2026-07-21 - Library Building Committee
Written from the auto-generated captions; names and numbers may be misheard. The recording opens during a vote on earlier minutes.
- Minutes of the prior meeting were approved on a roll call with several abstentions from members who were absent. A member noted the June 16 video had not been posted to the town's video channel.
- Contingency: about $517,700 approved to date (roughly 61 percent), with about $215,700 in potential changes pending; if all are approved, about $114,100 would remain and about 86 percent would be used.
- Budget report (June package): construction about 70 to 72 percent spent against its commitment; the architect nearly fully paid; about $1.76 million of the overall budget not yet committed, mostly furniture, fixtures and technology. Library staff said no technology has been bought yet, some furniture money is held back until the public uses the space, and grants are being sought to reduce costs.
- June invoices totaling about $75,570 were approved on a roll call.
- Construction update: finish lighting, drywall, paint, tile and ceiling grids are largely done; the slate roof is about 95 percent complete with copper edging remaining; about 90 percent of carpet tile is down on the main level and started on the lower level, ready for the first furniture delivery (shelving and circulation desk) on August 3. A July 13 contractor schedule showed substantial completion on September 24 and was described as conservative and the first the team trusted.
- Exterior trim paint work was delayed by a dispute over who would remove lead paint and the acceptability of the scraping; work was about 80 percent done around the perimeter, with sidewalk demolition and site work about to start.
- The memorial Stewartia tree beside the church appears to be in poor shape despite watering efforts; members said it must be fixed and the family treated respectfully, and asked the landscape architect and contractor for a recommendation.
- Members asked when the removed roof tile would be reinstalled (no date; waiting on material) and pressed that the contractor not be paid overtime.
- A special meeting was set for August 4 to approve upcoming change directives. The library director said to plan on a four-week closure between leaving the temporary space and the grand opening, with dates to come.
- A member asked who is responsible for a mural from the old Forbes building; the assistant town manager offered to help locate it, and it was treated as outside this committee for now.
- Trustees' awareness of the schedule was a concern; the owner's project manager was urged to brief the trustees, whose next meeting is the following night. The landscape contractor is still sorting out a replacement for an invasive plant in the plan.
Issues discussed
- Library Building Project
- Library Construction Completion and Reopening
- Library Project Budget and Contractor Payments
- Library Memorial Tree
- Forbes Building Mural Storage
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:08Great. Thank you.
00:10>> So, I will go across my screen for the
00:12vote. Bob,
00:14>> uh, Patrick, yes.
00:15>> Mary,
00:17>> I'm going to abstain.
00:18>> Lynn,
00:20>> pick up. Yes.
00:23>> Bill,
00:24>> abstain.
00:28Al
00:30>> Gordon. Yes.
00:34>> Uh Walter
00:35>> Leslie. Yes.
00:37>> Pete
00:39>> back. Yes.
00:42>> Uh Kate
00:49Karachu. Yes. Sorry, I'm on like three
00:51different screens so and one of them
00:53doesn't work but that's the one with my
00:54camera. So
00:56>> yes, [laughter]
00:57thank you Ed.
01:00>> Oh abstain
01:05>> and
01:07did I Sean?
01:09>> Eio yes.
01:10>> Okay. And I will also abstain because I
01:15was not there. Um but I think we have
01:17enough votes. Mary correct me if I'm
01:19wrong to approve those that set of
01:22minutes.
01:24>> Thanks. Yeah, we got six.
01:25>> Okay, thank you,
01:27>> Walter.
01:28>> Um, yeah, I just wanted to note that the
01:30minutes they're not the minutes, the the
01:33video of the 16th did not get posted
01:37to the uh West Bro TV. So, I don't know
01:41if we could still do that. Um, the
01:4430th's up there, but not the 16th.
01:47>> I will check with Aiden because I sent
01:49him both. So, I'll find out.
01:53>> Thanks. going on with that.
01:54>> Yeah, because I actually missed that
01:55meeting. So, I went to
01:56>> list
01:58>> I couldn't find it.
02:02>> Thank you, Lyn.
02:05Okay, so uh
02:08thank you for reminding us about minutes
02:10so we can move on to our um project
02:13discussion.
02:15>> Thank you.
02:17So is through a review um of our current
02:21uh potential change order and
02:22contingency status as of today. So total
02:26approved to date is $517,681.90
02:34uh or roughly 61% of the contingency
02:37with a total potential changes um
02:41estimated at this time are $215,72
02:45or roughly 25% of the overall
02:48contingency.
02:50Um, if everything that it has been
02:52submitted is approved as it is, then we
02:57will have $114,133
03:01remaining in the contingency
03:05and we will have used roughly 86% of the
03:08contingency.
03:12Any questions before I move on further
03:14into the financial update?
03:24So this is our um budget status report
03:27included in the June vendor invoice
03:30package which was sent out I believe
03:33yesterday
03:35um
03:38included in the link in the email that
03:40Lynn also it's the reminder email.
03:46So overall commitments for the for our
03:50for Vert.Ex's contract is 931,490
03:56uh with $810,933
03:59spent and remaining 120,000 roughly
04:03$120,500.
