2026-10-15 - Citizens' Advisory Board

Summary

Built from the posted tentative agenda and the City's video auto-generated captions (about 100 minutes); names and numbers may be misspelled. Minutes are not yet posted.

  • The September 17 minutes were approved by roll call, and the meeting adjourned by roll call.
  • Financial report on the half-cent Spring Forward SGF sales tax: first-year collections of about $7.2 million; FY26 revenue of almost $33 million against a $32,322,000 budget; FY27 projected at $34,182,000, with about $3 million collected so far because receipts lag two months. A 4% overhead fee is paid to the general fund. A $15 million commitment to the Art Museum is planned for FY28.
  • Staff issued a request for proposals for a program manager consultant team to support Spring Forward SGF and received five proposals. The estimated fee is $500,000 to $1 million. Board members questioned cost versus project spending, whether it is an eligible use of voter-approved funds, and whether Council approval is needed. No action was requested. See Spring Forward SGF Program Manager.
  • Parks and greenways: master plans for five parks (Park Master Plans for Five Parks, $500,000, completion targeted around May 2027); the McDaniel Park inclusive playground (about $800,000, $650,000 from the half-cent tax, construction after the new year; see McDaniel Park Improvement Donations); a roughly $3.6 million Meader Park pickleball complex; Lafayette Park improvements of about $1.4 million; and $850,000 for Dickerson Park Zoo, including a bald eagle exhibit and playground.
  • Trails: $4.3 million approved earlier in 2026, with $1.8 million for the Chadwick Flyer (awaiting rail corridor acquisition), $1 million for Grant Avenue North design, $1 million for an opportunity fund and $500,000 for a Frisco High Line connector study.
  • Art Museum: the construction manager's preliminary guaranteed maximum price came in over budget because of steel lead times, tariffs and fuel costs; the team was value-engineering and projected completion slipping from January 2028 to about June 2028. See Art Museum Phase Two Construction Contract.
  • Neighborhood plans: $500,000 for plans for all 26 registered neighborhoods, done simultaneously over 18 to 24 months by a consultant team, with a first visit on November 9.
  • Next meetings: November to cover community applications, the expo center, city projects and corridors; December to cover economic vitality and housing. A joint meeting with Council was discussed.

Agenda

  1. Roll Call
  2. Consideration of the September 17, 2026, Meeting Minutes
  3. Financial Report Presentation
  4. Program Manager Discussion
  5. Parks and Greenways Update
  6. Art Museum Update
  7. Neighborhood Plans Update
  8. Discussion regarding next steps
  9. Adjourn

Sources

Video

Watch the video

Transcript

No transcript: the recording is hosted on CityView, not YouTube, and no captions are available.

Transcript

These are Vimeo auto-generated captions; names and numbers may be misheard.

Transcript

00:01.24] All right. Good afternoon. Welcome, everyone.

00:04.26] We're at our appointed hour. I want to start off by just saying

00:08.08] happy Springfield Engineers Day.

00:11.10] Yay.

00:11.14] Many of you may not know, but-

00:12.92] That's all me

00:15.16] ... we're celebrating that today, and very thankful that Missouri State and Drury

00:19.10] both produce engineers here locally.

00:21.34] And

00:22.78] I am not an engineer, but I work alongside many talented folks,

00:26.72] and anyway, so I just thought I'd start that off.

00:29.20] Plus, we have many engineers that work with the city and are helping us with our

00:33.02] projects here. So,

00:35.74] if you see an engineer, pat them on the back today.

00:37.90] So, with that, we will call the meeting to order.

00:41.18] And, Ms. Greer, can you please do roll call?

00:45.26] Yes. Frederick?

00:46.76] Here.

00:47.96] Benetti?

00:48.80] Here.

00:49.34] Smart?

00:49.98] Here.

00:50.46] Volz?

00:51.00] Here.

00:51.56] Watson? Here. Forster?

00:53.44] Here.

00:54.06] Shaunt?

00:54.62] Here.

00:55.52] Lee?

00:56.14] Here.

00:56.80] Wherley?

00:57.42] Here.

00:58.96] All right. You were sent the September 17th meeting

01:02.68] minutes.

01:05.04] Just with that, are there any corrections or questions

01:08.92] on those?

01:13.04] Hearing none, is there a motion to approve as presented?

01:15.80] I'll make a motion to approve them.

01:17.86] Second.

01:18.52] Second.

01:20.10] Any further discussion? All those in favor say aye.

01:23.24] Aye.

01:23.84] Opposed, nay.

01:25.18] You have to do roll call.

01:26.16] I'm sorry. That's it.

01:29.44] Benetti?

01:32.10] Aye.

01:32.90] Smart?

01:33.62] Yes.

01:34.08] Volz?

01:34.68] Yes.

01:35.08] Watson? Yes. Forster?

01:36.94] Yes.

01:37.36] Shaunt?

01:38.00] Yes.

01:38.44] Lee?

01:39.38] Yes.

01:39.52] Wherley?

01:40.54] Yes.

01:42.30] I promise I'll do better on that. It's a hard habit to break after

01:46.40] many years of nonprofits, so.

01:48.84] All right. With that, we have Mr. Holtmann here to

01:52.44] provide us our financial report presentation and update on where

01:56.44] we stand with collections.

02:00.70] Good afternoon. My name's David Holtmann, and I'm the city's

02:04.28] finance director. You should all have a schedule here that

02:08.08] recaps the last two and a half years' worth of

02:12.40] activity for this new sales tax that went into effect

02:16.78] April 1 of 2024,

02:21.36] after our three-quarter cent police, fire, and pension tax

02:24.86] expired.

02:26.86] You can see in the first year, the first orange column, we collected about

02:31.18] $7.2 million.

02:35.18] In fiscal 26, starting out in the green column,

02:39.74] we show what our budgeted revenue was projected at

02:43.12] $32,322,000.

02:47.18] Good news for last year, we collected about

02:51.14] 600,000 more than that, right at almost $33

02:55.14] million in total. The other thing that we also have

02:59.16] identified here is we had about three quarters of a million dollars worth of

03:03.20] interest revenue. So,

03:06.12] in the green column, you can see

03:09.78] under the projects,

03:13.30] underneath the revenue items, you can see the

03:17.06] different allocations that were recommended

03:20.36] by CAB and were approved by City Council.

03:24.46] There was about $32.9 million

03:28.48] worth of expenses,

03:30.82] expenditures that were approved.

03:33.86] To date,

03:35.68] only

03:37.16] $1.4 million of that had

03:40.94] actually been spent. The rest of that is carried over into

03:44.26] the current year.

03:47.02] So, moving into the current year, fiscal 27,

03:51.84] our revenue projections

03:55.34] were to increase the sales tax to

03:57.22] $34,182,000.

04:01.92] To date, we've only collected

04:04.34] about $3 million of that. There's a two-month lag

04:07.68] for our sales tax to be received by the city.

04:11.36] And

04:13.54] the items of interest that

04:16.84] have already been recommended by

04:20.90] CAB and approved by City Council,

04:24.88] you can see we have about

04:26.08] $34,182,000

04:29.96] that has been allocated,

04:33.06] including the very last item that's highlighted in

04:36.78] yellow. That's for the Neighborhood Plus program.

04:41.02] That was brought before City Council Monday night

04:45.38] and is pending approval at the next City Council meeting.

04:49.28] So, I wanted to include that in there so you could see what those totals

04:53.20] were

04:54.40] with

04:55.42] that last recommendation anyway.

04:58.70] So, all that to say, looking at the bottom of the

05:02.48] page,

05:04.22] to see what has not been allocated

05:07.88] in total for this fund, and we have just under

05:11.76] $40 million worth of fund balance at the end of fiscal

05:15.40] 26.

05:17.36] We have about $6.8 million

05:20.32] in our reserve

05:22.06] that

05:23.28] we typically target for

05:25.92] funds that

05:28.84] we have

05:30.68] operating expenses in. This one's a little bit different.

05:34.10] So,

05:35.24] that's something that could be considered at a later date

05:39.24] as we get closer to the end of the 10-year term of

05:43.12] this program.

05:46.14] We had about $31.5 million from fiscal

05:50.18] 26 that had

05:52.22] not been expended.

05:54.18] They had been allocated but not expended.

05:56.80] And then in the current year, we have $2 million remaining that

06:00.70] has not been

06:02.38] allocated.

06:04.22] Totaled up just under

06:06.16] $3,180,000

06:09.38] for

06:10.84] funds remaining

06:12.94] in the current fiscal year. So

06:15.64] I went through that quickly.

06:17.54] I'd be happy to take any questions that anyone might have.

06:22.92] Yes, sir.

06:24.24] What's the overhead fee? Where does that go?

06:27.64] Yeah, that goes back to pay for all of the support services that are

06:31.44] provided by the general fund.

06:35.10] Like, for example?

06:36.70] Like city attorney's office, finance,

06:40.86] city manager's office, all of

06:43.60] the administrative activities that are conducted.

06:48.08] We have a cost

06:50.16] allocation study done

06:52.94] that

06:54.26] indicates what our

06:56.72] overhead costs are, and that's what that represents.

07:01.14] What's the percentage?

07:02.84] 4%.

07:03.64] 4%. Okay.

07:05.04] So further question on administrative services.

07:08.26] Is that,

07:10.00] other than staff, what do you call administrative services?

07:15.96] So really the cost to run the city, what we do is we take a

07:19.86] look at

07:21.70] all of the administrative costs,

07:24.28] and try to allocate that out by function, based on the

07:28.26] efforts that's been placed into that activity.

07:33.02] We can provide the board more detail on this.

07:35.44] We

07:36.46] do this with all of our funds, and we have a cost allocation model for that, and

07:40.44] it does represent 4%.

07:41.28] We have, yeah. So this last time we had...

07:44.78] I'm trying to think who did that.

07:45.90] It wasn't KPM, no.

07:49.28] We just recently updated-

07:50.50] I don't believe it was Forvis, but it was our internal audit firm that

07:54.36] performed the cost study, gave us an active

07:57.82] worksheet that we can adjust each year,

08:01.60] with that in mind, being able to go back and update it on a 5 to

08:05.64] 10 year basis. So

08:09.44] good questions.

08:11.70] I don't believe that overhead fee was in the prior financial information

08:15.62] we got last year, was it?

08:18.34] When we were getting regular updates, I don't think it was listed.

08:22.36] I don't think it was listed as an expense, so we didn't show it this way.

08:25.84] We just showed the available revenues, and so I think it was taken off the top of

08:29.10] available revenues, and so it was always there, but it wasn't listed out in the

08:32.73] financials like this.

08:34.88] Okay.

08:35.73] Because we do fund accounting with governmental accounting, we're very siloed on

08:39.70] how we approach these things, whether it's quarter cent, eighth cent.

08:44.84] There's the cost allocation of the general fund, it's assigned a certain percentage

08:48.60] of the cost across the board since everything is siloed.

08:52.00] So that's why we do the fund accounting, cost accounting

08:55.76] study, and we follow that model, and

08:59.70] we'll provide that information. But yeah, it was there last year.

09:02.46] It just was basically off the top, and it wasn't part of the

09:06.08] allocation process because it wasn't included.

09:13.94] We've been looking at a three-year planning horizon.

09:17.24] And so you've looked at the first-

09:20.48] I believe the first two years

09:22.60] ... first two years plus a quarter.

09:25.46] If we were to add the next fiscal year to that,

09:29.40] it would roughly be probably about $35 million more,

09:33.66] given that this next year's about $34 million.

09:36.56] Yeah.

09:37.94] Okay.

09:40.36] So one thing to keep in mind, you all did make the

09:44.22] recommendation for the second half of the art museum

09:48.00] contribution. So that represents a pretty good chunk of

09:52.04] fiscal '28's revenue at $15 million.

