2026-07-30 - Board of County Commissioners

Summary

Built from the official minutes (adopted record) and the auto-generated captions, which begin at the call to order and have a gap of about 14 minutes around 2:10 to 2:24; where they differ, the minutes are followed. Call to order 6:00 PM, adjournment about 9:46 PM. Present: Chairman Don Martin, Vice Chair Gloria D. Whisenhunt, Dan Besse, Richard V. Linville, Tonya D. McDaniel, G. Gray Wilson and Malishai Woodbury.

  • Rezoning F-1669 (Project Iron Spur data center): after the staff report from Chris Murphy (128.54 acres, three two-story buildings of up to 85 feet, about 1.1 million square feet; the planning board recommended denial 7-2 and staff found the plan inconsistent with the Rural Hall Area Plan and Forward 2045), the board heard a one-hour public hearing, 30 minutes each side. Supporters included the Rural Hall mayor, the project manager (who described a $2 million property value protection fund and a 55 decibel limit at the property line), landowners and several residents; opponents presented petitions with 1,243 signatures and raised noise, low-frequency sound, fire and rail hazards, water, health and compatibility concerns.

  • A motion to approve failed 2-5 on the recorded vote (see the minutes detail below). Dan Besse said the commissioners had received nearly 400 individual comments, 376 opposed, and that the vote was a rezoning decision, not a referendum on data centers. Tonya D. McDaniel urged the county to redefine "data center" in its ordinance. Gloria D. Whisenhunt and one other commissioner spoke in favor. A motion to deny followed, seconded by Tonya D. McDaniel; the minutes record that it passed 5-2.

  • Special use permit F-1667 (land clearing and inert debris landfill on Watkins Ford Road, 69.5 acres, about 37 acres of fill): heard as a sworn quasi-judicial hearing. The applicant's team described phased cells, buffers, groundwater monitoring and a market analysis; a nearby resident raised creek, runoff, road wear and dust concerns. The board approved the permit, 6-1.

  • Proclamation recognizing August 2026 as National Emergency Management Awareness Month, accepted by the emergency management office, which said it was also helping with a large water main disruption. The board supported naming the NC 67 Yadkin River Bridge for two Yadkin Valley regional leaders and declared intent to join the commercial property assessed capital expenditure program; all approved unanimously, along with the June 25 and July 9 minutes.

  • Public session: a Clemmons resident asked about the proposed asphalt plant on Gun Club Road. Staff said the land is zoned general industrial, the plant is allowed with a permit, and the air quality permit is a department decision, not a board decision. Another speaker argued against county property taxes on constitutional grounds, and another thanked the chair on his retirement. A candidate for county commissioner disputed that the Rural Hall opposition was an organized misinformation campaign.

  • Consent and regular items, all approved unanimously: a resolution to negotiate an amendment to the 2021 installment financing contract for up to $26.85 million in 2026 limited obligation bonds (public hearing set for August 13), with a $135,000 transfer for issuance costs and related capital project ordinance amendments; $1,916,168 in interest earnings to the airport element for building automation controls; five quantum meruit payments (including $247.50 for drug screenings, $68,618.80 for a soccer club exercise track and $18,340 for expedited DNA analysis); a Vision Zero grant of up to $129,669 for the Village of Clemmons and a community policing interlocal amendment; up to $2,828,218.25 for behavioral health crisis services; and several software and service contracts.

  • Also approved unanimously: sale of two 2004 Clemmons Fire Department trucks, a demolition order for a dwelling unfit for habitation, the tax collector's annual settlement, tax refunds, the May human resources and June benefit cap reports, and an employment agreement for the county attorney added after a closed session. Two state-required text amendments were deferred to the next meeting, and the chair thanked colleagues in what appeared to be his farewell meeting.

  • Minutes detail, F-1669: Chris Murphy reported the petitioner's agreed noise conditions (post-construction levels at residential property lines no higher than the greater of the pre-construction study level or 55 dBA in normal operation; generators in emergencies or testing held to a 60 dBA maximum; complaint-based noise studies limited to two per calendar year unless a limit is violated) and said staff found the plan inconsistent with the Rural Hall Area Plan Update and Forward 2045, while the Planning Board had recommended denial 7-2 on June 11. The board had extended the hearing to one hour (30 minutes per side) on July 9. Ten speakers were recorded in favor, including Rural Hall Mayor Terry Bennett, and twelve against, including Robin Smith. Martin moved approval (consistent with Forward 2045; three two-story buildings, 1,122,300 square feet), seconded by Whisenhunt; it failed 2-5, with Martin and Whisenhunt in favor and Besse, Linville, McDaniel, Wilson and Woodbury opposed (the minutes say Wilson voiced support in debate but he voted no). Besse's substitute motion to deny, finding the request inconsistent with Forward 2045 and the Rural Hall plan and the size, scope and hours inconsistent with LI-S zoning, was seconded by McDaniel and passed 5-2 (Martin and Whisenhunt opposed). The board then took a brief recess.

  • Minutes detail, F-1667: Gordon Watkins set out the quasi-judicial procedure. Whisenhunt moved to find all four findings proved and approve the permit; Martin seconded; it passed 6-1 with McDaniel opposed. Wilson asked about road conditions; the applicant said the existing site is about 11 acres with expansion.

  • Minutes detail, other: the intent resolution for the CPACE program and the bridge designation passed unanimously (the NC 67 Yadkin River Bridge would be named for Jimmie R. Hutchens and Joe C. Matthews; Forsyth and Yadkin counties must both adopt resolutions before the NC Department of Transportation takes it up). Items 10 to 14 (quantum meruit payments to Novant Health Occupational Medicine, Brodart, Matrix Health and Safety Consultants, the NC Rush Triad Soccer Club with a fund balance appropriation, and the Richland County Sheriff's Department) were taken in one motion and passed unanimously. Public comment (four speakers): noise at the proposed Gun Club Road plant, property tax rates, opposition to data centers, and Marsie West congratulating Martin on his retirement.

  • Clerk to the Board: Ashleigh B. Matthews.

Issues discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

01:59Mhm.

14:54>> Good evening.

14:56I'd like to welcome everyone to the

14:58regular July 30th, 2026 meeting of the

15:01Forsyth County Board of Commissioners.

15:04If you are here to speak about zoning

15:06cases, that's F-1667

15:09or F-1669,

15:12you do not need to fill out a speaker

15:13card. The public hearings for these

15:16items are first on the agenda.

15:19However,

15:20any citizens who are interested in

15:22participating in the public session

15:25portion of this meeting later,

15:27you may do so in person or by calling

15:31336-422-1200.

15:34That number again is 336-422-1200.

15:38You'll be placed on hold until the

15:40public session begins.

15:42Members of the audience who are

15:44interested in participating in the

15:45public session, please fill out a

15:47speaker card if you have not already and

15:49return it to our clerk. You could even

15:51do that now. But again, if you're here

15:53for the public hearings, you do not need

15:55to fill out a card.

15:57Um we will begin our meeting tonight

15:59with an invocation from my pastor,

16:02Reverend David Beam, from Mount Tabor

16:04United Methodist Church. It'll be

16:06followed by the pledge of allegiance led

16:08by Commissioner McDaniel. I'd like to

16:10invite everyone to stand who is able.

16:18>> Good evening, Mr. Chairman. I'm going to

16:20share a prayer adapted from Peter

16:22Marshall, who was the chaplain of the US

16:24Senate back in the late 1940s. Thought

16:26it was very appropriate for today. Pray

16:28with me.

16:31Almighty God, creator of all things and

16:33giver of every good and perfect gift, we

16:36ask for your presence and your blessing

16:38as we gather today.

16:40Grant us wisdom, humility, and

16:42discernment as we consider the matters

16:44before us and make decisions that affect

16:46the people of this county.

16:48We acknowledge that we all fall short.

16:51We confess our pride, our self-interest,

16:53and the times we fail to seek what is

16:55best for all people. Forgive us, renew

16:58our hearts, and shape our character so

17:01that we may serve with integrity,

17:03compassion, and courage.

17:05Help us not to become comfortable with

17:06the challenges that surround us or

17:09indifferent to the needs of our

17:10neighbors. Instead, give us eyes to see

17:13where help is needed and hearts that are

17:15willing to respond.

17:17We pray for all who have been entrusted

17:19with positions of leadership and

17:20responsibility.

17:22Give them wisdom to make sound

17:23decisions, strength to do what is right

17:26even when it's difficult, and the

17:28humility to listen, learn, and work

17:30together for the common good.

17:33May each person in this room be

17:34committed not to adding to the problems

17:36we face, but to becoming part of the

17:38solution.

17:40Remind us that when we seek your

17:41guidance, even the most difficult

17:43challenges can be met with hope and

17:45perseverance.

17:47We ask these things in the name of Jesus

17:49Christ our Lord. Amen.

17:51>> Amen.

17:53>> Pledge

17:54allegiance to the flag

17:55>> of the United States of America,

17:57to the republic for which it stands, one

18:01nation under God,

18:03indivisible, with liberty and justice

18:05for all.

18:07>> [clears throat]

18:11>> Thank you, Pastor Bean.

18:14First item on the agenda is our public

18:16hearing on the zoning petition of Julia

18:18Wall, Wall Family of North Carolina LLC,

18:22Jennifer Job, James Martin Serber Jr.,

18:25and James Martin Serber the III from RS

18:2920 and GI to LIS, Limited Industrial

18:33Special Zoning. And that's the zoning

18:35docket F-1669.

18:38I'd like to call on Chris Murphy,

18:39Planning and Development Services

18:41Director, to give us a brief overview of

18:44the request. He's done this twice before

18:47with us.

18:48So, you may begin.

18:55>> I can't promise you brevity, but I will

18:57give you the staff report and the report

18:59of the Planning Board.

19:01Good evening. This is a rezoning request

19:03of F-1669 to rezone a 128.54

19:08acre

19:09tract located at Northwestern side of

19:11Bethania Rural Hall Road, north of

19:12Tobaccoville Road, and the terminus of

19:14Glade Street. And the request is to go

19:16from RS20 and GI to LIS for several

19:21uses under that special use district

19:23request.

19:25This is the subject property shown on

19:27the Forward 2045 Growth Management Area

19:29Plan Map. It is located within GMA 3

19:32Suburban Neighborhoods.

19:36This is the subject property highlighted

19:38in yellow.

19:39Again,

19:40it is case F-1669.

19:44It is about 129 acres. You have

19:46residential property to the east,

19:49some limited business property to the

19:50southeast, some residential property to

19:53the south, and

19:54and southwest, and west, and then you

19:57have some existing GI and GIS property

19:59to the north and northwest.

20:06Subject property outlined in yellow on

20:08the countywide aerial imagery. You do

20:10see a couple of existing farm ponds on

20:13the property. Those are to remain. You

20:14also see some streams

20:17that travel through the central south

20:19central portion of the site.

20:21There is a Duke Energy substation to the

20:25north, and there are power lines that do

20:28traverse this property from the north

20:31northwest to the south southeast, and we

20:33will see those on some of the site

20:34imagery that we have later in this

20:36presentation.

20:37Again, calling attention to this has

20:40been an agricultural use. You do have

20:43some existing single-family homes

20:45located around the perimeter, along with

20:47some industrial to the north, and some

20:50limited business uses across Bethania

20:53Rural Hall Road.

20:57Subject property shown on the Rural Hall

21:00Area Plan Update. This is the subject

21:03property, and it is in a purple color,

21:05and that purple color represents the

21:07recommendation for a mixed-use

21:09development.

21:10Mixed-use in this context is a

21:12um

21:13could consist of residential along with

21:15other commercial and institutional uses.

21:19And that is the recommendation that came

21:20out of that plan, which was adopted in

21:222016.

21:25Again, it does have surrounding

21:27residential and commercial around it and

21:30some industrial to uh the north.

21:35I'm going to go through a few site

21:36images now. This is looking north from

21:38Bethania Rural Hall Road into the

21:39subject property.

21:42This is looking south along Bethania

21:44Rural Hall Road at the Rural Hall town

21:46hall. Subject property would be on the

21:49right-hand side of this image uh on that

21:51north side of Bethania Rural Hall Road.

21:55This is looking east along Bethania

21:57Rural Hall Road. The subject property is

21:59on the left.

22:01This is looking northwest on on Glade

22:03Street, uh and Glade Street is proposed

22:05to extend into the subject property as

22:07an emergency access.

22:09And that is uh this is the location

22:11where that terminus would be. This is

22:13that northern terminus of Glade Street,

22:15and this is where a proposed secondary

22:17interest would be, but it would be gated

22:18and used for only emergency purposes.

22:22Uh this is looking east from Glade

22:24Street at downtown Rural Hall.

22:28This is looking north into the subject

22:29property from just north of Nazareth

22:31Lutheran Church. Uh this is one of the

22:33ponds on the site that is proposed to

22:35remain.

22:38Again, looking north into the subject

22:39property.

22:41Looking north into the subject property

22:42along where the existing uh power lines

22:45are located, and you see the substation

22:46in the background.

22:48Uh that's this feature here where the

22:50topography goes down and then rises back

22:53up. This is one of those stream

22:54features.

22:57Uh this is the site plan. The site plan

23:00is composed of three two-story buildings

23:03with a maximum height of 85 ft.

23:06Uh each of those buildings

23:08each of those floors in those buildings

23:10is approximately 187,000 sq ft. So, each

23:13building is over 360,000 sq ft.

23:17If that math is right. Uh and is a

23:19proposed to be right around 1.2 to 1.3

23:22million total square feet. You do see

23:24that the buildings

23:26under this site plan have a north-south

23:29orientation and they do have outdoor

23:32equipment yards where generators and air

23:35handling units will be located. And

23:37whenever I get to the next image, I

23:39think it's the next image, you'll see

23:40what those buildings will look like. You

23:42do have one primary exit here off of the

23:44main entrance and exit off of Bethany

23:45Road Hall Road. You have the emergency

23:48exit off of Glade.

23:51Um you do have some proposed stormwater

23:53management ponds and there is this area

23:55that's been set aside as potential

23:57parkland to be dedicated to the town of

23:59Rural Hall.

24:01Again, substation, power lines pulling

24:04through the site, streams

24:07running through the middle of the site.

24:11This is

24:12one of the

24:13elevations of what the building would

24:15look like. Tilt-up concrete panels with

24:17some brick accents.

24:19Uh you also have a 30-plus foot tall

24:23noise attainment wall where the

24:24generators and some of the air handling

24:25equipment would be behind those

24:28behind that feature.

24:30There will also be some some of those

24:32type panels on the roof for the

24:34um

24:35air handling units that would be on top

24:36of the roof.

24:40This is looking a little bit closer at

24:42some of the outdoor equipment area.

24:43Again, this is the one of the proposed

24:45buildings. This is where the air

24:47handling and generator units would be

24:49and again this would be proposed to be

24:51enclosed with this fencing structure

24:54here that would help

24:57with some of the noise.

25:02Similar image, this is talk there are

25:06some similar type noise attainment

25:08features on top of the roof where some

25:10of the air handling equipment will be

25:12and this is a decorative fence that

25:14would be

25:16visible from public ways.

25:19And the entire site is proposed to be

25:21fenced.

25:23Um, but this decorative fence is what

25:25would be seen from public ways.

25:28Uh, this is a cut sheet and isometric of

25:31some of those air handling units.

25:34I will if there's any questions that

25:35need to be asked about that, I will

25:37defer to the petitioner, but again this

25:39was included as part of the

25:41request.

25:44Looking at the environmental features

25:45which I've already touched on, you do

25:47have again several streams that run

25:49through the property. You have the

25:51existing farm ponds. You have some

25:53proposed storm water management ponds.

25:55You have some buffer areas to remain

25:57around the edge and you have some buffer

25:59yards that will be installed. Again,

26:01streams running to the southwestern

26:03portion of the site.

26:05And the site does slope down obviously

26:07to those streams.

26:09As following that natural topography.

26:14At one of your earlier briefings, there

26:16was a request to

26:18examine whether or not the westernmost

26:21building could be reconfigured in a way

26:23that would

26:24um,

26:26lessen some of the impact to the homes

26:28along that western boundary. They took

26:30the rectangular building and have turned

26:32it more into a square building still

26:33getting the same square footage which

26:35allowed that building to be concentrated

26:36more to the northern portion of the site

26:39as opposed to extending

26:41uh, down in this area.

26:45So again, instead of a north-south

26:47orientation is more of a square

26:48orientation and centered or moved more

26:50towards the northern portion of the

26:52site.

26:56This is the revised

26:59condition related to the

27:02decibel level

27:04through some of those discussions with

27:05the petitioner.

27:07They have modified that condition

27:12going down to a 55 decibel versus a 60

27:15what was originally proposed and the

27:16request was to go down to 50. They split

27:19the difference and went to a 55 decibel

27:20level that they can attain.

27:22And so that is modified in your special

27:25use permit should it be issued and it's

27:28also in the written consent to

27:29conditions that's in your pocket. This

27:31is the revised set of conditions and

27:33B and C were the only things that were

27:35changed in that written consent to

27:36conditions, but again you do have that

27:38revised set in your pocket.

27:43>> [sighs]

27:43>> Provide a little bit of summation.

27:47We've been [clears throat]

27:49reviewing this and looking at this and

27:51talking about this since early 2026.

27:55Um

27:56and from where the plan came in to where

27:59it is today, great strides have been

28:02made to make this a site plan that can

28:05be approved and to make this something

28:07that would

28:08lessen the impact to the surrounding

28:09property owner. The developer you know

28:11worked very hard on this plan.

28:14Uh staff worked with them, gave them

28:17conditions of approval to mitigate the

28:19potential visual, auditory, and

28:20environmental impacts of the request.

28:23But however, the scale and intensity of

28:25the proposed use

28:27staff and the planning board both feel

28:28like could result in significant offsite

28:30impacts to nearby residents despite

28:32these conditions.

28:35The proposal is inconsistent with the

28:36Rural Hall Area Plan updates

28:38recommendation for mixed use development

28:40of the subject property.

28:42And the request is also inconsistent

28:43with the recommendations of Forward 2045

28:45to protect neighborhoods from

28:47inappropriate non-residential

28:48encroachment.

28:51This was heard by the planning board at

28:52their June 11th, 2026 public hearing.

28:55There were numerous speakers in

28:57opposition. As you see, there are

28:59numerous folks here tonight as well

29:01that spoke related to concerns to the

29:04incompatibility of the use with

29:06surrounding uses, the potential impact

29:08to property values,

29:10impact to the environment, the impact of

29:13noise, and the inconsistency with

29:15Forward 2045 and the Rural Hall Area

29:17Plan update.

29:19Following the public hearing and

29:20extensive discussion at the planning

29:22board level, the planning board did vote

29:24to recommend denial of this request by a

29:267-2 vote.

29:28And with that, I'll be glad to answer

29:30any questions.

29:31Any questions for Chris?

29:35Thank you very much.

29:37This is a public hearing

29:40and on July 9th, the Board of

29:41Commissioners voted to extend the public

29:44hearing time to a total of 1 hour.

29:47Speakers will have up to 30 minutes

29:49total to speak in favor of this request

29:52and up to 30 minutes total to speak in

29:55opposition.

29:57Due to the large number of attendees

29:59tonight and to ensure that voices are

30:02heard multiple, it is recommended that a

30:06spokesperson be appointed so you have

30:08several people who could perhaps speak

30:10for a group. And with the within the 30

30:15minutes, we're going to have speakers

30:17will be limited to 3 minutes each.

30:19However, if there were any time left

30:21over, we'll keep the 30 minutes on one

30:23timer, the 3 minutes on another. If

30:26there was any time left over within the

30:2730 with with folks going along, we could

30:30certainly have another 3 minute speaker.

30:33So, at that point, I'm going to get I'll

30:36wait till the first person comes up, but

30:38is there anyone wishing to speak in

30:40favor of the petition? This is in

30:42support of the data center.

30:49Correct. Come right up. If you're here,

30:51just give us your name

30:53and address.

30:59Let me get my timer set correctly.

31:05>> [clears throat]

31:10>> 3 minute timer set and the three minutes

31:12gives your name and address and we're

31:13ready to go.

31:15>> My name is Morty Serber. I live at 8094

31:18Glade Street.

31:20Uh Chairman Morton and South County

31:21Commissioners, I'm here to speak on

31:24behalf of the land owners.

31:26Julia Wall, uh James Serber the third,

31:31uh Julia Wall Serber, my wife, and Brian

31:35and Jennifer Wall Joe.

31:38When people ask why our family made the

31:40decision to sell this land,

31:42I think it's important to start with our

31:44history.

31:45The Wall family has called this farm

31:47home for over 100 years.

31:49My wife and her siblings are the fourth

31:51generation to care for this land.

31:55Their great-grandfather, grandfather,

31:57and father invested their lives here.

32:00I met my wife Julie in 1979

32:04after serving in the US Navy.

32:06After we were married, we built our home

32:09on the back side of the farm

32:11and raised our family there.

32:14I [clears throat] was raised 2 miles

32:15from the farm on Tuttle Road.

32:20Our roots run very deep in this

32:21community.

32:23Anyone that has farmed understands how

32:25much blood, sweat, and tears

32:27goes in we put into the land.

32:31We've also been blessed to

32:34enjoy the benefits of learning from the

32:36past generations.

32:38We've learned the rewards of hard work.

32:41The farm has had many agricultural uses

32:43through the years, including tobacco,

32:46dairy, beef cattle, horse,

32:49and horse breeding operations, along

32:52with raising all the grain, hay, and

32:54silage to feed all the livestock.

32:59My wife's father, Ed, had a saying that

33:01always made people smile.

33:05He said, "He couldn't get rid of any of

33:07his children. They just brought more

33:08home with them."

33:11And now we've raised the fifth

33:13generation,

33:14and the sixth generation is growing and

33:16learning on the farm today.

33:19This land isn't just where we live, it's

33:22how we lived.

33:24I want to be clear this was not a easy

33:26decision. Like so many family farms,

33:28times have changed.

33:31Many changes have occurred along the

33:32property line.

33:34>> [clears throat and snorts]

33:34>> Several businesses have moved in,

33:36concrete mixing companies,

33:39garbage companies,

33:41paving companies,

33:43mulch, pallet grinding companies.

33:46They've all changed the purpose of our

33:50farm.

33:51We're not able to do with the livestock

33:53what we once did along the property

33:55lines.

33:56>> [cough]

33:57[clears throat]

33:57>> It's become an expensive hobby, and

34:00most years you're lucky even to break

34:02even.

34:03>> [clears throat]

34:04>> While many families invested in

34:05retirement accounts, our family invested

34:08in the land.

34:10Rural life has changed, too. What once

34:11was a quiet farming community has grown,

34:14and today even driving a tractor on

34:16Bethany Rural Hall Road

34:18is a safety concern.

34:20>> [clears throat and cough]

34:20>> Mr. Server,

34:22let me just I was going to try to stick

34:23to my opportunities. You may return, but

34:26I was going to stop you in 3 minutes and

34:29see if we could have another speaker,

34:31and then if we don't have any, you can

34:32come back and we have our 30 minutes,

34:34so.

34:35>> All right.

34:35>> If there's another speaker, please come

34:37forward.

34:54>> I'm here on behalf of the town of Rural

34:56Hall. I'm the current mayor, Terry

34:59Bennett. Live at 267 Spring Ridge Road.

35:03I'm coming up because it probably would

35:05fall under the four because we made a

35:08decision to support it.

35:11Chairman, commissioners, and members of

35:13the public, thank you for the

35:15opportunity to speak. My name is Terry

35:17Bennett and I serve as mayor of Rural

35:20Hall. I'm here tonight on the behalf of

35:22the Rural Hall Town Council to explain

35:25why the council voted to support the

35:28proposed project Iron Spur.

35:31Um

35:33this has not been an easy decision for

35:35our community. Over the past several

35:38months,

35:39residents have expressed concerns,

35:42uh sincere concerns regarding traffic,

35:45noise, water resources, environmental

35:47impacts, view sheds, and the overall

35:50character of northern Forsyth County.

35:54Those concerns are real. They deserve to

35:56be heard and they should continue to be

35:58considered uh throughout this process.

36:02I and town and our town council share

36:05many of those same concerns when this

36:08proposal was first presented.

36:11However, after months of meetings with

36:13the developer, county officials, state

36:16officials, and members of our community,

36:19one fact became increasingly clear.

36:22The town of Rural Hall does not have the

36:25legal authority to determine whether

36:27this property develops.

36:29That authority rests with Forsyth

36:31County.

36:33As a municipality without zoning

36:35jurisdiction over this property, our

36:37decision was never between approving or

36:40denying the project. Instead, our

36:43decision was whether to remain on the

36:46sidelines or engage constructively in an

36:50in an effort to protect the long-term

36:53interests of our community if the if

36:56this project moves forward.

36:58We [clears throat] chose engagement.

37:00Our support should not be interpreted as

37:02an unconditional endorsement of every

37:05aspect of this proposal. Rather, it

37:08reflects our belief that if a project of

37:10this magnitude is ultimately approved,

37:14Rural Hall has a responsibility to work

37:16towards the outcomes that benefits our

37:19residents while helping mitigate impacts

37:22where possible.

37:24Our community will bear many of the

37:26demands association associated with this

37:29development. Our roads, emergency

37:32service, local government

37:34will experience increased demands over

37:36time.

37:38If those impacts are going to occur, it

37:40is only reasonable that the community

37:43sharing

37:44those responsibilities

37:46also share in the long-term economic

37:49benefits created by this project.

37:52That principle guided our decision.

37:56>> Mr. Mayor, are you close if you're

37:58close, you can finish up.

38:01All right. If you want you can come back

38:03later.

38:03>> Yeah, let me come back because I want to

38:05make sure we cover all that.

38:08>> Another speaker.

38:20>> Good evening, Chairman Martin, members

38:22of the board. I'm Michael Fess, the

38:23project manager for Iron Project Iron

38:26Spur. I wanted to address two things

38:27tonight. First one, the property value

38:30concern that was brought up at the last

38:32meeting, as well as um

38:35staff's two plan consistency findings.

38:38The concern we heard the most about a

38:40project this size was that it could

38:42lower the property values of nearby

38:43homes. That concern deserves a serious

38:46answer, and I want to give two.

38:48The first is the evidence. Two studies

38:51have been performed, one by George Mason

38:53University, a peer-reviewed study, and a

38:55second performed by a certified

38:57appraisal

38:59um firm out in Indiana. Both of those

39:01came to the same conclusion. Homes near

39:04the data centers rose in value

39:07essentially at the same rate as the

39:10surrounding county.

39:12Um

39:13two studies, two very different methods,

39:16the same answer. But we don't ask these

39:18families to rely on those studies alone.

39:21At our steering committee meeting on May

39:235th, the residents themselves asked

39:26whether the developer, the applicant,

39:28would compensate them if their values

39:30declined as a direct direct result of

39:33this project. I'm going to repeat that.

39:35The members of the steering committee

39:37requested that a a fund be put together

39:40on May 5th.

39:42The $2 million property value protection

39:44fund is our answer, and it's dedicated

39:46to the single-family homes closest to

39:48the project.

