2026-10-27 - Special Committee on Ways and Means Meeting

Summary

  • Chair Miguel Sanchez presided with Jill Davidson, Councilor Graves and Shelley Peterson among those present. The committee heard two updates: Downes Construction on phases 2 and 3 of the school building program, and LeftField Project Management on phase 4 (the newer bond-funded projects). Both exhibits were entered into the record unanimously (4-0); adjourned 9:08 PM.
  • Downes, phases 2 and 3: most projects were reported on schedule. A middle school upper campus was recently completed and in closeout. Pazarian is behind (contaminated soils and a work stoppage), with a recovery schedule and possible costs under review; its budget was given as about $79.6M after growing from a roughly $33-34M renovation in 2022 as the building grew from about 72,000 to 120,000 square feet. If it is not ready by September 2027, students stay at the swing site with temporary classrooms on the field.
  • RFK: about $77.7M, all new construction, started 3-4 months late after being pulled forward from phase 4 and redesigned; the presenter said it is probably 2-3 months behind, with 70% of subcontracts bought out. Lima/Storer is about $87M and on target; Mount Pleasant High is about $110M with a hybrid renovation and addition; West Broadway is about $84.5M and on track. Steel tariffs, including steel held up in Canada, are an emerging cost risk.
  • Reimbursement: the state certificate of post-construction is tied to housing-aid reimbursement. Some deadlines fall on June 30, 2027, but the agreements for most of these projects run to December 31, 2028 or June 30, 2029, so missing 2027 would delay reimbursement, not end eligibility. City finance said it assumes RFK will not finish by June 2027.
  • Cash flow and invoices: the city was closing on a $140M bond the next day, with cash expected to last through July 2027 and roughly $100M more borrowing likely then. Subcontractor invoices are reviewed by the owner's project-management team before the city pays. The state had asked for information about the project managers' billing; a reconciliation found a small under-billing of hours, which the presenter called an oversight.
  • Swing space: a district official said the Pazarian delay keeps the swing space in use for at least the first half of the school year; transportation costs of swing placements had not yet been modeled.
  • LeftField, phase 4: the program aims to add 3,000 new or like-new seats by 2030. State reimbursement approvals total about $469M against roughly $400M in cash flow, leaving about $70M to reprioritize. The base reimbursement rate was given as about 80%, near 90% with the bonus, but the bonus requires phase 4A projects to be substantially complete by June 30, 2029, which makes an August 2026 construction start critical. Presenters said labor and material costs are up about 27%, and a new tariff caused a $220,000 steel change order.
  • Proposed scopes discussed: a preK-8 new build for the King school (revised agreement about $90M, approved unanimously by the School Building Committee and School Board), consolidating Carnevale into DelSesto (Carnevale has structural problems tied to a landfill cap), a roof for Hope High School (about $3.5M) and smaller phase 4B projects. Over 160 stakeholder meetings were held, against a policy requirement of 15. Council approval of contract amendments and money is still needed.
  • The capital revolving fund started in 2022 with $8.3M, has paid for about $28M of work and is down to about $5.5M with no sustainable source to refill it. Councilors also asked about the August 2026 start, cost risk, swing space backups and a state requirement to spend 3% of the school operating budget on maintenance.

Issues discussed

Caption caveats: school names, several dollar figures and the exact reimbursement dates are read from auto-captions and may be misheard.

Agenda

See the posted agenda linked under Sources.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:00Hi, good evening everyone. My name is

00:02Sanchez. I'm following the special

00:04committee on ways and means to order.

00:06Uh, thank you everyone for being here.

00:09Um, I roll call please.

00:11>> Chair Sanchez,

00:12>> vice chairman Taylor.

00:14Councelor Davidson,

00:16Councilwoman Graves,

00:18>> present.

00:18>> Councilwoman Peterson, we have four

00:20present and one. We have more.

00:22>> Thank you. I'll recognize from our

00:24solicitor office here. councelor

00:27majority leader

00:29is here with us today

00:34from our slash everything else uh folks

00:38from our office thank you um at this

00:42time I will uh have anyone else to today

00:48in

00:50all

00:54the dragons

00:55Please

00:57testimony you're about to give true

01:02>> state

01:06chief financial official projects deputy

01:08finance director of

01:11>> John public

01:14director program management construction

01:18chief operating officer

01:20proced executive managing director of

01:23Awesome.

01:25I think we'll be

01:28um so it looks like it's all one big

01:31discussion. Um do you guys have a format

01:33on how we're going to pick it up or

01:38>> Yeah.

01:38>> All right. I was going to suggest you

01:40start with phase two and three and do

01:42the older projects first. So that would

01:44be downs. Um Crystal is here to support

01:47on financial questions throughout.

01:51>> Sorry.

01:54So there are paper copies.

01:57I think you might have them. We could

01:59pass them out.

02:02>> Be easier to read.

02:05>> I get a motion to answer exhibit one,

02:09please.

02:11>> Motion made by Peterson. Second by

02:13council Peterson. All those in favor I

02:17discuss

02:32um so

02:35we're going to go through one

02:36presentation and then a second

02:38presentation with you is that

02:41>> so you know the school projects that

02:44we've talked more about in this

02:46committee are phases two and three.

02:47Those are managed by Downs. Phase four

02:50projects, which are the newer like $500

02:52million bonds that you all passed,

02:54that's managed by left fields. So, you

02:58know, it's it's one one topic, but it

03:01covers two vendors.

03:03>> So, uh the balance so will speak on

03:08today's.

03:10That's right. Because it's two

03:12contracts. Yeah.

03:15>> Okay.

03:16>> How are you?

03:18>> How are you?

03:21>> So, the uh good evening everybody. Uh

03:23Jers, uh the presentation we're looking

03:26at had the ribbon going across

03:29because they're both very similar in

03:30color. Um so, we'll start off with um

03:34what we do is on a monthly basis, we

03:37provide this up tape to your school

03:39building committee. And what I did is

03:41utilize the presentation you just gave

03:44earlier this afternoon um and put this

03:47into the presentation so you have very

03:49similar and up-to-date information. Um

03:52so the second page is a overview of the

03:55projects. The projects in the green um

03:58are the projects that have been

03:59completed and we're pleased to say that

04:02Spaz Middle School, the upper campus was

04:04just completed recently. We had a ribbon

04:06cutting there a few weeks ago. Uh the

04:09schools on the bottom portion are the

04:12ones that are currently under

04:13construction. Uh there are Lima Store,

04:16Master West Broadways, Bizarian PreK8,

04:19Proing PreK8, M Pleasant, and RK.

04:25Those represent phase two and three and

04:27RK was initially in phase four was

04:29pulled into phase uh three as well, just

04:32for reference. Uh the third page is a

04:36dashboard that we have that kind of

04:37gives an overall status of what the

04:39project is. If it's behind schedule, if

04:41you want I could

04:44go crazy.

04:46Um and what this gives you

04:52um gives you an overall view of the

04:54projects. It's kind of like a health

04:56check for us before we call. Um so the

04:59the Pazarian project which has had a

05:01couple of challenges including a work

05:03stoppage by Ryum right now has a

05:06schedule that's been impacted um but

05:08there is a recovery um schedule that is

05:10being reviewed and and uh cost provided

05:14for it. Um overall um the other four

05:17projects Fogerty Messer Lima Gilbert Dor

05:21and Mount Pleasant are all scheduled. Um

05:24if you go by any of the sites and have

05:26been by the sites and you know councelor

05:28uh Peterson at RFK we just recently

05:31started a steel there as well that

05:33project is tracking a little bit behind

05:34schedule as well. That project did get

05:36started three or four months later than

05:38the other and they are quickly catching

05:39up. But this status dashboard just kind

05:42of gives you an overall uh kind of an

05:45idea of where we are as far as each

05:47schedule health of each project and it

05:49gives you some comments about some uh

05:51milestone dates. So again, good document

05:53to have and it's something that we could

05:55share monthly or quarterly basis as well

05:57so you guys have a good idea.

05:59>> Um question

06:02so so you've been presenting uh similar

06:06presentation to the school buildings

06:08maybe every how often

06:10>> monthly yeah at least monthly.

06:11obviously. Okay. Um, so I I I I know

06:14what the chief drying date is by

06:16speaking to to folks um that have been

06:18working more closely with this, but

06:20could you kind of not to go too in the

06:22weeds, but can you kind of describe some

06:23of the terminology on folks that Oh,

06:26>> absolutely.

06:28>> So, a drying day some critical

06:30activities that you track for a

06:33construction project are foundation

06:36getting out of the ground. You'll hear

06:37people say steel um which is a real

06:40critical um milestone as well. Drying um

06:43or you'll hear sometimes um building

06:47complete or not building complete but

06:49there's building enclosure. Um so

06:51basically when when when a milestone

06:53like a dryin days, it's critical to

06:56understand that that means the roof's

06:57on, the steel's in, and there's

06:59something enclosing the building. It

07:01doesn't have to necessarily be the brick

07:03or the metal panels that will be going

07:05there, but there's something there that

07:07is enclosed the building so that if it

07:08rains, it snows, sleeps, it it protects

07:12the building, so workers can work inside

07:14the building at that point without any

07:17impact. So again, it's a critical date

07:19because weather impacts construction a

07:22lot. Um, so we want to get these

07:24buildings weathertight, dried in so that

07:27they can continue to work, especially as

07:29you get into the winter months and um

07:31without any impact uh to what the

07:33weather might be out there, except for

07:34obviously the safety of of the

07:36individuals working out there and

07:38getting on the site. So that's why

07:40that's a critical milestone that we

07:42always track. Um, some of the other

07:44things we track are MEP, which is

07:45mechanical electrical power, which means

07:47that systems been turned on. Again,

07:49another critical milestone after the

07:51dryin date or building closure date. Um,

07:54we have these real big milestones that

07:56happen that that kind of make a big

07:58difference on the operation of the

08:00building and are better indication of if

08:03the project is on schedule than, you

08:05know, going by a project one day and

08:07only seeing five people there because

08:08it's been raining out and then the next

08:10day there's 30 people there. So, in a

08:12day by day, it's really difficult to

08:13gauge for projects on schedule or not.

08:16But these big milestones kind of tell

08:18you yes, they're making those

08:20milestones. They're either on target

08:22prior, you know, just a little before to

08:25the target or after that. So that's why

08:27we throw those dates out there with

08:30>> um simple question. How many total

08:32bioones are associated with each

08:36building?

08:38So we try to to identify like four or

08:40five, but I can tell you for a fact like

08:43many of these schedules could be

08:44anywhere from 25 to 30 pages on average.

08:47Some of them range to like 100 pages. Um

08:50some get very detailed and that's why we

08:52look at those big milestones and again

08:54like site work, starting site work,

08:57doing your foundations, right? Getting

08:59out of the ground they'll call it and

09:01they're tied into some very specific

09:03things too. So starting site work,

09:06digging, foundation, steel, dryin, and

09:10mechanical startups, right? So the

09:13reason why those are critical are risk

09:16related. So you digging the ground, you

09:18don't know what you're digging because

09:19you can't investigate everywhere. You

09:22get done digging, you get your

09:23foundation in, it takes risk off the

09:25table. So now you know that your budget

09:28is secure because you've just taken some

09:29some risk off. You got your foundations

09:32in. So now you know that your next

09:33milestone is that's critical to it which

09:36is the steel, right? So you get your

09:37steel off. These all eventually take a

09:41small amount of risk off and also help

09:43to to understand what the next milestone

09:45is going to be.

09:49>> Can you tell me what GMDs that is?

09:51>> Oh, that's a big one. Guaranteed maximum

09:53price. So that's something that we

09:55track. So each design, so we've have the

09:58delivery method we've chosen for these

09:59projects, which we started doing in

10:00Providence uh probably about six or

10:02seven years ago, is traditionally you go

10:05out and hire an architect. The architect

10:07designs the building for about a year to

10:0918 months. Then you bring the contractor

10:11on and the contractor's got to develop,

10:13you know, a scope of work based on those

10:15drawings. There's not a lot of

10:18communication or teamwork with that. We

10:21developed a method that's been out there

10:23for a long time as a procurement which

10:24is design build. We bring the architects

10:27and construction managers together on

10:29day one so that the builders start

10:31thinking about how they're going to

10:32build the project as the designers are

10:34building are designing it and they have

10:37constant communication because they're a

10:38team. So if the designer is designing

10:42something that is not within budget or

10:44that is problematic and in the past

10:46we've had problems with long lead items

10:48which is sometimes you just can't get

10:50certain materials because you know it's

10:52either not available or there's been

10:54some other issue that's happened with

10:55it. The builder will be aware of that

10:57and architect. So the builder will be

10:58able to respond immediately to their

11:00team and say we can't put that metal

11:02piano on the building because there's

11:04been a problem manufacturing that or

11:06getting that. they make those revisions

11:08immediately. It's streamlines. It

11:11usually is more cost effective um than

11:14the traditional method. Um and at the

11:17conclusion of either uh 60% completion

11:20of the construction documents or 100%.

11:23We request a guaranteed maximum price

11:26from that team that says yes, we agree

11:29that we will build this project for that

11:32price. And if anything within these

11:34drawings

11:36are not included or we made a mistake,

11:38we pay for it. It's our race. If you

11:41come in and you tell me, well, I'm going

11:43to add it in the playground. Well,

11:44that's that's a change order, right? So,

11:46the reason why we do that is we reduce

11:48change orders. Again, manage that risk

11:51because we want the money into the

11:53buildings as we can. Um, and we use that

11:55guaranteed maximum price process.

12:00So, um, do you have any depending

12:04a little more?

12:05>> Yeah.

12:06>> Oh, so you're you're going ahead.

12:07>> Sorry.

12:09>> That's all right. Um, so bio completion

12:11in order for them to develop the

12:13guaranteed maximum price. They're at

12:15risk. So, what they want to do is go to

12:18the market and subcontractors, right?

12:20Your mechanical contractor, your

12:21plumbing, your electrical, your steel,

12:24and go out and develop an RFP for that.

12:27get the proposals back, vet out those

12:29proposals and determine which

12:31subcontractor you want to use. Now,

12:34we're part of that process. They have to

12:35submit a document and say, "Okay, we we

12:38went to A, B, and C. We're selecting C."

12:40And we we want to understand why did you

12:42select C? Is it just because of low

12:45price? Is it low price or they can meet

12:47the schedule? So, there's many reasons

12:48why you would do that. So what that

12:50buyout um means is they're 80% I think

12:53we're 80% bought out at RFK means that

12:56they've went out to the market and we've

12:58agreed that 80% of the subcontractors

13:01are procured and again that's a big

13:04milestone to make sure that we are aware

13:06of because it's risk until they buy out

13:10the project and get us to GMP we're kind

13:13of you know working with them based on

13:16their estimate and most of the time the

13:18estimate is sometimes it's not right.

13:21Um, so we're always tracking that and

13:23making sure that we know exactly where

13:25we are with their GMP and their viable.

13:28Um, the other thing is we don't want

13:29someone to give us a GMP and they've

13:31only bought out 25% of the job because

13:33then we know there's 75% risk in there,

13:36uh, which could be a problem. So we want

13:37to make sure they significantly have

13:39bought out the project that the the

13:41construction documents are significantly

13:43done um before we can accept

13:46[clears throat] the GC guarantee maximum

13:48price.

13:49>> Thank you.

13:54>> Okay. So the next slide I think is an

13:56important slide as well. Um was several

14:00years ago I think at the finance

14:01committee and but occasionally at the

14:03school building committee we share this

14:04slide. Um this is just showing that you

14:08know we've always said the construction

14:10is a big economic engine. I mean it it

14:12really feeds the vendors, the suppliers

14:15in the surrounding areas, provides uh

14:18jobs for residents um for you know uh of

14:22not only Providence but the the state of

14:24Rhode Island. And this is just

14:26demonstrates how that works. Um, you

14:28know, we we track the percentages for

14:30MWB subcontractor percentages and you

14:32can see the majority of the projects are

14:34in that 20%. We're we're tracking

14:36towards the 20%, some are a little bit

14:38lower. Um, I think something else that

14:40we're proud of is the Providence

14:42residency hours. We track those. They

14:44can see thousands of hours have gone to

14:46um Providence uh residents. Uh we do

14:50attracted by percentage uh our minority

14:52workforce, female hours, and then as

14:55apprenticeship hours as well. So I think

14:57it's just a good thing for everybody to

14:59understand how the money flows back into

15:02province and and you know the importance

15:05of these projects as well on the local

15:07economy. Uh question. Um what was um

15:14I guess what what what has been like the

15:16main difference between uh the phase two

15:20uh projects and uh the phase

15:25three uh projects for the most part when

15:28it comes to Robin's residence is there

15:30just certain uh vendors getting work or

15:35>> Yeah, that's an excellent question. So

15:37we've starting back with phase one with

15:39the Narduchi project in Spaziana

15:41Elementary School um and um we we

15:46strongly encouraged our design buildings

15:48and our construction managers to go off

15:50actively go out and look for local

15:52vendors. Um I think as people got as

15:55more vendors have become very busy I

15:57think that there that opportunity has

15:58grown as well. So I think what's

16:00happened is now with our presence here

16:02and with the construction managers who

16:04have been have a good working relation

16:06province, we're finding more and more

16:08vendors. So and we're also pushing a lot

16:11of the subcontractors to hire locally as

16:14well because they all need to find

16:15workers. Um so you could see that as you

16:18go progress down, we're seeing our our

16:20worker hours u increase dramatically. Um

16:23and a lot of these projects are only

16:25halfway done. So, I think that hopefully

16:27you at the end of the day, I'm going to

16:28come back and bring this back to you and

16:30we're in the tens of thousands, which is

16:31what I'm hoping for. Uh, but it's it's

16:34that ongoing reach out um discussion.

16:37Um, and you know, it's it's it's a

16:40struggle right now to find contractors,

16:43workers in the construction industry

16:44right now. It's it's a it's an industry

16:46that's aging out. We strongly encourage

16:49we go to schools and talk about it. Um,

16:51and you know, we go into the community

16:53as well and and you can see that um, it

16:55looks like it's it's starting to show a

16:57little bit more success every time.

17:04But um, we provide a project overview

17:08uh, project. So we do this over slide

17:10that kind of talks about what the actual

17:12overall budget is. Uh, our student

17:15enrollment, is it a new construction?

17:17There's no swing space. And then we have

17:19our grade configuration. in this case a

17:216 through 8 and it's a four track

17:23school. So that means there's four

17:25classrooms per student. You'll see three

17:27track and four track. Sometimes we have

17:28some threetrack prek8s and we have some

17:30fourtrack prek8s. But in this case, this

17:33happens to be a four track.

17:35>> You said all those.

17:36>> So um what you'll see on the grade

17:38configuration is sometimes you you'll

17:40see it say three track versus four

17:42track. The four track or three track

17:44just means amount of classrooms per

17:46grade. So grade three might be a three

17:49track with only three classrooms per

17:51grade. But as you get to the upper

17:53grades, you might have a four track

17:55which means more children, more

17:56classroom. So there's four classrooms

17:58per grade. And you'll see in some of the

18:00projects we have three, four track or

18:03just a four track from from kindergarten

18:059.

18:08>> So we broken down into or is broken down

18:11into our two different campuses. It's uh

18:14two separate well two separate

18:16buildings. They call this the upper

18:18campus just because the upper grades I

18:20think is what it is. They're directly

18:22across from each other

18:24>> but they were both a new construction.

18:26>> Correct. Yes.

18:27>> And there's kids in school, right?

18:30>> Yes. Y

18:32>> So this next page is just a overall

18:35again like a dashboard. It kind of gives

18:36you a project glance. So again it gives

18:39you the schedule. In this case it's

18:41completed. The budget is right on

18:43target. Um our contract GMP is still um

18:47within the 29 million and the

18:49subcontractor buyout was 100%. We have a

18:52current outlook it just talks about

18:54where the project is right now and what

18:56it's called is close out. So as the

18:57project gets substantially complete

18:59there's a close out and what that means

19:01is training is happening at the school

19:04there's a handover to PBSD in this case

19:06in ABM where they are trained. they get

19:09all of the construction documents, the

19:12manuals, the operating procedures, all

19:14that kind of stuff. So, that's called a

19:15close out where there's a transfer of

19:17information and training that usually

19:19takes uh several months to do. Um, and

19:22that we track that as well as one of the

19:24milestones.

19:26U some key dates which will be more

19:28critical as we get to the next couple of

19:29projects, but again, we track those and

19:32milestones. And you can see some of the

19:33milestones that you get in the close

19:34out. It's the punch list. It's the close

19:36out. Um, and there's some wall graphics

19:39that still have to be done.

19:42And then I provide um some photos and

19:44you can see from the ribbon writing just

19:46a photo inside of the building and sort

19:49of how

19:53>> questions

19:57seems kind of low school. Is it not

20:00built or

20:03>> um the build? So between the two

20:04buildings it would be like a a prek.

20:07It's actually about 600 student maybe

20:09it's more than 600

20:15elementary um

20:19>> okay but it's the combined school. So

20:20traditionally it would be one big school

20:23with six or 800 kids. In this case it's

20:25two schools across from each other. So

20:26that's why the upper is only 300. So how

20:29many rooms have because the game between

20:31is is

20:33um 6 to 8

20:36they got 700 kids.

20:39>> Yeah. Yeah. So uh well with this it's a

20:42it's a four track.

20:45So that means it's four classrooms. It's

20:47only six, seven, and eighth in the upper

20:49campus. The prek through um five is in

20:53the building across the street. So

20:55that's one larger. I think that's about

20:57600. So it's 900 for total if I remember

21:00correctly.

21:01small.

21:02>> Yeah, this is the smaller middle school

21:04upper.

21:05>> Okay.

21:06>> Middle school part, right?

21:08>> If it was in one building, it would be,

21:10you know,

21:12>> close to 800, 900 kids on those

21:13buildings.

