  • The meeting was called to order with a quorum; the Vice Chair participated remotely. There was no general public comment. The captions begin at the call to order and have a gap of about 12 minutes from roughly 2:41 to 2:54.
  • SB 9 SB 450 Permanent Ordinance: staff proposed making permanent the interim ordinance implementing state housing laws SB 9 and SB 450, with changes drawn from applicant feedback: place objective design standards ahead of individual review, clarify accessory dwelling units with urban lot splits, relax or remove certain driveway, garage, roof, eave, stucco and window standards, and allow modest rear balconies. Commissioners supported raising the upper-story floor-area allowance from 35 to 40 percent, flagged a 22-versus-23 foot roof height inconsistency, and suggested "up to 20 feet" language for garage doors. The Commission recommended the ordinance with revisions, 6-0, and asked Council to consider objective design standards for Professorville.
  • South Palo Alto Bike Ped Connectivity: staff presented the El Dorado Avenue crossing alternatives Council had asked to study, A1 at about $72 million (tunnel under Caltrain, signalized Alma Street crossing) and A2 at about $87 million (full grade separation under both, requiring acquisition of two properties with four dwelling units), and a roughly $460,000 Measure B grant for planning. Speakers from the El Dorado neighborhood opposed both, citing narrow streets, emergency access, parking and acquisitions, and said a petition had over 300 signatures for a Loma Verde hybrid; other speakers supported a new crossing, calling the California Avenue tunnel substandard. Commissioners found El Dorado too constrained. On a motion by a commissioner, the Commission recommended 6-0 that Council hold A1 and A2 until conceptual designs of equal depth are done for Loma Verde Options B and C, the community hybrid and an overcrossing at the location staff finds most beneficial with least private impact.
  • Bryant Street Bike Boulevard Lincoln Avenue Traffic Calming: staff said Bryant carries about 2,100 vehicles a day, up about 35 percent since 2015, with an 85th-percentile speed of 28 mph, against a bike-boulevard target under 1,000 vehicles and 15-20 mph. Proposed measures include traffic circles at Kingsley and at Bryant and Lincoln, an upgraded Addison circle, curb extensions at Homer and Channing and a pilot ban on the eastbound Embarcadero left turn onto Bryant. Speakers strongly supported the project. One commissioner who lives nearby left before the vote, and the Commission voted 5-0 to advance the staff package, phased to start with the Bryant and Lincoln circle and the Embarcadero pilot, and to study the gap between curb extensions and sidewalks.
  • Staff also reported that on September 28 Council unanimously directed that the Caltrain Grade Separation alternatives advance from 15 to 35 percent design.

Agenda

Municipal Code amendment recommendation; South Palo Alto Bike/Ped Connectivity preferred design alternatives; Bryant Street Bike Boulevard and Lincoln Avenue traffic calming initial design.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

16:20Everyone like to call to order this

16:22regular meeting of the Planning and

16:23Transportation Commission for September

16:2630th, 2026. Mr. Tber, could you please

16:29take the role?

16:30>> Yes. Uh, Chair Chang,

16:31>> here. Uh, Vice Chair G here.

16:35Um, Commissioner Aken,

16:42>> we have a technical difficulty, so let's

16:44hang on for

16:44>> here with a non- workinging mic.

16:46>> Yes. Um, Commissioner Hecman

16:48>> here with a working mic.

16:50>> Yeah. Uh, Commissioner James,

16:52>> uh, here.

16:52>> Commissioner Tleton

16:54>> here.

16:54>> And then I did want to note, uh, I

16:56believe, uh, Vice Chair G will have to

16:58make a brief announcement.

17:00>> Yeah. Um I am participating remotely

17:05for the fourth time this year and I have

17:07no other adults in the room with me.

17:10>> Uh and chair we have quorum.

17:12>> Great. Thank you. Okay. Do we have any

17:15agenda changes, additions, and

17:17deletions? Assistant Director Armor?

17:19>> No, we do not.

17:21>> Wonderful. Okay. So, now is the time for

17:24in-person public comment on items that

17:27are not on the agenda. Do we have any

17:29raised hands or speaker cards?

17:33>> Uh to the chair, I have not received any

17:35comment cards for general public

17:36comment. If there's any members of the

17:38public that would like to speak to this

17:39item, uh please submit a card. Any

17:41members on Zoom, uh please raise your

17:43hand.

17:45>> We do not.

17:46>> Okay, great. Assistant Director Armor,

17:48could you start us off with the city

17:50official reports?

17:52>> Yes, absolutely. And and good evening.

17:54Welcome everyone. Um, I'll get us

17:57started. Just uh look ahead to future

18:01planning and transportation commission

18:02meetings on our next slide here. So,

18:05your next scheduled meeting is October

18:0814th. We have scheduled two items. A

18:11discussion of parking programs update

18:13and downtown parking modernization

18:15initiatives as well as consideration of

18:19a use permit amendment for the Peloalto

18:22Museum at 300 Homer Avenue. on October

18:2628th. We are currently scheduled to have

18:28two items, a discussion of the Corey

18:30Road Transit Connection and the a zoning

18:35text amendment that affects the property

18:37at 51 and Cena in regards to historic um

18:41transfer development rights and

18:43expansion. Also, please note that as an

18:46attachment B to the director's report in

18:49your packet, we did include a list of

18:52the expected dates for your meetings in

18:542027. So, as usual, for the remainder

18:58meetings of of this year and those for

19:00next year, if you are already aware of

19:03travel plans, for example, let staff

19:05know um so that we can be prepared and

19:09um avoid quorum issues at future

19:12meetings. Um, also thank you to those

19:14who have responded already to the

19:17question about a potential special

19:18meeting. We want to make sure that we do

19:20have the capacity as we approach the end

19:22of the year in case we need another

19:24meeting. As usual, we won't have a

19:26special meeting if we don't need it. But

19:28if there's something that's um is time

19:31sensitive, we want to make sure we keep

19:33things moving forward.

19:35And then on the next slide here, we have

19:39council dates either items that have

19:41recently occurred. So on September 9th,

19:44while we were having our most recent PTC

19:46meeting, the council had a special

19:49meeting. They initiated a discussion of

19:52the resoning at 470 Olive Avenue, but uh

19:56continued that for further discussion. I

19:59believe that is scheduled for 10:19 at

20:02this time. And the second reading of the

20:05ADU ordinance was also on consent that

20:08evening. there were some questions and

20:10concerns and so that was pulled from

20:12consent and is currently scheduled to be

20:15discussed um at on October 26th. We will

20:19combine that with a discussion of your

20:21recommendation from that same night

20:23about the potential separate sale of

20:25ADUs. So, uh, bringing that together for

20:28a discussion for council on September

20:3114th, the city council approved the

20:34parking garage at 375 Hamilton Avenue.

20:39And then upcoming on Monday, October

20:425th, the city council is scheduled to

20:45discuss the work plans um as proposed by

20:48four of the commissions and boards and

20:52um will be appointing the new

20:55commissioner for our one vacant seat. Uh

20:57I believe they are actually doing the

20:59interviews right now as we are here in

21:01our meeting. So, um, working to move

21:05forward that so that we'll have a

21:06complete set of seven commissioners. Uh,

21:09and there is no meeting scheduled on

21:12October 12th as that is a city holiday.

21:15With that completes my presentation, but

21:18we do have um Aussie Ors here to speak

21:22on behalf of transportation and give

21:23some updates. Thank you.

21:26>> Thank you, Assistant Director Armor. Uh,

21:28good evening, Chair Chang and

21:30Commissioners. My name is Aussie Ersi,

21:32senior transportation planner uh with

21:34the office of transportation updates for

21:36September 30th, 2026.

21:39Starting uh with project updates. Next

21:42slide, please. Uh for the rail grade

21:44separation project on August 25th and

21:4626, the office hosted two community

21:48meetings at Mitchell Park for the

21:50Charleston Meadow and Church Churchill

21:53grade separation projects. Both meetings

21:55were well attended and team received

21:57valuable feedback on the 15% design. On

22:01September 8th, the rail committee

22:02reviewed the 15% plans and recommended

22:04council advance the plans. And finally,

22:07on September 28th, uh just this past

22:10Monday, uh council reviewed the 15%

22:13plans and unanimously directed staff to

22:16advance the current alternatives to 35%

22:19design. Next slide, please.

22:23Rodeo season is here. A flagship program

22:25for the city's office of transportation.

22:27In midepptember through late October,

22:29the city's safe routes to school program

22:31is bringing second grade pedestrian

22:33safety excursions and third grade bike

22:36rodeos to all 12 elementary schools in

22:38Palo Alto. Thank you to all parent

22:41volunteers, teachers, secretaries,

22:43school PTAs for promoting these

22:45opportunities and encouraging so many

22:47people to volunteer.

22:49We encourage parents and students with

22:51this new school year to visit the city's

22:53safe routes to school web page for

22:55suggested walk and roll maps to your

22:58school. And I believe the link is on the

23:01slide.

23:03Next slide, please. Uh and for other

23:05transportation items, uh parking and an

23:07upcoming community event announcement.

23:10Um for parking, we are thrilled to share

23:13that our city's four new automated

23:15parking guidance systems are getting

23:17ready to go live. very soon at downtown

23:20garages, Alma South, Civic Center,

23:23Copper and Webster, and Bryant and

23:25Linton garages.

23:27If you've been near the garages lately,

23:29you've you've spotted testing underway

23:31and the hardware is fully installed, and

23:34we are currently working through

23:35software configurations.

23:37When drivers arrive, uh exterior matrix

23:40signs will display floor byfloor counts

23:43and total available uh public versus

23:46permit parking at a glance. And once

23:48you're inside, you may have seen this in

23:50other garages, but the interior IO

23:52lights make finding a spot effortless

23:54with green for open, yellow for permit,

23:56and red for occupied.

23:59Uh staff is teaming up with our vendor

24:01to build a data dashboard uh tracking

24:03occupancy trends, and we look forward to

24:05sharing our initial data with the

24:07commission at a future update. And

24:09finally, a quick announcement that we

24:11have bike paloto coming this Sunday,

24:13October 4th, at Fair Meadow School. This

24:15is a community organized event designed

24:18for riders of all ages and abilities to

24:20discover how easy and enjoyable

24:22enjoyable it is to get around town on

24:24two wheels. There are guided maps

24:26available on bikepalto.org's

24:29website and participants are encouraged

24:31to explore many of the Palo Alto parks

24:33and open spaces. Uh Fair Meadow will be

24:36the main hub and there will be fun

24:38interactive booths and activities

24:40throughout the day. So, we encourage the

24:42community uh to join us uh and we want

24:44to see a great turnout for that event.

24:46And I believe that concludes my updates.

24:49Happy to answer any questions. Thank

24:51you.

24:54>> Does anybody have any questions for

24:55staff?

24:58>> U Commissioner Aken,

25:01>> this is for AD Armor. Uh so I'm liazison

25:04to council in October. uh and I have

25:07scheduling constraints, meaning I will

25:09generally not be available after 10:00.

25:12So, uh I don't have a backup.

25:15Uh how should we handle that?

25:18>> We can work through the chair to

25:20designate a backup um if needed for

25:23those. Thank you for letting us know.

25:26>> Thank you.

25:28>> Thanks for bringing that up. Uh okay, no

25:32other questions, comments. All right.

25:34So, we're going to do our first action

25:36item tonight, which is a recommendation

25:38on an ordinance amending various Palo

25:40Alto Municipal Code chapters in Title

25:4316, Title 18, and Title 21. Um, to

25:48replace temporary ordinances

25:49implementing Senate Bill 9 and Senate

25:52Bill 450, and other state housing laws.

25:56Uh, so let's start with a staff

25:57presentation, please.

26:05Good evening. My name is Emily Kalis.

26:07I'm a senior planner in planning and

26:09development services. Next slide.

26:16The ordinance that you are reviewing

26:19tonight is the permanent ordinance um

26:22for an interim ordinance that has been

26:24in place since January 13th, 2025.

26:28The city council adopted interim

26:30ordinance 5645 amending the PaloAlto

26:33municipal code title 1618 and 21 to

26:37implement SB 450 and other state laws

26:41and also as a part of that ordinance

26:44adopted an objective design standard

26:46process to ministerially review twotory

26:49houses. Um that interim ordinance was uh

26:53initially valid for one year but then in

26:56January of this year it was extended

26:57until December 31st.

27:04As a part of um our year and a half of

27:09implementing that ordinance, we

27:11conducted a survey asking both

27:14applicants of individual review uh

27:17single family home applications and

27:20objective design standards projects

27:22which includes um SB9 applications for

27:26feedback on their experience with um the

27:29ordinance. And so the uh survey was sent

27:33to anyone who had applied um and was

27:36listed as the primary applicant in

27:38Asella um within the last two years. Uh

27:42the feedback we received included

27:44support for increased visibility and

27:46awareness of the ODS process and um

27:51supported uh that because the ODS

27:55process is a ministerial review um it

27:58does not have neighbor input. Um and so

28:02as a part of individual review um

28:04neighbors can provide feedback. It is a

28:08subjective process. So there can be

28:10variation from um project to project and

28:14the contextual um neighborhood and other

28:18um items are taken into consideration.

28:21Whereas in the ministerial process

28:24because it is objective and because

28:25every project will be treated um the

28:28same. It um does not have the

28:31opportunity for neighbors to appeal the

28:35decision. However, it also creates

28:37certainty for the applicant and the

28:39neighbors that the same criteria is

28:42being applied to all projects.

28:45Uh the applicant survey also provided

28:48feedback for asking for clarification of

28:51the applicability of the ODS. It is

28:54applicable to any uh new twostory home

28:58or second story edition regardless of if

29:01it is an SP9 project or not. um requests

29:04for illustrations to the objective

29:07design standards. This would be

29:08consistent with um documents that we

29:11have both for the multiple family

29:13objective design standards, individual

29:15review guidelines and uh zoning

29:18technical manual for the R1 zoning

29:20district. Additionally, some specific

29:23changes to individual standards have

29:25been difficult to interpret, comply

29:27with, or um disincentivize the use of

29:31the objective design standards. And so,

29:33um, some of that feedback has been

29:35incorporated into our recommended

29:37changes to the ODS.

29:39Next slide.

29:42>> As stated, this proposed ordinance

29:44incorporates the survey feedback. It

29:46will clarify the process, the ODS

29:49process for twotory houses, make minor

29:51changes to the standards themselves, and

29:54also make permanent other regulations

29:57from ordinance um 5645. the ones that

30:00are unchanged or ones that were, you

30:02know, um, state law requires this that

30:06were just kind of pulled into um,

30:08definition sections and things like

30:09that.

30:15Currently, any two-story home

30:16application may choose to meet the

30:18objective design standards or apply for

30:21individual review. This is um really

30:24what SB450 is about was creating this u

30:28ministerial process. And so um however

30:33currently the zoning code um explains

30:37what individual review is the criteria

30:39how to apply for that and then second to

30:42that says or you can do the objective

30:44design standards. Uh what this is

30:46putting forward is listing the objective

30:48design standards option as the first

30:50option and explaining if you choose not

30:52to meet those standards then you would

30:54go through individual review. Um it also

30:57updates references in other code

30:59sections. Um the IR process is primarily

31:02in chapter 18.12. Um but chapter 1810

31:06and 1813 also include references that um

31:09would need to be updated for

31:11consistency.

31:12Uh the other major change is that this

31:15would add the objective design standards

31:17directly to the code as a development

31:19standard. Um currently it is a separate

31:22document and it can be unclear that both

31:25the 1812 development standards and the

31:28objective design standards apply to uh

31:31these projects.

31:33Another minor change is clarifying for

31:36SB9 projects how ADUs may be used in

31:38combination. There's no change to um

31:43what is allowed but it clarifies um how

31:46and when ADUs are allowed.

31:50>> Next slide.

31:54The changes proposed to the objective

31:56design standards and the urban lots

31:58split standards which are also objective

32:01standards particular to lot splits under

32:04SB9 would streamline review for

32:06applicants and staff. uh remove

32:09redundant and overly restrictive

32:11standards particularly for corner lots

32:13and for oversized lots. It would also

32:16increase usability through uh targeted

32:19changes that I will review in the next

32:21few slides.

