2026-08-26 - Conservation Commission

Summary

Written from the auto-generated captions; names and numbers may be misheard.

  • Chairman Michael Garland opened the hybrid meeting; six members answered roll call, one remotely.
  • The 15 Hard Scrabble Road gravel wetland hearing (captions render it "Harts Gravel Road") was taken off the agenda because the applicant's engineer asked to continue it; the new date was to be set later (see 15 Hard Scrabble Road Gravel Wetland).
  • The August 12 minutes were approved as amended (a one-word typo fix).
  • 481 Washington Street: the developer of the new commercial building with a drive-through on a former gas station lot, which is in the aquifer protection district, said the petroleum company owner will clean up the site, with an LSP, tank removal and deed restrictions, before the sale closes, and that the deal dies if permits are not issued within 90 days. Members asked about the site assessment, state environmental comments and the cleanup timeline, none of which they had in hand. The engineer reported no impervious area within 50 feet and no alteration within 25 feet of the wetland, treated stormwater, and the vegetation to be removed. The hearing was continued to September 9 so the commission can review the peer review letter, state comments and owner letter; Planning Board was to meet September 8 and the Zoning Board still needed three pieces of relief (see 481 Washington Street Drive-Through Development).
  • Sidewalk and drainage along a road beside the Dark Brook Reservoir (name garbled in the captions): the Department of Public Works' request for determination covered about 1,000 feet of new 5-foot sidewalk, new catch basins at low points and an upgraded outfall; one swirl-chamber water quality unit lies in the 100-foot buffer. The commission voted a negative determination with the condition that erosion and sediment controls be in place before work starts.
  • 615 Southbridge Street: an amended order of conditions adding boulders every 5 feet and "do not mow" signs every 25 feet along the renaturalized riverfront area, at the state agency's request; the commission voted to accept the revised sheet three, to be recorded at the registry of deeds (see 615 Southbridge Street Riverfront Barrier Amendment).
  • Public works blanket order of conditions: the Town Manager and DPW Director asked the commission to reinstate the blanket order that was revoked after erosion problems on South and Church Streets, and took responsibility for poor communication. Members said they would not reinstate it that night: they want a list of planned road projects, an explanation of how the loss affects work, and a refreshed order (the 2008 order is outdated). Staff noted bid language had already been changed, and discussion turned to requests for determination with conditions for small paving jobs, notice after the fact for true emergencies, and the stormwater pollution prevention plan not replacing a local filing. Continued to a later meeting (see DPW Wetlands Review Procedures).
  • Enforcement against the contractor was set aside until their work in town is finished. The commission is still looking for a consultant for the South Street review; several firms had conflicts or had not responded (see South Street and Church Street Erosion Review).

Issues discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:05Uh good evening everyone. Uh this is the

00:07August 26, 2026 open meeting of the

00:10Auburn Conservation Commission which is

00:12being operated as a hybrid format under

00:14chapter 22 of the acts of 2022. The

00:18public can join the meeting remotely uh

00:20by telephone and dialing 224-501-3412

00:25and then entering access code

00:28645-782-357

00:31where you can join via computer at uh

00:34meet.go.comconference

00:38room 1.

00:40All supporting materials for tonight's

00:42meeting have been provided to the

00:44commissioners and they're available on

00:45our website. The public is encouraged to

00:47follow along using our posted agenda. My

00:50name is Michael Garland. I'm chairman of

00:51the commission. And before we start, let

00:53me do a roll call of our members. Uh

00:55Michel Kas

00:56>> here.

00:57>> Mark Slammo

00:58>> here.

00:58>> Ricky Arzmi

00:59>> here.

01:00>> Mark Kish

01:00>> here. Uh Nat Bickford

01:02>> here.

01:03>> Uh Megan Langley

01:06>> here.

01:06>> Okay. Megan is joining us remotely. Uh

01:10please note that anyone who wishes to

01:12speak before us tonight uh needs to fill

01:14a signup sheet which is at the end edge

01:17of the u the counter over there. And

01:19this meeting is being recorded by Arburn

01:21Cable Television. So without further

01:24ado, the first matter on our agenda for

01:27tonight is the 7 p.m. public hearing.

01:30Walsh Engineering a notice of intent to

01:32improve drainage with a subservice

01:35gravel wetland at 15 Harts Gravel Road.

01:37Is there a motion to open?

01:40>> Motion open.

01:41>> Is there a second?

01:42>> A second.

01:43>> Is there any discussion? All those in

01:45favor say I.

01:46>> I.

01:46>> I. I.

01:47>> Opposed. It's a vote.

01:49>> Is anyone here on behalf of Walsh

01:50Engineering?

01:54>> Did you hear from from Mike Walsh?

01:55>> Yes. He said he was going to show.

01:57>> Okay.

02:00>> Oh, what?

02:01>> He requested to have us to continue the

02:03hearing today.

02:04>> He requested to continue the hearing.

02:06>> Oh, we did? Yes.

02:07>> Okay. So, I I've been advised that Mr.

02:09Walsh did request to continue the

02:11hearing to September 9th. We don't know.

02:16>> You know, who's gone through planning,

02:17but

02:18>> so when we do this, we will um

02:21we will just take it off our agenda for

02:23this evening and then when we hear from

02:24Walsh Engineering regarding a new date,

02:26we will put it on uh the agenda for

02:29whatever meeting that's going to be.

02:32So, we have a few minutes before our

02:34next public hearing. So, why don't we

02:37review the meeting minutes?

06:16So um

06:19that on page it'll be page five. So 1 2

06:223 4 5 second paragraph

06:26um starting with inch of it should be

06:28rain not rail.

06:31Just a minor typo.

09:11Okay. Aside from that, I have no other

09:13changes.

09:18Um motion to accept the meeting minutes

09:21for August 12th

09:24>> as amended.

09:26>> As amended.

09:27>> Yeah. I mean I made one small change. Is

09:29there a second?

09:34>> Is there a second?

09:35>> Second.

09:36>> Second.

09:36>> Okay.

09:37>> Uh any discussion?

09:40>> All those in favor say I.

09:41>> I.

09:42>> I.

09:42>> I abstain. opposed.

09:46It's a vote. Okay. The next matter on

09:49our agenda for this evening is a 705

09:51public hearing. Matthew Doyle with

09:53Branded Realy Group H LLC for a notice

09:56of intent for a new commercial building

09:59uh at 481 Washington Street. Is there a

10:02motion to open?

10:04>> Motion to open.

10:04>> Is there a second?

10:06>> A second.

10:08>> Any discussion? All those in favor say

10:09I.

10:10>> I.

10:10>> I oppose a vote.

10:12>> Okay. Good evening. Good evening. Hi,

10:14I'm uh Robert Branga of Branded Realy

10:17Group 2. Um I know this is a continued

10:20hearing. I was unable to be at the last

10:22one. Yes, sir.

10:22>> Um I just wanted to give you some

10:24context before our engineer answers some

10:27of the questions that you raised at the

10:28last hearing.

10:29>> Um this property is owned by a petroleum

10:32company. It's generally, as I

10:34understand, a subsidiary of Getty Realy,

10:37which is a publicly traded REIT. Uh big

10:39company. Um, we have the opportunity to

10:44have this site cleaned up. It's a brown

10:46field now. I know it's in the aqua

10:47protection district, which is going to

10:49be of course prime concern to you. Um,

10:51right now there's no dealing, no

10:54management of the wastewater at all. Uh,

10:57we are proposing a state-of-the-art

10:59storm water management system, which I

11:00think you heard about at the last

11:01hearing, and we can get into any more

11:04questions you have about it here. Um,

11:06it's important to to understand the

11:08context. Um this property wasn't for

11:11sale to just anyone. Um we have we were

11:15picked by Getty to do the deal because

11:17we've done these before um in other

11:19parts of the country and in Worcester uh

11:22where we've taken a site

11:24um and I know you got an email earlier

11:26today. I don't know if all of you get a

11:28chance to see it describing the process

11:31um about what they're going to do. So,

11:34what'll happen is once we're able, if we

11:36get our permits within the permitting

11:37period, the 90 days, uh, they will then

11:40come in, then we're committed, we're

11:42locked in, they'll come in, have an LSP

11:45on the site, will then clean up the

11:47site. They will take everything out. If

11:49there's any contaminated soil, that will

11:51go to, they'll uh, back fill it with

11:53construction grade material. And I'm

11:55sure you're all aware, so stop me if I'm

11:57telling you something you already know.

11:58uh tank removal, the fire department has

12:00to supervise the the the they all have

12:03to be manifested. Every stage of their

12:06end of life cycle to where they go is

12:08all documented. Um the uh they do more

12:11testing to make sure that they got all

12:13the contaminated soil and then they'll

12:15backfill the property and then we'll

12:17close on it. There'll be a variety of

12:19deed restrictions on it so that future

12:22use is no further excavation.