04:11The architect is
04:14um committed
04:16with 1 million 421,500
04:21and spent to date 1,376,550
04:28with 44950
04:30remaining in their contract which is
04:32which which feels reasonable for what
04:35they have remaining.
04:38So
04:41all right um
04:44construction committed to date is
04:468,836,243
04:50was spent to date 6,31724
04:55with 2,51919
04:59left spent. Uh I believe they're roughly
05:02um 72 we're roughly 72%
05:06with our spent uh with our cash flow or
05:10they're 70%
05:13spent um with their project budget
05:17believe
05:20um
05:22FFN. So we have we have some some more
05:26committed uh this month with 453,997
05:32spent to date of that is 3,120.
05:36Uh so we're in good shape with both the
05:38FF and the the furniture and computer
05:42budget computers and technology budget
05:44um with more we can draw from with the
05:47temp space if we have overruns in either
05:50FFN or project contingency
05:55um
05:58which stands
06:01so total committed to date is 12
06:03million79,000
06:05868
06:07spent to date. It's $8,834
06:12$8345.
06:14We're left to spend 3,245,864
06:22and available that has not been yet
06:23committed is 1,762,452.
06:30any Oh, I see some hands raised
06:33like Peter.
06:35>> Yeah, the um furnishings and fixtures um
06:40the uncommitted amount,
06:44>> the available amount.
06:46>> Do we anticipate that all getting spent?
06:48It seems like it's late in the game for
06:50not being committed yet, but I just
06:52wondered for clarification.
06:55We we anticipate that that commitment
06:57value will increase as we receive um
07:02more um quotes and final final invoices
07:06from the vendors that we're contracted
07:09with through getting furniture.
07:14And we also anticipate the technology
07:17budget uh the commitments also going up
07:19slightly there as we um finalize what
07:24technology requirements are needed for
07:27the library
07:28as we draw closer to the end. Is there a
07:31guess Mike we can provide on that
07:33remaining that 461 or even Kate I know
07:35you both are working on that very
07:38closely um of that 461 is it fairly well
07:41spent out or or not spent out but um
07:44budgeted if you will for remaining items
07:50>> um
07:53>> I can I can talk on that mic if that's
07:55helpful. Um I think that we went into
07:58this um with the budget that was based
08:00on the estimate of what we need. Um my
08:03anticipation is that we will spend our
08:05our plan is to spend that money on FFN.
08:08So we've got um part of the way that the
08:11orders work is that we do a lot of back
08:13and forth before we actually get um the
08:17final quote order invoice in. Um and so
08:22it definitely looks like less is spent
08:24than is committed. Um, so there's that
08:28piece. The other piece is so technology.
08:30We've not purchased a single piece of
08:32technology for the space yet. So that's
08:35a big line that still has to get um
08:38purchased.
08:40So there's a lot of things that we can't
08:41do kind of until we get closer to the
08:43end. Partly
08:45um for things that don't have a a long
08:48lead time. Um, part of the strategy is
08:51to get the shelving up and then kind of
08:54see what we've got. Um, it's a little
08:57abstract to understand how much wall
08:58space we'll have. It's a little abstract
09:00to understand um, some of the space that
09:03we'll have. Um, the other piece of it
09:05that we were kind of discussing today
09:07after the meeting is that some of the
09:09FFN budget is put aside that we kind of
09:12purposefully will wait until
09:15everything that we ordered come in
09:17because we don't know how the public's
09:20going to interact with that space. We
09:22don't know if there's going to be things
09:23like storage shelving, things that we
09:25just kind of didn't anticipate needing.
09:28>> Um, those we may not be aware of until
09:31after we open to the public. um you
09:34know, we may have the public using, I
09:35don't know, something in a way that we
09:38just didn't anticipate and so we need to
09:40buy, you know, this table because we
09:43didn't think about the fact that we
09:44needed a table in that particular spot
09:46to use the selfch checkckouts or
09:47something like that. So, we do need to
09:49leave a little wiggle room in that um in
09:52that fund. Um and we're doing our best
09:54to
09:57to come in under budget if we can. So,
10:00one thing that's helpful is we've been
10:01applying for a lot of grants. um
10:03specifically technology grants that will
10:05help in that line. But I would say um my
10:09guess is we're gonna when all the dust
10:11settles we'll we'll probably be at what
10:13we budgeted there. um
10:20>> very helpful and I know as I said you
10:22Mike and and the LPA team has been have
10:25been working quite hard to try to get
10:27and manage all that and and evaluate all
10:30that just as you described in in great
10:32uh great detail there. Kate, thanks.
10:33Thank you.
10:38Any
10:42other questions on on this on Mike's
10:44presentation?
10:55Um, so invoices. Oh, I forgot to change
10:58the date on top of there. It should say
11:006:31. Um, but these are the invoices
11:04received for June. Um, so we've received
11:07invoices from Vert.Ex, LPA, BCM,
11:11Controls, which is the security vendor,
11:14um, that we've we've already we
11:16previously approved their budget for,
11:19and then, um, building evolutions, who
11:22is the commissioning agent, um, who you
11:25approved the amendment to Vert.ex
11:27contract for CW Mars
11:31who is a library vendor
11:33um and then SVER construction.
11:36So that totals out to $75,569.93
11:43uh recommended for payment during the
11:46period of June.
