2026-08-11 - Fire Station Building Committee

Summary

Written from the auto-generated captions; names and numbers may be misheard.

  • No public comment; minutes of July 7 approved.
  • Construction update: footings and the full building footprint are poured, masons doubled their crew and are building the foundation walls and elevator shaft, underground plumbing and electrical is going in, and the Prospect Street utility work finished smoothly with a police detail. Steel is still expected in September and the work is on schedule with the critical path unaffected. The site was reported clean and safe.
  • A pole-mounted camera takes a still photo every 4 hours for an end-of-project time-lapse, and the fire department flies a drone over the site every Monday, with photos on the town website. The contractor invited the committee to meet on site.
  • Change order one approved for a net $132,433.75: ledge removal around the foundation (quantity reduced about 18 to 20 percent for soil mixed into the hauled rock, priced at bid unit prices with a 15 percent markup) less a credit of about $29,000 for a fire hydrant no longer needed. A change order subcommittee reviewed it and asked for labor and material to be split out in future. More ledge around the apron and drainage is being quantified for a later change order, and crushed ledge may be reused as fill. It will be paid in requisition four.
  • Requisition three approved for $970,158.73 after review of stored materials; members asked about permit fees, two of which were waived by the town and are expected back.
  • Next meeting September 15, possibly starting with a walk of the site; adjourned.

Issues discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:05Good evening. This is the town of

00:06Auburn, Massachusetts Fire Station

00:08Building Committee meeting for August

00:1011th, 2026

00:12at 6:00 p.m. Calling meeting to order.

00:14Um

00:15uh the meeting is being recorded and

00:18broadcast by the local

00:20access cable TV. Ask if anybody else is

00:23recording. Nope, okay.

00:26>> [clears throat and cough]

00:26>> First item on the agenda is public

00:29comment.

00:30Don't have anybody here for a public

00:31comment. Okay, so we move on to

00:33um

00:34the next item the next item is review of

00:37the meeting minutes from July 7th.

00:39Um they're all set to Are there any

00:41questions, comments, corrections to

00:44those meeting minutes?

00:48Okay, seeing none, I would entertain a

00:50motion to approve these meeting minutes.

00:57And do we still have a motion to

00:59approve? Do we have a second?

01:05Okay, so we have

01:07motion to approve and a second. All

01:09those in favor?

01:10I. All those opposed?

01:13It's a vote.

01:15Uh

01:17Fourth item on the agenda is the updates

01:19from the project teams.

01:22Laffield, you're up first.

01:24>> Good evening, everyone. Um

01:27the last month on site has been very

01:28busy. I'm sure you've seen as you've

01:30been driving by. What's the latest on

01:32the minute at the beginning of July? Um

01:35so lots has happened. Masonry contractor

01:38is on site now

01:40and they are continuing to build the

01:42foundation walls with the brick. Um they

01:45built the elevator shaft too as well,

01:46which is looking great out on the site.

01:48It's kind of showing the elevations.

01:51Um the full footprint of the building

01:52has been poured.

01:54Um the footings have been poured also as

01:57well as a lot of the underground

01:59plumbing and electric has all been laid

02:01out.

02:02Lavangie, our electrical contractor, and

02:07NB Kenny have been on site as well, just

02:11working. I know they had a few people on

02:13site today and the past few days

02:16as they gear up and start mobilizing

02:18more and more. Um

02:20I know today

02:21it was a big day on site. The masons,

02:24they doubled their crew. They they were

02:26hard at work today and it was it was

02:28really nice to see.

02:29Um

02:31behind the scenes

02:32Tecton has been great getting back on

02:35submittals and RFIs as they come

02:37through. We met with the change order

02:39subcommittee the other day too as well,

02:42which was great. We finalized change

02:45order one, which you'll see

02:47in a moment too as well to review.

02:50Um

02:51And yeah,

02:54the site contractor uh

02:56Amarillo has been on site every single

02:57day too.

02:59Keeping a clean site. I know that was

03:01raised earlier last month to the GC that

03:05may not have looked the cleanest uh to

03:08the to the owner and to the visiting

03:10eye. So, they've been very on top of

03:12that, which has been great. As well as

03:14the safety, Dave's been on top of them

03:16about hard hats and the PPE and all that

03:19good stuff. So, it's been a clean site,

03:21clean site.

