2026-07-13 - Finance Committee

Summary

Based on auto-generated captions; names, dollar figures and details may be misheard.

Time on topic (from transcript timestamps; approximate, includes side talk):

Topic Minutes Share
Richer School Project 26 58%
Richer School Area Stormwater Bond 12 27%
Recreation Department Reorganization 5 10%
Other business 3 6%
  • Monday, July 13, 2026.
  • Called to order at 6:30 p.m., adjourned about 7:15 p.m. Councilor Irish chaired (apparently); all three votes were 5-0, each with a request for suspension of the rules at the July 20 council meeting.

Recreation Department Reorganization

0:37-5:10

  • Order 26-1009778: job description and salary ordinance for a new recreation coordinator.
  • Mayor's letter: the position is covered by the MMEA union contract and was approved by the union; it merges the former program manager and senior clerk roles, and the assistant recreation director job is reinstated.
  • Pay is set at the head clerk level. Changes to the terms would need to go back to the union.
  • Councilor Vital called the position much needed; recreation staff work around the clock.
  • Michael Ossing noted that, with the recreation director and assistant director salary changes, about a $39,000 shortfall or transfer will be needed.
  • Approved 5-0, with a suspension and advertising of the salary ordinance.

Richer School Project

5:10-22:15, 32:53-33:54, 35:40-43:39

  • Order 26-1009766: bond of $160,544,091 for the new Richer K-5 elementary school (total project about $162.5 million, with $2 million already appropriated for the feasibility study).
  • Presented by Christopher Eberly and John Lemieux of Vertex (owner's project manager), with the LPA architects present. The mayor's letter says the state school building authority (MSBA) approved the project and the city's schedule targets a fall 2029 opening.
  • The project is about 30 percent through design. Cost per square foot (about $792) is above the MSBA cap of just under $700, so the first roughly $90 to $100 per square foot is not reimbursed.
  • MSBA reimbursement: 78.8 percent on eligible costs (86 percent of the budget), about 63 percent of total cost; up to about $103.1 million back, leaving the city about $57.4 million for the school.
  • Tax impact per the treasurer: about $193 a year for the median home on average, peaking near $275 in about year three, around $20 lower than at an earlier estimate.
  • Ossing asked the comptroller to explain level-principal bonding (more paid up front, less interest). He warned that the $35 million fire station (about $150 more on the average bill) and a coming capital plan (about $50 more) add to the burden, and challenged Vertex to match the Goodnow school, which came in under budget and let the city rescind about $9 million in bonds.
  • Eberly said furniture and technology are budgeted at about $4.15 million, all but about $847,000 reimbursable; reuse of old Richer furnishings will be decided later.
  • Schedule: construction manager (at-risk) to be chosen by October, design development by year end, early packages as early as March, fall 2029 opening, closeout summer 2030.
  • Approved 5-0 on a motion by Councilor Fucillo, with a suspension.

Richer School Area Stormwater Bond

22:15-32:53, 43:39-45:10

  • Order (number garbled in captions, same as the school bond): $6.3 million for stormwater drainage design and construction.
  • Eberly said the DPW found recurring flooding every three years or so at Ripley and McGee Avenues; the school site contributes about 3 percent but the flooding reaches its southern entrance. Cost split: about $5 million construction and $1.3 million design.
  • City engineer Thomas DiPersio: Millham Brook was piped through the neighborhood in undersized trunk lines that surcharge in intense storms. Work is to double the trunk line (more than 1,000 feet, outfall at Glen Street), fix a MassDOT stilling basin and drainage channel behind the school, and add controls at the Lake Williams dam.
  • Councilor Oram asked about outfall capacity (DiPersio said the brook section can take it) and detention basins (no room); the new school will have its own detention.
  • Councilor Ducette confirmed there is no state money for this; it is all city.
  • Approved 5-0, with a suspension.

Other business

0:00-0:37, 33:54-35:40, 45:10-45:21

  • The comptroller (first name Brian, per captions) answered the bonding question.

Sources

Video

Watch the video

Transcript

Auto-generated YouTube captions; names and terms are likely misheard.

Transcript

0:03Good evening. I will call to order the

0:05Finance Committee meeting on July 13th,

0:082026 at 6:30 p.m.

0:11Uh, we have three items on the agenda

0:13this evening. Uh, proposed ordinance

0:15amendment uh, to the city code code

0:18chapter 125 personnel. Uh, proposed

0:21Richer K through 5 elementary school

0:23project bond uh, in the amount of

0:26$160,544,091.

0:30And also a proposed storm water bond in

0:33the amount of $6,300,000.

0:37I will begin uh, with order number

0:3926-109778.

0:43Um, that the proposed uh, ornament

0:46ordinance amendment to the city code

0:47chapter 125 personnel personnel section

0:515 preparation of classification

0:53descriptions. And to chapter 125

0:56personnel section 6 uh, salary schedule

1:00relative to the position of recreation

1:02coordinator. Um, I'll read the uh,

1:05letter submitted uh, by the mayor.

1:08Dear Council President Ossining and

1:10Counselors, enclosed for your review and

1:12approval is a job description and salary

1:15ordinance for the recreation coordinator

1:17position.

1:18This position is covered under the

1:20collective bargaining agreement between

1:22the City of Marlborough and the

1:23Marlborough Municipal Employees

1:25Association. MMEA

1:28and has been reviewed and approved by

1:30MMEA. Uh, the purpose of this job

1:33description is to align the growing and

1:35evolving needs of the recreation

1:37department through the reorganization of

1:40the positions within the department. Um,

1:43this job description has been uh,

1:45recalibrated due to the collective uh,

1:47collaboration between the recreation

1:49director, human resource department, the

1:51mayor's office, and MMEA.

