2026-10-01 - MAPS 4 Citizens Advisory Board Meeting
Summary
- Business and finance: The board approved the September 3 minutes and received the August 31 financial report from David Todd. Total MAPS 4 revenue stood at $880,542,222, trending 3.9 percent above target, with $492,181,810 spent to date. No citizens signed up to speak.
- Fairgrounds Coliseum: Final acceptance was approved and the maintenance bond placed in effect; the final work creates the connection to the Gateway of Champions promenade, a non-MAPS project (MAPS 4 Fairgrounds Coliseum Final Acceptance).
- Multipurpose stadium: The board approved bid packages 4 and 5 and a construction-manager amendment setting the guaranteed maximum price at about $19.7 million (MAPS 4 Multipurpose Stadium).
- Animal Welfare Center: Change order 7 with Crossland Construction ($168,281) was approved. Change orders 1 through 7 total a 4.07 percent increase over the original contract. Phase 1 substantial completion and a ribbon cutting are set for November 17, with the large-animal barn in phase 2 (MAPS 4 Animal Welfare Center Construction).
- Youth Center Phase Two: The preliminary report was approved for a 72,000-square-foot youth center on a site of more than 12 acres in south Oklahoma City, with a $14 million budget and construction beginning in mid-2027 (MAPS 4 Youth Center Phase Two).
- Neighborhood and community parks: Final plans for Washington Park were approved for bid advertisement, with a base bid a little under $5 million and bids expected in November (MAPS 4 Neighborhood Community Parks Phase 1C).
- Other change orders: The board approved a gas-service change order for South Lakes Park, a $123,874.99 change order for unsuitable soil under the old building at the Crisis Center (MAPS 4 Crisis Center Soil Change Order) and a no-cost time extension for Sidewalks Phase 1B.
- Family Justice Center: Staff reported a contract value of about $29.3 million with roughly $2 million in contingency and an estimated completion of July 7, 2027 (MAPS 4 Family Justice Center Construction).
- Homelessness projects: In the quarterly report, staff said the first two allocations are fully committed with 1,021 units in the pipeline (MAPS 4 Homelessness Projects Quarterly Report).
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
01:58We're a little early. Is that okay?
02:02>> Oh, perfect. Good morning. We will call
02:05to order our maps for citizen advisory
02:07board meeting for October 1st, 2026. Um,
02:12under items for individual consideration
02:15to a approval of minutes of September
02:173rd, 2026. um they were included in your
02:21packet. Were there any changes, updates,
02:23or adjustments? If not, I would take a
02:25motion in a second to accept as
02:28received.
02:51Kevin's not getting a vote option.
02:56>> Yes.
03:04>> And the motion passes. Thank you. Moving
03:06on to item 2B. Receive the MAPS for
03:09monthly financial report ending August
03:1131st, 2026. Mr. Todd. [clears throat]
03:14>> Thank you, Madam Chair. You have in your
03:16uh packet the monthly financial report
03:19for the period ending August 31st of
03:222026. On the revenue side for the month,
03:2412,923,596
03:28for fiscal year of 25,879,159
03:34and total of 880,542,222.
03:40I'm going draw your attention to the
03:423.9% that we are trending above
03:44collections or above target on
03:47collections
03:48and on the expenditure side for the
03:51month 8,813,720
03:55fiscal year of 20,431,999
03:59and a total of 492,181,810.
04:04>> Okay. Any questions for Mr. Todd?
04:07>> If not, yes.
04:10um referencing the maps three
04:11expenditures from last meeting. Will we
04:13see those on this report go forward or
04:15only when we vote on maps three
04:16projects?
04:17>> So
04:18>> So I I I didn't forget, [clears throat]
04:21but if we have an item, I'll put them on
04:23there. Do you want them all the time?
04:24>> I think just just related to the items
04:26is really helpful. Okay. Thank you.
04:29>> Okay. Any other questions? Okay. If not,
04:32I take a motion in a second to receive
04:34the financial report.
04:45I'm Yes.
04:46>> Okay. [clears throat]
04:50Okay. Motions are passed. Mark, could
04:53you take a look at Kevin's.
04:55Moving on to item 2 C. Recommend
04:57approval of final acceptance for the
04:59maps for Fairgrounds Coliseum and
05:02placing maintenance bond number two into
05:04effect. I love bringing final or final
05:07acceptance and completion of projects to
05:09you. Today we have Travis Paulie who's
05:11going to just take you through the
05:13finished product.
05:14>> Yeah. Um I know you're probably like,
05:17"Wow, we're still talking about this."
05:18But this is this is maybe not the most
05:20exciting part of the project, but it is
05:22really exciting because this is the
05:24final final uh portion of the project
05:26that needed to be completed. Um, so
05:28before I go into just some some images
05:30of it, I'll remind you of the phasing
05:32that we went through on this project and
05:33then give you a really quick update on
05:35this final portion of the show office.
05:37Um, so if you recall, uh, this project
05:40was done in four phases to make it all
05:42work simultaneously so that everything
05:44could continue operations throughout the
05:46entire construction of the project. So
05:48the first thing we had to do was remove
05:50a portion of the old Nor coliseum to
05:52make room for the new O coliseum. Once
05:56we built that, we removed the NORC
05:59arena, a portion of which was tied to
06:01that show office that you see there on
06:03the left side. Um, in order to save as
06:06much money as possible on this, we kept
06:07as all the show office that we could,
06:09except for the portions where the actual
06:12show office wall was also the Norc Arena
06:13wall. Uh so once we took down the Norc
06:16Arena, we had to finish off that show
06:18office to make uh it ready to receive
06:20the what's called the gateway of
06:22champions prominade that's being now
06:24constructed to connect the super barn
06:27system with the new ogeni coliseum. That
06:30project is not part of maps, but the
06:31show office kind of shape and uh plan
06:34for it was with that in mind.
06:38Um, so we we demolished the ring wall
06:40that was part of the NORC Arena and just
06:43really kind of finished out what was
06:44taken off in a a flat surface that could
06:47be connected to by the prominade. Um,
06:50this was a really really intricate um
06:53demolition process to try to make this
06:54all work and we did find some things
06:56that you guys have seen throughout uh in
06:59the process that we needed some change
07:01orders and things like that. But
07:02overall, I'll say it went really well
07:05considering how um complicated this
07:08demolition and reconstruction was. Um so
07:11this is where we stand today. Just a
07:13reminder, we we closed out the coliseum
07:16and opened it up. I believe it was June
07:1712th of 2025 was the final completion
07:20for that. So we've been operating the
07:22coliseum for well over a year now. We
07:24imploded the NORC on August of 2025.
07:26Once that was all cleared away, here's
07:28kind of what that looked like that you
07:30saw in the drawings where we had that
07:31curved wall uh that was an interior wall
07:34and then the remainder of the um the
07:36tunnel that connected the show office
07:37into the the former NOR.
07:40And then here's where we stand about a
07:41month ago. So you can see that prominant
07:44building is being built, but you can see
07:45there on the left side where the um the
07:48show office is all finished out and
07:49we'll look uh closer at that here in the
07:52next few slides. I'll say we're looking
07:53around the prominade because it built is
07:55built right up to it. Just a note that's
07:57not part of the project, but you can you
07:59can see how it's going to connect to it.
08:01Um, coming around the other side, you
08:02can see the roof extensions there. That
08:04roof was one of those change orders. We
08:06decided to go ahead and replace the
08:07entire show office roof. So, much better
08:10situation now with a full new roof on
08:12that show office. Um, and then coming
08:14around to the other side, you can see
08:16how it um extends on the uh on the east
08:19side there.
08:21going more at ground level. You can see
08:23that nice uh flat area so that the
08:25connector can come right up to it. Those
08:27double doors will open right into the
08:29the prominod connector. You can see how
08:30the materials are really seamless from
08:32the super barn into the show office. So,
08:34we were able to match all the materials
08:35of the superb barn to make this look
08:37like it's always been there. Uh same on
08:39the east side. Once again, you can see
08:41how the prominade is is abudding the new
08:43show office. And then hopping inside, uh
08:46this is looking at from the existing
08:48show office towards the new extension
08:49portion. We didn't really do any work.
