2026-10-06 - Board of Aldermen Special Meeting
Summary
Built from the city's posted agenda and minutes and the YouTube auto-generated captions of the hearing video. Approval status is not stated.
- The special meeting consisted only of public hearings on the capital bond resolutions; no votes were taken apart from adjournment at about 8:48 PM. Staff and consultants presented each project, and speakers for and against were heard on most. See Capital Bond Resolutions Fall 2026.
- R-26-059 ($3,000,000, wastewater treatment plant Phase I): concrete tank repair, resizing the chlorine bulk storage tank, septage receiving area changes and water meter replacement, required for permit compliance and paid from the self-funded wastewater enterprise fund rather than property taxes. A public works commissioner spoke in favor; residents asked for more backup and questioned the enterprise fund. See Wastewater Treatment Plant Phase I Upgrade.
- R-26-060 ($4,275,000, sewer infrastructure and casting replacement): the annual sewer repair, lining and casting program coordinated with paving, made up of $4,000,000 for sewer infrastructure and $275,000 for castings per the capital plan. No public testimony.
- R-26-061 ($2,550,000, various wastewater improvements): stormwater and combined sewer overflow work under the consent decree, infiltration and inflow reduction, sewer lining, levee repairs and secondary clarifier upgrades. Two public works commissioners spoke in favor; a resident asked about timing and suggested using surplus funds instead of bonding, and the engineer called the figures programming-level estimates.
- R-26-062 ($2,000,000, Four Hills Landfill): gas collection expansion and a $1,500,000 access road over the closed landfill for the new Phase 4 cell, emergency response and yard waste, saving about half an hour per truck trip. No public testimony.
- R-26-063 ($2,678,828, solid waste equipment): replacing four daily collection vehicles and a landfill excavator, with estimates that include possible tariff effects; purchases still need Board of Public Works and Finance Committee approval. No public testimony.
- The $5,000,000 pool resolution (the number is garbled in the captions; the Board's later votes list it as R-26-066): both Rotary and Centennial pools need full replacement per a September 2025 assessment, with leaking, failing liners and steel walls that cannot take another liner; work would be sequenced one pool at a time. One resident spoke in favor and others questioned the cost basis and bidding.
- R-26-072 ($43,500,000, DPW garage and fleet facility): the existing Stadium Drive garage covers only 67 of 268 registered vehicles, with structural, air-quality and hazardous-material concerns. The proposed addition of about 127,800 sq ft at 848 West Hollis Street would house about 170 vehicles. The guaranteed maximum price is $43.479 million ($314 per sq ft), and presenters said a five-year delay could raise the cost to $52 to $54 million. A commissioner projected $500,000 to $900,000 in yearly maintenance savings and about $14.7 million in equipment protected (presenter estimates). Commissioners spoke in favor; a resident questioned the total cost, tax impact and priority against a future fire station. See DPW Garage and Fleet Facility.
- R-26-073 (up to $3,183,200): not new debt but moving unspent, never-borrowed authorized funds from completed DPW projects to the garage project, kept as a separate resolution on bond counsel's advice; asked whether the funds could go to the pools, the administrative services director said transfers are limited to similar projects.
Agenda
Agenda PDF posted; see Sources.
Sources
- City meeting page: https://nashuanh.portal.civicclerk.com/event/7384/overview
- Agenda: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14727,plainText=false)
- Minutes: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14753,plainText=false)
- Agenda packet: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14728,plainText=false)
- Notice: https://nashuanh.api.civicclerk.com/v1/Meetings/GetMeetingFileStream(fileId=14652,plainText=false)
- Video: https://www.youtube.com/watch?v=MQC9s3L7BoI (Nashua Board of Aldermen meetings YouTube channel)
Video
Transcript
*These are auto-generated captions; names and numbers may be misheard.
Transcript
00:28All right.
00:30>> Put all the paper in the middle of the
00:32floor.
00:33>> Yeah.
00:58order on Tuesday, October 6, 2026 at 7
01:01p.m. in the aldermanic chamber, which
01:02has been duly noticed in two places,
01:05including the city's website in
01:07accordance with the requirements of RSA
01:0991A. The prayer will be offered by
01:12Alderman O'Brien and Alderman Johnson
01:14will lead us in the pledge to the flag.
01:20Almighty God, we have the high on and
01:22the serious duty to manage the affairs
01:24of our beloved city. Fill us, oh God,
01:28with a spirit of unity and understanding
01:30which enables us to face our multiple
01:33problems with a serene mind, with
01:35justice and charity for all so that any
01:38and all decisions made by us will always
01:41be for the betterment and greater
01:43happiness of all our fellow citizens. So
01:46help us God. Amen.
01:48>> Amen. I pledge algiance to the flag of
01:52the United States of America and to the
01:54republic for which it stands. One nation
01:58under God, indivisible, with liberty and
02:01justice for all.
02:10>> Let's start the meeting by taking a roll
02:12call attendance, please.
02:16Alderman Clemens here. Alderman Clay.
02:25Alderman Revan
02:26>> here.
02:28Alw Smith
02:30>> present.
02:31>> Alman Tebo
02:32>> here.
02:33>> Alderman O'Brien is present. Alman Greg
02:36>> here.
02:37>> Alderman Dow present. Alderman Sullivan.
02:48>> Alderman Senate.
02:55>> Alderman Johnson
02:56>> present.
02:57>> Automan Kelly
02:58>> here.
02:59>> Alman Morgan
03:00>> here. Alderman Lopez
03:06or President Wilshshire
03:08>> here.
03:09>> Okay.
03:13>> We don't have the mayor and corporate
03:16counsel.
03:20>> So we have 11 present.
03:22>> Yes, we do.
03:22>> Thank you.
03:23>> I'm sorry.
03:24>> Excuse me.
03:26>> Custom. I will turn the meeting over to
03:28Alderman Dow.
03:30>> All right. this
03:31>> for the zoom the video is off on the
03:33alder manic chamber. I don't know if
03:34that's intentional or usually that's on.
03:40>> If it is, I don't know how to fix it.
03:44>> See that little camera at the bottom
03:45left that says video slash? You think
03:48you can
03:50>> see if that does it? Oh, well, never
03:53mind.
03:54>> Got to be from inside there.
03:56>> We're going to go blind.
03:59We're AC tonight.
04:03Okay. This evening we have a public
04:05hearing on several
04:08uh resolutions.
04:09Um so I would ask that people keep that
04:12in mind when they're given testimony and
04:14asking questions. And the first uh
04:17public hearing we have this evening is
04:18on R26059
04:21authorizing the mayor and city treasure
04:23to borrow an amount not to exceed $3
04:26million through the issuance of bonds
04:29and or a loan through New Hampshire
04:31Department of Environmental Services
04:33state revolving loan fund for the
04:36wastewater treatment plant phase one
04:38upgrades project. Would you Yes. would
04:42you introduce yourself and give a brief
04:44overview?
04:45>> Yes, thank you. David Bush, wastewater
04:47superintendent. Uh so this is phase one
04:49of the wastewater's 20-year facility
04:51plan. Uh these projects are to renovate
04:55uh the items at the wastewater facility.
04:58also replace some items including
05:00concrete concrete tank repair, uh
05:03chlorine bulk storage tank resizing,
05:05septage receiving area modifications, uh
05:08also replacement of some uh needed water
05:11meters. Uh the upgrades for this project
05:15are all geared towards maintaining the
05:16existing infrastructure and meeting
05:19regulatory permit compliance as we are
05:21regulated by New Hampshire DEES and the
05:23US EPA. And uh I just want to point out,
05:26I know it's been brought up at other
05:27meetings, but for clarifications, this
05:29isn't funded through the taxes. This is
05:31uh the wastewater enterprise fund uh
05:34which are factored into the approved
05:35sewer rates.
05:37>> Thank you. Any uh amplifying questions?
05:41>> Thank you.
05:42>> Thank you.
05:44>> All right.
05:46I'll now call for testimony in favor of
05:48R26059.
05:52You have to come up to the mic.
05:57Thanks,
05:58Mr. Sheay.
06:00>> Thank you very much. Uh Paul Sheay,
06:02board of public works commissioner. I am
06:05coming here to speak in favor of of all
06:07of the public works related items
06:09tonight. I will not come up to speak on
06:12each of them. I do of course support
06:14this. Uh the wastewater treatment
06:16division is doing an excellent job
06:18making sure that we are keeping up with
06:20environmental concerns and there are a
06:22lot of areas for improvement in the
06:24facilities there. And so this is uh one
06:27one piece of that. Uh we have ongoing
06:30planning and process for further
06:32investment in wastewater treatment
06:34facilities which are all essential to uh
06:37treating the water and making sure that
06:39we treat the environment right.
06:42Thank you very much.
06:43>> Okay. And and before I go, I so I won't
06:46speak on all of these. I I will say that
06:48I'm in favor of them. Um and I'll I'll
06:51come back up when it comes time for the
06:52garage.
06:53>> Thank you.
06:54>> We'll note that.
06:56>> Others in favor?
07:01>> Lori Oralano Nasha. Um I just have a
07:03question on this the enterprise fund
07:06because this is wastewater. Um and it
07:08was stated that it doesn't uh involve
07:10taxpayer money. Is any part of the
07:12enterprise fund funded through the
07:15general fund? Do we is it totally 100%
07:18self-sufficient or does it require
07:20taxpayer money to cover the costs? I
07:23know we have some wastewater that bills
07:26that aren't paid for exactly how
07:30selfunded is it?
07:33>> Direct a photo. Do you want to handle
07:34that?
07:38>> Certainly. I I want to apologize for not
07:41being with you this evening. I uh
07:43nursing a bad cold. Um
07:46um yes, the answer to that question is
07:48it's it's a true enterprise fund and it
07:51is completely
07:53um funded by uh the wastewater fees.
07:59>> Okay. Thank you.
08:02Any other testimony in favor?
08:05Seeing none additional testimony and
08:07opposition
08:15name and city.
08:16>> Yes,
08:18>> my name is Bill Fo. My home is number 35
08:21Indian Rock Road. So, it's pretty
08:24obvious that all these resolutions are
08:26going to pass tonight. Um, they're all
08:28very worthy things to do and many of the
08:31aldermen have already endorsed them. So,
08:33a public hearing is kind of a moot point
08:35here, but um I am inquisitive. So, I
08:38will ask something. Um
08:41when the mayor introduced these
08:43resolutions the other night, he was
08:44sitting right there and he said, "This
08:46is a lot of money." He said that. So,
08:49you want to make sure you get it right.
08:51So, my question is or my disagreement
08:54with all this is why is there no basis
08:57for any of these numbers? There's no
08:58math. There's no explanation of the the
09:01um the process that was used to develop
09:03these budgets. There's no similar toss.
09:06There's no uh historical actuals.
09:09There's no quotes from suppliers.
09:11There's no I talked to this guy and I
09:13get this. There's no well I assume this
09:15and I applied a factor one. There's none
09:17of that in any of this. How can you do
09:19that? How is that even possible? How can
09:21you possibly
09:24uh accept this or deny it if you don't
09:27know whether the math is correct how it
09:31was developed? They may be very worthy,
09:34but if you don't see the math, you don't
09:36see the basis behind it. How can you
09:39know? Maybe, you know, Mr. Cummings
09:40likes to stand up a real time. Maybe you
09:42can ask him when he comes up to explain
09:45the basis be behind each one of these.
09:47I'm sure he did something to develop
09:49these numbers. I'm sure we just didn't
09:50pull him out of the right. So, can you
09:52ask him to please explain that? Thank
09:54you.
09:57>> Anyone else in opposition,
10:03>> Gloria Orano Nasha, I want to speak to
10:05the point that was just made because I
10:07reached out to an alderman to ask, "How
10:10do you know what you're looking at?" I
10:12mean, you did a ad hoc debt committee
10:14meeting at the end of June the 27th and
10:17all the projects were laid out, but the
10:19backup material wasn't there. Then we
10:22had the board packets come out last
10:24week. Total spending around $87 million.
10:28Nothing was in the board packet
10:29specifically supporting these. Now,
10:31we're here tonight with uh hearings for
10:34all of this spend. There's $66 million
10:37here to be spent tonight. There isn't a
10:39single piece of backup. John Sullivan
10:42said to me more than a week ago, I wrote
10:44to the administration and asked for all
10:47backup for all these bonds. I presumed
10:49it would be part of the board packet. So
10:51over the weekend when I looked at it and
10:53saw nothing. Yeah. How do I come out
10:56here and evaluate these numbers? And how
10:58do you I will tell you I reached out to
11:00Director Cummings to get the pool
11:03information because I could not wrap my
11:05head around $5 million for two pool
11:07renovations. And it was Turner Group who
11:09did it. And I can't wrap my head around
11:11that because I looked into Manchester
11:13bonds for pool renovations or
11:15expenditures. They didn't even bond.
11:18175,000 to renovate a pool. We have 5
11:22million for two pools. I can't wrap my
11:25head around this spending. And there's
11:27nothing here to justify it. And I think
11:30you do yourselves all short as agents
11:34for us and our the constituents when you
11:36don't have the backup. And then I have
11:38nothing to come here and go off of. You
11:42know, it's an awful lot of spending. I
11:43know when we come to the garage, I'm a
11:45hard no. The pool, I'm a hard no. These
11:47wastewater, which is project upgrades,
11:50how you built the 3 million, I have no
11:52idea. But at least it's been in the
11:54budget. I mean, but I I don't know how
11:58you expect us to intelligently question
12:00what you're questioning when you have no
12:02information. It's just amazing to me.