1:54Uh, the former city uh, senior clerk

1:57position within the recreation

1:58department no longer aligns with the

2:01operational needs of the department to

2:04to improve efficiency and better support

2:07departmental functions

2:09a restructuring was undertaken that

2:11reinstated the assistant recreation

2:13director position and combined the

2:16responsibilities from the former program

2:18manager and the senior clerk position

2:20into the recreation coordination

2:22coordinator position.

2:24The proposed salary ordinance amendment

2:26places the position at the same level as

2:28the head clerk pay schedule.

2:30While city council approval is required

2:33and appreciated any modifications to the

2:35job description or compensation

2:38structure would constitute a change to

2:41the terms that were negotiated and

2:43agreed upon and would therefore require

2:45further discussion within the union

2:47prior to implementation.

2:49Please do not hesitate to contact me or

2:51my office with any questions sincerely

2:54Jay Christian Zum is mayor.

2:56Um.

2:57I will open this up to committee.

3:00This is something that I support and I

3:02know

3:03uh uh.

3:05Chuck Theobald has been working

3:07diligently to get this the director

3:09getting this

3:11toward the city council council vital.

3:13>> Thank you Mr. Chair.

3:14The this position is is

3:16very much needed down the recreation

3:18department.

3:20This is one of the few organizations DPW

3:23being another one of you but they're

3:2524/7 they're in need down there at the

3:27recreation department and having

3:28somebody who has the the skill set to be

3:32able to uh

3:33prioritize and divvy out

3:35responsibilities to the managers and to

3:37DPW and other other departments across

3:39the city is critical for the department.

3:42So I would strongly suggest that we we

3:44uh

3:45approve the description and salary

3:46ordinance for the recreation

3:47commissioner.

3:48Or coordinator.

3:50>> Is that is that your motion?

3:51>> It is in my motion. Motion has been

3:53made. I will second that

3:55to approve order number 26109778

3:59that the proposed ordinance amendment to

4:00the city code chapter 125 personnel

4:03section 5 preparation classification

4:04descriptions and to chapter 125

4:07personnel section 6 salary schedule and

4:10the job description of the recreation

4:13coordinator. Any further discussion? Mr.

4:15Chair.

4:16>> Councilor Pajal. Thank you, Mr. Chair. I

4:18would just ask that we also make sure

4:20that we advertise

4:22and as well as ask for suspension when

4:24this is reported out on the floor.

4:25>> do that. That's a good good point,

4:26Council. And we're okay with that,

4:28committee?

4:29And to to average suspension and to

4:32advertise.

4:33All in Mr. President.

4:34>> Thank you, Mr. Chair. I just want to

4:36point out to the committee that

4:38before us on next Monday's night, we're

4:40going to be approving salary changes to

4:42the recreation director, the assistant

4:43recreation director, and then with this

4:45one, there's going to be a $39,000

4:47shortfall or transfer that's going to be

4:49needed to pay for all these positions.

4:52All right? So, even though, you know,

4:54everybody's all excited about them, we

4:55still got to pay for them.

4:58Thank you, Mr. Chair.

4:59>> Thank good point, Mr. President. All in

5:01favor?

5:021 2 3 4 5. It carries 5 to 0 with the

5:06suspension to advertise as well.

5:10Moving on to

5:12agenda item 26-109766.

5:17Proposed Richard K. 3-5 Elementary

5:20School project bond in the amount of

5:22$160,544,091.

5:26And I'll begin by reading the letter

5:29submitted by the mayor.

5:33Honorable President Osing and

5:35councilors, enclosed for your review and

5:37approval are two bond authorization

5:39requests for the Richard School project

5:42in the amount of $160,544,091

5:47to be bonded for the built built of the

5:50school and $6,300,000

5:53for the capital improvement project for

5:55storm water flooding.

5:57Our journey toward a new Richer School

5:59began in the summer of 2024.

6:02Since then, we have successfully

6:03completed several milestones, including

6:06the selection of the owner's project

6:07manager, OPM, and the feasibility study,

6:11and the schematic design phase. This

6:14vote will not only allow the project to

6:16move forward, but will have the final

6:18determination and the reimbursement

6:20rate. We are submitting the bond request

6:23for the total project projected dollar

6:25amount of the project because this is

6:27the process used to fund the project and

6:30cover its cost. We will receive the

6:32final determination of the city's cost

6:34during the June 24th MS MSBA meeting and

6:39vote and and determination of the

6:41reimbursement total. In the enclosed

6:44packet, you will find a letter from OPM

6:46Vertex with a breakdown of the cost and

6:49the expected reimbursement totals. These

6:51numbers are preliminary and are not

6:53final. Based on the scheduled date of

6:56the upcoming vote by MSBA on June 24th,

6:59the city council schedule, we needed to

7:02submit the packet for this meeting so

7:03you are as a body can approve the bonds

7:06and project costs at the July 20th city

7:10council meeting. The goal is to have

7:12this referred to the finance committee

7:14prior to the July city council meeting.

7:16The following the June 24th MSMBA vote,

7:20representatives from Vertex will attend

7:22the committee meeting to answer any

7:24questions, discuss the final project

7:26figures, and provide an update on the

7:28outcome of the MSBA vote. Regarding the

7:31bond of the storm water infrastructure

7:33improvements,

7:34this has been a long-standing issue in

7:37the area that requires necessary

7:39attention.

7:40With the construction of the new school

7:42moving forward, the opportunity to

7:43address this critical infrastructure

7:45need is now. Taking action at this time

7:48will help make sure the necessary

7:50improvements are made to support both

7:52the community and future developments.

7:54Uh we do not fix the storm water issue

7:57and build the school, we may see

7:58increase uh in flooding in the

8:00neighborhood that abuts the site. Uh

8:02thank you for your flexibility in

8:04accommodating meeting times as we work

8:06to maintain this ambitious schedule and

8:08achieve a fall 2029

8:11opening. I want to thank the school

8:13building committee, all the

8:15subcommittees, Vertex, LPA architects,

8:18school committee, city council, and

8:19everyone who has done their part uh to

8:21get this project to this milestone. If

8:24you have any questions or concerns,

8:25please do not hesitate to contact me

8:27sincerely, J. Christian Dumas, mayor.

