2026-09-01 - Library Building Committee
Summary
Written from the auto-generated captions; names and numbers may be misheard.
- Held remotely on Zoom with no public comment. The project team said the September 24 occupancy date had held for several months and was still being maintained; a fire department alarm test was set for September 14 and final cleaning was about to begin.
- Items still needed for occupancy: stair handrails (the glass balusters for the rear stair were not ordered in time, so temporary railings would be used; the ornamental stair railings were expected on time) and permanent front doors, expected that week. The elevator was complete and awaiting the state inspector. The chiller still needed manufacturer startup and was unlikely to be running by September 24, though it is not needed for occupancy.
- Roof: replacement clay tiles that had been mistakenly removed were on site and waiting on dry weather, and copper work was in fabrication. The project manager and the construction company's leadership had met the roofing contractor, who said he was juggling crews.
- The library director showed progress photos: mobile shelving on concealed casters, benches in three fabric colors, new circulation desk and holds shelving, and 16 study pods. She noted wrong chairs, a pod fabric installed inside out and tree-shaped lights to be replaced.
- Landscaping: the landscaper was due on site that Thursday for about four working days. Healthy existing front plants will be kept and spare plants used to screen the transformer, at a cost still being worked out; five viburnums will replace 20 invasive plants near the sign; a new ornamental memorial tree will be placed more centrally, and the committee asked that the memorial plaque be moved with it.
- Vote: the committee approved a construction change directive (CCD 13) for up to $18,000 for low-voltage wiring and programming linking automatic door operators and security hardware to power supplies, work no contractor had in scope. It passed by roll call, all yes.
- Budget: roughly $60,000 remained in contingency after counting all known exposures; fuller figures are to be presented at the mid-month invoice meeting on September 15.
- Meetings: the next meetings are September 15 and 29. Members decided the September 29 meeting stays on Zoom rather than opening the unfinished building to the public, with a separate public tour possible after occupancy.
Issues discussed
- Library Construction Completion and Reopening
- Library Project Budget and Contractor Payments
- Library Building Project
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:09and it's right at 3:30. So, I'm going to
00:11go ahead and call our meeting to order.
00:13This is the library building committee
00:16meeting Tuesday, September 1st. And I'll
00:19start with the um open meeting. Uh
00:23pursuant to chapter 2 of the acts of
00:262025, this meeting will be conducted via
00:28remote means. Members of the public who
00:30wish to access the meeting may do so in
00:32the following manner. Join us on Zoom.
00:36No in-person attendance of members of
00:38the public will be permitted, but every
00:40effort will be made to ensure the public
00:42can adequately access the proceedings in
00:44real time via technological means. In
00:47[snorts] the event we're unable to do so
00:48for reasons of economic hardship and
00:50despite best efforts, we will post on
00:53the select board's website an audio or
00:55video recording, transcript, or other
00:57comprehensive record of proceedings as
00:59soon as possible after the meeting. So
01:02with that, we are underway. Um, is there
01:06anyone present for public forum who
01:08would like to speak?
01:14Seeing none, we will move on to repair
01:18project update. So, we'll review and
01:21vote on some construction change
01:23directives.
01:25>> I can provide an update uh prior to
01:28that. Mike Williams uh is is on his way
01:30to his office after uh our regular
01:33construction meeting uh on site there
01:36this afternoon. He just texted me a few
01:37minutes ago. I said he isn't quite there
01:39yet. and he's [snorts] got uh part of
01:41that presentation to make. So um I'll go
01:45through the schedule and and if for Mike
01:47isn't on yet, maybe we can talk about
01:49the Red Sox or something like that while
01:51we're waiting for Mike to arrive. So I'm
01:53sure it'll just be momentarily. Um just
01:57a co and Mike one sure jump in. I do
01:59have a couple of things just up some
02:00updates from today in terms of schedule
02:02that I uh just noted that uh I thought
02:05would be of interest to to communicate
02:06to the to the group here. Um, I did see
02:10your email, uh, Moren just a few minutes
02:12ago. Uh, so we can go through Chris Pant
02:15and and I I know Chris, so uh, no issue
02:17at all just to work with a neighbor and
02:20the glare. Uh, we do have a couple of
02:21contacts at National Grid. Bob Tucker is
02:24reaching out to them just to see if we
02:26can uh, [clears throat] assist with
02:28making some headway there, but we'll uh,
02:30get Chris paying in the loop there as
02:32well.
02:33>> Thanks.
02:34>> Yeah. Yeah. All All good. Happy to try
02:36to try to help. I I I know the sounds
02:38like the path there to with the glare
02:40has been frustrating for the for the
02:42neighbor there. So, we'll do what we
02:44can.
02:45>> Yeah.
