommodates kind of the
44:59best mix of vehicles and also the
45:02accesses I think they thought could be
45:04more useful for the various divisions
45:07within the DPW. So the main portion of
45:09the garage here is drive-thru with
45:12angled parking for large and extra-large
45:14vehicles. We also have small mechanical
45:17spaces and a toilet in the upper left
45:19corner. And then these bays here, we've
45:23got tandem parking access from the south
45:25and the north. We have some smaller
45:28vehicle and storage spaces in the middle
45:30separating the two sides. And then these
45:32bays here are accessed from a door on
45:35this side. And then you see the fuel
45:37station has been located up there. And
45:40in this plan, we can accommodate 71
45:44vehicles.
45:47And then this also has a mezzanine. And
45:49this might get fine-tuned as we move
45:51into design, but the mezzanine areas are
45:55just over this northern portion of the
45:58plan here.
46:08That is the building plans. And then
46:12we are presenting three options for the
46:16exterior massing and the look of the
46:18building. And two of them are just using
46:23the um pre-engineered metal building and
46:26the insulated metal panels that are
46:28pretty standard for those. And the
46:30colors that you see are just to provide
46:32some visual interest to try to break up
46:34the large size of the building. But it
46:36would be
46:38I think pretty negligible negligible
46:40cost to change them because it's the
46:42same material. It's just getting a
46:44different color of the material. The
46:45third option we're showing has a screen
46:48that's on the main facade of the
46:50building facing South Street. And
46:54we're proposing that as a way also to
46:56try to break down the scale of the
46:59building and make it a little more
47:00street friendly and also providing some
47:03sort of solar shade because that whole
47:04face of the administration building is a
47:07large face to the west. So we were
47:09hoping that that screen would provide
47:11some shading for the occupants inside
47:13the offices on that side of the
47:15building. So this option is option A and
47:19it's the banding option. Just an
47:22overview of the site.
47:29Uh we've got the administration building
47:31here, vehicle storage there,
47:34administration and maintenance, the
47:36recycling center. We took a shot at what
47:38that might look like. And and the uh
47:41salt shed there. And and the site stays
47:43the same on all three of the the images
47:46I'm going to show you here. So the main
47:48idea of this and we've also had been
47:51requested to provide some monitors
47:52rather than skylights for the open
47:55office down below because it's a very
47:56large space and people towards the
47:58interior are pretty far away from the
48:00windows and don't get natural light. So
48:02the light monitor facing north will help
48:04them get light for that.
48:06>> And Paul, if I don't mind Oh, yeah.
48:08>> interrupting. And I think a point here
48:11to note is that we are required by
48:13building code for a space that size to
48:15have roof lighting or monitor lighting.
48:18Um and then working so working with our
48:20team um they chose this style as opposed
48:24to skylights because skylights are a
48:26facilities person's worst nightmare. So
48:29um kind of switched this that that was
48:32kind of the focus here, but it is
48:33required by code. And then, you know,
48:35one of the things that we heard, you
48:37know, a year and a half ago or two years
48:39ago when we started this process from
48:40our staff. Um, and this building is a
48:43clear example of that. There are many
48:44offices where there's no u natural light
48:48at all. Um, so this is helpful. It gets
48:51that whole pool area some some good
48:53light.
48:55And I have one question like why will
48:57you have two common areas not one
49:01the first
49:01>> oh and I think that was because it in
49:04the event that something needs to be
49:05happen in one of the common areas that
49:07partition can be closed off and then the
49:10other half could still be used by the
49:11DPW staff because that will basically be
49:13like a meeting room training room lunch
49:16area. I mean, that's that's it that's
49:18actually its main purpose is for
49:20meetings and and trainings for our staff
49:23and be able to have that separate. So,
49:25like if there's a training going on, you
49:27could still use the other space for
49:28something else. Um, and then I don't
49:31know if we'll get to a point where that
49:33is for public space other than voting,
49:35but like to be able to open that all up
49:38for the voting one, two, three times a
49:40year. what it is, what's the other has
49:42always been part of that process because
49:44>> and the voting the voting is there are
49:45two precincts there. There's precinct
49:47five and 10. So you need to petition in
49:49the two different rooms in order to
49:51accommodate each precinct separately.
49:56>> All right. So the main concept for this
49:58option is kind of the vertical banding
50:03on the buildings and the administration
50:05building and the vehicle storage sort of
50:07tie into each other with that vertical
50:08banding.
50:17So that's a bit more of a straight shot
50:19at the administration building. A look
50:22down the yard between the two buildings.
50:24And then this elevation is the side of
50:28the administration building there.
50:32And there are clear story windows at the
50:35maintenance portion just to try to get
50:36daylight in again to try to meet the
50:38energy code for daylighting within a
50:40space that is a certain story high,
50:43certain height and um just the square
50:45footage you need to uh provide
50:47daylighting inside there.
