2026-09-28 - Board of County Commissioners Briefing

Summary

Based on auto-generated captions; names and numbers may be misheard. Captions start at 00:26 and the briefing runs to about 1:18:50; speakers are not labeled, so many remarks cannot be tied to a named commissioner.

Time on topic (from transcript timestamps; approximate, includes side talk):

Topic Minutes Share
Countywide Data Center Moratorium 59 76%
Horizons Residential Care Center Septic Easement 6 8%
Zero Williams Road Surplus Property Sale 6 8%
Unified development ordinance miscellaneous text amendments 5 6%
Other business 2 3%
  • Monday briefing for the Thursday, October 1, 2026 meeting.
  • Chair Gloria D. Whisenhunt presided and County Manager Shontell Robinson walked through the agenda; a discussion item on data centers followed the agenda review.
  • The main event was a proposed six-month data center moratorium, which did not have the votes and was dropped.

Unified development ordinance miscellaneous text amendments

01:01-05:39

  • Public hearing item for Oct 1: staff bundle of text amendments to chapters 3 through 9, presented by Chris Murphy. Three clarifications (a five-foot facade offset for indoor storage, services and retail buildings; tree-save parking reductions, to be revisited in a broader parking amendment because the state ends parking minimums Jan 1; commercial and industrial subdivisions not limited to three lots on private streets).
  • Three changes to remove conflicts: townhomes and multifamily of fewer than four units exempted from design standards under a state law change; child day care space standards aligned with the state; and removal of the renewal requirement for land clearing and inert debris (LCID) permits, which has been in the ordinance since 1995 and never enforced.
  • Ten numbering, spelling and grammar fixes. Planning Board recommended approval unanimously May 14 with no opposition; Winston-Salem City Council adopted it the previous Monday. No questions.

Other business

05:39-07:41, 19:35-20:08

  • October as Domestic Violence Awareness Month and Bridges to Hope Family Justice Center resolution (wear purple Thursday); proclamation for the 25th anniversary of Winstonet; Sept 17 minutes not yet circulated by the clerk.
  • Forestry agreement with the state Forest Service: county share 40% (about $96,597 of roughly $241,000; figures as captioned), lower than last year because a fire truck was bought then. A commissioner asked whether the county has a fire dozer and what one costs; Cooperative Extension director Leslie Rose (name approximate) will check.
  • Two tax refund resolutions and the August benefit cap and financial reports; no questions.

Horizons Residential Care Center Septic Easement

07:42-13:26

  • Chelsea Swain explained that the county unknowingly paved a parking lot over the septic repair area of Horizons residential care center (on a lease dating to the late 1970s, now about 13 acres), and the item approves a septic agreement and access easements across Horizons Park land to fix that; no charge to Horizons.
  • Chris Weavil said the repair area is about 80 feet north of the field serving two new buildings, just outside the lease area, in the path of the multimodal trails now being built; no work is planned.
  • Dan Besse asked that the easement define the access route or a county review-and-approval process so users do not damage trails or clear extra land; staff said they would work with Horizons on that.

Zero Williams Road Surplus Property Sale

13:27-19:34

  • At the previous meeting the board delayed declaring the land surplus. The county then got a new offer of $328,450 from James Perkins (adjoining owner); the first bidder declined to raise his offer and his deposit is being returned. The tax department's suggested value was about $284,600.
  • If approved Thursday, the clerk would advertise in the Winston-Salem Journal for a 10-day upset bid process; any sale would come back to the board. A commissioner noted the offer more than doubles the earlier one (over $16,000 an acre).
  • Questions covered where it is advertised (newspaper, plus the county website), what the buyer uses the neighboring parcel for (staff did not know), and one commissioner's concern that nobody monitors the property; staff said grounds crews had posted no-trespassing and no-hunting signs the previous week. The county attorney said existing zoning (at least partly Yadkin River district) applies to any buyer.

Countywide Data Center Moratorium

20:01-1:18:46

  • Discussion item. The manager said staff takes no position for or against data centers. Dan Besse presented his own draft ordinance for a six-month countywide moratorium on new large-scale data center approvals under state statute 160D-107, modeled on Alamance County's. It would have exempted projects with vested rights, and included a work program to gather expert and out-of-state (for example Loudoun County, Virginia) input and consider noise rules, industrial wastewater pretreatment, and rules for areas not zoned for data centers. The board would first vote Thursday on whether to call a hearing, the earliest hearing being Oct 15.
  • He said two proposals likely to come back are exempt: the denied Rural Hall request (Project Iron Spur Data Center Rezoning (F-1669), rumored to return) and another on land already zoned for it.
  • County Attorney Gordon Watkins warned about Ecotip West LLC v. Chatham County (as captioned): a summary judgment for a data center after Chatham's moratorium, with attorney fees awarded and damages possibly in the millions; he recommended against a moratorium, said the downzoning law blocks most substantive limits, and said that if the board proceeds it should set aside a litigation contingency. He noted about 14 counties have moratoria, and that two bills (one giving counties authority over data centers, one ending downzoning) each passed one chamber but not both.
  • Debate: a commissioner asked whether one member drafting the ordinance invites a bias claim (attorney: some risk, mostly if someone says they will never approve one). Besse said he drafted it himself because staff was not going to produce one; Watkins and the manager said they had hoped for language that answered staff's legal concerns and that nobody on the board had directed them to draft one. Several commissioners voiced support for studying the issue and thanked the attorney for candor.
  • Reasons against: a commissioner said he would rather judge a specific proposal, as with Rural Hall, and was wary of the risk; another did not want to risk higher property taxes to pay a data center. Besse said gray-area proposals could come and that the legislature may not act until late November or December, and he named costs to residents' electric and water-sewer bills as unreviewed.
  • Outcome: Besse conceded he did not have the votes and, for the record, asked supporters to raise a hand: only he and Tonya D. McDaniel did. This was an informal show of hands at the briefing, not a recorded vote; no hearing was called. The chair and another commissioner thanked him; one commissioner objected that asking for the show of hands was not collegial.
  • Captions do not identify most of the other speakers, so the other five members' positions cannot be tied to names.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:26Good afternoon. We welcome our staff and

00:29our visitors. Uh we're here today for

00:32our briefing and it will in uh for our

00:36our meeting on Thursday, October 1st,

00:392026.

00:41Um and we will be we have a a discussion

00:45item after our briefing. So I will turn

00:48this over to our manager.

00:50>> Thank you, Madam Chair, and good

00:51afternoon, commissioner, staff, and

00:53guests. Agenda item number one is a

00:55public hearing on an ordinance amendment

00:57proposed by planning and development

00:58services staff to modify sections in

01:01chapters 3456 78 and nine of the unified

01:04development ordinances. Chris Murphy our

01:07planning director will brief this item.

01:11>> Good afternoon madam chair Mr.

01:14>> Good afternoon

01:14>> Mr. Vice Chair members of the board. Uh

01:17this is uh a

01:21staff change proposed uh sorry a text

01:24change proposed by staff. We do these

01:27every once in a while. We've collected

01:29items where we have found discrepancies

01:31or errors, spelling, numbering and or

01:34there are things that we need to correct

01:36uh related to uh clarification and or

01:40removing conflicts with other uh state

01:43or local regulations.

01:46UDOccc35

01:48includes three amendments that provide

01:50clarification to ordinance requirements.

01:52Um those three include the building

01:55offset uh dimension for the use indoor

01:58uh storage services retail and what that

02:02means is when you have a certain length

02:04of a building you have to either provide

02:05a reject a recess or a projection to

02:08kind of break up that facade. But we

02:10don't give currently a dimensional

02:11requirement related to that. So, we've

02:13had some arguments with architects that

02:15six inches is sufficient. So, um we have

02:19put a measurement in there that we think

02:20five feet uh should be um that

02:24measurement. Another one of those

02:26clarifications deals with how we uh do

02:30parking reductions for tree safe. Keep

02:32in mind this text amendment was started

02:34well before the general assembly took

02:36away parking requirements. That will go

02:38into effect January 1. We're going to go

02:40ahead and pro proceed with this, but um

02:44this will be coming back to you probably

02:46in our overarching parking text

02:48amendment that will come before you. Uh

02:50but just know we were already in the

02:52process of clarifying this reduction um

02:55whenever that change was made at the

02:57statute at the state level. Uh and then

02:59the final ordinance clarification is

03:02just providing clarification that

03:03commercial and industrial subdivisions

03:06are not limited to three lots on private

03:08streets.

03:09um

03:12transition from that to other uh we have

03:14three other amendments that remove

03:15conflicts with other state, county or

03:17local regulations or long-standing

03:21policy and or um

03:26process.

03:27Um the first one of those is the MLKO.