39:50And we didn't define closest loosely.

39:52So, we um handed out this sheet here,

39:56which has 56 properties on it, um all

39:59located within that 500-ft boundary.

40:07Those combined tax values of those prop

40:09residential properties are about 10 and

40:111/2 million dollars. Against that $2

40:14million fund, And covers roughly 19% of

40:17the combined value. Even in the scenario

40:19the research calls unlikely, real money

40:22is set aside in advance to stand behind

40:24those owners owners before a single

40:26foundation is poured. And it will be

40:28binding, tied to voluntary annexation

40:31into the town of Rural Hall or secured

40:34through a developer agreement with the

40:35town. No ordinance

40:38uh requires it. We're offering it

40:39because the families two streets over

40:41should not carry the risk of our

40:43investment.

40:46With the commitments on the table, let

40:47me turn to staff's two consistency

40:49findings. One was protect neighborhoods

40:51from inappropriate non-residential

40:53encroachment, and two the inconsistent

40:55with the Rural Hall Area Plan Update.

40:58The first finding concerns compatibility

41:01with the neighborhood. Goal four of the

41:032045

41:04plan's managed growth and land use

41:07chapter aims to create compatible

41:09transitions between land uses.

41:12The transition elements of our project

41:15include significant buffers ranging from

41:17four times the minimum width to over

41:201,000 ft,

41:22preserving 76% of the open as site as

41:25open space, excluding closed-loop

41:28cooling systems.

41:29>> Okay. Can I can you bring that thought

41:31to a close and we'll switch to another

41:33speaker?

41:34>> Absolutely.

41:36>> Mr. Kim, come come ahead.

41:38>> Thank you.

41:48Thank you all.

41:50>> Good afternoon commissioner and chairman

41:52and members of the community. My name is

41:54Carl Borgon. I'm from Germantown, North

41:56Carolina. Lived there 38 years. I've

41:58been working in data center and

42:00infrastructure technologies for over 30

42:02years, starting out in the mid-90s

42:04uh with uh

42:06um US Airways

42:08at Madison Park and then also at Lowe's

42:10Home Improvement Madison Park. after

42:13that. I've also worked for for several

42:15years at Wachovia Bank at Silas Creek

42:17and 4 and 1/2 Street.

42:19I have a extensive experience in

42:22data center infrastructures. The last

42:24several years I've been

42:25a senior infrastructure project program

42:28manager for Dell and DXC working on

42:31technologies all over the world.

42:34Because of this this is my experience.

42:36I've worked in data centers

42:38most of my life. Mostly as an engineer

42:41for many years.

42:42So the sound the there's the

42:46the

42:47you know there's just many different

42:49um

42:51jobs that are also

42:53very important. You know you've got HVAC

42:55jobs. You have special

42:57fiber specialist, network specialist,

42:59security officers, custodians,

43:01landscape, construction workers, project

43:04managers, many other skilled

43:05professionals in the area. And so

43:08there's been a lot of discussion about

43:09data centers

43:11and the experience

43:12they're the most cleanest, carefully

43:15maintained work environments

43:18of any industry and stuff. They're also

43:21temperature controlled, humidity

43:23controlled, and air quality very tight

43:25because of the equipment.

43:27And stuff. And so they're they're not

43:29noisy. They're very

43:30quiet for say inside the data center.

43:34We also had phones all over the um

43:39data center floor where we would talk on

43:40the phones. So if you're sitting in a

43:42really loud environment, you can't talk

43:44on a phone. But we were able to we

43:46didn't have cell phones at the time. We

43:48talked on the wall. Um

43:51now the

43:52technology

43:54you know the technology has all changed.

43:58And um

44:01over the last year I've come up with a

44:04nonprofit organization called Pine Hall

44:06Disabled Veterans. Our mission is to

44:08help disabled veterans in late and

44:10at-risk veterans rebuild their lives

44:12through transitional housing, workforce

44:14development, and training. As part of

44:16our mission, we're developing a data

44:18center infrastructure training program

44:20for South for uh

44:23Forsyth County. We're also working with

44:25Forsyth Technical Community College to

44:27create a training program in Danbury and

44:30eventually on our campus when we secure

44:32a location. Our goal is not just

44:34training veterans. We're also giving

44:36high school graduates and college

44:37students from Stokes and Forsyth County

44:40the opportunity to learn a valuable

44:41technical skills, so they're able to

44:43take and come

44:45and and have something other than just

44:48coming out of school and moving to

44:50Charlotte or Raleigh or someplace else

44:52because of jobs. We need jobs in our

44:54area.

44:55>> Yeah, if you can just finish the

44:56sentence.

44:57>> Okay. And so uh I'm

44:59um

45:02Yeah, we're I've spent traveling over

45:04the United States building data centers

45:06all over the world, and they're the most

45:07cleanest best environments that you can

45:10have to live in.

45:11>> Thank you.

45:12>> And um

45:13That's it.

45:14Is there another another speaker in

45:16support?

45:20>> Good evening, Commissioners. Scott

45:22Castle. I have multiple homes within the

45:24500 um foot distance of this proposed

45:27project. I've been in the community

45:30since 1991. I'm a retired Winston-Salem

45:33fire captain, firefighter EMT with

45:36specialty in hazardous materials as a

45:38technician, fire inspector, and rail car

45:40emergency responders. I have a degree in

45:43fire protection and I'm a licensed

45:45general contractor. I've been

45:47trying to use my training and experience

45:49to understand this proposal

45:52and um see what's the benefits to our

45:54community.

45:56Um I've had the opportunity to sit with

45:58community members on a steering

45:59committee addressing the concerns on the

46:01data center. We've discussed issues with

46:04decibel level noise, water usage,

46:06buffers, building elevations, design,

46:08low candle power directional, security

46:11entrance, etc. Let me just illustrate

46:14one point of noise in decibels. The

46:18maximum decibel level is said to be no

46:20more than 55 decibels at the property

46:23line. The inverse square law says that

46:26sound will drop 6 decibels for every

46:28doubling of distance under open air

46:31conditions. Buffers such as trees, sound

46:34barriers further reduce the noise.

46:36According to the planning commission,

46:37the detailed sound barriers of 30 ft

46:40surrounding all this equipment further

46:44uh makes this issue less concerning. The

46:47town of Rural Hall has been a major

46:48thoroughfare bordering Forsyth and

46:51Stokes. Old 52 Broad Street,

46:54Route 66 has been used for years as the

46:56core transportation road through this

46:58town. Highway 65, Rural Hall Bethania

47:01Road is the gateway to our two largest

47:03business parks, North Ridge Business

47:05Park and Forum Parkway. These two

47:08industrial areas have been in existence

47:10since 1980. They contain acreage four

47:13times larger than this proposal and the

47:16one mile down the road.

47:18Um

47:21one of the things that is is been in

47:24there and one of the signs, Rural Hall,

47:27um

47:28is keep it rural. Rural Hall is not

47:31rural anymore. It hasn't been for 20

47:34years due to the traffic and the

47:36business parks that are here. It's a

47:38nice slogan, but it's not accurate.

47:41Um

47:44To the east of the proposed site is the

47:45Yadkin Valley Railroad that came into

47:47town in 1881.

47:50Um it comes out of Winston-Salem and

47:52goes to the Yadkin Valley in Mount Airy

47:54every day. This

47:56uh depot is a major off loading site for

47:59Colonial Pipeline that usually 100 rail

48:02cars are located and stored in this

48:04town. The noise decibel of this train

48:07and this traffic is 110 decibels on a

48:10daily basis. The train depot alone is a

48:13significant higher hazard than this data

48:15center could ever be. To the north of

48:18grade street, we have general industrial

48:20businesses for site ready mix, ABC

48:22garbage, Stanly Road Paving, former

48:24Grady Furniture, AJ Pallet, former

48:27Yadkin Valley Mechanical, Spainhour

48:29Grading, Ken Gardner Company, Siemens

48:32Turbo Propane, Lantal Textiles, the

48:35Lowe's Truck Stop.

48:38>> Good. I'll see him come back.

48:50>> Good evening.

48:52My name is Donna Clayton. I live at 230

48:54Gaither Road. And I was an educator for

48:5621 years. I'll be honest with you. I'm

48:58not standing up here tonight as a tech

49:00guru or an expert on data centers. I'm

49:03standing here as someone whose heart is

49:04still very much in our classrooms.

49:07Every

49:08Even [clears throat] after stepping out

49:09of school building, you never really

49:10stop thinking about the kids in the

49:12county. You worry about their future.

49:14You care about their opportunities. And

49:15you want to make sure that they have

49:17every possible tool to succeed.

49:20This is the single reason I'm here

49:22tonight. I will always stand up for our

49:24school system. And I will always

49:25advocate for projects that have the

49:27genuine potential to support our

49:29students.

49:30When we talk about public education, we

49:32eventually have to talk about resources.

49:34We all want the best for our schools,

49:36updated facilities, competitive pay for

49:37our teachers, and modern tools for our

49:39students. But as anyone in education

49:41will tell you, these things take

49:43funding.

49:44That brings me to why I support the

49:46project. A data center campus on this

49:48scale represents a massive, reliable

49:50addition to our county's tax base. But

49:52what makes it truly unique and honestly

49:54a rare opportunity for our community is

49:56that it doesn't demand what it doesn't

49:58demand in return. When a new housing

50:00development comes in, it brings

50:02families. That's wonderful for our

50:04community, but it also means more kids

50:06in our halls, larger class sizes, and a

50:08higher cost for the county to serve

50:10those students. A data center does the

50:12exact opposite. It becomes a major,

50:14stable taxpayer, but it doesn't add a

50:17single child to a classroom roster. It

50:19expands our tax base without putting an

50:21extra strain on our school

50:22infrastructure. Beyond that,

50:25this isn't a

50:26here-today-and-gone-tomorrow business.

50:28Data centers involve long-term,

50:30multi-decade investments. They don't

50:32operate on a short-term boom-and-bust

50:34cycle. Now, I'm a realist,

50:36and I don't [clears throat] expect a

50:37single development to magically

50:39transform our classrooms overnight. But,

50:41over the long haul, this kind of

50:43durable, steady funding can make a

50:45quiet, powerful difference in the

50:46quality of education we can offer year

50:49after year. And finally, I want to think

50:51about what happens after graduation day.

50:53Every year, we watch incredible young

50:55people walk across the stage, diploma in

50:57hand, and every year too many of them

50:59pack up their bags and leave our county

51:01because they feel they have to go

51:02somewhere else to find a good-paying

51:03career.

51:04Data center campuses require a wide

51:06range of skilled technical roles,

51:08electricians, HVAC specialists, network

51:11technicians, security professionals, and

51:13facility engineers.

51:15Many of these high-demand jobs don't

51:18require a four-year college degree or

51:20massive student loan debt. They require

51:22solid technical training, strong

51:23problem-solving skills, and a good work

51:25ethic.

51:27This project gives our local kids a

51:28real, well-paying career pathway right

51:30here at our home. It gives them a reason

51:32and a financial ability to build their

51:34lives, buy their homes, and raise their

51:36own families right here in the county

51:37that raised them. When I look at this

51:39project, I don't see just server racks

51:41and concrete. I see a stronger tax base

51:44for our schools, and I see a future

51:45where our kids don't have to move away

51:47to thrive. Imagine what this looks like

51:50in practice. It gives our local high

51:51schools and CTE programs a different

51:53target to aim for. We can partner with

51:55these facilities to create

51:57apprenticeships, technical

51:58certifications, and hands-on training

52:00while our kids are still in school.

52:03>> Yeah, can I interrupt you? Sorry.

52:05What's the 3-minute part?

52:06>> I got you.

52:14>> Hello, my name is Joe Royce and I live

52:15at 772 Ashley Drive in Rural Hall. I

52:17come here tonight in support of the

52:19proposed data center to be built in

52:21Rural Hall. Approving this plan isn't

52:23abandoning Rural Hall's character. It

52:25complements the existing adjacent

52:27industrial development and provides a

52:29transitional zoning path from general

52:32industrial to light industrial to

52:33commercial, business, and residential

52:35uses.

52:36I would like to read you a quote from a

52:39statement published by the Catawba

52:40County Economic Development Corporation.

52:43"Data centers typically generate

52:45substantial property value due to the

52:47scale of the buildings, equipment, and

52:49technology infrastructure involved.

52:51At the same time, they generally place

52:53lower demand on traditional multiple

52:55services for many other types of

52:57developments. They do not typically

52:59create significant school enrollment

53:01growth, daily

53:03daily commuter traffic, solid waste

53:06collection needs, or frequent police and

53:07fire calls for service.

53:09That combination matters to residents in

53:11a practical way. New taxable investment

53:14helps pay for these services and roofs

53:16and proves communities

53:18count on, including firefighters, police

53:20officers, public safety equipment,

53:23parks, roads, water and sewer

53:25improvements, and other local needs.

53:27When major investments help carry that

53:29cost, residents and small businesses are

53:32not left carrying it alone. Today's

53:34modern data centers, like the ones in

53:36Catawba County, use closed-loop cooling,

53:39even uh newer technology in their

53:41operations. They are not using the open

53:43loop systems that have been associated

53:45with high water intensity. Newer

53:47facilities are implementing different

53:49infrastructure and sound barrier

53:51barriers to help eliminate the effects

53:54many have been vocal about. And the myth

53:56that it raises electric bills can be

53:58traced to the White House Ratepayer

54:01Protection Pledge, the Ratepayer

54:04Protection Act HR 99340,

54:07and in North Carolina, the North

54:08Carolina Utilities Commission set rates

54:10through a regulated process.

54:13Services

54:14we rely on such as banks, hospitals, and

54:16even grocery stores depend on the

54:18availability of data storage and

54:20processing that can provided by projects

54:22like this. Not to mention the the

54:24majority of the general public uses

54:26these facilities every day without even

54:28knowing it. Anytime you're on social

54:30media, using your smartphone, browsing

54:32the internet, using Google Maps to get

54:34somewhere, which I imagine many people

54:36use that to get here tonight, tracking a

54:39package delivery, or even watching

54:41Netflix, you're using a data center.

54:43Data AI

54:45and cloud storage are here, and it's

54:46here to stay. We should be showing

54:48support for it, capitalizing on the

54:50positive effects it can have, or other

54:54option

54:55it's to stand back, and keep our hands

54:57in our pockets, and let the other

54:59countries take the lead, and we know

55:01what consequences of that will be. So,

55:03tonight I hope you will support the

55:05project and vote for it. Let's open the

55:07window for opportunity for this county,

55:09and be a leader for others to follow.

55:11Thank you.

55:14>> We have 6 minutes left, so we can

55:16probably get two almost two speakers in.

55:34>> Good evening, board

55:35members, mem- neighbors, and everyone

55:38attending on this beautiful day.

55:40My name is Bishop Albert Saunders. I

55:42serve as senior pastor of the Great New

55:44Hope of Faith Love Connection Church.

55:46I don't I do don't understand I do stand

55:50before you tonight not as an engineer or

55:53developer

55:54or a zone expert. I stand before you as

55:58a pastor, a man who spent years walking

56:02alongside families in the community,

56:05celebrating baptism,

56:08having funeral services.

56:10Because I know this community, I care

56:13deeply about the future.

56:16When we talk about

56:18stewardship, we often think about

56:20protecting what we have. But I believe

56:23stewardship also means using the

56:26resource God has given us wisely to

56:29create the opportunity for future

56:31generation.

56:33This proposal dental center present more

56:37than more than just other construction

56:39project. I represent investment, jobs,

56:43present growth, it present opportunity

56:46to strengthen our local economy, while

56:49preparing our community for the future.

56:52As a pastor, I see young people looking

56:55meaningful career without having to

56:57leave home, see families hoping that

57:01they'll have to find a job somewhere

57:02else. I see churches, schools, and

57:04community organization that benefit when

57:07a community economically is healthy.

57:10Growth and preparation

57:12do not have to compete or with one

57:15another. We can work together when

57:18development is done to

57:21to faithfully represent to us.

57:24What we

57:25What has encouraged me about this

57:27project is that developer has

57:30demonstrated a willingness to listen,

57:32engage with the community, and working

57:35towards being good neighbors. That

57:37matters, relationship matters, that

57:39trust matters. I believe this project

57:41can provide a long-term benefit while

57:44respecting people who already call

57:46themselves community home. Tonight, I

57:49respectfully

57:51ask you to consider supporting the

57:53zoning request, not simply because of

57:56what we built, but because of what we

57:58can help build stronger family, greater

58:02opportunity, economy, growth, and hope,

58:05and expand our community. Thank you for

58:08your time and your service in the

58:10community in following

58:12Allow me to share my heart with you, and

58:15may God bless you, and thank you for all

58:17you doing in the community.

58:18>> Thank you.

58:19I probably time for one more.

58:23Got 2 minutes and 45 seconds.

58:25>> 45 seconds.

58:29>> All right, I'll jump right right into

58:31it.

58:32All right, to to our knowledge, no other

58:35proposal offers this combination of

58:37benefits. It preserves about 76% of

58:41property as open space while generating

58:43tax revenue for county services,

58:46schools, and public safety. If this land

58:47is going to change, we wanted it to

58:50change into something that benefits the

58:51community and the county.

58:54Another vivid saying has stayed with me.

58:57He always believed we could accomplish

58:59what we do on less expensive land.

59:03Looking back,

59:05I know he was right.

59:07>> [snorts]

59:07>> All the property owners agreed to this

59:09decision. We know we carry a deeper

59:12responsibility

59:13than anyone to protect this land. We've

59:17loved it, we've worked it, and cared for

59:19it for nearly a century.

59:22At the end of the day, this isn't about

59:24giving something up. It's about choosing

59:27what this land is the best suited for

59:29next.

59:31Our family has chosen a future that

59:33honors our legacy,

59:35protects the land, benefits our

59:37community,

59:39and allows us to continue farming the

59:42way the Wall family has for generations

59:45to come.

59:47Thank you for your time and

59:48consideration.

59:50>> You

59:51actually have a minute and 18 seconds

59:53left. If there's anyone else that wants

59:55to say a word, quickly.

1:00:00>> Mr. City Attorney, what Mayor, won't we

1:00:02let her let her

1:00:09>> Hello.

1:00:12My name is Antoine Salisbury,

1:00:15and I have the privilege of representing

1:00:17Neil AI, probably recognized as North

1:00:19Carolina's first black-owned artificial

1:00:21intelligence software and commercial

1:00:23robotics company.

1:00:25We're not here today because this

1:00:26project benefits our company alone.

1:00:29We're here because we believe it

1:00:30benefits our company, our community, our

1:00:33economy, and the next generation.

1:00:36This isn't simply about building another

1:00:38data center.

1:00:39Every artificial intelligence platform,

1:00:42every cloud application,

1:00:44every autonomous robot, every smart

1:00:46hospital, every modern manufacturer,

1:00:49every school embracing AI,

1:00:52depends on data centers.

1:00:55Without them, there is no AI economy.

1:00:58And if North Carolina wants to remain a

1:01:00leader

1:01:01in innovation, advanced manufacturing,

1:01:04and technology, we must invest in the

1:01:07infrastructure that powers it.

1:01:10As a local AI company,

1:01:12we've had a front-row seat to how

1:01:14quickly this industry is growing.

1:01:17Businesses across every sector are

1:01:19asking for AI solutions, robotics,

1:01:22automation, and cloud computing.

1:01:25Those technologies don't run on ideas

1:01:27alone.

1:01:28They run on reliable, secure,

1:01:30high-performance data centers.

1:01:32>> Thank you.

1:01:33We've reached our time, all right. Thank

1:01:35you.

1:01:35>> Thank you, sir. Thank you.

1:01:36>> All right.

1:01:40All right.

1:01:41Is there anyone wishing to speak in

1:01:42opposition to the petition?

1:01:44Do the exact same thing. Come on up. You

1:01:46can introduce and I'll get our timers

1:01:48going.

1:01:50>> My name is James Woodard. I live at 150

1:01:52Presswick Lane in Rural Hall. I'm going

1:01:53to present you guys these petitions.

1:02:05This don't count for me, right?

1:02:07>> Yeah, it is. Let's go.

1:02:11I'll stop for a second.

1:02:12>> Thank you.

1:02:14All right. What I put out there are some

1:02:16petitions. They are totaling uh

1:02:17signatures in Rural Hall's 1,243

1:02:20total signatures representing 11 and

1:02:221/2% of the population of the town of

1:02:23Rural Hall.

1:02:25All right. These rules that we have, we

1:02:28I represent a group of people, concerned

1:02:29citizens of Rural Hall. There's about a

1:02:31They're not all in here, but it's about

1:02:32150 or so of us. We're uh

1:02:35fairly well organized. We ran We kind of

1:02:37run the gamut from

1:02:39farmers, teachers, preachers,

1:02:40educational professionals, medical

1:02:42professionals, things of the like to

1:02:43just everyday folks.

1:02:45Uh we want to start out by saying we

1:02:48agree with the Plan Forward 2045. We

1:02:50agree very much with the Rural Hall Area

1:02:52Plan Update. We specifically agree with

1:02:56uh Mr. Chris Murphy's statement that

1:02:57even if these conditions are met, there

1:02:59would still be significant offsite

1:03:00impacts.

1:03:02Um that's

1:03:03separate and apart from the millions of

1:03:05forfeited dollars in tax revenue

1:03:07everybody keeps talking about. So,

1:03:09the space designated for mixed use, uh

1:03:11this site is not mixed use in any way.

1:03:13It is one single use and it prevents any

1:03:15further use for any period of time that

1:03:18anybody in this room is going to be

1:03:19here. All right, that's another good

1:03:21reason it's not compatible with the

1:03:22plan. Denial of this project implements

1:03:25the plan rather than simply citing it or

1:03:27paying any kind of lip service to it.

1:03:30Royal Hall residents again are excited

1:03:31to implement that plan. We encourage

1:03:34mixed use as opposed to just one single

1:03:37use which would limit any further

1:03:38potential for earning down the road. Um

1:03:40that being said, I'm going to kind of

1:03:42turn this over to the rest of our group.

1:03:43Sure, thank you.

1:03:51>> Hello, my name is Robin Smith. I live at

1:03:53807 Academy Street in Royal Hall, North

1:03:55Carolina.

1:03:57Um we know Montrose and Ross, but after

1:04:00that there's significant uncertainty.

1:04:02There are at least three layers between

1:04:04commissioners and the party using the

1:04:06end user of the data center. Each

1:04:08transfer dilutes whatever assurances are

1:04:10made on July 30th a little further.

1:04:14Project Iornsfer wants to build on land

1:04:16currently zoned residential and plan for

1:04:18mixed use if sold. The professionals at

1:04:20the planning board studied this area and

1:04:22feel mixed use is the best fit. Iornsfer

1:04:25is the only data center that I

1:04:27researched not zoned industrial for

1:04:29significant period of time before the

1:04:31data center was built.

1:04:35Noise issues are not a problem of the

1:04:37past as been told by you guys.

1:04:39Um there are that I know of there are

1:04:41six class action lawsuits filed in the

1:04:43last few months. We obviously still have

1:04:46noise issues from data centers.

1:04:48Um the the main reason for the noise

1:04:50issues is we are we are studying for

1:04:52DBA. That's what everyone's listening

1:04:54for, DBA. What's the DBA?

1:04:57And the problem is the DBC, the low

1:04:59frequency noises.

1:05:01And I know that there was just a an

1:05:03agreement that we would be measuring DBA

1:05:06at 55 from the property level, but we're

1:05:08not measuring DBC.

1:05:11Every standard treatment, screen,

1:05:13louvers, delivers its rate performance

1:05:15on mid and high bands and degrades the

1:05:19degrades sharply between 250 hertz for

1:05:22precisely where the hyperscale data

1:05:24center fans concentrate their energy.

1:05:28So that's the problem. So that's why

1:05:30those lawsuits are happening.

1:05:34And then I'm going to go through one

1:05:35final slide

1:05:36of Amber's here.

1:05:39I've got this well fifth I've got the 15

1:05:41best practices of communities

1:05:42considering data centers. I did look it

1:05:44up.

1:05:46And I I was going to present cuz I

1:05:47thought it was going to be in a

1:05:48different format. It's the very last

1:05:51slide I've got.

1:05:52I was comparing the noise or the Apple

1:05:54data center which I know everyone has

1:05:56visited visited and the Iron Spur

1:05:59proposal and trust me they are vastly

1:06:01different. I wish I could have presented

1:06:02that to you.

1:06:03But as far as noise 50 dB dBA

1:06:07we know Iron Spur is a no. Apple is a

1:06:10yes. Low frequency noise we know that we

1:06:14don't know because we don't know what

1:06:15their DBC rating is going to be. And I

1:06:17can tell you that I when I went to the

1:06:20Apple center I did not hear the Apple

1:06:22center behind the berms.

1:06:24Tier 4 backup generators. We know that

1:06:27they did not make a commitment to that

1:06:29last time Dr. Martin asked.

1:06:31Setbacks required at 500 feet 1,000 feet

1:06:35is ideal. That's ridiculous. I mean

1:06:37they're at like 140 feet setback. That's

1:06:40completely not in their plans.

1:06:42Required natural screenings or principal

1:06:44facades. They do have a principal facade

1:06:47but as compared to Apple who has berms.

1:06:50Limited building height to ensure

1:06:52compatibility with the surrounding

1:06:53structures.

1:06:54I mean this [clears throat] thing is

1:06:55going to be 85 feet three of them. So if

1:06:59you feels best practice is a standard I

1:07:03cannot see how you can vote for rezoning

1:07:05in good faith against the neighbors.

1:07:07Please vote no for rezoning and no for

1:07:10project Iron Spark. Thank you.

1:07:11>> Thank you.

1:07:17>> Hey, my name is Eve and I live on Broad

1:07:19Street in Rural Hall. I understand that

1:07:20we are not here today to talk about the

1:07:22substation that it

1:07:24uh just to talk about the land the

1:07:25substation will sit on. We're here about

1:07:27the rezoning of the land behind it. I

1:07:29encourage you to think outside the box

1:07:31of the data center campus. If you choose

1:07:33to rezone the Wall Farm, this means that

1:07:35the substation based on the proposal

1:07:37will be built on the land I will be

1:07:39showing you today.

1:07:41Our train depot took on the transport of

1:07:42butane about 2 years ago. As you can see

1:07:45from the images, uh the tanker cars hold

1:07:4733,960

1:07:49gallons, so we'll round that to 30,000.

1:07:52On average, there's about 30 butane cars

1:07:54that sit in the railyard. That's roughly

1:07:57900,000 gallons of butane that sit there

1:07:59if not more um each week. In this image,

1:08:02you can see in red where the butane

1:08:04tanker sit. Um I have outlined a portion

1:08:06of the area where the proposed data

1:08:08center campus will be. The other area

1:08:10here is the newest addition to Montrose

1:08:12development, which is where they plan to

1:08:13add a 3-acre substation.

1:08:15I had some videos for you, but given

1:08:17time restraint, I'm going to skip over

1:08:19those, but I'd like to come back if

1:08:20there's time.

1:08:22Um we did have a fire this year already

1:08:25on Anderson, which is a smaller street.

