2026-10-22 - Joint Board of Public Works and Committee on Infrastructure
Summary
Built from the city's posted minutes and the YouTube auto-generated captions of the meeting video. The posted agenda file is empty and the attached slides were only partly read.
- Joint meeting called to order at 5:30 PM at 848 West Hollis Street; eight members were present, a quorum. Mayor Donchess and one alderman were absent. No public comment. The August 27 minutes were approved by voice vote.
- DPW garage update from the owner's project manager (LeftField): after the aldermen's vote, a kickoff meeting covered the master schedule, a four-week look-ahead, requisition and invoice approval, and periodic inspections. The construction manager is still de-scoping subcontractors so all plan work falls within the guaranteed maximum price (GMP). An RFP went out for third-party testing agencies (concrete, rebar, steel, vapor barrier), a logistics plan was requested, and a commissioning agent will be hired. The solid waste facility cannot close, so operations must continue throughout construction.
- Site work: the Fire Training facility and a couple of hoop-style buildings must come down; the hoop buildings are to be relocated for winter snow operations. The scale house stays. Site mobilization could begin as early as the first week of November. Staff will not need to move into trailers. The new building is set up to be heated with landfill gas. Substantial completion is scheduled for June 2028.
- Invoices approved by voice vote: LeftField services through August 31 ($42,500), HKT Architects services through August 7 ($343,890.28) and a Harvey equipment deposit ($701,425.66), an early release to order equipment on schedule and part of the Harvey contract.
- Contracts and amendments approved, with one no vote: LeftField amendment for construction administration and closeout ($719,000), HKT amendment ($1,533,731), UTS of Massachusetts site testing (not to exceed $125,000), and the Harvey Construction contract and GMP, not to exceed $43,479,897, inclusive of the deposit. Insurance language and standard business terms in the Harvey contract are still to be finalized; the number does not change.
- Scheduling: the administrative services director proposed meeting monthly in the last week of the month, alternating around the Board of Public Works and Committee on Infrastructure. A Tuesday, November 24 meeting before the Board of Aldermen was floated, though some members objected to Thanksgiving week and asked for meetings no earlier than 5:30 or 6:00 PM; November 19 (a Board of Public Works date) was suggested instead. Nothing was decided; members will be polled. Adjourned by voice vote.
See DPW Garage and Fleet Facility. Members speaking included Alicia Gregg, Paula Johnson and Richard A. Dowd.
Agenda
Agenda PDF posted; see Sources.
Sources
- City meeting page: https://nashuanh.portal.civicclerk.com/event/7356/overview
- Agenda: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14827,plainText=false)
- Minutes: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14891,plainText=false)
- Agenda packet: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14828,plainText=false)
- Notice: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14826,plainText=false)
- Video: https://www.youtube.com/watch?v=K5cSZpEzoEM (Nashua Board of Aldermen meetings YouTube channel)
Video
Transcript
*These are auto-generated captions; names and numbers may be misheard.
Transcript
01:59Mhm.
02:18>> Thank you very much.
02:21I've got to call to order a joint
02:23meeting of the Committee of
02:24Infrastructure and the Board of Public
02:25Works.
02:27It's being held today, Thursday, October
02:3022nd,
02:332026 at 5:30 p.m. at 848 West Hollis
02:38Street and duly noted in two places,
02:41including the city's website in
02:43accordance with the requirements of RSA
02:4691-A {semicolon} 2, Roman numeral 2.
02:52Will the clerk please call the roll?
02:55>> Sure. Commissioner Paul Shea.
02:57>> Present.
02:58>> Commissioner June Leman.
02:59>> Present.
03:00>> Commissioner Matthew Gregg.
03:01>> Here.
03:02>> Commissioner Manny Espitia.
03:04>> Here.
03:05>> Mayor Jim Donchess, not here.
03:08Alderman-at-Large Alicia Gregg is here.