12:24uh you can't be used for outdoor

12:26recreation, residential, things like

12:28that because of the prior history of

12:30contamination. And again, um we've done

12:33this with other petroleum companies. So,

12:35they know we're familiar with the

12:37process. There are things we know we

12:39have to do that they know we'll do like

12:41vapor barrier, our our slab foundation,

12:44things like that.

12:45>> Sir, if I can just stop you there. So,

12:47has a 21eight site assessment ever been

12:50done in this property to your knowledge?

12:51>> Yes.

12:52Who did it if you know?

12:54>> Uh Getty had it done

12:55>> when

12:56>> uh they did it. Uh it's a good question.

13:00Uh it was in that email.

13:02>> I didn't and I didn't see the email,

13:03sir. So

13:05>> yeah,

13:05>> I believe they had a spill on the

13:07property. Uh and I believe it was done

13:10after that.

13:13>> And then again, there's going to be a

13:14full report after they do their cleanup.

13:16>> No, I understand that. Um so

13:21and was this reported to D to your

13:23knowledge?

13:23>> Yes. Um they they have a temporary the

13:26most recent thing with DOT

13:29um excuse me D is a temporary out of

13:31service status in 2023 when they

13:35decommission the tanks.

13:36>> It would be helpful to have that.

13:38>> And they pulled out um they pulled out

13:41the dispensers and the canopies in 2024.

13:49And and just so we're clear, as part of

13:51redeveloping the site, you're not going

13:53to put in any uh service um station.

13:56>> No

13:57>> aspect of it. No gas.

13:59>> Just retail. Straight retail and food

14:00service with a drone.

14:01>> Okay. Very good. Please go ahead.

14:08>> Good evening. My name is Alex Wood. I am

14:10a civil engineer with Thompson Lon

14:13Associates. Uh and as uh Mr. Bronco

14:17pointed out here, you know, a general

14:19introduction to the site, um just as a

14:21reminder, um the proposed project

14:24includes a 6,400 ft multi-tenant

14:27building with a Duncan uh and drive-thru

14:31as well as other commercial or retail

14:33uses. And uh just to reiterate uh from

14:36the last meeting that there will be no

14:38imperous area proposed within 50 ft of

14:41the wetland resource area and no

14:43alterations within 25 ft.

14:46Um last time we had discussed the storm

14:50water mitigation strategies given that

14:52the existing site uh just features

14:54runoff that is untreated and so uh the

14:57improvements

14:59uh are for example the roof will be

15:03routed to subsurface infiltration and

15:06the paved areas will be routed to a

15:08system of deep sump hooded catch basins

15:11and water quality units as well as great

15:13inlet water quality units for

15:14pre-treatment prior to infiltration.

15:18Also, as we discussed last time, uh

15:20there will be construction period

15:22erosion and sedimentation controls and

15:25permanent slope stabilizing features

15:27such as um on the easterly side toward

15:29the resource area. There will be

15:31conservation seed mix applied.

15:34Um we just wanted to provide a few

15:36updates based on the specific inquiries

15:38that were uh that were brought up by the

15:40commission at the last meeting. Um so

15:42there was a question raised regarding

15:44the composition of vegetation uh to be

15:47removed on the easterly side. So we have

15:49an answer from the wetland scientist uh

15:52regarding that. And so it says that

15:54vegetation in the upland area consisted

15:56of northern red oak, black cherry, red

15:59maple, nor maple, honeysuckle, green

16:02ash, and garlic mustard. And so as a

16:05reminder, there is a proposed landscape

16:07plan and tree clearing is kept to the

16:10minimum possible for the site layout and

16:13there is uh proposed plantings as part

16:16of the landscape plan. Another concern

16:19that was raised uh Mr. Bronco had

16:21already um touched on this was just

16:22regarding the uh historic use as a gas

16:26station and uh the removal of the gas

16:28pump infrastructure. Uh and so we do

16:30have uh comment from the owner u

16:33regarding that and we had um submitted

16:35that by email uh yesterday uh for the

16:38commission u get that

16:40>> uh to review.

16:41>> I'm not sure that we received that sir.

16:43>> Okay. Uh

16:46yeah I mean we we have a copy here. Um I

16:49believe um I believe that we had emailed

16:52it to you but maybe it got lost or

16:54something like that. So we can look into

16:56that. Um I just think when it when it

16:58comes to the specifics of it though, I

16:59mean Thompson Weston Associates isn't u

17:02part of that remedial process itself. So

17:05that's why I wouldn't want to

17:06paraphrase. We'd rather just point you

17:08directly to the words of uh Lee Mil

17:10Petroleum. So we do have a copy of it of

17:12that with us here um if if we need to go

17:15into that. And then we also are in

17:17receipt of comments from D um with

17:21respect to this notice of intent filing.

17:23and we would be happy to um look at the

17:25D comments um together this evening if

17:28you would like and um also hear any

17:30questions that you may have. Thank you.

17:34>> Do we get DP deep uh comments?

17:37>> I didn't see the D comments.

17:38>> So, apparently you have information that

17:40we have not received.

17:43>> Letter. Um

17:44>> well, I'd rather have it, sir.

17:45>> It's not very long.

17:47>> Well, all right. I mean, um but this is

17:49information that we would like to

17:50include in our file.

17:51>> Sure. Um um one I believe I misspoke

17:54when you said the 21 we haven't done one

17:57>> right now. I understand that Getty did

17:58you said back in 2023.

18:00>> It's somewhat irrelevant to our process

18:03because they're going to be in control.

18:05>> They control that site. They're going to

18:06clean it up. They're going to make all

18:07the decisions.

18:08>> But when but that I assume that's going

18:10to take place before you start your

18:11work. Correct.

18:12>> Before we start our work. Yes.

18:13>> And do we have any idea what that

18:15timetable is?

18:16>> Uh yes. It's very specific. If if we

18:18don't get our permits within 90 days,

18:20deal's dead and it's not going to

18:21happen.

18:22>> I see. Okay.

18:23>> Can we

18:24>> It's going to stay the way it is.

18:25>> Can we anticipate Getty filing with us

18:27as well?

18:28>> I'm sorry.

18:29>> Can we anticipate Getty filing with us

18:31as well?

18:32>> They'll do whatever they need to do

18:34whatever the requirements are. It's a

18:36big company. Like I said, we've done

18:37this, sir.

18:38>> They'll have um a licensed site

18:41professional that will be familiar with

18:43the process and will do everything with

18:45the town and the state. So what I'm

18:48hearing is that they're they need to do

18:50that thing. They need to remediate the

18:51site, evaluate the extent of

18:53contamination. Hopefully, although we

18:55don't know, we don't know what the

18:57extent is. Hopefully it's not

18:58significant, but you can't, assuming you

19:01get all your permits in place, you still

19:02can't start work until they do what they

19:04do.

19:04>> Correct.

19:05>> And we don't have any information

19:06concerning what that timeline may be

19:08from them. And I think you're telling me

19:11that unless you get your permits,

19:12they're not going to do it.

19:14>> That's my understanding. Yeah. All

19:16right. It would be nice to hear from

19:18Getty to find out.

19:19>> We we asked them. Um they're based in

19:21New York. They uh elected to send the

19:24email not to and not attend.

19:28>> Um

19:30it it's uh again it's

19:33the we've been through the process

19:35before and it's worked uh very well. Um,

19:38I mean, we we're we're secondary until

19:41they're done and they and they flip the

19:42green light on for us. And they also

19:44maintain an easement, a right to come

19:46back in, knock whatever we build down,

19:49and do more cleanup if they think they

19:50need to do it because obviously they're

19:52a deep pocket. Um, and they caused it.

19:55So, um, we have that's not ever happened

19:59to us before. Uh we've done our own

20:03version of this uh twice in Worcester.

20:06Once in Kelly Square, there's a a G

20:09Duncan Jersey Mike's car wash parcel

20:12across the street from Polar Park. We

20:14did that ourselves. We had bought that

20:16gas station. It was an old gas station.

20:19Raised it, cleaned the site, brought it

20:21back. I mean, it's a very linear

20:24process. The LSP uh and D generally make

20:28all the decisions. um and they'll

20:31greenlight it and if they need to engage

20:33the commission, they will engage the

20:34commission. Uh they're going to make

20:36sure they have every check off that they

20:37need before they hand us the keys and

20:40give us a deed. So,

20:42>> do you anticipate they would do this

20:44cleanup work this fall?

20:47>> Like I said, we're we have no decision-m

20:49authority once they once they begin the

20:51process, but they would prefer

20:53>> they giving you any indication.

20:55Uh well, I can tell you from my

20:56experience that they will move quickly

21:01once we've got our permits because they

21:04want to get the they want to close their

21:06books on it because it's an ongoing

21:08liability for them and they're publicly

21:09traded um and it affects their valuation

21:12and then they want our purchase price

21:14too. So, uh we've seen oil companies

21:17move with elacrity once

21:20our process is done.

21:22>> All right. And then you said permits.

21:24So, in in addition to the conservation

21:26commission, who else do you need to get

21:28permits from?

