  • Technology requests: A staff presenter walked through the IT list for the 2027 budget: server auditing and log collection, replacement of the on-premise data center systems and disaster recovery (end of life in 2027), a replacement access control server (in place since 2015) and access control and security cameras at three more fire stations, HR employee relations and recognition software, an AI program with governance and funding for AI-assisted meeting transcription, Starlink failover for police and fire sites, emergency blue light call boxes for recreation sites, and a distributed antenna system for the Bees Landing recreation center. See 2027 Technology Budget Requests.
  • IT restructuring: The IT request includes three director-level positions (IT operations, chief information security officer, innovation), a senior GIS systems administrator and a business analyst. New positions total about $673,000, with about $630,000 in ongoing operating costs and about $220,000 one-time, for a total request of roughly $2.4 to $2.5 million.
  • Greenway cameras: A councilmember asked whether cameras on utility poles along the West Ashley Greenway and bikeway were in the request. Staff said no: cameras in public parks are handled by the police department in its own budget, while IT covers city facilities. The councilmember said they would follow up with the police chief.
  • Facilities, parks and urban forestry: The section requested about 24 new positions and five salary upgrades, ranked by priority, plus funding for contract maintenance, HVAC and mechanical work, building system and life-safety repairs (with the fire marshal), roofs and building envelopes, parking lot paving, vehicles and equipment, and priority tree removals. Specific items named include sand filters for the James Island recreation pool (the city will be down a pool for about two years), ball safety netting at Bay View, and artificial turf at Marion Square. See 2027 Facilities Parks and Urban Forestry Budget Requests.
  • Context from staff: The section maintains about 120 parks, nearly 2,000 acres, and 211 buildings, and has delivered 165 projects worth about $1 billion in 12 years. The mayor supported growing the urban forestry crew, including for replanting after power line clearing. The neighborhood undergrounding coordinator position is proposed to be split with general fund support, since it is not a full-time job.
  • Funding sources: Staff said parks costs are mostly operating funds, with hospitality and other tourism dollars typically used for tourist-facing spaces such as White Point Gardens and Marion Square. Unforeseen repairs, such as a sewer line at a nonprofit tenant's city-owned building, come from the maintenance budget or the deferred maintenance reserve.
  • Outlook: The mayor said the city will likely not be able to accommodate everything requested. No votes were taken; the meeting adjourned. See also 2027 General Fund Budget Outlook.

Agenda

Agenda PDF posted; see Sources. Items not yet read.

Sources

Video

Watch the video

Transcript

*These are auto-generated captions; names and numbers may be misheard.

Transcript

00:00All right. Any other questions? I'm not

00:02seeing any.

00:06Um if there are no other questions on

00:09executive, we can move to some capital

00:12projects next.

00:13>> It's actually um it mayor.

00:15>> It all right.

00:19I think you're presenting on this.

00:24>> Yes, sir. Mr. Mayor, apologize. And I am

00:27not going to be nearly as uh I'm going

00:30to be pale in comparison to the last two

00:32presentations especially when it comes

00:34to the graphical representation for the

00:37budget proposal. I apologize. U

00:44>> let me do that here.

00:46>> Can you make that smaller? that this is

00:49a not exactly a uh graphically pleasing

00:54or appealing presentation. So,

00:57apologize. Let me zoom in here for you.

01:01Where am

01:04my presentation?

01:09Where is my zoom?

01:17me using the full extent of my bif

01:19focals on this.

01:20>> Yeah. No, I I apologize that is I was

01:23very illprepared. Here we go. Let's see

01:26sharing.

01:27>> I want to zoom in on this.

01:32>> Hi, I have some of the same thing. Would

01:34you like me to share? That way you don't

01:36have to worry about it.

01:38I can do uh if I'll do this real quick

01:41if let me know when when it becomes

01:43essentially uh viewable for the the

01:47details on the screen.

01:51All right, zoom in here.

01:59That better for presentate for

02:01visibility.

02:02>> Yep.

02:03>> All right. So, I'm just going to uh

02:06briefly there's quite a few uh new items

02:09that are on our uh request list, and

02:12I'll I'll go over uh each of them

02:14individually, but I'll I'll kind of uh

02:17go more in depth on the ones that are

02:19are of of higher priority or larger

02:22scale. Uh first is in including uh

02:25server auditing and log event collector.