08:51The only thing we did was uh to paint
08:53this full kind of corridor and tunnel so
08:56that everything looked cohesive. But as
08:58we step into the other end of this
08:59corridor looking back, um really just
09:02gives them a nice big open flexible
09:04space and closes off where that wall was
09:06removed. So this is a very basic space,
09:09but it'll be actually really really
09:11useful for the fairgrounds. And this is
09:13where their operators come in. So if a
09:15quarter horse show is coming in here,
09:16this is where they'll kind of set up
09:17their offices for the two weeks. And
09:19this is a nice big open space for them
09:21to utilize. Once again, looking back, we
09:24put in the windows there. So, you'll be
09:25able to see the competitors that are
09:27coming to and from from the tunnel uh
09:29into the the connector building uh
09:31through those windows there.
09:33And once it's all completed, that's what
09:35it'll look like as the prominog connects
09:37the coliseum over to the superb barn
09:40system. And the show office is on the
09:42right side of that prominade.
09:45That's what I've got for you today.
09:47Happy to present final completion of
09:49this project.
09:50>> Okay. Any questions?
09:53Okay. Kevin, did you from the venue
09:55committee? Anything?
09:56>> No, we had nothing. We're just grateful.
09:59>> Check. [laughter]
10:00>> Y.
10:01>> Yes. Agreed. Okay. Thank you so much.
10:04>> With that, I would take a motion and a
10:05second to approve for final acceptance.
10:16No, I'm not getting it.
10:19Oh, I don't think it's
10:32>> I'm not
10:43just There we go.
10:47further south. [laughter]
11:00Okay, the motion passes. Thank you. Item
11:032D, recommend adoption of resolution
11:05ratifying and approving agenda number
11:08one, two, three, and four for the maps
11:11for multi-purpose stadium. Um, package
11:14number four. Um, okay, Mr. Todd, I'll
11:18let you kind of go through all of that.
11:20>> Remember that this is a different uh
11:22type of project delivery that we have on
11:24this project. It's construction
11:26management management at risk. So,
11:28you're seeing all the little pieces that
11:29are coming to you each time. So, this
11:31package, you can see the list, fencing,
11:34canopies, mill work, overhead doors,
11:37security system, all these items. Okay.
11:40>> Any questions on this item?
11:43Not. I would take a motion and a second
11:45to approve.
12:06Okay, the motion passes. Item 2E, we do
12:09have a correction. Um but as it reads,
12:13recommend adoption or resolution
12:15ratifying and approving agendas number
12:17one and two for the maps for
12:19multi-purpose stadium packet bid package
12:22number five um again at risk um
12:26management at risk. So
12:28>> right, so [clears throat] the difference
12:29in your amendment versus what was in the
12:33in the agenda originally, we
12:36accidentally put in there that we're
12:37awarding 5.6 athletic equipment. that is
12:40not being awarded. So that is taken out
12:43on your revision. The numbers are all
12:45still the same.
12:46>> Okay. Any questions?
12:49>> Okay. If not, I would take a motion in a
12:51second to approve.
13:12Motion passes. Thank you. Item 2F,
13:15recommend approval of amendment number
13:17four to the construction management at
13:19RIT services contract with Lingo
13:22Construction for the multi-purpose
13:23stadium um for with an bid package
13:28numbers four and five amending the
13:30guarantee maximum price to
13:32$19,747,56427.
13:39>> So this is the amendment that we always
13:40do after we get these bids. We bundle
13:43what you just approved in items D and E.
13:45They're um bundled into the existing
13:49amount and added to it. So it's it's
13:52it's just a cumulative effect on the
13:54contract.
13:56>> Any questions? If not, I take a motion
13:59and a second to approve.
14:09>> The numbers were always right.
14:16The motion passes. Thank you. Item 2G,
14:18construction update on the maps for
14:20Oklahoma City, Louisa Mchune Animal
14:23Welfare Center.
14:24>> So, we're about six weeks from
14:25completion on the animal welfare center
14:28and thought it would be nice to show you
14:30what's
14:32completed so far. So, Todd Edmonds is
14:34here to take you through uh construction
14:36progress.
14:37>> Welcome, Todd.
14:38>> Great. Thank you, Mr. Todd. U glad to be
14:41here this morning to present to you an
14:42update on the Oklahoma City Louisa
14:45Mchune Animal Welfare Center. Um this
14:49will be the October update and uh we'll
14:51just go through uh a few construction
14:54photos to show you the current status of
14:56the project. It's moving along nicely.
14:58We'll have some cost updates and request
15:00approval of change order number seven.
15:03And then I'll uh briefly go over the
15:05current schedule.
15:08So this is uh the existing site plan. Uh
15:11the new so this this building will be
15:14built or this project will be built in
15:15two phases. Phase one is the main
15:18building there as you see on the top of
15:20the slide. That will be phase one and
15:22that will be completed um here at the
15:25end of this year. Um and then once phase
15:29one is completed, they will um move out
15:32of the existing building into the new
15:34building and then phase two will will
15:36start which is the large animal barn
15:38pasture and some additional parking.
15:42So here's a look of at the current uh
15:44status of the project. Most of the
15:46exterior materials have been installed.
15:49All of the doors, lights, uh doors, uh
15:52windows, siding. Uh this is a look as
15:55you would come in off the main entrance
15:57off of Bryant. Looking straight at the
16:00two-story uh atrium lobby entrance. And
16:03then to the left of that is the
16:05community room. To the right of that is
16:08the intake lobby.
16:11And then here's a look also from the
16:13east side of the building looking
16:14towards the southwest. Um in the
16:17foreground there is the clinic entrance.
16:20Um and then the other entrances that I
16:22spoke about. uh the intake, the
16:24adoption, and the community uh as you go
16:27south.
16:29So, you can see all the concrete work up
16:31at the main entrance is being completed.
16:33Uh landscaping will go in soon. Um and
16:37then uh some of the finished uh saw and
16:41other materials will be applied. So,
16:44here's another look uh looking towards
16:46the northwest. Again, that same east
16:49entrance uh of all the main entries.
16:52Here's a look at the south side uh
16:55looking towards the north uh northwest.
16:58Uh these this this these are the end of
17:00all of the kennel wings and you can see
17:02here most of the uh exterior finishes
17:04have been applied. Uh the exterior
17:07siding, the concrete block ways coat
17:09doors, windows, the roofing, all of that
17:12is wrapping up.
17:15And then here's another look on that
17:17south side. Uh there's a kennel wing in
17:20on to the left of this image. And then
17:22the chain link that you see in the
17:24middle uh that would be uh looking into
17:27one of the adoption playyards. And then
17:30the twotory structure to the right of
17:32that is uh adoption kennels on the lower
17:36level with office space on the second
17:38level where those upper upper floor
17:41windows are. Those those are all
17:42offices. And then to the far right of
17:45that is the community room.
17:48And then this next image is as if you
17:50were standing inside uh that adoption
17:53playyard looking back towards the south.
17:55Um the kennel wing is on the right. You
17:57can see all the windows uh that we've
18:00added for natural light uh to provide
18:03natural light into the to the kennel
18:05area. The artificial turf is installed.
18:08And then you can see on the left are
18:10some of the adoption kennels uh with the
18:12office space above.
18:15Here's a look at one of the uh lobbies.
18:19This is the clinic lobby. So, you can
18:22see there's a a rendering up in the
18:23right hand corner shows what u what we
18:26had designed this to look like and it's
18:28becoming very close to to um what we had
18:32imagined. Uh you can see here the the
18:34concrete floors have all been polished.
18:37The reception desk is being installed.
18:39The accent pane is up. the trusses are
18:42in and they're in the process of
18:44installing the um sealing product
18:48between the trusses.
18:51And then this is the intake lobby which
18:52is very similar to the clinic lobby. Um
18:56it will it just has different accent
18:58color. Uh there will be a reception desk
19:00where you see the large toolbox there.
19:02Uh and then there will be furniture in
19:04the uh large open lobby area.
19:09This is the two-story adoption lobby. On
19:12the left will be dog kennels and on the
19:15right right hand side will be cat
19:17kennels. Straight ahead there is a large
19:21uh reception desk where you would check
19:23in. Um and then there's a supervisor
19:26office uh right to the left of or just
19:29to the left of that uh check-in desk.
19:31All the glass up on the on the second
19:34level is looking up into the office
19:36area. And then you can see here the
19:38trusses, the wood trusses are installed
19:41and the ceiling product is currently
19:43being uh installed as we speak.
