2026-10-06 - Planning Board
Summary
Built from the YouTube auto-generated captions of the meeting video. The agenda has been read, and the posted minutes are an image-only PDF, so they were not read.
- Chair Jonathan Boucher opened the meeting at 7:00 PM with members Ted Brush, Trisha Hayes, Greg Hobson, Ken Huhn, Vice Chair Janet Jonas and Ross Whitford. The minutes of September 1 and the findings of fact for 201 Odlin Road and 8-10 Harlow Street were approved by unanimous roll call. See Fire Training Facility at 201 Odlin Road and 8-10 Harlow Street Development.
- The board found the City of Bangor's application for a roughly 6,700 sq ft Community Connector bus training center and renovation of the existing cold-storage bus barn at 511 Maine Avenue complete, then heard the project engineer: two new overhead doors at the end of the building so buses can enter straight in, a rebuilt exit onto Main Avenue, new sewer department parking, electrical service for a future hybrid and electric fleet, new street trees, and drainage with a vegetated filter. About 28 parking spaces are required and 83 are available. Staff had no comments and there was no public comment. See Community Connector Bus Barn and Training Center.
- After a separate roll call on each Land Development Code finding (erosion control, lot frontage, parking, utilities, lighting, fire protection, drainage, sewer, district standards and the approval standards, plus the state site location law), all unanimous, the board granted the land development permit and the site location modification for the 511 Maine Avenue project.
- The board then took up Waterstone Bangor LLC's minor subdivision and planned group development at 6 Bangor Mall Boulevard, splitting a 6.78 acre parcel into a 0.54 acre lot and a 6.24 acre lot in the parking area of the existing retail center. The applicant said no use is finalized and future development would return for site plan review. With no staff comment and no public comment, the board approved the subdivision and planned group development by unanimous roll call. See Bangor Mall Boulevard Subdivision.
- Other business: Planning Officer Anja Collette previewed a staff proposal to move the growth boundary to take in two parcels off Stillwater Avenue and Kittredge Road where the VA is considering a hospital; the parcels are now in a rural zone that would not allow it. Members were supportive, asked about alternate sites and sewer capacity, and engineering said sewer capacity work is under way in phases. A neighborhood workshop was set for October 29. See Growth Boundary Change for Stillwater Avenue VA Hospital Site.
- Staff also previewed the removal of the floor area ratio limit downtown, planned for a public hearing on October 20. Members generally supported it and asked about height limits, sunlight and a possible conditional-use guardrail; historic preservation review still applies downtown. See Downtown Floor Area Ratio Removal.
- Staff reported that the Land Development Code rewrite with consultants should finish its review by mid-November, with a public draft early next year and an airport overlay district still being developed. The board will not meet on election day, so November has one meeting; there will be two Planning Board vacancies next year; packet order was discussed and members were happy with it.
Agenda
- Chair introduction
- Old business: A. Meeting minutes of September 1, 2026; B. Adoption of findings and decisions for 201 Odlin Rd (Fire Training Facility at 201 Odlin Road) and 8-10 Harlow St (8-10 Harlow Street Development)
- New business, land development permits: A(i). Major site development and SLODA modification, 511 Maine Avenue, City of Bangor Community Connector, 6,070 sq ft training center and cold storage restoration (Community Connector Bus Barn and Training Center); A(ii). Minor subdivision modification and planned group development, 6 Bangor Mall Boulevard, Waterstone Bangor LLC, 0.54-acre and 6.24-acre lots from a 6.78-acre parcel (Bangor Mall Boulevard Subdivision)
- Other business: A. Proposed growth boundary change (Growth Boundary Change for Stillwater Avenue VA Hospital Site); B. Workshop on removing the floor area ratio restriction from the Downtown Development District (Downtown Floor Area Ratio Removal); C. Follow-up and thoughts on Land Use Plan updates; D. Adjournment
Sources
- Agenda: https://bangormaine.gov/AgendaCenter/ViewFile/Agenda/_10062026-942
- Minutes: https://bangormaine.gov/AgendaCenter/ViewFile/Minutes/_10062026-942 (posted as an image-only PDF, not read)
- Video: https://www.youtube.com/watch?v=oqGcFjeKTGA (City of Bangor YouTube channel, 1:02:04)
- Agenda Center: https://bangormaine.gov/AgendaCenter
Video
Transcript
*These are auto-generated captions; names and numbers may be misheard.
Transcript
00:00the button here and I should pop up.
00:06There we go.
00:14Yeah, we we can see it.
00:27Good evening and welcome to the
00:29applicant, staff, board members, and
00:30members of the public. This is the
00:31October 6, 2026 meeting of the city of
00:33Bangor's planning board. It's 7 o'clock.
00:36My name is Jonathan Boucher. I'm chair
00:38of the board. Uh board members are
00:40volunteers from the Bangor community.
00:42and other board members in attendance
00:43this evening include Ted Brush, Trisha
00:45Hayes, Greg Hobson, Ken Hune, Vice Chair
00:49Janet Jonas, and Russ Woodford. City
00:53staff members in attendance this evening
00:55include planning officer Ana Colette,
00:57assistant solicitor Grace Inennis, city
00:59engineer Jefferson Davis, and planning
01:01analyst Matthew Alier. Uh we thank them
01:04for their help in preparation for this
01:06meeting. We're going to start with the
01:08old business which includes the meeting
01:09minutes from September 1, 2026.
01:13Actually, that seems too well long ago.
01:15Can we correct that date? Is it
01:17September 1 was our last meeting?
01:20>> Um, well, I think September 15th was
01:22cancelled, so that's why we have this
01:25one.
01:26>> Okay. Yeah. So, the meeting minutes from
01:28September 1.
01:30Um, any any corrections or otherwise I'd
01:33look for a a motion? Move to approve
01:37>> and a second. Member um member Hinn with
01:40the motion and a second.
01:42>> Member Jonas and a roll call vote.
01:44Member Brush.
01:45>> Yes.
01:45>> Member Hayes.
01:46>> Yes.
01:47>> Hopson.
01:47>> Yes.
01:49>> Hun?
01:49>> Yes.
01:50>> Jonas?
01:50>> Yes.
01:50>> Member Woodford?
01:51>> Yes.
01:52>> And chair votes yes.
01:54>> Next we have the adoption of findings
01:57for 201 Oddlin Road and 8 through10
02:01Harllo Street. and we had the full board
02:03in attendance on September 1st. So,
02:07we'll move forward with a motion.
02:13>> Member Hinn Chair, I'd move that we
02:15approve the u
02:19cate the um motion is is presented and
02:22is approved by us.
02:24>> Okay. And a second.
02:26Member Brush. And a roll call vote.
02:28Member Brush.
02:29>> Yes.
02:29>> Member Hayes.
02:30>> Yes.
02:30>> Member Hobson. Yes.
02:33>> Hun.
02:33>> Yes.
02:33>> Member Jonas.
02:34>> Yes.
02:35>> Whitford.
02:36>> Yes.
02:36>> And the chair and the chair votes yes.
02:40>> Which brings us uh to my introduction
02:43for the new business. [clears throat]
02:45The planning board has two main roles.
02:47First, we review amendments to the land
02:48development code which typically include
02:50either changes to zoning districts or
02:52changes to the text within the code. But
02:54there are no amendment amendment items
02:56on the agenda tonight. Secondly, the
02:58board serves as the regulatory authority
03:00for the land development permits uh for
03:02land development permits commonly known
03:03as site plan review. Site plans are
03:05reviewed to ensure compliance with the
03:07city code as to parking, driveways,
03:09storm water management, lighting,
03:12landscaping and buffering, building
03:14location, environmental impacts, and
03:16shoreline zoning as may be applicable.