03:31Uh we have to exempt town homes and

03:34multif family units or developments of

03:36less than four units. And that's because

03:39the state statute was recently changed

03:41that basically classifies that as

03:44residential um under the residential

03:46code and you can't have design standards

03:48for things that fall under the

03:49residential code. So we have to make

03:50that exception. Uh historically we have

03:54had a um square footage measurement for

03:57both indoor space and outdoor play area

04:00that's been more restrictive been a

04:03higher standard than what the state has

04:04had for child daycare centers. And you

04:07know, we you heard recently uh that

04:11again, I think everyone knows that child

04:13daycare, we need more of it. So anyway,

04:16we can try to make our standards be

04:18consistent with the state, we wanted to

04:20take that opportunity. So that's a

04:21clarification in this. And then the

04:24final one is something um that has been

04:28in the ordinance since 1995. I've been

04:30here 26 years and we have never required

04:33an LCID to be renewed

04:35uh either at the elected body level or

04:37at the board of adjustment level. So

04:39again, we have 31 years of that being in

04:43there and it's never been a requirement

04:44for any renewal. We think it should be

04:46removed if you meet the findings of fact

04:48related to the issuance of a special use

04:50permit initially.

04:53We have ways to handle things if you run

04:56a foul of the ordinance, but if you met

04:58the findings of fact, there shouldn't be

05:00a reason to go back through for a

05:01renewal. Those are kind of the six that

05:04run beyond just standard um corrections

05:09to numbering or lettering, misspellings,

05:11and grammar. We have 10 of those that

05:12are also sandwiched in this text

05:14amendment.

05:16And with that, uh this was heard by the

05:18planning board at their May 14th, 2026

05:20public hearing. There weren't any

05:22speakers in opposition and following the

05:23public hearing, the planning board did

05:25vote unanimously to recommend approval

05:26of this text amendment. And it this also

05:29was adopted by city council on Monday

05:32night last week. And with that, I stand

05:35ready to answer any questions or go into

05:36any other detail that you might want to

05:38discuss.

05:39>> Questions?

05:42>> Thank you, Chris.

05:43Agenda item number two is a resolution

05:45recognizing October as domestic violence

05:48awareness month and in recognizing the

05:49efforts of Bridges to Hope Family

05:51Justice Center for Scythe County. We'll

05:53have staff here to recognize it on

05:55Thursday. And just a reminder, wear

05:57purple if you have purple for that.

05:59Agenda item number three is a

06:00proclamation recognizing the 25th

06:02anniversary of Winston Net. Um and Chair

06:05Wizenhunt will be presenting that

06:07proclamation at one of their upcoming

06:09events. Agenda item number four is

06:11approval of minutes for the meeting of

06:13September 17th. Madame Clerk, have those

06:15gone out yet?

06:17>> They have not, but I hope to get them

06:18out either this evening or tomorrow

06:20morning. Thank you. Agenda item number

06:22five is a resolution authorizing

06:23execution of an agreement with the state

06:25of North Carolina on behalf of its

06:27Department of Agriculture and Consumer

06:28Services for Forest Services. Leslie

06:31Rose, our cooperative extension

06:32director, will brief this item.

06:37>> Good afternoon, commissioners. So this

06:40agenda item would approve a contract

06:42with the North Carolina Department of

06:43Agriculture and Consumer Services, North

06:46Carolina Forest Service for Forcy County

06:49share of the costs associated with our

06:51county forestry department. The total

06:54cost for this fiscal year uh is

06:57$241,000494.

07:01The county share of that is 40% being

07:04$96,597.

07:07This is a decrease from last year. Uh

07:10last year they purchased a firet truck.

07:12They don't have that expense in there

07:13this year. Um and this has been included

07:16in the approved budget. I'm happy to

07:18take any questions you might have.

07:21>> Questions?

07:22>> Do we have a fire dozer?

07:25>> I don't believe so, but I can check into

07:28that and get back with you.

07:31>> How much does one cost?

07:33>> I also don't know that, but can look

07:34into it.

07:38Okay,

07:39other questions.

07:41Thank you, Leslie.

07:42>> Agenda item number six is a resolution

07:44approving the septic system agreement

07:46and authorizing the grant and execution

07:48of an easement to Horizon's residential

07:50care center across a portion of Force

07:52County owned real property. Chelsea

07:54Swain, our deputy general services

07:55director, will brief this item.

07:57>> Good. Good afternoon. This item is to

08:00approve a septic system agreement with

08:02Horizon's residential care center and

08:04grant access easements to Horizon's

08:06across a portion of Horizon's Park

08:09property. So, a little background on

08:11this item. As you all probably know,

08:13Horizon's residential care has um had a

08:16lease at this property on Horizon's Lane

08:18since the late 70s. They started out

08:20with about 35 acres of property and over

08:23time that's been amended and fluctuated.

08:25Currently they lease about 13 acres of

08:28property and with that they operate a

08:30septic system. The lease that they

08:33currently have does reference the septic

08:35system and it stipulates that it is

08:38their responsibility to maintain that

08:40system. However, the system is outside

08:42of their lease bounds.

08:44Unfortunately, the county unknowingly

08:46put a parking lot over the repair area

08:50for their septic system earlier this

08:52year. And we found out about it when

08:54their septic operator um notified us of

08:56that. And you may be thinking, how did

08:58we do that? And we just did not know

09:00that the repair area was where it was

09:02and there was nothing in the process of

09:05um constructing the parking lot that

09:06would have triggered an environmental

09:08review of that to tell us that that's

09:10where that was. So, we are correcting

09:12that mistake and error. And this item

09:16would approve the septic agreement and

09:19would grant them being Horizons and

09:22their operator access to cross into the

09:24county park property to maintain their

09:27septic system and pump their tank and

09:29access their repair fields. So, this

09:31really just puts Horizons in their

09:33system back in compliance with state um

09:35requirements. I'm happy to answer any

09:37questions and Chris Weevil is also here

09:38if you have any questions of him.

09:40questions.

09:42>> So, we're not charging them for an

09:44easement because we put a parking lot

09:46over the area in between.

09:50>> Well, we're Yes.

09:52>> Okay. Thank you.

09:55>> Um,

09:55>> Commissioner Vessie,

09:56>> thank you. Um, is there any um

10:02specific access roadway that they're

10:04presently using uh that this would apply

10:08to? Um,

10:11>> yes, they do have an access path and

10:12Chris and his team have dropped some

10:14recent gravel there to kind of make that

10:16a little bit nicer for them to access

10:18their tank to pump the tank.

10:20>> Would the easement limit them to access

10:23using that particular roadway?

10:27>> The roadway only goes to the tank. It

10:29doesn't go to the repair area as well.

10:32So, they would have access to go to

10:34multiple places, if that makes sense.

10:36But there's not actual roads going to

10:39all of those places.

10:40>> Okay. Um, is it possible or does the

10:43proposed easement define uh their

10:46pathways that they can use? Um,

10:50>> I don't believe we defined a pathway for

10:53that, but I'll let Chris speak to that.

10:54He's worked most on this.

10:59>> Good afternoon, commissioners. Um, no

11:01sir. Uh, there's not a defined path at

11:04the moment. All that we're doing or all

11:06that the state has required us to do is

11:08to identify a repair area. There's no

11:11actual work being uh taking place. Um so

11:14the the repair area that they have

11:16identified uh is about 80 feet north of

11:20the uh the current septic field for the

11:23two new buildings that that they just

11:24built there. Uh so it's just outside of

11:27their current lease area. So u the

11:29pathway is right off of an access road

11:32that they've got to the building. I I

11:34say that would be the the the area that

11:36I would, you know, most certainly think

11:38that they would use. Uh so there's not a

11:40lot um we're actually con uh in the

11:43process constructing the um Horizon's

11:46Park multimodal trails. So most of the

11:49spot has been cleared. Um the state has

11:52allowed us uh if we ever have to get in

11:54there and do the construction for the

11:56repair area. there's some trail that

11:58will be uh affected, but once the repair

12:00area or once the if the repair area is

12:03ever used, uh the pathways can go back

12:05on top of that. It's not going to

12:06preclude them from doing any of that

12:07type of work. So, I don't know if that

12:08answers your question or not, but

12:10>> um

12:12not [clears throat] quite. or your

12:15answer suggests that um a

12:19an access way could be defined and

12:22that's what I'm interested in seeing in

12:24this kind of easement rather than

12:26leaving open the question of how do you

12:29get the access because often um even a

12:32well-meaning uh user can be more

12:37destructive than necessary in terms of

12:39clearing additional uh area or you know

12:43imposing on uses like the trail.

12:47>> Correct. I don't know if I can answer

12:49that. Um we like I said, we do not have

12:51that that we've got the area defined. We

12:53do not have a pathway at this particular

12:55point in time. Um I don't know the way

12:57the contract reads, Chelsea. If they

13:00ever had to do anything at that point in

13:02time, we would have to maybe direct them

13:04where they could go.

13:05>> We would we could work with them to do

13:07that. Yes.