21:14>> Was um sorry for my lack of a so was the

21:19was the south or was the other campus

21:21called?

21:23>> We've always called it just elementary

21:24school. I don't know if there's any

21:26other name, but they just

21:27>> so the upper building is 6 through8.

21:30What's the other building?

21:31>> PreK through five.

21:32>> They used to call the prek through five

21:34building.

21:37>> So, so that has been that's been

21:39completed for a year now. Probably about

21:42two three years now.

21:43>> Yeah.

21:45>> Yeah. And it looks very similar.

21:52>> Yeah. Right here, John.

21:54>> Oh, there you go.

21:56Uh, Councilwoman Grace, the student

21:57capacity at the elementary school is 365

22:00according to slide one.

22:01>> Thank you.

22:01>> You're welcome.

22:06>> Uh, Mary forward to the next slide. So

22:09again, overall budget at 73 77 million.

22:13Our student enrollment there because

22:15it's all under one roof is 858 is the

22:18estimated it's new construction. They

22:20are temporarily housed at 85 Laurel

22:22Hill. That's our swing space. And here's

22:25an example of a grade. So this

22:28particular project, the grades preK

22:30through five are a three track. So three

22:32classrooms per grade. And then as you

22:34get to the upper six to eight, it

22:37becomes four classrooms.

22:40And that's because the need and the

22:41amount of students that are in the the

22:42middle school.

22:46Then looking at the project at a glance,

22:49um this project now is under

22:51construction.

22:52uh schedule is on track, budget is on

22:54track. We do have a draft GMP of $69

22:58million. And you'll always see that the

23:00GMP will be less than the budget.

23:02Although it's a big chunk of the budget,

23:04it is always less. It's usually in the

23:0680% 85%

23:08of the construction cost are the overall

23:11budget. Subcontractor bio is at a good

23:1495%. So we'd like to see that. And then

23:17you'll see your B dry in uh in December

23:21certificate of post construction which

23:23is the target that is the ride

23:25reimbursement date. Um the building is

23:27scheduled to be complete occup

23:32again it was because you recall I said

23:34that it takes several months after the

23:36project is complete to do all the

23:38training and transfer of paperwork. And

23:41you could see our milestone tracker on

23:43this one. Our ability dry in our

23:45permanent power. The permanent power is

23:48another one where you know sometimes

23:49we're waiting for ground energy to bring

23:51us transformer or have to change. Uh we

23:54had this issue at Spasiano where they

23:56had to run new telephone poles down the

23:57street. So that's another milestone that

23:59we track. Uh MEP startup which is

24:02something that I had mentioned before.

24:04our June 30th construction uh posted uh

24:08construction certificate and we also

24:10track our furniture delivery and then

24:12our August date fiscal this particular

24:15project um we have an MOA at least one

24:18MOA for each project. This particular

24:20project has two that is the

24:22reimbursement uh funding for this and

24:25those one expires on June 30 27 the

24:28other one on December 31st 2027.

24:32Um I was just saying question um so so

24:35looking at this milestone tracker I went

24:37back look at the splaziano

24:41tracker started um uh where this one

24:45ended. So it's two confirmed. Have the

24:49certificate of post construction been

24:53granted to

24:55>> Yes.

24:56>> Yeah. What about the ride reimburseable

24:59bring?

25:01>> We met that milestone for

25:03>> those have been all set with

25:05>> we we have a certificate from the

25:07architect that it was substantially

25:09complete and it was issued um June 30th

25:12of this past April.

25:14>> Yep. And it's occupied. want the

25:16building.

25:18>> So your milestones will change as the

25:20building progresses, right? So if I came

25:23back in two months, that building dry in

25:25would no longer be a milestone. Will be

25:27new milestones here that we're tracking

25:29at that time. If it's still there, the

25:31problem

25:33>> um

25:35yeah, I guess like for us it would be

25:38helpful if if uh if all the projects

25:41have all the milestones on there. So,

25:44>> yeah, that I mean

25:46>> we could do that. It would be

25:48>> a lot more pages.

25:50>> So, um

25:52>> we could figure out

25:56>> Sure.

26:01>> any digital version of this available

26:03that

26:05updates.

26:07>> Do you do you do a digital version about

26:09this or there's something like is this

26:10online?

26:11>> Oh, yeah.

26:12This is this is done at the SBC. This

26:14particular one I is changed from what we

26:17previously do just because I wanted it

26:19for both. Um and I think they really

26:20like this. So we're going to be doing

26:22this some very similar to this in the

26:23future. It's always on the SBC website

26:26every month after our meeting and we

26:28could you know on this once it's public

26:30we certainly can have anybody have it.

26:33We we usually keep it on you know our

26:35server as well or our online website

26:37too. There are websites for each

26:39particular project by the way. So if you

26:41wanted to see RFK, there's a website

26:42specific to to RFK that has like a

26:45summary. It doesn't get to this level of

26:46detail. It's more for public and just so

26:49they can see what's going on. There's

26:50one for RFK, there's one for SP, there's

26:52one for every project out there. We

26:54could give you a link to that and we

26:56could make sure that a link is provided

26:58for this every

27:09slide.

27:11again tracking GMP status, the draft was

27:14received and some of the the big

27:16procurement items on our side. So the

27:18design builder has their procurement,

27:20but we also have to make sure we're

27:22tracking our milestone, which is the

27:24procurement of furniture and technology,

27:26which is provided by the owner. And then

27:29you could see some photos right here of

27:30the condition of the property right now.

27:41Moving on to Gazerian. Uh that project

27:44budget is 79.60 million. Um the

27:48estimated student enrollments to be 858.

27:51It's an all new construction. I

27:53shouldn't say all new. The we're keeping

27:54the gym in the back which is getting

27:55renovated. Uh those students are

27:58temporarily housed at Narduchi. Um the

28:01grades are prek through eight and again

28:03it's a three track four track. So prek

28:05through five is three track three

28:07classroom 6 through eight is the four

28:09classroom the grade and at the top of

28:12each page you could see the team

28:14members. So on this particular case the

28:15deio and studio j are design build. So

28:18if you look at each each one as you go

28:20through and you're curious about who the

28:22construction and design team they're

28:23also up there. Well

28:28so project glance the schedule is um

28:31tracking behind right now. There were

28:33some issues. There were some

28:34contaminated soils that had to be

28:36removed. Did do a lot of work stoppage.

28:39Um that team is working diligently to

28:42try to uh

28:44do a recovery schedule. Um there are

28:47potentially some costs with that. We're

28:49looking at at what those costs might be.

28:52We've also uh been working with PPSD and

28:55the school principal on a plan B if the

28:57school is not ready for September of

29:002027.

29:02um that they can stay at Arduuchi. That

29:04space is currently not needed for swing

29:07space, but they do need another five

29:08classrooms. Um so we're looking at

29:10bringing some temporary classrooms in.

29:13Um we've developed a plan with PBSD.

29:16We're putting an RFP together um in case

29:19we do need it, we want to get it out to

29:20bid and have it um and make a decision

29:23probably around the early beginning of

29:25the of this year, the new year and um

29:29and be able to say, "Yeah, we need to go

29:31with plan B and have them stay there a

29:33little bit longer."

29:37>> I was just going to add that

29:40that's

29:42>> Yeah. So, we've we've worked with uh the

29:44principal what what ideally she would

29:47want to to do. Um and we come up with a

29:50couple different options and um she had

29:52a lot of input on it which was good. Um

29:55they do need it only for one grade

29:56level. Um and they only need five

29:59classrooms which is good. Um so we would

30:01have temporary classrooms out there that

30:03would be put on part of their field. So

30:05they have a large field out there. Um

30:07and then um they could manage that with

30:09just one grade level or either an entire

30:12year or potentially the building will be

30:15done midyear potentially or sooner they

30:18could do a midyear move. Um and again

30:20we're just trying to get our options

30:21together so that if there is if there is

30:24um or if there isn't a way to recover

30:26the schedule we at least have another

30:28plan in place where the kids can stay.

30:31>> I have a question on the uh delay

30:34project. Um, so on gauge

30:39the ignore number lost number on the

30:42bottom right.

30:48>> Okay. The the $79 million

30:52uh number right there. So this is this

30:56is the most up to date budget or that

30:58was the original budget.

31:00>> That is not the original budget. That is

31:02the up the the current budget that is in

31:05place. So, um it's a that's a very good

31:08question because Erin has probably the

31:10the most complicated history. Um and we

31:13just actually just went through this and

31:14I I I brought this up with the building

31:16committee because I said I want to

31:17remind everybody um started off as a 33

31:22million 33 $34 million renovation

31:25project in 2022.

31:27Um and [clears throat] then and that we

31:29were at that time we were doing St.

31:30Joe's too. I don't know if anybody

31:31remembers there's uh at that time there

31:33was a preka prop both at the old St. Joe

31:35site. Uh PBSD decided that that really

31:38didn't make sense for them. They

31:39transferred some of the money to Fogerty

31:41and some of the money to uh Pazarian. It

31:44grew to a prek aid at that time that was

31:46either going to be a renovation or a um

31:50new build. We didn't know at the time.

31:52Um we went through some discussions

31:55about uh using the rec center gym and uh

31:58demoing the existing gym. Um ultimately

32:01that didn't work out so we had to keep

32:02the gym up. Um and there's been a couple

32:05of changes. There was a in 24 there was

32:08a change to prek standards which took

32:11and said you know a building has to be x

32:13number size for each student. Um so that

32:17made some changes again um in 24 and 25

32:21which increased the original building

32:22from about 71 72,000 square feet to

32:25about 120,000 square feet. So this

32:28budget has grown um and increased over

32:31the years not because of

32:33>> any fault of anybody. It's just a matter

32:35of you know the plan for the project has

32:37changed and grown since initially. Um

32:41and and I I just said the same thing at

32:43the building committee. I'll say it here

32:44is I think that I, you know, at the end

32:46of the day, I think it was the best

32:48decisions that were made because to

32:50spend 34 $35 million on renovating that

32:52building probably would have been less

32:54than a band-aid on that building. There

32:56was a lot of issues with it. That is a

32:58challenging building just because you

32:59have a gym building, you have the pool,

33:01you have the rec center, you have

33:02residence, and then you have the street.

33:05Um, so it is a challenging building, but

33:07even to renovate that for that initial

33:0935 million, it probably wasn't the right

33:10idea to do it. I think this build new

33:12with keeping a portion of it although

33:15it's had added to the budget and is now

33:17where we stand. I think ideally this is

33:20you know the right project for that

33:22neighborhood for the next you know 30 to

33:2450 years.

33:26Um, council race.

33:30>> Um,

33:31so

33:33if this was going to be um t I mean was

33:38this a fixer up and then you decided to

33:41do this, did you change

33:46that green was supposed to be

33:49prek to ext?

33:53My question is if Nintendo

34:02is 78 million

34:06um

34:08why didn't you take the money's come

34:11from green there and if not why not

34:16because

34:18now we're talking about putting money

34:20somewhere

34:22Um

34:27when when was this all started where

34:29they they going along at the same time?

34:32I guess my question is um because you

34:36went down to 15 million. Now I see.

34:39Thank you so much. I said that we raised

34:42it up. I'm not sure we'll raise the

34:43price um for three. You know, my thing

34:47is if

34:49we switch to MOA,

34:51why is there

34:55a question of price for this?

34:59>> So, you asking and and I

35:02>> before you before I ask the clarity

35:04question to um the green uh that's in

35:09phase four or what phase

35:11>> that's correct. Yeah.

35:13>> So,

35:13>> yeah, I I would rather not answer that

35:16and I don't have the answers to that

35:17question, but

35:19>> so I I guess what what I'm putting

35:21together is here that the this budget

35:25increasing has no direct impact to the

35:28data.

35:29>> Can you That's correct. That's correct.

35:31Was that the question that you had last

35:33years or

35:34>> Well, if cuz this at one time was unexp

35:50before but the difference now.

36:00>> So I guess um I guess the question to be

36:03answered here is if this project went

36:06over a certain amount of dollars uh what

36:09project was impacted a couple years ago

36:12>> St. Joe's project

36:13>> which didn't continue. So Nathaniel

36:16Green was isn't on this MOA with bride

36:20that was applied for subsequently. So

36:22any money that you're seeing moving

36:24around related to Nathaniel Green is

36:26from the phase four pot.

36:29>> So back then the money that was impacted

36:31with this uh project going over budget

36:35or maybe over budget is not the right

36:36way going a different direction.

36:38>> Yeah. With the reprogramming and the

36:39changes in in the programming. Yes.

36:41>> Correct.

36:42>> Because this was approved on the 2022

36:44MOA. So there's versions of applications

36:46we submit to ride for specific projects.

36:49Um the Kazerian project was identified

36:52when we were submitting in 2021 for 2022

36:56and then evolved at that point.

36:58Nathaniel Green was part of the 2024 MOA

37:01submission. So from a timing

37:02perspective, a lot of these things were

37:04happening maybe at that stage

37:06application were being built but not

37:07like after the project had been approved

37:09and we had full ride approval.

37:16>> [clears throat]

37:18>> My last question on Darian um regarding

37:22the schedule impact um I know there's

37:25efforts being done to to get

37:29back

37:31you go into those specifics a little bit

37:33more.

37:34>> Sure. Um, a couple things that the the

37:37design build team, the construction team

37:38is doing right now is they're out in the

37:41market, the subcontractor market trying

37:43to get um, I guess agreements with the

37:47subcontractors that they can accelerate

37:50the project. In other words, they have

37:52the resources to be able to have workers

37:54there instead of five days a week, maybe

37:57six days a week, maybe instead of eight

37:58hours a day, 10 hours a day. Uh the

38:01problem is right now that is there's a

38:04lot of work not just in province even

38:05though there's a lot of work happening

38:06in province but throughout the state of

38:08Rhode Island and there's a cost to that.

38:11Um so they're finding subcontractors

38:13that can do it um and then they're

38:15finding subcontractors that cannot do

38:17it. We just don't have the workforce to

38:18do it. The ones that can do it are

38:20asking for a premium saying, "Hey, we

38:22have to pay our this individual, you

38:25know, half time and a half or double

38:27times or and we have to keep a

38:29supervisor there with them." So, there's

38:31a cost impact to that as well. So that's

38:34part part of what we're looking at right

38:35now, that cost impact to accelerate the

38:37schedule and try to get the school open

38:39on time and what that might be versus

38:43having those temporary classrooms

38:45installed um and then just have the

38:48project done at a regular pace um and

38:52see what the the differences and do an

38:54analysis on that.

39:01>> Any other questions? Um, is there anyone

39:03before we move on to the next five?

39:13>> Sure. I do have a quick question. Sorry.

39:16>> Sure. I'm I'm just going to apologize.

39:18This meeting is probably go a little

39:19late. Um, there's a lot to to go over.

39:23Hopefully people don't have anyone

39:25waiting at home for the immediate

39:27future. Um but uh regarding the swing

39:31space um at Rabuchi. So so if this goes

39:36into 2027

39:39um these students still need to be at

39:42the swing space. Um was was there plans

39:45for Narduchi to house another set of

39:49students?

39:51I guess I'm just trying to make sure

39:52there's no ripple effect uh happening uh

39:56regarding other projects using that

39:58space. Yeah,

39:59>> my understanding is I think we have like

40:00six swing spaces right now and I think

40:03>> six different swing spaces and I think

40:05there's a need for maybe four in phase

40:07four and when they get phase four

40:13>> sure Ben Holstein PPSD um yeah so the

40:17the construction delays at and our duchi

40:20uh are going to require that at least

40:23for the first half of the year and um

40:25conceivably for the duration of the year

40:27we would have those schools schools

40:28remaining in those facilities. That does

40:30not create um that does not put schools

40:34in phase 4 that are under that are going

40:37to be starting construction without a

40:39swings base location. It just puts us it

40:41takes those two options off the table.

40:43And Narduchi in particular is um

40:46something of a nicer space that we would

40:48probably choose to utilize if that

40:50option were on the table. So, everyone's

40:52going to have a home. Uh just maybe

40:55we're going to have to make a second

40:56choice for learn the schools.

41:07>> Yes. Yes.

41:09Along those lines

41:13has a safe development drive suitable

41:17learning spaces for the programming

41:19that's currently in their schools.

41:21Um what I want to point out before you

41:25what are what have you anticipated are

41:27some of the possible learning impacts

41:30>> I'm sorry

41:31>> learning outcome impacts

41:32>> yeah so one of the things that we've

41:34tried very hard to avoid and I think we

41:36we'll be able to avoid it is in

41:38particular putting middle schools who

41:40are moving into swing into elementary

41:43school buildings and this was there were

41:45a set of options that we were looking at

41:46that we thought potentially out of

41:48necessity that we were going to have to

41:50do um in particular Delesto Middle

41:53School. We were looking at the

41:55possibility of having to move that into

41:56one of our elementary schools that would

41:58be moving out uh once these buildings

42:00their new buildings are constructed.

42:03There were a lot of issues with that

42:04because the way in which an elementary

42:06school is designed and built uh is quite

42:09functionally different than that for a

42:11middle school. So there were security

42:13issues, lack of security cameras, you

42:15need fewer of them for elementary

42:16schools. we are um we have found

42:19solutions that are going to allow us to

42:21avoid that. So now we feel like um uh

42:25middle schools are either going to be

42:26swinging into middle school buildings.

42:28In some cases, we found ways to have

42:30them be able to swing in place so they

42:32actually don't need to move at all.

42:33We're going to move the construction

42:35around them, but in all cases, we are

42:38going to be moving uh student

42:40populations into facilities that are

42:42going to be suitable for their

42:43programmatic needs. There are instances

42:45in which we're going to need to make

42:46some modifications. There are we're

42:48going to want to have to put um some

42:50additional cameras in as necessary.

42:52Perhaps um uh you know, we're looking at

42:55options including building some

42:56additional classrooms potentially um in

43:00areas like uh parts of a of a um of a um

43:05like a stage area, but ultimately we

43:09feel like these would be suitable

43:10learning environments.

43:12a follow

43:16answer now, but I just want to raise a

43:18question about um impact on

43:20transportation costs.

43:23>> Yeah. So, so it's a it's a great

43:26question and one that we in full cander

43:28we have not yet modeled that out. But to

43:30the extent that we are moving students

43:32further away from their homes, there

43:35will likely be sorry schools further

43:38away from their homes, there will likely

43:39be an impact to transportation costs. Um

43:42the reality is we don't have a lot of

43:45great options on the table in terms of

43:47schools that are close to some of these

43:49schools that are going to be moving in

43:51and out of swing. So, um, throughout one

43:54example is we get a lot of feedback

43:57from, um, Barton and MLK, two schools on

44:00the east side, who are both going to be

44:01moving into swing that they would very

44:03much like to stay on the east side and

44:05we've looked at a range of options to be

44:07able to accommodate swings base

44:09locations on the east side and there are

44:11none that are practical. So, um, it sort

44:14of is what it is.

44:21um have the situation at

44:25improved the issue that they were having

44:29and all those other things I mean it's

44:31winter time now believe me

44:36I'm sure it's a great thing

44:40but if they're going to have to stay

44:44all those things we know the best

44:49people

44:50>> [laughter]

44:53>> Uh, so I'll confess I'm actually not

44:55aware of the heating issues at Narduchi

44:58that you've described. Um, is were these

45:00issues that happened last year in winter

45:02time?

45:03>> This year there there is the only issue

45:06we're aware of is the air conditioning

45:08is right there. Yeah, there's no air

45:11conditioning in that building. Um we've

45:14were we've been aware of during

45:16September when we had those hot days

45:18there there has been some issues there

45:21but as far as heat and not we have and

45:23that that building has been operating

45:24for about three years

45:26>> so I think it's been an air conditioning

45:27problem which they're they're trying to

45:30look at in certain parts similar units

45:33parts of the building there's air

45:35conditioning problem here

45:39>> is

45:43Thank you.

45:45>> Uh yeah, just for the record, um Kyle

45:48Deado is our director of property with

45:51project management uh has been very in

45:54the loop of school building

45:56construction. So he's building a

45:57conversation uh for dialogue

46:02that might

46:08all continue on conversation. Uh thank

46:11you uh Chris

46:15or

46:17yeah

46:18>> right all right so Lima store you can

46:20see that the budgets get bigger the

46:21budgets get awarded bigger $87 million

46:24budget 996 uh estimated student

46:27enrollment it's all new constructed

46:29there's no swing space because the Lima

46:31um children are still in the Lima

46:33building they will come over to the

46:34historic um upon completion this is a

46:38fourtrack four track so that means four

46:40classrooms for grades starting with prek

46:42all the way to 8th grade. That's why

46:43it's a bigger building, bigger budget or

46:47choice.

46:49Uh next page schedule is tracking them

46:52very well. It's on target. The budget is

46:54on target. We do have a draft PMP uh

46:57that is within uh the

47:00target. Uh their subcontractor bio is

47:03about 80% right now. Um which is again

47:06good. um they have very similar you'll

47:08see a lot of these projects have very

47:10similar milestone. They're all pretty

47:12much in the same

47:14schedule and looking to dry the building

47:18in the dirt really set it was in. So by

47:20December the dryin date uh they are uh

47:24working towards a certificate of post

47:26construction for June 30th 2027. The

47:29building is scheduled to be complete on

47:31or before August 30th where the project

47:33close out of December 2027.