09:56.06] So you can see the middle of the page, our art museum project, we just showed in

09:59.98] parentheses FY28 commitment of 15 million.

10:02.98] Since we're not yet in FY28 and it hasn't gone through the process

10:06.88] of it being formally part of the budget,

10:09.64] it's not listed here, because we're not showing FY28, but we want to make sure we

10:12.78] track that along. Council did approve the resolution

10:17.32] from the recommendation of this board, so that's something council's already

10:21.26] done in terms of resolving to fund that in the FY28 budget,

10:25.86] phase two.

10:27.18] Sure.

10:30.86] Are the funding for the neighborhood plans and parks

10:34.62] master plan,

10:37.48] not having that amount in the second column, does that mean

10:41.22] no

10:42.82] portion of that has been expended, just allocated?

10:46.98] Or all of that has already been allocated for both of those things?

10:51.70] So if you look at the far right column,

10:54.78] the last green column, that shows you what's remaining

10:59.14] in that particular line of funding.

11:02.32] Thank you.

11:02.62] Beyond the encumbrance. So we haven't yet spent that 406,000.

11:06.96] We've just started, and we'll get an update on neighborhood plans.

11:09.44] Just started with the consultant on that.

11:11.34] Right.

11:12.50] But we've encumbered those funds.

11:13.66] Got it. Thank you.

11:18.18] Any other questions?

11:20.78] David, thank you for the update.

11:23.08] Thank you.

11:23.50] This is the first of a series of updates that we'll be

11:27.04] providing on activity that

11:30.30] we've had from

11:32.22] over the past year. But for our new folks, let us know if you

11:36.20] have questions.

11:38.20] We can also,

11:40.12] toward the end of the meeting as we look at next steps,

11:43.28] hear from you all as far as,

11:46.00] do we need to schedule a supplemental

11:49.22] orientation or deeper dives into some of these.

11:52.96] So we'll see how the conversations go.

11:55.22] But we want to make sure you feel like you're up to speed on these projects

11:59.24] and

12:01.14] so

12:02.42] it'll take a little bit over the next couple of meetings, but we'll get everybody

12:06.76] to the same level here. Okay?

12:09.24] All right, let's go ahead and we have a program manager

12:12.80] discussion. Tim Rosenberry will be leading this, so Tim?

12:16.36] Thank you.

12:20.60] You have, as a handout,

12:23.80] an outline.

12:26.92] It's titled Summary of Requested Services of a Program Manager.

12:31.86] And

12:33.32] this text is just simply an edited down

12:38.42] version of what was included in the request for

12:41.88] proposals that the city issued

12:45.26] within the last 30 days.

12:48.38] And

12:50.86] this first paragraph, I guess, is worth reading.

12:53.40] It says, "A program manager will provide program-specific

12:56.82] services to assist in the development and management of Spring Forward

13:00.80] SGF." We're looking for people who have

13:06.00] consulted to municipal agencies on a multi-year,

13:10.08] multi-project capital programs intended to

13:13.80] produce transformational results through investments of

13:17.30] unprecedented quality and scope.

13:19.62] So this is a really special

13:21.90] project, and we need a really special consultant who's been

13:25.42] around these kind of projects before.

13:29.20] The program manager, we're asking them to essentially do three

13:32.94] things, to provide some administrative services,

13:37.38] to

13:39.52] help you all and city staff and city council

13:44.32] do program project identification,

13:47.90] and then to do an implementation plan.

13:52.98] So

13:54.50] under the administrative support services, one of the things we're going to ask

13:58.38] them to do is to participate in all

14:02.42] CAB meetings in person.

14:05.54] So you will

14:07.72] hear from them, and they will hear from you.

14:12.34] And the cadence of their work is probably going to be monthly, because

14:16.36] if you see

14:18.38] paragraph

14:19.80] 1D,

14:21.52] they're going to be reporting back monthly.

14:25.16] So,

14:28.70] their administrative support services are

14:31.88] primarily

14:34.74] coordinating staff, coordinating the public

14:38.76] input, coordinating you all's input, and coordinating

14:42.64] council.

14:48.38] Regarding program project identification

14:55.04] , the program manager will be asked to

14:57.80] be the person to put that log

15:00.70] of projects together,

15:02.70] to

15:05.96] build that catalog of all the projects that have been

15:09.78] suggested from the community, from staff, from CAB,

15:14.06] from council.

15:15.58] And that is an ongoing effort.

15:20.22] Then we're

15:21.64] asking them to be a pre-screener

15:25.38] of each of those projects

15:28.36] and to help us develop a clear

15:33.06] set of criteria,

15:35.36] which has

15:37.00] already been developed in large part, but it needs to be rounded out,

15:41.00] I think.

15:42.70] And then do the research on each

15:46.72] project and then to,

15:50.80] as it says in item D, formulate a screening method for projects

15:54.74] to be reviewed and recommended by you all.

16:00.38] Then

16:01.48] from your recommendation, it goes into the

16:04.72] implementation plan if council approves.

16:08.50] And so that's the next thing is item implementation plan

16:11.82] preparation.

16:13.74] And

16:14.96] I would just go to the last two bullets under

16:18.74] paragraph A,

16:20.90] and these show up at the top of the second page where

16:25.16] this

16:28.50] implementation plan would have project

16:31.86] descriptions of each one,

16:34.24] including the scope of work.

16:37.20] And then

16:39.98] some will have sub-projects, much like the neighborhood works that you all

16:43.62] approved last month.

16:47.38] And then

16:50.10] we need to be able to just have that all in one

16:53.94] place, in one catalog. We also want those project

16:57.86] budgets organized or broken down into

17:01.56] major cost categories.

17:06.02] It's important also to have a program schedule, particularly when we think about

17:09.90] the cash flow of this project. And that's

17:13.84] what this, in paragraph B, the second sentence

17:17.60] makes clear is that to the offerors

17:21.32] that we're asking for a cash available

17:24.96] approach

17:26.38] and sequencing the project so that

17:31.40] we can deliver what's been asked for on time in

17:35.38] the right priority.

17:41.80] Oh, then

17:43.22] paragraph C, we're asking for an online tool

17:47.26] for real-time program reporting and scenario planning

17:51.48] so that

17:53.14] staff can use that

17:56.00] for project management,

17:58.78] that the PIO can use that for

18:03.28] communicating back out to the public where we are on the

18:06.84] project, and where the CAB and council can

18:10.74] use it just to know where the heck we are at any

18:13.66] one given time.

18:16.31] And then there are bullets there that describe

18:20.21] each of the things that we ask for in that.

18:26.91] The end result will probably be a

18:30.79] fairly thick document that shows the implementation

18:34.83] plan and the project schedule.

18:37.61] We've asked them to be able to deliver all that in the next 12 months,

18:43.25] and then to monitor it as we go

18:46.79] forward.

18:48.53] And this would be for the

18:51.33] entire 10-year tax.

18:54.73] Knowing that

18:56.61] we're looking at 10 whole years,

19:00.27] this very last sentence at the bottom of page two, it says, "It's acknowledged

19:04.21] that projects may not be fully identified for the final

19:08.15] three years of the tax, and in that case, the

19:11.39] implementation plan may include placeholder projects in

19:15.27] lieu of fully

19:17.13] identified initiatives."

19:19.45] So, this is what we've asked

19:21.93] consulting firms to

19:26.85] propose these services. We've received

19:30.43] five proposals or proposals from five

19:34.25] firms,

19:35.45] and we are still in the process of evaluating those

19:39.41] proposals.

19:43.29] What questions do you all have of Tim?

19:48.93] Is there a part in this process where we're

19:52.33] able to ask questions to the firms that are being considered?

19:56.69] This

19:57.73] is an extension of staff, and typically,

20:01.15] boards aren't involved in

20:04.45] selecting consultants. So,

20:08.89] I don't know that there will be that chance.

20:13.07] You view this as a consulting arrangement, not an employee?

20:16.31] That is correct. What we're

20:19.91] ideally looking for is a firm that has done this.

20:24.51] And the

20:25.79] difference is this is managing the program but not managing the projects.

20:29.41] The individual projects would be managed by the city?

20:31.67] That's correct.

20:35.81] And that's a great distinction, Jeff.

20:37.35] That is the key way to distinguish

20:42.47] where their services end and where the-

20:46.45] City staff, yeah

20:47.91] ... city staff picks up on a solo basis.

20:51.29] So we've been at this for almost two years.

20:55.63] Why do we think this is necessary now

20:59.21] when we've been operating without it?

21:03.51] I'll

21:05.99] invite others to

21:08.07] state why it's useful.

21:12.17] But

21:13.27] I'll offer what I think, Cliff, is that

21:17.65] I feel like

21:20.55] we need more guidance from people with this kind of

21:24.49] experience. When I say we, city staff does.

21:29.19] For example, the MAPS program, which has often been used as a

21:33.05] reference to this,

21:36.41] Oklahoma City has a city staff focused

21:40.37] on MAPS of 16 people,

21:44.19] and they have a consultant that does this work.

21:48.91] And so

21:52.77] this has been a challenge for city staff,

21:57.01] frankly,

21:59.15] for us to be able to do this work adequately and

22:02.65] effectively, and at the same time, do our daily

22:06.67] work that

22:08.23] we're doing.

22:09.93] And I think that after we saw how

22:13.87] the Neighborhood Works program

22:17.09] was accelerated by having an outside consultant involved,

22:21.85] that that made a difference, and that we

22:25.41] believe that doing that for the entire program could make a difference.

22:30.21] Would it take a significant amount of work off the

22:34.25] plates of the people who

22:36.69] are in the room and who have been supporting us?

22:39.03] So I jump off that, what Tim said, the last part's really accurate, that

22:42.67] it's been a significant

22:45.09] amount of work for staff that already have full-time jobs. It's been a big lift.

22:50.59] I see some of that shifting a little bit with bringing in someone

22:54.89] or a firm or a group that can focus on this full time.

22:59.47] And

23:00.55] I think there'll still be a lot of time working with staff because we've

23:04.47] got a lot of

23:06.43] heavy staff involvement in this, but the actual coordination and scheduling and

23:10.39] all of the things that need to take place, I think will be

23:14.99] a shifting of the burden from staff to an extension of

23:18.85] staff. And so we're able to be able to assist them.

23:22.37] We'll be heavily involved, or have to be, as we go through each of the

23:26.45] plans as we present those to council or to the board here.

23:30.31] But,

23:32.03] I think there'll be a shifting and kind of expansion of our capabilities and

23:36.49] to serve this board in a way that's hands-on 100% full

23:40.17] time.

23:43.17] I have no expertise in this area, but I would say one recommendation

23:46.97] is to track that.

23:49.05] Figure out a way, once you have determined who the consultant is and they're doing

23:52.73] the program management, figure out some sort of mechanism to assess how

23:56.59] much load you lifted off city employees.

24:00.29] Because at some point in time, someone's going to ask the question, particularly if

24:03.13] the funding for this comes out of the tax.

24:05.41] Right.

24:08.97] Just to clarify, that is the intent, is the funding for this consultant would

24:12.65] come out of the resources here, and what's your

24:16.41] estimate for the services?

24:19.63] I'm guessing anywhere between a half a million and a million dollars

24:23.72] Every year?

24:25.22] No, for this scope of work.

24:28.50] Okay.

24:28.58] Yeah.

24:30.12] Well, then I would redouble my resolution that-

24:32.64] Yeah

24:32.92] ... you track the

24:34.72] effective

24:37.82] deliverable in terms of freeing up the city on the projects in

24:41.58] whatever mechanism makes sense to you all.

24:42.34] I think that's a good point.

24:43.94] Do you mean the million over the 10 years?