03:10Alderman Paula Johnson.
03:12>> Present.
03:13>> Alderwoman Venja Filatov Smith.
03:16Not here. Alderman Richard Dowd.
03:19>> Present.
03:19>> Vice Chair.
03:20Alderman-at-Large Michael O'Brien.
03:22>> Present.
03:23>> Okay, and then also in attendance we
03:25have Tim Cummings, Administrative
03:27Services Director,
03:28Lisa Footeau, Director of Public Works,
03:31and Joe Sullivan from Left Field. You
03:33have 1 2 3 4
03:365 6 7. I have eight in attendance. We
03:39have quorum.
03:41>> Okay.
03:42The mayor has
03:44other business to attend to this
03:46evening. He's a busy dude, so
03:49Also,
03:50too, hoping that we'll have Alderman
03:53Smith
03:54join us, you know.
03:56>> Okay.
03:56>> She sometimes has trouble commuting
03:58here. Okay.
04:00I'll declare a quorum and we'll get into
04:04general introductory remarks. I don't
04:07really have anything, so I'll look to
04:10uh
04:11Service Director Tim Pamment,
04:13Administrative Service Director Pamment.
04:15>> Well, uh thank you, Mr. Chairman. I am
04:18excited to be here this evening because
04:20it's been a long time coming to be able
04:22to make a report to you and to the
04:25general public that we should be in good
04:27stead to move this project to a new
04:29phase where we're bringing the project
04:31under construction.
04:33Um I will not steal our OPM's thunder
04:36this evening in terms of giving more of
04:39a report, but I did want to just uh
04:43thank not just this body, but the the
04:46Board of Aldermen at large um and the
04:50general public for all their assistance
04:53and help in in in getting us to to where
04:56we are
04:57now. So, thank you, Mr. Chairman, and I
05:00believe you have some traditional
05:03duties to to unfold to before we move on
05:06to a project update.
05:08>> Very good, and that we do. And so, now
05:11I'll open it up to public comment.
05:15Uh seeing nobody, I will close public
05:18comment.
05:19I will now open up approval of minutes.
05:22Do I have a motion?
05:24>> Yes, I'd like to make a motion to
05:25approve the minutes of the August 27th,
05:282026 meeting.
05:30>> Okay.
05:31And that comes from Alderman Alicia Gray
05:34and not her husband, Anthony.
05:37>> Well, he's a Commissioner. I'm an
05:38Alderman.
05:39>> Big difference, people.
05:40>> I think we'll just Yeah, that will
05:42discern it. Okay.
05:45Uh Uh
05:46any discussion on it?
05:48Seeing none, I'll call
05:50the vote. All those in favor say I.
05:52>> I.
05:52>> I.
05:53>> Opposed?
05:54Motion carried.
05:55Now, we're getting into the DPW garage
05:58project project general progress update.
06:02And I'll turn that over to
06:03administrative service director Ken
06:05Cummins and Mr. Joe Sullivan from Left
06:10Field Left Field.
06:12Okay.
06:12Gentlemen.
06:13>> Uh and I'll just hand it right over to
06:15Mr. Sullivan.
06:16>> Thank you, Mr. Cummings. First and
06:18foremost, you know, it's very exciting.
06:20It's been
06:21a long-term plan to have this building
06:23built by the Division of Public Works.
06:25But I've been on this project a little
06:27over 2 years now just getting it to this
06:29point.
06:30There were a lot of challenges as we
06:33went through this and and we disclosed
06:34it through the
06:36task as we went through each month. I
06:38want to thank Lisa Fado cuz she's
06:40probably been the
06:42the captain of the ship to make sure
06:44that, you know, we went in the a
06:45direction that we needed to do. She put
06:47the right team together, the right
06:49support together, and without this
06:51committee, the city, and the residents,
06:53we wouldn't have a building that we're
06:54going to have for the next 50 years. And
06:56I want to thank everybody for that.