13:08>> Okay. If Yeah. If you um can either

13:10define it or define a process for the

13:14county reviewing and approving the the

13:16route that they that they use, that

13:18would be that would satisfy that

13:20question. Thank you.

13:24>> Other questions? Thank you.

13:27>> Agenda item number seven is Chelsea's as

13:29well. It's a resolution declaring

13:31certain real property as surplus and

13:33authorizing publication of an offer to

13:34purchase county-owned real property by

13:36negotiated offer advertisement and upset

13:38bids procedure.

13:40So, as you all recall at your last

13:42meeting, we brought this item to you.

13:44This is to declare property at zero

13:46Williams Road as surplus and authorize

13:48the publication of an offer to purchase

13:50for upset bids. At your last meeting,

13:53you all voted to delay declaring this a

13:55surplus and delay advert um voting to

13:58advertise the offer. Since that time,

14:00the county has actually um received an

14:03additional offer from another gentleman,

14:05James Perkins, in the amount of

14:07$328,450.

14:10Um I did go back to the original offer,

14:13Mr. and um told this to him and asked if

14:16he, you know, would con was interested

14:18in increasing his offer to meet or

14:20exceed that. and he has bowed out from

14:23that process. We have are um in the

14:25process of returning him his deposit

14:26that he had already deposited with the

14:29county. So therefore, this item would is

14:32similar in nature, but actually would

14:34approve a different offer from a

14:35different individual. And again, this

14:38item would approve the offer from James

14:40Perkins in the amount of $328,450.

14:44And so just, you know, as a reminder and

14:47refresher, this is the property that the

14:49tax department had um suggested an

14:52equitable value would be around

14:54$284,600.

14:56So the current offer exceeds that

14:57amount. And if you all were to vote on

15:01Thursday to approve this item, that

15:03would then give the clerk authority to

15:06publish in the Winston Salem Journal the

15:08offer and um start the upset bid

15:10process. That would be a 10-day process.

15:12We would continue the upset bid period

15:14until no additional offers were

15:17received. Then we would work with the

15:19individual or entity who had the highest

15:21offer and negotiate a purchase agreement

15:24with them. We would then bring that

15:25agreement back to you all to approve for

15:28the actual sale. So any action on

15:30Thursday would not be approving a sale,

15:32just declaring this property as surplus

15:34and um approving to publish the offer

15:37for advertisement. So happy to answer

15:39any questions. questions.

15:42>> Is that put in the classified in a

15:44journal? Is that where it's advertised?

15:46>> It is in the Winston Salem Journal. Yes,

15:48sir.

15:48>> Is any place else?

15:50>> Um, we have listed them on our website

15:53before,

16:00but I was had wondered what

16:03advertisement it would uh

16:07be.

16:11other questions.

16:12>> Miss manager, did on the uh advanced uh

16:16email, did you put that in red so I

16:18would recognize it?

16:20>> I put it in red so everyone would

16:22recognize it. Yes, sir.

16:25>> Thank you.

16:27That more than doubles the offer on the

16:30property, I would think. Puts it up over

16:3216 grand an acre, something like that.

16:35>> Yes, sir. So, the adjacent owner who has

16:38made that offer, is that property

16:39currently used for residential or

16:43commercial purposes or is it vacant?

16:46>> There's a structure on it, but I don't

16:48know what he uses it for. Um, I don't

16:52believe he lives there all the time

16:54because he made reference that he lives

16:56downtown.

16:58>> Well, is it a residential structure?

17:00>> I don't know. I can't see it from the

17:02road and I haven't driven back there.

17:04>> Okay. Thank you.

17:07I do. Oh, go ahead.

17:08>> Go ahead, please.

17:09>> I do want to um put on the record as it

17:12relates to the use of this property, if

17:16I am reading this correctly by way of

17:19the um Mr. Perkins who is um proposing

17:22to um purchase the property that it

17:26reads only the property adjacent to this

17:28county land. It concerns me that no one

17:32is monitoring the use of the property. I

17:35would feel much safer owning this parcel

17:37and proper and properly managing it for

17:40safety. So I don't want to broadly

17:44assume he's just going to hold it just

17:47to make sure that it is used in a safe

17:50way. So did he indicate anything else

17:53that he was interested in?

17:54>> He did not. No, ma'am.

17:57I will say though that our um grounds

17:59team was out there last week and they

18:01did post quite a few signs on the

18:04property. You know, no trespassing,

18:06hunting is not permitted, those type of

18:07things.

18:10>> Mr. attorney if um

18:14and it's likely that somebody else may

18:17own it other than the county at some

18:19point, but would the owning not um

18:23clarify the uses that could be there?

18:29It it would current it it's currently

18:31zoned. Um I'm sure at least part of it

18:34is in the Yadken River zoning. I'm not

18:36sure if the entire property is um but

18:40the zoning would still apply unless

18:42somebody comes in and applies for a

18:44reasonzoning.

18:45>> Okay.

18:47>> Yes.

18:48>> Um can you show us where on the map uh

18:51the um the adjacent land owner that make

18:54that made the offer property is? Yes.

19:26Thank you.

19:30>> Are there further questions?

19:34>> Thank you.

19:35>> Agenda items eight and nine are refunds

19:37by the tax assessor collector. Eight is

19:39in the amount of $1,2876

19:43and nine is in the amount of $16,22169.

19:48And then we have our reports. 10 and 11

19:51are our reports. 10 is the August

19:52contributionbased benefit cap report and

19:5511 is the August financial report.

19:59And those are all of our agenda items.

20:01Um we're certainly happy to begin our

20:03discussion on data centers if no one has

20:05any other questions about the agenda.

20:08>> I think we're ready.

20:12What I'll say, I'll turn it over to um

20:14Commissioner Bessie has provided a

20:16proposed ordinance um for a data center

20:20moratorum. Um staff is here to answer

20:24any questions, provide any updated

20:26information. I do just for the record

20:28want to state that staff has taken no

20:31position in regards to whether we're for

20:33or against data centers. Our job as

20:36staff is to provide you with information

20:38and education on what the matter is. And

20:41so whether it's um you know it's appears

20:45to be supportive or not supportive, it

20:47has nothing to do with that. It has

20:48everything to do with our jobs providing

20:50education and information. With that,

20:52I'll turn it over to Commissioner

20:53Bessie.

20:54>> Thank you very much. Um,

20:57Madame County Manager and Madam Chair,

21:00um, what you have before you in this

21:02document,

21:04uh, is, uh, proposed ordinance imposing

21:08a temporary moratorium, and moratorium

21:10just means a pause. Uh, a temporary

21:13moratorum on the issuance of approvals

21:15for the development of large-scale data

21:17centers in Foresight County. Um

21:21this to the best of my understanding uh

21:25meets all the legal requirements for

21:27what is to be included in a mortorium

21:30resolution. uh and uh should the

21:35majority of the commission uh decide to

21:38go forward with this could be set for

21:42Thursday's meeting uh to uh vote on

21:46whether to call a public hearing and the

21:50earliest we could do that at that time

21:52would be the October 15 meeting to

21:56consider this or a version of this as a

21:59moratorum. Um uh the u

22:04the specific statutory requirements are

22:07included in 160D 107 moratorum.

22:10Uh and it provides authority to the uh

22:15to local governments to impose

22:18development moratoriums under certain

22:20conditions. Uh hearing is required. uh

22:24specifics apply regarding what um

22:28projects are exempt from the terms of

22:30the moratorum. Uh and those are specific

22:34in the statute uh and the statute is

22:37referenced uh in the draft resolution.

22:41Uh then there are required statements

22:43four of them uh a statement of the

22:45problems or conditions necessitating a

22:47moratorum and what courses of action

22:50alternative to a moratorium were

22:51considered by the local government and

22:54why those alternative courses of action

22:56were not deemed adequate. Second a

22:58statement of the development proposals

23:00subject to the moratorum and how a

23:02moratorium on those appro approvals will

23:05address the problems or conditions

23:06leading to imposition of the moratorum.

23:09Three, a date for termination of the

23:11moratorum and a statement setting forth

23:14why that duration is reasonably

23:16necessary

23:18to address the problems or conditions

23:20leading to imposition of the moratorum.

23:22Uh and for a statement of the actions

23:25and the schedule for those actions

23:27proposed to be taken by the local

23:29government during the duration of the

23:31moratorum to address the problems or

23:33conditions leading to imposition in the

23:35mortorium. Uh the draft before you uh

23:39contains each of those four

23:40requirements. Um, and I can tell you

23:42where I got the model that I was using

23:46for this. Um,

23:48I

23:51took three examples

23:54from uh

23:57county jurisdictions in here in the in

24:00the Pont um that um were comparable

24:05either in size or urban scope uh or

24:11proximity. Uh the the three models that

24:14uh I examined were Davy County,

24:17Cumberland County, Fateville uh and

24:20Alamance County. Of the three, the one

24:23that looked most comprehensive and

24:24carefully worded uh in my opinion was

24:28the Alamance uh version. And so I

24:31modeled the format of this resolution on

24:34that. uh shared the draft uh with the

24:38county attorney and the county manager

24:40who also discussed it with heads of of

24:43relevant departments um received their

24:47suggestions uh and made modifications uh

24:50in order to respond to the suggestions.