11:51Any questions on any of them?
11:57Do we need a vote to approve those,
11:59Mike?
12:00>> Yes.
12:01>> Okay. Could I have a motion, please?
12:05>> Motion to approve the invoices as shown
12:08on the screen.
12:09>> Thank you, Pete. Second.
12:14>> I'll second it.
12:15>> Thank you.
12:18So, I will go across my screen. Um, Pete
12:23>> Dbeck. Yes,
12:25>> Mary.
12:26>> Mary Johnson. Yes,
12:29>> Al
12:30>> Gordon. Yes,
12:32>> Walter
12:34>> Lesley. Yes,
12:36>> Bob.
12:37>> Peterson. Yes.
12:39>> Kate
12:42Croachio. Yes.
12:48>> I couldn't see if she voted.
12:52Yeah, we'll come back.
12:53>> Yes. Oh,
12:54>> there you go. Sean, [snorts]
12:57>> yes.
12:58>> Ed,
12:59>> yes,
13:02>> Bill.
13:04>> Yes,
13:05>> Lynn.
13:07>> Yes.
13:10>> And
13:12that looks like
13:15Oh,
13:17>> and I am a yes. So, invoices are
13:20approved.
13:21Thank you.
13:26Uh construction update. Uh so throughout
13:31the month of June, they continued
13:32installing uh MEP fire protection uh and
13:37finishes. So lighting. Um you can't see
13:40in the by the room I'm in. They've
13:41installed the finished lighting fixtures
13:43in the teen space. Uh they've completed
13:46most of the drywall installation.
13:47They're still doing some plaster work in
13:49the 1908 section. Uh they're continuing
13:52to apply paint around the building, but
13:54a majority of the spaces are finished
13:56painted with little signs up that say,
13:58"Please respect these walls are finished
14:00painted." The minute mill work
14:03installation is ongoing as spaces are
14:05available for them. The slate roof
14:09installation is has continued. is
14:11roughly 95% complete with the majority
14:14remaining is the copper installation
14:16along the edges of the roof. Um the PVC
14:21roof demo has taken place and that uh
14:25underllayment has gone down. So that
14:27includes the weather barrier.
14:29They're just awaiting um some material
14:32to finish that and also coordinating
14:35with the installation of the rooftop
14:37equipment there.
14:39Um interior tile is ongoing in the
14:43bathrooms. It's majority complete as
14:45well as a lot of the um plumbing
14:47fixtures have been installed
14:50and the inclu acoustical ceiling
14:53insulation is ongoing. A majority of the
14:55grids are installed if not all of the
14:57grids are installed with the uh tiles
15:01going in that have punctures for um
15:04sprinkler heads or HVAC diffusers or
15:07lights or things of that nature.
15:11Um and also going on was started last
15:14week. Um we have roughly 90% of the
15:18carpet tile installed on the main level
15:20and they've started on the lower level
15:22as well. So that'll be ready for our uh
15:25first round of furniture delivery which
15:27is the shelving and the circulation desk
15:30which is scheduled for the 3rd of
15:32August.
15:35We did receive a schedule update on 713
15:40from Siver. This is one of the first
15:43schedules in a little while that we
15:46received that we actually feel
15:47comfortable with and have some
15:49confidence in. Uh it shows a substantial
15:51completion date of 9:24.
15:54This is a very um conservative schedule.
15:56So it with that meaning that all the
15:58dates and the kind of timelines in there
16:01are built in such a way that um we have
16:04almost 100% certainty that they with
16:06barring unforeseen events that they will
16:10maintain those dates. Um so we're hoping
16:12to make improvements on that as we as we
16:15already are with with some of the
16:16finishes that are going on right now.
16:18Those have made improvements on that
16:20schedule already.
16:26I just want to follow up some of Mike's
16:28good comments. Uh the picture shows some
16:30other things that have happened now that
16:32you can actually see the library there
16:35uh with the trees having been been taken
16:37down and you can see that one tree is as
16:40we uh discussed with you folks uh does
16:42is still in place there. So
16:45>> the dogwood
16:45>> Yeah, the dogwood. Thank you. I was
16:47forgetting the name of that. Um, so
16:50we've we've really, as I think most of
16:52the committee knows, we've really worked
16:54sever hard to to provide a schedule that
16:57that we believe that they believe they
17:01can do. It it's been it's been quite a
17:03process of us trying to gain some
17:06confidence in their ability, I'll even
17:10say, to to provide a a a critical path
17:15schedule that that makes sense. and and
17:18short of Mike just taking it from them
17:20and doing it for them and handing it to
17:22them, um we've we've gone pretty far
17:25trying to to really force them to focus
17:28on this and and and execute it and we're
17:31still struggling with that. But um the
17:34progress has picked up significantly
17:36even since we last met two weeks ago. Um
17:39especially with finishes happening in
17:41the building as you can see with this
17:42picture. I don't want to jump ahead too
17:44far because we I know we have some
17:45updates from Bob as well, but um yeah,
17:48so I'll stop with some of the updates
17:50there, but it it we believe we're going
17:52to pick up sometime from the schedule
17:54that that Mike described. Um
17:57and that's what we have for the moment
17:59and I know we're working with the team
18:00to determine exactly when uh a move date
18:04will happen and and there are a handful
18:06of things in play there. So, we're we're
18:09really focused on that. um you know as
18:11we're in mid July here to to uh
18:14understand exactly what has to happen
18:16there and map out exactly what's has to
18:19happen there to to have the a move
18:21happen and the library open and with a
18:24lot happening uh there to to make sure
18:26we have everything covered. We're also
18:28making sure uh of what timing
18:30requirements we have and also I'll say
18:33what what we can get away with with
18:34starting a little earlier. So all of
18:36those things are happening right now to
18:39be able to provide uh you know that
18:41transition and and uh filling in dates
18:44for all the things I just mentioned. So
18:46it's it's a real team effort to to
18:48achieve that and that's uh you know
18:50we're right in the thick of it right now
18:52trying to make uh bring real dates to
18:54all those things.