47:37Um, this project is scheduled to be

47:39complete, but I also want to reassure

47:40you that the the MOA for this project

47:43memorandum of agreement for ride the

47:45ride reimbursement agreement milestone

47:46is 1231 2028. So, we're we are well

47:50ahead of that MOA and any reimbursement

47:53risk. Um, the risk would be the children

47:56not being there. this this schedule has

47:58been moving ahead very well. Um, and you

48:00can see just by the photos that it's uh

48:03enclosed. It's pretty close to dried in,

48:06which is what we call. Um, that's

48:09actually a real good example of part of

48:11a building being dried in already. And

48:13you can see once that roof's in and you

48:15got some sighting in place. Actually,

48:16these pictures are only about a week old

48:18and they already got brick started

48:19there. um you know that that they once

48:22they're in that condition, they could be

48:24working inside that building day, night

48:26if they had to. Um which is good because

48:29you know you're going to have weather

48:31delays and some other delays and

48:32there'll be long days sometimes um to

48:35meet these aggressive schedules.

48:40>> Um my question is about the contract for

48:42the five. Is there a

48:47a reason why that doesn't have to make

48:50all

48:51that? Um is there

49:02um

49:04I that I don't know the answer to that

49:06as that decision preceded uh preceded my

49:09involvement in the project. Um, do you

49:12know anything about how we arrived at

49:13these?

49:14>> I think this from from a programming

49:16standpoint, we arrived with PPSD about

49:18the needs of the neighborhood and the

49:20student population. Um, and in certain

49:23areas, there's a need for four classes

49:24for prek and lower elementary. In

49:26certain areas, there is not. And the

49:28Lima Stewart, I guess based on

49:30enrollment, past enrollment, there seems

49:33to be a bigger need to have four

49:35classrooms for grade starting in

49:37elementary. There certainly seems to be

49:39a need across uh providence for the

49:42middle school for four classes per grade

49:44but on the lower elementary that that

49:47was our understanding on the program.

49:48>> Okay. My question was um there's usually

49:53another six to eight will travel or

49:56further but usually the younger ones

49:58don't. So so you see there's more

50:01children at that age than you believed

50:04in in the other areas.

50:07>> Okay. Yeah, it's based on their

50:08enrollment from previous enrollment.

50:14>> Hey Joe, can you talk to me about this

50:17um ride agreement milestone date to the

50:21June 30th please? Um what is the

50:22difference? I mean my understanding

50:24throughout this whole program is that

50:27June 30th plus the substantial

50:28completion dates that help

50:30>> that's been a lot of confusion. There's

50:32only a few projects that have that June

50:3430th, 2027 date for their in their

50:36original memorandums agreement and that

50:40was Kazerian for example, right, which

50:42started in 22 is a $35 million project

50:44or 33 34 somewhere in that area um and

50:48then grew. So there's a portion of that

50:50funding that is tied to an MOA that

50:52expires on June 30th, 2027. Um that

50:57doesn't mean we don't get an extension

50:58for it. It just means a portion of it.

51:00That project also has other MOAs that

51:03expire in 2028

51:06and well I think there's two in 2028

51:08expire there. So that meaning if for

51:12some reason Lima store did not get done

51:15on June 30th it would not affect any

51:18reimbursement unless you get unless you

51:21went past that December 31st 2028

51:24deadline. We're you know nowhere close

51:26to that. everything will be closing or

51:29finishing the school at some time. Um,

51:31and that's a reimbursement issue that

51:33happens with the city as well, right?

51:35So, they go out and get the bonds and

51:36it's it's when they could collect that

51:38reimbursement that would mean that there

51:39would be another year before they could

51:41request that reimbursement.

51:48>> Any other questions?

51:54>> Pleasant. Um this is uh interesting

51:58project. This turned into a hybrid

51:59project is what we called originally. We

52:00had looked at demolishing the project

52:04and landed on um actually renovating a

52:07big portion and then adding a new

52:09addition in between and new between the

52:11gym and the existing campus. You can see

52:13that the building's not going to be

52:15white. Everybody asked that question

52:16like is that going to be white? It is

52:17not. That's just for the diagram. Uh but

52:20that is a a large phase project. So,

52:23we've already had a couple of phases

52:25that have been completed. Um, and we

52:27have another phase of classrooms that

52:29are going to be renovated and they'll be

52:31moving in right around Thanksgiving and

52:32then another phase in February. But

52:34there's multiple phases that'll be

52:36happening. Uh, it's a perfect example.

52:37Ben talked about like a phase swing

52:40space like they move the children

52:42around. We did this with classicalico as

52:44well where we finished a part of the

52:45building, moved them into the new part

52:47of the building, moved them out of

52:48another area, renovated that area, and

52:50then moved them back in there. take a

52:52lot of planning. Um um but it it is

52:55doable if you have enough classrooms to

52:57do it. And you know, Mount Pleasant

52:58being a large,

53:00you know, campus. We were able to do

53:03that. That section in the middle of the

53:05white is actually existing school that

53:06we're going to demolish this summer and

53:08then have a new addition going in there

53:10which will be a cafeteria, a STEM room,

53:12and some other um I think the new media

53:15center is going to be up in that area.

53:17That project budget is 110 million. the

53:20thousand student enrollment estimated um

53:22and it's occupied um in this phase. It's

53:25new construction and renovation.

53:31>> Um you may have against it I'm looking

53:34at this budget and it's much like

53:38>> so

53:41area of that that's basic

53:44>> the square footage in students. So a

53:45thousand students gets you bigger

53:47budget, bigger school, and bigger

53:49reimbursement.

53:50>> Okay. Even though this is really just

53:54>> renovation opposed to building

53:56>> Yeah, it's a renovation and new

53:57addition. Yeah, there's the the new

53:59white part there is a a new addition.

54:01>> Okay.

54:01>> All right.

54:02>> Is um is the assistant auditorium

54:04screen?

54:05>> The Yes, it is. Yes. And we're

54:07renovating that as well.

54:09>> Okay.

54:11um schedule is on track, budget is on

54:13track, and we have a draft TMP. And as

54:15you can see, it's $110 million budget,

54:17but the as you like I said before, the

54:20contract for the construction, a big

54:22portion of it, it's 102 million for the

54:24construction, and they are 96% bought

54:26out. Um they they've already done a

54:29couple of moves as I said, but there is

54:31a building dryin date for the new

54:33addition that's being built on the back.

54:35Um, this project is tracking towards the

54:38certificate of post construction on June

54:4030, 2027. But again, reminder that the

54:43ride MOA really doesn't expire until

54:46December 31st, 2028, which is, you know,

54:50quite a ways away. Uh, but we're still

54:51planning on meeting that date because of

54:54reimbursement for for the funding for

54:56the city. uh building is going to be

54:58complete in August and there will be

54:59some project this project will close out

55:01a little bit longer because they have to

55:03demo the building, build that new

55:05section during the summertime and then

55:06there's some landscaping and stuff that

55:08has to be done. So most of the other

55:10projects will be closing out by

55:11December. This one will probably be

55:13closing out closer to February

55:16of 2028.

55:18Same type of big milestone building

55:21dryin me startups. Um, and in this one

55:24they actually we've already procured the

55:26furniture, so we're we're installing

55:28furniture as they finish the phases as

55:30well.

55:32>> Uh, we have a question.

55:34>> Yes, please. Uh, Joe, can you speak to

55:37why it's often seems like it's more

55:40expensive to do these renovations in

55:41existing buildings versus demo and

55:43rebuild? I see 110 million here for

55:45Mount Pleasant just in addition to some

55:48of these new builds that are anywhere

55:50from 70 to 80 million to build 110.

55:53>> Yeah. What happens with renovations is

55:56it's a lot more difficult to get the

56:00spaces you need. Um it's a lot more

56:02difficult to understand what's behind

56:04every wall structurally. Although some

56:07of them were built very well, they were

56:09built difficult to demolish or to work

56:11around and put bigger classrooms in. So

56:14there's there's an added cost for going

56:16in and trying to renovate a building.

56:18They're usually not as efficient as a

56:20new build, right? A new build you could

56:22you can make the room whatever size you

56:23want. You don't have a hole sitting in

56:25the middle, right? Those kind of things.

56:27Um with with Mont Pleasant, we were able

56:29to do both though because that was such

56:31a big structure and that those big

56:33hallways. We were we were lucky where we

56:36that renovation is actually going to

56:37work out better than most. Um I don't

56:39know if you've been in classical or

56:41you're aware of classical room classical

56:43they have all the classroom the outside

56:45and you go in there and they have those

56:46big empty open spaces. Um so that's a

56:49perfect example of like a renovation.

56:51You're heating you're cooling that

56:52space. You're putting lighting in there

56:54that that you really don't use for

56:55education. So that's money that's being

56:57invested in there that you really don't

56:58use. So in M Pleasant for example

57:00there's an enormous basement in the

57:02entire thing. we can't use a lot of it.

57:04So, we either got to we still have to

57:06put lighting down there. You still got

57:07to put some kind of heat down there. So,

57:09you're you're you're putting money into

57:10spaces that you're not using for

57:12education usually when you're doing

57:13renovation for a number of there's

57:15actually an attic there too that has to

57:17have a sprinkler system in. So,

57:19renovation usually is not the best

57:21method. Uh but for Mount Pleasant, I

57:24think this hybrid approach was a better

57:26method because you got to keep an

57:27important part of history and you you

57:30got to add on at the same time. and and

57:33use it as swing space. So if there's not

57:36a lot of high school swing space that

57:38was available for us to move a thousand

57:41students um to be able to do that knock

57:43down and build it new.

57:51So on the last page of Mount Pleasant,

57:52you can just see some of the pictures of

57:54so the the two bottoms left and right

57:57are kind of the new phases where they're

57:59building inside and renovating and

58:01putting new walls up in there, a new

58:03ceiling, the doors. And then in the back

58:05of the building is a small addition

58:07that's coming as well. That's the steel

58:10you see up there.

58:15And then moving on to West Broadway,

58:17another bigger project with that's an

58:20$84.5 million budget. 996

58:23uh student enrollment estimated and it's

58:26again it's another four track four

58:27track. So prek through 8 is four

58:30classrooms.

58:33They are temporarily housed at Carl

58:36Laur.

58:38And going to the project at a glance

58:40schedule is very well on track. budget

58:43is on track and we do have a draft GMP

58:46of the 78.4 and they are about 80%

58:49bought out.

58:51Similar um situation as far as pick key

58:54milestones with the dry in a post

58:57construction building complete project

58:59close out and then similar to the other

59:02projects the milestone trackers which

59:04the building dry in permanent power is

59:06always a big one

59:08system startups and again although the

59:11project's getting done and a certificate

59:12of post construction is going to get

59:14issued on June 30 27 the actual MOA says

59:18that the project must be done on or

59:19before December mber 31st, 2028. Um, and

59:23we are out currently procuring furniture

59:26and technology. So, we'll have a better

59:28handle where we are with that budget in

59:30the next

59:35photos. You can see very all the

59:37projects are in very similar um

59:40situation as far as schedule. You got

59:41steel up, you're starting to enclose

59:43your building. Um, but they're all

59:46pretty much on track.

59:50And the part K is the last one. Any

59:52questions on before I move on to RK?

59:55I think RK

59:58is a 77.7 million budget. Um student

1:00:01enrollments 868 to all new construction.

1:00:04So we took down the um existing building

1:00:08and the rec center that was attached.

1:00:11They are at Hopkins right now.

1:00:17though project at a glance the schedule

1:00:19is slightly behind. They are in the

1:00:22market right now trying to procure um a

1:00:24more I guess aggressive schedule. Um so

1:00:28far they've been very successful. We'll

1:00:30know in the next week or two when they

1:00:31finish their subcontractor buyout. You

1:00:33can see they're only 70% so we're a

1:00:35little lary until they get closer to 80%

1:00:37that they have buy in from their

1:00:39subcontractors that they can meet the

1:00:41schedule. Um and they are right on

1:00:43target with their uh their KMP as of

1:00:45today.

1:00:47Uh they're building dry in as you can

1:00:48see it's a little bit delayed because

1:00:50they got started about three to four

1:00:51months later than everybody else because

1:00:53this project uh was part of the phase 4

1:00:55and then get pulled forward. Um we are

1:00:58tracking our certificate of post

1:01:00construction for June 30th uh just based

1:01:02on the uh we believe that they can by

1:01:05this aggressive schedule but we will

1:01:06keep everybody updated. Um they're

1:01:08looking right now for a building

1:01:10complete late August, early September um

1:01:13with a project close out of January

1:01:152028.

1:01:17um that uh we have similar milestones as

1:01:21you can see the structural steel and

1:01:22slab because it's not complete it's a

1:01:24milestone that we're tracking but then

1:01:26everything else is the building dry in

1:01:27the permanent power the MEP and again

1:01:30you could see your certificate of post

1:01:32construction although we're tracking and

1:01:34trying to get the the project done by

1:01:36June 30th 2027

1:01:38um that right MOA does not expire to

1:01:43June 30th of 2029 so we're two years

1:01:46ahead of back before we have any.

1:01:48Obviously, again, because of funding, we

1:01:50we definitely want to get it done and

1:01:52get it um you know, the post

1:01:53construction certificate um completed um

1:01:57so that we could the city could start

1:01:59obtaining first amendment.

1:02:01>> Uh

1:02:03why did

1:02:05move forward? [clears throat]

1:02:08>> I think it was uh it was based on a need

1:02:10by PPSD. if they had an opportunity to

1:02:13pull one of the projects forward, what

1:02:15would it be? And I think that they had

1:02:17uh numerous issues with the RFK facility

1:02:20and that was it was a couple that they

1:02:22had outlined at one point and I think

1:02:24RFK was the one that they eventually

1:02:25landed on as the right one to start

1:02:27moving forward. It was one one that was

1:02:30easier because it was going to be a

1:02:31demolition, right? So, you know, you're

1:02:33going to move out and that they could

1:02:35move not too far away to Hopkins. They

1:02:38could house it. I think there was a

1:02:39couple of reasons behind it. was the

1:02:41main like factor

1:02:43uh or financial out of it or I guess

1:02:48like what what the what the main purpose

1:02:49behind the question is that this is

1:02:52behind schedule um when it was not meant

1:02:56to to be on this schedule to begin with.

1:03:00So just I guess like when it when it

1:03:02comes the main concern anything that

1:03:04that we're expecting is obviously kids

1:03:07not having you know safe warm you know

1:03:11to learn. Um but then secondly uh the

1:03:15financial implications of this city. Um,

1:03:19so I I just want to make sure there's no

1:03:22uh financial concerns

1:03:24uh with this project right now

1:03:28um that we should not be first or should

1:03:31be aware of.

1:03:34>> So the decision was made because Hopkins

1:03:37was available for swing and the district

1:03:40wanted to,

1:03:43you know, get as much done as early as

1:03:45possible. a lot of encouragement from

1:03:48RIDE to get as much done as early as

1:03:49possible. As it relates to the delay,

1:03:52the impact will be a delay in housing

1:03:54aid reimbursement, which Crystal can

1:03:57speak to, you know, in her debt

1:03:59projections about what that does to the

1:04:01budget.

1:04:02>> Yeah. So, my current projection is

1:04:04assuming that the the RFP school will

1:04:07not finish on June 30th, 2027. Um, and

1:04:10so we're not, you know, at this point

1:04:13anticipating housing next fiscal year

1:04:15related to this project completion. One

1:04:18of the things we've been actively

1:04:20working on is trying to make sure we're

1:04:23being very nimble when we're borrowing.

1:04:25So, we're not doing the kind of easy

1:04:27thing, which is just borrowing $400

1:04:29million today to get projects done. We

1:04:32are actively working with the OPMS on

1:04:34cash flow for both phase two and three

1:04:36and then also phase four to see when

1:04:38we're going to need to strategically

1:04:39borrow so that we're hopefully right now

1:04:42things all stay according to schedule.

1:04:44We're going to be at a place where we

1:04:45are borrowing and immediately receiving

1:04:47the debt service reimbursement when the

1:04:49debt comes online on our books. Um with

1:04:52that said, it's you know we're keeping

1:04:54our fingers crossed and it's a constant

1:04:55monitoring. I think this is version five

1:04:58that I've done in the past 12 months of

1:05:00way more borrowing and how we're

1:05:01borrowing. Um, but that is something

1:05:03that's really critical and that's what's

1:05:05going to make this quite frankly

1:05:06possible. Like I don't to your point I

1:05:08don't know that we could afford

1:05:09borrowing $600 million today having to

1:05:12absorb that debt service for four years

1:05:14and then get a windfall once all of

1:05:16these projects come online. Um, so

1:05:18really working with Ride and I have to

1:05:20say they're um, the gentleman over there

1:05:23who works on housing aid has been like

1:05:25my best friend. We're on the phone all

1:05:26the time. Um, and and really trying to

1:05:29be thoughtful about when we're borrowing

1:05:31has been really beneficial to the city.

1:05:34For example, like the $140 million we're

1:05:36borrowing right now. We were able to

1:05:38stagger that in a way where we are

1:05:41literally closing tomorrow and using

1:05:44that bond to pay a portion of our

1:05:46September invoices because we did time

1:05:49it so tight that we would be able to not

1:05:52have to pay a full year of debt service

1:05:53this year for something that was not

1:05:56going to be complete until the end of

1:05:582027.

1:06:04I appreciate your

1:06:10council leaders and then we'll pile.

1:06:14>> Thank you. Um

1:06:17separate to this separate to my question

1:06:19I one thing I want to ask

1:06:22um can we get a a list of the current

1:06:26enrolled I just want to understand how

1:06:28much enrollment we have in the school

1:06:30currently um because these projects are

1:06:35large the number going that we're

1:06:37expecting for these projects is to be

1:06:39large and I'm looking forward at what

1:06:44happens in the future our enrollment is

1:06:46we'll move from there. So that's just a

1:06:48standard thing but as regards to RFK um

1:06:54you said slightly behind

1:06:56and

1:06:58my neighbors have tracked how behind we

1:07:00are to the tune of three or four months.

1:07:03I don't know if that is actually

1:07:05correct. I'm just saying perception is

1:07:07is that we're pretty pretty behind the

1:07:11ball and I don't know that we even

1:07:13achieve a structural stless on by

1:07:16December 2026 depending on our goal is

1:07:18going to get pretty soon and things like

1:07:20that. So I'm a little bit concerned

1:07:22about this projected timeline um and

1:07:24what the implications with this

1:07:26particular project. Um

1:07:30can you tell me broadly how behind you

1:07:33are and also um well let's start with

1:07:36that.

1:07:37>> Yeah. So I would say um although they

1:07:40keep tracking that they are about a

1:07:43month behind.

1:07:44>> I would say they're probably two to

1:07:45three months behind.

1:07:46>> Um and keeping in mind that they didn't

1:07:49get started until three or four months

1:07:50after everybody else. Right? Because we

1:07:52did reprogramming of the prek8. They

1:07:55came in late on that and then they had

1:07:58our redesign. So I would say they're

1:08:01probably two to three months behind. Uh

1:08:04if we have a harsh winter like we had

1:08:05last year, that three months could turn

1:08:07to four months very easily because one

1:08:09day of snow usually turns into two or

1:08:11three days of cleanup. So it's it's not

1:08:14a day for day delay. It's usually a two

1:08:16to three day delay. Um so we are

1:08:19concerned as well and we've been

1:08:20tracking it. we've we've all been

1:08:22talking about, you know, our concerns

1:08:24with it, but I I would I wouldn't

1:08:26hesitate to say too early right now.

1:08:31>> Can you explain why?

1:08:34I know that they were leaving their

1:08:35project, but we never actually

1:08:36understood um from the individual

1:08:40perspective why like we just thought

1:08:42that there was no worker.

1:08:43>> Yeah. So what happened is in 20. So

1:08:46they're another team. They bid a RFK

1:08:50project that was not the RFK project

1:08:52they're they're building right now,

1:08:53which is what happened to all of our

1:08:55design build teams. They bid a stage two

1:08:58that was submitted, approved by the

1:09:01building committee, by the council, by

1:09:03RIDE, and then a year later, Ride, NPSCD

1:09:06came back and said, "Well, these

1:09:07standards really don't work as well."

1:09:09Right? So we went back, they started

1:09:11reprogramming, we worked together to do

1:09:14that reprogramming. So the building that

1:09:17was originally proposed in the new

1:09:19building is about the is now about 20 to

1:09:2130,000 foot big, right? All all good

1:09:24good, right? Because ultimately you want

1:09:26the biggest and best building you can.

1:09:28So that delayed them because they had a

1:09:30set of documents they had bid and they

1:09:32were preparing to continue their design

1:09:34and they had to literally go back to the

1:09:36drawing order. In addition to that,

1:09:39during the summer of

1:09:43the fall or spring and summer of 25, I

1:09:46think we had some conversation about the

1:09:47rec center. Remember, originally that

1:09:50rec center was was slated to remain and

1:09:53it was going to be very difficult to

1:09:55renovate that little place and keep it

1:09:57there because it was really attached to

1:09:58the building. So, there was a probably a

1:10:00threemon period of time where we asked

1:10:02them for analysis. what's the cost to

1:10:05leave it versus the cost to just tear it

1:10:08down and building it. So ultimately it

1:10:11was almost a net zero. It was a couple

1:10:13hundred,000 more to just build new. Um

1:10:16so the new building now is going to have

1:10:18a new rec center. It's going to have its

1:10:19own separate vestibule for the rec

1:10:21center as opposed to just walking in the

1:10:23gym as we all know we used to do before.

1:10:25So those kind of things played into it.

1:10:27I think they they are responsible for

1:10:30some delays that happened with demo and

1:10:32abatement. I think there was some issues

1:10:33with department of health and they just

1:10:35didn't handle it well which delayed

1:10:36them. Um so those I would say those are

1:10:39the big three things like they didn't

1:10:40nothing big on site impacted them like

1:10:43cuz they're in where they hit some soil

1:10:45or something.