03:18We also ensure the plan meets the
03:20dimensional requirements for the project
03:22zoning district. We review larger site
03:24plans that trigger site location
03:26development with the main D as well
03:28under their requirements. Uh some uses
03:30are conditional uses that have specific
03:32conditions and requirements we use to
03:34review the project. State statute also
03:36outlines the requirements for
03:38subdivision review and the city has
03:39additional standards as to roadway and
03:41utility specifications. The board
03:43ultimately endorses a plan that will go
03:45to the registry of deeds if the plan is
03:46approved. There are two items on the
03:48agenda that are land development permits
03:51and further information on the city's
03:52codes and standards and the
03:54comprehensive plan may be found at the
03:56city's website. Our first
04:01Oh, excuse me. For um for these land
04:04development permits, we'll first
04:06consider the vote on the application's
04:08readiness for review and any concerns
04:10for conflict of interest. For all items,
04:12the applicant or their representative
04:14should then come forward to the podium
04:16and provide a brief introduction to the
04:17proposal and then they should stay at
04:19the podium while we consider any
04:20questions from the staff and or board
04:22members. Once the item has been
04:24presented, the applicant may be seated
04:26and we will allow time for public
04:27comment. For public comment, the person
04:30should come to the podium, introduce
04:32themselves, state if they're a Bangor
04:34resident and/or an abuter to the
04:35property as applicable and indicate if
04:38they are for or against the proposal.
04:40It's also helpful if you present your
04:42thoughts based upon the city codes and
04:43standards and the comprehensive plan as
04:45these are the primary documents used by
04:47the board to make our decision. All
04:49comments and discussions should remain
04:51respectful and considerate of others.
04:52Once public comments are completed,
04:54we'll close the item to public comment.
04:58The board will then deliberate on the
05:00proposal using the applicable standards
05:02for clarity when considering land
05:03development proposals. The code
05:05standards are typically read and voted
05:06on separately and then the final
05:08decision is read and voted on. If the
05:11applicant disagrees with the land
05:12development permit decision that the
05:13board has made uh then they can appeal
05:16the decision to the superior court of
05:17Maine. Once a project you're interested
05:19in has been reviewed, you may leave the
05:21meeting, but please be respectfully
05:22quiet so as not to disturb the review of
05:25other agenda items. On to new business.
05:28We have our first item which is a land
05:31development permit application for a
05:32major site development and site location
05:35uh of development SLOA for the
05:38construction of a 6,70 ft training
05:41center and restoration of existing cold
05:44storage building including a drainage
05:45and storm water including drainage and
05:47storm water improvements new parking and
05:49access drives located at 511 Maine Avenue
05:53map lot 001-001-G
05:56and the government and institutional
05:57service district GNISD.
06:00The applicant owner, City of Bangor,
06:02Community Connector,
06:04and staff have indicated the
06:05completeness of this application and its
06:07readiness for the board review. The fees
06:09are documented and paid. The applicant
06:10standing is confirmed. Do uh does the
06:13board have any concerns or conflicts of
06:15interest?
06:19>> Okay. Then if so,
06:22>> I'd look for a motion on the uh to
06:25accept the completeness. Member Jonas.
06:28>> Chair, I move the board finds that the
06:30application was deemed complete based
06:32today, October 6, 2026. That all
06:34applicable fees for the project have
06:35been paid per exhibit 3 of our packets
06:38the and that the proposed project is a
06:39major site development and major slow
06:41modification.
06:42>> Thank you. And a second. Second.
06:45>> Member Hune. The second and a roll call
06:47vote. Member Brush.
06:48>> Yes.
06:49>> Member Hayes.
06:50>> Yes. Robson,
06:51>> yes.
06:52>> Member Han,
06:52>> yes.
06:53>> Jonas,
06:53>> yes.
06:54>> Member Woodford,
06:54>> yes.
06:55>> And the chair votes yes.
06:57>> Um, so at this point, we'd like to
06:58invite the applicant to come up to the
07:00podium and give their presentation on
07:02the project.
07:07>> I think they'll add it to the uh they'll
07:09present it on the screen.
07:17Hi, I'm Shelley Lazad with Artifact
07:20Civil Engineer um working with the city
07:23of Bangor on this project. The the main
07:26goal of this project is uh to
07:30first um
07:33repair renovate the existing storage
07:36building that is now being used as a
07:38community connector storage for their
07:41the city buses. And um right now that is
07:44in pretty bad shape. So that that is a
07:47primary objective of this. In addition
07:50to that um the city is uh going to be
07:54consolidating the bus operations and
07:57providing a training center uh attached
07:59to the end of this building so that um
08:02you know everything is sort of centrally
08:04located. the um the bus drivers can be
08:08trained in in an appropriate facility
08:10and uh we'll have um you know ample
08:13parking for for those those needs. Uh
08:17right now the the site is um it it's
08:21been a many things I guess in the past
08:24um more recently since since it's been
08:26the sewer department on the front the
08:28back half has been the the parking for
08:31um the buses. Uh they they were also a
08:36recycling center at one point. And so
08:38the interior of it has um decent uh
08:42foundations and floors, but the shell is
08:45is uh is really in bad shape. So um and
08:50while while they're doing this, another
08:52major goal of this is to provide um
08:55appropriate electrical uh service so
08:57that u the future fleet of buses can be
09:01charged because the goal is to have
09:03hybrid and electric buses at some point.
09:06So, we want to make sure that they have
09:08um the appropriate services for that as
09:11well. And in addition to a couple other
09:14things that are happening on the inside
09:15of the building that aren't relevant to
09:17this land development permit um just for
09:19your information uh [clears throat] for
09:22this um situation right now, the uh the
09:24buses are now all housed in there, but
09:27they're parked in a very tight
09:29configuration and they have to come in
09:31from the side of the building. So, as
09:33part of this, we're we're providing two
09:35new overhead doors on the end of the
09:37building so that, you know, a bus can
09:39come in straight into the length of the
09:42uh the bus barn and uh park in the
09:46perpendicular spaces. So, that'll
09:48that'll make it easier for buses to get
09:50in and out in case there's ever an
09:51emergency and one bus needs to get out
09:54and another one is blocking the door,
09:56for example. Uh so, they have two two
09:58exits. So in doing so uh it creates a a
10:02very sort of like an obvious area to
10:07provide the uh required storm water
10:10treatment that we're u needing to do
10:12here because this is a redevelopment
10:14project from uh as a part of the airport
10:18slow that has been in existence for I'm
10:21not sure decades I guess. Um so that uh
10:26the design of the training center which
10:29is about 6,300
10:32square feet oh 670 square feet is what I
10:34have on here um that will uh that will
10:38sort of interconnect with these the bus
10:41um the bus entry and exit and it also
10:45provides a fairly decent uh private exit
10:50for the buses to make their complete
10:52like round about the building and not
10:55have to be con uh conflicting with all
10:58the other uh vehicles that are on the
11:01other side. As you know, there's that's
11:03a maintenance garage. And so there's a
11:05lot of vehicles that are in and out of
11:06there all the time fueling and washing
11:10the car wash. So, you know, the buses
11:12can be protected on their own side and
11:14and not have to worry about the traffic
11:16for for um for that. Um, so you know, in
11:20in like I said before, in doing so,
11:21we've created a nice big uh sort of like
11:24a radius type of a circle. It's like
11:28rectangular for for the exit. It's a
11:31existing exit now. It's going to be
11:34rebuilt and that comes out onto Main
11:36Avenue. And um then additionally,
11:40there's a parking a set of parking
11:44spaces along Main Avenue that will serve
11:47as the new parking for the sewer
11:49department and their vehicles to uh also
11:52put them in a location that avoids
11:54conflicting vehicles coming in and out
11:57on the other side. So, it'll it'll get
12:00all that, you know, traffic off to that
12:04side. um for the stormwater permit.
12:07Well, for the there aren't a lot of
12:10buffers required. There's a couple of
12:11street buffers and we did address those
12:14um with some new street uh trees along
12:17Main Avenue. U the the other side that
12:19happens to fall on Union Street has a
12:22fairly wide buffer already and none of
12:24those trees are being impacted by this.