24:53Uh I believe that this meets all the

24:55requirements if a majority of the

24:58commissioners wish to move forward with

25:00a discussion of whether or not uh to set

25:04a hearing for consideration of this. So

25:08from here it would be a two-step

25:09process. We would have to set the

25:12hearing and then at the hearing get

25:15public comments, consider any

25:18modifications that we wanted to make and

25:20vote yes or yes or no. So this is um at

25:24this point the question before the

25:26commission is whether or not to move

25:29forward the process of considering this

25:32not whether to take action on it but

25:35considering it. Uh and I can go into

25:38more details about any of the specifics

25:41uh of the four findings and the

25:44rationale for it. Uh in summary though,

25:48um rationale for doing this is that so

25:52many of the counties uh and

25:54jurisdictions near us have already

25:57adopted moratorium uh that if we don't

26:01put something in place, we are in effect

26:05uh inviting a slew of proposals that um

26:09uh we would never have the opportunity

26:12to uh uh to examine if we don't take

26:15action. At this point, uh the um

26:20uh the cautions that have been

26:21specifically offered uh regarding the

26:24action uh is that we can't propose to do

26:29anything that would be considered a

26:31downzoning under current law. Uh that is

26:34absolutely correct. That is recognized

26:36in the contents as I have drafted them.

26:39Um the uh

26:43and the salient

26:47part of the moratorum there is what

26:51potentially could we consider doing that

26:55would not run a foul of the downzoning

26:58prohibition. Uh there are uh matters

27:01that we could consider uh such as

27:04strengthening the county noise ordinance

27:07uh such as uh strengthening what we

27:09would anticipate we need in terms of uh

27:12pre-treatment of industrial discharges

27:15to uh our our sewage system. um such as

27:21uh additional limitations on property

27:24that was not zoned uh to allow data uh

27:31centers as defined in our current

27:33statute by right now.

27:38So the question is whether we want to

27:40consider

27:41putting a pause on entirely new

27:44proposals

27:46uh that would not include ones that have

27:48already started the process. uh for

27:51example um

27:54I'm aware of two cases where that is

27:57likely to um to see projects in motion

28:02that would be exempt from the the

28:04requirements of the moratorum uh or the

28:07pause I should say imposed by the

28:09moratorum because they have vested

28:11rights. Uh it is um uh rumored to be the

28:16case that um the applicants for the uh

28:21the the reasonzoning that we turned down

28:24earlier this year are coming back for

28:26another bite at the apple which they're

28:27entitled to do. Uh and if they file the

28:30necessary paperwork, they would be

28:32exempt uh and not affected by the pause.

28:36Um uh there I have just learned that

28:39there is apparently another uh data

28:42center proposal [clears throat]

28:45uh for what is now zoned uh for uses

28:50that

28:52allow a data center assuming that it has

28:55taken steps to give it vested rights by

28:58the time we were to adopt any moratorum

29:01resolution. uh and the earliest that we

29:03could do that would be the 15th of this

29:06month. They too would be exempt.

29:09Uh we have had our attention called to a

29:13recent decision uh in Chadam County with

29:16regard to a data center uh proposal that

29:20was in progress there. Uh I've read the

29:23uh the findings of fact. Um I have read

29:27the u uh the judge's order uh and just

29:32to to be blunt. It seemed like the

29:36Chattam County in that case

29:40attempted to

29:42stop processing

29:44approvals for a case that uh pretty

29:47clearly qualified to have vested rights

29:51and to be exempt from the proposal. So,

29:53we need to avoid making that kind of

29:55mistake. But if we do, then we would not

29:58be affected by the uh the terms of that

30:00decision.

30:03And that's my summary and I'm sure there

30:05are questions.

30:09>> I would like to ask our attorney to come

30:12forward and address this please.

30:24>> Good good afternoon [clears throat]

30:25commissioners and thank you for

30:28um allowing me to speak. I I would say I

30:31I I do want to lead off with the case uh

30:33Commissioner Bessie referenced and

30:35that's the Chattam County case. It's

30:36Ecotip West LLC versus Chattam County.

30:40Um I I have told you as you remember

30:43several times that there was litigation

30:45outstanding against one of these

30:47counties and that was Chattam County. um

30:51what happened in that case and I don't

30:53have all the facts um but a group came

30:57along they wanted to build believe a

31:00data mining um like cryptocurrency type

31:03of data center there county was against

31:06it they passed a moratorum and they said

31:10no one can build a data center for the

31:12next year and that's been in litigation

31:15since then

31:18unfortunately ely the opinion is

31:22poorly written and so I had to read I've

31:24I've had to read it several times

31:26because there are no findings of fact

31:28there are no conclusions of law the only

31:30conclusion of law is data center wins so

31:33what was alleged in that case uh reading

31:36from the order is the plaintist alleged

31:39that the moratorum itself was illegal

31:42they also alleged they had vested rights

31:47unfortunately we know how the judge

31:49reached the opinion. And so it's

31:52possible that the whole moratorum could

31:54be thrown out. Um and so the um from

31:59what I read, just looking it up online,

32:01the data center alleged that they

32:03invested $11 million

32:07to prepare for this data center. Um what

32:10the order says is Chattam County has to

32:12pay attorney's fees for the data center

32:16and they said come back in a couple

32:17weeks and we're going to decide damages.

32:19And so we don't know what those damages

32:21are quite yet. They could be $11

32:24million. They could be a multiple of

32:26that if you talk if you think about loss

32:28profits because there is no data center

32:30there. So, um I I I would urge you to

32:35consider that and and to and to have

32:37some caution because this is the only

32:39case that I know of in North Carolina

32:41where this has been litigated and

32:43Chattam County, which I believe is about

32:45a quarter of the size or less than for

32:48county could could really suffer because

32:50of this. And so, um that this is is

32:54dangerous. Uh I believe um Commissioner

32:59Messi did you know read through the

33:01statute about moratorum

33:03and um you know there there are certain

33:06circumstances where the board can

33:08approve a moratorum in this case as as

33:11I've said several times and it's been

33:13echoed by planning staff.

33:16It's dangerous for us because any really

33:19substantive change you might want to

33:21make would violate the down zoning. And

33:24so it's hard to see how you could

33:27permanently

33:28really limit data centers in the county

33:31under the current regime where we are.

33:34And that's not your fault. It's it's

33:36really what the state legislature has

33:38saddled us with. So, um you you

33:40obviously can reach whatever decision

33:42you want, but but I would

33:45bring to your attention as a warning

33:47that Chattam County case.

33:51>> Thank you. Are there questions from

33:52Gordon? There were no findings or

33:54conclusions though in that order, were

33:56there?

33:57>> No.

33:58>> But under rule 65, they're not required,

34:00are they? For injunctive rulings.

34:04>> Well, this this is a summary judgement.

34:06Um I I I mean the

34:08>> Well, that doesn't require them either.

34:10>> Yeah, it it's not required, but it's um

34:13if you were writing the order, you you

34:16would have you would have I'm sure been

34:18a little bit clearer on that. But it it

34:20it makes it hard for us to follow. So,

34:22it makes it hard to us to know

34:23definitively

34:25why the judge reached that decision. But

34:27regardless, the judge said that the data

34:30center wins and the county potentially

34:32owns owes many millions of dollars.

34:36>> Now, you know, I'm not saying they're

34:38going to have to pay that. They may

34:39reach a settlement or something like

34:40that, but um I would imagine they're

34:43going to owe quite a bit of money unless

34:44they somehow get the order overturned or

34:48they allow the data center to go

34:50forward.

34:53The question that I would have um I'm

34:55not first of all I wanted to just say

34:57that I'm not for putting this county

35:00into any kind of pearl or litigation.

35:03So, that's one. And my question to you,

35:06Gordon, and it's something that we had

35:08already talked about, but I think that

35:09constituents um should know. Um when I

35:13asked about whether the um

35:19they had already had an order previously

35:22on the records or was this after?

35:28>> I'm I'm sorry, I'm not following the

35:30question. You talking about the Chadam

35:31case? they already have an order for a

35:34moratorum before or did this happen

35:38afterwards?

35:40So, for example, if we already have two

35:42people that are in the queue

35:44>> for a moratorum, I mean for um a data

35:47center and we're trying to do this um

35:51I'm sorry I understand I understand your

35:53question. So, so the answer is I don't

35:55know because there if there were

35:57findings of fact it would say um ECOTIP

36:01did this step, they did that step, they

36:03fully qualified, they filed everything

36:05they did. Um, as I understand it, the

36:08data center says we we we filed

36:10everything. We have vested rights. The

36:12county says, "Oh, no, you didn't. You

36:13didn't you didn't complete your

36:15application." And so, I I I don't know

36:18the answer to that, but but you're

36:19right. Um and and and Commissioner

36:22Bessie included this in his proposed

36:24moratorum that if anyone does have

36:27vested rights,

36:29>> they they can still go forward. Now the

36:31question is what a court would consider

36:32vested rights. That could be tricky.

