2026-08-11 - Fire Station Building Committee
Summary
Written from the auto-generated captions; names and numbers may be misheard.
- No public comment; minutes of July 7 approved.
- Construction update: footings and the full building footprint are poured, masons doubled their crew and are building the foundation walls and elevator shaft, underground plumbing and electrical is going in, and the Prospect Street utility work finished smoothly with a police detail. Steel is still expected in September and the work is on schedule with the critical path unaffected. The site was reported clean and safe.
- A pole-mounted camera takes a still photo every 4 hours for an end-of-project time-lapse, and the fire department flies a drone over the site every Monday, with photos on the town website. The contractor invited the committee to meet on site.
- Change order one approved for a net $132,433.75: ledge removal around the foundation (quantity reduced about 18 to 20 percent for soil mixed into the hauled rock, priced at bid unit prices with a 15 percent markup) less a credit of about $29,000 for a fire hydrant no longer needed. A change order subcommittee reviewed it and asked for labor and material to be split out in future. More ledge around the apron and drainage is being quantified for a later change order, and crushed ledge may be reused as fill. It will be paid in requisition four.
- Requisition three approved for $970,158.73 after review of stored materials; members asked about permit fees, two of which were waived by the town and are expected back.
- Next meeting September 15, possibly starting with a walk of the site; adjourned.
Issues discussed
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:05Good evening. This is the town of
00:06Auburn, Massachusetts Fire Station
00:08Building Committee meeting for August
00:1011th, 2026
00:12at 6:00 p.m. Calling meeting to order.
00:14Um
00:15uh the meeting is being recorded and
00:18broadcast by the local
00:20access cable TV. Ask if anybody else is
00:23recording. Nope, okay.
00:26>> [clears throat and cough]
00:26>> First item on the agenda is public
00:29comment.
00:30Don't have anybody here for a public
00:31comment. Okay, so we move on to
00:33um
00:34the next item the next item is review of
00:37the meeting minutes from July 7th.
00:39Um they're all set to Are there any
00:41questions, comments, corrections to
00:44those meeting minutes?
00:48Okay, seeing none, I would entertain a
00:50motion to approve these meeting minutes.
00:57And do we still have a motion to
00:59approve? Do we have a second?
01:05Okay, so we have
01:07motion to approve and a second. All
01:09those in favor?
01:10I. All those opposed?
01:13It's a vote.
01:15Uh
01:17Fourth item on the agenda is the updates
01:19from the project teams.
01:22Laffield, you're up first.
01:24>> Good evening, everyone. Um
01:27the last month on site has been very
01:28busy. I'm sure you've seen as you've
01:30been driving by. What's the latest on
01:32the minute at the beginning of July? Um
01:35so lots has happened. Masonry contractor
01:38is on site now
01:40and they are continuing to build the
01:42foundation walls with the brick. Um they
01:45built the elevator shaft too as well,
01:46which is looking great out on the site.
01:48It's kind of showing the elevations.
01:51Um the full footprint of the building
01:52has been poured.
01:54Um the footings have been poured also as
01:57well as a lot of the underground
01:59plumbing and electric has all been laid
02:01out.
02:02Lavangie, our electrical contractor, and
02:07NB Kenny have been on site as well, just
02:11working. I know they had a few people on
02:13site today and the past few days
02:16as they gear up and start mobilizing
02:18more and more. Um
02:20I know today
02:21it was a big day on site. The masons,
02:24they doubled their crew. They they were
02:26hard at work today and it was it was
02:28really nice to see.
02:29Um
02:31behind the scenes
02:32Tecton has been great getting back on
02:35submittals and RFIs as they come
02:37through. We met with the change order
02:39subcommittee the other day too as well,
02:42which was great. We finalized change
02:45order one, which you'll see
02:47in a moment too as well to review.
02:50Um
02:51And yeah,
02:54the site contractor uh
02:56Amarillo has been on site every single
02:57day too.
02:59Keeping a clean site. I know that was
03:01raised earlier last month to the GC that
03:05may not have looked the cleanest uh to
03:08the to the owner and to the visiting
03:10eye. So, they've been very on top of
03:12that, which has been great. As well as
03:14the safety, Dave's been on top of them
03:16about hard hats and the PPE and all that
03:19good stuff. So, it's been a clean site,
03:21clean site.