24:47.16] Or could you re-explain what-

24:49.84] Yeah

24:49.98] ... your answer was to Jack?

24:51.16] Yeah. This is to formulate a 10-year plan.

24:54.28] Okay.

24:55.58] And

24:57.00] I'm estimating the fee to be somewhere between half a million

25:01.54] to a million dollars to do all of that work.

25:06.08] That would be paid in the first year.

25:08.20] It would likely be paid, yeah. Yes, in the first

25:12.12] year.

25:12.60] To the firm that you end up hiring.

25:14.36] Correct.

25:14.82] Do you anticipate this person to get more of

25:18.44] the community's projects on board, that we haven't seen a

25:22.38] lot

25:23.84] of projects. Do you anticipate that too?

25:26.40] Yes. That is one of the differences I expect to see out of

25:30.42] using this role.

25:39.64] Without seeing the proposals,

25:43.18] one of the things is looking at the value add, and

25:47.08] what do they bring to the table that

25:49.50] we'll get a million dollars plus in value out of their

25:53.54] services. And can you talk more about what you would anticipate

25:58.28] that you would see?

26:00.60] Are projects going farther? Or-

26:02.54] Yeah

26:02.54] ... some more tangible examples?

26:04.34] Yes.

26:06.74] I think, for example,

26:09.86] a firm that has done this for other cities, other

26:13.56] communities, can bring that knowledge of what they learned

26:17.48] to this. Sometimes,

26:20.38] at least speaking for myself, and my other colleagues may

26:25.16] have a similar kind of testimony,

26:27.66] is that I feel like I've been sometimes kind of

26:31.24] going in the dark, because this is

26:34.84] a new approach for us.

26:38.52] And

26:40.16] quite often, we

26:44.14] know what the project is before it's funded.

26:46.98] Now we have something that's funded, but we don't know what the project

26:50.86] is. And so this has been part of the challenge,

26:55.12] and the burden for me is to make sure that

26:58.96] we're, and for you all, clearly, and council, for all of us,

27:02.94] is to make sure that

27:06.72] we're spending every bit of money wisely.

27:10.76] I believe this is a wise expenditure given how small

27:14.54] a percentage it is of the total to bring in

27:18.44] outside expertise, both in terms of how these kind

27:22.52] of programs are run and

27:27.82] who's been through

27:31.08] the pitfalls of this kind

27:34.42] of program.

27:36.00] So

27:38.34] that's why I think this makes sense.

27:44.48] So I just want to--

27:46.98] Looking at the Neighborhood Works Plus

27:50.50] project that went out and all of the responses that came, we see

27:54.34] that there is requests for projects more than what even our

27:58.50] 30 million a year would be.

28:01.02] Oh, yeah.

28:01.30] So there's lots of projects that the community wants, but this

28:05.30] specific 30 million is designated from the ballot

28:08.98] language into three different categories.

28:11.76] So we have to be very specific, right?

28:14.16] We can't just, "Oh, this part of town wants

28:17.96] this infrastructure done over here," so we can't use that

28:21.62] half-cent to do just random

28:25.34] projects.

28:26.04] Yeah.

28:26.32] Because we have many projects that we need to do.

28:29.96] So we're going to be real specific on our three categories,

28:33.76] right?

28:35.14] I'll jump in on that.

28:37.36] Council's approved the ordinance for the Citizen Advisory Board.

28:41.22] It's the same

28:43.00] 11 criteria that you've kind of gotten used to seeing.

28:46.64] The eight original and three additional criteria. It's not a granting program.

28:50.98] It should meet those three categories.

28:53.78] They're kind of large categories, capital projects that are

28:56.92] transformational-

28:57.94] Yeah

28:57.94] ... neighborhood improvement projects, and parks and trails.

29:00.76] So that's still a focus. It's voter approved that way. It has to be that way.

29:04.74] It will be that way. That's what the consultant, if we go that way, has

29:08.50] to make sure they plug in.

29:10.22] Okay.

29:10.30] That they're going to take all those ideas that maybe we haven't seen some ideas.

29:14.32] We do have a portal out there and

29:16.76] had some limited interaction with the portal and providing input from

29:20.58] citizens on projects, but it isn't a granting program.

29:23.66] It's not giving money for projects that are just simply out there.

29:27.60] This is specific to those three categories.

29:29.50] It has to be in that area, and it has to be one of those three categories.

29:32.20] Good. That's what I wanted to clarify. Thank you.

29:35.88] So

29:37.18] I could wait and do this during discussion, but I want to give you a chance to

29:40.76] respond.

29:44.96] I have some concern over spending money like this.

29:49.88] When you recognize that

29:52.68] we're already paying $1.3 million for

29:56.26] staffing

29:57.74] per year here,

29:59.88] now you're adding another $750,000 to

30:03.78] that.

30:05.00] One concern is the people out there that voted for this

30:09.46] hate to spend money on this kind of thing.

30:12.70] Even though I would concede it has some value.

30:16.10] You spend money on marketing, you spend money on administrative costs.

30:20.22] It's

30:21.58] money that's not going into a project.

30:23.74] Yeah.

30:25.12] And so to Becky's point, we got a lot of projects.

30:29.48] We got arts projects, we got trails projects, we got

30:33.12] parks projects, we got street improvement projects.

30:39.78] I have a real concern that this both won't be supported generally and

30:43.78] will be thought of as being wasteful, that we have in-house people that we're

30:47.56] already having money allocated to help us with this.

30:50.96] We've been working for a couple of years.

30:52.74] We haven't had any problem allocating money.

30:56.64] Frankly, why wouldn't I, as a board member, rather have 750

31:00.62] grand go into improving a park

31:03.66] than hiring a consultant to tell me, "Well, we ought to improve a park"?

31:09.90] Yeah. I

31:11.66] have a hard time responding to that

31:15.14] other than

31:16.46] I hear you.

31:22.48] I guess the measure of how much

31:26.42] time that it takes staff away from other things that should

31:30.44] be being taken care of. I'm just curious

31:34.38] also why we need an additional consultant, unless it

31:38.30] indeed is going to make life much better

31:42.36] for the rest of you guys to

31:45.76] do what you're sitting on your desks to do.

31:50.22] So

31:52.24] I'll try to answer that. I don't know if I can answer it really much better than I

31:55.28] did before. It's been a heavy lift.

31:58.66] Every month-

31:59.04] It's been a problem

31:59.12] ... having a meeting and preparing for that, but it's part of our job to make sure

32:02.74] that we're presenting to the board what you want to be

32:06.66] seeing, and to help you make decisions, providing that

32:10.32] information you're asking for to make those decisions.

32:14.52] I see it shifting a little bit. I do see a tremendous amount of staff work still

32:18.40] needed because,

32:20.68] if you're talking about parks or an art museum or trails or

32:25.88] road improvement, beautification projects, enhancements, and

32:29.58] neighborhood issues, it's going to take a lot of staff work, and

32:33.74] we're still going to be heavily involved in that. I don't know.

32:37.30] It's hard to know now in advance exactly what kind of a

32:40.72] shift of the burden will be there.

32:45.68] That's hard to answer. Yes.

32:48.80] Would you anticipate seeing some cost savings on the overhead

32:52.78] fee?

32:54.66] Yeah, I was thinking-

32:55.38] Would it come out as a wash to some extent?

32:56.44] I was thinking we want to look at those categories for cost allocation.

32:59.96] We want to make sure we're not duplicating it.

33:02.40] If it's a shift to somebody somewhere else, I don't know if it

33:06.40] really will be that much in terms of the cost allocation study and

33:10.12] the overhead that is necessary, but we'll want to look at that.

33:14.32] Yeah.

33:14.60] I guess the other question I'd have for this person or group of

33:18.28] people,

33:20.50] their work, like this report you're talking about with the real-time program

33:23.96] reporting, is that something that's going to be publicly available?

33:26.42] Yes.

33:26.44] Or are those tools internally? So in theory, the community's going

33:30.36] to have a really good real-time update about as things are progressing?

33:34.60] It's the latter.

33:35.36] So it's a communication tool that way?

33:37.54] Yeah. That is public-facing as well as private

33:40.94] or internal

33:43.96] data reporting.

33:47.48] Okay, I have one more.

33:49.42] So since we've looked at Oklahoma City and their MAPS program and the

33:53.22] person that runs that,

33:55.70] can we hear any examples of how that

34:00.24] person really made that

34:04.02] impact on Oklahoma City? Do you know what I'm

34:07.64] getting at?

34:07.92] Yeah, I

34:09.54] do.

34:09.72] Can you help us make sense of the impact this will have?

34:14.00] Well,

34:16.08] I do know that the

34:18.00] program management consulting

34:21.74] firm on that has been the same one

34:25.16] for every one of the MAPS projects, and I think they're on

34:28.96] MAPS

34:30.22] four,

34:31.48] maybe.

34:33.42] And it's been for

34:36.30] multiple decades.

34:38.44] And

34:40.56] it's my understanding that

34:42.98] the consultant

34:45.64] also does

34:48.12] some project management.

34:52.16] But

34:53.60] a lot of this information

34:57.24] was derived from what we could find out from Oklahoma City

35:01.86] and the scope of work that

35:06.76] Oklahoma City, even with a MAPS

35:10.62] office on staff of 16 people,

35:14.54] still go out on a consulting basis for

35:18.40] this work.

35:20.16] I guess I'm trying to understand using Oklahoma City as an

35:23.76] example. Was this person instrumental in

35:27.82] changing their whole downtown design and-

35:30.74] I think the MAPS program has transformed Oklahoma City.

35:35.06] Okay.

35:36.84] No question about it, with Bricktown,

35:40.54] an arena, a minor

35:44.58] league ballpark, a new convention center.

35:50.78] Now doing trails and neighborhood improvements.

35:55.88] Oklahoma City even did something called MAPS for Schools.

36:01.06] Because the MAPS brand

36:03.76] over the decades had become so

36:06.42] trusted that

36:09.16] Oklahoma citizens,

36:11.82] I think, have come to expect it, and they see the

36:15.38] results.

36:18.66] So just to ask a more specific question, what I'm hearing is it's both the

36:22.64] amount of work and the level of expertise-

36:26.00] Correct

36:26.22] ... that the consultant would provide.

36:28.22] So once these two pages of deliverables are

36:31.60] accomplished

36:33.15] Is it then that the city could take on further work for

36:36.77] successive years, that the city could pick up this task and run with it?

36:40.59] Or we might be, a year or two years from now, entertaining

36:44.61] a motion to extend this contract in some way?

36:48.15] The way

36:50.17] the RFP was written was that

36:53.93] anything that's asked for after they

36:58.15] submit those deliverables will be considered additional

37:01.85] services.

37:05.41] And

37:06.85] the RFP was written in such a way that when they're done

37:10.89] with this,

37:12.77] we may not need them unless things change.

37:17.63] And if things change, then

37:21.59] we would either go back to them or staff could take care of it,

37:26.33] particularly with staff's exposure

37:29.21] to

37:30.85] what the-

37:32.37] And how they did

37:33.23] ... yeah, program manager did.

37:38.05] This may be a Colin or a Jordan question,

37:42.35] because the ordinance and the ballot language was referenced.

37:45.71] Knowing how the ballot

37:47.83] language was written and the ordinance was written, is this a

37:51.45] legal use of these funds if not considered a project?

37:56.85] It says that...

37:58.91] I had actually pulled it up here.

38:06.13] And I'm not an attorney, so I don't pretend to know, but

38:08.95] You're pretty close, though, right?

38:21.59] I think funding projects

38:27.45] almost has to contemplate the overhead

38:30.51] that is

38:32.59] tied to that.

38:34.95] You have overhead in any construction project,

38:37.87] right?