21:29>> Site plan approval from um the planning

21:32board and we need three pieces of relief

21:35from the zoning board. We've had a

21:37meeting each with them. Um and zoning

21:40board, I believe they were ready to

21:43approve it, but they had an advertising

21:45mistake. Um they only advertised one

21:49variance and and not all three pieces.

21:52We needed a special permit for the

21:53drive-thru and another piece of release

21:56uh a landscape buffer.

21:58>> Where are you with the planning board?

22:01>> Uh we had one complete meeting.

22:03>> Um we have a member here. Do you want to

22:05speak to it?

22:06>> Uh last time I remember I believe we

22:08asked you guys to come back with a

22:09traffic anal uh

22:12analytics for us. Um that's that's as

22:15much as I can remember.

22:17>> Yeah. And and the other thing was uh you

22:19were waiting for the peerreview results

22:21that you wanted to review before then

22:23before voting. Those are in uh we

22:25responded to those comments. Um

22:28>> review by whom?

22:29>> Peerre by whom?

22:31>> Uh Graves Engineering.

22:32>> Okay. We haven't seen that.

22:34>> We we just got it.

22:35>> Yeah.

22:36>> Two days ago. We can

22:38>> Yeah.

22:39>> Okay. I mean again it we just like to

22:42have as much information as possible so

22:43we can make an informed decision. You

22:45can understand that, right? read that

22:47letter from

22:49>> I'd rather have a copy.

22:50>> Well, we we'll make sure you have it,

22:52too.

22:52>> All right.

22:53>> But just so that you know what they're

22:55saying because that's the only

22:57communication that apparently they're

22:58willing to give.

22:59>> All right. Um I don't have any other

23:02questions. Any questions from the board?

23:09So, so it sounds like you're, if I'm

23:12going to make a football metaphor here,

23:15it sounds like you're at the 20 yardd

23:16line, but you're not quite ready to get

23:18into the end zone, at least tonight. So,

23:21um, my preference would be for the other

23:23information you've received, including,

23:25excuse me, the Graves, um, review, uh,

23:29whatever you got from Getty, um,

23:32the D, uh, D comments, and I understand

23:34they're not extensive. My preference

23:36would be to continue the public hearing

23:38this evening to our next meeting on

23:40September 9th, just because it sounds

23:42like you're you're moving along with the

23:43other boards, but you're also not quite

23:45there uh, as well. Is that fair? Uh

23:47again, the peer review was the last

23:49piece for I think a lot of that. Okay.

23:51Um we had a full traffic presentation.

23:54That was most of the planning board's

23:56concern.

23:58>> Um and then circulation within the site,

24:00how the drive-thru is configured. We

24:02looked at that. We can't make change

24:04that they thought we could and as you

24:06appear,

24:07it's probably impossible. Um and then

24:10whether and and we were asked to convey

24:14concerns of the town to do um because of

24:17the speed of the traffic on Route 20 um

24:20in the intersection there and that area

24:23is built up. There's more residences

24:24being built. There are businesses that

24:26are expanding which is a good thing. Um

24:28but it brings traffic. So uh that was

24:31mostly what I think believe the zoning

24:34board was ready to approve but planning

24:36had those questions. When are you going

24:38to meet with the planning board again?

24:41>> September 8th. Yeah.

24:42>> Okay. So, our next meeting is September

24:449th. So, do we have your ascent to

24:47continue the public hearing?

24:48>> Uh, yes. We'll request a continuence to

24:49and we'll get you that information.

24:51>> All right. Terrific. All right. Any

24:53questions from the board again? Any

24:55questions from the audience?

24:59>> There being none, I'll take a motion to

25:00continue the public hearing for um

25:03Branded Realy Group um two. Uh motion to

25:08continue the public hearing for BR

25:11Branded Realy Group to September 9th.

25:15>> What time?

25:16>> We can make it for uh some

25:20>> Thank you.

25:21>> Okay. Thank you. Okay. Uh there's been a

25:23motion

25:24>> second.

25:25>> Thank you. Any discussion? All those in

25:26favor say I. I. I. Oppos to vote. All

25:30right. Very good.

25:48Uh the next matter on our agenda is a

25:50710 public hearing. Uh the Auburn

25:52Department of Public Works request for

25:54determination of applicability for a

25:56proposed sidewalk improvement and

25:58stormwater drainage system repair along

26:00Binmar Avenue. Is there a motion open?

26:02Motion open.

26:03>> Is there a second?

26:05>> I'll second.

26:05>> Is there any discussion? All those in

26:07favor say I.

26:08>> I.

26:08>> I. Post.

26:10>> It's a vote.

26:12Good evening.

26:35Whenever you're ready.

26:37>> Good evening.

26:37>> My name is Larry Rossi. I'm a civil

26:39engineer that works for Wright Pierce.

26:41And with me tonight is uh Mr. Chuck

26:43Karen from Karen Environmental. We're

26:45here on behalf of the town of Auburn to

26:48present to you the RDA application for

26:50Brimmar Associated Sidewalk

26:52Improvements. Um we're talking about a

26:56limit of work uh approximately from the

26:59end of Warren Warren Road where the pump

27:02station is. Uh the scope of the project

27:05is on the westerly side of Binmar uh

27:08going north towards um the mass DOT uh

27:12rightway alongside of the bridge. Um

27:16it's approximately 1,000 lineal feet. Um

27:19we're abuing the the resource area of

27:21the Darkbrook Reservoir. So portions of

27:24the project are within the 100 foot

27:25buffer zone. Uh we submitted plans and

27:28details and so forth as well as a

27:30narrative uh to support this

27:32application. And tonight I have uh just

27:35a few of the the plan sets highlighted

27:38that shows the 100 foot buffer zone uh

27:41the limits of the erosion and

27:43sedimentation controls uh the the plan

27:45and the scope of work and the grading in

27:47black and white. uh and then I can flip

27:49through, you know, various uh

27:51presentation boards as needed. Uh but

27:53the the plan in front of you is is

27:55pretty much the focus of the area. It's

27:56on the southwest portion of the project.

27:59Uh like I said, it's it's abudding the

28:01the pump station and the scope of the

28:03work. There's an existing gravel path on

28:05the westerly side that kind of links um

28:09uh Warren Road sidewalk up towards uh

28:11the the bridge and the sidewalk that

28:13goes over the over the turnpike. Uh the

28:16scope of the project is is generally in

28:18that same uh path of the gravel path

28:21that's there today. Um it'll be a 5 foot

28:24wide sidewalk, puminous asphalt uh in

28:27accordance with the the town u detail

28:30and so forth. Um there will be um two

28:33new drainage structures that tie into

28:36existing drainage structures. Uh that

28:38area is on the southwest portion of the

28:41project and that discharges to an

28:43existing outfall. Um, as part of the

28:46scope, uh, that outfall will be

28:48improved. There's some erosion along

28:50along the hillside there. Um, and so

28:54we're proposing a new head wall,

28:55replacing the existing pipe uh, and and

28:58establishing a rip wrap energy

29:01dissipator or spillway. Um at that same

29:04location

29:05um roadway drainage currently conveys uh

29:09you know sheet flow overland flow

29:11towards the existing structures that are

29:14near the pump station. Uh we're

29:16proposing just based on the the

29:18differential settlement along Binmar. Uh

29:20the roadway is is relatively flat. Uh

29:23and there are some low points there

29:24today. So, we're proposing two new

29:26structures at those low points when um

29:29to kind of um reduce or or minimize some

29:33of the flooding that currently occurs.

29:35Um the sidewalk will be generally

29:38elevated as it relates to the to the

29:40travel way of the road. Uh there will be

29:43curbing. Uh there will be a horizontal

29:45separation between the the the the

29:48sidewalk utility strip or grass strip

29:51and the travel way. Um, continuing north

29:55uh where the turnpike uh has their

29:58maintenance driveway, there will be two

30:00accessible handicap ramps uh for uh safe

30:04crossing at that location and then the

30:06sidewalk will continue within the

30:08rightway uh but adjacent to the the two

30:11residential properties um on on the west

30:14side of Binmar. Um the scope of the work

30:17is is buffer zone. I know if there's any

30:20specific wetland related questions, uh

30:22Chuck can field those as it relates to

30:24the delineation along the Dark Brook

30:26Reservoir. Uh but in general, uh that's

30:29the scope of the project and we're here

30:31tonight to, you know, uh support the

30:33town and and request the commission to

30:35consider a negative determination.

30:39>> So, if I heard you correctly, you're

30:40going to be installing new drainage

30:41structures, right?

30:42>> That is correct. Yes. I don't see any

30:44details of those uh drain structures and

30:46what we've received.

30:48>> Um

30:49>> I what we have what I received was a set

30:51of construction drawings uh dated June

30:53of 2026 and I don't see um again any

30:57details relating to drainage structures.