32:26Um I thought it would be easiest to go

32:29through the standards that are proposed

32:31to change with um some examples of what

32:34it is shown as on a plan set. Um and so

32:39starting with two standards that would

32:42be proposed to be removed would be um A4

32:47um A5 and A7.

32:50Um

32:52A4 and A7

32:54uh limit the driveway width and garage

32:57width in a manner that essentially

33:01uh limits a project to having a onecar

33:04garage and a one car wide driveway. Um

33:08and so this change would um acknowledge

33:12that that can be overly limiting and

33:15allow for twocar garages

33:18um in locations where they fit. So you

33:23know in some cases um the way that the F

33:28is calculated the garage spaces do count

33:31towards the F. So many applicants do

33:33choose to have a onecar garage for that

33:35reason. Um but this at least gives them

33:37the option to choose. Um in terms of the

33:40screening landscaping, the site plan

33:42shows um that screening landscaping is

33:46required on the interior sides and rear

33:49of the lot. Uh the A5 standard was

33:53separated from the B7 and B8 standards.

33:57So A5 stated that a 2-ft wide planter

34:01strip was required around the perimeter,

34:03but then the details of what went in

34:06that planting strip are in standards B7

34:08and B8. And so this just consolidates it

34:13so that um the screening landscaping

34:16explains what is required and it is

34:18noted that you know your 24 ft box or

34:22your 24in box trees need to be in a

34:2424inch wide uh planter strip.

34:28Next slide.

34:31Uh this shows an example um streetscape

34:34diagram. Again, I included A7 just so

34:37you had an example of what a twocar

34:39garage looks like compared to a onecar

34:42garage. Um, but primarily this slide

34:46would be looking at A11, which is the

34:49changes to roof height for varied roof

34:51pitch and B3 and B4, which is contextual

34:54eve height. So, uh, standard A11 allows

34:59for, um, it limits the maximum height of

35:02the roof relative to the roof pitch. And

35:05so, the intention of this here is that,

35:08um, it tends to be more consistent with

35:11neighborhood development to have lower

35:13roof heights where the roof pitches are

35:16lower. For example, Iller neighborhoods

35:18have very uh, low pitched roofs, and

35:21this takes that into account. and um in

35:25the current standards has a 22 ft height

35:28limit. Um however, some of the feedback

35:30we received was that that in particular

35:33was overly restrictive. We are proposing

35:35to raise it to 23 ft um but keep the

35:38other heights the same uh for the mid

35:41sloped roofs of 25 ft and these steep

35:44sloped roofs of 27 ft.

35:48Uh B3 and B4 also affect how sorry

35:53um how the

35:56roof height is regulated relative to the

35:58neighbors. And so um B3 was for is for

36:03the first story and B4 is for the upper

36:05story stating that the eve height which

36:08is the corners of those roof lines um

36:11must be within a certain distance of the

36:14neighboring two houses on either side.

36:16And so some of the feedback we received

36:19was that you know that can be very

36:20limiting only looking at each house on

36:23either side as opposed to the block in

36:25its wider context. Um additionally we

36:28have A1 which regulates the height

36:31overall as well as um C11 which um

36:36basically either the standard daylight

36:38plane applies or a twoft lower daylight

36:41plane if adjacent to singlestory houses.

36:45And so um those two also help keep the

36:50home in scale with the neighborhood. Um

36:54and so we are proposing to eliminate

36:56standards B3 and B4 um because you know

37:01there are other things regulating the

37:03height. The application of these also

37:05was very unclear for corner lots

37:09um or say other cases where perhaps they

37:12didn't really have an adjacent neighbor.

37:15Next slide.

37:18Another standard we are proposing to

37:21remove from the ODS is um stucco

37:24texture. And so I included an image

37:27here. The standard itself refers to this

37:29technical services information bureau um

37:33document. And so, um,

37:37there are, you know, potentially other

37:40stucco textures that could be

37:42appropriate in PaloAlto and limiting it

37:44to only these two um is overly

37:47restrictive.

37:52>> Next slide. Sorry. Uh, likewise, there

37:55is a standard for window details. Um I

37:59didn't include photos of those in this

38:03particular um set, but it is worth

38:06noting that, you know, when we are

38:07reviewing the plans, we also don't

38:10typically receive photos of the windows

38:12that are going to be chosen. Um a lot of

38:15it is handled through, you know,

38:17architectural details and notes. Um and

38:20so you know this is kind of more um what

38:23we're often reviewing

38:27and similarly the uh details were very

38:31overly prescriptive and limited what

38:34options the homeowners had for um

38:36windows that they could install.

38:40And then a change that may be more

38:43substantial but would be likely to

38:46increase um use of the objective design

38:49standard process is second floor

38:51balconies. So the current um standards

38:55do not allow for rearfacing balconies

38:59which is um something that many uh

39:02individual review applications we review

39:04includes. And so we wanted to create an

39:07option to allow a modestly sized balcony

39:12that would be consistent with the

39:13individual review guidelines. And so,

39:17um, the image shown here with a a

39:21balcony that is well set in from either

39:24side set back as well as the rear

39:26setback and has the 5 and 1/2 uh foot

39:29tall privacy walls on either side uh

39:32would be consistent with what is

39:34currently allowed through individual

39:36review and could be applied in an

39:38objective manner uh through the ODS

39:40process.

39:44And so, uh, staff recommendation is that

39:47the PTC recommend that the city council

39:49adopt the draft ordinance.

39:53Thank you.

39:55>> Thank you very much, Miss Callus. Uh, do

39:58we have any clarifying questions from

40:00the commission

40:02before we take public comment?

40:04No.

40:05>> Oh. Uh, is this a ghost light,

40:07Commissioner?

40:09>> Okay. Sorry.

40:11Uh, okay. with that. Oh, vice chair G

40:14has a question.

40:16>> Thank you, chair. I had a very quick

40:19question. I really appreciate the

40:22compilation of attachment B which is on

40:25packet page 45 which lists basically all

40:30of the uh standards that you've

40:32mentioned. And I also really appreciate

40:35the way in which you've categorized

40:37this. it makes a lot easier for me to

40:38see like A stands for architectural

40:40detail and B stands for second floor

40:43massing etc. So my my question is for

40:47the items in section A for site planning

40:50and architectural detail

40:52are these requirements that already

40:54exist in section A are they already

40:56required for a single family like a

40:59singlestory house or would we be making

41:01these changes such that for a single

41:04family house you would still need to

41:05follow A through A1 through A16 while

41:09for now twotory houses you no longer

41:11need to follow

41:15Currently, all of these standards only

41:17apply to twostory houses. Um, and that

41:22is consistent with how the individual

41:25review guidelines only apply to

41:27two-story houses. Um and so singlestory

41:32houses are required to follow all of the

41:36uh development standards in code section

41:391812040.

41:41And these additional standards for

41:43twostory homes including both section A

41:46and section B um would be included in a

41:51proposed 182045.

41:56>> Okay. um kind of maybe asking a more

41:58detailed like a example. Let's take the

42:02planting strip, right? A5. So for the

42:05planting strip right now, if I were to

42:07build a single like a singlestory house,

42:09would I be required to have a two foot

42:12wide planting strip?

42:16>> You would not. Um and part of the reason

42:19for that is because you would not be

42:20required to have privacy landscaping

42:22between a singlestory house.

42:25Okay, thank you.

42:29>> Any other clarifying questions?

42:32Okay, so then we'll move on to public

42:34comment. Mr. Tber, are there any comment

42:36cards or raised hands online?

42:39>> Uh the chair, I've not received any

42:41public comment cards for this item. If

42:42there's any members on Zoom that would

42:44like to speak to this item, uh please

42:46raise your hand.

42:52And I have no raise hands on Zoom.

42:55>> Okay. Um, Commissioner Templeton said

42:57that she's not sure everybody in the

42:59public knows how to turn in a card. So,

43:02there's a stack of cards behind Mr.

43:03Tivera, and you can grab one of those

43:05cards and fill it out and then bring it

43:06back to Mr. Tivera.

43:08>> All right. Um, so with that, we're going

43:11to bring it back to the commission for

43:13discussion. And how I propose that we go

43:16through this is I'll just kind of go

43:17section by section through the staff

43:19report. And if we all agree with the

43:22staff recommendation, then we won't

43:24discuss that item. And otherwise, we

43:27will kind of take that area and maybe we

43:30can ask all of our specific questions

43:33that relate to that area at that time

43:35when we discuss it. Does that work for

43:37everybody? Uh, Commissioner Templeton.

43:39>> Um, a lot of activity just happened

43:41here. I just want to make sure no public

43:42comments came in.

43:43>> Yeah. And through the chair, uh, the

43:44comment cards submitted are for the next

43:46item.

43:46>> Yeah.

43:47>> Great. Thank you, Commissioner

43:48Templeton. Okay. So the first one um is

43:52on top of packet page 13 where these are

43:56the uh process changes where staff is

43:58proposing that we promote the ODS first

44:02and explain that as an option and then

44:04talk about the IR process. Does anybody

44:06have any objections to that or want to

44:08discuss that?

44:10Okay. So then that will be part of our

44:12recommendation. We will recommend the

44:14staff recommendation there. The second

44:17bucket is objective design standards

44:20changes. And I thought I would look at

44:22the entire bucket of things that staff

44:25suggests be eliminated. So that would be

44:27kind of the bottom twothirds of packet

44:31page 13. Uh so does anybody want to

44:35discuss any of these or have questions

44:36of staff for these? And we've got one

44:38light from Commissioner Aken to start us

44:41off. Ashley, I'm going to postpone

44:43because that light was set before you

44:45proposed the uh reviewed okay

44:48methodology. So, we'll just take that

44:51one off for now.

44:52>> Did you have one because the light's not

44:53working. Okay. So, uh, Commissioner

44:55James,

44:56>> it's just it's very kind of basic

44:58question, but I'm I'm can't tell you how

45:00happy I am to see Stuckco. Like

45:05the the the idea that either my neighbor

45:08or the city had an interest in what kind

45:09of Stuckco finish I would put on my

45:11house is kind of blew my mind. So, but I

45:14guess it goes to the question of I so I

45:16completely agree and applaud uh

45:18eliminating some of these sort of

45:20ownorous um

45:23uh sort of requirements, but I guess

45:25what I'm just curious about is like how

45:28do you how do you draw the line around

45:31what's ownorous? Cuz like some of the

45:32other ones seem like uh a little hard

45:36for me to kind of wrap my mind around

45:37too. But like I I think you I think you

45:39did a good job. I'm just kind of curious

45:41like how how do you decide what what

45:43should be eliminated and what should

45:45still be considered?

45:48>> For a lot of these standards, we do

45:50refer back to the individual review um

45:53guidelines and the houses that we review

45:57through that process. And so through

45:59that um we have an understanding of the

46:03items that kind of do and don't affect

46:06neighborhood character and are

46:09priorities for um neighbors when

46:12individual review projects are being

46:14proposed.

46:17But but I will add that if there are

46:19others that you have seen that that the

46:22planning and transportation commission

46:24wishes to recommend also be removed or

46:27modified um that could be part of the

46:30recommendation.

46:33>> Um so so basically it's like you're

46:35you're kind of not trying to favor um uh

46:39objective design standards over

46:41individual review. You're trying to kind

46:42of match them up a little bit. if I

46:45understood that correctly.

46:46>> I'll jump in on that. I the creation of

46:49the objective standards was based on the

46:52individual review. The choice of which

46:55ones to recommend for removal had to do

46:58with the feedback that we have heard and

47:00kind of the attention that different

47:01things have received over the years. And

47:05so trying to retain some of those

47:08details that we have seen are important

47:11to the community as um these projects

47:14have been reviewed through individual

47:16review um while removing those that that

47:20seem to not have as much of an effect um

47:22to try and simplify. Did I get that?

47:25Yeah.

47:27>> Thank you.

47:29>> Okay. Does anybody have any other

47:30questions or comments regarding these

47:32items that staff is proposing be

47:34eliminated?

47:38Okay. Uh that means that we will go with

47:41the staff recommendation for that bucket

47:42of items as well. Okay. The next area is

47:47on packet page 14 with the italicized

47:49line roof heights. So do we have any

47:53questions

47:54there or comments?

47:59No, please. Commissioner James,

48:01>> I I I think a lot of this is maybe sort

48:03of my inability to kind of uh well, I

48:07see sort of great value in like what

48:09you're doing like streamlining great

48:11more transparency. Love the process, the

48:13feedback from people. So, like I am

48:16really excited about what you're doing.

48:17It makes it easier for everyone uh staff

48:20and and residents who are building. Um I

48:24um I sometimes so I'm I'm I'm completely

48:28in favor of this, but I sometimes kind

48:29of get hung up in the little details of

48:32like why particularly it matters like if

48:35you have a maximum height that you need

48:39different heights for different roof

48:41slopes.

48:42And I'm sure there's a good answer. I

48:44just I just don't know what it is. If

48:48you think about the massing of a

48:52building, right, if it's got a flat

48:54roof, then having a height at 25 ft,

48:59it's going to be a much more substantial

49:02physical presence on the street.

49:04Whereas, if that same overall height

49:08were on a house that was a Victorian

49:11with with tall peaked roofs, the mass of

49:15the walls, the mass of the house is not

49:17going to be as substantial on the

49:19street. And because of that design of

49:22that peaked roof, you want to have the

49:24flexibility to go up higher and still

49:26get normal interior spaces, entry doors,

49:31etc., uh front porches um for that style

49:34of home. So that's why this flexibility

49:37has built been built in to try and have

49:41compatible massing on the street um

49:44while providing the flexibility for

49:46different styles of homes.

49:48>> I get that. So I think the um Yeah. So,

49:52I feel like, you know, this is sort of a

49:54streamline fasttrack process of like

49:56trying to have houses that are mostly

49:58like the other houses on your block. And

50:01I see great value in that. And I guess

50:03there's always a back door that you can

50:04go through individual route review. Um,

50:07I guess it's kind of like where I kind

50:08of trip up is I kind of if you've ever

50:10picked up Architectural Digest, every

50:12house in there is not typical. And so I

50:15kind of I don't want to sort of put the

50:16thumb on the scale and not allow sort of

50:20virtuos virtuous uh

50:23non-typical architecture, but but I

50:26think I'm sort of getting off track here

50:27a little bit, but thank you so much.

50:31>> Uh Commissioner Aken,

50:33>> chair real one this time. Uh on packet

50:37page 23 in the ordinance uh this is

50:4118.12 and045 A8 uh we have the height

50:45limit of 22 ft. Should that be 23?

50:50>> Yes, that should be 23 consistent with

50:52attachment B and consistent with how

50:54it's described in the staff report.

50:56>> Great. or the other uh knits of this

50:59kind that I've already sent you. Um do

51:02we need to review them tonight or do you

51:04have everything you need for those?

51:11>> I I think so little changes like that

51:13are the kinds of things corrections for

51:15consistency that we can go ahead and

51:18just incorporate. Um good.

51:21>> Want to confirm that we do actually have

51:23your list.

51:31Um, one one option uh for discussion

51:35might be the question you had about

51:37historic. Um, wasn't one of the kind of

51:41little details, but we could

51:45>> clear two historic questions, but we

51:48aren't quite there yet. So, correct,

51:50>> we'll check them later.

51:51>> All right. Thank you very much.

51:53Thank you, Commissioner Aken, for the

51:55good catch. Commissioner Tumbleton.

51:58>> Uh, yes. I guess I I guess I just wanted

52:00to give staff an opportunity to respond

52:02to the implicit question in Commissioner

52:05James uh comments. Um,

52:09people who have an innovative

52:11architectural approach can apply for

52:13individual review. Right. We're not

52:14blocking them. Correct. Right. Thank

52:16you.

52:18>> Okay. All right. So it sounds like

52:21there's no objection to the changes

52:23proposed for roof height. So we'll move

52:24on to uh the next area which is garage

52:27location italicides toward the bottom of

52:29pack packet page 14.