18:56So I'll turn over to Bob and Mike back
18:58to to continue. Uh question for from
19:01Walter though.
19:02>> Uh yeah if you could go back one
19:04picture. uh with the slate roof. Yeah.
19:07Um the sophets in that dental molding
19:10there don't look even really scraped
19:13yet. So I was a little surprised that
19:14that wasn't done
19:16>> sort of ahead of the roof or that we're
19:19this late into this thing and there's
19:21this outdoor work that seems like it
19:23could have been done all summer um
19:25that's not done. So could you comment on
19:27why that's so late in the schedule?
19:31>> Is Bob on this Bob's on this call right
19:33Bob?
19:36doesn't look like he is, but um is is
19:39this where where my cursor is? Is that
19:41where you're referring to? And the kind
19:42of this edge work here?
19:44>> Yeah.
19:45>> Um so part of what kind of delayed the
19:50start of that process was um
19:54>> some contention by the painter of first
19:59who owned the removal of the and the
20:02scraping of the paint.
20:05um and then
20:08back and forth because they decided that
20:11they were not going to perform that. So
20:13that then went to a different
20:15subcontractor and who performed the
20:17scraping and the the remediation of that
20:20that paint.
20:22Um and then there was some back and
20:23forth over the acceptability of the
20:26scraping by the painter. So that's gone
20:29some back and forth a lot.
20:30>> It's lead paint there. That's what the
20:32issue was.
20:32>> Yes. Yes.
20:34Um,
20:35so some back and forth between who did
20:37the scraping and then the painter saying
20:39it's not acceptable and then all that
20:41back and forth. So that's kind of what's
20:42delayed that process there. And as also
20:46kind of
20:48what might shed some light on the
20:49progress there is it's not a full
20:52scraping of that lead paint. It's kind
20:55of more of what you are seeing here
20:57where it's removing what is loose and
20:59then what can be re um sealed with the
21:03paint that's going to go on after.
21:06>> The update we received this morning and
21:08because we had this very discussion uh
21:11this morning is the it's about 80% done
21:14around the perimeter and and the one of
21:17the challenges the contractor has had is
21:19to finish this work. So the lifts that
21:22are required to get up into those spaces
21:24and to do that work uh will be done so
21:27that the landscape and the other site
21:29work can be done without needing to get
21:31lifts back on it again.
21:33>> So that was that's exactly the topic we
21:35were discussing this morning. Um, and
21:38actually even to mention on on the site
21:39work standpoint, you can see the trees
21:41are cut and in in the next couple of
21:44days, we'll have mobilization from the
21:46site contractor to start on the sidewalk
21:49work for us to do the demolition of that
21:51concrete that's there and then to
21:53continue right along uh and into until
21:56the completion of those new sidewalks
21:57that we talked about just in the last
21:59couple of meetings. So, we really expect
22:01in the next couple of weeks with the
22:03outside work being done, as you can see,
22:05it isn't quite done, but almost done.
22:07Um, very soon, they'll start that
22:09exterior work and and get all of that
22:11exterior work going. So, kind of kind of
22:13just in time, but also exactly as they
22:15have planned all along to to start that
22:18right about now.
22:19>> And just to add a little bit more to
22:21that, too, this photo, I believe, is
22:23from the I want to say the 30th of June.
22:27Um, so they've made progress since then.
22:29And also this is the last elevation that
22:32they are progressing to with that kind
22:34of work. They started at the uh side
22:36along Parkman Street and work their way
22:38around the front and then this is the
22:40side along the church parking lot. So
22:42that's kind of their last elevation to
22:43do.
22:47>> Um Mike or Steve could can I get an
22:50update on the stewardia
22:52the tree that's on the side by the
22:54church?
22:57>> Yeah. So, this it it has um
23:02it does not look great, but they have
23:04put in effort. They there's a one of
23:06those uh water swells around it right
23:09now to help to retain some water in
23:11there. Um but they're they're they're
23:14trying to
23:17keep it up as best as they can. Um but
23:21it it looks not in great shape.
23:26>> That's putting they're putting for forth
23:29greater effort. They've been putting
23:31forth effort since at least I remember
23:32joining the project.
23:34>> Um
23:36>> my thought was that it does not look
23:38great, but I haven't gotten up close to
23:39it. Just driving past to try and catch a
23:42glimpse. I don't see any leaves on it.
23:45>> And
23:47like I've said before, that was a that
23:49was a gift u in honor of someone who has
23:52since passed.