1:08:27Um you're going to have more transfer

1:08:29trucks and things going through there to

1:08:31build that substation area, and one of

1:08:33the trucks this year hit one of the

1:08:35power poles, brought it down, and we had

1:08:36a small fire in that area close to the

1:08:38butane tankers already.

1:08:40Um as you can see, the Duke Power

1:08:42substation

1:08:44um we is very close by, so we will have

1:08:47two large substations sitting on top of

1:08:49the butane tankers. Per the Forsyth

1:08:51County GIS and Montrose development map,

1:08:54this means the distance from the

1:08:55railroad tracks to the substation will

1:08:56be roughly 132 ft.

1:08:59In this image, you can see the fire

1:09:00station sits 0.6 miles from the railyard

1:09:02along with the elementary school. We

1:09:04have a wonderful fire department, but an

1:09:05explosion from these tankers will send

1:09:07shockwaves and metal shrapnel flying for

1:09:09hundreds of yards. Now, imagine 30 of

1:09:12these exploding. You're looking at

1:09:13roughly a mile mile radius fireball.

1:09:16Data centers

1:09:17The data center itself will sit 100 yard

1:09:19a few hundred yards away. Um that data

1:09:21center will hold lithium ion batteries,

1:09:24chemicals for their closed loop system

1:09:26like glycol, nitrate based corrosion

1:09:27inhibitors, diesel. These chemicals and

1:09:30materials also add to the many fire

1:09:32hazards in this area.

1:09:34I would like for you to notice in this

1:09:35image that there is no security around

1:09:38the railroad tracks or the rail yard.

1:09:40Other butane locations have security due

1:09:42to the hazardous nature. Data centers

1:09:45are usually secure locations because

1:09:47they've been known for terrorist

1:09:48targets. Tonight, I've shown you what an

1:09:50easy target this data center can be to a

1:09:52terrorist attack.

1:09:53Data centers do not grow communities,

1:09:55they bury them. Families and businesses

1:09:57help our communities grow and flourish.

1:09:59Please vote no to the rezoning. Help me

1:10:01protect my family. Help protect our

1:10:03community. Don't add more fuel to the

1:10:05fire by adding additional hazards to

1:10:08this area. Next time it won't be some

1:10:10great news story about a corn spill.

1:10:12It'll be catastrophic for our town.

1:10:15Thank you.

1:10:22>> Good evening. My name [clears throat] is

1:10:24Mark Allen. I live at 8717 Makena Court

1:10:28in rural Hall. I have three critical

1:10:30points I'd like to share with you really

1:10:31fast. Montrose has not honored their

1:10:34published values on their website. A

1:10:36hyperscale data center is not limited

1:10:39industrial services A and who we trust

1:10:42in this important rezoning case matters.

1:10:55So,

1:10:57this is a copy of their values um from

1:11:00their website, and I know it looks busy,

1:11:02but that's because they have not

1:11:03followed their values. So, I will

1:11:06simplify it.

1:11:07Each blue arrow points to ways they've

1:11:10conflicted with the values that they

1:11:12published on their website.

1:11:14I don't have time to go through all of

1:11:16them, but for example,

1:11:18Michael told us from Montrose that the

1:11:20air at the the site today likely would

1:11:23not pass air quality standards. [music]

1:11:25His solution is to add 200 diesel

1:11:28generators to the site.

1:11:30If you look at the red box that says

1:11:32community,

1:11:34it says, "Our projects enhance and

1:11:36integrate with the surrounding

1:11:37communities."

1:11:39Commissioners,

1:11:40do you believe 84-ft buildings

1:11:43surrounding homes that integrate and it

1:11:46integrate and enhance the community?

1:11:49This is certainly not the way Apple did

1:11:51it in Maiden.

1:11:54My second point is that a hyperscale

1:11:56data center operating 24/7 with diesel

1:11:59generators on the outside, equipment

1:12:00yards, fuel storage is not limited

1:12:03industrial services A per the UDO. If it

1:12:07met services A, the industrial activity

1:12:10would be on the inside, not the noise

1:12:13and emissions spewing from the outside

1:12:15as shown in the picture here from the

1:12:17Wells Fargo site on Silas Creek Parkway,

1:12:20and remember, Project Iron Spur could be

1:12:23up to 25 times worse if they have 200

1:12:25generators.

1:12:27So, who can be trusted? We've shown that

1:12:30the project management team cannot be

1:12:32trusted. The future owner operator is to

1:12:35afraid to even show up because of

1:12:37opposition is what we've been told. Much

1:12:39of the AI and data center industry hides

1:12:42behind NDAs, shell companies, circular

1:12:45financing.

1:12:47The one entity that Forsyth County knows

1:12:49well

1:12:50that the is the Forsyth Planning Board.

1:12:54The staff, as Chris Murphy said, has

1:12:55done the due diligence over several

1:12:57months. They've openly presented a sound

1:12:59case as to why this rezoning application

1:13:03should be denied.

1:13:06We ask that you trust not a couple of

1:13:08strangers from out of town or an unknown

1:13:10future operator,

1:13:12but put your trust in Forsyth County's

1:13:14well-thought-out plans, planning staff,

1:13:17officials, and the majority of Rural

1:13:19Hall residents.

1:13:23Thank you.

1:13:35>> I am Carol Newsom, 8495 Broad Street. At

1:13:40the March 30th meeting, the project

1:13:42manager presented the potential tax

1:13:44revenue for the county to be between 30

1:13:46and 60 million annually. By the time it

1:13:49got before the Planning Board, that was

1:13:51down to approximately 7.6 million

1:13:55annually.

1:13:56The construction could take up to 4

1:13:58years, and on top of that, it requires

1:14:01another year between the rezoning of

1:14:03being allowed, permitting, and

1:14:05entitlements.

1:14:06Up to 5 years of construction disruption

1:14:09with no large tax revenue.

1:14:11The data center, once operational, will

1:14:13not require many employees, not a large

1:14:16boost in our job market, not a lot to

1:14:19support our communities.

1:14:21The potential tax revenue could be a

1:14:23large sum, and we do need to weigh the

1:14:25benefits against the impacts and the

1:14:27potential risk. And as my community

1:14:29members have already pointed out, we

1:14:32could be betting on a bubble.

1:14:35The true benefit remains a projection

1:14:37rather than a guarantee.

1:14:39What is a guarantee, what is a proven

1:14:41and remains consistent, is that

1:14:44residential and local businesses can

1:14:46reliably provide the tax revenue

1:14:48required for the services that our

1:14:50communities need and want. As

1:14:53represented in Forward 2045 in the Rural

1:14:55Hall Area Plan, a mixed-use

1:14:58development would align with the current

1:15:01character of our small residential town

1:15:03and would allow for the controlled and

1:15:04consistent growth that our community can

1:15:07support without the tremendous impact

1:15:10that a data center would impose.

1:15:12To allow this property to be rezoned to

1:15:14allow for a data

1:15:15data center to go goes against the

1:15:17recommendations in Forward 2045, the

1:15:19Rural Hall Area Plan. It would go

1:15:21against the recommendations the Planning

1:15:23Department and the City County Planning

1:15:25Board voted. And we ask you to recommend

1:15:28them. Project Iron Spur would be

1:15:29inappropriate, non-residential

1:15:32development that would have a

1:15:33significant impact on my community.

1:15:37What the this consideration in this

1:15:39moment represents is American democracy

1:15:42doing exactly what it is supposed to do.

1:15:44Voters deciding what happens in our

1:15:47communities and our elected

1:15:48representatives being asked to be

1:15:50responsive and requiring companies,

1:15:54developers to be held accountable.

1:15:56Please vote denial for the rezoning and

1:15:58allow Rural Hall to grow as we have

1:16:00decided is appropriate for our community

1:16:03and require the developers to do their

1:16:05due diligence and to find a suitable

1:16:07location in Forsyth County to be a good

1:16:10neighbor. Thank you.

1:16:19>> Good afternoon. My name is Ulrike

1:16:21Viethaus.

1:16:22I live on 70

1:16:24794 Academy Street in Rural Hall. And

1:16:27before I begin, I ask that everybody

1:16:29please stand who is against the data

1:16:32center.

1:16:35Thank you.

1:16:37My family and I have lived in Rural Hall

1:16:40for over 30 years. Our home is located

1:16:431.2 miles from the proposed hyperscale

1:16:46data center. North Carolina House Bill

1:16:491189 considers 3 miles as a safe

1:16:53distance from a hyperscale data center

1:16:56due to various kinds of data center

1:16:59pollution which are generated 24/7

1:17:03365

1:17:05days.

1:17:07In my remarks, I first of all I want to

1:17:08thank all of you for your careful

1:17:11consideration

1:17:12of a historically significant decision

1:17:15you are making very shortly. Case F-1669

1:17:19zoning application LIS Services A and

1:17:24for extending our speaking time to 30

1:17:27minutes.

1:17:28I also want to thank the planning board

1:17:30once again for their thoughtful analysis

1:17:33and for upholding the zoning

1:17:35classifications

1:17:37that will be at the center of your vote

1:17:39today.

1:17:41I ask you, the Board of Commissioners,

1:17:43to align your vote with the Planning

1:17:46Board's analysis and conclusion as

1:17:48submitted for today's agenda to

1:17:51recommend rejection of the proposed

1:17:53zoning for two very simple reasons. One

1:17:57specific to our town and the other

1:18:00affecting all of Forsyth County.

1:18:03The reason number one regarding our town

1:18:06is by now fairly obvious, I think. As

1:18:08has been pointed out by the Planning

1:18:10Board and my colleagues, due to its

1:18:13massive industrial scale, the intensity

1:18:16of operations, the extractive nature,

1:18:20the several potentially life-threatening

1:18:23types of pollution, especially noise,

1:18:26air, and the dual fire hazard,

1:18:28um and the site's location in the heart

1:18:32of our town, zoned RS-20,

1:18:36a hyperscale center in the Forsyth

1:18:39County jurisdiction is clearly not

1:18:42permissible.

1:18:44Now to my second reason. I'm very brief.

1:18:47And this affects all of Forsyth County,

1:18:50including our small town of Rural Hall.

1:18:53Computer data centers have been in

1:18:55existence since the 1940s.

1:18:59Forsyth County's definition of a

1:19:01computer data center reflects earlier

1:19:04types of such centers.

1:19:07They have been classified as business

1:19:09services A operations. These operations

1:19:13are characterized by their small size,

1:19:16their minimum power demand, water

1:19:19consumption, noise, etc.

1:19:21Furthermore, business services A

1:19:25entities operate without internal

1:19:28external structures.

1:19:30>> Can I interrupt you? We're getting to

1:19:32your 3 minutes. If you can wrap it

1:19:34>> by now be self-evident.

1:19:36Thank you, Chairman Martin, that the

1:19:37proposed uh zoning classification is

1:19:40inaccurate, insufficient, and simply

1:19:44false. And in closing, if the proposed

1:19:47project should be approved by you under

1:19:49this misleading zoning rubric, the

1:19:52consequences for all of Forsyth County

1:19:55will be dire for the simple reason that

1:19:58it offers an entirely unregulated and

1:20:01thus immensely harmful invitation to all

1:20:05future hyperscale data center zoning

1:20:09applications. Please vote in alignment

1:20:12with the planning board, and thank you

1:20:14for listening to us.

1:20:22>> Good evening.

1:20:23My name is Charles Session. I live at

1:20:25582 Dock Ridge Road, Rural Hall, North

1:20:28Carolina.

1:20:29Um as with most things in real estate,

1:20:33it's about location, location, location.

1:20:38The scale and scope of such a data

1:20:40center

1:20:41right there

1:20:44across the street

1:20:46from town hall

1:20:48is unconscionable.

1:20:5184 ft, that's like taking

1:20:54the Phillips building

1:20:56and I'm showing my age because I know

1:20:58it's not called that any longer, but

1:21:00taking the Phillips building

1:21:03and putting it in my backyard.

1:21:06It doesn't work.

1:21:09I am not anti-data center,

1:21:12but what I am anti is placement.

1:21:16It doesn't fit.

1:21:18We have zoning laws and regulations for

1:21:22a reason.

1:21:24And the reason, as you have all stated,

1:21:27there's a a an appropriate place for an

1:21:31appropriate business.

1:21:33This is not the place for that.

1:21:36So I ask you

1:21:39not to decide whether a data center is

1:21:41good or bad,

1:21:42but please,

1:21:44location,

1:21:46location,

1:21:48location.

1:21:50The zoning law says we can have all

1:21:54types of mixed businesses

1:21:57in that location,

1:22:00but the data center does not fit.

1:22:03And if it does not fit,

1:22:06then please, don't permit. Thank you.

1:22:22>> My name is Jonathan Kisslingbury. I live

1:22:23at 770 Serena Drive, Ru Hall,

1:22:26and I am an adjacent property owner.

1:22:29This will be on my property line.

1:22:32Um I spoke to you before, voiced my

1:22:34concerns. This is a zoning issue,

1:22:36period. Right? Forward 2045.

1:22:40It's so important that was created a

1:22:43year and a half ago. If we deviate from

1:22:46that plan right now,

1:22:48anything forward, it means nothing, you

1:22:51know? You We It just doesn't mean

1:22:53anything.

1:22:54Um it's important that we follow the

1:22:55plan.

1:22:57Um this encroaches on on residential

1:22:59area.

1:23:00Let's face it. It's limited industrial.

1:23:03This is pretty industrial.

1:23:05I'm not opposed to data centers at all.

1:23:07I use technology. However, it needs to

1:23:10be placed in an area for industrial.

1:23:13It's that It's that simple.

1:23:15This is around a residential area

1:23:18in a town.

1:23:19You know, an educator spoke and I really

1:23:22appreciate educators.

1:23:24And

1:23:25here's the problem with that. You put a

1:23:26data center there,

1:23:28there's no growth for Ruha.

1:23:30That area

1:23:31and everybody talks about the starter

1:23:33homes.

1:23:34People can't afford homes nowadays. And

1:23:36if starter homes start small families, I

1:23:39had a starter home when I was a kid.

1:23:42Right?

1:23:44If we

1:23:45get rid of that land and we don't have

1:23:48any homes

1:23:49and

1:23:51in Ruha, the the schools,

1:23:53we're losing attendance. And when you do

1:23:55that, there's it's going to go away.

1:23:57There's not going to be any children in

1:23:59Ruha. There's no room.

1:24:01And I really want you to take that in

1:24:02consideration.

1:24:05Um I'm I'm opposed to that. This group

1:24:08has worked so hard and I appreciate what

1:24:11they have done.

1:24:13And

1:24:14there's a lot of people that are against

1:24:16this.

1:24:19Just please uh

1:24:20I Please vote no uh on this re- re- uh

1:24:23uh

1:24:24rezoning because it would look very

1:24:26suspicious. You know, it's almost this

1:24:28big project in middle of this area.

1:24:31Some might want think that could be spot

1:24:33zoning is concerned. I just think that

1:24:36for Rural Hall residents,

1:24:39we deserve better than that. I

1:24:41appreciate it. Thank you very much.

1:24:47>> We'll say we have 7 minutes and 12

1:24:49seconds left. So, we've got

1:24:52probably time for two and maybe a a

1:24:54third person start.

1:24:55>> Good evening. My name is Scott Boat. I

1:24:56live at 8580 Circle Drive and I'm

1:24:59neighbors with with John and some of the

1:25:01other people. Um

1:25:03I just wanted to come up here so that

1:25:04you see that there's other people in

1:25:05this room besides John that are going to

1:25:07be affected by this.

1:25:10People with homes and I'm one of them

1:25:11within the 500 ft. Like John, I'm not

1:25:14against data centers, but not in my

1:25:15backyard. I believe I

1:25:17deserve a little bit of peace.

1:25:20That's all I want to say. Thank you.

1:25:33>> Hello. Um

1:25:35A man in Virginia described living next

1:25:37to a data center like living inside of a

1:25:38prison. Noise and light and heat you

1:25:41can't escape and a well you can no

1:25:42longer drink out of. That's what these

1:25:44developers who repeatedly claim to be

1:25:47good neighbors are proposing. Locking

1:25:49this community in a prison cell and

1:25:50expecting us to applaud them for

1:25:52rearranging the furniture or adding a

1:25:54pretty wrought iron fence. These meager

1:25:57plan adjustments are a slap in the face.

1:25:59And that $1 million community fund is a

1:26:01pathetic excuse for generosity. Real

1:26:04estate consumer notices show that home

1:26:06values near data centers can plummet and

1:26:08lose up to 20% of their value. That's

1:26:10about $55,000 in stolen equity of the

1:26:13average homeowner in Rural Hall. That

1:26:15wouldn't even cover 18 homes.

1:26:18That fund is supposed to make the

1:26:19developers look compassionate and the

1:26:20decision-makers sleep a little better at

1:26:22night. But who will not sleep better at

1:26:24night? The people who have to live

1:26:26there.

1:26:27It doesn't matter how many times

1:26:28[clears throat] those men repeat, they

1:26:29are not good neighbors. Good neighbors

1:26:32don't put 200 diesel generators near

1:26:34schools. Good neighbors don't increase

1:26:35the risk of asthma, heart attack, or

1:26:37premature death for our families. Good

1:26:39neighbors don't guzzle millions of

1:26:40gallons of water from a community that

1:26:42is currently boiling their drinking

1:26:43water. And good neighbors don't let

1:26:45their friends poison us.

1:26:47Do you know who makes the most forever

1:26:48chemicals that are used in the cooling

1:26:50systems in data centers? It's Chemours,

1:26:53the company that poisoned 7,000 wells in

1:26:56North Carolina with PFAS. There is no

1:26:58amount of forever chemical exposure that

1:27:00is safe. It causes cancer. And Forsyth

1:27:02County treatment facilities do not

1:27:04filter out forever chemicals. So you're

1:27:06asking us to take on higher risks of

1:27:07cancer without having a solution that we

1:27:09could possibly afford. In Fayetteville,

1:27:11North Carolina, the government is paying

1:27:12$134 million to filter out forever

1:27:15chemicals from their drinking water.

1:27:17But it's not just that we have to worry

1:27:18about. And NBC News said 97% of wells

1:27:22tested near a Oregon data center had

1:27:23nitrate levels that violated the federal

1:27:25safety threshold. Of the first 30 homes

1:27:27officials visited, they described at

1:27:29least 25 miscarriages and six people who

1:27:31had their kidneys removed. So this begs

1:27:34many questions. How much poison do you

1:27:36expect to us to put up with so they can

1:27:38put up record profits? How much risk do

1:27:41you have do the people have to bear so

1:27:43rich men can reap rewards? How many bee

1:27:45colonies have to disappear? How many

1:27:46calves must be born stillborn? How many

1:27:48babies miscarried? How many riverbeds

1:27:50must run dry? And how many organs need

1:27:52to be carved from the flesh of our

1:27:54neighbors so rich men can carve out a

1:27:56little more profit? They are not good

1:27:58neighbors and voting for this rezoning

1:28:00project would mean you aren't either.

1:28:08>> Good afternoon. I live at 520 Helton

1:28:10Lane in Royal Hall. Been living there

1:28:12for 27 years.

1:28:14I don't want this data center there

1:28:15because for one, I'm stage three kidney

1:28:18failure and I don't need that. We don't

1:28:20need the air quality for these kids. I

1:28:23understand they want it there. We don't

1:28:24need it. Like they said, it's a it's too

1:28:26much danger

1:28:28for the community.

1:28:30I'm speaking for the town of Rural Hall.

1:28:32I'm not speaking what the mayor spoke

1:28:34cuz he don't know what he talking about.

1:28:36We don't need that in Rural Hall. He

1:28:38can't speak for everybody.

1:28:40I stay two football fields away from

1:28:43that property. And I don't want it

1:28:45there. I got grandkids that come and

1:28:47play. We got kids that play in the

1:28:49neighborhood. They don't need it.

1:28:52We got to think about everybody else's

1:28:54health. I understand they want to sell

1:28:56their land. That's money for them. But

1:28:58think about other people's health.

1:29:00We don't need the data center out there.

1:29:04Please do not vote for that out there.

1:29:07If you live by If you live by a data

1:29:10center, you'll hear the noise. You'll

1:29:12hear the security every week. We don't

1:29:14need that.

1:29:16We don't need it at all. Can y'all

1:29:18please do not let the data center come

1:29:20out there. That's why I made this shirt,

1:29:22no data center, not in our backyard.

1:29:33>> Dr. Martin, county commissioners,

1:29:36uh the current development plans as a as

1:29:39they are in the books now were developed

1:29:41with significant community input and

1:29:43represent the wishes of the impacted

1:29:45residents as codified by you in those

1:29:47official planning documents. Please

1:29:49stand by this work and Rural Hall's

1:29:52residents' wishes for their community.

1:29:55Even with the site modifications that

1:29:58the developers have proposed,

1:30:00Chris Murphy,

1:30:01the director of city-county planning

1:30:03staff, stated in in the briefing session

1:30:06that the scale and the intensity of the

1:30:08proposed use, we still believe could

1:30:10result in significant off-site impacts

1:30:12to nearby residents despite the

1:30:14conditions. Please vote to keep rural

1:30:17hall rural.

1:30:18In addition, I would ask that you

1:30:20consider a time-limited moratorium so

1:30:23that our current UDOs can be updated to

1:30:25address modern-day hyperscale data

1:30:28centers. Currently, the city-county

1:30:30planning board and staff are having to

1:30:31rely on written references to the

1:30:34inclusion of the term computer data

1:30:36center

1:30:37as an example of limited industrial

1:30:39services A business.

1:30:42This is clearly an inappropriate

1:30:43classification for modern HDCs given

1:30:46their significant impacts on neighboring

1:30:47residential and mixed-use neighborhoods.

1:30:50As County Attorney Gordon Watkins stated

1:30:52in the July 9th briefing,

1:30:55the definition of computer data center

1:30:57in our current

1:30:59UDOs, quote, "That definition was

1:31:02written many years ago and it may not

1:31:04have anticipated these huge huge data

1:31:07centers."

1:31:08A moratorium would allow for more

1:31:09careful study and consideration of

1:31:11lessons learned by other communities

1:31:13like Loudoun County, Virginia that have

1:31:15experienced negative impacts from the

1:31:17construction and operation of HDCs. A

1:31:20vote for rezoning for the hyperscale

1:31:22data center now would be premature. We

1:31:25really need time for further study and

1:31:27sensible modifications to our county's

1:31:29zoning ordinances to address these new

1:31:32types of operations.

1:31:34Thank you for your consideration.

1:31:40>> Hello, my name is Dale Morales. I would

1:31:42like to draw attention to the data

1:31:43center they damaged caused by data

1:31:45centers regarding infrasound, also known

1:31:48as DBC,

1:31:49in the surrounding area. I feel I can

1:31:51speak to this specific attribute given

1:31:53my experience in acoustics and audio

1:31:54engineering.

1:31:55I'll leave the environmental effects to

1:31:57someone more suited. Infrasonic

1:31:58frequencies are vibrations below the

1:32:01audible human perception.

1:32:03However, just because you cannot audibly

1:32:05hear a sound does not mean it cannot

1:32:07affect or harm you. We understand the

1:32:09ultrasonic frequencies of a dog whistle

1:32:12can be annoying even if you can't hear

1:32:14it. Prolonged exposure to infrasonic

1:32:16frequencies caused by data centers, by

1:32:18their cooling systems, and by

1:32:21can cause a myriad of negative health

1:32:23effects such as not limited to

1:32:25headaches, migraines, brain fog,

1:32:27irritability, dizziness, loss of

1:32:29balance, panic disorders, sleep

1:32:30disruption, heart palpitations, and even

1:32:33in some case seizures.

1:32:35Though invisible, these effects cannot

1:32:36be ignored.

1:32:37>> Let me Let me interrupt you for a

1:32:38second.

1:32:39>> Our time's up, but if you can kind of

1:32:40finish up in a

1:32:41>> I'm I'm last

1:32:41>> Finish up in about 30 seconds.

1:32:43>> Yeah, absolutely.

1:32:44Uh though invisible, these effects

1:32:45cannot be ignored.

1:32:47Uh this is not just a case of getting

1:32:48used to it. Proximity to constant

1:32:51infrasound is untenable. Thank you.

1:32:55>> All right.

1:32:58Thank you all for a a minute's worth.

1:33:00We're We have reached our our timeline.

1:33:03So, sorry. Thank you.

1:33:05Um So, I would declare the public

1:33:08hearing closed. All right.

1:33:11Um

1:33:12Actually, I want to make a couple of

1:33:13comments before we get to a motion part.

1:33:17Um before before making a motion, I do

1:33:19want to thank all of you who sent

1:33:22emails, texts, left voicemails during

1:33:25the lengthy discussion about this

1:33:26rezoning request. In fact, YouTube's,

1:33:29you name it. Been a lot of great

1:33:31presentations.

1:33:32All of you expressed your personal

1:33:34beliefs about data centers and how the

1:33:37data center would impact you.

1:33:39And many of you sent links, reports,

1:33:41YouTube videos, and presentations that

1:33:44provided a lot of information about the

1:33:45more technical aspects of cooling

1:33:47systems, compressors, generators, etc.

1:33:52On behalf of the entire commission,

1:33:54we want to thank you for remaining

1:33:56engaged and doing your homework. And in

1:33:59my opinion, this is the way local

1:34:01government should work. It's been a lot

1:34:03of healthy debate that's been going on

1:34:04for basically 6 months, but the last 3

1:34:07months has been more intense.

1:34:10Um I'd also like to just offer some

1:34:12context for this issue.

1:34:14Um the 2045 growth plan is a broad

1:34:18roadmap for land use in Forsyth County,

1:34:21and quite frankly, for the next

1:34:2438 years. I guess what we've got We've

1:34:25got 30 to 40 15 18 year 18 years.

1:34:29The Rural Hall area plan provides

1:34:32recommendations for land use around the

1:34:34town of Rural Hall.

1:34:36The current Rural Hall plan area plan is

1:34:3911 years old.

1:34:42North Carolina statutes allow citizens

1:34:44to file rezoning petitions that request

1:34:47specific changes from existing zoning

1:34:51plans.

1:34:52The county commissioners are charged

1:34:54with the final decision on whether a

1:34:56particular specific zoning change is

1:35:00made.

1:35:01I have voted against zoning changes that

1:35:04were approved by the planning board

1:35:07because I thought that the resulting,

1:35:08particularly traffic, would adversely

1:35:11affect the current conditions in those

1:35:13neighborhoods.

1:35:14I have voted for requests that the

1:35:16planning board did not approve because

1:35:19there were similar uses nearby, and I

1:35:21believe that the use would be

1:35:23compatible.

1:35:25The data center request is complicated

1:35:27for many reasons.

1:35:29Not least of which is the frenzy

1:35:31surrounding AI in America today.

1:35:35Clearly, jobs are being replaced by what

1:35:38AI can do, and many American workers are

1:35:42rightly fearful.

1:35:44Since data centers house the servers

1:35:46that allow AI to be used, that

1:35:49opposition has carried forward to a

1:35:51dislike of data centers.

1:35:53Over 70% of the US population recently

1:35:58surveyed is against data centers.