31:00>> The the drainage structures will be a a

31:024ft diameter deep sump catch basin uh in

31:06accordance to the town detail. um

31:09that'll link into the existing two

31:11structures uh adjacent to the pump

31:13station. I believe the scope of that

31:15those two structures will be to remove

31:17and replace uh in kind new piping, new

31:21infrastructure prior to discharging to

31:23the existing outfall. Uh we're proposing

31:26a a hydrodnamic separator uh to remove

31:29um in addition to the deep sumps with

31:31hoods uh a proprietary device a squirrel

31:34chamber to remove some additional

31:36suspended solids uh and even limited

31:39phosphorus before the out uh discharge

31:41into the existing outfall.

31:43>> Now will these drain structures are they

31:45within or being installed within the

31:46buffer zone?

31:47>> Uh no they are outside the limit of

31:49work. I can show you.

31:50>> Tell me where.

31:52I guess my question would be, is there

31:54anything like where you're proposing new

31:56construction again to replace existing

31:59uh drainage or that sort of thing? Is

32:01any of that within um the buffer zone?

32:04>> Um on this plane, can you see it? Okay.

32:06I can hold it up.

32:08>> Yeah. Okay, that's better. Thank you,

32:10sir.

32:11Oh, that's much better.

32:12>> Yeah.

32:13>> So, this line right here represents the

32:15buffer zone.

32:16>> Okay.

32:16>> This is a zoomed in scale in the

32:18plantet. There's an overall

32:20>> Gotcha. These are two existing

32:22structures here today.

32:23>> All right.

32:24>> So, we're proposing a new uh drainage

32:26truck um heading north and that would be

32:30on the next.

32:32So, here's the yellow buffer zone.

32:35Here's our green BMP. These are the two

32:39uh catch basins within the travel way

32:42that will convey storm water down

32:45towards the south of the existing

32:46structure. So these structures are

32:48outside of the 100 buffer zone.

32:50>> All right.

32:51>> We are proposing a new structure within

32:54the buffer zone and that is an a CDS

32:57unit a contact uh swirl chamber uh to

33:01remove some of the suspended solids and

33:04that would be longterm in addition to

33:07the self.

33:08>> What would the maintenance schedule be

33:10for that?

33:11>> Uh typically typically it's it's

33:13bianual. Um, you know, there's there's

33:16periodic uh visual observations of those

33:18structures, but typically um it's it's

33:22either scooped out or back in the truck

33:23twice a year.

33:25>> Okay.

33:27>> I don't have any other questions. Do you

33:28any questions from the board?

33:32>> Any questions from the audience?

33:37Okay. When would you propose to start

33:40doing this work?

33:42Um

33:44>> it's my understanding that um the town

33:46is currently soliciting bids. Uh so

33:49pending the you know the the approval

33:51tonight we can further then coordinate

33:52with with um Greg and and Joanna at the

33:56town. Okay.

33:57>> It's my understanding that they're going

33:58to commence work this you know late this

34:01summer early fall.

34:03>> Okay.

34:04All right. Um,

34:09if there's no comment from the public

34:11and no other comments from the board, is

34:13there a motion to close a public hearing

34:15for the request for determination of

34:16applicability?

34:18>> Uh, a motion to close the public

34:20hearing.

34:21>> Is there a second?

34:23>> I'll second.

34:24>> Any discussion?

34:26All those in favor say I.

34:28>> I.

34:28>> Opposed. It's vote. All right. Thank you

34:31very much. We will probably render a

34:33decision this evening. Thank you.

34:35>> Thank you.

34:50>> The next matter on our agenda is a 7:15

34:52public hearing. Mast Futures LLC

34:55requesting an amended order of

34:57conditions for 615 Southbridge Street.

35:00Is there a motion open?

35:02>> Motion open. Is

35:03>> there a second?

35:04Second.

35:04>> Is there any discussion? All those in

35:07favor say I.

35:07>> I.

35:08>> I.

35:09>> Post vote.

35:12>> Good evening.

35:17>> Uh good evening. Garrett Horsefall with

35:18Kelly Engineering Group, civil engineer

35:20representing the project. So um believe

35:23in month of June or July the commission

35:24issued order conditions for this

35:25project. after it was issued, um DP

35:29um wanted one extra thing added to the

35:31plan um in terms of just clarifying the

35:34riverfront resource areas um in terms of

35:37keeping them um undisturbed and then the

35:41renaturalized state which I believe the

35:43commission had added as part of the

35:44order

35:45>> um special condition 12. However, I

35:47think D wanted the physical barriers

35:49shown on the plan. So what we've done is

35:52place boulders every 5 ft and um signage

35:56um every 25 ft which basically says do

35:59not mow um do not encroach um

36:02renaturalized area um that was the

36:04request of D. So, none of the other

36:07items on the plan have changed um in

36:09terms of layout, grading, utilities. Um

36:12there's simply in that riverfront zone,

36:15um boulders every 5 ft on center and

36:17signage every 25 ft.

36:20>> I'm sorry.

36:28>> So, I I guess I'm a little confused. We

36:30issued the order of conditions and then

36:32you received comments from D. We had

36:34received comments previously which we

36:36had responded to. Okay. Um and they were

36:38satisfied with and then they followed up

36:41after receiving your order that they had

36:44an additional comment that they wanted

36:46just extra protection shown on the plans

36:50um in in that riverfront zone.

36:53>> Okay. And the changes that you made on

36:55your plan sheet uh or plan set, which

36:59plan would that be?

37:00>> Sheet three, the layout plan.

37:01>> Okay. So, the signs I believe are in a

37:03magenta purple color and the boulders

37:06are um every 5t or so.

37:09>> Sure. Want to see the big one?

37:11>> Yeah, that's right. I can look at this

37:12one.

37:14>> Yeah. You want to see the big one? Hold

37:16on. So, the Is it fair to say the dots

37:21represent the boulders you put in? The

37:23dots were the um

37:27that that was the renaturalized area

37:29sort of the the conservation seed mix

37:30that we were placing. The the boulders

37:32were sort of the ovalish shape if you

37:36want to call it that. All right.

37:42>> Right along the edge of the the parking

37:44field there.

37:46>> Okay. Yeah. So it shows up a lot closer

37:48on that one. Uh all right. So, um

37:54I guess I'm trying to figure out what

37:56the best way is to amend the order of

37:57conditions. You know, it seems to me one

38:00way to do it would just be to record uh

38:03u sheet number three with the registry.

38:06>> We could reference this is the most

38:08current plan set like you said, just

38:10making sure that the documents are all

38:11online, nothing else changed. Storm

38:13water reports the same.

38:15>> Sure.

38:17Um

38:18all right. Any questions?

38:23Okay. You have any questions? No. All

38:25right. Any questions from the audience?

38:29There being none, um, is there a motion

38:31to close?

38:33>> A motion to close.

38:34>> Is there a second?

38:38>> Second.

38:39>> Thank you. Is there any discussion? All

38:42those in favor say I.

38:43>> I. I.

38:44>> Opposed. It's a vote. All right. Thank

38:48you, sir.

38:48>> Thank you for your time.

39:07Okay.

39:12All right. So that the next matter on

39:15our agenda is a discussion concerning

39:18reinstating DPW's blanket order of uh of

39:21conditions that we issued

39:24originally I think back in 2008 and it's

39:26been periodically renewed and which we

39:28revoked a couple of meetings ago.

39:32So who would like to address that on

39:34behalf of the town? Miss Veio, you seem

39:37eager to address address it. Sure.

39:43Thank you so much.

39:47It

39:48>> is very interesting meeting.

39:51>> I didn't hear any jokes though.

39:54>> Trying to butter me up.

39:55>> I didn't hear any jokes. You said you

39:56want a joke.

39:57>> Well, we haven't finished yet. We

39:59haven't finished yet. So, any event, can

40:02you just uh identify yourself for the

40:03record, please?

40:04>> Yeah. Dory Veio, town manager for the

40:06town of Auburn.

40:08Joanna Puquin, town uh engineer, DPW

40:11director.

40:12>> All right. Very good.

40:13>> So, um I wanted to come tonight because

40:16I do know that there was a vote taken a

40:18few maybe last month, I believe, to

40:20rescend

40:22um our blanket order of conditions at

40:24the Department of Public Works. There

40:26has been some issues with one of our

40:27contractors that we've been dealing

40:29with. Um, and we're here to talk a

40:32little bit more about that because the

40:34impact of this recision is um I can't I

40:39can't say anything else but massive in

40:41our ability to not get things done

40:43because it was um taken back. So, I

40:47would like to talk more to you about it

40:49and what we can do to work with the

40:52commission to make sure that we're all

40:53on the same page and that we're

40:54communicating effectively. I take

40:56responsibility for um not communicating

41:00effectively. I'm the town manager and

41:02ultimately it falls on me. And I wanted

41:05to come tonight to talk to you about

41:07that cuz I'm I'm serious. We I did

41:10outreach to Mike a few times through the

41:12process. We were out in the rain. Um it

41:15was interesting, but we have to do a

41:18better job and we have to bring more to

41:19you, whether it's through a contractor

41:22or ourselves. our goals, believe it or

41:25not, even though the lack of

41:26communication lately doesn't feel like

41:28that, are actually the same. Um, and

41:31we're on the same page. And that's why I

41:33wanted to come and and see what your

41:36thoughts were, what you recommend that

41:37we do. We want to provide you all the

41:40information that you need and get

41:42feedback from you and make the proper

41:44changes. Since we have spoken um Mike

41:48the past month or so, we've made changes

41:51in the way we go out to bid and how um

41:55some of the language that we were using

41:57that allowed some of the situations to

41:59happen and that was because of you and

42:01your recommendations. So, we have

42:04instituted some of that and I wanted to

42:06just um be honest and and see what we

42:09can do to do a better job to work with

42:11all of you.