02:27So this will allow us to gather more

02:30information for records retention both

02:32compliance requirements uh for CEIS as

02:36well as just overall cyber security uh

02:39improvements requasures

02:42who logs into systems computer systems

02:44and logs that information. Uh the next

02:47three actually are all a single project

02:52that are indivi three individual systems

02:54that make up the larger data center uh

02:57systems within our onremise data center.

02:59And these house all of our server

03:02systems. There's the data protection

03:04appliance server infrastructure and the

03:07data center storage. These are three

03:10components we have that are currently in

03:12our existing data center go end of life

03:13in 2027. So these systems are replacing

03:17those aging systems. Uh the disaster

03:20recovery actually is the fourth uh

03:23component of that overall uplift that

03:26needs to be uh replaced due to age. The

03:31next is the access control system. This

03:34system handles the access control for

03:37many of the city facilities. That's the

03:39badge access like city hall. the system

03:43that we currently have in place. This

03:44upgrades the server. That server has

03:47been in place since the implementation

03:49in the Gillyard back in 2015 and is end

03:53of life and needing to be replaced.

03:57The next line is actually tied to the

04:00fire budget, I it budget and is

04:03expanding the access control system to

04:05fire stations. This will add three

04:09threeuh fire stations to that list.

04:11implementing access control for those

04:14fire stations. We're phasing that

04:16project out over multiple years and just

04:19tackling a few stations at a time. So,

04:21this will address uh the installation at

04:23three fire stations in the upcoming

04:25year. Uh the next item, fire station

04:29security cameras, add security cameras

04:32to fire stations. again those the three

04:36uh fire stations that we'll be adding

04:39access control to. We also add security

04:42cameras on the exterior of the building.

04:45The fire department helps us uh identify

04:48those areas they most want to record

04:52primarily ingress egress of these

04:54stations so that uh to improve the

04:56security of those fire stations.

04:59The next two are for the HRE uh HR dep

05:05department employee relations

05:06development platform and recognition

05:09software. The the titles kind of explain

05:12exactly which each one of those systems

05:14do their uh HR's requested these to help

05:18track the employee relations and then

05:21recognition for their expansion of

05:25programs for employee retention uh and

05:27relations. Uh the next item is AI

05:32program. The city is looking at the IT

05:35department is looking at expanding and

05:37adopting a full-fledged AI program. This

05:41includes the uh deployment the

05:45development of governance for AI uh to

05:49employ with deploy AI for employees

05:53augmentation and improved enhanced

05:55productivity. But we want to lay the

05:58groundwork for ensuring that the AI

06:00usage is safe both for citizen and and

06:04employee data that we're protecting all

06:07of that information as we leverage these

06:09new AI systems. This also includes

06:13funding for use of uh contracting with

06:17vendors as we develop

06:20custom AI programs. One of the things

06:22we're looking to tackle this year with

06:24some funding is uh currently with the

06:28clerk of council's office leveraging AI

06:32tools to enhance the and improve the use

06:36of transcriptions for these meetings.

06:39Uh, and so really take the onus off of

06:43an employee having to sit down, listen

06:45to a meeting, and physically transcribe,

06:48type out exactly what's said, leveraging

06:50AI tools to automatically do that. that

06:53allows the employee to then verify that

06:55information, but should significantly

06:59uh shrink the time that it takes for

07:02these meetings to get transcribed,

07:03allowing them to do that much more

07:06quickly and then do uh freeing up time

07:08to do other things, expand and just make

07:10them more productive overall.

07:14the Starlink uh failover project. This

07:17is a project for to uh improve our

07:21resiliency and emergency management

07:23where we're looking at identifying

07:25police and fire locations where we

07:27really want to ensure communications in

07:30the event of a natural disaster.