02:45>> Um
02:46>> uh so just a couple things that were
02:49brought up today. Most of the focus of
02:51the conversation, well, a good part of
02:53the conversation of the meeting is is
02:56about what do we need to get done uh for
02:59occupancy. You know, that's that's kind
03:01of the laser focus, if you will. Um and
03:04and in the meantime, Kate and her team
03:06is working on furniture and loading
03:08things and and all the things that go
03:10along with achieving occupancy than
03:12actually using facilities. So um so
03:14that's that's basically what the
03:16conversation is. So a couple of things
03:17for upcoming uh items. Uh we were
03:21delighted to hear just as before the
03:23meeting started the fire alarm blaring
03:26because we're dying to have the fire
03:27alarm test happen. Uh 9:14 is a test
03:31with the fire department. So, we're
03:32delighted to hear that. Just as almost
03:34as happy as we were about uh four weeks
03:38ago when we heard the the roofer banging
03:40away on the roof so loud it was hard to
03:41conduct the meeting, but we were
03:42delighted to hear that as well. So, it
03:44was kind of similar. Um couple of
03:47conditions exist. The stairways, so the
03:50stair I call it out out back if you
03:52will, kind of over by the bookrop on
03:55that side, the main stair. Uh and the
03:57stair the the main stair going up, the
03:59ornamental stair. Uh the challenge for
04:02occupancy is to have handrails in place.
04:04It sounds like a simple thing, but it's
04:06also an easy thing that if you don't
04:08have them, you don't get occupancy. It's
04:10a really that part of it is really
04:11simple. So the the the main stair there
04:16toward the bookdrop is a glass railing
04:19or [clears throat] glass um ballisters,
04:21if you will, and then a handrail on top
04:23of that. And the way that gets installed
04:25is the glass goes in and then they
04:26measure that [clears throat]
04:29um handrail that goes on top of the
04:31glass and and so that takes some time to
04:33get and wasn't ordered on time. So the
04:36glass isn't in yet. So there's going to
04:38be some temporary railings put in that
04:40back uh area, but the ones out of the
04:43ornamental stair, those railings should
04:44be in on time. um the front door beyond
04:48the you know the the Home Depot front
04:50door that's in place at the moment will
04:52be replaced by the the permanent doors
04:55and and I expect with their old
04:57Bostononians mobilization uh again uh
05:01this week um Wednesday to Friday hoping
05:04that those doors will be arrived will
05:07arrive and will be installed this week.
05:09We talked about final cleaning for the
05:11first time, which is a a great milestone
05:13to talk about cleaning. Um, and so
05:16they're going to have cleaning crews in
05:17to uh give the place the a once over
05:21prior to that 914
05:23uh fire department test on site. Uh, and
05:26we are able to confirm that that 924
05:29date uh for occupancy, we're still
05:32maintaining that. That's been the same
05:34date for several months running now. So
05:37happy to report that that hasn't
05:38slipped. We go through a long list of
05:41items every meeting that um to check on
05:44where is this and where is this um and
05:47and so we continue to make progress with
05:50um SVER indicating that that date is
05:53still good. So I think for a while there
05:55they would say just about anything so
05:57we'd move on with the meeting. Uh but
05:59now we're they're we're getting from
06:01them a little bit more confidently that
06:03that's when they're going to be able to
06:04deliver the building. um uh elevator uh
06:08is complete and now just out for uh
06:12state inspector to provide timing for
06:14their arrival and inspection. So, you
06:18know, things are coming together. Still
06:20are some outstanding items like the the
06:23chiller uh you need to have the
06:25manufacturer come out and perform the
06:27startup. Um and we're waiting to get
06:29dates confirmed when they can actually
06:31do that. So far, it's it's problematic.
06:34Even though the chiller provides
06:36cooling, uh we may or may not have that.
06:38It's unlikely we'll have that by the
06:409:24 date. Uh just to be realistic
06:43there. So, uh certainly can operate the
06:46building and as we are right now,
06:48perfectly comfortable uh environment
06:50there right now. And you don't need the
06:51chiller for occupancy, but we just need
06:53to go through with the building
06:55department. Some of these things that
06:57aren't quite ready, the the longer that
06:59conversation is usually the worse it is.
07:01You know, usually if you have a kind of
07:03a brief conversation, railings, chiller,
07:06and hopefully nothing else, everything
07:08else is in place, you know, then then
07:10it's a fairly simple thing. But, uh,
07:12we'll see how that goes. Those
07:14conversations are starting now. Um,
07:18Christina, just looking to see if Mike
07:20has arrived yet. I've done uh provided
07:23kind of a simple update for where we may
07:26stand. And Mike had indicated he hadn't
07:28quite made it back to the office when he
07:29texted me about maybe 15 minutes ago or
07:33something like that.
07:35>> I I can I can touch base with him to see
07:38if he's on his way. He said he was just
07:40about there. Let me just
07:42>> Okay.
07:44>> So, [clears throat] not arrived yet. And
07:46so, now we're into the Red Sox segment.
07:48Unless somebody has another direction we
07:50want to we want to go in here.
07:52>> I think Walter has a question.
07:54>> I do have my cap here. So, I am, you
07:56know, [laughter]
07:58I I always have questions. Um, and I I
08:02thought that the roof that was supposed
08:05to have tiles, which they took off
08:07mistakenly, had been installed and but
08:09now it's not. But maybe I was wrong. It
08:11was never installed. But what's holding
08:13up um the it's the 1980 building tile
08:18roof.