19:48This is the community or training room.
19:50Uh here the ceiling grid is in the light
19:53fixtures are installed. The pol the
19:56concrete floor is polished. Um we're
19:59getting very close to wrapping up this
20:00room. Uh once it's cleaned up, they'll
20:03start installing the the ceiling tiles
20:05and this this room will be near
20:07completion.
20:09This is a surgery area. The floors are
20:11being prepped for epoxy
20:15and once the walls u and the ceiling are
20:18complete, they will start installing
20:19that epoxy on the flooring.
20:23This is the long uh north south corridor
20:26that is the adoption wing. Uh this is
20:29this is part of what you saw in some one
20:31of the uh earlier photos that that had
20:33exterior uh kennels. These kennels have
20:37uh doors that slide up and open up so
20:39that animals can go both inside and
20:41outside.
20:43And here they're prepping uh was
20:45actually out there yesterday and they're
20:47installing epoxy flooring in this area.
20:50Uh should be complete today.
20:53And then this is a typical kennel wing.
20:56Um, you can see the kennel uh caging is
20:59installed. Uh, they're installing and
21:01the light fixtures are installed.
21:03They're currently installing ceiling
21:04tiles here and epoxy flooring.
21:08Another kennel wing, very similar. Uh,
21:11they're prepping for epoxy and epoxy
21:13flooring and ceiling tiles.
21:17This is one of the cat condo areas and
21:19you can see in the rendering up there,
21:21it will have cat condo uh caging along
21:25both sides for the cats.
21:28There are several of these small rooms.
21:33Um I want to run through all of the uh
21:37costs, current costs
21:40um and present change order number seven
21:43for for your approval.
21:46Um, I talked about a lot of epoxy
21:48flooring throughout the facility that's
21:50being installed. That epoxy flooring
21:52requires um a certain level of moisture
21:56content in the concrete. And our
21:58concrete had a very high level of
22:01moisture. So, in order to proceed with
22:04installing that epoxy and getting it to
22:06adhere, uh, an epoxy uh, primer is
22:10required to be installed first. So
22:13that's what this $81,653
22:16is for. Um, we changed the name of the
22:20facility to the the Louisa Mchune uh
22:23Animal Welfare Center, which also
22:25enlarged the signs and added some
22:28letters to the to the previously
22:30designed signage. The total for that
22:32change is $28,992.
22:37There was a roof drain uh that was
22:40rerouted and modified for $5,563
22:45in the exterior u playards for the
22:48adoption. Uh there was a a concrete
22:51block cap added to one of the walls in
22:55order to install fencing on top of that.
22:58Uh throughout the and and that cost is
23:01$3,72.
23:04Uh the majority of this facility has
23:06concrete block walls uh with aluminum
23:08door frames um in order to prevent
23:11rusting and durability. Um and those
23:14frames required some additional wood
23:16blocking to be installed in the concrete
23:18block. And the amount for that is
23:21$22,21.
23:24Uh there was some additional framing uh
23:27requested by the operator to provide
23:30visual and acoustic privacy and the cost
23:33of that is $8,981.
23:39The operator also uh requested some
23:41additional security camera locations
23:43throughout the facility. Uh the cost for
23:46that is $5,628.
23:50Uh we previously had to redesign the
23:53detention pond to avoid an existing gas
23:57line on the property. Um and because of
24:00that redesign, some additional trees
24:02need to be removed.
24:04Um
24:06there was some exposed steel in two of
24:08the lobbies that we have added some wood
24:11veneer uh to match those wood trusses
24:13that you saw earlier uh to to create
24:16some box beams. And that uh turned out
24:19it looks really really good. Uh they've
24:22completed that work and the cost of that
24:24is $2,100.
24:27And then a a gypsson board ceiling was
24:30added in the main vestibule for $2,845.
24:36And then a metal shroud was added around
24:40some uh drainage piping to prevent any
24:44future damage to nearby electrical
24:47equipment. And the cost for that is
24:49$4,000, [clears throat]
24:51excuse me, $4,94.
24:54So the total change order number seven
24:57is $168,281.
25:02The original contract amount was 34
25:04million 258 or 257
25:08[clears throat]
25:09and the previously uh approved change
25:12orders
25:14total 1,225,528.
25:19Excuse me. Drink of water.
25:21>> Almost got there.
25:22>> Almost got it.
25:27Excuse me. So the new contract amount is
25:30$35,650,86.
25:35So change order 7 represents uh an
25:38increase of 049%
25:41of the overall budget
25:44and all change orders 1 through 7
25:46represent a total increase of 4.07%
25:50over the original contract amount.
25:54Uh
25:56so
25:57all of the change so change order 7
25:59added 18 days uh to the total schedule.
26:03So for all change orders 1 through 7 the
26:05total number of additional days
26:08is 163 uh days.
26:13Sorry got to get some more water.
26:19So, uh, the original completion date was
26:21January 25th of 2027.
26:25The new completion date is now July 7th
26:27of 2027, but that includes both phases,
26:30phase one and phase 2.
26:32>> Okay.
26:34>> So, phase one substantial completion is
26:36is nearing. Uh, it is scheduled for
26:39November 17th, which is also the date we
26:41have scheduled uh for our ribbon
26:43cutting.
26:45And then phase two, which will be the
26:46large animal barn, that's scheduled for
26:48July 7th of 2027.
26:52>> Okay. Any Thank you, uh, Mr. Edmonds.
26:56So, any questions um for Mr. Edmonds?
27:00Yes, Jesse.
27:05>> Thank you. Exciting to see the progress.
27:07I think everybody's pretty excited for
27:09this to come to life. I'm curious about
27:12uh budgeting and contingency and where
27:14we stand on all that. I know that we've
27:16previously had a general, you know, we
27:18have about 3% I think of a contingency
27:20budget built in. Where do we stand on
27:22this project?
27:24>> I don't have the amount in front of me,
27:25but I know unless Todd knows what what
27:27it is, but we're still within our
27:29contingency amount, we still have that.
27:31>> We're we're okay is what I can say.
27:34Unless you know what the number is. Uh
27:36the number I remember from the meeting
27:38earlier this week was 900,000.
27:40>> That's right.
27:41>> Remaining. That's right.
27:42>> Okay. So despite the contract amount
27:44being we're 4% over the contract amount,
27:46that still is within a healthy
27:48contingency of just about 900,000.
27:50>> That's correct.
27:51>> Okay. Thank you.
27:52>> Great. Any other questions?
27:55Okay. If not, thank you so much.
27:57>> Thank you.
27:58>> Okay. Item 2H, recommend approval of
28:00change order number seven with Crossland
28:02Construction Company for the MAPS for
28:04Oklahoma City Louisa McHune Animal
28:07Welfare Center for an increase of
28:09$168,281.
28:21Motion passes. Item two, I recommend
28:23approval of preliminary report maps for
28:26use centers phase two.
28:28>> As you know, we just did a
28:29groundbreaking on youth center one and
28:32um Kale Wilson from Design Architects
28:35Plus is here to show you the preliminary
28:37report for you center 2.
28:39>> Welcome.
28:40>> Thank you, Mr. Todd. We're excited
28:42today. Start I know you just had the
28:44groundbreaking which is exciting, but
28:46we're starting on phase two. Again, the
28:48objective for all the youth facilities
28:50is to create community focused
28:51facilities in Oklahoma City. This one is
28:54located in South Oklahoma City. A map
28:57here shows you the general location of
28:58I240. It's just north of that off of
29:02Santa Fe between Santa Fe and Shields.
29:05A closer look at the site itself. This
29:08is a large site. Uh it's 12 plus acres.
29:11This building is 72,000 square feet. Has
29:14significant parking, which is always
29:15nice for a youth facility. Uh, and it
29:18does have an existing two-story facility
29:20with an elevator, which is nice. Uh,
29:22some brief pictures of the outside of
29:24what it sits like today. Uh, take focus
29:26on the top one because you'll see the
29:28change between that and what it's going
29:29to be today. A few pictures on the
29:31inside as well. Some of this will be
29:33removed during this project.
29:35Again, some [clears throat] additional
29:37pictures of the existing gym, youth
29:39fellowship, and dining hall as well.
