2026-07-21 - Library Building Committee

Written from the auto-generated captions; names and numbers may be misheard. The recording opens during a vote on earlier minutes.

  • Minutes of the prior meeting were approved on a roll call with several abstentions from members who were absent. A member noted the June 16 video had not been posted to the town's video channel.
  • Contingency: about $517,700 approved to date (roughly 61 percent), with about $215,700 in potential changes pending; if all are approved, about $114,100 would remain and about 86 percent would be used.
  • Budget report (June package): construction about 70 to 72 percent spent against its commitment; the architect nearly fully paid; about $1.76 million of the overall budget not yet committed, mostly furniture, fixtures and technology. Library staff said no technology has been bought yet, some furniture money is held back until the public uses the space, and grants are being sought to reduce costs.
  • June invoices totaling about $75,570 were approved on a roll call.
  • Construction update: finish lighting, drywall, paint, tile and ceiling grids are largely done; the slate roof is about 95 percent complete with copper edging remaining; about 90 percent of carpet tile is down on the main level and started on the lower level, ready for the first furniture delivery (shelving and circulation desk) on August 3. A July 13 contractor schedule showed substantial completion on September 24 and was described as conservative and the first the team trusted.
  • Exterior trim paint work was delayed by a dispute over who would remove lead paint and the acceptability of the scraping; work was about 80 percent done around the perimeter, with sidewalk demolition and site work about to start.
  • The memorial Stewartia tree beside the church appears to be in poor shape despite watering efforts; members said it must be fixed and the family treated respectfully, and asked the landscape architect and contractor for a recommendation.
  • Members asked when the removed roof tile would be reinstalled (no date; waiting on material) and pressed that the contractor not be paid overtime.
  • A special meeting was set for August 4 to approve upcoming change directives. The library director said to plan on a four-week closure between leaving the temporary space and the grand opening, with dates to come.
  • A member asked who is responsible for a mural from the old Forbes building; the assistant town manager offered to help locate it, and it was treated as outside this committee for now.
  • Trustees' awareness of the schedule was a concern; the owner's project manager was urged to brief the trustees, whose next meeting is the following night. The landscape contractor is still sorting out a replacement for an invasive plant in the plan.

Issues discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:08Great. Thank you.

00:10>> So, I will go across my screen for the

00:12vote. Bob,

00:14>> uh, Patrick, yes.

00:15>> Mary,

00:17>> I'm going to abstain.

00:18>> Lynn,

00:20>> pick up. Yes.

00:23>> Bill,

00:24>> abstain.

00:28Al

00:30>> Gordon. Yes.

00:34>> Uh Walter

00:35>> Leslie. Yes.

00:37>> Pete

00:39>> back. Yes.

00:42>> Uh Kate

00:49Karachu. Yes. Sorry, I'm on like three

00:51different screens so and one of them

00:53doesn't work but that's the one with my

00:54camera. So

00:56>> yes, [laughter]

00:57thank you Ed.

01:00>> Oh abstain

01:05>> and

01:07did I Sean?

01:09>> Eio yes.

01:10>> Okay. And I will also abstain because I

01:15was not there. Um but I think we have

01:17enough votes. Mary correct me if I'm

01:19wrong to approve those that set of

01:22minutes.

01:24>> Thanks. Yeah, we got six.

01:25>> Okay, thank you,

01:27>> Walter.

01:28>> Um, yeah, I just wanted to note that the

01:30minutes they're not the minutes, the the

01:33video of the 16th did not get posted

01:37to the uh West Bro TV. So, I don't know

01:41if we could still do that. Um, the

01:4430th's up there, but not the 16th.

01:47>> I will check with Aiden because I sent

01:49him both. So, I'll find out.

01:53>> Thanks. going on with that.

01:54>> Yeah, because I actually missed that

01:55meeting. So, I went to

01:56>> list

01:58>> I couldn't find it.

02:02>> Thank you, Lyn.

02:05Okay, so uh

02:08thank you for reminding us about minutes

02:10so we can move on to our um project

02:13discussion.

02:15>> Thank you.

02:17So is through a review um of our current

02:21uh potential change order and

02:22contingency status as of today. So total

02:26approved to date is $517,681.90

02:34uh or roughly 61% of the contingency

02:37with a total potential changes um

02:41estimated at this time are $215,72

02:45or roughly 25% of the overall

02:48contingency.

02:50Um, if everything that it has been

02:52submitted is approved as it is, then we

02:57will have $114,133

03:01remaining in the contingency

03:05and we will have used roughly 86% of the

03:08contingency.

03:12Any questions before I move on further

03:14into the financial update?

03:24So this is our um budget status report

03:27included in the June vendor invoice

03:30package which was sent out I believe

03:33yesterday

03:35um

03:38included in the link in the email that

03:40Lynn also it's the reminder email.

03:46So overall commitments for the for our

03:50for Vert.Ex's contract is 931,490

03:56uh with $810,933

03:59spent and remaining 120,000 roughly

04:03$120,500.

04:11The architect is

04:14um committed

04:16with 1 million 421,500

04:21and spent to date 1,376,550

04:28with 44950

04:30remaining in their contract which is

04:32which which feels reasonable for what

04:35they have remaining.