1:36:02Another issue is that the early

1:36:04large-scale data centers, we've talked

1:36:07we heard some testimony tonight or

1:36:09comments tonight about the very small

1:36:11ones back in the 30 20 and 30 years ago,

1:36:14but the large ones, they have been noisy

1:36:17and use a lot of water and power. That

1:36:19information was shared particularly by

1:36:22the uh

1:36:23um the city manager in Maiden North

1:36:25Carolina that talked about their first

1:36:27generation their first equipment was

1:36:29actually very different than the

1:36:30equipment that they have now.

1:36:33Many people complained and one can find

1:36:35examples of many bad situations posted

1:36:39on the internet

1:36:41everywhere.

1:36:42It is probably fair to say that we're in

1:36:44the second and third generations of the

1:36:46large data centers.

1:36:49Closed-loop water systems do reduce the

1:36:51demand for water and power companies

1:36:54have adjusted their rate structures and

1:36:57pre-treatment is now required before

1:36:59connecting to a public sewer.

1:37:02Duke Energy has shared with us that a

1:37:03recent study of the impact of large

1:37:06power users on residential rates and

1:37:08found that residential rates will be

1:37:10about $4 a month less for electricity

1:37:14for an extended period.

1:37:16New data centers

1:37:18are less noisy as we've heard some of

1:37:20that testimony and the generators are

1:37:22limited to 100 hours of operation a

1:37:25year.

1:37:27And the final context I want to mention

1:37:29is that the proposed data center site

1:37:31will not remain as it is.

1:37:35The land has been in the owner's family

1:37:37for over 100 years

1:37:40and now they want to sell it and I

1:37:42understand that.

1:37:44So, this farm will become something else

1:37:47if not developed into a data center.

1:37:50Personally, I think it is likely that a

1:37:53large subdivision will be built, which

1:37:56will not require a zoning change.

1:37:59That large subdivision will produce a

1:38:01lot of traffic and and and noise to

1:38:04boot. And since it is unlikely to be in

1:38:07the Rural Hall town limits, the town

1:38:09will not receive any tax benefit from

1:38:12this development.

1:38:14The chair of the planning board made

1:38:16this comment at the end of their meeting

1:38:18back in June.

1:38:20Sometimes you have to be careful what

1:38:22you ask for.

1:38:24Speaking of Rural Hall,

1:38:26there are signs around the town

1:38:28suggesting that the mayor should be

1:38:30impeached. Mayor's here tonight.

1:38:32The recent decision by the town council

1:38:35to support the data center request, if

1:38:37the land were annexed into the town

1:38:39limits, was simply not a popular

1:38:42political decision. And the mayor and

1:38:44some of the council members in Rural

1:38:45Hall are up for re-election this

1:38:48November.

1:38:49It appears to me that the council was

1:38:51looking out for the long-term interest

1:38:53of Rural Hall.

1:38:55Significant tax revenue and a new park,

1:38:57if the commissioners if the

1:38:59commissioners approve the rezoning.

1:39:02That decision was simply doing what they

1:39:04were elected to do. If some change did

1:39:06occur,

1:39:07then how can Rural Hall best benefit?

1:39:11And I do want you to know that our

1:39:12attorney prepares

1:39:14two motions before every rezoning case

1:39:18to make sure they're all in compliance.

1:39:20One to approve and one to oppose. So,

1:39:24when it sounds like legalese, it is.

1:39:27Um but it was actually prepared

1:39:29beforehand and we have one of each.

1:39:32So, I'd like to make this motion. I'd

1:39:34like to move that the zoning map

1:39:36amendment F-1669

1:39:39and the alternate site plan and special

1:39:41use district permit be approved on the

1:39:44basis of the following.

1:39:46The proposed special use zoning map

1:39:48amendment as petitioned by Julia Wall,

1:39:50Wall Family of North Carolina

1:39:52LLC, Jennifer Jobe, James Martin Serber

1:39:56Jr. and James Martin Serber III to

1:39:59rezone 128.54 acre piece of property

1:40:01from RS 20 residential building single

1:40:04family 20,000 square foot minimum lots

1:40:07and GI general industrial to LI S

1:40:10limited industrial special use with uses

1:40:13of agricultural production crops,

1:40:15agricultural production livestock

1:40:17offices, parking, commercial recreation

1:40:20facility, public testing and research

1:40:21lab transmission tower services A and

1:40:24utilities

1:40:26is consistent with the recommendations

1:40:28of the Forward 2045 Comprehensive Plan

1:40:30and is reasonable in the public interest

1:40:32because

1:40:34one, the subject property consisting of

1:40:36open fields, four single houses, single

1:40:39family houses, and several accessory

1:40:41buildings is located on the northwestern

1:40:44side of Athena Rural Hall Road north of

1:40:47the Buckatabon Road and at the terminus

1:40:49of Glade Street and is adjacent to

1:40:51properties owned GI, LB, RS 20 and RS 9

1:40:56with adjacent and nearby uses of a Duke

1:40:58Energy substation, various industrial

1:41:01uses, a church, cemetery, convenience

1:41:03store, restaurant, government office, a

1:41:06warehouse building, utilities, and

1:41:08single family houses.

1:41:10The proposed LIS zoning is primarily

1:41:12intended to accommodate limited

1:41:14manufacturing, wholesale and

1:41:16warehousing, research, and industrial

1:41:18development which in their normal

1:41:19operations have little or no adverse

1:41:22effect upon adjoining properties in

1:41:24growth management areas 1, 2, 3, and 4

1:41:27and metro activity centers.

1:41:30Three, the proposed site plan features

1:41:31three two-story buildings totaling 1.1

1:41:35million square feet of interior space,

1:41:37housing data centers, associated

1:41:39parking, and stormwater ponds and

1:41:41parkland.

1:41:42The site is located in growth management

1:41:44area three, adjacent to the Rural Hall

1:41:46downtown activity center, and has access

1:41:48to public water and sewer.

1:41:51And five, the proposed use is consistent

1:41:54with Forward 2045 comprehensive

1:41:56comprehensive plan, which recommends

1:41:59industrial uses adjacent to other

1:42:01industrial and utility uses, and the

1:42:04site plan has designed buffers to

1:42:06protect single-family houses. And

1:42:09although it doesn't provide housing as

1:42:11as is typical of mixed-use development

1:42:14recommended by the Rural Hall area plan

1:42:16development, it does provide a park.

1:42:20Is there a second to that motion?

1:42:22>> I will second that motion.

1:42:24>> Have a second by uh Commissioner

1:42:25Wizzinard. Now discussion.

1:42:27>> I'd like to speak in opposition to the

1:42:29motion that is on the floor and note

1:42:31that if this motion fails, I will make

1:42:33the motion to deny

1:42:35uh the requested petition.

1:42:38First, I want to

1:42:40note that this is a vote on a rezoning

1:42:44proposal. It is not a referendum on data

1:42:47centers.

1:42:49As such, that should not be the issue

1:42:51here. The issue should be whether this

1:42:53is consistent with our plans

1:42:56uh and I would say with the um

1:43:00the wishes of the impacted directly

1:43:02community

1:43:04uh and whether

1:43:05uh

1:43:07there is any reason to overturn that.

1:43:11I'd like to note that in addition to the

1:43:13disparity that we saw in the room here

1:43:16today

1:43:17uh in public support

1:43:19um which by the way goes to the question

1:43:22of whether the

1:43:24Rural Hall area plan adopted in 2016 is

1:43:28still relevant today.

1:43:30Um

1:43:32the support that we have um

1:43:34heard in messages for several months now

1:43:37uh is overwhelmingly in opposition to

1:43:41the proposed rezoning.

1:43:43At the

1:43:44uh time of the June 11 hearing before

1:43:48the planning board, which voted 7 to 2

1:43:50to

1:43:51uh deny the proposal,

1:43:53uh they had in their record

1:43:57um 63

1:43:59public comments with regard to the

1:44:01proposal.

1:44:03Of those 63,

1:44:0560 were in opposition. And of those 60,

1:44:10at least 38 were residents of Rural

1:44:14Hall.

1:44:16Since that time

1:44:17uh

1:44:19and in fact beginning I was able to go

1:44:21back to my records from early May.

1:44:25Uh we have received in

1:44:28uh ex- well, we have received almost 400

1:44:32uh

1:44:33unique individual comments. That is not

1:44:35duplicate comments, not any of the

1:44:38repeat commenters, but

1:44:41um

1:44:42in excess of 400 individuals or

1:44:44households commenting.

1:44:46Of those

1:44:48376

1:44:51were in opposition.

1:44:53Only 33 total during that time were in

1:44:56support. It is clear that the community

1:45:00of Rural Hall and nearby considers the

1:45:04Rural Hall area plan adopted in 2016 to

1:45:08be their current preference.

1:45:11We have also received specific comments

1:45:16uh during that time that I think are

1:45:19worthy of note because they describe

1:45:22situations from people who would be

1:45:24directly impacted here.

1:45:26Uh we have uh, a

1:45:30a message that we received in early June

1:45:34uh, from a lady with speaking with

1:45:37regard to her father who has lived at

1:45:408010 Glade Street for the better part of

1:45:4340 years. He is a Vietnam veteran uh,

1:45:47and she is asking on his behalf that we

1:45:50not uh, put a massive new industrial

1:45:53structure immediately behind his home.

1:45:57Um,

1:45:58we received another uh, message from a

1:46:01resident of Tobaccoville Road uh, who

1:46:04noted that her parents built there in

1:46:061961

1:46:08and in her words, my mother of 91 my

1:46:11mother at 91 years old does not deserve

1:46:14her last years living in these

1:46:16circumstances of a massive new

1:46:18industrial facility in her backyard.

1:46:22Uh, we have uh,

1:46:24a a letter an email

1:46:27from a younger lady who is writing on

1:46:29her behalf and on behalf of her parents

1:46:32uh, who she says have been residents of

1:46:33Forsyth County for 30 years. My family

1:46:36moved to a voluntary agricultural

1:46:38district in rural Hall in 2014 because

1:46:42we wanted space to grow fruits and

1:46:44vegetables, raise animals, and keep

1:46:46bees. We've been operating

1:46:49Sassafras Family Farm for more than a

1:46:51decade.

1:46:53Uh, and they are troubled by the

1:46:55location of this data center and the

1:46:57potential effects of its noise and

1:46:59vibration on their operations including

1:47:02their bees. We had an

1:47:04an email from another beekeeper who

1:47:06lives uh, in property adjacent to the

1:47:09site concerned about that. Um,

1:47:12it seems clear that uh, the community

1:47:15that would be directly impacted

1:47:16overwhelmingly opposes uh, this petition

1:47:20for rezoning.

1:47:22>> Other discussion?

1:47:24>> Yes, I'd like to um ditto all of the uh

1:47:28comments that Commissioner Bessie has

1:47:31made as well. I will be voting in

1:47:33opposition to this as well today. I've

1:47:35sat with this community through several

1:47:38meetings um relative to the pros and the

1:47:42cons. And I'm not saying that I'm

1:47:44against data centers, but I'm against

1:47:47data centers in Rural Hall.

1:47:50With that being said, I wanted to say

1:47:51thank you to the staff for the report

1:47:54regarding the negative aspects of the

1:47:56proposal. And I want to also thank this

1:48:00community for staying informed and

1:48:02engaged um relative to this matter. So,

1:48:05thank you. I'll keep it short and sweet.

1:48:08>> Other comments?

1:48:09>> Yes, thank you, Mr. Chairman. Um I'm

1:48:11still the newest member of this

1:48:14commission, and I have not seen a zoning

1:48:16petition up to this point that carries

1:48:19the magnitude of this matter.

1:48:22Um I have been disappointed on occasions

1:48:24with some of the hysteria and some of

1:48:26the questionable scientific information

1:48:29uh about this, but I I'll tell you I'm

1:48:31impressed um and one I think it was the

1:48:33lady here. Someone made a comment about

1:48:36how democracy should function, and I'm

1:48:38very

1:48:39impressed by the outpouring of sentiment

1:48:42that has come from this community.

1:48:44Uh and and we've also received some

1:48:46wonderful scholarly uh information uh

1:48:50treatises on all sorts of things uh

1:48:54alternatives. They We've got a whole

1:48:56section here about where you can put a

1:48:58data center in

1:48:59Forsyth County. And I heard a number of

1:49:01you say you weren't against data centers

1:49:03per se. Uh and I I hope I'll find out

1:49:06that that's correct at a later date. Um

1:49:10you know, I've heard negative comments

1:49:11about the developer, about the mayor and

1:49:14his staff. Demonizing them is, in my

1:49:16opinion, totally inappropriate. We've

1:49:18met with the developers. Uh they've been

1:49:20very candid in their discussions

1:49:23uh with us. I respect them. I wish they

1:49:25had an end user at this point. I went

1:49:28with the chairman down to Maiden and we

1:49:30looked at the data center there and the

1:49:32town of Maiden, you know, was just

1:49:34flushed with cash and they don't have

1:49:36any complaints about it, but that data

1:49:37center is not in the town. So, you know,

1:49:41if we get to a question about whether or

1:49:44not it would be a problem in this

1:49:46location. I believe that based on the

1:49:49science that I've read that the water,

1:49:51the noise,

1:49:52uh the power issues, the aesthetics, I

1:49:54believe all of those could be properly

1:49:57addressed.

1:49:59But, you know,

1:50:01we've had so much fun reading over 400

1:50:03emails and commissioners actually do

1:50:05that uh cuz that's what we're supposed

1:50:07to do and I appreciate that very much,

1:50:10but um

1:50:13the consistent theme that comes through

1:50:15there is with regard to the location as

1:50:17some of the other people

1:50:19have mentioned. Um

1:50:21Uh I I know it's not consistent with the

1:50:234045 plan. I'm impressed with the

1:50:26recommendations of the staff that serve

1:50:28this county so well in that regard. So,

1:50:32you know, get down to the consistent

1:50:34theme that I've seen that I think is

1:50:36genuine and sincere and that is

1:50:39the comments repeatedly that Rural Hall

1:50:43is a small, slow, sleepy town and we

1:50:47love it that way and that's the way that

1:50:50we want to keep it. And you know, we're

1:50:52not a Nancy state yet where we, you

1:50:55know, the socialist model in Europe

1:50:56works pretty well in that regard, but in

1:50:58America uh something like that doesn't

1:51:00really work. You know, I don't know that

1:51:02we make the decision that this is

1:51:05something that they ought to have when

1:51:06we just cram it down everybody's throat.

1:51:09Um and so

1:51:11I'm satisfied that there are other

1:51:13suitable locations in the county for a

1:51:17project like this and I just, you know,

1:51:20am concerned that uh

1:51:22it might be uh better to find one of

1:51:25those sites.

1:51:27>> Other discussion.

1:51:28>> Yeah.

1:51:29I would just like to say, oh, I'm sorry.

1:51:31I didn't mean Okay, I just wanted to say

1:51:33that I would not be in support of the

1:51:36current motion because

1:51:39um I am here to represent the citizens

1:51:42of Forsyth County

1:51:44um and you all have come out in such a

1:51:48an ideal democratic way. I think that

1:51:51your concerns are very

1:51:54um reasonable and aligned with national

1:51:57concerns about data centers. I um like

1:52:02others, I am not at this point anti-data

1:52:05centers. It's just that I don't know um

1:52:09about the ramifications of what will

1:52:11happen from a health perspective. Um it

1:52:14seems um that there is promise for great

1:52:18revenue and I will say Forsyth County is

1:52:21in need of some additional revenue, but

1:52:24not at the cost of the will of the

1:52:27citizens here of Forsyth County. So, the

1:52:31one thing that I would put on um

1:52:34consideration for Forsyth County is for

1:52:37us to

1:52:38continue to do more research and to

1:52:41redefine data center as um we know it

1:52:45now so that it is more appropriate to

1:52:47the times that we find ourselves. And

1:52:50that's going to be some work on the part

1:52:52of staff and this commission, but I

1:52:55think it would be well worth um the

1:52:58energy so that the developers who are

1:53:01coming into Forsyth County doesn't have

1:53:03to go through all of what they're

1:53:06they've probably have had to endure

1:53:08because we don't yet have maybe a an

1:53:12appropriate way to assess whether

1:53:14Forsyth County

1:53:16um what we desire as it relates to

1:53:19bringing data centers just not maybe

1:53:22publicly there yet. So, I would

1:53:25um you know, again just highly suggest

1:53:27to the county that we revisit what

1:53:30um we see ideally where data center

1:53:33should go in Forsyth County so that

1:53:35developers don't come and waste so much

1:53:37time, energy, and money

1:53:39um in trying to figure this piece out.

1:53:42So, um that's where I stand. Thank you.

1:53:45>> Any other comments?

1:53:46>> Just a few. Um I did second the motion

1:53:49because I agree with it. Um I know so

1:53:53many folks in Rural Hall because I grew

1:53:55up in that area. Um my family did our

1:53:58grocery shop in there.

1:54:00Did our bank in there.

1:54:02Uh I love Rural Hall. Always will.

1:54:05Uh

1:54:07I'm very disturbed by what has happened

1:54:10through all this. You have neighbors

1:54:13against neighbors, families against

1:54:15families. It is so heartbreaking to see

1:54:19what has happened in Rural Hall. And

1:54:22yes, we did receive huge amounts of

1:54:25emails. I will tell you

1:54:27several of the emails had no addresses.

1:54:31I don't know where they came from.

1:54:33Uh I figure you all did, but I don't. Uh

1:54:37I think it was an organized

1:54:39misinformation campaign.

1:54:42Um I hate that for Rural Hall because I

1:54:45know there are so many people who were

1:54:48in favor of this. Um

1:54:51I've been told if you came out um in

1:54:55favor of it, you got blown up on

1:54:56Facebook. God bless Facebook.

1:55:00Uh it is causing more trouble than it

1:55:02will ever be worth.

1:55:04Um,

1:55:05but please know

1:55:07we have spent huge amounts of time on

1:55:10this. It's not that we don't know about

1:55:13data centers.

1:55:15We've been to workshops, some of us

1:55:16have. Uh, some of us in February went to

1:55:20three workshops in Washington.

1:55:23Uh, we've talked with the folks in

1:55:24Loudoun County that have 300 data

1:55:27centers.

1:55:29Um,

1:55:30the the all the things that's been said

1:55:32about Loudoun, I didn't find that to be

1:55:35true in talking with the commissioners

1:55:38from Loudoun County.

1:55:40Uh, we've done the best we can to get

1:55:43all the information we need. Uh, I think

1:55:46that this,

1:55:47uh,

1:55:48would would be a great opportunity for

1:55:52Rural Hall. I admire the, uh, mayor and

1:55:55the city council for doing their job.

1:55:59And their job was to come to terms with

1:56:02what was best for Rural Hall.

1:56:04Financially, it it would be wonderful

1:56:08for Rural Hall.

1:56:09Uh,

1:56:10we all, and it would be great for

1:56:12Forsyth County. We all need to have

1:56:14methods of being able to finance the

1:56:17services that we're mandated to service

1:56:21and find ways to do it other than

1:56:23raising property tax. And that's what

1:56:26we're faced with all the time. So, I

1:56:29believe I'll always will believe that's

1:56:31reason I'll vote for it, that this was

1:56:34the best thing for Forsyth County. I'm

1:56:36sorry if you all do not agree. Um, but I

1:56:40I do my homework and I do believe that

1:56:43this is the best thing in the long run.

1:56:46I believe that these folks have every

1:56:50every right to sell their property. I

1:56:53don't think anybody should to

1:56:55to this family selling their property.

1:56:58And what I hear is that I love to ride

1:57:02by and see that farm.

1:57:05Well,

1:57:06that farm is costing them a bunch of

1:57:08money for them to be able to provide it

1:57:11for other people.

1:57:12Um

1:57:13I fear what's going to happen because

1:57:17they are going to sell.

1:57:19I fear that you're going to have about

1:57:20340

1:57:22small box houses to look at.

1:57:25>> [applause]

1:57:28>> I I don't think you'll be clapping. I

1:57:31really don't think you'll be clapping.

1:57:33Thank you.

1:57:35>> All right, we're ready to vote.

1:57:36All those in favor, please say I.

1:57:38>> I.

1:57:40>> Those opposed?

1:57:41>> No.

1:57:43>> Ocean Care is defeated.

1:57:46>> [applause]

1:57:53>> Mr. Chairman.

1:57:54>> Yes.

1:57:54>> Um I would like to make a motion.

1:57:57Uh I move the zoning map amendment

1:57:59F-1669

1:58:01including site plan and special use

1:58:03district permit be denied on the basis

1:58:06of the following.

1:58:08The proposed special use zoning map

1:58:09amendment as petitioned by Julio Wall,

1:58:12Wall Family of North Carolina LLC,

1:58:15Jennifer Job, James Martin Serber Jr.,

1:58:18and James Martin Serber III to rezone a

1:58:23128.54

1:58:25acre piece of property from RS-20

1:58:28residential building single family

1:58:3020,000 square foot minimum lots and GI

1:58:34general industrial to LIS

1:58:38limited industrial special use with uses

1:58:42of agricultural production, crops,

1:58:45agricultural production, livestock,

1:58:47offices, parking, commercial,

1:58:51uh recreation facility,

1:58:53public, testing research lab,

1:58:56transmission tower, services A, and

1:58:59utilities

1:59:00is neither consistent with the

1:59:02recommendations of the Forward 2045

1:59:05Comprehensive Plan, nor reasonable or in

1:59:08the public interest because, one, the

1:59:11subject property consisting of open

1:59:13fields, four single-family houses, and

1:59:16several accessory buildings is located

1:59:19on the northwestern side of Bethania

1:59:21Rural Hall Road, north of Tobaccoville

1:59:24Road, and at the terminus of Glade

1:59:26Street, and is adjacent to property

1:59:28zoned GI, LB RS120 and RS9, with

1:59:33adjacent and nearby uses of a Duke

1:59:35Energy substation, various industrial

1:59:38uses, a church, cemetery, convenience

1:59:41store, restaurant, government office

1:59:44a warehouse building, utilities, and

1:59:46single-family houses.

1:59:49Two, the proposed LIS zoning is

1:59:52primarily intended to accommodate

1:59:54limited manufacturing, wholesaling,

1:59:57warehousing, research, and industrial

1:59:59development, which, in their normal

2:00:01operations, have little or no adverse

2:00:04effect upon adjoining properties in

2:00:07growth management areas 1, 2, 3, and 4,

2:00:10and metro activity centers. Three, the

2:00:14proposed site plan features three

2:00:16two-story buildings totaling

2:00:201,122,300

2:00:23sq ft of interior space, housing data

2:00:26centers, associated parking, and

2:00:28stormwater plant ponds, and parkland.

2:00:32Four, the site is located in growth

2:00:34management area three, adjacent to the

2:00:37Rural Hall Downtown Activity Center, and

2:00:41has access to public water and sewer.

2:00:45Five, the size, scope, and hours of

2:00:47operation of the proposed facility and

2:00:49use are inconsistent with the LI zoning

2:00:53category.

2:00:54Six, the proposed use is inconsistent

2:00:58with the Ford 2045 comprehensive plan,

2:01:02which recommends industrial uses be a

2:01:05part of a designated business or

2:01:07industrial park, rather than adjacent to

2:01:10residential uses to minimize off-site

2:01:13impacts.

2:01:14And the site plan is inconsistent with

2:01:17the Rural Hall area plan update, which

2:01:19recommends mixed-use development,

2:01:22including residential uses, and

2:01:25recommends that neighborhoods be

2:01:26protected from inappropriate commercial

2:01:29and industrial encroachment.

2:01:32>> Sir, second.

2:01:33>> I'll be happy to second that.

2:01:35>> Seconded by Commissioner McDaniel. Any

2:01:36discussion?

2:01:38>> I'd like to make a comment.

2:01:40Given my particular situation,

2:01:42>> [clears throat]

2:01:45>> over the years, I've attempted

2:01:47particular zoning matters and other

2:01:49things, but zoning matters, too,

2:01:52uh

2:01:55let people

2:01:57know

2:01:59why I was doing or was going to do

2:02:02uh explanation for it. And so,

2:02:06>> [clears throat]

2:02:06>> over time, I come to the conclusion for

2:02:09me,

2:02:10I just as well hadn't said anything.

2:02:12It's And that's just [snorts] only for

2:02:15me.

2:02:16Others are better wordsmiths than I am.

2:02:22When I 17, 18 year Well, let me just say

2:02:25this next. The landowner

2:02:28has the right to sell their land.

2:02:31And the landowner has got a right to

2:02:34sell the land

2:02:36at

2:02:37a

2:02:39a higher value use

2:02:42>> [cough]

2:02:42>> than it is now.

2:02:45And

2:02:46it's likely

2:02:48that that may come about and that higher

2:02:50uses

2:02:52likely to be dense dwellings because

2:02:56it's uh

2:02:57sewer available.

2:02:59And so

2:03:02uh

2:03:03that may uh come and I wouldn't doubt

2:03:06that we would have opposition here if it

2:03:08does.

2:03:09And probably the main reason for it

2:03:12would be it because it would cause more

2:03:16traffic if it was there. So now I'm

2:03:19going to go back a little

2:03:20ways. [clears throat]

2:03:22When I was 17 18 years old,

2:03:25my mother and daddy both passed. And at

2:03:28that time 18 you wouldn't consider

2:03:30adult, it'd be 21.

2:03:33I couldn't sign any documents. So

2:03:37uh a

2:03:39real estate person came by

2:03:43just months after

2:03:45uh

2:03:46my daddy had passed and

2:03:50wondered if I'd be interested in selling

2:03:52the land.

2:03:54Well, I wasn't interested in it. I

2:03:56wasn't old enough anyway. I couldn't

2:03:58assign the papers.

2:04:00But

2:04:01what I had what I had there ended up

2:04:03with was

2:04:05that's how I thought I was going to

2:04:08end up surviving. I didn't have any idea

2:04:11about selling it. I was just going to

2:04:14survive. Try to. I didn't have anybody

2:04:17to

2:04:18uh

2:04:20help me. The only person that close to

2:04:22me was left was my

2:04:24grandmother and she was aged then not in

2:04:27uh

2:04:29good health.

2:04:32I learned many things out of that

2:04:33surviving. One of them was

2:04:37that I found out you could

2:04:40survive on little money in long time

2:04:43back.

2:04:44Uh

2:04:45I didn't

2:04:47just a little was it was little cuz I

2:04:50can remember remember that

2:04:52I know I did not have more than $100 in

2:04:55cash.

2:04:57And so

2:04:58as time went on

2:05:01money didn't bother me too bad cuz I

2:05:03thought I could get by with uh

2:05:05always get by with less than what I had.

2:05:08And so uh

2:05:11I'm still there at the farm.

2:05:14I've expanded the farm.

2:05:17And there was some near me about 5 years

2:05:19ago

2:05:21uh

2:05:22that was for sale.

2:05:24And for whatever the reason

2:05:26uh

2:05:27the person didn't contact at all of the

2:05:30There's three or four other neighbors,

2:05:32all of them but me.

2:05:34Didn't contact me.

