2026-10-07 - Joint City County Planning Committee

Summary

A discussion meeting: the only vote was approval of the September 2 minutes (by voice vote); the three substantive items were presentations with no action.

  • The meeting started at 9:33 a.m. without a quorum, which arrived with a late member. Councilmember Baker chaired. The agenda order was changed to hear green building before growth management trends.
  • Green building certifications: planning staff compared seven certifications with Comprehensive Plan policies on energy and materials, heat island mitigation and stormwater. Findings: five of seven reference HERS scores, four address heat islands (only one sets a minimum), and four touch on stormwater but none set a minimum. Staff recommended requiring a pre-certification timing mechanism, treating Greenguard as a materials certification rather than a whole-building one, using HERS targets, and requiring specific green stormwater infrastructure for the stormwater policy. Members raised affordability, flexibility and unintended consequences, asked for a cost breakdown, and discussed workshops with the Homebuilders Association and tying this to the future Land Development Code. See Green Building Certifications and Comprehensive Plan Policies.
  • Growth management trends, the first report since the 2023 Comprehensive Plan: from October 16, 2023 to June 22, 2026, 107 privately initiated zoning map changes and annexations were decided, with 92 city approvals, 12 city denials and 3 county approvals. Inconsistent approvals added about 223 acres to residential place types. The urban growth boundary has not moved. For a two-year review of 82 cases, developments committed to 84.85 acres of added tree coverage beyond code and $1.2 million was proffered for schools; the policy on school land proffers was removed because it had never been used. See Growth Management Trends Report.
  • Housing: the estimated need fell from 60,000 units (2022) to 51,300 (2025). About 37,000 units have been approved through development plans since 2020. Of the 2,746 proffered affordable units on file, 314 were built, 788 were under construction and 528 had site plan approval. The Housing and Neighborhood Services director said the department monitors 20% of the portfolio each year; no corrective action plans have been needed so far.
  • Members asked for a one-page community summary, a better dashboard, annual or biennial reporting, project-scale and geographic breakdowns, fiscal impact analysis, and inclusion of EMS costs in future growth area review.
  • Multimodal development standards: planning staff and consultants presented a draft that replaces a vehicle-focused transportation impact analysis with a point-based, context-sensitive system for pedestrian, bicycle, transit and street improvements above code requirements. Members praised the flexibility but worried applicants could avoid needed street standards; next steps include refining scoring, site testing, NCDOT coordination and ordinance language, to move with the Land Development Code. See Multimodal Development Standards.
  • The planning program projects update was made available without discussion, and the meeting adjourned at 12:24 p.m.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

02:14morning everybody. Chris, are we good?

02:18>> All right. Good morning everybody. Um,

02:20we don't currently have quorum. I think

02:22uh we have a few folks running late, so

02:24they should be here any minute now. But

02:26we're going to go ahead and get started.

02:29Um it's 9:33 and we are getting started

02:33on the joint city county planning

02:35committee uh meeting on October 7th. Um

02:39can we get a roll call please?

02:44>> Chair Baker

02:45>> here.

02:45>> Vice Chief Vice Chair Lee.

02:49Uh, Mayor Prom Cababiierro,

02:52Planning Commissioner Shagaris,

02:55Planning Commission

02:58>> here,

03:00>> Commissioner Jacobs

03:01>> here,

03:02>> Council Member Copek,

03:04>> Commissioner Valentine,

03:05>> Commissioner Valentine is walking

03:06through the door. Perfect timing,

03:08Commissioner.

03:14>> All right. Good morning. Uh, adjustments

03:16to the agenda. But we're just going to

03:18go ahead and move um six above five. But

03:23other than that, we're good. Okay,

03:26that's the only adjustment to the

03:27agenda. Any announcements?

03:34All right, we now have quorum. So, um

03:37can I get are there any comments on uh

03:40the minutes from September 2nd?

03:45If not, uh, can I get a motion to

03:47approve the minutes from September 2nd?

03:50>> Second.

03:50>> All right, we've got a motion and a

03:52second. All in favor, please say I. I.

03:55>> I.

03:57>> All right, the minutes from September

03:582nd have passed. Uh, city and county

04:01managers priority items.

04:07>> Good morning, Adrian Miles with the city

04:08attorney's office. The city has no

04:10priority items this morning.

04:13Curtis Massie from the county attorney's

04:15office and the county has no priority

04:17items.

04:19>> All right, getting started with the

04:21agenda here. We are again moving six

04:24above five. So, let's go ahead and jump

04:26into

04:28and council member Copac is here. I know

04:30that know that you wanted to be here for

04:31this agenda item, too. So, I'm glad

04:33you're here. Uh the green building

04:35commitments item six.

05:13All righty. Good morning everybody. My

05:15name is Brianna. Good morning. My name

05:17is Brianna Beetle, research planning

05:18specialist with the re with the the

05:19planning and development uh department.

05:22And today I'm going to be discussing

05:23with you all this project we've been

05:24working on the last couple of months. um

05:26researching green building

05:27certifications and how these

05:29certifications that we've been um that

05:31we're seeing a lot with applicants um

05:32relate with some compound policies

05:34surrounding greenbased infrastructure.

05:38All right. So, as I stated previously um

05:41a lot of these certifications have been

05:43reoccurring with um our offers and so we

05:45wanted to be making some recommendations

05:46for how these policies should be

05:48interpreted and whether or not they meet

05:50policy standards. Um, just as a quick

05:53aside, we're not going to be asking for

05:55any changes to the comp plan today. Um,

05:56so we do not um, foresee any vote

05:58needing to take place. We're just asking

06:00for general feedback and consensus on

06:03today.

06:06All righty. And just a little overview

06:07of today's presentation. Today we're

06:09going to be um talking about some

06:11background where this project came from

06:12and then letting you guys know um our

06:15analysis um and our findings with the

06:17certifications and how they and how they

06:18relate to policies 49, 96, and 108. Just

06:22as a quick um reminder of what those

06:24policies are, 49 um looks at energy

06:26efficiency, air quality, and material

06:29selection. 96 is looking at heat island

06:31mitigation and 108 looks at storm water

06:34and touches on a little bit more on heat

06:36island mitigation. And then we're going

06:38to be talking about some recommendations

06:40and how these certifications can um

06:42relate to those policies and how we

06:44recommend changing those policies as

06:46commentary a little bit.

06:50Okay. So this project emerged from like

06:53I said earlier us receiving many

06:54profiters um promising to get one of

06:56these green building certifications. Um

06:58but we wanted to see uh what these

07:00certifications won for were for one for

07:03one thing but also like what they

07:04address which led to this project. And

07:07in analyzing these certifications and

07:08their technical documents um we had kind

07:10of two main concerns going in. um one

07:13how um how applicable each of these

07:16certifications were to the polic were to

07:18the policies in the comp plan and two um

07:20we wanted to see if they had any type of

07:22um uh timing mechanism or

07:24pre-certification pre-approval um that

07:27could show intent to go forward with

07:29these promise certifications. So kind of

07:31looking at that enforcability aspect of

07:33it all.

07:36Okay. And so what were our findings? Um

07:40luckily most green building

07:41certifications were pretty holistic and

07:43address um a wide range of topics and

07:45the most common structure that we saw

07:47was having some sort of minimum

07:48requirements um with additional options

07:50to receive um any credit um to hit those

07:53certifications um to hit those uh

07:56certification scores. Um and luckily

07:58most green certifications green building

08:00certifications also had that type of um

08:02pre-certification pre-approval or um

08:05that timing mechanism that we were

08:06looking for to have some to have um as

08:08an enforcement mechanism. And just

08:11touching on this last note right here

08:13regarding Greenguard. Um we were

08:16Greenguard was one of the certifications

08:17that we had researched and we came to

08:19the conclusion that Greenguard is not a

08:22green building certification and is more

08:24of a materials certification. but we're

08:26going to get into that in a couple more

08:27slides.

08:32So, starting out with policy 49, policy

08:3449 largely addressed um like I said

08:36earlier, energy efficiency, air quality,

08:39and material selection. Um and what was

08:41a great finding was that all the

08:43certifications that we looked at um

08:46touch on um like had some type of

08:47minimum requirements related to these

08:49three components in some way. Um, but a

08:52lot some certifications did have more

08:54minimum requirements than others. Uh,

08:56but and like a couple of them did have

08:58like some additional things that you

09:00could do for like extra points to earn

09:01the credit, but they all did have some

09:03um but they all did have some type of

09:04minimum requirements while more some had

09:06more than others.

09:08And there was multiple ways to hit on

09:10these um um on these different policy 49

09:13components. Um [snorts] this really big

09:16one that we saw was this HERS score,

09:17this home energy rating score. And we

09:20saw that five out of seven

09:21certifications referenced the HERS score

09:23in some capacity and which was really

09:25great because the HER score does

09:26correctly correlate to having um more

09:28home efficiency and lower utility costs.

09:31And as for air quality, one common way

09:33that we saw to hit on that was through

09:36low VOC materials. VOCC standing for

09:38volatile organic compounds.

09:41It sounds like a sounds like a mouthful.

09:43Um but those are essentially chemicals

09:46um that are in paints, glues, acrylics,

09:48um etc. that can be within the home and

09:50they can very easily get into the

09:52atmosphere and can be very toxic. So,

09:53it's very important to keep those levels

09:55low, which we're going to touch on green

09:57guard a little bit more with that one

09:58because green guard actually is a

10:00certification that does look at VOCC

10:02materials and um it ensures that V that

10:05those VC materials are kept at low

10:08levels. And what was really great was

10:10that we saw that green guard was um an

10:12option with other green building

10:14certifications to get that credit for

10:16material selection. So we saw that in

10:18LEAD for example that getting green

10:20guard gold could be counted as a credit

10:22towards getting certification getting

10:24certified with LEAD.

10:29And then policy 96 policy 96 tackled

10:32heat island mitigation and we saw that

10:35four out of seven the certifications had

10:37um relevant standards to this policy. So

10:38they somehow they reference heat island

10:40mitigation in some capacity. However, we

10:42saw that only one certification,

10:44enterprise screen communities, had any

10:46minimum standards for this policy. The

10:48rest of the certifications um had these

10:50optional or additional things that you

10:52could do but were not required unlike

10:54enterprise had.

10:58And then lastly, policy 108. The main

11:00theme with this one was addressing green

11:02rainwater or storm water infrastructure.

11:04And it also touched on heat island

11:06mitigation a little bit more. And same

11:08thing we saw that four out of seven of

11:09these certifications as well um touched

11:11on um touch on this theme as well. Um

11:15but the difference was that no

11:16certifications here had any minimum

11:18requirements um just these non-required

11:20additional things that could be done to

11:21earn some credit towards the

11:23certification.

11:26So some general recommendations that we

11:28are looking to make is one um in order

11:31to meet these policies we're asking that

11:33um that the certification must have that

11:35tie and mechanism that we were talking

11:36about beforehands um before certificate

11:39of compliance. So this is going to

11:40remove energy star and green globes as

11:43um certifications that we are looking to

11:45consider because they do not have that

11:47time and mechanism to promise beforehand

11:49that they will get the certification.

11:51And then as we reasoned earlier, green

11:53guard is not going to be counted as a

11:55green building certification because it

11:57does look at more of materials rather

11:59than the building as a whole itself.

12:04And then our policies um relating to

12:06policy 49 um would be these kind of

12:10three touch points here um to meet the

12:12policy. number one having that same

12:15timing mechanism once again prior to COC

12:17that pre-approval that pre-builds um

12:19certification that we can have um also

12:21adding the HERS index as a target um and

12:25then also once again having green guard

12:27as a qualifier for certified low VOCC

12:29materials once again

12:34let me go back really quickly um and

12:37this below here is um just some

12:39suggestions on how we how we intend to

12:41make these uh changes within the within

12:43the policy commentary itself. We're not

12:45be changing um the policy, just the

12:47commentary to give some more guidance to

12:49applicants for the future.

12:52And then as for policy 96, um our

12:56recommendations here is number one,

12:58commitment um a commitment to enterprise

13:00green communities um their pre-build

13:01approval would be the only green

13:03building certification that would be

13:04able to meet this policy. um instead if

13:09uh applicants did not want to go through

13:10enterprise they would have to commit to

13:12other mitigation strategies which can be

13:14found in these certifications they just

13:16weren't required was the almost the main

13:18thing that we're running into. So

13:20looking within these uh standards to see

13:21like what are the strategies that they

13:23have and using those um instead of the

13:25green building certification itself

13:27counting and um and then right down

13:31here.

13:34Yes. And then um changes to commentary

13:36will include different green different

13:38green um green infrastructure measures

13:41um such as we have we have highlighted

13:44below shaded or permeable hardscape

13:46vegetative walls or roofs and reflective

13:48or light colored materials.

13:52And then finally um policy 108 our

13:55recommendations for here for policy 108

13:57would be that no green building

13:59certification would meet this policy um

14:01at least of the green build the green

14:03building certifications that we have

14:04researched. Um offers will need to

14:07commit to specific rainwater or storm

14:09water green infrastructure features

14:11instead of a green building

14:12certification itself. Um and any um any

14:17text commitments should be analyzed on a

14:18case to on a case- by case basis and

14:20should be done in partnership with the

14:22storm water review um to look at more

14:24green infrastructure practices. Um so

14:26because of that we are not recommending

14:28any changes to this policy commentary

14:31and that is all we have for today. Any

14:33questions?

14:35>> Awesome. Um this is perfect. Thank you

14:38so much for this uh great presentation.

14:40Um great work. we have our regulations

14:42and then above our regulation we have

14:43our expectations and we really need this

14:46kind of work and y'all to to take the

14:48lead on that and I think that that's

14:49that's what this has done. Uh questions,

14:51comments, colleagues, I'm looking to my

14:53left here first.

14:54>> Council member want to go after.

14:57>> Yeah, absolutely.

15:01>> Good morning everyone. Um uh keep going.

15:04Not this one. Not this one. I guess it's

15:06around Energy Star. So, it used to be

15:08with Energy Star that you would as a

15:11builder you had to have a certifier go

15:15through the building, do all kinds of

15:17tests, and then that's what let the home

15:19be energy certified. Is that just a

15:20different process than it used to be?

15:23I believe it is the same process, but

15:25also what we ran into with Energy Star

15:27as well. Um, Energy Star really just

15:29looked at um energy efficiency um

15:31instead of like the building as a whole.

15:33So kind of the same in the same vein as

15:35um green guard. It kind of hits on that

15:37one component um rather than green cert

15:40like green certification as a whole.

15:42>> Okay. Can we get a cost breakdown of

15:44every single program that it would cost?

15:46That would be really helpful.

15:47>> Absolutely.

15:48>> Um I appreciate this. I I don't want to

15:52ding people because they couldn't get

15:54lead, which also has issues quite

15:57frankly. Um, and I don't I guess what

16:02I'm worried about is it's hard to do

16:04some of this, right? It's not

16:05straightforward and and that's a

16:07structural issue of this country, right?

16:09Like this is we don't believe in climate

16:11science in this country, right? Um, so I

16:14think I'm a little bit concerned around,

16:16okay, well, you could get Lovoc

16:18materials in a house, right? But because

16:20you couldn't pony up for lead, then

16:22we're kind of punishing you in a way.

16:24And I will say that a lowvoc house is

16:26better than no Lovak house. I would say

16:29an energy certified house or building is

16:31still better than no Energy Star. So I

16:35appreciate the work and I think it's

16:36right. But we have to give flexibility

16:38especially since we are literally not

16:40allowed to do this, right? This is why

16:41it's all encouraged. It's all it's not

16:43in our UDO. We can't put it in our UDO.

16:45Um and so I I think it's right, but I we

16:50have to allow flexibility. Um and I

16:54worry that we are going to end up

16:57hurting ourselves in a process of trying

16:59achieve while good solid goal

17:04you know

17:06it it's like unintended consequences

17:08right where people are just not going to

17:10they're going to look at the cost of

17:11some of these higher standards let's

17:13just say what they are right more total

17:15more you know comprehensive they're

17:17going to look at that cost and they're

17:18going to say yeah I'm not going to

17:20profer that necessarily I might profer

17:22native plantings or I might give more

17:23door affordable housing, but that's just

17:25not something I'm going to pursue.

17:27Whereas maybe they would have been more

17:29open had it been, you know, a lower bar

17:32to entry. So that's just where I'm at.

17:34>> Can I piggy back?

17:37>> I I hear you saying like don't let

17:39perfect be the enemy of good.

17:41>> So I think just in general, is there a

17:44way to even have different levels?

17:47>> Yeah. um like you know meeting this

17:50highest level versus you know the

17:52minimum level or something like that

17:54that would give some flexibility.

17:57>> Yeah. Like I'll just say like the Energy

17:59Star program. No, it's been many years.

18:01My husband was an Energy Star certifier

18:03for builders for many years. It is not

18:05an easy thing to get.

18:07>> Um the tests that you do on those homes

18:09and those buildings, it's pretty

18:11thorough. Um and I don't Yeah. Like is

18:15there a way to tar it like okay good

18:17effort above average versus an A right

18:21like the same I want the approach to be

18:22the same way we approach grading a thing

18:26right like I many of us have been in

18:28spaces where we have a rubric a

18:30candidate may not be ex like exceeding

18:32or a student may not be exceeding but

18:34that doesn't mean that there weren't

18:37expectations met if that makes sense.

18:42>> Good morning.

18:43>> Go ahead. Yeah. [clears throat] Good

18:45morning GCCPC members. I'm Payton

18:47Burgess with the planning and

18:48development department working on a

18:50little bit of a sore voice so I

18:52apologize. Um, one of the things that we

18:55tried to do with this research uh

18:57project is build in options and

19:00flexibility. So what like the main

19:03reason with Energy Star is that there's

19:06not a sort of guaranteed certification

19:08option that can happen before COC. And

19:11so when we ran into, you know, the issue

19:14with not having a timing mechanism, what

19:16we kept seeing was, oh, this will be

19:17provided back to the city within 12

19:19months of receiving the COC. And there's

19:23not, you know, sort of a a metric on

19:25staff's end that we can ensure that one,

19:27that gets checked for, and two, you

19:29know, if if people are living in the

19:30building and the building is occupied

19:32and they don't get their Energy Star

19:33certification, our goal is not to kick

19:35people out of the building because they

19:37didn't, you know, successfully complete

19:39Energy Star. Um so it's not necessarily

19:42trying to hit a higher standard. That is

19:45one thing that we looked at. Um we just

19:47wanted you all to have the information

19:48about what you know the different levels

19:50of certifications were. Um but our

19:53recommended changes to the policy do

19:54include um options such as utilizing low

19:58VOCC materials and committing to getting

20:02the HERS um the home energy rating

20:04system index target score which is

20:06utilized by Energy Star. Um but that's a

20:09metric that can be received before

20:11certificate of compliance so that it's

20:13something that just the city can make

20:15sure on our end um is achieved before

20:18people actually move in and before the

20:20project is complete. Um so the the goal

20:22wasn't to necessarily raise the bar. Um

20:25the goal was to provide information to

20:27you all to to see maybe where the bar is

20:29in comparison to other things. Um, but

20:32you would receive credit to meet the

20:35policy and exceed UDO standards for

20:38doing the HERS index, for utilizing low

20:40VOCC materials. Um, the only issue with

20:42Energy Star, it is it's a great program.

20:44It just isn't something that we can

20:46guarantee through the zoning system

20:48happens because there isn't that timing

20:50metric before COC.

20:52>> I have a follow-up if that's okay. Can

20:53we get information? because it used to

20:55be that you would get the building

20:56energy starred and that is what then

20:58your home when it goes for market is an

21:01energy star home. So that's how it's

21:03being sold which means that there's not

21:04a person in that house. So um that would

21:07be because I just had this conversation

21:10with a developer who was trying to do an

21:11energy store and they said the same

21:12thing and I'm like that's not actually

21:14how the program works and so can we just

21:17get some background information at least

21:18it didn't used to work that way. I'm

21:20being very transparent and that was a

21:23decade ago. Maybe it's different than it

21:24used to be, but it had to be to be

21:27Energy Star certified for sale anyway.

21:29Like if you wanted to market your home

21:31that way, there was a process that got

21:34you certified and then you were able to

21:36share that with the consumer. So that's

21:39why it should be able to get before CI

21:43um COC.

21:44>> Yeah. I think um so I think part of what

21:46you're mentioning is the the HERS score

21:48that we've talked about um because that

21:50is actually like the HERS home energy

21:52rating system index target is a metric

21:56created by the Energy Star program. So I

21:59>> So that's how it's being sold. This

22:01house or this building is scored

22:02whatever on this test. And so you and

22:04there that that's your kind of um

22:08uh

22:10standard as a buyer, right? like, okay,

22:12if I want a lower energy cost, I can say

22:14that this score, this building or this

22:16apartment or this whatever score this

22:17and so I have an understanding of what

22:18my energy bill is going to be. Okay,

22:20thank you.