12:27Uh the [clears throat] uh the site plan
12:30does include some new some new plantings
12:33as was requested by the uh forestry
12:36department and in in um in trying to
12:41replace what was removed because there
12:43are a few trees that are going to be
12:44taken out. They're um they're you know
12:46distributing those throughout the
12:48throughout the green space there. Um
12:50[clears throat]
12:51the number of parking spaces was
12:53determined based on like the the
12:55congregate um or the aggregate number of
12:58spaces that would be required for the
12:59uses that are in this building on this
13:01lot. And it was determined that uh you
13:05know we need a total of I think uh
13:10have a number here in my head 28 parking
13:12spaces. uh only only need 28 parking
13:16spaces, but there are 83 parking spaces
13:18that are going to be available for for
13:20everyone to park on here. The existing
13:22ones are on the back side over near uh
13:25the Union Street uh side and those will
13:29be re reconfigured at some point so that
13:32it is a more defined parking space for
13:36employees. And then the other side um
13:38with the new parking for the sewer
13:41department has a few spaces there and
13:43there's a handicap spot um as the
13:46typical requirements one per 25. So
13:49there's there's two um provided and I'm
13:52sure there are more that could be
13:54delineated but there there really isn't
13:56uh you know it's not a requirement. So
13:59there's there plenty of them where they
14:01need to be. Um
14:05the improvements in drainage are um
14:08mainly to uh provide uh proper drainage
14:11from around the bus bus barn building.
14:13The back of it right now is very flat
14:15and they have a lot of roof runoff that
14:17comes down there and then uh we're
14:19adding a couple of catch basins and de
14:22diverting all that around uh the
14:24building and then eventually taking it
14:26back in to the storm drain that cuts
14:28across from the where the new sort of
14:32where the new training center is going
14:33to be and it goes down across um main
14:37avenue eventually. And that is also the
14:40same outlet that we will be discharging
14:42the um the vegetated filter for the
14:46storm water treatment. Um I'm sure you
14:49might have questions but um I could
14:53explain more let you guys ask.
14:57>> Thank you. Um are there any staff
14:59comments?
15:01>> Um I don't think we had any comments on
15:03this. All
15:07right. Any any questions for staff or
15:09for the applicant?
15:16>> Um, all right. We'll go to
15:19Thank you. We're going to open up public
15:21comment.
15:22So, public comments opened up.
15:28Any Yeah, there's no one on Zoom. Then
15:32we'll be closing public comment
15:35and I'll put it back to the board to see
15:37if there's any other questions or
15:38discussion before we move on to review
15:41of the standards.
15:46Yeah.
15:47All right. In that case, we'll move on
15:49to the applicable provisions and
15:51findings.
15:53Um [clears throat] we'll start with um
15:56part one that the project meets the
15:57requirements of articles 2 and 12. I'd
16:01look for a motion on the first item
16:02there under part one. Member Hun.
16:05>> Yeah, chair. I move that the board finds
16:06that based on exhibit two, the applicant
16:08satisfied land development code section
16:11165-33.1's
16:13requirements surrounding erosion
16:15sediment control.
16:16>> And a second member brush. And a roll
16:19call vote. Member Brush.
16:21>> Yes.
16:21>> Hayes.
16:22>> Yes.
16:22>> Hobson.
16:25>> Yes.
16:27>> Yes.
16:28>> Member Jonas?
16:28>> Yes.
16:29>> Member Woodford?
16:29>> Yes. Chair votes yes. Um item two,
16:33member brush.
16:35>> Mr. Chair, I move the board finds that
16:37based on exhibit 2, the applicant
16:39satisfied land development code section
16:42165-68
16:44requirements for lat fronted lot
16:46frontage.
16:47>> Thank you. And a second.
16:49Member Hayes. And a roll call vote.
16:50Member Brush.
16:51>> Yes.
16:51>> Member Hayes.
16:52>> Yes.
16:52>> Member Hopson.
16:54>> Yes.
16:55>> Yes.
16:55>> Member Jonas?
16:56>> Yes.
16:56>> Member Woodford?
16:57>> Yes.
16:58>> The chair votes yes. Item three,
17:01member Hayes.
17:04>> I move the board finds that based on
17:06exhibits 2 and 16, the applicant
17:09satisfied land development code section
17:12165-72
17:14regarding the required number of parking
17:17spaces. Section 165-73's
17:20requirements regarding parking area
17:23location and screening. and section
17:26165-74's
17:28requirements regarding parking area
17:31design, construction, and maintenance.
17:34>> Thank you. And a second.
17:35>> Second.
17:36>> Member Woodford. And a roll call vote.
17:38Member Brush.
17:39>> Yes.
17:39>> Member Hayes.
17:40>> Yes.
17:40>> Member Hopson.
17:41>> Yes.
17:43>> Yes.
17:43>> Member Jonas?
17:44>> Yes.
17:44>> Member Woodford?
17:45>> Yes.
17:46>> Chair votes yes. Item number four.
17:48>> Member Brush.
17:51>> Mr. Chair, I move that the board finds
17:53that based on exhibits 27,
17:5713- 15, 20, and 21, the applicant
18:00satisfied land development code section
18:02165-79
18:05requiring adequate utility service,
18:08including water, electricity, fire
18:10protection, and provision for storm
18:13water runoff.
18:14>> Thank you. And a second,
18:15>> chair.
18:16>> Uh, member Jonas and a roll call vote.
18:18Member Brush,
18:19>> yes. Member Hayes,
18:20>> yes.
18:21>> Member Hobson,
18:22>> yes.
18:23>> Yes.
18:24>> Member Jonas,
18:24>> yes.
18:25>> Member Woodford,
18:26>> yes.
18:26>> And the chair votes yes. Item five.
18:29Member Jonas.
18:29>> Chair, I move the board finds that based
18:31on exhibits 2 and 21, the applicant
18:33satisfied land development code section
18:36165-80 requiring that whenever possible,
18:38all uses and developments shall be
18:40provided water service from the Bangor
18:42water district.
18:43>> Thank you. And a second.
18:46Member Han. Roll call vote. Member
18:48Brush,
18:49>> yes.
18:49>> Member Hayes,
18:50>> yes.
18:50>> Member Hopson,
18:51>> yes.
18:52>> H,
18:53>> yes. Member
18:54>> Jonas,
18:54>> yes. Member Whitford,
18:55>> yes. And
18:56>> chair votes, yes.
18:58>> Item six.
19:00>> Member H.
19:01>> Sure. I move that the board finds that
19:02based on exhibits 2 and 8, the applicant
19:05satisfied land development code section
19:07165-81
19:09requiring providing adequate lighting
19:11and preventing uh light pollution and
19:13trespass.
19:14>> Thank you. And a roll uh and a second.
19:17Member Hayes and a roll call vote.
19:18Member Brush,
19:19>> yes.
19:19>> Member Hayes,
19:20>> yes.
19:20>> Member Hobson,
19:22>> yes.
19:23>> Yes.
19:24>> Jonas,
19:24>> yes.
19:25>> Woodford,
19:26>> yes.
19:26>> Chair votes yes. Item seven.
19:30>> Member Brush.
19:32>> Mr. Chair, I move the board finds that
19:34based on exhibit exhibits 2 and 20, the
19:37applicant satisfied land development
19:39code section 165-82
19:43requirements regarding having adequate
19:46fire protection.
19:47>> Thank you. And a second. Member Hun. And
19:51a roll call vote.
19:53Member [clears throat] Brush.
19:54>> Yes.
19:55>> Member Hayes.
19:56>> Yes.
19:56>> Member Hopson.
19:57>> Yes.
19:58>> H.
19:59>> Yes.
19:59>> Member Jonas?
20:00>> Yes.
20:00>> Member Woodford?
20:01>> Yes. The chair votes yes. Item number
20:04eight.
20:07Member Hayes.
20:09>> I move the board finds that based on
20:11exhibit 2, the applicant satisfied the
20:13land development code section 165-83
20:17requiring adequate electrical services.
20:20>> Thank you. And a second. Uh, member Hun.
20:23And a roll call vote. Member Brush.
20:25>> Yes.
20:26>> Member Hayes.
20:27>> Yes.
20:27>> Member Hobson.
20:28>> Yes.
20:29>> H.
20:30>> Yes.