06:58Um that being said, I'd like to just
07:00provide a a few updates.
07:02Um
07:03with the
07:05vote that occurred, we put together a
07:08kickoff meeting with the CM, the
07:11architect, and Left Field along with key
07:14personnel from Division of Public Works
07:16just to go over what the expectations
07:19are. We had a kickoff agenda, what um
07:22standardization should happen throughout
07:24this process.
07:26We went through our vice middle
07:29processes. We went through what the
07:31approval process will be with each of
07:33the requisitions and and payment
07:35invoices that would be required. We went
07:37through dynamics of the The mechanism
07:41such as master schedule, four-week look
07:43ahead, uh we're going to be having uh
07:46meetings of notification of ins-
07:47periodic inspections as needed. And we
07:50went through that in pretty much uh
07:52extensive detail so that everybody
07:54understood the baseline of where we were
07:55going from there. In addition to that,
07:58Hobbs uh
07:59are going to continue to de-scope all of
08:02their subcontractors, make sure that all
08:04of the work inclusive of those plans and
08:07specs are within the GMP. Um and um the
08:11final GMP will be bringing to the
08:13committee the tonight just for approval.
08:16Additionally, uh we put a RFP out for
08:20testing agencies. That's the third-party
08:24entities that test the concrete, rebar,
08:26steel, any other, you know, vapor
08:28barrier uh within the building just to
08:30ensure that
08:32not only is the specifications and plans
08:34being met, but the installation
08:35practices are being done appropriately.
08:39We've updated the website based on the
08:41most current information and conditions
08:43with the city. And um
08:46during our kickoff meeting, we requested
08:48a logistics plan. That logistics plan
08:50gives a uh clear understanding as to
08:54what the CM's plans are as far as how
08:57they're going to position, you know, the
08:58job trailer, their laydown area for
09:01materials, where the subcontractors may
09:04uh
09:04lay uh all of their construction
09:07trailers and and uh materials. Um they
09:10provided that to the city and us. We
09:13went over it um at our kickoff meeting.
09:15We're providing details back to them for
09:17feedback just so that if there's
09:19operational issues,
09:21the kicker here is that we can't close
09:24the solid waste facility. So, that has
09:25to stay in operation during this whole
09:27process. So, it's not about just
09:29building a building. We have to make
09:30sure the operations and the staff have
09:33the ability to do what they need to do.
09:36So, that's a task that we've done over
09:38the
09:39last, you know, few weeks. Next steps,
09:43um
09:44a few buildings have to come down. So
09:46they have Department of Public Works is
09:48working closely internally to figure out
09:50how they're going to reposition and
09:52relocate some of the structures that
09:54they're going to need for the winter
09:55conditions.
09:56Um
09:57a commissioning agent will be hired to
09:59review any and all equipment associated
10:02with this building, not only
10:03specification related, but installation
10:06practices.
10:07We're going to continue having our
10:09weekly meetings with the design team,
10:11Harvey and Leyfield in the city, just to
10:13ensure that, you know, any hiccups or
10:16glitches that may come up, we're
10:18addressing them early so that they don't
10:19affect critical path in the schedule.
10:22And then site mobilization, we've been
10:25informed that they're looking to
10:26mobilize as early as the first week in
10:28November.
10:29So that that's the course of action over
10:31the next few weeks.
10:34And
10:34>> And then, Mr. Chairman, just just one
10:36point I want to illustrate is we will be
10:38transitioning to our standard owners
10:41uh project manager type meetings that
10:44we've done in the past, and as we
10:46transition to that process, we will
10:48reach out to you all and make you aware
10:50of how that gets developed and
10:51standardized and incorporate
10:53appropriately
10:55uh the the individuals so you can
10:57participate in that process.
11:00>> Any questions? Yep.
11:02>> Any questions?
11:04>> Okay.
11:05>> Uh Commissioner Greg, and then we have
11:07Alderman Johnson.