29:42The project itself, uh,
29:46the building itself has been added on to
29:48several times. Every color on here is
29:50really a different a different addition
29:52to this existing project. Again, it's
29:55two stories as well. Uh,
29:58the second floor is not over the entire
30:00facility. Uh but this project the
30:04outline you see in red uh that area of
30:08the building will be removed for our new
30:10additions. We will keep the existing in
30:13yellow and green and remodel those
30:15facilities.
30:18It will leave 42,000 ft of the existing
30:21facility. So we remodel that portion of
30:24the building. Uh if you look at the
30:26proposed site plan again, we have a I'll
30:29call it a light orange. I'm not sure
30:30what color that is. We talk about
30:32remodeling the gym in the south portion
30:34of the building. The blue is the new
30:36addition. Uh the red is also a new
30:39addition. We highlighted that because
30:41that will be a tornado shelter uh that
30:43was requested uh for this project as
30:46well. Again, you can see we reid the
30:48parking just on the west side towards
30:50Santa Fe. Uh we also have proposed
30:53soccer fields just off the screen as
30:55well as football and basketball courts
30:58there in blue in the parking lot. Uh
31:00there's several other items you'll look
31:01at as alternates later in this project
31:03where we call a courtyard for the early
31:05childhood area as well as the outdoor
31:08area for teens and a playground area
31:10which are on the far right hand side of
31:12this project.
31:15We look closer just at the floor plan
31:17itself. Uh we've kind of broken it off
31:19into areas. So you can see student areas
31:21compared to administrative areas. Uh the
31:24lobby being the main entrance off Santa
31:26Fe to the west. The admin is directly
31:29south of that. And the area that's
31:32labeled early childhood center is the
31:34tornado shelter. Again, we put the
31:36younger children there. They don't have
31:38to travel very far. Uh same with
31:40elementary age kids, which are down the
31:41south hall, elementary lounge. Uh again,
31:44they're the shortest travel between
31:45there and the shelter space as well.
31:48Uh, as you go to the east into the green
31:50area, it's a really all existing space.
31:53It's a great dining room space, a great
31:55gymnasium space, and on the far right
31:58hand side, we don't put the teens far
31:59away from each other, but they like to
32:01be by themselves over to the side, but
32:02they have a great teen lounge area.
32:04We'll show you here in just a minute as
32:06well. You'll notice there are two
32:07entrances, one out to the front of the
32:09building as well as a entrance to the
32:11south that works well for them for after
32:13hours facilities as well as a teen
32:15entrance separate from the younger
32:16students.
32:19We go to the second floor. Uh we have
32:20middle school children in the south wing
32:23and really everything in the green area
32:25is used by everybody from a dance floor
32:28to art rooms to music rooms.
32:31Here's
32:33a building as it sits today looking from
32:35Santa Fe in front of you. Here is the
32:38proposed look of that building today.
32:40Again, if you remember, we tore down the
32:42buildings in front of it. Uh the red is
32:44an existing building and actually the
32:45building to the right is existing. We've
32:47just put a new veneer on it.
32:51We look at different materials. We're
32:52trying to blend with the existing
32:54building as much as possible. Again, we
32:56have brick accents, stone accents, as
32:58well as metal panels and ephus on the
33:00building.
33:03A few more looks. You can see the
33:04basketball court and football court in
33:05the background. Uh, as well as some play
33:08areas in the background.
33:12Just a little closer look at the main
33:13entrance. This is still looking from
33:15Santa Fe, really kind of towards the
33:16southeast.
33:19If you go behind the building, we talked
33:21about the teen entrance and and
33:22basketball gymnasium entrance. This is
33:24really an existing building that works
33:26great for this facility as a drop off
33:28area. Again, the fenced in area you see
33:31to the right hand side is really the
33:32outdoor space for teens.
33:36This is looking back from the north. Uh
33:38between those two buildings was the
33:40early childhood play area. That one was
33:41the blue canopies as well as the uh
33:43storm shelter there on the north end of
33:45the building. A little closer look at
33:48the area between for the younger
33:50children.
33:53Again, back to the front entrance. We
33:54put this here because everyone always
33:56likes a night shot. So, we we try to put
33:58night shots in there. Uh again, we have
34:01a few of these pictures that you can
34:03look at at night. Again, this is looking
34:04from Santa Fe back towards the facility.
34:09But we're not done. And since we go
34:11inside the building, this is a picture
34:13looking at the front entrance as if you
34:14walked in the front door with the uh
34:17reception lobby. The reception desk is
34:19on the right. The hallway you see
34:21directly in front of you is the hallway
34:23that goes all the way down to the
34:24gymnasium. Uh we have some learning
34:26stairs and some waiting areas that when
34:28the kids get picked up, they can have a
34:30waiting area inside the lobby space.
34:33Uh again, we're just looking to the left
34:35now. That actually goes into the early
34:37childhood, which would be the tornado
34:39shelter in this case. Again, with a
34:41small seating area.
34:45We're just looking back towards the main
34:46reception desk with the elementary down
34:49that hallway.
34:51We labeled this. Make sure no one gets
34:52lost.
34:54Again, this is looking from the learning
34:56stairs back towards the main entrance of
34:58the facility.
35:00The middle school entrance is up the
35:02stairs uh to your on your left hand
35:04side.
35:06A shot inside the early childhood area.
35:09Again, we're staying with the same color
35:10palette and this has really been
35:11coordinated with the Boys and Girls
35:13Clubs as well.
35:14uh to create exciting spaces for them.
35:18Again, just another shot in there. We go
35:20down to the gym area. If you remember,
35:21the gym early was pretty plain. Those
35:24existing pictures back, uh we've really
35:26refinish the floor. They already had a
35:28gym floor. Uh we'll obviously add paint.
35:31Uh we added some side goals as well. And
35:34off to the right, you can see the teen
35:35club entrance, which is uh the doors to
35:37the right, and we'll look at that here
35:39just in a minute. The one unique place
35:41about this, this gym actually has a
35:43walking track around it. And that's an
35:45existing walking track that we'll take
35:46advantage of as well.
35:49And here is the teen area. Uh again,
35:53it's an open space. They have multiple
35:55areas that they use from sitting,
35:56reading, computer labs.
36:02The budget, uh we started with a $9.5
36:05million budget. There was funding added
36:06in the geo bond that brought us up to a
36:09$14 million budget. Right now, the
36:11estimated construction cost is around
36:1313.9 million.
36:16We do have alternates on the project and
36:18and really we try to make these
36:19alternates fairly simple to bid as well.
36:21If we don't get them, fairly simple to
36:23buy. These are the outdoor play areas.
36:25The first one is for the prek and
36:26kindergarten. Uh the next one is the
36:28elementary playground which was the far
36:30east. Uh we also added number three uh
36:34during the first project uh they added
36:37this as a request so we added it as well
36:40just in case that we have the same dance
36:41floor that they had in phase one. Again
36:44there's some additional uh furniture and
36:46equipment that was needed uh and the
36:49sports soccer field as well as the
36:52football and basketball court will be
36:53alternates. And the last item there is
36:55some existing parking lot repairs. Uh
36:57the parking lot's not in bad shape.
36:58There's a few places we need to patch
37:00and repair, but we also like to put an
37:01emulsion coat over so it looks all brand
37:03new when it's done with new striping.
37:05So, just for a nice finished look and
37:07that's really over the existing parking
37:09lot. The new will be in front of the
37:11building to the west already shown on
37:12the site plan.
37:15You look at the schedule. Uh we'll go
37:17through the plan council completion of
37:20construction documents. Uh the exciting
37:22part here is uh starting in June or July
37:26of 2027 and ending in winter of 28
37:32with that.
37:34>> Any questions?
37:37>> Any questions? Okay. Fantastic. It looks
37:41great.
37:41>> Thank you.
37:42>> We're excited.
37:43>> Appreciate you.
37:45>> Okay.
37:46Um, so with that, recommend approval of
37:50Oh, whoops. Get back to computer.
37:52Recommend approval of the preliminary
37:54report.
38:12Our
38:23system is a little sleepy this morning.
38:25>> Yes, exactly. Yeah.
38:27>> Yeah.
39:06You want to just do a verbal vote?
39:16>> Yes.
39:17>> Yeah.
39:18>> You need a motion, right? I'll move
39:20approval.
39:21>> Move.
39:21>> I'll second.
39:22>> Okay, we've got a motion and a second.