8:30And we did we did through our email as

8:32well receive the letter from uh the uh

8:35the MSBA

8:37um determining uh that we were approved.

8:40Um at this time, I would like to bring

8:42up

8:45Are you Are you Yeah.

8:47If you could do your uh introduction and

8:50start your slideshow as well. Thank you,

8:52Chris.

9:04>> So, um my name is Christopher Eberly.

9:06I'm the project executive from The

9:08Vertex Companies. We've been working

9:10with the city of Marlborough since

9:12October of 2024. With me tonight is John

9:15Lemieux, our senior managing director um

9:19for The Vertex Company. Also joining us

9:21um as needed is um Peter Caruso,

9:25Chris Lee, and Christina Besmann for

9:28those on this side. She's behind the

9:29column.

9:31Um they are the principal in charge,

9:33project manager, and project architect

9:35from Lamoureux Pagano Architects.

9:38Um also with us tonight as needed for

9:41the um stormwater is Ted Scott.

9:45And

9:46um

9:47So, I'd like to thank you for uh having

9:50us here tonight. We've been working for

9:52quite a while on this um since October

9:5524 and since February 25 with the

9:58designers to advance this exciting

10:01important project. The project

10:05The project is at about 30% of its

10:08overall design phase at this time. And

10:10so, this is the time that the MSBA has

10:12you vote to approve the total project

10:14budget. As you can see on the screen,

10:19as you can see on the screen, um we have

10:22progressively decreased the pros cost of

10:24this project both in terms of its soft

10:26cost and also its construction cost as

10:28we've developed this since our initial

10:30numbers were available in June of 2025.

10:34And with the most recent cost, we are

10:37looking at a total project cost

10:38inclusive of the previously authorized 2

10:41million for the feasibility study of 162

10:44million 544,091

10:48dollars.

10:49Now,

10:50this these refinements have been the

10:52work of LPA, the work of Vertex, and the

10:54work of the school building committee as

10:56they've made disciplined decisions

10:58throughout the project to ensure that

10:59the project comes in at an affordable

11:02cost for the taxpayers of Marlborough.

11:05Here you can see a chart that is put out

11:07by the MSBA that places all of the

11:09projects that are within their purview

11:11on the same chart with their bid dates.

11:14As you can see, we've highlighted the

11:15Goodnow project because at the time the

11:17Goodnow project within its one-year time

11:20frame was the lowest cost project in the

11:24MSBA pipeline. Now, at that time, you

11:26could build a project for almost close

11:28almost at the reimbursement rate in

11:31terms of funding caps, but one of the

11:34things that we noticed is that with the

11:35richer project that we're proposing

11:37tonight, not only are we again

11:39the um lowest cost MSBA project within

11:43the last year,

11:44but similar to the Goodnow project that

11:47was 5% below the cost of its next

11:49nearest project, we're 4% below the cost

11:53of the next nearest project, another

11:55Vertex project in Wrentham.

11:58Now, as we look at the budget, it's

12:00think it's important for you to

12:02understand that this budget is

12:04all-inclusive. The MSBA has a fairly

12:08restrictive

12:09um schedule that's included in your

12:11packet that describes all the areas of a

12:14project and making sure that you budget

12:16comprehensively for the project, both in

12:18terms of covering design fees, covering

12:21soft costs, covering FF&E and

12:23technology, covering the construction

12:25itself, and also carrying a healthy

12:27contingency.

12:29In putting together this budget,

12:31the OPM designer services, the estimated

12:34construction costs, the furniture,

12:35fixture, and equipment are all

12:37professionally estimated. So, we brought

12:40in an estimator that working with the

12:42Vertex company, an estimator working

12:44with LPA. They both estimated the same

12:46drawings and they reconciled those to

12:48arrive at that construction cost.

12:50We also had um LPA working with their

12:53consultants develop a furniture cost

12:56based on actual pricing and a review of

12:59what furniture was necessary so that we

13:00could establish an accurate budget, and

13:02we reviewed the technology and computers

13:04that would be part of the project. Now,

13:06those two are important because the MSBA

13:08also reimburses for those costs, so it's

13:11important to both find a reasonable for

13:13the project value, but also to include

13:17something that will maximize the

13:18reimbursement that is available on a per

13:20student basis.

13:23We've also um

13:25as I mentioned,

13:26you have already appropriated 2 million

13:28of this amount, and I think that's

13:31important to echo because it really it

13:33lowers the amount that you're looking to

13:34spend now.

13:37Now, in your packet, there is a very

13:40very complex spreadsheet, and that

13:43spreadsheet takes into account all the

13:44things that the MSBA uses when they

13:46determine what your reimbursement is,

13:49and in making sure that you have a

13:51comprehensive budget. It'll take into

13:53account their category and ineligible

13:55costs, which are based on the guidelines

13:58of the grant program that you're

13:59pursuing. It will take into account the

14:01cost and budget caps,

14:03any ineligible building area,

14:06any reimbursement rates or changes to

14:08those reimbursement rates, and the

14:10eligibility of things like contingency,

14:12but also things that are excluded scope.

14:15Now, it would take us hours to go

14:17through all the details of this, and so

14:18what I've developed today is a way to

14:20try and simplify this for all of you so

14:22that I can

14:24co- uh informatively explain how the

14:27system works, and what the reimbursement

14:30will be for the city of Marlborough.

14:33Now, this is the Reader's Digest version

14:36of the

14:38MSBA program. Ultimately, what it means

14:40is that you are going to receive your

14:43base rate

14:45for all eligible costs. The base rate is

14:47recalculated up until you come to the

14:49agreement with the MSBA, and they

14:51actually raised your base rate based on

14:53socioeconomic factors that they study

14:56from when you originally agreed to the

14:57feasibility study. So, moving forward,

15:00you'll have a higher reimbursement rate.

