  • What: Change orders on the MAPS 4 sidewalks and related amenities program, phases 1B, 2A and 2B, adding sidewalk alignments.
  • Where it stands: The board approved three increases: $152,266.56 (phase 1B), $373,703.25 (phase 2A, caption read as $373,7325) and $29,295.74 (phase 2B). Staff said sidewalks are going in across the city.

Details

  • Phase 1B: amendment number three and change order number ten with EMC Services, $152,266.56. Staff explained bids came in lower than budgeted, so contractors are adding alignments and adjusting quantities.
  • Phase 2A: amendment number three and change order number five with Nash Construction Company, $373,703.25 (same situation).
  • Phase 2B: amendment number two and change order number three with Ellsworth Construction OKC, $29,295.74.
  • Contractor and company names are from auto-captions and may be misspelled.