04:38So

04:41all right um

04:44construction committed to date is

04:468,836,243

04:50was spent to date 6,31724

04:55with 2,51919

04:59left spent. Uh I believe they're roughly

05:02um 72 we're roughly 72%

05:06with our spent uh with our cash flow or

05:10they're 70%

05:13spent um with their project budget

05:17believe

05:20um

05:22FFN. So we have we have some some more

05:26committed uh this month with 453,997

05:32spent to date of that is 3,120.

05:36Uh so we're in good shape with both the

05:38FF and the the furniture and computer

05:42budget computers and technology budget

05:44um with more we can draw from with the

05:47temp space if we have overruns in either

05:50FFN or project contingency

05:55um

05:58which stands

06:01so total committed to date is 12

06:03million79,000

06:05868

06:07spent to date. It's $8,834

06:12$8345.

06:14We're left to spend 3,245,864

06:22and available that has not been yet

06:23committed is 1,762,452.

06:30any Oh, I see some hands raised

06:33like Peter.

06:35>> Yeah, the um furnishings and fixtures um

06:40the uncommitted amount,

06:44>> the available amount.

06:46>> Do we anticipate that all getting spent?

06:48It seems like it's late in the game for

06:50not being committed yet, but I just

06:52wondered for clarification.

06:55We we anticipate that that commitment

06:57value will increase as we receive um

07:02more um quotes and final final invoices

07:06from the vendors that we're contracted

07:09with through getting furniture.

07:14And we also anticipate the technology

07:17budget uh the commitments also going up

07:19slightly there as we um finalize what

07:24technology requirements are needed for

07:27the library

07:28as we draw closer to the end. Is there a

07:31guess Mike we can provide on that

07:33remaining that 461 or even Kate I know

07:35you both are working on that very

07:38closely um of that 461 is it fairly well

07:41spent out or or not spent out but um

07:44budgeted if you will for remaining items

07:50>> um

07:53>> I can I can talk on that mic if that's

07:55helpful. Um I think that we went into

07:58this um with the budget that was based

08:00on the estimate of what we need. Um my

08:03anticipation is that we will spend our

08:05our plan is to spend that money on FFN.

08:08So we've got um part of the way that the

08:11orders work is that we do a lot of back

08:13and forth before we actually get um the

08:17final quote order invoice in. Um and so

08:22it definitely looks like less is spent

08:24than is committed. Um, so there's that

08:28piece. The other piece is so technology.

08:30We've not purchased a single piece of

08:32technology for the space yet. So that's

08:35a big line that still has to get um

08:38purchased.

08:40So there's a lot of things that we can't

08:41do kind of until we get closer to the

08:43end. Partly

08:45um for things that don't have a a long

08:48lead time. Um, part of the strategy is

08:51to get the shelving up and then kind of

08:54see what we've got. Um, it's a little

08:57abstract to understand how much wall

08:58space we'll have. It's a little abstract

09:00to understand um, some of the space that

09:03we'll have. Um, the other piece of it

09:05that we were kind of discussing today

09:07after the meeting is that some of the

09:09FFN budget is put aside that we kind of

09:12purposefully will wait until

09:15everything that we ordered come in

09:17because we don't know how the public's

09:20going to interact with that space. We

09:22don't know if there's going to be things

09:23like storage shelving, things that we

09:25just kind of didn't anticipate needing.

09:28>> Um, those we may not be aware of until

09:31after we open to the public. um you

09:34know, we may have the public using, I

09:35don't know, something in a way that we

09:38just didn't anticipate and so we need to

09:40buy, you know, this table because we

09:43didn't think about the fact that we

09:44needed a table in that particular spot

09:46to use the selfch checkckouts or

09:47something like that. So, we do need to

09:49leave a little wiggle room in that um in

09:52that fund. Um and we're doing our best

09:54to

09:57to come in under budget if we can. So,

10:00one thing that's helpful is we've been

10:01applying for a lot of grants. um

10:03specifically technology grants that will

10:05help in that line. But I would say um my

10:09guess is we're gonna when all the dust

10:11settles we'll we'll probably be at what

10:13we budgeted there. um

10:20>> very helpful and I know as I said you

10:22Mike and and the LPA team has been have

10:25been working quite hard to try to get

10:27and manage all that and and evaluate all

10:30that just as you described in in great

10:32uh great detail there. Kate, thanks.

10:33Thank you.

10:38Any

10:42other questions on on this on Mike's

10:44presentation?

10:55Um, so invoices. Oh, I forgot to change

10:58the date on top of there. It should say

11:006:31. Um, but these are the invoices

11:04received for June. Um, so we've received

11:07invoices from Vert.Ex, LPA, BCM,

11:11Controls, which is the security vendor,

11:14um, that we've we've already we

11:16previously approved their budget for,

11:19and then, um, building evolutions, who

11:22is the commissioning agent, um, who you

11:25approved the amendment to Vert.ex

11:27contract for CW Mars

11:31who is a library vendor

11:33um and then SVER construction.

11:36So that totals out to $75,569.93

11:43uh recommended for payment during the

11:46period of June.

11:51Any questions on any of them?

11:57Do we need a vote to approve those,

11:59Mike?

12:00>> Yes.