1:10:50>> Thank you chairman. I have a couple

1:10:51questions in regards to start with the

1:10:54delays. What um construct like what cost

1:10:57and impact did it have to the

1:10:58construction costs? with you know

1:11:00inflation happening if any some of these

1:11:02delays how's that affected the budget

1:11:04having these delays going

1:11:07>> I I could say we've been fortunate I can

1:11:09tell you from our perspective all of

1:11:12these projects and I could and like I

1:11:14said Fogerty Lima all started at a

1:11:17significantly smaller budget and we had

1:11:20design build contracts none of we did

1:11:22not allow any of those contractors to

1:11:24increase their cost their personal fees

1:11:27are contractual so those

1:11:29But as far as other costs, we didn't

1:11:31long to do that. So on a square footage

1:11:33basis, we utilize basically the same

1:11:35square footage price that they bid to

1:11:37increase the size of those buildings. So

1:11:39incrementally, any of those delays did

1:11:42not increase any cost force. Those were

1:11:45absorbed in either um the design,

1:11:49working together better as a team with

1:11:51the design or in the subcontractor

1:11:53market going out and getting more

1:11:55competitive numbers. Um I can't think of

1:11:58any delay. The only the only delays or

1:11:59impacts we are seeing and it's and it's

1:12:02odd because we're just starting to see

1:12:03it is steel because of the 100% tariff.

1:12:06We had steel just recently stuck on the

1:12:09other side of Canada and there's an

1:12:11impact there. Outside of that, we have

1:12:15worked diligently on behalf of

1:12:17Providence to make sure that those costs

1:12:20did not impact the actual cost of the

1:12:22school. We made those teams go back

1:12:24negotiate better numbers with their

1:12:25subcontractors work on being on more

1:12:28efficient designs. Um those kind of

1:12:30things are what we did.

1:12:32>> Thank you Joe question.

1:12:35>> Um just trying to get an understanding

1:12:37of these milestone deadlines. So again

1:12:39if we go back RFK was advanced from

1:12:42phase 4.

1:12:43>> Correct. Now um I see the milestone here

1:12:46for June 30th is for the certificate of

1:12:47post construction but the reimbursement

1:12:50agreement milestone is in 2029 which is

1:12:53aligned with page to do the phase 4

1:12:55correct line. So this project is

1:12:58tracking to have the same basically

1:13:00deadline as the phase for project stand

1:13:03even though it's going to be complete in

1:13:06September 2027 the financial

1:13:08reimbursement deadlines if we don't hit

1:13:10it it's just like a year delay basically

1:13:12>> it be a loss of eligibility it'll just

1:13:14be a delayed reimbursement

1:13:16>> if for some awful reason this went

1:13:19beyond June 30th of 2029 and we were not

1:13:22able to get an extension from Ride it

1:13:24would be ineligible

1:13:26That's what that day means is like this

1:13:28is the last day we can complete the

1:13:30project in order for it to be eligible

1:13:32for reimbursement.

1:13:33>> So if it doesn't hit the 2027, it would

1:13:35just be a a delay on it.

1:13:36>> It would just be a delay in when we

1:13:38receive it. And again, that's where

1:13:39we're trying to really make sure that

1:13:40I'm not borrowing in advance of that

1:13:43project completion. And it requires

1:13:45quite a bit of conversation back and

1:13:48forth with Joe and those teams to make

1:13:50sure that we're in finance aware of like

1:13:53Joe here. I mean, in May, that's all

1:13:55we're talking about is housing aid to

1:13:56make sure that like I'm aware that we

1:13:58are budgeting for the correct number

1:14:00that the projects we were anticipating

1:14:02completing in the fiscal year are on

1:14:04track. Um, and so make and then signing

1:14:07up on those forms so that we can make

1:14:08sure we are again not in a place where

1:14:11we are paying out an inordinate amount

1:14:13of debt service while we're waiting for

1:14:14projects.

1:14:16Think

1:14:22that concluded. I had some pictures on

1:14:24the RFK at the end and that concluded my

1:14:27presentation. Um, does anyone have any

1:14:29questions for Joe?

1:14:37Um my question uh take that back.

1:14:42Um so in terms of uh

1:14:47cash flow for projects in phase three

1:14:52um sorry Crystal we're probably getting

1:14:55a little bit

1:14:56>> that's okay. Um,

1:14:59so is is there any cash flow or good

1:15:01concerns at this moment for any of of

1:15:04these projects?

1:15:05>> No, not at this time.

1:15:06>> Not at this time.

1:15:07>> No, we um like I mentioned, we are

1:15:09closing on the $140 million bond

1:15:11tomorrow. We are anticipating that that

1:15:13should be enough cash to get us through

1:15:15July of 2027. We're going to be

1:15:17monitoring that. So, if it's looking

1:15:19like cash is getting low, we need may

1:15:20need to expedite our timeline, but we

1:15:22are hopeful that we can close as early

1:15:25as possible in July of 2027 to kind of

1:15:28pay up all those June bills that are

1:15:30inevitably going to arrive in July. Um,

1:15:32that also gives us the benefit of

1:15:34pushing that first debt service payment

1:15:35out an entire fiscal year, which is why

1:15:37we always try to borrow in July where

1:15:39possible. Uh, so at this point in time,

1:15:41I do not have concerns about cash flow.

1:15:43Um,

1:15:45I would certainly bring them to your

1:15:46attention, but part of not having that

1:15:48concerns is this constant monitoring of

1:15:51ensuring that, you know, our fiscal

1:15:53agent or our our uh budget analyst for

1:15:55capital project like every month is

1:15:57looking at that bank statement, looking

1:15:59at reconciliations, projecting based on

1:16:00what she's previously spent, what she'll

1:16:02need for the upcoming years, comparing

1:16:04that to our projections from the OPMS.

1:16:06Um there's been a lot of work done

1:16:09internally in finance to make sure that

1:16:11we can be nimble because there is

1:16:13exposure if we get it wrong. Um and so

1:16:16we're wanting to make sure that we have

1:16:17all of our our ducks in a row and have

1:16:19done all sorts of checks and balances to

1:16:21make sure that that does not happen.

1:16:22>> So thank you for that. Um $100 million

1:16:26bond

1:16:28uh

1:16:29>> so tomorrow we're closing on $140

1:16:30million

1:16:32uh and that should fund us through the

1:16:34spring and into the summer.

1:16:36Uh, and then we're right now looking

1:16:39like we're going to need to borrow

1:16:40another hund00 million in July of 2027.

1:16:49>> 140 million shared

1:16:54through June. Correct.

1:16:56>> Correct. [clears throat]

1:16:58>> June or

1:17:00June?

1:17:01>> Well, June cash flow probably

1:17:03>> or May. Well, it depends on when these

1:17:06vendors submit their invoices. It's

1:17:07always different timing, right? I'm I'm

1:17:09a contractor. I'm going to do my work

1:17:11for the month of June. I'm going to

1:17:12reconcile that. I'm going to send you a

1:17:13bill in July. Um, so I'm expecting the

1:17:16cash that we would need to outlay in

1:17:18July will be there when we close on that

1:17:22bond. And it will likely be for work

1:17:24performed in May and in June and

1:17:27probably even July. Um, there is

1:17:29commissioning and work that does go

1:17:30beyond the substantial completion date

1:17:32and so we see that pretty regularly.

1:17:34Well, just because the building is done

1:17:36does not mean we're done paying bills on

1:17:38that building. So, we don't necessarily

1:17:39need to have 100% of that budget in hand

1:17:41at that point in time. Um, which is why

1:17:43we are able to again hopefully extend it

1:17:46to July right now. That's where the

1:17:48projections at. If we had to escalate

1:17:51it, then we would be looking at a

1:17:53potential debt service item we would

1:17:55need to think about for the 2028 budget.

1:17:57we are early enough to budget and plan

1:17:59for it. But um that is one of the risks

1:18:03if we kind of

1:18:06somehow speed things up even more than

1:18:08we already are. But at this point I

1:18:09don't think that that's a risk we're

1:18:11going to be facing.

1:18:13>> Cool. Um in terms of invoices, um how

1:18:17does that how does that work? Are those

1:18:20done through

1:18:22uh the subcontractors? Is that only

1:18:24through you those or like the over.

1:18:28>> Yeah. So on our projects, the

1:18:29subcontractor's bill, the construction

1:18:31manager, design build team, they submit

1:18:34that to us for review. Um we have our

1:18:36comments, whatever. We make our

1:18:38recommendation. Then we take those and

1:18:40submit them to the city.

1:18:43Um and then there from there our our

1:18:46staff um runs them through Watson which

1:18:49is our ERP system and creates a

1:18:51requisition to the bank which then gets

1:18:52signed off by the finance director goes

1:18:55over to the bank and the bond pays those

1:18:56things directly.

1:19:04>> Thank you. Based on that, um, are we

1:19:08planning to going out and inspecting

1:19:10reviewing everything that's kind of

1:19:11being invoiced over to make sure that

1:19:13everything is compliant and all that

1:19:15stuff is happening as heading forward.

1:19:19>> We have a we have a team of 18 people.

1:19:22uh two individuals are tasked with just

1:19:25going to the site every single day and

1:19:28each one of them has a project manager

1:19:30that's assigned to it and they're the

1:19:31ones that are they're inspecting for the

1:19:33invoice and project executives. So

1:19:35there's at least four and there's an

1:19:37assistant project manager. There's

1:19:38usually four members of for each project

1:19:41that are doing that work.

1:19:43>> And do we do that part on the city side

1:19:45as well? like just to make sure that

1:19:47there's some sort of

1:19:49>> I don't know how efficient like I'll be

1:19:51honest I don't know that we have the

1:19:52expertise to even do that inhouse. Um

1:19:55some of these draw down requests are are

1:19:58like a 100 pages long of subcontractor

1:20:00things that you know our capital bond

1:20:03analyst is great at accounting but

1:20:04understanding in the weeds of like what

1:20:06has been done regarding an invoice is

1:20:08not necessarily the role of finance in

1:20:10general. um we rely on project managers

1:20:13in this case our OPM to make that

1:20:15decision on our behalf and that's the

1:20:16case with any capital project. So, for

1:20:18example, if public property is working

1:20:19on a capital project, they submit an

1:20:21invoice. They've attested that these

1:20:23services have been gone. Finance is not

1:20:26necessarily like pulling that bill,

1:20:27calling like doing an inspection to make

1:20:29sure that that's happened. That's not

1:20:31necessarily our role. That's the role of

1:20:32the project manager to validate and sign

1:20:34that yes, the work I'm approving has

1:20:36been done and is in accordance with the

1:20:37contract.

1:20:38>> Sure. From the finance perspective, I'm

1:20:40actually talking about the actual

1:20:41property perspective. I'm not saying

1:20:42that nobody's doing anything. I'm not

1:20:45saying that anything is going above and

1:20:46beyond, but I'm just saying that if

1:20:47we're getting invoiced for something now

1:20:50is telling us, "Yep, we're good to go."

1:20:52That anybody's just going to I mean, I

1:20:54love that we're have a wonderful

1:20:56relationship with the company, but is

1:20:59everything up to par. Is public property

1:21:02going in saying, "Hey, actually, you

1:21:04know, we're reviewing this and it

1:21:06doesn't seem like this is actually based

1:21:08on what we've already approved. Does it

1:21:10actually look like this is legit? Is

1:21:12there something that we can do? Just add

1:21:13the digital oversight in terms of these

1:21:15big big projects and we're going to be

1:21:18housing some of our our most important

1:21:21constituents in there. I just want to

1:21:22make sure that from the perspective of

1:21:24the city, we're also taking into account

1:21:25what other performance measures we might

1:21:27need to based on.

1:21:31>> Yeah, that's the that's the contractual

1:21:34role of an OPM. So if the city wanted to

1:21:37bring that inhouse

1:21:39>> and not hire an OPM, then public

1:21:41property could hire the people that

1:21:43would do that. But because we have an

1:21:45outside owner's project manager, we're

1:21:47basically just, you know, the city is

1:21:50using Downs or left field to do that

1:21:53work on our behalf. Okay. Thank you.

1:21:58>> Um

1:21:59I don't want to speculate. Um but I uh

1:22:06tuned in to a couple of the school

1:22:07building community meetings uh recently

1:22:10and there was uh topics of concern with

1:22:14ride uh invoices

1:22:16uh to not get into Louisa where what's

1:22:19the current stage of any uh concerns

1:22:23that you might have with invoicing at

1:22:26this point that could that be clear

1:22:28where where we at

1:22:30I

1:22:32who that question is addressed.

1:22:35>> Uh I could take a stab at it. So um we

1:22:37have received RID's request for

1:22:39information. Um it is due tomorrow and I

1:22:41will be sending that over to ride

1:22:42tomorrow morning

1:22:44>> and there was a question about D's

1:22:46invoicing.

1:22:47>> Y

1:22:48>> that DS did reconciliation with finance

1:22:51and I think what was the dollar amount

1:22:53of discrepancy that was found

1:22:56>> was four hours for one person over six

1:22:59month period of time.

1:23:00>> Yeah. [clears throat] What's the dollar

1:23:02on it?

1:23:04>> Less than $1,000.

1:23:07>> And and in and true transparency, our

1:23:11contract does not say that we could only

1:23:13build up to 40 hours a week.

1:23:15>> So we we we on our own behalf only bill

1:23:18you up to 40 hours a week, but our

1:23:21contract is a rate. And if we we really

1:23:24followed the contract, if we worked

1:23:26because a lot of our our my staff works

1:23:28on Sunday or Saturdays when they're out

1:23:30there working fee, one individual build

1:23:33for that Saturday to there over a three

1:23:35or four month period of time. Um but our

1:23:38contract is not clear and does not say

1:23:40that we could only build 40 hours. We've

1:23:42taken that as being a responsible

1:23:43contractor saying most of our employees

1:23:46are salaries so we're only going to bill

1:23:47you 40. Um, so it was an oversight of

1:23:51four hours over a six month, three, six

1:23:54month period of time that added up to I

1:23:57don't even think it was $1,000. It was

1:23:58probably

1:24:00$400 or $500.

1:24:02>> Yeah, I I would I would share that's

1:24:06kind of the same uh sentiment that I've

1:24:09come to conclude with those concerns.

1:24:12Um, obviously keep an eye on it going

1:24:14forward. Um, but that's kind of where

1:24:17I'm at with that one. Uh, any other

1:24:20questions uh for circumstances?

1:24:24I have one more time. Um, Joe, with all

1:24:28these projects tracking towards, you

1:24:30know, next year summer completion 2027.

1:24:34Um, can you just define the committee

1:24:36what RI defines as substantial

1:24:39completion in order to meet the

1:24:41eligibilities for the reimbursement?

1:24:43Also, when you guys are turning these

1:24:45buildings over, what does that look

1:24:47like? What are the inspection, the

1:24:48commissioning, [clears throat]

1:24:50>> um, you know, technology, swing space

1:24:52for PBSD? How are we communicating that

1:24:54to sequence swing spacing? Like what

1:24:57does the project turnover look like with

1:24:58substantial completion? Okay, so I'll

1:25:00answer the first part first about the uh

1:25:02the ride post construction certificate.

1:25:05Uh, typically that means a certificate

1:25:07of substantial completion, which is the

1:25:09contract definition. That means the

1:25:11building is done for its intended use.

1:25:13Doesn't mean every floor is in place.

1:25:15Doesn't mean every walls in paint been

1:25:17painted. It means the building is done.

1:25:20Windows are in for the most part. Doors

1:25:23are in. You could use the building. They

1:25:24might be testing the fire alarm. The

1:25:27electrical is turned on. Those kind of

1:25:29things are done. Can you maybe you don't

1:25:32have furniture in there yet. Um those

1:25:34are the kind of things um that are

1:25:36substantial completion. Um so that's the

1:25:39definition pretty much uh of that. Um

1:25:42and then um as far as the building

1:25:44turnover um you know as some lessons

1:25:47learned we just talked about this

1:25:48actually at the building committee about

1:25:49moving some lessons learned on the

1:25:51turnover was you know we work with PBSD

1:25:55to make sure that we give like a month

1:25:58uh buffer in between when the students

1:26:01move in and when they can come in and

1:26:02start getting the building ready

1:26:04operationally. So, in other words, they

1:26:06have to come in, they have to do some

1:26:08stuff technology-wise, right? They have

1:26:09to put their Wi-Fi in, they have to put

1:26:11certain things in, they have to start

1:26:13bringing ABM in to be familiar with the

1:26:15building. Uh, we do that transition. So,

1:26:18we're we're looking at an August

1:26:19occupancy. We usually try to do that

1:26:21transition starting in mid July. So,

1:26:24there's a six week. In some cases, we

1:26:27may not have that six week. We may only

1:26:29have four weeks, but we always make sure

1:26:30that there is some kind of buffer. And

1:26:32at that time you know we are usually

1:26:35transitioning where furniture is being

1:26:36moved in at the same time so that there

1:26:38is some interaction with PPSD anyways

1:26:40when as we bring furniture in um the

1:26:43technology is being installed at the

1:26:44same time by vendors but there's also

1:26:47usually the the PPSD IT person because

1:26:50there's some proprietary stuff that they

1:26:52have to do for switches and stuff. So

1:26:53we're working together during that time

1:26:55period. commissioning is happening at

1:26:57the same time to make sure that the

1:26:59building is working uh appropriately and

1:27:02properly and as designed. Um and there's

1:27:05conflicts going on. There's usually

1:27:06those couple walls that are being

1:27:08painted. There's floors that are still

1:27:09being installed. This kind of thing.

1:27:12>> So I'll say the decision was oh this

1:27:14door might not be this really that's

1:27:17normaliz that's that's normal because

1:27:19throughout the course of any

1:27:20construction there's always going to be

1:27:21a door that's got lost somewhere got

1:27:24broken. There's always going to be some

1:27:25glass that got broken. There's always

1:27:26going to be a wall that got marked up or

1:27:28a leak happened because they're testing

1:27:30the system out and they have to repaint.

1:27:33That's that transition period. That's

1:27:34why we don't want the buildings to be

1:27:36done on August 30th. When we say the

1:27:38building to be done on August 30th,

1:27:39there's that six week transition where

1:27:42the contractors are on site starting the

1:27:44systems up, making sure the heat works,

1:27:46making sure the air conditioning work,

1:27:48making sure all the lights work. They're

1:27:49going to find out something's going to

1:27:50happen, right? So that's that

1:27:53transition. So when you hear like a door

1:27:54is missing or something's missing, it

1:27:57usually means something happened. Either

1:27:59it got delayed, it got broken, something

1:28:02happened at the end.

1:28:04>> Thank you.

1:28:11>> Thank you so much.

1:28:12>> Thank you.

1:28:15Chris, I am going to leave.

1:28:24>> Would the council like me to sit here or

1:28:26may I stand and present?

1:28:36They have crystal.

1:29:27I know. We did something.

1:30:01Uh motion to Enter exhibit two to the

1:30:05record. Motion by councel, second by

1:30:08councel. All in favor.

1:30:22>> Are you going to do a stand up?

1:30:23>> That's okay. My hands

1:30:26afraid.

1:30:30>> We would have a serious problem.

1:30:33She knows everything.

1:30:41>> Yeah.

1:31:22Good morning.

1:31:38Praise

1:31:43the glory of yours.

1:31:47>> Members of the committee, thank you so

1:31:48much. My name is Christopher Spiegel.

1:31:51I'm project executive with left field.

1:31:52I'm also the managing director of left

1:31:54field and geographic. I have two

1:31:56colleagues with me today who are also

1:31:58leading this project.

1:32:00>> Liliana left field.

1:32:06Um, in addition to Andy, Liliana, as uh,

1:32:08as Ben and everyone knows, we have a

1:32:10substantial team uh, dedicated to this

1:32:12project, including experts that are

1:32:14specifically tied into mechanical,

1:32:16electrical, and plumbing. And as the

1:32:18projects move further into design, we're

1:32:19bringing on another staff of project

1:32:21managers and clerks of the works, your

1:32:23points earlier about who checks to make

1:32:25sure that we're paying for what's on

1:32:27site. Those are the clerks of the works,

1:32:29and we'll be on joining them relatively

1:32:31soon. Um, I had another chance to

1:32:34myself. So, um, again, my name is

1:32:37Spiegel. Um, I've been an OPM

1:32:39specifically working in Rhode Island the

1:32:40last 10 years. Uh, Rhode Island in terms

1:32:43of our Nebraska island, we currently

1:32:45have $1 billion worth of school

1:32:47construction construction and this

1:32:50project represents another $42 million

1:32:52of design with building

1:32:55on the agenda today.

1:33:03Ah uh you will talk a little bit about

1:33:06community schools 2030 mission and

1:33:08progress today

1:33:10basis three so I won't take up too too

1:33:13much of your time we'll talk about phase

1:33:15four timeline we'll talk about the

1:33:16priorization requirements compulation fe

1:33:19studies and then we'll give a little bit

1:33:20of stakeholder engagement um I have

1:33:23prepared a number of slides here at the

1:33:25back of the presentation specifically to

1:33:27address questions that we've heard at

1:33:29SPC or the pile health and that's a

1:33:31message to us that you're prepared

1:33:33council grade some of those questions

1:33:35relate directly to the renovation cost

1:33:37at green as you requested at the last

1:33:40school board

1:33:41>> is that you saying the same questions

1:33:43towards the end

1:33:44>> no

1:33:48context the 23rd vision with over $1

1:33:51billion in funding this is that once in

1:33:53a lifetime generational investment to be

1:33:56able to invest in our students to not

1:33:57just receive our base reimbursement rate

1:33:59but also a bonus point which should be

1:34:02over 10% which represents a $46 million

1:34:05savings to the city of province that

1:34:07those taxpayers here taxpayers do not

1:34:09have to pay.