38:42.07] I don't know if that is a short enough answer to the question.

38:44.59] Thank you.

38:45.35] We certainly can look in that a little deeper just to make sure that

38:49.57] it

38:50.55] fits that. It has to be a part of what voters approved.

38:54.91] So is this an action item today?

38:57.65] We are not asking for your approval because we

39:02.31] haven't finished vetting

39:04.25] the proposals.

39:08.69] Up to this point, I think we've leaned on our content experts

39:12.99] for parks and greenways, for the art museum, and others, and they've

39:16.79] been the experts out vetting those projects and then working with the

39:20.73] consultants, because they're on the front lines of these areas, and

39:24.65] they know what the needs are, and they are in the industry.

39:27.97] So we've depended on their expertise.

39:30.37] Plus, they're the ones that stand to gain the most by new parks and

39:34.15] greenways and new art museum. So they have a

39:37.87] significant amount of skin in the game.

39:40.19] That's where our focus has been up to this point.

39:43.43] I think

39:44.59] now that this has been out here and we've had a chance to hear some of the

39:48.41] pros and cons, maybe you can go back and think

39:52.37] about some of the questions or concerns that were raised, and we can have it

39:56.37] on the agenda to talk about in our next meeting,

39:59.85] maybe ways to respond to some of those concerns.

40:02.83] I think we really want to maximize the value that

40:06.75] we have for these funds, and that

40:09.93] if a consultant can help us realize much more value,

40:13.63] then I think it's something to consider.

40:16.31] But we want to see as much go to benefit our

40:19.43] citizens as possible.

40:21.81] So,

40:24.37] trying to think through this,

40:30.41] and following up on Rusty's thought there, do we expect

40:34.31] this

40:36.17] brings us a plan

40:38.91] that says, "Here are eight projects

40:42.55] that we should fund over the course of the next

40:46.51] eight years?"

40:49.35] They're going to put a plan together that

40:52.81] outlines the work generally to be done?

40:57.05] Or is it something less than that?

41:00.17] No, it's casting the vision with

41:04.59] specific

41:07.59] implementation steps over the 10-year period.

41:12.87] So that we know at the end of this work, we

41:16.49] know here's an expansion of youth sports,

41:20.21] here's meeting facilities, here's an outdoor arena,

41:24.67] here's X money for neighborhood projects, here are

41:28.49] four street beautification projects we're going to have done.

41:31.87] They're going to work to outline an overall plan?

41:34.69] And

41:36.05] here is the schedule for delivering them, and here's what the cash flow looks

41:40.05] like, and

41:42.29] all of those things, yes.

41:43.57] Okay.

41:44.77] Yes.

41:45.35] So rather than us taking it

41:50.53] project by project or trail project by trail

41:54.17] project, this person is going to integrate all of that

41:57.73] thing into one big plan, one big project

42:02.07] that we'll then approve as they come up and as we knock them off?

42:05.99] I think the way the consultant will work, Cliff, is they will be

42:09.85] meeting with you monthly, and you all together will be building

42:13.87] that 10-year stack.

42:15.77] Over the course of the next year?

42:17.39] Correct.

42:19.87] Okay. One last thought.

42:22.85] So since the funds for this consultant will be

42:26.64] Part of the funds from the half-cent tax.

42:30.36] Is that something that has to be approved with council?

42:32.50] Will this position have to go to council for approval?

42:36.22] It's not a position, so no, it wouldn't require council approval.

42:39.46] Okay, so it doesn't require us saying, "Yeah, let's spend some of our money

42:43.46] on a consultant," and then that doesn't have to go?

42:45.72] Well, I may have answered too quickly. We need to make sure.

42:49.88] Previously, we had approvals for

42:52.78] bringing on a consultant to work with

42:55.78] parks and others, so. But that was expenditure of your fund, so we need to

42:59.80] vet that fully. I may have answered too quickly.

43:02.54] The

43:03.54] proposals that I've seen,

43:05.60] just looking through their proposed personnel,

43:09.84] is they're proposing teams of at least

43:14.14] five, maybe even 10 people to work on this project.

43:18.34] And so when we talk about this program manager, we're not talking

43:22.36] about a person-

43:23.38] Okay

43:23.38] ... we're talking about a team of experts.

43:26.48] Okay.

43:26.54] That's helpful.

43:27.26] People who

43:28.92] are involved in city planning, in capital budgeting,

43:32.92] in urban design, in facilities.

43:39.36] When I talk about bringing in expertise, it's not one expert,

43:42.94] it's a team of experts.

43:45.02] That's helpful.

43:46.12] Right. So as far as being an action item, it's not

43:51.00] hiring or making this decision, or saying, "Yes, spend the money for this

43:54.52] position." We don't need to make a decision on-

43:56.98] We're not asking for anything from you today.

43:59.70] Okay.

44:01.04] But your questions have been tremendous.

44:03.80] But I think you would want to know that if the sense of the room

44:07.54] is, we don't want to fund this.

44:09.46] Yeah.

44:10.16] Right? You need to know that, otherwise

44:13.16] you're wasting time.

44:14.34] Right.

44:15.78] I've heard you.

44:17.22] Exactly.

44:18.14] And it may be possible, I don't want to put words in your mouth, but it may be

44:20.62] possible that some amount of the funding could be taken out of the 4% overhead.

44:24.74] We'll look at that.

44:27.24] We certainly don't want any duplication of what overhead

44:31.02] is being provided, it could be removed from that. We'll look at that. Yes.

44:34.58] So the only thing I would point out on that, though, is

44:37.98] it costs money to

44:40.42] make things happen.

44:42.46] And the assumption that it can just happen at the cost of another

44:46.06] program, that's not the board's role here, that's

44:49.92] city council.

44:51.94] So,

44:53.36] I say that as the protector of the general fund and of

44:57.44] all city budgets.

45:00.14] We can't pass that cost onto something else, and

45:04.02] that's what I just want to leave with this board.

45:08.00] With that in mind, and understanding that this is a unique program then, is there

45:11.06] also just an example of when the city has gone into a similar

45:14.52] consulting relationship that we could even just see and understand

45:18.44] what the impact would be, and how that would work?

45:20.32] Well, and certainly, I think Tim mentioned it, Neighborhood Works+, just

45:24.40] is a microcosm of what that looks like at the neighborhood project level,

45:28.98] which was very successful in bringing those plans

45:32.86] forward, those projects forward, vetting those projects, having multiple

45:35.80] neighborhood meetings, bringing that proposal back here for

45:40.08] the $5 million and then bringing it to council.

45:42.32] Putting that together, that's been a very successful working relationship

45:46.30] with that consultant.

45:48.80] So I guess that's probably the closest example to this, perhaps.

45:53.64] Tim, I don't know if there's others?

45:55.14] We probably have a lot of ones, others, but that's the closest.

45:58.06] Has Public Works retained consultants to design whole

46:02.00] programs or...

46:03.02] Not on the program level. For us, mostly it

46:06.88] is designing specific projects.

46:11.02] All right, well appreciate everyone's feedback.

46:13.56] We have this information.

46:16.90] If you have additional questions, let us know, but we'll have this on the agenda

46:20.08] for next meeting. So thank you, Tim.

46:21.56] Thank you.

46:22.68] All right, let's go ahead and proceed.

46:24.38] We have our next update that we will get from Parks and Greenways, and Ron

46:28.26] Schneider is going to kick that off. Ron?

46:38.76] Greetings, everyone. My name is Ron Schneider, I'm the director of parks for the

46:42.80] Springfield-Greene County Park Board, and I was asked to give

46:46.78] an update on the parks and trails projects that have been

46:50.50] funded so far,

46:52.64] recommended by the Citizens Advisory Board, approved by city

46:56.28] council earlier this year. With me today

47:00.32] is Ben Tegeler, who's going to talk specifically about the trails

47:03.74] projects, and then Jackson Thompson is also here

47:07.62] from the Dickerson Park Zoo. So I think distributed

47:11.54] to each of you is a list of all the parks and trails projects that

47:15.50] have already been approved.

47:18.38] In that spreadsheet is the total project

47:21.86] amount for each project, the amount that's been

47:25.76] allocated by CAB to go towards that project, and then if it's a

47:29.30] continuation project,

47:31.92] it has prior investments noted for each

47:35.58] project, and then our estimated timeline of

47:38.88] completing each of those projects.

47:41.36] So,

47:42.74] I'm going to run through each of them individually, at least the park projects, and

47:45.92] then I'm going to turn it over to Ben.

47:47.70] So over $11 million has been allocated so far towards parks and

47:51.68] trails projects. Beginning with the park

47:55.74] master plan development, and this is for five

47:59.70] of our most beloved parks, including Sequoyah Fast Night,

48:04.05] Silver Springs, Grant Beach, and Nathaniel Green Close

48:07.91] Memorial Park. The primary objective of these plans is

48:11.87] to shape the future of the parks through extensive public

48:15.79] engagement and stakeholder input that will provide a roadmap

48:19.81] for future improvements. So $500,000 in funding

48:23.77] was approved for this initiative.

48:25.75] We went through an extensive request for qualifications

48:29.39] from

48:31.27] planning firms, landscape architects.

48:33.99] We had 13 responses, so really

48:37.89] a lot of interest in this project. Playing Designs Studio was hired to perform the

48:41.87] work, and they're actually doing interviews and

48:47.03] collecting data currently. So they're doing internal

48:50.65] stakeholder meetings, meaning they're meeting with our staff right now

48:54.51] to talk about maintenance, operations, and programming at each of those

48:58.41] parks. They have a multi-phase approach that includes data collection,

49:02.45] two rounds of public engagement,

49:05.75] visioning and concept development, and then master

49:09.53] plan adoption support. And we expect these plans to be completed

49:13.97] and delivered to the Park Board and City Council in the second

49:17.91] quarter of 2027. We're eyeing May

49:21.67] of next year for those plans to be completed and presented.

49:25.87] The second project on your list is the inclusive playground at

49:29.53] McDaniel Park.

49:31.35] This was the third phase of planned improvements at McDaniel Park.

49:35.43] Phase one and two included the addition of a new bicycle pump

49:39.47] track, which is being donated by the Trail Spring

49:42.65] organization.

49:44.47] And phase two

49:46.37] was the construction of a very nice pavilion and

49:50.23] restroom facility that will serve the park, and that was a

49:53.67] donation from the Hatch Foundation.

49:56.07] So altogether, there is nearly $2 million in private

49:59.95] investment or donations that are going into the project at McDaniel

50:03.87] Park.

50:05.33] And phase three adds an

50:08.93] inclusive destination playground.

50:11.45] The estimated cost of that playground is $800,000,

50:15.35] with about $650,000 coming from the Half Cent

50:19.23] for SGF funding.

50:21.63] We recently went through a competitive bid process for the construction

50:25.75] of

50:27.43] the pavilion

50:29.33] and the site work for the park,

50:32.91] and just awarded the construction contract.

50:35.67] So we expect dirt to move on this project

50:39.59] fairly soon,

50:40.99] more likely right after the first of the year, once the contracts are

50:44.39] finalized, and we expect completion to be in probably

50:48.41] mid-summer, July or August of 2027.

50:51.57] So that's the first of the park projects that you'll really see dirt

50:55.55] moving on, so excited about that.

50:58.85] The third project is the Meader

51:01.45] Park Pickleball Complex,

51:03.93] and this project was roughly $3.6 million.

51:07.25] This replaces the existing

51:10.85] courts at Meader Park that are in poor condition.

51:14.27] As you recall, they are an adaptive reuse of old tennis courts.

51:17.75] So with this project, we fund

51:21.59] the construction of at least 16 dedicated

51:25.31] pickleball courts,

51:27.41] a restroom pavilion, which we currently do not have at that park,

51:31.91] site amenities that will support pickleball play and tournaments

51:35.53] there.