12:01>> Okay. Could I have a motion, please?

12:05>> Motion to approve the invoices as shown

12:08on the screen.

12:09>> Thank you, Pete. Second.

12:14>> I'll second it.

12:15>> Thank you.

12:18So, I will go across my screen. Um, Pete

12:23>> Dbeck. Yes,

12:25>> Mary.

12:26>> Mary Johnson. Yes,

12:29>> Al

12:30>> Gordon. Yes,

12:32>> Walter

12:34>> Lesley. Yes,

12:36>> Bob.

12:37>> Peterson. Yes.

12:39>> Kate

12:42Croachio. Yes.

12:48>> I couldn't see if she voted.

12:52Yeah, we'll come back.

12:53>> Yes. Oh,

12:54>> there you go. Sean, [snorts]

12:57>> yes.

12:58>> Ed,

12:59>> yes,

13:02>> Bill.

13:04>> Yes,

13:05>> Lynn.

13:07>> Yes.

13:10>> And

13:12that looks like

13:15Oh,

13:17>> and I am a yes. So, invoices are

13:20approved.

13:21Thank you.

13:26Uh construction update. Uh so throughout

13:31the month of June, they continued

13:32installing uh MEP fire protection uh and

13:37finishes. So lighting. Um you can't see

13:40in the by the room I'm in. They've

13:41installed the finished lighting fixtures

13:43in the teen space. Uh they've completed

13:46most of the drywall installation.

13:47They're still doing some plaster work in

13:49the 1908 section. Uh they're continuing

13:52to apply paint around the building, but

13:54a majority of the spaces are finished

13:56painted with little signs up that say,

13:58"Please respect these walls are finished

14:00painted." The minute mill work

14:03installation is ongoing as spaces are

14:05available for them. The slate roof

14:09installation is has continued. is

14:11roughly 95% complete with the majority

14:14remaining is the copper installation

14:16along the edges of the roof. Um the PVC

14:21roof demo has taken place and that uh

14:25underllayment has gone down. So that

14:27includes the weather barrier.

14:29They're just awaiting um some material

14:32to finish that and also coordinating

14:35with the installation of the rooftop

14:37equipment there.

14:39Um interior tile is ongoing in the

14:43bathrooms. It's majority complete as

14:45well as a lot of the um plumbing

14:47fixtures have been installed

14:50and the inclu acoustical ceiling

14:53insulation is ongoing. A majority of the

14:55grids are installed if not all of the

14:57grids are installed with the uh tiles

15:01going in that have punctures for um

15:04sprinkler heads or HVAC diffusers or

15:07lights or things of that nature.

15:11Um and also going on was started last

15:14week. Um we have roughly 90% of the

15:18carpet tile installed on the main level

15:20and they've started on the lower level

15:22as well. So that'll be ready for our uh

15:25first round of furniture delivery which

15:27is the shelving and the circulation desk

15:30which is scheduled for the 3rd of

15:32August.

15:35We did receive a schedule update on 713

15:40from Siver. This is one of the first

15:43schedules in a little while that we

15:46received that we actually feel

15:47comfortable with and have some

15:49confidence in. Uh it shows a substantial

15:51completion date of 9:24.

15:54This is a very um conservative schedule.

15:56So it with that meaning that all the

15:58dates and the kind of timelines in there

16:01are built in such a way that um we have

16:04almost 100% certainty that they with

16:06barring unforeseen events that they will

16:10maintain those dates. Um so we're hoping

16:12to make improvements on that as we as we

16:15already are with with some of the

16:16finishes that are going on right now.

16:18Those have made improvements on that

16:20schedule already.

16:26I just want to follow up some of Mike's

16:28good comments. Uh the picture shows some

16:30other things that have happened now that

16:32you can actually see the library there

16:35uh with the trees having been been taken

16:37down and you can see that one tree is as

16:40we uh discussed with you folks uh does

16:42is still in place there. So

16:45>> the dogwood

16:45>> Yeah, the dogwood. Thank you. I was

16:47forgetting the name of that. Um, so

16:50we've we've really, as I think most of

16:52the committee knows, we've really worked

16:54sever hard to to provide a schedule that

16:57that we believe that they believe they

17:01can do. It it's been it's been quite a

17:03process of us trying to gain some

17:06confidence in their ability, I'll even

17:10say, to to provide a a a critical path

17:15schedule that that makes sense. and and

17:18short of Mike just taking it from them

17:20and doing it for them and handing it to

17:22them, um we've we've gone pretty far

17:25trying to to really force them to focus

17:28on this and and and execute it and we're

17:31still struggling with that. But um the

17:34progress has picked up significantly

17:36even since we last met two weeks ago. Um

17:39especially with finishes happening in

17:41the building as you can see with this

17:42picture. I don't want to jump ahead too

17:44far because we I know we have some

17:45updates from Bob as well, but um yeah,

17:48so I'll stop with some of the updates

17:50there, but it it we believe we're going

17:52to pick up sometime from the schedule

17:54that that Mike described. Um

17:57and that's what we have for the moment

17:59and I know we're working with the team

18:00to determine exactly when uh a move date

18:04will happen and and there are a handful

18:06of things in play there. So, we're we're

18:09really focused on that. um you know as

18:11we're in mid July here to to uh

18:14understand exactly what has to happen

18:16there and map out exactly what's has to

18:19happen there to to have the a move

18:21happen and the library open and with a

18:24lot happening uh there to to make sure

18:26we have everything covered. We're also

18:28making sure uh of what timing

18:30requirements we have and also I'll say

18:33what what we can get away with with

18:34starting a little earlier. So all of

18:36those things are happening right now to

18:39be able to provide uh you know that

18:41transition and and uh filling in dates

18:44for all the things I just mentioned. So

18:46it's it's a real team effort to to

18:48achieve that and that's uh you know

18:50we're right in the thick of it right now

18:52trying to make uh bring real dates to

18:54all those things.

