2026-10-22 - Joint Board of Public Works and Committee on Infrastructure

Summary

Built from the city's posted minutes and the YouTube auto-generated captions of the meeting video. The posted agenda file is empty and the attached slides were only partly read.

  • Joint meeting called to order at 5:30 PM at 848 West Hollis Street; eight members were present, a quorum. Mayor Donchess and one alderman were absent. No public comment. The August 27 minutes were approved by voice vote.
  • DPW garage update from the owner's project manager (LeftField): after the aldermen's vote, a kickoff meeting covered the master schedule, a four-week look-ahead, requisition and invoice approval, and periodic inspections. The construction manager is still de-scoping subcontractors so all plan work falls within the guaranteed maximum price (GMP). An RFP went out for third-party testing agencies (concrete, rebar, steel, vapor barrier), a logistics plan was requested, and a commissioning agent will be hired. The solid waste facility cannot close, so operations must continue throughout construction.
  • Site work: the Fire Training facility and a couple of hoop-style buildings must come down; the hoop buildings are to be relocated for winter snow operations. The scale house stays. Site mobilization could begin as early as the first week of November. Staff will not need to move into trailers. The new building is set up to be heated with landfill gas. Substantial completion is scheduled for June 2028.
  • Invoices approved by voice vote: LeftField services through August 31 ($42,500), HKT Architects services through August 7 ($343,890.28) and a Harvey equipment deposit ($701,425.66), an early release to order equipment on schedule and part of the Harvey contract.
  • Contracts and amendments approved, with one no vote: LeftField amendment for construction administration and closeout ($719,000), HKT amendment ($1,533,731), UTS of Massachusetts site testing (not to exceed $125,000), and the Harvey Construction contract and GMP, not to exceed $43,479,897, inclusive of the deposit. Insurance language and standard business terms in the Harvey contract are still to be finalized; the number does not change.
  • Scheduling: the administrative services director proposed meeting monthly in the last week of the month, alternating around the Board of Public Works and Committee on Infrastructure. A Tuesday, November 24 meeting before the Board of Aldermen was floated, though some members objected to Thanksgiving week and asked for meetings no earlier than 5:30 or 6:00 PM; November 19 (a Board of Public Works date) was suggested instead. Nothing was decided; members will be polled. Adjourned by voice vote.

See DPW Garage and Fleet Facility. Members speaking included Alicia Gregg, Paula Johnson and Richard A. Dowd.

Agenda

Agenda PDF posted; see Sources.

Sources

Video

Watch the video

Transcript

*These are auto-generated captions; names and numbers may be misheard.

Transcript

01:59Mhm.

02:18>> Thank you very much.

02:21I've got to call to order a joint

02:23meeting of the Committee of

02:24Infrastructure and the Board of Public

02:25Works.

02:27It's being held today, Thursday, October

02:3022nd,

02:332026 at 5:30 p.m. at 848 West Hollis

02:38Street and duly noted in two places,

02:41including the city's website in

02:43accordance with the requirements of RSA

02:4691-A {semicolon} 2, Roman numeral 2.

02:52Will the clerk please call the roll?

02:55>> Sure. Commissioner Paul Shea.

02:57>> Present.

02:58>> Commissioner June Leman.

02:59>> Present.

03:00>> Commissioner Matthew Gregg.

03:01>> Here.

03:02>> Commissioner Manny Espitia.

03:04>> Here.

03:05>> Mayor Jim Donchess, not here.

03:08Alderman-at-Large Alicia Gregg is here.

03:10Alderman Paula Johnson.

03:12>> Present.

03:13>> Alderwoman Venja Filatov Smith.

03:16Not here. Alderman Richard Dowd.

03:19>> Present.

03:19>> Vice Chair.

03:20Alderman-at-Large Michael O'Brien.

03:22>> Present.

03:23>> Okay, and then also in attendance we

03:25have Tim Cummings, Administrative

03:27Services Director,

03:28Lisa Footeau, Director of Public Works,

03:31and Joe Sullivan from Left Field. You

03:33have 1 2 3 4

03:365 6 7. I have eight in attendance. We

03:39have quorum.

03:41>> Okay.

03:42The mayor has

03:44other business to attend to this

03:46evening. He's a busy dude, so

03:49Also,

03:50too, hoping that we'll have Alderman

03:53Smith

03:54join us, you know.

03:56>> Okay.

03:56>> She sometimes has trouble commuting

03:58here. Okay.