15:02They evaluate your maintenance school

15:05score, and they found that you were in

15:06the top 25th percentile in terms of

15:09maintenance of the schools that they

15:10look at, so you got an extra 1.54%

15:14on top of that. We've also made the

15:17decision that you would be moving

15:18forward with the green schools program,

15:21and so by meeting the requirements of

15:22the Opt-in Energy Code and delivering a

15:25school that provides a higher quality of

15:27air quality for the students, you'll get

15:29an additional 4% of those eligible

15:31costs. Now, I keep saying the same

15:33thing, which is eligible costs, and

15:35that's an important component of the

15:36MSBA grant program. They put certain

15:39caps in place, and I've shown some of

15:41them on the screen here, that establish

15:43up to those amounts, they will reimburse

15:45those costs.

15:47Now, in their analysis of your total

15:49project budget, they found that 86% of

15:52those costs in that budget were

15:54eligible. And so, of those amount, that

15:57is what you will receive your 78.8%

16:00reimbursement on. Works out to be about

16:0263% in total of the costs of the project

16:05will be coming back to Marlborough from

16:07the state.

16:11So, here I've just illustrated a little

16:12bit about how that reimbursement works.

16:14It's a paid as spent, so you as you

16:18incur costs associated with the grant

16:20program, the MSBA will receive a

16:24reimbursement request that will itemize

16:26those costs as the warrants go out to

16:28pay those bills. They review those, they

16:30audit them on the fly throughout the

16:32entire process, and that, based on what

16:35those eligible costs determined by that

16:37audit are, you'll receive the payments

16:40periodically, usually monthly,

16:42throughout the course of the project.

16:44I've illustrated here sort of the two

16:46differences because what you'll find is

16:48that much more of the costs in the

16:50design phase are eligible. And so, I've

16:53illustrated using the cash flow that's

16:55in your packet, what you can expect in

16:57terms of reimbursement should all of the

17:00facts and figures that we have provided

17:03show to be eligible after that audit.

17:06And what you find is that about 74% of

17:08those costs in design end up being

17:11reimbursed.

17:12When you get to construction, you're

17:14much more exposed to the cost caps. They

17:17work out to be just under $700

17:20um per square foot. And so, of that

17:23amount of that cost cap,

17:25because you are so much higher than it

17:27at the $792

17:30per square foot that the project came in

17:32at, you are actually that first hundred

17:35or ninety or so dollars a square foot is

17:38not reimbursed. The effect of that is

17:41that when you get to construction versus

17:43design, where you're getting 74% of the

17:46costs in design, by the time you're in

17:47construction, you're closer to 63. But

17:50construction makes up so much of the

17:53overall grant reimbursement that

17:55ultimately, should you spend every

17:57dollar,

17:58you would get 63% of those dollars back

18:01from the state

18:02if the eligibility calculations after

18:04audit prove true through the course of

18:07the job.

18:09Now,

18:10to make that clearer, I came up with a

18:12couple of different scenarios here to

18:14help explain how your decisions and the

18:18school building committee's decisions as

18:19they move through this project can have

18:21a huge effect on your reimbursement.

18:23So, the first option in the green box is

18:25that you decide to spend every dollar

18:28within your budget. You follow all the

18:30rules, everything ends up eligible. The

18:33city of Marlborough can look at a

18:34project that is 160,000 square feet that

18:38they would get for 59,400

18:41and 9,098

18:43dollars,

18:44which is a great value. It's much better

18:47than a lot of communities are getting

18:48from the MSBA.

18:50Now, construction, let's say, comes in

18:535% under budget. You hire your CM, they

18:56get their bids, and we find out that the

18:58bids are 5% down. What you can see here

19:01is that while

19:03the um

19:06construct or the eligible costs are

19:08almost the same,

19:09you're still getting

19:11103 million 59,192

19:14dollars. So, you're only losing roughly

19:1870,000 dollars in grant,

19:20but you're spending

19:226 million dollars less.

19:25Because the way that they do they

19:27calculate it is that they calculate

19:28where you are at bid,

19:30they'll adjust your grant down.

19:32They'll say, "Oh, this what we thought

19:34would be construction, that's that

19:3670,000 dollars, you're not going to need

19:39because your bid came in low, but we'll

19:40still pay you up to a quarter percent of

19:43your soft cost contingency and up to 1%

19:46of your construction contingency." Now,

19:48let's say the bid comes in, we spend

19:51everything up to up to bidding, the bid

19:54comes in exactly on target, but we're

19:56disciplined in the construction phase.

19:58We don't encounter a lot of unforeseens.

20:00When that extra scope comes up, the

20:02school building committee says, "We

20:03don't really need that. We want to be

20:05fiscally disciplined." as they've been

20:06through the process.

20:08In that case, you're still going to get

20:11that same grant because you've spent

20:14every dollar up to that point, but the

20:17total project cost to the city is going

20:19to be 54 million 919,997

20:23dollars. And the reason is that because

20:26they cap your costs, all that spending

20:28above that cost is spending that is paid

20:32for 100% by the city of Marlborough,

20:35whereas the spending under those cost

20:36caps get reimbursed. And the best dollar

20:39spent

20:41is the one that you don't spend because

20:43you get that full dollar back for all

20:45that stuff over the top that you don't

20:47need to put the money into.

20:51Now, it's important because construction

20:53is schedule and cost. It's important to

20:56just touch on the schedule and see what

20:58the commitments that we're working on

20:59here are.

21:01We're coming to you today because our

21:02schedule requires a very aggressive

21:04approach. We're currently procuring the

21:06CM now. I know you previously this body

21:09voted to approve the CM at risk

21:12approach. We're currently soliciting

21:14qualifications and we hope to have the

21:16CM CM on board in October. We're moving

21:19forward with design development, which

21:20is roughly 50% of the design phase,

21:23hopefully by the end of the year.