18:56So I'll turn over to Bob and Mike back

18:58to to continue. Uh question for from

19:01Walter though.

19:02>> Uh yeah if you could go back one

19:04picture. uh with the slate roof. Yeah.

19:07Um the sophets in that dental molding

19:10there don't look even really scraped

19:13yet. So I was a little surprised that

19:14that wasn't done

19:16>> sort of ahead of the roof or that we're

19:19this late into this thing and there's

19:21this outdoor work that seems like it

19:23could have been done all summer um

19:25that's not done. So could you comment on

19:27why that's so late in the schedule?

19:31>> Is Bob on this Bob's on this call right

19:33Bob?

19:36doesn't look like he is, but um is is

19:39this where where my cursor is? Is that

19:41where you're referring to? And the kind

19:42of this edge work here?

19:44>> Yeah.

19:45>> Um so part of what kind of delayed the

19:50start of that process was um

19:54>> some contention by the painter of first

19:59who owned the removal of the and the

20:02scraping of the paint.

20:05um and then

20:08back and forth because they decided that

20:11they were not going to perform that. So

20:13that then went to a different

20:15subcontractor and who performed the

20:17scraping and the the remediation of that

20:20that paint.

20:22Um and then there was some back and

20:23forth over the acceptability of the

20:26scraping by the painter. So that's gone

20:29some back and forth a lot.

20:30>> It's lead paint there. That's what the

20:32issue was.

20:32>> Yes. Yes.

20:34Um,

20:35so some back and forth between who did

20:37the scraping and then the painter saying

20:39it's not acceptable and then all that

20:41back and forth. So that's kind of what's

20:42delayed that process there. And as also

20:46kind of

20:48what might shed some light on the

20:49progress there is it's not a full

20:52scraping of that lead paint. It's kind

20:55of more of what you are seeing here

20:57where it's removing what is loose and

20:59then what can be re um sealed with the

21:03paint that's going to go on after.

21:06>> The update we received this morning and

21:08because we had this very discussion uh

21:11this morning is the it's about 80% done

21:14around the perimeter and and the one of

21:17the challenges the contractor has had is

21:19to finish this work. So the lifts that

21:22are required to get up into those spaces

21:24and to do that work uh will be done so

21:27that the landscape and the other site

21:29work can be done without needing to get

21:31lifts back on it again.

21:33>> So that was that's exactly the topic we

21:35were discussing this morning. Um, and

21:38actually even to mention on on the site

21:39work standpoint, you can see the trees

21:41are cut and in in the next couple of

21:44days, we'll have mobilization from the

21:46site contractor to start on the sidewalk

21:49work for us to do the demolition of that

21:51concrete that's there and then to

21:53continue right along uh and into until

21:56the completion of those new sidewalks

21:57that we talked about just in the last

21:59couple of meetings. So, we really expect

22:01in the next couple of weeks with the

22:03outside work being done, as you can see,

22:05it isn't quite done, but almost done.

22:07Um, very soon, they'll start that

22:09exterior work and and get all of that

22:11exterior work going. So, kind of kind of

22:13just in time, but also exactly as they

22:15have planned all along to to start that

22:18right about now.

22:19>> And just to add a little bit more to

22:21that, too, this photo, I believe, is

22:23from the I want to say the 30th of June.

22:27Um, so they've made progress since then.

22:29And also this is the last elevation that

22:32they are progressing to with that kind

22:34of work. They started at the uh side

22:36along Parkman Street and work their way

22:38around the front and then this is the

22:40side along the church parking lot. So

22:42that's kind of their last elevation to

22:43do.

22:47>> Um Mike or Steve could can I get an

22:50update on the stewardia

22:52the tree that's on the side by the

22:54church?

22:57>> Yeah. So, this it it has um

23:02it does not look great, but they have

23:04put in effort. They there's a one of

23:06those uh water swells around it right

23:09now to help to retain some water in

23:11there. Um but they're they're they're

23:14trying to

23:17keep it up as best as they can. Um but

23:21it it looks not in great shape.

23:26>> That's putting they're putting for forth

23:29greater effort. They've been putting

23:31forth effort since at least I remember

23:32joining the project.

23:34>> Um

23:36>> my thought was that it does not look

23:38great, but I haven't gotten up close to

23:39it. Just driving past to try and catch a

23:42glimpse. I don't see any leaves on it.

23:45>> And

23:47like I've said before, that was a that

23:49was a gift u in honor of someone who has

23:52since passed.