08:19>> Can you speak to that, Mike? I think the
08:20tiles are on site is where that stands
08:23this moment.
08:24>> Yeah. So the they just they just got the
08:27material that they needed to replace the
08:29ones that they mistakenly uh removed. So
08:32that's on site now. And kind of what's
08:34just holding that from progressing is
08:36that it's raining today. Um so once once
08:40the weather clears up, they're going to
08:42be back on site to install that. As well
08:44as the uh remaining copper work there is
08:47in pre-fabrication right now. We got
08:49that update today.
08:51>> Okay. So the materials finally [snorts]
08:53arrived. Yeah, those materials and SVER,
08:56you know, they're not shy about
08:57explaining. They're still looking to,
08:59you know, drag the roofer forward to the
09:01finish line. So, it's it's a it's a
09:04little better. You know, it's it's
09:05really not far from being 100% complete.
09:07It really isn't.
09:09>> Um but the the dragging forward
09:11continues. We did I don't know if we had
09:13this conversation with this group or
09:14not, but we did meet with the roofing
09:16contractor right after um they had said
09:19they weren't returning their calls and
09:20that kind of thing. So Kyle Dupel, the
09:23fella, the the I think he's the COO, I
09:27think, of Siver at this point, um, uh,
09:30he and I met with the roofing
09:32contractor, the fellow who owns Young
09:34Developers, and that was a couple of
09:36weeks ago now. So he said all the right
09:38things and and was not argumentative at
09:40all and and, you know, just a matter of
09:42him juggling his resources. He did, if I
09:44if I mention this group, you can stop
09:46me. He mentioned he does run 60 uh
09:49roofers as the firm does which is more
09:54than I expected honestly. Um but you
09:57know is is what it is. Um,
10:00so we're I could tell you what Mike is
10:02going to present and then have him
10:03present it because he's I know he's
10:05already too um partially he's going to
10:07present the landscape plan, plantings
10:10plan if you will, because I know he's
10:12been working very closely with the
10:13landscaper to update the direction
10:16that's going. He has a location uh for
10:19the replacement memorial tree there and
10:22where that's going to go. Just so
10:24everybody understands and and sees the
10:26presentation, that work has not started.
10:29If you haven't been by, uh the front
10:32fence is still up, so that doesn't look
10:34different. But behind the fence looks
10:36very very different in that all the the
10:38junk and equipment and construction
10:40things are are gone from there. And it's
10:42really a raed and lome u condition is
10:46what's there now.
10:47>> [clears throat]
10:47>> And I think the um for the schedule they
10:50handed out this morning, the landscaper
10:52will be on site on Thursday, this
10:54Thursday. Uh and and it's not a long u
10:58uh installation period. They've got four
11:00working days scheduled based on what the
11:02the SER team handed out today uh to do
11:06to do the work. It does show it on
11:08Monday, which it's unlikely they'll be
11:09there on uh this Labor Day Monday, but
11:12uh four working days to to go through
11:14it.
11:16Um,
11:18not seeing blanket. I'm just seeing if
11:20there's anything else on the schedule
11:21here to uh to mention.
11:23>> I think Kate had a question.
11:26>> Oh, sorry.
11:28I was just going to offer instead of
11:29talking about Red Sox, I had every time
11:32my team [clears throat] and I go to the
11:33space, we take photos and I was going to
11:35offer to show some, but Mike
11:39>> Mike just arrived. So, I think we can
11:42>> we [clears throat] can we can take it
11:44off to him if he's if he's made it in
11:45and he feels ready.
11:46>> If you want if you have a couple, Kate,
11:48just as we didn't get the tour in, if if
11:50you have them if they're teed up there
11:53or if you could tee them up, I think
11:54that the team might might uh I
11:56appreciate that.
11:57>> Fantastic.
11:58>> Yeah. Yeah. Yeah. Absolutely.
11:59>> Sure.
12:02Um, so this is our unhinged. I don't
12:05know if you guys can see that. Okay.
12:08So, every time we go around, we take a
12:11bunch of photos so that a for posterity,
12:13right? So that we have them
12:15>> um and to show progress. So you guys can
12:17see that blown up a little bit bigger.
12:19Yeah.
12:20>> Yes.
12:21>> Okay. So that's the entryway.
12:24Um, al also some of these pictures we
12:27take because we're looking at very
12:28specific things, so you can take that
12:30for what it is. But you can see the uh
12:32historic rooms. We're starting to get um
12:34some shelving in there. Those curved
12:36units you're seeing are actually mobile.