1:34:11We will leverage instruction to improve

1:34:13outcomes through prek extension and

1:34:15prepaid donations stay and early access

1:34:18to high quality programming as well as

1:34:20ensure high quality learning

1:34:21environments for all students. This

1:34:23context 2030 was development outside of

1:34:25our building project. However, it

1:34:27influences and it absolutely has an

1:34:29effect on how we look at prioritization

1:34:31and how we address those projects that

1:34:33Joe did. So, in terms of progress today,

1:34:36Joe did a great job. As you can see,

1:34:38phase one and constructing phase two and

1:34:40three,

1:34:42then we'll talk about our phase four

1:34:44timeline. In the winter and spring of of

1:34:4624, PPSC identified phase four projects

1:34:49and submitted stage two. Now, as Gerald

1:34:52put it, what we put into stage two very

1:34:55often changes between what is actually

1:34:57designed in double stage three. A couple

1:35:00examples that show were originally a $33

1:35:02million project moved up to an $80

1:35:04million project. This is very common to

1:35:07go through these MOA adjustments and the

1:35:08reason for that is that your stage two

1:35:10is designed with as much flexibility as

1:35:12possible. is to maximize your

1:35:14reimbursement rate and then during the

1:35:16stage three where left field is

1:35:17currently in we refine those solutions

1:35:20and make sure that the solution that

1:35:21we're that we're pushing forward that

1:35:23will recommended meets a number of

1:35:25objectives that will we'll go through

1:35:27this process. So in winter spring of

1:35:292024 that's stage two was submitted.

1:35:32They went through all of the all of the

1:35:34recommended project approvals and then

1:35:36the fall winter of 2025. Phase four

1:35:39projects were prioritized between phase

1:35:414 A and 4. We were brought on

1:35:45technically February is when we uh or

1:35:47shoulders proceed and left field has

1:35:49been working on this phase 4 project

1:35:51since then. I want to clarification

1:35:54right here which we'll go into a little

1:35:55bit later but we're talking about

1:35:57differences between our approval our

1:35:59reimbursement from the state and our

1:36:01cash flow. There is a delta and what our

1:36:04reimbursement rate is which is 469

1:36:07million to what our cash flow which is

1:36:10roughly about 400 million. So despite

1:36:13everything that we were going through,

1:36:15these projects were always going to have

1:36:16to have some rep prioritization

1:36:18associated with them above and beyond

1:36:20what Joe Sandy talked about in his

1:36:21presentation, which is it's very typical

1:36:23through this process for us to realign

1:36:25based on lessons learned where our

1:36:27funding is the project environment and I

1:36:30can get into that. We are currently here

1:36:32meeting community engagement on the

1:36:33phase four projects and we've um begun

1:36:36our schematic design process and I'll

1:36:38touch base a little bit more where we

1:36:39are coming winter 2026 and beyond

1:36:42continuing our design continuing our

1:36:44engagement continual

1:36:53purposes. Um, you're talking about

1:36:56stages. Um, how many how many stages?

1:37:01So, are the stages attached to a phase

1:37:04or are they attached to an individual

1:37:06project?

1:37:06>> That's a great question. So, the ride

1:37:08process is five stages and those stages

1:37:11apply to all of the projects. Stage one

1:37:14is where you define your problems. So,

1:37:16that's your facilities conditions

1:37:17assessment. It's when you go through all

1:37:18your buildings, you look at your

1:37:20enrollment projections, and you say,

1:37:22"These are the issues that we're

1:37:23currently having." Stage two is where

1:37:25you take that information you gained

1:37:27during the phase one, and you develop a

1:37:29number of solutions to that. You haven't

1:37:32fully decided on what your solutions

1:37:34are, but the intent is to provide you

1:37:36with as much flexibility as possible so

1:37:38that during stage three, you can res

1:37:40refine all of your assumptions and move

1:37:42forward with the set of prioritized

1:37:43projects. That was done in phase two. It

1:37:46was done in phase three. We are

1:37:47recommending moving forward in phase

1:37:49four where there has been a project um I

1:37:52worked on in Rhode Island where MOA

1:37:53alignment was not required to some level

1:37:56because budgets set two years before

1:37:58construction start things change

1:38:00especially COVID tariffs material price

1:38:02increases enrollment changes so you you

1:38:05have to nimble and adapt.

1:38:07>> Did I answer your question?

1:38:08>> Yeah. So the original phase 4 MLA and

1:38:12these are all the projects was new

1:38:14builds are like new at the following

1:38:16schools restore to new at the following

1:38:19schools. So this is what we originally

1:38:21presented

1:38:24and then what we did from there was we

1:38:28were tasked by PPSD and the Sydney

1:38:30Providence to go through feasibility

1:38:32studies. These feasibility studies took

1:38:34a look at the stage two. They took a

1:38:36look at all of the other information

1:38:37that has happened since that stage two

1:38:40and we've developed a system for us to

1:38:43really give PBSC a full overview of what

1:38:46is going on to schools and potential

1:38:48ways to so don't have to get into exact

1:38:52principles but as you can see we did

1:38:53mechanical electrical assessments we

1:38:55looked at historical conditions we

1:38:57looked at ways that you could change

1:38:59floor spacing around we took a look at

1:39:01ADA accessibility we did decision trees

1:39:04this one is for ML MLK about how we

1:39:06should be making decisions, site plans,

1:39:09cost analysis. We even did renderings

1:39:11and this was a very comprehensive effort

1:39:13over a number of months and gather as

1:39:15much data to provide the city province

1:39:17the best tools to make these.

1:39:20So what were the key findings from the

1:39:22state? First is that additional funding

1:39:25would be to support high special

1:39:27education populations.

1:39:29Roger Williams special education

1:39:31population is approximately 24%.

1:39:34ride regulations are generally

1:39:36reimburseed about 8%. So the original

1:39:38budget assumed an 8% uh special

1:39:41education population. Our budget and our

1:39:44revised budget that we split assumed a

1:39:4524% special education population. So

1:39:48that's the reason why budget

1:39:50but Dr. Martin Luther King rebuild

1:39:53identifies the most impactful cost

1:39:55effective approach which is renovation

1:39:57or building on site. Look at the current

1:39:59problem right there. This is a perfect

1:40:01example of how a stage two differs from

1:40:03a stage two and a stage two multiple

1:40:05options will take a renovation project

1:40:08uh a new build on the existing site

1:40:10swinging the kids out as well as a new

1:40:12build on what is cloly referred to as

1:40:14the little farm place action under

1:40:16control of the city province and public

1:40:19psy. So again example of making a pivot

1:40:23based on stage three different stage

1:40:25three at carne valto we identified

1:40:28structural issues at carne val that will

1:40:30prohibit any renovations at this now

1:40:32what does that mean the original budget

1:40:34for carne val was only $1100 we've

1:40:38identified significant structural

1:40:39concerns that pay no there no immediate

1:40:41concerns should say that but we cannot

1:40:43make an investment in that building

1:40:45without first addressing structural

1:40:46concerns because of the site conditions

1:40:49including some envirment environmental

1:40:50cap and dem issues would make that

1:40:53structural work.

1:40:56So that's one of the issues that we we

1:40:59encountered. And then for a full prek

1:41:01through 8 program, we actually are so

1:41:04underutilized right now currently at

1:41:06delesto that we'd be able to fit the

1:41:08entire client bow population, all of the

1:41:10special education, all of their services

1:41:12into the Delesto school. That is a

1:41:16construction efficiency. If we can build

1:41:18one school that can house all of those

1:41:20students as opposed to two, you are

1:41:21saving money. You're not paying two

1:41:23contractors. You're not paying two sets

1:41:24of general conditions. You're not paying

1:41:26two sets of overhead and profit, two

1:41:28sets of insurance, two sets of

1:41:29subcontractor bonds. It significantly

1:41:31reduces the cost and allows you to put

1:41:33more money into the project as opposed

1:41:35to soft costs for

1:41:38what?

1:41:41>> Um, we're not cramming these kids in

1:41:43there and I these are special needs at

1:41:45least.

1:41:47>> So, yes. So,

1:41:49if I can be vulnerable for a second. I

1:41:52have two children um in my island public

1:41:54schools get vocal on the my boy is

1:41:57autistic. My daughter has some severe

1:42:00emotional issues that she's currently

1:42:01working through. I can tell you that

1:42:04when PPSD is not in the room and they

1:42:05always can't be, special education has

1:42:07to advocate for me at the table. So,

1:42:10making sure that we have the appropriate

1:42:12spaces, not just um the breakout spaces,

1:42:15but so classrooms when needed fixed up

1:42:17pullouts have been included in this

1:42:19design. And we are reviewing that all

1:42:21with Ryan.

1:42:26um at one of the um school board

1:42:28meetings they were talking about how we

1:42:31really don't have enough special

1:42:36ed teachers in the classrooms and

1:42:39if we were to put in what they're

1:42:42requesting is that going to add more

1:42:45stress to us.

1:42:47>> So that's an operational issue I don't

1:42:48think I'm qualified to discuss. Do you

1:42:51know um

1:42:52>> I'm not start we had more what?

1:42:55>> Stress because

1:42:58we're we're putting a lot of people into

1:43:00this thing

1:43:02and now we're expecting art to expand

1:43:08into students. Now we're saying well

1:43:11we're going to put two schools in one.

1:43:13We're not expecting that to expand. And

1:43:15if you are,

1:43:18we also need to take into consideration

1:43:20that we're going to need more teachers

1:43:23and the special ed really needs more

1:43:25teachers because they are under staff.

1:43:27So I want to know

1:43:30have we taken all that into

1:43:32consideration?

1:43:34>> Yeah. So um Delesto would be the site of

1:43:37the combined school is substantially

1:43:39underutilized at the moment. And so when

1:43:42we run the numbers, there is ample

1:43:45there's ample room for that building to

1:43:48absorb both student populations.

1:43:50Um,

1:43:52as it will relate to staffing impacts, I

1:43:55think we haven't made any that that's

1:43:57two years down the road going we'd be

1:43:59making the decisions and any staffing

1:44:01adjustments that we would make would be

1:44:03driven based upon the student enrollment

1:44:05numbers at the time um as well as what

1:44:08our current staffing levels were as a

1:44:11function of many things including folks

1:44:13potentially retiring between. So to the

1:44:17question of um there being deficiencies

1:44:20currently in terms of headc count around

1:44:23um special special education teachers um

1:44:28I I'll confess that's a little bit

1:44:29outside of my domain but I have heard

1:44:32that that is a there we have acute

1:44:34challenges in hiring special education

1:44:37teachers these days. So, um, in a

1:44:40combined school, I have no illusions

1:44:42that that situation would disappear, but

1:44:45nor would it necessarily be any worse

1:44:47than it currently is because merely by

1:44:50combining two schools, you're not

1:44:52necessarily changing the composition of

1:44:54students in school and what their needs

1:44:56are. um you're just um kind of more

1:44:59efficiently creating the ability for um

1:45:02you trying to do some of this less less

1:45:05efficient operating costs that are

1:45:08resulting from maintaining separate

1:45:10under

1:45:15sorry follow up to that this program

1:45:18when we go through actually will be some

1:45:20of special education because currently

1:45:23two of these schools that we are

1:45:24proposing build new or likely

1:45:26renovations

1:45:27currently can't accept a lot of ADA

1:45:28students because of the composition of

1:45:30the buildings. As an example, Martin

1:45:33Luther King Jr. is not ADA accessible in

1:45:36his current whatsoever. So any student

1:45:38with a mobility issue cannot go to that

1:45:40school there. Roger Williams hasn't got

1:45:43an elevator. There's there's lots of

1:45:45sorts of different ways that by building

1:45:46new and by renovating and adding these

1:45:48seats, we should be able to alleviate

1:45:50and maybe more kids can stay in their

1:45:52home communities as transfer across.

1:45:56Sorry. Do we have

1:45:59do we have um

1:46:02numbers already that the guesstimate I

1:46:05guess I should say of of the students

1:46:07now? Um what numbers do you have?

1:46:14>> Yeah, I mean you do. Um but you have

1:46:19>> uh the projected enrollment for the new

1:46:22school or special education population.

1:46:24>> No, the projected enrollment.

1:46:33We are um 550 is the enrollment 728 at

1:46:38Elto.

1:46:43Yeah, carnival would be an addition

1:46:50>> because uh if you remember I'm pulling

1:46:52this off our swing space worksheet that

1:46:54we used and because we're not swinging

1:46:55kids out in carnal that was a

1:46:57consideration. We were counting numbers

1:46:59of students and how we could figure them

1:47:00out. But that's an absolute I can get

1:47:02that answer to you

1:47:03>> if you could.

1:47:04>> Yeah, of course.

1:47:06>> It's something that's I I care about.

1:47:07So, we'll make sure we get it to you.

1:47:10>> Um

1:47:10>> uh Chris have a question. Um so from the

1:47:14original base for MOA uh Valley and

1:47:20OESTO was was planned to be one school.

1:47:24>> No, they were planned to be two separate

1:47:26schools with their current grade

1:47:27configuration. The original budget was

1:47:3011 $12 million for Carneal and about $11

1:47:33million for for Delesto. They wouldn't

1:47:36change it was planned not to change the

1:47:38educational programming. However, I

1:47:40think the district since that MOA the

1:47:42district the way that the district's

1:47:44moving has been towards more preK

1:47:46through AIDS for a number of reasons um

1:47:48that PPSD has was talked about but um

1:47:51but no that was

1:47:52>> what's I I' I've heard and yeah I've

1:47:56heard uh regarding some concern where

1:48:01does does that play a factor into

1:48:05>> absolutely so

1:48:07are both built on a site that is what's

1:48:09called an envirment enironmental cap on.

1:48:11That means that uh when those schools

1:48:14were being built, it was determined that

1:48:15the soils uh were originally

1:48:17contaminated and what they did was they

1:48:20provided a twoft cap of clean material

1:48:23on top of that contaminated soil. Then

1:48:25full transparency, they were built on a

1:48:27landfill and it's actually one of the

1:48:29reasons why we have school sighting laws

1:48:31in Rhode Island is because of that of

1:48:33that project. because of that

1:48:35environmental work, we really don't want

1:48:36to go for two feet because it becomes

1:48:39incredibly expensive. It adds a ton of

1:48:40time to our schedule by going to GDM.

1:48:43There's a whole public process and there

1:48:45have been lawsuits filed at the school,

1:48:47you know, years ago, but we don't want

1:48:49to walk into any of that because it

1:48:51could slow down our project.

1:48:52Unfortunately, to fix structural issues,

1:48:55I have to go down deep. I have to go

1:48:57down below the foundations. I have to go

1:48:59at least 5 feet, which is 3 feet below

1:49:01that environmental cap. And more

1:49:03importantly, I have to go out. I can't

1:49:05fix right on top of it. I have to go out

1:49:08and under, which means now I'm

1:49:10excavating around major sections of that

1:49:1370,000 square foot building to remain

1:49:16pull dirty soil out, put clean soil

1:49:18back, fix the structural, put soil back

1:49:21in. And to give you above order of

1:49:23magnitude about what we expect just a

1:49:25soil remediation to cost, we had war. We

1:49:29had some contaminated soils that were

1:49:30not as bad as these on a similar site

1:49:32with $5 million

1:49:36high schools.

1:49:44>> Yeah, Chris, do these concerns are they

1:49:47also at Dela

1:49:49at all?

1:49:50>> So, they are it's the same site. They

1:49:51are dela. However, the reason that we

1:49:54thought Delasto would be a great

1:49:56efficient property for you is that it

1:49:57does not have those structural concerns.

1:49:59So, Delhi val

1:50:03immediately on the brink. So, as the

1:50:05soils have settled because

1:50:09they have a 2 ft of cap that has caused

1:50:11types of pictures. It's caused some

1:50:12structural issues at the school. Delesto

1:50:15was built differently. Dela was built on

1:50:17something called piles. Piles are large

1:50:20concrete pillars that are drugged down

1:50:22into the ground and they go all the way

1:50:24to the bedrock or the soil, which means

1:50:26that we've got something that we're

1:50:27building on which is connected to

1:50:29something that's not going to move.

1:50:30That's why you don't see the settlement

1:50:32issues with the building. Are there some

1:50:34settlement issues in the parking lots

1:50:36and things like that? Yes. But fixing

1:50:38those does not require me to go 5 ft

1:50:40down. It does not require me to excavate

1:50:42foundations. So that's why when we're

1:50:45looking at this project, we looked at

1:50:46utilization. We looked at enrollment. We

1:50:48looked at the space needs and we looked

1:50:50at structural issues and we said

1:50:54we spend money fixing the structural

1:50:56issues of carbon. You're going to eat a

1:50:58substantial amount of that budget and $1

1:51:00million you're certainly not going to be

1:51:02able to do any educational enhancements.

1:51:04If you've got health and safety projects

1:51:05and being projects fire code that have

1:51:08priority that we have to do this

1:51:10project. So for us there's unfortunately

1:51:15you know it would um involve closing

1:51:18about moving your students in but in

1:51:21terms of a difficult decision for us to

1:51:23make as project managers. This one was

1:51:26was a little bit easier than some of the

1:51:27other ones because we had the space

1:51:29right there. we really wouldn't be

1:51:30breaking up a community as it was to say

1:51:33as and we don't have the structural

1:51:35issues and we because of the building

1:51:38size and it's underutilization we don't

1:51:40have to expand right it's we still need

1:51:43to put an elevator and tents like that

1:51:44in in the center of the building but we

1:51:46don't have all of this hidden sunk cost

1:51:48that don't translate to student hour

1:51:51they translate to just keeping the

1:51:53building as

1:51:55>> I I think my next question is this is

1:51:57going to be an occupied phase ation

1:51:59acts. Correct. Um what controls

1:52:03[clears throat] are in place to make

1:52:03sure you don't you saying you don't have

1:52:05to dig deep into the ground. So the

1:52:07environmental concerns are not a concern

1:52:09with the children who are going to be in

1:52:10there while renovations are happening.

1:52:12Correct. Um so when you phase it, do you

1:52:15do one half of the building and the

1:52:16other kids are the other half? And how

1:52:18do you have controls on site to make

1:52:20sure children safely? Awesome question.

1:52:23So, um, originally we would, what we

1:52:26would like to do is renovate this

1:52:27building with no students. You know, it

1:52:29makes it much easier for us. Of course,

1:52:32because of the phase three projects and

1:52:34two of those projects potentially

1:52:37requiring that those swing spaces that

1:52:39we would swing kids in are no longer

1:52:41available, um, the city uh, PBSD asked

1:52:44us to take a really hard look at the

1:52:46building and see if there's a way that

1:52:48we can keep these kids inside the

1:52:49building and still do the renovation.

1:52:52And what we've been able to work with

1:52:54through a number of meetings and a lot

1:52:56of blood, sweat, and tears that we would

1:52:58essentially revive the building on its

1:53:00vertical access, we would take one whole

1:53:03three floors of a building over at a

1:53:05time with where enrollment is. You could

1:53:07fit all of the students that are

1:53:09currently there within that other

1:53:10vertical half of the building and that

1:53:12the larger spaces on the ground floor

1:53:14would be renovated over the summers.

1:53:16We've been working very closely with the

1:53:18principal. He's very much in favor of

1:53:20keeping his kids in that building and

1:53:22not swinging out for a lot of the

1:53:24reasons that he talked about that Joe

1:53:25talked about there really isn't a space

1:53:27for many school kids to swim into

1:53:29without making a substantial investment.

1:53:31So when it becomes again throwing costs

1:53:34after something that we'd much rather go

1:53:36to school

1:53:39>> uh counselor Grace

1:53:40>> so we've been talking about the tracks.

1:53:42So what are what are you foreseeing for

1:53:44tracks in this building? Oh, this is a a

1:53:47threetrack, pre 3K through three track,

1:53:50four track, four track at the middle

1:53:51school.

1:53:52>> Um, so the students at Carter Valley,

1:53:55they will stay there until uh this whole

1:53:59project is done.

1:54:05>> Um,

1:54:07um, again, conditions have changed since

1:54:10the stage two report. our team went out

1:54:12there and we said, "Why is this roof

1:54:14spongy?" And we uh we noticed that they

1:54:17they need a roof replacement. So that's

1:54:19why we increase the scope of work over

1:54:22there is for that roof replacement. And

1:54:24then at one high school, originally a

1:54:26budget of $20 million. That school needs

1:54:28a lot of work. Um we estimate the total

1:54:31cost to make that building completely

1:54:33like new at about $70 million. We've

1:54:36been able to increase the budget because

1:54:38we felt that $20 million sure would

1:54:40replace the boilers, you know, things

1:54:42like that. But it's such a large school.

1:54:44It's a huge school, but would be able to

1:54:46do any of the education center

1:54:47enhancements that they want, right? They

1:54:50want to use CCTV spaces.

1:54:52You know, they they want the teachers

1:54:54have been very about making sure HBAC

1:54:57HBAC system works properly, right? So,

1:55:00all of these types of things are well to

1:55:02them to make sure that we can have those

1:55:04health and safety still provide some

1:55:07student focus

1:55:12>> uh is a comprehensive electrical upgrade

1:55:16part of the whole renovation.

1:55:18>> So new electrical services part of the

1:55:20and as well as providing new electrical

1:55:22service to rooms so we can have more

1:55:24technology in the classroom.

1:55:30any questions on some of the key items.

1:55:34>> Um, also one thing we took about is

1:55:37where are prek through pathways located

1:55:39across the city? PPSC is 100% buy in on

1:55:42the prek through 8 model and looking at

1:55:44where currently those pre-k schools are

1:55:46going to be complete as far bases.

1:55:49There's a big gap over here on the east

1:55:51side. There was Dr. MLK was originally

1:55:53slated to get a pre-paid survive by

1:55:56maximizing that investment bringing the

1:55:58additional finance to our project were

1:55:59able to create a prek rate in that area.

1:56:02It also again this program also gives

1:56:04people a lot of options if you if you're

1:56:07like me someone who likes a smaller

1:56:09community for their son um because he

1:56:11wants to be with his we want him to see

1:56:13his interest rate eight years. We want

1:56:14him to know the principal for longer. We

1:56:16want him to understand his specialist.