36:34There could be a third or a fourth

36:38data center out there that hasn't gotten

36:40in touch with Chris or Kirk and they

36:43they may pop up and say, "Oh, wait, wait

36:45a second. We we we have vested rights

36:47too because by right we could put in a

36:50data center today and you've taken that

36:52away from us. I'm not saying that's a

36:53good or bad argument, but we we don't

36:56know what we don't know.

36:58>> So I heard you say permanent and I think

37:01that Commissioner Bessie is offering um

37:03just a pause temporarily, right?

37:06>> So with that language

37:09um could you share your thoughts around

37:13it being temporary? Well, a moratorium

37:16is by definition temporary. Um, I I I

37:18think you still run the risk of somebody

37:21saying, "I have a right today to erect a

37:25data center and you're taking that away

37:26from me and you're really what you're

37:28really doing is a pretext and you're

37:29just doing it because you don't like

37:31data centers." That's that's the

37:32allegation. I'm not saying they

37:33necessarily win on that, but that's the

37:36that's what they would say.

37:37>> And and this is my last question. So,

37:39playing on words, um, pause is the

37:42purpose, right? So that's our purpose.

37:45The purpose would be for us to give time

37:48for ourselves to listen to the

37:50constituents, gather more information.

37:53Again, we've had that presentation, so

37:55we're continuing to do that. Um, we're

37:58learning what the impacts are going to

38:00be on the environment. Um, and then

38:02we're un better understanding what the

38:05safeguards are before moving forward.

38:08So, if we were to use the word pause

38:11versus moratorum,

38:13would that work?

38:14>> No. I I mean, it doesn't matter what

38:17term you use. It's the same thing. The

38:19the statute refers to a moratorum. So,

38:21it it doesn't matter what word you use.

38:24And so, um whether or not that's legal,

38:27that's a question. But, um the

38:30terminology wouldn't make a difference.

38:32>> Okay. Thank you.

38:34I do have u one question to um the

38:37county attorney. So in in all due

38:40respect to um commissioner best and I

38:44appreciate you doing this hard work. Um

38:48I do want to ask about

38:51um maybe your opinion about one of us

38:54who obviously we are political people

38:56and we have our own opinions about

38:58things and then we do the research and

39:01present this is how our oratorial will

39:05come out to the public. Then someone who

39:09um like a company that wants to bring in

39:12or develop a a data center, would they

39:15be able to say there is bias in our

39:18morator because one of us sort of

39:21created the documentation to

39:25have one in our county. Is that a is

39:28that a risk factor? You think

39:30>> there there is some risk in that?

39:31Obviously, you're entitled to to your

39:33own opinion. And I and I would state and

39:37things change from day to day. So, this

39:39not may not be exactly correct. Last

39:41time I checked, I believe 14 counties

39:44had enacted moratoria for data centers,

39:47but that means 86 had not. So, the great

39:49majority have not uh enacted those. Um

39:53there there could be an allegation of

39:54bias. I mean, if one of you came out and

39:56said, you know, I'm never going to

39:58approve a data center. I don't care

40:00where it is. um that could cause some

40:03problems even in a reasonzoning. But but

40:05you do still as as I keep telling you

40:08with a with a reasonzoning because it's

40:09legislative, you do you do have quite a

40:11bit of authority. Um if if if it got to

40:14a special use permit then we then we

40:16would be in trouble. If if we got to a

40:18special use permit hearing, which we

40:20don't we don't have here and and you

40:22said I'm against data centers, then you

40:24really could you really could not be

40:26unbiased.

40:28But so I'm sorry that's that's a long

40:30way of talking around the issue, but um

40:33I think you're okay expressing opinions

40:36about it one way or the other as long as

40:38you don't close it off permanently like

40:42saying it could never exist. A data

40:44center could never exist.

40:45>> I think my question is about obviously

40:47we all have opinions but only

40:50commissioner Bessie has proposed a

40:52moratorum. Would you then say, "Oh, it's

40:54not his."

40:56In essence, we created it as staff. we

40:59recreated this document to put before

41:01the commissioners that just based on you

41:06know staff recommendation that because

41:08that would be I think something that I

41:12would and again with all due respect to

41:15um Commissioner Bessie I would want

41:18staff to create the document that we

41:20would obviously you would but I'm just

41:22saying as of right now it appears that

41:25the moratoria is coming from maybe one

41:28commission additional verses from the

41:30work of staff.

41:32>> That's because it is um we you know we

41:35we've we've we've appeared before you a

41:37couple times and and you know our at

41:40least my recommendation is is against a

41:43moratorum and but any one of you or

41:46three of you or four of you can

41:48certainly propose something and and if

41:49the board is in favor of something

41:51obviously you you can vote on it. Um,

41:54again to to echo what the manager said,

41:58we're we're not trying to be for or

42:00against data centers. We're we're just

42:02trying to protect the county.

42:03>> So would you then this is my last

42:05question. I don't want to keep going

42:06around a circus. I guess my question

42:08directly to you is if we as a body or

42:13the majority decide we want the

42:15moratorial, would you and your staff

42:17then present one to us for us to vote

42:20on?

42:22I could do that, but knowing I've

42:25already told you that I'm I'm not I

42:28don't recommend it. But I mean, you

42:30know, if if we're instructed to do it,

42:32we can come up with the best version we

42:35can. But I what I'm telling you is I

42:37don't think we can come up with a

42:39version that is going to protect the

42:41county.

42:41>> Fair enough. Thank you.

42:42>> I I was going to ask you had you read

42:45this when that was presented to you from

42:48Commissioner Bessie?

42:49>> Yes.

42:51Thank you.

42:53>> I have a question. Um

42:57Gordon, aren't you in effect saying to

42:59us that because in your opinion there is

43:02no way to um uh enact meaningful uh

43:08condition requirements

43:11uh on the placement or the uh uh the

43:17setbacks, the noise, the the water

43:21discharge, etc. because in your opinion

43:24there's no way to enact those um under

43:27current law

43:29that uh we should not even consider uh a

43:36pause to collect other expert opinions

43:40and information. In effect, we have

43:42heard

43:44nothing on the legality of this other

43:47than my research and your research and

43:50opinion. We have not heard from other uh

43:54legal uh experts or those who have you

43:58know different experience with this

43:59issue.

44:01>> So I I think there are ways that this

44:03could be addressed and and we we've

44:05spoken about this. I I think um

44:09you know planning staff could be

44:11researching

44:13what a res what a restriction would look

44:15like and be ready with a restriction if

44:18we can convince the legislature to to

44:20get rid of down zoning or to provide the

44:24county authority over data centers.

44:25There were there were two bills as I

44:27mentioned uh in my last presentation.

44:29One passed the House, one passed the

44:31Senate.

44:32One would give you authority over data

44:35centers. one would get rid of down

44:36zoning. Unfortunately, they didn't come

44:38together. And so if if we could be ready

44:42with something if that did happen, that

44:44would that would be something we could

44:45do. Um, alternatively or at the same

44:49time really um and and planning staff

44:52has has has been working on this to some

44:54extent with with the past proposal for

44:56for a data center is to come up with

44:59reasonable

45:01conditions if somebody asked for a

45:04reasonzoning. So, um, you know, I

45:06understand

45:08one or two cases are probably coming

45:11before you. One, one of them would be

45:13resoning. The one you've already heard

45:15would come back in a different iteration

45:18if they had, you know, kind kind of

45:20plugandplay conditions based on their

45:23research. That's something we could be

45:24preparing now. And I think to some

45:25extent they've already done that.

45:28Just to clarify though, Gordon, because

45:30I want to make sure the board is clear.

45:31Those are recommendations, but neither

45:33recommendation would involve a moratory.

45:36That's correct. I just want to make sure

45:37we're clear on that.

45:40>> If if I can, um, Commissioner Bessie, so

45:43what I'm hearing, are you saying that

45:46you've spoken to someone at the

45:48association for some assistance around

45:52this? No,

45:55>> no,

45:58>> I'm not really sure who Are you talking

45:59about the NCAACCC?

46:00>> Yes, I know.

46:02>> I don't really know that they would have

46:03anything to say about this. I

46:06>> mean, they've provided um I mean, and

46:08some of you sat in on it. I mean, you

46:10know, education, which we've seen, and

46:13Nico has provided information, which

46:15we've seen, school of government has

46:16guidance out there, which we've seen,

46:18and all of that is being considered. At

46:20the end of the day, it comes down to a a

46:24legal interpretation of um with the

46:26downzoning statute

46:28>> and and I have to I'm sorry to probably

46:30answer the question better. Um I have

46:32spoken with the school of government um

46:35about that and attended several

46:36presentations and and

46:39you know I even I even I was trying to

46:40come up with some kind of way we could

46:42do this and and everything I came up

46:44with got shot down. So, um,

46:48yeah, I I have consulted with the school

46:50government.