51:36.85] So a great project, very well received.

51:40.77] And we recently went through a competitive RFQ process

51:44.81] to hire a design firm for that project.

51:47.17] So we have Plane Design Studio who's helping with that, Own

51:50.97] Engineering, and Hood Rich Architects have teamed up

51:55.09] for that project. So

51:57.25] we expect to have final design in the second quarter of the summer of

52:01.25] 2027, followed by bid administration for the project,

52:05.17] and then tentatively, we're looking at construction starting in the fall of

52:09.25] 2027 and the project being completed in the spring of

52:12.87] 2028.

52:16.47] Improvements to Lafayette Park

52:20.17] is the next project on your list.

52:22.95] And in 2025, we engaged with

52:26.17] neighborhood residents, the neighborhood

52:29.53] association, other stakeholders to develop a master plan

52:33.59] for Lafayette Park. We did this in-house with our planning team.

52:38.25] Recommendations from the plan included updated walkways that were

52:42.19] ADA compliant, new playground equipment,

52:45.73] replacement of the old tennis court with a new tennis court, and combined with

52:49.71] pickleball,

52:51.11] new landscaping, signs, and site amenities.

52:54.13] So the total investment

52:56.35] in Lafayette Park would be roughly $1.4 million,

53:00.69] and we are working on final design for this project and

53:04.55] anticipate construction starting

53:07.23] probably late summer or early fall of 2027.

53:11.29] And then the last park project that I have to report on is the Dickerson Park

53:15.33] Zoo, which you funded $850,000 worth

53:19.25] of improvements there. That include the construction of a bald eagle exhibit,

53:23.51] installation of a new playground, and the development of a

53:27.49] master plan and strategic plan for the zoo that will lead

53:31.49] us through the next several years of potential improvements.

53:35.73] For the playground project, we recently solicited proposals for a

53:39.75] natural-themed playground that will complement the Tropical Asia animal

53:43.31] exhibit.

53:44.75] And staff is leveraging the $400,000 of CAB

53:48.53] funding with

53:50.99] donor support as well as

53:54.95] some grants that will expand what we could do with that playground project.

54:00.19] We expect completion of the new playground

54:04.29] To be completed in the summer of 2027.

54:09.47] And then our zoo crew is also working on a free-flight

54:13.49] bald eagle aviary that will house three fully flighted

54:16.93] eagles and incorporate natural features, immersive viewing,

54:21.17] and conservation-focused interpretation.

54:24.77] This habitat will be located right next to the bear exhibit,

54:28.95] which we just opened up a new boardwalk earlier this year.

54:32.81] So more great improvements coming to that area of the zoo.

54:36.81] And then last, we are just really getting started on the

54:41.09] master plan process, and we're still in the

54:44.67] RFQ stage of that, where we're putting together

54:48.77] a request for qualifications that will go out to

54:52.59] firms that could do this work on our behalf.

54:55.45] So with that being said,

54:58.43] that's the park projects that I have to report on.

55:00.85] I'll stay here and I guess turn it over to Ben to

55:04.75] present the trail projects, and then we'd be happy to take any questions you may

55:07.81] have.

55:09.25] Thanks.

55:12.63] Thanks, Ron.

55:13.21] Mm-hmm.

55:14.91] Like Ron said, I'm Ben Tegler. I'm the executive director of Ozark Greenways, and I

55:18.71] just want to reiterate the why of why I'm here from a trail

55:22.63] perspective. Trails have ranked in the top three of most of our park surveys

55:26.65] in the past five years, and it's a top 10 priority in our comprehensive plan

55:30.47] forward SGF of ungapping our map. While our network is strong and we have

55:34.49] a lot of greenway trails, the priority is being laser-focused on connecting those

55:38.39] gaps, connecting neighborhoods, parks, or commercial areas, and making this a

55:42.23] better place to live and a higher quality of place.

55:45.77] So from what was approved in February by city council, we had $4.3

55:49.59] million, 1.8 for the Chadwick Flyer.

55:52.01] That's for construction from the Kisik, where the power plant is north

55:56.05] to the Trail of Honor, so connecting that segment on the south.

55:59.87] We've got a million dollars for planning and design of Grant Avenue North from

56:03.37] where it terminates currently at College Street all the way north to Lost Hill

56:07.39] Park. That's about five miles all the way north and having

56:11.75] basically from Lost Hill Park all the way to Wonders of Wildlife and connecting

56:14.97] tons of neighborhoods, amenities, schools,

56:17.87] and commercial areas along that corridor.

56:20.69] We also got a million dollars for an Ungap the Map.

56:23.83] This is kind of an opportunity fund when we have small gaps

56:27.77] or planning engineering acquisition that we can

56:30.99] leverage

56:32.39] when an opportunity arises. We've had a lot of those happen in the past few years

56:35.53] that we're trying to focus on and get connected and fix long-term

56:39.19] problems where trails have been closed.

56:42.39] Again, kind of that

56:44.67] leverage fund. And we also got $500,000 for the Frisco High

56:48.63] Line connector. Basically, the whole northwest quadrant of the

56:52.53] city

56:53.67] has zero trails and how do we connect to the 35-mile rail trail all the

56:57.67] way to Bolivar and also have local and regional connectivity?

57:01.03] And there's a big idea behind this of square to square.

57:03.45] How do we connect Bolivar to Willard, to Springfield, to Ozark,

57:08.33] and have one continuous regional trail system?

57:11.07] But at the same time, how do I leave my front porch and be at a coffee shop on

57:15.01] C Street or

57:17.11] at a ballgame downtown? So these are also multi-year

57:20.93] projects, not one-year projects. Our timing's a little different from parks.

57:24.47] We're working with the railroad, we're working with preliminary engineering,

57:28.49] concept engineering, right of way acquisition, and some other things.

57:31.29] So a lot of these are more kind of in this public works domain that we've been

57:35.15] partnering with those project managers and Dan's team.

57:38.07] That's been great. There's definitely when we talk about heavy lift for staff, I've

57:42.07] experienced that with some of the public works staff of

57:45.25] them having full-time jobs and being burdened of taking on this extra

57:49.15] of negotiating contracts. Us as Ozark Greenways aren't able to

57:53.07] negotiate that, so we depend on our partners at public works, and it definitely

57:56.77] adds a little bit of strain to them.

57:58.19] So we're doing everything in our power to help move that along, but

58:02.23] just want to throw that out there. Where we are today, the Chadwick Flyer, we had

58:06.19] $3 million of previous ARPA funding that was completely

58:10.33] there to survey, get it engineered, and final construction documents.

58:13.33] That is completely wrapped up.

58:15.67] We are waiting on just the acquisition between the city and BNSF,

58:20.01] which my understanding is that we're close.

58:21.89] We have some agreements in place, and it's just the timing of working with the

58:25.77] railroad.

58:27.39] Everything inside of Ozark Greenways control and parks control is

58:31.11] done, and again, that acquisition.

58:32.77] But once we get that railroad corridor, we are ready to move

58:36.77] forward going out to bid for a construction consultant,

58:40.19] and we assume it would take about 12 months to get that

58:43.61] completed.

58:45.53] For the Frisco connector, we are currently working to get under contract

58:49.73] with the consultant to expend about $38,000 of that

58:52.93] $500,000 for a feasibility study.

58:55.55] A lot has changed since we last met with the 444 project that

58:59.35] MoDOT's doing of Interstate 44.

59:01.77] And a lot has changed in a positive way that gives more opportunity while

59:05.29] they're doing surgery on that or at division and at

59:09.09] Kearney and making a lot of changes that allows us the opportunity to get in

59:12.95] there and not only plan and engineer, but maybe take a look at constructing some of

59:16.77] these. So what was just funded for this was engineering and design, but we may be

59:20.51] coming back to see if we can carry those dollars further and just get

59:24.39] away from the design engineering and have some construction improvements and make

59:28.29] that connectivity happen sooner than we originally expected.

59:32.73] So that feasibility study also opens up with the $25 million

59:36.83] RAISE grant of a north-south connector connecting Young Willie all the way

59:41.01] north-south.

59:42.53] And then again, Nichols and connecting to Grant Avenue.

59:45.07] I wish I had a map to show you, but just verbal now.

59:49.05] This helps us expend those dollars, make sure we're being great stewards of this,

59:52.29] and have

59:54.01] a gut check of feasibility before we get into preliminary engineering and make sure

59:57.89] that we're picking the most direct route that has the biggest bang for our buck.

60:01.57] So we've got about 460,000 preserved for design right away and possibly

60:05.23] construction

60:08.18] Moving on to Grant Avenue North corridor, we're leveraging public works

60:12.06] in-house surveying. We got some bids back that were about a

60:15.88] half a million dollars to survey the entire corridor.

60:18.32] So we've kind of pivoted to say, how can we not spend that just in surveying,

60:23.46] and get farther along in engineering,

60:26.88] and being a little more focused on that?

60:28.50] They've been great to identify that work in-house, and then they have some new

60:32.82] technology and lidar data coming through that helps us evaluate those

60:36.80] right of way constraints, and essentially saving budget to focus on what was

60:40.36] funded.

60:42.10] We're hoping to have all that wrapped up by the end of the year and having a

60:45.08] consultant in spring of '27. And then

60:49.04] coordination again with MoDOT, Grant Avenue to the north is expanding,

60:53.70] with access to 44, which has changed a little bit of

60:57.60] the scope, and again, allowed us to change and try to work together with

61:01.60] their team. And we've been very close of how to make that connection happen with

61:05.62] more vehicle traffic now coming down Grant.

61:07.64] It kind of changes our design parameters from a completely multimodal,

61:11.66] because we'll have a lot more cars coming on and off 44 into the north

61:15.58] side of Springfield.

61:18.98] So that's all happening. And then our Ungap the Map fund, that million-dollar

61:22.76] opportunity fund, we've been working with MoDOT on some trails along Kansas and

61:26.70] Grand. We've been re-looking at Ward Branch, near the library center of the

61:30.16] underpass there, of how to reopen that.

61:32.98] Also Sunshine to Bennett. The city's doing a complete street

61:36.64] project from Bennett at Enterprise, all the way west to the art museum.

61:40.50] The Chadwick Flyer currently dies at Sunshine, so there's a small gap between

61:44.18] Bennett and Sunshine we'd like to figure out and get that engineered, and final

61:48.02] design and construction, so when dollars arrive, that we're able to capitalize on

61:51.80] those.

61:53.00] And then wrapping up the final design for the Lake Springfield Bridge,

61:57.64] which crosses over to Lake Springfield Park and connects us to Chadwick and

62:01.98] the Trail of Honor, which came before this board last year,

62:06.34] for FY27.

62:09.02] So where we're going, we're dependent on MoDOT a lot for some of these corridors

62:12.46] and negotiating with them and trying to figure some things out and build the trail

62:15.74] while the road's already open.

62:18.42] We plan to come back to this board and council to try to get as much to change

62:22.28] just from design engineering to add some construction to these.

62:25.98] So if there's an opportunity for us to build that, we build it and get

62:30.00] that connection and ungap that map right then and there.

62:34.92] And so we funded planning. We're trying to turn the planning into shovel-ready

62:38.18] projects and turn the trail into the ground, and get things

62:42.16] moving.

62:44.78] I think that's basically it for my update.

62:47.70] Be happy to answer any questions.

62:50.74] I have one question. Would you say again, the Young Lily connection, where does

62:54.36] that go?

62:55.64] Sure.