03:23Safe site, yeah.

03:25It's been looking great.

03:27Moving forward the next month or so, do

03:29have the update if you I think you all

03:31have the update in front of you too as

03:32well. Um

03:34But yeah, underground's going to

03:35continue. The masons going to continue.

03:39We're still

03:40gearing for steel in September.

03:43We're still on track for that. We're on

03:45schedule. It's safe to say we're we're

03:47going to maybe going a little out of

03:49order to the original schedule, but

03:51we're still maintaining that critical

03:52path, which has not been affected. So,

03:54that's all good news.

03:56Um

03:57that Techton continues to to respond to

03:59those submittals.

04:01And um also the work on Prospect Street,

04:03that was successfully complete um

04:05smoothly. It took a couple days. We had

04:07a police detail. I don't know if anyone

04:10drove by during those couple days, but

04:12it was moving smoothly.

04:14I

04:15I don't know if you had anything to

04:17Um

04:19And then the uh the foundations will be

04:23backfilled and then poured. Uh the the

04:25pad slabs will be will be poured

04:27following the Mason's uh

04:30foundation wall build.

04:32So, I do have some pictures too just

04:34from this is late last week

04:37uh when the

04:39the elevator shafts are being built, but

04:41now they they took those down since

04:43then.

04:44Um things do move quick over there, so

04:46if one thing's up one day, it's down the

04:48next. They're If it's not there, then

04:50it's up the next, so

04:52um

04:54Yeah.

04:55Progress is going great. I don't know if

04:56Steve has anything else to add.

04:58So.

04:59Uh

05:00>> Um not really. It's It's that's well It

05:02doesn't look like much, but they've done

05:04a ton of work. This is all foundations

05:05are done.

05:06I'm focusing on Mason's also focusing on

05:09the the walls there.

05:11Takes to the foundation walls. So, we're

05:14doing the exterior shell walls. So, the

05:16elevator shaft will be building the

05:17elevator shaft early.

05:19We are using steel for our elevator

05:21shafts for our bracing

05:22structure.

05:24See here what I

05:26What's the other side of that?

05:27Um but they just I was there today. They

05:29just started doing the initial courses

05:31of the um

05:33CMU block

05:34foundation walls.

05:36Around there.

05:37See maybe here

05:40uh

05:40the bracing

05:41on the walls.

05:45>> And then Dave's done great uh every day

05:47doing the QA QC on site too as well,

05:50making sure means and method are correct

05:52and to the specifications, so

05:55I applaud Dave for that too as well.

05:59Thank you.

06:06Yeah.

06:12Yeah, super high. I know what you're

06:13saying. Yep.

06:14Okay, in the drift. [clears throat]

06:33Good question. Yeah.

06:38Yes.

06:39Yes, it is. Yeah. Yeah, I believe that

06:42there's the it takes a picture every

06:454 hours. Yeah, so that has been

06:47documented. I'm pretty sure this the

06:49department has been keeping the taking

06:51the SD drive out of there. I'm not sure

06:54how they've been holding that, but

06:55>> Yeah, so just to be clear, it's not a

06:57video camera. It's a it's a camera

06:59that's mounted to the pole in the car

07:00dealership and it takes a still

07:02photograph every 4 hours. And what we'll

07:05do at the end of the project is we're

07:07going to create a time-lapse video with

07:09all of that still photography. So, it's

07:11not a it's not a video camera with a

07:13live feed.

07:15>> Thank you.

07:16In addition to that too, the fire

07:17department has been bringing the drone,

07:19I want to say once a week maybe.

07:22Yeah, every Monday. Yeah, they've been

07:23bringing it over site, taking pictures,

07:25scoping out everything from bird's eye

07:26view, so it's been

07:28great documentation. Just

07:30to hold everyone accountable and see the

07:31progress.

07:34>> Yeah, if you

07:37we were just talking before and the

07:39you You to the website on the town

07:42website and stuff and you go to the fire

07:43station building, you'll see the the

07:45latest updates. Drone there's four drone

07:48shots I think on there.

07:51Yeah.