52:32Any comments?

52:36All right. No comments. So we're going

52:38to go with that. Next one is garage door

52:40widths at the top of pack page 15. Any

52:43comments?

52:48Mr. Aken

52:49>> minor one just suggesting that perhaps

52:51the language should be up to 20 feet

52:53rather than 20 feet which implies it

52:57might have to be exactly 20 ft.

53:00>> Oh,

53:02that seems like a good suggestion.

53:04Everybody's nodding. So, we're going to

53:06incorporate that as a up to 20 ft

53:10and that will be our recommendation.

53:12Hopefully, somebody can help me keep

53:14track of these modifications. That's the

53:15only one so far that I've flagged. Okay.

53:18And then uh next item is balconies kind

53:22of in the middle of pack page 15.

53:25Do we have questions or comments about

53:27that topic?

53:30All good. All right. We will go with the

53:32staff recommendation now. Moving on to

53:34packet page 16. ADUs with urban lot

53:37splits.

53:42Um, so this is about to per this is a

53:46clarification that just states that ADUs

53:48are allowed on urban lot splits under

53:50late state law. No comments. I don't see

53:52any. Okay. Um, next item is objective

53:56design standards for urban lot split

53:58changes.

54:02I will start with this one. I have a

54:04question about what this means and if uh

54:07Miss Callus could please explain it to

54:10us that would be helpful. What's going

54:12what was Yeah, what it means.

54:16>> Apologies that that was omitted from the

54:19presentation that was an accident. Um

54:22essentially there are three uh approved

54:27layouts for how an urban lot split can

54:29be divided. Um

54:32side by side, you know, if the property

54:35is a rectangle, you cut it in half down

54:37the middle. They both have street

54:38frontage. Uh the second and third is a

54:41flag lot uh with one lot in the front

54:44and one lot in the back. The only

54:46difference is one has a flag pole that

54:49is um

54:51fully divided and deeded to the rear

54:54property so that it has you know 10 or

54:56so feet of frontage on the street

54:58itself. The second is an easement so

55:01there is um a shared uh portion of land

55:06essentially between the two lots or part

55:08of the um first lot which is like

55:11undevelopable to provide access to the

55:13rear lot. Um, as the standards are

55:16currently written, if a property is more

55:19than 200 feet deep, um, they are

55:23required to do the flag lotiguration.

55:26And so this did not take into account

55:28that we have

55:31not a huge number, but certainly many

55:34lots um, that in addition to being 200

55:37ft deep are also quite wide, like 150

55:41200 feet wide. And so requiring them to

55:44do a front and back configuration when

55:47um down the middle makes more sense. We

55:49would like to create that option.

55:52>> Um and then um kind of as a part of

55:55that, there's also a standard that

55:58requires a shared driveway between the

56:01two lots. And so again, initially when

56:04we were thinking about a 60 foot wide

56:07lot being divided, um that would be

56:11helpful, potentially necessary, but

56:14since it isn't necessary for all, um

56:18possible lots that are divided, we want

56:20to create an option for lots that do

56:22have sufficient frontage to accommodate

56:25um one driveway per lot as that option.

56:28And so it would rely on existing codes

56:31in other sections that have minimum

56:33distance between allowable driveways and

56:35that sort of thing um that don't need to

56:38be included in this ordinance because

56:40they are in other sections of the code.

56:42>> Okay. Thank you so much for that

56:44explanation. It's very helpful and seems

56:45to make sense to me. Does anybody else

56:47have any questions or comments? Okay,

56:49great. So then that moves us on to um

56:52standards which are not changed. So

56:54really, I'm asking the commission if

56:56there's anything else that we think

56:58should be changed or comments about

56:59that. And we've got one from

57:00Commissioner Hecman.

57:07>> Um so actually I've got a few of these,

57:10but um in this round to keep this flow,

57:13I just want to talk about the one that

57:14staff has highlighted in the staff

57:16report, which is the 35 or or 40% issue.

57:19Um um in a after we go through this I

57:22would like I've got a few things in the

57:25ordinance which I think are things that

57:27are not changing that I want to get

57:30clarification of or possibly suggest a

57:32change. So but for this um I just um

57:36want to register support for the um uh

57:41idea of increasing this to 40%. Um I

57:45happen to live on a standard 6,000 foot

57:48lot. Um, our house is just under 2,000

57:50square ft. And we have on our um second,

57:54it's a two-story. Uh, the second story

57:57was added in two parts by the prior

57:59owner in the 80s. And we have a master

58:02bedroom with an interior master bath and

58:06closet and then uh two bedrooms with a u

58:11between them um a second bathroom

58:13upstairs. And I think that that that is

58:16a highly desirable arrangement. You

58:18know, our our kids grew up all able to

58:20be up on the upper level with us without

58:24us all having to share one bathroom. And

58:26as I, you know, read the the

58:28descriptions of, you know, typical

58:30square footage for these sorts of

58:32things. I would be concerned that we

58:34might limit somebody building a

58:35two-story to that kind of configuration

58:38where the option was to put kids

58:40downstairs or have them in a cubby

58:44bedroom upstairs and not have two

58:46bathrooms. So, um, uh, for me, that's

58:49why I like the flexibility of, uh, going

58:53to the 40% to make sure that that that

58:56doesn't unintentionally happen, uh, in

58:58these designs that can be up to 2550 ft.

59:06>> I was going to say the same, but less

59:07eloquently.

59:08>> Oh, wonderful. And then I think we've

59:10got uh, Commissioner Aken.

59:13>> Yeah. Um, so, uh, seeing this, I

59:17immediately went out at measured

59:20to see what our, uh, bedroom sizes were,

59:23and we meet the, uh, 35%

59:27uh, standard fairly comfortably within

59:29the estimates that staff made. However,

59:32what's missing is passage space. Um, so

59:36while uh I think 35% is probably

59:39sufficient for the rooms themselves, I

59:41have no objection if we want to raise to

59:4340 in order to deal with some of the

59:46ancillary spaces you might need.

59:50>> That makes sense to me. I'm I have no

59:52objection. So, does anybody any

59:55commissioner have an objection? And then

59:56we'll just incorporate this into our

59:59rolled up motion.

1:00:01Nobody has an objection. So I think what

1:00:03we're proposing here is that we would

1:00:06the PTC would recommend a shift to 40%.

1:00:09Correct? Okay. Great.

1:00:13Okay. Um and then I don't think there's

1:00:16anything to discuss for housing element

1:00:18consistency. So then that takes us on to

1:00:20modifications for for historic at the

1:00:23top of packet page 18. And I know that

1:00:26Commissioner Aken has something for that

1:00:27one. So let's start with him.

1:00:30>> Yeah, a couple of things. Uh first was a

1:00:33clarification. Um in the uh draft

1:00:36ordinance on back at page 34, it

1:00:39discusses urban lot splits located

1:00:41within an historic district. And I have

1:00:45a question as to whether that applies to

1:00:46any lot in a district or only to the

1:00:49lots of contributors.

1:00:55>> Where is this?

1:00:5834F

1:01:00>> subpart F13.

1:01:03>> Correct.

1:01:11>> Yes. So, um that language is taken

1:01:14directly from Senate Bill 9. Um and so

1:01:18it is my understanding that it is any

1:01:20home in the district as opposed to um

1:01:23being limited to contributing

1:01:24structures. Um, but it would, yeah,

1:01:29remain in the ordinance as written by

1:01:31the state.

1:01:34>> Okay. There probably some interesting

1:01:35trade-offs there, but I don't think I'm

1:01:38able to evaluate them tonight. Um, I'll

1:01:41go ahead and throw in my other historic

1:01:44U issues comment um, which is in

1:01:48response to the question posed on packet

1:01:50page 18. Uh, so 12 years ago I was

1:01:53serving on the Professorville design

1:01:55guidelines committee. Um, and I argued

1:01:58for objective standards for

1:01:59Professorville back then, but I was

1:02:02overruled. Um, so I would suggest that

1:02:06we recommend uh that more objective

1:02:09standards be developed. Uh, though I

1:02:12expect it'll probably be a low priority

1:02:15project. So, um let's just make sure

1:02:18that uh if there's agreement that that

1:02:21request is documented.

1:02:23>> Okay.

1:02:24>> Uh Commissioner Hackman,

1:02:27>> I I I think I feel the same on this as

1:02:29Commissioner Aken. Um recognizing that

1:02:32the um we're not I I take it from the

1:02:37way staff has posed this in the staff

1:02:39report that we're really talking about a

1:02:41specialized set of design guidelines uh

1:02:44objective standards that take into

1:02:46account the historic nature of these

1:02:47structures and so I do think it's likely

1:02:49a low priority. Uh I do think that uh

1:02:52ultimately um we should be able to

1:02:54achieve it and and uh I think the

1:02:58benefit is we'll have a streamlined

1:03:00process that because of these specially

1:03:03tailored objective standards will

1:03:06address sort of the typical concerns we

1:03:10might hear from neighbors uh applying

1:03:13the more subjective standards. So I like

1:03:15the idea of moving that recommendation

1:03:17to council. Um, does any commissioner

1:03:20object to moving that recommendation?

1:03:23All right. So, I'm going to include that

1:03:25also in our recommendations.

1:03:28>> May I follow up just a second?

1:03:30>> Yes, please.

1:03:31>> Uh, yeah. The uh one of the

1:03:33characteristics of Professor Hill is

1:03:35that it is um a salad of different uh

1:03:40building sizes, architectural types, and

1:03:43historical significances. So that's why

1:03:47it's interesting to try and uh come up

1:03:49with some objective standards rather

1:03:51than making it as entirely subjective as

1:03:54it is today.

1:03:57>> Thank you for that additional detail,

1:03:58Commissioner Aken. All right, so that

1:04:00takes us to other changes and I think

1:04:02this is when maybe Commissioner Hecman

1:04:04had some other ideas. So, let's discuss

1:04:05those and we'll start with his ideas and

1:04:08then if any of us

1:04:09>> Oh, if Yeah, if I may through the chair.

1:04:12Um, we've got a hand up on Zoom.

1:04:15>> Yes, Councelor Yang.

1:04:18>> Thank you. Sorry. I just wanted to

1:04:20clarify uh in response to Commissioner

1:04:22Aken's question about the historic

1:04:25district, if it's anything in the

1:04:27district or only contributing

1:04:28structures. um that language that you uh

1:04:33pointed out on packet page 34 is

1:04:35actually outdated and um there is a more

1:04:41narrow uh exception now in the state

1:04:43law. Um basically it has to be either a

1:04:48contributing structure uh or you are um

1:04:53demolishing exterior walls. Um

1:05:00that yeah, it's got to be a contributing

1:05:02structure or or listed individually.

1:05:06>> All right. Thank you. Um so does that

1:05:08mean then that before this moves to

1:05:10council, staff will update that section

1:05:13with the new newly updated changes to

1:05:16state law?

1:05:17>> That's right. Yeah, we'll make that

1:05:18correction.

1:05:19>> Perfect. Thank you. All right. Now on to

1:05:22the additional items that Commissioner

1:05:24Hecman had wanted to discuss.

1:05:28>> Uh thank you. So I think probably front

1:05:30to back in the ordinance is the most

1:05:32logical way uh to go through this. And

1:05:36so um I think all of uh well my comments

1:05:39are going to start in section four uh

1:05:41which is on packet page 22. And as I go

1:05:44through, I will just sort uh we've

1:05:46already had a few comments to the

1:05:48ordinance and I've located the correct

1:05:50places. So I'll just flag that reference

1:05:53for ease of staff uh going forward. So

1:05:56on packet page 22, the concept of up to

1:06:0020 ft rather than 20 just just 20 ft is

1:06:03going to be found at uh uh 1812045A

1:06:07subp part 4 just below the bottom uh

1:06:10just below just above the bottom of the

1:06:12page.

1:06:13Um and then moving on to uh 23

1:06:17packet page 23 in subp part 8 is the

1:06:21change commissioner Aken mentioned uh

1:06:23should be 23 instead of 22.

1:06:26Um then I get to my first question which

1:06:29is in uh subp part 11

1:06:32um we're talking about um

1:06:35uh windows with minimum dimensions of 3

1:06:39feet and I just I was trying to

1:06:40understand what does that mean? Does

1:06:42that mean it has to be 3 feet by 3 feet?

1:06:46Um or just one dimension has to be three

1:06:49feet.

1:06:51So uh I'm I'm personally curious and

1:06:54then um maybe we could change that

1:06:56language to make it clear.

1:07:02>> Yes. The intent is for um a window that

1:07:06is a minimum of 20 square feet with a

1:07:10minimum dimension in

1:07:13one of the um

1:07:16>> in either direction.

1:07:17>> In in either direction, but I don't want

1:07:18to like measure it diagonally like a

1:07:20screen

1:07:23>> vertical or horizontal.

1:07:25>> Yeah.

1:07:27So, I could do 3 feet by seven feet.

1:07:31>> Could I do 2 feet by 10 feet because I

1:07:34still have one dimension that's at least

1:07:36three feet?

1:07:37>> No. One the smallest dimension would

1:07:40need to be at least 3 feet.

1:07:42>> Okay. So, you may want to maybe this is

1:07:45in practice not an issue because nobody

1:07:48wants a 2x10 window. Um but you might

1:07:51consider um putting the word each or or

1:07:55some other change. Um moving on in the

1:07:59in subp part B the second floor massing

1:08:03uh the uh subp part two uh this is where

1:08:06I think we have consensus of the

1:08:08commission to go to the 40% rather than

1:08:1135 figure. Um and then a question I have

1:08:15regarding uh subp part three um uh

1:08:20height of a roof over attached garage

1:08:23not exceeding 15 ft. So uh in my house

1:08:26our master bedroom is built directly on

1:08:29top of the garage. And so in our house

1:08:32the roof above the garage is probably 22

1:08:35or 23 feet tall. So, what I'm wondering

1:08:37is, does this mean you can't have a

1:08:41bedroom above a a garage?

1:08:50The intent is to limit the onestory

1:08:55height of a garage. Um, and typically

1:08:59with things like the daylight plane, um,

1:09:03and the position of a garage typically

1:09:05being on the edge of a house, we do more

1:09:10frequently see, um, that the garage has

1:09:12a one-story form um, as opposed to a

1:09:16part of the house over it. Um, so we

1:09:19will definitely take a look at that

1:09:21because limiting that is not necessarily

1:09:23the intention there.

1:09:24>> Okay. Thank you.

1:09:27Uh let's see uh now packet page 24

1:09:30middle of the page subp part seven

1:09:34um

1:09:36uh where privacy landscaping is required

1:09:38and there's a an easement like a public

1:09:41utility easement on along an interior

1:09:43lot line you you plant basically between

1:09:48the easement and the building correct so

1:09:51I first wanted to ask is an interior lot

1:09:54line those

1:09:55side or rear. Is that right?

1:09:58>> Yes, that's correct.

1:09:58>> Okay. So, my house

1:10:01u again standard 60 by 100 lot and I

1:10:04think the back 5 ft of our lot is a is a

1:10:09power line easement to the PaloAlto

1:10:11utilities as I think is directly across

1:10:14our back fence. The neighbor has a 5T.

1:10:17So, what this says to me is and

1:10:20incidentally um I have lovely lush

1:10:23landscaping back there that blocks the

1:10:26visibility between my neighbor and I to

1:10:28both of our benefits. And every couple

1:10:31of years, the PaloAlto utilities comes

1:10:33by and trims whatever they need to uh to

1:10:37keep them off the lines. And it it it

1:10:39works great. But when I read this, what

1:10:41it tells me is I if I were to tear down

1:10:43and rebuild, I would have to essentially

1:10:45create a no man's land back there, my

1:10:48back five feet, as would my neighbor

1:10:50behind me. And so we would have like my

1:10:53privacy five feet in from my property

1:10:56line cutting our already um narrow

1:11:00backyard making it more narrower as

1:11:03would my neighbor. And so we'd have

1:11:05privacy 5t of dirt fence 5t of dirt

1:11:10um their privacy u landscaping. I I

1:11:15um I don't think that's likely the

1:11:18intent here to create that. And so I'd

1:11:20ask staff, and again, I think this is

1:11:23probably existing language that's just

1:11:25been transported. Um, but I'd ask staff

1:11:28to look at that and and uh consider

1:11:31whether that's really what we want.