2:05:36And I I couldn't figure that out then

2:05:38and I can't figure it out to this day. I

2:05:40quit trying to figure on it. The house

2:05:42is there now and

2:05:44uh

2:05:46they're not bothering me and I know that

2:05:47they don't like it when they get behind

2:05:49a tractor and it takes them extra few

2:05:51minutes to

2:05:53uh

2:05:53get home. So

2:05:57the man

2:06:01not sure what he was thinking. He did He

2:06:04was wondering whether there was anybody

2:06:06around it or two or three together that

2:06:09might put something together. Well, it

2:06:12wasn't a crowd that could have put

2:06:14something together if he'd allowed them

2:06:15to do it, but he didn't want whatever

2:06:17the reason

2:06:18didn't want to do that. Main point is

2:06:23I got sense enough to know

2:06:25I I went to that property um at least

2:06:29twice. One time

2:06:31in on the interior of it and then

2:06:33another time I came in off of Circle

2:06:36Drive up on the north side and I thought

2:06:38I could get all the way to it, but it

2:06:40was some private drives up there and so

2:06:42I didn't

2:06:43uh

2:06:44attempt it. I could see the

2:06:46uh

2:06:47substation, but I did go in on uh

2:06:52uh at the Anglade Street and I'd always

2:06:56noticed the two-story house up there on

2:06:58I've been through Brohall many times. Up

2:07:02there on the hill and that one field it

2:07:04comes out there to the highway.

2:07:07I I'd noticed that every time I ever

2:07:09went by and I just wondered what was

2:07:11back there.

2:07:13And so

2:07:14uh that day two three months back when I

2:07:18went to see it

2:07:20when I got down to the end of the street

2:07:22I could see it was

2:07:24uh

2:07:24private drive so

2:07:26I go on through the

2:07:28woods trees on both sides

2:07:32and it wasn't just a small field

2:07:35it was a big field. I don't know how

2:07:37many acres in the field. I know it was

2:07:39trees rounded it, but it would uh

2:07:42big. Might be 100 acres open land in it.

2:07:45I don't know.

2:07:46So

2:07:48but the point is

2:07:50the man or the family has the right to

2:07:53sell

2:07:55the property even

2:07:59>> I would just like to

2:08:01um

2:08:04add that um

2:08:06some of us just came back from the

2:08:09National Association of Counties

2:08:12um national meeting

2:08:14and we did have um

2:08:18you know, workshops about the data

2:08:21centers and again in my opinion

2:08:24I think that

2:08:26um there are you know, pros and cons on,

2:08:30you know, both sides. For me,

2:08:33I don't have enough information as it

2:08:37relates to

2:08:39our county moving in a specific

2:08:42direction around data centers. And I

2:08:45think because it's undefined, it's

2:08:47unfair to then,

2:08:52burden the citizens without

2:08:55a clear definition of how we're moving

2:08:57forward. I'll give an example because

2:08:59Vice Chair Wizenhunt

2:09:02made reference to Loudoun County. So,

2:09:05the information, and I, you know,

2:09:08applaud you all as citizens that came

2:09:10from the 15 best practices was from the

2:09:13Vice Chair of Loudoun County. And when

2:09:17you um

2:09:19measure best practices of of this

2:09:23situation, it just doesn't meet their

2:09:27model. And that is one that we were able

2:09:31to go to Loudoun County, but also we I

2:09:33was able to have conversation with the

2:09:35Vice Chair. So, I you know, I'm not

2:09:39in per se disagreement with Vice Chair

2:09:43Wizenhunt as it relates to she has

2:09:45enough information, but I will reiterate

2:09:48that I just don't have enough

2:09:50information at this point to

2:09:53um to um

2:09:56um I would say approve something of this

2:09:59magnitude from the standpoint of someone

2:10:01wanting to bring in

2:10:03data centers. And again, I would

2:10:05encourage this county with staff, you

2:10:08know, experts around what is the vision

2:10:11of data centers in Forsyth County. So,

2:10:13we have

2:10:15in my opinion

2:10:17a our own best strategies, our own

2:10:20footprint in Forsyth County to bring

2:10:22data centers. So, I just wanted to add

2:10:25that before we finalize the vote.

2:10:28>> Any other discussion?

2:10:31All in favor, please say I.

2:10:32>> I.

2:10:33>> Those opposed?

2:10:34>> No.

2:10:35>> I. No.

2:10:36Motion carries.

2:10:38We're good.

2:10:39>> [clears throat]

2:10:39>> I'd say we probably can take take it we

2:10:42we need to set up for a different kind

2:10:43of hearing. I think we can take about a

2:10:4510-minute break and return.

2:10:50Well spoken.

2:24:36>> Ready for item two.

2:24:39>> Okay, please.

2:24:42>> Item two, the second item on the agenda

2:24:45is a public hearing and consideration of

2:24:47a special use permit request by

2:24:50Elizabeth Ann Tucker

2:24:52for a land clearing and inert debris

2:24:55landfill for property located on the

2:24:57south side of Watkins Ford Road, east of

2:25:01High Point Road and west of Idlewood

2:25:03Road zoning docket F 1667.

2:25:09And Chris Murphy, our planning

2:25:10development services director, will give

2:25:12a preliminary statement on the rezoning

2:25:15case. And by the way, he has to be And

2:25:18this is a Everybody has to be sworn in

2:25:20that speech speaks tonight. And actually

2:25:23the commissioners act pretty much as a

2:25:25jury here. And and so for to begin with,

2:25:28Chris Murphy has to be sworn in sworn in

2:25:31and our

2:25:33swooned in sworn in and our clerk Ashley

2:25:35Matthews um will do that.

2:25:42>> Ask those people to be quiet.

2:25:45>> I did.

2:25:51>> Good evening. It's been a while since

2:25:52I've been up here, but it's already been

2:25:53a long meeting. Uh this is uh case

2:25:56F-1667, which is a special use permit

2:25:59request for a uh 69.5 acre tract of

2:26:02property located between I-74 and

2:26:04Watkins Ford Road

2:26:06east of High Point Road. Uh this is an

2:26:08elected body special use permit for a

2:26:10landfill, uh land clearing, and inert

2:26:12debris uh LCID greater than 2 acres.

2:26:16Uh I will pause briefly and give the

2:26:18county attorney the uh ability to

2:26:20provide a little bit of procedural

2:26:22explanation.

2:26:24>> Uh thank you, Chris. Um

2:26:28as uh Mr. Murphy indicated, this is a

2:26:30quasi-judicial hearing um and as the

2:26:32chairman indicated, this is based on

2:26:34sworn testimony during this hearing,

2:26:36which is taking place right now. Um

2:26:39there have been no communications with

2:26:42people outside of the hearing, and I

2:26:44appreciate the commissioners uh

2:26:45forwarding to me any questions they

2:26:47received from the public on that.

2:26:49Uh the testimony must be based on

2:26:52relevant facts,

2:26:53and some testimony, such as traffic

2:26:55projections or property evaluations,

2:26:57must be based on expert testimony. The

2:27:00four required hearings to approve um the

2:27:04application are one, that the use will

2:27:06not materially endanger the public

2:27:08health or safety if located where

2:27:09proposed and developed according to the

2:27:12application and plan as submitted and

2:27:13approved.

2:27:15Two, that the use meets all required

2:27:17conditions and specifications.

2:27:19Three, that the use will not

2:27:21substantially injure the value of

2:27:22adjoining or abutting property, or that

2:27:25the use is a public necessity.

2:27:27And four,

2:27:29the location and character of the use if

2:27:30developed according to the application

2:27:33and plan submitted and approved will be

2:27:35in harmony with the area in which it is

2:27:37to be located and in general conformity

2:27:39with the 4 2045 comprehensive plan.

2:27:43Once the Once the proponent has offered

2:27:47evidence of these four findings, the

2:27:48burden

2:27:50shifts to opponents of the R&E to

2:27:53produce specific evidence that at least

2:27:55one of the four findings has not been

2:27:57met.

2:27:59And that is it. So, I'll turn it back to

2:28:01Chris.

2:28:07>> Get just a little bit of context and

2:28:08background. This is the subject property

2:28:10shown on the 4 2045 growth management

2:28:12area plan. It is located in GMA 4,

2:28:16uh, which is the future growth area just

2:28:19south of some property located within

2:28:20the town of Kernersville on the south

2:28:22side of Watkins Ford Road.

2:28:25Uh, this is the subject property

2:28:26highlighted in yellow.

2:28:28Uh, again, you have the subject property

2:28:30of almost 70 acres here on the south

2:28:34side of uh, Watkins Ford Road. You have

2:28:37the existing LCID landfill operated by

2:28:40the same entity, which is located here

2:28:42to uh, the west of the subdivision that

2:28:45is located within uh, the town of

2:28:47Kernersville. The LCID uh, that is

2:28:51already operating that went that went

2:28:52through an expansion process about 18

2:28:54months ago uh, was permitted in 2018.

2:28:58Uh, and um, the subdivision

2:29:02um, wasn't constructed until later in

2:29:042018.

2:29:06And again, this is across the road from

2:29:07that existing subdivision, um,

2:29:10there within the town of Kernersville.

2:29:13Subject property uh, outlined in yellow.

2:29:17Again, it's a primarily agricultural

2:29:19piece of property, again located across

2:29:22the street across Watkins Ford Road from

2:29:25this subdivision within the town of

2:29:26Kernersville. And this is the LCID

2:29:30operation that is uh, currently in use

2:29:34and this is an area planned for the

2:29:37future.

2:29:40I incorrectly, uh,

2:29:42said that was a church last time. That's

2:29:43actually, uh,

2:29:45a building that's owned, uh,

2:29:48a shop that's owned by the same folks

2:29:49that are going through the process, uh,

2:29:51to establish the LCID,

2:29:53uh, at this location.

2:29:55Church is a little bit further to the

2:29:57west.

2:29:59>> [clears throat]

2:30:00>> Subject property, uh, shown on the

2:30:02Southeast Forsyth County Area Plan

2:30:04Update Map, uh, it is shown for large

2:30:07lot residential,

2:30:09um, but an LCID is, uh, permitted as,

2:30:13uh, a use allowed through the issuance

2:30:16of a special use permit in the zoning

2:30:18district. Uh, again, this isn't a

2:30:20rezoning request. This is a special use

2:30:21permit request.

2:30:25Uh, this is looking south at the subject

2:30:26property from Watkins Ford Road.

2:30:30This is looking west on Watkins Ford

2:30:31Road. The subject property is on the

2:30:33left.

2:30:35This is looking east along Watkins Ford

2:30:37Road. The subject property is on the

2:30:38right.

2:30:40Uh, this is the site plan that has been

2:30:42submitted, uh, of this 69 and 1/2 acres,

2:30:45I believe, that these two separate

2:30:47parcels account for

2:30:50I go to my notes so I don't give you

2:30:51incorrect information.

2:30:53Uh, account for, uh, 37 total acres of

2:30:57LCID fill. This larger cell is

2:30:59approximately 29 acres. This cell is 8

2:31:02acres. Again, this is a land clearing

2:31:05and an inert debris landfill. This isn't

2:31:06a sanitary landfill with trash. This

2:31:08isn't a construction and demolition

2:31:10landfill with

2:31:11um, materials from construction sites.

2:31:13This is, uh, just as the name implies,

2:31:16land clearing, uh, so dirt,

2:31:19trees, stumps, uh, inert debris, such as

2:31:22concrete, rock, and those kind of things

2:31:24is what would be going into,

2:31:26uh, this landfill. There is a recycling

2:31:28area. They are showing the required

2:31:29buffer yards around the entire

2:31:31perimeter.

2:31:32Um they have agreed to some right-of-way

2:31:34dedication along Watkins Ford Road. And

2:31:36again, just for context, this is the

2:31:38proposed LCID and the existing LCID

2:31:42property is about 500 ft to the

2:31:44northwest, and the actual cell that is

2:31:46being filled is about 1,000 ft to the

2:31:48northwest.

2:31:52Regarding the four special use permit

2:31:54findings that the county attorney went

2:31:56over.

2:31:57Um

2:31:59the first finding is that the use will

2:32:01not materially endanger the public

2:32:03health or safety if located where

2:32:04proposed and developed according to the

2:32:06application and plan as submitted and

2:32:07approved. From a staff perspective, we

2:32:10think that that answer is no. The

2:32:11proposed use LCID greater than 2 acres

2:32:13is not a threat to the public public

2:32:15health or safety.

2:32:17Excuse me, the presumption is that the

2:32:18if the use is permitted in the zoning

2:32:20district, it is not a threat to public

2:32:22health or safety unless proven

2:32:24otherwise.

2:32:26As far as finding two, that the required

2:32:29use that the use meets all required

2:32:31conditions and specifications. From a

2:32:33planning staff perspective and the

2:32:35planning board itself, we

2:32:37say yes to that. Uh the subject request

2:32:40will meet the minimum UDO of

2:32:42the minimum requirements of the UDO. The

2:32:44site plan that is before you does meet

2:32:46those minimum requirements. So, that

2:32:48finding should be for yes.

2:32:50For finding three, that the use will not

2:32:52materially substantially injure the

2:32:54value of adjoining or abutting property

2:32:56or that the use is not a public

2:32:57necessity.

2:32:58I mean, this isn't a public necessity

2:33:00because this isn't being operated by the

2:33:02public, and planning staff does not have

2:33:04the expertise to make property value

2:33:06determinations. That needs to come from

2:33:07an expert, which I believe you will hear

2:33:09testimony um after me to that finding.

2:33:13And then finally, the fourth finding,

2:33:15that the location and character of the

2:33:17use, if developed according to the

2:33:18application and plan submitted and

2:33:20approved, will be in harmony with the

2:33:22area in which it is located, and in

2:33:24general conformity with forward 2045.

2:33:27Uh staff's and planning board's final

2:33:29Staff's finding on that is yes, there

2:33:31there is an existing LCID landfill

2:33:33greater than 2 acres use that's located

2:33:36within 500 ft of the request.

2:33:39Uh beyond that, the presumption is that

2:33:41if the use is permitted in the zoning

2:33:43district, uh it is compatible with the

2:33:45area unless proven otherwise. And again,

2:33:48that's some of the testimony uh that is

2:33:51will be heard tonight is related to

2:33:52that, and that's why we're having the

2:33:53public hearing in this quasi-judicial

2:33:55manner.

2:33:57As far as the recommendation, a land

2:33:59clearing and inert debris landfill

2:34:00greater than 2 acres requires the

2:34:02issuance

2:34:03uh of a special use permit from the

2:34:05elected body following a site plan

2:34:07review by the planning board in the AG

2:34:09zoning district.

2:34:11The planning board did determine that

2:34:12the site plan meets all UDO requirements

2:34:14on March 12th of 20 26 at their meeting.

2:34:18What's before you to do

2:34:21now is to hold the public hearing and

2:34:23then make a determination regarding the

2:34:24four findings, and then either issue or

2:34:27deny the special use permit request.

2:34:30And with that, I'm available to answer

2:34:31any questions.

2:34:32>> Any questions for Chris?

2:34:34There was one comment

2:34:37from

2:34:37uh I think a neighbor living out in that

2:34:40area

2:34:41critical of the proposal on the ground

2:34:43that the roads out there that would be

2:34:46used were tar and gravel and could not

2:34:48withstand the effects the deleterious

2:34:51effects of

2:34:53heavy moving or commercial

2:34:55equipment vehicles.

2:34:57Do you have any information about that?

2:34:59I can't tell what the four qual-

2:35:01requirements that would fit into.

2:35:04>> Yeah, I I don't have any specific

2:35:06comment related to that regarding the

2:35:08four findings. I will say again that

2:35:10there is a LCID that currently already

2:35:12operates out there.

2:35:14I'm not aware of any adverse impacts on

2:35:17the existing roadway, but again, I can't

2:35:19honestly say that I travel that road

2:35:21that often, but I have not heard of

2:35:23anything and I've not heard anything

2:35:24from DOT. I know that there are I think

2:35:26there are some future road projects

2:35:28scheduled for Watkins Ford Road under

2:35:30the NCDOT NCDOT's transportation plan,

2:35:34but I don't know what the horizon year

2:35:35on that is. I know that there are some

2:35:37things in the works

2:35:40for that whole section of Watkins Ford

2:35:42Road.

2:35:44>> Could you remind me again in the acreage

2:35:46of the of the of the of the LCID that's

2:35:48in use right now?

2:35:51>> I cannot because I I don't have that

2:35:53information. I know where it is, but I

2:35:54don't know the acreage. That's probably

2:35:56a question that's better left for the

2:35:58petitioner.

2:36:00>> Okay.

2:36:01So, we're we're ready to begin. I've got

2:36:03a couple preambles and we'll get started

2:36:05and the first is that

2:36:06the board uh will not be limited to

2:36:09consideration of such evidence as would

2:36:12be admissible in a court of law.

2:36:14Discussion and deliberation among the

2:36:16board shall occur in open session

2:36:19and the board may question any witness.

2:36:22All evidence must be presented prior to

2:36:25the board rendering a decision.

2:36:28The process of approving the issuance of

2:36:30a special use permit is quasi-judicial

2:36:32um as our attorney has explained and it

2:36:35does require speakers for this

2:36:37particular hearing to speak under oath.

2:36:41The board requests that both proponents

2:36:43and opponent opponents refrain from

2:36:45making a repetitive statement or asking

2:36:47repetitive questions. Each side should

2:36:50consider appointing a spokesperson, if

2:36:52possible, to conduct cross-examination.

2:36:55The board will allow both sides to

2:36:57present their views and to cross-examine

2:37:00each witness.

2:37:02Anyone who intends to present an

2:37:04argument in favor of this matter, just

2:37:07please come forward and go ahead and you

2:37:10can move to the podium.

2:37:12Take your time.

2:37:20Our clerk Ashley Matthews will

2:37:22administer an oath to all of you.

2:37:30>> Be clear that the testimony you shall

2:37:31give to the Board of Commissioners shall

2:37:32be the truth, the whole truth, and

2:37:34nothing but the truth.

2:37:36>> I do.

2:37:37All righty.

2:37:45Good evening, Commissioners. We just

2:37:46need your We just need your name name

2:37:47and address. And I I didn't read that.

2:37:49Please do. Going forward, you state your

2:37:51name and address for the record.

2:37:52>> Okay.

2:37:53My name is Tanner Boles. I live at 7300

2:37:55Watkins Ford Road, which is directly

2:37:58adjacent west properties in in question.

2:38:01I'll start my statement. Good evening,

2:38:03Forsyth County Commissioners and county

2:38:04staff.

2:38:05I'm the current owner operator of Union

2:38:07Cross Land Development LCID located at

2:38:097301 Watkins Ford Road in Kernersville

2:38:11on the north side of Watkins Ford Road.

2:38:13As staff has stated, I am petitioning

2:38:15for special use permit for new LCID

2:38:17landfill on property that's currently

2:38:18owned by my mother on the south side of

2:38:20Watkins Ford Road. I want to reiterate

2:38:21that the LCID landfill,

2:38:23which is land clearing and inert debris

2:38:25such as logs, stumps, limbs, yard waste,

2:38:27untreated wood, brick, block, concrete,

2:38:29none of which can be painted or include

2:38:31chemical treatments.

2:38:33The proposed parcel is directly adjacent

2:38:35to my personal home and farm, also

2:38:37located on the south side of Watkins

2:38:38Ford Road. This land has been in my

2:38:40family and been farmed for 50 years. As

2:38:42this is a quasi-judicial

2:38:44a quasi-judicial hearing, my statement

2:38:45will be brief and relevant to the four

2:38:46facts of finding. It will be followed by

2:38:48my consultants and professionals who can

2:38:50further elaborate and answer any

2:38:51questions that you may have. The goal of

2:38:53this project is to be able to utilize

2:38:55the southern land with the needed

2:38:56purpose for the area of southeast

2:38:58Forsyth County and ultimately be able to

2:38:59revert the area back to agricultural use

2:39:01upon completion and closure.

2:39:03Considering the timeline within the

2:39:04original petition filed 9 years ago on

2:39:07the northern property our current

2:39:08operation and life expectancy is right

2:39:10on schedule. Our plan is to proceed

2:39:12across the road when our current north

2:39:14side is full.

2:39:16We will then fence and have cattle graze

2:39:18at landfill site as no structures will

2:39:20be built.

2:39:21This is the same plan for the proposed

2:39:22south site which we are seeking approval

2:39:24this evening. The south site will be

2:39:26developed in phases and submitted to the

2:39:28NCDQ

2:39:29to maintain agricultural production on

2:39:31all available acreages and then not

2:39:33immediate use for LCID or accessory

2:39:35operations. In short,

2:39:37we will still grow crops, hay cattle,

2:39:39and use the land until it's transitioned

2:39:41LCID use. Areas that are at capacity

2:39:43will then be fenced and pastured upon

2:39:45approval of the NCDQ waste management

2:39:47division.

2:39:48The need for this proposed facility has

2:39:50been demonstrated and justified by

2:39:52continued use with the town of

2:39:53Kernersville solid waste division for

2:39:55the management of their organic debris

2:39:57as well as the city of Winston-Salem's

2:39:58traffic field operations divisions for

2:40:00the same.

2:40:01By using our facilities municipalities

2:40:02have been able to serve, save, and and

2:40:05or reallocate funds for other uses by

2:40:07having a close and competitive option

2:40:09over higher fees and transportation

2:40:10costs to other facilities in the county.

2:40:12Our customers include tree service and

2:40:13removal companies in the community

2:40:15whether it be selective tree removal or

2:40:16emergency response due to storms and

2:40:18natural disasters.

2:40:20Furthermore, the very neighborhoods

2:40:21being built close proximity to the

2:40:22current north landfill may have utilized

2:40:24our facility for debris purposes whether

2:40:25they realize it or not.

2:40:27Whether it be in the clearing of the

2:40:28trees for the initial construction or

2:40:30municipal management of organic debris.

2:40:33I myself am the owner-operator and

2:40:35involved in day-to-day operations

2:40:36management even going to lengths to

2:40:37close my business in adverse weather to

2:40:39keep a clean facility as well as keeping

2:40:41public roads clean. I will say again

2:40:43that I live here along with many of my

2:40:45family members and neighbors.

2:40:47I feel that being neighborly is

2:40:48respectful is of utmost importance to

2:40:50myself and our operations. There are

2:40:52strict protocols set in our operations

2:40:54manual to make sure that we screen and

2:40:55even refuse unacceptable waste that

2:40:57should go and and will go to other

2:40:59appropriate and permitted facilities. In

2:41:018 years of operation we have been being

2:41:03inspected not only by the NC DEQ

2:41:05division Waste Management annually, but

2:41:07also the EAP of Forsyth County.

2:41:09We've had no violations to date.

2:41:11Those reports are public record and

2:41:13available on the NC DEQ website and can

2:41:15be searched by our permit number 34-26.

2:41:18Any contact with E-Forsyth EAP would

2:41:20also validate this statement. We strive

2:41:22to continue these standards if approved

2:41:24for the future facility and continue to

2:41:26service our community.

2:41:28Thank you for hearing this petition this

2:41:29evening. I will now will now turn my

2:41:30time over to our real estate valuation

2:41:32specialist and then our landfill

2:41:33engineering consultant. Thank you again

2:41:35for your time.

2:41:40>> [clears throat]

2:41:41>> Mr. Chairman, you might ask if anyone

2:41:42wanted to ask any questions.

2:41:44>> One one for each one. I I apologize.

2:41:46Come on up here.

2:41:53This is for pri- In fact, we've done a

2:41:54couple of these just In fact, I I was

2:41:56here when we did yours the first time.

2:41:58>> Correct. Yes, sir.

2:41:59>> And we and we actually had peo- We

2:42:00actually had people sort of a little

2:42:01back and forth and it actually worked

2:42:03out okay. Uh but I I was going to wait

2:42:06till we got but this is good. Um I and

2:42:08I'm going to be just a not an opponent.

2:42:10I just have a question. Back to the how

2:42:12many acres are in the in the LCID you're

2:42:14operating now?

2:42:15>> The initial

2:42:16>> Yeah.

2:42:16>> permit application was 6.49 acres. The

2:42:19additional was approximately four.

2:42:22So, we're right at 11 acres in the the

2:42:24expansion. Um

2:42:26based on what you and I had conversed

2:42:28about in the past uh

2:42:30and and current VDOs,

2:42:32um

2:42:33figuring out the

2:42:36procedures and and

2:42:39in planning and everything of that

2:42:40nature is

2:42:42is basically the regards of the reason

2:42:44that this cell development on the south

2:42:46side is so large at one time. It will

2:42:48not all be done at same time.

2:42:51Um we we phase it. We only disturb what

2:42:54we must.

2:42:56Uh you know, with soil and water

2:42:57conservation and erosion control

2:43:00actually keeping part of the current use

2:43:03is still in pasture and hay field and it

2:43:05will only be utilized in the LCID when

2:43:08it's necessary.

2:43:10>> Is there anyone opposed here present

2:43:14that would like to question make a

2:43:16comment relative to what has been

2:43:18presented so far?

2:43:24>> Not seen anyone. Any other questions

2:43:26from our folks?

2:43:27>> Yeah,

2:43:28in

2:43:30in drought periods such as we've

2:43:32recently been in, is there any

2:43:33aggravated risk of

2:43:37fire involving

2:43:40vegetative waste at

2:43:41>> You'd be surprised it's actually quite

2:43:43the opposite.

2:43:45>> So there's nothing in in your operations

2:43:48manual with regard to minimizing that?

2:43:50>> Oh yes, there's there's policy and

2:43:52procedure and such.

2:43:54>> Would you

2:43:55be able to comment just briefly on what

2:43:58those processes are?

2:44:00>> When we do hotspot inspections every day

2:44:03on daily basis, we did have a

2:44:06a fire that was called in by a neighbor

2:44:08and I'm probably sure that's what you're

2:44:09referring to.

2:44:11It was called in as any other

2:44:15combustion fire could cuz it is organic

2:44:17waste, green waste. It was during the

2:44:19blizzard in February when everything was

2:44:21ice covered.

2:44:23I reported that. It was contained with

2:44:25less than 1,000 gallons of water that

2:44:27fire report we actually have

2:44:29from town of Kernersville and Union

2:44:31Cross Fire District and was contained

2:44:35within 3 hours. Fire Department left

2:44:37scene. I immediately contacted Division

2:44:39of Solid Waste the following business

2:44:41day.

2:44:42They came out and spected. We also have

2:44:43those inspection reports available for

2:44:45anyone who want to look at it.

2:44:46>> Thank you.

2:44:47>> Was it incendiary?

2:44:49>> Sir?

2:44:50>> Was it incendiary?

2:44:51>> No.

2:44:56>> Other questions?

2:44:59All right. Now we can switch to your

2:45:01second speaker.

2:45:03Just identify yourself and um

2:45:06um name and address.

2:45:08>> Good evening. Chris Martin with

2:45:09Tri-County Real Estate. Uh we were

2:45:11contacted by Mr. Bowles to do a

2:45:14market analysis of the home sales in the

2:45:17area. Uh in doing that um

2:45:20research, uh the closest neighborhood to

2:45:22the current LCID uh is the Watkins

2:45:24Landing uh development.