11:08>> Um is there any impact to
11:11uh number one, to the
11:13building here as it relates to I mean,
11:15obviously, demolition aside, is there
11:17any impact to the building and the folks
11:19that are here as they're going to have
11:20to be relocation to other locations for
11:22a portion of it, or do we feel like
11:24>> We We did have a proper a proper phasing
11:27aspect to this building. I mean, there
11:29will be some infrastructure that will be
11:32need to be tied into, but um you know,
11:35my expectation and and understanding is
11:37that we'll know well in advance when
11:38that'll happen and we'll coordinate it
11:40with the city operations as we move
11:42forward. But that was one of the strict
11:44policies that we as we're building this
11:46building operations shall not be
11:48interrupted.
11:49>> Okay. Great.
11:49>> Right.
11:50>> Alderman Johnson.
11:51>> Thank you. Now, which buildings will be
11:54torn down?
11:55>> Um the fire training facility be will be
11:57taken down and that's going to be uh
12:00relocated uh based on the fire
12:02department's coordination. And then
12:04there's a couple of exterior
12:07um
12:08hoop buildings I want to call them.
12:10They're like the rounded um
12:12>> the C span structures, yeah.
12:13>> they'll be uh we're looking to relocate
12:16them so that they can utilize them over
12:17the winter months to perform snow
12:20uh coverage and details with that. Those
12:22are the buildings that
12:23>> Solid waste building.
12:24>> Yeah. Mhm. Yeah.
12:26>> Does that include the rail cars?
12:30Yeah, I didn't get to see that.
12:31>> They're already They've been removed.
12:33>> They've been removed.
12:35>> Final one today.
12:36Yeah.
12:37>> Excavated, yeah.
12:39>> You can They're out there.
12:41>> Go get a piece of history.
12:43Follow up.
12:44>> Yes. Thank you. Now, the building by the
12:47waste station Wait. Is that one staying
12:49up or is that one coming down? by the
12:51waste
12:52>> Which which building?
12:53Do you mean the the scale the scale
12:55house? Yeah.
12:56>> Yes.
12:56>> No, that'll stay.
12:57>> That's staying.
12:58>> Yes.
12:58>> So, is that being upgraded or updated in
13:01there?
13:02>> We do have plans to update it, but it's
13:04not part of this project. Okay. So, but
13:06it it will stay there, yes.
13:07>> Okay.
13:07>> Yep.
13:08>> Shouldn't be interrupted.
13:09>> Well, it won't be interrupted, correct.
13:11>> Alderman Dow.
13:12>> A couple things. Um
13:14are you going to relocate some of the
13:15people in the trailers like we did for
13:17this building and
13:20>> Um I don't think there's going to be any
13:21Well, first of all, um
13:24specify your question one more time just
13:26so I have a clear understanding.
13:27>> Well, we we put some people in a trailer
13:29because we didn't have Of course, they
13:31get office space in here now, I suppose,
13:32but
13:33>> Yeah, there won't be any need to locate
13:35any of the staff in trailers whatsoever.
13:38Um the only trailers that'll be on site
13:40will be the construction um personnel.
13:43>> Okay, so they'll have that construction.
13:44>> Yep.
13:45>> Um and we're planning to heat the new
13:48building with gases from the landfill,
13:51correct?
13:51>> Correct.
13:52>> And we set this building up to take
13:54advantage of that. We the holes in the
13:56concrete and everything for the piping.
13:58>> That's all part of the construction.
14:00>> Good.
14:03>> Uh Commissioner Speedy,
14:05assuming winter is
14:08not rough, uh
14:11which [laughter] is a big assumption to
14:12make.
14:13>> Do you have a Do you have that magic
14:14ball that you're looking into?
14:16>> Forget all those plows. We'll just
14:18You know, keep the snowblower out for
14:19the whole winter.
14:20Um until until May.