20:30>> Member Jonas. Yes.
20:31>> Member Woodford.
20:32>> Yes.
20:33>> The chair votes yes. Item number nine.
20:37>> Member Hun.
20:38>> Chair, I move that the board finds that
20:39based on exhibits 2713 to 15 and 21, the
20:43applicant satisfied the land development
20:44code section 165-84 requiring provisions
20:48for surface water and storm drainage.
20:50>> Thank you. In a second. Member Brush.
20:53And a roll call vote. Member Brush.
20:55>> Yes.
20:55>> Member Hayes.
20:56>> Yes.
20:56>> Member Hopson.
20:57>> Yes.
20:58>> H.
20:59>> Yes.
20:59>> Member Jonas.
21:00>> Yes. Member Woodford.
21:01>> Yes.
21:01>> The chair votes yes. Item number 10.
21:05>> Member Brush.
21:07>> Mr. Chair, I move the board finds that
21:08based on exhibit 9, the applicant
21:10satisfied land development code section
21:12165-85
21:14requiring information on sewer flows and
21:18section 165-86
21:21regarding compliance with sewer
21:23regulations.
21:24>> Thank you. And a second.
21:25>> Member Jonas. And a roll call vote.
21:27Member Brush.
21:28>> Yes.
21:28>> Member Hayes.
21:29>> Yes. Yes.
21:29>> Member Hopson.
21:30>> Yes.
21:31>> Hun?
21:32>> Yes.
21:32>> Jonas?
21:33>> Yes.
21:33>> Member Woodford?
21:34>> Yes.
21:35>> The chair votes yes. That completes part
21:36one and brings us to part two that the
21:38project meets the requirements of
21:40section 165-97
21:42Government and Institutional Service
21:44District GNISD and the section 165-101
21:48Shopping and Personal Service District
21:50SNPS. There's one item here. Member
21:52Jonas.
21:53>> Chair. I move the board finds that based
21:54on the findings made in part one of
21:56section 4 of this document, the project
21:58meets the requirements of section
22:00165-97B
22:02for uses within the government and
22:03institutional service district or known
22:05as GNISD and section 165-101B
22:09for uses within the shopping and
22:11personal service district known as SNPS.
22:14>> Thank you. And a second member Hune and
22:16a roll call vote. Member Brush,
22:18>> yes.
22:18>> Member Hayes,
22:19>> yes.
22:19>> Member Hobson,
22:20>> yes.
22:21>> Member Hun,
22:22>> yes. Member Jonas,
22:23>> yes.
22:24>> Member Woodford,
22:24>> yes.
22:25>> And the chair votes yes. Which completes
22:27part two and brings us to part three.
22:29The project meets the requirements of
22:31section 165-114 land development
22:33approval standards. Um I'd look for a
22:36motion on item one.
22:39Member Brush.
22:41Mr. Chair, I move the board finds that
22:42based on exhibits 2 and 16, the
22:45applicant satisfied land development
22:47code section 165-114B's
22:51requirements that the proposed parking
22:53and loading layout are arranged in a
22:56reasonable and safe configuration and
22:59section 165-14
23:01C's requirement that all proposed access
23:04drives are reasonably necessary and
23:07safe.
23:07>> Thank you. And a second, member Hun. And
23:10a roll call vote. Member Brush,
23:12>> yes.
23:12>> Member Hayes,
23:13>> yes.
23:13>> Member Hopson,
23:14>> yes.
23:15>> Member Hune,
23:16>> yes.
23:16>> Member Jonas,
23:17>> yes.
23:17>> Member Witford,
23:18>> yes.
23:19>> The chair votes yes. Item two.
23:22>> Member Hun.
23:23>> Chair, I move that the board finds that
23:25based on exhibit 2, the applicant
23:27satisfied land development code section
23:29165-114
23:31C's requirement that all proposed access
23:33drives from the site to any public
23:35rightway are reasonably necessary and
23:37safe.
23:38>> Thank you. and a second.
23:41Member Brush. And a roll call vote.
23:43Member Brush,
23:44>> yes.
23:44>> Member Hayes,
23:45>> yes.
23:45>> Member Hobson,
23:46>> yes.
23:47>> Member Hun,
23:48>> yes.
23:48>> Member Jonas,
23:49>> yes.
23:50>> Member Whitford,
23:50>> yes.
23:51>> Chair votes yes. Item three.
23:55>> Member Hume. Chair, I move that the
23:57board finds that based on exhibits 27
23:59and 14 to 15, the applicant satisfied
24:02land development code section 165-114D's
24:06requirements regarding minimizing
24:08adverse effects from storm water runoff
24:11and ensuring adequate storm water uh
24:13collection capacity.
24:14>> Thank you. And a second
24:17uh member Hayes and a roll call vote.
24:19Member Brush,
24:20>> yes.
24:20>> Member Hayes,
24:21>> yes.
24:22>> Member Hobson,
24:23>> yes.
24:24>> Member Hune,
24:24>> yes. Member Jonas,
24:25>> yes.
24:26>> Woodford,
24:26>> yes.
24:27>> And chair votes yes. Item number four.
24:30>> Member H.
24:32>> I move the board finds that based on
24:34exhibits 2 and 8, the applicant
24:36satisfied land development code section
24:39165-114E's
24:42requirements that all outdoor lighting
24:44shall be designed, installed, and
24:46maintained to avoid unreasonable adverse
24:50effects from light and pollution.
24:52>> Thank you. And a second. Member Jonas.
24:55And a roll call vote. Member Brush,
24:56>> yes.
24:57>> Member Hayes,
24:58>> yes.
24:58>> Member Hobson,
24:59>> yes.
25:00>> Member Hun,
25:01>> yes.
25:01>> Member Jonas,
25:02>> yes.
25:02>> Member Woodford,
25:03>> yes.
25:04>> The chair votes yes.
25:06>> Item five,
25:08>> Jonas.
25:08>> Chair, I move the board finds that based
25:10on exhibits 2 and 22, the applicant
25:12satisfied land development code section
25:14165-114F's
25:16requirements for landscaping.
25:19>> Thank you. And a second, member Hun. And
25:21a roll call vote. Member Brush. Yes.
25:24>> Member Hayes.
25:24>> Yes.
25:25>> Member Hobson.
25:26>> Yes.
25:27>> Member Hume.
25:28>> Yes.
25:29>> Member Jonas.
25:30>> Yes.
25:30>> Member Woodford.
25:31>> Yes.
25:31>> And the chair votes yes. Item six.
25:34>> Member Brush.
25:36>> Mr. Mr. Chair, I move the board finds
25:38that based on exhibit 2, the applicant
25:40satisfied land development code section
25:43165-114G's
25:45requirement that the location of the
25:48buildings meets all
25:50required setbacks and are suitable to
25:54are situated to avoid unreasonable
25:57adverse effects on adjacent properties
26:00or public rights of way.
26:02>> Thank you. And a second member Hayes and
26:04a roll call vote. Member Brush. Yes.
26:06>> Member Hayes.
26:07>> Yes.
26:08>> Member Hobson.
26:09>> Yes.
26:10>> Member Hinn.
26:10>> Yes.
26:11>> Member Jonas.
26:12>> Yes.
26:12>> Member Woodford.
26:13>> Yes.
26:13>> The chair votes yes. Item seven.
26:17>> Member H. Chair. I move that the board
26:19finds that based on the findings uh
26:21above in this part three and also in
26:23part one of section four of this
26:26document. The applicant is in compliance
26:27with 38 MRSA uh section 484
26:32um
26:34and applicable departmental
26:36environmental protection regulations
26:38which includes chapters 371, 372, 373,
26:43375, 376, 377 and 500.
26:47>> Thank you. And a second. Member Brush.
26:49In a roll call vote. Member Brush.
26:51>> Yes.
26:51>> Member Hayes.
26:52>> Yes.
26:52>> Hobson.
26:53>> Yes.
26:54>> Member Hune.
26:55>> Yes.
26:55>> Member Jonas. Yes.
26:56>> Member Woodford.