42:15I'm not sure if there's anything else

42:16that could be said. Um, again, I I the

42:20DPW is under my purview. I I also take

42:24responsibility. I should have

42:26communicated um much better about what's

42:30going on with our roadway projects and

42:32that's something that I am going to

42:35correct. Um, I think that, you know,

42:39ultimately I would like to work

42:42together. Um, you know, we have, as Dory

42:46said, we have a co common goal. Um,

42:48storm water is under engineering. We're

42:51looking to be um, you know, we we're

42:53looking to protect um the natural

42:56resources in town. Um, just like you,

42:59we're just a little bit further away

43:01from the wetlands. Uh so we've always

43:03worked with um the land use enforcement

43:05officer to make sure that um you know we

43:09communicate our our concerns if we're

43:12out on the site and doing inspections.

43:15Um you know we we communicate whatever

43:17concerns we have um relative to

43:20wetlands. Um so I I just I want to

43:23broaden that relationship and you know

43:26work with with the um commission and uh

43:30and and move forward with you know with

43:33a relationship that we can you know of

43:35trust.

43:36So, um I um your predecessor Joanna Bill

43:40Coyle uh at least in the past had

43:45presented us with a list of um of

43:47streets that were being going to be

43:48worked on. And I I know we haven't seen

43:51that from the DPW in recent years. The

43:54other thing, of course, is that of of

43:56all the work that you're planning to do,

43:58I have no idea uh how many of those um

44:01of of those repair jobs or other

44:03projects um would trigger our

44:05jurisdiction. And so without knowing

44:07where you're doing the work, it's just

44:09we can't evaluate uh you know what

44:12impact if any that work is going to

44:14have. And I think um you know I I think

44:17Lynch is an extreme case as we've

44:19discussed um because for a variety of

44:23reasons um uh

44:26which I won't get into tonight because

44:28we've actually already spoken about

44:29them. I we want to make sure that there

44:31isn't a repeat of of that situation

44:34because you know

44:36we know that um and I spoke to Greg

44:39Sodto yesterday I think and you know the

44:43the fact that they decided to undertake

44:45church and south streets at the same

44:47time to suit their schedule didn't um

44:51benefit the town um at least from my

44:53point of view. Uh, I think it's um it

44:56led to and the fact that they didn't

44:58install version control measures. We

45:00think there's been environmental impact

45:02and now we're going to have to hire

45:03someone. Then we voted to hire a

45:05consultant to determine uh whether there

45:07is an impact and what the extent of that

45:09impact is. Um a situation that um could

45:14should have been avoided and um it's

45:17still um I'm just still scratching my

45:21head over why it it um they didn't take

45:22it seriously. But aside from that, so um

45:27I think the first step is to get a sense

45:29of of where you're going to be doing the

45:31work. The second is of those projects. I

45:34presume that there are certain projects

45:35that have no will well and impact

45:37whatsoever. And clearly if if there's if

45:41you're not um doing work with you know

45:43within our jurisdiction and as as you as

45:46you know Joanna from our conversation

45:48you know our jurisdiction is is more

45:50extensive than the wellness protection

45:52act and we did that uh for a reason uh

45:54because um our you know we our wetland

45:57uh system here in Auburn the streams and

46:00uh uh the channels it's an important

46:02resource and um people I think take it

46:05for granted but uh it's it's highly it's

46:08veryant important and we're the stewards

46:10of protecting it. So, um and and I will

46:14also say this, I think whatever order we

46:17issued back in 2008 probably needs to be

46:19upgraded as well. You know, it's

46:21probably uh it would make sense to

46:23revisit it to determine what what

46:25worked, what maybe could work better and

46:28that sort of thing. M

46:29>> so um I my sense is that the first thing

46:32I would want to see is to get a sense of

46:34what you are proposing to work on and

46:36then from there we can get a

46:38determination of of whether of what

46:40needs to be done you know now for

46:42example you know we have um we have

46:44Binmar that came before us tonight you

46:47know and in that case um you know there

46:50was SWIP done but they also had the good

46:51sense to file um an RDA with us because

46:55you know that's what that's what the the

46:57SWIP requires and what your contract

46:59requires as well. So, um that that's my

47:02initial my initial thought is before we

47:05would um maybe reinstate it, I'd like to

47:07see what you're working on.

47:09>> So, um we have started the process of of

47:12um starting that communication. Um Greg

47:15had um sent over uh some documents um on

47:20the roads that are being done. Um so

47:23it's basically uh um sheets of the

47:27location of the road work um delineating

47:30wetlands and basically pointing out you

47:33know if there's any drainage

47:35infrastructure is being changed or

47:36anything like that. So um we can forward

47:40that along however you would want to to

47:43do that if if you'd like to have it sent

47:46out directly um through the chair or

47:48through Nat, however that works. Um do

47:51that. What you could do is if you have

47:53um a list of proposed projects and I

47:55understand you want to streamline the

47:57process so that you don't have to do an

47:58RDA or notice of intent. Well, if you do

48:01a notice of intent, then clearly there's

48:03going to be more work that has to be

48:04done. But for those projects where an

48:06RDA may very well just make make a

48:09determination of whether um you know, we

48:12think more needs to be done or not, that

48:15would be helpful. And also we have um

48:17and I I don't know if you're aware of

48:19this but we have in the past issued

48:22negative determinations but with

48:24conditions so that for example rush

48:26control measures um um you know certain

48:30notifications to us that sort of thing

48:32and that has actually proven to be

48:34pretty effective. So it's instead of a

48:36full-blown notice of intent, you've got

48:39basically a positive determinate or a

48:41negative determination but with with

48:43enhancements or protections.

48:46So is there um any possibility of us

48:50providing that documentation as part of

48:52that blanket order of conditions um with

48:57um already determined areas if there

49:01we where there where there is um any

49:05proximity to wetlands um showing where

49:08um we're directing the contractor to put

49:12erosion control prior to any

49:14construction. Obviously, um in addition

49:16to any other areas that might, you know,

49:18um might be uphill up gradient,

49:20sometimes we put erosion control

49:22upgradient, you know, um just so that um

49:25runoff doesn't go onto private property.

49:28>> Can I just

49:29>> Yeah, please go ahead. So, when I've had

49:33contractors come to my house to do work,

49:37most of the contractors that are doing

49:39work at my house will say to me, "I'm

49:42not going to do this until you get

49:44permits."

49:46>> Most competent contractors will look at

49:50an area and already know that it's a

49:52wetland and what they need to do and

49:54whether or not they need to have a a

49:56permit for it. So I don't understand

50:01like why aren't these contractors

50:04looking at it saying we need to do this?

50:07>> So the in the past we haven't had this

50:10issue. We've worked with another

50:12contractor and they and

50:15whether it was the SWIP or whether it

50:18was um any other permitting um authority

50:22um they knew, okay, there's a sensitive

50:25area. There's a a possibility of um

50:30erosion that I I'm going to need to

50:32control and they they've addressed it

50:34before, you know, before any any

50:37construction started. Um this is a new

50:40contractor that we haven't worked with

50:42in a long time that was working on South

50:45and um Church Street and

50:50that's not that's not been my

50:53experience. It's it's a our my

50:55experience with this contractor is

50:57unlike what we've been used to for

51:00>> nothing written in the contract that we

51:03have with that contractor saying that

51:05they're responsible for any damage

51:07that's done to the environment or any

51:09damage that's done on the job because of

51:13their negligence.

51:15>> I believe there might be I I can't

51:18imagine that there isn't I I'd have to

51:20refer back to the the contract. It's

51:22been a long time and it's a it's a long

51:24contract, but I can't imagine that there

51:25isn't um language. So,

51:29>> you know, the other option too,

51:31Michelle, and we're getting a little off

51:32track here, but you know, as you know,

51:34we have the ability to fine and I mean,

51:36I think in terms of we discussed at our

51:39last meeting, and I know you weren't

51:40present. No, it's all right.

51:42>> But we were um we talked about issuing

51:44an enforcement against Lynch and um you

51:47know, we have the power to impose fines.

51:50I think the only question is we have to

51:52figure out how to impose the fine. There

51:54has to be a logical uh basis for it. And

51:56I I'm inclined not to do anything with

51:58lunch until they finish the work in the

52:00town.