22:20>> This score would meet the energy star

22:22standards. It's just not technically

22:23certified yet.

22:24>> Okay, thank you.

22:25>> Yeah, absolutely.

22:26>> I'm going to go to my right. Oh, did you

22:28want to say something? Go ahead.

22:29>> If I could just I think the other thing

22:30that we're trying to do to Payton's

22:32point about flexibility is you'll see

22:34some of these systems have different

22:35levels like I think lead is the most

22:37famous one with like you know golden

22:38silver, golden plat whatever, right? So

22:40we're not specifying a level in this

22:43commentary. We're just saying you could

22:44pick from these to further give people

22:46options. The cost implications, my

22:50understanding is kind of twofold. One is

22:52the improvements that you make to the

22:55structure in terms of, you know, uh

22:57higher RV value insulation or whatever.

23:00Um, and then there's the cost of the

23:03certification of hiring the independent

23:05third-party consultant to come do all

23:07the testing and do that and that um that

23:10in and of itself can kind of be a

23:12barrier. So, we can we can do a little

23:14digging as to um kind of what those

23:17costs might be. It'll be harder to kind

23:20of put a cost together on what the um

23:23improvements to the structure cells may

23:25be because it's such a wide range of

23:26options, but we can we can research the

23:29other. Can I have a and this doesn't

23:31affect y'all's department, but is there

23:33a way because I see our targets

23:35especially around affordable housing and

23:37this isn't um planning necessarily. It

23:39may fall to legal. Is there a way

23:42especially if we are funding a project

23:44from the city that we can have a subsidy

23:47pool so if it's we want our you know

23:51litec deals we want the things that the

23:53city is subsidizing to maybe meet that

23:55green standard right but that builder

23:57maybe can't afford it right is there a

24:00way to create

24:02um public money so that they could

24:04achieve it right we under I you know

24:06like that's that's a question that I

24:09have and I know it's not falling to

24:10planning, but I want the nice things,

24:13right? Everybody wants nice things. I

24:15can't afford a hybrid plug-in. It's too

24:17damn expensive, right? So, I'm going to

24:18go get a gas car because that's what I

24:20can afford. And if we want some of these

24:22things to happen, we're going to have to

24:23subsidize it. And we can't subsidize

24:25private, but maybe we can achieve it in

24:28in the things that are publicly funded.

24:29>> And can I just add, we we have adopted

24:32that policy. Um, recently we Durham

24:35County, we and you could get a copy of

24:38it. we adopted a, you know,

24:41sustainability, green building, whatever

24:44policy that applies to all of our

24:46projects and including ones that are

24:50funded with, you know, like the 300 and

24:52500 East Main Street. Um, so we we

24:56recently adopted that.

24:59>> Go ahead. Yes. Thank you, chair. That

25:00Thank you for your presentation. And so

25:03to the the issue of credits uh your your

25:06colleague just spoke uh a little bit

25:08about that. Uh but on the issue of of

25:11flexibility certainly that helps to to

25:13bridge the gap with regards to

25:15certification. Correct.

25:16>> Yeah absolutely. A lot of them ran on

25:18like um a point a pointsbased system

25:20where like they have those minimum

25:21requirements but there's multiple

25:22different avenues in order to achieve

25:24points. So like for like material

25:26selection for example like they had like

25:27a basement requirement of like maybe

25:29like this level of VOCC materials but

25:31you can also use this type of material

25:32in your home this type of material. They

25:34had different many different avenues in

25:36order to get that credit.

25:37>> Can you provide some some additional

25:39examples?

25:41>> Um let me give me one second to think.

25:44Want to use energy efficiency.

25:50>> Payton Burgess again. Hello. [laughter]

25:54Um, when you say credits, are you

25:58talking about the for the policy or for

26:00like the certification?

26:01>> The certification. Yeah, the

26:03certification itself.

26:04>> Oh, um, they are all so very different.

26:06Uh, attachment A in your packet. It's

26:09like this master spreadsheet that kind

26:11of breaks down some of the different

26:13things. Um,

26:14>> I I merely asked the question. I mean, I

26:16have the packet, but sometimes it's good

26:18for the the public to to hear some of

26:21the things and have some context. So

26:22that's why I asked the question. Yeah.

26:23>> Yeah. Absolutely. What we found was that

26:25some of them focused on different things

26:26like energy starve for example that we

26:28looked at was very focused on um minimum

26:31requirements for energy efficiency

26:33standards but it didn't have any

26:34standards and really any other category.

26:36Whereas lead for example had minimum

26:39requirements in energy efficiency. It

26:41also had minimum requirements and I

26:42think water efficiency. Um it also had

26:45requirements about site selection. Um,

26:48and so just like looking at the

26:50different certifications and and one

26:52thing that we wanted to do with this

26:53whole project was like sort of comparing

26:55apples to oranges, right? Like these are

26:57all green building certifications, but

26:59they all do different things. So putting

27:02them into categories of okay, what

27:05exactly do they do? Where do we have

27:07those minimum standards? Where are maybe

27:09other certifications going above and

27:11beyond and are way hard way harder to

27:13get? Um, and kind of breaking that down

27:15for you all. Overall, I mean, there were

27:17there are minimum requirements for

27:19different certifications in all sorts of

27:22categories. Um, from yeah, heat island

27:25mitigation as was a part of this

27:27PowerPoint to energy efficiency to um

27:31recycling and and the utilization of

27:34like recycled materials in your project.

27:36And I mean even there were standards on

27:39how to operate the construction site in

27:42a way that doesn't you know cause a

27:44noisy environment to neighbors. Um so

27:47across the entire certification metrics

27:50we'll call it. Um I mean there were so

27:52many different standards in different

27:55categories. Does that kind of answer

27:56your question? Uh yes and so and I think

27:58more to the point of uh mayor prom when

28:02she was talking about the you know this

28:04being costly for for many in many

28:06situations this shows that you can

28:08bridge the gap even under those

28:10circumstances to to get to a

28:11certification that aspirationally we all

28:14think is a you know where we're headed.

28:16So thank you.

28:18>> I'm I'm glad you raised the uh concept

28:21of people watching in on this meeting.

28:23So I am going to take one minute to just

28:26take a step back for people who might

28:28not understand. So we have our

28:30development regulations

28:32um and those apply to zoning case the

28:35zoning that that is on the land um and

28:38some people come in and they want to

28:40change the zoning that applies to them

28:42um so that they have different

28:44development regulations that apply to

28:45them. This is not part of any of that.

28:48This is um sometimes we receive offers

28:52from folks who are trying to change the

28:54zoning that applies to the land that are

28:56go above and beyond

28:58uh the zoning uh requirements under the

29:02existing UDO. And of course, we're

29:04looking at the the new um UDO aka the

29:08LDC

29:09um which would have even newer

29:12development regulations. So this is just

29:15helping to inform us about uh

29:18recommendations that the planning

29:20department uh might make to a applicant

29:23or prospective applicant when they come

29:25in the door um and they're thinking what

29:27do I what do I what should I do? How can

29:30I uh go above and beyond the the UDO in

29:33in requesting um in requesting this?

29:36That doesn't mean that they have to do

29:38this. Many won't. Um, some will. Um, but

29:42this is a way and and what you've you

29:44all have done is is said here's here's

29:47where in that application process for

29:49going above and beyond on these

29:50different certifications we can get in

29:52writing and not just verbally say we

29:56hope to do this. We can get this in

29:58writing. Um, and again they can pick

30:01from a wide array. They could not do any

30:03of this. Um, this is a discretionary

30:06approval uh process. So, I'm hoping that

30:11helps lay the a little bit of the

30:12foundation where we are. Council member

30:14Copek, um, Commissioner, uh, would are

30:17you going to want to ask any questions?

30:19No. Okay. Council member Copek.

30:20>> Yeah. Thanks to all my colleagues for

30:22questions and comments. The chair

30:23helpfully made many of the comments I

30:24was just about to make, so I'll make it

30:25short. Um, I'll just say I appreciate

30:28the work that you've done to tighten

30:29this up. I feel like just like staff and

30:31this body did in um kind of going

30:35through the E process for technical

30:37revisions on the comp plan. I just think

30:39this helps bring greater clarity and

30:41makes it easier for all parties to use.

30:43Uh and would just associate myself with

30:45the rest of my colleagues comments.

30:46Thank you.

30:51>> Yeah. Well, I think I mean this and then

30:53you know some other items on our agenda

30:55today really are fantastic. I just want

30:58to really applaud the staff for doing

31:02this kind of work which is re is the

31:05real policy work of digging in and

31:08seeing how how things are really working

31:10and making recommendations.

31:12So thank you so much. This is really

31:15great work. Um, so since we the county

31:19commissioners don't really sit on

31:22zonings, resonings, it's um I would love

31:26to just hear I I mean I've gotten a

31:28little glimpse of the context, but I'm

31:31just curious um I look, you know,

31:33looking back at the the other report

31:36about the how the policies are being

31:39implemented, you know, and kind of

31:41trying to look at the numbers, um trying

31:44to understand like How is this really

31:46happening in real time? I'm I'm really

31:49thrilled to see that people are trying

31:52to, you know, achieve these policies. I

31:56think this is showing that uh we are

32:00making progress towards implementing the

32:04adopted comprehensive plan goals. Um

32:08knowing that these are not required,

32:10these are aspirational, right? But the

32:13fact is that people are wanting to do it

32:16in our community. So I'm just curious,

32:18are you seeing this with smaller

32:21developers, big developers, both? Like

32:25what how is this h playing out in in

32:28real time just want to understand a

32:31little bit more.

32:34>> I think that um my opinion, my

32:36perception um I think that the bigger

32:38developers or the bigger bigger projects

32:40have a lot more flexibility in what they

32:41can offer. Uh and so it depends. So some

32:44folks are offering more on affordability

32:46or they're doing more traffic um or

32:49buffering or whatever to to to respond

32:51to community. Um we are seeing more of

32:54these types of profers. I would say that

32:57smaller projects are and when I say

32:59smaller, I'd say anything under 100

33:01units. Um especially under 50 units,

33:04they're just not going to have the

33:05margin to play as much. And we have to

33:08be really honest and transparent. And I

33:10personally think we are um it's good to

33:13move the goalpost, but we also have to

33:15be really diligent that we are not

33:18letting um the perfect be the enemy of

33:21the good and and really understanding

33:22how the applicant is arriving at our at

33:25our door, for lack of a better word. And

33:28believing that proformers are real

33:30things and that money are it's a real

33:33thing and a bank is not going to give

33:34you money if it doesn't think it's going

33:35to get a return. And we have to be

33:38honest with ourselves that that is a

33:40reality and it's not made up.

33:44>> Um yeah because I think also that's

33:46really helpful. Um these policies

33:50are important because

33:52for a few reasons. One is there we're

33:55we're addressing issues around climate

33:57change that are real and that we're also

34:01addressing,

34:02you know, people living in a healthier

34:04home. And at the end of the day, if

34:08we're talking about affordable housing,

34:09it's important to have the big picture

34:12that they're living in a home that

34:14they're not going to be paying through

34:15the roof on utilities. Um it's again

34:18with climate change, you know, with

34:21colder winters or hotter summers, you

34:23know, if you're paying exorbitant um you

34:27know, uh utility bills, it's going to

34:30counteract your affordable housing. So I

34:33think I think I I really think these are

34:36important policies, you know, if we look

34:39holistically at, you know, housing. Um,

34:43so I I appreciate the flexibility also

34:48um in people being able to meet them and

34:50I'm what I'm assuming is if the larger

34:53developers are doing it as part of their

34:55marketing as well maybe that this is

34:57what we're offering to people. Um so

35:01when I looked back at the report on how

35:05the policies are being implemented for

35:0849 96 and 108 I thought it was

35:12interesting just to see the numbers in

35:14how many are actually meeting it

35:19not meeting it um and not applicable and

35:22there is a good amount

35:25um when it is possible who are not

35:27meeting this just any idea idea.

35:31Um just I mean this not really

35:35scientific but do we know why

35:40so many for instance 49

35:42it was 13 exceeded

35:4623 were not applicable and then 40 were

35:50not met. So obviously in that area most

35:54are not meeting it. Um just any idea

35:57what is happening or playing out.

36:04>> So you're looking at policy 49.

36:06>> Yes. Just for instance, I looked at all

36:08three, but yeah.

36:11>> Yeah. Um the reason why some are not

36:14applicable

36:15would be if these were um zoning map

36:19changes that only included uh commercial

36:21development. So this only applies to

36:24residential or commercial that have the

36:27have had the possibility to include

36:29residential at the time of site plan. Um

36:32so that's why there's some discrepancies

36:35with a lot of these housing policies

36:37versus um a lot of the reasonings that

36:39come in as industrial or commercial

36:41development. So that sort of explains

36:43the variability on that

36:44>> and how about 40 unmet.

36:50So

36:51>> they just did not provide any green

36:53building. They did not provide any uh

36:55profer to address

36:56>> okay

36:57>> uh green buildings a lot of the times

36:58that is that certification. So we would

37:03>> basically when we started this in 2023 a

37:06lot of the the first cases the comp plan

37:09was new. We weren't seeing any type of

37:11certifications in like the late 2023

37:1424

37:16>> but it's progressed uh since then.

37:18>> Okay. So that initial period was an

37:21interesting time. So

37:23>> okay,

37:23>> not everyone um does the same thing as

37:26they do now.

37:27>> Yeah, I'll also say that you know uh it

37:31is extremely rare to have a case that

37:35meets almost all or all of the

37:37applicable policies, right? And so to

37:40Mayor Prom's point, applicants are

37:42having to choose like where they're

37:43going to put their limited amount of

37:46kind of discretionary money they have

37:47built into their project performs and

37:50whether you know um if is if their

37:52priority is going to be you know

37:54profiting affordable housing then maybe

37:55they can't profer you know some of these

37:57certifications because they're choosing

37:59where they're going to put that money.

38:01So I think that is a lot of the calculus

38:04that goes into what folks figure out

38:06that they can profer. Um, and why we see

38:09that in a lot of these cases, you know,

38:12there's a good amount of folks that

38:13don't touch these policies.

38:15>> Yeah.

38:16>> Oh, I'm sorry.

38:16>> Go ahead.

38:17>> In addition, the a lot of these housing

38:20policies, the 32 uh typically applied to

38:24just to uh zoning map changes. So, a lot

38:27of this data includes annexations as

38:29well. So, if there was only an

38:31annexation,

38:32those initial 32 policies wouldn't be

38:35applicable. So, that's another reason

38:37for that variability. Uh-huh. Yeah. I

38:39thought it was interesting that in this

38:41one there were zero that met but 13 that

38:44exceeded.

38:46>> So it cannot um because there's no UDO

38:50standards for green building anytime you

38:52include it as a proper it's

38:55>> can't be it has to be exceed. Okay.

38:57>> And we're not legally allowed to have

38:58this. That's why it's not there is no

39:00standard because we're not allowed to

39:02ask for a standard

39:04>> or require a standard. We're we're

39:05asking for a standard but we cannot

39:06require it.

39:07>> Right. And then when we are able to

39:10adopt the LDC,

39:12how what how will that look? Because I I

39:16I know there was a portion in the LDC

39:19that was related to um a you know

39:23getting higher density with doing some

39:26of these things. So could you just

39:28remind us that when we do pass the LDC

39:32what will this some of these what will

39:35happen related to these three policies

39:38that we're looking at right now?

39:39>> I'll defer to Bo

39:43>> Bo Dinsky land development.

39:45>> Yeah. and the draft land development

39:47code. uh two things. There was there

39:49were provisions where you could get

39:50additional density and if you chose to

39:53build under those development

39:55regulations similar to like a a density

39:57bonus, there would be additional

40:00requirements um with uh I believe some

40:05of the certifications, but it was it was

40:06also other things getting at green

40:09building um and sustainability in

40:11general, which may be less than uh sort

40:15of the certification standards, but

40:16we're build concrete design improvements

40:19that we can't otherwise require. Uh,

40:22additionally, um, for larger

40:24developments and I don't remember the

40:25exact threshold, uh, there was a

40:27requirement to meet a certain score on a

40:29sustainability matrix and, um,

40:34also getting to the same point and that

40:36was actually required across the board

40:37for developments of a certain size or

40:38commercial developments. So, uh, this is

40:41obviously a component of that. um when

40:43we're looking at sort of sitewide,

40:44right? Like it's more than just the

40:46improvements of the building or it may

40:47be different than just the energy

40:49efficiency, but this this research will

40:51certainly feed into uh potential

40:54additional um rows in the matrix itself.

40:58So

40:58>> yeah, I was going to get into that

41:00because this is just discretionary

41:04>> for this

41:05>> site or this land that's going through a

41:07discretionary review process. But the

41:09LDC would build essentially our own

41:12point system in to the regulations that

41:15would apply to all development, not just

41:16if they're going through a discretionary

41:18process.

41:19>> Right. So, I think it's important for us

41:22and for the community to understand the

41:25importance of us being able to adopt the

41:27LDC because there's so many things that

41:30people care about that we're going to be

41:33so much more effective at

41:36being able to do and see happen when

41:39that when we are able to adopt that.

41:43>> Council member Copek.

41:45>> Yeah. Thank you, Chair. So,

41:48first of all, I'll just say we've also

41:49heard from a few developers during that

41:51discretionary review process

41:54who've said that they just have not done

41:57these sorts of certifications before in

41:59other projects. And we've seen I think

42:01maybe on a couple projects movement

42:03where developers uh work to integrate it

42:05into a project because they were seeking

42:07to align with the comp plan. But I think

42:09part of its cost, you know, part of it

42:12is also just, you know, a lack of

42:15movement on this uh particularly in the

42:17US. Uh and so having this in place is

42:19something we point to is another way we

42:21can sort of nudge development in this

42:23direction. But I agree with the

42:25importance of passing the LDC where we

42:27have the sustainability matrix where it

42:29just applies, you know, to all

42:30development versus just these rare cases

42:32in discretionary review. I want to say I

42:35was excited to hear about the county and

42:37what you've put in place uh in terms of

42:39policies for for your projects. And so

42:41that's something that I definitely want

42:42to look at. And just going back to Mayor

42:45Prom's um you know comment about you

42:48know subsidizing LITC uh and you know

42:50other projects to help sort of move this

42:52along because it is expensive and it can

42:54be difficult to do. Uh and the point

42:56that um Commissioner Jacobs made around

42:59energy affordability. I think that's

43:01something that actually came up in

43:02discussion with director Vinius who's

43:04here in the room today uh when we had

43:06discussions around our affordable

43:08housing strategy that you know this is

43:10really a crucial part of affordability

43:12and these you know issues are linked uh

43:16and the work of the comp plan and our

43:18affordable housing strategy are linked

43:19and so I just love how uh you all were

43:21sort of putting those together and I

43:23want to just highlight those again.

43:25Yeah, I think you um rais a a good point

43:28about um there's a cost to learning

43:30something new. There's a cost associated

43:33with learning how to build something

43:35more sustainably and do something

43:37better. And so there is a part of this

43:39is a culture shift and and the cost will

43:42be higher as you're learning, but once

43:44you build a culture where it's normal to

43:46build more sustainably, you're lowering

43:48that cost. Um and and we're not there

43:50yet, but I think that was a a good

43:52point. Yes. Thank you. Is there an

43:55opportunity for us um

43:58in the city just like we do some things

44:00around you know OEWD around folks having

44:04capacity building to learn some things

44:05about how to run a business. It's the

44:07same thing for our building community

44:08around learning. So again like this is

44:12this is decades in right my husband went

44:14to architecture school and like fighting

44:17to like how do you design a thing? How

44:19do you put uh or how do you orient a

44:21building so it's closer to HVAC system

44:23so you're not running uh wiring longer

44:26than you need to and it is a huge

44:27culture shift and and a lot of it is

44:29people are used to doing a thing a

44:30certain way. We're all like this right

44:32contractors are used to doing a thing a

44:34certain way and if we want it to be done

44:36differently I think you a have to

44:38incentivize it. Um, and you know, I

44:42mean, you get a you if you don't smoke,

44:44you get a different rate on your health

44:46insurance, right? Like, we have to think

44:47about it that way. Um, so is there is

44:50there opportunities for the city to uh

44:53get some folks in to encourage even the

44:56smaller projects um who who don't have,

44:59you know, if you're if you're brand new,

45:00and we've seen this recently, a small

45:03development, the person really doesn't

45:05know what they're doing. It's their

45:06first time in their their learning curve

45:08is huge. a lot of those folks are more

45:10local and so that's the ecosystem we

45:12want to keep creating. Can we think

45:14about doing some workshops, bringing

45:16some folks in, really creating that

45:18ecosystem of learning? Same thing with

45:20our contractor community. Can we work

45:22with um the homebuilders association and

45:26other folks and and really not have this

45:29adversarial thing that we've got going

45:30on right now and be like, okay, how do

45:32we do this together so that ultimately

45:34you get something that you want? you can

45:36market a product in a certain way and we

45:40get more sustainable um housing and and

45:42buildings out there.