1:11:34>> Um,

1:11:36the utilities department will not allow

1:11:39new landscaping to be planted in an

1:11:42easement. And so there are, you know,

1:11:44many many examples where there is

1:11:46existing landscaping that does get um

1:11:49trimmed when work is required, but they

1:11:50will not allow new landscaping to go in.

1:11:53And um I'm not 100% sure, but I think if

1:11:56you're doing a new house, they might

1:11:58also require it to be removed. And so

1:12:00the intent of this standard is to make

1:12:04sure that those properties are not

1:12:06exempt from providing privacy

1:12:08landscaping um between the two homes. Um

1:12:12but something we could consider is

1:12:15clarifying

1:12:17um where we discuss in B7 that um

1:12:22existing trees can be retained um that

1:12:27discusses you know across lot lines.

1:12:32um

1:12:35kind of looking at how maybe something

1:12:37in there can reflect. Um yeah, and I

1:12:42would add to that that in addition if

1:12:44something is existing in that as you

1:12:47said it gets trimmed and therefore might

1:12:49not be providing the privacy that was

1:12:51intended um by you know planting uh

1:12:55trees in that area to be tall to to

1:12:57screen between windows for example.

1:13:00However,

1:13:01if the commission would like to

1:13:03recommend removal of this, it could be

1:13:05done. That could be included as part of

1:13:08your recommendation. Okay. I

1:13:14I don't want to cut the utilities

1:13:17commission out of this discussion, but I

1:13:19I do have serious concerns when when I

1:13:23hear that that the utilities group

1:13:26doesn't want anything done in the back

1:13:28fivet of potentially my house because to

1:13:32me that feels like a taking if I if I

1:13:34can't use it, right? I I mean basically

1:13:37if I want I have to I'm going to be

1:13:39required to have this privacy screen

1:13:41which is going to really kind of block

1:13:42my ability to get back there and then I

1:13:46and I can't use it uh because I the only

1:13:48thing I could do is plant it. I suppose

1:13:50I could you know put a walkway there but

1:13:53I'd have to walk through my privacy

1:13:54screening to get there. So, I'd like to

1:13:58just take this out uh recommend that

1:14:01this come out and then I'd suggest that

1:14:03there be some internal

1:14:06discussion uh within the departments

1:14:09about

1:14:10how this is really how this really

1:14:13should work.

1:14:18One one option would be just to state

1:14:21that the existence of a pee along a

1:14:25property line does not exempt the the

1:14:28property from requirements of privacy

1:14:30screening. Um because as they do um

1:14:34propose a new home, they would need to

1:14:36comply with with whatever that easement

1:14:39requirement is. The intent here wasn't

1:14:43to say this is where you have to put

1:14:45your screening trees. I mean, that's how

1:14:47we we put it in here to try and clarify,

1:14:50but um

1:14:53if that helps.

1:14:54>> Yeah. And I don't really have

1:14:57an objection to tackling it that way. I

1:14:59do feel like it's kicking the can down

1:15:01the road because the real issue I have

1:15:03here is is there a policy in the city

1:15:07that with new home construction that's

1:15:09twotory so it requires a privacy screen

1:15:12if there's an easement which there is in

1:15:14very many occasions um you can't use

1:15:17that land you effectively can't use that

1:15:19land because it's on the wrong side of

1:15:20your privacy screen. Yeah, I think

1:15:22Commissioner Hecman is raising an

1:15:24objection to the utilities policy more

1:15:28than um the privacy screening per se.

1:15:31So, it's just something that um like we

1:15:35hadn't been aware of before and it may

1:15:38have this strange effect of creating a

1:15:4210-ft wide no man's land um that's

1:15:45unusable for property that or

1:15:48practically unusable for property owners

1:15:51on either side of it

1:15:54all over the city.

1:15:55So I I do think the assistant director's

1:15:59suggestion is kind of an eloquent way to

1:16:02kick it down the road a little bit. Let

1:16:04us move the recommendation forward. And

1:16:06again, I would just encourage there be

1:16:08some departmental discussions um and

1:16:10investigation about whether because I I

1:16:14you know I haven't heard anybody

1:16:16complaining about this that that I had

1:16:19to have a 5-ft no man's land in the back

1:16:21of my yard. So, so I'd like and and so

1:16:24maybe it's not really a problem, but it

1:16:27just appears one because we don't have

1:16:28all the answers. So, so I'm going to uh

1:16:32uh u support um Miss Armor's suggestion

1:16:36that that the language be something

1:16:39along the lines of of the existence of a

1:16:42pee does not um uh eliminate the

1:16:46requirement for privacy landscaping. Is

1:16:50that

1:16:51that along the lines of what you were

1:16:53suggesting?

1:16:56>> Yes.

1:16:56>> Okay. Uh let's see. I don't think I I

1:17:00think I have one more.

1:17:06Oh. Um on packet page 34, um I'll just

1:17:10point out that in uh 21.1030 1030

1:17:14subp part F. That's where

1:17:17uh Assistant City Attorney Yang is going

1:17:18to update the language currently listed

1:17:21as historic district.

1:17:23Um on packet page 36 at the top. So this

1:17:28has to do with the U flag lot split uh

1:17:32where we're listing as uh one option the

1:17:35minimum street frontage uh be 10 feet

1:17:37wide per parcel. And my my only question

1:17:41there is whether uh that would

1:17:45essentially equate to a 10 foot wide

1:17:46driveway on a on a flag lot of that

1:17:49configuration. My only question is

1:17:52whether that u dimension will satisfy um

1:17:56uh our fire department. Um because I

1:18:00know in some of the jurisdictions I work

1:18:01um they refer to a minimum driveway size

1:18:04as 12 feet. And so um

1:18:09I know that other sections of the zoning

1:18:12code refer to driveway minimums as 10 ft

1:18:15of clear space um 8 ft of which must be

1:18:17paved. Um

1:18:21okay.

1:18:21>> And I know that for lots that are deeper

1:18:25than 150 ft, there are different buyer

1:18:29access requirements. I don't quite know

1:18:31where those intersect. Um, but it I see

1:18:37what you're I see what you're saying and

1:18:40the fire department would still be

1:18:43reviewing the parcel maps and it may be

1:18:46possible that there could be instances

1:18:49where a 10-ft minimum would not satisfy

1:18:54um access requirements for certain

1:18:56properties, but I don't believe it's

1:18:58universal enough to recommend changing

1:19:01this standard. Well, so but I'm

1:19:02wondering if we could augment the

1:19:03standard to say 10 feet wide per parcel

1:19:06or um wider as necessary to meet fire

1:19:09code.

1:19:12>> Yes.

1:19:13>> Okay.

1:19:17Uh let's see.

1:19:20Uh packet page 37,

1:19:23which is the last one. So I'm sorry this

1:19:27is taking so long. 18. Uh yeah, pack

1:19:30page 37 subp part G. Um so this puts an

1:19:35obligation uh on the director um where

1:19:38the director denies an application, they

1:19:40have to

1:19:42um come back to the applicant

1:19:46uh with a description of how the

1:19:48applicant can remedy the application.

1:19:51And I was just curious,

1:19:54is it possible that there's a scenario

1:19:56where the application can't be remedied

1:19:59and so the director cannot meet his

1:20:01obligation

1:20:02of this uh or of you know of this

1:20:05language and needs to tell the applicant

1:20:09there's no way this can fit.

1:20:14So I don't know that um that might

1:20:16require some coitation and so

1:20:20>> this may be a legal question because

1:20:22that does look like the sort of thing

1:20:23that might have come from state law.

1:20:26>> Mr. Yang,

1:20:27>> that that requirement is taken from the

1:20:30state law. Um, so

1:20:34it is probably possible that there's

1:20:37some strange lot out there where it

1:20:40wouldn't be possible uh to remedy the

1:20:43application. Um, but we'll just have to

1:20:46cross that bridge when we get there.

1:20:48Guess this is the language that we

1:20:50passed.

1:20:50>> Yeah. Well, that it wouldn't be the

1:20:52first time that uh our state legislators

1:20:54were shortsighted uh in their crafting,

1:20:57if you if I use that term loosely, of of

1:21:00statutory language. Okay. So, we're

1:21:02going to leave that one alone. And those

1:21:03are my comments. Thank you.

1:21:06>> Okay. I don't see other lights, so I

1:21:07think we're probably ready for a motion.

1:21:10Uh does somebody want to take a stab at

1:21:12it or I'm happy to, but then I need

1:21:14help.

1:21:17>> Sure. Yeah. So, um

1:21:21uh I will move the staff

1:21:27recommendation

1:21:28with the uh revisions to the draft

1:21:32ordinance uh referenced in my comments

1:21:35just concluded and a um include in the

1:21:40recommendation

1:21:42uh that the

1:21:44get to 15 18. Yeah. Um

1:21:50that the council consider directing

1:21:52staff to develop objective design

1:21:54standards for professorville as a future

1:21:57council objective.

1:22:02>> Second.

1:22:02>> Second.

1:22:03>> Okay. Great. Commissioner Aken second.

1:22:05>> Do you think Oh, sorry. Do do you think

1:22:07we need to add uh additional comments

1:22:10that Commissioner Aken had already

1:22:12emailed as part of the motion or does

1:22:14staff already just have that?

1:22:18I think the corrections are already

1:22:20included is what staff had clarified.

1:22:24>> Okay.

1:22:25>> Yeah, my substantive comments have all

1:22:27been addressed. The rest are typos and

1:22:29clarifications and language. Nothing

1:22:32significant.

1:22:34>> Great. Any further discussion?

1:22:37All right. Mr. Tivera, could you please

1:22:39take the vote?

1:22:40>> Yeah. U Commissioner Aken?

1:22:43>> Yes. Uh Commissioner Templeton?

1:22:45>> Yes. Commissioner Hecman,

1:22:48>> yes. Uh, Commissioner James,

1:22:50>> yes. Vice Chair G,

1:22:52>> yes.

1:22:53>> Chair Chang,

1:22:53>> yes.

1:22:54>> Motion carry 6.

1:22:56>> Wonderful. Uh, and thank you to Miss

1:22:58Callus for a really excellent staff

1:23:00presentation and staff report that

1:23:02helped us take care of all of this.

1:23:04Thank you. All

1:23:07right, with that we move on to our

1:23:11second action item, item number three,

1:23:15which is a discussion of the South

1:23:17Powalto bike ped connectivity review of

1:23:20the preferred design alternatives and

1:23:22network enhancements for the Midtown

1:23:24bicycle and pedestrian undercrossing.

1:23:27So

1:23:29I want to

1:23:31remind people because it looks like we

1:23:33have a lot of interest here tonight and

1:23:36I want to remind people of our

1:23:38procedures. So if somebody in chambers

1:23:41would like to comment later on process

1:23:44for that is to grab a comment card from

1:23:47behind Mr. Chava uh complete it and then

1:23:49give it back to Mr. Java. Um, in

1:23:53addition,

1:23:55uh, it's a reminder that, so we're going

1:23:57to start with the staff report and then

1:24:00if somebody wants to make a public

1:24:02comment, that person should raise their

1:24:05hand on Zoom or turn in their speaker

1:24:07card within 5 minutes of the end of the

1:24:10staff presentation because then we will

1:24:13uh, make a determination at that point

1:24:15based on the number of people interested

1:24:17in speaking on how many minutes to give

1:24:19each speaker.

1:24:21All right. So, let's start with the

1:24:22staff presentation.

1:24:26>> And with that, I will pass it off to our

1:24:28office of transportation staff to give

1:24:30the presentation this evening.

1:24:33>> Thank you. And good evening,

1:24:34commissioners. My name is Charlie

1:24:35Kohl's, senior transportation planner

1:24:37with the office of transportation, also

1:24:39the project manager for the South Palto

1:24:40bike ped connectivity project. I'm

1:24:42joined by Ria Hud Low, our chief

1:24:45transportation official. Sylvia Starlac,

1:24:47our transportation planning manager. Uh

1:24:49we also have two consultants on the line

1:24:51uh part of the project team here to

1:24:53assist with questions.

1:24:56Next slide please.

1:24:59Staff recommend the PTC review the two

1:25:02preferred design alternatives for a new

1:25:03grade separated bicycle and pedestrian

1:25:05uh rail crossing in the vicinity of

1:25:07Elorado Avenue, also known as the

1:25:09Midtown bicycle and pedestrian

1:25:10undercrossing. the planning level

1:25:12assessment of those alternatives, the

1:25:14initial circulation study, and the draft

1:25:16network enhancements to integrate the

1:25:18undercrossing into the surrounding

1:25:19street network. This meeting is intended

1:25:22to obtain PTC feedback on the two

1:25:25alternatives and associated network

1:25:27enhancements prior to the next phase of

1:25:29community engagement and release of a

1:25:30public draft report. And if PTC chooses,

1:25:34staff recommend that the PTC take action

1:25:36to provide a recommendation to council

1:25:38on up to two alternatives to advance to

1:25:4115% design and endorse the accompanying

1:25:44network enhancements for further

1:25:45refinement and presentation with the

1:25:47community for the next phase of

1:25:49community engagement. Next slide,

1:25:51please.

1:25:53Here's the agenda for this evening. I

1:25:55will go through some slides rather

1:25:56quickly uh since most of this

1:25:58information is in your staff pack uh

1:26:00staff report, but I'll spend um extra

1:26:02time on several slides as I think

1:26:04there's some important context to to

1:26:06expand on. But as always, happy to

1:26:08answer any questions when we get to PTC

1:26:10discussion. Next slide, please.

1:26:13Next slide, please. The purpose of the

1:26:16south palletto bike ped connectivity

1:26:18project is to improve bicycle pedestrian

1:26:20access across the rail corridor in the

1:26:21southern portion of the city by

1:26:23identifying a location and locally

1:26:25preferred design concepts for a new

1:26:27grade separated bicycle pedestrian

1:26:29crossing. The current scope of work with

1:26:31the project team as approved by the city

1:26:32council on September 9th 2024 is

1:26:35summarized on this slide.

1:26:37Next slide please.

1:26:40The need for additional grade separated

1:26:42bicycle pedestrian crossings has been

1:26:44identified in several prior city council

1:26:47adopted plans, county plans, and council

1:26:49discussions as a long-standing east west

1:26:52connectivity challenge. The rail

1:26:54corridor and Alma Street create a

1:26:56significant 1.3 mile barrier in low

1:26:58stress walking and biking access across

1:27:02uh the the rail alignment between

1:27:04California Avenue and the undercrossing

1:27:06there and Meadow Drive and the Agrade

1:27:08rail crossing at at Meadow Drive which

1:27:10forces long out of direction detours and

1:27:13exposure to high stress segments such as

1:27:15Oregon Expressway and Meadow Drive.

1:27:17Relevant city and county plans are shown

1:27:19in your screen and discussed further in

1:27:21your staff report. In several council

1:27:24discussions, council members have

1:27:25expressed an urgency and would like to

1:27:27see this project move forward as soon as

1:27:28possible. I will also add that the city

1:27:31council that at the city council meeting

1:27:33on Monday this week, city council

1:27:35members referenced this project and it

1:27:37appears that they may be interested in

1:27:39this project being constructed first

1:27:41before other rail grade separation

1:27:43projects. Next slide, please.