12:04And also some of these bond amounts 2.5
12:07million 2 million what was through ad
12:10hoc committee debt committee what was
12:12our decision on not bonding at a certain
12:15level we were going to try and use cash
12:18we finished the first first quarter of
12:202027 where do we stand on salaries where
12:22do we stand on employee cycles what was
12:25our spend rate do we have cash that we
12:27can cover some of these that we don't
12:28have to bond out 20 years and pay 3 4
12:315000 in interest to do what I call for a
12:35municipality fairly short money projects
12:39because all of this is bonded and next
12:41hearing you got a whole bunch of bonds
12:43that are a million dollars just a
12:45million. We weren't going to bond for a
12:47million. We got a lot of it. So I'm not
12:49I'm not supportive of that. But you know
12:52I'm here and I'm here totally blind and
12:54I feel somewhat ignorant because I don't
12:56have any data to to argue with you on
12:58what you're looking at for spending.
13:00Nothing. It was never published.
13:03>> Anyone else in opposition?
13:07Seeing no one, once again, testimony in
13:09favor.
13:12Seeing none,
13:14once again, testimony in opposition.
13:17Seeing none,
13:19I will now close the public hearing on
13:22resolution R26059
13:25at 7:13
13:27p.m. And I will open the public hearing
13:31on resolution R260
13:34at 7:13
13:36p.m. R26060
13:38authorizing the mayor and the city
13:40treasurer to issue bonds not to exceed
13:434,275,000
13:45for the city's sewer infrastructure
13:47improvement and sewer and drain casting
13:50replacement programs.
13:55Uh good evening, Dan Hudson, city
13:57engineer. Um um I represent uh DBW
14:00Engineering uh work closely with
14:02wastewater on these projects. Um so this
14:05is our annual bond request for sewer
14:07infrastructure and castings. Uh through
14:10this program we do all the pipe repair
14:12work, the pipe lining work um and
14:15investigation of those pipes. In
14:17addition, we replace broken castings uh
14:20through our paving program, but this is
14:21where the funding comes from for that
14:23work uh that's that's uh coordinated
14:26with the paving program. Um,
14:30basically, uh, with these bonding
14:32authorizations, then we go and we
14:33contract all the the work and, um, we
14:36don't know exactly what we're going to
14:38run into. We video pipes, we find
14:40things, we can fix things when we have
14:41this funding in place. U, but it's not
14:43not as simple as, you know, uh, one
14:46little defined project and we're bidding
14:47that out and here's the result of it.
14:49So, um, if we didn't have this money,
14:52uh, in place, then we wouldn't be able
14:53to do the things that we need to do to
14:54keep our system up to snuff and, uh, and
14:56be able to respond quickly to issues.
14:58So, be happy to address any questions.
15:00>> Any amplifying questions?
15:02>> Yes, Alderman Tibo. Thank you, Mr.
15:05Chair.
15:06>> How do you come up with that that that
15:08amount? Do some math for me.
15:10>> Sure. So, there's two aspects, and this
15:12comes from the CI uh P uh report as
15:15well, but um there's $4 million for the
15:20capital infrastructure, the uh sewer
15:23infrastructure improvement program, and
15:24then a different CIP, there was the sew
15:27drain sewer drain and casting re
15:29rehabilitation for $275,000.
15:32So, the net of those two is the total of
15:34this resolution.
15:36>> Followup. So that's the money that the
15:38company that's doing the work told you
15:40it's going to cost. Is that
15:42>> No, as I indicated, we do this
15:43resolution and then we'll bring
15:45individual contracts
15:47>> for approval. Right. Right. So uh this
15:50establishes the funding source that we
15:52have to be able to go out, hire the
15:53engineers, hire the uh the inspectors,
15:56hire the construction folks to do the
15:58work. Every one of those individual
15:59contracts come back comes back before I
16:01mean assuming it's within the purchasing
16:03policy, right? uh exceeding the uh
16:05$25,000 which almost everything is every
16:07single contract comes back for
16:08subsequent approval.
16:09>> If we didn't authorize this money now,
16:12you wouldn't be able to go do that.
16:13>> We couldn't go design and plan and and
16:15and implement these projects.
16:16>> Okay. Thank you.
16:17>> You're welcome.
16:18>> Any other amplifying questions?
16:21Thank you, Mr. Ludson.
16:24Okay. Okay, I'll now open up testimony
16:26in favor
16:27of R260.
16:33Seeing no one, testimony in opposition.
16:39Seeing none, once again, testimony in
16:42favor.
16:45Seeing none, testimony and opposition.
16:48Seeing none, I'll close the public
16:51hearing in R 260 at 7:16
16:55p.m. and we'll open the public hearing
16:58resolution R26061
17:00at 7:16 p.m.
17:05R26061
17:07authorizing the mayor and city treasur
17:08issue bonds not to exceed $2,550,000
17:13for various wastewater capital
17:16improvements.
17:18Again, for the record, Dan Hudson, city
17:20engineer. So, this is a host of, if I
17:22added up correctly, seven different CI
17:25uh C projects um CIP projects um uh
17:29totaled up into this one resolution. Um
17:32a variety of things. One's the annual
17:34storm water management abatement. So
17:35that's that's the money we use to do
17:37drainage improvements um throughout the
17:39city. CSO consent decree operational
17:42expenditures. Uh there was a consent
17:44decree from EPA and that that gives us
17:47the funding to uh address and uh follow
17:50through on all the commitments that were
17:51made as part of that. Um Cso flooding,
17:55everybody's familiar with what CSOS are.
17:57Uh uh and we try to eliminate those. Uh
18:00and we do that through making various
18:02improvements. again some some uh
18:04drainage and uh storm water separation
18:06projects. Infiltration inflow, that's
18:08the program where we try to eliminate
18:10clean water in the sewer pipes because
18:12we're paying to treat that, but yet
18:13we're not charging anybody for that
18:15because it's just leaking into our
18:16pipes. So, uh that's accomplished
18:18through through some some uh study to
18:21find out where we have it. And then uh
18:23also the lining program. Um we have a
18:26levy. We're required to continue to
18:28address any issues found on the levy
18:30that Army Corps identifies. Um, so
18:32that's funding for that. And then
18:35there's a couple other individual
18:36wastewater projects, secondary clarifier
18:38upgrades and exterior dock and tank
18:40coating that if you have specific
18:41questions, I'm sure uh, Superintendent
18:43Bush can answer that. But um, just a in
18:46summary, a totaling up of a number of
18:48various projects um, that we would like
18:51to get funded and be able to accomplish.
18:53So happy to address any questions.
18:54>> So this is the type of work that the
18:56federal government oversees and make
18:57sure that we do.
19:00>> Yes. Yes. So everything's permit driven.
19:01I mean uh we have storm water permits,
19:04we have uh permits for the the
19:06wastewater treatment facility and and go
19:08on and on and on. All these programs
19:10stem from those various permits. Um
19:12they're somehow uh tied in. You know,
19:15the city city has an integrated plan
19:17where we've gone through and evaluated
19:19all the permitting uh requirements and
19:21the projects that need to happen to uh
19:23stay in conformance uh in good standing
19:26in our with our permits. And this is
19:28kind of the follow of that. all these
19:30various programs kind of are aligned
19:32with those permit requirements.
19:34>> Amplifying questions.
19:40>> Seeing none.
19:41>> Thank you.
19:41>> Thank you. All right. Now, we'll open up
19:45R 26061. Testimony in favor.
19:55>> Hi, I'm June Lemon. I live here in NSHA.
19:58I'm a commissioner of public works. I
20:01want to say that wastewater
20:03is extremely important and as both uh
20:07superintendent Busher and our city
20:10engineer have explained, a lot of this
20:13is driven by permitting issues. We don't
20:15get to dictate to the state how much we
20:18do. The state gets to dictate to us what
20:21we do and then we have to pay for it.
20:24So, I'm in favor of these also because I
20:28like being able to turn my tap on, have
20:31clean water, and then flush my toilet
20:34and have it go away. So, I just see
20:36these as necessities. None of us wants
20:39to spend this kind of money, but this is
20:44what it costs. It's like, you know, my
20:46daughter works at Market Basket.
20:48Somebody came in with a basket full of
20:50stuff and said, she said, "This is, you
20:52know, $125."
20:54And the person said, "Well, I'd like to
20:56spend 80." And Lucy said, "But this is
20:58what the food costs. This is what this
21:01costs." Thank you.
21:03>> Okay. Any other testimony in favor?
21:11Commissioner Shane,
21:13>> I know I said I wasn't going to come up,
21:14but I was hoping. Um,
21:18Board of Public Works Commissioner Paul
21:20Sheay. I wanted to offer some insight
21:22for constituents here that a lot of
21:24these items um that have come before you
21:28tonight already have had some amount of
21:32discussion and review at the Board of
21:34Public Works. Uh there's a lot of
21:36information uh available as to what has
21:40been uh fleshed out conceptually uh what
21:43has come in in terms of bids so far. uh
21:47some of the items will come before us in
21:49the future. Uh the board of alderman
21:51will uh provide approval for the bonds
21:54and then the contracts relative to the
21:56items uh will uh either go out to bid um
22:00or or otherwise uh be reviewed and and
22:03determined uh who the the preferred uh
22:07local company is as I understand it.
22:09Sometimes there's uh contracts that that
22:12that that's the way that it works out.
22:15And I could I could misunderstand, but I
22:17believe I believe that's how it works.
22:18And and so um as these items progress um
22:23after funding is approved um there's
22:26always an opportunity for uh further
22:28constituent input at the board of public
22:30works. We're always glad to hear from
22:32you. As far as the uh wastewater items
22:36go, um we do very well here in Ashe in
22:41terms of our our wastewater rate. Uh
22:43there's a very detailed uh presentation
22:46on on how that works out and how it
22:48compares. Uh we are we're doing a good
22:50bit better than uh Manchester in terms
22:52of the cost of wastewater treatment and
22:55the the rate of pay that constituents
22:57have, wastewater customers have. Uh and
23:00and that information is also available
23:03Thank you.
23:03>> Okay. Any other testimony in favor?
23:08Seeing none additional testimony and
23:10opposition.
23:19Lori Ordano Nasha. I just want to
23:21understand a couple things with this
23:23one. Um,
23:25do we have the permits? Do we have the
23:27cost of the permits to do this uh
23:30wastewater work? Is that known already?
23:33Are we waiting for quotes on this or are
23:35we pretty certain of the amount the 2.55
23:38million?
23:42>> Mr. Hudson, do you want to answer that
23:43or?
23:49>> Again, these are more estimates in a
23:51programming level uh funding so that we
23:53we we know, okay, we have a million
23:55dollars to spend on drainage. then we
23:57can go and uh finish designing a project
24:00and put out the bid knowing that that's
24:01what we have to spend that type of
24:02thing. So, so no, we don't have the
24:05these these have come up every year kind
24:07of similar similar numbers. We tend to
24:09index this so for inflation so we can
24:11keep up but but these are more uh
24:13programming level items and then as
24:15where comes up that this is the funding
24:17that we use to do it. So, we have
24:19historical information to base our
24:23quotes on and we can only spend up to
24:26the value of what's approved in this
24:28bond and if there's money left over goes
24:30back.
24:31>> Correct.
24:31>> So, correct. Y
24:37>> Okay. And as we So, these you know, if
24:40they get authorized the middle of
24:41October, then they can proceed with the
24:43process of going out um to bid and get
24:46quotes. um what is that time frame to uh
24:51finally have um a vendor or a contractor
24:55selected and that process done? When
24:58would we actually begin working on these
25:02um projects? When can we anticipate a
25:05start time?
25:12>> I think that depends a lot on which uh
25:14which program you're talking about. Um
25:17we're we're we continue we're working
25:19year round, right? So uh each year we
25:21come and we ask for additional funding,
25:23but we're still spending down the
25:24previous year's funding and then
25:26starting this new funding. So it's it's
25:27kind of a continual process. Um there
25:30might be some individual one-off
25:31projects. For instance, on the levy, you
25:33know, we have a slide gate project that
25:35we need to do at some point, a repair or
25:36a uh replacement, and we're
25:38investigating that, but that might be an
25:40individual one. We might bring in a
25:41contractor uh um directly on that or we
25:45may bid bid bid something out. You know,
25:47we may need to bring somebody in to help
25:48us troubleshoot and figure out what we
25:49need to do. So, it really all depends. I
25:51mean, we we uh we do a vast amount vast
25:53amount of work every year and um um and
25:57this is the money that we do it with.
25:58So, if we want to keep up and stay with
26:00our permit requirements and everything,
26:01we need a funding source and this is the
26:03funding source.
26:04>> Thanks.
26:05>> Thank you. Um
26:08why can't we write these resolutions?
26:11Um given that this is an evolving
26:13process, it runs the year. Um the time
26:16when these come in is somewhat unknown.
26:18Um but it staggers through the year.
26:21Instead of saying that we're going to
26:22issue bonds, why don't we write these to
26:25issue bonds or use surplus money so that
26:29we're authorizing it both ways? because
26:32every year we run a surplus that's
26:35pretty large, like 30 million or more.
26:39Um, and the mayor always talks about
26:41this really healthy surplus we have.
26:43Since the whole idea of the ad hoc
26:46committee was to reduce bonding on lower
26:49level items, why not write these
26:52resolutions with an and or um option and
26:56then as it evolves, they have approval.
26:59It's either going to come through a bond
27:01or it's going to come through surplus.