26:57>> Yes.
26:57>> The chair votes. Yes.
26:59>> Member Hompson, would you like to read
27:00us the decision?
27:02>> I'm sorry I don't have it on my screen.
27:04I couldn't find it.
27:05>> Oh, I understand. I was just trying to
27:06involve you.
27:08>> I [laughter]
27:09uh would would someone like to provide a
27:11motion. Member Brush.
27:13>> Mr. Chair, I move the board finds that
27:16the project meets the requirements for
27:19land development for a land development
27:21permit for a major site development and
27:25major SLOA modification and therefore
27:29the board grants the land development
27:31permit and SLOA modification for the
27:34proposed project.
27:35>> Thank you. And a second. Uh member
27:38Woodford and a roll call vote. Member
27:39Brush.
27:40>> Yes.
27:40>> Member Hayes.
27:41>> Yes.
27:41>> Member Hopson.
27:43>> Yes. Member Han.
27:44>> Yes. Member
27:45>> Jonas.
27:46>> Yes. Member
27:47>> Woodford.
27:47>> Yes.
27:48>> And the chair votes? Yes.
27:53>> So, um, with that, the applicant can
27:55reach out to, uh, code enforcement
27:57office for more guidance. Thank you.
28:03Which brings us to our next land
28:05development um item, [clears throat] the
28:07land development permit application for
28:09a minor subdivision and planned group
28:11development for the creation of a 0.5
28:14uh.54
28:18acre uh and 6.24 acre lot from an
28:24existing 6.78 acre parcel located at 6
28:29Bangor Mall Boulevard. Map lot 061-016-A
28:34and the shopping and personal service
28:36district SNPS the applicant owner
28:38waterstone Bangor LLC. Uh the staff have
28:41indicated the completeness of this
28:43application and it readiness for board
28:44review. The fees are documented and
28:46paid. The applicant standing is
28:48confirmed. Uh does the board have any
28:50concerns or conflicts of conflicts of
28:52interest?
28:55And I'd look for a motion on accepting
28:58this uh the this application's
29:00completeness. Member Hun.
29:01>> Yes, Chair. I move that the application
29:03was deemed complete on October 6, 2026.
29:07The applicant paid all applicable fees
29:10um specified in exhibit 3 and the
29:13proposed project is a minor subdivision
29:15modification and plan group development.
29:18>> Thank you. And a second. Member Brush.
29:20And a roll call vote. Brush.
29:22>> Yes.
29:23>> Member Hayes. Yes.
29:24>> Hopson.
29:25>> Yes.
29:26>> Member Hume.
29:26>> Yes.
29:27>> Jonas.
29:27>> Yes.
29:28>> Woodford.
29:28>> Yes.
29:29>> Chair votes. Yes.
29:30>> Let's see.
29:32>> At this point, we'd invite the applicant
29:34to come up to the podium to provide
29:37their presentation.
29:47>> The minor subdivision amendment
29:51development. create the.54
29:55acre lot in the northwest corner of the
30:00existing property along Bangor Mall
30:03Boulevard. It'll be creating an out
30:06parcel in the uh parking lot area for in
30:10the parking lot of Bob's Discount
30:13Furniture in the Burlington Coat
30:15Factory. Um
30:18at this point, alls we're uh looking for
30:20approval for is to create that new law
30:23out of the existing lot that's there.
30:26Um, future development would come back
30:28for a site plan approval. Uh, any any
30:31other required uh permit applications
30:33for any development within this new lot.
30:36And it'll be a uh plan group
30:38development. So, um be a lot of shared
30:42uh site features u between the existing
30:44development and anything that's proposed
30:46there as far as parking access
30:49um
30:50eliminating any sort of buffers and
30:52setbacks between the two uh developments
30:54on there.
30:58Happy to answer any questions that that
31:00the board has at this time.
31:04>> Thank you. Um,
31:07any comments from the staff?
31:09>> No comments.
31:11>> Any questions for the applicant from the
31:14board? Remember,
31:15>> you know, you don't have a purpose right
31:17now for you just
31:21for that particular parcel.
31:23They're uh in talks for a proposed
31:26development on on that lot, but um
31:30nothing's finalized at this point and we
31:32haven't finalized any sort of uh plans
31:35for a development there yet.
31:38>> Okay.
31:40>> Thank you. And member Jones,
31:41>> I just to follow up on that. So I read
31:44throughout the packet, you know, there's
31:45no defined use yet, but how did So how
31:48did you decide what size the lot should
31:49be?
31:53We've done a preliminary plan for
31:54something that could go there.
31:56>> Fair.
31:58Okay.
31:58>> And it uh
32:00>> I don't think he wants to tell you.
32:02>> And I I respect that. I was just
32:03curious. A lot of businesses
32:05>> I don't want I don't want to say
32:06anything.
32:06>> Yeah. A lot of businesses don't want to
32:07commit until we've done our part. I get
32:09that. And I don't really particularly
32:11>> care what goes
32:13>> They were working towards a lease
32:15agreement with a potential
32:17>> uh development on that. Okay.
32:18>> parcel, but nothing's been finalized
32:20yet.
32:21>> Right. Thanks. Yeah, I think it's it it
32:23would be suitable for
32:25more than just one specific use on that
32:28law and it's sized appropriately for
32:31would say a variety of uses.
32:34>> Thank you. Any other questions?
32:37We'll open it up to public comment.
32:42And seeing no one to approach, we will
32:47close public comment.
32:52Um, so I'd like to return to the board
32:56to see if there's any discussion
32:58or additional questions. I know we just
33:02had a chance, but
33:08seeing none,
33:10um, [clears throat]
33:13then we should move on to the Let me get
33:16to my
33:20Then we should move on to the standards
33:21and the findings applicable provisions
33:24which uh starts us off with part one
33:26that the project meets the requirements
33:28of section 165-126
33:30for a minor subdivision. I'd look for a
33:32motion on part one. Member hint
33:35>> chair. The board finds that based on
33:37exhibits 278 and 9, the project meets
33:40the requirements of land development
33:41code special 165-126F1
33:46regarding compliance with state of Maine
33:48guidelines for subdivision approval
33:50contained in 30-ra
33:54uh section 4404.
33:56>> Thank you. And a second
33:58member brush. And a roll call vote.
33:59Member Brush,
34:00>> yes.
34:01>> Member Hayes,
34:02>> yes. Member Hobson,
34:03>> yes.
34:04>> Member Hun,
34:05>> yes.
34:05>> Member Jonas,
34:06>> yes.
34:06>> Member Whitford,
34:07>> yes.
34:07>> Chair votes yes. Item two,
34:12member Hun.
34:13>> Uh, chair, I move that the board finds
34:15that based on exhibits two and nine, the
34:17project meets the requirement of land
34:19development code section 165-126F2
34:23regarding conforming uh to the existing
34:25lot
34:27um dimension and area regulations of the
34:30zoning district. Section 165-126F3's
34:35requirements of abudding an existing
34:37improved public road and section
34:40165-126F4's
34:43requirement on the angle of uh side lot
34:46lines uh to street lines.
34:48>> Thank you. And a second
34:51member brush. Thank you. On a roll call
34:54vote. Member Brush.
34:55>> Yes.
34:56[clears throat]
34:57>> Member Hayes.
34:58>> Yes.
34:58>> Member Hobson.
34:59>> Yes.
35:00>> Member Hune. Yes.
35:01>> Jonas.
35:02>> Yes.
35:02>> Woodford.
35:03>> Yes.
35:03>> And the chair votes yes. Item three.
35:07>> Jonas.
35:07>> Chair. I move the board finds that based
35:09on exhibit 2, the project meets the
35:10requirements of land development code
35:12section 165-126F
35:15part 6 regarding the plaque containing
35:17all information required in section
35:19165-126D
35:21parts 1 through 8.
35:24>> Thank you. And a second. Member Hune.
35:27And a roll call vote. Member Brush.
35:28>> Yes.
35:29>> Member Hayes.
35:29>> Yes. Member Hobson,
35:31>> yes.