39:24All those in favor, please say I.
39:26>> I.
39:26>> Any oppose? Same sign.
39:28>> Okay,
39:29>> got it.
39:33>> Okay. Item 2J, recommend approval of
39:36final plans and specifications to be
39:38approved and advertised for bid for the
39:40maps for neighborhood and community
39:42parks phase 1 C.
39:43>> So, this is 1 C. We've already done A
39:46and B. Darren Scott from Kimley Horn.
39:50Darren Scott from Kimley Horn is here to
39:53show you what's in these plans.
39:55>> Oh, good morning board. Uh yeah, excited
39:57to uh show you the final bid package for
40:00uh phase one of the uh neighborhood and
40:03community parks. Uh this was part of the
40:05preliminary report that was approved
40:07back in December of uh last year uh that
40:11went through the the master planning
40:12process and then the the public outreach
40:15in coordinating with the parks
40:16department. Uh so the budget on this uh
40:19is about $5.1 million. Of that there's
40:23$650 or $650,000 of 2017 bond money that
40:28was included. Uh and then the park
40:30specific funds that were dedicated in
40:32the MAPS resolution specifically for
40:35Washington Park. Uh right now u the
40:38opinion of probable cost uh we're
40:40sitting at um a little under five
40:43million on the base bid with some
40:44alternates. So, we're we're under the
40:47the fixed limit of construction cost
40:49right now.
40:51Uh this uh master plan here was done
40:53during the master planning process. Uh
40:56we wanted to take a full look at the
40:58park uh and see what the the full vision
41:00would be knowing that this would be
41:02beyond the budget of what the mass fund
41:05would provide. Uh but uh wanted to make
41:08sure everything was in the right place.
41:09So, this was approved through the the
41:11previous master plan. Uh and then since
41:14that time we had stakeholder meetings um
41:17and determine what was the priority of
41:20those improvements to be done. So this
41:22is what uh we landed on. Uh the priority
41:25was the playground splash pad area, the
41:27sports court areas um and then a plaza
41:30up at uh Fourth Street and and High
41:33that's just right across from the
41:34Patriots and development. And then in
41:36addition to that enlarged parking lot to
41:39to u accommodate all the the
41:43improvements. Uh here is an enlarged
41:45look of that plaza. So this is
41:48essentially u the corner of fourth
41:50street and high. So like I mentioned
41:52before, Paige Woodson is across the the
41:54road. This is also along fourth street
41:56which is getting a streetscape
41:58improvement through the innovation uh
42:00project and other maps project. So close
42:03coordination with that project as far as
42:05materials um and amenities. So this will
42:08tie in nicely to that project as well.
42:11Uh one of the uh desires was to be able
42:13to have events um small events in a in a
42:17plaza space. So this accommodates that
42:19uh farmers market uh any other kind of
42:21special smaller gatherings u in that
42:25area.
42:26Uh the other uh area that that we'll
42:29look at is the sports court area. So,
42:31this includes four basketball courts, a
42:33football court, two full-size tennis,
42:36uh, and then three dedicated pickle
42:38ball. So, really nice space, uh, with,
42:41uh, shading. So, a pavil alternate
42:44pavilion there next to footsaw and then
42:47small shading uh, canopies in between
42:49those those fields or those courts.
42:53Uh, the parking lot, as I mentioned,
42:55it's increased in size uh, and and
42:57redone. So, this provides more capacity.
43:00We also added a speed table to it. So
43:02there there has been some um people
43:06going around and around uh tearing up
43:09the parking lot and not creating a safe
43:10environment. So the speed table will
43:12help curtail the the the drifting around
43:15the the edges there. So a nice nice
43:18addition. It also will tie into the
43:20potential legacy trail that's on that
43:23south side of the property. Uh that
43:24could serve as a trail head for it as
43:26well.
43:28uh the playground space. So, we have it
43:31broken up into a few different areas. Uh
43:34smaller uh kids space, 2 to five age
43:37range, a 5 to 12, and then a splash pad
43:40with a center grass berm area in
43:43between. So, a really nice enhanced
43:45playground for this park uh over what it
43:47currently um has. Here's a a few
43:50renderings of that larger space. So,
43:53this is the the 5 to 12. So you have
43:55towers, you have some embankment slides,
43:58um and then some some ADA accessible
44:00ramps too that that go up to different
44:02levels. So a fully inclusive uh
44:05playground.
44:07This is an view of the smaller 2 to five
44:10age range. U so again smaller elements,
44:12some more interactive panels uh on the
44:15ground and then some u ADA and universal
44:19design features in that as well. And
44:22then the splash pad uh tying in u the
44:26the theming, the colors and everything
44:28tied together um using u using that
44:31between and we have some some larger
44:33water elements and then some smaller
44:34ground sprays. So a wide range of u a
44:38groups can can use it. And then this is
44:40a be a fly through of what that space
44:45looks like. So as I mentioned there's
44:46there's swings there. You can see the
44:48companion swings going together. those
44:50embankment slides and and burned area.
44:53This is all turf um in the for the the
44:57play surface. Um and then you can see
44:59yeah different side slides and then the
45:01the tower uh and then those ramps. Uh
45:04you can see you can get up to those
45:06different levels uh going through there
45:09and then the the larger slides coming
45:11down off that tower. Um, and once it
45:14gets through this, it'll move over to
45:15the the kids uh play area or the two to
45:18five year old play area.
45:21You can see some some theming that that
45:24can be done. And and as far as the the
45:26colors and everything that can be
45:27selected uh and refined as we we get
45:30into shop drawings for this. Um so
45:34here's the the smaller kit area. So
45:36spinners, some play panels, smaller
45:38slides. uh still have the embankment um
45:41slide area and then climbers there as
45:44well
45:46uh to to go in. You can see those colors
45:48tying together. That center area is that
45:50grass berm which is turf as well. It
45:53kind of blends with the other but um it
45:55is just an open burm area. And then
45:57here's the splash pad with bigger water
46:00dumping bucket u some interactive play
46:03features and then some of those small
46:04ground elements as well.
46:07So that is a fly through of what the
46:10playground looks like. Uh schedule uh we
46:14uh pending approval from from your board
46:17and council in October. The notice to
46:20biders will go out in November. Notice
46:22proceed uh in December time range and
46:25then a 365day schedule. So uh next
46:28December would be when this would be
46:30completed. So
46:32>> but that is there any questions?
46:33>> Any questions?
46:36That looks fun. I was gonna say I think
46:38that looks really fun.
46:40>> Um, thank you.
46:41>> So, with no questions, I take a motion
46:43and a second to approve.
46:54[clears throat]
47:04We'll just do a verbal vote again. Um,
47:07>> motion to approve.
47:08>> Okay, so we have a motion and a second.
47:11Shay. Uh, all those in favor, please say
47:13I.
47:14>> I.
47:15>> Any oppose? Same sign.
47:17>> Perfect. Okay. Item 2K, recommend
47:21approval of change order number five
47:22with Shiloh Enterprises for the MAPS for
47:25South Lakes Park Improvements for an
47:28increase of $1,32.
47:30>> This is a change order for a gas
47:32service. OMG will put in 100 ft of line
47:36and after that they u expect
47:39reimbursement. So we needed 800 feet. So
47:43this is $1,000 for 700 feet of line. I
47:46think it's a pretty good number.
47:47>> Okay. [laughter]
47:49Okay, any questions?
47:52Okay, if not, uh, let's just do verbal.
47:55Okay, I take a motion in a second. Okay,
47:58Joy moves. Whoops. Are we move? Okay,
48:01it's actually working.
48:04Okay.
48:09Okay, the motion passes. Item 2L,
48:12construction update on the maps for
48:14family justice center. A lot going on
48:16with the Family Justice Center and Dan
48:19Hayes from AHMM is here to show you all
48:22those great things they're doing out
48:23there.
48:24>> Hi Dan.
48:24>> Hi.
48:25>> Thank you for being here.
48:26>> Delighted to be here today to give you
48:28an update on uh Mapsville Family Justice
48:30Center. There's a lot happening on site.
48:33If you've been to Midtown recently, you
48:34would have seen it looks very different
48:36than the image that you see in front of
48:38you. Uh but just to orientate everyone
48:40uh that the project site is directly
48:42opposite the existing Palomar building
48:44um 11th Street to the north, Hudson to
48:47the east and Parkplace to the south.