45:45>> Yeah, we you know we have a very good

45:47working relationship with the

45:48homebuilders association. We meet with

45:50them regularly and partner um on a bunch

45:53of things. So it's certainly a

45:55possibility and something that I will

45:57discuss with their leadership about um

46:00you know the possibility of doing a

46:02workshop or something. We also have been

46:05trying quarterly to uh have a specific

46:08kind of uh we call it resoning round

46:11table. It's a meeting with folks um in

46:13the development community that

46:14specifically work on um resonings. And

46:17so that's another venue where we could

46:19have maybe a little kind of mini

46:21training session on, you know, um these

46:24these programs kind of what they entail

46:27and connect them to some resources so

46:29they could um avail themselves of them.

46:32So

46:34this morning, um this goes back to uh

46:38with our lobbying firms and I mean this

46:39is to me an opportunity of like we know

46:43who's in Raleigh but affordability is an

46:45issue that everyone is feeling and so if

46:47there is opportunities to work with our

46:51the realtor community, the development

46:53community around legislation

46:56incentivization at the state level. Um,

46:59I know that that's like pipe dream right

47:01now, but we're seeing interesting things

47:03happening on both the housing and

47:04transit side because everyone is feeling

47:07that, including Republicans. And so,

47:09where are the opportunities around, you

47:13know, we we want certain standards and

47:15we're going to have to provide

47:16incentivization around that. So, if we

47:19want larger developers to have this kind

47:21of building standard, is there money?

47:23And we're not going to be able to afford

47:24that at the local level, but what are

47:25the opportunities to work with other

47:27communities pushing that needle at the

47:29state level?

47:34I just want to follow up on Mayor Bert's

47:38idea about um how do we this is what we

47:42learned in Grand Rapids

47:45about how how do we pull people together

47:48and work together in a positive way

47:50towards a goal at the community level.

47:53Um, I really love that idea of how do we

47:56do, you know, bring people together,

47:58workshopping on building up skills on on

48:02some of these goals and um what comes to

48:06mind is also Durham Tech because um you

48:10know we have that's one of the skill

48:12trades or one of the [clears throat]

48:13areas of focus at Durham Tech. So even

48:17going to in terms of how we're people

48:20are being trained right now, you know,

48:22whether it's construction,

48:25uh, you know, HVAC,

48:28um, things like that. Um, so we could

48:30even think about bringing Derm Techch

48:33into that conversation about how how are

48:36they teaching people um about

48:41building in a sustainable way. So if we

48:44really want to create an ecosystem

48:48that would be great.

48:51>> Thank you all for your wonderful

48:52comments. Are there is there anything

48:54else? No.

48:57Um thank you for this work. I I just

48:59want to add one other thing which is

49:00that um you know this is about uh the

49:04buildings. Um but there's so much more

49:07that goes into sustainable development.

49:10uh the way that the buildings interact

49:12with the streets and are arranged on the

49:14site and are arranged relative to

49:17adjacent buildings and adjacent sites.

49:20Um and so but this is that this is an

49:23important piece with regard to buildings

49:25specifically and uh yeah this is uh

49:28really great work, great project, really

49:31important information. Um

49:34most of my questions were already

49:37discussed and answered. I guess one

49:39final question I have is

49:42um scenario where we've adopted the the

49:45LDC, are we still going to be would we

49:49still be using this kind of thing um at

49:52the discretionary review stage?

50:02So uh yeah, we certainly um with the

50:07additional requirements that would be in

50:08the land development code on by right

50:10development um we imagine we don't know

50:14this for for sure but that that could

50:17also become a menu for particular

50:19commitments. Um not the same thing but

50:21similar to today the way that uh an

50:23applicant may commit to a particular

50:25housing type in the current UDO. I

50:27imagine that uh uh someone requesting a

50:29resoning could profer, hey, we will be

50:32doing X certification out of those lists

50:34or or other site improvements, right?

50:36Like perfect. You know, there's there'll

50:37be a lengthy list. So,

50:38>> perfect.

50:39>> All right. Thank you so much. Uh

50:43the next item, are we ready for number

50:46five? Okay.

50:49Because we can also they need more time.

50:55>> We're good. Okay. All right. We're going

50:56to go back to item number five, which is

50:58the growth manage management trends and

51:01analysis. This

52:13Thank you so much.

52:16Um I'm here to present the growth

52:17management trends and analysis report

52:20and if you read through it, thank you so

52:21much. I know it was a bear of a

52:23document. Um so as part of this

52:27presentation I'll present data on growth

52:29trends regarding legislative actions

52:32focusing on aspects of land use

52:33specifically the place type map and

52:35changes uh the urban growth boundary

52:37future growth areas uh comprehensive

52:40plan policies and affordable housing and

52:44um this is information only so no

52:47actions required from you um so there's

52:49no vote that is required once I finish

52:53>> Andy let me step in real quick and just

52:56uh you all are probably noticing this

52:58slide. So, this is something that has uh

52:59the city council has started for their

53:02work session presentations to give

53:03clarity to the council as to like what

53:05the ask is if there is one. I thought it

53:07would be good to include that here also

53:09because I think sometimes there's

53:10confusion like do you need a vote, do

53:11you not need a vote, what do you need?

53:13So, we're kind of triing it today. I

53:15just wanted like you know later y'all

53:17can give us some feedback if you want us

53:18to keep using this. Um

53:20>> so far so good. I think uh lots of

53:23smiling.

53:27>> Cool.

53:29Awesome. Um so just to give you some

53:31background, um the reason why I'm here

53:33is because of the comp plan in 2023. It

53:35was adopted and it included four big

53:38things as part of this report. One's the

53:40urban growth boundary, one's the

53:42establishment of the future growth

53:43areas, the place type map and the

53:46specific D policies that uh tie into uh

53:49zoning map changes and annexations.

53:54Um so there are three time periods of

53:56this report. Um the first period is

53:59going to be the place type map and the

54:01UGB status. So that time period is from

54:03October 16th, 2023 to June 22nd, 2026.

54:09So over that time period, there's been

54:11107

54:12um privately initiated zoning map

54:15changes and annexations decided by the

54:16board of county commissioners and the

54:18city council. Uh within the city, 92

54:21cases were approved, 12 denied within

54:23the county. Of the three cases heard,

54:26three were approved.

54:28Now, some background information

54:30regarding the comp plan. Um it does

54:32establish the place type map. And in

54:35that map, there are seven general place

54:37types. Um and within those seven, there

54:40are 20 specific ones that we deal on a

54:43daily basis.

54:46Um

54:47this slide here just shows sort of the

54:49breakdown of the approvals and denials

54:52of the cases that staff found consistent

54:54and inconsistent with the place type

54:57map. So of those under 170 107 cases, um

55:03those that were approved within the city

55:04and were consistent were 76. Those

55:07within the city approved but found

55:09inconsistent were 16. Uh 12 were denied.

55:13Um within the city, five were five of

55:17those were consistent and seven were

55:18inconsistent within the county. One was

55:21found consistent by staff and two were

55:23were found inconsistent.

55:27So what does that really mean? Um, so

55:30anytime an inconsistent zoning is

55:32approved, it automatically changes the

55:34place type per state law. And so what we

55:37see here is sort of what those changes

55:40look like. So a lot of the inconsistent

55:43um zonings that were approved um

55:47increased the residential places to

55:49about uh 223 acres that were gained.

55:53Um those 223 acres uh came from those

55:57places um industrial places, employment

55:59places, commercial and pretty heavily

56:02those mixed use places within the comp

56:04plan.

56:07The interesting thing is when you sort

56:09of look at it um from the initial to the

56:12existing overall there isn't that um

56:16much percentage of change. The most

56:18percentage that we've seen is about 1.6%

56:206% change of a specific uh general place

56:23type.

56:25Now when you look into those 20 specific

56:28place types um there's some interesting

56:30uh data points. Uh specifically um there

56:34are three main one ones that were added

56:35to suburban commercial gained over 13

56:38acres. Mixed residential neighborhood

56:40place types uh gained 138 acres and then

56:44close to 100 acres were added to the

56:46apartment and townhouse neighborhood

56:47place type.

56:50Um specifically

56:53um from the neighborhood services place

56:55type about 12 acres were removed. Uh 11

56:58acres were removed from highway

56:59commercial 42 from transit opportunity

57:02areas

57:03and more importantly uh 112 acres were

57:07lost or removed from the mixed

57:08neighborhood place type.

57:12The other component of this first part

57:14of the report is an update on the UGB.

57:17And as a reminder, the urban growth

57:20boundary is just a policy that

57:22delineates where utilities should go.

57:24Um, a few of the highlights are in

57:26orange.

57:28Um, since the adoption, it has not

57:31moved.

57:32Um, we've had three annexations

57:35outside the UGB and all were denied. And

57:38within the UGB, uh, 1,800 acres have

57:42been annexed into the city.

57:46The other component is an update on the

57:48future growth areas. And within the comp

57:51plan, it identifies eight areas that

57:53sort of need infrastructure upgrades.

57:56The types of infrastructure that's

57:58wanted in most of those is either fire

58:00or utility services.

58:02Uh some highlights. Um no FGA has been

58:05removed since adoption. And four of the

58:08six cases um that were in the FGA were

58:11denied.

58:14And here is an update on some movement

58:16within those FGAAS. Um within the

58:20Southeast FGA, we did lose um 87 acres

58:25through an annexation.

58:27At the same time, uh fire station 21 um

58:31is included in the proposed CIP. I

58:33believe it's for design work of that

58:35fire station and that would eventually

58:38be located within that FGA.

58:41The other FTA where we've seen movement

58:43is the Southwest FTA. Um the Celeste

58:47Circle pump station has been completed.

58:49Uh so we can knock that off. Um in

58:53addition, uh the Downing Creek and

58:55Downing Woods pump station upgrades,

58:57those CDs have been approved and Downing

59:00Creek is expected to be completed in

59:022027 and Downing Woods is expected to be

59:05completed in 2028.

59:09So, a few key takeaways from this part

59:11of the report. Um, again, the EGB

59:14remains unaltered.

59:16Uh, investment is still needed in six of

59:18the eight FGAs to support development.

59:20And because of the initial uh changes to

59:24the place type areas, the ability to

59:26meet the 15 minute city uh community

59:28goal may be impacted by the loss of

59:30mixeduse places and neighborhood

59:32services over time. So, in the future,

59:34that just may be something that we have

59:35to continue to look at.

59:38So, I will break uh if you guys have any

59:41questions regarding this this part.

59:44>> I'm going to just start with a couple um

59:46and then I'll turn to colleagues. I'll

59:48go to my right first and I'll go to my

59:50left. Um just a quick reminder is this

59:54so this is our first kind of growth this

59:58is a growth management report and

1:00:01presentation

1:00:02>> correct?

1:00:02>> Okay. Yes. And this is it is this

1:00:04intended to be kind of like

1:00:05comprehensive in growth management or

1:00:07just just very specifically looking at

1:00:10like change in place type.

1:00:12>> I think the idea is to grow. Um this is

1:00:15the first step.

1:00:16>> Okay. Okay.

1:00:17>> Um there's a lot of learning that can be

1:00:19done with this. Um feedback's always

1:00:21wanted.

1:00:22>> Okay.

1:00:22>> But again this is our first dab since

1:00:25the comp plan has been adopted.

1:00:26>> Perfect. Perfect. Okay.

1:00:27>> Yeah. And there's a few more sections.

1:00:29So the presentation isn't done. This is

1:00:31just the end of the first. So, I just

1:00:32want people to

1:00:33>> There's more. And you're just pausing.

1:00:35>> Yeah.

1:00:36>> Okay. Okay. Yeah. Got it. Got it.

1:00:40>> Yeah.

1:00:40>> I I would I would support waiting to the

1:00:42end, colleagues. Everybody supports.

1:00:44Okay.

1:00:45>> Fantastic. Thank you.

1:00:47>> Well,

1:00:49um second period. Um

1:00:53all right. So the second component of

1:00:55this report involves sort of a review of

1:00:57the comp plan policies. As most of you

1:01:00know, incorporated into the staff report

1:01:02is a comp plan policy review document

1:01:04where staff sort of analyzes the comp

1:01:06plan or the development plan and its

1:01:09consistency with those policies. Um so

1:01:12the full the full report is an

1:01:14attachment A. Um but I wanted to show

1:01:16you sort of sort of a highlight of what

1:01:18the analysis actually looks like. Um so

1:01:22each policy the 36 um policies that were

1:01:26analyzed uh each one um examines its

1:01:31applicability, its consistency and how

1:01:34the policies are exceeded, met, not met

1:01:36or applicable.

1:01:38And then and the main body of that is

1:01:41sort of a qualitative analysis of sort

1:01:44of how the policies were met and sort of

1:01:47how staff's interpretation has changed

1:01:49since the first um since the first uh

1:01:52comp plan was adopted in 2023.

1:01:56Here's just a breakdown of what was

1:01:58actually reviewed. And this is the a

1:02:00two-year stint versus like a two and a

1:02:02half year uh versus the previous one. So

1:02:04this is only it takes into account cases

1:02:07from October 16th, 2023 to October 16th,

1:02:102025.

1:02:11Within that period, 82 cases

1:02:14um were reviewed using those policies.

1:02:18Um from the cities uh of those 74 were

1:02:21approved, six were denied. In the

1:02:23county, the two were approved.

1:02:27Now I recognize it's a bear of a

1:02:29document that attachment but I just

1:02:31wanted to point out a few highlights uh

1:02:33from that document regarding policy 32.

1:02:37This is the historic preservation or

1:02:39historic policy um within our document.

1:02:43Um so within that two-year period uh we

1:02:45had three cases that actually included

1:02:47historic structures. Um those

1:02:49development plans include additional

1:02:51protections. Those were in the form of

1:02:53full or temporary protection. um for

1:02:56them. Um the way that they did that was

1:02:59to prohibit demolition as a zoning

1:03:00condition. Policy 33. Um one of the

1:03:04interesting things is no development

1:03:06plan included a solely single family

1:03:09residential development. Of the six or

1:03:12seven that included single family as a

1:03:14an allowed house. Um there is either a

1:03:18maximum requirement or or a minimum

1:03:21there's a minimum requirement of an

1:03:23additional housing type to ensure that

1:03:25nothing was fully single family which I

1:03:28found was pretty interesting.

1:03:31Um

1:03:32so policy 48 um this refers to the

1:03:36accessibility policy.

1:03:38Um so there's only two types of ways

1:03:41that we've seen this being committed

1:03:42before. Generally, if it's an apartment

1:03:45building development, they will include

1:03:49um elevators as part of a zoning

1:03:51condition which goes above and beyond

1:03:54which would meet this policy. And

1:03:55typically for town houses or um those

1:04:00single family ones, they will include uh

1:04:03first floor living or at grade

1:04:04entrances. So, those are some of the

1:04:06ways that this policy has been met over

1:04:08the past two years and currently. Um,

1:04:1149, I won't get much into detail because

1:04:14you guys had that conversation.

1:04:17Um, a few of the transportation

1:04:18highlights. Um, again, 55, 57,63, those

1:04:23are the transportation ones and as you

1:04:25know, they're always met by meeting UDO

1:04:27standards. And one of the reasons why we

1:04:29consolidated that in the E

1:04:35And here are a few of the environmental

1:04:36and public spaces policies. Um, one of

1:04:39the more interesting things is policy

1:04:4185.

1:04:43Um, this is the infamous one where we

1:04:45want tree coverage beyond what the UDO

1:04:47requires. And so in that two-year stint,

1:04:50we have um in development plans, they

1:04:54have committed to an additional 84.85

1:04:57acres of tree coverage beyond what the

1:05:00UDO requires. Um I'm sure that will

1:05:03increase um with the cases past this

1:05:06time period, but that is an interesting

1:05:08fact. Um policy 96 um again a few of the

1:05:14ways that it's only committed to or

1:05:17consistent by that we've seen is

1:05:19limiting impervious surface or double

1:05:22counting additional tree coverage and

1:05:23sort of how you meet that. And policy

1:05:26101 is the native plantings policy. So,

1:05:30of those of the all the cases that

1:05:33exceed it, 50 of those actually include

1:05:35all plantings to be native. And what

1:05:37we've seen is there's a variety of ways

1:05:39to meet this policy. One, you can either

1:05:42commit to all required plantings and

1:05:44what that includes is uh street trees,

1:05:47vehicle use area landscaping, project

1:05:50boundary buffers. this type of

1:05:52commitment that does all plantings um

1:05:57pretty much requires all those areas to

1:05:59be native species but we've seen certain

1:06:02percentages whereas it's like 75 or 50%

1:06:05where they may include street trees or

1:06:08um that type of thing. So there's a

1:06:10variety, but we that was an interesting

1:06:12fact, something that came out of

1:06:16um here the educational policies. Um

1:06:19policy 152, um there's in that two-year

1:06:22stint, $1.2 million have been profered

1:06:25through the legislative process.

1:06:28And policy 155, uh no one's done that

1:06:32yet. That's one of the reasons why it's

1:06:33been removed and that is the the ability

1:06:36of an applicant to actually profer land

1:06:38for a school and one of the reasons why

1:06:41it was removed. I do want to highlight

1:06:43as part of our work. One of the things

1:06:45that we continuously do as stated before

1:06:48is examine these policies and its

1:06:50effectiveness achieving the goals of the

1:06:51comp plan. And so what Bri and Payton

1:06:55did uh previously uh we will continue to

1:06:58do that as um as time permits.

1:07:04All right, third period. You guys ready?

1:07:08All right. Cool. So along with the place

1:07:12type map, the UGB, the FGA, and those D

1:07:15policies, housing and specifically

1:07:18affordable housing is a big theme of the

1:07:20comp plan.

1:07:22In 2022, it was projected that we needed

1:07:2560,000 housing units.

1:07:28In 2025, that's come down to 51,300

1:07:31housing units needed.

1:07:36Here we go.

1:07:38So, here we have a breakdown of uh

1:07:41approved housing units per the site

1:07:43plan. Um, and this is since 2020. And

1:07:48what you see is

1:07:50there's about 37,000 units that were

1:07:53approved with development plans or

1:07:55associated with the development plan.

1:07:58In addition, um there's actually a total

1:08:00of 27,000

1:08:03units approved in site plans. When you

1:08:06break down that 27,000

1:08:08units approved, about 19 are with those

1:08:12um approved development plans and about

1:08:148,000 are by right developments.

1:08:18And currently there are 8,000 units

1:08:20under review. Of those about 6,500 are

1:08:24through um associated with the

1:08:26development plan and the 1500 are

1:08:28developed associated by by right

1:08:30development.

1:08:34what what does that actually look like?

1:08:36Um so here um this slide shows you sort

1:08:39of what's been constructed uh since

1:08:422023. So in fiscal year 2023

1:08:46uh a little about uh 5,500 units have

1:08:49been built in the city and the county.

1:08:51Uh the blue is the city, the county as

1:08:54the teal, which is my wife's color. Um,

1:08:59in FY24,

1:09:01uh, there's about 3,000 units being

1:09:03built or were built, uh, 4,400 in 2025

1:09:07and then, uh, 5,700. So, about close to

1:09:115,000 units a year, um, since 2023.

1:09:15So, roughly about 5,000 units are

1:09:17actually constructed uh, a year on

1:09:20average.

1:09:24So, what does that mean for affordable

1:09:25housing? um at least through the

1:09:27legislative process.

1:09:30Um so here we have a breakdown of

1:09:35of a a lot of different things.

1:09:39Um just to get your head around uh the

1:09:41top part. So

1:09:44we have a number of current development

1:09:46plans that are active that have been

1:09:48approved and on file. those development

1:09:51plans

1:09:53um allow or require or have proper um a

1:09:58maximum of 27 or 2,700 affordable units

1:10:03as part of this zoning condition.

1:10:07Does that make

1:10:09So there are 27 So within all the

1:10:11development plans in Durham, there are

1:10:132700 affordable units that need that

1:10:16would be required to be built if built

1:10:18out to full capacity.