46:52>> If I may, um, in section five of the

46:55draft, and by the way, I had originally

46:58thought that, um, we would be able to

47:00get a draft that was correct and

47:03complete as to form um, from the

47:06attorney's office. I would have been

47:08happy to start with that. Uh, I drafted

47:12this myself because it was clear that I

47:15was not going to get that. Would that be

47:17a fair statement?

47:21>> So, no, I I did not draft one. That's

47:23correct.

47:24>> Okay. Um, if I can refer you to section

47:27five, the work program. Uh, there are

47:30three parts to that and they address um

47:34what we've been discussing about here.

47:38uh that is what the purpose uh what kind

47:41of information would be collected during

47:43the pause

47:46and during and I'm not talking about

47:50just the staff looking at this and

47:53giving us their interpretation of what

47:55they recommend. I'm talking about our

47:58looking at this information directly and

48:01determining what we want to ask to be

48:04prepared.

48:06Now gathering Uh the start first

48:08paragraph talks about gathering

48:09information materials on appropriate

48:11conditions and limitations on the siding

48:13and development of large-scale data

48:15centers including best practices or

48:18recommendations from the National

48:20Association of Counties, the NC

48:22Association of County Commissioners,

48:24other jurisdictions in North Carolina

48:27that have studied the issue and other

48:30states which have experience addressing

48:32the impacts of large-scale data centers

48:35and subject matter experts on relevant

48:37environmental and utilities impacts and

48:40public comments would be taken. What I'm

48:43thinking about in this case when I

48:44reference other states talking about

48:47just across the state line in Virginia,

48:49you know, Loen County uh is considered

48:53the epicenter for data center

48:56development in the United States pro

48:58possibly in the world at this point. Um

49:01their county officials have direct

49:04experience in dealing with the problems.

49:06They have direct, concrete, substantive

49:09recommendations to make. Some of them we

49:11probably couldn't do under current

49:14statute. Some of them perhaps we could.

49:17I think we owe it to ourselves and our

49:22constituents

49:24to take the time to hear that

49:27information directly,

49:29not simply filter it through our

49:33outstanding staff. Because There are

49:36going to be different opinions on what

49:39is important and what will work and we

49:42need to consider those different points

49:44of view.

49:45>> Well, Mr. Bessie, I have been to Nico

49:49workshops and I've been to NCACC

49:52in east in uh NCACC. They had a workshop

49:56that had uh a guy from Lowden County

50:00there.

50:01>> I was there.

50:02>> I know you were. So to don't do not make

50:05the public believe that commissioners

50:09have not studied this issue because I

50:12know for a fact I have I know you have

50:15um and we've gone to workshops but

50:18neither is Niko nor NCAC going to make a

50:23recommendation because they represent

50:26everybody and neither of them are going

50:29to send you information that will say

50:33uh data centers are not good for you or

50:36data centers are good for you. They're

50:38not going to do that. I think what they

50:40have done and I think that uh it would

50:42be u of interest to the public to hear

50:46this. Uh they have made recommendations

50:50regarding conditions that uh should be

50:53addressed that uh um and alternatives

50:58u that other jurisdictions have followed

51:02and the folks in in Logen County um have

51:07that you know lived experience uh that

51:11we don't have here yet. And I think that

51:14it would be of interest to the public to

51:16bring in some folks uh in a public

51:18setting where they could hear and ask

51:21questions. Um that's the kind of process

51:25that this gives us an opportunity to do

51:28in a meaningful way. Uh it um uh it

51:34provides a a legal means of putting a

51:37temporary pause on new projects started

51:41and not trying to throw a monkey wrench

51:43in projects that already have vested

51:45rights and that was Chadam County's

51:47error.

51:50Uh but Paul's own new ones coming in. uh

51:54and we would take that kind of

51:57information and then we would you know

52:00consult with our legal counsel UNCC

52:03school government other available

52:04information regarding potential options

52:07for implementing conditions and

52:08limitations deemed to be needed to

52:11address the potential issues identified.

52:13Options considered may include county

52:16ordinance changes uh including

52:19comprehensive changes to development

52:21ordinance definitions and conditions. uh

52:24changes to development ordinances that

52:26apply only to properties which are not

52:28at present in zoning districts which

52:30allow data centers, noise ordinances and

52:34industrial weight wastewater

52:36pre-treatment conditions as well as

52:38requests for statutory adjustments. So

52:41if at the end of the process a majority

52:46of the board says we agree with Gordon's

52:48basic assessment that there isn't

52:50anything that we can do that would be

52:52meaningful uh except ask for statutory

52:56change that's written in as an option.

52:59Uh so we do have legal options

53:02referenced uh in the work plan.

53:06Uh

53:09there is plenty of grounds for

53:12reasonable disagreement on whether we

53:15should do a moratorum. I respect uh our

53:19expert uh attorney Watkins opinion that

53:24it's not worth doing. I do not share

53:26that conclusion.

53:29I think that the public examination

53:32process that this would entail

53:36is worthy in its own sake because as I I

53:40believe

53:42one of my colleagues has pointed out

53:45that there is a great deal of

53:47misinformation running around. Uh and we

53:50can we can take meaningful action to uh

53:55help remedy that by bringing in in a

53:59public setting uh outside uh experts uh

54:03you know subject matter as well as legal

54:06and experienced local governments and

54:09other jurisdictions to help go over the

54:11complications.

54:13>> Can I just say that um I I appreciate um

54:18I County Attorney Gordon Watkins stand

54:22firm. Good gracious. Because you know I

54:25know that just even when I was on the

54:26school board I wanted Dion to do a whole

54:29lot of stuff. Shade no we trying to keep

54:31you all off the front of the paper and

54:34all kind of other issues. And so I do

54:37want to empower you to do what we ask

54:41you to come and serve to do on behalf of

54:44the citizens and this board. So, thank

54:47you for saying, "Hey, I hear what you

54:49all are saying. I respect your opinion,

54:51but I have to give you, as Commissioner

54:55Bessie said, my expert opinion. What you

54:58all do with it, it is on you. So, thank

55:01you for standing strong in an opinion

55:03that I absolutely respect whether or

55:06not, you know, I go one way or the

55:09other. So I don't want um you or staff

55:12to feel any way like you know you have

55:15to be compromised in order to do what

55:18you know the citizens expect you all to

55:20do which is to give us the information

55:22we need so that we can govern in an

55:25effective way. But with that being said,

55:28I do

55:30um respect what Commissioner Bessie is

55:33trying to bring to light to this

55:35community around

55:37um although we have gone to sessions, I

55:40think as county commissioners um and and

55:43I and I still don't feel comfortable

55:46where I am about data centers. I think

55:49that it is, you know, a learning process

55:52um for for sure. I think that we may

55:55have had the benefit of the information,

55:57but a lot of our citizens have not had

56:00that information and I don't know

56:02whether uh hearing is going to per se

56:06give them the information that's needed

56:09versus the county um and even maybe this

56:12city coming together to offer some

56:15sessions throughout this community

56:16around data centers. And therefore, it's

56:19not politicized. is just hey this is a

56:22large enough county and city and you

56:25know they're coming so let's try to

56:27provide information to our citizens

56:30um so that they can come I think in a

56:33hearing and be empowered with um

56:36information that you know um all things

56:39being equal maybe they have been able to

56:41come out and hear um from the county and

56:44cities around um data centers but my

56:47question to

56:49lastly commissioner Bessie is what is

56:52your argument against just voting no on

56:55a data center if we're not ready to move

56:58forward versus the moratorial?

57:02>> That is an alternative. Um not all

57:05potential

57:07um uh requests are going to fall uh

57:12under the

57:17as clear a case as we were looking at in

57:20the um uh uh the the rural hall adjacent

57:24request. um that was a um uh

57:30an area zoned for agriculture and

57:33lowdensity residential. Um there was no

57:36question that data center use uh was not

57:41allowed uh in that zoning. Uh and it was

57:44a cleancut uh case where an up or down

57:47vote uh was all we needed to do. Um

57:50there

57:52could well be gray area cases that come

57:55forward uh in which we would um uh would

58:00want time to study the issue. Uh and

58:03this would give us time. This would give

58:05us that six-month pause. And I would add

58:09that uh the legislature is not currently

58:13in active session.

58:15uh they're not going to come back until

58:17late November at the earliest and

58:20possibly not till December to consider

58:23uh action on either of the bills that um

58:26that attorney Watkins referenced. Um uh

58:30a six-month pause on uh new projects

58:35that do not have vested rights.