04:00I'll declare a quorum and we'll get into

04:04general introductory remarks. I don't

04:07really have anything, so I'll look to

04:10uh

04:11Service Director Tim Pamment,

04:13Administrative Service Director Pamment.

04:15>> Well, uh thank you, Mr. Chairman. I am

04:18excited to be here this evening because

04:20it's been a long time coming to be able

04:22to make a report to you and to the

04:25general public that we should be in good

04:27stead to move this project to a new

04:29phase where we're bringing the project

04:31under construction.

04:33Um I will not steal our OPM's thunder

04:36this evening in terms of giving more of

04:39a report, but I did want to just uh

04:43thank not just this body, but the the

04:46Board of Aldermen at large um and the

04:50general public for all their assistance

04:53and help in in in getting us to to where

04:56we are

04:57now. So, thank you, Mr. Chairman, and I

05:00believe you have some traditional

05:03duties to to unfold to before we move on

05:06to a project update.

05:08>> Very good, and that we do. And so, now

05:11I'll open it up to public comment.

05:15Uh seeing nobody, I will close public

05:18comment.

05:19I will now open up approval of minutes.

05:22Do I have a motion?

05:24>> Yes, I'd like to make a motion to

05:25approve the minutes of the August 27th,

05:282026 meeting.

05:30>> Okay.

05:31And that comes from Alderman Alicia Gray

05:34and not her husband, Anthony.

05:37>> Well, he's a Commissioner. I'm an

05:38Alderman.

05:39>> Big difference, people.

05:40>> I think we'll just Yeah, that will

05:42discern it. Okay.

05:45Uh Uh

05:46any discussion on it?

05:48Seeing none, I'll call

05:50the vote. All those in favor say I.

05:52>> I.

05:52>> I.

05:53>> Opposed?

05:54Motion carried.

05:55Now, we're getting into the DPW garage

05:58project project general progress update.

06:02And I'll turn that over to

06:03administrative service director Ken

06:05Cummins and Mr. Joe Sullivan from Left

06:10Field Left Field.

06:12Okay.

06:12Gentlemen.

06:13>> Uh and I'll just hand it right over to

06:15Mr. Sullivan.

06:16>> Thank you, Mr. Cummings. First and

06:18foremost, you know, it's very exciting.

06:20It's been

06:21a long-term plan to have this building

06:23built by the Division of Public Works.

06:25But I've been on this project a little

06:27over 2 years now just getting it to this

06:29point.

06:30There were a lot of challenges as we

06:33went through this and and we disclosed

06:34it through the

06:36task as we went through each month. I

06:38want to thank Lisa Fado cuz she's

06:40probably been the

06:42the captain of the ship to make sure

06:44that, you know, we went in the a

06:45direction that we needed to do. She put

06:47the right team together, the right

06:49support together, and without this

06:51committee, the city, and the residents,

06:53we wouldn't have a building that we're

06:54going to have for the next 50 years. And

06:56I want to thank everybody for that.

06:58Um that being said, I'd like to just

07:00provide a a few updates.

07:02Um

07:03with the

07:05vote that occurred, we put together a

07:08kickoff meeting with the CM, the

07:11architect, and Left Field along with key

07:14personnel from Division of Public Works

07:16just to go over what the expectations

07:19are. We had a kickoff agenda, what um

07:22standardization should happen throughout

07:24this process.

07:26We went through our vice middle

07:29processes. We went through what the

07:31approval process will be with each of

07:33the requisitions and and payment

07:35invoices that would be required. We went

07:37through dynamics of the The mechanism

07:41such as master schedule, four-week look

07:43ahead, uh we're going to be having uh

07:46meetings of notification of ins-

07:47periodic inspections as needed. And we

07:50went through that in pretty much uh

07:52extensive detail so that everybody

07:54understood the baseline of where we were

07:55going from there. In addition to that,

07:58Hobbs uh

07:59are going to continue to de-scope all of

08:02their subcontractors, make sure that all

08:04of the work inclusive of those plans and

08:07specs are within the GMP. Um and um the

08:11final GMP will be bringing to the

08:13committee the tonight just for approval.

08:16Additionally, uh we put a RFP out for

08:20testing agencies. That's the third-party

08:24entities that test the concrete, rebar,

08:26steel, any other, you know, vapor

08:28barrier uh within the building just to

08:30ensure that

08:32not only is the specifications and plans

08:34being met, but the installation

08:35practices are being done appropriately.