1:10:22Now what we've seen is we've only had

1:10:25100 or 314 of those units have been

1:10:28constructed.

1:10:30those units that are tied to those

1:10:31development plans, those affordable

1:10:32units that are tied to the development

1:10:34plans, um 788 are under construction,

1:10:40more than half of those already have the

1:10:42deed restrictions in place regarding the

1:10:44AMI um and tenure. Um and then we also

1:10:49have a number of 528 site plan approved

1:10:53units. Um, and what this really shows is

1:10:58a lot of these numbers fall within that

1:10:5980% range that we're looking for for

1:11:03development plans. As most do not know,

1:11:06when you commit to um a max intensity or

1:11:09density with the development plan, you

1:11:11have to at least build 80% of that

1:11:13intensity. So, the range of the

1:11:15affordable units to what could be built

1:11:17would fall in that 80% range. Just a

1:11:20point of clarification. What you're

1:11:22saying is that when even though a

1:11:25certain number of units are approved,

1:11:27when it comes down to building the

1:11:29project, the developer may not actually

1:11:32build that number and then the

1:11:33corresponding number of affordable

1:11:35units.

1:11:36>> Correct. Depends on how they profer it.

1:11:38>> Um most of what we see is a percentage

1:11:41of the total. However, there are a few

1:11:43instances where they commit to a raw or

1:11:46a hard number

1:11:47>> and that in that situation that would

1:11:50not change.

1:11:51>> Okay?

1:11:51>> Because it's just one's a percentage of

1:11:53what is built and then one's just a hard

1:11:55one.

1:11:56>> Okay?

1:11:58>> Um

1:11:59and then the bottom two. So

1:12:05um so there are 605

1:12:08um affordable units

1:12:13that basically the development plans

1:12:15have not um proceeded to site plan. So

1:12:19okay

1:12:21and then we have about 40

1:12:23>> meaning that that development just

1:12:24because the thing gets approved doesn't

1:12:26mean it's going to get built and so

1:12:27within that that 605 includes or there

1:12:31that includes 605 affordable units.

1:12:34>> Yes. So the 5,000

1:12:36units that are getting construction

1:12:38constructed what got approved is way

1:12:41higher essentially.

1:12:43I

1:12:43>> mean the the 5,000 is sort of the the

1:12:45the overall numbers. Okay. Of what's

1:12:47being constructed? These are

1:12:48specifically the units. The these are

1:12:50the

1:12:51>> Yeah. No, I got the overall I'm saying

1:12:52that like I guess maybe you have it.

1:12:54What

1:12:55>> what's the maybe I missed it. Uh what's

1:12:59the percentage of like success versus

1:13:02failure? So like to I'm not saying that

1:13:04but like something gets approved it

1:13:06doesn't get built right like what is

1:13:08that

1:13:10do you understand what I'm post shaking

1:13:12is that

1:13:18>> so to your first question yes um we

1:13:22don't have that metric because the

1:13:23zoning is in perpetuity and so for

1:13:27example there are units that are being

1:13:30built under PDRs that were approved

1:13:32moved a long time ago that or in that

1:13:355,000.

1:13:36>> It's hard to track essentially.

1:13:37>> We're not going to be able to get at

1:13:39that success because some of the 605 may

1:13:41be built

1:13:42>> down the road. Okay. Thank you. I

1:13:45appreciate that. Um could we also get

1:13:48analysis of if if possible from other

1:13:51planning departments across the state

1:13:52around voluntary profers around

1:13:54affordability and what they're seeing?

1:13:55Thank you.

1:13:56>> Sure.

1:14:00All right. And here is just a few sort

1:14:03of metrics regarding the AMI and tenure.

1:14:06Uh what we've seen is that um

1:14:10the most the most common AMI is 80%. Um

1:14:14depending upon the housing type, it

1:14:16could be defined as affordable or income

1:14:17restricted. Um the other is 60% which is

1:14:21pretty standard for the um

1:14:25correct the rental side. Um but we are

1:14:27seeing a a mix of AMIs. Um, and so that

1:14:32is what the orange or the purple uh

1:14:35refers to. And within the mixture of

1:14:37AMIs that are included in a development

1:14:39plan, that's where you actually see

1:14:42lower AMIs because um we tend not to get

1:14:46anything lower than 60 except for one or

1:14:48two times since then, but that's been

1:14:50paired with um like a higher higher AMI.

1:14:55Um and likewise we've seen AMIs higher

1:14:58than 80% but those have been paired with

1:15:00AMIs of 60 and 80 depending upon. So

1:15:03that's that's where the those different

1:15:05AMIs stay is in the in the mixed um

1:15:10>> and then because of our some of that was

1:15:12like 80% AMI is tied to for sale and 60%

1:15:15is tied to rental. So is that why we're

1:15:17also seeing that breakdown?

1:15:20>> It depends on how they they structure

1:15:22their profer basically. Um

1:15:26we are currently seeing that they are

1:15:28just committing to UDO affordable which

1:15:31assumes 80 and 60 and so that would sort

1:15:34of be a mix if there's a mix of housing

1:15:36types in this calculation.

1:15:40Um the other interesting thing is um the

1:15:44most common tenure of these affordable

1:15:45units is 30 years uh which is at least

1:15:48is a good thing. Um, we have seen a few

1:15:53developments that include a lower tenure

1:15:55that have been improved over the years.

1:15:57Uh, but nothing above a 30-year tenure

1:15:58has been approved yet. So, that may be a

1:16:00goal in the future. Um,

1:16:05awesome. I believe this is where Sarah

1:16:08steps in.

1:16:15>> Good morning. I'm Sarah Venius, director

1:16:17of housing and neighborhood services

1:16:18with the city. Um, and the housing and

1:16:22neighborhood services comes in after the

1:16:25units and projects are approved. So, on

1:16:27the monitoring side, so we're going to

1:16:29I'm just going to share very briefly

1:16:30what that process looks like. So, um,

1:16:34once the units are approved and built,

1:16:38um, annually, Housing and Neighborhood

1:16:40Services monitors 20% of the total

1:16:43portfolio of units approved. So um you

1:16:47heard the you saw in the earlier slide

1:16:49the total units. So right now that's

1:16:52four projects that were profered that

1:16:55have been built. Um that includes about

1:16:58300 units. Um, so we're currently

1:17:02monitoring a a very small number of

1:17:05units um that were profered that have

1:17:07been built and that's a very small

1:17:09portion of the 2500 total units that

1:17:13were responsible for monitoring because

1:17:15they have city money in them. So um the

1:17:18first units that we monitored came

1:17:21online in 2025. So this is a a new

1:17:24function for us and you saw that there's

1:17:27many projects that are under

1:17:28construction right now. Uh so we expect

1:17:30that there's going to be more and more

1:17:32um units that we'll be monitoring. Um so

1:17:36to say a little bit about what the

1:17:37process looks like um the process starts

1:17:40with our team sending out a letter to

1:17:42the owner to let them know that we're

1:17:44going to monitor them. Um we then um

1:17:47select a sample a random sample of units

1:17:50to look at and then um we our team looks

1:17:54at all of the documentation related to

1:17:57affordability. So, we're looking at rent

1:18:00roles. We're looking at documentation

1:18:02from the tenants to confirms that the

1:18:05leases were signed and and and correctly

1:18:08all of that documentation. And then we

1:18:10also do a physical inspection. So, one

1:18:12of our inspectors goes on site and looks

1:18:14at the condition of the units. Um once

1:18:17that's completed, we meet with the

1:18:21developer owner um and share with them

1:18:25the results of our monitoring and exit

1:18:27conference. Um if there are correction

1:18:30action, corrective actions identified, a

1:18:32plan is put in place and we give them a

1:18:34time period to address those issues. Um

1:18:37to date, we haven't had any uh

1:18:40corrective action plans needed for the

1:18:43projects that I mentioned. Um so that is

1:18:46good news. Um but we have a process in

1:18:48place if that is necessary. Um and we do

1:18:52that annually. So um this is an annual

1:18:55process. Next year we'll do it again for

1:18:58the four projects and any new projects

1:19:00that come online. And the trigger for

1:19:02that um as was mentioned earlier is when

1:19:0580% of the affordability requirements

1:19:08are met or the CO anniversary and

1:19:11whichever comes first. So, um, that's a

1:19:14little bit about the monitoring process

1:19:16and I'll turn it back over to planning

1:19:18staff.

1:19:19>> Second, uh, Director V, is this your

1:19:21only slide?

1:19:21>> Yes.

1:19:22>> Okay. Um, colleagues, just so that you

1:19:25don't have to sit down and stand up

1:19:27again, does folks have questions or

1:19:29comments? I

1:19:30>> I have a quick question. What happens

1:19:31when somebody is not in compliance?

1:19:34>> So, we would uh document that in a

1:19:37corrective action plan and give them a

1:19:39period of time to address the issues

1:19:41identified. So if there were physical

1:19:44issues with the building, they would be

1:19:46responsible for addressing those and

1:19:48then we would come back again or request

1:19:50documentation until those issues are

1:19:53addressed.

1:19:55We haven't had to do that yet. Um but we

1:19:59have had we have that process in place

1:20:01for the other units that we monitored

1:20:03and we have had to do correction

1:20:05corrective action plans and generally

1:20:07speaking um our partners are very

1:20:09responsive and address the issues. That

1:20:12would also technically be a zoning

1:20:14violation and so we would issue a notice

1:20:16of violation and pursue enforcement

1:20:18there too. And as you know through that

1:20:20mechanism um if they're are

1:20:22non-compliant after a we have to give

1:20:24them a grace period to come into

1:20:25compliance. If they don't do that fast

1:20:27enough, then we could issue citations of

1:20:30$500 a day for every day they stay

1:20:32non-compliant. So, we have two avenues,

1:20:33both um the housing and neighborhood

1:20:35services through their plan and us

1:20:37through our enforcement actions.

1:20:41>> Council member Copek.

1:20:43>> Yep.

1:20:44>> Thank you. Um so, Director Vignas, I'm

1:20:47curious. I know this is a new process

1:20:50for your department

1:20:52and hopefully under the new LDC we'll

1:20:56see a proliferation of more affordable

1:21:00units as the LDC seeks to give new types

1:21:04of incentives to byite development as

1:21:08well um to achieve you know some sort of

1:21:11density bonus by incorporating

1:21:13affordability but I imagine there'll be

1:21:15some sort of monitoring that as well so

1:21:17both um I I guess like what we would see

1:21:20through discretionary review and also

1:21:22what we might see under the new LDC.

1:21:25um

1:21:27you know will that also fall under your

1:21:29department and have you gotten feedback

1:21:32or sort of evaluated

1:21:35how how sort of difficult or ownorous

1:21:37the process might be just because I feel

1:21:39like we've heard in the past that the

1:21:41documentation and that followup both in

1:21:45Durham and across the country sometimes

1:21:46is a reason why developers don't

1:21:49participate and seek to get the benefit

1:21:51of the bonus or maybe it's just not

1:21:53structured well but but we hear feed

1:21:55back that that could be difficult for

1:21:56them. So, is that something you've

1:21:58heard? Are we evaluating? How do you

1:22:00think about that?

1:22:01>> Yeah, I think um that is certainly

1:22:03something that I have heard as well. Um

1:22:06and I think that's something that we

1:22:08will be collaborating with planning on

1:22:11to look at both through the LDC process

1:22:13but also through our housing plan is

1:22:15looking at, you know, what what new

1:22:18tools and strategies can we use? how can

1:22:20we improve the approach we've already

1:22:22been using um to streamline things. Um

1:22:26so I think I think there's a lot of

1:22:28pieces to that. I think part of it is

1:22:31education and support and capacity

1:22:33building for partners when they do have

1:22:36affordability commitments because it is

1:22:38a different line of business for market

1:22:40rate developers if they have not done it

1:22:42before and I think we need to support

1:22:44them and help them be successful. Um,

1:22:47but I think there's also structural

1:22:49issues and that's what part of what

1:22:51we're we're collaborating with planning

1:22:53on and also will be examined through our

1:22:54our housing plan.

1:23:00>> And um and you've you came from Chapel

1:23:03Hill Director Venius and Orange County

1:23:05has done a good job of moving these into

1:23:08um the portfolio of community partners

1:23:10such as the community home trust. um is

1:23:12that something that we're looking into

1:23:14as well through the um affordable

1:23:17housing strategic plan?

1:23:19>> Yes. And I will say that one of the four

1:23:21projects that has come online um we do

1:23:25have a model for that. So some of the

1:23:27units went to um Durham Community Land

1:23:29Trust who is a missiondriven affordable

1:23:32housing provider. Um so that is

1:23:35something that that we will be exploring

1:23:38um

1:23:40through our housing plan and we have

1:23:42done some of already.

1:23:43>> Awesome. Thank you. Questions? Yep.

1:23:46That's it. That's all. Thank you,

1:23:48director Venice.

1:23:55>> Awesome.

1:23:57And just to wrap it up, um so key

1:24:00points, um again, UGB has not been

1:24:03expanded. Infrastructure improvements

1:24:06have been made in two of the eight FDAs.

1:24:08Um the 15-minute community strategy may

1:24:10be impacted if place type trend

1:24:12continues. And then again, uh 2746

1:24:17profit affordable units are on file. So

1:24:21I'm happy to answer any questions you

1:24:22may have.

1:24:25Colleagues, I'm going to start on my

1:24:26right again, then go left, council

1:24:29member.

1:24:30>> Yeah, thank you, chair. Okay, so a play

1:24:32in three acts here. Um, this is the I'll

1:24:35do my best to work through this.

1:24:38So under first of all the just you know

1:24:41general growth management trends

1:24:43analysis you know just focusing a bit on

1:24:45this um you know small percentage but

1:24:50still notable shift from mixed use to

1:24:53mixed residential

1:24:55um you know and the possibility that

1:24:57that could impact ability for 15-minute

1:24:59city. Is there some sort of threshold

1:25:02that we think about in this where it

1:25:04becomes more meaningful where we should

1:25:07start being more concerned? Um how kind

1:25:11of consistent or inconsistent is you

1:25:13know 1.6% with what we've said we need

1:25:15and want over time. Yeah, I don't think

1:25:18there's a threshold right now, but I

1:25:20think maybe in the future um doing a

1:25:24geographical component or a GIS analysis

1:25:26of those place types to see if there are

1:25:29any existing gaps

1:25:31>> um for the uh 15-minute city would be

1:25:33useful. Um but as of just a general

1:25:37threshold of a certain percentage of

1:25:39acreage, I think you would need that

1:25:40geographical component to see how

1:25:42everything works together to make the

1:25:4415-minute city.

1:25:45>> Okay? because all the place types are

1:25:48working as one um to ensure that there's

1:25:51a 15-minute city.

1:25:53>> So,

1:25:53>> and we may see eb and flow over time to

1:25:57in one direction or or another.

1:25:59>> Correct.

1:26:00>> Um yeah. Okay. Thanks. Also interesting

1:26:02to see, you know, community employment,

1:26:04industrial, rural, these areas that were

1:26:06more or less flat, but really these two

1:26:09in areas interacting mixed use and mixed

1:26:11residential was was was notable. Um

1:26:15uh so second, you know, just to make

1:26:18sure I'm clear on language, you talked

1:26:19about losing 87 acres from a future

1:26:24growth area due to annexation.

1:26:25>> Correct.

1:26:26>> And so just when when um when a property

1:26:30is annexed, then it is then it is no

1:26:33longer in future growth.

1:26:36>> Not necessarily. It really depends on

1:26:38sort of the intensity of what's being

1:26:40proposed. So we've had two within the

1:26:42FGA. Uh one was a partial is the Virgil

1:26:46Road assemblage portion where the

1:26:49majority of it was outside the FGA but a

1:26:52portion of it was inside but a good

1:26:54chunk of it was inside the FGA and so

1:26:56that was the decision point to remove

1:26:58it. Um there was a second annexation

1:27:00which was a single family one just to

1:27:02connect two city utilities I think in

1:27:04the Fletcher Chapel FGA and because of

1:27:08its um non-impact basically

1:27:12>> um we decided to leave that. So that's

1:27:17okay.

1:27:18>> Okay.

1:27:19Um,

1:27:21let's see here

1:27:23in terms of so I see that the Celeste

1:27:26Circle Pump Station completed the

1:27:27upgrade. When it comes to Downing Creek,

1:27:30Downing Wood, and the Southwest FGA,

1:27:33you know, there was some language about

1:27:35where they are in the process. Has

1:27:36construction started on either of those?

1:27:39Um,

1:27:40>> I'm not sure if it's construction has

1:27:42started, but the CDs have been approved.

1:27:44>> Okay.

1:27:45>> So, it'll start soon hopefully.

1:27:47>> Okay. And who is doing that development?

1:27:50Who's paying for that development for

1:27:52that infrastructure?

1:27:53>> City.

1:27:54>> So those are city projects that are

1:27:55underway.

1:27:56>> I think the city has hired Carolina

1:27:58Civil Works to do the upgrade to one of

1:28:00them.

1:28:01>> Okay.

1:28:02>> Um

1:28:03>> so I know that there was like a request

1:28:05for that.

1:28:08>> Okay.

1:28:10Um

1:28:12and um which parts of the the kind of

1:28:17Southwest FGA does that cover? Will

1:28:19those three projects basically cover

1:28:21>> all of that or part of it?

1:28:24>> No, it'll well it depends on it's a

1:28:28tough question because there's two

1:28:29components of that actually FGA. one is

1:28:32a series of pump station improvements

1:28:34throughout that area for existing

1:28:36neighborhoods and the large substantial

1:28:38of that FGA is actually for um

1:28:41undeveloped land that would be developed

1:28:44in the future. Um so the the exact map

1:28:48of that we do not have but it may be

1:28:50based on the um there is a map that I

1:28:53found regarding sort of where those pump

1:28:55stations the the area of the pump

1:28:56stations would serve.

1:28:57>> Yeah, that'd be helpful to see.

1:28:59>> Okay.

1:28:59>> As a followup. Yeah. Thank you. I'll

1:29:01talk about that.

1:29:03>> Um, all right. So, next the comp plan

1:29:06consistency.

1:29:07>> Sure.

1:29:09>> So, this is a beautiful document

1:29:11>> made for great nighttime reading. So,

1:29:12thank you for this sort of, you know,

1:29:15compilation of of information

1:29:17>> insomnia.

1:29:18>> Uh, yeah. Um, I am curious. Is there an

1:29:21Excel document that sort of underpins

1:29:23the Word PDF table that would allow us

1:29:26to sort by applicability,

1:29:29by exceeds, meets, does not meet across

1:29:32the different policies or like what does

1:29:35the underlying data set look like?

1:29:37>> Um, it's a very big spreadsheet. Um,

1:29:42Erin seen it.

1:29:43>> Um, I love I love a big spreadsheet. So,

1:29:46if that's something you're also able to

1:29:47share, that would be that'd be great. So

1:29:50>> yeah, just just be aware that it's going

1:29:52to change every time

1:29:53>> Yeah.

1:29:54>> a case is approved. It's all going to

1:29:56change.

1:29:57>> Yeah. And the format of this current one

1:30:00will be changing to reflect the E

1:30:04changes.

1:30:05>> Okay.

1:30:06>> So the current one that I've built only

1:30:08reflects the 36 policies that have been

1:30:11normal um since the ER was approved. And

1:30:15so there's a number of policies removed

1:30:17but a few added. So I'll need to build

1:30:20that.

1:30:20>> Sure. And just understanding it's a

1:30:22snapshot that can change. But

1:30:23>> it's always it's dynamic

1:30:25>> generally a proponent of

1:30:28receiving the underlying data to make it

1:30:30easier for analysis not just from

1:30:32planning but kind of in in all areas is

1:30:34something I ask

1:30:34>> and that's what we've incorporated into

1:30:36our closeout procedure. So after city

1:30:39council, we will actually do a post

1:30:42approval analysis of a development plan

1:30:44because as you guys all know at council

1:30:48a number of profers are made and that

1:30:50sort of changes the initial count that

1:30:51you see on the staff report versus the

1:30:53final version.

1:30:55>> And so what you see here is a reflection

1:30:57of the final product of a development

1:30:58plan after you guys

1:31:01approve or deny.

