Gaylord Boulevard Pedestrian Bridge

At a glance

Based on auto-generated captions; names and numbers may be misheard.

  • What: a planned pedestrian bridge over Gaylord Boulevard near the Santa Fe garage, connecting to the parking garage.
  • Where it stands: Debbie Miller presented it on 2026-10-13 (consent docket item 9AO); council had been briefed the week before.
  • Next: bids are expected in December; the work is split into two packages and this is the first.

Details given

  • Construction budget about $5.8 million; total budget about $7.6 million.
  • Bridge crosses on the west side of the railroad tracks, with an elevator tower and a staircase.
  • A contractor captioned as "Lingo Construction" was mentioned.
  • No council questions. The consent docket passed unanimously.

From the video (2026-10-27)

2026-10-27 - Oklahoma City Economic Development Trust: The Trust approved up to $2.1 million of TIF No. 2 funds; Public Works reported a $5.8 million construction budget, $7.6 million total, construction January through September.

Sources

Discussion time

About 2 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-13 - City Council 2

Log

  • 2026-10-13 - City Council - Debbie Miller presented renderings, a $5.8 million construction budget ($7.6 million total) and December bids. No questions.
  • 2026-10-27 - City Council - Public Property Authority accepted a skywalk easement from ParcFirst@Bricktown and SFPG for the bridge, and the consent docket approved final plans for subcontractor bids on Bid Package 2 (CMAR Project MC-0594-2).