1:27:46Here's the overall study area for the

1:27:48project which which focus on the rail

1:27:51corridor in the southern portion of Palo

1:27:52Alto south of Oregon Expressway. The

1:27:55preferred concepts we are discussing

1:27:56today are in the vicinity of Elorado

1:27:58Avenue which is identified with a blue

1:28:00dot on your screen. I also wanted to

1:28:02note that there are many other ongoing

1:28:04and future projects that are happening

1:28:06in this part of the city. This includes

1:28:08the new housing to be built per the

1:28:09city's adopted housing element update

1:28:11and recently adopted North Ventura

1:28:13Coordinated Area Plan, which would will

1:28:16transition the North Ventura area into a

1:28:18more mixeduse transit oriented

1:28:20neighborhood with more housing. There's

1:28:22also the ongoing San Antonio Road area

1:28:26plan effort, the Coverly Community

1:28:27Center project, rail grade separation

1:28:29projects at Church Hill Meadow in

1:28:31Charleston, and much more. Overall,

1:28:34there's a lot happening and all these

1:28:35things go together. and a bicycle and

1:28:37pedestrian undercrossing in South Pala

1:28:39will support all these other projects in

1:28:41the future by providing traffic relief

1:28:43as well as supporting a robust low

1:28:45stress bicycle and pedestrian network

1:28:47for in town travel in support of the

1:28:49city's mobility and sustainability

1:28:50goals. Next slide, please.

1:28:55Here's the project timeline which shows

1:28:56where we are in the overall study

1:28:58process approved by the city council. In

1:29:00late 2025, the city council directed

1:29:02staff to continue focusing evaluations

1:29:04on two bicycle and pedestrian rail

1:29:06crossing concepts in the vicinity of

1:29:08Elorado Avenue, also called alternatives

1:29:11A1 and A2 with a preference for A2.

1:29:14Alternative A1 was defined as a tunnel

1:29:17with a signalized crossing of Alma

1:29:19Street at Elorado Avenue. And

1:29:21alternative A2 was defined as a tunnel

1:29:23under both Alma Street and the Cal Train

1:29:25tracks in the vicinity of Elorado

1:29:28Avenue. I also want to emphasize that

1:29:31the preliminary concept designs for

1:29:32alternative A1 and A2 are still in a

1:29:35very early planning stage. The city has

1:29:37not made a decision to construct a new

1:29:39bicycle pedestrian undercrossing at

1:29:41Elorado Avenue. We are now in the third

1:29:44phase of community engagement. City

1:29:45council is the final decision maker for

1:29:47this project and will use input from

1:29:49these engagement activities to provide

1:29:50direction on which alternative or

1:29:52alternatives should move forward to 15%

1:29:55design and what network enhancements

1:29:57should be a prioritized modified or

1:29:59adopted or added prior to the release of

1:30:02a public draft report.

1:30:04We expect to complete this round of

1:30:05engagement and present the preferred

1:30:07alternatives and network enhancements

1:30:09for city council consideration in late

1:30:112026 tenatively scheduled for December

1:30:147th 26 meeting.

1:30:17Next slide please.

1:30:21Uh we we presented the site last time.

1:30:23We wanted to include it again because it

1:30:25frames the rest of this discussion and

1:30:27acknowledges that we are still at the

1:30:29very early stages of a high-profile and

1:30:31complex project. There are multiple

1:30:33stakeholders and agencies involved

1:30:35including the city, Cal Train,

1:30:37neighborhood residents, community

1:30:38groups, and potential outside funding

1:30:40partners. There are also many complex

1:30:42engineering, utility, rightway, traffic

1:30:44circulation, and emergency access

1:30:46considerations. And there may be and

1:30:49there are many design trade-offs that

1:30:50will be explored going forward. The goal

1:30:52tonight is not to approve or provide a

1:30:54recommendation

1:30:56on the final project design project

1:30:58design. We are still in the conceptual

1:31:01planning phase. Designs remain very

1:31:03flexible and there's still substantial

1:31:05community engagement and technical

1:31:06design work ahead. What we are looking

1:31:08for is your feedback on the basic design

1:31:10concepts, the refinements that should be

1:31:12studied further and the surrounding

1:31:14network enhancements that should move

1:31:15forward with this project. Next slide,

1:31:17please.

1:31:19I'll now talk about uh community

1:31:21engagement and what we've heard to date

1:31:23through the first two major phases of

1:31:25engagement.

1:31:27Uh phase one shown on your screen uh is

1:31:30an overview. So shown on your screen is

1:31:32an overview of the tools and activities

1:31:33that was used during phase one of

1:31:34community engagement.

1:31:36Phase one of engagement occurred in the

1:31:38spring of 2025. Introduced the project

1:31:40to the community and gain input on the

1:31:42goals, priorities, and opportunities and

1:31:44possible um crossing locations for the

1:31:47great separated bicycle pedestrian

1:31:49crossing. Input and feedback from the

1:31:51community helped establish design

1:31:52priorities and evaluation criteria and

1:31:55informed the development of eight

1:31:56preliminary rail crossing alternatives

1:31:58commissioned by the city for the

1:31:59community uh consideration. Next slide,

1:32:02please. The main takeaway from phase one

1:32:04was strong support for a new crossing to

1:32:07improve connectivity and safety for

1:32:08bicyclists and pedestrians in southern

1:32:10Paloalto. Committee members identified

1:32:13improving mobility as a top design

1:32:15priority, followed by enhancing the user

1:32:17experience and maximizing ease of

1:32:19construction. We also heard that the

1:32:21crossing itself is not enough.

1:32:22Additional infrastructure in the

1:32:24surrounding neighborhoods is needed to

1:32:25create a safer and more connected

1:32:27network for people walking and biking.

1:32:29Next slide, please.

1:32:32Here's an overview of the tools and

1:32:33activities used during phase 2 which

1:32:35occurred in fall of 2025 where the city

1:32:37gathered feedback on the eight

1:32:39preliminary rail crossing alternatives

1:32:41at six different locations in South Palo

1:32:43Alto. The goal of phase 2 was select was

1:32:46to select and advanced two crossing

1:32:48alternatives. Next slide, please.

1:32:52Shown on your screen are the eight

1:32:54preliminary design concepts that were

1:32:56presented to the community during phase

1:32:572. The project team considered over 25

1:33:00potential design alternatives. This

1:33:02looked at bridges and tunnels as part of

1:33:05the initial screening process and those

1:33:0725 and of those 25s, eight were selected

1:33:09based on the project goals and community

1:33:11design priorities informed through

1:33:13public input. Alternative A shown here

1:33:17is the same basic design concept as

1:33:19alternative A1 that we'll be discussing

1:33:21tonight. Alternatives B and C are two

1:33:24concept designs at LMover Verde Avenue.

1:33:26I'll circle back to these designs in my

1:33:28next slide. So, I just wanted to mention

1:33:29that here. And next slide.

1:33:33During phase two, the community showed

1:33:35the most support for the rail crossing

1:33:36concepts located at Elorado Avenue,

1:33:38Lomde Avenue, San Antonio Road, and Fern

1:33:41Avenue. We heard support for the

1:33:43alternatives that minimize impacts to

1:33:44private homes, provide direct routes,

1:33:47reduce long crossing distances, uh

1:33:50reduce long distances between existing

1:33:52crossings, serve higher bicycle and

1:33:54pedestrian demands, and improve user

1:33:56comfort and safety. We also heard

1:33:58specific interest in design refinements,

1:34:00including tunnel height and depth, ramp

1:34:03length, use of the east side of Alma

1:34:05Street, and a desire for full grade

1:34:07separation under Alma Street.

1:34:10Based on community feedback and a

1:34:12recommendation from the rail committee

1:34:13and staff, the city council directed

1:34:15staff on December 1st, 2025 to advance

1:34:17the alternatives in the vicinity of

1:34:19Elorado Avenue, alternatives, which are

1:34:21called alternatives A1 and A2 for

1:34:23further evaluation and a preference for

1:34:26alternative A2.

1:34:28Now, a common question that we've

1:34:30received recently is um uh explain

1:34:34further explanation as to how city

1:34:36council came to the um kind of the

1:34:38conclusion of the focus on Elorado

1:34:40Avenue. And so, if I may, I just wanted

1:34:42to spend a few minutes kind of talking

1:34:43through that because I think it's

1:34:44important uh context and it's it's been

1:34:46quite a while since that conversation.

1:34:49Uh so city council considered various

1:34:51challenges with with all concepts and um

1:34:53the discussion mostly focused on the

1:34:55concepts at Elorado Avenue which is uh

1:34:58referred to as or was referred to as

1:34:59Elorado A alternative A and uh the

1:35:04crossing there were two crossing

1:35:05concepts at Lovery Avenue which were

1:35:07referred to as alternatives B and C.

1:35:10Uh property impacts was a major

1:35:12discussion point as part of that

1:35:14conversation. Alternative A requires a

1:35:16portion of a parking lot in the west

1:35:18side on the west side of the railroad

1:35:20tracks and no residential properties.

1:35:22Both Lomma Verde alternatives u

1:35:25alternatives B and C requires at least

1:35:27two residential properties likely more

1:35:30in the very constrained area on the east

1:35:32side of the railroad tracks.

1:35:35Residential property impacts again was a

1:35:37major consideration and at the time uh

1:35:39city council was not willing to accept

1:35:41property impacts if there was an

1:35:42opportunity. um and there were other

1:35:44options available which is part of the

1:35:47reason why Elorado Avenue rose to um to

1:35:49the top of their list. Elorado Avenue

1:35:52would also serve as a connection uh so

1:35:55uh connectivity uh between nearby

1:35:57destinations between Midtown and the

1:36:00Vure neighborhoods. Uh there was

1:36:02discussion of the MVCAP area which I

1:36:04talked about before and the additional

1:36:06housing that will be going there. Um,

1:36:09also there's a new park in the Ventura

1:36:11neighborhood and the a strong connection

1:36:13to the Stanford reacher research park

1:36:15which is a major employment center in

1:36:17the city of PaloAlto.

1:36:19Elorado also connects well with the

1:36:21existing bike network. Uh there's the

1:36:23portage bike path recently installed

1:36:25nearby on the east side of the railroad,

1:36:27sorry, west side of the railroad tracks.

1:36:28I might be getting my east and west

1:36:30mixed up here. Um there's also the Bull

1:36:32Park path that's a bit further across El

1:36:36uh El Camino Riale

1:36:38and uh uh to the north connecting to the

1:36:42Bryant Street bike boulevard or I guess

1:36:44that would be to the east potentially

1:36:46and potentially through all the way to

1:36:47Hoover Park and uh through Hoover Park

1:36:50and connecting all the way to

1:36:51Middlefield. Uh so there's discussion

1:36:53there about the opportunities to kind of

1:36:55complete that connection u for bikes and

1:36:57pedestrians.

1:37:00Um, El Dorado and El Carmelo connections

1:37:02were also discussed as a preferable

1:37:05bicycle routes because of the lower

1:37:06volumes on Elorado and El Carmelo and uh

1:37:09that was um compared to the higher um

1:37:12vehicular volumes uh so lower vehicular

1:37:15volumes on Elorado and Carmelo and uh

1:37:18compared to the higher vehicular volumes

1:37:20in comparison uh on Lomie Avenue. Uh so

1:37:24there was a desire council desire to um

1:37:28if we're looking at adding more bikes on

1:37:30a roadway, prioritizing a roadway where

1:37:31there's less vehicles.

1:37:35Uh so all that being said, uh city

1:37:37council directed staff to explore a full

1:37:39grade separation option under Cal Train

1:37:42and Alma in this area. Uh and that's uh

1:37:45the the kind of the the place which this

1:37:47alternative A2 was created. And so that

1:37:50part of our direction was to explore

1:37:52what concepts might be possible um in

1:37:56this Elorado vicinity. So hopefully that

1:37:58help that context kind of helps frame

1:38:00the discussion tonight. Next slide

1:38:02please.

1:38:05We're now in phase three of community

1:38:06engagement where we're gathering

1:38:07feedback on the draft Elderorado Avenue

1:38:10concept alternatives and proposed

1:38:11network enhancements for additional

1:38:13refinement prior to the release of a

1:38:15public draft report. Summary of the

1:38:17tools and activities being used during

1:38:18phase three is listed here. Next slide.

1:38:24Uh, next slide please.

1:38:27This slide provides a sideby-side view

1:38:29of the alternatives A1 and A2. A1 would

1:38:32include a sign a tunnel beneath the Cal

1:38:34Train tracks and users would cross Alma

1:38:36Street at a new signalized crossing of

1:38:39um at Elorado Avenue. A2 would provide a

1:38:42full grade separated tunnel beneath both

1:38:43the Cal Train tracks and Alma Street.

1:38:46The current representative A2 uh concept

1:38:49is also referred to as A2A in your staff

1:38:51report was selected among six variants

1:38:54because it balanced user experience,

1:38:56accessibility, utility constraints, and

1:38:58neighborhood impacts.

1:39:00Next slide, please.

1:39:03At this planning level, A1 has fewer

1:39:06anticipated utility impacts, a lower

1:39:09cost estimate of approximately 72 72

1:39:12million, preserves two-way vehicle

1:39:14access across Elorado Avenue, and has no

1:39:16immediate emergency access concerns

1:39:18identified at this stage. The main

1:39:20trade-off is that users will still cross

1:39:22Elma Street at grade, although at a new

1:39:24signalized crossing that's designed for

1:39:26bicyclists and pedestrians. Overall,

1:39:28this means A1 is simpler and less

1:39:30impactful in several ways, but it does

1:39:32not fully respond to the community

1:39:33interest in avoiding an ATR grade on a

1:39:35street crossing.

1:39:37It's important to emphasize that at at

1:39:40this stage, the signal shown um is not a

1:39:43final design concept. Um at this stage

1:39:46the project is really identifying the

1:39:48location and function of a potential

1:39:50signalized crossing. Its detailed

1:39:52geometry, signal phasing, permitting uh

1:39:55u permitted turning movements and

1:39:57related roadway treatments have not been

1:39:59determined. There's a broad range of

1:40:02possible designs each with different

1:40:03trade-offs. For example, the city could

1:40:06prioritize bicycle and pedestrian

1:40:07comfort and safety, neighborhood traffic

1:40:09management, vehicle access and

1:40:11circulation, transit operations,

1:40:13emergency response, or some other

1:40:15combination of these objectives.

1:40:19Those policy and design priorities would

1:40:21guide the ultimate signal configuration

1:40:23if alternative A1 moves forward into

1:40:25subsequent design phases. The current

1:40:27planning level analysis assumes that

1:40:30left turns at Elorado Avenue and Alma

1:40:32Street would be restricted during the

1:40:34peak period and shows a decrease in

1:40:36vehicle trips on Elorado Avenue. This is

1:40:38an analytical assumption used to

1:40:40understand the potential circulation

1:40:42effects, not a final operational

1:40:44decision.

1:40:47So the key point is that A1 identifies a

1:40:49potential signalized crossing at this

1:40:51location but it does not predetermine

1:40:53the final uh signal design or traffic

1:40:56operations. Next slide please.

1:41:02So this slide illustrates one possible

1:41:05operational concept for the new proposed

1:41:07signal with left turn restrictions. It's

1:41:10intended to show how access management

1:41:11could help discourage cut-th through

1:41:13traffic on Elorado Avenue while

1:41:15maintaining a direct crossing for people

1:41:17walking and biking. This is not a

1:41:19proposed final signal design. Depending

1:41:21on city and community priorities, future

1:41:24designs could evaluate other approaches,

1:41:26including different turn restrictions by

1:41:28time of day, ride-in ride out

1:41:30operations, physical turn control

1:41:32measures, pedestrian and bicycle focus

1:41:34signal operations, or related

1:41:36modifications at nearby intersections to

1:41:38accommodate vehicular circulation. If A1

1:41:41advances, future design phases would

1:41:43evaluate those options through further

1:41:45traffic analysis, engineering design,

1:41:48emergency access review, and agency

1:41:50coordination, and of course, additional

1:41:52community engagement. The objective

1:41:54would be the objective would be to

1:41:56identify an intersection design that

1:41:57appropriately balances safety and

1:41:59comfort for people walking and biking

1:42:00with neighborhood access, circulation,

1:42:02and operational needs. Next slide,

1:42:04please.

