90 Cherry Street Single-Family Home
At a glance
- What: a Notice of Intent from Brandon Foley (236 Cross Street, town garbled in the captions) to build a single-family home and driveway within Riverfront Area and the buffer zone to a bordering vegetated wetland (a former fish-farm pond) at 90 Cherry Street.
- Where it stands: first hearing on 2026-10-20 ran about 40 minutes, the longest item of the night. Continued to November 17, 2026 so the applicant can respond to a list of requests.
- What's next: a revised driveway location, a mitigation/planting plan, clearing limits and fill volume, and a state (DEP) file number, which had not been issued.
The proposal
- About 2,300 sq ft house footprint on a flag-shaped ("hockey stick") lot, served by town sewer (no septic) run along a roughly 336-foot, 12-foot-wide driveway.
- Driveway needs variances under the town wetlands bylaw for work in the 15-foot no-disturb and 30-foot zones; the consultant said about 6 to 8 feet of the outer riparian zone is affected and cited 400 to 500 sq ft of driveway within the 15-foot zone.
- Riverfront analysis: an 801 sq ft allowance versus about 600 sq ft of proposed permanent impact (lot treated as post-1997, so no larger grandfathered area).
- Driveway raised about 3 feet on retaining walls under 4 feet high (roughly 50 to 60 feet on each side), with drainage channels, a drainage column behind the blocks and a small culvert for water and wildlife passage.
- Erosion control: doubled straw wattle and silt fence, rip-rap construction entrance, street sweeping. A roughly 2,000 to 2,200 sq ft rain garden is proposed, plus removal of old farm debris (docks, barrel structures, wire fence, tires).
- The consultant's alternatives analysis covered no-build, a roughly 1,400-foot driveway from Cherry Street across a family-owned lot (about a quarter mile, rejected), and access through 92 Cherry Street (rejected because it would force that owner to move a driveway).
Main concerns raised
- Driveway encroachment next door: the neighboring driveway at 92 Cherry Street was apparently built partly over this lot (and a buried propane tank sits close to the line). Commissioners asked the applicant to work with the neighbor, move the neighbor's driveway back onto her own land, and shift the new driveway toward the property line, out of Riverfront Area. They called it messy and not strictly a Commission matter, but wanted it settled before approval.
- Waiver of the 15-foot no-disturb zone: commissioners said a waiver normally comes with enhancements, and asked for a planting plan with a schedule, a monitoring period, and a location tied to the plan.
- Retaining wall design: a stamped, construction-level wall design should be provided up front because the Commission has seen walls fail.
- Snow storage: posts or a guardrail to keep plowed snow out of the resource area; the hammerhead turnaround was suggested as the snow area.
- Tree clearing: a neighbor across the street was concerned about tree loss in the area (including clearing at a separate nearby house site that the applicant's consultant said is not this client's project and not in a wetland buffer). The Commission noted it only controls work within 100 feet of a wetland resource area.
Requests for the November 17 continuation
- Look at removing the driveway from Riverfront Area (relocating the neighbor's driveway and shifting this one).
- Show a limit of clearing and keep the rear forested area.
- Improve the former farm trail with plantings, around wetland flags 12 to 16, in a ratio of at least 1 to 1 for the 15-foot zone impact (the consultant floated about 500 to 600 sq ft).
- Provide an approximate fill volume for the 3-foot driveway lift, and a planting plan with shrubs in the rain garden.
Discussion time
About 40 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-10-20 - Conservation Commission | 40 |
Log
- 2026-10-20 - Conservation Commission — first hearing on the Notice of Intent (about 40 minutes); consultant Doug Dylan presented, Vasela Harry Antony and Joanne Hubard spoke; Commission asked for a driveway relocation, mitigation planting plan, wall design and clearing limits; continued to 2026-11-17.