What: replacing the DPW and water and sewer facilities on South Street with a new administration building and vehicle storage building (about 65,000 square feet), versus renovating the existing buildings. The 2025 design was roughly $30.7 million.
Where it stands: on 2026-09-09 the committee leaned toward the new, more prefabricated design; a full estimate is due around October 22 and a Select Board presentation is targeted for November 24.
2026-10-29 - 2026-10-29 - Municipal Facilities Optimization Committee: Recommended option reviewed: new 29,325 sq ft admin and fleet building, existing garage kept as cold storage, about $31.2 million total; consensus to take it to a Select Board workshop.