180 Harding Street (BDDW-26-20)
At a glance
Based on auto-generated captions and the posted minutes; names may be misheard.
- What: Building Demolition Delay Waiver (BDDW-26-20) to replace all windows on the second and third floors of 180 Harding Street, the first step in converting two vacant floors to apartments.
- Where it stands: approved 6-0 on 2026-08-06 with a split-material compromise.
- Next: none recorded.
The proposal
- Architect Jeremiah Gallant for the owner (apparently Dino Lorusso, who also owns Crompton Place at 138 Green Street).
- Existing windows are historic (over 50 years old) but not original; many are dry-rotted, boarded up or missing, including swivel/pivot units.
- Applied for aluminum-clad wood; the owner then preferred black vinyl, citing cost (about two to three times) and neighborhood precedent.
- Design: transoms over fixed center units; rear elevation six-over-one replacing concrete block.
Commission concerns
- Material change from the application; the chair and Jeffrey Burnett wanted cost comparisons and elevations. Staff pointed to a financial hardship filing.
- Michelle H. Johnstone: no full wood-to-vinyl replacement has been approved in her seven years; vinyl has been allowed on side and rear elevations. The Walker Shoe tax credit project used wood or clad wood.
- Grids between panes disfavored on the front; applied exterior grids preferred.
Decision
- Harding Street elevation: no-grid aluminum or aluminum-clad wood.
- Side windows: vinyl, aluminum-clad wood or aluminum.
- Rear block openings: six-over-one vinyl with grids between the glass.
- Approved 6-0. The owner said he was in a hurry (6 to 8 weeks to order, winter coming).
Discussion time
About 30 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-08-06 - Historical Commission | 30 |
Log
- 2026-08-06 - Historical Commission - Hearing; compromise on window materials; waiver approved 6-0.