23:54>> And I'm not really sure how
23:57the committee will explain to the family
24:01that the contractors killed her tree.
24:06So, I don't know what recourse we have
24:09or what we can do to
24:12to fix that beyond it doesn't look good.
24:16>> Well, we've got to do something that's
24:17unacceptable to have treat a gift that
24:20way, whether it's purpose or not. But we
24:22we need to fix that.
24:28Maybe we'll get some comment from the
24:30landscape uh contractor and and
24:33architect to help us figure out what
24:35what best is there is to do. Uh I'm
24:38certainly not an expert. I think you
24:40guys probably all know that, but it
24:42wasn't in fabulous shape before the
24:44project started to be clear. But uh you
24:46know that doesn't mean we can't find a
24:48solution here and and you know so nobody
24:50has to have an awful report back to the
24:52to the family. that that's for sure.
24:54None of us want to have that as a result
24:56here. So, I'm sure we can work on a
24:58solution and and bring the landscape
25:00architect in to uh help us figure out
25:03how best to proceed. Is it is it in a
25:05spot just to to kind of look at that for
25:07a second, is it in a spot that is um
25:11desired or would a different spot be
25:13better? And I don't know the answers to
25:15those questions. It turns out that it
25:17was inadvertently planted on it was it's
25:22over the property line on the church
25:24property. So, if there was a way to move
25:26it onto the library property, that would
25:28be ideal, but it's not something that I
25:31would say, let's
25:33>> drop a a ton of money to move the
25:35[clears throat] tree.
25:36>> Um,
25:37>> so that's just that's my thoughts. Um,
25:41others have hands up. So, let's um let's
25:44go to Bill because his hand was up
25:45first.
25:47>> Yeah, regarding the tree, it has not
25:49been well taken care of during the
25:51construction and
25:53>> Stever has been on top of it. Uh, but
25:55they need to push even harder. Uh
25:58secondly, the schedule as Steve said the
26:00recent one that they submitted 7:13
26:04plus with the comments at today's
26:06afternoon meeting uh make me feel
26:09comfortable for the first time in the
26:11project that we will make the schedule
26:13dates that are in there. I think Bob
26:16feels the same way. Um thank you.
26:24>> Go ahead, Lee.
26:26Oh yeah, on on the tree I was singing,
26:28we do also have the wonderful resource
26:30of our of the new tree warden in the
26:33department of public healthy or public
26:35works. He could probably help with that,
26:37too. But I I I've been somebody who's
26:40donated things in memory of like my
26:41mother at the library and stuff and and
26:43those things are um you know kind of
26:46emotionally
26:47important to families and we want to be
26:50very respectful of their gift and and
26:54make it okay for them. Maybe even get a
26:57little of their guidance if it can't
26:59stay there. You know what else would
27:01they like to do? Maybe a different type
27:03of tree or in a different spot. but that
27:05we will support them and that that it
27:06won't cost them anything that we will
27:08take care of this um whatever way we
27:11have to gifts from the library you know
27:14funding something whatever we need to
27:17make good on it um and then whenever you
27:20have a minute I did want to talk about
27:21the storage of the painting but I can
27:23wait on the agenda for you to give me
27:26some time for that
27:28>> thank you Bill
27:30>> yeah the uh town aberist is a great
27:33person but in In this case, Steve,
27:35please rely upon our engineer and the
27:39contractor to make a solid
27:42recommendation. That's what we have to
27:44go through with our project. Thank you.
27:56This is a more recent photo um of the of
28:01the the main floor space of the library
28:04uh just outside of the team space where
28:05I am now. So you can see the the carpet
28:07tiles have gone down. The ceiling grid
28:10is up mostly finished painted just if
28:13there's any, you know, minor touchup
28:16areas and most of the ceiling grids with
28:19penetrations like this for the um I
28:22believe anal electrical device and then
28:24the diffusers have been installed as
28:26well as the lights the finished lights
28:29on as well.
28:32>> Um this is the lower level today. So,
28:35this is them starting to install the
28:37carpet tiles on in the children's
28:39library area. We have the the ceiling up
28:44and it's the grid up uh and the final
28:46lights are on there down there as well.
28:51So, that is the end of our presentation.
28:56There any questions or additional
28:58questions?
29:06seeing my I have one. Sorry, I couldn't
29:09have one also.
29:10>> Go ahead. Um, [clears throat]
29:12go ahead, Walter.
29:14>> Yeah. Um, the the roof where the the
29:19ceramic tile got taken off. When's that
29:22getting reinstalled?
29:28>> I don't have a def definitive answer,
29:30Mike. I don't know if you do.
29:31>> I don't have I don't have a I don't have
29:33a concrete date yet as that is um one of
29:36those items that we're waiting on the
29:37material for.
29:40>> Um
29:40>> we can speak to the performance of the
29:42roofer which has improved significantly
29:46uh as everybody has participated one way
29:48or another and dragging them forward but
29:50they have uh provided the manpower on
29:53site and they they've done a good job.