03:23Safe site, yeah.
03:25It's been looking great.
03:27Moving forward the next month or so, do
03:29have the update if you I think you all
03:31have the update in front of you too as
03:32well. Um
03:34But yeah, underground's going to
03:35continue. The masons going to continue.
03:39We're still
03:40gearing for steel in September.
03:43We're still on track for that. We're on
03:45schedule. It's safe to say we're we're
03:47going to maybe going a little out of
03:49order to the original schedule, but
03:51we're still maintaining that critical
03:52path, which has not been affected. So,
03:54that's all good news.
03:56Um
03:57that Techton continues to to respond to
03:59those submittals.
04:01And um also the work on Prospect Street,
04:03that was successfully complete um
04:05smoothly. It took a couple days. We had
04:07a police detail. I don't know if anyone
04:10drove by during those couple days, but
04:12it was moving smoothly.
04:15I don't know if you had anything to
04:17Um
04:19And then the uh the foundations will be
04:23backfilled and then poured. Uh the the
04:25pad slabs will be will be poured
04:27following the Mason's uh
04:30foundation wall build.
04:32So, I do have some pictures too just
04:34from this is late last week
04:37uh when the
04:39the elevator shafts are being built, but
04:41now they they took those down since
04:43then.
04:44Um things do move quick over there, so
04:46if one thing's up one day, it's down the
04:48next. They're If it's not there, then
04:50it's up the next, so
04:52um
04:54Yeah.
04:55Progress is going great. I don't know if
04:56Steve has anything else to add.
04:58So.
04:59Uh
05:00>> Um not really. It's It's that's well It
05:02doesn't look like much, but they've done
05:04a ton of work. This is all foundations
05:05are done.
05:06I'm focusing on Mason's also focusing on
05:09the the walls there.
05:11Takes to the foundation walls. So, we're
05:14doing the exterior shell walls. So, the
05:16elevator shaft will be building the
05:17elevator shaft early.
05:19We are using steel for our elevator
05:21shafts for our bracing
05:22structure.
05:24See here what I
05:26What's the other side of that?
05:27Um but they just I was there today. They
05:29just started doing the initial courses
05:31of the um
05:33CMU block
05:34foundation walls.
05:36Around there.
05:37See maybe here
05:40uh
05:40the bracing
05:41on the walls.
05:45>> And then Dave's done great uh every day
05:47doing the QA QC on site too as well,
05:50making sure means and method are correct
05:52and to the specifications, so
05:55I applaud Dave for that too as well.
05:59Thank you.
06:06Yeah.
06:12Yeah, super high. I know what you're
06:13saying. Yep.
06:14Okay, in the drift. [clears throat]
06:33Good question. Yeah.
06:38Yes.
06:39Yes, it is. Yeah. Yeah, I believe that
06:42there's the it takes a picture every
06:454 hours. Yeah, so that has been
06:47documented. I'm pretty sure this the
06:49department has been keeping the taking
06:51the SD drive out of there. I'm not sure
06:54how they've been holding that, but
06:55>> Yeah, so just to be clear, it's not a
06:57video camera. It's a it's a camera
06:59that's mounted to the pole in the car
07:00dealership and it takes a still
07:02photograph every 4 hours. And what we'll
07:05do at the end of the project is we're
07:07going to create a time-lapse video with
07:09all of that still photography. So, it's
07:11not a it's not a video camera with a
07:13live feed.
07:15>> Thank you.
07:16In addition to that too, the fire
07:17department has been bringing the drone,
07:19I want to say once a week maybe.
07:22Yeah, every Monday. Yeah, they've been
07:23bringing it over site, taking pictures,
07:25scoping out everything from bird's eye
07:26view, so it's been
07:28great documentation. Just
07:30to hold everyone accountable and see the
07:31progress.
07:34>> Yeah, if you
07:37we were just talking before and the
07:39you You to the website on the town
07:42website and stuff and you go to the fire
07:43station building, you'll see the the
07:45latest updates. Drone there's four drone
07:48shots I think on there.
07:51Yeah.
