Capital Improvement Plan Major Update

At a glance

  • What: the four-year major update of the Capital Improvement Plan, now for fiscal years 2028 through 2032, led by Jeanne Hooks and Mark Spanioli.
  • Where it stands: kickoff on October 15; no decisions. Council affirmed the process (criteria weighting, paired comparison, Eisenhower exercise at the February retreat).
  • Next: work session November 10 to divide active commitments from new project concepts and share visions; community engagement moved toward December-January; funding scenarios from financial advisors in January-March.

Key points

  • Staff sees capacity of roughly $40 million across FY2028-32, issued in two to three rounds; construction costs keep rising.
  • Active projects are treated as committed; the cricket field project is about $6 million including a $1 million increase discussed on October 13.
  • Requested additions to project summaries: scope, timeline, gap or completion value, funding source, future operating impact.
  • Harrison Kesling asked for explicit decarbonization weighting and "small bets"; staff will show sustainability impacts per project.
  • Planning concepts: parks master plan, transportation plan, town center visioning, sidewalk gaps, space needs study, Harris Mill leftover land, Town Hall Drive and Church Street corridors.

Discussion time

About 57 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-15 - Town Council Work Session 57

Log

From the video (October 27, 2026)

Church Street Park phase two cricket field funding was decided separately at this meeting (approved); parks master plan and CIP discussions continue November 24. See 2026-10-27 - Town Council Regular Session.