1:42:08Alternative A2 provides the full grade

1:42:10separation under both Alma Street and

1:42:11the Cal Train tracks. This is a new

1:42:13concept design that responds directly to

1:42:15community interest in city council

1:42:17direction and in avoiding an atgrade

1:42:19crossing of Alma Street in the vicinity

1:42:21of El Elorado Avenue. Several variants

1:42:24explored for A2 in the vicinity of

1:42:26Elorado are discussed in your staff

1:42:28report. At this planning level, A2 has

1:42:31greater utility risk, a larger

1:42:33structure, deeper excavation, and a

1:42:35higher estimated cost of approximately

1:42:3687 million. It would require full

1:42:39acquisition of two east side properties

1:42:40containing four dwelling units and

1:42:43emergency access constraints would need

1:42:45to be uh further resolved. So, a central

1:42:48question could be whether the benefit of

1:42:50a full grade separation under Alma

1:42:52Street outweighs the additional property

1:42:53access, utility, cost, construction,

1:42:56emergency access challenges at the

1:42:57Elorado location.

1:43:00Next slide, please.

1:43:03The city received a petition requesting

1:43:06an evaluation of the Lommo Verde Alma

1:43:08median hybrid plan. The petition and

1:43:10supporting materials are included in the

1:43:12staff report. At a high level, this

1:43:14concept would relocate the proposed

1:43:15signalized Alma Street crossing from

1:43:17Elorado Avenue to Lomma Verde Avenue. It

1:43:20would then connect that crossing to the

1:43:23proposed rail underpass near Elorado

1:43:25Avenue and Park Boulevard through an

1:43:27approximately quarter mile bicycle

1:43:29pedestrian facility along the east side

1:43:31of Alma Street adjacent to the rail

1:43:33corridor.

1:43:35Next slide please.

1:43:38This is not yet a city developed

1:43:40alternative and it is not and it has not

1:43:42been fully developed or evaluated at the

1:43:44same level as alternatives A1 and A2.

1:43:47For discussion purposes, we have

1:43:49completed an initial highle review to

1:43:52identify some key trade-offs for the

1:43:53community to consider. For this concept

1:43:55to advance further, we would require

1:43:57city council direction and additional

1:43:59community outreach, including outreach

1:44:01to potentially affected LMA verde area

1:44:03residents.

1:44:05As listed on your screen, there are

1:44:06several potential benefits associated

1:44:08with this concept. First, it would use

1:44:11the shorter tunnel beneath the cow train

1:44:13tracks similar to alternative A1 rather

1:44:15than requiring a longer structure

1:44:17beneath Alma Street and the rail

1:44:19corridor. Second, locating the

1:44:22signalized crossing at Loma Avenue would

1:44:24strengthen bike access from that

1:44:26corridor and could use the landscaped

1:44:28area between Alma Street and the rail

1:44:31corridor for the connecting facility.

1:44:34Third, based on this preliminary review,

1:44:36the concept may avoid full residential

1:44:38property acquisitions anticipated with

1:44:41the current A2 concept.

1:44:44Next slide, please.

1:44:48Uh this is a continuation of the initial

1:44:51feedback. So, one primary consideration

1:44:54is the directness and anticipated use of

1:44:57this um crossing and its proposed

1:44:59design. Compared with the crossing at

1:45:01Elorado Avenue, this concept adds

1:45:04approximately one quarter mile of travel

1:45:06along the Alma Street corridor between

1:45:08Lomover Avenue and the underpass. That

1:45:10additional distance may be more

1:45:12acceptable for bicycle trips um compared

1:45:15to some walking trips and people

1:45:17traveling to and from the areas north of

1:45:19Lomma Verde may need to travel south to

1:45:22cross Alma Street and then backtrack

1:45:24north along the penina bicycle facility.

1:45:27Because directness and travel time

1:45:29strongly influence whether people choose

1:45:32to walk or bike, the additional quarter

1:45:33mile and required backtracking in this

1:45:35concept would likely make it a less

1:45:37effective facility, particularly for

1:45:39pedestrians and reduce expected use

1:45:41compared with a more direct crossing.

1:45:44Lower use facilities that are

1:45:47constrained or isolated also face

1:45:50greater maintenance, security, and

1:45:52unwanted activity challenges over time,

1:45:54potentially creating pressure for

1:45:56operational uh changes or closure. Palo

1:45:59Alto has experienced related concerns.

1:46:02Um, and an example of this is the former

1:46:04pedestrian undercrossing beneath El

1:46:06Camino Royale near the Page Mill Road

1:46:08and Oregon Expressway intersection.

1:46:11This outcome is not inevitable, but it

1:46:14underscores the importance of designing

1:46:15a route that is direct, visible,

1:46:17well-lit, and integrated with the

1:46:19surrounding street network from the

1:46:20outset. The concept would also require

1:46:23additional work beyond the over

1:46:24underpass itself. This includes

1:46:27construction of a long um of a long-term

1:46:30mainten construction and long-term

1:46:31maintenance of the parallel bicycle

1:46:33pedestrian facility. EVA eval evaluation

1:46:36of a box covert extension and supporting

1:46:38structure near Madera Creek and review

1:46:41of potential effects on drainage,

1:46:42landscaping, utilities right ofway and

1:46:45apartment driveway access near the LMA

1:46:47Verde um Avenue and Alma Street

1:46:49intersection.

1:46:53Further uh a further consideration is

1:46:55the user experience along the parallel

1:46:57facility because it would be located

1:46:59between Alma Street and the rail

1:47:00corridor. The future design would need

1:47:02to carefully address visibility,

1:47:04lighting, sight lines, emergency access,

1:47:07and convenient and convenient entry and

1:47:09exit points so that the route feels

1:47:11open, safe, comfortable at all times of

1:47:14day. The city would also need to assess

1:47:17how the new signal and crossing

1:47:18operations could affect vehicle

1:47:20movements on Lom Verde Avenue and

1:47:22adjacent streets. It's also important to

1:47:24understand that if council directs staff

1:47:26to evaluate it further, staff would need

1:47:28to pause the project, develop a scope of

1:47:30work and cost estimates, obtain

1:47:32authorization for additional consultant

1:47:34work, prepare conceptual designs and

1:47:36cost estimates, update the technical

1:47:38technical analysis, and conduct focused

1:47:40engagement um with uh key residents and

1:47:44and stakeholders. Pausing or materially

1:47:47extending the project would likely

1:47:49increase construction costs through

1:47:51continued escalation,

1:47:53lengthen delivery timeline, and

1:47:55heightened the ris risk of the project

1:47:58um not actually advancing to

1:47:59construction. This is a lesson that

1:48:01staff have heard from other peer

1:48:02agencies who wish that they had moved

1:48:05great separation projects faster. Again,

1:48:08staff have not completed a formal

1:48:09evaluation of this concept. For this

1:48:11concept to advance further, we would

1:48:13require city council direction. Next

1:48:15slide, please.

1:48:19So these next slides will now focus on

1:48:21again just the alternatives A1, A1 and

1:48:24A2.

1:48:26The purpose of this assessment is to

1:48:27compare the relative advantages,

1:48:29disadvantages, and risks between A1 and

1:48:31A2 at a planning level. It's based on

1:48:33information readily available at this

1:48:35stage and is not intended to represent

1:48:37final engineering conclusions. The

1:48:40alternatives were evaluated against a

1:48:42subset of criteria drawn from the prior

1:48:45project phases. So the version of this

1:48:47table may look familiar to you. Higher

1:48:50scores are shown on black in black or in

1:48:52darker gray represent stronger alignment

1:48:54with community values whereas lower

1:48:56scores are shown in light gray um

1:48:59indicate weaker alignment. These results

1:49:01are one of several considerations in the

1:49:03process of selecting alternatives. Next

1:49:06slide please.

1:49:08The project project team also prepared

1:49:10an initial circulation study that looked

1:49:12at how each alternative could affect

1:49:13neighborhood circulation and travel

1:49:15patterns in the in the Midtown

1:49:16neighborhood. Overall, the study found

1:49:19that the crossing fits well within the

1:49:20surrounding low volume, low stress

1:49:22neighborhood street network. Nearby

1:49:24neighborhood streets currently carry

1:49:25under 200 vehicles per hour during peak

1:49:28periods, which is within typical bicycle

1:49:30boulevard thresholds.

1:49:32The initial circulation study as as I

1:49:35mentioned earlier assumed left turns

1:49:36would not be per permitted at the

1:49:38Elorado and Elma Street signalized

1:49:40intersection during the peak hour.

1:49:42Traffic on El Dorado Avenue is projected

1:49:44to decrease by approximately 30 vehicles

1:49:46per hour. Those trips would be

1:49:48redistributed to nearby parallel

1:49:50streets. Next slide please.

1:49:54Shown on the screen is the Oh, next

1:49:56slide please.

1:49:58Shown on the screen is uh the proposed

1:50:00network enhancements which fall into

1:50:01several categories. First is an Elorado

1:50:04Avenue bicycle boulevard and operations

1:50:06package. I would also like to note that

1:50:09due to the current width of Elorado

1:50:11Avenue parking adjustments may be

1:50:12considered during design refinement to

1:50:14address daylighting, visibility and

1:50:16emergency access needs. Second is

1:50:19intersection and crossing safety.

1:50:21Third is vehicle speed and cutthrough

1:50:23management. And fourth is placemaking

1:50:25and wayfinding.

1:50:27Overall, the intent is to make the new

1:50:28undercrossing connect with the broader

1:50:30network of comfortable, intuitive, and

1:50:32accessible walking and biking routes.

1:50:34So, now that I've covered the crossing

1:50:36alternatives at Elorado Avenue design

1:50:39network uh changes, I'll briefly

1:50:41summarize the feedback we are hearing

1:50:42through phase three of engagement so

1:50:45far. And there's additional information

1:50:47in your staff report. Next slide,

1:50:49please.

1:50:51Next slide, please.

1:50:54During phase three, we are generally uh

1:50:56we are uh we have generally heard a

1:50:58broad support for improving bicycle and

1:51:00pedestrian rail crossings in South Palo

1:51:02Alto alongside differing views on the

1:51:05appropriate location, design, timing,

1:51:07and level of investment. Feedback on

1:51:10alternatives A1 and A2 is mixed. Some

1:51:13community members favor A1 as a simpler,

1:51:15lowerc cost option, although traffic

1:51:18operations remain a concern. Others

1:51:20expressed concerns that A2 would be more

1:51:22complex and costly with greater

1:51:24potential impacts on residential

1:51:26properties and utilities. We have also

1:51:28heard requests to evaluate the LMA verde

1:51:31uh Elma hybrid plan and other crossing

1:51:33locations

1:51:35in the Elorado Avenue. Residents raised

1:51:37concern that the roadway width parking

1:51:39driveway access cut through traffic and

1:51:41emergency um emergency access response

1:51:45as concerns.

1:51:46Finally, there is support for targeted

1:51:48traffic homing and bicycle boulevard

1:51:50improvements with requests for further

1:51:52analysis and community engagement. Next

1:51:54slide, please.

1:51:56Next slide.

1:51:59So, the feedback we receive during this

1:52:01next phase will help refine the

1:52:02alternatives and the network

1:52:03enhancements before the project returns

1:52:05to council. Near-term scheduled

1:52:07engagement meetings are shown here,

1:52:08noting that these dates are tentative.

1:52:10Additional community engagement is being

1:52:12planned for this project. So, please

1:52:13check the project web page in the city

1:52:14calendar for the latest meeting schedule

1:52:16for this project. Uh, next slide please.

1:52:21Next steps for the project team

1:52:22following completion of conceptual

1:52:24design including uh includes the

1:52:26presentation

1:52:28um sorry the following the completion of

1:52:30conceptual design includes the

1:52:32presentation uh the refined 15% designs

1:52:35and network enhancements as well as

1:52:36funding and imple uh funding and

1:52:38implementation plan to the community for

1:52:40feedback and consideration in early 2027

1:52:43followed by a final report in spring of

1:52:452027. Staff will then pursue subsequent

1:52:48phases as directed by the city council,

1:52:50including the next steps shown on your

1:52:51screen. Next slide, please. I also

1:52:54wanted to share that the city has been

1:52:56awarded approximately a little bit less

1:52:58than $460,000 in funding from the 2016

1:53:02measure BIC and pedestrian planning

1:53:05grant study program cycle 3 for this uh

1:53:08for this project. This grant award would

1:53:10fund the next phases of work including

1:53:12additional data collection, analysis,

1:53:14review of conceptual designs and

1:53:16community engagement, collaboration with

1:53:18Calra for thirdparty review and Cal

1:53:20Train board review as part of the rail

1:53:22corridor use policy process.

1:53:26That completes that presentation. I look

1:53:29forward to discussion. Thank you.

1:53:33Um, so I'm going to give I think we can

1:53:36have like five minutes of clarifying

1:53:37questions from the commissioners while

1:53:39we wait for additional um public

1:53:42commenters to turn in cards or raise

1:53:44their hands on Zoom. So, I'm going to

1:53:46start with Commissioner Tumbleton.

1:53:50>> Thank you very much for um a thorough

1:53:53presentation. I appreciate bringing in a

1:53:55lot of color for some of the decisions

1:53:57that have been made so far. Um, I also

1:54:00want to to state for staff and also for

1:54:03the benefit of the public that our

1:54:04purpose here is to um do our due

1:54:08diligence. So, we're going to ask some

1:54:09tough questions and that's okay because

1:54:12I'm sure you're prepared for them and

1:54:14it's it's part of our process. So, um I

1:54:17hope that uh any questions I bring will

1:54:20be taken in that light. Um, so the first

1:54:24thing uh that that I noted um when you

1:54:27were talking about the benefits of uh

1:54:31the crossing at this location

1:54:34um was a list of of benefits like

1:54:38accessing Baron Park and uh other

1:54:42trails. Do you recall

1:54:45providing that list? Um, and I know that

1:54:48this location, um, this proposed

1:54:51location is about half a mile from the

1:54:55California Avenue underpass. Is that

1:54:58right?

1:55:00>> That's correct.

1:55:01>> Right. And so, are any of these benefits

1:55:04exclusive to the Elorado crossing or do

1:55:07they also occur at the California Avenue

1:55:10crossing?

1:55:16So, the benefits of uh the benefits that

1:55:19I mentioned are the connection between

1:55:21the Midtown and Ventura neighborhoods.

1:55:24Um the NVCAP, the North Ventura

1:55:26Coordinated Area Plan area with the

1:55:28additional housing there.

1:55:29>> You mean NVCAP where the California

1:55:31Avenue underpass is? Like I I'm I'm just

1:55:35trying to be really real. This is this

1:55:37is all very approximate. So, um those

1:55:40the don't worry that's that's fine.

1:55:44>> Let's yeah, let's go through the items

1:55:46um in response to your

1:55:48>> I only want the items that are not

1:55:49available from the California um Avenue

1:55:52crossing.

1:55:53>> Okay. So, to clarify what you're

1:55:55interested in knowing is what benefits

1:55:58does this particular uh crossing add to

1:56:02what's already available through the

1:56:04California Avenue?

1:56:05>> Right. and put this another way um

1:56:07because our responsibility is to

1:56:09evaluate this and recommend to city

1:56:11council

1:56:12>> um what justifies the $80 million and

1:56:16how many other years it's going to take

1:56:17and so that's

1:56:19yeah so just to respond to that question

1:56:22thank you for your question um so

1:56:24council did weigh that consideration

1:56:27when they were choosing this this

1:56:29location it is I think it was the

1:56:31furthest north of the eight locations is

1:56:34that right from the previous step. Um,

1:56:36and so that was that was something that

1:56:39they

1:56:41that they weighed um along with the

1:56:43property impacts and other and other

1:56:45considerations

1:56:47>> and and would you share I mean that

1:56:49that's the part of the recap of what

1:56:51happened at council that I'm missing and

1:56:53so that's why I'm asking for clarifying

1:56:55purposes because we've got over 30

1:56:59people here um in in person to discuss

1:57:02it but we also have to evaluate and give

1:57:05feed feedback. So, um, again, I I I can

1:57:08read your expression here, like why is

1:57:09she asking this, but this is this is

1:57:11important to get us all on the same

1:57:12page. So, thank you. I appreciate you

1:57:14taking the time to share that with us.