23:54>> And I'm not really sure how

23:57the committee will explain to the family

24:01that the contractors killed her tree.

24:06So, I don't know what recourse we have

24:09or what we can do to

24:12to fix that beyond it doesn't look good.

24:16>> Well, we've got to do something that's

24:17unacceptable to have treat a gift that

24:20way, whether it's purpose or not. But we

24:22we need to fix that.

24:28Maybe we'll get some comment from the

24:30landscape uh contractor and and

24:33architect to help us figure out what

24:35what best is there is to do. Uh I'm

24:38certainly not an expert. I think you

24:40guys probably all know that, but it

24:42wasn't in fabulous shape before the

24:44project started to be clear. But uh you

24:46know that doesn't mean we can't find a

24:48solution here and and you know so nobody

24:50has to have an awful report back to the

24:52to the family. that that's for sure.

24:54None of us want to have that as a result

24:56here. So, I'm sure we can work on a

24:58solution and and bring the landscape

25:00architect in to uh help us figure out

25:03how best to proceed. Is it is it in a

25:05spot just to to kind of look at that for

25:07a second, is it in a spot that is um

25:11desired or would a different spot be

25:13better? And I don't know the answers to

25:15those questions. It turns out that it

25:17was inadvertently planted on it was it's

25:22over the property line on the church

25:24property. So, if there was a way to move

25:26it onto the library property, that would

25:28be ideal, but it's not something that I

25:31would say, let's

25:33>> drop a a ton of money to move the

25:35[clears throat] tree.

25:36>> Um,

25:37>> so that's just that's my thoughts. Um,

25:41others have hands up. So, let's um let's

25:44go to Bill because his hand was up

25:45first.

25:47>> Yeah, regarding the tree, it has not

25:49been well taken care of during the

25:51construction and

25:53>> Stever has been on top of it. Uh, but

25:55they need to push even harder. Uh

25:58secondly, the schedule as Steve said the

26:00recent one that they submitted 7:13

26:04plus with the comments at today's

26:06afternoon meeting uh make me feel

26:09comfortable for the first time in the

26:11project that we will make the schedule

26:13dates that are in there. I think Bob

26:16feels the same way. Um thank you.

26:24>> Go ahead, Lee.

26:26Oh yeah, on on the tree I was singing,

26:28we do also have the wonderful resource

26:30of our of the new tree warden in the

26:33department of public healthy or public

26:35works. He could probably help with that,

26:37too. But I I I've been somebody who's

26:40donated things in memory of like my

26:41mother at the library and stuff and and

26:43those things are um you know kind of

26:46emotionally

26:47important to families and we want to be

26:50very respectful of their gift and and

26:54make it okay for them. Maybe even get a

26:57little of their guidance if it can't

26:59stay there. You know what else would

27:01they like to do? Maybe a different type

27:03of tree or in a different spot. but that

27:05we will support them and that that it

27:06won't cost them anything that we will

27:08take care of this um whatever way we

27:11have to gifts from the library you know

27:14funding something whatever we need to

27:17make good on it um and then whenever you

27:20have a minute I did want to talk about

27:21the storage of the painting but I can

27:23wait on the agenda for you to give me

27:26some time for that

27:28>> thank you Bill

27:30>> yeah the uh town aberist is a great

27:33person but in In this case, Steve,

27:35please rely upon our engineer and the

27:39contractor to make a solid

27:42recommendation. That's what we have to

27:44go through with our project. Thank you.

27:56This is a more recent photo um of the of

28:01the the main floor space of the library

28:04uh just outside of the team space where

28:05I am now. So you can see the the carpet

28:07tiles have gone down. The ceiling grid

28:10is up mostly finished painted just if

28:13there's any, you know, minor touchup

28:16areas and most of the ceiling grids with

28:19penetrations like this for the um I

28:22believe anal electrical device and then

28:24the diffusers have been installed as

28:26well as the lights the finished lights

28:29on as well.

28:32>> Um this is the lower level today. So,

28:35this is them starting to install the

28:37carpet tiles on in the children's

28:39library area. We have the the ceiling up

28:44and it's the grid up uh and the final

28:46lights are on there down there as well.

28:51So, that is the end of our presentation.

28:56There any questions or additional

28:58questions?

29:06seeing my I have one. Sorry, I couldn't

29:09have one also.

29:10>> Go ahead. Um, [clears throat]

29:12go ahead, Walter.

29:14>> Yeah. Um, the the roof where the the

29:19ceramic tile got taken off. When's that

29:22getting reinstalled?

29:28>> I don't have a def definitive answer,

29:30Mike. I don't know if you do.

29:31>> I don't have I don't have a I don't have

29:33a concrete date yet as that is um one of

29:36those items that we're waiting on the

29:37material for.

29:40>> Um

29:40>> we can speak to the performance of the

29:42roofer which has improved significantly

29:46uh as everybody has participated one way

29:48or another and dragging them forward but

29:50they have uh provided the manpower on

29:53site and they they've done a good job.

29:55they've responded to the designer's

29:58review of the work and to make uh I mean

30:01normal course of the work to make

30:03corrections as as per field visit

30:05comments and so it's it's far improved

30:10you know certainly always could be

30:11better but it's far improved from where

30:13it was in terms of you know the firing

30:15or not firing and and and all of those

30:17things were worked through. Um, so just

30:19to to mention that to this group, it,

30:22you know, they're still there and

30:22they're they're working hard to, you

30:24know, get this thing to the finish line.