07:32uh this this is leveraging the

07:34satellitebased Starlink uh

07:36communications so that if we have a

07:38large-scale natural disaster whether it

07:41be man-made or natural u to ensure

07:45communications and resiliency for

07:47communications at these locations. The

07:50emergency 911 phone blue light towers is

07:53a project to deploy uh which you

07:57probably familiar with. You've see them

07:59around college campuses. There's some on

08:01the the Ravenel Bridge, the those 911

08:04call boxes with the blue lights. We're

08:07looking at uh deploying several of these

08:09both at pools uh or any recreation

08:13sites. They're currently in design with

08:15some of the projects that are currently

08:17going into uh in development. John's

08:20Island as well as u on Playground Road,

08:24uh the WL Stevens Pool. Uh those are

08:26built into those projects. This project

08:29allows us to retrofit recreation sites

08:31and city facilities, city parks uh with

08:35these systems to uh improve uh safety

08:38and and allow for emergency

08:41communications u by citizens in these

08:44public spaces.

08:46The cellular dash system, this is

08:49specifically for the bees landing

08:51recreation center. This is an

08:52augmentation for the uh DA stands for

08:55distributed antenna system. uh for the

08:59cellular system when you go into that

09:01building the cellular reception in that

09:03area is very poor and then once you go

09:07into the building it's practically

09:09non-existent. This dash system uh puts

09:12an antenna on the roof distributes that

09:14within this uh facility so that when you

09:17go into the building you don't lose uh

09:19cell service.

09:22the IT department restructure. This

09:25project is actually uh calling for three

09:28positions. The restructuring of the

09:31department, what we're looking to do is

09:33as the IT department focuses on

09:37innovation, we want to expand the

09:39operation and the offerings of

09:41innovation with the city as well as

09:42improve the cyber security program uh

09:47that's handled by the IT department.

09:50This is calls for three positions. A

09:52director of IT operations, a chief

09:55information security officer as well as

09:57a director of innovation. These three uh

10:01positions would then be over those three

10:03divisions uh within the IT department

10:06allowing them to focus on the

10:07operations. The IT uh operate director

10:11of operations would focus on the

10:13day-to-day functions of the IT services.

10:16The director of innovation would work

10:18with GIS and our enterprise systems

10:20group to focus on the enterprise systems

10:24as well as exploring what new systems

10:27can be leveraged, how we can leverage it

10:30to improve the other departments to

10:33serve the other departments and their

10:34needs to serve the citizens. is looking

10:37at it uh amplifying as a force

10:40multiplier as a value ad for those

10:42departments leveraging new systems that

10:44would just make all the departments more

10:46efficient. That's something that uh the

10:49city really has an opportunity to

10:51improve in how we the IT department

10:54assist the other departments in

10:55facilitating their uh their core

10:59functions and the functions that they

11:01need to uh serve the citizens.

11:04The next is another position for a

11:07senior GIS systems uh administrator.

11:11This position is primarily focused will

11:14be focused on maintaining the physical

11:17GIS systems. Right now the GIS uh

11:20department Roberts uh is currently doing

11:23most of these functions that this this

11:26position is looking to cover. he he's

11:29having to be the administer day-to-day

11:32for a lot of these systems and this will

11:34allow him free up time for him to expand

11:37the systems uh and really focus more

11:40again on that innovation focused uh and

11:44data analytics positions that he already

11:47does right now but it will free him up

11:48to do a lot more of those functions. The

11:52business analyst uh is under the uh

11:55enterprise systems group uh that's also

11:59again focused on uh and then another

12:02innovation uh forward position

12:05leveraging

12:07how we currently utilize our enterprise

12:10systems. How can that be improved and

12:12optimized and get a lot more value out

12:15of those systems that we currently have?

12:20That uh that is it for

12:24the new projects. Just as this is a

12:27summary what we're looking at new

12:28position requests total approximately

12:30673,000.

12:33uh ongoing operational

12:35uh expenses is approximately 630,000

12:39with 220,000 as a one-time total budget

12:43request uh for the uh fiscal year uh 2.4

12:47million approximately 2.5 million

12:52and I know that was a lot of information

12:54all at once uh drinking from a fire

12:57hose. Are there any questions about any

12:59of those projects? Councilman Wearing,

13:01looks like you have a question.

13:03>> Yeah, [clears throat] I do. Not so much

13:04the project. We go back to the emergency

13:06911. I asked this when we had, you know,

13:10Chief Walker and his team uh present and

13:14I think some of this would have spilled

13:15over in your area. Uh

13:17>> yes, sir.