62:56.00] You said that was $25 million that you're looking-

62:58.68] The Raized grant goes west from

63:02.38] essentially Scenic, or downtown all the way west to

63:05.70] Rutledge-Wilson. There's no connection when you get west of West Bypass,

63:10.00] north to Young Lily. That entire neighborhood, and they just became a registered

63:12.82] neighborhood association, is disconnected from Rutledge,

63:16.68] and it is kind of in a pocket. So, we're looking at, in that feasibility

63:20.50] study, how do you connect them north-south, not only to the Frisco Line, but to

63:24.44] Rutledge-Wilson and to each other in that west side of West Bypass there and to the

63:28.46] Walmart and some of those amenities there.

63:31.48] But again, that's just the feasibility of that $40,000 out of that

63:35.26] $500,000 to explore if there's a feasible route.

63:39.00] And we've also been talking to the developer at Grand and West Bypass there

63:42.78] of connecting directly to Rutledge because again, K Point and those subdivisions

63:46.36] don't have any connectivity. Even though the park is outside their back

63:50.38] door, they can't get to it without driving.

63:54.06] Thank you.

63:55.66] Any other questions?

63:57.98] Thank you, gentlemen, for your updates.

64:00.34] To me, these are some of the shining stars of what the Forward

64:04.28] SGF dollars, Springforward dollars can do.

64:07.06] And when it's invested, this is overwhelmingly what the citizens told

64:10.94] us they wanted in

64:13.28] Forward SGF, and it's great to see these plans coming to life.

64:17.24] And so keep up the good work, and we want to continue to cheer you

64:21.28] on and see results so our residents can get out and enjoy

64:25.28] these spaces. So thank you.

64:27.92] Thank you very much.

64:31.08] And then we'll turn to Nick Nelson,

64:35.98] for an art museum update.

64:38.04] So Nick?

64:41.94] Good afternoon. For those of you who don't know me, I'm Nick Nelson.

64:44.92] I'm the director of the art museum and excited to be here

64:48.80] and give you guys an update on the art museum.

64:52.48] Unfortunately, I don't have slides, so

64:55.42] I'm a little bit of a disadvantage.

64:57.84] After we received the funding, or the council approved the funding for

65:01.74] the half-cent Springforward tax for the art museum, that was in

65:05.66] February 2026,

65:08.26] we shifted focus from completing phase one to planning

65:12.20] for phase two of the project.

65:15.36] So we continued working on items in phase one that would carry into

65:19.22] phase two,

65:21.04] while our design team worked on a transition plan.

65:25.04] On August 14th, the full phase two construction documents were

65:28.68] released

65:30.10] by our design team. Our construction manager at risk

65:33.96] began pricing work packages with their

65:37.20] subcontractors, and a little over a week ago, they gave

65:40.84] us the preliminary

65:43.66] guaranteed maximum price. If you recall, the construction manager at risk

65:47.96] provides a guaranteed maximum price of the

65:51.68] full construction cost of the project.

65:54.90] We have faced a few challenges.

65:58.14] The guaranteed maximum price came in higher than expected.

66:02.06] So we've had some longer lead times on steel

66:05.96] procurement as well as some higher price

66:09.40] escalations. These are really due to market

66:12.60] conditions, including higher demand for steel,

66:16.60] some uncertainty related around things like tariffs

66:20.36] and fuel costs and things like that.

66:23.00] These are really kind of market conditions that are driving that.

66:26.46] So we're currently working with our design team and our construction

66:30.48] manager at risk to bring those

66:33.02] costs in line with our budget.

66:37.60] We do have some timeline extensions too related to

66:41.36] the steel procurement,

66:45.76] and some

66:47.00] expected delays there.

66:49.32] In the coming week, we hope to have the

66:54.02] GMP, the guaranteed maximum price, finalized, and to

66:57.98] council for approval so we can move forward

67:01.04] with construction. So,

67:05.58] probably the big question is: What is that difference?

67:09.54] We're looking at anywhere between

67:13.92] $700 to half a million dollars over

67:17.80] what our budget was. It was higher, and we've been

67:21.98] kind of whittling it down. In fact, this morning I was in a meeting

67:25.80] talking about the height of doors and how many

67:29.54] outlets we need on a wall, or in the amphitheater.

67:32.54] So we're really getting into the weeds, trying to figure out ways

67:36.26] to

67:37.78] value engineer the project without value engineering.

67:40.96] Value engineering.

67:41.34] So

67:42.42] we are

67:44.02] absolutely committed to bringing the highest quality-

67:47.64] Yes

67:47.74] ... to our community

67:50.54] in a timely manner. And we feel like we're in the right direction.

67:54.68] We've come a long way with it, and we'll be,

67:59.34] I shouldn't say hopefully, we will be getting it into a point

68:03.08] where we'll be confident moving forward and again, next week or

68:06.92] so,

68:08.00] getting that

68:09.70] pinned down.

68:11.50] The timeline for the project is, as I said,

68:15.20] impacted by steel procurement. There's a lot of demand for steel

68:19.22] currently.

68:20.62] Our original

68:22.48] target for final completion was January 2028.

68:27.06] Our most recent projections are we don't

68:30.90] think we'll

68:32.14] be able to deliver final completion before June 2028.

68:36.04] So that puts us about six months

68:39.38] behind. But we are going to, again, continue to work to

68:44.08] figure out ways to deliver as quickly as possible

68:48.62] within the current market conditions.

68:52.08] So,

68:54.16] in all, the project has been

68:57.72] moving forward in a really good way.

69:00.40] We've done

69:01.70] public hard hat tours prior to moving into phase two

69:05.72] and had some great public

69:08.24] response from the project, and we're just really excited about

69:12.48] getting underway on phase two and reopening our

69:16.24] museum.

69:18.64] Anybody has any questions? Yeah.

69:20.00] Nick, how's your fundraising going?

69:22.74] It's going well. We've been able to

69:25.92] identify some name spaces, and

69:29.20] we continue to raise money,

69:32.86] and we'll continue to raise money.

69:34.08] What we're looking at now is, as we

69:36.98] finish off fundraising for the project, shifting

69:40.78] into operations and endowments so that we'll be ready to go when we've

69:44.28] reopened. There is a point where we have to

69:47.92] commit to a project, so there's

69:51.62] going to be a point where we have to stop capital fundraising

69:55.70] just because we have to move forward with a contract and

70:01.06] a complete project. So we're kind of getting to that point, and if we

70:05.06] can bring the cost

70:07.16] down through

70:09.10] these efforts of finding efficiencies,

70:13.42] that'll bode well for that sort of shift of fundraising for

70:16.76] operations.

70:19.76] Yeah.

70:21.28] Is there an area now at the museum that is

70:25.62] available for a public function or meeting?

70:29.96] Is it open for anything like that?

70:33.62] What's the auditorium scheduling? And then what's the big lobby?

70:37.30] Can anybody have a-

70:39.10] Unfortunately,

70:41.68] the whole west part of the museum is actually getting demolished.

70:45.14] Oh, okay.

70:47.36] And I'm happy to give anybody on the committee a tour of the

70:51.22] facility.

70:52.58] The project really touches almost every single room in the

70:56.26] museum. So if you go there,

70:58.26] there's no space to...

71:03.24] Everything's under construction.

71:05.68] But we have been activating our outdoor spaces.

71:09.48] We have launched a program called On the Lawn, where every second Saturday we do

71:14.70] concerts and yoga and art activities out in

71:18.70] the Hatch Lawn

71:20.66] by the amphitheater. So we are still using the site.

71:23.98] We are continuing with our great partnership with Parks to do Pops

71:27.94] in the Park,

71:29.44] which will be coming up in June. And so we're trying to keep the

71:33.32] site as active as possible considering the

71:38.16] scale of the construction project.

71:43.86] Any other questions?

71:46.88] Hearing none, Nick, thank you for the update.

71:50.34] We can talk about some of this in next steps, but one thing I

71:54.54] would throw out kind of along that line is, especially for any of the new members,

71:58.38] if there's an interest in tours, Nick and his crew have been

72:02.44] great ambassadors, giving tons of hard hat tours.

72:06.36] But that's something we'd need to coordinate with Colin and the

72:10.24] city clerk's office. We don't want to violate any special meeting laws

72:14.24] or

72:15.80] regulations. But giving tours,

72:19.74] it helps to be on the ground and go through those facilities,

72:23.58] both with art museum, but greenways and parks as well.

72:27.76] And so that may be something over the next few months, we look at having

72:32.08] some opportunities to get on the ground and get to see some of

72:36.08] these spaces.

72:37.92] I think each of these partners have great stories to tell,

72:41.72] and so we can also work with Cora on that.

72:45.02] But let's all be thinking of maybe some potential field trips.

72:49.30] We've given 85 hard hat tours to, I think,

72:53.56] 500 people or something like that in the past.

72:56.20] So we're kind of old hats in hard hats.

73:01.10] Old hard hats.

73:02.20] Hey, Nick, is there a timeline? Because I know demo's starting.

73:04.96] Is there a timeline if we're going to do a tour?

73:07.06] It probably needs to be expedited, correct?

73:10.00] Either that or we'll have to figure out.

73:11.82] We can certainly work around their demo schedule.

73:16.93] And yeah, either-

73:18.39] So they've paused tours for a minute, correct?

73:20.73] Yeah, we have paused tours, but we can figure out how to make one

73:24.63] work.

73:25.93] Probably either before or after the major demolition

73:29.79] happens would be best.

73:32.75] And I can coordinate with everybody on when would be the best

73:36.59] time, especially our construction-

73:37.99] As long as we don't have

73:39.79] five people going in this board. If it's a

73:43.47] few at a time to work with Nick on just a tour of that, that's not

73:47.23] a stunted meeting. Just work with him on just taking a look at that if

73:51.23] you're interested.

73:51.45] If you're interested.

73:52.39] Yeah.

73:52.67] Yeah.

73:53.25] Yeah.

73:54.29] I think in particular, the art museum, for those who are new,

73:58.09] we talked about having the art museum be a hub or

74:03.15] having activities radiating out of that.

74:05.55] And so when you're on the art museum site, you're not only seeing what is happening

74:09.25] there, but you're thinking of, well, how does it connect with Phelps

74:13.21] Grove Park? How does the Greenway Trail reach out down Bennett all

74:17.19] the way to the Chadwick Flyer?

74:19.83] What are the new tennis courts going to look like right outside the French fries?

74:23.57] So,

74:25.09] you see all those pieces coming together, which is what we want all of our projects

74:29.59] integrating and building on one another to create momentum.

74:34.01] And so anyway, again, keep that in mind.

74:36.99] I think

74:38.23] that the idea of getting out and about, now we're getting into...

74:42.11] We had summer yesterday, and

74:44.93] we're going to turn into fall, and it'll quickly be Thanksgiving before we know it.

74:48.89] So some of this may need to wait till spring, but

74:53.11] I would be very interested in getting out and getting folks on the

74:56.95] ground.

74:58.71] All right. Thanks, Nick.

75:00.63] With that, Steve is going to lead us in an update of the

75:04.55] neighborhood plans, which we funded.

75:07.37] Oh.

75:09.13] Well, hello, everyone. Good to see you. My name's Steve Childers.

75:12.63] I'm the Director of Planning and Development.

75:14.31] I just have a brief update to tell you where we're at, and happy to answer any

75:17.21] questions. I have taken a hard hat tour.

75:19.93] It's really cool, so if you do get to do it.

75:22.95] You may actually think when you're there, "How does this museum and the

75:26.49] park fit into the greater neighborhood?" Well, we're going to deal with that

75:30.45] when we get to the plans.

75:32.61] So,

75:33.99] you may or may not recall, but the CAB

75:38.13] had

75:39.59] recommended approval, and it was approved by the city council to budget

75:43.27] $500,000 for completing

75:46.77] neighborhood plans for each individual registered neighborhood.

75:51.51] When we did that, we had 24 registered neighborhoods.

