  • What: rehabilitation of the primary clarifiers at the Deer Creek Wastewater Treatment Facility: new mechanisms, better catwalk access, covers and biological trickling filters for odor control; estimated cost about $17.5 million.
  • Where it stands: plans and specifications approved for bidding on September 29, 2026.