1:31:02>> Okay, great. Um, all right. So, there's

1:31:05a lot that's encouraging looking at how

1:31:07we've done so far with comp plan

1:31:09consistency, you know, discouraging

1:31:11housing segregation by income and

1:31:12housing type 100%, sidewalks,

1:31:14transportation, investment, access to

1:31:16transportation 100%. So, this is in and

1:31:19many others that were very high. Um, a

1:31:21couple questions on those one around

1:31:23policy 119, established service area

1:31:26within the UGB

1:31:28um, at 100%. Um, you know, how do we I

1:31:32mean, I know

1:31:35Do we have an explicit definition that's

1:31:37in the complaint of how we define

1:31:40um meeting established service? because

1:31:42that's something we sometimes hear

1:31:43including like on Monday we'll hear that

1:31:46you know a belief that a proposal does

1:31:48not align with policy 119 but you know

1:31:52the staff recommendation is saying or

1:31:54staff analysis is saying that it is in

1:31:56line with

1:31:57>> I guess there's um a distinction between

1:32:00sort of what the policy is intended and

1:32:01what staff can actually look at

1:32:04>> um right now the FIA is what we use to

1:32:08determine that policy in in terms of its

1:32:11consistency. Um I think there may be

1:32:15things that we could do in the future um

1:32:17to make it more aligned with policy but

1:32:19that is the mechanism that we have right

1:32:21now just to

1:32:25>> try to use that policy as best we can.

1:32:27>> Uhhuh. And FIA is

1:32:28>> the fiscal impact analysis. the

1:32:31attachment H, correct? Um the attachment

1:32:33H and sort of the the huge section in

1:32:36the memo that details sort of the cost

1:32:38and expenditures or the expenditures and

1:32:41um revenues that are expected at the

1:32:43annexation. So that's where that sort of

1:32:45lives.

1:32:46>> Yeah. And for county commission

1:32:46colleagues, one thing that comes up is a

1:32:48question around EMS service and how that

1:32:50factors in we think about total uh

1:32:52impact. Of course, we also don't see

1:32:53county revenues in our documents, but we

1:32:57are now seeing EMS costs outside of the

1:33:00FIA, but it's something that we can

1:33:01compare and think about and be in

1:33:03conversation about since I know that's a

1:33:05keen area of concern and interest. Um

1:33:09um you know, we're 100% sewer costs

1:33:11borne by developers. Does that factor

1:33:14into the FAA as well when we're getting

1:33:18like infrastructure built by

1:33:22by developers

1:33:23>> sort of the one of the policies deals

1:33:26directly with um sort of the

1:33:29infrastructure requirements that's it's

1:33:32one of the later ones

1:33:36I think it's one

1:33:40uh 128 that's sort of where that deals

1:33:43with that.

1:33:43>> Yeah.

1:33:44>> Um again when you annex into the city um

1:33:48applicants have got to sign a utility

1:33:50extension agreement which sets the

1:33:51framework or expectations of how those

1:33:54utilities will be built by the applicant

1:33:56and then maintained eventually by the

1:33:58city.

1:33:59>> Okay.

1:34:00>> So um that's sort of where it's taken

1:34:01care of.

1:34:02>> Okay. All right. Yeah. because I think

1:34:03often whether it's you know like

1:34:06utilities you know sidewalks like you

1:34:08know there are instances where there are

1:34:10cases that come before us where we're

1:34:12able to get those sorts of public

1:34:14benefits

1:34:15>> sure

1:34:15>> that otherwise would not happen or would

1:34:17be a cost to to the city. Uh and so just

1:34:21always curious how that fits into how we

1:34:22think about a fiscal you know the fiscal

1:34:25impact of it. So you

1:34:28>> um all right so there's you know there's

1:34:30a number of them that are low which

1:34:31we've already talked on some of those in

1:34:33previous discussion you know there is

1:34:34the topic of public open space um that's

1:34:37something that I've reached out to the

1:34:38CEO to the attorney's office about to

1:34:41look into so I appreciate attorney Miles

1:34:43and team sort of looking into when we

1:34:45hear from HOAs that it's just too big of

1:34:49a liability we can't do it um you know

1:34:51like how how solid is the ground you

1:34:54know on which those claims are based.

1:34:56And so I look forward to hearing in the

1:34:58future, you know, kind of the assessment

1:35:00of like how we should interpret those

1:35:01those claims because I think it was only

1:35:03at 18%

1:35:05um um alignment with a comp plan around

1:35:08publicly available open space and

1:35:10developments that were approved. Um

1:35:12okay, so third act, last question and

1:35:14I'll hand it off. Thank you my

1:35:15colleagues for your patience as I work

1:35:17through all of this. Um

1:35:18>> so we have the 2746

1:35:21um affordable units profered. you know,

1:35:24some that are moving forward, some are

1:35:26sort of in the future. I'm curious from

1:35:28you. I don't know if Director Vignas is

1:35:29still here, but if we have a record of

1:35:33in the same time period, how many

1:35:36publicly subsidized affordable housing

1:35:38units did the city and county build or

1:35:40start the process of building over that

1:35:42same time period? And I realize you may

1:35:44not have that answer. Um, yeah, I don't

1:35:46have that completed. I can reach out to

1:35:48housing neighborhood services after I'd

1:35:50be interested to

1:35:52>> you know to see you know how many units

1:35:54are we getting from this discretionary

1:35:56review process you know how many over

1:35:58the same time period has you know our

1:36:00public bodies you know been successful

1:36:02at you know sort of initiating on our

1:36:04own um so um I will pause there and

1:36:09thank you for this presentation and you

1:36:10and your team for all this work uh

1:36:12really appreciate it so thank you

1:36:14>> well Matt I can tell you right now what

1:36:16it's been on the county side minus the

1:36:19projects that we've done jointly with

1:36:21the city through the ARPA funding where

1:36:23we've partnered with the city but the

1:36:25ones that we've built has been 300

1:36:28um with our two projects not will be

1:36:31complete 2027

1:36:33but during that time period 300 units

1:36:36>> which is also the county stepping in new

1:36:38territory uh and building affordable

1:36:40housing which is really amazing but so

1:36:43300 is

1:36:44>> 300 it's going to take us 10 years.

1:36:4810 years to build 300 units.

1:36:52>> Um, Director Young, you're good. All

1:36:54right. Uh, Mr. Burton, did you have

1:36:57anything?

1:36:57>> No. Okay, let's go to my left.

1:37:00Go ahead.

1:37:02Um, thank you for this. This is actually

1:37:05really, really good information. And I

1:37:06heard um um

1:37:10council member uh Copac ask about like

1:37:16reporting, you know, he was asking how

1:37:18can he get a spreadsheet about this so

1:37:20forth. Um I was just curious. So how

1:37:23often

1:37:25will we get this kind of summary?

1:37:29Um

1:37:29>> so a great question. Um,

1:37:31>> right. And so I'm kind of going

1:37:33somewhere with that. It probably get

1:37:35answered with the second part of that.

1:37:37>> Okay.

1:37:37>> So, you know, we get a lot of mainly the

1:37:41city council gets a lot of questions

1:37:42about this sort of thing, right? These

1:37:45numbers. Um, is it feasible to have like

1:37:50a dashboard

1:37:52that shows this? I don't know how

1:37:54difficult it would be to update. I don't

1:37:55know how automatic

1:37:58numbers are as as units come online or

1:38:02or whatnot, but would it be feasible to

1:38:04have some sort of dashboard that the

1:38:06community could look at

1:38:09um that shows these kind of numbers

1:38:11because this is this answers a lot of

1:38:13questions that people have about

1:38:16building and about that sort of thing.

1:38:18I'm curious.

1:38:20I don't know how, again, I don't know

1:38:22how difficult it would be to maintain,

1:38:24but I was just curious about that.

1:38:27>> Yeah, that's a great question. We

1:38:28actually have a link on our website um

1:38:30that is kind of a light dashboard that

1:38:32we built years ago. Um it needs to be

1:38:36kind of updated, expanded, revamped.

1:38:38That's on our kind of wishto-do list

1:38:40when we have a little free time. So, um

1:38:42some of this, like for instance, the

1:38:45number of units built is online. So

1:38:48there there is some information, but we

1:38:49do want to take a bigger holistic

1:38:51revamp. I do think that there's some

1:38:53other information that was in this

1:38:54presentation that isn't on that

1:38:55dashboard. I think would be good. And we

1:38:57hear a lot from, you know, residents, I

1:38:59think, that are um

1:39:02quoting numbers about like the total

1:39:04amount of units, you know, that that um

1:39:06we have approved and how we do or don't

1:39:09need to, you know, be uh approving

1:39:11anymore. I think there's some double

1:39:13counting there going on. So I I would

1:39:16like for us to have that information as

1:39:18kind of the credible source of that data

1:39:21online. So that's something we're going

1:39:22to be working on.

1:39:23>> So that was just a question.

1:39:26>> Sure.

1:39:26>> If it was if that's feasible. And the

1:39:29reason I say feasible is because I've

1:39:31been on the other end of having to

1:39:32update a manual dashboard before and I

1:39:36know the pain of that. So I'm not

1:39:38suggesting that. I'm just curious if we

1:39:41could if this information could be be

1:39:43available in public cuz I would never

1:39:45ask the staff to do something I wouldn't

1:39:47want to do and I I wouldn't want to do

1:39:49that.

1:39:50>> Yeah, I I will tell you that our life

1:39:52will become a lot easier when the new

1:39:54clarity system um we will be able to

1:39:56build dashboards directly from that. So

1:39:59right now some information is ported

1:40:03from LDO through a system called data

1:40:05hub that the city has and there is still

1:40:08some manual entry but the dashboard

1:40:10online reads from that system. So it's

1:40:12kind of a hybrid right now. So we'll

1:40:14look and see what we can do with a

1:40:16reasonable amount of effort.

1:40:18>> Yeah.

1:40:18>> Thank you.

1:40:18>> And we have provided clarity with the um

1:40:22>> sort of the framework of the t the

1:40:24affordable tracker the stages of

1:40:26production tracker. So the the platform

1:40:29is aware of sort of the data that we

1:40:30currently use

1:40:32>> and ideally they'd be building that into

1:40:34it.

1:40:34>> I I I could wait for that.

1:40:36>> Yeah. Yeah.

1:40:38>> Thank you.

1:40:40>> Uh Mayor Prom,

1:40:43>> thank you. This is I'm in the tables and

1:40:45all the very dense information. Um

1:40:47>> Sure.

1:40:48uh with the like we updated the park one

1:40:53um to be a little bit more realistic

1:40:56based on our development patterns and so

1:40:58curious about because I think originally

1:41:00it was like the 15-minute city goal

1:41:03being like oh you can walk to a park

1:41:04within 15 minutes and then parks and

1:41:06wreck was like yeah that's not an

1:41:07achievable goal based on our own plans

1:41:09and so we kind of tiered it. um with

1:41:12that policy breakdown comparison. I

1:41:15guess it it I'm not seeing it. Is it

1:41:17>> it's not included in this one.

1:41:19>> Okay.

1:41:19>> So

1:41:21for the policies post E,

1:41:24>> they'll have a a breakdown of

1:41:26>> it didn't get incorporated until the

1:41:28Even though we talked about it sooner,

1:41:29it didn't get incorporated. Okay. Thank

1:41:30you. Because I know we talked about it

1:41:32kind of before the rest of the other

1:41:33policy changes. Okay. That that was one

1:41:35question. So I appreciate that. Sure.

1:41:37And then um I think what would be

1:41:39helpful so some of these where it says

1:41:41policy not met etc. It would be it would

1:41:44be helpful to have an understanding of

1:41:46the scale of the project um because I

1:41:50think a smaller project not meeting a

1:41:52goal to me is is different than a large

1:41:55project not meeting the goal. So I think

1:41:57that would be helpful to have that sense

1:41:59of it. Um, we talked about that earlier

1:42:01with just the green building standards

1:42:03that some folks aren't meeting them

1:42:05because their project is small and they

1:42:07can't really afford it. And that's going

1:42:08to be applicable to a lot of these

1:42:10policies. And so, again, I I want us to

1:42:13be real honest about if if we're going

1:42:15to really create a a local ecosystem of

1:42:18local builders. There's trade-offs

1:42:19there, right? Which is those folks

1:42:21aren't going to come in the door with

1:42:22the same kind of money. Um, so that's

1:42:25one. Um,

1:42:26>> I think that could be done. I could it

1:42:28could be categorized because we already

1:42:30denote sort of the scale of a

1:42:33development plan in the metrics. So

1:42:36establishing sort of a category of big

1:42:39or small.

1:42:39>> Yeah. Like 50 units or 70 whatever that

1:42:42threshold is. And and I I think folks

1:42:44have y'all have a better understanding

1:42:45of where really that breakdown is um of

1:42:48of I may be talking to to to more folks

1:42:51out there of like where is that

1:42:52breakdown for even for us to have an

1:42:54understanding on council of like this is

1:42:5630 units like we may want all these

1:42:58policies met but or this is 50 units.

1:43:01It's just not achievable and you just

1:43:03have to make the decision on like do we

1:43:04want the housing or not. Um so that's

1:43:06one

1:43:07>> I'm going to tack on on one little

1:43:09thought there because I I agree with

1:43:10that. Um, and maybe it's not a project

1:43:13by project breakdown or a reszoning by

1:43:16reasoning breakdown, but like a acreage

1:43:18breakdown. I don't know if that's

1:43:20feasible through your spreadsheet, but

1:43:22>> No, we track acorage with each

1:43:23development plan.

1:43:24>> Just a thought there.

1:43:25>> Okay.

1:43:26>> Thank you. Um Um,

1:43:29that was one question. And then the

1:43:31other piece that I think would be

1:43:32interested interesting and you said it

1:43:34to geography. So

1:43:36>> some of this like we've maybe losing

1:43:37mixed residential. I I would love to see

1:43:40where we're losing it because

1:43:44a lot of our annexations and things are

1:43:45on a certain side of town and Brier

1:43:47Creek is going to be a commercial suck

1:43:49for that entire area. So folks coming to

1:43:52me and saying it's really hard to put

1:43:54smallcale commercial because there's so

1:43:56much other commercial.

1:43:58I understand that argument. Do I like

1:44:00it? No. But I understand it versus like

1:44:03nh actually on this side of town you

1:44:05should have put a commercial and that

1:44:06was a miss on our part. Um, so that's

1:44:08the other piece I kind of want to have

1:44:10an understanding around.

1:44:14>> Commissioner,

1:44:17>> this is fantastic. Um, I'm wondering how

1:44:21often will we get these reports? I mean,

1:44:23maybe I guess we already asked this, but

1:44:26just is this part of the five-year

1:44:29review process that we're supposed to

1:44:31have just that is baked in? Is this what

1:44:35we're getting from that? So, we were

1:44:37doing this as part of kind of in to

1:44:40coincide with the two-year E cycle.

1:44:42>> Okay.

1:44:43>> Um, so I I think that's what we had

1:44:45thought we would do is do this every two

1:44:48years.

1:44:49>> Okay.

1:44:51Really helpful. Um, first of all, I just

1:44:53want to say big picture

1:44:56>> that this data shows that what we're

1:45:01trying to do is being done. And I just

1:45:03want to say kudos to the city council

1:45:06because when you look at what is

1:45:09happening in terms of land use

1:45:12and urban growth boundary uh meeting

1:45:16policies

1:45:17creating affordable housing we are

1:45:21basically in generally meeting the

1:45:23goals. So this is what this data shows.

1:45:28Um, and I what one of my requests is I

1:45:32would like this document to be

1:45:35summarized into a one pager that is a

1:45:38report to the community. This can't just

1:45:41be sitting here in this meeting with all

1:45:43of us. This needs to be and to your

1:45:46point, Chair Lee, um, this has to be

1:45:49able to be shared out in a comprehensive

1:45:53in a very easy to understand way with

1:45:56our community.

1:45:59how what is happening is executing the

1:46:02goals of the comprehensive land use plan

1:46:05even without having pass the LDC and

1:46:09once we pass that LDC we will be even

1:46:12more successful. So, um could we get

1:46:15something again just a one pager hits on

1:46:19this the highlights

1:46:22um that could be our you know whether

1:46:25the planning department puts it out with

1:46:27the city and county PIO

1:46:31and also you mentioned

1:46:34um that you staff does a kind of debrief

1:46:38after every single um you know resoning

1:46:41case or you you know, decision that's

1:46:44made. Um, you know, I'm just thinking

1:46:47like Go Triangle does this thing where

1:46:50they put out a report after every, you

1:46:53know, meeting kind of what what happened

1:46:55in the meeting. Um,

1:46:58I'm just wondering what what people

1:47:00don't understand is what you just talked

1:47:04about in that comment you said looking

1:47:06at how did the case change from when it

1:47:09originally came in to the planning

1:47:12department then went through the

1:47:13planning commission then went to the

1:47:16city council.

1:47:18What are the changes that happened

1:47:20through that process and what did we end

1:47:22up with? because again what the

1:47:24community sees as oh the planning

1:47:26commission voted against that and the

1:47:29city council approved it and that's a

1:47:33simplistic

1:47:35uh you know kind of understanding of the

1:47:38process that doesn't reflect the

1:47:41complexity of what the process is meant

1:47:44to be which is you know that the

1:47:47planning commission does their very

1:47:50expert detailed analysis

1:47:53you know they may vote against it

1:47:54because they are putting out all the

1:47:56things that need to change and then when

1:47:59it gets to the you know governing body

1:48:02changes are made. So, is there a way if

1:48:06you could do some type of um you know

1:48:09reporting out where you also are able to

1:48:14show

1:48:16how the what was finally agreed on were

1:48:20approved and how that project changed. I

1:48:23don't know if I'm making any sense.

1:48:25>> Yeah, you make perfect sense but I think

1:48:26Aaron

1:48:28>> thanks Eron came with the planning

1:48:30department. Um so we have started

1:48:32collecting that data that information

1:48:35and has really spent the last year

1:48:37setting up um all the data

1:48:42compilation all the infrastructure that

1:48:44we need to be able to do this in a much

1:48:46more uh much more quickly um in the

1:48:52future. Uh, and I thank Andy. And the

1:48:54reason I'm up here is that um, today is

1:48:57Andy's last day, so he won't be doing

1:49:00any of that.

1:49:00>> Oh, no.

1:49:01>> Um. [laughter]

1:49:03>> Oh, no.

1:49:05>> Right.

1:49:08[laughter]

1:49:10>> You want to Yeah.

1:49:14>> What?

1:49:14>> I'm supposed to walk away silently.

1:49:17Um, no. I'm working closer to home. Um,

1:49:20I'm helping I'll be helping Burlington

1:49:22with their long range efforts. So, it's

1:49:24a 20 minute drive versus an hour and 10.

1:49:27>> Darn.

1:49:29>> Um,

1:49:30>> you're leaning into that 15inut city.

1:49:32[laughter]

1:49:33>> Sir, do you know anybody in a bad word?

1:49:38>> So, so we the rest of us who remain uh

1:49:42we'll do our best to get these to you in

1:49:44as timely a manner as as we can. Um, but

1:49:48yeah, I really applaud Andy for putting

1:49:50together the I mean, you want to see

1:49:53some spreadsheets, we've got some

1:49:54spreadsheets for you. Um, but yeah,

1:49:57that's all been put together now. So,

1:49:58it's something that, uh, the rest of us

1:50:00are going to be able to continue. Um,

1:50:03but yeah, if you'll bear with us in a

1:50:06little bit, uh, as we're short staffed,

1:50:08uh, putting that together to move

1:50:09forward.

1:50:10>> We hear that. I think in the very least

1:50:12though we could still do the kind of

1:50:15summation of this report that we're

1:50:17getting.

1:50:17>> Yeah.

1:50:18>> Yeah. Yeah. Okay. Yeah. Sarah, by the

1:50:20way, you'll be working on that,

1:50:22>> right? Um I just want to also just to

1:50:24highlight a few things that I think is

1:50:26important for the report. Number one is

1:50:29there's been no net change in the uh

1:50:32loss of rural land. I think that is

1:50:34really really important holding the fact

1:50:37that we've held the urban growth

1:50:39boundary that we have not lost any rural

1:50:42land. You know we had a recent update of

1:50:46our farmland plan and report that shows

1:50:49that we have lost a lot of farmland and

1:50:54in Durham County over the past you know

1:50:5630 years and or 20 years since the where

1:51:00it was last done. So this is very very

1:51:03important that we hold the line on

1:51:06protecting our rural land and the urban

1:51:08grass boundary and we're doing that and

1:51:09I think that's really important. Um also

1:51:14increasing the residential and

1:51:16specifically mixed types of residential

1:51:19cuz you you said we're we're I just I

1:51:22don't know if you realize you said that

1:51:24the issue with us losing mixed

1:51:26residential it's mixed use, right?