14:22Um
14:23how long do you What do you What do you
14:25perceive the uh the timeline to be?
14:27>> Well,
14:28that's the magic question. Based on the
14:31provided master schedule that Harvey had
14:33provided, we're looking June of '28
14:37for substantial completion.
14:39And then what that means, substantial
14:40completion, is it's for its intended
14:42use. There is always punch list uh
14:45monetized punch list that's performed at
14:47a time and then close out during that
14:49duration. So, I want them in the
14:51building so that just in case, you know,
14:53we find any other little glitches that
14:54we we could add to the punch list to
14:56make sure that it's operational. So, um
14:59we'll be very thorough with that.
15:03>> Any further questions?
15:05>> Now, I've got one other item. I just
15:06wanted to introduce Jason Cody. He's
15:09from Harvey. He'll He'll be the
15:11project manager uh on behalf of them to
15:14manage this project appropriately.
15:16>> Yeah. Thank you for having me. We uh we
15:18look forward to working with DPW, the
15:20city, and Left Field to
15:22get this job going.
15:24>> Yep.
15:25>> I hope you have a coffee maker for the
15:27trip.
15:27>> [laughter]
15:28>> It's priority number one.
15:30>> I was told an espresso, but I don't know
15:32how far that
15:37>> [laughter]
15:41>> Big screen TV.
15:43>> Any further questions including a coffee
15:45maker or anything?
15:46>> [laughter]
15:48>> Okay. Seeing none,
15:49we'll move on to the next DPW garage
15:53project project approval of invoices.
15:57Alderman Blais.
15:58>> Thank you. I'd like to make a motion to
16:00approve Leftfield services through
16:02August 31st, 2026, number 200721
16:07in the amount of $42,500.
16:10HKT Architects Incorporated services
16:13through August 7th, 2026, number 0010
16:18-022442
16:20in the amount of $343,890.28.
16:26And Harvey
16:28Is it Body?
16:29Body equipment deposit invoice 26021
16:34in the amount of $701,425.66.
16:40>> Okay. Director Cummings, would you like
16:41to introduce this?
16:42>> Yes, if I may, Mr. Chairman. So,
16:45pretty standard. I'll start with the
16:47last one first. This is if you will,
16:50something that you could look at as like
16:52an early release. We want to get going
16:54on making sure we have the right
16:56equipment on hand for the building
16:58project. So, this 700,000 and change is
17:01part of the Harvey contract that's going
17:05to be approved later on down the line
17:08in in the agenda here. So, it's part of
17:10the 43 and change million, but we do
17:13want to instead of waiting a month to
17:15get this invoice approved. We want to
17:17get it approved this evening so we can
17:19we can get the piece of equipment
17:21ordered so we can stay on schedule. The
17:24other items, Mr. Chairman, are pretty
17:26standard contracts all recommended by
17:29Left Field or myself for approval this
17:33evening. Thank you.
17:36>> Okay. Any discussion on the motion?
17:39Seeing none, I'll call for the vote. All
17:41those in favor signify by saying aye.
17:44>> Aye.
17:44>> Opposed?
17:45>> None.
17:46>> One name?
17:47>> One name.
17:47>> One name.
17:48>> Aye. Motion carried.
17:51Uh
17:52now the DPW garage project approval of
17:56contract proposals and amendments. Open
17:59to debate.
18:00>> Thank you. I'd like to make a motion to
18:02approve Left Field Amendment services
18:04through construction administration and
18:06closeout for $719,000.
18:09HKT Amendment services through
18:11construction administration and closeout
18:14for $1,533,731.
18:18UTS of Massachusetts Incorporated
18:21contract site testing for NTE figure of
18:25$125,000
18:26and Harvey Construction contract and GMP
18:29construction for
18:31$43,479,897.
18:37>> Okay. Director Cummings, introduction,
18:39please.
18:39>> Uh yes, thank you, Mr. Chairman.