75:55.99] Now we have actually 26 registered neighborhoods, Lily

75:59.99] being one of those.

76:01.93] Another one that we have added was actually East Central.

76:05.79] So,

76:07.03] I think as we get through this process, we're going to learn a lot over the

76:10.81] next 18 to 24 months, and then staff should be able to

76:14.65] conduct the plans individually for those coming forward.

76:18.69] So I think we're going to be just fine.

76:21.41] So earlier this year, we put out a request for a

76:24.71] proposal to select a consultant to guide us through

76:28.61] this 18 to 24-month process.

76:31.67] We have chosen a consultant. The consultant is Freese

76:35.61] and Nichol Incorporated.

76:38.25] We've already had a couple Zoom meetings with

76:42.19] them to get prepared, but they are going to come make their first visit

76:46.19] physically here to the city on November 9th.

76:50.33] At November 9th, they're going to meet with both the Planning and Zoning

76:53.73] Commission as well as the City Council in a City Council lunch meeting,

76:58.23] so that they can give a presentation to the City Council,

77:01.71] so they can set expectations, and make sure that

77:05.69] everyone understands what these neighborhood plans will be and what they're not

77:09.31] intended to be.

77:11.25] So we want to make sure that everybody is comfortable with what's going to be the

77:14.59] outcome of that.

77:16.55] That is also going to include

77:19.53] a neighborhood open house event. So while they're in town, there

77:23.49] will be a neighborhood open house event.

77:25.79] Our neighborhood team is currently working with them right

77:29.73] now to kind of structure what that's all going to look like.

77:33.43] But I was texting just a minute asking some questions of the staff,

77:37.44] because I anticipated a question, and whether you have this or not.

77:42.23] We have had the question, "Well, how are you going to prioritize these

77:45.11] neighborhoods?" And to be honest, there's really not going to be a

77:48.39] prioritization of the neighborhoods, like we'll do one, and then two, and then

77:51.87] three. We're going to do these simultaneously.

77:54.57] So we're going to have

77:56.89] consultant leads that will consist of two or three

78:00.41] individuals that are on that team, and there are going to be six

78:04.35] groups of four neighborhoods. So we're going to try to get this

78:08.31] done. This is a lot of work to have individual plans done for

78:12.33] over 24 registered neighborhoods, and we do think we can do this

78:16.09] in 24 months. There will be a lot of citizen

78:19.79] engagement.

78:21.33] So I'm looking forward to it. It's going to be exciting.

78:25.01] It's going to be a really cool project.

78:26.79] We can come back and give you as many updates as you want, as frequently as you

78:30.59] want. Just let us know. But that's where we're at right now, so...

78:35.83] Steve, you might add that it would be good to keep this body updated

78:39.67] on when those open houses are taking place-

78:42.63] Sure

78:42.71] ... because it will be helpful for you all to see what's going on with those plans

78:46.61] and that engagement. I just want to applaud the planning department for taking

78:50.49] this on simultaneously because it's what's best for the community, and it'll get

78:54.35] all of the neighborhoods excited that they're going to be a part of something

78:57.27] really big. And we'll make a big deal about it along with them.

79:00.31] And we're working hand in hand with PIO.

79:03.41] We've brought them onto the team. We have regular meetings, and so as we're

79:07.27] communicating with P&Z and City Council, we'll communicate with you guys, too,

79:11.29] and we'll make sure that we settle those out, all the dates, any meetings, any of

79:14.33] that stuff. So attend what you'd like or as many or not as many as

79:18.33] you want and be a part of it, so...

79:22.42] I would just like to say this is progress as promised.

79:25.20] Yes.

79:25.94] Because

79:28.54] from an ACT position, we've been asking for this for about four or

79:32.24] five,

79:33.72] is that or longer, years? So I am

79:37.10] ecstatic. Thank you.

79:39.26] This is a recommendation from Forward SGF as well.

79:43.08] It does say that we need to do this, so it's really cool to be able to

79:46.98] see one of our recommendations in Forward SGF move forward

79:50.96] as well.

79:51.40] It is remarkable because typically a neighborhood plan can take up to

79:55.36] 18 to 24 months.

79:58.08] So

79:59.38] it's hard to keep those plans fresh when it takes that long-

80:02.96] Yeah

80:02.98] ... especially over 24, but having this effort to get

80:06.96] everyone, everyone will be on a similar playing field then.

80:10.70] And we won't have one neighborhood with a fresh plan and someone whose plan

80:14.80] is 10 years old. So some of the things I would hope

80:19.70] is that, in each of those neighborhoods, we highlight the

80:23.78] Spring Forward projects that are already committed.

80:27.00] And so parks projects, greenways, that those are really

80:30.60] highlighted- ... as these are coming attractions coming soon

80:34.48] and have that be part of the discussion and the

80:38.14] visioning for that.

80:40.92] The other thing is,

80:42.92] would love to see, we've talked about using our funds to

80:46.92] spur additional development, both on the residential and neighborhood

80:50.88] hub side. So,

80:53.30] will they be looking at, for each neighborhood, doing a

80:56.60] GIS review of vacant or

80:59.96] underutilized properties?

81:02.32] I think that's definitely going to be a part, and thank you for your first part of

81:05.34] the comment.

81:06.98] We have already made sure

81:10.72] to engage the other initiatives that are being funded by

81:14.44] CAB as well. We probably had our first joint meeting

81:18.40] with Parks and Planning the other day because we knew that we

81:22.26] needed to talk about that. Because the parks that

81:26.24] Ron mentioned, they're in neighborhoods, and so we know that's going to

81:30.22] be a significant piece. So we're going to be meeting on a quarterly basis, Ron, I

81:34.24] think, just to make sure that we're in tune with that.

81:37.10] We're going to make sure that their consultants and our consultants are talking

81:40.64] about those things so that we don't,

81:43.84] we don't want to have duplicative efforts-

81:46.38] Mm

81:46.46] ... but we also want to have coordinated efforts. So that's going to be one thing.

81:49.66] So we set up those regular meetings.

81:52.34] The second thing is, on the Neighborhood Works Plus,

81:56.50] actually have two members of the planning staff that

82:00.36] are on the team and have been through the whole consulting

82:04.56] process with them. So we're staying very engaged.

82:08.14] Those silos have been broken down, and we're all working really good

82:11.96] to have interdepartmental discussions about that stuff.

82:15.84] But yeah, I think

82:17.64] we've really talked a lot about opportunities and what might exist.

82:20.88] And the exciting thing is, is that you're going to talk to the neighbors and the

82:24.86] neighborhoods and say, "What opportunities do you see in your

82:28.18] neighborhood that you think could be a potential project?" And

82:32.52] you're going to get it directly from them.

82:34.02] So yeah, I think the vacant lots, the opportunity areas, the

82:37.72] intersections that could have potential redevelopment

82:41.46] opportunities, I think all that's in play.

82:43.88] Yeah.

82:44.12] So.

82:45.16] Well, I think, yeah, that's our chance to...

82:47.62] It's so hard to communicate with people these days.

82:51.06] For those who come to the meeting, we want them to know what's coming,

82:54.68] and that they can tap into that. I think we also need to make sure that the Spring

82:58.68] Forward branding is prevalent,

83:01.30] because again, we are going to want this renewed in eight years,

83:05.26] and we want them to see their support in

83:09.00] action, so.

83:09.82] I don't think you have to worry about the branding.

83:13.14] We get reminded of it all the time. And so, trust me,

83:17.20] yes, it will be a part of it, so.

83:18.70] We should have 30 signs rolling out-

83:21.24] Yeah

83:21.34] ... relatively soon, letting our residents know about

83:25.16] these projects. Of course, this body is

83:28.44] responsible for the recommendations for Spring Forward SGF, so these are

83:32.60] Spring Forward dollars. So you are starting to see

83:36.34] videos roll out as these things get started, and it's a three-prong

83:40.34] approach of

83:41.76] it's coming, we're in the middle of it, and then, wow, look at what,

83:46.78] it's done. Okay? So we would love to have your participation in

83:50.70] building that excitement and communicating about it, but more to come on that.

83:54.30] And to elaborate on Steve's point, the different departments, Parks, Public

83:58.12] Works, and Planning, the triple P,

84:00.80] coming together and making sure that all of these things

84:04.76] are aligned with one another is a game changer.

84:07.76] You think that those things happen naturally.

84:10.86] Mm.

84:11.06] They don't always, for many reasons, but under this Spring Forward

84:14.60] SGF, it provides an umbrella brand that we can make

84:18.60] sure we're communicating just how exciting this $300 million

84:22.68] over 10 years is. Big deal for Springfield, so FYI.

84:27.16] Where's your signage going to go? You got 30. Where can, what do you think?

84:30.28] Every Neighborhood Works Plus project, which is 20.

84:33.16] Yeah.

84:33.62] So those individual projects. What else, Kristen? Kristen designed this.

84:36.78] She goes here.

84:37.26] There it'll be one-

84:37.90] And this is based off of what we do for the quarters and the 8 Cent completed as

84:41.00] promised, based off of that concept.

84:42.86] So we've got

84:44.76] larger billboard-sized signage for where we've got the right of way to do that for

84:48.56] some of those bigger projects, as well as potentially more like

84:52.58] pole-sized neighborhood-type signs that would go near

84:56.32] sidewalks and traffic calming and some of those more neighborhood-level

85:00.08] projects. But we're still in the concepting of this to make sure that it'll print

85:03.56] and be visible by drivers.

85:06.20] And we can't violate our own sign laws.

85:08.52] Right. Or sad.

85:11.48] You can, but-

85:12.36] But it wouldn't be a good thing.

85:14.10] This might be a

85:16.54] good topic for one of your future meetings, just an update on our

85:19.92] communications plan and strategy to show some of the branding, take a few minutes

85:23.86] to show that

85:25.57] Because I think it's a big piece of making sure that voters know, citizens

85:29.33] know what we're doing, what you've approved, which is part of what we're doing here

85:33.17] is

85:34.41] you've recommended and councils approve two and a half years of funding

85:38.47] for these projects already. There's a lot, as you can see, that's going on, that's

85:42.45] taking place since you've recommended and these things have been approved.

85:46.41] Sometimes it's hard to see these things, but we want to make sure, and that was

85:49.07] part of-- appreciate Rusty and Lauren wanting to make sure that we did the update

85:52.29] so you can see exactly where we've been and what's happened since you've

85:55.93] recommended these projects.

85:58.21] Last meeting, you talked about NeighborWorks Plus.

86:00.03] That's $5 million of projects that council's approving that will be going forward

86:04.07] out of the $70-plus million of potential projects in neighborhoods in

86:07.93] that bucket. So there's a lot of potential areas for projects to

86:11.97] be looked at.

86:14.05] And to follow up on that, I'd like to have a

86:17.67] communications update as part of every agenda.

86:21.23] Just taking a few minutes for Cora and Kristen to give us an update, and

86:25.51] so we plan. For those who maybe haven't seen the latest

86:29.85] social media on Renew Jordan Creek-

86:32.87] ... we've had Kirkland out giving a video tour

86:36.75] of the latest fun stuff around that.

86:40.09] Our airport team does a great job. So using social

86:43.83] media to, in fun ways, highlight what we're doing

86:47.39] together with these investments.

86:49.65] But if we could have a standing item on the agenda for communications

86:53.59] each month.

86:54.55] Sure.

86:54.85] I think it needs to be two-way. Something that Lauren and I have talked about is

86:59.33] we want to get an update and a regular report of the portal,

87:03.89] so that-

87:04.51] Mm-hmm

87:04.57] ... those ideas that are coming from the community, that we're getting those

87:08.89] reports on what's coming in, what's come in to date.