1:51:29because we've actually improved on the

1:51:31mixed residential which is good housing

1:51:34different housing types different price

1:51:36points but um so I think that that's

1:51:40also really really important um and that

1:51:43we haven't

1:51:45um we've held also the line on the

1:51:47future growth areas and even doing that

1:51:51there was an increase in I believe it

1:51:53was 1,00 over 1,800 increas increase

1:51:59development within the urban growth

1:52:01boundary. So one one of my questions is

1:52:04and maybe that we already have this is

1:52:07how much land is developable or

1:52:11redevelopable based on I know if we had

1:52:15the LDC it would be more but if we don't

1:52:19go into the future growth areas we hold

1:52:21the urban growth boundary

1:52:24what how much land is available for

1:52:28meeting our goals I'm just do we have

1:52:30that kind of information.

1:52:34>> Here's Bill with the assist.

1:52:39>> I'll say as a part of the LDC project,

1:52:42we have attempted at trying to find that

1:52:46number um like area acreage. incredibly

1:52:50difficult and um I don't want to say

1:52:53there's no value in that because there

1:52:54certainly is right like how much you

1:52:56know undeveloped land is there but who

1:52:58wants to sell what existing development

1:53:01is redevelopable right like you know we

1:53:04don't know the necessarily the occupancy

1:53:06of a particular shopping center so

1:53:08there's so many factors but we are

1:53:09trying to come up with that and um if

1:53:13we're able to uh determine some some

1:53:16concrete numbers it'll be a part of the

1:53:17LDC considerations Okay, cuz I say that

1:53:20and again coming back from Grand Rapids,

1:53:23you know, we ideally we really would

1:53:25rather see redevelopment of old shopping

1:53:29centers and, you know, parking lots, um,

1:53:32more density development in our our our

1:53:36transit areas, more transit oriented

1:53:39development, you know, we want to see

1:53:41that rather than moving outward period.

1:53:44um we want to see development where we

1:53:47have existing infrastructure where

1:53:49delivery of services is going to be less

1:53:52expensive you know all of that so that

1:53:54that that's why I asked that um um and

1:53:58then

1:54:00I would do we knowing that we basically

1:54:04have in this time period already 314

1:54:08affordable units built another 788

1:54:12under construction that's over that's

1:54:15like,00 units. What is the average cost

1:54:18of building

1:54:20uh a housing unit? Do we know that right

1:54:25now? Anybody?

1:54:27>> What would be a fair number? What would

1:54:29be a conservative number? Cuz I did this

1:54:31last night, but not a calculator.

1:54:34Um I I'm

1:54:37>> so so I think I mean even if we could

1:54:40get that information which would be

1:54:41privately held and and is not

1:54:43necessarily being shared with us I think

1:54:45there would be such a huge delta between

1:54:49certain types of units and other types

1:54:51of units that I don't know that an

1:54:53average would really be

1:54:56yeah useful because you'd have such a

1:54:58you'd have such a standard deviation

1:55:01>> um between and such a such a broad range

1:55:06of costs and that they are so dependent

1:55:08on materials on land on the just yeah I

1:55:14don't know that a there's an average

1:55:16cost would be of

1:55:17>> a one-bedroom apartment versus a

1:55:20three-bedroom single family those are

1:55:21going to be very different even per

1:55:23square foot cost.

1:55:25>> Yeah.

1:55:25>> So and and I think that it may be

1:55:27misleading to average all that together.

1:55:29So I took a very low number 250,000

1:55:33right and multiplied it by 1,100 and I

1:55:37you know that's very low right today

1:55:40that's two over $275 million okay and I

1:55:45just I just put that out there to say

1:55:47that what we're getting which we can't

1:55:51afford to do um you know and it's going

1:55:55to be more than that the value of of how

1:55:59much money is we are basically saving uh

1:56:04the public sector from having to try to

1:56:06meet this need. And I I just again this

1:56:09is a really really key point. The county

1:56:12we're it's going to take us 10 years to

1:56:15build 300 units and it that has been

1:56:18done with heavy public subsidies. I I

1:56:22cannot tell you how much public money

1:56:25has had to I mean I can go back and

1:56:27look. We've had to build two parking

1:56:30decks to subsidize. We've had to provide

1:56:33uh you know basically grants. Uh there

1:56:36are many many different forms of public

1:56:38subsidy that we are putting into the 300

1:56:42units. If we break it down per unit, I

1:56:44think I saw at one point

1:56:47um it it's it's a lot of money and it's

1:56:50we don't have the ability to to build

1:56:54all these we don't have the ability to

1:56:56build,00 affordable units and so I just

1:56:59I just we have to be able to explain

1:57:02this to um the community and to what

1:57:06public benefit this is is happening by

1:57:10the profers that are being made. So I

1:57:13just I just wanted to highlight that. Um

1:57:16last thing is though I do want to raise

1:57:19I am concerned about

1:57:22the current criteria around evaluating

1:57:26the future growth areas because if we

1:57:29are just looking at

1:57:32um city water and sewer I we're I think

1:57:35that we are leaving out other important

1:57:38considerations about that and I just

1:57:40want to raise that as a future topic for

1:57:43discussion because We know for instance

1:57:46EMS and fire and

1:57:50>> fire is included in that.

1:57:52>> So EMS

1:57:53>> it's EMS which is not city function

1:57:55which is why we haven't historically

1:57:56included it. Yeah, we've got to get EMS

1:57:59included in this evaluation of future

1:58:02growth areas as we are with now with

1:58:05resonings because we are we are at a

1:58:08real crisis level with uh county EMS and

1:58:11response time and it's so expensive.

1:58:14Last night, Carolina Arbors gave us

1:58:16$55,000 which is amazing. You put that

1:58:20together with that first profer we've

1:58:22gotten the 350,000

1:58:25you that together buys us an ambulance

1:58:28and that's huge right but that's one

1:58:30ambulance that doesn't include the staff

1:58:33the personnel which is an ongoing cost

1:58:36um so I don't want to poo poo that

1:58:39that's f that is important and huge and

1:58:42we need more of that but I just want to

1:58:45know I really want to be able to follow

1:58:48up on the issue about EMS and how that

1:58:51could be also included in the evaluation

1:58:54of um the future growth areas.

1:58:57>> Can I

1:58:59very quickly

1:59:02>> you

1:59:02>> I'm done.

1:59:04>> Thank you. I think that that I think

1:59:06that that's actually something that

1:59:07needs to come up at Joint City County

1:59:09versus JCCPC. Uh quite frankly, because

1:59:12that's where we're having some of these

1:59:13harder conversations. I will say we

1:59:15merged fire. You know, when I was first

1:59:17on council, there was and it might be

1:59:19time to really think about this keeps

1:59:21coming up as resources get harder. Where

1:59:23where does it make sense to merge

1:59:25certain departments? Um, we we put EMS

1:59:27in our fire houses already. Like what

1:59:30how are we doing that? And is it how are

1:59:32we going to deliver a thing more

1:59:34quickly? I know that there's been a a

1:59:36long backlog of ordering ambulances and

1:59:39that whole process that goes back to the

1:59:40pandemic. And I'll say all of our

1:59:42firefighters or almost all of them are

1:59:43EMS certified. But we have some things

1:59:45that we need to think about and that's

1:59:46really um the conversation needs to be

1:59:49happening at joint city county. Um and

1:59:51>> who's the chair of that?

1:59:52>> Joint city county. It's chair it's chair

1:59:55Dr. Lee and then the mayor. So I'm

1:59:57flagging that because I know there's

1:59:58staff in here that kind of sit in both

2:00:00spaces um to to help us remember to have

2:00:03that conversation there. And then just

2:00:04very quickly, this kind of highlevel

2:00:07summary um is there a way to maybe add

2:00:10it to our packets at resoning.

2:00:17Can you say more? What high level what

2:00:19specific mean?

2:00:21>> Yeah, just like

2:00:25>> I think that or we've talked about a

2:00:28dashboard or whatnot. I think that there

2:00:29needs to be I I've been very clear that

2:00:32the comp plan is our northstar and there

2:00:35are some things that we need to discuss.

2:00:37The last one, where is it? The third,

2:00:38the 15 minute, the the community type.

2:00:40There's we've got to manage that. But

2:00:42basically, what I'm seeing is that we

2:00:43are honoring the thing we said we were

2:00:45going to honor and we are doing it to

2:00:47the best of our ability and that needs

2:00:49to be report out to community or

2:00:51whatever. But where where folks are

2:00:53seeing where are they showing up the

2:00:54most? They're showing up at our

2:00:55resonings every other Monday. And so I

2:00:58would like a consistent reminder of this

2:01:01is the plan the community approved. This

2:01:03is the thing that both the county

2:01:04commission and city council approved and

2:01:06we are following it. Um, do there needs

2:01:10to be some adjustments? Yes. And we're

2:01:12also doing the thing that we said which

2:01:13is planning staff is doing incredible

2:01:16analysis and work to make sure that we

2:01:19are adhering to a plan. And folks can

2:01:22sit there with their misinformation, but

2:01:24they need to be reminded that it is

2:01:25misinformation. And I think that we need

2:01:28to be a little bit more forthright

2:01:29because that's not what's being shared

2:01:33and we are creating a vacuum of

2:01:35misinformation at our uh Monday night

2:01:39meetings and it's our job as an

2:01:41institution to you can choose to believe

2:01:43it or not but don't say you didn't have

2:01:47the information.

2:01:52>> Yes. Thank you chair. Um, so definitely

2:01:55support Joint City County taking up the

2:01:59merger discussion, which I think over

2:02:01time it'd be good to look at other

2:02:03departments as well. I know it's

2:02:04something that Commissioner Jacobs has

2:02:06talked about and just looking for those

2:02:08efficiencies to find ways that we can

2:02:10operate with greater effectiveness and

2:02:12also reduce cost over time in the short

2:02:16term. Uh, I want first of all want to

2:02:18thank the staff for including EMS in the

2:02:22memo. Um, I'm wondering if it's possible

2:02:25and not too much of an effort to have in

2:02:29the the FIA,

2:02:31you know, after doing what is applicable

2:02:33to the city having a different line

2:02:35there that includes uh EMS as a cost

2:02:39just because I think that's where we go

2:02:41and look to eyeball the summary of of

2:02:43what the impact will be and this seems

2:02:45to be the main missing piece.

2:02:47And then second of all, um, you know, do

2:02:51we have access to how do we think about

2:02:53the revenue side from the county,

2:02:56uh, for these sorts of projects, too, so

2:02:59we're getting a fuller picture of the

2:03:01expense and revenue side of projects

2:03:03coming before us.

2:03:06I'm not asking for a real-time

2:03:08dashboard.

2:03:08>> Yeah. So that the FIA document itself,

2:03:12Andy Curtain, if I'm wrong, that is

2:03:13actually produced by budget management

2:03:15services, right?

2:03:16>> Correct. Planning to shepherds their

2:03:18process.

2:03:19>> So we would have to talk to them,

2:03:21>> JJ.

2:03:21>> Um, and just kind of see what they think

2:03:25about that. Um, we we can certainly have

2:03:29a conversation with our county

2:03:30colleagues about

2:03:32uh kind of a a county

2:03:36FIA,

2:03:37if you will. Um I think that may be

2:03:42there may be some additional

2:03:44complications there. Like for instance

2:03:46um

2:03:48in cases where uh there's an annexation

2:03:52but there's not a zoning change. There's

2:03:54really not going to be a change for

2:03:57county costs because those sites are

2:03:59already in the county. They already have

2:04:00to provide social services and this and

2:04:02that regardless, right? And so like for

2:04:04for example, EMS is one where if the

2:04:07zoning is not changing, then there is no

2:04:11um EMS says there's no addition there's

2:04:14no additional impact. They're already

2:04:15serving that land the way it's zoned. Um

2:04:19so I think that those are like nuances

2:04:20we would have to work through, but we

2:04:23can certainly have that conversation

2:04:24with county budget staff and and see

2:04:27what they think.

2:04:27>> Is this something you would initiate or

2:04:29should I initiate?

2:04:30>> We can initiate that.

2:04:31>> Okay. And can we include I know you do

2:04:33schools but kind of having it more

2:04:35formal because the schools are that's

2:04:38our costs that's a county expense.

2:04:42Um and then my last question is um

2:04:48so the FGA

2:04:50included in the comp plan the future

2:04:52growth areas

2:04:56are do those reflect our understanding

2:04:58of what's possible for buildout under

2:05:00the current UDO or does it include also

2:05:04what is possible under the LDC

2:05:08and if it doesn't include clude what's

2:05:11possible in the LDC. Is there a time

2:05:14when we should have another look at the

2:05:16future growth areas and what we're

2:05:17investing there if we think the LDC

2:05:20which envisions you know the next

2:05:22increment of density all throughout the

2:05:24city where we have existing

2:05:26infrastructure you know would be a more

2:05:29you know sort of uh you know efficient

2:05:31you know way to invest in housing versus

2:05:33this growth out. How should we think

2:05:34about that?

2:05:38>> Scott is coming to address that.

2:05:40Morning.

2:05:41I'm Scott Whiteman with the planning

2:05:43department. So the the place time map in

2:05:45the future growth areas assumes what it

2:05:48would be built out as if you know all

2:05:50the infrastructure were in place. But

2:05:52our um strategy with the LDC before it

2:05:55was paused was for the areas designated

2:05:57for residential outside the city which

2:05:59would include most of the future growth

2:06:01areas uh would be have a lower density

2:06:04kind of transitional zoning the RB

2:06:06zoning so that it couldn't be built out

2:06:09at what the comprehensive plan um

2:06:13envisions until it's annexed and we can

2:06:16ensure that we have enough services to

2:06:18to to provide

2:06:31process.

2:06:37>> Yeah, go ahead. um concerning the 2746

2:06:41profer affordable housing units when

2:06:44they come in front of us and they have a

2:06:46reasonzoning and then they say they're

2:06:47going to do that many affordable units

2:06:50and then it's reszoned um I've seen a

2:06:53number of these parcels maybe not I know

2:06:56one specifically it was just put back up

2:06:58for sale with another because I guess

2:07:01the assumed value of that land is now

2:07:04increased since it's been reszoneed if

2:07:07somebody else buys that land, are they

2:07:10obligated to meet that previously

2:07:14profered affordable housing or can they

2:07:16just have a different plan and not do

2:07:19it?

2:07:20>> So, the affordable units that are

2:07:21profered through a development plan is

2:07:24essentially um a specific zoning

2:07:26condition for that parcel. And because

2:07:29it's a specific zoning conditions to a

2:07:32parcel, if you want to change a zoning

2:07:34condition, you'd have to go back through

2:07:36the resoning process to amend it. So it

2:07:39runs with the land until it's changed by

2:07:41council or whoever approved the

2:07:44development plan.

2:07:46>> And I'll just add in many cases

2:07:48restrictive covenants are placed on

2:07:49those properties as well um in

2:07:51conjunction with housing services and

2:07:54CAO.

2:07:55review those restrictive covenants when

2:07:57um prior to CO and those are placed on

2:08:00the property.

2:08:02>> So even if it's a completely blank piece

2:08:04of property,

2:08:07>> so the restrictive covenants are placed

2:08:08prior to certain of occupancy. So that's

2:08:12that's after the buildout has gone

2:08:14through those are placed on the property

2:08:15in order for them to receive it as part

2:08:17of the zoning condition that's

2:08:18identified in the site plan.

2:08:19>> Yeah. But anyone that purchases a piece

2:08:21of property, even before it's developed,

2:08:23they have to adhere to those zoning

2:08:25conditions. All of them, whether it's

2:08:27affordable housing, whether it's

2:08:28additional buffers, whatever.

2:08:30>> Um, so they just they they're buying

2:08:32that piece of property with all those

2:08:35restrictions.

2:08:36>> Okay.

2:08:37>> You changed the base zoning, so there's

2:08:38new base zoning, so it's whatever is

2:08:41there.

2:08:42>> Yeah.

2:08:42>> It's not a loophole.

2:08:43>> No.

2:08:44>> No.

2:08:48>> All right. Um, so we've talked a little

2:08:50bit about kind of like an a live um

2:08:54update to a dashboard. Um, we've talked

2:08:57about the every five years, every two

2:09:00years. I I would be really interested in

2:09:02just kind of a a end of year report on

2:09:08what happened and development and

2:09:11planning kind of implementation. I know

2:09:13that that's uh a common uh annual

2:09:16reports are are pretty common in

2:09:17planning departments. Um I've I've seen

2:09:20se the LA planning report and the

2:09:23Alexandria planning report. Um and I I

2:09:26like those models and they have pictures

2:09:29of some of the developments that have

2:09:30been constructed. Um I think that would

2:09:33be really interesting. They have maps

2:09:36associated with them. They're pretty

2:09:37accessible both to elected and appointed

2:09:40bodies and to the public. Um,

2:09:42>> so you're looking for something more

2:09:44than say the planning commission annual

2:09:45report that we per

2:09:48currently

2:09:49>> I think we we have all these different

2:09:51reports and moving pieces. Uh, is there

2:09:53a way for us to simplify and kind of

2:09:56bring it all together? Um, so like this

2:09:58would be part of a broader report.

2:10:03>> Yeah, we've talked internally about

2:10:05doing kind of an annual report on

2:10:07development, if you will, I think.

2:10:09[clears throat] Yeah. Um, so that's

2:10:12still a goal. I will tell you just in

2:10:14full transparency, uh, particularly, you

2:10:17know, since the reorg, I still have 18

2:10:20vacancies across the department and, um,

2:10:23we're trying to like keep 18 18

2:10:26vacancies across the department. So, uh,

2:10:28we're trying to keep the lights on and

2:10:30everything moving. I I don't want to

2:10:31like it is something you and I have

2:10:33talked about. It is one of the things I

2:10:35do want to accomplish. I can't commit to

2:10:37know exactly when I can get that done

2:10:39yet just to be honest. and may maybe uh

2:10:42we start it every two years or whatever

2:10:44there's capacity for but I do think it's

2:10:46yeah and I do think it's really

2:10:47important and also currently we are

2:10:50getting different reports of different

2:10:52things in different places and can we

2:10:54consolidate that uh and kind of have the

2:10:58planning department endofear report um

2:11:01and again maybe it's currently we have

2:11:04to face the realities of uh 18

2:11:06vacancies. Yeah. Yeah. Um, and you know,

2:11:10humans are visual creatures. I think

2:11:12being able to see an actual visual,

2:11:15especially as we talk about um, truth

2:11:18and um, dispelling myths, um, you know,

2:11:21a visual that's not an AI uh, image um,

2:11:24showing really what is there and and if

2:11:27there are aerials or things like that so

2:11:29that we can kind of see those big and

2:11:31I'm not talking about like this house

2:11:32got constructed. I'm talking about um

2:11:34this entire subdivision uh these 40

2:11:37acres got built out or this large

2:11:40mixeduse building got up built um having

2:11:42having uh visuals I think is is really

2:11:45important and also having the the maps

2:11:48>> because there's a there's a lot of

2:11:50numbers and tables here and um you know

2:11:53I think knowing where these things are

2:11:56taking place is really important for for

2:11:58us. Um, few questions. How many acres

2:12:02have been annexed over this time?

2:12:05>> Uh, 1,200

2:12:07>> 1,200. Okay.

2:12:08>> Yeah.

2:12:10>> Um,

2:12:10>> 12,000

2:12:12somewhere stack deep in here.

2:12:17>> No,

2:12:19correct.

2:12:21Hold on.

2:12:231,800 acres.

2:12:25>> 1,800. Okay. Okay.

2:12:27>> Um, yeah. So, I just think thinking

2:12:30holistically about I know some of this

2:12:33is in the E, too. I'm trying to remember

2:12:35everything that's in the E, but

2:12:37combining the E with this I think would

2:12:39be uh really really useful and having

2:12:41that that full summary. um the maps um

2:12:46kind of having a sense of our targets

2:12:49for proximity to parks uh and as we

2:12:52build out in new developments um kind of

2:12:55like acres of forested or farmland

2:12:58that's been converted to something else.

2:13:00>> Sure.

2:13:00>> Um and then also like VMT and VMT per

2:13:04capita. So, as we as we have these these

2:13:07goals for uh transitioning to a more

2:13:10transit oriented and walkable community,

2:13:13um how is VMT per capita changing and

2:13:16how is it in in the new kinds of

2:13:18developments that we're seeing? How is

2:13:19VMT changing? Um to an earlier slide,

2:13:23you uh showed us the uh profer for

2:13:27school sites or the school sites profer

2:13:29zero.