18:41So no additional comments really. I
18:43think all this is very straight forward.
18:45Um the only note that I'll make is the
18:47There is some insurance issues that we
18:49are going to continue to work through
18:52and some pretty standard standard
18:55business terms that we need to finalize
18:57on the um
18:59uh contract for Harvey, but the the
19:02number does not change. We are seeking
19:04approval of a not to exceed $43,479,897
19:10uh this evening, uh but we will be uh
19:13looking to to update the insurance
19:15language in this in this contract. And I
19:17just wanted to put that on the record,
19:19but otherwise,
19:20uh it is as presented. Thank you.
19:23>> Okay. Any discussion on the motion? All
19:26in uh excuse me, Commissioner votes.
19:29>> I'll have it.
19:30>> Um
19:31the Harvey Construction contract and GMP
19:34total the 43 million there, is that
19:36inclusive of what we just approved?
19:39>> Correct.
19:39>> Okay, I wanted to make sure that it
19:40wasn't pulled out. Okay, great. Thank
19:41you.
19:42>> Not in addition to.
19:43>> Not in addition to.
19:45>> Further questions?
19:47Seeing none,
19:48I will now call for the vote. All those
19:50in favor signify by saying I.
19:52>> I.
19:53>> I.
19:53>> Opposed?
19:54>> Nay.
19:55>> Okay, one nay.
19:57Um
19:58motion approved.
19:59Other expenditures for approval.
20:02>> None.
20:02>> None at this time.
20:03>> And old business. Anybody got any old
20:06business we'd like to bring up?
20:09Okay, seeing none,
20:11comes to
20:13Alderman Dowd.
20:14>> If I may, Mr. Chairman.
20:16>> [laughter]
20:16>> Yeah, I was just going to ask is there
20:17anything else?
20:18>> Thank you. Yes. Uh well, and this is for
20:20conversation purposes. We are going to
20:22need to start meeting monthly uh on a
20:25more regular basis, and I will work with
20:28you all to develop a time
20:30uh that's appropriate. I I think we'll
20:33probably try to flip back and forth
20:35between the Board of uh Public Works on
20:37a Thursday and before an infrastructure
20:39on a Wednesday, uh but
20:42believe it or not, the next time we
20:44would need to meet is actually the week
20:46of Thanksgiving.
20:47And and so I am suggesting maybe we do
20:50it on the Tuesday before the Board of
20:52Aldermen on November 24th.
20:55Um just uh
20:56just uh for conversation purposes, cuz I
20:59I believe the Infrastructure Committee
21:01meeting on the November 25th most likely
21:04will be canceled, though I have had no
21:06conversations with the chairman on that.
21:09Um and obviously Thanksgiving being that
21:11Thursday, I don't see any any any
21:13business being conducted. So, that was
21:15the rationale for the dates behind this.
21:18I would like to keep track uh
21:20schedule in terms of the last
21:23We the last week of the month being when
21:27this joint body meets. So, that's that's
21:29why I am offering this up.
21:33>> Uh
21:34Oliver Johnson.
21:35>> Thank you. I would appreciate we didn't
21:36stop meetings really before 5:30 or 6:00
21:40because there's no way, especially in my
21:42situation right now, running from work
21:44and trying to get home and get to the
21:46meetings.
21:47So, I'd be
21:47>> I understood.
21:48>> Okay, thank you.
21:50>> Oliver Stout.
21:52>> Yeah, and I know you know this, but
21:54coordinate with Donna.
21:57>> [laughter]
21:57>> It has been drilled into my head.
21:59>> Yes.
21:59>> Thank you.
22:02Okay.
22:03>> And I'm looking at my
22:04>> First of all, I don't think we're
22:06meeting on Thanksgiving.
22:07>> I I had a feeling.
22:08>> I have other plans.
22:09>> Somebody take your head off.
22:13Yeah.
22:14>> And November 24th is half Friday, yeah?