12:38And all of the mobile units that we got
12:40are concealed caster. So um they are
12:43movable, but they don't look movable,
12:45which is really important. Um this uh we
12:48have these twin benches going in uh
12:50beneath the uh windows. these none of
12:53the shelving is in its permanent place
12:54yet. But um one of the things to look at
12:57is that this fabric um on this bench we
13:01actually are getting in three different
13:02colorways. Um so in the historic
13:05building it shows here in this kind of
13:06green color. We liked it because it
13:09added color but also it looks like
13:10bookspines. Um but that in the adult
13:14area it's in a navy color way and in the
13:17teen area it's in more of a a purple
13:19color way. So, it kind of brings all of
13:21the the rooms together. Um,
13:25there's going to be some weird There's
13:26Caitlyn on the Hi, Caitlyn. There's me
13:28and Caitlyn goofing. Um, so we have slat
13:31wall. We've got some issues with that.
13:32We'll figure it out. I'm just running
13:34through these really quickly. Um, that
13:37one's really cool because it's from the
13:38historic entrance. You can see how
13:41beautiful the lights look here and the
13:43brand new circ desk. Um,
13:47and like a really nice view of that
13:48room. Um, this is from the circ desk.
13:52You can see where the holds are. So, we
13:54got very specialty hold shelving and it
13:56blends in really nicely with that wall.
13:59We've got the keypad up on the study
14:01room door, which is really exciting,
14:03although I'm not sure they're functional
14:04yet. Um, these are chairs that Aotti
14:08sent us that are the wrong chairs. We're
14:09not going to talk about that right now.
14:11Um this is uh so we've been talking
14:15about these study pods for a while. Um
14:17these are the ones that are kind of in
14:19the main area. We have two sets of three
14:21in the main area. Each of those sets of
14:23three comprise of two singles and one
14:26duo. Um and they kind of snake with each
14:29other. So we've got two of those in the
14:31front and then through the back we've
14:33got an additional uh 10 study pods. So,
14:37a total of 16 study pods, six duos,
14:41um, nine singles, and then one handicap
14:44accessible. Um,
14:47but we think they look beautiful here.
14:49Um, and they're really usable when you
14:51sit in them. They're really, they're
14:52sound dampening. Um, they've got power
14:55in them. They've got a place to put all
14:57your stuff. I think short of being able
14:59to build 12 study rooms, this was the
15:01best we could do. So, we're really
15:03excited about these. Um, and isn't she
15:06just stunning? Um, just really, really
15:09fun. These are the ones that are along
15:11the back. One thing I'll note is that
15:13these the one uh to the right that looks
15:16gray, the fabric was actually installed
15:19inside out. And so,
15:22while it looks gray, it is not correct.
15:24So, they are fixing that. Um, again,
15:28inside out, it's supposed to be a light
15:29blue. It is not. So, just ignore that.
15:31But just I think this gives you kind of
15:33a view of where those go. So that's
15:34where the study carols were before. Um
15:37and so I think there was only maybe five
15:39or six of them in that area. So we've
15:41really been able to add a lot more
15:42seating
15:44um in that spot and not block the the
15:47windows which is great.
15:50And that's uh study room B in the back.
15:53So you can kind of see it all the way
15:54down. So that's the second study room.
15:57Those little carols would will help with
16:00sound absorption, too, right? I mean,
16:02>> yeah, they got Yeah, it's pretty nice.
16:04>> So, here you can see that kind of snake,
16:06the brand new shelving up in the adult
16:09area. Um, the units to the left uh are
16:13mobile on casters. We can move those
16:15around.
16:17Um, another view of those study pods.
16:20Another view of us looking distraught.
16:24Um,
16:26I'm really I'm sorry I'm flipping
16:27through this fast because there's so
16:28many of them. But yeah, more bench.
16:30That's the team.
16:32Um,
16:34slat wall up. And then I think there's
16:36like a couple really quick ones on
16:37children's. But thermostats, which is a
16:40whole thing. Third floor. Don't those
16:42floors look amazing? So, they just
16:43finished the floors.
16:45>> Um, and it really looks like a whole new
16:47place. We're really excited about that.
16:49Um, you'll notice, maybe Moren will be
16:51the only one as excited as me, but the
16:54pipe that was coming out in that corner
16:56leading to nowhere is now gone. Um,
17:00>> it's miraculous.
17:03>> We're We're just absolutely thrilled.
17:06This is children's. So, this is the
17:07picture books uh over on the right side.
17:10Um, this metal is a color called slate
17:14storm storm, but it's like a It looks
17:16gray here, but it's more of a blue. It
17:18matches in really good with that corner.
17:20Um, and then zoomed out, you see the two
17:22trees in the middle. These lighting
17:24units are supposed to be green. They are
17:26currently working on a replacement for
17:29those. So, those will be fixed. So, they
17:30will actually look like trees and not
17:32just, you know, silver circles. Another
17:35thermostat that wasn't purposeful, I
17:36promise, but we are distraught over the
17:38amount of thermostats. Um, and then just
17:41to I don't know if you can see this. And
17:43also, just please don't judge how many
17:45tabs I have open. That is just who I am
17:47as a person. Um, so you can see the navy
17:50colorway in this. These are the wrong
17:53chairs, but this is the right fabric.