29:55they've responded to the designer's
29:58review of the work and to make uh I mean
30:01normal course of the work to make
30:03corrections as as per field visit
30:05comments and so it's it's far improved
30:10you know certainly always could be
30:11better but it's far improved from where
30:13it was in terms of you know the firing
30:15or not firing and and and all of those
30:17things were worked through. Um, so just
30:19to to mention that to this group, it,
30:22you know, they're still there and
30:22they're they're working hard to, you
30:24know, get this thing to the finish line.
30:26So other than having a definitive answer
30:29to your question, Walter, that's at
30:30least the update for how they're how
30:32they're doing.
30:33>> But I mean, you guys said you're more
30:35confident in this schedule, but is
30:37something like that on a schedule or
30:39it's not on a schedule? I don't quite
30:41understand how you guys operate with
30:44that. It's just something you think will
30:46get done between now and then.
30:49Well, the schedule's something like 400
30:51lines long and and certainly every
30:53single thing to be done isn't on the
30:55schedule. The the the flat roof area and
30:57the the synthetic slate tile areas are
31:00listed the to go back and make the
31:02correction of the area where they took
31:03off where they should have taken off.
31:05That's not listed as specific line item.
31:07So to your to your point um you know
31:09we'll we'll certainly have an answer uh
31:11back on that um and get back to the
31:14committee window.
31:17>> Thanks
31:19>> Sean. I saw your hand next.
31:22>> Yeah. Um no thank you Moren. I just saw
31:25that you had listed our next meeting
31:27being four weeks out and there being
31:32two months left
31:34in this um project. That's that's
31:37basically halfway. Should we schedule a
31:40meeting in between or would we just do
31:43that if required?
31:47>> What is the um so
31:51looking to Steve and Mike, are there
31:53going to be things that are coming up
31:55that you're going to need us to vote on
31:57or weigh in on that would require us to
31:59meet more often?
32:02>> What do you think, Mike? I think that it
32:06the short answer is yes in that um it'll
32:10more or less be like what we had on the
32:1330th of June where we met and approved a
32:16CCD and went through that specific type
32:18of update. Um,
32:22as far as an update of of this nature, I
32:26don't know, but that's up to the
32:28committee if they want to be more
32:29frequent than that. Then
32:31>> as as needed might do it, as Sean
32:33suggested, because
32:35>> today we're we're in a good place. We
32:37don't have anything that is in need of a
32:39CCD because we covered all that with the
32:41last meeting two weeks ago. Um, but I
32:44think maybe if we have an as needed date
32:46to at least know when the committee can
32:48get together and and we'll do the
32:50meeting if if if necessary. You know, we
32:52can provide updates certainly. Um, but
32:55in terms of committee action,
32:56[clears throat] um hopefully we don't
32:59need it, but you know, we may as as you
33:00said, Sean, as we're getting close to
33:01the end here.
33:03>> Mike Williams, did you want to weigh in
33:05on that? Is that why your hand is up?
33:07>> Please. Yeah. Um, definitely. Uh there
33:10there are a a handful of items that have
33:15come to light in the last few days that
33:18um will have a cost impact. So um we
33:22will have some recommendations. It would
33:23be helpful to have one towards the end
33:26of um July
33:29to review those and get the approval to
33:32proceed as a CCD.
33:38>> Well, maybe two weeks out from today
33:40happens to be August 4th
33:42just to say that date just because it's
33:45two weeks. Is that something just
33:47worrying you know you can take this
33:50conversation? Um,
33:52Mike Williams, is that helpful? Like if
33:57we tried to call a meeting for the
33:59fourth?
34:01>> Yes, that would be helpful.
34:03>> Okay. So, looking at the committee um
34:07are do we have a quorum available for
34:11um August 4th?
34:14>> I'll check.
34:16>> I am not available.
34:21Pete is not
34:23um is anybody else not available? That
34:25would be I think the easier way because
34:27I can't see all of you on my screen.
34:34So, it sounds like we do have a quorum.
34:36So, um we'll plan to do a meeting on the
34:404th, same time, and um we'll have agenda
34:45items ahead of time. Um,
34:49sounds good.
34:51Okay, Ed, did you have a question?
34:54>> One, the comment, one of the meetings,
34:56one of the sets of minutes actually said
34:59that the contractor was requesting a
35:01meeting on July 30th, if I recall
35:03correctly. So, I think August 4th will
35:06work for that and that's covered. Um,
35:07this is just information from me. Kate,
35:09are you planning to do you have a date
35:11for your grand opening or
35:14not yet? Okay.
35:17>> No, so what we're doing is we kind of
35:19have that that date where we believe
35:21substantial completion will occur and
35:23we're trying to kind of work backwards
35:25from there in a phased moving approach,
35:28>> right?
35:28>> Um and so really trying to get as much
35:31done over there as we can before we
35:33shutter our doors here. Um we had a
35:35discussion at our last board of trustees
35:37meeting. I do anticipate and actually
35:39the guidance from both MBLC and also
35:42almost every library director I talked
35:44to is to anticipate a 4-week closure. Um
35:48and so that is what we're anticipating
35:50here from the moment we close our doors
35:52here in Tempace to the day that we do
35:54our grand opening uh [clears throat] at
35:56the other space to be about four weeks.
35:59So um I I can't give you exact dates um
36:03yet. I don't think we're at that point
36:05um with everything kind of a little bit
36:07fluid. I do anticipate we'll be closer
36:09to knowing what those dates are.