08:39We've updated the website based on the

08:41most current information and conditions

08:43with the city. And um

08:46during our kickoff meeting, we requested

08:48a logistics plan. That logistics plan

08:50gives a uh clear understanding as to

08:54what the CM's plans are as far as how

08:57they're going to position, you know, the

08:58job trailer, their laydown area for

09:01materials, where the subcontractors may

09:04uh

09:04lay uh all of their construction

09:07trailers and and uh materials. Um they

09:10provided that to the city and us. We

09:13went over it um at our kickoff meeting.

09:15We're providing details back to them for

09:17feedback just so that if there's

09:19operational issues,

09:21the kicker here is that we can't close

09:24the solid waste facility. So, that has

09:25to stay in operation during this whole

09:27process. So, it's not about just

09:29building a building. We have to make

09:30sure the operations and the staff have

09:33the ability to do what they need to do.

09:36So, that's a task that we've done over

09:38the

09:39last, you know, few weeks. Next steps,

09:43um

09:44a few buildings have to come down. So

09:46they have Department of Public Works is

09:48working closely internally to figure out

09:50how they're going to reposition and

09:52relocate some of the structures that

09:54they're going to need for the winter

09:55conditions.

09:56Um

09:57a commissioning agent will be hired to

09:59review any and all equipment associated

10:02with this building, not only

10:03specification related, but installation

10:06practices.

10:07We're going to continue having our

10:09weekly meetings with the design team,

10:11Harvey and Leyfield in the city, just to

10:13ensure that, you know, any hiccups or

10:16glitches that may come up, we're

10:18addressing them early so that they don't

10:19affect critical path in the schedule.

10:22And then site mobilization, we've been

10:25informed that they're looking to

10:26mobilize as early as the first week in

10:28November.

10:29So that that's the course of action over

10:31the next few weeks.

10:34And

10:34>> And then, Mr. Chairman, just just one

10:36point I want to illustrate is we will be

10:38transitioning to our standard owners

10:41uh project manager type meetings that

10:44we've done in the past, and as we

10:46transition to that process, we will

10:48reach out to you all and make you aware

10:50of how that gets developed and

10:51standardized and incorporate

10:53appropriately

10:55uh the the individuals so you can

10:57participate in that process.

11:00>> Any questions? Yep.

11:02>> Any questions?

11:04>> Okay.

11:05>> Uh Commissioner Greg, and then we have

11:07Alderman Johnson.

11:08>> Um is there any impact to

11:11uh number one, to the

11:13building here as it relates to I mean,

11:15obviously, demolition aside, is there

11:17any impact to the building and the folks

11:19that are here as they're going to have

11:20to be relocation to other locations for

11:22a portion of it, or do we feel like

11:24>> We We did have a proper a proper phasing

11:27aspect to this building. I mean, there

11:29will be some infrastructure that will be

11:32need to be tied into, but um you know,

11:35my expectation and and understanding is

11:37that we'll know well in advance when

11:38that'll happen and we'll coordinate it

11:40with the city operations as we move

11:42forward. But that was one of the strict

11:44policies that we as we're building this

11:46building operations shall not be

11:48interrupted.

11:49>> Okay. Great.

11:49>> Right.

11:50>> Alderman Johnson.

11:51>> Thank you. Now, which buildings will be

11:54torn down?

11:55>> Um the fire training facility be will be

11:57taken down and that's going to be uh

12:00relocated uh based on the fire

12:02department's coordination. And then

12:04there's a couple of exterior

12:07um

12:08hoop buildings I want to call them.

12:10They're like the rounded um

12:12>> the C span structures, yeah.

12:13>> they'll be uh we're looking to relocate

12:16them so that they can utilize them over

12:17the winter months to perform snow

12:20uh coverage and details with that. Those

12:22are the buildings that

12:23>> Solid waste building.

12:24>> Yeah. Mhm. Yeah.

12:26>> Does that include the rail cars?

12:30Yeah, I didn't get to see that.

12:31>> They're already They've been removed.

12:33>> They've been removed.

12:35>> Final one today.

12:36Yeah.

12:37>> Excavated, yeah.

12:39>> You can They're out there.

12:41>> Go get a piece of history.

12:43Follow up.

12:44>> Yes. Thank you. Now, the building by the

12:47waste station Wait. Is that one staying

12:49up or is that one coming down? by the

12:51waste

12:52>> Which which building?

12:53Do you mean the the scale the scale

12:55house? Yeah.

12:56>> Yes.

12:56>> No, that'll stay.

12:57>> That's staying.

