  • What: The state's June framework for evaluating data centers over 25 megawatts and Executive Order 658 (September 8, 2026), which starts implementing it, and how Worcester should respond.
  • Where it stands: The advisory committee held off endorsing the framework and formed a three-member ad hoc subcommittee to report back by the October 19 meeting. Proposed positions: use the framework to evaluate any proposal, no non-disclosure agreements with the city, the sustainability department and the committee at any community-benefits table, and a 5-megawatt threshold.

State context

State-level rules, including Executive Order 658 and a statewide list of local moratoriums and bylaws, are on Massachusetts Data Center Policy.