58:38Pause on new projects that do not have

58:40vested rights. um would uh give us the

58:45opportunity among other things to see

58:47what the legislature is going to

58:49actually do on this.

58:52But just waiting for the legislature to

58:55act when it has no firm timetable

58:59uh and no assurance that it will act at

59:01all, I think is a an unsatisfactory

59:05substitute for for our moving forward

59:07with what we could do.

59:10>> I have a question. I'm not not going to

59:12limit myself to just one, but I've got

59:15one for right now.

59:19Go back on the tape just a little bit

59:21about four or five questions ago or

59:26observation. It was observation you

59:29made, Commissioner Bessie, in regard to

59:32your u uh

59:35your draft. I couldn't have done better

59:38myself. I I didn't uh I looked to see

59:41whether we'd got the email early this

59:44morning, hadn't got it. Looked at it

59:46again, hadn't got it,

59:49and looked at it just before I was

59:52getting ready to come out here. And

59:54there it had popped up. So, I did take

59:57the time to read it. So, that was just

1:00:00about

1:00:0211 11 o'clock, I believe. I don't know.

1:00:05I didn't pay attention to what time it

1:00:06was sent, but I took the time to read it

1:00:08anyway. So, but in reference in your uh

1:00:15draft,

1:00:19>> you it my interpretation of that is and

1:00:22that's that's that's fine. I took a lot

1:00:25of time to work through that. Um

1:00:30it seemed to be that

1:00:32uh in the conversation back and forth

1:00:35with you and um Mr. Watkins,

1:00:40you felt like you had to do that because

1:00:42the county attorney hadn't done it

1:00:44hadn't done a draft. In the last month

1:00:48or so when we've been discussing this,

1:00:51has it any time the majority of the

1:00:54board

1:00:56requested that he draft anything?

1:01:00>> I don't believe so. Well, we've had

1:01:02>> and he he's

1:01:05uh

1:01:07if if I come up with uh something and I

1:01:12probably could, but I'm don't have

1:01:14anything at present that I wanted the

1:01:18attorney to uh draft for me and it was a

1:01:21controversial matter

1:01:26and he knew it and most likely he'd

1:01:28probably tell me that it was I don't

1:01:30know but I I think you probably would.

1:01:33Uh

1:01:35then

1:01:37if it was controversial then uh if I

1:01:40want to try to get it forward, I would

1:01:43uh try to convince the Ford whatever the

1:01:46issue that I had was well I want the

1:01:49attorney to draft something for me

1:01:52because it's controversial and

1:01:55and he don't do that.

1:01:59And then if the board uh

1:02:04if the board directs him

1:02:07uh to do that then

1:02:11I think that's probably what he uh would

1:02:15need to do at the direction of the U

1:02:19board. But if if wherever we get to on

1:02:23this

1:02:25and there's got needs to be some kind of

1:02:28draft

1:02:30If the attorney's not in uh involved in

1:02:35doing that,

1:02:38then

1:02:41I guess I got a problem myself. I won't

1:02:44uh u with all you've got there without

1:02:49the attorney uh

1:02:52giving if it's

1:02:55it just seems to be that he can't uh uh

1:02:59give advice but as good as what you've

1:03:01got written down there and I'd say it's

1:03:03all strictly by the law u

1:03:09I don't think I'm going to totally

1:03:10accept that without the attorney our

1:03:13attorney

1:03:15I don't know how he's going to do it

1:03:17without at least saying these things is

1:03:20what uh needs to uh be put in a draft.

1:03:25And I think

1:03:29some way he can uh he's

1:03:33if we ask him to do some work or the

1:03:35county manager to do some kind of work,

1:03:41they probably do it more often than we

1:03:43think for

1:03:45that. They got opinions, but to go ahead

1:03:47and and they don't tell us what it is.

1:03:49And majority of the board ask them

1:03:52direction to do that, they do it.

1:03:56So,

1:03:57um,

1:03:59with all the good work you got there,

1:04:00I'm just wherever we end up, majority

1:04:04ends up going to go forward, then

1:04:07somewhere along the line,

1:04:10um, our attorney is going to have to be

1:04:12involved in it, too, or either uh might

1:04:16be something I couldn't support.

1:04:19>> Well, and I think that's quite a

1:04:21reasonable uh suggestion. Um uh in this

1:04:25case I was hopeful and I recognizing

1:04:29that there was no board mandate u

1:04:31because um it's been difficult to get

1:04:33this to a vote of any kind. Um but there

1:04:36was no board majority mandate. Um in

1:04:40order to put us in a position where we

1:04:43could discuss the possibility we needed

1:04:45a draft of what a resolution would look

1:04:49like. Um uh I when you know, uh when our

1:04:55our county manager um pointed out to me

1:04:59that staff were uncomfortable

1:05:02drafting,

1:05:04uh and please correct me. Um, so what I

1:05:07will say is I reached out to

1:05:08Commissioner Bessie to ask if he had any

1:05:11language or specific items he would like

1:05:14us to consider because based on the

1:05:16information um that we presented at the

1:05:19last meeting, we were really unclear

1:05:22because on from staff's perspective,

1:05:25we did not see a pathway forward with a

1:05:27moratorum and so we were hopeful that um

1:05:30Commissioner Bessie had some language

1:05:32that would address those concerns. So I

1:05:35asked him if he had any language or

1:05:36recommendations. Um, when we received

1:05:40back, quite honestly, we were surprised

1:05:42because we thought there was going to be

1:05:43something that was different than what

1:05:45we discussed as concerns and what we

1:05:48received back wasn't. Um, it it really

1:05:51it didn't address any of the concerns

1:05:52that we previously stated um that we did

1:05:56not feel comfortable with the moratorum

1:05:59a as such because of all the things

1:06:01we've already discussed. So, at that

1:06:04point on the staff level, we were a

1:06:06little bit at a well, what are we going

1:06:08to present on Monday? Because what we've

1:06:11received does not address any of those

1:06:12concerns, which is why I then reached

1:06:14out to Commissioner Bessie to ask him

1:06:16then, how would you like us to go into

1:06:19today's discussion? Would you like us to

1:06:21send the draft ordinance to the board?

1:06:24That's kind of how how we are here. And

1:06:27if I may, um,

1:06:30what county manager Robinson and I are

1:06:33saying is pretty much the same thing

1:06:34with different points of emphasis. Um,

1:06:37uh, I

1:06:40had indicated that I was going to ask

1:06:42the board to consider a moratorum.

1:06:46uh and uh county manager Robinson

1:06:49indicated basically that after talking

1:06:52to other staff uh that they were looking

1:06:55for

1:06:57alternatives to a moratorum that

1:07:01I mean that's that's the upshot

1:07:03>> I I will say we weren't necessarily

1:07:04looking for alternatives to a moratorum

1:07:07we were hopeful that you were going to

1:07:09present something um and provide us with

1:07:12language that gave clarity that a

1:07:14moratorum was allowed. So, something

1:07:16different than what we had previously

1:07:18discussed. We thought you were going to

1:07:20provide us with a draft that addressed

1:07:22those concerns. Um, so we thought you

1:07:26would actually have something that you

1:07:28sent to us that we would say, "Oh, okay.

1:07:30Yes, we can do this moratorum, but

1:07:32unfortunately the draft that we received

1:07:34did not address staff's concerns."

1:07:38And that's the puzzler because I did in

1:07:41fact uh draft language that addressed

1:07:45the concerns that were raised.

1:07:48Uh and you know the

1:07:52they were what were we going to study?

1:08:00What would we consider in the process of

1:08:03that study? It's in there. uh and what

1:08:06potential

1:08:08outcomes

1:08:09could we see that's in there as well

1:08:14respectfully I think we have a

1:08:16difference of opinion on what addresses

1:08:19the substantive issues and what is

1:08:21adequate perfectly legitimate

1:08:24but that's why I drafted a resolution

1:08:28there was no way to get a resolution

1:08:31for a moratorum before this body as a

1:08:36for consideration

1:08:38through staff work alone.

1:08:41>> Can I just say um Commissioner Bessie,

1:08:44if it makes you feel any better, the

1:08:45county is an equal opportunist. I have

1:08:48wanted to create things and Shantel

1:08:50says, Shay, do you have the votes? No.

1:08:53So then I may go and talk to attorney

1:08:56Watkins and we go back and forth around

1:08:58the two and then I'll create something

1:08:59and share it with you all. I think

1:09:02probably some of the

1:09:05concern that, you know, I even felt, you

1:09:10know, sort of um I was very empathetic

1:09:13with um the county attorney when you

1:09:15said that, hey, we asked you to do

1:09:17something, you didn't do it. And it made

1:09:19him look like he is not responding to us

1:09:24as a body versus, you know, I did, you

1:09:28know, this is the best that I can do

1:09:30without, you know, the the the counties,

1:09:33you know, doing it for me, if you will.