12:58>> Yes.

12:58>> So, is that being upgraded or updated in

13:01there?

13:02>> We do have plans to update it, but it's

13:04not part of this project. Okay. So, but

13:06it it will stay there, yes.

13:07>> Okay.

13:07>> Yep.

13:08>> Shouldn't be interrupted.

13:09>> Well, it won't be interrupted, correct.

13:11>> Alderman Dow.

13:12>> A couple things. Um

13:14are you going to relocate some of the

13:15people in the trailers like we did for

13:17this building and

13:20>> Um I don't think there's going to be any

13:21Well, first of all, um

13:24specify your question one more time just

13:26so I have a clear understanding.

13:27>> Well, we we put some people in a trailer

13:29because we didn't have Of course, they

13:31get office space in here now, I suppose,

13:32but

13:33>> Yeah, there won't be any need to locate

13:35any of the staff in trailers whatsoever.

13:38Um the only trailers that'll be on site

13:40will be the construction um personnel.

13:43>> Okay, so they'll have that construction.

13:44>> Yep.

13:45>> Um and we're planning to heat the new

13:48building with gases from the landfill,

13:51correct?

13:51>> Correct.

13:52>> And we set this building up to take

13:54advantage of that. We the holes in the

13:56concrete and everything for the piping.

13:58>> That's all part of the construction.

14:00>> Good.

14:03>> Uh Commissioner Speedy,

14:05assuming winter is

14:08not rough, uh

14:11which [laughter] is a big assumption to

14:12make.

14:13>> Do you have a Do you have that magic

14:14ball that you're looking into?

14:16>> Forget all those plows. We'll just

14:18You know, keep the snowblower out for

14:19the whole winter.

14:20Um until until May.

14:22Um

14:23how long do you What do you What do you

14:25perceive the uh the timeline to be?

14:27>> Well,

14:28that's the magic question. Based on the

14:31provided master schedule that Harvey had

14:33provided, we're looking June of '28

14:37for substantial completion.

14:39And then what that means, substantial

14:40completion, is it's for its intended

14:42use. There is always punch list uh

14:45monetized punch list that's performed at

14:47a time and then close out during that

14:49duration. So, I want them in the

14:51building so that just in case, you know,

14:53we find any other little glitches that

14:54we we could add to the punch list to

14:56make sure that it's operational. So, um

14:59we'll be very thorough with that.

15:03>> Any further questions?

15:05>> Now, I've got one other item. I just

15:06wanted to introduce Jason Cody. He's

15:09from Harvey. He'll He'll be the

15:11project manager uh on behalf of them to

15:14manage this project appropriately.

15:16>> Yeah. Thank you for having me. We uh we

15:18look forward to working with DPW, the

15:20city, and Left Field to

15:22get this job going.

15:24>> Yep.

15:25>> I hope you have a coffee maker for the

15:27trip.

15:27>> [laughter]

15:28>> It's priority number one.

15:30>> I was told an espresso, but I don't know

15:32how far that

15:37>> [laughter]

15:41>> Big screen TV.

15:43>> Any further questions including a coffee

15:45maker or anything?

15:46>> [laughter]

15:48>> Okay. Seeing none,

15:49we'll move on to the next DPW garage

15:53project project approval of invoices.

15:57Alderman Blais.

15:58>> Thank you. I'd like to make a motion to

16:00approve Leftfield services through

16:02August 31st, 2026, number 200721

16:07in the amount of $42,500.

16:10HKT Architects Incorporated services

16:13through August 7th, 2026, number 0010

16:18-022442

16:20in the amount of $343,890.28.

16:26And Harvey

16:28Is it Body?

16:29Body equipment deposit invoice 26021

16:34in the amount of $701,425.66.

16:40>> Okay. Director Cummings, would you like

16:41to introduce this?

16:42>> Yes, if I may, Mr. Chairman. So,

16:45pretty standard. I'll start with the

16:47last one first. This is if you will,

16:50something that you could look at as like

16:52an early release. We want to get going

16:54on making sure we have the right

16:56equipment on hand for the building

16:58project. So, this 700,000 and change is

17:01part of the Harvey contract that's going

17:05to be approved later on down the line

17:08in in the agenda here. So, it's part of

17:10the 43 and change million, but we do

17:13want to instead of waiting a month to

17:15get this invoice approved. We want to

17:17get it approved this evening so we can

17:19we can get the piece of equipment

17:21ordered so we can stay on schedule. The

17:24other items, Mr. Chairman, are pretty

17:26standard contracts all recommended by

17:29Left Field or myself for approval this

17:33evening. Thank you.

