MAPS 4 Family Justice Center Construction
At a glance
- What: Construction of the MAPS 4 Family Justice Center.
- Where it stands: Contract value about $29.3 million with roughly $2 million contingency remaining; estimated completion July 7, 2027.
Based on auto-generated captions; names and figures may be misheard.
Sources
Log
- 2026-10-01 - MAPS 4 Citizens Advisory Board Meeting - construction update received, including a change order package of about $184,000 for kitchen, therapy sink, door and finish items.
- 2026-11-05 - MAPS 4 Citizens Advisory Board - amendment number two to the architect contract approved, $12,240, for design of a new cook hood and related plumbing, architectural and structural changes that had earlier been value-engineered out.