17:54So, we think it'll really blend in
17:56really nicely with that space. So, that
17:59is a really very quick look at some of
18:03the furniture that's been uh delivered
18:05so far. Um,
18:07but yeah, we we're trying to take
18:10pictures of the entire process and have
18:12been uh throughout so that we can we can
18:14have it ready. um for for when more
18:17furniture comes and we want to look back
18:20at what things used to be.
18:22>> It's gorgeous.
18:24>> Yeah. I mean, that's the first pictures
18:26we've seen where it wasn't construction.
18:28It was actually looking like a a room.
18:32>> Notice the end caps show on the shelves.
18:34That's nice. Also,
18:36>> that's beautiful.
18:37>> Yeah.
18:39>> Cool.
18:44Okay, we're Mike, we're waiting uh for
18:47your arrival. Uh I did preface the group
18:50just to explain you were going to
18:51describe plantings and some of what you
18:55have there and um and
18:59>> uh kind of give an update as far as
19:00schedule for some of the dates that we
19:02reviewed today in the project meeting.
19:04So everybody's up to speed on that and
19:06so turn it over to you.
19:08>> Okay. Thank you. Sorry for my tardiness
19:11rushing back from the job site. Um so uh
19:16what I can do so
19:19previous conversations about what are
19:21the what are the changes we can make uh
19:22to the plantings uh both the replacement
19:26for the memorial tree and uh the
19:28replacements for the invasive um
19:33um
19:35plants around the the signs and
19:37elsewhere. So, just to give you an
19:39update on where we're at with that, I'm
19:41going to share my screen and just show
19:43you a markup of the site plan, uh, the
19:45landscape drawing.
19:51So, as you can see here, similar to what
19:54we looked at with the the sidewalk, uh,
19:57up this uh, footprint here is the
20:00building, the two gardens out front, uh,
20:02the sign as well, our transformer off to
20:06the side. So what you're seeing here,
20:08I'm going to zoom in.
20:11The scope of work in the base contract
20:13was basically replacing kind the
20:16planting the plants that existed at the
20:19building before construction started.
20:21So uh that's what this drawing shows bas
20:24a plant for plant replacement
20:28matching the same plants that were there
20:31uh again before construction started.
20:35um many of those plants are are
20:39healthy still um of the existing plants.
20:43So we were toying with the idea of
20:48instead of replacing healthy mature
20:51plants uh where we can maintain those uh
20:56and take the plants that we own and
20:59supplement the area around the the
21:02transformer and try to obscure the
21:04transformer a little bit further. Uh
21:07well right now it's not really obscured
21:09at all except for the construction fence
21:10that's there. Um, so this would be to
21:13try and beautify that area a little bit
21:16better. Not entirely sure how many of
21:19these
21:20the uh the plants that we own in the
21:22contract will actually be able to be
21:24used around the transformer. That's
21:26something that the the landscape
21:29contractor is going to work out once he
21:31really dives into those existing gardens
21:34to see what is healthy and worth saving
21:38and don't need to be replaced. So once
21:40he's had that done, he's going to do a a
21:44layout. Basically, he's going to come
21:45out with the plants he's purchased for
21:47the project and use the spare plants and
21:50just sort of lay them out physically
21:51around the transformer. At which point,
21:53we'll go we'll go out and look at them
21:55with them and give them a blessing to
21:56proceed with that.
21:58There is is a
22:02there will be some cost associated with
22:04this and that um it is a a little bit
22:08extra effort to prepare around the
22:11transformer to receive new plants as it
22:13is to just replant in the existing
22:16gardens. Uh being that u the existing
22:20he's got to clean up those gardens got
22:23to sort of give the existing plants that
22:25are worth saving a little bit of care.
22:27and he can't just um sort of go in there
22:30with with heavy equipment and just kind
22:33of rake everything out with a backhoe.
22:35It's a little bit more um there's a
22:37little bit more finesse and um and
22:39expertise to do that work and then also
22:42to again prepare the you know a planting
22:44bed around the transformer. So there's
22:46some additional costs there. We we don't
22:48know what those costs are yet but those
22:50are being worked out now. Uh and we'll
22:53we'll have those for you the next time
22:54we meet.
22:56Um, so those are the front gardens. Uh,
23:01around the sign is where we had the, um,
23:05I got to look it up again. Sorry. The
23:07LMB were the la or Lauria, which were
23:12the invasive plants that we were asked
23:14to um, find a substitution for, which is
23:18was the decision to go with the
23:19viburnum.
23:21The viburnum are a little bit larger
23:23than the laipi that were specked. So
23:26instead of the 20 la we're going to do
23:28five viburnums and the reason for that
23:31being the viburnums are going to get
23:32larger. So we don't want to block the
23:35view of that sign onto west main street.
23:37So what the landscaper suggests is that
23:40we do two on either side of the sign and
23:44then as a backdrop do three more. So
23:46five total viburnums in in lie of the 20
23:50la piece. The viburnums are a little bit
23:52more expensive. So it's basically a a
23:55swap of plantings at that location.
23:59Um so that that's the invasive um
24:03planting replacement scope.