36:12>> Um you know, I would say within the next
36:14few weeks, maybe even next month or so,
36:17knowing that it's construction. So, as
36:20much as we we think we know, um we're
36:23we're going to do our best and most
36:24informed uh decision with with the team.
36:28Okay.
36:28>> Thank you.
36:34Go ahead, Bill.
36:36>> Yeah, that's a very smart answer and all
36:38of us on the team and the trustees
36:41should follow the lead of Kate. There's
36:44too many last minute things. So if we
36:46start saying that it's going to open on
36:49a particular date, uh stay away from it
36:52until like Kate says and Steve has said,
36:56uh we follow through with this final
36:59push from the contractor. Uh secondly,
37:03uh at the last couple of meetings,
37:05there's been comments that the
37:07contractor does not expect to charge any
37:12overtime. And as far as I'm concerned, I
37:16will push Steve and the whole project to
37:20not allow any overtime payment. They've
37:24been too late, too slow through the
37:26whole process up until the last month or
37:28so. I just wanted the committee to be
37:32aware of that so that we're all speaking
37:34with the same language.
37:36>> Thank you.
37:38>> Thank you.
37:39>> Thank you, Bill.
37:43>> Yeah. I uh wondered if it'd be possible
37:45to have another time when the library
37:48building committee could do an on-site
37:50walk through and see the
37:53>> finished near nearer finished state and
37:57um
37:58>> provide better input frankly
38:00>> to the to the voting and so forth.
38:04>> You want to have the meeting in person
38:05two weeks from now?
38:08>> Unfortunately, that's the one.
38:09>> Oh, that's right. [laughter] You
38:10couldn't get there.
38:17and let us know what might work. You
38:19know, we're we can accommodate, you
38:21know, basically anything that you guys
38:22may want to assemble.
38:24>> Okay.
38:26Bill, did you have another question?
38:28Comment.
38:28>> Uh, no, that's a good idea to get
38:31through, but there's a lot of activities
38:33here and the last time people uh said
38:36they would be there and they didn't show
38:39up. So, I would recommend highly that
38:42when you say you're going to be there,
38:43make sure you're there because it's
38:45going to take time away from the
38:48activities that need to be need to be
38:50done andor cleaning areas so that you
38:53can walk through. So, let's make sure
38:55that we follow through with that.
39:00>> Go ahead, Lee.
39:02>> Oh, thank you. So, I'm sorry I was late
39:04getting here. Um, my apologies on the
39:07painting. How many of you have actually
39:09seen that mural that Julia Lincoln
39:12painted in the 50s?
39:14Nobody. I think it's in storage up on
39:17the top floor, which isn't a good place
39:19for it. But I I think to go back to kind
39:21of the first issues about it, we don't
39:24have anyone who's accepted
39:26responsibility for the evaluating the
39:29painting, for storing it, for deciding
39:30where it's going to go. It obviously
39:32isn't the responsibility of the library
39:34to do that. It just sort of ended up
39:36there. Um, we need to figure out, I
39:39think, who wants to take responsibility.
39:41I think it probably should be the board
39:42of Slackman or the town manager,
39:45assistant manager, somebody who can make
39:47decisions about it because we should
39:50evaluate it for value. It should be
39:51insured. I don't know if it's insured
39:53just overall town insurance. Um, and
39:57who's going to take responsibility for
39:59it and where it will where its final
40:01best resting place is. So, I wondered if
40:03it's something that you would like me to
40:05go to the board of selectmen with and
40:07talk to them about it and see if they're
40:09willing to take responsibility. But in
40:11the meantime, I would like an
40:12opportunity to to look at it and see if
40:16it's being damaged right now and if
40:18there's something we have to do right
40:19away. I have a personal stake in it
40:21because I'm in the picture. My parents
40:23are in the picture and um a friend of
40:26ours painted that, Julia Lincoln. So I
40:28have it sort of a emotional attachment
40:30but it's a lovely lovely painting that
40:32shows the history of Westboro painted in
40:34the 50s. Um so we want to make sure it
40:37ends up in a good safe visible place as
40:39a wonderful treasure for the town. So
40:43does anyone have any ideas other than
40:45what I'm suggesting perhaps for me to go
40:48to the selectman and talk to them about
40:50it and go and view it first so I can see
40:51how it looks right now and take a photo
40:53of it. I don't even think we have a
40:55photo. Um the uh
40:58>> I know that the painting you're talking
41:01about is it is not in the library. Um it
41:04has not been in the library. Um last
41:06that I knew of it, it was at the Art and
41:09Frame Emporium and Ed U. Turner was
41:13storing it there. Um Right.
41:15>> And I'm going to defer to to Sean since
41:18his hand is up because I think he wants
41:20to weigh in on this.
41:22>> I spoke to Ed and he said it was at the
41:24library. So now I'm not sure where it
41:26is.
41:27>> Okay,
41:28>> well I'll tell you what, Lee. Um yeah,
41:30I'll talk to the town manager and the
41:32two of us will work to I guess see if we
41:36can locate it to begin with
41:39um and then determine um some course of
41:42action for it.
41:44>> That'd be wonderful.