52:01>> I I have to agree with that. And I mean

52:03at this point

52:05>> because you know the what what is it um

52:07the you can't the horse has gotten out

52:10of the barn

52:11>> and that's exactly it.

52:12>> So something like that. I mean, so this

52:14I I guess what Mike was saying, we could

52:17only kind of move forward and

52:19>> Mhm.

52:21>> I mean, I I guess like

52:23>> I will say this, if if you're hoping for

52:26us to reinstate the blanket or of

52:28tonight, I mean, my feeling is no. My

52:32feeling is is that you need to give us

52:34some more information. We're not opposed

52:36to it, but we need more from you. And

52:40like I said, we need a list of streets.

52:42We need to get a sense and you're not

52:44telling me how you said it's impacting

52:46your work. You need to explain to me how

52:48it's impacting your work. I mean it

52:50didn't certainly it didn't impact what

52:53you're proposing to do for Binmar. So if

52:55you can explain to me how not having the

52:58blanket order affects your ability to to

53:00to do the things you need to do. I need

53:04to know that. I think we all need to

53:05know that.

53:06>> So if I may, Mr. Chairman, first of all,

53:08and I and I sent you an email today.

53:10There should have been a public hearing

53:12to retract this this um

53:16>> blanket order of concern.

53:17>> Is that according to town council

53:19>> or is that your own opinion?

53:21>> No, I'm I'm serious.

53:22>> No, I I didn't. If you want me to, I

53:24can. I I

53:26all I'm saying is that we we have

53:30contractors that are trying to do the

53:32right thing, which is Binmar. Um Lynch

53:35we've had problems with before. They

53:37were the low bidder. They will never

53:38come back and work in town again. As far

53:40as long as I'm town manager, we've had a

53:42lot of issues with them. More than just

53:45what you guys are aware of, there's been

53:47a lot of issues. We do have insurance.

53:50We do have coverage. We can go after

53:52them. It would be helpful if if you

53:56could help us with that a little bit

53:57because it gives us a little bit more

53:58teeth. So when they are low bidder next

54:00time, we don't need to we have something

54:03that we can bypass them.

54:05>> They are very difficult to work with. I

54:07went on the site. We were all on the

54:09site. You were on the site. It was not a

54:12good situation. They had minimal

54:16protections. I saw it myself and I don't

54:18even know what they were supposed to

54:20have. I just saw that it just wasn't

54:22enough. Um the work that I'm talking

54:25about is less about our contractors

54:26because they need to come in front of

54:28you anyway. I think they should always

54:30come in front of you and give you the

54:32plan. So that is not I don't want this.

54:36That's not necessarily where I'm

54:37concerned. I'm concerned about our guys

54:40doing projects for us that we need to

54:42talk to you about and give you

54:44information about. That's what the order

54:46of conditions that I'm worried about

54:47necessarily our work. Um, and I want to

54:50work with you on how best to relay that

54:52information. The contractual side of it,

54:54I think they're very clear. Like I said,

54:57we've amended the bid, especially how

55:00long roads will be open and and things

55:02like that that we had discussed because

55:04that led to this problem as well, but

55:06more if our guys are going out to do any

55:09type of work and it's near a water

55:12within the 100 ft.

55:13>> So, you're talking about an emergency

55:15situation.

55:16>> Yeah. But Yeah. Yeah. Pretty much it

55:18would be an emergency situation, right?

55:20But we still need, you know,

55:22>> so I I think you need to if you want to

55:24distinguish if you're telling me, you

55:26know, we really if we have an emergency

55:28situation, there's a, you know, a

55:30pothole that could swallow a Buick, you

55:32know, it makes sense to me and that's

55:34the middle of the street, but maybe it's

55:35within 100 ft of the Wellins or

55:37something. I mean, I think an emergency

55:39situation probably entitles you to not

55:42having to give us immediate

55:43notification, but letting us know after

55:45the fact. Um but again it's a question

55:48of you know and we found out about Lynch

55:52after the fact and after it had rained

55:55after uh it made a mess of the roads uh

55:58on South Street and the the side streets

56:00off of South Street and Church Street

56:02too for that matter and um you know no

56:05one no one wants to be caught uh

56:07offguard like that um and I know and I

56:10know that's your feeling too. Um, you

56:12know, so I I guess I need to know

56:15specifically

56:18what you're asking for because I'm it's

56:20not clear to me what you're asking for.

56:22You're just saying, well, reinstate the

56:23the order the blanket order conditions.

56:25And I'm saying to you, for what? For

56:28what type of work are you talking

56:29emergency situations? That's what I'm

56:31saying. And and the only way we will

56:33know that is if you tell us what you're

56:35doing. So, I mean, I'm sure there are

56:36instances where you have emergencies,

56:40legitimate emergencies, where maybe

56:41you're within our jurisdiction and that

56:44c can't wait. I understand that we meet

56:46twice twice a month. Um, but but if if

56:50you're talking about other like smaller

56:52projects where you can give us or tell

56:54you tell us where the the work is being

56:56done,

56:57>> that would be helpful.

56:58>> No, I agree with you there.

56:59>> We haven't seen that. We haven't seen a

57:01list of

57:01>> I agree of what DPW has done in in

57:04years.

57:05um six times since 2010 2020 which is

57:09not a lot.

57:10>> It is not a lot. You know how much road

57:11work road work we've done since 2020 and

57:14no one's come before you. It's not

57:16acceptable. We've had this I've had this

57:19conversation

57:20um with my staff. There was a

57:22misunderstanding that is very clear now

57:26in regards to responsibility and we take

57:29that very seriously and that's why I'm

57:31here. So, I'm telling you, um, you don't

57:34have to reinstate this, but if there are

57:38projects that are being impeded,

57:42um, I'll probably give you a call and

57:44ask what you want us to do, and it may

57:46be an emergency. Like, that's my biggest

57:48concern. Um, most things are planned,

57:52and if they're planned, there should be

57:54no problem.

57:55>> I think we all agree. Okay. Um this was

57:58an extenduating circumstance that no one

58:01is happy about. Not one person in um the

58:06town is happy about and they shouldn't

58:08be. So we will be holding them

58:11accountable as much as we can and we

58:12hope that you do too.

58:13>> Okay. Would you like to speak?

58:16>> Yeah, if you don't mind. Sorry.

58:17>> Hi, my name is Pete Borie. I'm the

58:19assistant DPW director, sewer

58:21superintendent. So through the chair, if

58:23I could just ask for some clarification.

58:25When we go out to bid and hire

58:26subcontractors and require them to

58:29prepare and provide us with a storm

58:31water pollution prevention plan, which

58:33is often called the SWIP, which is done

58:36under the contractor's um EPA NIP's

58:41permit number, subsidiary of that,

58:43>> right? Um, do you consider that being a

58:46parallel permit to our order of

58:49conditions or I I just need some

58:52>> I know the square for lynch talked about

58:54I believe it said that they had to

58:56comply with local bylaws and

58:58regulations.

58:59>> Our contract requires the contractor to

59:02um make sure they adhere to any local

59:06and state rules and regul understood.

59:09>> Yeah.

59:10So, and I've heard this argument before.

59:12Uh, you know, I've had a spirited

59:13discussion uh with an engineer friend of

59:16mine who thinks that this whip exempts

59:19um the contractor from filing uh with

59:22the locality and I disagree with him on

59:24that. So, I think um

59:28I mean I guess my position would be

59:30since our uh bylaws and regulations are

59:33more stringent than the Wellness

59:35Protection Act in the in the state that

59:37they have to file. But again, it it's,

59:39you know, I we're talking about

59:41something in a vacuum. I if I would want

59:43to know specifically like in the case of

59:46of Lynch, and that's a perfect example.

59:47They should have filed a notice of

59:49intent with us.

59:50>> So,

59:51>> I have no doubt no doubt about that in

59:53my mind

59:53>> through the chair. So, when you mention

59:55notice of intent versus RDA,

59:57>> right,

59:57>> there's a big difference there as far as

1:00:00timing and

1:00:02>> us being able to have our contractors be

1:00:04efficient. And I'm not arguing either

1:00:06way. I'm just trying to clarify

1:00:09what rules you're going to want us to

1:00:11follow moving forward. So, and I just

1:00:13want to see if we if there's a

1:00:15separation between our blanket order of

1:00:17conditions and what our some contractor

1:00:20is going to apply for either through an

1:00:23NOI or an RDA. Um I I would ask that

1:00:27that the commission consider an RDA with

1:00:30the ability to condition it. that way

1:00:33there we're not waiting four to 6 months

1:00:36for mass D to provide us with a number.