13:18>> Mr. Torres, uh we have these linear

13:20parks that we have enhanced and

13:22encouraging people to use the the West

13:25Ashley bikeway and the West Ashley

13:27Greenway that runs a good bit Actually,

13:31soon we'll have the u the bridge, the

13:33bike bridge over to Ashley. Um

13:37going back to Chief Mullen, uh there was

13:39some talk about putting u uh cameras on

13:44on high, so to speak, I guess, on maybe

13:46some of Dominion's uh power poles out

13:49there that would relay to camera at the

13:54police station so those bikeways and

13:56greenways could be monitored. Uh has is

14:00has is that incorporated in any of your

14:02um

14:04request?

14:04>> No, that no sir, that's not in included

14:07in any of these projects.

14:09Generally the the the police department,

14:11they they do currently have security

14:14cameras uh throughout the city and al in

14:16these projects and they handle that

14:18exclusively within their budget. They

14:21handle the the placement working with

14:23the contractors. So those types of

14:26security cameras uh are generally

14:28handled directly by the uh by the police

14:32department especially when they're in

14:33these public spaces in the parks.

14:35>> The cameras that the IT department

14:37generally uh handles are on city

14:41facilities. Uh we work with capital

14:44projects either when the the facility is

14:47being developed and built u or when

14:50there's a retrofit. And we work with the

14:53primarily with the fire department on

14:55their facilities, but those more

14:57public-f facing spaces, the police

14:59department handles generally directly.

15:02>> Well, in that case, mayor, I need to

15:04circle back with Chief Walker there

15:05because, you know, this again, we're

15:07doing things to enhance those spaces to

15:10to attract more people to use them. Uh,

15:13but you know, we need to have eyes on

15:15there. I mean some years ago uh people

15:18used um the greenway as access to break

15:22in the back of people's homes. Okay.

15:24>> So um

15:26>> um I mean we picked up security for a

15:30while over there but obviously

15:31technology can help with that a whole

15:33lot better. So um uh I was thinking it's

15:36crossed over into your area miss Mr.

15:38Torres but um

15:41>> no sir then there there is that gray

15:43area. Yeah, I do understand your answer.

15:46So maybe I need to go back and and

15:48circle back with Chief Walker because

15:50that's something that uh we've been

15:53talking about uh for a number of years,

15:55as I say, since Chief Mullen was here.

15:58So um uh and that's before we started

16:02repaving and resurfacing and putting in

16:05new pedestrian bridges and stuff for

16:07people to enjoy. um instead of waiting

16:12for something to happen, I think it's

16:13better to be proactive.

16:15So anyway, I'll circle back with with

16:18the chief on that.

16:20>> Good point. Yeah.

16:23>> Any other questions for it and I

16:31Okay, who we got next?

16:38By the way, Mr. stories. I think your

16:39graph I thought your graphics were

16:40terrific.

16:42>> Yeah, [laughter]

16:45>> I was very illprepared especially

16:47especially following the [laughter]

16:50>> um Mayor Parks says next.

16:53>> All right. Uh who's running on this one?

16:57We got

17:00Clark.

17:02>> Yes, sir. We got we've got Michael

17:04Kennedy, Clark, and myself. and I'll

17:06I'll quarterback us through the uh the

17:08PowerPoint.

17:10>> All right, sounds good. Edmond

17:13>> here.

17:14>> Floor is yours

17:16and screen is yours.

17:18>> Let me know when you all can see that.

17:26>> We got it.

17:29>> All right. Well, thank you everyone for

17:31allowing me this opportunity uh to to

17:34present these budget requests for 2027

17:36for facilities and capital project

17:38section. Um I fully realize that we have

17:43a lot of requests on the docket. Um and

17:46I'll just jump right in here and try to

17:48get through this as quickly as possible.

17:56Um is our mission statement right here.

17:59And as you're reading through that, I

18:00just want to add that um we're here to

18:02provide turn-key services to the city

18:05public city employees and the public. We

18:09design everything from small plantings

18:11in public spaces to new vertical

18:13infrastructure. Currently, our section

18:16maintains the majority of city's assets

18:17to provide infrastructure for city

18:19employees to conduct business and

18:20enhance public spaces to be enjoyed by

18:22the public. We're able to do this.

18:27We're able to do this.

18:30We are able to do this by the

18:32>> by the funding that that is available to

18:34us. We fully understand the challenges

18:37of carving out funding for services when

18:39there are so many needs throughout the

18:40city. And we understand that funding is

18:42limited.