35:32>> Member Hume,
35:32>> yes.
35:33>> Member Jonas,
35:33>> yes.
35:34>> Member Woodford,
35:34>> yes.
35:35>> Chair votes yes. Which completes part
35:37one and brings us to part two that the
35:38project meets the requirements of
35:39section 165-69
35:42for a planned group development. That's
35:44one item here. I look for a motion.
35:46Member Brush.
35:47>> Mr. Chair, I move the board finds that
35:50based on exhibit 2, the applicant
35:52satisfied section 165-5069
35:57of the land development code regarding
36:00the requirements for planned group
36:02development.
36:03>> Thank you. And a second member Hayes on
36:05a roll call vote. Member Brush,
36:07>> yes.
36:07>> Member Hayes,
36:08>> yes.
36:08>> Member Hopson,
36:10>> yes.
36:10>> Hun, yes.
36:11>> Member Jonas,
36:12>> yes.
36:12>> Member Woodford,
36:13>> yes.
36:13>> The chair votes yes. Which brings us
36:15which completes part two and brings us
36:17to our decision. I look for a motion on
36:19the decision. Member Hume.
36:21>> Chair, I move that the board finds that
36:23the project meets the requirements for a
36:25a minor subdivision modification and
36:27plan group development and therefore the
36:29board grants the land development permit
36:31for the proposed project.
36:33>> Thank you. And a second. Member Brush.
36:35And a roll call vote. Member Brush.
36:37>> Yes.
36:37>> Member Hayes.
36:38>> Yes.
36:39>> Hobson.
36:40>> Yes.
36:40>> Member Hinn.
36:41>> Yes.
36:42>> Jonas.
36:42>> Yes.
36:43>> Woodford.
36:43>> Yes. The chair votes yes. Thank you. Uh
36:47that brings us to the end of that item.
36:51You can follow up with the code
36:52forcement office if you have any
36:54questions or need more guidance.
36:57And uh which brings us to other business
37:01and uh planning officer Colette. Uh we
37:04have the proposed growth boundary
37:06change. Is it the first item that you'd
37:08like to start with?
37:09>> Yes. Um although I do just want to
37:11mention a few things before I start on
37:13that because I'm sure I'm going to
37:14forget otherwise. Um the first thing is
37:18um you all are pretty good about this
37:19normally. I just wanted to give you a
37:21reminder that when you are speaking to
37:24try to like lean forward to speak into
37:25the microphone because if you are leaned
37:27back then people on Zoom can't hear as
37:29as well. Um that was mainly a complaint
37:32we got about HPC but I just thought I
37:34would let you all know. Um, also if you
37:38could, I think we said something when we
37:40sent you the packet, but if you know of
37:41anyone who might be interested in being
37:43on the planning board, please spread the
37:44word because we do have two vacancies
37:46coming up next year. Um, and then I did
37:49just want to ask you all if you're good
37:51generally with the way we've ordered
37:53things in your packets or if there's a
37:55way you'd like us to change that. Any
37:58thoughts on that?
38:02>> Does anyone have any comments on on
38:05that? Make sure you lean forward though
38:06if you have anything to say.
38:08>> Um, just out of curiosity, is it two
38:11positions plus the associate or to
38:13including?
38:14>> I think it's to including the associate.
38:22>> And then as far as packets, any
38:24questions there?
38:25>> I appreciate the packets.
38:27>> Okay, great. Okay.
38:28>> Yeah. I I like having it front loed with
38:31the uh the index
38:33>> and with the findings because then you
38:36can kind of know what to be looking for
38:40if you read through the findings and
38:41then have concerns about any of them. I
38:43think it helps guide the rest of the
38:45reading.
38:45>> Okay.
38:46>> Especially on trickier ones.
38:48>> Yeah. Okay. And we try to um order
38:52things after that like um in order of
38:55when they come in. So, if we have staff
38:57comments, um, then we'll put like the
39:00response to comments to that. And, um,
39:03just wanted to make sure that you don't
39:05see the need to put like revised
39:07materials after those comments or if you
39:09like having all the materials up front
39:11and then the communication after that.
39:13>> I might ask, and I I'd put it out to you
39:15guys if you agree. I Well, the part I
39:18enjoy the best is seeing the email
39:20correspondence and seeing the engineers
39:22notes and things like that. that helps
39:24me understand uh what to be looking for
39:28and then to be thinking if there's any
39:30gaps as I'm reading forward to come to
39:32that after the fact after reading
39:34through and looking through all these
39:35different maps. Um it almost means after
39:38you look at that you have to go back and
39:41it's only really when there's tricky
39:42ones uh that that might happen. Does
39:45anyone ever think it would make sense to
39:46have the correspondence and the engineer
39:48notes? I think the engineer notes have
39:50to come at the end after the different
39:52details, but
39:54yeah, I I don't really see any problem.
39:57I think we're getting there one way or
39:58the other. It would be a tiny tweak and
40:01a tiny benefit at
40:03>> all.
40:03>> All right. Just wanted to make sure. So,
40:06um I did forget to print my memos for
40:09these two items, so I'm going to be
40:10reading off my phone.
40:12>> I think I have a copy of it if you want
40:13it.
40:14>> Oh, okay. Um sure.
40:16>> Yeah, you just have to give me a second.
40:23Ruffle ruffle.
40:27>> Which ones do you want to start with?
40:28>> At the very end, the growth boundary.
40:31>> You want you want the whole thing or
40:33>> that and the
40:37Yeah, I guess so.
40:38>> Thank you.
40:40>> I'm working on it.
40:40>> I think it's actually on the back here,
40:42so I'm all set. Okay.
40:43>> Yeah. Thank you. Um so yes for the
40:46growth boundary change um this is a
40:49staff proposal to potentially change the
40:53growth boundary um that was in the 2022
40:56comprehensive plan on that um particular
40:59parcel that you see on that map that
41:01it's teal um teal is the RRNA zone um
41:06and we outlined these two parcels in
41:09cyan if you're looking at the map um so
41:13these are off Stillwater Avenue um and
41:16Kitridge Road. So, the VA is looking at
41:19potentially putting a hospital on these
41:21two parcels. Um but obviously the one
41:24that is in RNA would not allow a
41:26hospital use. Um so they would need a
41:29zone change, but typically we wouldn't
41:31recommend a zone change to something a
41:34lot more intense zone outside of the
41:36growth boundary. Um so the cleaner
41:40option is to change the growth boundary.
41:43Um particularly in this case where you
41:46could pull in water and sewer from still
41:50water if a use is going to traverse both
41:53of those lots and then this is also in a
41:56pretty developed area already. It's not
41:58like it's you know kind of way out of
42:00town. Um, so we thought it made sense to
42:05look at this for a potential growth
42:06boundary change. Um, the growth boundary
42:09isn't necessarily set in stone. Like you
42:13can change it along the way if it makes
42:15sense. Sometimes conditions can change.
42:17Um, but you know, we do have to go
42:20through a quite a process for it. You
42:22know, we have to um, the formal process
42:25is to bring it to you all. We have to
42:27give the public 30 days notice
42:28beforehand and then um goes to council
42:31for the final adoption, but we also have
42:33to send it to the state for them to
42:35review and approve because technically
42:37it's a change to the comprehensive plan.
42:39Um we would also be uh proposing a
42:43public workshop ahead of time ahead of
42:45that formal meeting where we talk to all
42:47the abutters um and you know talk about
42:50why we're proposing this and all the ins
42:52and outs of it and get their feedback.
42:54um council and it's a good idea um to do
42:58this ahead of time, but council really
42:59wanted to get a feeling for like how
43:01people in the area would feel about this
43:03just because on Kitridge Road especially
43:05like that's really like a boundary, you
43:08know, between very developed to very
43:10rural, you know, and people around that
43:12live up Kitridge might have very strong
43:14feelings about it. Um so we are planning
43:17a public workshop on this at the end of
43:20the month on October 29th. Um, and we'll
43:23be letting all the abuters know and um,
43:25so we we will get that feedback then.