07:52So,

07:53you'll see those on there.

07:55And they're pretty neat.

07:57Good good perspective on the job.

08:00>> Yeah, yeah. It's like a sky view.

08:03>> And it looks like the plans, too, when

08:04you look at it from above. So, that's

08:06the

08:06You're like, "Oh,

08:08I've been staring at the plans for so

08:09long." You look at that and you're like,

08:10"Oh, I recognize that."

08:12So.

08:15>> Yeah,

08:16I know the fire department did visit the

08:18site last week after hours just to take

08:22a peek at it, see what was going on. I

08:24know that it was discussed during our

08:26job meeting today as well that we'd love

08:28to have the building committee show up

08:31maybe next month for next month's

08:32meeting. We can talk about that when

08:34we're scheduling the next one at the end

08:35of the meeting, but yeah, it's certain

08:37certainly something that we're looking

08:38forward to having everyone come out and

08:41take a peek walk the site, you know.

08:43Yeah, it'd be nice.

08:45So.

08:45>> So, yeah, we can talk

08:49>> Yeah, yeah. Yeah, no Yeah, no sandals.

08:52Yeah, we'll talk about that then.

08:54Sure, [laughter] yeah. Everyone's

08:55wearing a roof for the for a year.

08:59>> Okay, any other questions just about

09:01general progress? Okay.

09:03>> Do you have access to the bid docs? Is

09:04that

09:05>> Yeah, everyone should have got Did

09:06everyone No?

09:07>> No.

09:08>> Nothing.

09:08>> Nothing.

09:09>> Nothing.

09:09>> Nothing.

09:11>> All right, I'll follow up with Noreen. I

09:13was told that you

09:15received that.

09:16Cuz I gave them the list cuz Dave took

09:18it last meeting. So, I gave everything

09:21All right, I'll I'll double check

09:22though.

09:23>> Sometimes it goes to junk mail.

09:26>> Wasn't in there.

09:29>> I'll follow up with you guys then. I'm

09:31sorry about that.

09:33I gave Noreen the list. So, I can

09:35definitely follow up. I'll have an

09:36answer for you tomorrow.

09:45>> Okay.

09:46Uh

09:47moving on. So, brick review and change

09:50orders.

09:51>> Yeah, for now. So, you

09:53>> Yeah, so payment requisition

09:54requisition three.

09:56I think I gave you a few copies.

10:01Uh or there's one big copy here. I think

10:03you picked it up. Let's see.

10:05I also it was in your emails, too. Um

10:07well

10:09Also

10:09>> You can give it I already sent the email

10:11to them so they can see.

10:14>> So, these are the wet copies.

10:16Um

10:19Yeah, so the review process for the rep

10:22uh

10:23it's typically submitted the 20th of the

10:26month, right around there. Uh Tech-Con

10:29and their team will review it for

10:31it even goes up to anyone on the

10:33committee as well as Joe and then they

10:36uh will vet the key numbers, make sure

10:38that the stored materials are still

10:39there.

10:40Um I know that

10:42uh Joe has gone out to

10:44CJF, who is the

10:46tiler, the

10:48the tile uh sub trade, make sure that

10:50the stored materials were there, and

10:52they were. Um

10:53and I know that Matt from Tech-Con came

10:56up with a long list of items that uh

10:58were responded to and adjusted uh in the

11:01rep that you see today. So, um it goes

11:04through a vetting process

11:06before

11:07it gets signed by myself and Stephen,

11:10so.

11:13I think the amount uh I don't have an

11:15answer for you.

11:17Yeah, if you want to show the agreed

11:18amount, that's

11:24>> Has it been

11:25>> change orders.

11:26>> Has it been Yeah, I was going to say.

11:28Yeah, I was going to say we should do

11:29the change order first.

11:30>> Oh, we can do that.

11:30>> Do you want to start there?

11:31>> Yeah.

11:32>> Oh, wait. Okay.

11:33>> Oh, yeah. Yeah.

11:41>> So, typically

11:43we're going to have a line item agenda

11:45just outlining change orders. And if we

11:47don't need to use it, we won't use it,

11:49but at least it'll be part of the agenda

11:50moving forward. Typically, change orders

11:52are discussed and if the recommendation

11:54from subcommittee is the recommendation

11:57of the full committee, it usually gets

11:59included

12:00uh within the requisition.