2:13:30>> Yeah. Um that's not kind of not

2:13:33surprising because those schools really

2:13:36want large very very large sites. Um

2:13:40>> yeah. Uh so and I've worked in I've

2:13:43worked in communities where um

2:13:46where parcels of land were would be like

2:13:48square miles out west of the

2:13:50Mississippi. Um, and that was those were

2:13:53places where you would get school sites

2:13:56profiter just gifted um gifted to you

2:13:58and you could even like demand which

2:14:00site you wanted. Um, but maybe something

2:14:04more likely would be something like a a

2:14:07fire station land or or EMS. Um, right.

2:14:11Um, and of course we've talked about

2:14:13parks and and trails and those kinds of

2:14:14things.

2:14:17Um, you showed us the number full

2:14:19numbers of units annually. Um it'd be

2:14:21interesting to see um a breakdown by

2:14:24typology.

2:14:27Um,

2:14:30and then I think the the remaining

2:14:32questions I have are coming back to some

2:14:35points that um, Council Member Copac was

2:14:37making

2:14:39about I know this is a big something we

2:14:42just keep talking about is the fiscal

2:14:46impacts and kind of like fiscal impact

2:14:47analysis, costbenefit analysis, fiscal

2:14:50impact model. We use all these terms.

2:14:52Um, I think it'd be I think we need to

2:14:55address that directly and head on. I

2:14:58think that's a project by itself and

2:15:00something that we shouldn't just kind of

2:15:01like pick out around the edges, but

2:15:04needs to be addressed very directly. Um,

2:15:07and kind of understanding the long-term

2:15:09life cycle cost of of um, we look at

2:15:13those at annexation, the annexation. Um

2:15:17so thinking holistically with our county

2:15:20partners about um revenue and

2:15:24expenditures over a 20 or 30 you know

2:15:27life cycle cost of infrastructure I

2:15:30think would be really really important

2:15:31for us to to do. Um and we do have

2:15:35uh some policies and some actions in the

2:15:37comprehensive plan with regard to those

2:15:39things. And we even have um a policy

2:15:42that we're going to analyze greenhouse

2:15:44gas emissions as well. Um and so I would

2:15:49be interested in in us taking a look at

2:15:51that.

2:15:56>> Yeah, go for it. Just on that specific

2:15:58point, um I mean is that something

2:16:01given, you know, we're 18 people down,

2:16:03is that something like through school of

2:16:04government, you know, a student project,

2:16:08you know, is that something that could

2:16:09be done with outside support, sort of a

2:16:13discrete project to look at it more

2:16:16quickly, even if it isn't as detailed as

2:16:17we might like in the long run. I don't

2:16:19know, just a just an idea. How do we

2:16:21utilize those university relationships

2:16:23locally?

2:16:24Yeah, that's definitely something that

2:16:26we can look at and you know we have

2:16:28availed ourselves um you know Bri who

2:16:30gave the presentation earlier she's one

2:16:32of our interns so we do have some um

2:16:35some capacity it's a matter of like

2:16:38prioritizing but then looking for

2:16:39opportunities with other uh we sometimes

2:16:42get uh invites from some of our local

2:16:44universities to hey uh we're looking for

2:16:47project ideas is there something that

2:16:48you need done um so yeah we can we can

2:16:51explore that a little bit more

2:16:52>> and also dangerous this work too as

2:16:55well. But

2:16:57>> yeah. Yeah,

2:16:58>> of course.

2:16:59>> Not sure if that's also the job

2:17:02specifically of our planning staff. I

2:17:04think it's more honestly that's the

2:17:06joint I would say the city and county

2:17:08managers. I mean we this has come up

2:17:11because for instance

2:17:15we needed you know we needed uh

2:17:18increased uh infrastructure to that the

2:17:21city controls. the Snow Hill pump

2:17:23station to serve Treyburn. Um because we

2:17:27had companies that needed to expand and

2:17:30Treyburn and the city did not have the

2:17:33capacity to increase the pump state uh

2:17:36to increase the capacity at the Snow

2:17:40Hill pump station. So, the county spent

2:17:42$30 million to upgrade the Snow Hill

2:17:45pump station, and the city is the one

2:17:48who now benefits from the increased um

2:17:51fees that companies that are outside of

2:17:54the city pay for those services. That's

2:17:57an example that I don't think that's the

2:17:59planning department's responsibility. I

2:18:01think that's more between the city and

2:18:03the county working together. There are

2:18:05so many places where we collaborate and

2:18:08work together. For instance, related to

2:18:11RTP, we provide the sewer capacity

2:18:14through our Triangle wastewater

2:18:16treatment plant, but we they all the

2:18:19companies and now we're going to have

2:18:21residential development with the RTP 3.0

2:18:24and commercial, they rely on city water.

2:18:28So, we're we're joined at the hip on

2:18:30this. And I think it is to me I I want

2:18:34to with Sarah saying that she has 18

2:18:36vacancies.

2:18:37I'm just worried about

2:18:39>> Absolutely. And and there's long range

2:18:41planning that's happening outside of the

2:18:44planning department and the long range

2:18:45planning division of the planning

2:18:47department, right? Like the IT team is

2:18:48looking at the paper uh paper alleys,

2:18:52paper streets. Um DDI did their own

2:18:56small area plan, you know. So uh these

2:18:59types of things are distributed around.

2:19:01So we we you know we need to have the

2:19:03conversation about if the planning

2:19:06department is over capacity at a certain

2:19:08at a certain point who else can within

2:19:11the city or within the county or getting

2:19:13a consultant can can take it on. You

2:19:15know I think we need to have that

2:19:16conversation. But but yeah, I think I do

2:19:19think that um

2:19:22we need to target the fiscal impact

2:19:24analyses kind of head on and and really

2:19:26do a thorough overhaul of of our

2:19:30costbenefit analysis. And that is again

2:19:32that that's in multiple actions and

2:19:35policies. U develop a methodology for

2:19:38city and county staff to estimate the

2:19:39long-term maintenance costs of public

2:19:41infrastructure. That's that's in the

2:19:42comp plan. There's se several others

2:19:44similar. So, not just coming from me,

2:19:46coming from our coming from our plan.

2:19:49And uh this meeting was supposed to end

2:19:5120 minutes ago, [laughter] but this was

2:19:53a really important topic. I think it was

2:19:55important that we talk about it. Um,

2:19:59and

2:20:01ne next steps. What What do you think in

2:20:04terms of thinking about we've we've got

2:20:07some folks talking about a dashboard

2:20:09where we've talked about kind of like

2:20:12multi-year or annual updates. We talked

2:20:15about potentially keeping this as is or

2:20:18consolid or or folding it into a broader

2:20:21um delivery of

2:20:25review of planning and development.

2:20:27>> Yeah, I think what we could do is

2:20:29certainly um one of the things I heard

2:20:31that it would be relatively easy to do

2:20:33is to take a lot of this and turn it

2:20:35into like a one-pager real infographic

2:20:38friendly type thing um that could be

2:20:41shared more broadly. Um that's one

2:20:43thing. Uh

2:20:46I would like to say that we will

2:20:48definitely do this every two years. If

2:20:50we can do it annually, we we will. Um

2:20:55maybe something that coincides, you

2:20:56know, first of the year we roll out a

2:20:58work program um that we do like early I

2:21:02call it the early detection and warning

2:21:03system with you all in February. So

2:21:05maybe at that beginning of the year mark

2:21:07um which is also when we're putting

2:21:09together like board and commission

2:21:10annual reports. Um that's a a big

2:21:12reporting time for us. So, um maybe we

2:21:15can do it um then and maybe between now

2:21:19and the first of the year we just work

2:21:21on repackaging this data set into you

2:21:25know something like that. Um and then

2:21:27see if we can kind of keep it up

2:21:29annually. We'll take a look at the

2:21:32dashboard stuff that's online and see

2:21:35what might need to be updated, what we

2:21:37might could easily add right now before

2:21:39clarity happens. Um, but if not, we will

2:21:42definitely be building out a bigger,

2:21:44better dashboard with clarity.

2:21:45>> Yeah, I think that makes sense. I don't

2:21:47I don't want us to go chasing our tails.

2:21:50Um,

2:21:52yeah. No, and I think you you hedged

2:21:56your comments about the amount of work

2:21:57um that like a live uh dashboard, but

2:22:00people do need well, I mean, we all need

2:22:02to see what's happening. You know, we

2:22:04need the realities on the ground to be

2:22:07relayed to us and to the public. And um

2:22:10would you take a look at some other

2:22:12examples of kind of like those annual

2:22:14reports? The ones that I can think of

2:22:16off top of my head that I like are like

2:22:18the Los Angeles uh planning department

2:22:20and then the Alexandria Virginia um

2:22:23Raleigh does one every year. Yeah. So

2:22:25those are two that I like. I haven't um

2:22:27looked at the Raleigh one recently, but

2:22:29um really good ideas in those.

2:22:32We're going to miss you.

2:22:34>> Gonna miss y'all. I will say it really

2:22:36has been an honor to serve you and the

2:22:38residents of Durham. Um I've learned a

2:22:41lot over the four and a half years here

2:22:43and thank you for your patience

2:22:45for my lack of public presentation

2:22:47skills at council. Um but I do

2:22:50appreciate you guys um just being nice

2:22:53about it. Um so so yeah

2:22:56>> and congratulations on your your new job

2:22:58too.

2:22:59>> I appreciate that.

2:23:00>> Yeah. And thank you.

2:23:02>> Go back. You want to Oh.

2:23:08Thank you.

2:23:08>> All right.

2:23:11U we have um really just one more item

2:23:15here which is the the multimodal

2:23:18development standards update item seven

2:23:22with Lisa Miller. Oh

2:23:26>> good morning everyone. Lisa Miller with

2:23:27the planning department. Um, I am going

2:23:30to just introduce Jennifer Baldwin is

2:23:33here from Three Oaks Engineering, our

2:23:35consultant that we're working with on

2:23:36this project. Um, we will try and do a

2:23:39quick version of the presentation given

2:23:41the time. Um, and then we'll both be

2:23:44available to answer questions.

2:23:48Great. Thanks, Lisa. And excited to

2:23:51share our progress since the last time

2:23:53we met earlier this year. Um, and we've

2:23:58got, you know, I'm going to do a shorter

2:24:00presentation so that we can have the

2:24:01most time for the discussion because

2:24:03we're really hoping to get some feedback

2:24:04from y'all, um, as we continue this

2:24:06process. And some of the updates or the

2:24:09highlights that we wanted to make sure

2:24:11it was clear some of the the changes. We

2:24:13came earlier in the spring thinking we

2:24:15were going to do a multimodal

2:24:16transportation impact analysis and

2:24:19figure out how to get that TI process

2:24:21updated to be more focused on multimodal

2:24:24improvements. and we have since shifted

2:24:26to what we're calling the multimodal um

2:24:29development standards. And so that's the

2:24:31MMDS acronym. Um, and mainly we shifted

2:24:35because we heard you earlier in the year

2:24:37and through all of our staff and

2:24:38stakeholder conversations that we really

2:24:40wanted this process to be flexible and

2:24:43it's not a one-sizefits-all and there's

2:24:45so much nuance and so to roll this out

2:24:48the TIA process is very vehicular driven

2:24:51and requires a lot of extenses data that

2:24:54we just don't have access to. And so bad

2:24:57data in, bad data out. And we were as we

2:25:00kind of really um talked about it, we

2:25:02were just concerned that that would

2:25:04create a lot more staff impact and

2:25:07struggles for you all. And so also in

2:25:10the part of the conversations and the

2:25:11collaboration just had some really good

2:25:13ideas of a more simple process that

2:25:16could meet the goals of what we were

2:25:17trying to accomplish which was to get

2:25:19more um bike ped infrastructure safer

2:25:22system um alignment with development.

2:25:25And so just a shout out to all of the

2:25:27different partners. This has truly been

2:25:28a collaborative process and it's been

2:25:30iterative. You know we've had a lot of

2:25:32conversations. We've met with NC do the

2:25:34TPO has been joining the conversations.

2:25:37Um, and I'll talk a little bit later

2:25:38about we also had a stakeholder meeting

2:25:40with local development practitioners

2:25:42that provided really great insight into

2:25:44the process and how it could look in the

2:25:46future. And so this draft concept that

2:25:49we are sharing that you had in your

2:25:51packets and I'm going to walk you

2:25:52through a an example test site um really

2:25:55kind of thinks about more about building

2:25:58a point safe based approach. And so

2:26:01it's, you know, if you come in with a

2:26:03development, it would assign based on a

2:26:05series of questions that would ask, um,

2:26:07and what those answers, where it's

2:26:09located, is it on a transit route, um,

2:26:11what is the existing conditions like,

2:26:13and it then it would assign a certain

2:26:15score that you would need to meet based

2:26:16on your site plan. And so that site plan

2:26:18analysis helps to identify what those

2:26:21bike ped um, transit and safe system,

2:26:24and street enhancements look like.

2:26:28And so, how does it work? And really we

2:26:31one the first part is we establish the

2:26:33requirements. So the applicant submits

2:26:34the development you know the site plan

2:26:37and staff would review and confirm that

2:26:39applicability um and what the minimum

2:26:42score would be which I'll talk a little

2:26:43bit later about these steps. Um and then

2:26:46the the site would be evaluated based on

2:26:48context about some of our pre-screening

2:26:50questions. a score would be assigned and

2:26:53then the the great thing about this in

2:26:55our minds is that it gives the developer

2:26:57full flexibility to they can figure out

2:27:00how they can make their site plan meet

2:27:02that minimum score. So we're not honing

2:27:04in that you must have XYZ. There's lots

2:27:07of different options of how they can

2:27:08navigate based on the points that they

2:27:10need for their site approval.

2:27:13and the methodology that we're working

2:27:15on. You really kind of walked through

2:27:17this is just another flow of what it

2:27:18looks like in terms of there's

2:27:20pre-screening and the site context

2:27:22because I think that's the harder part

2:27:23about the livability improvements that

2:27:25we're looking for in transportation is

2:27:28so contextsensitive. Is the site

2:27:30downtown? Is it in Durham County? Is it

2:27:32on a statemaintained road or is it on a

2:27:34city road? There's a lot of nuance that

2:27:36goes into um you know what that ultimate

2:27:39score will look like. And then the place

2:27:40types also play a big role. So the menu

2:27:43of elements, the applicant selects the

2:27:45elements that they want to or can add to

2:27:48their site plan to meet the minimum

2:27:50requirement and then the staff

2:27:51coordination that happens to get the

2:27:53site plan approved moves forward.

2:27:57All right, so I'll just fly through

2:27:58these. Um, and really the intent of our

2:28:01conversation today is we wanted to focus

2:28:03a little bit more on just the process

2:28:05and the methodology and just some, you

2:28:07know, overall reactions. We're still

2:28:09working through what the right elements

2:28:11are. Staff has spent a lot of time

2:28:13thinking through making sure we're

2:28:15getting all of the elements um that are

2:28:17separate from what the UDO already

2:28:19requires. So, this is not something that

2:28:21is going to change current requirements

2:28:24and can't be stacked. So, just because

2:28:26you know currently requires um a

2:28:29sidewalk or transit improvement doesn't

2:28:31mean that can count towards the points

2:28:32that they needed. So the goal is that

2:28:34there's lots of additional elements that

2:28:36they can get beyond what's already being

2:28:38required. So we're working through what

2:28:40those elements look like and then what

2:28:42the actual score um would be associated

2:28:44with. And the scores we're trying to

2:28:46match them with the level of effort

2:28:48because we do recognize that some

2:28:50elements are going to be more costly and

2:28:52so they're going to be worth more than

2:28:54adding a bike rack. Um and the ultimate

2:28:56goal is to make sure that we're not

2:28:58doing the the least expensive elements

2:29:01just to meet a minimum score. So we

2:29:03don't want this to be an arbitrary

2:29:04scoring process.

2:29:06Um so in the pedestrian and I should

2:29:08have mentioned earlier but the

2:29:09methodology is set up that there's four

2:29:11different categories. So it's pedestrian

2:29:13enhancements and improvements really

2:29:15highlighting safety improvements of how

2:29:17we can make the pedestrian environment

2:29:19safer and um more comfortable. And then

2:29:22we have a category for bicycle

2:29:24improvements. How can we think about

2:29:26bicycle traffic? um you know making it

2:29:28safer and and um looking at the

2:29:31[clears throat] trail system as well and

2:29:32then the microobility and the connection

2:29:34to transit from a bike perspective.

2:29:37We have a transit category that we've

2:29:39worked really closely um with our

2:29:41transit partners to think about the

2:29:42accessibility of the bus stops, the

2:29:44access to the bus stops um and then also

2:29:47how we're um handling the crossings and

2:29:51visibility of pedestrians getting on and

2:29:54off the bus and crossing the street and

2:29:55going to the site and um other

2:29:57destinations.

2:29:59And then the final category is street

2:30:01design improvements. So this is just all

2:30:03of the other elements of the street

2:30:05itself. So the frontage of the site um

2:30:08in terms of how we can calm traffic and

2:30:10really go after the vision zero

2:30:12priorities of trying to reduce traffic

2:30:14fatalities and um serious injuries. So

2:30:17this is looking at reduce crossing

2:30:19distances, certain traffic calming

2:30:21elements. Um it gets us detailed into

2:30:24the tight curb radi to make that

2:30:25pedestrian crossing shorter. So a lot of

2:30:28other of the core street enhancement.

2:30:32Okay, so now we're getting into the math

2:30:33portion of the presentation and math is

2:30:35not my strong sort suit. So hopefully I

2:30:38will walk through through this because

2:30:39this doesn't this isn't a huge difficult

2:30:41um equation and that's really one of the

2:30:43reasons we went with this concept

2:30:45because we think it can be very simple

2:30:47to understand and hopefully to um you

2:30:50know maintain and move forward. And so

2:30:53the site is entered the way that we've

2:30:54got the point set up is that it does

2:30:56consider the the sites that are less

2:30:58than 2 acres or greater than 2 acres.

2:31:01And so that I think the conversation

2:31:03earlier is just to show that a smaller

2:31:04site, you know, lower cost. We don't

2:31:07want to unfairly have them doing the

2:31:09same as a huge site. However, in some

2:31:11cases where the smaller acreage still

2:31:14has a really high place type, the you

2:31:17can see the scoring will change. So a

2:31:19small less than 2 acre site, but in

2:31:22downtown is going to have a higher score

2:31:24than a less than 2acre site in a place

2:31:26type of established residential. So,

2:31:28we've tried to build in some of that

2:31:30flexibility and to really tie it back to

2:31:32your place types. And then for the

2:31:35greater than 2 acres, we're also looking

2:31:37specifically at the estimated daily

2:31:39vehicle trips. So, if the site is really

2:31:42bringing in a lot higher ADTS would also

2:31:45have a corresponding higher multimodal

2:31:47DS score.

2:31:51And then once you set what each site

2:31:53plan is going to have a minimum score,

2:31:55there's this the process is we were also

2:31:58trying to think about how we can within

2:31:59that minimum score requirement get us

2:32:03exactly what we need for that specific

2:32:04site. And the thought process here is

2:32:06that we would have the site and the

2:32:08developer and the applicant answer a

2:32:10series of questions. Is the site within

2:32:13a quarter mile of an existing bus route?

2:32:15Is the site identified in the walk bike

2:32:18plan priority? Um, so has it been

2:32:20elevated from other planning efforts as

2:32:22a high priority bike ped corridor? Is it

2:32:25on the high injury network? Those three

2:32:27questions and corresponding answers were

2:32:29considering the tier one element and are

2:32:32going to be worth more points. So the

2:32:34the site plan would have to have a

2:32:36little bit of a higher threshold in the

2:32:38different categories. Tier two is is the

2:32:41site within a/4 mile of a school? Is it

2:32:44adjacent to a greenway trail? And then

2:32:46is it a quarter mile from a park or

2:32:48community center? And so you can see

2:32:50that those are worth two points from the

2:32:52different required categories. And the

2:32:54yellow box just highlights the goal of

2:32:56these questions helps us see if a site

2:32:59plan comes in and based on the place

2:33:01type, it's going to require 40 points of

2:33:04the 40 points, we're going to require

2:33:06specific categories. So again, trying to

2:33:09think through that you're not just going

2:33:11to go put in a 100 bike racks to satisfy

2:33:13the 40 point requirement. We really want

2:33:16it's on a high ridership transit

2:33:18corridor. We're going to really focus in

2:33:20and require a portion of the points to

2:33:22be in the transit investment. It still

2:33:25allows the developer to have some

2:33:26flexibility on the elements, but it

2:33:28gives a little bit more guidance on the

2:33:30specific mode of travel um and elements

2:33:32that we're looking for.