18:44Uh just a quick overview on the

18:46presentation. It's really broken up

18:47between staffing requests and funding

18:49requests. Um and our structure here's a

18:53very short org chart here. Um we

18:57basically have three major divisions

18:59here. Capital projects, facilities, we

19:02also call them building ops and then

19:04parks ops. So really the vertical

19:07construction and then all the park

19:08spaces and horizontal green spaces and

19:11then capital projects. Um interestingly

19:14enough this time of year capital

19:16projects doesn't generally have a lot of

19:17requests for operational costs. It's all

19:20in their project budgets for the most

19:21part. This is primarily going to be

19:23building ops and and parks ops.

19:27Um, it's about 150 employees. It kind of

19:29varies a little bit dayto day. Um, and

19:33let me jump right in here. So, our

19:35staffing requests are big. I realize

19:37that we're making 30 requests here. You

19:39know, in looking at our our staff

19:42currently, we have a lot of employees

19:44that are starting to age out, especially

19:46more in facilities, a little bit more in

19:48grounds. Um, we're looking, we're

19:51constantly expanding our park spaces,

19:54our building infrastructure, and the

19:57only way that we can compensate with

19:58that is by adding staff. Capital

20:01Projects has been very good over the

20:02last um 12 years to to add a lot of

20:05infrastructure. So, that kind of breaks

20:07down to 24 new positions being

20:10requested, five salary upgrades to

20:12existing staff. Uh, and you can kind of

20:15see the mix and the breakdown right

20:16there. And again, it's going to be

20:18really heavy in facilities, parks, ops,

20:20and urban forestry.

20:25Um, on the lighter side of things, um,

20:28this is these are the smaller divisions

20:30in in parks. Basically, a couple of

20:33upgrades to some existing salaries. Um,

20:37you know, the employees are working

20:38hard. Uh, they're stepping up, taking on

20:41more responsibility, and we thought it'd

20:43be appropriate to compensate them for

20:44that. And then the last item there is

20:47the NSSF

20:49funds uh coordinator for parks. Um we've

20:53had this position for probably a little

20:55less than three years now. And this this

20:59employee is dedicated to working with

21:01neighborhoods and Dominion to help

21:03underground projects. And upon assessing

21:06that in the last three years, we've

21:08noticed that it's not a full-time job.

21:11And we would like to kind of split the

21:13funding for this position um from

21:16another funding source. I believe it

21:17would be general funds uh to help out

21:19with the workload here in capital

21:21projects. Um that individual is very

21:24excited to have that opportunity and

21:26fits right in our culture right here.

21:30Um jumping into facility management and

21:33services. I kind of broke this apart in

21:35management and services is kind of two

21:37different things. U facility management

21:39is really they're doing a lot of work

21:42orders. Uh and this is the the the

21:45breakdown of the request and everything

21:47that's indicated as a P over there is a

21:50priorities. So what I would encourage

21:52everyone to do when they're looking down

21:53and trying to sharpen the pencil and

21:55find funding is really look to those

21:58priority numbers. The higher the

21:59priority number is is the more urgent

22:02need that we have for that position. Um,

22:06this is the staff that performs most of

22:07the work orders and general maintenance

22:09in and on our buildings and foundation

22:11inventory. Over the last year, the

22:13senior staff have identified several

22:15positions severely needed to properly

22:17distribute the workload. Many of the

22:19existing staff are wearing multiple hats

22:21and as I said earlier, they're starting

22:23to age out, so we're constantly putting

22:25more responsibilities on the staff that

22:28is, you know, getting closer and closer

22:29to the end of their um career here at

22:31the city. So, we need to add more

22:33positions and kind of spread that out a

22:35little bit more. Um, the most urgent

22:38priorities here really I would identify

22:40as one, two, and eight.

22:46Jumping over to parks ops. Uh, this is

22:49the staff that touches all of our

22:50managed green spaces throughout the

22:52city. And I hope everyone has

22:53opportunities to go out into our park

22:55system because it is it's absolutely

22:57wonderful to experience that throughout

22:59the day and on the weekends. Over the

23:02last year, senior staff have identified

23:04several positions to really need to

23:06properly distribute workload. Many of

23:08the existing staff are taking on new

23:10parks and grounds to maintain and

23:11beautify. The most urgent ones here

23:14again are the top three that I'm listing

23:16here, two, six, and seven.