1:56:18We want a specialist to grow with him.

1:56:19That's a great model for my daughter. I

1:56:21think she's gonna want to go to a middle

1:56:23school mom. She's gonna want to go to an

1:56:24acne. She's gonna want to go to a bishop

1:56:25because that is something that best

1:56:27suits her. So, by having a pre-k over

1:56:29here as well as a middle school option

1:56:31and a prek through five elementary

1:56:33option, you're really getting all the

1:56:34flexibility of that part of province

1:56:37that you currently have some other

1:56:39parts.

1:56:40>> Uh, we have a couple questions Peterson.

1:56:43>> Sorry, there's one through eight for the

1:56:45bides. Is that what you're bringing up

1:56:47currently?

1:56:48>> No, there's another one. But this is

1:56:50allowing and that's going to be

1:56:53>> yes

1:56:55Burton has a high enrollment as well

1:56:56with a pre we're expanding prek as well.

1:57:00So you have one kind of option for each

1:57:02a prek through five a prek through eight

1:57:04and a middle school options all on one

1:57:06side.

1:57:11Yeah, I think I realized it. Um, so

1:57:15you're Nathan Bishop falls in that area.

1:57:21>> So that's kind of the amount of the

1:57:23school remaining.

1:57:26>> Yes. The two middle schools that are

1:57:27slated to remain open are Matt Green and

1:57:30Baylor. They both have incredibly high

1:57:33uh weight lists, right? They're both

1:57:36very popular schools within the

1:57:37districts and I think a lot of parents

1:57:39do [clears throat] like that model. some

1:57:41other parents like a pre-k mom. I think

1:57:43this gives a lot of flexibility and

1:57:45we're talking about enrollment declines.

1:57:47I know that's always part of these

1:57:48conversations. A big way you can

1:57:50increase enrollment. A is expanding

1:57:52prek, which we'll tell you about how

1:57:53we're going to do that in a second, but

1:57:55it's giving parents flexibility. It's

1:57:57giving parents the ability to say, "This

1:57:59pathway works for my child. Providence

1:58:02Public Schools offers this pathway to my

1:58:04child. I don't have to

1:58:11Um, so as we move through the revised

1:58:14MLM, what were some of the ration? We

1:58:16want to get more students to new new

1:58:18like schools by 2030. Establish a prek

1:58:21hub for specialized instruction, right?

1:58:23Where we can have our testing and a

1:58:25large amount of our prek, especially

1:58:26some of our most vulnerable students in

1:58:28the state building. Provides a prek path

1:58:31in province preserve seats at high

1:58:33demand schools. As an example, I think

1:58:36they agree. If we were to decrease the

1:58:38transition to prek through eight, you're

1:58:40not going to be able to accept as many

1:58:42middle school students that you

1:58:43currently have and that's a real driver

1:58:45for that school is that moves. It does

1:58:48reduce inefficient inefficient operating

1:58:50costs by rightsizing capacity to rely on

1:58:52enrollment and it does allow the program

1:58:54to address both educational placements

1:58:57and warm safety drive. So, it's not just

1:59:01a bunch of engineers, architects, and

1:59:03consultants that inform this decision.

1:59:05As part of our stakeholder engagement

1:59:07process, but prior to coming to this

1:59:09recommendation,

1:59:11um, left field, PBSD, as well as our

1:59:13project partners from the design build

1:59:15side, I've held over 160 meetings in

1:59:20terms of stakeholder review. We have

1:59:22that doesn't include the hundreds of

1:59:24meetings that our staff has had across

1:59:26these six projects talking about

1:59:28everything but hundreds more digital. We

1:59:31released surveys as well to parent

1:59:34groups to PTO's we have them distributed

1:59:36through PPSD's communication system with

1:59:39the help of faces. He also developed a

1:59:41number of videos and these videos are in

1:59:44multiple languages and they're spoken in

1:59:46multiple languages not a translation

1:59:48reader. And what these feasibility study

1:59:50these videos do is they talk about a

1:59:52what the right process is b why we did

1:59:55these feasibility studies and what we're

1:59:58looking for. And now that we are moving

2:00:00forward with the revised MOA, we would

2:00:02then do another series of videos for

2:00:04each school about what their project is.

2:00:07We would also look for feedback notes

2:00:09about what else constituents would want

2:00:11to hear and we could quickly pivot to

2:00:13adopt more videos. They're very

2:00:14userfriendly. They're animated and

2:00:17they're they're designed to really get

2:00:19down to people that don't have a lot of

2:00:20experience with construction because I

2:00:22talk a lot in acronyms move very fast.

2:00:26So these are a way for people to watch

2:00:28rewatch and get a firm understanding of

2:00:30what is going on at this point.

2:00:33>> Yeah. Um can you just reflect a little

2:00:37bit on what you learned from the

2:00:39community meetings about whether

2:00:40communities you think are the one?

2:00:44Yeah, there's so the pre-kate model has

2:00:46a lot of buy in at Dr. MLK. So that

2:00:49that's I think in general what we hear

2:00:52from a lot of parents is sustainability

2:00:54is always an issue. Are these buildings

2:00:56going to be sustainable? Green space is

2:00:59always an issue. Are these buildings

2:01:00going to have green space? How are these

2:01:02projects going to provide community

2:01:03betterments for community members that

2:01:07uh that don't have students in the

2:01:08school? Right? Not everybody in

2:01:10Providence has a kid in the school, but

2:01:12everybody in Providence lives in

2:01:13Providence and they're paying for these

2:01:14projects. So, we try to look at how we

2:01:16can be better engaged as part of these

2:01:18projects as well. Overwhelmingly though,

2:01:21especially for for what we've heard from

2:01:23all of our stakeholder engagement

2:01:25meetings. There really isn't a lot of

2:01:28push back to what we're proposing. I

2:01:30think we have had some concerns about

2:01:32what does a prek through 8 model do in

2:01:35terms of specifically how do you keep

2:01:38middle school students and sixth,

2:01:39seventh, and eth apart from your young

2:01:41students. The difference between my

2:01:43six-year-old and my 10-year-old is huge.

2:01:45They learn differently. They act

2:01:47differently. But the difference between

2:01:48a prek student and an eighth grader is

2:01:51even bigger. So, a lot of parents want

2:01:53to know from a design perspective, how

2:01:56do we keep these populations separate

2:01:58while also still providing them all of

2:02:00the same resources throughout the

2:02:01building? And the way that we do that is

2:02:03we design the building with different

2:02:05communities with inside a prek to

2:02:07community, a K to 2, a three to five,

2:02:10and a six seven and eight. And if I'm

2:02:12lucky enough to come back to this group

2:02:13and present designs about how I'm much

2:02:16more visuals will really help me show

2:02:18you how I'm doing that.

2:02:21>> We can guarantee that. We're going to

2:02:23leave it for.

2:02:25[clears throat]

2:02:25>> Sorry.

2:02:26>> You said if you're lucky enough to

2:02:28>> Oh, you get this is my first time so

2:02:30far. So,

2:02:32>> quick question on this this slide

2:02:34though. Uh Chris, um so is are these

2:02:38like are these um required in like the

2:02:41contract with you or is this this

2:02:44something that you do on your own or?

2:02:47>> So out of all of these meetings, only 15

2:02:51I think were required by school board

2:02:53policy or by not we don't have a

2:02:56contractual obligation, but we do what

2:02:58the owner tells us to do. Um, I think

2:03:01for a lot of this it was to make sure

2:03:03that when we did have an MOA alignment,

2:03:05when we did have to prioritize projects

2:03:07that we were showing you that we not

2:03:10only did all of the hard work of the

2:03:11data collection, the feasibility, the

2:03:13requirements, but we also made sure that

2:03:15we respected what we were hearing from

2:03:17the community. And you know, sometimes

2:03:20doing this much stakeholdering can be a

2:03:22detriment, right? You're hearing from a

2:03:23ton of people, you're getting a lot of

2:03:25ideas. And unfortunately, you're going

2:03:26to have to say no to a lot of people. In

2:03:29this case though, when we're talking

2:03:30about doing things like demolishing

2:03:32Martin Luther King, so for those of you

2:03:34that that don't know, Dr. Martin Luther

2:03:36King, um, was really built at a time

2:03:38when that neighborhood specifically

2:03:40needed a community resource. And the

2:03:43building has a lot of history with civil

2:03:45rights activism, civil rights

2:03:46engagement, and we were very concerned

2:03:48about if we're going to take down this

2:03:50building, how can we talk to the

2:03:52community about moving that culture

2:03:55while still demolishing this building?

2:03:56And we really were worried that we were

2:03:58going to have a lot of perspective

2:03:59demolishing the building. And what

2:04:00concurred overwhelmingly our state

2:04:02building engagement is we want the new

2:04:04building. We want you to respect the

2:04:06culture. Make sure that you're

2:04:07[clears throat] carrying that culture

2:04:08into the new building, but demolish the

2:04:10school. We won't stand in the way of

2:04:12that sort of process is what we're

2:04:14hearing from our community engagement

2:04:15and I know I've done several with with

2:04:17you in the neighborhood as well. We

2:04:20really are doing a ton of support for

2:04:22this and that's one of the areas we

2:04:23thought we were going to get a lot of

2:04:24push back. Now, part of that is also

2:04:26related to phase three projects. If you

2:04:28remember during phase three, there were

2:04:29some questions about demolition for some

2:04:31of the schools that did have an impact

2:04:33on schedule. We wanted to make sure that

2:04:35we got out ahead of that if there were

2:04:37going to be any issues on demolition

2:04:38that we knew about them now and we had

2:04:40plenty of time to work through them

2:04:42prior to our demolition date which is in

2:04:45the summer. So, we just wanted to get

2:04:46out way ahead of it because as I'll

2:04:49explain in a second, we have a different

2:04:51MOA constraint besides just our our

2:04:54timeline. We have a bonus point MLA

2:04:57restriction that the phase two and three

2:04:59projects don't have.

2:05:06Um,

2:05:08so our proposed FOC

2:05:11for projects is an agreement. The

2:05:14original MOA is signed based on the

2:05:16original list of projects and MOAS can

2:05:20as they have it in Providence for phase

2:05:22two and three and for all of my other

2:05:24clients they absolutely change between

2:05:26what is is stage two and what is

2:05:29eventually built. will show the overall

2:05:32MOA project as well as proposed new MOA

2:05:34for projects based on the district

2:05:36recommendations and we have received

2:05:38approval unanimously by both the

2:05:40province school building committee and I

2:05:42think from the province school board

2:05:44which I think is generally reflects

2:05:46pretty broad. We have been presenting on

2:05:49this MLA every single month since we've

2:05:51been engaged and I think we we listen

2:05:54very closely as I hope you'll see

2:05:55council on the graves we listen to the

2:05:57questions and we try to pivot and

2:05:58provide information to help answer.

2:06:03So for both Emily and Neielson RF pay as

2:06:06discussed we showed this here even

2:06:09though he's in phase three because it

2:06:11does affect that non budgets so that

2:06:14money from phase 4 is being used to fund

2:06:17the wasted profit. Dr. Marlin June the

2:06:20original MOA was $48 million and it was

2:06:23a new build or renovations at the prek

2:06:25through 5 level. We're asking for new

2:06:28builds at the prek through 8 level. the

2:06:30revised MOA that was approved by RI

2:06:3290,415

2:06:34million.

2:06:35Why do you want to go better? The

2:06:37original budget was two separate

2:06:39projects at $105 million. Because of

2:06:43that special education population, we

2:06:45were able to get this increased to $112

2:06:48million.

2:06:50Delesto Cornal, as you can see, very

2:06:52small projects for both of those

2:06:54projects, only 11.4 and 12.9. and

2:06:57they're both for selective renovations.

2:07:01The scope of work revised would be a

2:07:02great view to the K through8 as a great

2:07:05value of $50 million at the Delto School

2:07:08and the current plan currently would be

2:07:12the way that the PPSD and Sydney

2:07:14province asked us to explore is can this

2:07:17building be demolished and can we add

2:07:19green space there? that is there's not a

2:07:21lot of green space specifically in that

2:07:23in that part of town and so however I

2:07:26will say that there are multiple funding

2:07:28opportunities available for sites just

2:07:30like carbal a great example is tal

2:07:33stadium conducted if anybody's been to

2:07:35RFC game all of the site work and

2:07:38remediation was funded through grounds

2:07:41there are multiple opportunities at the

2:07:42federal and the state level for us to

2:07:44pull money into this so for the time

2:07:47being that building remains when we're

2:07:49done with it it will be turned over to

2:07:51the care and control

2:07:53and then the decision will be made on

2:07:55this feature. Um perhaps the

2:07:57subcommittee about what happens to that

2:07:58building should be brought together but

2:08:00we will do as directed. your ex

2:08:06question.

2:08:07Uh proposed MOA adjustment. Is this

2:08:10still proposed or have these have these

2:08:12been approved by

2:08:14>> so it's not proposed, right?

2:08:15>> Well, the school board approved this.

2:08:18Yes. Unanimously. School building

2:08:20community school board. I say proposed

2:08:22because you all control the contracts

2:08:25for all of these design builders. And

2:08:27while I can continue to move forward

2:08:29through design, everything is set on

2:08:30rise in if I don't have buyin from this

2:08:33group and city council on amending those

2:08:35contracts. I can't move forward with

2:08:37money.

2:08:42As I said, they're looking at a

2:08:44additional ask of about 3.49 million for

2:08:47a new roof at Hope High School

2:08:50originally at 25 million and at 40

2:08:53million. You will also notice that none

2:08:56of these projects rely on any capital

2:08:58reserve funding. Capital reserve funding

2:09:01is a separate budget that is controlled

2:09:03by Crystal and her team that allows us

2:09:05to continue to do work. It is a

2:09:07revolving fund, meaning as those

2:09:08projects get finished, they get

2:09:10reimbursed or money goes back into it.

2:09:12We have found a way to push forward

2:09:15several projects into CRF based on this

2:09:18revise down the way that we've

2:09:20submitted. We're going to talk about

2:09:22that a little later as well.

2:09:24In terms of phase 4B,

2:09:27classical at 1509,

2:09:30math brain at 28, and all the following

2:09:34schools, smaller schools, these already

2:09:36have very small budgets because in

2:09:38today's day and age, we're not really

2:09:40doing that much with $5 million with

2:09:42what construction costs are. So, what we

2:09:46were able to do is pull money into

2:09:50net green after conversations that we've

2:09:53had with the principal over there about

2:09:55what their high priority projects are

2:09:57for that building and um we are already

2:10:00moving forward with advancing some of

2:10:02those into next summer's CRF round of

2:10:05funding. So we're planning on doing

2:10:06projects in that.

2:10:08>> Wait, can you say that again?

2:10:14>> You have a question.

2:10:16>> Yes, I have been waiting for speech. Um,

2:10:20I want to say thank you for

2:10:23finding some ways to get it from that

2:10:27middle to 28. Um,

2:10:32however,

2:10:35we also know that is this going to bring

2:10:38this up to life?

2:10:42That was one of the questions I had.

2:10:46Um

2:10:49the other one is we already know that

2:10:50there's a boil there was a boiling issue

2:10:53there. Is this going to add more money

2:10:57because we're going to have to get a new

2:10:59boy or is this supposed to be part of

2:11:01that

2:11:03um raising funds and secondly I believe

2:11:07they have new boilers

2:11:10everything. Okay. Three.

2:11:13It was a long time ago.

2:11:15We

2:11:15>> put a new one in in 2018.

2:11:17>> Yes.

2:11:19[laughter]

2:11:20But my thing is um

2:11:22>> I don't expect you to go into a

2:11:24mechanical. So I don't even know.

2:11:27>> So how old are those other to boilers?

2:11:30Because I because I I I usually notice

2:11:33that once

2:11:34it around the same then the other thing

2:11:38tends to go too. So,

2:11:40>> so has that been figured into anything?

2:11:44Um,

2:11:46what was happen that's first question

2:11:49about the cost of renovations. I have

2:11:51specific slides that a little bit later

2:11:54if I could use those to help illustrate

2:11:55my points.

2:11:56>> Okay. Well then that's

2:11:57>> that's

2:11:58and then in terms of the boiler list so

2:12:00when left field was doing our visibility

2:12:02studies one of the things that we

2:12:04identify as a project that needs to move

2:12:05forward was a replacement HAC

2:12:08>> in conversations with the principal he

2:12:11has also stated that that's one of his

2:12:13prior that security as well as a student

2:12:15centric

2:12:17talk to later is what his plan was so

2:12:20that I mean boiler replacement was

2:12:22always expected to go forward what we're

2:12:24doing now in light recent situations is

2:12:27we are pushing that project forward. We

2:12:29are taking money out of the CRF to fund

2:12:31it so that we can do it this summer. As

2:12:34of today, I've already called the design

2:12:37bill team that's assigned to this

2:12:38project and said, "How quickly can you

2:12:40get on it?" And we can move forward

2:12:42incredibly quickly on that. We don't

2:12:44have to get it out. We don't have to

2:12:45call team up and get right into this on

2:12:49and we would recommend not just fixing

2:12:51the boilers. We would recommend

2:12:54replacement as well as doing some of the

2:12:56HBAC work on that first score. The

2:12:59principles really have an issue. Okay,

2:13:01that was my

2:13:02>> uh counc continue your question then

2:13:04we'll go to Davidson.

2:13:06>> Yeah. Um that was my other question

2:13:07because not just the boilers is this a

2:13:11situation. Um,

2:13:14what

2:13:17I asked you what the ages are and all

2:13:19that other stuff, but you said you're

2:13:20going to go into more depth of

2:13:25>> because I still haven't let new.

2:13:29>> Okay. Okay.

2:13:32>> Okay. Then I then I will wait patiently.

2:13:37>> Um, thank you. just when when are these

2:13:40expected to go? Like I know you're

2:13:42talking about the Venio, but when like

2:13:44are the rest of them expected to start?

2:13:47>> I think that's a that's a great

2:13:48question. I think that work needs to be

2:13:50done on the CRS side to figure out why

2:13:52these are moving forward. I believe we

2:13:54have I don't want to

2:13:56>> $5.5 million for the CRF right now. $5

2:13:58half million in the state of equipment.

2:14:00So those

2:14:02>> become one like you take classical first

2:14:04and then

2:14:05>> so I think given the situation right now

2:14:08our recommendation for a major project

2:14:11next summer would be an HBAC regulation

2:14:14that will eat up a substantial amount of

2:14:15that first round of CR. We have

2:14:18additional projects that are happening

2:14:19already fire alarm stuff uh across the

2:14:22code projects across the portfolio but I

2:14:27think we all know we can't have a

2:14:28situation like that again. So it has

2:14:31been asked of us as director facilities

2:14:33and then to figure out a way where we

2:14:36can get one of these projects done this

2:14:38summer with Sierra.

2:14:39Yeah, I would just add to that that um

2:14:43Sarah funding which is a $70 million a

2:14:46year revolver is used not only to fund

2:14:49these projects but also for Aboriginal

2:14:52projects for example right um uh there's

2:14:56a bait in work happening at high school

2:14:58right now around the speeus and so I I

2:15:01think it's important that we be clear

2:15:03about the fact that if you look at these

2:15:05numbers um they're not on a on a 30-year

2:15:08basis is going to be CRF is not going to

2:15:11be 100% allocated to these does need to

2:15:14cover basic operating costs as well and

2:15:16then we should also say that this is

2:15:18these projects currently are depending

2:15:20on

2:15:22if there is an addition of additional

2:15:24cash either be bond approval or budget

2:15:27line transfers which I'm not prepared to

2:15:29speak to as Mr. seeing these projects

2:15:31can be pulled out of CR and into a

2:15:33different funnel and I think that's more

2:15:35of a question about how your debt

2:15:37service is structured when certain debt

2:15:39is coming offline. It sounds like the

2:15:41way that Crystal is borrowing this is

2:15:42incredibly smart which might make it

2:15:44easier for us to have other funding at

2:15:47different times but I'm I'm not prepared

2:15:49to speak to exactly how we can fund it.

2:15:51All I can say is that if we are told to

2:15:53execute, we're given a budget, we will.

2:15:59>> So all of the projects

2:16:01on page 4B are proposed to be funded

2:16:06through CRF and not bonds.

2:16:09>> They're proposed to be funded by a

2:16:10different source than the $400 million

2:16:12bond. That $400 million bond is one of

2:16:15the primary drivers about why the

2:16:17product fastest projects because the

2:16:19approval value is $465 million but our

2:16:24cash is only $400 million.

2:16:26>> So again as I said at the beginning no

2:16:27matter what we have to do because of our

2:16:29cash flow we could only do $400 million

2:16:32worth of projects and there were going

2:16:33to be approximately $70 million project

2:16:35that had to be private class.

2:16:38>> That's this adds up to 7 million.

2:16:42Wait, Crystal, how how did you uh send

2:16:45$70 million of capital revolving funds?

2:16:49>> Um I am not aware of a way to do that

2:16:52without investing

2:16:55fund. Uh the current CIP which was

2:16:58approved in July does have a future

2:17:02unfunded potential investment of $5

2:17:04million. I want to say it's in fiscal 28

2:17:06or 29. Um but at this point we have not

2:17:09bonded for those dollars and I have not

2:17:10identified a funding source to

2:17:12reappropriate into the revolving at this

2:17:14point in time. Um there is possibility

2:17:17that in favor favorable market condition

2:17:20we will be able to identify bond premium

2:17:22that could potentially be used to fund

2:17:24the development fund. With that said,

2:17:27right now we're balancing the we are

2:17:31assuming that any bond premium we're

2:17:33earning is covering the interest

2:17:35payments while the projects come online.