07:52So,
07:53you'll see those on there.
07:55And they're pretty neat.
07:57Good good perspective on the job.
08:00>> Yeah, yeah. It's like a sky view.
08:03>> And it looks like the plans, too, when
08:04you look at it from above. So, that's
08:06the
08:06You're like, "Oh,
08:08I've been staring at the plans for so
08:09long." You look at that and you're like,
08:10"Oh, I recognize that."
08:12So.
08:15>> Yeah,
08:16I know the fire department did visit the
08:18site last week after hours just to take
08:22a peek at it, see what was going on. I
08:24know that it was discussed during our
08:26job meeting today as well that we'd love
08:28to have the building committee show up
08:31maybe next month for next month's
08:32meeting. We can talk about that when
08:34we're scheduling the next one at the end
08:35of the meeting, but yeah, it's certain
08:37certainly something that we're looking
08:38forward to having everyone come out and
08:41take a peek walk the site, you know.
08:43Yeah, it'd be nice.
08:45So.
08:45>> So, yeah, we can talk
08:49>> Yeah, yeah. Yeah, no Yeah, no sandals.
08:52Yeah, we'll talk about that then.
08:54Sure, [laughter] yeah. Everyone's
08:55wearing a roof for the for a year.
08:59>> Okay, any other questions just about
09:01general progress? Okay.
09:03>> Do you have access to the bid docs? Is
09:04that
09:05>> Yeah, everyone should have got Did
09:06everyone No?
09:07>> No.
09:08>> Nothing.
09:08>> Nothing.
09:09>> Nothing.
09:09>> Nothing.
09:11>> All right, I'll follow up with Noreen. I
09:13was told that you
09:15received that.
09:16Cuz I gave them the list cuz Dave took
09:18it last meeting. So, I gave everything
09:21All right, I'll I'll double check
09:22though.
09:23>> Sometimes it goes to junk mail.
09:26>> Wasn't in there.
09:29>> I'll follow up with you guys then. I'm
09:31sorry about that.
09:33I gave Noreen the list. So, I can
09:35definitely follow up. I'll have an
09:36answer for you tomorrow.
09:45>> Okay.
09:46Uh
09:47moving on. So, brick review and change
09:50orders.
09:51>> Yeah, for now. So, you
09:53>> Yeah, so payment requisition
09:54requisition three.
09:56I think I gave you a few copies.
10:01Uh or there's one big copy here. I think
10:03you picked it up. Let's see.
10:05I also it was in your emails, too. Um
10:07well
10:09Also
10:09>> You can give it I already sent the email
10:11to them so they can see.
10:14>> So, these are the wet copies.
10:16Um
10:19Yeah, so the review process for the rep
10:22uh
10:23it's typically submitted the 20th of the
10:26month, right around there. Uh Tech-Con
10:29and their team will review it for
10:31it even goes up to anyone on the
10:33committee as well as Joe and then they
10:36uh will vet the key numbers, make sure
10:38that the stored materials are still
10:39there.
10:40Um I know that
10:42uh Joe has gone out to
10:44CJF, who is the
10:46tiler, the
10:48the tile uh sub trade, make sure that
10:50the stored materials were there, and
10:52they were. Um
10:53and I know that Matt from Tech-Con came
10:56up with a long list of items that uh
10:58were responded to and adjusted uh in the
11:01rep that you see today. So, um it goes
11:04through a vetting process
11:06before
11:07it gets signed by myself and Stephen,
11:10so.
11:13I think the amount uh I don't have an
11:15answer for you.
11:17Yeah, if you want to show the agreed
11:18amount, that's
11:24>> Has it been
11:25>> change orders.
11:26>> Has it been Yeah, I was going to say.
11:28Yeah, I was going to say we should do
11:29the change order first.
11:30>> Oh, we can do that.
11:30>> Do you want to start there?
11:31>> Yeah.
11:32>> Oh, wait. Okay.
11:33>> Oh, yeah. Yeah.
11:41>> So, typically
11:43we're going to have a line item agenda
11:45just outlining change orders. And if we
11:47don't need to use it, we won't use it,
11:49but at least it'll be part of the agenda
11:50moving forward. Typically, change orders
11:52are discussed and if the recommendation
11:54from subcommittee is the recommendation
11:57of the full committee, it usually gets
11:59included
12:00uh within the requisition.