43:28But we did want to bring it to you all
43:29ahead of time too to get your thoughts
43:32um, before we set the wheels in motion
43:35for the formal change. So,
43:40>> any questions?
43:42No, I I'm I was excited to see that uh
43:46uh because um being a healthc care
43:48provider myself um and knowing that you
43:51know I don't sure most of the public
43:52aware is aware that the only VA hospital
43:55we have now currently was commissioned
43:57by Abraham Lincoln
43:58>> really it was the first VA hospital in
44:01the country and so to have one up here
44:04would be um would be a really good thing
44:07for veterans.
44:10>> Any other questions?
44:12Jonas. Oh, member brush.
44:14>> What about the availability of alternate
44:16sites for that?
44:18>> Yeah, that's a good question. Um, I
44:20don't know all of the sites that the VA
44:23was looking into. I do know they were
44:25potentially looking into one near the
44:27airport um where the city owns some
44:30land. It's called the main business
44:31enterprise park, but I think they did
44:33have concerns about being that close to
44:35the airport and noise and things like
44:37that. So, they're looking at this area
44:39instead.
44:42I get I get the message that it's the
44:46alternate sites are limited. They're not
44:48not abundance of them.
44:50>> Yeah, I believe so.
44:51>> Thank you.
44:53>> And just to follow up, I did a quick
44:54survey of Bangor wondering where else it
44:57might go because I know we often when we
44:59get public feedback, we say it's a great
45:01idea, we support it, but we just don't
45:03want it in our backyard. So I did and I
45:05didn't find any place that looked like
45:07it was available in anything that wasn't
45:09also R RNA. So um so I so in that regard
45:13I really do support this. I do have a
45:15question though about the sewer capacity
45:18out there because I remember last year
45:23>> we
45:25approved a preliminary site plan for a
45:29very large housing
45:31>> um development that was going further
45:32out Still Water Road just a little bit
45:34further and then I believe I've read in
45:36the paper
45:37>> um recently that they have not been able
45:39to build because of the lack of sewer
45:41capacity. So that's a good question and
45:43and Jeff might be able to speak on that
45:44more. That's
45:45>> for you, Jeff. I can tell you that the
45:46VA is actively working with sewer to
45:48resolve some of those issues.
45:50>> Yeah. So um engineering has been working
45:54for the past year on getting capacity
45:56out there. So we're going to get we have
45:58a multi-phase project. Uh phase one is
46:01happening now. Uh phase two is going to
46:03happen in a few weeks. So, we're going
46:05to have capacity out that within, you
46:08know, definitely by the end of this
46:09year, we'll have capacity for the the
46:12housing development that you mentioned
46:13earlier, uh, plus some more. And then
46:16we're going to be working on phase three
46:17and four of that next year and the year
46:19after. So, um, that shouldn't be an
46:22issue here going forward.
46:23>> Great.
46:24>> Yeah.
46:26What is the plan? What do you have any
46:28idea what the water department's
46:30planning on doing with water line? Isn't
46:32that another uh thing that holds back
46:36the growth?
46:37>> They haven't. Well, I mean, the growth
46:39boundary does follow water service
46:42areas, but the water district hasn't
46:43expressed any water capacity concerns
46:46out there, if that's what you're asking.
46:51Yeah.
46:57So,
46:59um, I was going to raise this to your
47:01question, too. So, I'm glad that we were
47:02thinking on the same, uh, wavelength.
47:07Um, your question for us tonight,
47:09though, is to just elicit some
47:12conversation with us or are you looking
47:14to see if there's any objections from
47:15the planning board or possible?
47:18>> Yeah, I mean, to see if there were any
47:20objections. if you felt strongly about
47:23that this shouldn't change. Um, and any
47:26other feedback you might have?
47:43>> Does anyone have any additional thoughts
47:44or conversation?
47:48>> Okay.
47:50Just want to make sure Greg Greg, you're
47:51um you're all set, too.
47:55>> Yeah, I'm fine with it.
47:57>> Okay.
47:59All right. So, yeah, like I said, um we
48:02plan to have that workshop on October
48:0329th, so we'll see what happens.
48:08>> Brings us to our next item about the
48:11workshop uh on removing the floor area
48:14ratio.
48:15>> Yes. Um, so this change we're proposing
48:18is also because of a potential
48:20development downtown. Um, and this and
48:23actually I found out about another one
48:24today that this limitation is holding
48:26back. Um, so changing the floor area or
48:30removing floor area ratio from our
48:32downtown development district. Um,
48:35it is somewhat of an outdated
48:37dimensional control. It's kind of
48:38confusing and hard for people to
48:40understand. Um, a lot of modern codes
48:42don't include them because they don't
48:44really get the outcome that they're
48:47intended to get as far as controlling
48:48like building scale and form and things
48:51like that. Um, when we're thinking about
48:54how do we control, you know, the form of
48:56buildings downtown really design
48:58standards help a lot and maximum height
49:01if that's something we want. Um, you
49:04know, and if something is above a
49:05certain height, requiring it to be set
49:07back from the road a little bit. Um, and
49:10all of those are things that we're
49:11looking at with the new land development
49:12code. Um, and the other like the
49:16consultants are proposing to get rid of
49:18the standard for all zones in the new
49:21land development code. Um, and instead
49:23focus on those like setbacks and height
49:25and and things and design standards. Um
49:29I will say though for downtown they are
49:31proposing if it's within a certain
49:33distance of residential the height would
49:35be capped at around 60 feet and then um
49:38it would have a greater setback from
49:40residential if you're in the downtown
49:41district. Um but at this time we just
49:44wanted to do this one small change um
49:47and then we'll worry about all the other
49:49changes when we actually do the land
49:50development code update. Um, I will say
49:52when we brought this to the bed
49:54committee last night, um, they did
49:56express some concerns that we don't have
49:58a height limit at all downtown and you
49:59know whether we want to see skyscrapers
50:02downtown potentially. I will say we
50:03don't have demand for skyscrapers right
50:05now and the case is that people are
50:08looking at adding stories. I think it's
50:10just a few stories um to add residential
50:12units. So, um I also don't think people
50:17could really get a return on investment
50:19from building a skyscraper in Bangor
50:21right now, but um so they were more
50:24comfortable with like waiting till we
50:25get to the land development code update
50:27to talk about potential height limits
50:29downtown.
50:30Um so we may be proposing an overall
50:33height limit downtown or like if you go
50:34above a certain height, say 100 feet,
50:37then it's conditional use. um we do that
50:39in waterfront development district but
50:42that's something we'll also discuss more
50:43with our consultants and um and so I but
50:47I just want to put that out there as a
50:48consideration um
50:51and also just for reference I didn't
50:54explain what floor area ratio was so
50:56I'll just go back to that um but
50:58basically it's the total gross floor
51:01area of a building all stories in
51:03included divided by the area of a lot so
51:06if you have a 40,000t building overall
51:09on a 10,000 foot lot's 4.0 floor area
51:124.0. The building right across the
51:14street, Redmond Oneshell, is um 4 and a
51:17half. And then the one where um that new
51:20credit union and people credit union, I
51:22think on State Street next to the um
51:26the stream, that's 5.3.
51:29So um those are already above current
51:33area ratio. Um and we did fel feel like
51:36this aligns with the comprehensive plan
51:39um to really encourage more housing and
51:42infill in our core urban area. So
51:48is there any feedback on that
51:53brush? Yeah, I I just support the effort
51:56to find alternative
52:00measures for
52:02protecting sunlight and building style
52:06or bulk of the building. I think those
52:08are important considerations.
52:11>> I understand it's difficult to get a
52:13measure, but I encourage the search for
52:16that. Yeah, that's definitely something
52:18we've mentioned um mainly in our
52:21residential areas, you know, when it
52:23comes to building height and like making
52:25sure people aren't, you know, shaded
52:27out. And I think we can control for that
52:30with building envelope standards. So, um
52:33you know, if you're within a certain
52:35distance of the property line, your
52:37height is lower and then you would
52:39gradually increase as you go in. It's
52:41like what we do now, but the um
52:43standards might be tweaked a little bit
52:45downtown. I think it's harder because it
52:48is meant to be such an intense the
52:51densest commercial zone. Um but it's
52:54definitely something that we can ask the
52:56consultants about like you know are
52:58there design standards we could use that
53:00would protect sunlight more in downtown.