50:53Then just a couple more views of the
50:55vehicle storage building. On both
50:58buildings, we're providing CMU Wayne
51:01coat at the bottom just to try to
51:02protect the metal panels, keep them up
51:03off the ground so they don't weather it
51:05and deteriorate just from salt and
51:08weather and also vehicles moving around.
51:10So, it tries to keep the building
51:12somewhat protected with a more durable
51:14base.
51:19And this next option is the wedge. And
51:22it's because we've got this we're using
51:25the different colored panels there that
51:26kind of have these two different wedges
51:28meeting on the administration building.
51:31And then the vehicle storage has a bit
51:34more of a color blocking um pattern to
51:37the insulated metal panels.
51:44And there's front facade for the
51:46administration. The same view down in
51:48between the buildings into the yard and
51:50that south elevation of the
51:52administration building.
52:06And then this last option is the screen.
52:08This is the one as far as pricing. We're
52:10going to ask that it be priced as an
52:12alternate so the town can decide whether
52:14they want to accept it or not. But the
52:17main element is this perforated metal
52:20screen that will be out the front. The
52:22building itself is going to be a little
52:24more simple. We won't have all the color
52:25changes because the screen sort of uh
52:28has that element to break up the
52:29building and to present a more um
52:32communityfriendly face, I guess, to the
52:35to the street.
52:41These are the same angles on the
52:43administration building
52:48and then the vehicle storage building.
52:54That is it.
52:56>> Thank you.
52:58>> So you it's almost a metal screening
53:00right over the windows. Mhm.
53:02>> Got it. Like a diff diffuser.
53:04>> Exactly.
53:12Great.
53:13>> And and just so everybody's aware, um
53:16all DPW division managers met with um
53:20all our Navy last met with HKT last
53:22week. Um
53:25and they brought m they brought more
53:27designs to us. We narrowed it down to
53:30these three here. Um we worked through
53:33the actual programming of it. Um there
53:36were very minor um changes, doors here,
53:39doors there, a couple other different
53:41things, but um for the most part um you
53:44know, and our group was really I think
53:46excited at this point about what they're
53:49seeing here. Um and I have not heard any
53:53negative comments since the meeting. So,
53:55I take that as, you know, everybody was
53:57really pleased with the way the layout
53:59was happened and um I I think it's been
54:02a good it's been a really good uh
54:04process.
54:05>> Was there a preference on the design?
54:07Did I don't know if they saw all three
54:09design options.
54:11>> Um I think the the the com the
54:14conversations were more about the roof
54:15line and the windows. Um there were some
54:18com comments about the screen. I think
54:21there is a little concern about the
54:24maintenance of that and what that looks
54:26like. Um, but HKT is, you know, we
54:30talked about u they showed us some
54:32different options for that too. So,
54:34we'll still work through that with uh
54:36with to understand it better.
54:39>> Sure.
54:42>> And if you'd like to see anything else,
54:44let me know. I'll I can run back through
54:46any of the plans or
54:48>> No, no. I mean obviously I mean I'll you
54:51I'll be there occasionally to vote
54:53assuming I don't move but it's really
54:55it's really the town's building and it's
54:57it's the it's the worker the workers are
54:59going to be going there every day. So I
55:01like you know to a to a certain extent
55:05short of you know some exorbitant cost
55:08defer to what their preference is
55:10>> I and I think
55:11>> I think that workplace environment I
55:13think is very important. Mhm. And
55:15>> I think HKT did a good really good job
55:17of um
55:20really make having a lot of efficiencies
55:22within the space. Um we [clears throat]
55:24have some room for growth. Um like
55:26there's a couple of extra
55:29>> um private offices right now that we
55:32don't have people for. Um the pool area
55:36has plenty of room for some growth in
55:37there with staff. Um, but you know, I
55:41think they did a real good job keeping
55:43everything pretty tight and and fairly
55:46efficient. So,
55:48>> would the mezzanine areas be areas of
55:50potential expansion depending on what
55:52would happen, you know, say 20 years
55:54from now?
55:55>> Depends on the type of expansion
55:57>> that's proposed for that because
55:58mezzanines are restricted to the amount
56:01of area that they can
56:04cover.
56:05>> Okay? because they're open to the the uh
56:08level below
56:09>> and so by code they're restricted to how
56:11much how big they can be relative to the
56:13area that they open onto they also need
56:16to stay open so if you start enclosing
56:18it I'm working on a project right now
56:19goass it where they enclose their whole
56:21mezzanine and it's wildly
56:24[clears throat]
56:24>> against code
56:26>> so you just you can use it but you you
56:28have to be careful in how
56:30>> and I think in this case like those
56:32mezzanines were really used for a
56:34inexpensive
56:35storage solution
56:37>> um to just utilize that space,
56:39>> you know, because we have the high roof
56:42line in the maintenance area. We need
56:44that for the
56:45>> for the fixing the trucks. So, I think
56:48we just
56:49>> it would be important to note that
56:50that's
56:51>> that upper part of the picture. It's not
56:54a true second floor, right? So when you
56:57make reference to it, it's really just
56:59the
57:00>> these four the three or four orange
57:02platforms, you know, that are that look
57:05like
57:06>> crawl space type of
57:07>> except it's it's it's no it's tr truly
57:10truly a structure that you'll, you know,
57:12set of stairs to go up and it's do it a
57:14lot in fire stations and as well just to
57:17because you have the clear story height.