1:57:15So

1:57:17what is Oh, so yeah, I mean that was

1:57:21that was one of the things that they

1:57:22kind of weighed that the location,

1:57:26you know, didn't ex didn't provide as

1:57:28much benefits as some of the other

1:57:30locations potentially in the middle of

1:57:32the area. I mean they they're rang

1:57:34between Meadow, Charleston, San Antonio

1:57:38and then Calab. So that was part of

1:57:41their discussion and I think on balance

1:57:43they were particularly concerned about

1:57:46property impacts. So that was part of

1:57:48the decision there. But they did want to

1:57:50provide a new pedestrian bicycle

1:57:52undercrossing in the South PaloAlto

1:57:54area south of Oregon expressway. It's

1:57:56barely south of Oregon though. Like did

1:57:58you I guess what I'm trying to ask is

1:58:00did staff discuss that with council?

1:58:04Yes, that that was part of the

1:58:06discussion of that council had right.

1:58:08the the discussion of how of these

1:58:12different options as mentioned this was

1:58:14the one that was farthest north um there

1:58:18were some you know concern that if they

1:58:20were too far south then it wasn't um

1:58:23applying to as many PaloAlto residents

1:58:27and so

1:58:29yes this doesn't give as much access as

1:58:32some of those that were further south

1:58:35might have given but it also didn't have

1:58:38the impacts they were concerned about of

1:58:41property acquisition for example. Um so

1:58:45inputs in this discussion and feedback

1:58:49in tonight's discussion about the

1:58:52concern that maybe this isn't giving

1:58:55enough benefit to balance the the cost

1:58:58and impacts that absolutely can be part

1:59:01of the feedback that you provide tonight

1:59:03and when we get to that discussion part

1:59:05we can talk

1:59:05>> can I just quickly interject on this was

1:59:07council aware of the price tag at the

1:59:10time because when it was at came to the

1:59:12commission I had asked You know, we had

1:59:14said that Lumie might be more expensive

1:59:16than Elorado, but we didn't know how

1:59:18much more, and we certainly didn't know

1:59:22that on the low end, this would cost $72

1:59:25million. So, at the time, council was

1:59:29balancing, you know, which options to

1:59:32advance. Was council aware of the order

1:59:36of magnitude of um like the price tag

1:59:40for this?

1:59:42The last phase we did not have um cost

1:59:45estimates, construction cost estimates.

1:59:47We had only developed cost estimates

1:59:50once we had uh options narrowed down.

1:59:54However, as part of the evaluation,

1:59:56construction cost was a consideration

1:59:59but it was um presented as you know

2:00:02high, medium, low kind of ranking and

2:00:05compared the eight alternatives against

2:00:06one another.

2:00:07>> Right. Okay. because like 3 versus 5

2:00:10versus 10 is one thing and then 72

2:00:14versus 75 versus 78 would be a different

2:00:17kind of right and and that is the

2:00:20benefit of having this discussion again

2:00:23at this point where we're still only 5%

2:00:26design. Um we've done enough work that

2:00:29we can get some numbers. They will get

2:00:30more and more precise as we go along.

2:00:33>> Oh, you definitely got our interest now.

2:00:35and and so we can have this discussion

2:00:37so we can receive the concerns from the

2:00:39public and from the PT.

2:00:41>> Thank you. I still have more questions.

2:00:42So, um I that those great questions,

2:00:45Chair Chang, thank you. Um so, uh the

2:00:48other um thing we we talked about this

2:00:51is only half a mile south of the

2:00:52existing southernmost crossing in

2:00:54PaloAlto. Um and then um you know

2:00:58there's like about two miles to get to

2:01:01the border of uh the city down by San

2:01:03Antonio. Are um not part of this

2:01:07presentation so far, but I'm going to

2:01:09ask the question. Are we thinking that

2:01:11bikes will be able to get through if

2:01:13ever um grade separations are performed

2:01:17at Meadow and Charleston?

2:01:20Is that why we're thinking not to put

2:01:21them there? I'm just trying to

2:01:23understand what's the logic. Um so um

2:01:27the grade separations came to council on

2:01:29Monday night and they um recommended

2:01:32that staff continue through to the 35%

2:01:36uh design uh something that they

2:01:38>> on both of those two

2:01:40>> on uh Meadow Charleston and Church Hill.

2:01:43>> Oh okay great we have a grant that

2:01:46covers all three.

2:01:47>> Awesome. Um

2:01:49and part of that conversation they

2:01:51reiterate, they've said it previously,

2:01:53but they reiterated that Charleston is

2:01:55their first priority and our bikes going

2:01:58to be yes included. So that's sort of

2:02:00the mentality of why it's not so

2:02:03desperate that we're putting this up

2:02:05here because we're going to have an

2:02:06opportunity 10 or 20 years down the road

2:02:09in in South Palo Alto. Is that right?

2:02:11>> Yeah, they're thinking about the whole

2:02:13corridor. So yeah.

2:02:14>> Awesome. Okay. Well, um thank you for

2:02:16clarifying that. I appreciate those are

2:02:17my clarifying questions.

2:02:19>> Mr. Aken,

2:02:22>> is it worth pursuing discussion of

2:02:26additional modifications to A2 tonight?

2:02:31>> Yes, we welcome all your feedback.

2:02:35>> Okay, thank you. I'll have some later

2:02:37then.

2:02:40>> Um, okay. So, I have a question that

2:02:43would be great if Mr. Kohl's could

2:02:45explain why bridges why the options

2:02:49um you know we started with almost 30

2:02:51options and then got narrowed down to

2:02:53eight and I think it might be helpful

2:02:54for the public to understand why bridges

2:02:57were eliminated.

2:03:00>> So that has to do with the Calra

2:03:03electrification system and the clearance

2:03:05and the amount of uh space it would take

2:03:08to actually get over the electrification

2:03:10system. Um it's approximately just to

2:03:13give a level like a sense of the height

2:03:15it's approximately three stories up that

2:03:17you would have to go and so to meet

2:03:19current ADA standards what that means is

2:03:21you have a very long ramp and what this

2:03:23equates to is a very big structure um

2:03:26which requires space. So um we looked at

2:03:29that along the whole South Palatoto

2:03:31corridor between Oregon Expressway and

2:03:33San Antonio and um ultimately

2:03:37recommended that those uh ideas didn't

2:03:40advance any further past that initial

2:03:42kind of early phase where you know it's

2:03:43part of the 25 or so conceptual designs

2:03:46that were originally evaluated.

2:03:47>> Yeah. Essentially due to cost and

2:03:49practicality and feasibility of those

2:03:51really long ramps. Correct. Okay. And so

2:03:55that's thank you for the context because

2:03:56I just wanted everybody here to hear

2:03:57that. Um secondly,

2:04:01question about what the funding sources

2:04:02for this ultimately would be. Are these

2:04:05you know if it's a 72 million or 80

2:04:08whatever million uh dollar project is

2:04:12that going to be something that would

2:04:13come out of PaloAlto's general fund or

2:04:15would it be funded from other grants or

2:04:17funds that are designated for a

2:04:20crossing? Um, we don't currently have a

2:04:22funding plan for this project, but we

2:04:25would be seeking grant funding and we

2:04:27would expect that that would cover the

2:04:28bulk of the costs.

2:04:30>> Thank you. That's also helpful to

2:04:31understand.

2:04:32>> Okay. Um, I don't see other lights right

2:04:35now.

2:04:37Um, so I've got a request for a break,

2:04:41but I want to make sure that we don't

2:04:44No, I don't want to make the members of

2:04:45the public wait for that. So, let's

2:04:48start by saying um let's check in to see

2:04:51how many people have submitted

2:04:54or public comment and so that we can

2:04:56make an assessment. And I think that we

2:04:57might take a break in the middle really

2:05:00short because we need a bio break up

2:05:02here.

2:05:03>> Um but let's see how many speakers we

2:05:06have first.

2:05:07>> Yeah. Uh through the chair, we have 14

2:05:09requests to speak uh being 12 individual

2:05:12speakers and two group speakers.

2:05:14>> Okay. and then online

2:05:16>> uh one one is included on those one

2:05:20online then they're already on the list.

2:05:22>> Okay. So then I think what we'll do is 2

2:05:24minutes per speaker and then for groups

2:05:27we can stick to the 10 minutes but I

2:05:30just want to beg the public for their

2:05:31understanding that at a certain point we

2:05:33might take a very short break so that we

2:05:35can address our needs. Thank you.

2:05:39>> Sorry. Oh yeah. and we'll still hear

2:05:41everybody but we'll just

2:05:44>> Yeah. Um our first uh group speaker is

2:05:46David H speaking on behalf of five um

2:05:51>> sorry and also just could we please just

2:05:54in the this is just a decorum and how we

2:05:57handle this um for public comment in the

2:05:59public meetings just please refrain from

2:06:02applause or cheering or booze. Uh thank

2:06:06you. Yeah, and also for the public uh

2:06:08there is a timer on the pulpit so that

2:06:12you can uh see your time uh when it ends

2:06:14and nearing ending. Um but with that

2:06:16being said uh David you may begin.

2:06:19>> Respected chair Chang and members of the

2:06:23planning and transportation commission.

2:06:26I am speaking on behalf of 300 residents

2:06:29and voters in Poalto. We have signed a

2:06:32petition objecting to the city's

2:06:34proposed bike path

2:06:37on Elorado because of serious safety and

2:06:39health concerns and we are asking the

2:06:42city to consider the city and commission

2:06:45to consider an alternative hybrid

2:06:47proposal which we believe maximizes

2:06:50utility for the city. Next slide please.

2:06:53The dominant issue is a structural one.

2:06:56El Dorado is simply too narrow to safely

2:06:59handle higher additional volumes of

2:07:01traffic. The easiest way to understand

2:07:04this is to drive north on Elma Street

2:07:07and make a right turn onto Alada. I

2:07:10presented photos in this slide to

2:07:12illustrate the situation. As you are

2:07:15entering Alado shown at the left photo,

2:07:18you will need to rapidly slow down from

2:07:19about 35 miles an hour to make the turn.

2:07:22You will be squeezing often between cars

2:07:25parked on both sides of the street.

2:07:29Furthermore, you can encounter cars

2:07:31trying to exit El Dorado as shown in the

2:07:33right photo. You will have only interest

2:07:36to spare to avoid a collision. Next

2:07:38slide, please. And next slide, please.

2:07:43This slide shows a car that did not

2:07:45negotiate the turn into Elorado and

2:07:47ended up crashing into Cindy and Dave's

2:07:50fence at the intersection of Elorado and

2:07:53Elma. They have had numerous accidents

2:07:55on their property over the years. Next

2:07:58slide, please.

2:08:00Again, the dominant issue is a

2:08:02structural one. El Dorado is the

2:08:05narrowest street between Oregon

2:08:07Expressway and San Antonio Road. El

2:08:10Dorado is 27 feet wide. In comparison,

2:08:14El Camalo is 35 ft wide and Lom Verde is

2:08:1842 ft. Next slide, please.

2:08:23On top of this already tight and crowded

2:08:25situation, the city has proposed to

2:08:27layer on a bike boulevard with

2:08:29additional bike and pedestrian traffic.

2:08:32I will now go through how the city's

2:08:35proposals on this narrow street may play

2:08:38out. The city is considering two

2:08:40alternatives for a bike crossing to

2:08:42connect Elorado to Park Boulevard. A1

2:08:46would establish a traffic light at Alma

2:08:48to allow surface crossing of bicycles

2:08:50across Elma and then create a tunnel

2:08:52under the train tracks to continue well

2:08:55to connect ultimately to Park Boulevard.

2:08:58A2 would create a tunnel under both Elma

2:09:01and the train tracks.

2:09:03All variants of A2 would require eminent

2:09:06domain and the taking of private

2:09:08residences in whole or in part. One

2:09:12variant would take units of affordable

2:09:14housing at Alorado and Elma.

2:09:17Why take housing at all when the city

2:09:19needs more housing units? Next slide,

2:09:22please.

2:09:24A1 would place a traffic light at Alma.

2:09:27This would be the only traffic light

2:09:28between Churchill and Grocery Outlet.

2:09:31This would draw a neighborhood traffic

2:09:32wanting to make protected turns.

2:09:35Navigation apps such as Google Maps

2:09:37would route cut through traffic here.

2:09:39The result is very likely to be much

2:09:42higher traffic volumes.

2:09:44To put this in perspective, this would

2:09:47be on top of the 2600 additional bike

2:09:49and pedestrian trips daily estimated by

2:09:52the city for this bike path. Next slide,

2:09:54please.

2:09:56This increased volume of traffic is

2:09:58likely to result in traffic congestion

2:10:02which could further result in delay and

2:10:05emergency response vehicles

2:10:07service to culac residents especially at

2:10:11peak hours. This would adversely affect

2:10:1590 houses of residents as shown in the

2:10:18picture.

2:10:20Increased accident risk for residents

2:10:22exiting and entering their driveways

2:10:24along Elorado is another further result

2:10:27that could happen. Next slide, please.

2:10:32The proposed traffic circle at Bryant

2:10:34Alvo will have numerous negative

2:10:37consequences.

2:10:38Ross Road is already proof of this. As

2:10:41you can see from the map cutouts of Ross

2:10:43Road and El Dorado cut out to the same

2:10:46scale, the circle size for Elorado would

2:10:48be smaller than Ross Road, further

2:10:51exacerbating dangers and risks. Why

2:10:54repeat a flawed and dangerous design?

2:10:58Next slide, please.

2:11:00We neighbors are concerned that the

2:11:01proposed traffic circle would present

2:11:04increased collision risks to pedestrians

2:11:07and school children and also for

2:11:09residents living near the intersection.

2:11:11Increased collision risk from cars and

2:11:13bikes exiting out of the traffic circle.

2:11:17Next slide please.

2:11:19And next slide.

2:11:23And next slide.

2:11:27If a city wants to maximize utility to

2:11:30the residents of Palo Alto, why not make

2:11:32a choice that makes sense? Lumber Verde

2:11:36passes through the centrid of population

2:11:38between East Meadow and Oregon

2:11:40expressway.

2:11:41As stated before, Lumber Verde is much

2:11:44wider. That's 42 feet compared to

2:11:47Alorado's narrow 27 ft. Next slide,

2:11:51please.

2:11:54Lumber Verde has a far better reach. It

2:11:56crosses middlefield and continues to

2:11:58west bayshore. Then in half a mile it

2:12:01connects to the bike bridge across 101

2:12:04allowing access to the bay lens and

2:12:06shoreline areas. Elorado by comparison

2:12:09stops at Kalper.

2:12:12Next slide please.

2:12:14So how can Lom Verde be connected to

2:12:17Park Boulevard? To figure this out. I

2:12:20went to examine Elma Street and made

2:12:23measurements. The landscaping strip

2:12:25between the east edge of Arma and the

2:12:27sidewalk is 16 feet. The width between

2:12:31the west edge of Arma and the rail

2:12:33railroad ride ofwayo is about 11 ft.

2:12:36That's according to diagrams and city

2:12:38proposals.

2:12:40If 5T is left as a safety barrier next

2:12:43to the sidewalk, there is potentially

2:12:4622 total feet width available from both

2:12:51sides of armor.

2:12:53Next slide, please.

2:12:56I next pulled elements from the city's

2:12:58proposals and existing infrastructure

2:13:01and develop the hybrid plan. The

2:13:03elements are as follows.

2:13:06Locate the traffic light at Lom Verde

2:13:09between Lumber Verde and Elorado. Shift

2:13:12Alma Street eastwards to widen the

2:13:14median strip between the railroad and

2:13:16Elma.

2:13:18And then from the 22 feet of resulting

2:13:20available width, construct a protected

2:13:23bike and pedestrian path in the median

2:13:25strip and connect from the traffic light

2:13:28crossing to the city's proposed tunnel.

2:13:32A prime benefit of this plan is no

2:13:34eminent domain private house

2:13:36acquisitions.

2:13:38Next slide, please.

2:13:41With the list of concerns reviewed in

2:13:44this presentation and the hybrid plan,

2:13:46we created the neighborhood petition to

2:13:48inform neighbors and present our

2:13:50objections and solutions to the city. To

2:13:53date, 300 residents have signed this

2:13:56petition. This is a large majority of

2:13:58the 400 houses in the neighborhood

2:14:01between Elma and Kappa Street in Oregon

2:14:04Expressway and Matadoro Creek. We

2:14:07neighbors have opposed this Elorado bike

2:14:09path choice also at the transportation

2:14:12department community workshop on August

2:14:1427.