17:36>> Okay. Any discussion on the motion?

17:39Seeing none, I'll call for the vote. All

17:41those in favor signify by saying aye.

17:44>> Aye.

17:44>> Opposed?

17:45>> None.

17:46>> One name?

17:47>> One name.

17:47>> One name.

17:48>> Aye. Motion carried.

17:51Uh

17:52now the DPW garage project approval of

17:56contract proposals and amendments. Open

17:59to debate.

18:00>> Thank you. I'd like to make a motion to

18:02approve Left Field Amendment services

18:04through construction administration and

18:06closeout for $719,000.

18:09HKT Amendment services through

18:11construction administration and closeout

18:14for $1,533,731.

18:18UTS of Massachusetts Incorporated

18:21contract site testing for NTE figure of

18:25$125,000

18:26and Harvey Construction contract and GMP

18:29construction for

18:31$43,479,897.

18:37>> Okay. Director Cummings, introduction,

18:39please.

18:39>> Uh yes, thank you, Mr. Chairman.

18:41So no additional comments really. I

18:43think all this is very straight forward.

18:45Um the only note that I'll make is the

18:47There is some insurance issues that we

18:49are going to continue to work through

18:52and some pretty standard standard

18:55business terms that we need to finalize

18:57on the um

18:59uh contract for Harvey, but the the

19:02number does not change. We are seeking

19:04approval of a not to exceed $43,479,897

19:10uh this evening, uh but we will be uh

19:13looking to to update the insurance

19:15language in this in this contract. And I

19:17just wanted to put that on the record,

19:19but otherwise,

19:20uh it is as presented. Thank you.

19:23>> Okay. Any discussion on the motion? All

19:26in uh excuse me, Commissioner votes.

19:29>> I'll have it.

19:30>> Um

19:31the Harvey Construction contract and GMP

19:34total the 43 million there, is that

19:36inclusive of what we just approved?

19:39>> Correct.

19:39>> Okay, I wanted to make sure that it

19:40wasn't pulled out. Okay, great. Thank

19:41you.

19:42>> Not in addition to.

19:43>> Not in addition to.

19:45>> Further questions?

19:47Seeing none,

19:48I will now call for the vote. All those

19:50in favor signify by saying I.

19:52>> I.

19:53>> I.

19:53>> Opposed?

19:54>> Nay.

19:55>> Okay, one nay.

19:57Um

19:58motion approved.

19:59Other expenditures for approval.

20:02>> None.

20:02>> None at this time.

20:03>> And old business. Anybody got any old

20:06business we'd like to bring up?

20:09Okay, seeing none,

20:11comes to

20:13Alderman Dowd.

20:14>> If I may, Mr. Chairman.

20:16>> [laughter]

20:16>> Yeah, I was just going to ask is there

20:17anything else?

20:18>> Thank you. Yes. Uh well, and this is for

20:20conversation purposes. We are going to

20:22need to start meeting monthly uh on a

20:25more regular basis, and I will work with

20:28you all to develop a time

20:30uh that's appropriate. I I think we'll

20:33probably try to flip back and forth

20:35between the Board of uh Public Works on

20:37a Thursday and before an infrastructure

20:39on a Wednesday, uh but

20:42believe it or not, the next time we

20:44would need to meet is actually the week

20:46of Thanksgiving.

20:47And and so I am suggesting maybe we do

20:50it on the Tuesday before the Board of

20:52Aldermen on November 24th.

20:55Um just uh

20:56just uh for conversation purposes, cuz I

20:59I believe the Infrastructure Committee

21:01meeting on the November 25th most likely

21:04will be canceled, though I have had no

21:06conversations with the chairman on that.

21:09Um and obviously Thanksgiving being that

21:11Thursday, I don't see any any any

21:13business being conducted. So, that was

21:15the rationale for the dates behind this.

21:18I would like to keep track uh

21:20schedule in terms of the last

21:23We the last week of the month being when

21:27this joint body meets. So, that's that's

21:29why I am offering this up.

21:33>> Uh

21:34Oliver Johnson.

21:35>> Thank you. I would appreciate we didn't

21:36stop meetings really before 5:30 or 6:00

21:40because there's no way, especially in my

21:42situation right now, running from work

21:44and trying to get home and get to the

21:46meetings.

21:47So, I'd be

21:47>> I understood.