57:19>> Yeah.
57:20>> How can we make some storage without
57:23>> paying for an entire second floor?
57:25>> Makes sense. I mean, our current
57:26building actually has a few of those
57:28already.
57:28>> That's what I was Yeah.
57:30>> Yeah. Yeah.
57:38>> Yeah.
57:40>> Any other questions for Paul?
57:45>> No. Keith? No. No.
57:47>> Anything for John or Brian?
57:51All right. We'll move on then. Item
57:52number seven, discuss the meeting
57:54schedule and potential select board
57:56presentation in November.
57:57>> Do you want to do Can we do six?
57:58>> I'm sorry.
58:00>> Are we good? Do we need to talk about
58:01six?
58:02>> I'm No, it's my bad.
58:04>> Um
58:05>> I know we have to redo it.
58:07>> Yeah. So, I think we'll skip six.
58:09>> Okay.
58:09>> Okay. So, we'll move that to the next
58:11meeting.
58:11>> Yeah.
58:13>> So, discuss meeting schedule and
58:15potential select board presentation in
58:17November.
58:19>> I think so. So I think um
58:26so I'm not sure there's a need for a
58:28MOAC meeting between now and
58:32October 22nd when they're going to do
58:34their reconciliation.
58:35>> Mhm.
58:36>> Um so I would look to
58:40this group to decide if
58:43having a meeting that following week is
58:46appropriate or the first week of
58:49November.
58:51So the question I would have so what I
58:54would say is is if you could plan for
59:00let's assume the number tracks where we
59:01hope it tracks and stays where it is
59:04right I worry that if we have to have a
59:06we need to have a meeting right we need
59:09to have it in o uh maybe sooner rather
59:12than later um
59:16so maybe set it up for that last week of
59:18October but If
59:21>> you know what I'm saying, right? If we
59:22if if it suddenly comes in and we're
59:24like, "Okay, we got to run back to these
59:26guys and say, come up with some options,
59:28>> not to finalize it, but just come to the
59:30end with,
59:32>> hey, here are some thoughts on how we
59:34could
59:34>> make some adjustments if the market has
59:36gone crazy or anything with tariffs and
59:38all that."
59:39>> Um,
59:41but that doesn't happen instantaneously,
59:43right? So, I guess when would you want
59:46to let's work backwards. Perfect
59:49scenario. When would you want to meet?
59:51When's a select board meeting?
59:54>> So, we haven't chosen one, but I think
59:56we're targeting the second meeting in
59:59November, which falls on third week,
1:00:03>> week the 16th.
1:00:05>> It would be November 24th would be this
1:00:08would be the second meeting in November
1:00:10for
1:00:11>> That's plenty of time. Okay, good. for
1:00:13select board.
1:00:15>> I just want to make sure we had enough
1:00:16time
1:00:18to react. That gives us a month. I mean,
1:00:21we would take it all obviously, but if
1:00:24I would say plan an MC meeting for that
1:00:28last week of October,
1:00:31>> and if we need to pivot because
1:00:34something happened, we can then
1:00:36communicate and maybe push an extra week
1:00:39if the team needs time to
1:00:41>> Do we want to plan? I know there's a
1:00:44couple people missing, but um the 28th
1:00:47at 6 PM.
1:00:49>> Sure.
1:00:52Yeah, I can do that. Does that work for
1:00:55you?
1:00:55>> Yeah, it's fine too.
1:00:58>> Mark.
1:01:03>> Okay, let's just Yeah, stick with that.
1:01:08>> October, right?
1:01:09>> 26th on October.
1:01:11>> 20 October 28th.
1:01:14Wednesday,
1:01:15>> Wednesday, 28th.
1:01:27>> [snorts]
1:01:30>> All right. Then if we need another
1:01:31meeting, we will
1:01:33yeah put one together.
1:01:38Let's hope not. All right. Anything else
1:01:40on meetings?
1:01:43There being none, item number eight,
1:01:44other business.
1:01:46Anybody have anything else?
1:01:50Oh, I don't
1:01:51>> going once, twice.
1:01:53>> Oh, thank you.
1:01:54>> Three times. All right.
1:01:56>> Item number nine, motion to adjurnn.
1:02:00>> So moved.
1:02:02>> Second. I have a
1:02:02>> motion and a second to adjurnn. All
1:02:04those in favor? I I
1:02:06>> Thank you, everybody. Thank you, Mark.