SELCO Battery Storage Agreements
At a glance
- What: Two shared-savings battery storage installations of five megawatts each, one at a former National Grid substation yard and one on a private Hartford Turnpike lot.
- Where it stands: Agreements signed; SELCO shares revenue and savings with the developers at no capital cost. Operation is likely by fall 2027.
Sources
Log
- 2026-09-22 - SELCO Commission - General manager reported the signing; the main target is transmission cost savings.
- 2026-10-27 - 2026-10-27 - SELCO Commission Meeting: battery storage award noted; SELCO's project is next in the queue, with activity expected next year.