- What: The state's June framework for evaluating data centers over 25 megawatts and Executive Order 658 (September 8, 2026), which starts implementing it, and how Worcester should respond.
- Where it stands: The advisory committee held off endorsing the framework and formed a three-member ad hoc subcommittee to report back by the October 19 meeting. Proposed positions: use the framework to evaluate any proposal, no non-disclosure agreements with the city, the sustainability department and the committee at any community-benefits table, and a 5-megawatt threshold.
State context
State-level rules, including Executive Order 658 and a statewide list of local moratoriums and bylaws, are on Massachusetts Data Center Policy.
Log
- 2026-09-14 - Green Worcester Advisory Committee - Member presentation on the framework and executive order; debate over weak wording and exemptions; endorsement postponed; subcommittee formed 7-0.