12:03So, there change order one

12:05consists of two different items. First

12:07one I discussed last meeting about the

12:09ledge quantities that we encountered

12:11on site around the perimeter of the

12:14foundation.

12:15We quantified them. They gave us the

12:18overall trucking slips associated with

12:21this attached to change order.

12:23There was approximately

12:2518 to 20% reduction in the overall

12:28quantity because when you

12:30when we did the top of the top of rock

12:33and then we went to the bottom of top

12:35of, you know, the density of ledge when

12:38it's in the ground is X. When you break

12:41it up and you put it in a pile and then

12:44haul it out of there, you get a little

12:46bit of a cross contamination of just

12:48soil in general. So, we took a 20%

12:50reduction

12:51off of the quantities that were

12:53submitted and came up with that $138,000

12:57of ledge that was removed out. That was

12:59trucked directly from the site.

13:01Um there is markup with a 15% along with

13:05that, which brought it up to $61,000 for

13:08the overall ledge for that particular

13:11location. In addition to that, there was

13:13a second change. We would we

13:16looked at the drawings and there was a

13:18fire hydrant that was not going to be

13:21necessary on site. So, we took a credit

13:24on that. We've asked them for the

13:25breakout for labor and material which

13:28they provided and it was about a 29,000

13:31in change reduction in the in the

13:34contract. So the net turned out to be

13:36100 and

13:4030 about 160.

13:41>> Yeah, 130.

13:42>> 132,433,75.

13:46We brought it to the sub committee. We

13:47had a

13:48lengthy discussion um

13:50about like

13:52the process and how we got there. Just a

13:54refresher for everybody's memory and to

13:55bring them back up to speed. We did do

13:57test borings and test pits um on site

14:00and we did it a pretty good grid pattern

14:03across the open

14:04the side of that property. Um the

14:07borings and test pits did show on the

14:10report there was resistance and what

14:12resistance could be two two or three

14:14different things but typically it's

14:16either rocks or ledge and they

14:18identified it on the

14:20uh

14:21on the geo tech report. What we did as a

14:24team, we carried a certain value of uh

14:28ledge removal. Um obviously you know as

14:31the ledge was discovered it was higher

14:33up towards the Dunkin Donuts property

14:35and then

14:36tapered off towards the parking lot

14:38section. Obviously uh and the quantities

14:41were reflected in that as well.

14:43So this is what we captured. We uh with

14:45our on site rep as well as our team

14:48every week has been

14:49uh reviewing the information and the

14:51topographical um

14:54report that came

14:55the side of your and our team just to

14:57make sure that you know everybody's

14:59playing by the same rules.

15:03Any questions?

15:05>> [clears throat]

15:06>> We anticipate just so we're all clear,

15:08we're we anticipate another

15:11uh round of ledge uh

15:13around the apron area and some of the uh

15:16drainage and infrastructure on the

15:18outside of the foundation is being

15:20quantified right now. We've been

15:22senseless. We're probably going to

15:24schedule another meeting with the

15:26uh change order committee just to

15:27discuss those quantities. We'll present

15:29it to them and give them the facts

15:31associated with that. And I'll probably

15:33present to that on next week.

15:35That should be the

15:37majority

15:38of ledge discovered. We're We're We

15:40would have exposed it and at least

15:43uh removed it so that in the near future

15:45we won't have to deal with it.

15:46The good news is imported material uh

15:49we're going to get a break on that

15:50because obviously some of the ledge

15:51that's uh leaving is going to be uh

15:54crushed and it's going to be utilized

15:56for uh

15:58material back on site as you know kind

16:00of fill in some of the

16:01uh structural fill if if it passes

16:04specification. So, it'll be It should be

16:07uh

16:08a a net not favorable to us.

16:13Questions at all?

16:15>> I was just going to say so the change

16:17order subcommittee did meet yesterday

16:20to review the two items that are here

16:22plus the future

16:24um item and uh the three of us agreed to

16:28um

16:29essentially bring this forward to the

16:30committee for full approval. The The two

16:32items I think we've felt that there was

16:34enough information backing it to go

16:37ahead and and approve those.

