SELCO Substation Transformer Replacement

At a glance

  • What: Replacement of a failed substation transformer with a spare unit bought from National Grid.
  • Where it stands: Temporary engineering done and the spare was being delivered; swap expected to take about two weeks. A permanent replacement has a lead time of at least three years, and SELCO received a $1.5 million insurance payment.