30:26So other than having a definitive answer

30:29to your question, Walter, that's at

30:30least the update for how they're how

30:32they're doing.

30:33>> But I mean, you guys said you're more

30:35confident in this schedule, but is

30:37something like that on a schedule or

30:39it's not on a schedule? I don't quite

30:41understand how you guys operate with

30:44that. It's just something you think will

30:46get done between now and then.

30:49Well, the schedule's something like 400

30:51lines long and and certainly every

30:53single thing to be done isn't on the

30:55schedule. The the the flat roof area and

30:57the the synthetic slate tile areas are

31:00listed the to go back and make the

31:02correction of the area where they took

31:03off where they should have taken off.

31:05That's not listed as specific line item.

31:07So to your to your point um you know

31:09we'll we'll certainly have an answer uh

31:11back on that um and get back to the

31:14committee window.

31:17>> Thanks

31:19>> Sean. I saw your hand next.

31:22>> Yeah. Um no thank you Moren. I just saw

31:25that you had listed our next meeting

31:27being four weeks out and there being

31:32two months left

31:34in this um project. That's that's

31:37basically halfway. Should we schedule a

31:40meeting in between or would we just do

31:43that if required?

31:47>> What is the um so

31:51looking to Steve and Mike, are there

31:53going to be things that are coming up

31:55that you're going to need us to vote on

31:57or weigh in on that would require us to

31:59meet more often?

32:02>> What do you think, Mike? I think that it

32:06the short answer is yes in that um it'll

32:10more or less be like what we had on the

32:1330th of June where we met and approved a

32:16CCD and went through that specific type

32:18of update. Um,

32:22as far as an update of of this nature, I

32:26don't know, but that's up to the

32:28committee if they want to be more

32:29frequent than that. Then

32:31>> as as needed might do it, as Sean

32:33suggested, because

32:35>> today we're we're in a good place. We

32:37don't have anything that is in need of a

32:39CCD because we covered all that with the

32:41last meeting two weeks ago. Um, but I

32:44think maybe if we have an as needed date

32:46to at least know when the committee can

32:48get together and and we'll do the

32:50meeting if if if necessary. You know, we

32:52can provide updates certainly. Um, but

32:55in terms of committee action,

32:56[clears throat] um hopefully we don't

32:59need it, but you know, we may as as you

33:00said, Sean, as we're getting close to

33:01the end here.

33:03>> Mike Williams, did you want to weigh in

33:05on that? Is that why your hand is up?

33:07>> Please. Yeah. Um, definitely. Uh there

33:10there are a a handful of items that have

33:15come to light in the last few days that

33:18um will have a cost impact. So um we

33:22will have some recommendations. It would

33:23be helpful to have one towards the end

33:26of um July

33:29to review those and get the approval to

33:32proceed as a CCD.

33:38>> Well, maybe two weeks out from today

33:40happens to be August 4th

33:42just to say that date just because it's

33:45two weeks. Is that something just

33:47worrying you know you can take this

33:50conversation? Um,

33:52Mike Williams, is that helpful? Like if

33:57we tried to call a meeting for the

33:59fourth?

34:01>> Yes, that would be helpful.

34:03>> Okay. So, looking at the committee um

34:07are do we have a quorum available for

34:11um August 4th?

34:14>> I'll check.

34:16>> I am not available.

34:21Pete is not

34:23um is anybody else not available? That

34:25would be I think the easier way because

34:27I can't see all of you on my screen.

34:34So, it sounds like we do have a quorum.

34:36So, um we'll plan to do a meeting on the

34:404th, same time, and um we'll have agenda

34:45items ahead of time. Um,

34:49sounds good.

34:51Okay, Ed, did you have a question?

34:54>> One, the comment, one of the meetings,

34:56one of the sets of minutes actually said

34:59that the contractor was requesting a

35:01meeting on July 30th, if I recall

35:03correctly. So, I think August 4th will

35:06work for that and that's covered. Um,

35:07this is just information from me. Kate,

35:09are you planning to do you have a date

35:11for your grand opening or

35:14not yet? Okay.

35:17>> No, so what we're doing is we kind of

35:19have that that date where we believe

35:21substantial completion will occur and

35:23we're trying to kind of work backwards

35:25from there in a phased moving approach,

35:28>> right?

35:28>> Um and so really trying to get as much

35:31done over there as we can before we

35:33shutter our doors here. Um we had a

35:35discussion at our last board of trustees

35:37meeting. I do anticipate and actually

35:39the guidance from both MBLC and also

35:42almost every library director I talked

35:44to is to anticipate a 4-week closure. Um

35:48and so that is what we're anticipating

35:50here from the moment we close our doors

35:52here in Tempace to the day that we do

35:54our grand opening uh [clears throat] at

35:56the other space to be about four weeks.

35:59So um I I can't give you exact dates um

36:03yet. I don't think we're at that point

36:05um with everything kind of a little bit

36:07fluid. I do anticipate we'll be closer

36:09to knowing what those dates are.

