11 Cliff Street (Lily LLC)

At a glance

Based on auto-generated captions; names and details may be misheard.

  • What: amendment (PB-2026-070) to the approved definitive site plan for a commercial building at 11 Cliff Street that serves as a dispatch base for a landscaping business.
  • Where it stands: Planning Board approved the amendment 5-0 on 2026-08-26.
  • Next: structural engineer's slope letter is due before the certificate of occupancy.

The proposal

  • Applicant: Lily LLC (principal captioned "Danila Matoss"); attorney Mark Borenstein of the firm captioned "Principal Bell".
  • Changes since the original (2024) approval: large boulders found on site were used for a boulder and riprap wall in place of the tiered wall, and a septic system was added (the building was first planned as dry; now has a water line, bathroom or kitchen).
  • Inspectional Services' structural engineer was comfortable with the slope; staff added a condition for a professional engineer's letter certifying stability before occupancy.

Conditions changed at the hearing

  • Struck: 1C (minimum 10 trees along the east line; the plan already shows an evergreen row), 1Q (covered bike parking; staff on site said bikes can be kept inside) and 1R (EV charger; the two EV-ready spaces remain).
  • Amended: 1D to call for wall drain outlets for the retaining wall; 1V (trees stay 10 feet from the new water line, so one tree is shifted; shrubs may stay) with the ambiguous "etc." removed.
  • No public comment.

Discussion time

About 12 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-08-26 - Planning Board 12

Log

  • 2026-08-26 - Planning Board - Item 8: public meeting on the site plan amendment; approved 5-0 with the conditions above. Staff presenter Stephen Cary; Leslie Rodriguez had no DPW comment.