21:25And then we'll be doing early packages

21:27as early as March. And the goal would be

21:30that we have 100% of the drawings 1 year

21:33from now

21:34going to bid, but we'd have early

21:37packages that would allow us to start

21:39early mobilization and early

21:41um structure packages so that we can

21:43begin the wheels moving of the

21:44construction machine and really have

21:47shovels in the ground as soon as school

21:48is out at the Richer school at the end

21:50of this school at this next school year.

21:53So all told, that's what allows us to

21:55open the school in the fall of 2029

21:59and

22:00close out the construction in the summer

22:02of 2030 after we've finished all of that

22:05site work that we're not able to get

22:07done because eventually winter will hit.

22:12And

22:13with your permission, Mr. Chair, I'll

22:15just continue on the storm water.

22:16>> Thank you. Thank you.

22:17>> Um so the storm water came up through

22:20the course of the job. It was identified

22:23by the DPW that they had a recurrent

22:25issue at Ripley and McGee Avenue where

22:28every 3 years or so they would have

22:31substantial flooding.

22:32And the substantial flooding would occur

22:34at the intersection of um Ripley Ave and

22:37McGee, but it would also occur

22:41through this area that is also wetlands

22:43on the back side of the site. And so we

22:45wanted to understand what the impact of

22:48that storm water would be on the project

22:51and how the project's impact would also

22:54affect that storm water.

22:56And so uh we retained the civil engineer

22:59through the designer Nitsch Engineering

23:01to do a study to they did HydroCAD which

23:04is some computer modeling of how

23:06drainage works within the area and they

23:09determined that while the school only

23:11committed 3% to the problem, the problem

23:15encroached on the school. It encroached

23:17on the southern entrance which serves as

23:19both a bus and parent entrance to the

23:21school. And so it had the potential of

23:24if you're going to spend $162 million to

23:26build this school, wouldn't you want to

23:28make sure that we're keeping the water

23:29from taking taking over? So in

23:32discussions with the DPW, we researched

23:34various ways that we could move forward

23:36with it. We identified a budget um

23:39working with the DPW and um Tom DePersio

23:42who is also here tonight.

23:44And we identified that it's about $5

23:46million in construction to pursue two of

23:48the options that were in that study.

23:51And a contingency was reasonable for

23:53design costs of about $1.3 million that

23:56would pay to bring the designer on board

23:59and to do the to run the project

24:01separately from the school project

24:03entirely as a DPW project. That was an

24:06important distinction because the MSBA

24:08will only

24:09allow you to have one project as part of

24:12their vote. They want it to be entirely

24:15separate for various reasons, legal

24:17procurement requirements as well as they

24:19want to make sure that when they report

24:21on the cost of schools, they're

24:23reporting on the cost of the school, not

24:26the cost of the school plus whatever the

24:27city or town decides to tack on to it.

24:31So ultimately

24:33what we're before you today to discuss

24:36is that you have

24:39a budget before you that's $162,554

24:43or $544,091.

24:45You have already appropriated $2 million

24:48of those dollars. So you are looking at

24:51a school that will give you that will

24:53cost you $160,544,091.

24:58The MSBA, if you spend every dollar,

25:02will give you 103 million 134,993

25:06dollars.

25:08If you spend everything but half your

25:10contingency, they will give you that

25:12same amount.

25:14When you take that out, you're looking

25:16at the total cost of that school being

25:1857 million

25:20409,098

25:23dollars. And if you take the Add the

25:25storm water to that to that, the two

25:27appropriations combined are 63,709,098

25:32dollars.

25:33Similar to what we did when we visited

25:35the Urban Affairs Committee for PSR, we

25:36reached out to the treasurer and asked

25:39him to help us with the tax impact. He

25:41found that for the average um

25:45median home,

25:47the annual impact would be on average

25:49193.23

25:51cents. And in that highest single year,

25:53which is about year three,

25:55it would be 275

25:58dollars and 50 cents, which both numbers

26:01are

26:02um about 20 dollars lower than they were

26:05at PSR.

26:07And as the letter that we have provided

26:09to each of you tonight also states, the

26:12MSBA has confirmed at their board

26:14meeting that they will fund the project.

26:16So, the next step would be to enter into

26:18a project scope and budget agreement

26:20with the MSBA pending approval of the

26:22financing. So, if you vote next week to

26:25fund the project, that would be the next

26:28step. We like to describe the project

26:30scope and budget and the project funding

26:32agreement is like buying a house. You

26:34put in an offer and you sign that offer.

26:36That's your project scope and budget

26:37agreement. And then your project funding

26:40agreement is the thing that actually

26:41starts the grant flowing. So, that's

26:43what those two documents are. So, should

26:46this committee ultimately vote to fund

26:48the project on Monday, those would be

26:51the two next step and then the MSBA

26:54would begin the reimbursement project.

26:56LPA and Vertex would continue to design

26:58your building and by the time we get to

27:01October, we'll have a third partner in

27:03on board with the CM so that we can

27:05deliver this school in 2029.

27:09With that,

27:10I will open it up to questions that

27:12myself or any of the assembled partners

27:16that we've worked with very successfully

27:18on this project are able to answer.

27:20>> Thank you, Chris. Thank you, Chris.

27:21>> Councilor Vital?

27:22>> Mr. Chair, could we please have Mr.

27:24DePersio give us a little breakdown of

27:27what the uh

27:28the the water project's going to entail?

27:32>> Please.

27:34Thank Thank you, City Engineer DePersio.

27:50>> Uh thank you, councilors.

27:52So, uh Chris did a good job of

27:54explaining kind of how we came to the

27:56decision that this drainage project

28:00um needs to be done in conjunction with

28:03the school project and Nitsch

28:05Engineering

28:07uh did a good job at from a high level

28:09of breaking down all the different

28:11components to this drainage issue.

28:14Um

28:15the short version is that Millham Brook

28:20is piped through the neighborhood there

28:22when that neighborhood was built. They

28:23took the brook and put it in a drainage

28:26trunk lines through the neighborhood

28:27that are they're undersized now.