16:39Um we did get the

16:40sort of we had some requests on some

16:42additional uh formatting and and the way

16:45we want to see this going forward so

16:47that we uh

16:49basically we get

16:50material and labor separated out when we

16:52get these change orders and and some you

16:55know, formatting and presentation things

16:57as well.

16:58Um so, the the change order here and I

17:01had

17:01assumed we're okay with those two items

17:03and calling it change order one versus

17:05having two change orders.

17:06>> change order one. It It was

17:08It was produced from bid docs and signed

17:11by both uh director back here, OPW.

17:14>> So.

17:15>> Yes, so that second round of ledge will

17:16be

17:17PC of three or four depending on when

17:19>> Yeah.

17:21Cuz there's a couple of just to be

17:22clear, it's change order one but the

17:25it's proposed change order is that gate

17:26compass it could be you know, one it

17:28could be seven. That gets included in

17:30change order.

17:33>> Can I just through the chair ask how

17:35does

17:36uh the cost get calculated? Is it square

17:38foot? Is it by pound? Is it by ton?

17:40>> It's by unit cost. So uh we have in the

17:44documents we we felt we're going to

17:46encounter so we asked them for even the

17:48price on that. It was part of the um bid

17:51documents and part of the specifications

17:53and we calculated off of that.

17:56>> And is it split between the cost of

17:58breaking it up and getting out of the

17:59ground and trucking it off?

18:00>> Combination.

18:02So it's means and methods. I mean I've

18:04seen people remove legs by blasting as

18:07well. It's it's by unit price.

18:09Based on that.

18:10>> Thank you.

18:11>> You're welcome.

18:16>> [clears throat]

18:16>> Any other questions?

18:18Comments?

18:19>> Okay.

18:20>> Okay.

18:21Thank you.

18:22>> Take a vote.

18:24>> Um

18:26It is change It is change order one in

18:28the uh

18:31It's not in requisition three though, is

18:32it?

18:33>> Yeah.

18:34>> It's not.

18:34>> No, it'll be in four.

18:35>> Okay.

18:37Okay.

18:39So um

18:41taking one at a time then. So

18:42change order one

18:45He's presented the uh subcommittee met

18:47on it and looked at it and everything

18:48made the recommendations.

18:50Um there's no other questions or

18:52comments and stuff. I'd entertain a

18:53motion to approve

18:55change order one.

18:56>> So I'll move that we approve change

18:59order number one dated August 11th, 2026

19:03for a total of $132,433.75.

19:13>> Okay, so you have a motion. Motion to

19:15approve change order one. Do we have a

19:17second?

19:18>> I'll make a second on that.

19:21>> Second.

19:22>> And

19:23>> Okay.

19:25Um so motion to approve change order one

19:28dated 11/20/26

19:31for $132,433.75.

19:35Um all those in favor?

19:37>> Aye.

19:37>> Aye. Thank you. All those opposed?

19:39That's approved.

19:41>> Okay.

19:41>> [clears throat]

19:42>> So yeah, change order one will be

19:43included in pay requisition four next

19:46month.

19:46>> Okay.

19:47>> Why'd you give me this?

19:48>> So

19:50>> Well, I can probably It's online.

19:52>> Okay, so why'd you give me this?

19:53>> I don't know if anyone wanted it I had a

19:56hard copy of it.

19:56>> Oh.

19:58>> But you Joe has one online, but we don't

19:59need it.

20:00>> Okay.

20:01>> Um

20:03and then

20:05requisition three was sent out to

20:07everybody in their packets and stuff. I

20:08don't know if there's any questions,

20:09comments

20:11on what was presented and stuff

20:14for requisition three?

20:26>> All right. Can we put that up with the

20:28Do you have that accurate?

20:29>> Yeah, I have it, but I didn't

20:31>> Do you have a copy? I just want to

20:34give the total, I guess, when we get

20:36there.

20:39>> I think I have it.

20:40>> 27,000 you have?

20:41>> Okay.

20:42>> But the

20:43>> Yeah.

20:43>> permitting fees included in that?

20:47>> Only a portion. So

20:49the interest

20:50>> Yes.