48:50This is was original CGI uh that we
48:52proposed of the building. Um and this is
48:55where we currently sit today. So on the
48:58first floor, the the brick work is is
49:00nearly complete now around the whole of
49:02the building. Um the the windows are
49:04almost in. You can see there just on the
49:06corners the they're the missing some
49:07glazing, but apart from that we've we're
49:09moving pretty uh pretty quickly uh on
49:12getting the building watertight. Um and
49:15it's it's starting to come together.
49:17This is another view uh of the CGI
49:19looking down Hudson uh on the corner of
49:21Hudson 11th at the back of the building.
49:24Um this is what this currently looks
49:25like now. So in this um view all of the
49:28brick work is complete on the first
49:30floor. Uh the glazing on the on the
49:32second and third floor as I said is
49:34almost in and uh they are commencing the
49:38cladding panels uh on the black strips
49:40that you see there the horizontal black
49:41lines.
49:43Moving inside the building uh this is a
49:45view of the reception area u uh on the
49:48right of the image there is the where
49:49the reception will be on the left is the
49:51waiting area uh and and in the distance
49:53there is the entry into the building u
49:56uh through to the courtyard space. So
49:58that's how that's proposed to look and
50:00and this is where we currently stand
50:01today. So they're currently working from
50:04the third floor down. So the third floor
50:05is the most finished and the first floor
50:07is the least finished. But you can see
50:09all the mechanical equipment has now
50:10been installed. The starting on the
50:13framing uh and the drywall uh and the
50:16block work that you see there is um it's
50:19not an official storm shelter, but it's
50:21a hardened area of refuge uh for severe
50:24weather uh which has been completed.
50:27Uh just another look there on the
50:28outside of the entry. U that brick work
50:31is now complete. Uh you can see some of
50:32the texture patterns there uh on the
50:34left to that and starting to look really
50:36good. Uh this is the uh cafe area on the
50:41corner of Hudson and Park Place. Uh this
50:43was a original CGI. This is what this
50:47space currently looks like. So again,
50:49MEP uh equipment is all in place and
50:52they're starting to uh wrap up there
50:54with the internal walls uh and the
50:56drywall. You can see there on the left
50:58that big gray box. Uh exciting
51:00milestone. The site now has permanent
51:02power uh which is a which is a big step
51:04forward. So uh they're making good
51:06progress. There's another view of that
51:09space looking towards where towards
51:10where the counter would be for the for
51:12the coffee shop.
51:14Uh this is the children's sanctuary area
51:17inside the building. Um this was the
51:19original CGI. I'm excited to report that
51:22the the slide is definitely happening
51:24now. We have shop drawings. They've been
51:26approved and it's in it's in production.
51:28But this is what that space currently
51:30looks like. So big tall double height
51:31space, lots of natural light. Uh they're
51:33just finishing up there with the framing
51:35and the and the drywall.
51:38Moving around to the back of the
51:39building, um where we have the courtyard
51:41space. Um
51:43this is uh where we where we uh where we
51:46were with the CGI uh and this is
51:48currently where the building stands. So
51:50you can see this is where they're most
51:52uh advanced with regards to the
51:54cladding. All the grit work is complete.
51:56The windows are in and you can see there
51:58at the top uh the metal panels um are
52:01starting to go in which is an exciting
52:03moment.
52:05Uh moving up to the second floor. Uh
52:07this is the the partners floor. Um and
52:10this is the central space, collaboration
52:12space, uh break space, um with a kitchen
52:15and an outdoor terrace. Uh and this is
52:18where we we currently stand. So that you
52:20can see there uh all the uh the kitchen
52:22is starting to go in and you can see the
52:24the glazing going in there to the uh
52:26terrace area uh looking out over the
52:28city. Uh this is the office space uh in
52:32in the partner areas. So there's open
52:34office space in front of you. On the
52:36right there are cellular offices. Uh the
52:39doors and glazing to those offices is
52:42currently being installed and the
52:43external glazing there to the left is is
52:46complete.
52:47Moving up to the third floor. Uh this is
52:50a community space uh with views out over
52:52the city. Uh and it's currently looking
52:55like this. So it's actually progressed a
52:56little bit further from when this image
52:58was taken. They're now started to paint
53:00the walls uh and the glazing is in uh as
53:03well at the end there.
53:06Uh that's just another view of the one
53:08of the breakout spaces that community
53:10room and another external terrace space.
53:12But you can see there on the walls there
53:14the right that first base
53:15[clears throat] coat of paint has has
53:17gone in. That's another view of one of
53:20the meeting rooms uh on that third
53:22floor.
53:23And then just a couple more close-ups
53:25here of the brick work which looks uh
53:27really good when you you get up close.
53:29Cross's done a great job. Um and then
53:31moving rounds again some of those brick
53:33patterns uh giving a bit of shadow and
53:36texture to the facade.
53:38Uh exciting update this week as well the
53:40the uh 1% for our artist sent us a an
53:44update here. This is a copper sculpture
53:47uh I don't think you quite get sense of
53:48scale but it it's large uh that sits in
53:51the courtyard. So, as you come through
53:53into the building and and uh look
53:55through into the courtyard, you're
53:56you're faced with this uh sculpture,
53:58which we think will be a really nice
54:00addition to that external space.
54:03So, u we're currently on change order
54:06number seven. Um this is where it
54:08stands. The total is just over $184,000.
54:12And I'll run through each one of these
54:14items individually uh to explain where
54:16that where that money is coming from. So
54:18the first um is a change to the kitchen.
54:21So on the third floor adjacent to the
54:23community space uh there is a kitchen.
54:26Uh the operator initially from day one
54:28wanted that to be a kitchen that they
54:30could cook in. But due to budget
54:32constraints we we took that out um of
54:34the of the design and just made that a
54:36prep kitchen um for serving the
54:39community space. But now that we're over
54:4150% through uh into construction and we
54:44still have a healthy contingency, uh the
54:46operator would now like to move forward
54:47and and have uh the the ability to be
54:50able to cook in that kitchen uh
54:52installed. So that includes a range and
54:54a hood uh and commercial extraction. So
54:57the majority of that 164,000 is to cover
55:00the extraction unit that will sit on the
55:02roof. Uh by doing this work now uh it
55:05saves the operator further cost to
55:07install that later down the line because
55:08we obviously have cranes and things on
55:10site that will be needed to lift that
55:11equipment into place.
55:14Um and the another part of the change
55:17order is uh to move some uh doors. So in
55:20that community space um there there's a
55:23large storage area for the storing of
55:26tables and chairs to be able to
55:27reconfigure that space. the when we
55:29walked the the room with the operator,
55:32they felt that it would be better to
55:33have the doors relocated directly off
55:35that community space instead of uh from
55:38the service corridor at the back. So, uh
55:40those doors had been installed, so we
55:42had to flip those round which uh
55:44incurred the the cost.
55:47Um the operator also uh wanted to add um
55:51in a sink to one of the therapy uh
55:54meeting spaces, group rooms to allow
55:57them to be able to do art therapy. Um
55:59that was slightly challenging with the
56:02um the concrete slab and where we could
56:04run pipes. Um so we have to bring pipes
56:06up uh and be able to plum that uh
56:09additional sink in. So, uh, that's where
56:11the $13,000 comes from, mainly to do
56:14with the infrastructure regarding, uh,
56:16installing the pipe work.
56:19Um, the the lobby area that we showed
56:21you earlier, uh, it was the original
56:23design intent was for that to be painted
56:25green. So, it was the same color on the
56:27outside of the building and it came uh
56:29in into the interior. Uh, green is also
56:32a very calming color. Um, however, the
56:34the operator's keen for that to be
56:35purple, uh, which is the color of
56:37domestic violence and also Palomar's key
56:40color as well. Um, so easy to change the
56:42the paint, um, but unfortunately purple
56:45tiles are slightly more expensive than
56:46green tiles and there's a little bit of
56:48tiling in there at a coffee point which
56:50incurred a slight increase in cost.
56:54Um it's it's hard to believe with the
56:56weather that we've been having recently,
56:58but there were 19 weather days uh due to
57:00to rain and storms between April and
57:02July. Uh so that's the the contractors
57:05asking for additional 19 calendar days,
57:07but obviously no increase to the
57:09contract value.