2:17:37So, it's a matter of balancing the debt

2:17:40service we want to take on and how we

2:17:41want to use that premium. We want to use

2:17:43it to soften the impact of the debt

2:17:45service coming online for $400 million

2:17:48of borrowing, of which we don't have

2:17:50$400 million of debt coming off of our

2:17:52books. Or do we want to take that bond

2:17:54premium, put it directly into projects

2:17:56and get it reimbursed in a different

2:17:58way, or do we want to transfer it into

2:18:00the revolving fund and revolve those

2:18:02dollars? I can tell you because it is a

2:18:05revolving fund and because it does

2:18:07revolve anywhere from um you know a low

2:18:1080% to one year we got bonuses that put

2:18:13us above 90%. Um we have been able to do

2:18:18$28 million worth of work in five years

2:18:20but we were the greatest amount of spend

2:18:23in any given year was $7.6 million and

2:18:26that was after our initial investment of

2:18:288.3. So starting in 2022 when the city

2:18:32uh contributed $3.3 million and PPSD

2:18:35contributed $5 million as capital fund

2:18:38we have been able to successfully turn

2:18:40it into quite a bit of project

2:18:41completion. Um but it is now down to

2:18:44$5.5 million and every year we revolve

2:18:46it that will shrink proportionally by

2:18:48the reimbur the difference between 100%

2:18:50spend and the reimbursement.

2:18:53>> We got a lot of decisions and

2:18:54conversations uh to do about this going

2:18:56forward. I mean just a quick question on

2:18:58everything that you said. What's is

2:19:00there what's the what's the sustainable

2:19:02funding source to the revolving funding

2:19:04do anything? I

2:19:06>> what what

2:19:08>> no no no I mean that and that's kind of

2:19:09the risk of this right until we sit down

2:19:12and I think that's got to be one of the

2:19:13conversations that potentially happens

2:19:15with the next administration what

2:19:16happens with the council is

2:19:18what does the investment what sort of

2:19:20investment do we want to make in the

2:19:22revolving bud and how can we identify

2:19:23funds to do that um you know not to get

2:19:27too far ahead but I've already started

2:19:29looking at fiscal year 2028 because

2:19:31that's where we're at in this season and

2:19:33I can tell you our operating budget is,

2:19:36no surprises, facing some pretty

2:19:38significant constraints next year out of

2:19:40the gate. And so, one of the ways I'm

2:19:43trying to mitigate those increases is by

2:19:45being strategic in how we're borrowing

2:19:47for debt service. But, you know, I think

2:19:50holistically we're going to need to look

2:19:52at again like where the city's

2:19:54priorities are once we are in budget

2:19:56season probably when we're looking at

2:19:58CIP and trying to weigh how and what we

2:20:01want to make investments in knowing that

2:20:03certain things that are fixed costs that

2:20:05are are going to go up and um you know

2:20:08again maybe we

2:20:10pursue other strategies within

2:20:12administration still kind of early on in

2:20:15that process to to see where we go But

2:20:18uh at this point in time I don't have

2:20:20like a a source of funds identified

2:20:24to to reinvest in fun. The only

2:20:27resources I have at this point in time

2:20:29are $5.5 million in there right now.

2:20:32>> So it's trending towards zero then now

2:20:34>> eventually it will get to zero without

2:20:37any capital

2:20:38>> as the current.

2:20:39>> Yes. And so our strategy to help with

2:20:42that is that we will identify shovel

2:20:44ready projects that are designed and

2:20:46ready to be bid so that when you all

2:20:49have those discussions about how we want

2:20:50to fund an additional $60 million of

2:20:52approval that you have available for

2:20:54reimbursement, we can pull the trigger

2:20:56very quickly for projects and we don't

2:21:00>> um what private insurance identified as

2:21:04a result of that five million or

2:21:06whatever it is that you can do shovel

2:21:09regulation So primarily it would be

2:21:12projects at classical and green. Um

2:21:14grade be looking at a boiler

2:21:16replacement. We're also looking at a

2:21:17student centric investment over there.

2:21:19Perhaps an auditorium refresh. Um

2:21:22security is another project we'll be

2:21:24looking at. Classical also has um

2:21:27principal bar bless his heart. He's an

2:21:29amazing advocate for his school. He's

2:21:30got a little bit more grandeur visions

2:21:32than I think $15 million would be able

2:21:34to capture. His original budget was only

2:21:3620 million wouldn't have captured the

2:21:38ground. But we have to identify quick

2:21:40shuttle ready projects that we can do

2:21:42very very quickly at I said security

2:21:46enhancements HBAC at green and a

2:21:48classical window replacement part of

2:21:51that wasn't able to be done as part of

2:21:53phase two but they didn't have the

2:21:54budget for they'd like us to do now

2:21:56they'd also like us to take a look at um

2:21:59their auditorium their music um spaces

2:22:01as well they also would like to take a

2:22:03look at that you know outside the

2:22:04auditorium they have that lovely space

2:22:07currently it's underutilized

2:22:09You know, we heard some great

2:22:10conversations about can we turn that

2:22:12into a potential revenue generating

2:22:14thing. There's, you know, host actual

2:22:16events in outside that little

2:22:17auditorium. So, there's there's a lot of

2:22:19things that we need to at least give you

2:22:21guys one order of magnitude pricing on

2:22:23and I think we go back to school

2:22:25building committee and we say you take

2:22:26us to the shovel ready. Which one should

2:22:29we get to design?

2:22:30>> Uh, I have a question. Thank you,

2:22:33chairman. Um so Chris said we have $400

2:22:36million

2:22:37>> capacity cash

2:22:39>> in the last presentation two and three

2:22:42nothing from the last previous one into

2:22:44any of our capacity during these

2:22:47projects and that's not the reason why

2:22:48we're doing kind of prioritizations. No.

2:22:51So actually what actually what this MO

2:22:54does is it actually takes scope more

2:22:56scope out of the capital reserve and it

2:22:58puts it in the bottom fund. Okay.

2:23:00>> Because the budgets were slightly

2:23:01adjusted by rise down to the tune of

2:23:03about 2.5% we were able to take 2.5% or

2:23:07$13 million out of CRF and move that

2:23:10into bond. So we were able to to work on

2:23:13it.

2:23:13>> Yeah. question was just like if any cost

2:23:16in projects prior to this limited your

2:23:18ability to

2:23:19>> I can't speak for how how they borrow

2:23:21but I was told I've got $400 million and

2:23:24$469 million approval yeah we have to

2:23:27make that work

2:23:28>> correct we have $400 million of voter

2:23:30approval for the bas projects that

2:23:33funding has been identified explicitly

2:23:35for these with the exception of RFK

2:23:38which was expedited to increase

2:23:41>> thank before we move on quick question.

2:23:44Um I I'm pretty sure you've answered

2:23:45this already, but just to, you know,

2:23:47fully understand on my end, how well

2:23:52what the the $2 million and $3 million

2:23:54uh uh items for all the schools uh below

2:24:00Daniel Green. Um

2:24:03is that need identified already or like

2:24:05what are we just throwing numbers? So

2:24:08these numbers were prepared as part of

2:24:09your stage two. So left field didn't

2:24:11have a role in developing this, but I

2:24:14can tell you that the way it was

2:24:16designed was for maximum flexibility.

2:24:18You're always going to have to do an MA

2:24:20alignment. Some districts do many.

2:24:22That's why you see in the official

2:24:24documentation from RID, this is

2:24:25amendment one. Once we move forward with

2:24:28phase 4 A, we have a better idea of what

2:24:30we want to do in phase 4 B. There is the

2:24:33potential that these numbers do change

2:24:35again. you know, does Bishop become 20

2:24:37million? Does, you know, there there are

2:24:39ways that we can move this around, but

2:24:41for a number of reasons I'll get into in

2:24:43terms of risk management where I need to

2:24:45cut phase four. We just have to cut it

2:24:47forward. Delays at this point. Well,

2:24:51there's a whole bunch of

2:24:53>> All right, let's keep moving. Thank you.

2:24:57>> So, um through this through this up here

2:25:00as well, equity in terms of spending,

2:25:02that's important. So, here's a basic

2:25:04graph of how money was spent in phases

2:25:06one through three in this light green

2:25:08and how money was proposed to be spent

2:25:10in in phase 4. Um, as you can see,

2:25:13pretty relatively even across the best

2:25:17it can be across the board based on

2:25:18population, but this is a it's a great

2:25:21split in terms of identifying areas that

2:25:23didn't get spent really as much in

2:25:25phases

2:25:27uh in phases one and three and

2:25:29increasing those numbers in phase four

2:25:31to help drive a little bit equity in

2:25:33terms of the overall construction.

2:25:39So goals that we we talked about

2:25:41earlier, how can you continue to

2:25:43implement vision 2030?

2:25:46This program will get through 3,000 new

2:25:49or like new suit seats by 2030. A big

2:25:53part of this was being able to provide

2:25:54newer used access to new or like new

2:25:58seats across providence. And I have a

2:26:00slide that can show you how to do that.

2:26:02How can we maximize our available cash

2:26:04flow? at least 100% of the currently

2:26:06available funding at the highest

2:26:08reimbursement rate. So why does that

2:26:11matter so much? I'll get into this a

2:26:12little bit more detail. But our MOA

2:26:15technically expires on June 30th, 2030.

2:26:19However, our bonus points, it's an

2:26:21additional 10% reimbursement enshrined

2:26:23in state law outside of Providence

2:26:26expires on June 30th, 2029. So, we

2:26:30already have a year taken off our

2:26:32schedule that I need to build to or the

2:26:34district could forfeit over $40 million.

2:26:38How can we reduce non- educational

2:26:39operating expenses? Well, a carnival

2:26:41closure alone saves $500,000.

2:26:44We also believe we have the data to show

2:26:47this, not in this presentation, but

2:26:49transportation costs should be helped as

2:26:51well. B by by being able to have

2:26:53families with younger and older kids in

2:26:56the same school, it reduces the amount

2:26:58of students that might need to take the

2:26:59bus because your younger student and

2:27:01your older student now go to the same

2:27:03school, which takes a look at that.

2:27:04Also, we're building energy efficient

2:27:06building systems across all of the

2:27:08schools. It's going to save you a ton of

2:27:10money since you're operating across. As

2:27:11you can see in Nine, you're making do

2:27:13with a 30-y old boiler, a 28y old

2:27:15boiler, and a gold boiler. But by

2:27:18putting in energy efficient appliances,

2:27:20getting as much off fossil fuels as

2:27:21possible, we aren't going to be subject

2:27:23to these crazy heating rates that have

2:27:26just skyrocketed 75% over the last year.

2:27:30How can we prioritize permanent high

2:27:32quality learning environments? I already

2:27:33kind of talked about this. We're trying

2:27:34to remove expensive remediation scopes

2:27:38such as the soils at Coin Valley. And by

2:27:41combining projects, we're reducing the

2:27:43amount that we're paying on stuff that

2:27:45doesn't deliver outcomes. I'm not again

2:27:46I'm not paying two contractors. I'm not

2:27:48paying two sets of architects. I'm not

2:27:50paying two sets of overhead profit, two

2:27:52insuranceances, two bonds. Um what

2:27:55lessons have we learned from phases one

2:27:56and three and and how can we implement

2:27:58them in phase four? It's a great

2:28:00question that came up tonight. School

2:28:01building committee. A lot of things look

2:28:03great on paper, right? But until we

2:28:05actually put them into operation, we

2:28:07don't know if these are going to be the

2:28:08right solutions. And we've already

2:28:10received feedback from those teachers.

2:28:12Trust me, those teachers have let

2:28:13everybody know what they like and they

2:28:15don't like about some of these new

2:28:16designs and we can incorporate that into

2:28:18this and how can we sequence our

2:28:20projects to manage swing space across

2:28:22PPS. It's a reality that two of these

2:28:25projects are scheduled to to run behind

2:28:28which means that those two swing space

2:28:30options aren't available. So, as we

2:28:31looked at this plan, we looked at how

2:28:33are ways that we can swing students in

2:28:36space. Dela is a great example of that.

2:28:39How can we reduce the amount of swing

2:28:40space we need? If we don't swing kids

2:28:42out of Cardinal Valley, I don't use

2:28:44spring space for Cardinal Valley. And if

2:28:46we can sequence our work at Roger

2:28:49Youngwoods, we don't have to move the

2:28:51Youngwood students out of there for a

2:28:53whole. So, we have a whole year we don't

2:28:55have to swing those people out. So, that

2:28:56was a consideration because swinging

2:28:59students costs money. It's money that

2:29:01doesn't go into operation go, excuse me,

2:29:05money that doesn't go into your final

2:29:06project. So,

2:29:10we do want to talk about some cost and

2:29:12timeline risks. Um, as I mentioned, for

2:29:15this additional 10% reimbursement, all

2:29:18phase 4 A projects must be substantially

2:29:20complete by June 30th, 2029. I think Joe

2:29:23did a good job explaining what

2:29:24substantial completion is. But if we do

2:29:28not have all of our projects completed

2:29:30by that time, we lose up to $46 million

2:29:33investment, which will absolutely affect

2:29:35future bases of projects. If Crystal

2:29:38doesn't get those,

2:29:40>> well, I just want to clarify the

2:29:43reimbursement is based on our debt

2:29:45service. So, we are going to we don't

2:29:47necessarily lose 46 million.

2:29:52We theoretically would lose the

2:29:53reimbursement on the 46 million

2:29:55environment which equates to about $4

2:29:58million in increased cost to the

2:30:00operating budget.

2:30:02>> So what what's the um in terms of that's

2:30:06all has to do with ride reimbursement,

2:30:08right? Correct. So it goes from what is

2:30:10it 91 reimbursements? 81.

2:30:12>> So our base reimbursement rate for these

2:30:14projects is 80.201%.

2:30:17When you add that 10% on it brings you

2:30:19up to about 90%. So that $4 million

2:30:22represents about 10 million or 10% of

2:30:24the debt service payment that we would

2:30:26be making

2:30:27>> and that is state law or what what

2:30:31>> the bonus points expiring strong in

2:30:33state law. I would take it out to the

2:30:34legislature to to move that whether or

2:30:37not I mean provinces obviously it's a

2:30:39city in Rhode Island. I'm sure you guys

2:30:41have a lot of pressure that you can put

2:30:42on that. But I think what they're

2:30:44concerned about is that they expend the

2:30:46province. They have to expend the bonus

2:30:48points for the other two billion dollars

2:30:50for construction that's going on in the

2:30:52state. And I don't know if the state

2:30:55budget would be able to capture that

2:30:58additional bonus

2:31:01political

2:31:03we will cross

2:31:06collaboration I think is more. I like

2:31:09the collaboration better too, but it's a

2:31:11reality of what we're working with. By

2:31:12adding extra year without those bonus

2:31:14points,

2:31:16you know, who's to say, but we

2:31:18absolutely don't like if I'm going to

2:31:19get these projects completed on time and

2:31:22>> how did the con the rise in construction

2:31:25costs factor into that great slides on

2:31:28that too. Thank you, K. Set me up for my

2:31:30slides. So, so construction costs have

2:31:33increased annually. Our budgets are

2:31:35fixed. labor material costs have

2:31:37increased by 27. I have some slides on

2:31:39some data. And if we don't remain on

2:31:42schedule, cost increases could miss us

2:31:44case growth damage, right? If I'm not

2:31:46able to pull in that additional

2:31:49reimbursement on the $46 million, do I

2:31:52now need to have to reduce the cost of

2:31:54my projects to make sure that Crystal

2:31:56can still fund her capital that she

2:31:58needs to in terms of um

2:32:02there we go. So, let's talk a little bit

2:32:04about management on schedule. So again,

2:32:07everything drives back to the

2:32:08substantial completion date on June

2:32:1030th. So all of these tasks are

2:32:13dependent on the preceding task being

2:32:15complet.

2:32:20We're in schematic design. Right now

2:32:23we're asking for your this is a

2:32:25presentation, but we we will be asking

2:32:26for your approval to move this forward

2:32:28to contracting

2:32:30main to main [clears throat] schedule. I

2:32:32have to do what's called early release

2:32:33packages. I think you you saw what Joe

2:32:36Danti talked about how they buy the job

2:32:39specifically at certain times. They

2:32:40don't buy it all at once. So by using

2:32:43early release packages, I can extend

2:32:45this as long as I can, but I still can't

2:32:49move that end. So I can increase our

2:32:51ability to design, but that just means

2:32:53I'm condensing my construction schedule.

2:32:57Um bottom line, if I cannot get the

2:33:00early release package reviewed, bid

2:33:01awarded support for construction start

2:33:03from August, we're jeopardizing that

2:33:05additional fund because the schools

2:33:09probably will not be substantially

2:33:10complete by June 30. So like how

2:33:12confident are you in um

2:33:17uh start date August 26?

2:33:25It's going to depend on

2:33:27>> board of contract referral then back to

2:33:30this committee and approvals back to

2:33:33>> I don't know exactly but I know that I

2:33:35need to go to you and I need to go a few

2:33:36other people's contracts.

2:33:38>> Yeah.

2:33:41>> That'll probably have to be what the

2:33:43first six months of next year. Yes.

2:33:45>> Yeah. So we'll see those in the winter

2:33:47and spring. I think one of the questions

2:33:48about the date is it August of 26.

2:33:52>> Oh, sorry. Yeah.

2:33:54>> August.

2:33:55>> Yeah.

2:33:57>> Like, did we already do this?

2:33:59>> Yeah. No, sorry. That was confusing all

2:34:02those.

2:34:03>> Yeah. But chairman, they these contract

2:34:05amendments from the phase 4A will come

2:34:07to the board of contract and supply, but

2:34:09will have to be referred to to like the

2:34:11threshold of the contract. still come

2:34:12back here for approval with you guys

2:34:16>> in order to start.

2:34:19>> Um that'll be probably late spring.

2:34:22>> So um right now we currently have the

2:34:24design builders under contract for their

2:34:26original dollars as you can see. Some

2:34:29have changed pretty substantially. With

2:34:31that being said, I have millions of

2:34:32dollars available to me. I can keep them

2:34:34moving forward on design for the time

2:34:37being. But when I start buying those

2:34:38early release packages, steel, concrete,

2:34:42uh site work, those are very expensive

2:34:44packages. So we'll need an injection of

2:34:46cash prior to or approval of the

2:34:49contract prior to March April for me to

2:34:52get all these contractors in the ground.

2:34:57>> In terms of risk management costs, so

2:35:00the projects are delayed, we can expect

2:35:01additional cost increases. That's just

2:35:03our list. Our current budgets have

2:35:06accounted for forecast inflation until

2:35:082027. That is critical. The budgets, the

2:35:10MOA budgets that you see before you have

2:35:12included cost escalation to that date.

2:35:15However, if it pushes out past that, we

2:35:18can expect additional costs. So, just to

2:35:19give you an idea, PBI growth for school

2:35:22construction projects 5 to 6% higher,

2:35:25and I do have the data to back this up.

2:35:27Uh, higher material prices and labor

2:35:28costs increase over schematic design. is

2:35:31between 6 and 7%. And the forecasted

2:35:34increases for public K through12

2:35:36projects show signs of stabil

2:35:38stabilization of 36%.

2:35:41But this is critical here for current

2:35:43market conditions. I currently have fuel

2:35:45costs over a $150 more than they were

2:35:48when this MLA was considered as part of

2:35:50the 2024 approval. I am paying tariffs

2:35:52now. It limits my subcontractor supply

2:35:55market. A lot of stuff can be made in

2:35:57the USA. A lot of stuff still isn't or

2:35:59still cheaper to buy abroad. As an

2:36:02example, up until a few weeks ago, it

2:36:04was still cheaper for most of my

2:36:06projects to buy their steel in Canada

2:36:08because American companies increased

2:36:10their prices as the tariff went up. Why

2:36:13they did that is a whole different

2:36:15discussion, but they raised their prices

2:36:17because Canada had to raise their

2:36:19prices. So with this new tariff that

2:36:22just went into effect, I now have a

2:36:24$220,000 change order for more ste. So

2:36:27for us it's important to keep these

2:36:29projects moving forward to not subject

2:36:31ourselves to additional we have no idea

2:36:34what new tariffs can we put on but the

2:36:36faster I move through these projects the

2:36:38better chance I have of what the

2:36:40conditions are now they are to buy out

2:36:43if I can budget it now and we buy it out

2:36:45in March we remove a ton of risk on the

2:36:49project

2:36:51we're hopeful again prices start to dip

2:36:54down you know we're hopeful that um fuel

2:36:57costs go back down but they are absolute

2:36:59drivers of these projects.

2:37:03So just to give you an example, here's

2:37:05January 2024 when this was approved.

2:37:08This is producer price index for new

2:37:10school buildings construction pretty

2:37:12significantly. You can see that rate

2:37:14just in these two years. Something that

2:37:16I'm dealing with which absolutely

2:37:17affected the way alignment because the

2:37:20budgets that were set in 2024 don't ray

2:37:22true with the cost of construction. Now

2:37:24I don't know if anybody heard of

2:37:26forecast back then if you have been

2:37:28feeling a 7% growth in construction

2:37:30which is way above and beyond what

2:37:32traditional inflation is. Here's an

2:37:34example of new construction. These are

2:37:37both we took a look at how projects have

2:37:39changed during the bid period. So if you

2:37:41see here our bid period of 2024 to the

2:37:45bid period expected for us in 27 costs

2:37:48have just kept continuing to increase.

2:37:50So the sooner I can get these guys under

2:37:52contract and have them sign my guarantee

2:37:54maximum price to lock in with that cost

2:37:56the better for our projects and this is

2:37:59the same thing with unfortunately with

2:38:01addition renovation school construction

2:38:03projects the delta is lower because we

2:38:06don't have to buy so much new but as you

2:38:08can see between 2024 and 2026 you have

2:38:12doubled what you had from 2020

2:38:16to 2020. the substantial cost increases

2:38:19in the construction market which just

2:38:20makes us again want to move forward

2:38:23spot.

2:38:26So

2:38:28that was great.