28:30And what happens in intense storm events

28:33is where the brook enters the drainage

28:35system, it surcharges and and floods

28:38that area as Chris said, and uh sort of

28:42the wetland system that really surrounds

28:44that whole southern part of the school

28:45site. It's all tied into that Mill Ham

28:47Brook flow.

28:49Um so

28:51there's a couple of

28:53phases we call them of the drainage

28:54project that were uh

28:57in the

28:57design uh

28:59phase is starting now.

29:01One is to kind of double up the size of

29:04that trunk line.

29:06Um

29:07that's a big project. It's It's

29:09difficult to

29:10>> the development, right?

29:11>> Right, all the way through.

29:13Uh

29:14that's one piece of it, and the other

29:16piece is going to involve um

29:19some of the MassDOT infrastructure for

29:21the highway.

29:22Um there's a big uh stilling basin they

29:25call it that's behind the school.

29:28And uh and a drainage channel

29:31doesn't function properly. So that's

29:34that's a piece of it that we're going to

29:35have to get MassDOT. We've started

29:37conversations with them

29:39to get them on board for that work.

29:41Um

29:42and I also want to do some work at

29:45the Lake Williams Dam because

29:49to the extent we can kind of get a

29:50spillway there that we can easily

29:52control, we can maybe

29:54close that in advance of a big storm and

29:56kind of delay that that part of the

29:58flow, too. So there's several different

30:00components to it, but that's kind of the

30:01overview.

30:03>> Scheduling, if this gets approved by

30:04this body, when can you begin?

30:07>> So we're we're working on the drainage

30:10improvement part through the

30:11neighborhood in-house now. So um we

30:15anticipate anticipate being ready to

30:18go out to bid with that part when we

30:21have the funding.

30:25>> Thank you.

30:25>> And the other part, like I said, we're

30:27working with MassDOT, so we're a little

30:29bit

30:30beholden to their schedule, so hopefully

30:32we can get them uh to move on that part

30:34of it, too.

30:34>> Our ideal schedule was to do it in

30:37concert with the school so that it'd be

30:39a separate contractor. They'd be doing

30:41the work on their own, but we'd do it in

30:43two phases, ideally one that begins as

30:46soon as the

30:48winter ends next year, and then the

30:51second one would begin the following

30:53year.

30:54So that by the time we open the school,

30:56the goal would be that both are

30:59um

31:00are complete. Obviously, that requires

31:04DOT to work with the city and the other

31:07components there, and um we've had lots

31:09of conversations with the DPW to make

31:12sure that the contractor that we hire

31:14for the school understands their role

31:16in um working with that contractor and

31:20getting them access when they need to

31:21through the site to make sure that the

31:23both can occur concurrently.

31:25>> Right.

31:26>> Thank you.

31:28Thank you, Mr.

31:28>> Thank you, counselor.

31:29Thank you, Engineer DePersio. Got

31:31counselor Orum.

31:36Is there a question for

31:37>> A question. Uh

31:38Tom, you can stay up there, too.

31:40Um

31:41So, how much lineal feet uh

31:44are there in this pipe that we have to

31:46replace?

31:49>> Uh

31:50I don't know the exact number, but it's

31:52uh

31:53it's over 1,000 ft.

31:55>> I see. So, it's going to go through

31:57several streets, then.

31:58>> It is.

31:59>> It has to be replaced by the three.

32:00>> Yeah, all the way to the outfall at Glen

32:03St.

32:03>> was my other question, the outfall.

32:04Where is the outfall, and will it be

32:06able to handle

32:07I'm sure you've studied it. Will it be

32:09able to handle all this additional flow?

32:11>> Yes, the outfall is at Glen St. It back

32:13into Millham Brook.

32:15Um that section of the Brook has uh

32:19it has the capacity to handle that.

32:22>> Okay, and there's no detention basins

32:24planned for this or anything like that

32:25to slow it down before

32:26>> No, there's really there's really no

32:28place to do anything like that.

32:31>> Thank you.

32:31>> Yep.

32:32>> Thank you, Mr.

32:33>> being said, the new school will have

32:34detention

32:36on the facility, so that that piece of

32:38it, that's going to be an improvement as

32:39well.

32:40>> Thank you.

32:41>> Thank you. Thank you, Engineer

32:43DePascale. I'll open up to any further

32:45questions of the council.

32:48No.

32:49President Ossining.

32:51>> Thank you, Mr. Chairman.

32:53>> Thank you, Mr. Chairman. I was wondering

32:54if I could have Comptroller and then

32:56maybe Chris answer these questions.

32:59So, the

33:00the

33:02tax impact, right? I mean, it's nice to

33:04say we want a new school and how much

33:05it's going to cost, but

33:07you know, people want to know what's it

33:08going to cost them, right? That that's

33:11So, you go through a scenario where you

33:13say it's up to $275,

33:16then drops down. Could you give an up

33:18Could you or Brian give us a

33:21insight as to why it's Cuz my mortgage

33:23doesn't go up or down, right? My

33:24mortgage is

33:25fixed at this rate and it's good for 30

33:27years.

33:32>> If Brian can answer that easily more

33:34easily than I can while I shuffle

33:36through my papers and find

33:38the tax impact.

33:41>> So,

33:42let me answer the tax impact.

33:43>> So, how does the city do their bond?

33:49>> All good.

33:50All right. Thank you.

33:52So, the city we do our bonding, we're

33:54very aggressive. We do level principal,

33:56unlike your mortgage, which is a level

33:58payment. So, your mortgage is the same

34:01over 30 years, we'll say,

34:03amount every month.

34:05The way the city does it, we divide

34:08we take the

34:09principal, we divide it by the number of

34:13years

34:14and we take that level off the every

34:17year, so that we pay a lot more up front

34:20and less later on in the schedule. Why

34:23we do it that way is because, as you

34:25know, we're always adding more bonds.