57:11So this is a a summary of currently
57:13where we stand. The original contract
57:15value was uh about 28.7
57:19million. Um the change orders that we've
57:22had to date to add up to about $520,000
57:25which takes the contract value up to
57:27$29.3.
57:29Um but we have a healthy contingency
57:33still of about $2 million. So as I said
57:36earlier, we're about 50 just over 50%
57:38weight through construction. So we feel
57:40pretty good about where we sit with
57:41regards to the the the contingency
57:43remaining. Um the uh completion date has
57:47shifted slightly um and it's estimated
57:50to be completed in July 7th uh 2027.
57:53We're hoping some of the those 46 days
57:56that you see there under change order
57:58number seven. A lot of that to do is
58:00with the leading time for the extract
58:02equipment that I mentioned earlier for
58:04the kitchen. We're hoping that that can
58:06come quicker uh and that will reduce the
58:09number of additional days required.
58:12Just looking forward over the next
58:14month, um, as I mentioned, they're
58:16wrapping up with the brick work, the
58:19metal panels will be continuing to go
58:21in, uh, throughout October, uh, along
58:24with finishing up the glazing.
58:25Mechanical uh, equipment is is all
58:28installed and complete. Uh, interior
58:30framing and drywall continues. Uh, and
58:32they have just started with, uh, wall
58:35and floor tiling um, as well.
58:38>> And that's it for today. Thank you.
58:40>> Great. Any questions?
58:42>> Any questions?
58:45>> Okay. Thank you so much for being here.
58:46>> Thank you.
58:47>> Item 2M is recommend approval of change
58:51order number seven that we just went
58:53through.
59:05We could move
59:09up just
59:11Okay.
59:13>> Okay. Um, we are going to adjust and
59:16move up item 2 and 2P. So, recommend 2
59:22is recommend approval of change order
59:24number one with L5 construction for the
59:27Oklahoma City Robert Rad Rabbitz crisis
59:32center for an increase of $123,874.99.
59:37don't like starting off projects with
59:40change orders like this, but what we
59:42expected when the building was removed
59:45was a decent pad or or dirt under the
59:49building, and that's just not the case.
59:51It was built in, I think, 1910
59:54originally.
59:55>> Gracious.
59:55>> So, it's been there a while. So, this is
59:57to take out about 4 ft of soil and bring
1:00:00back in engineered soil, compact it um
1:00:04so that we don't have settlement on on
1:00:08the new building.
1:00:09>> Any questions?
1:00:11>> Not. I take a motion in a second.
1:00:22Motion passes. Thank you. Item 2P,
1:00:25recommend approval of change order
1:00:27number nine with EMC services on the
1:00:31maps for sidewalks and related amenities
1:00:34phase 1B.
1:00:36>> So this is a a change order on sidewalk
1:00:38project. It is a no no cost change
1:00:41order. It is just for days. And the
1:00:43reason why we had to add days is because
1:00:46um as we have money still in the budget
1:00:49and we can amend we add more sidewalks.
1:00:52We did those sidewalks on Douglas by uh
1:00:55Southwest Medical. So, um this is just
1:00:58to help straighten out the days that
1:01:01they were owed.
1:01:02>> Okay. Any questions? Not. I take a
1:01:05motion in a second.
1:01:14Motion passes. Thank you. Now, we'll go
1:01:17back to item 2, quarterly report on the
1:01:19maps for homelessness projects.
1:01:24Welcome.
1:01:25>> Right. [clears throat] So, we have a
1:01:26quarterly report. Mark Jill is here
1:01:28today to take you through that.
1:01:31>> Yes. Thank you. For those of you that
1:01:32don't know me, my name is Mark Gilllet,
1:01:34the executive director at the Oklahoma
1:01:36City Housing Authority. Mr. Shen is
1:01:39enjoying some nice vacation time.
1:01:44500 units of supportive housing,
1:01:471,500 units of renovated public housing,
1:01:51and 150 workforce units are the goals
1:01:55for the maps for homelessness program
1:01:58over the 10 years of the allocations.
1:02:05This map shows where allocations number
1:02:08one and number two are being uh located.
1:02:12To look there, there are 10 projects
1:02:16um scattered around Oklahoma City and we
1:02:20will continue to place those projects,
1:02:24new projects in various locations around
1:02:28the city. [clears throat]
1:02:31This is allocations one and two uh chart
1:02:35showing that 1,021
1:02:39units are currently in the pipeline for
1:02:42the MAPS for homelessness program. Uh
1:02:45you'll see each of those listed there.
1:02:48um from those that started back in uh
1:02:512024
1:02:53uh to those that will extend out through
1:02:562029
1:02:58at this point in time.
1:03:03Allocation number one was $10.7 million.
1:03:08You can see that it's 100% committed or
1:03:11expended at this point in time. uh
1:03:14divided among several different projects
1:03:17and we're going to talk about those
1:03:18projects in detail now. Crestston Park
1:03:22phase one which is 28th and 29th Street
1:03:26and Martin Luther King for 170 units of
1:03:31renovated public housing. Um, it's a
1:03:35$2.5 million investment from the MAPS
1:03:39program with a lot of other leverage
1:03:42funds being uh committed to that
1:03:44program. Now, it's important for you to
1:03:46understand that this is a collaborative
1:03:48partnership between uh Restore Oklahoma
1:03:52City, Northeast Oklahoma City
1:03:54Renaissance, Open Design, and the
1:03:57Oklahoma City Housing Authority. Uh
1:04:00there is currently on the street an RFQ
1:04:03for a master developer uh to come in and
1:04:06help the uh neighborhood groups uh
1:04:09redesign Crestston Park. Currently uh if
1:04:12you drove by uh Crestston Park today,
1:04:14you'd see a fence around it because
1:04:16we're uh abating the asbestous that does
1:04:21exist in those properties. And then so
1:04:23in the next couple of weeks, we will
1:04:26actually begin uh demolition of 26 uh
1:04:3028th and 29th Street. And then that
1:04:33master developer will come in and help
1:04:35us plan that property and then hopefully
1:04:38also be able to look at 26th and 27th.
1:04:45Dorset uh Place Veterans Community uh
1:04:48has a $2 million commitment from MAPS.
1:04:5237 units are in place for veterans that
1:04:57uh are formerly homeless individuals.
1:05:01That property is 100% occupied at this
1:05:04time. So, we're very pleased that the
1:05:06partnership with the VA has produced
1:05:09housing for those uh very well-deserving
1:05:12folk. Um phase 2 at Dorset is in the
1:05:17works right now. It will be 33
1:05:20additional units. That's a building
1:05:22directly behind the veterans uh program
1:05:25and will uh determine who will be the
1:05:27occupants of those very soon.
1:05:31Vita Nova permanent supportive housing
1:05:34units of 76 units. Uh the old Motel 6 at
1:05:391800 East Reno. uh that is being
1:05:43converted as we speak. That is a $3.4
1:05:46million commitment from maps. And then
1:05:50these are some of the current
1:05:51construction pictures of Vita Nova. Uh
1:05:55we began demolition in May. So you see
1:05:58the community center on the top of of
1:06:01the three pictures there being uh
1:06:04demolished.
1:06:05And then uh as you move towards the
1:06:08bottom row of pictures, you see the pool
1:06:10that used to be there uh demolished. And
1:06:13then if you look at the far right
1:06:16picture, you'll see what the new walls,
1:06:18the exterior walls to the units uh will
1:06:21look like. And then if you look at the
1:06:23middle bottom picture, you can get a
1:06:26reference of where you're located
1:06:27because that is Okana emerging on the
1:06:30horizon there.
1:06:38Oak Grove Apartments. Uh definitely one
1:06:40of the largest apartment communities
1:06:41that the Oklahoma City Housing Authority
1:06:43owns is public housing conversion
1:06:46project number two. That will be 306
1:06:50units of newly built and renovated
1:06:53public housing. Um, we are pleased to
1:06:57say that we last week received a 4% tax
1:07:01credit allocation from the Oklahoma
1:07:03Finance Authority. Uh, and we're very
1:07:06pleased with that because that will let
1:07:07us uh finalize the financing plan for
1:07:10Oak Grove. um will be renovating uh 270
1:07:14units and coming back with 36 units
1:07:18because of an agreement with the ONQ
1:07:20corporation to develop a uh fullervice
1:07:24gas station there with a fresh food
1:07:26option also and then uh our general
1:07:30contract will be selected through an RFQ
1:07:33here in the next year.