2:45:27And in the past 1,000 days or almost two

2:45:30two years, nine months,

2:45:32they have sold There's been 74

2:45:34properties that have been sold in that

2:45:35neighborhood. Um

2:45:37and of that, the average home selling

2:45:40average homes are selling at 98.4% of

2:45:43the asking price, which is

2:45:46at or above what normal standards are.

2:45:49Um so, our estimation is the land the

2:45:52current landfill has had no impact on

2:45:54the sales price of the neighborhood

2:45:55according to what we've been able to

2:45:56determine.

2:45:58>> Any questions?

2:46:01Any We have an opponent. Yes, please

2:46:03come forward.

2:46:03>> Why did you take a

2:46:04>> Uh

2:46:05you also have to get sworn in.

2:46:07Just get sworn in and you can step up

2:46:09and identify yourself. Get sworn in

2:46:11first.

2:46:18>> The testimony you shall give to the

2:46:19Board of Commissioners shall be the

2:46:20truth, the

2:46:24>> And if you would just identify yourself,

2:46:26your name and address.

2:46:27>> Alchin. I live in Watkins Ford Landing,

2:46:30I guess the neighborhood he's referring

2:46:31to.

2:46:32>> All right. Now you can ask your

2:46:33question.

2:46:33>> Is there a reason why you used 1,000

2:46:35days instead of just like the past year?

2:46:38>> 1,000 days does cover the past year.

2:46:40>> No, but like why not just limit to the

2:46:42last 365

2:46:43>> as far as we can, so

2:46:45>> But the neighborhood wasn't done yet, I

2:46:47guess. So, you're going to sell more

2:46:48houses cuz there's builder incentives on

2:46:51a bunch of the houses, right?

2:46:55But we finished this year.

2:46:57>> Could Could I ask the two of you to get

2:46:58closer to the microphone because I'm a

2:47:00little more hearing challenged?

2:47:02>> I mean, we we just picked dates to go by

2:47:04is what we did. I mean, that's that's

2:47:05common practice. We go back Normally, we

2:47:08only go back 6 months, but in this we

2:47:09went back almost 3 years.

2:47:11>> Okay.

2:47:12>> Sir, could you repeat your question

2:47:13again and get just a little bit closer

2:47:15cuz I'm trying to understand the

2:47:17context.

2:47:18>> question is why use a thousand the past

2:47:20thousand days because our neighborhood

2:47:22just finished this year. So, the last

2:47:23house sold this January, so it's going

2:47:25to I guess

2:47:27look like there's lots of sales because

2:47:28the neighborhood was being built and

2:47:30finished and then there was builder

2:47:31incentives to actually buy the houses.

2:47:34>> Got it now. Thank you.

2:47:36>> That's my question.

2:47:37>> All right, that's good.

2:47:38>> Thank you.

2:47:39>> Any follow-up from here or any follow

2:47:41Anyone else in the audience that would

2:47:42like to ask a follow-up question? Or

2:47:47Sir, okay. Thank you.

2:47:53Just identify your

2:47:54identify yourself and address

2:47:56>> Yes, my name is Stacy Smith and I'm

2:47:58senior engineer with uh Smith Gardner.

2:48:00My office is located at 14 North Bol-

2:48:03Bolen Avenue in Raleigh, North Carolina.

2:48:06I'm a licensed professional engineer in

2:48:07the state of North Carolina among other

2:48:09states.

2:48:10I hold a bachelor's and master's degree

2:48:12in civil engineering from NC State

2:48:13University. My area of practice is in

2:48:16solid waste related engineering,

2:48:18permitting, design, construction, and

2:48:20operations for over 30 years.

2:48:24Uh the applicant engaged our firm to

2:48:26investigate the subject site and prepare

2:48:28a plan for development of a land

2:48:30clearing and inert debris landfill

2:48:33facility in compliance with local,

2:48:34state, and federal rules. Our findings

2:48:38and site plan development are included

2:48:39in the submitted uh application

2:48:42represented in our our site plan. Also

2:48:46have a

2:48:47full report that I can submit as well if

2:48:51uh

2:48:51if that's needed. Um but I I wanted to

2:48:55point out that uh as a matter of

2:48:57information, the local planning approval

2:48:59is the initial element of permits and

2:49:01approvals necessary to obtain an NC DEQ

2:49:04solid waste permit whereby multiple

2:49:06agencies at the local, state, and

2:49:09federal levels will conduct review of a

2:49:12comprehensive application. The point is

2:49:14that the facility of this type will

2:49:16maintain review and compliance by

2:49:17multiple agencies to ensure appropriate

2:49:20environmental stewardship.

2:49:22Uh within the my um evaluation that was

2:49:27uh represented in the site plan, we uh

2:49:30reviewed flood plain restrictions,

2:49:32cultural resources, natural and historic

2:49:34preserves, endangered and threatened

2:49:36species, clean water act restrictions,

2:49:39waste buffers and setbacks, uh emergency

2:49:42access, ground water buffers, storm

2:49:45water management, operations, closure,

2:49:48and post-closure. It is our opinion that

2:49:50the proposed plan and development

2:49:52complies with the required regulations

2:49:53and standards and if operated in

2:49:55accordance with the proper permits, will

2:49:57not materially endanger the public

2:49:59health, safety, and general welfare.

2:50:02And um and I don't know if it's

2:50:03appropriate to submit my report. I have

2:50:06multiple copies if if that should be

2:50:09appropriate.

2:50:10>> And one was submitted to with your app

2:50:13>> Only the site plan

2:50:14the way your process goes is just site

2:50:17plan and we answer a lot of questions,

2:50:19but I actually have a separate report

2:50:21that I prepared for

2:50:22uh Mr. Bowles and Mr. Tucker.

2:50:26>> For me, I think your credentials speak

2:50:28for itself and and that you have

2:50:29prepared a report and answered the

2:50:31questions according to the

2:50:33kind of your expertise.

2:50:34>> Well, thank Thank uh Chairman Martin,

2:50:36but I mean if he's prepared a report, I

2:50:38would like to have it.

2:50:40>> Okay.

2:50:40>> Yes, thank you.

2:50:41>> Right.

2:50:41>> I'll take it.

2:50:42>> Please submit that.

2:50:52>> Mr.

2:50:53Uh since he referred to it, might be a

2:50:54good idea to have a copy in the record

2:50:56in case of future action.

2:50:57>> Okay, looks like we're all going to get

2:50:58one.

2:50:59>> Okay, that's good.

2:51:02>> All right, do you have any other

2:51:03questions or should we look at the site

2:51:06plan if you have that available?

2:51:08>> What wants to come forward? Come forward

2:51:09to No, no, not you. Yeah.

2:51:12The young lady out in the

2:51:14audience there.

2:51:22Hang on a second, we'll swear you into

2:51:25>> Thank you.

2:51:26>> Thank you.

2:51:38Thank you for the copies.

2:51:39>> Yeah, I I appreciate it. Thank you.

2:51:42But this was helpful.

2:51:48>> for the testimony she'll give to the

2:51:50board of

2:51:55>> Now, yeah, just tell us your name and

2:51:57address and you can ask your questions.

2:51:58>> Yeah, my name is Sunny Chen. I live at

2:52:007263 Hunt Gate Drive in the development

2:52:03that is just um above the proposed area.

2:52:07There is a large creek in that area. You

2:52:09touched on how you plan to mitigate

2:52:11water exposure. I just wondered if you

2:52:13had more information about it.

2:52:19>> So, um the the uh as a part of the

2:52:22initial evaluation, we had a uh and

2:52:24within my

2:52:26um report that we shared with you, there

2:52:29is a subsequent report by Enver

2:52:31Environmental.

2:52:32Uh he's a biologist specializing in

2:52:34wetlands and streams. And one of the

2:52:36first things we'll do is identify where

2:52:39um you know, waters of the US, wetlands,

2:52:41and so forth. And that gets uh

2:52:43incorporated into our map. Um we will

2:52:46buffer those streams as well as the

2:52:49entire site with the road that is

2:52:51surrounding the site. That has channels

2:52:54and diversions that will deliver the

2:52:57stormwater to the the stormwater basins.

2:53:00Okay. And in those stormwater basins,

2:53:01that's where we manage the runoff from

2:53:03the facility. Uh that gets permitted

2:53:06with the state. Also gets permitted with

2:53:09uh Winston-Salem.

2:53:10And uh and that's where we can kind of

2:53:12manage and sample and all of the other

2:53:14things that may uh you know,

2:53:17help us make sure, ensure

2:53:20uh that uh we're protecting the

2:53:22environment.

2:53:23And again, if anywhere in that stream,

2:53:25right? The other is the buffers, right?

2:53:27Again, we we stay out of that riparian

2:53:30zone by 50 ft.

2:53:34>> Okay.

2:53:35>> Okay.

2:53:36>> Looking at your pictures here.

2:53:37>> Yeah.

2:53:37>> And and your

2:53:40Any other questions relative to that?

2:53:42And and young lady just spoke, would did

2:53:44you get a copy? Would you like to see

2:53:46his that stream part of that? He could

2:53:50>> Or could you show me on the map where

2:53:52you reside?

2:53:54Yeah.

2:54:03>> It might barely be on there.

2:54:08>> So if you're looking at the um where it

2:54:10says RS12S

2:54:12PRD,

2:54:13>> I see that.

2:54:13>> If you see there's there's a mouse you

2:54:15can use. It's like a white button.

2:54:16>> Sorry.

2:54:17I live right here.

2:54:19>> Okay.

2:54:19>> Oh, I clicked it.

2:54:22Right where the mouse is currently.

2:54:26>> Fair enough.

2:54:27>> Would you would you like to see near

2:54:28too.

2:54:29>> You guys are together.

2:54:31>> Yes.

2:54:31>> Okay, fair enough. Thank you.

2:54:33Thank you.

2:54:35>> Any other question

2:54:37>> Engineer

2:54:39The The development there, is it on the

2:54:42upgrade

2:54:44>> [clears throat]

2:54:45>> a higher

2:54:46higher grade level

2:54:49than

2:54:50the proposed site?

2:54:53>> The

2:54:54um

2:54:54You're talking about the the Watkins

2:54:56Ford development?

2:54:57>> Yes.

2:54:58>> Uh well, it's it's divided by the road.

2:55:01Uh any runoff from this facility would

2:55:05be directed in a channel, and the lower

2:55:07lying area is is going to be where where

2:55:10the stream is. So, most of the storm

2:55:12water's going to be directed away from

2:55:14that.

2:55:15>> So, the

2:55:16>> [clears throat]

2:55:17>> the drainage of the

2:55:19this whole area in yellow is from

2:55:25Is the topo

2:55:27uh

2:55:29grade from west to east down?

2:55:38Or the the drainage and natural drainage

2:55:40from on the topo of the property, is it

2:55:45on the property in question?

2:55:47>> So, the natural drainage of the area

2:55:49now, yes, it there's a high spot uh

2:55:52where I'm showing my my mouse now, and

2:55:55it drains towards Watkins Ford.

2:55:58But then it it will flow back towards

2:56:01Abbot's Creek along the road.

2:56:03Uh and again, in the in the case of uh

2:56:05what we're doing again, all of that

2:56:07would be redirected to the the basins in

2:56:09the center.

2:56:11But uh

2:56:11>> Even though that center is a high spot,

2:56:14the way the

2:56:15>> [clears throat]

2:56:15>> the grade is, it goes down and then goes

2:56:18back to the east.

2:56:20>> Well, and then the other thing that will

2:56:21happen in the development of landfill,

2:56:23we do

2:56:24uh again excavate out. And so one of the

2:56:28requirements of this always permit is

2:56:30that we're at least 4 ft above the

2:56:31groundwater. And so there has been

2:56:34piezometers and wells

2:56:36put on the site right now where we're

2:56:38monitoring groundwater.

2:56:43>> Other questions?

2:56:47Is there any are there any other

2:56:49speakers that you would like to invite

2:56:51on the in favor of proponent side?

2:56:56All right.

2:56:57Is there anyone that would like to

2:56:59present an opposition

2:57:01statement

2:57:03um that then the proponents could ask

2:57:05you questions. In other words, you you

2:57:07kind of like your own first. Would

2:57:09either of you like to make any just come

2:57:11up and you've already been sworn in?

2:57:17>> I guess hello commissioners. My name is

2:57:18Chunsheng Chen. I live in in

2:57:217263 Hunt Gate in Watkins Landing. Uh so

2:57:23my main opposition is in the fact that

2:57:25it's at a LCID. It's more the fact of

2:57:27how close it is to a creek and then into

2:57:30a watershed.

2:57:31So I'm a engineer for Volvo Trucks,

2:57:34which is a heavy-duty trucking company,

2:57:36and we are very aware of how much I

2:57:38guess tire pollution we generate. And

2:57:41that's something that I guess an

2:57:43increase a larger LCID would bring in

2:57:45more trucks. Uh so like dump trucks and

2:57:47semi trucks.

2:57:49And when you have uh trucks with heavier

2:57:51axles, the I guess the damage to the

2:57:53road and the tires is proportional to um

2:57:56the power of

2:57:59the fourth power. So

2:58:01let's say the weight is five times more

2:58:03between a dump truck and F-150 pickup,

2:58:05that means you're generating 600 and um

2:58:0925 times the wear and tear on the road

2:58:11and on the tires. So my concern is all

2:58:14that um dust and pollution is going to

2:58:17wash into the watershed because

2:58:19naturally the stream when it rains uh

2:58:21water will run down the road and then

2:58:23into the stream there.

2:58:25And I guess that leads to leads me to my

2:58:28um next point. So, one of the themes of

2:58:31Forward 2045 is to have clean air and

2:58:33water and I think this would I guess not

2:58:36help the clean water because we would be

2:58:38washing tire dust into the water.

2:58:41And then um while the plant has buffers

2:58:44so um my previous job was at John

2:58:46Deere's at the excavator excavator plant

2:58:48designing the excavators. Uh they tend

2:58:50to leak hydraulic oil and you have to

2:58:52constantly grease them and then there's

2:58:54always just grease on the machines. So,

2:58:56the other concern was the grease and the

2:58:58hydraulic oil would wash into the river

2:59:00no matter how much of a buffer you have

2:59:03something will I guess eventually leak

2:59:05through or you will have an accident of

2:59:07some kind.

2:59:09And then uh lastly on the clean air um

2:59:14So, this is a much larger [snorts] LCID.

2:59:16So, right now we have some like when

2:59:18it's dry there are some like light dust

2:59:20storms that come over from the current

2:59:22LCID next to us.

2:59:24But with this much larger one um my

2:59:26concern would be that there would be

2:59:27dust clouds and then they would kind of

2:59:30inhibit

2:59:32on the roads around us and we are also

2:59:33next to uh I-74. So, if the wind picks

2:59:37up and blows towards I-74 you might have

2:59:39the chance of a dust cloud.

2:59:41Um

2:59:43yeah, that's all I have. Thank you.

2:59:45>> DPO

2:59:47Someone would like to ask some questions

2:59:48or provide a rebuttal to that.

2:59:50>> I would like to provide a rebuttal to

2:59:52that.

2:59:55>> Hey, just just so you're clear this year

2:59:57is your opportunity to ask questions of

2:59:59him not

3:00:00>> just said that statement and I was just

3:00:01wondering if this is in standing concern

3:00:03with your review of any

3:00:06>> No, I'm just saying you can ask him

3:00:07questions now if you want to. You'll

3:00:09you'll have a chance to do a rebuttal

3:00:10later.

3:00:11>> Okay, so I can ask him questions.

3:00:13>> Yes.

3:00:13>> Okay. I don't have any questions.

3:00:16>> Okay.

3:00:16>> Okay.

3:00:17>> Are you the one who submitted the email

3:00:20complaint with regard to the character

3:00:22of the road service there?

3:00:25>> I don't think that was me.

3:00:27>> Okay.

3:00:29>> But we did submit a bunch of petitions

3:00:30to the planning board. I don't know

3:00:32where those went.

3:00:33>> And just to be clear, the board can't

3:00:35consider anything that was took place

3:00:37outside of this hearing. So, I mean,

3:00:39you've already presented what you wanted

3:00:41to present here.

3:00:43>> Okay. All right. Thank you.

3:00:45>> Did you get one of these?

3:00:51Yeah, could he get one of these cuz

3:00:53there's some pictures in there um when

3:00:55you talked about um

3:00:58the dust clouds, runoff,

3:01:01all those things and I

3:01:03I'm not an expert, but just kind of

3:01:05looking at that and

3:01:08I just wanted you to look at it and

3:01:10share your thoughts. Thank you.

3:01:14>> I'd like to ask Mr. Murphy a question.

3:01:19Does that road have a weight limit on

3:01:21it?

3:01:23>> Commissioner Lovelace, I have no earthly

3:01:24idea.

3:01:25That's not anything that's part of the

3:01:27planning analysis.

3:01:29I mean, I would assume it

3:01:30>> Well, reason I raised the question

3:01:32because he talked about weight of the

3:01:34trucks, dump trucks.

3:01:36>> I mean, again, you know, I can't speak

3:01:38>> That's not one of the findings, ain't

3:01:39it?

3:01:39>> That's not one of the findings and

3:01:40again, I can't speak to what I mean,

3:01:42obviously, I think every I don't know

3:01:44about roads, every bridge has a weight

3:01:45capacity.

3:01:47Um but I don't know what that would be

3:01:49if there are bridges on Watkins Ford

3:01:50Road, but you know, obviously,

3:01:53Mr. Boyles is already operating an LCID

3:01:55out here, so there are already existing

3:01:57trucks that are on Watkins Ford Road

3:01:59going to the existing LCID. I would

3:02:01suppose if it was an issue,

3:02:03NCDOT would have already done something

3:02:06about it.

3:02:07>> uh

3:02:09So, that's not one of the findings, but

3:02:11I was just trying to establish if what

3:02:14uh

3:02:17there are

3:02:18>> [clears throat]

3:02:20>> I think so- some roads have uh secondary

3:02:23roads have weight limits and it's posted

3:02:25as well as the

3:02:27uh

3:02:29bridges. That's what I was just trying

3:02:31to establish that. That's all.

3:02:36If it were

3:02:37>> [clears throat and cough]

3:02:39>> Well, I'll just stop there.

3:02:42>> So, could you Could you look on page um

3:02:46I think it's page

3:02:48document ID 44 on page one of seven.

3:02:54And there's a

3:02:56when you talked about the the

3:02:59downstream from the crossing, gentlemen

3:03:02described that, right?

3:03:05You One of you guys, I can't remember

3:03:07who it was, talked about how that

3:03:09downstream was coming.

3:03:11Where it was going.

3:03:12>> Th- That's right. So, yeah.

3:03:14>> And I see this on the picture

3:03:17that was given here.

3:03:19>> Okay. Okay, so these are the

3:03:20>> So, I'm I'm asking him like

3:03:25>> [laughter]

3:03:26>> Sure, it's page uh number seven. I think

3:03:28it's seven. It's in the back where the

3:03:30photos are.

3:03:31I just see that deep

3:03:34um

3:03:35downstream there.

3:03:37And I'm just wondering if that enough?

3:03:41>> Yes. So, these pictures are associated

3:03:44with the wetlands and stream assessment.

3:03:47>> Okay.

3:03:48>> And so, this is the condition of the

3:03:50site today.

3:03:51>> Right.

3:03:51>> Yeah. And and so, yes, I mean he he is

3:03:54basically looking at characteristics of

3:03:57the hydrology, the biology of the

3:03:59plants, the

3:04:00uh the moisture conditions in the soils

3:04:02in in a number of these pictures. And uh

3:04:05and yes, we would we would buffer this

3:04:07and it would be protected in the

3:04:09development of landfill and such that

3:04:11again, these streams will continue to

3:04:13operate as they were uh again in the

3:04:16development of landfill.

3:04:20>> Could I ask you what do you have any um

3:04:23I guess an opinion on terms of water

3:04:26runoff off of the asphalt that goes into

3:04:30us and draining ditches on both sides.

3:04:32And I understand part of that will end

3:04:33up draining into Abbot's Creek. Is

3:04:35that's the correct?

3:04:37>> So,

3:04:39um

3:04:40again, I'm I'm I'm not necessarily a

3:04:42traffic person. Uh however, we do

3:04:45develop a lot of these sites. We did

3:04:47speak to uh Winston-Salem DOT and NCDOT.

3:04:52And uh

3:04:53you know, as as we would

3:04:55gain a driveway permit into this site,

3:04:58usually that opens up additional

3:05:00discussions for DOT if other

3:05:02improvements need to be done other than

3:05:04the driveway. Our early discussions with

3:05:07uh

3:05:07both DOTs was it it the traffic wasn't

3:05:12substantial enough that it needed much

3:05:15more study.

3:05:18>> Well, if that were an issue if the uh

3:05:20hydraulics on specifically the highway

3:05:24that

3:05:24Mr. um

3:05:26Chairman's talking about is

3:05:30if there was uh restrictions in that

3:05:33regard by the uh DOT, there would be out

3:05:36there on 74 also because it's got uh

3:05:40>> Yeah.

3:05:40>> hundred more times traffic than Watkins

3:05:43Ford Road does.

3:05:44>> Yeah.

3:05:47>> Thank you.

3:05:47>> A- Any any other [clears throat]

3:05:48questions

3:05:51related to that?

3:05:52>> Well, I just wanted to just This is no

3:05:55questions, just a statement that I'm I'm

3:05:57reading from the staff report about the

3:06:00negative aspects of this proposal. And

3:06:04the gentleman has already talked about

3:06:06um the foot tail heel

3:06:08and how inconsistent that would be to

3:06:10the character of the area

3:06:14in addition to the Southeast precise

3:06:16area plan update and their

3:06:18recommendations um

3:06:20for this lot space.

3:06:23But nonetheless, I just wanted to share

3:06:25that.

3:06:26Thank you.

3:06:28>> Are there any any other

3:06:30comments that that basically from the

3:06:33opposing side that would like to be made

3:06:36before we offer a rebuttal opportunity?

3:06:39No other comments.

3:06:41Now we're at the

3:06:42rebuttal part and uh

3:06:45the proponent can actually

3:06:47present a rebuttal.

3:06:53>> Okay.

3:06:55To the question of the topography,

3:06:58um

3:06:59it is currently in cropland use and the

3:07:02basins that are on the image that are up

3:07:04on the screen

3:07:05uh all the water flows

3:07:07south and east with the exception of one

3:07:09small area. Uh there's a this plan and I

3:07:13I believe that Mr. Murphy had stated

3:07:14this in maybe a prior meeting that it

3:07:17looks

3:07:18there's a 100-ft buffer in here

3:07:21and but due to the size of the site

3:07:23itself is 70 acres that that looks very

3:07:25small, but 100 ft is is actually quite

3:07:28large. And if

3:07:30all the water is directed on the south

3:07:33side of Walkers Ford Road, when this

3:07:34construction happens, the buffer yards,

3:07:36the fencing, the berms, the diversion,

3:07:39it will all stay on the south side and

3:07:42go the direction the natural grade

3:07:44progression direction from

3:07:46the this point forward. There will be no

3:07:48no no misdirection or dumping of water

3:07:51in any direction that's toward the north

3:07:53or the the northwest or east or the west

3:07:56for that matter the topography is higher

3:07:58on this side and and it goes downstream

3:08:01downhill this this water comes from uh

3:08:04I-74

3:08:05and goes through the site and these

3:08:07buffers are 100 ft on each side so

3:08:09there's a 200 ft buffer there and it

3:08:11doesn't look very large and in

3:08:13comparison other site plans you may see

3:08:15but because the site plan is 70 acres

3:08:18Abbott's Creek is here in this area and

3:08:20our restricted areas on the floodplain

3:08:22floodways are back this far.

3:08:25So and the road impacts uh

3:08:27Watkins Ford Road I've lived on for

3:08:3130 years ish. Um there is no speed limit

3:08:34on Watkins Ford Road. There used to be a

3:08:37weight limit bridge here at Abbott's

3:08:39Creek. There was a construction

3:08:40approximately 10 years ago to replace

3:08:42that and the average uh on the roads

3:08:44that are not posted the gross vehicle

3:08:46weight ratings for those roads are

3:08:4880,000 lb. Uh no truck traffic that

3:08:50comes into our landfill exceeds that.

3:08:52Those are not our trucks. We do not own

3:08:54the the trucks that come in and out of

3:08:55our landfill but generally you have to

3:08:57have a permit from the state to do such.

3:08:59Um

3:09:00the traffic itself

3:09:02it is

3:09:04consistent has been consistent over the

3:09:069 years that we've been in operation.

3:09:08There's been no drastic uptick in the

3:09:10amount of volume that we have received.

3:09:12It has been very consistent. It was

3:09:14actually low in the beginning and in

3:09:15couple years in it's been very

3:09:17consistent since.

3:09:19This would only move that to a different

3:09:20location. It wouldn't add to it.

3:09:23>> I see what you're saying.

3:09:24>> And the small area of concern was where

3:09:27on the map can you show me?

3:09:29>> Small area of concern of what?

3:09:30>> said that there was one small area.

3:09:33>> Uh the small area that is currently uh

3:09:35water runoff is is right here.

3:09:38>> So was that near where they live?

3:09:40>> It it does not go the direction. There

3:09:42the topography if you look right here

3:09:43and if you look on a broader map you can

3:09:45look those up somewhere.

3:09:46The elevation, if you Mr. Limbo was

3:09:48asking, it

3:09:50it is almost even as far as elevation

3:09:53from sea level with the current

3:09:55subdivision [snorts] and the current

3:09:57topography of the field that this is in

3:10:00state.

3:10:02The the water goes to to

3:10:04a crosswalk is forward road and directly

3:10:06dumps into a on-site permanent pond that

3:10:09is on the the eastern side of this road

3:10:13of this entrance road. It never gets

3:10:15anywhere near

3:10:16the housing the houses at all for that

3:10:18development.

3:10:20>> Fair enough.

3:10:21>> Going back to the

3:10:23>> [clears throat]

3:10:24>> drainage the the uh

3:10:30I just try to

3:10:33Well, I think I know what But the the

3:10:35brown area on the east end down there

3:10:39is that the catch basin for the biggest

3:10:42part of the

3:10:43uh

3:10:45>> No, sir. That's That's the recycling

3:10:47area

3:10:47>> Okay. Okay.

3:10:48>> for leaves mostly.

3:10:50Um but currently the town of

3:10:52Kernersville brings all their their

3:10:54leaves uh

3:10:55to us to compost. And this is a sediment

3:10:59pond. This is a sediment pond. This is a

3:11:02sediment pond. And here's one as well.

3:11:04And like I said, I'll reiterate the

3:11:05whole point of due to the large scale of

3:11:08the site plan, these ponds are massive.

3:11:10They are large. They have done go

3:11:11through the hydraulics and all those

3:11:14things that were necessary in the plan

3:11:16to meet the county UDO specs and the

3:11:19state DEQ requirements for the ponds to

3:11:21catch all of the runoff from the site on

3:11:24and it's in multiple areas. And this

3:11:27this cannot be any further east due to

3:11:29the flood plain area floodway area.