27:03That'll come back to you to be
27:04evaluated. If they don't have the whole
27:07plan done and a vendor or contractor
27:09selected and quotes finished until like,
27:11you know, March or April of next year,
27:14you're going to know a lot about your
27:16budget at that process. Q1 is done. By
27:18Q3, you'll have a lot of ideas on what's
27:20going on here in your budget. And then
27:23you don't have to bond all this because
27:25you would have the time. I would like to
27:26see language that is andor and gives the
27:29option of using surplus funds instead of
27:31all the bonding. Just a thought. Thank
27:33you.
27:34>> Any other testimony and opposition?
27:38Seeing none testimony once again in
27:40favor.
27:42Seeing none, once again, testimony and
27:44opposition.
27:46Seeing none, I'll now close the public
27:50hearing and resolution R26061
27:52at 7:27
27:54p.m. And I will open the resolution the
27:57public hearing and resolution R26062
28:00at 7:27 p.m. R 26062 authorizing the
28:05mayor and city treasur to issue bonds
28:07not to exceed $2 million for various
28:10improvements at the solid waste
28:12department of four hills landfill.
28:17Jeff Laflur, superintendent of solid
28:19waste. So, uh, as stated, this is for a
28:22couple projects at the landfill. Uh, one
28:23of them is the gas expansion that I have
28:25to do every year. Uh, we have to put in,
28:27uh, gas system collection systems for
28:31the landfill to, uh, eliminate uh,
28:33emissions to the to the air. Uh, the
28:36other project is a $ 1.5 million access
28:39road that goes over the closed landfill.
28:41It's going to give us new access to the
28:43new phase 4 landfill. It'll give us
28:45quick access there in case of an
28:46emergency. Uh the state likes to see
28:49that in our operating permit that we
28:51will have proper access to our landfill.
28:54If there's ever a landfill fire, the
28:55fire trucks need to get there. This will
28:57also give me uh an opportunity to have
29:00access to the yard waste areas where my
29:02trash trucks drive to. Uh currently
29:05we're driving down the hall road going
29:07up over an active landfill all the way
29:09around the back of the landfill and you
29:11know doing unneeded damage to trucks
29:14that don't have to go out to the
29:15landfill. They can go right over this
29:17new access road, have quick access, dump
29:20their loads and get back out on the
29:21road.
29:22>> So I understand the state approved the
29:24building of this road.
29:25>> Yes, sir. It's been engineered and the
29:27state gave me an operating permit to do
29:29this project. And I'm sure you have the
29:30engineering expertise to get a solid bid
29:33on what it costs for the road.
29:35>> Absolutely. That's why I
29:36>> And you have a lot of historical data on
29:38the collection system.
29:40>> Absolutely.
29:40>> Any amplifying questions?
29:43>> Yes, Alvin Morgan.
29:45>> Uh thank you. Uh I love that you had
29:48mentioned about that length of time and
29:51giving us really kind of what that looks
29:52like. Can you give us an idea of how
29:56much manpower time we are saving on any
29:59given day with them not having to do
30:01that
30:02>> that same drive
30:03>> to driving up front? I mean, we're
30:05saving uh half an hour of time probably,
30:08you know, by the time they go out to the
30:10landfill all the way around the back.
30:11It's a 300 acre landfill. So, it's a
30:14mile probably a long drive to go out
30:16back to dump and then another mile back.
30:18I mean, and you're again, the wear and
30:20tear for the vehicle is going up over an
30:22running landfill right now.
30:24>> Follow up.
30:25>> So,
30:27I'm trying to paint the picture for
30:28people of what this looks like. So,
30:31>> half an hour per trip, per truck,
30:35>> and how many trips on a really full
30:37trash day do they make?
30:38>> On a real on a a big day when we're
30:40picking up 100 tons a day on yard waste,
30:43they could go out two or three times a
30:44day.
30:44>> Yeah. And how many trucks do we have?
30:46>> Four to five. Thank you.
30:49>> Okay. Any other amplifying questions?
30:53All right. I'll now open it up for
30:54testimony in favor of R 26062.
31:00Seeing none,
31:02testimony in opposition.
31:05Seeing none,
31:08testimony in favor once again.
31:11Seeing none, once again, testimony in
31:13opposition. Seeing none.
31:18I will close the public hearing at R262
31:22at 7:31
31:25p.m. And at 7:31, I will open the public
31:28hearing on R263
31:31authorizing the mayor and the city
31:33treasur to issue bonds not to exceed
31:362,678,828
31:39for the purchase of a solid waste
31:41capital equipment.
31:45>> Good evening. Michael Rush, Fleet
31:46Superintendent. This bond resolution is
31:49to replace five pieces of equipment at
31:51the solid waste facility. Four of them
31:53are daily use collection vehicles for
31:56trash, yard waste, and recycling, and
31:58one is an excavator for the landfill.
32:01Um, these assets have been evaluated by
32:03the fleet department and are deemed to
32:05be close to end of life. So, we're
32:07seeking approval to go through the
32:09process to purchase new ones to replace
32:11them.
32:11>> And all of these are listed in the
32:13resolution itself. I believe they are.
32:16Yes.
32:16>> Yes.
32:18>> Okay. Any amplifying questions? Alderman
32:20Greg.
32:21>> Thank you. How often do these have to be
32:23replaced? Like end of life. How many
32:25years did that
32:26>> uh seven 7 to 10 years depending on the
32:29type of equipment? Um, we do move some
32:31trucks to the back line so that we have
32:33some reserve pieces for when we have
32:36downtime for scheduled maintenance,
32:38annual uh natural gas inspections
32:40because that is required under the
32:41federal government for the natural gas
32:43vehicles for over the road. Um, you
32:46know, they're a little dirty. They see
32:49salt just like all the other trucks in
32:50the city. So, if we could keep that off
32:52them, you know, we might get a little
32:54bit longer life out of them at times.
32:56Okay,
32:57>> all set. Um, just one other thing. And
32:59these are all in surf, right? They're
33:01surf vehicles,
33:02>> correct,
33:03>> Alderman Tibo?
33:04>> Yeah, I think that was partly Thank you.
33:05That was partly my question, I guess, is
33:08these ones have all fall on fell on the
33:10schedule they're supposed to fall on,
33:12right?
33:12>> Correct. They are scheduled on the surf
33:14purchase list.
33:15>> Perfect.
33:16>> Any other questions?
33:18>> Yes, Alman Ran.
33:20>> Thank you, Mr. Chairman. Given that some
33:22of these numbers are accurate to the
33:24dollar, are these actuals or estimates?
33:26>> Uh, this is an estimate. Um, it's kind
33:30of hard. Some of these vehicles, some of
33:32the parts come out of Canada. Um, so
33:34this number is based on the potential to
33:36have a tariff increase
33:39and it's based on us talking to our
33:41vendors, seeing what those numbers look
33:43like.
33:43>> So, it's a calculated estimate.
33:45>> It is a calculated estimate.
33:47>> Thank you.
33:47>> And the authorization will still have to
33:49go through finance for final approval
33:52and account to buy them, right?
33:53>> It'll have to go through the board of
33:54public works and then through the
33:55finance.
33:56>> Finance. Any other questions?
33:59Thank you. Seeing none, I'll open up
34:02testimony in favor of R 26063.
34:07Seeing none, testimony in opposition to
34:09R 26063.
34:13Seeing none, once again, testimony in
34:15favor of R 26063.
34:18Seeing none, once again, testimony and
34:21opposition R 26063.
34:24Seeing none, I will close the public
34:26hearing on R26063
34:28at 7:34.
34:31And at 7:34, I will open up the public
34:34hearing on R2606,
34:36authorizing the mayor and the city
34:38treasured issue bonds not to exceed $5
34:40million for the repair and renovation of
34:42two public inground swimming pools.
34:50>> Good evening, Brian Conit, your park
34:51superintendent. Um this is to replace
34:55two pools. Um we have Rotary Pool which
34:57was built in 1973. We have Centennial
35:00Pool um that the Turner Group believes
35:02was built in 1960. I do have a
35:05historical synopsis made from an old
35:08wreck uh superintendent null troutier
35:10from 1895 to 1975 that said the pool was
35:14installed in 1948 on Sergeant F. So I
35:18don't know which is true. We had an
35:20assessment done in September 17th of
35:222025 that stated both pools need to be
35:26replaced. Um they've had liners put in
35:29them both of them. Both liners need to
35:32be replaced. We've had leaking issues at
35:33both of the pools. Um talked to the
35:37vendor that replaced the liner back in
35:392018 at Centennial Pool and he said,
35:41"You won't be able to do it again. the
35:43steel walls behind the vinyl wall um or
35:46the vinyl liner cannot be used again. Um
35:49that's how decrepit they are. I'd like
35:51to mention on how heavily the pools are
35:54used. Um
35:57you know, I'm I'll sit here and say that
35:59I think it's a great benefit to the
36:01community. Is my favorite part of being
36:03the superintendent of the parks
36:04department? No. It take a lot of time, a
36:08lot of money, but when I go there and I
36:10see the benefit that the community gets
36:12out of it, I change my mind completely.
36:15I'd be happy to answer any questions on
36:17this if there are.
36:17>> And just for clarification,
36:19this is for two pools. We're not doing
36:21them at the same time. We're going to do
36:23one we thought we were going to do in
36:25the fall, but looks like spring and then
36:27the next one possibly next fall. So, all
36:29the funds won't be spent at one time.
36:31And this is to replace the pools. not
36:35really repair them.
36:36>> We're going to be advertising the bid to
36:39replace Rotary Pool. And that is a great
36:41point, Alderman Doubt, is that we're not
36:43re rating these pools there beyond that
36:46point. This is a total reconstruction,
36:49which is why the cost is so high.
36:52>> Debo.
36:53>> Thank you, Mr. Chair. So, I got a couple
36:55questions, uh, clarifying questions. Um,
36:58so
37:00if you don't fix or if you don't replace
37:03these,
37:05how long will they last being able to be
37:07used? Like when would they have to be
37:08shut down for good?
37:09>> Alderman Tibo, I I don't have a crystal
37:11ball, but I know that Rotary Pool loses
37:15somewhere from 2 to 4,000 gallons. um
37:18let's say every two days and the liner
37:21at Centennial Pool is bubbling off the
37:24steel walls now as we speak. I don't
37:28know at one point they will become
37:30unusable but we are close.
37:33>> Okay. Um and the other one the other my
37:36other question is during public comment
37:38uh it was kind of scoffed at that they
37:40would cost 5 million. So 2.5 million to
37:43replace each pool. Is that an act? I
37:46mean, is that how much it costs to to do
37:48a pool these days?
37:50>> It says right here, I brought the
37:52assessment that was done back in 2000 uh
37:55or September of 2025, excuse me.
37:59Uh as discussed, it is likely that both
38:02replaced pools will be of similar size,
38:04depth, and a perimeter of concretes that
38:05are both similar as what's there. It is
38:08therefore our opinion that the probable
38:09construction of cost for each pool is
38:11expected to be in the range of $2.5 to
38:13$3 million in 2025. I bring that to
38:17everyone's attention too because we all
38:20know prices have gone up. Um and to
38:24speak to H&L Turner, they've replaced
38:26three pools for the city of conquered
38:28and they've also done work for the city
38:29of Manchester as well. Um so I don't
38:32know if that answers your question, but
38:34I'd be happy to answer anymore.
38:35>> Yeah. Thank you. set.
38:40You all set? Director photo, you didn't
38:41want to add anything.
38:45>> I'm all set. Thank you. I I wanted to
38:47add the engineers estimate from HL
38:49Turnover.
38:50>> The superintendent added that.
38:52>> All right. Thank you.
38:54>> We're all set.
38:56>> Thank you.
38:57>> All right. I'll now open up testimony in
38:59favor of R266.
39:13that you Commissioner Shay or your son
39:24introduce yourself.
39:26>> My name is Paxton.
39:29Uh,
39:32and I live in Nasha.
39:37And
39:40I don't really know what to say.
39:42>> Do you want to share your experience?
39:44>> Do you want to share your experience at
39:46the pools and and what it means to you?
39:49>> Yeah.
39:51I went to I don't know the name of the
39:54pool, but I went to one of these pools
39:56once and then it was really fun.
39:59and then
40:01>> centennial pool
40:04>> and I went there with my friends
40:09and then we had
40:12a picnic after I think I remember I
40:17remember and then
40:22>> what is it what does it mean to get
40:23stable
40:24>> it's fun
40:28>> do we have a pool at home?
40:31>> Not at our house.
40:33>> Yeah. No, but we do go to pools.
40:36>> Yeah.
40:37>> And And what does it mean to kids who
40:40don't have pools to be able to have a
40:42pool in the summer?
40:44>> Good.
40:45>> Yeah. It it means a lot to kids. Can I
40:48Can I join you?
40:49>> Yeah.
40:50>> Uh it means a lot to kids in our
40:52community to have access to a place to
40:54swim. Um, not everyone is so blessed to
40:58have a pool at their home and it's a
41:00place where kids gather and have fun and
41:02spend time in the sun and then maybe
41:04have a picnic afterwards
41:06and this is one of the best investments
41:09that that you're considering.
41:12>> Thank you.
41:13>> Anything else?
41:17>> Super fun.
41:19>> Thank you very much.
41:20>> All right.
41:21>> Good job.
