MAPS 4 Animal Welfare Center Construction
At a glance
- What: Construction of the MAPS 4 Animal Welfare Center by Crossland Construction.
- Where it stands: Phase 1 substantial completion and a ribbon cutting are set for November 17, 2026; phase 2, the large-animal barn, is set for July 7, 2027.
Based on auto-generated captions; names and figures may be misheard.
Sources
Log
- 2026-10-01 - MAPS 4 Citizens Advisory Board Meeting - change order 7 ($168,281) approved; change orders 1 through 7 total a 4.07 percent increase over the original contract, with about $900,000 in contingency remaining.
- 2026-11-05 - MAPS 4 Citizens Advisory Board - program update: ribbon cutting for the animal welfare center set for November 17 at 2 p.m.