3:11:31So, that that orange spot right there is

3:11:34only a small accessory recycling area

3:11:36for leaves.

3:11:37>> I didn't use the right term, but the

3:11:40sediment basin is what I was referring

3:11:42to a sediment basin and a catch basin.

3:11:45>> Yes, sir.

3:11:45>> I'll look look at it and see if there's

3:11:47a difference in it. I think they do the

3:11:49same thing.

3:11:51>> It's getting late and this is my last

3:11:53question, I promise. Um for the

3:11:56development, how many homes is in that

3:11:58development?

3:12:00>> 112.

3:12:01>> Okay.

3:12:02Thank you. That's all I had.

3:12:04>> Any further questions?

3:12:05>> One one brief question regarding the

3:12:07dust.

3:12:08You indicated that the present use is

3:12:11agriculture is it crop use, is it

3:12:13pasture?

3:12:15>> It is crop use. It was in pasture at one

3:12:17time.

3:12:18My property is is to the west. It's

3:12:20right here

3:12:21on this western edge of the fill area.

3:12:23It will remain

3:12:25the initial fill area will be this

3:12:27section on

3:12:29closest to I-74, furthest away from any

3:12:31residence.

3:12:33Like I like I stated previously, this

3:12:35entire area will not be disturbed at one

3:12:37time.

3:12:38This this will be phased. It goes

3:12:40through a phasing process with DEQ. So

3:12:42our disturbance areas are not

3:12:44you're not having a massive area of

3:12:46disturbance and having water run off and

3:12:48mud and silt go into Abbot's Creek.

3:12:50It and it will be remaining crop land.

3:12:53Likely in the future in the near future

3:12:55will be just grass and hay.

3:12:56>> Okay.

3:12:57Um

3:13:01Actually, that that's that's an

3:13:03interesting difference.

3:13:04For comparison,

3:13:06what's the current crop use?

3:13:08What current what

3:13:09>> Current crop use is is fallow at the

3:13:11moment. On this side back here, this was

3:13:13recently cleared

3:13:15and [clears throat]

3:13:16we planted wheat and had a wheat crop on

3:13:17it this calendar year.

3:13:19Uh

3:13:20this this particular section on this

3:13:21side had a wheat crop on it. And this

3:13:25area over here is currently planted in

3:13:26grass and my farm is planted in grass

3:13:29for hay.

3:13:30>> All right.

3:13:31Thank you.

3:13:31>> What is in You finished?

3:13:34>> Yes, thank you.

3:13:35>> [clears throat and cough]

3:13:36>> What is in the uh

3:13:38agriculture is under a different

3:13:40regulation USDA and so

3:13:44the regulation until

3:13:47you start using that other if whenever

3:13:50you first start taking out I don't know

3:13:53when that would be two acres is all he

3:13:55can open is that right Mr. Murphy?

3:13:59At one time?

3:14:03>> That's a state permitting I I'm not sure

3:14:05what the state permitting requirements

3:14:07are.

3:14:07>> Well, it's just a small amount but

3:14:09nevertheless uh

3:14:11it is

3:14:12long as it's in the agriculture part

3:14:14it's under those regulations but when he

3:14:16starts to use this then he's got to go

3:14:20over to all of those other regulations.

3:14:24>> Yes, that's correct.

3:14:36>> Any other questions?

3:14:41Righty. Oh, yes. Go ahead.

3:14:44>> Yes.

3:14:44>> I want to add I mean some of the the

3:14:46questions have been around operations

3:14:48and so as a as again his current

3:14:50operation has an operations manual

3:14:53that operations manual must meet a lot

3:14:56of criteria within the state rules

3:14:59that's probably referenced by rule in

3:15:01here but without getting exhaustive we

3:15:03didn't cover it but it includes not

3:15:05having an open area of debris of more

3:15:09than one acre before it has to be

3:15:11covered. Once you get past areas then it

3:15:14needs to be covered with more soil and

3:15:16then it'll it'll get seeded down to

3:15:19stabilize it. So again as he said it's a

3:15:21progression.

3:15:23You know, the areas get opened in cells.

3:15:27You know, at

3:15:28the the current rate Uh, you know, we

3:15:30project his site Probably has another

3:15:33five or so years. This site here will

3:15:35probably have 25 to 30 years. Uh, so

3:15:38again, it just stays on. Now, what

3:15:40drives the increase is is the homes.

3:15:44Right? And and again, as we continue to

3:15:46densify homes in our area, that is

3:15:49driving the need for for these things.

3:15:52Not only in the initial clearing and

3:15:53development, but also the continued

3:15:55maintenance of

3:15:57yards and and bushes and and all that

3:16:00sort of stuff. So, I think again, you

3:16:02know, we we do annual reports.

3:16:05Um, you know, there's there's storm

3:16:07water inspections that go on.

3:16:09Uh, he has his state inspections.

3:16:12Uh, there is requirements to keep dust

3:16:14down. Uh, there's requirements, again as

3:16:16he said too, on, you know, monitoring

3:16:18and managing the potential heat.

3:16:20Uh, there's discussions in the

3:16:22operations manual about when it's steam,

3:16:24when it's smoke, uh, you know, cuz

3:16:27again, I

3:16:28again, I

3:16:29I don't know if I've shared all this

3:16:30with him, but again, he did have that

3:16:31fire and he he resolved it fairly quick

3:16:35well quickly, you know? And that's

3:16:37really what we want to set the

3:16:38operations up and it's usually done by

3:16:40dirt, smothering it, not putting a lot

3:16:43of excess water, and uh, and Tanner's

3:16:45operation certainly has been very

3:16:47responsible.

3:16:50>> Righty.

3:16:52I declare that the public hearing is

3:16:54over. It's closed.

3:16:58Do we have motion?

3:16:59>> I do. Um,

3:17:01I move that the Board of Commissioners

3:17:02find that the proponent has proved the

3:17:05four required findings of fact based

3:17:08upon testimony presented in the hearing

3:17:12on July 30th, 2026,

3:17:15and that the special use permit attached

3:17:19here to and included in the agenda item

3:17:22be approved.

3:17:25>> I'll second that motion. Any discussion?

3:17:27>> Brief comment. Uh, I think the uh,

3:17:30petitioner has done a good job of

3:17:31responding to the concerns raised.

3:17:36>> Agreed.

3:17:38>> Other comments?

3:17:39>> Yeah, um I appreciate um all of the

3:17:42information today, but I

3:17:45more appreciate the citizens being here

3:17:48and you being able to verbalize for me.

3:17:51I'm not a subject matter expert, but at

3:17:53least I kind of um better understand

3:17:56what those other constituents are

3:17:58probably having to uh contend with. Um I

3:18:01didn't hear anything from them. I

3:18:03haven't received any emails.

3:18:05Nonetheless, I thank you for being here

3:18:06and your testimony today.

3:18:11>> All right.

3:18:12We're ready for item three.

3:18:16Um next item on the agenda

3:18:17>> We've got to vote.

3:18:18>> Oh, I'm sorry. We need to vote. We've

3:18:19got We have a motion, we have a second,

3:18:20we've had discussion. All in favor,

3:18:21please say I. I. Any opposed?

3:18:24>> No.

3:18:25>> We have one opposed. Motion carries six

3:18:27to one. [clears throat]

3:18:28Thank you all.

3:18:31Now, the next item on the agenda is a

3:18:33resolution recognizing August 2026 as

3:18:37National Emergency Management Awareness

3:18:39Month.

3:18:43August Burning coming forward. And who

3:18:46is reading this?

3:18:48>> Drew, I'm I'm

3:18:50>> Great.

3:18:51>> Okay.

3:18:51>> Thank you.

3:18:53Whereas emergencies and disasters,

3:18:55including natural, man-made, and

3:18:56technological, can occur unexpectedly,

3:18:59posing significant threats to life,

3:19:00property, and the environment. Whereas

3:19:02the Winston-Salem Forsyth County Office

3:19:05of Emergency Management, Forsyth County

3:19:07Emergency Managers across all sectors,

3:19:09community leaders, the North Carolina

3:19:11Division of Emergency Management, and

3:19:13the Federal Emergency Management Agency

3:19:15dedicate countless hours to developing

3:19:17preparedness, response, recovery, and

3:19:19mitigation programs to protect the lives

3:19:21and property of all persons living in

3:19:23the United States and US territories.

3:19:25Whereas emergency managers across the

3:19:27United States and US territories are

3:19:29charged with establishing and

3:19:30maintaining the capabilities necessary

3:19:32to effectively direct, coordinate, and

3:19:34support emergency and disaster response

3:19:37and recovery efforts. And whereas the

3:19:39efforts of our nation's emergency

3:19:41managers have helped millions of

3:19:42community members across the United

3:19:44States recover, rebuild, and become more

3:19:45resilient in the face of adversity. Now,

3:19:48therefore, be it resolved that the

3:19:50Forsyth County Board of Commissioners

3:19:52hereby recognizes August 20, 2026 as

3:19:54National Emergency Management Awareness

3:19:56Month in Forsyth County and encourages

3:19:59all citizens to express their sincere

3:20:00appreciation for emergency managers in

3:20:02every sector who work diligently to

3:20:04prepare, protect, and serve our clients,

3:20:07county, states, tribes, territories,

3:20:09regions, and organizations against all

3:20:11hazards and risk. Adopted this 30th day

3:20:14of July, 2026.

3:20:16>> Second.

3:20:17I have second. Um any discussion? All in

3:20:19favor, please say

3:20:20>> Aye.

3:20:20>> Aye.

3:20:21>> Any opposed? Motion carries unanimously.

3:20:23And

3:20:24August, we'd be happy to hear from you

3:20:26and thank you for being here for just a

3:20:28a few hours.

3:20:28>> Uh thank you very much and good evening,

3:20:30everyone. And so, I'll just say thank

3:20:32you for the proclamation.

3:20:34Uh very quickly, uh the Office of

3:20:36Emergency Management is the local agency

3:20:38responsible for planning and

3:20:40coordinating our community's response to

3:20:42disasters

3:20:43uh and large-scale emergencies. These

3:20:46include natural disasters, man-made

3:20:48disasters, and technological disasters.

3:20:51Uh we do this by working with all our

3:20:53local partners, which includes local,

3:20:55municipal, regional, county, state,

3:20:58federal, nonprofits, and private

3:21:00institutions.

3:21:01Uh one example of that, obviously, is

3:21:03over the past 48 hours,

3:21:05our team has been doing that that

3:21:06mission by uh assisting with the large

3:21:09water main disruption.

3:21:11Uh our office is a very small team of

3:21:13only five individuals, including myself.

3:21:16Uh we typically work behind the scenes

3:21:18and out of the public side.

3:21:20Our office accomplish this mission

3:21:23by conducting training exercises,

3:21:25planning, grants, public education, and

3:21:27responding to incidents

3:21:28uh 24/7 365.

3:21:31So, I think personally the proclamation

3:21:34is an excellent way to get the word out

3:21:36on what our team does and what our

3:21:37mission is.

3:21:39And with that, I just want to say that I

3:21:41I think I'm here to accept the

3:21:42proclamation on behalf of my small team

3:21:45who were unable to be here this evening

3:21:48because of ongoing events and incidents.

3:21:51Uh so, again, thank you uh for the

3:21:53opportunity to be here and and greatly

3:21:54appreciate the proclamation.

3:21:57>> August, we appreciate what you do. Were

3:21:59you close to having to responding to a

3:22:01man-made disaster that we had yesterday?

3:22:04>> Uh we're still responding,

3:22:06but things are improving.

3:22:08>> Oh, that's a

3:22:09very difficult thing. A lot of people

3:22:10have have had probably not a lot of

3:22:12sleep in the last uh

3:22:14couple of couple days, actually. So,

3:22:15thank you for that.

3:22:17>> Well, and also real quickly, I want to

3:22:19several other county agencies and

3:22:21departments

3:22:22and and quite a few, actually, have been

3:22:24assisting in this response. So, I just

3:22:26wanted to put that information out.

3:22:28>> Thank you.

3:22:29>> Thank you.

3:22:34Okay.

3:22:52>> [applause]

3:23:00>> All righty.

3:23:08I just found the attachment that I need

3:23:11Sorry, I'm still not quite there.

3:23:18Well, let me get to it.

3:23:25Next we have a resolution supporting the

3:23:27designation of North Carolina Highway 67

3:23:30Yadkin River Bridge as the Jimmy R.

3:23:32Hutchens and Joe C. Matthews Bridge. Um

3:23:36and I actually do have just for those of

3:23:39you do not know anything about the those

3:23:41two particularly, I did want to mention

3:23:44their names and tell you a little bit

3:23:45about them. As I think I indicated on

3:23:48Monday,

3:23:49um I was approached from the

3:23:51Yadkin County Commission chair

3:23:54um actually have this to to consider

3:23:56this proposal.

3:23:58Um they've already adopted it and I'll

3:24:00tell you a little bit about Jimmy

3:24:01Hutchens Um he actually just died 1999.

3:24:07And Jimmy Hutchens served as the

3:24:08executive director of the Yadkin Valley

3:24:10Economic Development District um from

3:24:131971 until his death in early 1999.

3:24:17In nearly three decades of innovative

3:24:19leadership, he transformed a modest

3:24:21community action agency into a

3:24:24multi-county institution delivering

3:24:26weatherization, transit, workforce

3:24:29training, senior services, and historic

3:24:32preservation across Yadkin, Surry,

3:24:35Stokes, Davie, and surrounding counties.

3:24:38He's done a number of other things

3:24:41um but particularly has been very active

3:24:43in Yadkin County.

3:24:45Um Joe Matthews, Joe C. Matthews um

3:24:49he was born 1932 and died 1997.

3:24:53And basically he was the person who got

3:24:56the initial federal grants um compiled.

3:25:00He compiled all the technical proposal

3:25:02filings to get federal matching dollars

3:25:04for highway connectivity, safety

3:25:07expansions, and rural secondary bridge

3:25:10upgrades throughout the Northwest

3:25:13Piedmont including infrastructure along

3:25:16the North Carolina 67 Corridor. So, he

3:25:19was he was in our sort of predecessor of

3:25:21the Northwest Piedmont um

3:25:25Council of Governments.

3:25:26Um we used to be a part of that when it

3:25:28was Northwest Economic Development

3:25:30Commission.

3:25:31And now we have we are now associated

3:25:33with Piedmont Triad um regional

3:25:36consortium. So, um he was very active in

3:25:40a number of issues uh

3:25:42throughout the Northwest. Both of them

3:25:45have relationships to infrastructure and

3:25:47bridges. So, I I would entertain a

3:25:51motion to approve um the naming of the

3:25:53bridge of the across the connect Yadkin

3:25:56and Forsyth County uh the Joe Matthews

3:25:59and Jimmy Hutchins Bridge.

3:26:02>> Move for approval.

3:26:04>> Motion approved by uh Commissioner

3:26:05Wizznant, second by Commissioner Bessie.

3:26:07Any discussion?

3:26:08>> I have a

3:26:09question about um the resolution

3:26:12supporting the designation.

3:26:15Does that mean Forsyth County has some

3:26:17say so in that designation or we're just

3:26:20supporting their recommendation to

3:26:23designate that bridge after those

3:26:25individuals?

3:26:26>> As I understand it, both counties that

3:26:30where the bridge connects between Yadkin

3:26:33and Forsyth have to adopt exactly the

3:26:36same language in order for it to be I

3:26:40guess it goes to it's an application

3:26:42that goes with a resolution to DOT to go

3:26:45through a naming process. I think that's

3:26:47accurate.

3:26:51>> Thank you.

3:26:54>> Um any other discussion? All in favor,

3:26:56please say I. I. Any opposed? Motion

3:26:59carries unanimously.

3:27:02Um all righty.

3:27:04And number five is a proclamation

3:27:05recognizing the accomplishments Oh, we

3:27:07don't need to do that. We already did

3:27:08that. I'll skip over. Resolution

3:27:09declaring intent of the County of

3:27:11Forsyth, North Carolina to participate

3:27:13in the commercial property assess

3:27:15capital expenditure program.

3:27:22Someone reading that or we just act on

3:27:23that?

3:27:24>> I think Mr. Chairman, you just act on

3:27:25it.

3:27:25>> Yeah, I'm over approval. A motion from

3:27:28uh

3:27:29Vice Chairman Wilson I'd be happy to

3:27:31second that. Any discussion?

3:27:34All in favor, please say I. I. Any

3:27:36opposed? Um motion carries unanimously.

3:27:41And finally, the minutes for me.

3:27:43Um do we have approval of the minutes

3:27:45for the meetings of June 25th and July

3:27:489th, 2026?

3:27:51>> So moved.

3:27:51>> Motion approved by Commissioner Bessie.

3:27:53Is there a second?

3:27:54>> Second.

3:27:55>> Seconded by uh Commissioner McDaniel.

3:27:57Any discussion?

3:27:58All in favor, please say I.

3:28:00>> I.

3:28:01>> I. Pleased to turn the rest of meeting

3:28:03over to uh

3:28:04>> Public session.

3:28:06>> We don't gosh, we need a public session.

3:28:08I have misplaced my

3:28:10I had it here cuz I was looking for the

3:28:12bridge information.

3:28:14Thank you. We have this is This is an

3:28:16opportunity for anyone from the public

3:28:17who has signed up and Madam uh

3:28:20Clerk, do we have any cards or

3:28:22telephones?

3:28:23>> We don't have any telephone calls, but

3:28:24we have some speaker cards. And I think

3:28:26several have left, so we're going to go

3:28:28through these pretty quickly.

3:28:30First speaker is Anna Brodsky.

3:28:35Okay.

3:28:36We'll skip her.

3:28:40Elizabeth Burns.

3:28:43Yes, ma'am. Please come forward.

3:28:45>> State your name and address for the

3:28:46record.

3:28:53My name is Elizabeth Burns. I live at

3:28:554671 Forest Manor Drive in Clemmons,

3:28:59North Car- Actually, it's a

3:29:00Winston-Salem mailing address, but it's

3:29:02Clemmons.

3:29:03Uh I'm the Lone Ranger from the Clemmons

3:29:06group. Um I appreciate your longevity

3:29:09here and your

3:29:10patience.

3:29:11Um coming to

3:29:13talk to you about 6010

3:29:16Gun Club Road.

3:29:18And that's in Winston-Salem.

3:29:20On that road, it is commercial. It is

3:29:23zoned commercial.

3:29:25We have Golden Foods. They manufacture

3:29:27sausages. We have Salem Fabrication

3:29:30Technologies Group, and they distribute

3:29:32fabrication tooling, supplies, and

3:29:34machinery.

3:29:35We have A1 Clemmons Mini Storage. And

3:29:38Innovia Films uh America, they do

3:29:41plastics for shipping and wrapping and

3:29:44things like that.

3:29:45And then on Kenneman Road, we have Joyce

3:29:47Farms. That's a food processing plant.

3:29:50Um

3:29:51Clemmons Gymnastics Center, Creative

3:29:53Drama Children's Theater, uh Holly Tate

3:29:56Fine Catering, and there's a few other

3:29:58smaller businesses kind of interspersed

3:30:00throughout that.

3:30:03And then we have a proposed asphalt

3:30:05plant.

3:30:08Gun Club Road is very narrow.

3:30:10The ingress egress uh right next to the

3:30:13bridge that is slated to be replaced

3:30:15next year. Uh but even before that, it's

3:30:18pretty precarious when you're coming

3:30:19over that bridge and something coming

3:30:21out of Gun Club Road. Gun Club Road is a

3:30:23very narrow road.

3:30:25Um

3:30:28Behind Gun Club Road, as the crow flies,

3:30:33there are hundreds and hundreds of

3:30:35residential homes, single-family homes.

3:30:38Right across the I-40 bridge, you've got

3:30:41a very large Catholic church.

3:30:43You have numerous uh residential areas.

3:30:47You've got apartments, you've got

3:30:48townhouses.

3:30:50Um

3:30:51in addition to small little um

3:30:54patio home communities.

3:30:56Like I said, we're talking about

3:30:57hundreds of families.

3:30:59Just beyond that, there's an out patient

3:31:01out patient surgical facility. Little

3:31:03bit beyond that, there are two large

3:31:05medical facilities.

3:31:07Now, I do understand that Gum Club Road

3:31:09is, as I said, zoned commercial GI,

3:31:12general industrial.

3:31:14And it was zoned that many, many, many,

3:31:16many years ago. So, I get that. But,

3:31:19what we're being told by the leadership

3:31:21in Klemons, there's nothing we can do.

3:31:24As a citizen of the United States of

3:31:26America, I do not accept that. That is

3:31:29unacceptable.

3:31:31Um

3:31:32considering this plant going in, again,

3:31:35as I said, hundreds of families being

3:31:37affected, uh a number of businesses that

3:31:40cater to children,

3:31:41uh

3:31:42food processing plants,

3:31:44I think it's not just a disregard to

3:31:47allow this to go in, but an actual

3:31:49disrespect of the people in that

3:31:52community, of which I'm one, and only

3:31:54since December. I moved here from New

3:31:56Hanover County

3:31:57to avoid a lot of things, and now we're

3:31:59faced with this.

3:32:02Um

3:32:05The only thing I can really say is

3:32:07whoever decides the final they've

3:32:09applied for their air quality permit,

3:32:11Maymead.

3:32:13At the end of the day, whoever decides

3:32:15that this can go through,

3:32:17y'all get to go home

3:32:19and enjoy the peace and quiet of your

3:32:20home. It's a done deal, you probably

3:32:23wouldn't think about it again. I

3:32:24wouldn't if I were you.

3:32:26But, the rest of us go home after that

3:32:28decision is made, 24/7, 365

3:32:32days a year, we get to smell it,

3:32:35we get to hear it,

3:32:37and we get to be affected by it.

3:32:39Gone will be all the I couldn't count

3:32:42how many little gardens are in the

3:32:43backyards of the people in the

3:32:44neighborhood. Swimming pools. I wouldn't

3:32:47allow my child I wouldn't get in the

3:32:48swimming pool with the particulates that

3:32:51are put out from an asphalt plant.

3:32:54We're not as a lot of people said

3:32:56earlier, we're not anti-growth,

3:32:59we're not anti-business, we're not

3:33:01anti-asphalt company, but there are many

3:33:03other commercial sites that would be

3:33:05better suited for Maymead.

3:33:08Um

3:33:09I don't know that they're even aware of

3:33:10what they're coming into in the

3:33:11residential area. But I would encourage

3:33:14somebody to look at this and I mean is

3:33:16there even any way we could speak with

3:33:18or you could speak with Maymead, even

3:33:20offer some tax incentive to look at

3:33:22another parcel.

3:33:23>> Yeah, our

3:33:24Two three minutes are up.

3:33:26And

3:33:26>> [clears throat]

3:33:27>> I don't know I know where you're talking

3:33:28about and I know where it is, but you

3:33:29might just be able to speak to this

3:33:31gentleman over here. He might know a

3:33:32little something about it. Do you know

3:33:33something about it?

3:33:36>> It's in the village of Clemmons.

3:33:37>> Oh, so it's not still

3:33:39>> It's in Clemmons zoning jurisdiction.

3:33:41It's GI. Clemmons allows a an asphalt

3:33:44plant

3:33:45with a permit issued by

3:33:49us, but we that's because they contract

3:33:52with us.

3:33:53So, they have to get a air quality

3:33:55permit. We're one of I think two

3:33:59local jurisdictions in the state that

3:34:00issue their own air quality permits. So,

3:34:02they'll have to apply for an air quality

3:34:03permit through Forsyth County, but then

3:34:05if that air quality permit gets issued

3:34:07and they apply for a

3:34:10permit to build an asphalt plant because

3:34:13it's existing GI, we would have to issue

3:34:15the permit.

3:34:16And it's based on Clemmons' zoning.

3:34:21>> But the air quality permit will come

3:34:22here.

3:34:23>> I understand that.

3:34:25>> I I

3:34:26>> Okay.

3:34:26>> Just appreciate that clarification cuz I

3:34:28was a little lost, but

3:34:29>> So, there's nothing we can do.

3:34:31>> I thought there were several permits

3:34:33required for an asphalt plant. Um and

3:34:37what is the current status of their

3:34:40petition?

3:34:41>> Nothing's been submitted to us. I can't

3:34:43speak to air quality. Again, I'm sure

3:34:45there are other state and federal

3:34:46permits they have to get. I'm speaking

3:34:48solely about the land use aspect of it

3:34:51because the land is owned GI and the

3:34:54Clemson's unified development ordinance

3:34:56allows an asphalt plant with a Z. And

3:34:59whenever something's in the table as a

3:35:00Z, that means they go to the person that

3:35:02issues the construction permit to get

3:35:05the permit approved. But of course,

3:35:06yeah, they would have to do whatever

3:35:08local, state, and federal air quality,

3:35:10environmental quality, those type of

3:35:12permits, they would have to get those as

3:35:13well.

3:35:14But from a

3:35:16permit issuance standpoint,

3:35:18if they brought in an application for an

3:35:20asphalt plant and it met all the

3:35:22requirements in the Clemson's UDO, we

3:35:23would have to issue that permit.

3:35:26>> Okay.

3:35:26>> Noise is one of them.

3:35:30>> Thank you. We kind of went a little

3:35:31little further beyond in in discussing

3:35:34this from from a public comment

3:35:35standpoint, but if you'd like to say one

3:35:37word,

3:35:37>> Just one one question. Um

3:35:40does our

3:35:43Department of Environmental Quality

3:35:44issue the air permit?

3:35:47>> Yes, sir. They do review the permit and

3:35:49issue the permit.

3:35:50>> And if they

3:35:52that is a departmental decision, not a

3:35:54board decision. Is that correct?

3:35:56>> Yes, sir. That's correct. They're Yeah.

3:35:58>> And if if there is a if there are public

3:36:00comments on that, that would go to the

3:36:03to the department.

3:36:04>> Yes, sir.

3:36:04>> And then if there were an appeal

3:36:07on

3:36:08you know, whatever grounds are are

3:36:10permissible,

3:36:13where would the appeal go? Um

3:36:15superior court?

3:36:17Um the state EPA?

3:36:19>> I would say they have their own board

3:36:21that handles those, but if that um

3:36:25if it went beyond that, it would depend

3:36:27on what the actual permit is. We we

3:36:30could certainly have minor speak to

3:36:32that, but it's

3:36:34the issue that was brought

3:36:36before you today is really a Clemens

3:36:38issue.

3:36:39>> Yeah.

3:36:39>> Um it's whether or not it meets the air

3:36:41quality permit is not

3:36:44really um

3:36:45one where there's a lot of discretion.

3:36:47It's very much, you know, technical.

3:36:49>> Yes.

3:36:49>> So you but it would not come before this

3:36:51board, the Board of Commissioners.

3:36:53>> That that I just wanted to know the

3:36:56to to whom to refer the the citizen and

3:36:58that would be

3:36:59um DEQ and the processes there and they

3:37:02could inform me about that.

3:37:06Thank you.

3:37:08Do we have any other

3:37:13Do you have other cards?

3:37:16>> I'm glad I'm not the only one.

3:37:18>> Yeah.

3:37:19>> Yeah, we're all half asleep.