12:03So, there change order one
12:05consists of two different items. First
12:07one I discussed last meeting about the
12:09ledge quantities that we encountered
12:11on site around the perimeter of the
12:14foundation.
12:15We quantified them. They gave us the
12:18overall trucking slips associated with
12:21this attached to change order.
12:23There was approximately
12:2518 to 20% reduction in the overall
12:28quantity because when you
12:30when we did the top of the top of rock
12:33and then we went to the bottom of top
12:35of, you know, the density of ledge when
12:38it's in the ground is X. When you break
12:41it up and you put it in a pile and then
12:44haul it out of there, you get a little
12:46bit of a cross contamination of just
12:48soil in general. So, we took a 20%
12:50reduction
12:51off of the quantities that were
12:53submitted and came up with that $138,000
12:57of ledge that was removed out. That was
12:59trucked directly from the site.
13:01Um there is markup with a 15% along with
13:05that, which brought it up to $61,000 for
13:08the overall ledge for that particular
13:11location. In addition to that, there was
13:13a second change. We would we
13:16looked at the drawings and there was a
13:18fire hydrant that was not going to be
13:21necessary on site. So, we took a credit
13:24on that. We've asked them for the
13:25breakout for labor and material which
13:28they provided and it was about a 29,000
13:31in change reduction in the in the
13:34contract. So the net turned out to be
13:36100 and
13:4030 about 160.
13:41>> Yeah, 130.
13:42>> 132,433,75.
13:46We brought it to the sub committee. We
13:47had a
13:48lengthy discussion um
13:50about like
13:52the process and how we got there. Just a
13:54refresher for everybody's memory and to
13:55bring them back up to speed. We did do
13:57test borings and test pits um on site
14:00and we did it a pretty good grid pattern
14:03across the open
14:04the side of that property. Um the
14:07borings and test pits did show on the
14:10report there was resistance and what
14:12resistance could be two two or three
14:14different things but typically it's
14:16either rocks or ledge and they
14:18identified it on the
14:20uh
14:21on the geo tech report. What we did as a
14:24team, we carried a certain value of uh
14:28ledge removal. Um obviously you know as
14:31the ledge was discovered it was higher
14:33up towards the Dunkin Donuts property
14:35and then
14:36tapered off towards the parking lot
14:38section. Obviously uh and the quantities
14:41were reflected in that as well.
14:43So this is what we captured. We uh with
14:45our on site rep as well as our team
14:48every week has been
14:49uh reviewing the information and the
14:51topographical um
14:54report that came
14:55the side of your and our team just to
14:57make sure that you know everybody's
14:59playing by the same rules.
15:03Any questions?
15:05>> [clears throat]
15:06>> We anticipate just so we're all clear,
15:08we're we anticipate another
15:11uh round of ledge uh
15:13around the apron area and some of the uh
15:16drainage and infrastructure on the
15:18outside of the foundation is being
15:20quantified right now. We've been
15:22senseless. We're probably going to
15:24schedule another meeting with the
15:26uh change order committee just to
15:27discuss those quantities. We'll present
15:29it to them and give them the facts
15:31associated with that. And I'll probably
15:33present to that on next week.
15:35That should be the
15:37majority
15:38of ledge discovered. We're We're We
15:40would have exposed it and at least
15:43uh removed it so that in the near future
15:45we won't have to deal with it.
15:46The good news is imported material uh
15:49we're going to get a break on that
15:50because obviously some of the ledge
15:51that's uh leaving is going to be uh
15:54crushed and it's going to be utilized
15:56for uh
15:58material back on site as you know kind
16:00of fill in some of the
16:01uh structural fill if if it passes
16:04specification. So, it'll be It should be
16:07uh
16:08a a net not favorable to us.
16:13Questions at all?
16:15>> I was just going to say so the change
16:17order subcommittee did meet yesterday
16:20to review the two items that are here
16:22plus the future
16:24um item and uh the three of us agreed to
16:28um
16:29essentially bring this forward to the
16:30committee for full approval. The The two
16:32items I think we've felt that there was
16:34enough information backing it to go
16:37ahead and and approve those.