34:28So, as that one declines, then we bring

34:30on the next one and decline, we bring on

34:32the next one. If you do it where it's

34:34always level, you're always adding to

34:37that payment. So, we try to do it this

34:40way, and also it saves you interest. By

34:42paying a lot of principal up front and

34:44level principal, you pay less interest

34:46over the life of the project. And in

34:49this case, it's millions of dollars.

34:50>> So, so that's the point that I wanted

34:52the public to understand and why the why

34:55the payment schedule set up that way so

34:57that it actually does benefit the tax

34:59payers. Cuz what's not said here

35:02is a $35 million fire station,

35:05which is now going to add another $150

35:08>> [snorts]

35:08>> to the average tax bill.

35:10All right. We have a capital plan that

35:13has not come down yet that usually runs

35:15in the order of 10 to 12 million dollars

35:17that's going to add

35:19my math, $50

35:21to the average tax bill. So, as you vote

35:24on this, it's not just a single bond.

35:27You need to take the whole concept. Now,

35:30I'm confident the city's got the

35:31capacity to handle it.

35:33Now, the taxpayers may not like the fact

35:35that we have the capacity to handle it,

35:38but you you but you're voting on is

35:40going to be

35:42you know, increasing the average tax

35:45by about $275

35:47if both project Well, both projects have

35:49to be approved in order to make the

35:51project work. You can't just do the

35:53school and not do the the storm water.

35:55The storm To me, the storm water we need

35:57it regardless of whether we do the

35:58school or not. The storm water piece of

35:59that

36:00is going to have to get done, and that

36:01would show up on a future capital plan.

36:05So, Chris, I'm going to challenge you.

36:07Um

36:09for the Goodnow school,

36:10uh we have we were able to rescind about

36:129 million dollars worth of bonds.

36:15So, I'm going to put it out to you that

36:16it came in under budget. It came in

36:18ahead of schedule. Um

36:20I'm confident you guys can pull off the

36:22same feat cuz we do estimate

36:24conservatively, and that'll all work out

36:26in the end, but I just wanted to like to

36:28challenge you to the fact that uh

36:30uh there's a benchmark before you that

36:32was able to rescind a significant

36:34portion of the bond that we approved for

36:35good now, and I'm hoping that uh you and

36:37your team uh can do the same thing. I'm

36:40confident you will based on the

36:42presentations I've seen uh your team

36:44make uh in various uh meetings

36:46uh over the last year, so uh

36:50hopefully you accept the challenge.

36:52>> I I can certainly accept that challenge.

36:54Um well, uh as any financial advisor

36:57will tell you, past results are not a

37:00guarantee of the future. I can tell you

37:02that my MSBA project that is closest to

37:05construction

37:07um had a $159

37:09million

37:11budget, and it is currently $22

37:16million

37:17another year and a half to go.

37:20>> So, counselors, I'm not guaranteeing

37:22this, but I'm just saying past

37:23performance I mean, they're they are

37:25estimates. They they put the best they

37:27can cuz they're trying to predict what

37:29the price of wood, steel, pick the

37:31product is going to be 3 4 years from

37:33now,

37:34uh and what labor costs are going to be,

37:36but uh hopefully they've done their uh

37:38proper estimating, and this should be

37:41the highest it is and not

37:44come in

37:45any higher than what they're projecting.

37:47If you want John wants to say something.

37:49>> join in cuz he has much more statistics

37:51about

37:52>> Well, I'm not going to give statistics,

37:53but what I will say is um

37:56you know, having the benefit of a CM on

37:58our team in the next few months, that's

38:00the benefit of the build that's actually

38:02going to do the project in this year as

38:05we keep moving forward, you check that

38:07you're well within that schematic design

38:09budget, at design development, you check

38:12it again at construction document. So,

38:13we're going to have numerous occasions,

38:15and we will challenge that CM as well.

38:18Just hey, just because we have X amount

38:20of millions for construction, we want

38:22you to do better. We're hiring you to

38:24come to the table to help give us ideas

38:26to do better. So, that if we don't have

38:28it, and LPA doesn't have it, hey CM,

38:30what have you done recently that can

38:32help bring this thing in to keep our

38:34project in that lower right-hand corner

38:36because listen, it's it's great cuz I've

38:39sat in communities where that number is

38:40at the other end, and it's a

38:42it's a much harder discussion, but

38:45I think the team's done a phenomenal job

38:47with keeping the numbers down, and the

38:49challenge is finding the right CM that

38:51will sing that sheet of music with us so

38:53that we can, you know, we talk in

38:56extremes because it's easier for the

38:57math. If you spend all of this, you will

39:00get all of this, but that was my

39:02question to or my comment to Chris was

39:04the best dollar is the one not spent.

39:06You don't worry about any reimbursement

39:07in a dollar if it never comes out of

39:09your pocket, right? And that's that's

39:11super important these days where we know

39:13this is not the only community. We hear

39:16that very same list of capital coming,

39:19you know, potential issues with

39:20operating budgets, right? All sorts of

39:22things. So, we we hear it, and we, you

39:25know, we take it to heart because

39:27ultimately, you know, we want you to be

39:28happy and not stress over this thing

39:31from, you know, from the get-go. So,

39:33we're going to work to work to do just

39:34that.

39:35>> Thank you, John. Thank you, Mr.

39:36Chairman.

39:36>> Thank you, President Eisen. Council

39:38Vidal.

39:38>> Thank you, Mr. Chair. Gentlemen, it's my

39:40understanding that all furnishings, all

39:42equipment, all technology is going to be

39:45reimbursed. So, we're going to get a new

39:46school with everything new inside.

39:49>> They're

39:49>> There is a limit to the reimbursement in

39:51terms of they do it per student. So,

39:54they have um I'm not going to know the

39:56number off

39:58>> 1,900 for furnishings per student, and

40:011,700 for for technology.