41:24>> All right. So now still in testimony in
41:27favor
41:29seeing none additional testimony and
41:31opposition
41:39Lori Ordano Nasha um understand all the
41:43community benefits to having a pool. I
41:45really do believe in them and I think
41:47they're vitally important to our city
41:49and our kids in the summertime who don't
41:51have other activities. I don't question
41:54that at all. This is not really written
41:57correctly because it calls for repair
41:59and renovation and I think it should be
42:01the full construction of two new pools.
42:05They're going to be um reconstructed
42:08pools. Um I still question I saw the
42:11quote from the Turner group from 2025.
42:15Um that was one group. Have we gone out
42:18to bid with others? I am still very
42:21concerned about five million for two
42:23pools. I really am. And now maybe it's
42:25going to be six or seven to construct
42:28two swimming pools for a city. I think
42:31that's enormously expensive. And I would
42:34hope we would gather some bids and take
42:36a close look at that. Um, you know, I'm
42:39not doubting that they need it based on
42:41the age. Totally makes sense. But, you
42:44know, I'm really concerned when I see
42:46project cost the next one coming in. You
42:48know, I think our city and cities in
42:51general end up falling prey to some very
42:53high contractor costs because we don't
42:56necessarily have building construction
42:59contractor teams within the city to
43:01evaluate these. And we pay a lot. We pay
43:04a lot more than private business pays, I
43:07believe. Um, and I can tell you my
43:10husband constructed one heck of a big
43:11160,000 foot facility in South Carolina
43:15for heavy equipment with cranes and
43:17machinery for $20 million. Um, and so I
43:21I understand big projects, but we pay a
43:25lot as a municipality and I think we're
43:28not getting competitive pricing often on
43:30some of these big projects, which um,
43:33you know, I I I think we need to do a
43:35much better job and lean in much harder
43:38with developers when it comes to cost.
43:39So that's my concern with R266.
43:43Thank you.
43:44>> Any other testimony in opposition?
43:53My name is Bill Fero. My home is number
43:5535 Indian Rock Road. So, thank you to
43:58the DPW guy that stood up and talked and
44:01gave basis for the $5 million. But it
44:04sounds like, if I understood the math
44:06correctly,
44:072.5 to 3 million in 2025
44:12doesn't equal 5 million in 2027.
44:15So, don't you think maybe this should be
44:186 million, 6 and a half million?
44:21Thank you.
44:24Any other testimony and opposition?
44:28Not seeing once again testimony in
44:30favor.
44:32See none additional. Once again,
44:35testimony and opposition.
44:37See no additional, I will close the
44:40public hearing on R266
44:43at 7:44
44:45p.m. and at 7:44 p.m. I will open up our
44:50the public hearing on R26072
44:52authorizing the mayor and city treasurer
44:54to issue bonds not to exceed $43,500,000
45:00for the design, construction, and
45:02equipping of a division of public works
45:05garage and fleet maintenance facility.
45:08Director Cummings.
45:10>> Yes. Thank you, Mr. Chairman. For the
45:11record, Tim Cummings, director of
45:13administrative services, uh, here this
45:15evening to to speak uh, relative to
45:18R2672
45:20and it goes handinand glove with R2673,
45:24I'm going to ask that the PowerPoint
45:26presentation uh, get uh, brought up this
45:28evening and um, as as that PowerPoint
45:31presentation gets gets brought up um,
45:33and and before we recognize Director
45:36Photo who is going to be um, uh,
45:39introducing the the the the conversation
45:41and and presentation this evening. Do
45:44want to note for the record that we have
45:46um our uh treasur tax collector Diane
45:49Mahaland on this evening and she's
45:51participating remotely. So I want to
45:52make sure everyone is aware of that in
45:54case a question arises and I want to
45:56thank her for for being here. uh behind
45:59me after director photo speaks it will
46:01be handed off to the various consultants
46:03who will speak to the the differing
46:05elements of the of the presentation that
46:08is that is before you and their slides
46:10and and finally uh uh Mr. Chairman, I
46:13want to note that um everything that
46:15you're uh hearing about this evening,
46:17but specifically these two resolutions
46:20uh that are being laid before you uh
46:22follows and adheres to the hard work
46:24that we did and build up to this evening
46:26through the ad hoc uh process. And so I
46:29think that's a a significant point that
46:31we want to make sure we note for the
46:32record. We are not deviating from plan
46:34and everything that we've anticipated
46:36along the way. we have been working
46:38towards this evening um and building
46:41momentum and and also it should be noted
46:43that this project is uh a project that
46:46is good in good standing before the
46:48joint committee on the board of uh uh uh
46:51public works and in infrastructure and
46:53and there is monthly meetings where a
46:55lot of this project is discussed in in
46:57detail. So, with those comments being
46:59said, I'm going to ask uh director photo
47:02to to uh lead us uh this evening and I
47:05will be clicking the slides as
47:06necessary. So, I just ask that she says
47:09next so I can move it on appropriately.
47:11>> Also, I wanted to mention that uh
47:13Commissioner DPW Commissioner Greg is
47:15online with us from California. So, as
47:19well, Director Photo.
47:22>> Yes. Thank you. Good evening. Lisa
47:24photo, director of public works. On
47:26March 23rd, we provided the board of
47:28alderman with a presentation of the DPW
47:31garage. Since that was six months ago,
47:34we thought it made sense to provide a
47:36condensed version of that presentation.
47:39Joining me as presenters this evening
47:41are Commissioner Greg Mattie Greg,
47:43administrative services director Tim
47:45Cummings, Joe Sullivan the city's owner
47:47project manager from left field, Jeff
47:50Albertie, president of Weston and
47:52Samson, Rob Pruner, executive president
47:55of Harvey Construction and Scottlair CEO
47:58of Fitz Meerachi. I also want to note
48:01that our architect Jet Senna from HKT uh
48:04is also present. The picture on the
48:07screen that you see right now is more
48:10than half of the city's public works
48:12staff who build and maintain our city's
48:14infrastructure. The DPW garage and
48:17maintenance facility that we're
48:19discussing tonight is not about building
48:20a nicer garage for city employees. It's
48:23about protecting equipment that the
48:25taxpayers of Nashville already own and
48:28providing a healthy and safe work
48:29environment for our public works first
48:31responders.
48:33Today, the city maintains a public works
48:36fleet of 364 vehicles and equipment. 268
48:41of those are registered vehicles where
48:43and all of that 364 vehicles and
48:46equipment is worth about $45 million.
48:49These are the vehicles and equipment we
48:51use to plow, sweep, maintain roads,
48:53sidewalks, traffic lights and parks,
48:56fill potholes, pick up trash, respond to
48:59sewer backups, respond to emergencies,
49:03etc.
49:04Right now, 67 of 268
49:07or two 25% of registered vehicles are
49:10stored inside, leaving 201 registered
49:13vehicles in snow, ice, rain, and extreme
49:18cold and heat because our current
49:19streets garage was built nearly 50 years
49:22ago, is crumbling, and no longer meets
49:25the needs of our division. A modern
49:28facility would allow 170 registered
49:31vehicles or 64% of the registered
49:34vehicles
49:35to be kept indoors which will reduce
49:38breakdowns, extend vehicle life and
49:41improve response times during storms and
49:43emergency. It also creates a safe,
49:46healthy working environment for the
49:48employees who are out plowing streets at
49:502:00 in the morning.
49:53Public Works has been a good steward of
49:55tax dollars, saving millions over the
49:57years on such projects as the skate
49:58park, Main Street sidewalks, Adon Park,
50:02the landfill recycling buildings, just
50:04to name a few. We don't ask for a lot,
50:07and when we do, we need it. The garage
50:10and fleet maintenance facility is about
50:12the reliability of essential city
50:14services, safety, and long-term
50:16financial responsibility. It ensures
50:19that when residents need our services,
50:21the equipment required to do that work
50:23is ready and dependable. And with that,
50:26I'd like to turn it over to Jeff
50:28Albertie from Wesson and Samson.
50:39Well, good evening. My name is Jeff
50:40Albertie. As uh Lisa indicated, uh I'm
50:44president of West and Samson and I
50:46appreciate the opportunity to present to
50:47you this evening and uh I had an
50:50opportunity opportunity to present to
50:51you back in March on this project. And
50:53during that presentation, I spent quite
50:55a bit of time uh outlining the
50:57deficiencies in the existing facilities
51:00uh at the Stadium Drive site. But this
51:02evening, what I wanted to do was provide
51:04a highle summary of those deficiencies.
51:06I think that's important to set the
51:07stage for why the city needs this
51:09facility. Um and then from there we'll
51:12talk about the proposed facility which
51:13will address these deficiencies and
51:15provi pro provide the city with a new
51:17and safe facility for the division of
51:20public works and the community as a
51:22whole. So the first deficiency and I'll
51:25show you some photographs of what we
51:26observed through an independent
51:28evaluation of the existing conditions
51:30but the first was really related to the
51:32inadequate storage for the DPW fleet.
51:35the DPW fleet, which is one of the
51:37largest investments in vehicles and
51:39equipment that the city has made, and
51:41the DPW does their best to protect that
51:42equipment by storing as much equipment
51:44inside as possible. However, because the
51:47facility is wolffully undersized, that
51:50equipment has to be stacked in like a
51:52can of sardines, as you can see in the
51:54photograph on the right. And this not
51:56only makes it difficult to navigate the
51:58building, but it also makes access
52:00unsafe and inefficient for the staff
52:02when they're trying to access that
52:04equipment or move it out to uh respond
52:06to the needs of the community.
52:09Because the existing facility is
52:10undersized as uh as the director
52:12indicated, more than 80% of the fleet is
52:15forced to be stored outdoors, exposing
52:17this multi-million dollar fleet to harsh
52:20winter conditions, which in turn impact
52:22vehicle life expectancy. It increases
52:24maintenance costs. It contributes to
52:26operational inefficiencies and exposes
52:29the employees to unnecessary safety
52:31issues when accessing accessing this
52:33equipment in severe weather.
52:38Similar to the vehicle storage area, the
52:39fleet maintenance area. This is the area
52:41responsible for maintaining this
52:43critical first responder DPW fleet. This
52:46area is undersized for today's equipment
52:48and fleet maintenance operations. This
52:50negatively impacts the safety and
52:52efficiency for the fleet maintenance
52:53staff. And as you can see from the
52:55photos in the bottom right, there is
52:56little to no room to move around this
52:58equipment to perform the regular and
53:00emergency maintenance activities that
53:02are needed to maintain this fleet.
53:06This is a view of the break room that
53:08exists at the existing site. And the
53:10break room is the only space, this
53:11particular break room is the only space
53:13available to support up to 45 staff on a
53:16regular basis. And if you look at that
53:18photograph and you start counting up the
53:19chairs, you'll see that uh that that
53:22space is significantly undersized for
53:23that 45 those 45 staff. But what makes
53:26it a lot worse is that during a storm
53:28event, this room needs to support
53:29upwards of 75 staff who could be here
53:32for a 24-hour or 48 hour uh storm event.
53:36So clearly this space is in is
53:38inadequately sized. And what happens is
53:39the staff are forced to actually take
53:42breaks in the vehicle and equipment
53:43storage area, that first photograph that
53:45I showed you. So, you can imagine it's
53:47an unsafe condition and has uh very poor
53:49air quality for staff to be taking
53:51breaks.
53:52I also had an opportunity to take a look
53:54and inspect the mechanical systems or
53:57I'll say the lack thereof in the
53:59existing facility. The first photo shows
54:01a very old and outdated boiler system
54:04and adjacent to that is some of the
54:06heating components or what's left of
54:08them. This equipment is old and in many
54:10in many cases not operational. And I
54:13also spent some time when I was walking
54:15through the facility to look for the
54:16ventilation system. When you have that
54:18equipment stored inside a storage
54:20graduate, it's important to have a
54:22proper ventilation system to exhaust the
54:24fumes. And uh based on my observations,
54:26the building does not have a functional
54:28ventilation system. In fact, the really
54:31only ventilation system is to open up
54:33the overhead doors to allow fresh air
54:35in. And while that may be okay in the
54:38warmer months, you can imagine in the
54:40winter months, uh that is uh definitely
54:43not uh energy efficient.
54:45And with regard to the structure itself,
54:47in the last photographs in the bottom
54:48right at the stadium drive facility, the
54:51city had an independent building
54:53envelope evaluation completed by D21
54:55architects in November of 2025. Uh this
54:58study determined that the envelope
55:00showed clear signs of extensive
55:01deterioration and widespread material
55:05failure throughout. And the photos in
55:07the bottom right show some of the
55:09systemic envelope cracking and
55:11significant corrosion that's impacting
55:13the integrity of this existing building.
55:17And finally, one of the other uh aspects
55:19that was um evaluated was an independent
55:22assessment uh hazardous materials and
55:24identification study which was also done
55:26in October of 2025 by Universal
55:29Environmental Consultants. And based on
55:31those observations uh that building uh
55:33has issues with asbestous, PCBs, and
55:36lead paint. And furthermore, the air
55:38quality tests that were completed within
55:40that building identified elevated levels
55:42of carbon monoxide as well as total
55:44volatile organic compounds, both of
55:47which present potential health hazards
55:49and safety concerns for staff working
55:51within the existing facilities. So in
55:53summary, the existing facility is
55:55undersized for current DPW operations
55:58and the building systems and the
55:59envelope have exceeded their useful
56:01life. And these deficiencies contribute
56:03to inefficient and unsafe working
56:05conditions while providing inadequate
56:07protection for the city's substantial
56:09investment in the DPW fleet. So that
56:12helps to set the stage. I know it's a
56:14little bit on the negative side. So, I
56:15want to turn it to the positive side and
56:17talk about what is going to be provided
56:20at a high level overview of the proposed
56:22garage and maintenance facility addition
56:24at the West Hall Street site, which will
56:26address all of these deficiencies that
56:28we just discussed and provide a safe and
56:30efficient facility for DPW staff while
56:33protecting a large portion of the city's
56:35DPW fleet. This image here is an aerial
56:38photograph showing the existing DPW site
56:41located at 848 West Hollis Street. And
56:44you can see in the center, this is a
56:46view of the existing DPW offices. And
56:49what's being proposed is a an addition,
56:52a garage and maintenance facility
56:53addition to the back of that building
56:56shown here with a white outline. It's
56:58100 approximately 127,800
57:01ft² addition. It includes ancillary
57:03support site uh site items such as
57:06employee parking, assault storage
57:08structure, as well as the circulation to
57:10access in and around that building.