22:18>> If you'd like to bring one.
22:21If this quorum, I'll bring one.
22:24>> [laughter]
22:25>> All right, so we'll float that and I
22:27think we're going to have the same
22:28scheduling.
22:30Probably won't be until January where we
22:32can get into a start of a proper a cycle
22:35because Christmas.
22:37>> Uh
22:37>> All right, well, we'll work through
22:38that, but yep, it will be it will be
22:40something like early early in the last
22:43week of December.
22:45>> Maybe if you plan the meetings ahead on
22:47a list and send out the list, so
22:50make sure everybody's
22:52>> The Board of Public Works also meets on
22:54the 19th of November.
22:56>> Just
22:59>> We'll discuss that.
23:01Put me on list.
23:02>> I will.
23:03>> [laughter]
23:05>> All right.
23:06>> I would I just want to mention one
23:07thing. I I would want a commitment from
23:09everybody because that's Thanksgiving
23:11week. So, that's that's a tough
23:13time to have meetings. So,
23:15we might want to Is it Can everybody
23:16meet on the 24th?
23:20Yeah.
23:22>> But, there's going to be a Board of
23:23Aldermen meeting unless I know
23:27I will be in California, so the remote
23:29would be great.
23:31>> But, that's going to be a quorum
23:32problem.
23:34>> All right. Well,
23:35the best way probably to do this is
23:38poll [snorts] the the members of the
23:40Audit Committee. I'll poll the members
23:41of my committee.
23:42>> Okay.
23:43>> And then we'll contact Director
23:44Cummings. So, we'll talk to our
23:46administrative services and put
23:48something on the docket.
23:50Yeah, I'm sure she can find a place
23:52whether here or in the chamber to meet
23:55and everything else. So,
23:57these holidays kind of jam us kind of
23:59close.
24:02Anybody else got anything for the good
24:04of the
24:06wide world? Alderman Gray?
24:08>> Yeah.
24:09>> [laughter]
24:09>> Commissioner.
24:10>> It's close enough.
24:12>> What uh
24:13why can't we do the 19th?
24:16>> Uh good question.
24:20>> Well, part part of the issue and I don't
24:22want to get into this now is we got to
24:23make sure we can get the recs done in
24:25time and and and this paperwork that
24:29goes into making it a successful and
24:32productive meeting. So, standardizing
24:34this and making sure we have a certain
24:36cadence so that way Harvey, more than
24:39anyone, can build a timeline backwards
24:42that can get the invoices in, vetted,
24:44submitted to us, and us also get it on
24:48the agenda appropriately.
24:50Takes takes some coordination.
24:52>> I think you'll probably find that like
24:54you'll get more people here on the 19th
24:55and and I get the whole concept of
24:57having to rush to get that done, but I
24:59it's better than the alternative of just
25:01not being able to have quorum.
25:02>> They can forecast, but at the end of the
25:04day we'll be able to get the
25:05requisition, review it, they'll forecast
25:08towards the end of the month, and we'll
25:09be able to present confidently what that
25:11value is.
25:12>> Okay.
25:13>> So, now also two other committees on the
25:15Ottoman side
25:17are running [clears throat] at the same
25:18time constraints, so
25:20>> Okay.
25:20>> availability
25:21>> of the
25:23>> place to meet, so
25:25Uh
25:25so, stand by your computers, you know,
25:27waiting for that email
25:32>> So, Jason, just be prepared for that and
25:34try to have the wreck as soon as
25:35possible available. That's all. In
25:38preparation.
25:41>> Is that it?
25:41>> That's it. Everybody got it?
25:43>> All right.
25:44So, I would move to adjourn.
25:46>> I'd like to make a motion to adjourn.
25:49>> Okay.
25:50All those in favor signify by saying I.
25:52>> I.
25:53>> Opposed?
25:55The motion has no name.
25:56>> No name. No name. No name.
25:59>> All right, try.
```*