1:00:39Um cuz again the projects I I can

1:00:43understand if it's a large scale project

1:00:44and that's what the RDA will allow you

1:00:46to to assess a large scale project that

1:00:49may need to go in front of D. Yes. um

1:00:52some of our smaller paving projects

1:00:53where only a portion of it might be in a

1:00:55resource area. May may maybe that that's

1:00:58a negative determination and you will

1:01:00have the flexibility to make that

1:01:02determination as needed. So again, the

1:01:05biggest question for me is is does the

1:01:09SWIP run parallel with our order of

1:01:12conditions or is our order and can in

1:01:15essence keep our order of conditions

1:01:17separate. that way there. If the

1:01:19contractor we hire does not adhere to

1:01:22the SWIP and the erosion and control

1:01:25plan and it's not adequate, our blanket

1:01:27order doesn't get attached to that and

1:01:30the town or the DPW is a little

1:01:32protected from what a contractor might

1:01:35do that we don't necessarily have

1:01:37oversight as far as means and methods

1:01:40go.

1:01:40>> Yeah, I understand that. I I I take your

1:01:42point.

1:01:43>> Thank you.

1:01:43>> Thank you.

1:01:48I think that's what I was trying to say.

1:01:50>> Okay.

1:01:51>> I was trying to separate it the two.

1:01:54Like, so if they're a large project, we

1:01:56have a contractor, they have to come

1:01:58before you. And what I feel like is that

1:02:00they're being tied and I don't know

1:02:03enough. This isn't my area of expertise,

1:02:05obviously, and I don't know enough. So

1:02:08what Peter was saying is that if the are

1:02:11our the town our DPW order of conditions

1:02:14is separate from what all the

1:02:17contractors have to do.

1:02:19>> Understood. Understood. And I think when

1:02:22um the problems with Lynch's work uh

1:02:24came uh to our to my attention to the

1:02:27commission's attention it um because

1:02:30nothing had been done. It was unclear. I

1:02:32mean, I didn't learn about the script, I

1:02:34think, until re until

1:02:38a few days before our last meeting,

1:02:40whenever we had our meeting. And uh, you

1:02:42know, again, my my thought was, well,

1:02:45why wasn't this provided to us at from

1:02:47at the at the at the get- go,

1:02:49>> you know? So, um,

1:02:52I mean, I I I take your I really do take

1:02:55your point, and I I don't want you to

1:02:58get the impression that that we

1:03:00penalized you. Although maybe we did.

1:03:03Um, but I I just think again there has

1:03:07to be and and you know I understand I

1:03:11think that Lynch is is the outlier.

1:03:13Lynch is like the the bad apple. Okay.

1:03:17Of all the work, you know, and I don't

1:03:19know how many uh um out outside

1:03:21contractors you or third party

1:03:23contractors you deal with, but it seems

1:03:25to me that u they by far have been um

1:03:29the least responsive. How's that? So,

1:03:33um, but but we need to know what you're

1:03:34doing. I mean, so we can do an

1:03:36evaluation. So, um, and that's that's

1:03:40all I have to say. I don't know if

1:03:41anyone else on the board has any

1:03:42comments. Please join us. I I'm the only

1:03:45one who seems to talk, so please jump

1:03:47in. Anyone?

1:03:48>> I'm curious about your plan, right?

1:03:50because you know I would imagine being a

1:03:53civil engineer myself that you're

1:03:56planning this work now for next year or

1:04:00subsequent years. So you know some of

1:04:03these impacts

1:04:06for planning purposes and maybe you

1:04:08could come before us or with that list

1:04:12December.

1:04:15I I do I'm not a chapter 90 guy, so

1:04:17that's not my thing. But your storm

1:04:20water improvements, your water

1:04:22improvements, anything uh you know,

1:04:25sewer, sanitary sewer, that kind of

1:04:27stuff, you guys are obviously planning

1:04:32two, three years, four years, five

1:04:34years,

1:04:35>> if I may through the through the chair.

1:04:37Sure. Um so we do have a broad plan of

1:04:41what roads we're looking at um re

1:04:44resurfacing. Um it's fluid because a

1:04:49road it might disintegrate you know

1:04:52within a year and we we have to pivot.

1:04:56So there is there is a planning process

1:04:58but there is also um there's a lot of

1:05:00variables that are in place uh whether

1:05:03it's the road disintegrating or a pipe

1:05:06or dealing with a lot of metal pipes

1:05:08that are disintegrating all at once. So

1:05:12um so we we kind we do have to pivot um

1:05:15you know as as the year goes by. Um in

1:05:19addition to the fact that um our budget

1:05:23isn't usually finalized you the um the

1:05:26the town budget gets finalized a lot

1:05:29earlier than the state budget. So um

1:05:33I'm going to say

1:05:34>> but you could but you could because you

1:05:36have an idea.

1:05:37>> We have an idea. It's just

1:05:38>> and you could kind of come in and go

1:05:40yeah it's fluid. It's variable. Some

1:05:42things may go or may not go or may move

1:05:45but these are the jobs that may have

1:05:48impacts for us

1:05:50>> if if I can through the chair I think

1:05:52it's worthwhile to provide that list to

1:05:54you even if it's even if it changes so

1:05:57that you at least have an idea

1:05:59>> exactly

1:05:59>> because

1:06:02if you don't even have the list that

1:06:04changes then you don't have anything um

1:06:07and that's what we had talked about and

1:06:09like each year and I've watched it the

1:06:11last couple years it does change, but

1:06:12the majority stays the same. And one of

1:06:15the things that we have to do that

1:06:16Joanna and I have talked about is

1:06:19timing. The timing of all this road

1:06:22construction is always crunched.

1:06:25Doesn't have to be like that. It

1:06:27doesn't. And and if things were planned

1:06:30sooner, whether we're submitting

1:06:32information to do sooner in the year, it

1:06:34gives us more time, whether it's us or

1:06:37the contractor, to go in front of you

1:06:38and to share the information with you

1:06:40and get feedback from you. That is my

1:06:42goal with DPW. Um, and then even if we

1:06:47do that, we still have plenty of time in

1:06:49the season if it we just have to do it

1:06:51early enough in the year. The first

1:06:53start, the first thing would be to give

1:06:54you the list that we're working from.

1:06:56You can see we can even do and correct

1:06:59me if I'm wrong, but we can check on

1:07:02those lists what's within 100 ft of a

1:07:05water body. We can like it's fairly easy

1:07:08to tell. We should be able to do that.

1:07:10We can we can definitely provide a a

1:07:12general list. Um the the the specifics

1:07:15that you know where the drainage system

1:07:18is being changed or anything like that

1:07:20that wouldn't happen until you know

1:07:23before before construction. But

1:07:25absolutely I I'm happy to share.

1:07:27>> Yeah. You know, as a resident too, I'll

1:07:29be out driving around. I may know the

1:07:31list. I may just kind of, you know, I

1:07:33didn't see South Street till I think I

1:07:35tried to drive down and it was closed

1:07:37and I just

1:07:39didn't bother. But it's just I know I

1:07:42have to put lists together and I have to

1:07:43get approvals for budgets, etc. So,

1:07:45right.

1:07:46>> And I I know things move,

1:07:48>> but still I just to have it out there.

1:07:52>> Thank you.

1:07:52>> I think it'd be helpful.

1:07:55>> It was a few years ago that they were

1:07:58doing work on Oxford Street. I don't

1:08:00know if it's Oxford Street. near the

1:08:01church near St. Joseph's Church

1:08:04>> and

1:08:06I had driven by.

1:08:07>> This was before you guys. So, yay.

1:08:10Sorry, the pressure is off. Yeah,

1:08:12exactly. When they were doing the work

1:08:15though, I live near there and there was

1:08:18a again a big rain event and the water

1:08:21was ripping down the hill into the pond.

1:08:26So even though it wasn't within a

1:08:28hundred feet

1:08:30>> that they were doing the work, the water

1:08:32was running down that hill into the

1:08:35waterway. So sometimes even though the

1:08:37work may not be within 100 ft,

1:08:40>> it's it does impact that waterway and

1:08:43the storm drains.

1:08:44>> So

1:08:45>> absolutely. And I think even on South

1:08:47Street, I saw that because I mean, yes,

1:08:50there was work within 100 ft of the

1:08:52water, but I think it even started

1:08:54farther away when I saw the stream

1:08:56coming down. Um, you I agree with you

1:09:00100% that any any place like that small

1:09:03stream um

1:09:06could have potentially had a huge

1:09:08impact. And the same thing with the the

1:09:11pond and the lakes. anytime we're doing

1:09:14any work near there I have this newfound

1:09:16respect for um controls erosion controls

1:09:20now since this has happened with Lynch

1:09:22which I I sort of like because I'm

1:09:24interested in it but now when I see

1:09:26construction I live in Wester I see

1:09:28construction work I'm like and I see

1:09:30what they're using I'm like that's not

1:09:31going to hold up that's not going to

1:09:32hold up in a good rainstorm

1:09:33>> you should complain to the conservation

1:09:35commission

1:09:36>> I saw what happened like it some of the

1:09:39controls worked but a good rainstorm

1:09:42they did not went right over. That's

1:09:43right.