2:38:30>> I have some green slides up now.

2:38:34>> So what we did as far as building the

2:38:36opportunity in Darrison, we took a look

2:38:38at just a just a renovation of the

2:38:41project. Not that we addressing any of

2:38:43the educational programming. We looked

2:38:45at a renovation addition. At a minimum,

2:38:47an addition would need to be put on this

2:38:48building for an elevator because it's

2:38:50currently not up to code in terms of

2:38:52mobility. And then we looked at a full

2:38:55new construction option. As you can see

2:38:57here with option one renovations without

2:39:01kind of a typical renovation, and while

2:39:03this may be true for preK grade schools,

2:39:05I think a little bit more of this would

2:39:06be in yellow if it was just a middle

2:39:08school to be fair. Um, you can see that

2:39:11a full renovation, just a basic

2:39:13renovation, doesn't really capture to a

2:39:15lot of these items that you would have a

2:39:18middle school, preK through eight or a

2:39:20new middle school level.

2:39:22So, this was just informing some of the

2:39:25next slides that we did take a look with

2:39:27an architect and a builder as well about

2:39:30what these innovation what these

2:39:32different options were to do from an

2:39:34educational advocacy perspective.

2:39:36As having said that, you can see

2:39:40The numbers that we have here, estimated

2:39:42costs for a renovation at NAR without

2:39:47going to be addressing a lot of the

2:39:48educational enhancements is $64 million.

2:39:52It's primarily a health and safety

2:39:53renovation with some student um

2:39:55accessible projects. But having said

2:39:57that, this 64 million is only costs, but

2:40:01it's not your full GMP value to build

2:40:04into that as well. The per ride soft

2:40:06will account for up to additional 20% on

2:40:08the project.

2:40:11Having said that, council grace, you are

2:40:14correct. If this was to stay a middle

2:40:15school renovation and not a prek through

2:40:18eight renovation, we could see this

2:40:19number drop. And the reason for that

2:40:21being is that if it stays a middle

2:40:23school, I don't have to run new plumbing

2:40:25into the building for prek and K

2:40:26classrooms. That's an educational

2:40:28requirement of PPSD. If I don't have to

2:40:31trench through that existing force,

2:40:34bring in new mechanicals, that is a cost

2:40:36savings. I will say that it's absolutely

2:40:38cost saving. However,

2:40:42what are cost drivers for any renovation

2:40:44specifically to navigate? No matter

2:40:46whether you need to do a middle school

2:40:47renovation or if you're building a prek

2:40:49renovation, unfortunately, a lot of the

2:40:51big cost drivers remain the same. Energy

2:40:55codes,

2:40:58upgrades to the lateral system. In terms

2:40:59of structure, we have to upgrade lateral

2:41:01systems. Accessibility, we still don't

2:41:04have an accessible route to the main

2:41:06entry. Doors at the rear of the building

2:41:07have ramp transitions which

2:41:10yes and no. Building systems is a big

2:41:13one. Existing HVAC right here is the

2:41:16major one. Systems do not provide unreal

2:41:19air quality. The systems should be

2:41:21replaced. So no matter what project you

2:41:23do here, you still have these call

2:41:25strikes for renovation, whether it's a

2:41:27middle school or prek through8

2:41:28renovation. Having said that,

2:41:30Councilwoman, we do expect that if you

2:41:33turn into a middle school as opposed to

2:41:35a regular middle school as opposed to a

2:41:37prek options, we estimate you're saving

2:41:39about $6 million and not having to run

2:41:41those plumbing include to prek and

2:41:44classrooms. Now, that being said, you

2:41:46still probably want to have some

2:41:47additional educational enhancements to

2:41:48their building, and we'd have to take a

2:41:50look at where that budget would be.

2:41:54So, lots of questions, I'm sure.

2:41:56>> Yeah. Well,

2:41:58what um

2:42:02um

2:42:04what is the significance of this ramp?

2:42:06um

2:42:09um accessibility

2:42:12may have ramps transition.

2:42:15>> So it's a it's an it's an equity issues

2:42:18and uh right now students if they have

2:42:20mobility issues they can't get to all

2:42:22floors in the building but you're also

2:42:23putting them into the back of the school

2:42:24as opposed to the main entrance. So,

2:42:26it's it does become inequities for those

2:42:29ramps. We'd have to triple check the

2:42:32elevations to make sure that they're

2:42:33100% EA compliant. They function as they

2:42:36need to right now. But the issue with

2:42:38ramps as opposed to elevators in a

2:42:40building is ramps are very long and have

2:42:42very low slopes. I can only go up,

2:42:47you know, 5%. I can only go up to 5%.

2:42:51So, if I'm building a very tall ramp, I

2:42:53need to go way out across the job site.

2:42:56that site is pretty condensed into that

2:42:58neighborhood. So, in order for me to

2:43:00redo these ramps, if you're looking at

2:43:01more site work or things like that, but

2:43:04it's just not

2:43:04>> cost effective.

2:43:05>> He keeps talking about elevators that

2:43:07there is an elevator an elevator that's

2:43:10not being curved. You can't get a

2:43:11motorized wheelchair in there. It

2:43:13>> is.

2:43:20I'm gonna look at this most of course.

2:43:27[clears throat]

2:43:28[laughter]

2:43:28>> So I think we've already had space

2:43:31conversation as part of this. I did keep

2:43:32the slide just in case to kind of see

2:43:34where space is moving. Final decisions

2:43:37on space will come down from PPS in

2:43:40November. But as we said for our

2:43:42projects only Bartan and Dr. believe

2:43:45their champion Robbie Williams will be

2:43:47swinging young will be swinging out

2:43:49through the year and when that year

2:43:51happens and you're familiar with much

2:43:53more spring space options on your table

2:43:55because all of these three phase three

2:43:57projects

2:44:02um seats in enrollment project

2:44:03enrollment someone asked a question

2:44:05about oh you did council about about

2:44:07enrollment the projected 2030 enrollment

2:44:10is right about here after the conclusion

2:44:13of phase 4 way you'll have relatively

2:44:17new seats or newer likely seats access I

2:44:21should say access and where students

2:44:22choose to go based on school conditions

2:44:24and based on school choice it's a

2:44:25different conversation but we will have

2:44:27access to those

2:44:30um if you take a look at what the future

2:44:32statement is after phase 4 a um nine

2:44:35elementaryaries 10 days two middles nine

2:44:39highs 18 brand new schools um and then

2:44:43some considerations consider nothing is

2:44:47set in stone but is there the potential

2:44:49to move one more elementary school

2:44:52right here you can see and I will say

2:44:54this slide was not developed by me they

2:44:56had this slide for a while

2:44:58investment in this school

2:45:02>> wait who was that developed by you guys

2:45:04didn't

2:45:05>> yes this was developed prior to

2:45:07>> do you know what the um highlighted ones

2:45:10are

2:45:12>> oh they just have to do phase uh phase I

2:45:15believe within these are all things

2:45:22>> I think

2:45:28>> I'm not sure

2:45:39we can say from you this

2:45:43find out that I'm preaching in my eyes

2:45:45trying to

2:45:47No. Um, but

2:45:51it didn't happen.

2:45:54Um,

2:45:56so again, this is not going to take any

2:46:05but

2:46:07does get a lot of work. I think that

2:46:11in terms of what the principal said his

2:46:13priorities were and I know we've spoken

2:46:15with you security industry safe and a

2:46:19student centered enhancement you can

2:46:21absolutely get that and get a really

2:46:23nice budget what money to spare we

2:46:26estimated boiler project between $2 and

2:46:28$3 million we did a touring renovation

2:46:32in North Providence of similar size for

2:46:34$1.8

2:46:35billion. HBC renovations can get

2:46:37expensive pretty quickly if we're doing

2:46:39a full one, specifically because of the

2:46:42age of the building, opening up

2:46:44ceilings, potentially exposing us to

2:46:46hazardous materials that have to be

2:46:48removed. It can drive up the cost as

2:46:50well. But $28 million with those other

2:46:53two being such kind of lowcost drivers,

2:46:56>> get a significant rational project.

2:47:01I guess like the issue though is that we

2:47:03don't have those 28 million dollars that

2:47:04identify,

2:47:06>> right?

2:47:17>> I I know we're coming to you all.

2:47:23We um I mean I'll say that this is our

2:47:26conversation.

2:47:30>> So I got a little bit more information

2:47:31on val in case anything's interested. I

2:47:33know the question came up. I think I've

2:47:35already touched on this but you know

2:47:38this was one of the main one of the

2:47:40first slides we have on when we develop

2:47:42ideas.

2:47:44Here's some examples some of the most

2:47:46issues but not immediate danger to

2:47:49students but before I can do anything to

2:47:51the school I need to solve this and

2:47:53that's going to be a major cost driver.

2:47:55You can see just major cracks, you know,

2:47:59doors Georgia separating um the school

2:48:03was built in a landfill.

2:48:05>> So I have a question. Um obviously you

2:48:10or anybody in this room built that

2:48:12school

2:48:14and it seems like it was built in 1999

2:48:172044 billion which was $89 million back.

2:48:23So that's a school that did not live out

2:48:25his lifespan or the investment that God

2:48:28was made in it.

2:48:29>> So um you the big question that all of

2:48:34us ask is how do we make sure that

2:48:37>> oh it's a great question. So I can't

2:48:39tell you what they did back those

2:48:40projects but I can tell you we're we're

2:48:42high and that's we've already done phase

2:48:44one environmental assessments. We've

2:48:46already started our outreach with with

2:48:48DM. In fact, one of the first calls that

2:48:51we had was for DN the very beginning of

2:48:52this project. We're also allocating

2:48:54significant resources within the budget

2:48:56to make sure that we are covered in case

2:48:58we run into any dirty soils. But the

2:49:01main thing about it is is that we're

2:49:02doing our due diligence to make sure

2:49:04that where we're building if it does

2:49:06need structural enforcement that we have

2:49:08that includes geotechnical

2:49:10investigations about soil strata. What

2:49:14um environment phase one environmental

2:49:15also takes a look at the history of the

2:49:17site. What was it used for? prior. So I

2:49:20can't tell you what happened during then

2:49:22but I can tell you that we are not

2:49:24looking back and we don't have the data

2:49:26to prove to you that we're not

2:49:32>> you know

2:49:34and we're basing that on the fact that

2:49:36this side of that building is

2:49:42um solid

2:49:43>> solster

2:49:47I don't I can't tell you why two schools

2:49:49built both are relative at the same time

2:49:51pretty much a lot of the same building

2:49:53materials and everything like that one

2:49:54why one was chosen to be on piles and

2:49:57the other one was chosen to be slab on

2:49:59grade maybe they started differently I

2:50:01don't have all the details on that but

2:50:03so far from all the work that we've done

2:50:06okay in terms of investigating the soils

2:50:09and things like that and the work we've

2:50:10done at Williams we haven't seen any

2:50:12safety issues now there is going to be a

2:50:15little bit of ledge that we're going to

2:50:16deal with at MLK so led I just basically

2:50:19exposed bedrock. We are going to have to

2:50:21trim some of that back. That does have a

2:50:24cost driver. But what we're currently

2:50:26doing is we're looking at ways to design

2:50:28that building to use the slope to our

2:50:30advantage because that's um that's that

2:50:33that site slopes pretty severely from

2:50:35one side to the other. So instead of us

2:50:37digging out that slope and that ledge,

2:50:40which is very expensive, how can we

2:50:42design the building to work within that

2:50:44in that so you're not spending a bunch

2:50:47of money on stuff that no one sees. So

2:50:50the current designs have done a pretty

2:50:52great job.

2:50:53>> Okay,

2:50:53>> another quick question. Um, it's

2:50:56probably hard to answer, but

2:50:59uh, a new school building construction

2:51:02in today's time, what's like the like

2:51:04what's like the lifetime that that folks

2:51:07are are shooting for? Obviously, I know

2:51:09like maintenance and neglect and all

2:51:11that traffic, but what's like the

2:51:13average lifetime that a new school being

2:51:16built in today's uh, day and age um,

2:51:18it's projected to have? So if you're

2:51:20just talking about building

2:51:21infrastructure and things like that, as

2:51:23technology changes, of course, subs will

2:51:26become to get obsolete a little bit

2:51:27quicker than 50 years. But for all of

2:51:29the products that we specify as part of

2:51:31these projects, as well as the line

2:51:33construction regulations, we have to

2:51:34design to a minimum of 50 years

2:51:36lifespan. Now, certain building

2:51:38components will be replaced before that

2:51:40such as your roofing systems generally

2:51:42last 30 years as opposed to 50 years. um

2:51:45HBAC systems as new technology comes in

2:51:48or we replace boilers at 20 years as

2:51:50opposed to 40 years there will be

2:51:52capital expenditures over that but the

2:51:54basic shelf designs is at least 50 years

2:51:59um you reminded me of something that

2:52:01James ask uh or reimbursement

2:52:06um a school has to stay open for how

2:52:09many years is there like a penalty that

2:52:12the city would have to pay for So we

2:52:14don't

2:52:16>> uh I do not I do not know I know during

2:52:19the fun

2:52:21that

2:52:23>> Wow

2:52:36service

2:52:39the school become vacant temporarily

2:52:42they maycept ception but once it is

2:52:45rolled off the botto

2:52:49so it's with the bond and not the ride

2:52:51reimbursement.

2:52:54>> So ride has some regulations about if

2:52:58you accept a newer and fewer bonus point

2:53:00which is an additional 5%

2:53:03you cannot reopen those schools as

2:53:07schools in the shortterm period. So

2:53:09let's say you were to close carnival val

2:53:12you were to keep it as an empty building

2:53:14and then five years from now you wanted

2:53:17to reopen it with your enrollment and

2:53:18things like that that would happen but

2:53:21having said that ride could try to claw

2:53:23back a little bit of that money. So for

2:53:26a lot of our clients, what they want to

2:53:28do is get that off the ropes as quickly

2:53:30as possible by transferring care of

2:53:32control of that building to the city or

2:53:34for a lot of our clients, they'll

2:53:35demonish the buildings because they're

2:53:37not heating it and mauling it and doing

2:53:39everything else that cost operation,

2:53:42>> right?

2:53:44>> That's cool.

2:53:46>> Um just enrollment alignment. I just

2:53:49have a slide on this just in case you're

2:53:51understood, you know, why again

2:53:52consolidation is needed.

2:53:55um similar details on enrollment

2:53:58alignment. Um here's a look at what

2:54:01group of post foreign school project in

2:54:04general

2:54:07and then I've also included upcoming

2:54:10statement of engagement across all of

2:54:12the projects

2:54:17and then here's some examples. So all of

2:54:20the all of the meetings that we've had

2:54:23per school are also listed out here. So

2:54:26you can see the types of engagement that

2:54:27we did, what the dates were, who those

2:54:30stakeholder

2:54:33were.

2:54:38>> Thank you for

2:54:44Any

2:54:51last

2:54:53questions,

2:54:55comments, concerns?

2:54:59>> No.

2:55:06>> Yes. Thank you, chairman.

2:55:10>> Thank you. for us. You touched upon a

2:55:12little bit, but could you kind of

2:55:13describe this committee again just an

2:55:15overview of your swing space plan um and

2:55:19identify what dependencies you have with

2:55:21previous phases and what schools are

2:55:24needed to swing into

2:55:27projects that were done in the previous

2:55:29phase and are there any convincing PBS

2:55:32looking to activate any um sites that

2:55:35are not currently being used? Um my just

2:55:39concern is that if anything is delayed

2:55:41what backup plans do we have to ensure

2:55:44that we are swinging

2:55:46>> that's why

2:55:48UC is doing for

2:55:51I would like to demolish this building

2:55:53for that first day as an example or

2:55:55start my demolition but we are looking

2:55:58at this as what is the bigger sin us

2:56:01starting a few weeks late and not

2:56:04demolishing the schools until we're

2:56:05absolutely sure about all the basic

2:56:07projects that's coming in on time

2:56:08because if we if we demolish a school

2:56:12and then you have no home for those 800

2:56:14students for even a week that's a pretty

2:56:17substantial problem. So once PPSD and

2:56:20the city give us 100% buy in start

2:56:23demolishing the schools but as a

2:56:25precaution I have our schedules start in

2:56:27August so that we absolutely know the

2:56:31substantial completion dates can hit on

2:56:32June 30th we can move students in before

2:56:35we start them.

2:56:37>> What schools are you depending on from

2:56:38phase two and three to get done swing

2:56:40in? Well, we've tried to mitigate that

2:56:42by by swinging in place in Delto, not

2:56:46moving that. Um, I think the two

2:56:49projects that that um that Joe mentioned

2:56:52that are tracking behind are the ones

2:56:54that we're we're looking at. Um,

2:56:57>> and

2:57:00uh and again, our schools don't swing

2:57:02into those. That's how we've worked out

2:57:03our plan, but there's a high level of

2:57:06confidence in the other schools

2:57:08completing on time. So, we don't we

2:57:10don't have that concern. But, I mean, if

2:57:12we're talking in worst case scenarios

2:57:14and one of those schools doesn't

2:57:15complete on time, I would have to hold

2:57:16demolition of one of my schools until

2:57:19we're sure that those kids can move.

2:57:21Which is why I'm I'm nervous about

2:57:23pulling the trigger on demolition until

2:57:25everyone feels really good about where

2:57:27we are.

2:57:32>> Did you want to answer?

2:57:33>> Yeah, I was um so here in Canada, we

2:57:36know we're going to be delayed. Um the

2:57:39the Messar and Pogy projects are

2:57:41currently on schedule such that we can

2:57:44utilize their current building and

2:57:46Laurel Hill as swing spaces for uh some

2:57:50of the phase four be moving into them.

2:57:53Obviously to the extent that OBC said

2:57:56schedule slips on those projects and

2:57:59they wind up no longer on track for

2:58:02completion by start school that would

2:58:04create issues for us. We do have one

2:58:07additional school that um is uh was

2:58:11under consideration state

2:58:14with the Lima school. Um but in a worst

2:58:17case scenario, we could use that as an

2:58:20option to solve for one of these

2:58:22additional projects or to uh become

2:58:26behind schedule.

2:58:30to Chris's point last last beh you know

2:58:34staying in place

2:58:38one of these

2:58:45followers

2:58:47>> not exactly for that um we all know is a

2:58:51fairly new

2:58:53>> which is not

2:58:55>> yes

2:58:57>> how are we going to make sure that we

2:58:59don't go through the same issue

2:59:02about the heating or air conditioning or

2:59:05whatever because they already have had

2:59:08issues.

2:59:09>> So

2:59:11are you changing what you put in? What

2:59:13what are you doing? Because we don't

2:59:15want to go through that.

2:59:16>> Let me just give you one statuto way

2:59:19that what happens before technically

2:59:21can't happen again. So there is a law

2:59:22task which doesn't believe 3% 3% of your

2:59:26operating budget every year has to go

2:59:28into the maintenance and repair of your

2:59:31schools. that did not exist prior to a

2:59:34few years ago. So, individual school

2:59:37budgets had a long

2:59:40encouraged the city at that time to not

2:59:43put an air conditioner in to put a deer.

2:59:46We're not doing that anymore.

2:59:47>> That's what I want. Okay. I'm sorry. I'm

2:59:50sorry. I was talking big picture. Uh

2:59:52well, you can you can finish yours too,

2:59:54but I want to that's not any other

2:59:58>> I think you know you have a difficult

3:00:01job as stewards of taxpayers are

3:00:04incredibly important but 60% of the city

3:00:07has students that do not attend schools

3:00:10right so you have to balance your budget

3:00:12every year that school what money goes

3:00:15into school funds and what money goes

3:00:17into not school funds and then before

3:00:20that 3% % operating requirement existed.

3:00:25We saw a lot of people trying to make

3:00:27sure that their budget would work and

3:00:28they would defer meanings, deferments,

3:00:30deferments, deferments. Now, by having a

3:00:33set standard you have to invest every

3:00:35year or you could potentially lose out

3:00:38on housing aid, it elimmits that ability

3:00:40to constantly defer you have 53% of your

3:00:43operating budget.

3:00:46>> I say I don't know. Uh oh.

3:00:50>> And it's a percentage of the school

3:00:51department's budget, not our operating

3:00:53budget.

3:00:56>> But when departments had to manage their

3:00:58budgets, we overall city budget deferred

3:01:01maintenance was one of those things that

3:01:03in every single island I did.

3:01:10>> That's it. I [clears throat] could use

3:01:12the air condition.

3:01:22>> I don't have any other questions. Does

3:01:24anyone else?

3:01:29>> Yeah. Yeah.

3:01:32Um uh Chris, I just want to thank you um

3:01:35a tremendous amount. Um, like I said,

3:01:37this is going to be uh continuous

3:01:40conversations.

3:01:41>> Yes.

3:01:41>> Um, you know, as honestly speaking, the

3:01:44the past two years have been a little

3:01:47difficult, you know, when we don't have

3:01:49full control of of our schools. Um, but

3:01:51but now that that's not the case

3:01:53anymore. Um, you know, and and we're

3:01:56seeing some challenges come up with some

3:01:59timelines and stuff. It's, you know, a

3:02:01huge responsibility that we all as 15

3:02:05city councilors um have to engage. I'm

3:02:08obviously want to give a huge shout out

3:02:10to Kyle uh from our staff who's been a

3:02:13tremendous amount of help and was

3:02:15>> going to continue to be a tremendous

3:02:17amount of help. Obviously, Brandon,

3:02:18thank you for being here as well.

3:02:21>> Um yeah, just want to say thank you and

3:02:23I'm excited to keep working as

3:02:26collaborative with you as possible.

3:02:28Crystal obviously

3:02:30seemed none of this is possible without

3:02:32you guys. So thank you. Um and with that

3:02:35being said I will entertain a motion to

3:02:37adjourn. Motion made by signing of

3:02:41animal saber.

```*