57:13This is a blowup of the proposed floor
57:15plan and I just wanted to highlight some
57:17of the main components of the building.
57:19There are really three main components.
57:20The first is the vehicle storage and
57:22operations area. This is the area shown
57:25in green as well as beige. This space is
57:28a significant step up from what exists
57:30today. In fact, the current facility can
57:33only house, as was mentioned earlier, 67
57:35pieces of equipment. And as you saw
57:37them, they were jam-packed in. Under
57:39this new uh scenario, under this new
57:41proposed plan, this new facility will be
57:43able to house 170 pieces of equipment.
57:46And the new facility will not only
57:48protect the equipment and help extend
57:49its useful life, but it will also
57:51provide organized and accessible storage
57:54that allows the staff to safely and
57:56efficiently access that equipment,
57:58improving the overall operational
58:00efficiency of the DPW.
58:02The next area is the fleet maintenance
58:05area, which is the L-shaped area shown
58:07highlighted in blue. This new area will
58:10provide fleet maintenance staff with a
58:11safe and efficient workplace, uh, which
58:14in turn will help to protect the city's
58:15investment in their vehicles and
58:17equipment through improved maintenance
58:19operations. This will improve fleet
58:22reliability, making sure the DPW has the
58:24resources it needs to reliably serve the
58:26community.
58:31The uh the third and final area that I
58:33just wanted to touch on is the wash bay.
58:35And we heard a little bit about vehicles
58:37that need to be replaced because of the
58:38how they're exposed. Uh so the wash bay
58:41is the light we call it a light red
58:43highlighted area to the right, the
58:45appendage off of the uh green storage
58:47area. And this new washbay will allow
58:49the DPW to properly clean and maintain
58:52vehicles and equipment, particularly
58:54following winter operations when they're
58:56exposed to road salt and other corrosive
58:58chemicals. This will help protect the
59:00city's investment in the fleet while
59:02also providing a dedicated location to
59:04appropriately capture and manage any of
59:06the wash water. In the bottom right, the
59:09blue box there, that's a proposed new
59:11salt storage structure about 10,500
59:13square feet that'll store salt product
59:16that's used to maintain the streets for
59:18safety throughout the city. And in the
59:20upper right is a city-wide automatic
59:23vehicle wash that's being shown. This
59:25particular feature is not included in
59:28the current design, but planning has
59:30been made to potentially accommodate one
59:32in the future. So, it's being shown on
59:33the plan.
59:35So, let's take a quick look at the
59:37overall massing of the proposed
59:39addition. The red arrow represents a
59:41view looking towards the proposed
59:43addition. And the next few slides will
59:45show the building elevations as well as
59:46some 3D rendering views from the street.
59:49And one of the strengths of the design
59:51is how it works with the existing
59:53topography and the natural vegetation
59:55buffer to create a facility that really
59:57fits well within the site and its
59:59surroundings.
1:00:01So this first this first view is along
1:00:03the west elevation which faces West
1:00:05Hollis Street and you can see the
1:00:07two-dimensional building elevation in
1:00:09the bottom and if you look where the
1:00:12text appeared there you can see the
1:00:14existing DPW offices and behind those
1:00:17DPW offices is the vehicle storage and
1:00:19vehicle operations area. So using the
1:00:21topography and the natural vegetation,
1:00:23I'll show you in a moment that DPW is
1:00:26able to really construct this facility
1:00:29in a way that uh really has no visual
1:00:31impact. This is a view looking uh from
1:00:34the entrance in front of the DPW office
1:00:36area. And you have to look real hard to
1:00:38see the building further in the
1:00:40background.
1:00:44Uh this next view is on the left side.
1:00:46This is of the north elevation. This is
1:00:50a view from the recycling center. And so
1:00:52again, you can see the DPW offices on
1:00:54the right. You can see the topography,
1:00:56the darker line, how it steps down. So
1:00:58the design team used that to help
1:01:00control the overall massing. And behind
1:01:02the or to the left of the offices, you
1:01:06can see the vehicle storage area. And to
1:01:08the left of that is the vehicle
1:01:09maintenance, fleet maintenance. And so
1:01:12similarly, if you look at a photograph
1:01:14with that overlaid on a view from the uh
1:01:17West Hall Street, you can see just a
1:01:19portion of the existing DPW offices and
1:01:21a very small portion of the vehicle
1:01:23storage area. So really fits in well
1:01:25with the surrounding area.
1:01:27So in closing on my piece of the
1:01:30presentation, I just wanted to talk
1:01:31about uh the benefits. And I say this
1:01:35often when I talk about uh new
1:01:36facilities like this is I could probably
1:01:38spend a whole hour just talking about
1:01:39the benefits, but I won't do that this
1:01:41evening. I'll just provide you the
1:01:42highlights. Um, and number one and first
1:01:44and foremost, it provides a code
1:01:47compliant, OSHA compliant, and safe work
1:01:49environment for city employees. It'll
1:01:52protect the city's multi-million dollar
1:01:54investment in their vehicles and
1:01:55equipment by putting a large portion of
1:01:57the fleet undercover. It's going to
1:01:59provide a much more modern fleet
1:02:01maintenance area, improving uh
1:02:03maintenance and safety and efficiency
1:02:05operations.
1:02:07uh all of the spaces will make public
1:02:09works uh much more efficient and respon
1:02:12in turn you'll have better response
1:02:14times to serve the public and putting
1:02:16the equipment and protecting that
1:02:17equipment indoors will reduce fleet
1:02:19maintenance costs as well as unscheduled
1:02:21maintenance activities
1:02:23and as I've shown you from the
1:02:25conditions of the existing facility by
1:02:27constructing this facility eliminates
1:02:29the need to invest money and band-aids
1:02:31for the existing substandard facility or
1:02:34replace a facility that gets mandated
1:02:36due to the current conditions that exist
1:02:38there today. So, at this point, I'm
1:02:40going to turn it over to Rob to talk
1:02:41about the budgeting process.
1:02:49Good morning, folks. Good evening,
1:02:51folks.
1:02:53Good morning soon, though. Um, my name
1:02:56is Rob Pruner. I'm with Harvey, and I
1:02:58appreciate the opportunity to come speak
1:03:00with you tonight and briefly explain how
1:03:02we arrived at tonight's GMP. Um, as you
1:03:06can see, back in 2021,
1:03:09there was a concept that was developed
1:03:10and that was a blue sky. Everything's
1:03:12perfect. How what's the program going to
1:03:14look like and how much it's going to
1:03:15cost? And that was roughly at that $66
1:03:18million range back in 2021.
1:03:21As things evolved, um, the DPW and the
1:03:24team understood that that that was way
1:03:26beyond the city's means in terms of
1:03:28being able to financing that kind of
1:03:29facility. So they had to work on on
1:03:31reducing the program yet still being
1:03:34able to service the city in many
1:03:35different ways. Um so we we took the
1:03:39taking another step back. We did take a
1:03:41look at what it would cost to to
1:03:43renovate um this the existing building
1:03:46on Stadium Drive. And it used to be
1:03:49years ago that it was less expensive to
1:03:51renovate than it was to build new. And
1:03:53that has changed now. Now it's just as
1:03:56expensive to build to renovate as it is
1:03:58to build new. except for the the
1:04:00downside to renovations are you it takes
1:04:03longer, you do not get the program that
1:04:05you want. Um so so we we determined it
1:04:09would probably cost about $20 million to
1:04:11replace that building. And as you've
1:04:12seen the pictures, uh there really was
1:04:15not a great chance structurally or from
1:04:18an envelope perspective to renovate the
1:04:20existing building. So it really would
1:04:22have had to been replace it in kind. But
1:04:24that would not have meet the even even
1:04:26building replacing that building it
1:04:27would not meet the uh program
1:04:29requirements of roughly 130 140,000
1:04:32square feet of space that's needed. Um
1:04:34so we determined it would probably cost
1:04:35around 46 thou $46 million if you could
1:04:38build it on Stadium Drive, but the but
1:04:40the real estate doesn't allow you to do
1:04:41that anyway. So they they we had to
1:04:43start looking elsewhere. In May of 2025,
1:04:47um the the the design evolved into
1:04:50138,000 plus uh square foot facility and
1:04:53we estimated the cost to be around $44.7
1:04:56million. Um moving forward as as the
1:04:59design kind of continued to evolve and
1:05:01decisions were made. Um in October, um
1:05:05we're sitting here and we're we're at
1:05:0643.479
1:05:08million uh for a 138,400T
1:05:13facility. And I do I apologize. There is
1:05:15an a mistake on that 317 per square
1:05:18foot. It's $314
1:05:20per square foot that that we're
1:05:22currently at. And it's important to know
1:05:24that 3 months ago we were at 45.5
1:05:27million and the DPW came to us and said
1:05:30we need to think about savings. We need
1:05:32to find ways that we can we can uh
1:05:34protect our program and the things that
1:05:36we need to service the city. Um but we
1:05:39got to bring the cost down. So, we came
1:05:41up with 50 or 50 or 60 different ideas
1:05:43on how we could bring the cost down. And
1:05:45as a result, uh the city said said yes
1:05:47to about $2 million worth of that,
1:05:49getting us to this $43.4 million.
1:05:54Um and that process was well thought out
1:05:57and I was I was encouraged by the the
1:05:59way that the committee thought about
1:06:01balancing size of the building, program
1:06:03of the building, schedule as well as
1:06:05what is financially feasible from the
1:06:07city's perspective.
1:06:09So, that's kind of where how we got to
1:06:11where we are today. And that's a GMP.
1:06:13Um, we've started to bid this out a
1:06:15little bit. Um, we will take every bid
1:06:17package. Um, and and bid it out to at
1:06:20least a minimum of three different
1:06:22trades in each trade group, three
1:06:25different electricians. We'll get six or
1:06:27eight different numbers. Same thing on
1:06:29mechanical site all the way through. We
1:06:31do have done full detailed estimates.
1:06:34So, we do know exactly where every line
1:06:35item in this budget uh kind of falls. We
1:06:38we uh we have provided for
1:06:41contingencies. The way that this works,
1:06:43this is construction management. So any
1:06:46any savings that is found throughout the
1:06:48process comes back to the city for you
1:06:50to decide what you want to do with it.
1:06:52Um and we're hopeful that hopeful that
1:06:54we're able to save some of that
1:06:55contingency money and and and make sure
1:06:57that the city is able to to take that
1:06:58back and and work with it. Um so that's
1:07:02kind of how we got there. I do want to
1:07:03just mention three quick things. one is
1:07:05in terms of cost that there is a cost of
1:07:07doing nothing. Um and and I I I say that
1:07:11with all sincerity because we're running
1:07:13at about a four to five um per month uh
1:07:17escalation clip right now and over the
1:07:19last four months it's been ranging
1:07:21around 4.7 uh%. Um so waiting 5 years to
1:07:25do to do this could could change that
1:07:27price to 52 to 54 million if I do my
1:07:31math correctly. Um based on that 43.4 4
1:07:34million. Um so so the and that does not
1:07:38include the cost of uh fixing emergency
1:07:41items, leaks, things that are going on
1:07:44with the existing stadium building. So
1:07:46there's that cost as well as the
1:07:48escalation cost in construction over the
1:07:49next 5 years if if you choose to wait.
1:07:52Um I also tariffs is a word that gives
1:07:54people hives these days. Um and and we
1:07:58account for that and we do we we we have
1:08:01tariff contingencies that are outlined
1:08:03in excuse me in our estimate. Um and
1:08:06it's important to know that we we vet
1:08:08that out with the subcontractors. We
1:08:10talk to them about what pricing risks
1:08:12are out there. Um and we gauge those in
1:08:15our estimate. It's it's all reflective
1:08:18in this detailed estimate that the
1:08:19committee has has has looked at. And
1:08:22finally, I think I think if if you
1:08:25choose to move forward with this, you're
1:08:27talking about a 50 plus year building.
1:08:29This is a building that's going to take
1:08:30a very different approach than was taken
1:08:33in the 1970s. In the 70s, there was an
1:08:35oil crisis. There was a financial
1:08:36crisis. Materials were not made the way
1:08:39they are today. So, it was a risky it
1:08:41was a risky move 50 plus years ago to
1:08:44build this building. Today, we're
1:08:45talking about stronger durability of
1:08:47product. structurally, we we've got a
1:08:49very structurally sound building. Um the
1:08:52envelope is going to protect the people
1:08:53and the vehicles inside this building.
