Town Center Construction
At a glance
Based on automatic speech-to-text; names and numbers may be misheard.
What: Construction of the Town Center.
Where it stands: Underground utilities complete and on schedule for next summer; early concrete pours and a Town Hall Drive closure still being worked out.
Log
2026-10-27 - Town Council Regular Session
Eleven extra early-morning concrete pours (1 a.m. to 5:30 a.m.) are needed for slab curing, with community notification. A proposed four-month closure of Town Hall Drive for wetland pipe outfall work would add about a minute of fire response time; staff told the contractor to return with a Plan B in two to three weeks.