24:06Um, and then for the replacement of the
24:08memorial tree that is currently at the
24:11side of the library that is no longer
24:13healthy, we found um uh a species that
24:18uh Kate has reviewed with the family
24:22um of the um the tree was dedicated to
24:25and we um came to an agreement that the
24:29aello
24:32tree um forgive me for not having an
24:35image of what that will look like, but
24:37it is another or ornamental shade tree
24:40type species. Um, but what we're looking
24:43to do is bring it a little bit more
24:45forward on site, more centrally placed.
24:48It still allows room for programming
24:51through that front yard area. Keeps it
24:54away from the water line and the
24:56building property line. Um,
24:59and we just feel that that's the most
25:01appropriate spot for it. It also
25:04provides a nice balance for from the
25:06sign on the opposite side of the
25:08sidewalk.
25:10Um, and then just another area plantings
25:12that we hadn't gone over. We own some
25:14replacement shrubs around our new book
25:16drop area too to green up that side.
25:22Uh, so that's our that's our current
25:24plan for for new plantings. Um, any any
25:28questions on that?
25:30>> I have a question, Mike. Uh, with the
25:33new memorial tree, will you be
25:36relocating the plaque as well?
25:40>> Uh, you know, that wasn't on our radar,
25:42but it should be. We We can do that.
25:44Yep.
25:45>> Thank you.
25:54>> Any other any questions for Mike?
26:02All right.
26:03>> No questions. Thanks for the update on
26:05that.
26:07>> You're welcome.
26:08>> Um I have a question on uh you mentioned
26:11putting something around a transformer.
26:13Are we allowed to have plantings around
26:15that thing other than the yellow lolly
26:18um columns? Whatever big bright yellow
26:20things.
26:21>> Yeah, good good question. Um, we are,
26:26uh, we can't put them right up against
26:28the transformer, but we can have some
26:30distance there. And as long as we
26:33maintain access around it, this actually
26:35sits within sits in a concrete curb
26:38that's filled with stone that's provides
26:41a 2 to 3 ft of clearance as it is. And
26:44then the ballards provide another foot
26:47or two uh, above and beyond that. So
26:49there's there's at least 4 ft of
26:51clearance just on what the constructed
26:56um structures there are out there
26:58between the the columns, the curb, and
27:00the the stone around it. So um we're
27:04providing we will allow plenty of access
27:07around that transformer.
27:09>> Just uh
27:10>> that's nice. for the uh in the long run
27:14or in the short run, you should probably
27:15talk to the the landscaping guy about
27:17how often you need to check for pruning.
27:20If you give it if you leave it long
27:21enough, it's going to grow into the
27:22transformer. So, some you someone will
27:25want to prune the transformer side of
27:27the the plants that are going in there.
27:31>> Good point.
27:32>> Plus, they're much smaller than I'm
27:33imagining.
27:34>> No, no, you're you're very accurate.
27:36These will shrubs uh if they're uncared
27:40for, they um they could impact the the
27:44transformer. Yep.
27:53>> And any other questions on that? Um
27:56>> um just sort of unrelated, but it's in
27:58your picture. The little um butt outs on
28:01the walkway or to put the benches in
28:04that were there before. Mhm.
28:06>> Okay.
28:07>> Correct.
28:08>> Yep. And that work's actually done now
28:10and the benches are back in place.
28:12>> Oh, well.
28:15>> Didn't know.
28:18>> Marine's favorite benches.
28:20>> I know. I love those benches.
28:26>> I should say uh Bill and had had pretty
28:28sharp eyes and noticed that the slope of
28:31th that area uh was a little off. Um, so
28:36we we went back and reviewed it before
28:37they poured the concrete and um and got
28:42it corrected. So, thank you, Bill, for
28:44bringing that up and making sure
28:46>> we got it right.
28:47>> Mike, are you saying that they're level
28:52>> enough that you don't feel it?
28:53>> Sort of flat.
28:55>> Yeah.
28:55>> That's amazing. [laughter]
28:58[snorts]
28:58>> Yeah. So, right now it's only pitched to
29:00get the keep the water off the the
29:02walkway.
29:04>> Nice. [snorts] Most people can't
29:06perceive that. Yep.
29:09>> Yep.
29:11Levelish and stable. How's that?
29:14>> Perfect.
29:15>> Okay.
29:17All right. Um Steve, did you want me to
29:20go through schedule? Is that is that was
29:23that your note in progress?
29:28>> I think the next thing for you is the
29:30the electrified
29:32hardware.
29:34Okay.
29:35>> Uh CCD13.
29:36>> CCD13.
29:38Um so we identified after talking with
29:43some of the subs um
29:47that uh there's uh some work that we
29:50need to add to the contract which is
29:52wiring between
29:56uh security devices uh electronic
29:58hardware and power supplies. So, um,
30:04numerous locations we have electronic
30:06hardware, meaning like an an auto
30:08operator, push a button on the wall, the
30:10door swings open electronically and
30:13automatically. Um,
30:17there are a handful of conditions where
30:20um,
30:23contractor didn't own that scope of
30:24work.
