- What: Bids for the first two MAPS 4 neighborhood and community parks packages (phases 1A and 1B) came in over budget and were rejected.
- Where it stands: The board approved ratifying the addenda (agendas one to four, as captioned) and rejecting the bids for both phases; the projects will be revised and rebid.
Details
- Phase 1A bids were about $750,000 over budget and phase 1B about $1.8 million over, according to a board member; staff called the overruns significant and said this does not happen often.
- Staff will make changes and send the projects out for bid again.
- Related: MAPS 4 Neighborhood Community Parks Phase 1C.
Sources
Log
- 2026-11-05 - MAPS 4 Citizens Advisory Board - bids rejected for phases 1A and 1B; both approved.