20:52>> Not all.

20:53There are like um

20:56there was one or two permits that were

20:58outside of

21:00standard practice that

21:04>> Well, I saw

21:05two of them in two of them there. At

21:07least at least two.

21:08>> Right. Okay.

21:15They were waived by the town. So, we'd

21:17expect that money back.

21:20>> On those two, I'm I'm pretty sure we and

21:23I have I'll check with the chief. He was

21:24looking at it. Those two entities were

21:26the only two that were re-charged with

21:28the project.

21:29I don't know the reason behind it but

21:31I'll check.

21:32>> Okay.

21:33>> Right now, we're tracking the fee

21:35waivers.

21:36>> I mean, it's like $3,000 total or

21:38something.

21:40>> Most

21:41most projects in the Commonwealth, they

21:43tend not to bond

21:45revenue fees. Now, I've had it where

21:48they include revenue fees in my day.

22:02Typically,

22:04you know, most

22:15>> Cuz like the water district is separate,

22:17so any any permit fees there the town

22:20doesn't

22:22Yeah, so that would have to be paid but

22:23adding anything to the town, I I

22:25wouldn't want to pay.

22:37>> [laughter]

22:50>> No, I was just wondering, you know, why

22:51we were paying us to pay us.

22:59Okay.

23:14>> She has the email.

23:16>> What?

23:17>> You got it. Okay.

23:19>> Are we ready?

23:21Anyone else?

23:23All right.

23:24I'm going to make a motion that we

23:26approve requisition three

23:28uh for the total of $970,158.73.

23:38>> All right. There's a motion to approve

23:40requisition three. Uh

23:42do we have a second?

23:43>> Second.

23:44>> Do we have a second?

23:46Um

23:48So

23:49uh the motion and the second to to

23:52approve requisition three for nine

23:54hundred seventy thousand one hundred

23:57fifty-eight and seventy-three cents. Um

24:01So all those in favor?

24:03>> Aye.

24:03>> Aye.

24:04>> All those opposed?

24:05It's approved.

24:15All right. Um

24:18So I think our next agenda item is the

24:19second public comment section and still

24:22no public comment here.

24:24Um So right now tentative our next

24:28meeting would be September 15th.

24:31Um

24:32and we may

24:34make that a site visit with site visit

24:36first and then come here or do

24:38something.

24:38>> I think I'd rather meet right on site.

24:41>> All right. Good week.

24:41>> So you could make arrangements with the

24:43proper cable television

24:45>> Do a remote. Yeah. Yeah.

24:47>> You could have the meeting in the truck.

24:48>> Okay.

24:49>> And then

24:52>> Alternatively too, I don't know if West

24:54Street would be open, but I know it's a

24:56close quarters to the site to be sure.

24:59>> It's all or nothing as far away from

25:01anything.

25:02>> [laughter]

25:03>> This is pretty close, too.

25:05>> Oh, it is?

25:06>> It's down the street.

25:07>> Yeah, I got to came a different way,

25:08huh?

25:09>> Yeah.

25:09>> I don't mind that. Sorry, scratch that.

25:12Yeah, but on-site definitely. We should

25:13like if we would

25:15you want to meet on-site prior? I don't

25:17know if everyone's available like half

25:19hour or before like 5:30-ish?

25:22You wanted to like you know what I mean?

25:24Like meet as a Yeah, meet as a committee

25:26there, walk the site, and then go to the

25:28trailer have the meeting that way you

25:30know kind of what we're talking about

25:32and see if you guys

25:33reply to us.

25:35Give you an update, which I'm sure we

25:37will.

25:38>> Yep.

25:38>> Yep.

25:39>> Okay.

25:39>> Yeah.

25:41>> Sounds good.

25:43All right. So, I guess that brings us to

25:45the end of our agenda for tonight. So,

25:47take a motion to adjourn.

25:49>> So moved.

25:51>> And all those in favor?

25:53>> I

25:53I think we need a second.

25:54>> Wait a minute.

25:55>> Second.

25:56>> Second.

25:57>> It's all moved.

25:58>> All those in favor?

25:59>> Aye.

25:59>> We're there.

26:00>> Thank you.