41:45>> Yeah. I I don't know if you want sort of
41:47email me maybe a few specifics about it.
41:50I don't know if it has a title or that'd
41:52be great and and I will take it from
41:54there.
41:55>> And um so just for you Sean, the mural
42:00came out of the Forbes building. It used
42:02to be in the um second floor hallway of
42:04the Forbes building. So it's it doesn't
42:07really have a connection to the library.
42:09Um and
42:12>> um
42:14I don't I think it's something that we
42:16had been approached at one time about
42:18displaying in the library. At the time
42:20the trustees said said no. But if it
42:24were going to be displayed in the
42:26library that would be a library trustee
42:27decision, not
42:30necessarily the purview of this um
42:33committee.
42:34>> Right. So yeah. So, it's possible it's
42:37been stored since work was done on the
42:40Forbes building or something. So, well,
42:42well, let's see if we can um I guess
42:45first track it down and Lee I'll I'll
42:48follow up with you and then we'll
42:50>> right
42:50>> see what we can
42:51>> Thank you.
42:52>> Thank you, Bill.
42:55>> Yeah, thank you, Sean, for following up
42:56on this, but there's no way that any of
42:58this can be addressed during the
43:00construction period. It'll be months
43:02after the construction. Thank you. Mhm.
43:05>> I sort of consider this a um an issue
43:09outside of this committee.
43:10>> Yes.
43:12>> At least, you know, for the foreseeable
43:14future.
43:15>> Mhm.
43:16>> Okay.
43:18>> Are there any other building related
43:20issues
43:22that we would like to discuss?
43:32Um, you know, this has been a very good
43:35working committee. I'm uh I've talked to
43:38Steve a little bit. I'm a little
43:39concerned that the trustees have a a
43:42real accurate understanding of where the
43:45project is at this time. And I've talked
43:49to Steve and uh I believe Mary feels
43:52somewhat the same way is that Steve and
43:55whoever he recommends come with him, go
43:58to the trustees the next trustees
44:00meeting or call a meeting so that they
44:02fully understand where we are and where
44:05the schedule is etc. So please take that
44:08as advice. Thank you.
44:11>> Thanks Walter. Uh yeah, I was just
44:14wondering um when we last met there was
44:17some discussion about the laap
44:20um and since then I've spent a couple
44:23weekends pulling it out of my own yard.
44:25But I was just wondering whether there
44:27was any further input from the um uh
44:31landscape people on a substitution.
44:36We did discuss that today at our our
44:38project meeting and and I know there was
44:39a clarification needed and the
44:41contractor is getting the um spo is it
44:45Spalain on on this? Yes, Spolain is the
44:47landscape contractor uh and they had
44:50questions on it. They did come to the
44:51site. So, we're just uh we don't have
44:53anything specific to report on it, but
44:55we're on it and and we know and
44:56understand exactly what is to be done.
44:58Uh the designer is going to issue that
45:00uh the documents that that clarify that
45:02as well. So uh certainly not not
45:05forgotten. We just don't have specific
45:07progress to what we'll what what I
45:09expect is we'll bring back a
45:11recommendation to provide in its place
45:14and bring that back to you guys for
45:16honestly I don't remember how to what we
45:18said as far as how to approve whatever
45:20gets recommended but unless someone
45:22tells us differently we can bring it
45:23back to you guys.
45:25>> Yeah, I'm pretty sure we said that your
45:28weekly
45:29>> uh small crew could just approve it at
45:32that point.
45:33um which what we voted but and it has
45:35only been two weeks since our last
45:36meeting but I just thought I would ask
45:38because
45:39>> thanks
45:41>> Mary.
45:42>> Yeah, thanks. I just wanted to um add to
45:45what Bill said. Um I agree. I do get
45:48concerned about um the trustes overall
45:51view of understanding of the timeline of
45:53the project. We do have a online Zoom
45:57meeting. Tomorrow night is our next
45:58trustee meeting um if anyone's able to
46:00come to that Steve or we can throw
46:03another meeting on so that you can give
46:05an update to the trustees about the
46:07current status of the project.
46:10>> Whatever you guys need, we'll happy to
46:12happy to do work with you guys and make
46:14presentations
46:16or would be helpful.
46:17>> Okay, great. Thank you.
46:22>> Any other building related issues?
46:26Move to adjurnn.
46:29>> Second.
46:30>> Oh, was that a motion to adjurnn, Bill?
46:33>> Yes.
46:34>> Oh, thank you.
46:35>> Second.
46:38>> All right. Uh Lee,
46:41>> yes. Bill,
46:44>> yes.
46:45>> Walter,
46:46>> Leslie, yes.
46:48>> Mary
46:49>> Johnson, yes.
46:50>> Al
46:51>> Gordon, yes.
46:53>> Bob,
46:54>> Petraella, yes. Ed
47:04>> Baldwin. Yes. [laughter]
47:06>> Kate
47:09>> Karachio. Yes.
47:10>> Don
47:12>> Eel. Yes.
47:13>> Pete.
47:14>> Donbeck. Yes.
47:16>> Lynn.
47:19Yes.
47:24And I am a yes. So we are adjourned.
47:27Thank you everybody.
47:28>> Thank you. Bye
47:29>> bye.
47:30>> Thank you.