1:09:35And I think that's maybe for me at

1:09:38least, that's some clarification that I

1:09:40would like to make to the citizens that

1:09:43unless it's a body of us, we don't tell

1:09:45staff what to do. You know, we may ask

1:09:48for help so that then we can share

1:09:51information with one another. But I do

1:09:54think that at least from and I think

1:09:56from all of our experiences, you know,

1:09:58when we go through of course proper

1:09:59channels that staff, you know, will

1:10:02assist. But it seemed like earlier you

1:10:04made a point to say that the county

1:10:07attorney was not responsive to something

1:10:09we asked him to do.

1:10:11>> If let me let me just let me just say

1:10:13something. Um it's not that I don't want

1:10:16to do this. It's not that I'm refusing

1:10:19to do this. It's that what I understood

1:10:22the board saying to me multiple times is

1:10:26is there a way forward with a moratorum?

1:10:28and I've said repeatedly, "No, I don't

1:10:31believe there is." And so that's still

1:10:34my response. I I believe the Cadam

1:10:38County case is a real warning. And I

1:10:41would say if you do want to go forward

1:10:43with a moratorum, you need to really

1:10:45think seriously about setting aside a

1:10:47contingency if we get sued on it because

1:10:49that's a real possibility. Okay? So, I I

1:10:52don't that doesn't bring me any joy

1:10:54because what I want to do is I want to

1:10:56give you all um the maximum choices. I

1:11:02just feel like the legislaturator's tied

1:11:04your hands on this one. And so, I I

1:11:06don't think I'd be doing my job if I

1:11:08just came up with a moratorum and I

1:11:10said, "Alamance passed it. That's good

1:11:12enough." And so, I'm not I'm not going

1:11:13to do that. I'm not going to say because

1:11:14Alamance passed it, we should pass it.

1:11:17So, I mean, I given you my opinion.

1:11:19Obviously, you don't have to agree with

1:11:20me, but

1:11:22>> that's what my opinion is.

1:11:23>> Attorney Watkins, if I if I could ask

1:11:25this question. Does continuing education

1:11:28on this issue require a moratorum?

1:11:33>> I mean, obviously not. And and and as

1:11:35the chair and well, I mean, I've seen

1:11:37many of you at at education events, so I

1:11:40know that many of you have attended

1:11:41those and but but obviously, yes, we we

1:11:44we all need to continue to learn more.

1:11:48Well, I love telling the county staff

1:11:50what to do. Um,

1:11:53hardly ever do it. Um, but I I want to

1:11:56commend our county attorney and also

1:11:58Commissioner Bessie for the hard work

1:11:59they put into this matter. Um, I mean,

1:12:02it's a high level discussion and I

1:12:04appreciate that. I'm afraid I come back

1:12:06around though to Commissioner

1:12:08Woodberry's position and that was well,

1:12:11you know, why can't we if look at

1:12:13another data center if one gets proposed

1:12:16uh and make a decision about it and I've

1:12:18already voted against one in this uh

1:12:20county because I thought it was the

1:12:22wrong one under the circumstances. I

1:12:24hear now we may have a couple of more

1:12:26coming. Um, and I think what I said at

1:12:28the last meeting that fell on deaf ears

1:12:30was it really helps me as a mere lawyer

1:12:35to know a specific project proposal to

1:12:39which I can respond. I mean, we've

1:12:41gotten a lot of education just dealing

1:12:43with the last one. And as Commissioner

1:12:44McDaniel said, uh, we heard the public

1:12:48commentary on that. We heard how they

1:12:49felt about it and and I welcome that

1:12:52also. But when you look at a proposal

1:12:57and I see in the uh the draft from

1:13:00Commissioner Bessie, I I commend him for

1:13:02saying there are multiple sites in this

1:13:03county um that are that still remain.

1:13:07When you look at a specific uh proposal,

1:13:10I think that one is in a position to try

1:13:13to assess that and determine what

1:13:15conditions need to be imposed. Uh we

1:13:18we've heard about it. We've read about

1:13:19it. I visited a big data center at a

1:13:22town called Maiden where they're crazy

1:13:23in love with it. Um, you you know, you

1:13:26got these features of of noise and the

1:13:29uh power grid, the loop water system

1:13:31aesthetics and other environmental

1:13:33considerations, who's the enduser, and

1:13:35that's crucial. We didn't have that in

1:13:37the one for rural hall. And of course,

1:13:39zoning undergards all of that. So, uh, I

1:13:44just think that, uh, this proposal here

1:13:47is not one that works in that context,

1:13:50uh, because if it did or if I could see

1:13:53a way to see clear to do that, you know,

1:13:56then I might be so inclined. So, given,

1:14:00you know, the risk averse nature of what

1:14:02you're describing to us, uh, and I'm not

1:14:05as riskaverse or I am as riskaverse as

1:14:07anybody else, uh, because of my

1:14:09background. Um, I do take I take pause

1:14:13in approving something like this.

1:14:19>> One more.

1:14:23>> I know there's been a lot of concerns

1:14:25about property taxes.

1:14:29I've got to focus on that and I would

1:14:32never want to subject our county to be

1:14:35having to increase our property taxes to

1:14:38potentially pay a data center. So, uh, I

1:14:42kind of have to take the guidance that

1:14:44our attorney has on this because I just

1:14:47wouldn't want to subject our county like

1:14:49potentially what Chattam County is

1:14:51having to face raising taxes to pay a

1:14:54data center.

1:14:56I would just I would just add to that

1:14:58that um polls are coming in 70 to 80% in

1:15:03favor of the constitutional amendment

1:15:06to limit property taxes. So you may not

1:15:09have the ability to raise property tax.

1:15:12>> So or lower benefits.

1:15:16>> Thank you. Um I wanted to say that I was

1:15:20not intending to denigrate attorney

1:15:23Watkins. um but merely to explain why I

1:15:28had to draft something if anything of

1:15:30this nature was going to be before the

1:15:33board for consideration.

1:15:35Uh and I, as I indicated, I do respect

1:15:39um your professional analysis. Uh I

1:15:43don't share all the points. I think that

1:15:45in the Chattam County case, for example,

1:15:47it is crystal clear that the liability

1:15:51there was based on uh Chadam's declining

1:15:56to recognize

1:15:58um what seemed on the facts presented uh

1:16:02pretty clearly a strong case uh to be

1:16:05considered an exempt project. Um I do

1:16:09think that there are uh reviews that we

1:16:13are passing up by declining to take this

1:16:17uh process step. Uh such as a review on

1:16:20the costs to the uh uh the constituents

1:16:25here of uh increases in electric bill of

1:16:28increases in their water sewer bill. U

1:16:31if we have uh too many poorly sized,

1:16:34poorly located facilities of of this

1:16:37type. Um, at this point it's it's clear

1:16:41that I don't have the votes to move

1:16:43forward. Um, and I'm going to take that

1:16:46as the the uh uh the response of the

1:16:51commission, but I would like for the

1:16:54record if there is anyone else who wants

1:16:56to join me in saying that we should move

1:16:58forward with this process to just hold

1:17:00up a hand uh and see let folks see who

1:17:04is for and who is against. and I see

1:17:06myself and Commissioner McDaniel holding

1:17:08up a hand to consider this.

1:17:10>> So, Commissioner Bessie, what I wanted

1:17:12to say to you um relative to your

1:17:16position with this, you are the atlarge

1:17:19um commissioner. So, that means that you

1:17:22um are responsible for the constituency

1:17:24throughout Force County. I will tell you

1:17:28that I do support you. Nonetheless, we

1:17:31don't have um the support on this board.

1:17:34So, the hand raises is really not

1:17:36necessary. I will tell you, thank you

1:17:39for this body of work. I'm getting the

1:17:41emails like you are. Again, do not be

1:17:44dismayed. We've done what we could do.

1:17:47And um you just don't have what you

1:17:50need. So, we'll just move forward.

1:17:53>> And I would just say um and I know you

1:17:55said the last person chair, so I

1:17:58apologize, but I just take issue with

1:18:00asking for the straw poll. I think that

1:18:03that's not where I thought this would

1:18:06end up. I I thought that and in all due

1:18:09respect, um, Commissioner Bessie, I

1:18:11thought that we landed in a good space.

1:18:13I don't have the votes. Let's just move

1:18:14forward. But to ask us to take a straw

1:18:18poll, that wasn't collegial. I thought

1:18:21that I I think that that wasn't a good

1:18:23show of how we can support one another.

1:18:26So, I just wanted to put that on record.

1:18:28is not that I don't support informing

1:18:30studentu citizens and having their voice

1:18:32be heard. I think we're just at a point

1:18:35where we need to figure out with staff

1:18:38how to move forward. But I I I just

1:18:42don't appreciate that last part.

1:18:46>> Thank you, Gordon. We appreciate you. Um

1:18:49have a motion to adjurnn.

1:18:54Have

1:18:54>> a motion and a second. We're jar.