53:03So
53:05>> member
53:06>> I'll just add a comment in that regard.
53:10I I did live downtown for a year. Um,
53:12and there are parts of downtown that get
53:14very very little sun, especially
53:17depending on what side of the building
53:18that you're on, but get very little sun
53:20in the winter because the sun's so low
53:22in the sky and it comes up and the um
53:25county building is the county offices
53:27block it until it gets up to a certain
53:29point and then Haley Ward would block it
53:30when it gets just over to the other
53:32side. So,
53:33>> I'm not sure that trying to protect that
53:37really particularly feasible in all
53:38cases with something overarching like
53:42this. Um, so I'm in favor of making the
53:44changes just to promote again more more
53:46infill, more housing,
53:52>> require giant mirrors on the side of
53:53buildings, let the light back down.
53:56>> Not great for birds. I [laughter]
54:00>> the um you talked about um conditional
54:04use for height and I wondered if talking
54:08about if there's a way to put
54:10conditional use into
54:12into this so that we'd still have an
54:15opportunity to discuss like have some
54:18grounds to discuss it. If it was a
54:21fringe case, saying no requirements
54:25is probably fine, but maybe still
54:28putting some guardrail against
54:31um a condition like a scenario that
54:35would really
54:37not wouldn't go against this. I think we
54:41um wouldn't necessarily on its face be
54:44against the the requirement in the code
54:47but would potentially be something that
54:50we wouldn't want to approve but I guess
54:52we'd have other avenues to review that
54:56in site plan review.
54:57>> Are you saying for this change currently
55:00to add some provision in for conditional
55:02use?
55:03>> So would you remind me what the standard
55:05is right now? What the percentage is? Is
55:07it 04?
55:08>> It's 4.0 Z is the area ratio.
55:13>> Um,
55:16so I wouldn't say anything that's below
55:184.0. I would say anything that's below
55:20and then some strange number that's very
55:23low, if that makes sense, or very high.
55:27>> So you're saying keep the floor area
55:29ratio, but make it so that if you go
55:32above that, it's a conditional use.
55:36>> Yeah. I don't know this what if that's
55:38worth considering. If you feel like that
55:40still gives us some
55:42uh parameters or like a avenue to
55:47>> um do you think that it might be better
55:51to do like do a preliminary like a
55:55height limit and then say like I
55:57mentioned if you're over 100 feet or are
56:01you more concerned with other aspects of
56:02what the four area ratio controls?
56:04>> I'd have to like understand like the
56:06scenario a little bit better. It's hard
56:07to vis en envision when it would become
56:10a problem.
56:12Um
56:15it might be nice to see a couple
56:17examples of the ones that are not in
56:20compliance today that we're looking to
56:23you you mentioned the one across the
56:24street.
56:25>> Yep. And the um Six State Street where
56:29um Goldman's offices are. Do you know
56:31where that is? So it's like right across
56:33from Baymore Savings Bank down on stage.
56:36Okay. Right next to the bridge.
56:37>> Yeah.
56:38>> Yeah.
56:41>> Just putting it out there. If we were
56:43thinking about conditional use, I know
56:44we don't want to perpetuate conditional
56:46uses uh
56:49um because it it creates uncertainty for
56:52developers, I would assume.
56:55But um
56:57just adding it to the conversation.
57:00Any
57:04other conversation on this item?
57:08>> Is there consensus? Like how do we feel
57:10about what um Jonathan has said? Do does
57:14anybody else feel that way?
57:21>> Crickets.
57:23[laughter]
57:24[gasps]
57:27Uh, I I think I would mostly be um kind
57:31of seconding what the vice chair said. I
57:33mean, up is the way to go in a lot of
57:35these building scenarios downtown. Um,
57:41people are really good at kind of coming
57:43in with these knee-jerk um reactions of,
57:47you know, throwing a word around like
57:49skyscraper. I think skyscraper I think
57:5140 floors or more,
57:53>> you know. I think the Empire State
57:54Building or the Sears Tower or I was in
57:58Kansas City before I moved here and um
58:00there was one skyscraper in downtown
58:02Kansas City and that was pretty much it.
58:04You know, I don't think anyone in Maine,
58:08let alone Bangor, is thinking more than
58:1010 stories, you know, at most. And even
58:12that I would be surprised to see. Um but
58:16I think that is the way to go with
58:18housing, especially in a downtown area.
58:29Anybody else want to chime in?
58:36All right. Um,
58:39I I I'm get getting the feeling that
58:43maybe overall we're good with making
58:46this change right now and then when we
58:48do the whole land development code
58:50update, we'll have more guard rails
58:53around building form and things like
58:55that. Is everyone good with that?
58:58And I will note, Jonathan, um if it
59:01makes you feel any better, uh we do have
59:04historic preservation protections for
59:06much of downtown. So,
59:08>> well, that's right.
59:09>> They do have purview over that and
59:11that'll that will control a lot of the
59:13building form for much of downtown. So,
59:18um
59:19so given that, I will um plan to bring
59:23this to your October 20th meeting for
59:25the formal public hearing.
59:28Thank you.
59:29>> Our next item was just general thoughts
59:31on the land development code update and
59:33lane use planning.
59:35>> Um yeah, so um I kind of mentioned like
59:39a few parts of the new code already. Um
59:43we are still in the midst of working
59:45with our consultants on review. Um it's
59:48been really tough. October is a crazy
59:50month. It's been really tough working
59:51with everyone scheduled to get those
59:53meetings, but we have a lot scheduled
59:54for October to review the code. Um the
59:57consultants are optimistic that like
1:00:00we'll finish up by mid November, maybe
1:00:03early November and having a public draft
1:00:06out by early next year. Um so we'll see.
1:00:10There's still a lot of mapping work that
1:00:12also needs to be done. Um I haven't had
1:00:15a chance quite yet to finish the
1:00:17reviewing the whole new zoning map. Um
1:00:20and we also have to look at um the
1:00:23there's in the airport area. Um the
1:00:27airport has consultants that are working
1:00:28on a potential airport overlay district
1:00:30that would restrict uses around the
1:00:32airport. Um so that's another moving
1:00:35piece. And then um we have to look at
1:00:40you know wetlands and um resource
1:00:43protection areas and things like that.
1:00:44So there's a lot of different um irons
1:00:46in the fire with the code. So
1:00:53>> any any dates coming up uh look forward
1:00:56to?
1:00:58>> Can't give you a specific date yet. So
1:01:02sorry.
1:01:02>> Any other questions or comments from the
1:01:04board.
1:01:06We do have a document to sign.
1:01:10>> There should be findings and then the
1:01:11subdivision plans you reviewed tonight.
1:01:13So
1:01:13>> very good.
1:01:15And member Jonas,
1:01:17>> I just want to confirm. I think
1:01:18everybody was copied on the but we've
1:01:20decided we're not going to have a
1:01:21meeting on election day.
1:01:23>> Right. Okay. So,
1:01:24>> right.
1:01:24>> Yeah.
1:01:25>> But we will have another meeting in
1:01:26October.
1:01:27>> Provided there is enough material to
1:01:30review.
1:01:30>> Yes, there will definitely be a meeting
1:01:32um October 20th. So,
1:01:35>> so 10 20th will be our next meeting.
1:01:38>> I'm not sure that I got that email
1:01:40>> about election day.
1:01:41>> Yeah.
1:01:42>> Oh, I'm sorry. I think I was just
1:01:44emailing Janet. So, yes, you will not
1:01:45have a meeting on election day. You just
1:01:47have one meeting in November.
1:01:49>> Perfect. It's on Thanksgiving.
1:01:52>> November 15th, I think, is that meeting.
1:01:55So,
1:01:57>> well, thank you everyone. Uh, any other
1:01:59final comments before we adjourn?
1:02:02It is 801
```*