1:09:44>> And it's just it's disturbing on what

1:09:46can happen and the impact that has on

1:09:47our environment. So, I just Yeah, I I

1:09:50agree with you. I think we need to be

1:09:52much more conscientious. Um, and we feel

1:09:55exactly the same way you do. And I think

1:09:57improved communications, changing the

1:09:59timeline, changing what's in the bid

1:10:01dock, so no road is open for that amount

1:10:03of time, which was absurd. um and making

1:10:08sure they come before you with not just

1:10:10their SWIP, but like from what I I'm not

1:10:13real familiar with SWIPS, but from what

1:10:15you said, they were it wasn't that

1:10:17strong. It

1:10:19>> Well, the problem is that we never saw

1:10:20the SWIP and and as Peter indicated,

1:10:23it's really that's a different process

1:10:25through it's through the EPA and and

1:10:27their their NEPTAS permit,

1:10:30>> National Pollution Discharge Elimination

1:10:32System.

1:10:34So, um, so that that's a different

1:10:36jurisdiction, but just because they have

1:10:38a they've done a SWIP doesn't relieve

1:10:40them of their responsibility to file

1:10:42with us. And, you know, and and I think

1:10:44to to u Mr. Bora's point, you know, they

1:10:48can have a SWIP and it may be that uh an

1:10:50RDA is sufficient. You know, I would

1:10:52submit that um that one should have

1:10:54filed. I don't know that that an RDA was

1:10:57appropriate, but I think I mean they

1:10:59started that project in June, right?

1:11:03So, it's been we're going on the third

1:11:04month now and um they they had

1:11:08sufficient time to file with us. So,

1:11:09that's not an excuse, you know, and

1:11:11again um I think in emergency situation,

1:11:15I think you do what you need to do. You

1:11:17know, you don't have you notify us maybe

1:11:19after the fact, but uh you don't have

1:11:21to, you know, worry about filing an RDA

1:11:23with us. I mean, exent circumstances, I

1:11:26think, require immediate action.

1:11:30So um okay

1:11:37so I think we have a handle on this. I

1:11:38think we um maybe we can continue this

1:11:41discussion at our next meeting.

1:11:43>> Yep.

1:11:43>> Okay.

1:11:44>> Thank you so much.

1:11:45>> Thank you for coming in.

1:11:46>> Of course. Thank you.

1:11:59All right. So, we've got some decisions

1:12:01to render.

1:12:06Uh, let's do u Masked Futures LLC first.

1:12:10So,

1:12:12I mean,

1:12:14we already issued an order of

1:12:16conditions. DP modified it. I just

1:12:19wonder if by just um recording the plan

1:12:23sheet number three on their amended

1:12:24plans if that's sufficient.

1:12:27>> Sufficient enough for me. Yeah. Me, too.

1:12:29It's like little dots on on any

1:12:32>> Okay. Seriously,

1:12:33>> it's clearly labeled.

1:12:35>> It is clearly It's tiny, but it's

1:12:36clearly labeled. So, if that's the case,

1:12:39is there a motion um to that effect,

1:12:41please?

1:12:45>> How would I say this one? A motion to

1:12:47accept the plans for sheet three with

1:12:50our previous order of conditions.

1:12:52>> Yeah. With the requirement that it be

1:12:53recorded at the registry of deeds. Did

1:12:55you say that?

1:12:56>> I did.

1:12:56>> I think so.

1:12:57>> Okay. Ma'am, didn't hear that part. All

1:12:58right. Is there a second?

1:13:00>> Second. Is there any discussion? All

1:13:02those in favor say I.

1:13:04>> I.

1:13:04>> I.

1:13:06>> Megan, you awake?

1:13:08>> Yes. I

1:13:09>> Okay. All right. Anyone opposed? It's a

1:13:11vote. Um, with respect to um Brenmar.

1:13:17Now, one of the drainage um what what do

1:13:21you call it? a a cy not cyclone, but

1:13:24there's going to be um a um a drainage

1:13:29uh structure that is going to be

1:13:30installed within 100 ft of the wetland.

1:13:34Now, and apparently it's the only one,

1:13:36but I'm a little disturbed by the fact

1:13:38that they didn't provide us with any

1:13:39details concerning the other drain

1:13:41structures they're going to be

1:13:43installing. So, wasn't any in the

1:13:46details?

1:13:47>> This is what I got. I got a site plan. I

1:13:50did not see I got drawings.

1:13:53That's what I got.

1:13:56Unless you got something I didn't get,

1:13:58which is certainly possible.

1:14:01>> I thought I saw usually I could be

1:14:03wrong, too.

1:14:03>> There's usually a detail page. Uh Mark,

1:14:05as you know, at the back,

1:14:08>> uh go back C503.

1:14:10>> Is it

1:14:11>> forward?

1:14:13>> Oh,

1:14:14>> yeah. And

1:14:15>> well, hush my mouth. All right.

1:14:18>> Right. Nope.

1:14:19>> Okay. All right. You're right.

1:14:21>> C503.

1:14:23>> It's a contact.

1:14:24>> Okay.

1:14:26>> NY CDS.

1:14:28>> Well, I would say that they have

1:14:29provided that to us then.

1:14:31>> Yeah.

1:14:32>> I just thought you didn't have it.

1:14:34>> I didn't have one.

1:14:35>> Yeah. Okay. So, um,

1:14:40do we want to I mean, it seems to me

1:14:42since they are doing work within the

1:14:44buffer zone, but it's not it's not like

1:14:48within 25 ft. Do we want to just maybe

1:14:51put in some language to make sure that

1:14:52they are extra special careful when they

1:14:55install that um that unit?

1:14:58>> So, negative determination with

1:15:00>> with a condition.

1:15:03So, is anyone up to making a motion?

1:15:07Anyone? Buer.

1:15:10>> All right.

1:15:12>> Mark, you have the civil

1:15:13>> Yeah, that's

1:15:14>> engineering experience. I was going to

1:15:15say

1:15:16>> motion to

1:15:19motion negative determination of

1:15:21applicability.

1:15:22>> Okay.

1:15:23>> With a condition that the erosion

1:15:28sedimentation controls are in place

1:15:32prior. before work.

1:15:33>> Work stop prior to commencement of any

1:15:36work.

1:15:36>> Okay, that's fair.

1:15:39>> Is any you want anyone want to discuss

1:15:41that? Megan, is that good with you?

1:15:45>> Sounds great to me.

1:15:49>> Thank you.

1:15:50>> Megan,

1:15:51>> yeah. Can you not hear me? That sounds

1:15:53good to me.

1:15:54>> Okay. All right. So, there's a motion.

1:15:56Is there a second?

1:15:57>> All right. Is there any discussion? All

1:15:59those in favor say I.

1:16:01>> I. opposed. It's a vote. All right.

1:16:07>> Okay. Um

1:16:10Nat, do you have anything else?

1:16:12>> No, we got a couple things coming out

1:16:13the pipeline. So,

1:16:14>> okay. But nothing for tonight?

1:16:16>> No. I mean, I have reached out to a

1:16:18couple of different um environmental

1:16:20contractors for hiring a consultant for

1:16:22South Street.

1:16:24>> A lot of conf a lot of people have

1:16:25conflicts of interest.

1:16:27>> I reach Is that right?

1:16:28>> Yes. I've reached out to Ecotech. They

1:16:30have a conflict of interest. Um, they're

1:16:32they don't have any uh

1:16:34>> name on staff.

1:16:35>> Well, they they have too much on their

1:16:37plate. Um, FWCA has a conflict of

1:16:39interest. I've also reached out to CDM

1:16:42Smith. Haven't heard back. GZA, haven't

1:16:44heard back. Titanbond, haven't heard

1:16:45back. And I have not been able to reach

1:16:46Margaret Washburn.

1:16:48>> Okay. As in, you leave messages and she

1:16:50doesn't respond.

1:16:51>> I wasn't even able to get to her

1:16:53voicemail. I think the number I got

1:16:55might not be working. Uh, Paul Dequila

1:16:57is reaching out to his contacts to see.

1:16:59Yeah, maybe go on Google.

1:17:00>> I did go on Google.

1:17:01>> You couldn't find anything, huh? She

1:17:03might be retired. I don't know. Well,

1:17:06>> it's summer. She could be on vacation.

1:17:07>> She could be on vacation.

1:17:09>> Okay.

1:17:10>> I have been

1:17:10>> Well, I appreciate your efforts. Um, but

1:17:12yeah, if you could u stick with that.

1:17:15>> Oh, I will be.

1:17:16>> Okay. In that case, if there's no new

1:17:19business, is there a motion to adjurnn?

1:17:21>> Motion to adjurnn.

1:17:22>> Yep.

1:17:23>> A second.

1:17:24>> Yep. Is not Yep. is not submission. It

1:17:27has to be a second.

1:17:29Okay. All those in favor say I.

1:17:31>> I.

1:17:32>> I.

1:17:32>> I.

1:17:33>> Yeah. No one opposes it ever. All right.

1:17:35It's a vote. All right, everyone. Thank

1:17:36you very much.