23:23urban forestry. So, this is an

23:25interesting group. It's a very tight

23:26group. Um, they have certainly a tall

23:29order with the tens of thousands of

23:31trees that the city has and we have a

23:33fairly small urban forestry group. Um,

23:36there's also the the initiative to

23:38relief the city and that's going to need

23:42some additional staff to support that

23:43effort. So, the most urgent needs on

23:46this one would be five and nine. uh this

23:49would really almost double the size of

23:52urban forestry for what they are right

23:53now.

23:55>> This is just if I may um something that

23:59I've been uh a strong advocate for uh if

24:02for no other reason. I mean, we

24:05mentioned the urban canopy. Um, but

24:08another effort that we all hear plenty

24:11about is

24:14um the trimming of trees around power

24:18lines. And this crew will help um you

24:23know in the bearing of power line

24:25efforts or initiative.

24:28Not that they would be doing the actual

24:29bearing, but just having the uh

24:33uh crews available to plant trees back

24:36when we do drop power lines. So, um it's

24:40a hell of a crew they have over there

24:42and I think it makes a lot of sense to

24:45uh expand it. So, I wanted to just throw

24:47that in there, that plug in there for

24:49you, Edmond. [snorts]

24:50>> Thank you, Mayor. This this is a very

24:52hardworking group, too.

24:55>> Agreed.

24:56>> Okay. This is the kind of the second

24:58half of it. Uh, a little bit more than

24:59halfway through this. So, now there's

25:01the funding requests. We have that

25:02staffing that we need to do be doing

25:04work orders on a constant basis. And

25:06then there's the funding requests, which

25:08are, you know, contract maintenance. The

25:10contract managers are hiring stuff out

25:12and they're managing that. It's

25:14equipment. It's a lot of other things

25:15that help support the staffing. So, it's

25:17kind of a two-pronged approach here. And

25:19again, I realize that that's a very

25:21large number there.

25:24Um, this is broken down a little

25:26differently now because we're getting

25:27into the depths of facilities. Here on

25:29the left hand side is HVAC mechanical

25:31and finishes. Um, and you can kind of

25:34see the spread of type of work here. Um,

25:37same thing, you know, it's it's like

25:38owning a home. Your HVAC needs to be

25:40replaced. We have dozens of facilities

25:43throughout the city that we're dealing

25:45with this on a constant basis here. So,

25:47we're trying to prioritize the the

25:49projects that need these things the

25:51most. In some cases, we have the ability

25:53to kind of stretch the service life of

25:55some of these things. And in some cases,

25:57we're getting closer and closer to the

25:58end of that service life, which is

26:00increasing that priority right there.

26:02Um, in this particular case here, we're

26:05looking at um

26:09really five and 11 are the two biggest

26:13ones. Um, and James Island wreck pool

26:17and sand filters. That's a little bit

26:19more critical just because we're down a

26:20pool in our inventory right now. We will

26:22be down for the next two years. So, it's

26:24absolutely critical that we fund that

26:26one to make sure that that pool is is

26:28operating as it needs to because

26:30there'll probably be a little bit more

26:31strain on it for the next two years

26:33before we build the two new facilities.

26:37Um on the right hand side there, this is

26:39building system repairs. So, this is

26:41more of kind of the the life safety

26:43realm here. Um, we've identified

26:46multiple projects that are very high on

26:48the priority list and working with the

26:50fire marshall on this. Um, and we're

26:52still kind of flushing some of this

26:54stuff out. It is it is feasible

26:56sometimes to move these back because the

26:58service life can be extended a little

27:01bit more with minor repairs and we're

27:03certainly digging deep into that to see

27:05if we can get a little bit more service

27:06life out of this equipment uh to help

27:09reduce that that budget request. But we

27:12would identify as three, four, six, and

27:15seven as the most needy on that list on

27:18the right hand side there.

