Library Project Budget and Contractor Payments

At a glance

  • What: tracking the library renovation budget (reported as about $13.9 million including roughly $1 million of contingency; construction bid $8.3 million), change directives and monthly payments to Seaver Construction and other vendors.
  • Where it stands (Oct 20): in a worst case with all open change directives counted, about $46,000 remains in the original construction contingency; a little over $1 million of the appropriation is uncommitted. About 70% of changes are unforeseen conditions (about $351,000, roughly 3% of the bid).
  • Next: an owner change order is expected at the November 3 meeting; retainage and warranty items will be billed after move-in.

Votes

  • Oct 20: monthly vendor invoice packet approved (10 yes). Seaver Construction September requisition of $717,705 approved (10 yes); with $171,057.85 approved earlier the total is $888,762.85.

Open questions

  • Leftover funds: borrowing happens only as needed, so unspent authorization would likely be de-authorized at a future town meeting. Whether the committee still exists in spring, and who may authorize added work such as extra trees, is unclear.
  • Close-out: a one-year workmanship warranty; retainage invoiced in the first months; accounts may stay open for months.

Sources

Discussion time

About 20 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-20 - Library Building Committee 20

Log