Wastewater Treatment Plant Projects

At a glance

  • What: the shared Westborough-Shrewsbury treatment plant's large capital project and rotor replacement problems.
  • Status (Aug 20): capital project about 12 percent complete, running to mid-2028; two rotors failed and are under a three-year warranty, with a vibration study planned.