27:24We always love to talk about roofs and

27:26building envelopes because that's what

27:27keeps the weather out, especially when

27:28we have a 4-in rainstorm like we did

27:30earlier in the week. Um, roofs and

27:33building envelope is absolutely

27:34critical. And if if you don't keep those

27:37service life up on those things with

27:39repairs and eventual replacement, you

27:42get water damage into a building and

27:44that starts to spend a lot of money with

27:46remediation, air monitoring and stuff

27:49like that. And we always like to

27:51identify the roof and building envelope

27:53replacements early on so we can get

27:55ahead of that. We have been doing a

27:57really good job over the last several

27:59years with that and I hope we can

28:00continue to do that. The most urgent

28:03items here would be 9,14 and 16.

28:12Um, this is kind of lower on the list

28:14here, but some of these items have been

28:16on our list for a number of years. I

28:18think you all have probably seen this

28:20previously when when Jason Kronberg has

28:22presented this items like the Bay View

28:25ball safety netting. We we've gotten a

28:27lot of uh constituents that have asked

28:29about that recently. um parking lot re

28:32rehabilitations. We have gravel lots in

28:34most cases where we have to constantly

28:36groom them. We try to pave them when we

28:38can. So, we've built a number of these

28:41in here and these are really kind of the

28:42highlights and and the highest ranked

28:44ones or park structures sites and

28:46equipment.

28:50Parks ops. So, another large group, the

28:55largest in in parks department,

28:57hardworking individuals, constantly

28:59going out there and doing everything

29:01that they can. They need some support

29:03too from time to time. Uh, and it's not

29:05always staff that they need. We

29:07identified a number of things that would

29:09kind of help their um their efficiency,

29:11help them store materials, um help with

29:14areas that are heavy wear and tear like

29:16the Maran Square Farmers Market,

29:18artificial turf. There's so much time

29:20and money that goes into keeping that

29:22area green for the public and it gets so

29:24much use. So, you know, converting that

29:26over to official turf, that would be a

29:29big win and would help on the general

29:31operating cost reductions of trying to

29:33keep that that lawn and green and and

29:35looking wonderful. Um, of course, we

29:37always need vehicles and equipment to

29:40support that staff. Those are a little

29:42bit more higher ranked because those

29:44individuals, they're in their vehicles

29:45and they're using it this equipment

29:47every single day.

29:52Um, I'm circling back to urban forestry

29:54and mayor, this kind of picks up a

29:56little bit of what you were were

29:57mentioning. We have a lot of priority

30:00one removals identified and and that

30:02really should be very high on the

30:04priority list. Those are trees that you

30:07know are getting probably end of the

30:09their lifespan or that they have uh some

30:12disease or rot in it and they're being

30:14identified uh per the tree survey as

30:17being removed earlier than later.

30:24And this would also be some of this

30:25would be uh contract labor. Maybe some

30:29can be done with in-house labor, but

30:30again we're overt taxing the existing

30:32staff that we have on. So this may be

30:34contracted labor out as well.

30:39So this is just kind of a summary page.

30:42I know they're big numbers. Just want to

30:44reiterate, you know, 120 parks in our

30:46system, almost 2,000 acres of of parks

30:50and open space.

30:52Several hundred buildings and building

30:54space that we're constantly in doing

30:56work orders every day to keep these

30:57businesses open. uh keep employees in

31:00there working and keep our green spaces

31:02green and enjoyable for the public.

31:07This next slide is really just kind of a

31:09breakdown of where that those funding

31:11requests are. There are a lot facilities

31:14management and facility services.

31:16Um parks and urban forestry and

31:19horiculture, they have a kind of a mix

31:21in there too. Um, but we are growing

31:23from a facility standpoint. And we're

31:25growing very quickly. And that kind of

31:28segus into this last slide of questions,

31:31but I wanted you to kind of focus in on

31:33that that little um additional text that

31:36I added in there. It's a really proud

31:39number to see that in 12 years,

31:42165 projects and a billion dollars worth

31:45of assets. And I personally take a lot

31:47of pride in that because I came to the

31:48city about 13 years ago and I've been

31:52involved with just about every one of

31:53those projects. Obviously, the team has

31:55done all this stuff, but it's it's

31:58really impressive what we've done here.

32:00And this is circling back on grounds and

32:03facilities. They need to maintain all

32:05this all these facilities and spaces

32:07that we've developed. And that's part of

32:09the reason why we have such a large

32:11budget request right now. Any

32:15questions?