1:08:56So, we foresee this as being more than a
1:08:5850-year investment um for the city. And
1:09:01and I think that uh you can have
1:09:03confidence in that from a both a
1:09:04maintenance and a and a construction
1:09:06perspective. So, I again, I appreciate
1:09:09having the opportunity to kind of just
1:09:10quickly outline from the construction
1:09:12perspective uh where we're at and uh I
1:09:15appreciate having this opportunity to
1:09:17speak with you. And I think I'm turning
1:09:19things over to Scott to talk a little
1:09:20bit about sustainability.
1:09:29>> Okay. Hello everybody. My name is
1:09:31Scottlair. I'm the CEO of Fitz and
1:09:33Tatachi Engineering. We're the
1:09:35mechanical, electrical, plumbing, fire
1:09:37protection engineers for the for the
1:09:40facility. And I want to talk to you
1:09:41mostly tonight about something I've
1:09:43talked to you in the past a little bit
1:09:44about. It's the sustainability, energy
1:09:46efficiency
1:09:48um components of the building. Just to
1:09:50kind of make sure you understand that
1:09:52we're really, you know, driving home
1:09:54sustainability in this particular uh
1:09:57project opportunity. Um we're looking at
1:10:00high performance envelopes. We're
1:10:02getting ready for foldable voltaics,
1:10:05um, you know, high efficiency lighting,
1:10:07uh, energy recovery ventilation, uh,
1:10:10radiant heating. You know, there's a
1:10:12number of different things that we're
1:10:13doing here, but there's one sort of very
1:10:15unique opportunity that we're taking
1:10:17advantage of with this particular
1:10:18project, and it has all to do with the
1:10:20location. Um, as you all know, this
1:10:23location is at the the landfill site for
1:10:26Hills. Um, and there's been a an on-site
1:10:29methane recovery um, generation plant
1:10:33there for sort of decades at this point
1:10:35that's been running. Um, that particular
1:10:38plant's been generating energy that um,
1:10:40the city essentially gets money for as
1:10:43it's sold back onto the grid. Um, but
1:10:46that that plant also generates a lot of
1:10:48heat and that heat is really just going
1:10:50up the stack and going outside and it's
1:10:52been doing that for decades. Um but this
1:10:54particular project opportunity gives you
1:10:56a great opportunity to take advantage of
1:10:58that. And so we have worked into this
1:11:01project the ability to recover um the
1:11:04heat that's um generated off the methane
1:11:07plant. It basically heats the whole
1:11:09facility. Um and really you can think of
1:11:11that as sort of free heat. Um which and
1:11:14it's a lot. It's a big building. There's
1:11:15a lot of heat. It gets cold here. Um so
1:11:18we really you know it's a very unique
1:11:20opportunity that you don't get in most
1:11:22projects. Um, and but we are definitely
1:11:25taking advantage of it here and it
1:11:26lowers the the energy uh use and the the
1:11:30emissions on this project significantly.
1:11:33And then you just click to the next
1:11:34ones. And just, you know, there's a
1:11:36couple of graphs down here that talk
1:11:37about the amount of energy, but I think
1:11:39the best way to think about it is really
1:11:42just, you know, looking at that top
1:11:44bubble. you know, using this design and
1:11:47the way that we put things together
1:11:48here, it really saves the amount of
1:11:51energy that almost a hundred homes use
1:11:53in a year. So, um, which is quite a bit
1:11:56of energy there. And then talking about
1:11:58how much emissions is reduced, it's
1:12:00about this, it's actually like taking
1:12:01more than a 100 cars off the road. So,
1:12:04those are kind of the sort of feel of
1:12:07the numbers we're talking about here.
1:12:09And that's coming from all these
1:12:10sustainability features that are
1:12:12implemented into the project that
1:12:14everyone's presenting here. Um, as you
1:12:16know, to include obviously the methane
1:12:18recovery and the heat recovery off of
1:12:20that. So, next one. Um, and just, you
1:12:24know, we talked earlier about health and
1:12:26safety type uh improvements with the
1:12:28project. Um, just summarizing some of
1:12:31those as they relate to the mechanical
1:12:33electrical systems in the building. Um
1:12:35the ventilation side, you heard there's
1:12:37no ventilation in the other building. We
1:12:39have sort of high efficiency ventilation
1:12:41in the in the new facility. Um that has
1:12:44appropriate air changes. Um has sensing
1:12:47of you know vehicle exhaust, other other
1:12:50potential pollutants. Um we we're
1:12:53capturing any kind of vehicle uh
1:12:56emissions. Um we're recovering energy
1:12:58from the air that we're bringing in and
1:13:00bringing out. Um that's on the energy
1:13:02side. uh any welding, things like that.
1:13:04We're pick up all those exhausts and
1:13:07bring them to the outside. Um and then
1:13:09we also are implementing radiant
1:13:10heating, which um if you're not familiar
1:13:12with that, it's essentially heating the
1:13:14floor instead of heating the air. And if
1:13:16you think about a lot of the operations
1:13:18in fleet and areas like that, and this
1:13:20is specific to the fleet area. Um you
1:13:23you know, it's a kind of a high bay
1:13:25facility. There's no reason to heat the
1:13:27entire area. You heat where the people
1:13:29are, which is down at the floor. So uh
1:13:32again another energy efficient kind of
1:13:34way for us to to really provide a lot of
1:13:37thermal comfort um for the type the
1:13:40employees that are working in the
1:13:41facility.
1:13:42So I just wanted to kind of summarize
1:13:44again the uh energy efficiency and and
1:13:47you know carbon reduction type items and
1:13:50the health and safety features that have
1:13:52been built into this uh exciting
1:13:54project. So, thanks a lot.
1:13:58I think I'll pass it off to Commissioner
1:14:02Greg who's
1:14:05>> Thank you, Scott. Uh, I I just want to
1:14:08take a moment to thank Director Photo
1:14:10and the team for continuously looking
1:14:11for ways to give back money to the city
1:14:14as well as the thorough work on this
1:14:16presentation. It really has been kind of
1:14:18a joy to be part of this. And of course,
1:14:20thank you alderman for your time
1:14:21tonight. For the record, my name is
1:14:23Commissioner Greg. I'm the vice chair of
1:14:25the board of public works and much of
1:14:27what I'm presenting to you has been
1:14:28brought up by my colleagues. But for my
1:14:30part, I'm going to focus on some of the
1:14:32important numbers starting with three.
1:14:35First, we estimate that about 875,000 a
1:14:39year in mainten maintenance savings will
1:14:41be made establishing a possible range of
1:14:43about 500,000 to 900,000. So, where do
1:14:47these numbers come from? Vehicles stored
1:14:49outside of New Hampshire winters break
1:14:51down more, they wear out faster, and
1:14:53they cost more to keep running. And the
1:14:55research published on this in Fleet
1:14:57Maintenance and Government Fleet
1:14:58magazines, which are two industry
1:14:59publications for fleet managers, they
1:15:02compared municipal fleets stored indoors
1:15:04and outdoors. It found what some of us
1:15:06know to be true living in New Hampshire,
1:15:08that outdoor storage costs roughly three
1:15:10times as much over a vehicle's life,
1:15:13about 8,000 more per vehicle per year.
1:15:16move 103 vehicles indoors, which is our
1:15:18plan, and that adds up. I'll walk
1:15:20through the details in a couple of
1:15:22slides. Second, 103 more vehicles moved
1:15:25out of the weather and into a garage.
1:15:28Third, 14.7 million in city equipment
1:15:30protected that's sitting outside today.
1:15:33Over the life of this building,
1:15:34maintenance savings alone recovers 25 to
1:15:3745 million before we count safety,
1:15:38compliance, or what it would cost to
1:15:40keep patching the old one. Uh, if we can
1:15:43go to the next slide. So, here's where
1:15:45we're at today. We have 364 vehicles and
1:15:48pieces of equipment and 268 of them are
1:15:51registered. We can house 67 today
1:15:54extremely uncomfortable in the street
1:15:55apartment building. That leaves 201
1:15:58registered vehicles outside or in cold
1:16:00storage through New Hampshire winters.
1:16:0245 million in fleet value. 3/4 of it
1:16:05exposed. And the building we do have is
1:16:07nearly 50 years old with the OSHA,
1:16:10asbestous, and air quality problems you
1:16:12saw earlier. This isn't a building we
1:16:14can keep patching. If we can go to the
1:16:16next slide. So that new garage that
1:16:19we're talking about changes that
1:16:20picture. The capacity goes up to 170
1:16:23vehicles, about 2/3 of our registered
1:16:25fleet. Uh I think this says 67 on the
1:16:27slide deck. I think uh director photo
1:16:30mentioned this. It's about it's closer
1:16:31to 64% but close enough. 2/3 of the
1:16:34registered fleet. So that's about that's
1:16:36103 more vehicles indoors protecting an
1:16:39additional 14.7 million in equipment.
1:16:42It's also a modern building. Proper
1:16:44drainage so we're not running
1:16:45contaminants into storm water,
1:16:47environmental protection, and a
1:16:48workspace that's OSHA compliant. Our
1:16:51employees work in this building every
1:16:52day. So they deserve one that's safe and
1:16:54that has proper air flow and other
1:16:56accutrants.
1:16:58If we can go to the next slide. Earlier
1:17:01I mentioned the industry research. So
1:17:03here's what it says and where those
1:17:04numbers came from. The study from
1:17:06government fleet looked at a 60 vehicle
1:17:08municipal fleet over 50 years. Stored
1:17:11outdoors, these vehicles cost 38 million
1:17:13to maintain and operate. Stored indoors,
1:17:1613 million. That's where the three uh
1:17:18that's where the three times figure
1:17:20comes from. We scaled that to our 103
1:17:22additional vehicles. That straight math
1:17:24lands us near the top of our range
1:17:26around 875,000 a year. We set the low
1:17:29end at 500,000 just in case the fleet
1:17:31doesn't match the study perfectly. So
1:17:33that's how we get the 500 thou 500 to
1:17:35900,000 r range per year and
1:17:38extrapolated over 50 years we get 25 to
1:17:4045 million over the life of the
1:17:42building. Uh where do these savings come
1:17:44from? Fewer breakdowns, less unscheduled
1:17:47maintenance, vehicles that last longer
1:17:49before they need replacing, less wear
1:17:50from cold starts, and crews who don't
1:17:52start a snowstorm uh by digging out the
1:17:54trucks. If we can go to the next slide.
1:17:58About 20 years ago, the city had a
1:18:01proposal for a public works garage. If
1:18:03we had built it then, we'd have saved a
1:18:04ton of money in a like for-like
1:18:06comparison. We didn't. And here's what
1:18:08waiting would cost now. You build it
1:18:10today, 53.5 million for everything. Wait
1:18:145 years, about 71 million once you add
1:18:16construction inflation and the
1:18:18maintenance savings that we'd lose. 10
1:18:20years, about 88 million. 15, we're
1:18:22looking at about 110 million. And that
1:18:25chart's conservative. It just assumes
1:18:27about 4% inflation below the national
1:18:29average and current construction
1:18:30inflation. Waiting doesn't save money.
1:18:33It just moves the bill to a bigger
1:18:34number. So, if we can go to the next
1:18:36slide,
1:18:38here's the decision in front of
1:18:39everybody. A 53.5 million investment
1:18:42that protects 14.7 million in fleet
1:18:44assets, moves 103 more vehicles indoors,
1:18:47extends the vehicle life, cuts
1:18:49maintenance 15 to 25%, and gets our
1:18:52crews out the door faster when storms
1:18:53hit, which then gives us faster
1:18:55capability to get our fire trucks and
1:18:56first responders on the road to assist
1:18:58emergencies. It saves an estimated 500
1:19:01to 900,000 a year. And a 5-year delay
1:19:04adds at least 12 million, closer to 17
1:19:06million on our own chart. We also have a
1:19:09AAA, as many of you know, a AAA bond
1:19:10rating right now, which means we borrow
1:19:12at some of the best rates available.
1:19:13This facility has to be replaced
1:19:15eventually. Question is whether or not
1:19:17we do it on our terms at today's price
1:19:19or as an emergency at tomorrow's price.
1:19:21So, we are asking you in front of the uh
1:19:24board right now to consider doing it
1:19:25now.
1:19:30>> And that should be wrapped up.
1:19:33>> D Cummings.
1:19:36>> Yes. Uh thank you, Mr. Chairman. Uh uh
1:19:39Tim Cummings, director of administrative
1:19:41services. So that concludes our formal
1:19:42presentation this evening. I I would ask
1:19:45that you uh look favorably on R2672
1:19:51uh when when it comes forward for uh
1:19:54voting and and for your final
1:19:55recommendation uh before it goes to the
1:19:58full board of alderman. I'll note that
1:19:59we are trying hard to get this project
1:20:01under construction for this fall. Um if
1:20:05we were to receive approval of the of
1:20:07the bond, we would um at the at the full
1:20:10board of alderman in um October, we
1:20:14would then have a joint committee
1:20:15meeting where we still need to get the
1:20:17contracts uh authorized and that would
1:20:19be the the particularly the GMP hoping
1:20:22to do that um at the at the end of the
1:20:24October for a notice to proceed and
1:20:26really to start the project in earnest
1:20:28in November.