2:33:35And so what we've been doing so that was

2:33:37the process the concept that we have

2:33:39been you know iterating and as I

2:33:41mentioned before we met with

2:33:42stakeholders and then our teams have

2:33:44also been scoring previous site plans

2:33:47because and we've changed a lot what we

2:33:50learned through the scoring of the site

2:33:51plans is this really giving you guys

2:33:54what you want to see out of the process

2:33:55and so it's been updated. We're going to

2:33:57continue to score and test some new

2:33:59sites and evaluate

2:34:04and then all right so I'll run through

2:34:05this really quickly but this was just

2:34:06our thought in terms of helping you see

2:34:09what a hypothetical test site would look

2:34:11like. So let's just say we have a site

2:34:13plan come in that's new mixeduse

2:34:15neighborhood greater than 2 acres. It's

2:34:18got about 3 to 5,000 ADTS estimated

2:34:20daily vehicle trips. Um it's on an

2:34:23existing bus route. There's sidewalk gap

2:34:25along the site plan frontage and it also

2:34:28has a planned bicycle facility nearby

2:34:30from the um adopted bike pet plan. And

2:34:33so the box on the right just shows you

2:34:34based on the place type and the scoring

2:34:37that site plan would have a minimum

2:34:39score of 35. And then how they answered

2:34:42the two tiers of questions. It is on a

2:34:44bus route. It's in the bike ped plan.

2:34:47It's not on the high injury network. Um

2:34:49and then for tier two, it's not within a

2:34:52quarter mile of a school and it's not

2:34:53adjacent to a trail or um within a

2:34:56quarter mile of a park or community

2:34:58center. So based on those answers, then

2:35:01you look at minimum score requirement of

2:35:0435. You do an assessment of the site

2:35:06plan that was submitted. So the base

2:35:08score and that base score, the site plan

2:35:11is only um achieving five points. So

2:35:14that means they're only adding elements

2:35:17that are worth five points in the

2:35:19process. So then they have a gap um of

2:35:2230 points that they need to fill in. So

2:35:24that 30 points, those tier questions

2:35:28because it's on a high transit route and

2:35:30because there is a big gap in the

2:35:31sidewalk network and bicycle, we're

2:35:33going to require 16 of those 30 points

2:35:36to be chosen within those specific mode

2:35:39categories. the the developer still the

2:35:42site, you know, they the applicant still

2:35:44has that flexibility of how they spend

2:35:47those required points, but they have to

2:35:49pick certain elements by mode based on

2:35:52how they answered the questions.

2:35:54And then they're ultimately going to

2:35:56have the 14 points that they can pick

2:35:58across all elements.

2:36:01So that's just an example. This slide

2:36:02shows you that there's a hundreds of

2:36:05scenarios of how the applicant could

2:36:07satisfy the point requirement. And so it

2:36:10truly is trying to push it back on the

2:36:12applicant to then take in the guidance

2:36:15that's been given the the um the score

2:36:19that they need to meet, the minimum gap

2:36:20score, and then come back. And there's

2:36:22going to be a lot of collaboration that

2:36:24the the applicant is already doing with

2:36:26the city or the county in terms of

2:36:28getting their site plan approved to

2:36:30really navigate how they're going to

2:36:31fill that requirement.

2:36:35And then my final slide, and I'm happy

2:36:37to answer any questions, is what are our

2:36:39next steps? This is not a done process.

2:36:41We still have some more work to do.

2:36:43We're working to refine the scoring

2:36:45elements and the points. We're going to

2:36:47continue to do additional site testing

2:36:49to make sure that we can refine the

2:36:51amount of points and and we're really

2:36:53meeting the goals that we set out at the

2:36:55beginning of the process. We need to

2:36:57have a little bit more collaboration

2:36:58with NC DOT to make sure that as we

2:37:01start digging into a draft ordinance

2:37:03andor our design guide that we're going

2:37:05to put out with this scoring process, we

2:37:08understand how statemaintained roadways

2:37:09and properties that are coming in on DOT

2:37:12roadways are going to operate within

2:37:14this system. Um, and then ultimately we

2:37:16need to draft that ordinance language as

2:37:18well as a guide. One of the key

2:37:20takeaways from the stakeholder

2:37:22practitioner is just giving them a

2:37:24similar presentation and the tool. They

2:37:27had a ton of questions. There's only so

2:37:29much, you know, that you could

2:37:30communicate. So once we answered some of

2:37:32their questions live, I think they were

2:37:33a lot more comfortable, but we

2:37:35definitely will be putting out a guide

2:37:36book that walks through exactly kind of

2:37:38what I just did, gives examples of other

2:37:40site plans, so it's really clear. We'll

2:37:43be developing some template um

2:37:45worksheets of in terms of when a

2:37:48developer or an applicant is interested

2:37:50in submitting a site plan. Here is some

2:37:52those tier questions, some forms to try

2:37:54and make it as easy on staff as possible

2:37:57to intake and develop this new process.

2:38:00And then ultimately once we are all

2:38:02comfortable and we kind of move through

2:38:03the process, we will be sharing this

2:38:05with BPAC and also going through the

2:38:08public hearing process for adoption with

2:38:10all the different boards.

2:38:13So happy to answer any questions or go

2:38:15into a little bit more detail on any of

2:38:17those slides if you need it.

2:38:22>> Colleagues,

2:38:27um, [clears throat] oh th this is

2:38:30excellent. I really like the scoring um

2:38:34of the different pieces and people can

2:38:36you can select which ones. I'm curious

2:38:38about the how things are scored. Yeah,

2:38:41>> I'm curious about about that. Here's

2:38:45why. I come from a development

2:38:46background. This looks a lot like agile

2:38:49and um

2:38:51you know, sprint planning or whatever

2:38:53you want to call it. Um

2:38:58it would it it's really difficult to

2:39:01score something how difficult it is to

2:39:03do, right? And I'm I'm asking is it

2:39:06scored on the difficulty of whatever the

2:39:10project is? And if so, I would if you

2:39:14all are still thinking about the scoring

2:39:15elements, how it all works, I would

2:39:17suggest the Fibonacci scale. That's what

2:39:19they're using agile. And because a four

2:39:23and a five is really difficult to tell

2:39:25between a four and a five, but a three

2:39:26and a five,

2:39:27>> yeah,

2:39:28>> is different. And then five and a eight,

2:39:30right? Of course, going that way. then

2:39:33eight and 13 and so forth. So, um, but I

2:39:37absolutely love the or how you all are

2:39:40organized in doing that because it's

2:39:42very transparent and what's being done,

2:39:45what could be expected on both sides in

2:39:48that. Um, I love the plans. I love the

2:39:51ideas. I love how how you all are

2:39:53planning for like the crosswalks and

2:39:56that sort of thing. That is excellent.

2:39:58It's very visual and it's very easy to

2:40:01understand.

2:40:02And I really like that. But I'm really

2:40:04curious about what your thoughts on how

2:40:07you're coming up with the scoring of the

2:40:09different

2:40:11>> parts and um how you're managing that.

2:40:14>> Yeah, I'll I'll um start is so how we've

2:40:17developed the scoring and and just to be

2:40:18clear, you're talking about how we're

2:40:20going to assign what a crosswalk is

2:40:23worth versus a bike lane versus curb

2:40:25extensions. And that's been a scale of

2:40:28level of investment or the difficulty of

2:40:31implementation. And so trying to kind of

2:40:33match that and then ultimately also

2:40:36making sure that we're not having a

2:40:38minimum score of 152, you know, so

2:40:41trying to have that balance. Um, I will

2:40:44say that still we've been more focused

2:40:46on making sure we've got the right

2:40:48elements and that we're thinking about

2:40:50the requirement of scores within each

2:40:53category because if we want to require

2:40:5630% of the minimum score to be in

2:40:58transit, we have to make sure that the

2:41:01scores in transit can actually equal 30%

2:41:04of an average minimum score. So, there's

2:41:06a lot of complexity, but I really liked

2:41:08your guidance too on thinking about the

2:41:09three versus five, which we've used that

2:41:11a little bit. I think that once we are

2:41:13set on the elements and the overall

2:41:16process, then we can spend a bit more

2:41:18time on our site evaluations,

2:41:21adjusting the scoring as needed.

2:41:25>> Thank you. Thank you,

2:41:27>> Council Member Copac.

2:41:29>> Yeah, thank you. Thanks for this

2:41:30presentation and the work. I also do

2:41:32really appreciate the the flexibility uh

2:41:34and the coverage across pedestrian,

2:41:36bicycle, transit need, street design and

2:41:38the attempt to kind of make it relevant

2:41:41to specific projects and not giving

2:41:43credit for just meeting UDO. So, thank

2:41:45you for all that. Um, you know, as you

2:41:48get into the uh the the scoring, uh I

2:41:52just, you know, I'm glad that you're

2:41:53involving practitioners and getting that

2:41:55feedback. I'd be curious to know now or

2:41:57in the future like if you've run past

2:42:00projects through and seen how they've

2:42:02scored Yep. to help you adjust the

2:42:04scale.

2:42:05>> Yeah. I should have mentioned too Lisa

2:42:06sent out they actually scored they chose

2:42:08whatever site they wanted to and they

2:42:10used that and did some of them not all

2:42:12the practitioners that we invited did

2:42:13that but several of them took the time

2:42:16to submit their own scoring and that was

2:42:18really helpful to see somebody who

2:42:19hasn't been invested in the several

2:42:21conversations how they interpreted the

2:42:23the guidance. Um and we'll use those SI

2:42:26evaluations too.

2:42:27>> Okay. Yeah. And just the last thing I'll

2:42:29say having been involved in a number of

2:42:31certification programs just to be uh

2:42:34careful about not getting too weighed

2:42:36down with complexity uh and finding that

2:42:38balance between trying to cover all the

2:42:40bases but not making it too difficult to

2:42:42go through for staff and for uh

2:42:44practitioners. And I imagine that's

2:42:46something you're thinking about in your

2:42:47evaluation process. So yeah, thank you

2:42:49very much.

2:42:49>> Yeah, thanks.

2:42:55did and um

2:42:58>> I just excuse me. Um I just think this

2:43:02is fantastic. Um it's really exciting to

2:43:07think about this being implemented. So,

2:43:09thank you so much uh for coming up with

2:43:12basically some type of system

2:43:15um and um that can be implemented and

2:43:19that's could be user friendly not only

2:43:22for the applicant but also for staff and

2:43:26um so I just want to say kudos

2:43:30uh wondering when I know you've laid out

2:43:33the next steps do we have a goal on

2:43:36timeline of when we are hoping this can

2:43:39be adopted.

2:43:42>> So, our hope is to incorporate this into

2:43:46the LDC and have them move forward

2:43:49together. Um, there would be a

2:43:53assessment needed in order to determine

2:43:56how this could function if it were to be

2:43:58a standalone text amendment to the UDO

2:44:01under the downzoning legislation. Um, so

2:44:05that's our intention is trying to get

2:44:07this uh sorted and pulled into that in

2:44:10the hopes that that can move forward

2:44:11together. Otherwise, it'll it'll be some

2:44:13additional work to figure out.

2:44:15>> Okay.

2:44:18Well, obviously as as soon as possible

2:44:22would be good. Um, I just want to also

2:44:24mention I appreciate that you're going

2:44:26to create a like an implementation

2:44:28guide, but similar to a lot of the

2:44:31things that we've been talking about

2:44:32today, like how do we actually help

2:44:35people

2:44:37um through something like this is, you

2:44:39know, maybe doing some training sessions

2:44:42and ver, you know, whatever.

2:44:45So, thank you.

2:44:48I'd like to have a better understanding

2:44:50of who this is applicable to because

2:44:52like with TAS it's just around there's

2:44:54certain like it gets triggered by a

2:44:57thing and so wanting a better

2:44:59understanding of that.

2:45:01>> Yeah, we're still working through that

2:45:02in more detail. We're trying to focus on

2:45:04the process but the intent is that some

2:45:07things it would not be applicable to

2:45:09when we come back to the size. We we

2:45:12landed we went through a lot of

2:45:13different scenarios but we really

2:45:14thought about the size of the site

2:45:16itself and how it works through the

2:45:18process and then have been working to

2:45:20evaluate whether this is um coming in

2:45:23through reszoning um versus a site plan.

2:45:25So our focus so far has been in the site

2:45:27plan process and phase because that's

2:45:30where you can really influence and see

2:45:31how the the natural environment the

2:45:34physical entities will be improved. Um,

2:45:36but we're also kind of having more

2:45:38conversations about how this would

2:45:39impact for reasonzoning and could be

2:45:41profered into the process.

2:45:43>> Okay. Thank you. I just would like a

2:45:44little bit more information on that when

2:45:46we can. Um, it goes back to what we've

2:45:49been saying through the whole day is it

2:45:52the

2:45:53>> the smaller projects don't have the the

2:45:55space. So, our rules have to really be

2:45:59mindful of that. Not that we don't want

2:46:00to achieve these other things, but

2:46:03some of that is going to have to come

2:46:05through just our CIP process versus

2:46:07through the development process.

2:46:08>> Yeah.

2:46:11>> One quick addition, I think that we

2:46:13actually just in the last couple of

2:46:14conversations identified that we want to

2:46:16establish a threshold that under which

2:46:19it's exempt um because of that very

2:46:22issue that's come up in our

2:46:23conversations amongst staff. So,

2:46:27>> other than that, thank you. This is

2:46:29great.

2:46:29>> Thanks for the presentation. Um, can I

2:46:31just ask? So, why not just require what

2:46:35we need instead of having the whole

2:46:39point system?

2:46:40>> It's a great question. Um, and I think

2:46:42the the easier answer is it's it's not

2:46:45not that black and white. Um, each site

2:46:47is so different, the nuances of it. And

2:46:50I should say too in the scoring of this,

2:46:52there's could be some sites that are c

2:46:54certainly applicical in the process that

2:46:56when we evaluate, they already have the

2:46:58best transit infrastructure, already has

2:47:00really good bike and already has

2:47:01sidewalks. So then we're going to have

2:47:03to adjust that minimum score because the

2:47:05base existing condition isn't going to

2:47:08um need additional enhancements. And it

2:47:11also goes into transportation and bike

2:47:13ped specifically multimodal is is very

2:47:16contextsensitive and it is very

2:47:18dependent on um comfort [clears throat]

2:47:21and that's harder data to be able to

2:47:23evaluate. So you truly have to evaluate

2:47:26the existing site to be able to see

2:47:28what's most appropriate and what

2:47:29elements would need to be applied and

2:47:31and then adjust that minimum score. And

2:47:34the UDO um is already requiring a lot of

2:47:37the base multimodal elements. So this

2:47:40process is really trying to what's the

2:47:41next step that gets a little bit of the

2:47:44missing gap elements that we're we're

2:47:46not seeing in Durham and Durham County.

2:47:48And that's those comfort level um type

2:47:51of elements.

2:47:54And correct me if I'm wrong, I think

2:47:55memory serves that part of this is

2:47:57because um you know we can't require

2:48:01that people make off-site improvements

2:48:03for instance, but one way that they

2:48:05could get some of the points they need

2:48:07maybe to do those off-site improvements.

2:48:10And so if we just build in the basic

2:48:12requirements, which we pretty much

2:48:13already have, we are forgoing the

2:48:16opportunities that some people might

2:48:17choose to do that because maybe there's

2:48:20not a whole lot else that they could do,

2:48:21right? So, that's also been part of the

2:48:24thinking, I think.

2:48:24>> Yeah.

2:48:25>> Okay, that was very helpful. I

2:48:27appreciate that. I count me as an

2:48:28open-minded skeptic. Um, I need to see

2:48:33more a little bit more here. Um,

2:48:36>> in my mind, we have our standards, we

2:48:38apply them, we look at the context, um,

2:48:41and apply them appropriately.

2:48:44>> Um, so

2:48:46the off-site stuff makes sense to me.

2:48:48Um,

2:48:51this seems complicated.

2:48:53Uh, like another layer of of, you know,

2:48:56and then we've got the point system for

2:48:57the green building and, um,

2:49:02>> an an open-minded skeptic at this point.

2:49:05Uh, I feel like I need to need to see a

2:49:06little bit more because like if we want

2:49:08a tight curb radius, for example, I saw

2:49:10that on the slide, we'll just we should

2:49:13just have a tight curb radius.

2:49:17There's a lot of and this is the nuance

2:49:18in the black and white for

2:49:20transportation standards and a lot of

2:49:22you know it's easy to say if there's

2:49:23standards but a lot of it is engineering

2:49:24judgment and so there's not a specific

2:49:27you must have X because the X won't work

2:49:30in all occasions and so that's why the

2:49:32thought process for this was to be able

2:49:34to have a little bit more of that

2:49:36context sensitive approach built in um

2:49:40and especially when it goes to bike ped

2:49:42standards uh you know we've been

2:49:44debating as planners and engineers years

2:49:46for decades on the right what's the

2:49:48right facility and it's continuing to

2:49:51progress and so that was raised from our

2:49:54practitioner perspective is something

2:49:55it's going to be a bit more longterm but

2:49:57you know the city and the county and the

2:49:59state really needs to have more design

2:50:01standards available for bike ped um ele

2:50:05you know infrastructure because there

2:50:06just isn't any and so we we're going to

2:50:09need to provide some of that detail and

2:50:10the guidance and and point to national

2:50:13best practices is

2:50:16>> yeah I was just going to offer for

2:50:18anyone that might be interested I think

2:50:20one thing that we'd be happy to do right

2:50:22staff they're like what are we doing

2:50:24[laughter]

2:50:25is for anyone that maybe wants to sit

2:50:27down at a separate meeting and we can

2:50:29kind of do what what we've done as staff

2:50:31and walk through an example and like you

2:50:33know how it plays out on an actual plan

2:50:36we'd be happy to set up you know some

2:50:39meetings for anyone who's interested and

2:50:40wants to sit down with staff to do that

2:50:42>> that would Yeah, I think that'd be that

2:50:44would be interesting. I I guess what I

2:50:46want to make sure we don't do is um make

2:50:50it possible to not

2:50:53uh follow our standards um and allow

2:50:57them to do something else. Um, and if we

2:51:02and also I want to make sure that like

2:51:03if on our side our transportation

2:51:06planners or or or our planning

2:51:08department is reviewing a case and it's

2:51:10like well we need this here but the

2:51:13point system allows the other side to

2:51:16determine oh no actually I don't want to

2:51:18do that I want to do this instead. I

2:51:20just want to make sure that and I I get

2:51:23the the I get the flexibility and I get

2:51:25the context sensitivity

2:51:27um and the opportunity to maybe get some

2:51:29stuff off site. I think that's all uh

2:51:31fantastic. Um I think th that those are

2:51:35the things that are on my mind, you

2:51:36know. Um and if we want type curb tight

2:51:39curb radi, we just get tight curve radi

2:51:42and that kind of thing. So,

2:51:44>> um, but I keep an open mind and look

2:51:47forward to, um, more information down

2:51:50the line. C,

2:51:51>> could could we have that total to to

2:51:55Council Member Baker's point around

2:51:57there's lots of different things at play

2:51:59here with different standards. And so, I

2:52:01think what would be helpful at some

2:52:02point is to have actual a test case.

2:52:04It's like, okay, we're requiring or

2:52:06potentially doing all these things. How

2:52:08do they interplay together with an

2:52:09actual case? even if it's like one we

2:52:12already have seen. Um because

2:52:16I think if the rules are fair and folks

2:52:18the development community perceives them

2:52:20as fair as far as like okay I can

2:52:23respond to that. What I can't respond to

2:52:26is ambiguity. Um the two things that I

2:52:29hear consistently are the rules aren't

2:52:31straightforward and the time takes too

2:52:33long. We don't mind doing the rules if

2:52:36we know what they are. And so I think

2:52:38that that's the that kind of

2:52:40predictability is what we hear most

2:52:43often. Um and that also goes to the

2:52:45predictability of what's it going to

2:52:46take to get through a process. So I

2:52:48think that that's the um tension point.

2:52:51Um and when we're doing it in all these

2:52:53different ways which are all very

2:52:55compelling and necessary, but what is

2:52:57that kind of interaction together?

2:53:00Yeah, I think Council Member Cabar,

2:53:02Mayor Prom and I find ourselves on

2:53:05opposite sides of a lot of development

2:53:06stuff, but I think where we find

2:53:07ourselves on the same page is definitely

2:53:10making what we want the easiest thing to

2:53:12do. Making that process really easy, the

2:53:15outcome. Yeah. So, any other Well,

2:53:19there's no one else left over there.

2:53:22Okay. Thank you so much. Thank you for

2:53:25the presentation. And item eight is uh

2:53:28just our planning uh program projects

2:53:30that is available to people if they want

2:53:32to take a look. And uh I am going to

2:53:36adjourn us at 12:24. Thanks everybody.