30:26Um
30:27so what this CCD does is it puts the
30:31scope of work into Sver's court to get
30:34that work done. Uh mostly it's all low
30:38voltage wiring connecting power supplies
30:42devices and electronic hardware to work
30:45properly.
30:47Um
30:48and uh we have a we're recommending a
30:51not to exceed value of 18,000. Mike, is
30:55that right?
30:57>> Yes.
30:57>> So, 18,000 on that. Um, and again, it's
31:00it's it's
31:02mostly labor. Um, and we're we think
31:07we're we're rather conservative with
31:08that number. Uh, allowing a couple a
31:12couple workers per day for each door
31:14opening as a conservative value on that.
31:18So, it's wiring, it's programming,
31:21um,
31:23for those those handful of door
31:24openings.
31:27>> Um, Mike, can I ask a question about
31:29that?
31:30>> Yes, I should stop.
31:31>> Um, you said the contractor didn't own
31:34the scope of that. Does that mean it
31:36wasn't part of the original scope or
31:40what what does that mean exactly? So the
31:43electrical drawings had diagrams showing
31:46all these connection points and um in
31:51relationship to those diagrams the
31:53electrical engineer had identified
31:58uh certain pieces of that work to be
32:01done by the owner's security vendor
32:05other than BCM controls who's not who's
32:07working more for the town than for the
32:09library and we really don't have them on
32:12board for this scope of work. There
32:14really isn't an owner security vendor to
32:16perform that work.
32:19Um so, uh we acknowledge that um it's
32:23really not the
32:25electrical subcontractor scope and it's
32:28not Sver as a GC scope of work. Um so
32:33they they're justified.
32:35>> Yeah. Thank you. This Yep.
32:39Any
32:44questions about
32:47um this construction change directive?
32:56Then can I have a motion to approve?
33:01>> Motion to approve
33:03>> and a second.
33:04>> Second.
33:05>> Thank you. So I will go down my list.
33:08Mary
33:11>> Johnson. Yes.
33:14>> Uh, Bill
33:15>> Lane. Yes.
33:17>> Kate
33:19>> Karacio. Yes.
33:21>> Lynn.
33:22>> Dukeup. Yes.
33:24>> Walter.
33:25>> Leslie. Yes.
33:27>> Ed.
33:28>> Yes.
33:30>> Al.
33:31>> Al.
33:32>> Gordon. Yes.
33:34>> Pete.
33:35>> Banbeck. Yes.
33:36>> And I'm a yes. So that is approved.
33:41>> Thank you.
33:45>> Thank you all. And
33:48I think that is everything
33:51on our agenda. Um any other building
33:54related issues?
33:57>> Um how are we on the budget at this
33:59point? I'm sorry, Bill, you go ahead.
34:01You're first.
34:02>> No, that's all right. No, I just wanted
34:03to say that we're very fortunate with
34:06the team of LPA and Vert.Ex that have
34:10worked very hard in the past month and a
34:12half to bring the contractor in as close
34:16as possible along with Kate and her team
34:19bringing the necessary things in at the
34:22to keep it on schedule. So, we're very
34:24fortunate for that team.
34:28>> Agree completely.
34:32So, I I'm just wondering how much
34:36headroom we have now in our budget.
34:40>> We typically go through that report in
34:43the in the middle of the month meeting
34:44when we have the invoice meeting.
34:46>> Okay. I can wait two months unless if
34:48you if you guys aren't alar two weeks.
34:50[laughter]
34:52>> Two weeks.
34:52>> Two weeks. Sorry.
34:53>> Are you referring to like the
34:54contingency budget?
34:56>> Yeah, that's exactly right. I just
34:57forgotten the word contingency. But
35:00>> with all the exposures that we
35:02>> Yeah. With all the exposures that we
35:03have at the estimated costs that values
35:05that we have right now, we have roughly
35:08$60,000 remaining in the contingency.
35:11>> Okay.
35:11>> When all said and done,
35:13>> keep in mind there are several items
35:14that we don't have um we have
35:17commitments that are not up to the full
35:19line item amount as well.
35:22>> Uh and we haven't done anything with
35:24that. I mean, you haven't done anything
35:26with that. So, uh, we'll go through that
35:28at the next meeting, you know, as we do
35:30the middle of the month, uh, meeting.
35:32Two weeks, good segue. So, should we go
35:34two weeks from today, which would be the
35:3515th? Is that Mike Bonfan? Does that
35:37work? The 15th or is that too early?
35:39>> That's that's the next the one that we
35:41have on the
35:42>> Okay,
35:43>> that's what we've been planning towards
35:44with the monthly items.
35:46>> Perfect. Thank you.
35:51any other questions or any building
35:54related issues we need to discuss
35:57while we're here.
35:59Um I guess uh my question was going to
36:04be given what where we are almost at the
36:08end of project whatever um but there's a
36:113-w weekek gap between the 15th and the
36:156th of
36:17October. So, I was just wondering if we
36:19were thinking about when the meeting
36:21after the next meeting would be. Um,
36:24whether it'll be the 6th or the 29th
36:26because we've been
36:28I I don't know what we need to support
36:31our construction or finishing up.