36:12>> Um you know, I would say within the next

36:14few weeks, maybe even next month or so,

36:17knowing that it's construction. So, as

36:20much as we we think we know, um we're

36:23we're going to do our best and most

36:24informed uh decision with with the team.

36:28Okay.

36:28>> Thank you.

36:34Go ahead, Bill.

36:36>> Yeah, that's a very smart answer and all

36:38of us on the team and the trustees

36:41should follow the lead of Kate. There's

36:44too many last minute things. So if we

36:46start saying that it's going to open on

36:49a particular date, uh stay away from it

36:52until like Kate says and Steve has said,

36:56uh we follow through with this final

36:59push from the contractor. Uh secondly,

37:03uh at the last couple of meetings,

37:05there's been comments that the

37:07contractor does not expect to charge any

37:12overtime. And as far as I'm concerned, I

37:16will push Steve and the whole project to

37:20not allow any overtime payment. They've

37:24been too late, too slow through the

37:26whole process up until the last month or

37:28so. I just wanted the committee to be

37:32aware of that so that we're all speaking

37:34with the same language.

37:36>> Thank you.

37:38>> Thank you.

37:39>> Thank you, Bill.

37:43>> Yeah. I uh wondered if it'd be possible

37:45to have another time when the library

37:48building committee could do an on-site

37:50walk through and see the

37:53>> finished near nearer finished state and

37:57um

37:58>> provide better input frankly

38:00>> to the to the voting and so forth.

38:04>> You want to have the meeting in person

38:05two weeks from now?

38:08>> Unfortunately, that's the one.

38:09>> Oh, that's right. [laughter] You

38:10couldn't get there.

38:17and let us know what might work. You

38:19know, we're we can accommodate, you

38:21know, basically anything that you guys

38:22may want to assemble.

38:24>> Okay.

38:26Bill, did you have another question?

38:28Comment.

38:28>> Uh, no, that's a good idea to get

38:31through, but there's a lot of activities

38:33here and the last time people uh said

38:36they would be there and they didn't show

38:39up. So, I would recommend highly that

38:42when you say you're going to be there,

38:43make sure you're there because it's

38:45going to take time away from the

38:48activities that need to be need to be

38:50done andor cleaning areas so that you

38:53can walk through. So, let's make sure

38:55that we follow through with that.

39:00>> Go ahead, Lee.

39:02>> Oh, thank you. So, I'm sorry I was late

39:04getting here. Um, my apologies on the

39:07painting. How many of you have actually

39:09seen that mural that Julia Lincoln

39:12painted in the 50s?

39:14Nobody. I think it's in storage up on

39:17the top floor, which isn't a good place

39:19for it. But I I think to go back to kind

39:21of the first issues about it, we don't

39:24have anyone who's accepted

39:26responsibility for the evaluating the

39:29painting, for storing it, for deciding

39:30where it's going to go. It obviously

39:32isn't the responsibility of the library

39:34to do that. It just sort of ended up

39:36there. Um, we need to figure out, I

39:39think, who wants to take responsibility.

39:41I think it probably should be the board

39:42of Slackman or the town manager,

39:45assistant manager, somebody who can make

39:47decisions about it because we should

39:50evaluate it for value. It should be

39:51insured. I don't know if it's insured

39:53just overall town insurance. Um, and

39:57who's going to take responsibility for

39:59it and where it will where its final

40:01best resting place is. So, I wondered if

40:03it's something that you would like me to

40:05go to the board of selectmen with and

40:07talk to them about it and see if they're

40:09willing to take responsibility. But in

40:11the meantime, I would like an

40:12opportunity to to look at it and see if

40:16it's being damaged right now and if

40:18there's something we have to do right

40:19away. I have a personal stake in it

40:21because I'm in the picture. My parents

40:23are in the picture and um a friend of

40:26ours painted that, Julia Lincoln. So I

40:28have it sort of a emotional attachment

40:30but it's a lovely lovely painting that

40:32shows the history of Westboro painted in

40:34the 50s. Um so we want to make sure it

40:37ends up in a good safe visible place as

40:39a wonderful treasure for the town. So

40:43does anyone have any ideas other than

40:45what I'm suggesting perhaps for me to go

40:48to the selectman and talk to them about

40:50it and go and view it first so I can see

40:51how it looks right now and take a photo

40:53of it. I don't even think we have a

40:55photo. Um the uh

40:58>> I know that the painting you're talking

41:01about is it is not in the library. Um it

41:04has not been in the library. Um last

41:06that I knew of it, it was at the Art and

41:09Frame Emporium and Ed U. Turner was

41:13storing it there. Um Right.

41:15>> And I'm going to defer to to Sean since

41:18his hand is up because I think he wants

41:20to weigh in on this.

41:22>> I spoke to Ed and he said it was at the

41:24library. So now I'm not sure where it

41:26is.

41:27>> Okay,

41:28>> well I'll tell you what, Lee. Um yeah,

41:30I'll talk to the town manager and the

41:32two of us will work to I guess see if we

41:36can locate it to begin with

41:39um and then determine um some course of

41:42action for it.

41:44>> That'd be wonderful.

41:45>> Yeah. I I don't know if you want sort of

41:47email me maybe a few specifics about it.