16:39Um we did get the
16:40sort of we had some requests on some
16:42additional uh formatting and and the way
16:45we want to see this going forward so
16:47that we uh
16:49basically we get
16:50material and labor separated out when we
16:52get these change orders and and some you
16:55know, formatting and presentation things
16:57as well.
16:58Um so, the the change order here and I
17:01had
17:01assumed we're okay with those two items
17:03and calling it change order one versus
17:05having two change orders.
17:06>> change order one. It It was
17:08It was produced from bid docs and signed
17:11by both uh director back here, OPW.
17:14>> So.
17:15>> Yes, so that second round of ledge will
17:16be
17:17PC of three or four depending on when
17:19>> Yeah.
17:21Cuz there's a couple of just to be
17:22clear, it's change order one but the
17:25it's proposed change order is that gate
17:26compass it could be you know, one it
17:28could be seven. That gets included in
17:30change order.
17:33>> Can I just through the chair ask how
17:35does
17:36uh the cost get calculated? Is it square
17:38foot? Is it by pound? Is it by ton?
17:40>> It's by unit cost. So uh we have in the
17:44documents we we felt we're going to
17:46encounter so we asked them for even the
17:48price on that. It was part of the um bid
17:51documents and part of the specifications
17:53and we calculated off of that.
17:56>> And is it split between the cost of
17:58breaking it up and getting out of the
17:59ground and trucking it off?
18:00>> Combination.
18:02So it's means and methods. I mean I've
18:04seen people remove legs by blasting as
18:07well. It's it's by unit price.
18:09Based on that.
18:10>> Thank you.
18:11>> You're welcome.
18:16>> [clears throat]
18:16>> Any other questions?
18:18Comments?
18:19>> Okay.
18:20>> Okay.
18:21Thank you.
18:22>> Take a vote.
18:24>> Um
18:26It is change It is change order one in
18:28the uh
18:31It's not in requisition three though, is
18:32it?
18:33>> Yeah.
18:34>> It's not.
18:34>> No, it'll be in four.
18:35>> Okay.
18:37Okay.
18:39So um
18:41taking one at a time then. So
18:42change order one
18:45He's presented the uh subcommittee met
18:47on it and looked at it and everything
18:48made the recommendations.
18:50Um there's no other questions or
18:52comments and stuff. I'd entertain a
18:53motion to approve
18:55change order one.
18:56>> So I'll move that we approve change
18:59order number one dated August 11th, 2026
19:03for a total of $132,433.75.
19:13>> Okay, so you have a motion. Motion to
19:15approve change order one. Do we have a
19:17second?
19:18>> I'll make a second on that.
19:21>> Second.
19:22>> And
19:23>> Okay.
19:25Um so motion to approve change order one
19:28dated 11/20/26
19:31for $132,433.75.
19:35Um all those in favor?
19:37>> Aye.
19:37>> Aye. Thank you. All those opposed?
19:39That's approved.
19:41>> Okay.
19:41>> [clears throat]
19:42>> So yeah, change order one will be
19:43included in pay requisition four next
19:46month.
19:46>> Okay.
19:47>> Why'd you give me this?
19:48>> So
19:50>> Well, I can probably It's online.
19:52>> Okay, so why'd you give me this?
19:53>> I don't know if anyone wanted it I had a
19:56hard copy of it.
19:56>> Oh.
19:58>> But you Joe has one online, but we don't
19:59need it.
20:00>> Okay.
20:01>> Um
20:03and then
20:05requisition three was sent out to
20:07everybody in their packets and stuff. I
20:08don't know if there's any questions,
20:09comments
20:11on what was presented and stuff
20:14for requisition three?
20:26>> All right. Can we put that up with the
20:28Do you have that accurate?
20:29>> Yeah, I have it, but I didn't
20:31>> Do you have a copy? I just want to
20:34give the total, I guess, when we get
20:36there.
20:39>> I think I have it.
20:40>> 27,000 you have?
20:41>> Okay.
20:42>> But the
20:43>> Yeah.
20:43>> permitting fees included in that?
20:47>> Only a portion. So
20:49the interest
20:50>> Yes.