36:36>> Well, we can have that meeting, Walter,
36:38on site because we'll have occupancy by
36:40then.
36:41>> Knock on wood. Yeah. [laughter]
36:44>> We could do it on the 29th of this area.
36:46No, no, I didn't say that. [laughter]
36:51>> Um I I was under the impression we were
36:56going every two weeks just to keep
36:58things moving. So looking at the 29th,
37:02does that work for everybody on the
37:04team? Is that And looking at um Vertex
37:07and LPA, is that what you were expecting
37:10also?
37:15U this this meeting was set up to
37:17address issues if they come up um in
37:19between the middle of the month meeting
37:22uh which is exactly what today is which
37:23is then if things come up which has
37:25worked perfectly um probably not what's
37:28the team think the 29th or or um the
37:32week whatever the one after that is uh
37:35just said hang on a sec
37:39or the sixth um
37:42>> the 29th is actually better for me than
37:44the six
37:49>> when we go 29th for this meeting and if
37:51we don't need it we'll cancel but
37:53otherwise we'll have the meeting on the
37:5529th. How does that sound?
37:57>> Yeah, we got thumbs up from there.
37:58>> We still have it in person in the uh in
38:02the library [clears throat] on the 29th.
38:04>> So the the 20 Let me just make sure I
38:06have my days correctly. So the so that's
38:09a Tuesday. So the Thursday prior is the
38:12date that uh we're indicating is the
38:15date for occupancy and and the way that
38:17works is you need the fire department to
38:19sign off and he's out today and then you
38:22you know so that's what happens right
38:23around that 24th date. Um which I'm not
38:27hedging. I'm just saying that's that you
38:29know in terms of a very specific date.
38:31So uh we can plan on it to be on site
38:33and we sure hope not to have to change
38:35that. How's that for a real truthful
38:37answer?
38:40Sounds good.
38:42>> And just to make sure we meet open
38:45meeting requirements, um if members of
38:48the public wish to attend the meeting in
38:50person, they would be able to do that at
38:52that point.
38:53>> Yep. We have occupancy. So, yep. Once we
38:56have occupancy,
38:56>> yeah, fully, you know, your I mean, it's
38:58now two, but fully your building to do
39:01with as you wish.
39:03>> Okay. I would yeah I would be concerned
39:05about allowing members of the public in
39:07before we're open to the public. So I
39:09would I would I would prefer to have it
39:11somewhere else. Even if we have
39:13occupancy, we won't be moved in. We
39:15might have
39:17boxes everywhere, things everywhere. I I
39:20I would just be careful about that
39:21because I don't know that we have a way
39:23to safely allow members of the public
39:25into the building. I think this group
39:27I'm not worried about, but I am worried
39:28about opening those doors to the public
39:30after being closed and whether uh folks
39:34might see that as an opportunity to get
39:35in and see the building and then we
39:37can't accommodate everybody there. So, I
39:40think that for sure after occupancy we
39:43can find a way to get in there. We could
39:45do a tour. We could do it just the same
39:46way we did the last one where it was um
39:48a public meeting for a tour with no
39:50discussion.
39:52um which still kind of follows all those
39:54things separate from um a meeting. But I
39:58would I would be really hesitant. I
40:00would I would that would have to be a
40:02discussion with the board of trustees
40:03too, I think. But I I would
40:07it would not be what I would do.
40:09>> Yeah. So like the tour if we don't
40:12deliberate, it's not a it can be a
40:14public we can observe and that doesn't
40:18have to be at the same time as the
40:19meeting. Yeah.
40:22I would feel more comfortable with that.
40:27>> Say that again, Mary. I missed the
40:28beginning. I was just saying I agree
40:30with Kate. That would make me a little
40:31bit uncomfortable. I feel more
40:32comfortable not just keeping it on Zoom.
40:37>> Okay. So, for that 29th meeting, we'll
40:40stay on let's stay on Zoom and then um
40:44we'll see how it goes after that and
40:47we'll get in there when we can. Um,
40:51I know we'll be as excited as the public
40:53to see it. So, we'll just stick to Zoom.
40:56So, next meeting is in two weeks on the
40:5815th and then we will meet again on the
41:0029th. [snorts]
41:05All right. Can I have a motion to
41:08adjurnn?
41:09>> Motion to adjurnn.
41:11>> Thank you. Second.
41:13>> Second.
41:14>> Thank you. Uh, Mary
41:17>> Johnson. Yes,
41:19>> Bill.
41:20>> Lenain. Yes,
41:21>> Pete.
41:22>> Danbeck. Yes,
41:24>> Kate.
41:26>> Yes,
41:27>> Lynn.
41:28>> Duke. Yes.
41:29>> Walter
41:30>> Lesley. Yes.
41:32>> Ed
41:34>> Yes.
41:34>> Al
41:35>> Gordon. Yes.
41:38>> And I am. Yes. So, we are adjourned.
41:41Thank you everybody. See you on the
41:4215th.