1:20:30>> Thank you. Are there any one that want
1:20:32the board that wants to amp add any
1:20:34amplifying questions of the
1:20:36presentation? I know we've seen this
1:20:37several times. Okay, seeing none,
1:20:41I'll now open up testimony in favor of R
1:20:4526072,
1:20:50Commissioner Sheay,
1:20:55uh, Board of Public Works Commissioner
1:20:56Paul Sheay. I thank everyone for their
1:21:00part in this presentation tonight. It
1:21:02was very thorough and covered a lot of
1:21:03the reasons, so I don't need to say too
1:21:06much. Uh I was up here uh sometime last
1:21:09year and um and we reviewed this project
1:21:13and talked about it and I spoke on what
1:21:15we would prefer. And for me the the
1:21:18biggest
1:21:20factor in making this investment is uh
1:21:24preference to ensure that our employees
1:21:26have a safe and healthy working
1:21:28environment and a place where they can
1:21:30do their job efficiently and we can take
1:21:33care of our our people. Um, I I also
1:21:37just want to say because my son will be
1:21:39very pleased, um, and he's been very
1:21:42patient tonight that I I appreciate
1:21:45Matty Greg, uh, Commissioner Greg's, uh,
1:21:47presentation. Uh, it's very good to get
1:21:50those numbers in because that's a a
1:21:52tough thing to account for. So, it's
1:21:55exceptional that he did the the leg work
1:21:58there. So, so thank you to Commissioner
1:22:00Greg for that. And my son is very
1:22:02pleased that the number 67 appeared in
1:22:05the in
1:22:08the presentation three times and um it
1:22:11it put a little spark in him uh at at a
1:22:15a tiring hour. So um
1:22:18anyh who um thank you all so much. Uh I
1:22:21I appreciate your support for for the
1:22:23work of our our city workers and for the
1:22:26infrastructure that's required uh to to
1:22:29get the job done. And um thank you.
1:22:32>> Okay. Any other testimony in favor?
1:22:37>> Seeing no additional testimony in
1:22:39opposition,
1:22:49Lori Erdolano Nasha. So, you know, my
1:22:52concern is cost. Um, and I think the
1:22:54board has expressed that concern over
1:22:57time when we look at this project from
1:22:59the design phase and the amount of money
1:23:02needed to uh design or do planned design
1:23:06work, architectural work for this
1:23:08building. And I know we see the bond for
1:23:10435. We have an additional $3.1 million
1:23:14added to that. And with the design work,
1:23:16I think we're clearly up over a project
1:23:19total cost of around 52 million. That's
1:23:22a lot of money. And I just want to say
1:23:24this because I looked at the capital I
1:23:26looked at the ad hoc committee and
1:23:28needs. First of all, I don't know how
1:23:31this fits into the bonding plan of, you
1:23:35know, trying to minimize bonding
1:23:36annually to $30 million. Um, this would
1:23:40go clearly past that. I'm concerned
1:23:43about our budget process in general in
1:23:46this city. Um, you know, if you look on
1:23:49page 11 of the budget, that is the
1:23:52amended budget that was voted on by the
1:23:55board at the end of June. Uh, on page
1:23:5811, you had the mayor's statement of the
1:24:01estimated increase to the budget. And in
1:24:03that book or in that report at the end
1:24:06of June once it was amended, it was
1:24:082.97%.
1:24:10The real budget increase is 8 12% after
1:24:14spending down 6 million out of surplus
1:24:18to knock it down two more points. It was
1:24:20closer to 10 1 12%. Nowhere near. It was
1:24:24three times higher than what we had
1:24:27believed it was going to be. I don't
1:24:30know why it's so difficult to get a
1:24:34pretty solid number on what that
1:24:36increase is going to be by the time you
1:24:38vote your budget, but I know that I
1:24:41don't believe taxpayers anticipate the 8
1:24:4512% increase they're going to see in
1:24:47December. A lot of them are going to get
1:24:49hit with escrow issues cuz that's a lot.
1:24:5210 uh $10,000 of taxes are going to go
1:24:55up another 850 bucks. It's a lot. And
1:25:00and you know when I looked at the
1:25:01projects and I saw the fire station we
1:25:03need is that for Arlington Street I
1:25:06think a very old station that would in
1:25:08far part service um downtown. I can
1:25:12understand that need. Um that's going to
1:25:15be an expensive project and that comes
1:25:17up in the next year or so. Um I'm all
1:25:20for that. I you know it's a 1800's
1:25:23building. You've done a lot of
1:25:25development downtown with a lot of new
1:25:27construction and new buildings, taller
1:25:30buildings. Um, you have a fire station
1:25:33that's very old, very crowded. Um, no
1:25:36doubt doesn't have the workroom or the
1:25:39space for the um, firemen the way a
1:25:42modern station would have. And that's
1:25:45going to be a really important need, a
1:25:47public safety need. And I understand
1:25:49that if I were to pick a project that I
1:25:51think is an important need that I had to
1:25:54make choices on, I'd pick a fire station
1:25:56over a storage facility for equipment. I
1:25:59would um you know, I came to the last
1:26:03board meeting where
1:26:05I think two hours of the presentation
1:26:07was on a potential new art center at Elm
1:26:10Street um auditorium for somewhere on
1:26:14the cost of 32 or 34 million. really
1:26:17mind-boggling. I just don't see us
1:26:20having um the taxpayer
1:26:24um support for that in the end. And I
1:26:26know not many people show up to say
1:26:28much. I don't think they know what to
1:26:29say because they don't know what they're
1:26:31facing. But,
1:26:34you know, it's it's really concerning.
1:26:36And the other thing is I think a lot of
1:26:38our project management and I'm not this
1:26:41is not true of DPW because I think you
1:26:43have a good finance person uh a good
1:26:46numbers person in um DPW who keeps track
1:26:50of spending. That is not true in other
1:26:53projects within the city. We don't have
1:26:56the resources to track spending and that
1:26:59becomes a real problem for me when I
1:27:01look at projects overall in this city.
1:27:04Um, so you know, I I wasn't supportive
1:27:08of this from the beginning. I think
1:27:10we've done a lot to support DPW. We gave
1:27:13them a new building. We closed the old
1:27:15building and gave it to the um police
1:27:17department to do training. Um, we
1:27:20improved, you know, air quality, worker
1:27:22conditions with a new facility. And um
1:27:25we've consolidated everything over on
1:27:27Holl Street which has plus and minuses
1:27:29when you look at road traffic and all
1:27:31for those that live in that ward. But um
1:27:35you know it can't be an endless ask. And
1:27:38I don't envy what you have to decide
1:27:41here. Um I just think that some
1:27:44thoughtful decisions about how much
1:27:47you're going to throw on the back of
1:27:48taxpayers becomes an issue. I think the
1:27:51total cost and I know it showed like
1:27:53$314 a square foot based on the 43
1:27:56million but when you look at allin with
1:28:00the cost of the project it's well over
1:28:02$400 a square foot to end up with that
1:28:05facility when you look at design and the
1:28:07additional bonding money maybe $450.
1:28:10It's a lot. It's a lot and it's a
1:28:12garage. I've never been able to wrap my
1:28:15head around that cost for a garage.
1:28:19Um
1:28:21the other thing is we see a year coming
1:28:24up where you know adequacy aid from the
1:28:27state is reduced. We all I think at the
1:28:30last board meeting it was mentioned that
1:28:31we can't count on the state as much. We
1:28:33have to count on taxpayers. That
1:28:35continues to be the trend. It will
1:28:37continue to be the case here. It will
1:28:40continue to be the case with school
1:28:41funding. And God only knows what um
1:28:45the Supreme Court will decide on the
1:28:46funding case and what will happen in
1:28:48November in the election. But there's a
1:28:51lot of uncertainty there and I do think
1:28:53that overall the burden is going to be
1:28:56on the taxpayer for a lot of these costs
1:28:58and there's a downshifting to
1:28:59municipalities from the state. They've
1:29:02struggled with their own revenue issues
1:29:03up there. I I think you have to be
1:29:06mindful of that and we have to
1:29:07anticipate that that's going to be the
1:29:09case. So those are the reasons I don't
1:29:12support this project. You brought a fire
1:29:14station this year. I'd say okay 1800's
1:29:16building and a fire station that
1:29:18services downtown is a safety need is a
1:29:22immediate need is uh meets the uh
1:29:25development that we've done down here. I
1:29:27could get behind that and and understand
1:29:30that that's a requirement for a larger
1:29:31scale project, but I can't do it for a
1:29:34parking garage. Thank you.
1:29:36>> Anyone else for testimony and
1:29:38opposition?
1:29:40Seeing no one
1:29:43testimony once again in favor.
1:29:48Commissioner Lemon.
1:29:51>> Hi, Commissioner June Lemon. Uh, Board
1:29:53of Public Works. We have been working on
1:29:56this project for a long time and I
1:30:00understand everybody's concern about the
1:30:02money. I mean, I'm a taxpayer in the
1:30:05city just like everybody else. But there
1:30:08is an issue of safety here as well as of
1:30:11money. There's an issue of how much
1:30:14money are we willing to lose in our
1:30:16fleet if we do not protect the assets we
1:30:20have. And personally, I just lost a car
1:30:23this week because of the rain.
1:30:25Seriously, it was given to me. I did not
1:30:27know that the design um features
1:30:31had grommets. It had, not only did it
1:30:34have a sunroof that was leaking, which I
1:30:36was not aware of because I just got this
1:30:38car, was given to me, so I'm not out a
1:30:40lot of money, but um the grommets filled
1:30:43up, so the water did not drain
1:30:46appropriately away from the car. So
1:30:49basically, water came in and it shot all
1:30:51the electronics. For me, that's a
1:30:55$10,000 loss. Personally,
1:30:58um I don't want to see this happen to
1:30:59the city vehicles, which are way more
1:31:01sophisticated, cost a lot more money,
1:31:04and I also am very concerned. No one who
1:31:07has spent time in the current city
1:31:09garage feels like employees should have
1:31:12to work out of there, particularly
1:31:13employees who are doing very heavy duty
1:31:17work like snowplowing. So, you know, I
1:31:22didn't come up for every single
1:31:23resolution. I support all of them and I
1:31:28really support this one. I really think
1:31:29it's time that we just do this. And um
1:31:33when um Ms. Ornalano said, you know,
1:31:36it's not an what did she say? It's not
1:31:38an endless stream of money. I don't
1:31:40think we ask for an endless stream of
1:31:42money except that we have to ask for
1:31:45things that have to be done for the
1:31:47city. You know, we don't we are not
1:31:49cavalier about the money we ask for. Um,
1:31:53we have detailed discussions about this
1:31:56at the board of public works meetings
1:31:58and at the joint special meetings. So, I
1:32:01hardily recommend this project and I ask
1:32:04for your support.
1:32:05>> Thank you. Any other testimony in favor?
1:32:09Seeing no additional, once again,
1:32:11testimony and opposition.
1:32:14Seeing none,
1:32:16I'll close the public hearing on R26072
1:32:19at 8:32
1:32:21p.m. And at 8:32 p.m., I'll open the
1:32:25last public hearing on R26073.
1:32:31Changing the purpose of up to 3,183,200
1:32:37of unspended
1:32:39bond proceeds from various division of
1:32:41public works capital projects to the
1:32:44division of public works garage and
1:32:45fleet maintenance facility project.
1:32:49Director Cummings.
1:32:50>> Yes, thank you for the record. Tim
1:32:51Cummings, director of administrative
1:32:52services, and uh uh I just thought I
1:32:54might start it off this evening. Uh but
1:32:56uh director photo is online and
1:32:58certainly want to provide her an
1:32:59opportunity to speak on this as well if
1:33:01uh if need be. But I thought it would be
1:33:04uh important and imperative to note for
1:33:06the record that this particular
1:33:07resolution is not new bonding. What we
1:33:10are doing is taking existing bonding and
1:33:12just repurposing those funds. So we're
1:33:14not adding any additional debt service.
1:33:16I think that's a really critical point
1:33:18that I wanted to make explicit this
1:33:20evening. Um, so, so that's that's one.
1:33:23Two, these projects have all come to
1:33:25fruition and so they're they're done and
1:33:26completed and so uh this would be a a
1:33:30good and I submit to you an appropriate
1:33:32use uh being uh uh fiscally prudent uh
1:33:35with our with our uh scarce scarce
1:33:38dollars. Um, Mr. Mr. Chim, I also kind
1:33:41of want to take an opportunity if you if
1:33:43you will to to respond to some of the
1:33:45comments that were made uh just just a
1:33:47moment ago because I think it's
1:33:48important to note for the record that um
1:33:51this body and the general public should
1:33:53not be scared for the amount of bonding
1:33:55that we're doing. Um we spent a lot of
1:33:58time over the summer looking at this.
1:34:00That's what the whole ad hoc process was
1:34:03about. So you don't have to feel like uh
1:34:06where, you know, you need to pit one
1:34:08project against another. fire versus
1:34:10library versus DPW. The reality is the
1:34:14city of NSHA has a lot of capital
1:34:15expenditures and a lot of needs and we
1:34:17thought about it in a very um uh
1:34:20deliberative manner. We developed a
1:34:23policy. We're adhering to the guidance
1:34:24that was given and we are working
1:34:26towards and this is an important
1:34:28critical element. We're not talking
1:34:29about authorizing up bonding when we
1:34:32were doing our exercise. we were talking
1:34:33of selling up debt and we are selling
1:34:36debt in a certain way over a period of
1:34:39time to keep our tax rates stable and so
1:34:42that's those points are really critical
1:34:44so you so so those finer points are not
1:34:47missed to the general public because I
1:34:49don't want anyone to be scared thinking
1:34:51oh we're authorizing $60 million of
1:34:53bonding we're authorizing $80 million of
1:34:55bonding and suddenly the tax rate is
1:34:57going is going to shoot up no that is
1:35:00not the case what you will have is
1:35:03authorized spending for certain capital
1:35:05projects that we will sell the debt over
1:35:08a certain period of time and we need to
1:35:10balance that so we have a tax rate that
1:35:13remains stable and that was the whole
1:35:15point of why we took the time this
1:35:17summer and why I can stand here
1:35:19confidently before you and tell you so
1:35:21long as we follow the plan we will have
1:35:23a stable tax rate when it comes to the
1:35:26debt service because that is a known
1:35:29commodity we have certain debt falling
1:35:31off welay layering new debt in. We've
1:35:34we've programmed it appropriately so we
1:35:37won't see a spike in our debt service
1:35:39budget which is in our operational
1:35:41budget. Uh so Mr. Chim, I thought that
1:35:43was a really critical point for for you
1:35:45all to have as you consider the various
1:35:47resolutions before you this evening.