32:16>> Something to be proud of, Edmond. I

32:17mean, know you and your team. I mean,

32:19that's uh that's impressive. Not to

32:22mention, I love the stats on the U

32:25120 parks. I didn't think I don't I

32:28didn't quite realize we almost have

32:302,000 acres and um 211 buildings. That's

32:36That's kind of mind-blowing. U

32:37Councilman Wearing, you have a question?

32:40>> Yeah. Yeah. Um listen uh excellently

32:44pres presented man I almost felt like I

32:46was it was almost professorial like a

32:49professor in class. So very well done.

32:52Um you're right 165 projects a billion

32:55dollars. That's some person. Um let me

32:59ask this is a question more of um um

33:02Miss Wharton. uh when we fund uh you

33:06know parks department does all of that

33:09come from a majority of it come from

33:11general funds or do we

33:14>> operationally

33:17>> council wearing probably mostly

33:19operationally yes for some of the

33:21facilities the repairs and uh deferred

33:24maintenance on the facilities we could

33:26use other funding sources depending on

33:28the facility type

33:29>> so we look at that to see what other

33:31funding sources we can use,

33:34>> right? One of the things I'm thinking

33:36about was uh do we ever think about for

33:39instance White Point Gardens or even

33:41Marian Square? Obviously tourist visit.

33:43>> Yeah, we we do we use hospitality

33:45typically for those or one of the other

33:47tourism dollars for any any upgrades

33:50that we do or maintenance on those areas

33:52or in those areas.

33:53>> All right. And when we have this back to

33:56Thank you, Miss W. Back to Mr. Deose.

33:59Um, we have a several situations I

34:03believe where with nonprofits who fill a

34:07huge void, um, we let them use a city

34:11building, I don't know, for a dollar a

34:13year or something like that, you know.

34:14Um um

34:17and I'm think there's a building next to

34:20Dart Hall Library that the city owns and

34:22we let

34:24it's kind of like darkness the light you

34:26know it's very tough situation where

34:28abused children you know and families

34:31get counsel uh they have a a sewage

34:35situation I don't know if it's ever come

34:37to your attention where they've had that

34:39line cleaned out a number of times I

34:41really believe it's a situation where

34:44sewer line coming into the building uh

34:46probably needs to be replaced. Should

34:49something like that pop up,

34:53is there a carveout in a budget request

34:55that you have for example in front of us

34:57or we have to scramble in a different

34:59direction?

35:01>> Unforeseen costs like that, if that

35:03became like an emergency repair, we

35:05would go into um really just the

35:08maintenance budget to pay for that if it

35:10if it's something that that budget can

35:12absorb. We always know there's going to

35:14be unforeseen in all of our projects and

35:17all of our facilities. So, we try to

35:19account for that. Um, if we know it's

35:22coming, we want to identify it as a new

35:25program and have a cost and try to limp

35:27along until, you know, we can get

35:28approval on that. So, it really kind of

35:31just depends on the situation.

35:33>> Um, Council Wearing, if I could add to

35:35that, we also have deferred maintenance

35:38that we reserve every year for those

35:40types of things as well. So,

35:42>> Okay. Good. Thanks a lot. Thanks again,

35:44Mr. Mos, for your presentation. Well

35:46done.

35:47>> Welcome.

35:49>> Questions.

35:52>> Any I agree.

35:55I'm You know, Councilman Wearing, you

35:57didn't really give those same accolades

36:00on the presentation I gave, but

36:02[laughter] it's okay.

36:05>> Well, you know, I I had my sunglasses on

36:07with all those graphics you had up

36:09there.

36:09>> Yeah. [laughter]

36:12Thank you. I agree. That was very well

36:14done and um very thoughtful and um

36:18appreciate the time and effort that you

36:20and your team put into putting that

36:22together. And it is a big number. Uh we

36:25we um in all likelihood will not be able

36:28to uh accommodate everything, but uh I

36:31think it was very thorough and and

36:34um like I say, well thought out. So

36:36appreciate the effort there. any any

36:38other questions from any of the other um

36:41ad hoc committee members on uh this

36:45presentation.

36:50Okay, let's do we have another one?

36:53>> Nope, that was it, mayor.

36:56>> All right. Well, um

36:59uh if there's nothing else for the good

37:01of the cause, then uh this meeting I

37:04will call adjourned and appreciate

37:07everybody's Simon.

```*