41:50I don't know if it has a title or that'd

41:52be great and and I will take it from

41:54there.

41:55>> And um so just for you Sean, the mural

42:00came out of the Forbes building. It used

42:02to be in the um second floor hallway of

42:04the Forbes building. So it's it doesn't

42:07really have a connection to the library.

42:09Um and

42:12>> um

42:14I don't I think it's something that we

42:16had been approached at one time about

42:18displaying in the library. At the time

42:20the trustees said said no. But if it

42:24were going to be displayed in the

42:26library that would be a library trustee

42:27decision, not

42:30necessarily the purview of this um

42:33committee.

42:34>> Right. So yeah. So, it's possible it's

42:37been stored since work was done on the

42:40Forbes building or something. So, well,

42:42well, let's see if we can um I guess

42:45first track it down and Lee I'll I'll

42:48follow up with you and then we'll

42:50>> right

42:50>> see what we can

42:51>> Thank you.

42:52>> Thank you, Bill.

42:55>> Yeah, thank you, Sean, for following up

42:56on this, but there's no way that any of

42:58this can be addressed during the

43:00construction period. It'll be months

43:02after the construction. Thank you. Mhm.

43:05>> I sort of consider this a um an issue

43:09outside of this committee.

43:10>> Yes.

43:12>> At least, you know, for the foreseeable

43:14future.

43:15>> Mhm.

43:16>> Okay.

43:18>> Are there any other building related

43:20issues

43:22that we would like to discuss?

43:32Um, you know, this has been a very good

43:35working committee. I'm uh I've talked to

43:38Steve a little bit. I'm a little

43:39concerned that the trustees have a a

43:42real accurate understanding of where the

43:45project is at this time. And I've talked

43:49to Steve and uh I believe Mary feels

43:52somewhat the same way is that Steve and

43:55whoever he recommends come with him, go

43:58to the trustees the next trustees

44:00meeting or call a meeting so that they

44:02fully understand where we are and where

44:05the schedule is etc. So please take that

44:08as advice. Thank you.

44:11>> Thanks Walter. Uh yeah, I was just

44:14wondering um when we last met there was

44:17some discussion about the laap

44:20um and since then I've spent a couple

44:23weekends pulling it out of my own yard.

44:25But I was just wondering whether there

44:27was any further input from the um uh

44:31landscape people on a substitution.

44:36We did discuss that today at our our

44:38project meeting and and I know there was

44:39a clarification needed and the

44:41contractor is getting the um spo is it

44:45Spalain on on this? Yes, Spolain is the

44:47landscape contractor uh and they had

44:50questions on it. They did come to the

44:51site. So, we're just uh we don't have

44:53anything specific to report on it, but

44:55we're on it and and we know and

44:56understand exactly what is to be done.

44:58Uh the designer is going to issue that

45:00uh the documents that that clarify that

45:02as well. So uh certainly not not

45:05forgotten. We just don't have specific

45:07progress to what we'll what what I

45:09expect is we'll bring back a

45:11recommendation to provide in its place

45:14and bring that back to you guys for

45:16honestly I don't remember how to what we

45:18said as far as how to approve whatever

45:20gets recommended but unless someone

45:22tells us differently we can bring it

45:23back to you guys.

45:25>> Yeah, I'm pretty sure we said that your

45:28weekly

45:29>> uh small crew could just approve it at

45:32that point.

45:33um which what we voted but and it has

45:35only been two weeks since our last

45:36meeting but I just thought I would ask

45:38because

45:39>> thanks

45:41>> Mary.

45:42>> Yeah, thanks. I just wanted to um add to

45:45what Bill said. Um I agree. I do get

45:48concerned about um the trustes overall

45:51view of understanding of the timeline of

45:53the project. We do have a online Zoom

45:57meeting. Tomorrow night is our next

45:58trustee meeting um if anyone's able to

46:00come to that Steve or we can throw

46:03another meeting on so that you can give

46:05an update to the trustees about the

46:07current status of the project.

46:10>> Whatever you guys need, we'll happy to

46:12happy to do work with you guys and make

46:14presentations

46:16or would be helpful.

46:17>> Okay, great. Thank you.

46:22>> Any other building related issues?

46:26Move to adjurnn.

46:29>> Second.

46:30>> Oh, was that a motion to adjurnn, Bill?

46:33>> Yes.

46:34>> Oh, thank you.

46:35>> Second.

46:38>> All right. Uh Lee,

46:41>> yes. Bill,

46:44>> yes.

46:45>> Walter,

46:46>> Leslie, yes.

46:48>> Mary

46:49>> Johnson, yes.

46:50>> Al

46:51>> Gordon, yes.

46:53>> Bob,

46:54>> Petraella, yes. Ed

47:04>> Baldwin. Yes. [laughter]

47:06>> Kate

47:09>> Karachio. Yes.

47:10>> Don

47:12>> Eel. Yes.

47:13>> Pete.

47:14>> Donbeck. Yes.

47:16>> Lynn.

47:19Yes.

47:24And I am a yes. So we are adjourned.

47:27Thank you everybody.

47:28>> Thank you. Bye

47:29>> bye.

47:30>> Thank you.

47:31>> You