20:52>> Not all.
20:53There are like um
20:56there was one or two permits that were
20:58outside of
21:00standard practice that
21:04>> Well, I saw
21:05two of them in two of them there. At
21:07least at least two.
21:08>> Right. Okay.
21:15They were waived by the town. So, we'd
21:17expect that money back.
21:20>> On those two, I'm I'm pretty sure we and
21:23I have I'll check with the chief. He was
21:24looking at it. Those two entities were
21:26the only two that were re-charged with
21:28the project.
21:29I don't know the reason behind it but
21:31I'll check.
21:32>> Okay.
21:33>> Right now, we're tracking the fee
21:35waivers.
21:36>> I mean, it's like $3,000 total or
21:38something.
21:40>> Most
21:41most projects in the Commonwealth, they
21:43tend not to bond
21:45revenue fees. Now, I've had it where
21:48they include revenue fees in my day.
22:02Typically,
22:04you know, most
22:15>> Cuz like the water district is separate,
22:17so any any permit fees there the town
22:20doesn't
22:22Yeah, so that would have to be paid but
22:23adding anything to the town, I I
22:25wouldn't want to pay.
22:37>> [laughter]
22:50>> No, I was just wondering, you know, why
22:51we were paying us to pay us.
22:59Okay.
23:14>> She has the email.
23:16>> What?
23:17>> You got it. Okay.
23:19>> Are we ready?
23:21Anyone else?
23:23All right.
23:24I'm going to make a motion that we
23:26approve requisition three
23:28uh for the total of $970,158.73.
23:38>> All right. There's a motion to approve
23:40requisition three. Uh
23:42do we have a second?
23:43>> Second.
23:44>> Do we have a second?
23:46Um
23:48So
23:49uh the motion and the second to to
23:52approve requisition three for nine
23:54hundred seventy thousand one hundred
23:57fifty-eight and seventy-three cents. Um
24:01So all those in favor?
24:03>> Aye.
24:03>> Aye.
24:04>> All those opposed?
24:05It's approved.
24:15All right. Um
24:18So I think our next agenda item is the
24:19second public comment section and still
24:22no public comment here.
24:24Um So right now tentative our next
24:28meeting would be September 15th.
24:31Um
24:32and we may
24:34make that a site visit with site visit
24:36first and then come here or do
24:38something.
24:38>> I think I'd rather meet right on site.
24:41>> All right. Good week.
24:41>> So you could make arrangements with the
24:43proper cable television
24:45>> Do a remote. Yeah. Yeah.
24:47>> You could have the meeting in the truck.
24:48>> Okay.
24:49>> And then
24:52>> Alternatively too, I don't know if West
24:54Street would be open, but I know it's a
24:56close quarters to the site to be sure.
24:59>> It's all or nothing as far away from
25:01anything.
25:02>> [laughter]
25:03>> This is pretty close, too.
25:05>> Oh, it is?
25:06>> It's down the street.
25:07>> Yeah, I got to came a different way,
25:08huh?
25:09>> Yeah.
25:09>> I don't mind that. Sorry, scratch that.
25:12Yeah, but on-site definitely. We should
25:13like if we would
25:15you want to meet on-site prior? I don't
25:17know if everyone's available like half
25:19hour or before like 5:30-ish?
25:22You wanted to like you know what I mean?
25:24Like meet as a Yeah, meet as a committee
25:26there, walk the site, and then go to the
25:28trailer have the meeting that way you
25:30know kind of what we're talking about
25:32and see if you guys
25:33reply to us.
25:35Give you an update, which I'm sure we
25:37will.
25:38>> Yep.
25:38>> Yep.
25:39>> Okay.
25:39>> Yeah.
25:41>> Sounds good.
25:43All right. So, I guess that brings us to
25:45the end of our agenda for tonight. So,
25:47take a motion to adjourn.
25:49>> So moved.
25:51>> And all those in favor?
25:53>> I
25:53I think we need a second.
25:54>> Wait a minute.
25:55>> Second.
25:56>> Second.
25:57>> It's all moved.
25:58>> All those in favor?
25:59>> Aye.
25:59>> We're there.
26:00>> Thank you.