40:04>> Do you guys believe that that will be

40:06>> Oh, probably especially

40:08it's more challenging if at an older

40:10school, but for high school middle

40:12school and high school where there's

40:13that much more technology, where the

40:16furniture is bigger, it's easier to

40:18achieve in a small in small school for

40:21the smaller humans, right?

40:22>> So if we So if we have a new school, new

40:24new furnishings, new equipment, new

40:26technology, we have an old school which

40:28has all that stuff. Is there any value

40:30to that facility and what's in it?

40:33>> So it's a great question and that's part

40:35of what will be discussed as the project

40:37keeps moving. What do you want to do

40:39with the the old old stuff? Do you want

40:41to recycle it through the the other

40:44schools? Is it, you know, is some of the

40:46stuff in richer

40:4710 years old and there is other schools

40:50it's 20. Yeah, absolutely. The value is

40:52is more of that value to you.

40:54Um ultimately when the CM is on board,

40:57they are coming on board to manage that,

41:00but they will be part of the process to

41:02say,

41:03"Okay, if we've got to empty the school

41:05out,

41:06you know, this is going to be part of

41:07our number. If we're going to recycle

41:08it, here's what we can suggest."

41:10Um or it's a wholesale, "Guys, it's all

41:13yours. Take it and use it, you know, as

41:15you like." But

41:17>> To add to that, um

41:19I had to take the glasses off for this

41:20one.

41:21Um the budget carries about 4.15 million

41:25for technology and furniture combined.

41:29Of that, all but 847,000

41:32are reimbursed. Now, we base that off of

41:36an actual accounting of what we think

41:38the furniture will be at this time using

41:40unit costs at this time and a little bit

41:43of contingency and a little bit of

41:45escalation. Now, we have to do that now

41:47so that we make sure we carry an

41:48appropriate budget so that we can

41:50deliver on the goals of Marlborough by

41:52the time we get to buying that stuff in

41:552029.

41:57But the reality is that we're going to

41:58make decisions the closer we get to

42:00those about every aspect of this budget

42:03to try and deliver the project for the

42:04best value for the citizens of

42:06Marlborough. And if we can deliver it

42:09for, you know, that

42:123.2 by reusing something because that's

42:14the decision that the school building

42:16committee chooses to move forward, that

42:18just adds to that graphic I showed you

42:20where every dollar that you don't spend

42:22of that $847,000,

42:25that comes straight out of Marlborough.

42:27MSBA's not paying that portion of it,

42:29but you want to make sure you get every

42:30dollar that MSBA is paying for.

42:32>> Thank you, gentlemen. Thank you, Mr.

42:33Chair.

42:34>> Councilor Vital.

42:35>> Thank you, Chris. Thank you, John.

42:37Any further discussion

42:39in the committee?

42:40If no further discussion, I will

42:41entertain a motion.

42:48>> Mr. Chair.

42:49>> Councilor Ficciolo.

42:49>> Thank you, Mr. Chair. Um I've enjoyed

42:52the presentation and conversation and um

42:54with that would move to approve the

42:57proposed Richer K-5 Elementary School

42:59Project Bond in the amount of

43:01$160,544,091.

43:06>> Thank you, Councilor Ficciolo. Uh

43:07motion's been made and seconded uh to

43:09approve order number 26-19766

43:12proposed Richer School K-5 Elementary

43:15School Project Bond and the

43:16appropriation amount of $160,544,091.

43:24Councilor Ficciolo.

43:25>> Mr. Chair, I would just ask that um that

43:27uh a suspension is asked at the next

43:29meeting so we

43:30>> Councilor Ficciolo. Thank you.

43:30Absolutely well noted.

43:33All in favor?

43:351 2 3 4 5. That carries with the

43:38suspension. Thank you, Councilor

43:39Ficciolo. Uh next up is order number

43:4226-19766

43:46uh proposed stormwater bond in the

43:48amount of $6,300,000

43:51for the design, construction, and

43:53improvement of the stormwater drainage

43:55and related municipal infrastructure. Um

43:58we were uh

43:59nicely educated by uh engineer DePersio,

44:02so I will certainly entertain a motion

44:05on this if the committee is ready to do

44:07so.

44:07>> Mr. Chair.

44:08>> Councilor Picillo.

44:09>> Thank you, Mr. Chair. Move to approve

44:11the proposed storm water bond in the

44:13amount of $6,300,000.

44:15>> Thank you, Councilor Picillo. Motion's

44:17been made made made and I will second

44:19that to approve order number 109766

44:22proposed storm water bond and the

44:25appropriation amount of $6,300,000

44:27for the design, construction, and

44:29improvement of the storm water drainage

44:30and related municipal infrastructure.

44:32Any further discussion?

44:34Councilor Duso.

44:35>> Thank you very much, Mr. Chair. Just for

44:37a clarification, there is no state

44:40coverage of this expense. This is all on

44:42us, right?

44:42>> That is correct.

44:43>> Okay. Just

44:44wanted to confirm that. Thank you.

44:45>> as President Assing mentioned earlier,

44:47too, and engineer to prove that these

44:48things that needed to be done

44:50uh prior to this.

44:51>> Yeah, completely understandable. Yes.

44:53Okay.

44:53>> Thank you, Councilor Duso.

44:54>> Yep.

44:56>> Motion's been made and seconded. All in

44:57favor? 1 2 3 4 5. That carries with a

45:01suspension, Councilor Chair.

45:03>> to ask. Thank you, Mr. Chair.

45:04>> so much, thank you so much, Picillo.

45:06Councilor Picillo.

45:08With that said, I will entertain a

45:10motion to adjourn.

45:12>> Mr. Chair.

45:13>> Councilor Byrnes.

45:14>> Motion to adjourn.

45:15>> Motion's been made and seconded to

45:17adjourn. All in favor? 1 2 3 4 5. We are

45:21adjourned at 7:15 p.m. Thank you.