87:12.55] And we see how many have we been able to address, and still what's

87:16.45] out there.

87:17.89] So that will be one of the other items on the agenda for next

87:21.85] meeting. So with that, any other questions for

87:25.51] Steve on neighborhood plans?

87:28.73] Thank you.

87:29.23] Thank you, Steve.

87:29.69] You're welcome.

87:30.53] Thank you.

87:32.95] So shortly after our last meeting, Lauren and I were able to meet with

87:36.99] Colin and go through the next few months of generally what we

87:40.97] saw as some of the major topics. So today

87:44.95] was a flurry of updates,

87:48.81] but getting a community applications update for

87:52.91] November.

87:54.77] We anticipate we'll be getting an expo center update at that

87:58.65] meeting.

88:00.11] A city projects update.

88:03.05] You recall Tim in Public Works provided a list of city

88:07.05] projects shortly before we took our hiatus,

88:11.01] and so we'll have that back in front of us.

88:15.43] And then corridors. The initial presentation on corridors.

88:20.09] We'll be working with Public Works, and Dan, his team will be giving

88:23.89] us some ideas. And corridors are called out in Forward

88:27.45] SGF, and there's seven different

88:31.09] high-profile corridors that are listed in Forward SGF.

88:34.59] We're not going to tackle all seven, I don't think, but we can start with one or

88:38.55] two and having that conversation.

88:40.87] So those will be the items that we anticipate for November.

88:45.55] We have penciled in for December, economic vitality and

88:49.27] housing.

88:50.67] Housing is a topic that we haven't yet been able to get to,

88:54.27] and so we're looking on that. And like we've

88:58.25] had for parks and greenways, having the industry experts

89:02.55] come together and come to us with consensus recommendations is the goal

89:06.85] of what we would like to see in both those categories.

89:11.27] We've asked Colin,

89:13.57] we're interested in having another joint meeting with city council.

89:17.49] Last year, that was in January at the airport.

89:20.55] I think we found value in that, and we want to make

89:24.25] sure that we're on the same page with city council and the things that we're

89:27.95] doing

89:29.61] are in line and aren't going to be dead on arrival when it

89:33.61] comes to their dais. So,

89:36.29] if there's interest from council, I think we would certainly want to

89:40.31] have that joint meeting and do an update.

89:43.45] And then

89:45.19] after that, start making some recommendations and

89:49.03] start digging into next level of funding.

89:52.13] Yes, sir.

89:52.55] Please.

89:53.21] That last piece, though, to me, is to some extent connected

89:57.19] to

89:58.77] are we hiring a consultant or not?

90:01.31] Because if we're hiring a consultant, I think we've got to be careful

90:05.23] about getting out in front and funding projects.

90:08.63] If we're not hiring a consultant, then it's

90:12.25] a different deal. Is that...

90:15.99] Absolutely. Yeah. So we'll have that continued discussion next

90:19.93] month. And Lauren, you've had some thoughts about just

90:23.97] a process for evaluating potential projects and initiatives and

90:28.15] so-

90:28.39] Yeah, and it calls it out a little bit in there.

90:30.03] I would just love to see for this group, and of course, want everyone's feedback.

90:33.99] I think it would be helpful from a public perception piece on

90:37.81] how,

90:39.33] matrix may be too strong of a word, but how we're making decisions toward funding

90:43.35] in terms of why we're funding X over Y.

90:45.47] I think we have the 11 criteria, but we're not always sort of utilizing those in

90:49.43] terms of a

90:50.75] checklist when we're looking at these things.

90:52.55] I just think as we're thinking broader about storytelling and the brand of

90:56.49] Spring Forward, how are we having an objective

91:00.69] view on some of that? But it read a little bit in the RFP that that may be a piece

91:04.09] of that if that's the direction we go, but I'd love to see something like that.

91:07.93] We didn't really hit on that today in the Tim lead.

91:10.31] That would be one of my questions of vetting. I love the idea of a plan.

91:13.15] I think that's great. I geek out over efficiency, but a piece of

91:17.17] that being if this is making it easier for people to apply

91:21.05] and easier to vet the projects, that makes me way more

91:24.87] likely to lean into it than-

91:27.66] Because we are answering to our community.

91:29.62] And so I don't want to get so focused on the deliverable

91:33.48] of the plan and what we're funding that we lose the piece of like, how does this

91:37.08] make it easier for our community to get engaged?

91:40.86] Yeah.

91:41.08] Okay.

91:43.96] What other feedback, thoughts?

91:47.48] Yes.

91:48.30] So, one thought I had, and I don't mean to be critical

91:51.88] by saying this, but

91:58.10] as I listen to the tenor of the meeting today,

92:02.80] in my mind, and we got around to it at the end through Cora and

92:06.96] Steve talking about what an amazing opportunity

92:10.98] this is.

92:13.40] We've got almost $400 million

92:17.42] over 10 years to make transformational

92:20.86] projects in our community.

92:24.74] And yet I heard a lot of, but kind of like this was a

92:28.56] burden for people to work on this.

92:31.42] This should not be a burden to work on this.

92:34.44] And I know we get sucked into the tyranny of the urgency and all the

92:38.70] stuff we have to do in our routine jobs, et cetera.

92:43.32] My encouragement to staff would be minimize that,

92:47.48] shift that away, because here's an opportunity to

92:51.50] work on $400 million of cool stuff.

92:56.08] My guess is you don't have a lot of other things that are more important

93:00.02] than this.

93:01.52] I think about Ron, and Ron wasn't a part of this, but Ron's got to

93:05.56] deal with hundreds of employees and all sorts of issues, and

93:09.54] programming, and on and on and on. This is the only

93:13.46] opportunity he's going to have to have real difference.

93:17.24] And so this has got to be the priority,

93:21.14] not returning some crank's call about some b***h they have

93:24.98] somewhere, right? It's got to be focus on the cool

93:29.32] stuff we can do, and

93:33.58] this isn't a burden. This is an opportunity.

93:38.10] What I would just throw in there, and maybe as

93:41.12] a defense for the people who have a lot of work, is

93:44.88] that our city

93:47.04] works for the public

93:49.06] and have to respond to the public, and having worked in

93:52.64] similar situations, even though they should be focused

93:56.48] on our $400 million,

93:59.18] then they have to answer that phone.

94:01.34] They get interrupted. So

94:04.44] I'm torn

94:07.14] with how many interruptions, how many thousands of calls.

94:11.06] Should we answer that cranky person's call or should...

94:16.66] So

94:19.22] it happens.

94:21.58] Maybe Colin doesn't have to answer the cranky person's call.

94:24.88] Well, to hear you use the word transformation, because that's the critical part of

94:28.44] this, is that if we don't come to these meetings imagining what this

94:32.62] city and MSA look like in 10 years and in 20 years, we're not doing our

94:36.68] job to start thinking big because

94:39.82] we have some advantages on other places.

94:42.44] And I've

94:43.76] only been here two and a half years, but I've said this a lot over town.

94:47.06] It's time to mash the gas pedal. It's time to get ahead.

94:49.64] And this $400 million lump of clay has been

94:53.44] handed to us. Let's do big things.

94:56.80] Let's do it.

94:58.86] And this group has all-- as we have surveyed ourselves, we have,

95:04.16] at least as originally composed, everyone in this group was

95:08.04] like, "We have to do big things with this."

95:12.18] Yes, we got to fix sidewalks. Yes, they're small projects that we can fund.

95:16.88] But we may never have another opportunity to do really big

95:20.68] things. And so let's continue to think

95:24.44] big.

95:25.88] I have a question.

95:27.10] Excuse me.

95:27.70] As far as that goes, big things and the future of

95:31.34] Springfield,

95:33.10] I personally was very disappointed when the convention center

95:37.04] didn't pass in the vote, and I think it's because, at least in my

95:40.98] neighborhood, people didn't understand what that means for

95:44.72] Springfield and how we don't have anything

95:48.62] of that scope right now that can take that

95:52.20] place. "Oh, we already have a convention center." No, that convention

95:56.22] center is nothing. It doesn't

96:00.00] perform to the

96:02.98] greater scope of where we would like to see ourselves

96:07.00] in the United States as a city that

96:10.62] invites bigger things to Springfield.

96:14.62] So is there a way for us to revisit the

96:18.26] convention center in some way that can

96:22.46] bring it back to life? Can we

96:24.96] look at that and find a way to

96:29.58] maybe

96:30.82] educate

96:32.60] people on what a convention center means to

96:36.24] Springfield?

96:37.98] So I can just jump in a little bit there. I would say stay tuned.

96:43.06] Obviously, the convention center as a convention center concept with the

96:46.72] additional tax is not something that's being proposed.

96:49.62] However, we still own the Expo and Events Center

96:53.28] facility. That project,

96:56.44] as proposed, it's a transformational project, which is part of

97:00.36] one of the three buckets, large scale transformational project, economic

97:04.10] development project, that's

97:06.28] a downtown project that

97:10.82] leverages dollars,

97:12.88] goes way beyond the cab funding, potentially.

97:16.18] So I would say stay tuned. There's certainly--

97:19.86] the 30 million is there for that type of a project, and I think

97:23.62] we'll leave it there maybe for now and come back

97:27.64] because it's something that needs to be

97:29.93] Really discussed and vetted in

97:32.43] this arena and others to make sure that it's exactly what the

97:35.99] community's looking for.

97:38.23] Well, maybe the community doesn't understand what they're looking for.

97:44.83] It's finding that balance of listening to what are the concerns,

97:48.81] and then

97:50.09] seeing what's the path forward-

97:51.67] Mm-hmm

97:52.47] ... to best utilize facilities and the assets the city has.

97:57.49] We have a pretty big lever to make some things happen.

98:00.61] So,

98:01.73] all right.

98:01.85] I think the more we can do to celebrate that, because to Cliff's point,

98:07.05] the whole goal of this fund is to really make investment in a big way, and a

98:10.91] lot of what we've done thus far,

98:13.37] outside of the convention center, which failed, has been

98:16.83] planning, design.

98:20.21] Ground hasn't been broken. Art museum is in progress.

98:24.27] But we have to be celebrating these things and making sure through the branding

98:27.77] it's known that it's happening and what it's tied to.

98:30.93] And beyond that, this is not all the city's doing.

98:34.28] You may want potholes to be fixed. That's happening, too, just not

98:38.19] with CAB money.

98:39.05] Mm.

98:40.13] So I think it's just a broader communication strategy of like...

98:43.65] Because I've heard, you all may have too, that, "I thought CAB money was for

98:48.01] XYZ, or for this specific thing, not what's being proposed." And it's just that

98:51.95] constant reminder of

98:53.89] we really are looking at transformational things, and you may not see them built

98:57.85] tomorrow,

98:59.33] but they're in progress, which is really important. So.

99:03.29] That's good.

99:05.45] Well said.

99:07.33] All right. Given that high note, which I will say

99:11.25] is a breath of fresh air, we need more of this type of

99:15.09] optimism and hope that we can point our community towards, because

99:19.03] we do have a lot of good things to build on.

99:21.89] So with that, I would entertain a motion to adjourn.

99:26.43] So moved.

99:28.01] Second.

99:28.77] Okay. Mrs. Greer.

99:32.45] Smart?

99:32.99] Yep.

99:33.65] Boltz? Yes. Watson?

99:35.49] Yes.

99:35.99] Forster?

99:36.69] Yes.

99:37.19] Shaunce?

99:37.91] Yes.

99:38.82] Lowe? Yes. Sutcliffe?

99:41.23] Yes.

99:41.79] Nattie? Yes. Worley?

99:43.55] Yes.

99:44.73] Thanks everyone.

99:45.41] Good.

99:45.61] Good meeting.

99:45.85] Thank you.

99:46.35] Good meeting.