1:07:37So important part of maps uh for
1:07:39homelessness is leveraging uh allocation
1:07:42number one. Uh you'll see that the maps
1:07:45for allocation uh in the the line of
1:07:48numbers on the left had an allocation of
1:07:518.5 million dedicated towards housing.
1:07:55You can see on the far right number that
1:07:57we have leveraged that against $124
1:08:00million and that is not the final uh fig
1:08:04figure at this time because Crestston
1:08:06Park is still to be determined what that
1:08:09cost will be and that will dramatically
1:08:11increase that leverage.
1:08:14Now we move on to budget allocation
1:08:16number two which was also $10.7 million.
1:08:21You can see that uh several projects are
1:08:24included in that. We'll talk about those
1:08:26projects in a minute. And you can see
1:08:28that at the end end of the day, as of of
1:08:30today, we have only $10,000 that's not
1:08:34committed. And so that allocation is
1:08:37also fully committed uh or expended at
1:08:40this time.
1:08:43The first project we'll talk about is we
1:08:45host Alliance. That's 38 units right
1:08:49across the street from the homeless uh
1:08:52alliance office and shel and uh uh
1:08:56supportive service area. Um that's a mil
1:08:59maps uh investment of $1.7 million. The
1:09:03total development cost there is just
1:09:05over 6.7
1:09:0738 units of permanent supportive housing
1:09:10for folks that are formerly homeless. uh
1:09:14we have anou with we are society who
1:09:18will be operating that facility for uh
1:09:21those residents. Um you can see that we
1:09:24host alliance has begun work on that
1:09:27site. Uh from this picture you can see
1:09:29the early site work beginning to occur
1:09:32in these pictures. Uh and then also the
1:09:36building footings and the wall framing
1:09:38will be coming up in the next couple of
1:09:40weeks.
1:09:47West Haven Flats is our first workforce
1:09:51housing project in Oklahoma City. Uh
1:09:54that's 132 units. And of that 132 units,
1:09:5955 of those units will be projectbased
1:10:03subsidized housing. So, a mixed income
1:10:06affordable housing project being built
1:10:10in in Oklahoma City. That has a maps for
1:10:13investment of $1 million and the total
1:10:17development cost there is just over $57
1:10:19million. Invite you all to the
1:10:22groundbreaking ceremony which will be
1:10:24held Tuesday there at the uh at 6400
1:10:28Shiloh Drive in Oklahoma City. We're
1:10:31really excited about this opportunity to
1:10:34bring workforce housing in Oklahoma
1:10:36City.
1:10:39Then the big news of the day is that the
1:10:41city of Oklahoma City and the Oklahoma
1:10:43City Housing Authority a couple weeks
1:10:45ago were awarded what they call the
1:10:47Choice Neighborhood Grant. It's the
1:10:49largest grant that the Department of
1:10:51Housing and Urban Development awards in
1:10:53the United States. There were four
1:10:55awards provided and we did receive one
1:10:57of those and that is for the area
1:11:00surrounding Will Rogers Courts
1:11:02development. So that will be our public
1:11:04housing project renovation number three.
1:11:07Um that currently has a $2.5 million
1:11:12maps commitment in it. that commitment
1:11:15will grow over the third, fourth, and
1:11:18fifth allocations after those are
1:11:20awarded by uh by the city council
1:11:23ultimately. Um and so uh we're really
1:11:26excited about this. Um it's going to uh
1:11:29be a total renovation of of the property
1:11:32uh surrounding Will Rogers Courts all
1:11:34the way from the Wheeler district over
1:11:36to Stockyard City. Basically from the
1:11:39river down to 25th Street. So, a total
1:11:42transformation of that neighborhood is
1:11:44coming. It's an exciting time in
1:11:46Oklahoma City.
1:11:49This is West Lawn Gardens. If you uh
1:11:51orient yourself towards Mark Twain
1:11:54Elementary, uh that is where this
1:11:57project will be located. 40 units of
1:12:00workforce housing. Uh that has a MAPS
1:12:03commitment of $1 million.
1:12:05That is a partnership with the housing
1:12:07authority in as much kowanas clubs
1:12:11engaged learning city care and sunbeam.
1:12:15So, all of those partners are working
1:12:17together with AHM to develop a community
1:12:20inclusive neighborhood for folk that
1:12:23have uh children perhaps living uh uh
1:12:26I'm sorry, children attending Mark Twain
1:12:29so they can live closer to that property
1:12:31and feel safe and secure as they go to
1:12:34school and live in that neighborhood.
1:12:40I think we're all very familiar with the
1:12:42pivot program in Oklahoma City. Uh they
1:12:45came to the housing authority and asked
1:12:47if they could uh increase their number
1:12:50of units up to 50, which would be nine
1:12:53additional units. And so that will be
1:12:55supportive housing project number four.
1:12:58That's for homelessness
1:13:00for sorry that's for homeless atrisisk
1:13:03youth. Uh the MAPS commitment is
1:13:06$564,000
1:13:09and Pivot has received a a national
1:13:12housing trust fund dollar to support the
1:13:15balance of the $1.4 million. So that
1:13:18project will be occurring very soon
1:13:20also.
1:13:22So this is the leveraging chart for the
1:13:25allocation number two. You can see this
1:13:29uh uh allocation had $10.1 million
1:13:34allocated toward housing needs has 432
1:13:38units uh total identified and the uh
1:13:41current uh leverage and that's not the
1:13:44final leverage uh because there are some
1:13:47of those uh projects that are not yet
1:13:49financed out. Currently though, we have
1:13:52$118 million leveraged against that $10
1:13:56million.
1:14:00So, where are we at at this current time
1:14:03and 90 days out? Uh, Vita Nova is under
1:14:06construction. We host Alliance is under
1:14:09construction. Will Rogers Courts just
1:14:12received the Choice Neighborhood Grant.
1:14:14Crestston Park phase one. We're abating
1:14:18and demolishing and performing the site
1:14:20work as we speak. West Haven Flats uh is
1:14:24under construction. They broke uh and
1:14:26they're breaking ground uh in in
1:14:28October. And then Oak Grove uh just
1:14:32received the low-income housing tax
1:14:34credit approval and we're moving forward
1:14:36with that process.
1:14:40So, that's a lot of work coming to you
1:14:42from the Oklahoma City Housing Authority
1:14:44to uh complete the homelessness uh
1:14:46program of the MAPS for program. So,
1:14:48happy to answer any questions.
1:14:50>> Any questions?
1:14:52Looks like a lot of progress is being
1:14:53made. Thank you very much. Appreciate
1:14:56you being here.
1:14:58>> Okay, [clears throat] that's all for our
1:15:00individual items. Item three,
1:15:02discussion. Do we have any discussion
1:15:04items?
1:15:05>> Anything further? Okay. Item four, uh,
1:15:07advisory subcommittee reports. Any
1:15:09reports from subcommittees?
1:15:13>> No. Okay.
1:15:14>> Let me just say one thing.
1:15:14>> Yes.
1:15:15>> And I [clears throat] meant to Travis
1:15:16isn't here, but populist did a marvelous
1:15:18job on the coliseum and it was a real
1:15:21pleasure for our subcommittee to work
1:15:23with them. His presentations were great.
1:15:25Everybody was engaged and and it went
1:15:27really well.
1:15:28>> Great. That's good to hear. Thank you.
1:15:30It's always nice to give accolades to
1:15:32the people that are doing work.
1:15:34>> Yeah.
1:15:35Okay. Um item five, update status. Mr.
1:15:39Todd,
1:15:40>> I think we've covered quite a bit today.
1:15:42[clears throat and cough] We're still
1:15:43building sidewalks. There there were
1:15:45other um updates at subcommittee level
1:15:48for a lot of things that are going on.
1:15:50Um the the South May Trail, as I said,
1:15:54sidewalks, some more park stuff. So,
1:15:57lots lots going on.
1:15:59>> Yep. Okay. Item six, comments by board
1:16:02staff, citizens. No citizens have signed
1:16:04up to speak. Anything from the board?
1:16:07Any comments? Anything staff?
1:16:11No. All right. Thank you for being here.
1:16:14Item seven, we are adjourned.