21:48>> Okay, thank you.

21:50>> Oliver Stout.

21:52>> Yeah, and I know you know this, but

21:54coordinate with Donna.

21:57>> [laughter]

21:57>> It has been drilled into my head.

21:59>> Yes.

21:59>> Thank you.

22:02Okay.

22:03>> And I'm looking at my

22:04>> First of all, I don't think we're

22:06meeting on Thanksgiving.

22:07>> I I had a feeling.

22:08>> I have other plans.

22:09>> Somebody take your head off.

22:13Yeah.

22:14>> And November 24th is half Friday, yeah?

22:18>> If you'd like to bring one.

22:21If this quorum, I'll bring one.

22:24>> [laughter]

22:25>> All right, so we'll float that and I

22:27think we're going to have the same

22:28scheduling.

22:30Probably won't be until January where we

22:32can get into a start of a proper a cycle

22:35because Christmas.

22:37>> Uh

22:37>> All right, well, we'll work through

22:38that, but yep, it will be it will be

22:40something like early early in the last

22:43week of December.

22:45>> Maybe if you plan the meetings ahead on

22:47a list and send out the list, so

22:50make sure everybody's

22:52>> The Board of Public Works also meets on

22:54the 19th of November.

22:56>> Just

22:59>> We'll discuss that.

23:01Put me on list.

23:02>> I will.

23:03>> [laughter]

23:05>> All right.

23:06>> I would I just want to mention one

23:07thing. I I would want a commitment from

23:09everybody because that's Thanksgiving

23:11week. So, that's that's a tough

23:13time to have meetings. So,

23:15we might want to Is it Can everybody

23:16meet on the 24th?

23:20Yeah.

23:22>> But, there's going to be a Board of

23:23Aldermen meeting unless I know

23:27I will be in California, so the remote

23:29would be great.

23:31>> But, that's going to be a quorum

23:32problem.

23:34>> All right. Well,

23:35the best way probably to do this is

23:38poll [snorts] the the members of the

23:40Audit Committee. I'll poll the members

23:41of my committee.

23:42>> Okay.

23:43>> And then we'll contact Director

23:44Cummings. So, we'll talk to our

23:46administrative services and put

23:48something on the docket.

23:50Yeah, I'm sure she can find a place

23:52whether here or in the chamber to meet

23:55and everything else. So,

23:57these holidays kind of jam us kind of

23:59close.

24:02Anybody else got anything for the good

24:04of the

24:06wide world? Alderman Gray?

24:08>> Yeah.

24:09>> [laughter]

24:09>> Commissioner.

24:10>> It's close enough.

24:12>> What uh

24:13why can't we do the 19th?

24:16>> Uh good question.

24:20>> Well, part part of the issue and I don't

24:22want to get into this now is we got to

24:23make sure we can get the recs done in

24:25time and and and this paperwork that

24:29goes into making it a successful and

24:32productive meeting. So, standardizing

24:34this and making sure we have a certain

24:36cadence so that way Harvey, more than

24:39anyone, can build a timeline backwards

24:42that can get the invoices in, vetted,

24:44submitted to us, and us also get it on

24:48the agenda appropriately.

24:50Takes takes some coordination.

24:52>> I think you'll probably find that like

24:54you'll get more people here on the 19th

24:55and and I get the whole concept of

24:57having to rush to get that done, but I

24:59it's better than the alternative of just

25:01not being able to have quorum.

25:02>> They can forecast, but at the end of the

25:04day we'll be able to get the

25:05requisition, review it, they'll forecast

25:08towards the end of the month, and we'll

25:09be able to present confidently what that

25:11value is.

25:12>> Okay.

25:13>> So, now also two other committees on the

25:15Ottoman side

25:17are running [clears throat] at the same

25:18time constraints, so

25:20>> Okay.

25:20>> availability

25:21>> of the

25:23>> place to meet, so

25:25Uh

25:25so, stand by your computers, you know,

25:27waiting for that email

25:32>> So, Jason, just be prepared for that and

25:34try to have the wreck as soon as

25:35possible available. That's all. In

25:38preparation.

25:41>> Is that it?

25:41>> That's it. Everybody got it?

25:43>> All right.

25:44So, I would move to adjourn.

25:46>> I'd like to make a motion to adjourn.

25:49>> Okay.

25:50All those in favor signify by saying I.

25:52>> I.

25:53>> Opposed?

25:55The motion has no name.

25:56>> No name. No name. No name.

25:59>> All right, try.

```*