1:35:48Thank you.
1:35:50>> Any amplifying questions?
1:35:52>> No. All right.
1:35:54>> I have a question.
1:35:55>> Yes. Dman Johnson.
1:35:58>> Thank you. Um to Director Cummings,
1:36:00please.
1:36:02Cummings.
1:36:08>> Thank you.
1:36:10How long how are you spreading this out
1:36:14to sell the bonds? Is it going to be one
1:36:16year, two year, three years because of
1:36:18the fact that and how much is falling
1:36:21off? So when debt is falling off, we're
1:36:24adding a new debt, but it's not going to
1:36:26hurt us because there is definitely
1:36:29whatever's falling off is less debt
1:36:32because I've calculated how much
1:36:34interest on all of this except for the
1:36:367-year plan. And with everything you're
1:36:40asking for, that's over $124 million
1:36:42worth of interest that we're paying out
1:36:44on all this debt. That's a lot of money.
1:36:47Johnson, that's probably a question for
1:36:48the budget hearing because that doesn't
1:36:50have anything to do with these
1:36:51>> these particular items. We're just
1:36:54transferring money that's already
1:36:55existing in the bonding. We're not doing
1:36:57additional bonding.
1:36:58>> So maybe he can answer me about the
1:37:00what's falling off in the process here.
1:37:02That is not good because I'm just
1:37:04picking up what he said. So
1:37:06>> what's falling off and
1:37:08>> I mean this this has worked over the
1:37:10years when they built the two new high
1:37:12schools which I was involved in that was
1:37:15175 million 20 years ago. They're all
1:37:18paid off. The middle school project uh
1:37:22was was
1:37:23close to 200 million and we didn't spend
1:37:26all of that. We re we're actually doing
1:37:28another project with some of that
1:37:30funding and and that will start falling
1:37:32off. So there's a there is a schedule
1:37:35that's available that shows how all the
1:37:37money falls off from the various years
1:37:39from the various budgets. So we can talk
1:37:43more about that in budget. Alman Morgan,
1:37:46>> uh thank you. Um to director Cummings,
1:37:50can I have some help on clarifying
1:37:53just the language on this? Um
1:37:57reading 026 uh 026 073 talking about the
1:38:013 million going towards public works
1:38:03garage and fleet maintenance facility
1:38:05project. Is that in reference to 072
1:38:08right before
1:38:11>> Dr. Cummings?
1:38:14>> Uh that's correct if if I may Mr.
1:38:17Chairman. So 026073
1:38:20for the 3.1 million is uh
1:38:24monies from miscellaneous projects that
1:38:27would be repurposed for the DPW garage
1:38:29fleet maintenance facility which is
1:38:31referenced in the resolution right
1:38:32before the resolution right before is
1:38:35new debt. This wouldn't necessarily be
1:38:37new debt. It's repurposed debt.
1:38:39>> Follow up um
1:38:43>> high level. So, I'm just curious why um
1:38:47why you would choose to apply that 3.1
1:38:49million to this specifically versus say
1:38:52one of the other ones we looked at
1:38:55tonight that would have equated to the 3
1:38:58million.
1:39:00It
1:39:00>> I think these are not enterprise funds
1:39:02that we're transferring tonight. The
1:39:04other projects we talked about were
1:39:05enterprise funds, different type of
1:39:07money.
1:39:09>> So,
1:39:09>> director coming.
1:39:10>> Yeah, thank you if I may, Mr. Jim. So,
1:39:12so, uh, all great points and certainly
1:39:15we could we could look at it a couple
1:39:17different ways. I think first and
1:39:19foremost, this question wasn't
1:39:21necessarily asked, but I think it's
1:39:22important to put out there for the
1:39:23record is um, we got advice from our
1:39:26bond council that we really needed to
1:39:28separate these uh, two resolutions into
1:39:32separate this effort into two separate
1:39:34resolutions, not bundle it into into
1:39:37one. Um we essentially have these uh the
1:39:41various needs. As we all know the city
1:39:43has has a lot of needs. The DPW project
1:39:47total project cost is is something in
1:39:50the order of $53 million. You have 43
1:39:53million of hard construction debt and
1:39:55that's the hard construction cost and
1:39:57that's what this new debt resolution
1:39:59covers. But then there's other costs as
1:40:02well that this 3.1 is uh would cover. Um
1:40:06I believe off the top of my head we've
1:40:09offer authorized about about $5 million
1:40:12in in debt for pretty much design. Uh
1:40:15we'll have this uh 43 million then
1:40:18another 3.1
1:40:20um which you know is going to bring us
1:40:22up to about 48 uh to to $50 million
1:40:25which is still under the total project
1:40:27cost that we're actually going to need
1:40:29because to everyone's point we're trying
1:40:31to do this as efficiently as possible
1:40:32and we believe that you know as time
1:40:34goes on we will be able to to bring the
1:40:36project cost down um as we go on. Uh so
1:40:40we didn't want to ask for anything more
1:40:43than we needed because we are certainly
1:40:45very conscious of all the various needs
1:40:47out there and uh as everyone has alluded
1:40:50to um at the start of this evening is is
1:40:54the budget and the money for this
1:40:56project has been forefront in our minds
1:40:59and constantly when when when uh the the
1:41:03numbers were coming in we were asking
1:41:04ourselves what can we do to bring this
1:41:06project in uh you know in line and So
1:41:10through the great work of the
1:41:11consultants here, we had project numbers
1:41:14that were 23 $4 million higher and we we
1:41:16were able to bring it down. And we're
1:41:18trying to do that because we're being
1:41:20conscious of all the various needs that
1:41:22are out in the city. And we don't want
1:41:23to uh uh authorize additional debt that
1:41:26we don't we don't necessarily need, but
1:41:28we do need the 3.1 and the 43 if we're
1:41:31tracking towards a $53 million project.
1:41:34Thank you. And all of these funds are
1:41:37remaining from DPW projects only. So
1:41:40it's going to from there to another DPW
1:41:43project.
1:41:44>> You have a follow-up.
1:41:45>> Yeah. To you then. So your explanation
1:41:48is what was what I was looking for.
1:41:50Could this 3.1 million be used for say
1:41:54um towards the pools? So we're only
1:41:55taking out 2 million instead of five.
1:41:58That was my question.
1:41:59>> Bond council doesn't look at it that
1:42:02way. They try to keep thing if you going
1:42:03to transfer the money it have to be to a
1:42:05similar project.
1:42:06>> Got it. Thank you.
1:42:08>> All right.
1:42:12I'll open it up now to testimony in
1:42:14favor.
1:42:17Seeing none testimony and opposition.
1:42:27My name is Bill Faro. My home is number
1:42:2935 Indian Rock Road. This is certainly a
1:42:32very worthy use of this money, but I
1:42:37don't understand the unexpended bond
1:42:40proceeds.
1:42:41Earlier this evening, Mr. Chairman, you
1:42:44said that if we bond more than we bond
1:42:47more than we need that that extra amount
1:42:49goes back. I'm not sure what that means.
1:42:52goes back is it doesn't go back unless
1:42:55it's a motion of of this board to put it
1:42:57back somewhere. In this instance, we are
1:42:59taking it and putting it back somewhere
1:43:01else in a similar project in accordance
1:43:04with the bond council.
1:43:05>> Okay. But this 3,183,000
1:43:09whatever that didn't go back.
1:43:13It just it just sat there just we
1:43:15continue to pay on it. We continue to
1:43:17pay principal interest on that. All
1:43:19right. When you said goes back,
1:43:21>> it's you made it
1:43:23>> going to another DPW project.
1:43:25>> I understand that, sir.
1:43:26>> It's money that was not spent. It was
1:43:28not costing us anything
1:43:30>> because we never is spent that money on
1:43:33that project. That money now that's left
1:43:36in the authorization of that particular
1:43:39bond.
1:43:39>> Okay.
1:43:40>> Is being transferred to R26072.
1:43:45>> So why did you say that it could go
1:43:47back? You said in other instance you
1:43:48said it could go back
1:43:50>> because one other avenue we have as a
1:43:53board on other projects is that we could
1:43:58take that if there was money left in a
1:44:00bond
1:44:02by similar type of motion as to 73
1:44:06we could dissolve that and never bond
1:44:09it.
1:44:12>> Where would that excess revenue go?
1:44:14>> It's not excess revenue. It just
1:44:16wouldn't be ever be bonded.
1:44:17>> Well, you said you bonded more than you
1:44:20spent than you than you needed is what
1:44:21you said earlier.
1:44:23>> Yes. Let's hypothetically say you bond
1:44:26$5 million. You only spend four. This
1:44:29board could dissolve the last million
1:44:31and never bond it if they wanted to.
1:44:34>> But you've already bonded it.
1:44:36>> Doesn't make any difference. It's only
1:44:37when we bond something, we bond amount
1:44:41of money that could be spent on a
1:44:42project. doesn't mean we're going to
1:44:44spend it. It gets spent by other means.
1:44:47>> You authorize the bonding.
1:44:49>> Yes. But that doesn't mean that we have
1:44:52to spend it.
1:44:53>> But you you infer that you actually
1:44:56borrowed the $5 million.
1:44:58>> No, no, no, no, no. This money has not
1:45:01been borrowed yet.
1:45:03>> It's been authorized, but not borrowed.
1:45:07>> This
1:45:07>> if we borrow it,
1:45:08>> this this 3,18 different story. This
1:45:113,183 has not been borrowed yet.
1:45:15>> Not that I'm aware of. No, it's it's
1:45:17money that's it calls it
1:45:18>> authorized in in that bond that's being
1:45:20transferred to this bond.
1:45:22>> It calls it unexpended bond proceeds.
1:45:27>> It hasn't been spent.
1:45:30Director Cummings, you want to amplify
1:45:32on that?
1:45:36>> No.
1:45:36>> Miss Mullen, do you want to jump in? No.
1:45:45>> Has this 3 million?
1:45:47>> No. There we go.
1:45:48>> Okay.
1:45:50>> No, I think it's been pretty well
1:45:51covered. Um,
1:45:55you know, the money is going to be um
1:45:58removed from the being used for the
1:46:00other projects and just being um
1:46:04used for this project. And
1:46:09um
1:46:11as far as going from
1:46:16um sorry I'm tired.
1:46:19Um sorry from going from
1:46:25>> I'm just going to let it go at this
1:46:26point.
1:46:27>> Yeah.
1:46:27>> Is there another question?
1:46:28>> It's the way bonds work and you have to
1:46:31understand the way bonds work and I
1:46:32don't think you do.
1:46:33>> I apologize for my ignorance. Okay.
1:46:35>> All right. I tried to explain it to you.
1:46:37Let me try and ask the simpler question,
1:46:38right?
1:46:39>> Has this $3,183,200
1:46:43been bonded yet?
1:46:46>> No.
1:46:48>> I can definitively tell you that based
1:46:50on the type of motion we're trying to
1:46:51pass.
1:46:52>> All right. That it's a little bit
1:46:53confusing that it's called unexpended
1:46:55bond proceeds,
1:46:57which makes
1:46:59>> those authorized for us to to borrow,
1:47:02but we haven't done it yet.
1:47:04>> Okay. But Mr. Cummings said this is not
1:47:06new bonding,
1:47:08right?
1:47:10>> It's not new debt.
1:47:11>> It's not new debt. It's moving this
1:47:15amount of authorized funds to a
1:47:17different project. Period.
1:47:22If you don't understand that, maybe you
1:47:24ought to visit the finance director uh
1:47:27at some point.
1:47:28>> That's enough.
1:47:29>> All Mr. Director Cummings.
1:47:32>> Uh thank you. I mean, another way we
1:47:34could look at it is you could make this
1:47:363.1 million go away, right? But then all
1:47:40we would need to do is increase the 43
1:47:42by 3 million, which is another way to
1:47:45kind of get to the same ends uh the same
1:47:47end goal. And certainly if that was the
1:47:50brothers, you could do that, but this
1:47:51was a way to do it uh efficiently as as
1:47:54possible. Thank you.
1:47:57>> Any other amplifying questions? No.
1:48:00>> All right.
1:48:03Any other testimony and opposition?
1:48:05Seeing none, testimony in favor again.
1:48:08Seeing none, testimony and opposition
1:48:11again. Seeing none, close the public
1:48:14hearing in R 26073 at 8:48
1:48:18p.m.
1:48:20And Alderman Clemens, do you have a
1:48:22motion for this?
1:48:23>> I do. I motion to adjourn.
1:48:26>> Motion is to adjourn.
1:48:28I don't think we have anyone online. So
1:48:31all in favor signify by saying I.
1:48:33>> I opposed. Motion carries. We'rejourned
1:48:36at 8:48.
1:48:39All right. So,
```*