3:37:24>> Daphne Pace

3:37:28Walter Vaughn

3:37:32>> Please come forward state your name and

3:37:34address for the record.

3:37:38>> If I put something on here will show

3:37:39everyone behind me?

3:37:42Oh, good.

3:37:43This is Walter Vaughn, 393 Bagly Springs

3:37:46Road in Ronda, North Carolina.

3:37:48I'm here to discuss a matter of the

3:37:50Constitution.

3:37:52They say ignorance of the law is no

3:37:53excuse and after I get done today there

3:37:55will be no excuse.

3:37:57The Bible simply says to correct,

3:37:58rebuke, and teach.

3:38:00You're supposed to go before your

3:38:01brother if you have a concern, a

3:38:03grievance. So today we're going to lay

3:38:05out the grievance.

3:38:06We've already laid it out three times in

3:38:08Wilkes and we're moving into the lawsuit

3:38:09section.

3:38:10I am in no way threatening.

3:38:13I'm just talking about the Constitution.

3:38:16Hopefully everyone can see Article 1

3:38:18Section 8.

3:38:19I'm going to read it once.

3:38:22Probably won't catch it, but I'll read

3:38:23it a few more times. The people of this

3:38:25state shall not be taxed or made subject

3:38:27to the tax or payment of any impost or

3:38:29duty without the consent of themselves.

3:38:34That's the first part.

3:38:35Or their representatives in the General

3:38:37Assembly, that's the second part. And

3:38:40this is the catch to the General

3:38:41Assembly.

3:38:42Freely they give.

3:38:44If I freely give it, I can freely take

3:38:45it away.

3:38:47Now, my next one I want to bring up.

3:38:51We go back to the Declaration of

3:38:52Independence, right?

3:38:55This is our founding fathers.

3:38:57The 13 colonies, the people that wrote

3:39:00the Declaration of Independence. This is

3:39:02how I can tie it to history.

3:39:04It says right here,

3:39:06"For imposing taxes on us without our

3:39:09consent."

3:39:11So, I've just laid out foundational

3:39:13history.

3:39:15And I want you to understand

3:39:19that when I read this again, you

3:39:20probably still won't catch it.

3:39:23But right now, we're looking at legal

3:39:24lawsuits against our commissioners. Why?

3:39:29Cuz I'm going to read this one more

3:39:29time, and I'm going to see if you guys

3:39:31catch it. "The people of this state

3:39:32shall not be taxed or made subject to

3:39:34the payment of any impost or duty

3:39:37without the consent of themselves or

3:39:38their representatives in the General

3:39:40Assembly freely given."

3:39:43Most people in this room didn't catch

3:39:44it.

3:39:45Maybe not even the lawyers. The lawyers

3:39:48will tell you that that the Machinery

3:39:50Act gives you authority. Machinery Act

3:39:52is a light switch. You flip it on and

3:39:53off. Somebody has to flip it on and off,

3:39:55right? For it to work.

3:39:57They'll say, "Well, Article 5 gives us

3:40:00authority."

3:40:01Sorry, guys. Your Declarations of

3:40:03Rights, Article 1, was created first in

3:40:06North Carolina. Everything hangs on one.

3:40:10Just like the Bible,

3:40:11all the commandments hang on two.

3:40:14I'm not going to read it anymore. I'm

3:40:15simply going to tell you.

3:40:18You see commissioner under the chain of

3:40:21command in Article 1, Section 8 at all.

3:40:24I I myself. I see representative.

3:40:28I don't see any of you guys there.

3:40:31Now, under statute 153A,

3:40:34you guys are dealing with Raleigh. You

3:40:36and Armor Raleigh.

3:40:39And if you don't have anything on the

3:40:40books,

3:40:41which I already know you don't.

3:40:43My county doesn't.

3:40:45It says that you got authorization from

3:40:47Raleigh

3:40:48to tax people on their property,

3:40:51guys are all on the fence.

3:40:54First First issue is deprivation of

3:40:57rights.

3:40:58You denied me of my right.

3:41:00You didn't allow me to consent.

3:41:02The second one is treason.

3:41:05Under the Declaration of Independence,

3:41:09this

3:41:10was an act of war.

3:41:12Our founding fathers wrote it is an act

3:41:14of war.

3:41:16And And when you talk about an act of

3:41:19war against the state,

3:41:21when you look up the definition of

3:41:23state, what is the state?

3:41:25It's the people.

3:41:27So, I appreciate your time.

3:41:29I just want you to know this is the

3:41:30first notice.

3:41:31Read your Constitution.

3:41:33Don't listen to the lawyers.

3:41:35It's like our lawyer said,

3:41:37Raleigh has all authority.

3:41:39>> Thank you.

3:41:40>> You guys have any questions?

3:41:42>> No.

3:41:43>> Appreciate it.

3:41:47>> The next speaker is Chelsea Mullins.

3:41:53Mike Beresey.

3:41:56Please come forward and state your name

3:41:57and address for the record.

3:42:03>> My name is Mike Beresey. I live in 3331

3:42:06Hilly Drive.

3:42:08First of all, I want to thank um

3:42:12Denise Price for her swift action

3:42:15to my dilemma a couple of months ago.

3:42:18Okay?

3:42:19Hey, you, sir. I want to thank you for

3:42:22making me who I am.

3:42:24Um

3:42:27we exchanged emails

3:42:29in the beginning.

3:42:31And um

3:42:33I

3:42:34said I had a proposal to do.

3:42:37And um

3:42:39you said, "Well, bring it to the board."

3:42:41And I told you I I don't know. I I was

3:42:44scared.

3:42:46And then you said, "Well, you can do

3:42:48it."

3:42:50That's what you said.

3:42:52Um

3:42:53so that led me

3:42:56to stand up here, make my proposal, and

3:42:59that led me to do other things in my

3:43:02life that I was scared to do.

3:43:04I had you in my mind, in my head,

3:43:07saying, "You can do it."

3:43:11For me going forward

3:43:13to better myself

3:43:15you will be there saying, "You can do

3:43:18it."

3:43:20I appreciate you.

3:43:22And you will be missed

3:43:24by me.

3:43:27Um

3:43:28thank you for doing that for me. Thank

3:43:31you for encouraging me to go forward

3:43:34and be a better part

3:43:38of myself.

3:43:40Okay. Um

3:43:43as far as um

3:43:46this board being intimidated

3:43:49you all know that I do not like

3:43:52people to intimidate my elected

3:43:54officials.

3:43:56Okay?

3:43:57I am I was opposed to the data center.

3:44:01And somebody in this uh you said

3:44:04you was intimidated because you was for

3:44:08it.

3:44:11Or something similar to that in

3:44:13Facebook, something like that.

3:44:15Um

3:44:17don't let anybody intimidate you.

3:44:20Stand your ground.

3:44:24If you are for something,

3:44:26okay. If you're against something,

3:44:30okay.

3:44:32I am for each and every one of you.

3:44:36Because you're are our elected

3:44:39officials.

3:44:43Sir,

3:44:44your legacy will live on in me.

3:44:48Thank you very much.

3:44:50>> Thank you.

3:44:57>> The next speaker is Foothill Sierra

3:44:59Club.

3:45:05Not a name on that one.

3:45:09Jane Stegner.

3:45:14Sunny Chin.

3:45:17Rhonda Maze.

3:45:19Marci West.

3:45:21Please come forward and state your name

3:45:23and address for the record.

3:45:26>> Thank you, commissioners. I know it's

3:45:28late. Um, Marci West, 331 Carolina

3:45:31Circle, Winston-Salem, and I'm also a

3:45:33candidate for county commissioner,

3:45:34District B.

3:45:36Um, I just wanted to talk a little bit

3:45:37about the data center and the work that

3:45:39was done by the group here. There was a

3:45:41suggestion made that this was a

3:45:43coordinated misinformation campaign, and

3:45:46I can assure you it absolutely 100% was

3:45:49not.

3:45:50The organization of folks in rural Hall

3:45:53was such an amazing group of liberals

3:45:56and conservatives, men and women,

3:45:59professionals,

3:46:01workers, tradesmen, retired people,

3:46:04all different types of people who came

3:46:06together,

3:46:08and they they all researched in great

3:46:12detail the impacts of data centers. They

3:46:16looked at the sound impacts. They looked

3:46:19at the pollution impacts. They looked at

3:46:21the health impacts, the risks of leaks.

3:46:24They looked at how close it was to their

3:46:26houses.

3:46:28Amazingly close. Um, I know that the

3:46:31Maiden data center was mentioned as a

3:46:33comparison and that Maiden data center

3:46:35is much much has much more land, much

3:46:40larger buffers,

3:46:42had had berms around it,

3:46:45much

3:46:46and much lower. So, when you look at the

3:46:48higher level, I mean, 85-ft buildings,

3:46:52hundreds of feet away from residences,

3:46:54it's just not at all conceivable. Um,

3:46:57and and then there's been this

3:46:59discussion about, "Well, then you're

3:47:00going to have a bunch of small houses."

3:47:02Well, I can tell you that the folks in

3:47:04Roll Hall that we're meeting

3:47:07are not opposed to development. What

3:47:09they really would like is a mixed-use

3:47:11development that has housing and has

3:47:13commercial that they can go and walk to.

3:47:16They can have as a community center.

3:47:18They're actually quite excited about

3:47:19that opportunity. They even agreed that

3:47:21if it was a 350 houses, that would be

3:47:24better than a data center in terms of

3:47:26how it would impact their daily lives.

3:47:28So, I just wanted to say that that was

3:47:31it just was amazing. I've never seen a

3:47:34group of people who did not know each

3:47:36other before pull together so closely.

3:47:38And so, I I thank those of you who are

3:47:40willing to listen

3:47:42uh to those folks um and and uh

3:47:45and hear their concerns. I also wanted

3:47:49to on a completely different subject

3:47:50just thank Don Martin for his service to

3:47:53the community. You've worked for many

3:47:55many years. You've provided a lot of um

3:47:59really good thoughtful impact uh as

3:48:02you've made your decisions. I have not

3:48:04always agreed with those decisions, but

3:48:06I I do appreciate the fact that you've

3:48:09brought your expertise to the community.

3:48:11I think it's a little bit sad that

3:48:13you're not going to be here for the

3:48:14final 5 months of your 12-year term, and

3:48:17I do think that we actually will miss

3:48:19your expertise in those 5 months. But, I

3:48:22wish you well in your retirement. So,

3:48:23thank you very much.

3:48:32>> Now,

3:48:33turn the meeting over to the county

3:48:35manager.

3:48:36>> Thank you, Mr. Chair, and good evening

3:48:38again, commissioners, staff, and guests.

3:48:40The agenda items before you have been

3:48:41briefed and hopefully questions

3:48:43answered. Agenda item number eight is a

3:48:45resolution of the Board of Commissioners

3:48:47of the County of Forsyth, North

3:48:48Carolina, authorizing the negotiation of

3:48:50an amendment to an installment financing

3:48:52contract, directing the publication of

3:48:54notice with respect thereto, and

3:48:56providing for certain other related

3:48:58matters thereto. In an amendment to the

3:49:00fiscal year 27 budget ordinance to

3:49:02transfer funds to the county capital

3:49:04projects ordinance to pay cost of

3:49:06issuance related to the 2026 limited

3:49:08obligation bonds, and an amendment to

3:49:10the county capital projects ordinance to

3:49:12appropriate proceeds from the 2026

3:49:14limited obligation bonds in a room

3:49:16financing into the budget reserve for

3:49:18future capital projects, and to

3:49:19appropriate the transfer from the

3:49:21general fund to pay cost of issuance.

3:49:23Essentially, item eight is a resolution

3:49:25that authorize authorizes the

3:49:27negotiation of an amendment to the

3:49:28county's existing 2021 installment

3:49:31financing contract in order to finance

3:49:34up to 26 million 850,000 dollars of

3:49:37interim limit limited obligation bonds

3:49:39for county capital projects as detailed

3:49:41in the fiscal year 27 capital

3:49:43improvement plan. The resolution also

3:49:46authorizes the application to approve

3:49:48the financing with the local government

3:49:50commission, and to retain bond counsel

3:49:52and financial advisory services. It also

3:49:55calls for a public hearing on August

3:49:5713th, 2026 with regard to this

3:50:00financing, and allows the county to

3:50:02reimburse any expenditures tied to the

3:50:03finance projects that may be incurred

3:50:06before the financing contract is

3:50:07executed. And B is an amendment to the

3:50:0927 budget ordinance to appropriate

3:50:11$135,000

3:50:13of general fund dollars originally

3:50:15appropriated for debt service for the

3:50:162026 limited obligation bonds and

3:50:19transfers them to the county capital

3:50:21projects ordinance to pay for the cost

3:50:22of issuance. And finally, C is an

3:50:24amendment to the county capital projects

3:50:26ordinance to set aside proceeds from the

3:50:2726 limited obligation bonds for future

3:50:30capital projects and to appropriate the

3:50:32transfer from the general fund to pay

3:50:34for the cost of issuance.

3:50:36>> Move approval.

3:50:37>> Motion approved by Vice Chair Whisenant.

3:50:39Do we have a second?

3:50:40>> Second.

3:50:40>> Second by uh Commissioner Wilson. Any

3:50:43discussion?

3:50:45All in favor, please say I. I. Any

3:50:47opposed? Motion carries unanimously.

3:50:49>> Agenda item number nine is an amendment

3:50:51to the county capital projects ordinance

3:50:52to appropriate SKIF interest earnings to

3:50:54the airport element. This item

3:50:56appropriates $1,916,168

3:51:00of interest earnings for the 4001 North

3:51:02Liberty project for a contract with

3:51:04Hoffman Building Technologies to replace

3:51:06the building automation controls.

3:51:09>> Do we have a motion?

3:51:10>> Move approval.

3:51:11>> Motion approved by Vice Chair Whisenant.

3:51:12Second?

3:51:13>> Second.

3:51:14>> Second by uh Commissioner um Wimberly.

3:51:17Any discussion?

3:51:18All in favor, please say I. I. Any

3:51:21opposed? Motion carries unanimously.

3:51:23>> Agenda item

3:51:24>> I actually have a suggestion. Could you

3:51:25take 10 through 14? They're all Quantum

3:51:29Meruit

3:51:30uh issues and we heard the details of of

3:51:33those, I guess, on Monday. And I would

3:51:35suggest we just take them all together.

3:51:37>> Sure.

3:51:38>> there were six Quantum Meruits, but

3:51:41>> Yeah.

3:51:41Okay, agenda item number 10 is a

3:51:43resolution authorizing the Quantum

3:51:45Meruit payment to Novant Health Employer

3:51:47Solutions LLC doing business as Novant

3:51:49Health Occupational Medicine in the

3:51:51amount of $247,000

3:51:54I'm messing up to a $247, I'm sorry, and

3:51:5750 cents for services rendered during

3:51:59May and June 2026 for the Sheriff's

3:52:02Office for drug screenings for

3:52:03applicants.

3:52:05I I need to double-check that number.

3:52:06Double-check that number for me, Denise,

3:52:08please. Agenda item number 10. We're

3:52:09going to go to 11. Um resolution

3:52:11authorizing quantum meruit payment to

3:52:13Brodart Company in the amount of

3:52:15$4,601.25

3:52:18for the purchase of fiction and

3:52:19non-fiction books during fiscal year

3:52:21ending June 2025. And 12 [snorts] is a

3:52:24resolution authorizing quantum meruit

3:52:25payments to Matrix Health and Safety

3:52:27Consultants LLC in an amount not to

3:52:30exceed $4,580

3:52:32for risk assessments of lead-based paint

3:52:34and asbestos hazards during the period

3:52:36January 29th, 2026 through June 30th,

3:52:392026. And 13 is a resolution authorizing

3:52:42quantum meruit payment to the North

3:52:44Carolina Rush Triad Soccer Club Inc. in

3:52:47the amount of $68,618.80

3:52:50for the construction of a 2,965-ft

3:52:54paved exercise track and an associated

3:52:56amendment to the fiscal year 2027 budget

3:52:58ordinance to appropriate fund balance

3:53:00for a quantum meruit payment to North

3:53:02Carolina Rush Triad Soccer Club Inc. And

3:53:0414 is a resolution authorizing quantum

3:53:07meruit payment to the Richland County

3:53:08Sheriff's Department in the amount of

3:53:10$18,340

3:53:12for expedited DNA analysis for the

3:53:14Sheriff's Office. Denise, can you

3:53:16confirm 10 for me?

3:53:17>> $247.50.

3:53:19>> Thank you. That's what I thought. Okay.

3:53:20And um back to 10, it was Novant um

3:53:23Health Occupational Medicine and it was

3:53:25in the amount of $247.50.

3:53:27So, that's 10 through 14.

3:53:29>> They're approved.

3:53:30>> Those are approved by Vice Chair

3:53:31Wisenhunt. I'm happy to second. Any

3:53:33discussion? All in favor, please say I.

3:53:36I. Any opposed? Motion carries

3:53:38unanimously.

3:53:39>> Thank you. Agenda item number 15 is a

3:53:41resolution authorizing acceptance of a

3:53:43grant and execution of an agreement of

3:53:45conditions with the North Carolina

3:53:46Governor's Highway Safety Program on

3:53:48behalf of the Village of Clemmons as

3:53:49part of the North Carolina's Vision Zero

3:53:51initiative and a resolution authorizing

3:53:54an amendment to the interlocal agreement

3:53:56between Forsyth County and the Village

3:53:57of Clemmons for community policing

3:53:59services. This essentially will accept a

3:54:01grant in the amount up to $129,669

3:54:05and amend the interlocal agreement

3:54:07between the county and the Village of

3:54:08Clemmons.

3:54:09>> Is there a motion?

3:54:10>> Move approval.

3:54:11>> Motion approved by Commissioner Wilson.

3:54:13>> Second.

3:54:14>> Second.

3:54:14>> Seconded by Vice Chair Wisenhunt. Any

3:54:16discussion? All in favor, please say I.

3:54:19>> I.

3:54:19>> Any opposed? Motion carries unanimously.

3:54:22>> Agenda item number 16 is a resolution

3:54:24authorizing execution of an agreement

3:54:26with Partners Health Management to

3:54:27support behavioral health crisis

3:54:29services in an amount not to exceed

3:54:31$2,828,218.25

3:54:36for fiscal year 27 and the approval to

3:54:38execute sub- subsequent amendments that

3:54:41do not change the scope of the project

3:54:43and these are state funds.

3:54:45>> Is there a motion?

3:54:47>> Move approval.

3:54:48>> Motion approved by Vice Chair Wisenhunt.

3:54:50>> Second.

3:54:51>> Second.

3:54:52>> Seconded by Commissioner Bessie. Any

3:54:53discussion?

3:54:55All in favor, please say I. I. Any

3:54:57opposed?

3:54:58Motion carries unanimously.

3:55:00>> Agenda item number 17 is a resolution

3:55:01authorizing execution of an agreement

3:55:03with PSNI LLC for school nurse software

3:55:06licenses at the Department of Public

3:55:08Health in an amount not to exceed

3:55:10$123,750

3:55:12over a 3-year term to support digital

3:55:15case management for students receiving

3:55:17school nurse services.

3:55:18>> Happy to make that motion.

3:55:19>> Is there a second?

3:55:20>> Second.

3:55:21>> Seconded by Commissioner Bessie and

3:55:22Commissioner McDaniel. Any discussion?

3:55:24All in favor, please say I. I. Any

3:55:26opposed? Motion carries unanimously.

3:55:29>> Agenda item number 18 is a resolution

3:55:31authorizing execution of an agreement

3:55:33with Safe Air Systems Inc. to provide

3:55:35maintenance, testing, and repair of

3:55:36breathing air compressors at 10 county

3:55:38fire stations. This is a 3-year contract

3:55:41in a total not to exceed amount of

3:55:42$55,953.27.

3:55:47>> Motion approved by Commissioner Bessie.

3:55:49Is there a second?

3:55:49>> Second.

3:55:49>> Second.

3:55:50>> Second by Commissioner Limbo and Wilson.

3:55:52Any discussion? All in favor, please say

3:55:55I. I. Any opposed?

3:55:58Motion carries unanimously.

3:55:59>> Agenda item number 19 is a resolution

3:56:01acknowledging notice from the Clemmons

3:56:02Fire Department Inc. of its intent to

3:56:04sell capital property valued at over

3:56:06$10,000 and approving the sale pursuant

3:56:09to section 14 of the July 1, 2026

3:56:12agreement between Forsyth County and the

3:56:13Clemmons Fire Department Inc. This is to

3:56:16sell for them to sell two two 2004 fire

3:56:20trucks.

3:56:21>> We have a motion.

3:56:23Motion approved by Commissioner Bessie.

3:56:25Is there a second?

3:56:25>> Second.

3:56:28Great.

3:56:28>> Second by Commissioner Wilson. Sorry,

3:56:30didn't hear it. Any discussion?

3:56:32All in favor, please say I. I. Any

3:56:34opposed? Motion carries unanimously.

3:56:37>> Agenda item number 20 is a resolution

3:56:39awarding and authorizing execution of a

3:56:40contract for community portal software

3:56:43to Benefate LLC doing business as

3:56:45Neighborly Software. This is a five-year

3:56:48agreement and a total amount not to

3:56:49exceed $192,000.

3:56:51This software is used to process a

3:56:53variety of applications, payments, and

3:56:55reports related to behavioral health

3:56:57funds, opioid settlement funds,

3:56:58community grants, and community

3:57:00community and economic development

3:57:02programs.

3:57:03>> I'll move approval.

3:57:04>> Motion approved by Vice Chair Wizened

3:57:05up. Is there a second?

3:57:08>> [snorts]

3:57:09>> Happy to second. Any discussion?

3:57:11All in favor, please say I. I. Any

3:57:13opposed? Motion carries unanimously.

3:57:16>> Agenda item number 21 is a resolution

3:57:18authorizing execution of an amendment to

3:57:20the agreement with Central Square

3:57:21Technologies LLC for its One Solution

3:57:24Law Enforcement Information Technology

3:57:26Platform System and Services and the

3:57:28Neverfail Platform. This will increase

3:57:31the existing contract by $29,373.77

3:57:35for a revised total contract not to

3:57:37exceed $1,362,533.19

3:57:42and this is for the Sheriff's Office

3:57:43Records Management System.

3:57:45>> I have a motion.

3:57:47>> Motion to approve.

3:57:48>> Motion to approve by Commissioner

3:57:49McDaniel.

3:57:50>> Second.

3:57:51>> Seconded by Commissioner Wilson. Any

3:57:53discussion?

3:57:55All in favor, please say I. I. Any

3:57:57opposed? Motion carries unanimously.

3:57:59>> Agenda item number 22 is a resolution

3:58:01awarding and authorizing execution of an

3:58:03agreement for a computerized maintenance

3:58:05management system. This will award a

3:58:073-year contract to Brightly Software

3:58:09Software Inc. in a total amount not to

3:58:12exceed $318,767.42

3:58:16for a work order management system

3:58:18that's being used by General Services,

3:58:20Parks and Recreation, and the airport.

3:58:22>> We have a motion.

3:58:23>> Approved.

3:58:24>> Motion approved by Commissioner Bessie.

3:58:26Happy to second it by Commissioner

3:58:28McDaniel. Any discussion?

3:58:30All in favor, please say I. I. Any

3:58:32opposed? Motion carries unanimously.

3:58:35>> Agenda item number 23 is an ordinance

3:58:37ordering the Forsyth County Community

3:58:39and Economic Development Department to

3:58:40declare a dwelling unfit for human

3:58:42habitation and otherwise to effectuate

3:58:45the purpose of the Forsyth County

3:58:46Minimum Housing Code. This order will

3:58:48direct the Community Economic

3:58:49Development Department to demolish the

3:58:51property located at 22884

3:58:54Fraternity Church Road.

3:58:56>> Move for approval.

3:58:57>> Motion approved by Vice Chair Wilsonet.

3:58:58Is there a second?

3:58:59>> Second.

3:59:00>> Seconded by Commissioner Bessie and any

3:59:01discussion?

3:59:03All in favor, please say I. I. Any

3:59:05opposed?

3:59:06Motion carries unanimously.

3:59:08>> Agenda item number 24 is a resolution

3:59:10approving the Tax Collector's Annual

3:59:12Settlement for fiscal year 2016 and

3:59:13prior years. This is an annual

3:59:16requirement for the board to accept this

3:59:18report.

3:59:19>> Motion to approve. Motion approved by

3:59:21Commissioner Lindahl. Is there a second?

3:59:24>> Second.

3:59:25>> Seconded by Commissioners Bessie and

3:59:27Vice Chair Wilsonet. Any discussion?

3:59:30All in favor, please say I. I. Any

3:59:32opposed? Motion carries unanimously.

3:59:35>> Agenda items 25 through 27 can be taken

3:59:37together. Though they are

3:59:39tax collector um refunds. Um 25 is a

3:59:43resolution approving refunds by the tax

3:59:45assessor collector in the amount of

3:59:47$27,803.88.

3:59:5026 is approving assessor refunds in the

3:59:53amount of $12,553.67.

3:59:57And 27 is denying refunds in the amount

3:59:59of $6,462.11.

4:00:03>> We have a motion.

4:00:05>> Motion to approve.

4:00:06>> Motion to approve by Commissioner

4:00:07Bessie, second by Commissioner Limville.

4:00:09Any discussion? All in favor, please say

4:00:11I. I. Any opposed? Motion carries

4:00:14unanimously.

4:00:15>> Agenda items 28 and 29 are our reports.

4:00:1828 is the May human resources report and

4:00:2029 is the June contribution based

4:00:22benefit cap report.

4:00:24>> I have a motion to accept reports.

4:00:26>> So moved.

4:00:27>> Motion to approve by Commissioner

4:00:29Bessie, second by Commissioner Wilson.

4:00:31Any discussion?

4:00:32All in favor, please say I. I. Any

4:00:35opposed? Motion carries unanimously.

4:00:38>> Agenda item number 30 is an added item

4:00:40following close session. It's a

4:00:41resolution approving an employment

4:00:43agreement for the county attorney.

4:00:45>> Move to approve.

4:00:46>> Motion to approve by Vice Chair Wisdom.

4:00:48Do I have a second?

4:00:48>> Second.

4:00:49>> Second by Commissioner Bessie. Any

4:00:50discussion?

4:00:52All in favor, please say I. I. Any

4:00:54opposed?

4:00:56Motion carries unanimously.

4:00:58>> We do have two planning discussion

4:01:01items. They are text amendments. They

4:01:05are required by the state. Correct,

4:01:08Chris? They're required by the state.

4:01:10We're happy to brief them tonight. I see

4:01:12the faces. Or if you would like, we also

4:01:16can do it at the next meeting.

4:01:18>> We'll do it at the next meeting.

4:01:19>> [laughter]

4:01:21>> That's good.

4:01:23>> Before we adjourn, I'd like to say it's

4:01:25been a pleasure. Thank you for the

4:01:27reception on Monday. I appreciated the

4:01:29very kind gift cards and cards. And I

4:01:32will write you a formal thank you note

4:01:34now that I have more time.

4:01:37We shall

4:01:38We stand adjourned.

4:01:40>> All right.