2:14:16Here we voted on the city's proposals. I

2:14:18have already emailed the voting results

2:14:20to the commission. About 80 to 90% of

2:14:23the neighbor votes were strongly against

2:14:25all of the variants of the city's

2:14:27Elorado bike path proposals.

2:14:30Next slide, please.

2:14:33Many of us 300 signitories are here

2:14:36today in person or online.

2:14:40We ask the city and planning and

2:14:42transportation commission to one

2:14:45completely remove Alorado Avenue from

2:14:47consideration for the South Palto bike

2:14:50ped connectivity project.

2:14:53Two, formally evaluate the hybrid plan.

2:14:58Uh so at this point uh chair Chang can I

2:15:03ask that those in the audience who

2:15:05support the position and the hybrid plan

2:15:08stand up or is that going to be so would

2:15:12you please stand up or wave your hands.

2:15:17Thank you. Thank you chair Chang and

2:15:20commission.

2:15:22>> Thank you very much. Next speaker. Our

2:15:24next speaker is Annette G speaking on

2:15:26behalf of five followed by Bruce H.

2:15:38Good evening, Chair Chang and

2:15:40commissioners. I do support a south Palo

2:15:44Alto bicycle and pedestrian crossing in

2:15:48the stretch between Cal A and Meadow,

2:15:50but El Dorado is not the right street.

2:15:55Why shoehorn a major transportation

2:15:58project into the narrowest and most

2:16:01constrained streets in the corridor when

2:16:04other and better alternatives exist?

2:16:08As said, the El Dorado is only about 27

2:16:11feet wide, has approximately 25

2:16:15driveways, and serves five culde-sacs

2:16:18with about 175 homes. Those who live on

2:16:22culde-sacs that are closest to ALMA

2:16:25right now have difficulties in exiting

2:16:28their driveways.

2:16:30Both alternatives A1 and A2 would

2:16:33significantly affect neighborhood

2:16:35access, circulation, parking, and

2:16:38potentially emergency response.

2:16:42The staff report does not adequately

2:16:44reflect the community opposition both at

2:16:47the August 27th meeting as well as the

2:16:52meeting on Sunday when over a hundred

2:16:55residents of the Elorado neighborhood

2:16:58came out to oppose the Elorado crossing.

2:17:02And David mentioned the sign the

2:17:04petition now has over 300 signatures in

2:17:08an area and I counted them today on a

2:17:10zoning map of about 525 households in

2:17:14support of the LMA Verde hybrid

2:17:17solution. That is a very high

2:17:19percentage. So I ask you for several

2:17:22options. First take off the Rube

2:17:26Goldberg A1 alternative from

2:17:29consideration.

2:17:31A2, as mentioned, would require the

2:17:34acquisition of four residents, three of

2:17:38which are lowincome housing run by Alta.

2:17:41And the council, as you know, has

2:17:43strongly avoided eminent domain of

2:17:46residential properties. A2 would

2:17:49restrict El Dorado to a narrow 13 foot

2:17:52one-way westbound street with the fire

2:17:55department already complaining about

2:17:58emergency access. The staff report also

2:18:01identifies significant utility

2:18:04conflicts, including a 24in

2:18:06high-pressure gas line, water and sewer

2:18:09lines, and their concerns about a toxic

2:18:12plume.

2:18:14There also is restricted driveway

2:18:16access, and one property wouldn't even

2:18:19be able to access their driveway.

2:18:22Second, direct staff to fully evaluate

2:18:26alternatives, especially the Loma Verde

2:18:30hybrid solution, but also there's El

2:18:32Carmelo in Matadora Creek. As mentioned,

2:18:36LMA Verde is over 15 feet wider than El

2:18:40Dorado. It's midway between the points

2:18:44and already functions as a bicycle

2:18:48corridor. And it goes all the way to

2:18:50Beayshore.

2:18:52Council member Bert's

2:18:54motion on o in December of last year

2:18:58asked staff to determine whether El

2:19:00Carmelo or El Dorado was a better

2:19:03option. That council member request

2:19:08deserves a clear answer. Third,

2:19:12reconsider the best solution for a

2:19:15traffic light and remove A1 from

2:19:18consideration. A traffic light at Lomma

2:19:21Verde would make more sense. It's

2:19:24further south. It would provide a better

2:19:26buffer to absorb a higher volume of

2:19:28cars, especially during peak hours.

2:19:32The assumptions that were at council on

2:19:35December 1 that favored El Dorado,

2:19:39including an eminent grade crossing to

2:19:42Meadow, which does not look likely now,

2:19:44have changed in cost have changed since

2:19:47the December 1 council meeting as

2:19:50engineering analysis has progressed.

2:19:55I invite you to come to Elorado and see

2:19:58the conditions for yourself. and we did

2:20:00invite you. We do need a South Palo Alto

2:20:06bike crossing. I know any choice of this

2:20:09crossing is going to have consequences,

2:20:12but

2:20:14if you pick a solution, put it in a

2:20:17location that is the safest,

2:20:20most practical, and has the least impact

2:20:25on the surrounding re residents. El

2:20:28Dorado is not that location. Thank you.

2:20:33>> Thank you.

2:20:35>> Our next speaker is Bruce A followed by

2:20:37Stanley Q.

2:20:41>> Thank you. Uh my name is Bruce Arthur.

2:20:44I'm the chair of the payback committee,

2:20:45but I'm here speaking from just myself

2:20:47tonight. I'm also a Midtown resident

2:20:49who's not far from this. Not immediately

2:20:51Jason, but pretty close. I just want to

2:20:53say how important it is that we add a

2:20:56low stress bike and pedestrian crossing

2:20:58in this section of town. Uh the

2:21:00California AB tunnel is lovely, but it's

2:21:02not low stress. I was in it this morning

2:21:04facing hordes of middle schoolers riding

2:21:06at high speeds. It is not ADA compliant.

2:21:09It is dark. It is narrow. It is too

2:21:11steep. We need something more along the

2:21:12lines of what we have at Homer. But that

2:21:14that's a, you know, that's what we want.

2:21:16This item has been on the it's in the

2:21:182024 pedestrian bike plan. It's also in

2:21:21the 2010 pedestrian bike plan. It's been

2:21:23on the books as a request for a very

2:21:25long time. It is really, we need to make

2:21:27something happen here. This connection

2:21:30also connects the two better bike routes

2:21:32in Palo Alto, connects Bryant Street and

2:21:33Park Boulevard. These are both excellent

2:21:35bike routes. And by adding a a

2:21:36connection that goes between them, you

2:21:38really make them much higher utility. It

2:21:40makes it easy for me to get to edgysical

2:21:42uh therapy on El Camino. It makes it

2:21:44easy for people on the other side of

2:21:45town to get to Calav. This is just a

2:21:48wonderful way to connect to existing

2:21:49structures.

2:21:50Additionally, I also want to say that

2:21:52after talking to some residents, the

2:21:53speed of the vehicles on Alma is a

2:21:56problem. And that's sort of outside the

2:21:58scope of this, but I like the idea of

2:22:00adding a light to Alma just to slow down

2:22:02the racetrack between East Meadow and

2:22:03all the way up to Churchill. And in

2:22:05fact, it might be a good idea to

2:22:07consider adding lights at Alma Verde and

2:22:09even at Oregon A where it comes out to

2:22:11allow cars coming up Oregon to make a

2:22:13left and go south on Alma. uh slowing

2:22:16down the traffic on Alma would be a big

2:22:18benefit to the people who live there. Um

2:22:20a lot of the affordable apartments in

2:22:21PaloAlto in that section of town and

2:22:23those people deserve a street that works

2:22:24for them, not just as a as a you know

2:22:26expressway. Thank you.

2:22:29>> Our next speaker is Stanley Q followed

2:22:31by David M.

2:22:36>> Hi. Um I'm the property owner of the

2:22:41>> and what Oh, okay. Sorry. I'm the I'm

2:22:45Stanley Quan and I'm the property owner

2:22:47right at near the corner at 149 Elorado

2:22:51and I urged the planning commission to

2:22:54just basically cancel this project and

2:22:57reject all proposals. Um,

2:23:00if if the A2 alternative is is uh

2:23:05implemented or even the other one,

2:23:07basically there's a tunnel wall that's

2:23:10like built right in front of my property

2:23:11and I would only be have a right turn

2:23:14into my driveway and uh backing out of

2:23:18or exiting the driveway would be

2:23:19extremely difficult. Um, not only that,

2:23:23the current proposals would use eminent

2:23:26domain and purchase all the neighboring

2:23:28houses around me. Um, I think this would

2:23:32be kind of an abuse of of of of city

2:23:36funds. Um,

2:23:39so I don't really think there is a need

2:23:41for the panel at Elorado because we do

2:23:44have the um the uh California Avenue

2:23:48exit and uh the the California Avenue uh

2:23:52pedestrian uh tunnel crossing. And if

2:23:55you would enhance it with better

2:23:57lighting, perhaps it would make it look

2:23:59a little bit be safer. um you could

2:24:01spend the same amount of money um making

2:24:03that that that tunnel wider, but

2:24:06basically you all have the same benefits

2:24:08of the California Avenue um crossing

2:24:11instead of at Elorado. Um the other

2:24:15thing is that the current study for the

2:24:18uh projection of number of people that

2:24:21would actually be using the the Elorado

2:24:23tunnel for the year 2031 is only 100 or

2:24:27se 70 people walking

2:24:30uh through the tunnel and 150 bicycle

2:24:33trips at the 8 8 a.m. to 9:00 a.m. um uh

2:24:37crossing. So for a project that would

2:24:40cost roughly $80 million,

2:24:43it seems like the total number of people

2:24:45that would actually use a tunnel uh is

2:24:48is is is

2:24:50pretty much not a good use of of city

2:24:53funds.

2:24:53>> This concludes your time.

2:24:55>> Okay. Anyway, I urge you to uh uh cancel

2:24:58this project. Uh

2:24:59>> our next speaker is David M.

2:25:08Okay. And I just wanted to um say

2:25:10something that I'd forgotten to say. So

2:25:12if you agree with speakers before you

2:25:14don't feel the need to use up your two

2:25:16minutes, uh you can just say I agree

2:25:19with that other person. Thank you.

2:25:23>> Very good. Thank you. Uh thank you for

2:25:25allowing me this opportunity to uh speak

2:25:27on behalf of the hybrid program, the

2:25:29hybrid project. Um I happen to be that

2:25:31resident at the corner of El Dorado and

2:25:33Alma and since 20 since 2002 I've have

2:25:3724 years of experience at that

2:25:39intersection and if you want any you

2:25:41know firsthand knowledge of how that how

2:25:44unsafe that uh intersection is just ask

2:25:48the um I can't uh the the Elorado as we

2:25:53mentioned is less than 28 ft wide. Uh

2:25:56it's the long it's the narrowest um

2:25:59stretch along that stretch of uh Alma

2:26:02and uh we already know that there's

2:26:05parking issues we've talked about um

2:26:08along that uh along that corridor. So um

2:26:11I'm here to simply say that as a

2:26:14resident uh who is in that um eminent

2:26:18domain discussion uh for both A1 and A2

2:26:23um I have to say I'm quite opposed to

2:26:25the the present uh alternatives at those

2:26:28two loc at those of those two projects.

2:26:31So in conclusion, I'll basically say um

2:26:34I'm in support of the hybrid program,

2:26:36the hybrid hybrid plan and uh that's

2:26:40that's all I got to say. Thank you.

2:26:42>> Thank you.

2:26:43>> Our next speaker is Sherei Vasan S

2:26:46followed by Paul A.

2:26:49>> Hi. Um so um I speak for myself. So any

2:26:54outburst, any show of irritation at the

2:26:57whole proposal is just my fault, not my

2:26:59family or my friends.

2:27:01Um, I don't know how this even came

2:27:05through. I mean, you're asking good

2:27:07questions and I don't know why you have

2:27:08to be so polite. You know, why are you

2:27:10doing this when there's California

2:27:11Avenue? I biked and I go to California

2:27:14Avenue under pass to go to the

2:27:15California, you know, that's where the

2:27:16shopping is. So you what's there in

2:27:19venture? So the whole thing doesn't make

2:27:21sense. So I strongly object. My kids

2:27:24grew up there. They learned to bike on

2:27:27Elorado and this you know and then they

2:27:32go to Hor Park. It is a peaceful

2:27:35community and you're ruining it with all

2:27:38this stuff. I don't know what those

2:27:40surveys are. I don't know if you ask

2:27:42them, hey, do you want the bike pass or

2:27:44you want to cut off the $72 million?

2:27:46What did they say? You know, it just

2:27:49makes no sense. So I don't know how how

2:27:52to say it and as I was listening to the

2:27:54previous point you know how you were all

2:27:56saying you know my house is already tall

2:28:00you know how is it all these new rules

2:28:03how is it going to affect you know

2:28:05that's what that's what we all here for

2:28:07you made a plan but you didn't even talk

2:28:10to anyone or most of us will be affected

2:28:14and some of what you're proposing

2:28:17basically puts me in house arrest I

2:28:19cannot get out of the house cuz it's

2:28:20going to be a you know electric bike or

2:28:24whatever stuff is going to be going one

2:28:26side and you know next what uh if I get

2:28:30on wheelchair you're going to have a

2:28:31blue lane so that I can just take my

2:28:33wheelchair and go. I don't know it's

2:28:35just I shouldn't say stupid but uh it

2:28:40just makes no sense.

2:28:43So I strongly oppose it. Okay city

2:28:46council has done this stuff. I'm going

2:28:49to be active. I thought I would just

2:28:51take my spiritual path and be peaceful,

2:28:54but you guys have gotten me out of this

2:28:56stuff includ

2:28:59>> nuts. Don't do this.

2:29:03>> Our next speaker is Paul A, followed by

2:29:05Arthur L.

2:29:14>> Good evening. My name is Paul Appan. My

2:29:16wife and I have lived on Emerson Street

2:29:18near El Dorado for 50 years.

2:29:22We know the troubles with El Dorado.

2:29:25We've lived it. Tonight, I want to ask

2:29:27one question. Is El Dorado the correct

2:29:30location for this grade separated

2:29:32crossing and class 3B Boulevard? We

2:29:35believe the answer is no. The street is

2:29:38too narrow. drivers regularly run uh

2:29:41stop signs driving at speeds appearing

2:29:44um well above 25 miles per hour and

2:29:47oversized overweight vehicles are

2:29:50common. Those are things that are not

2:29:52great for bicyclists.

2:29:55As we've as you've heard over 300

2:29:57neighbors have signed petitions opposing

2:29:59both city plans. But let me explain our

2:30:02concerns starting with the Alma

2:30:04intersection. Plan A1 adds a traffic

2:30:07light. Navigation apps will send drivers

2:30:09to that light to turn left onto Elma,

2:30:12pushing more cars onto El Dorado. That

2:30:14is in that is the opposite of what a

2:30:17bicycle boulevard is meant to do. Cars

2:30:19queuing at the light will also block

2:30:21residents trying to leave their

2:30:23driveways and culde-sacs.

2:30:25Plan A2, the tunnel, would require

2:30:28taking entire homes through eminent

2:30:30domain and elim and eliminate parking

2:30:33for homes opposite the tunnel. It could

2:30:36also slow emergency service responders

2:30:38to nearby homes. No design should move

2:30:42forward without a comprehensive response

2:30:44time analysis.

2:30:47Additionally, closing El Dorado

2:30:49eastbound will shift that traffic to

2:30:52Colorado or El Carmelo. Now, the bicycle

2:30:55boulevard, because El Dorado, El Dorado

2:30:58is a substandard width street, parking

2:31:00would be limited to one side to fit

2:31:02two-way traffic and more cyclists.

2:31:08You've heard that there's 25 driveways

2:31:10on on the street. picture backing out of

2:31:12one watching pedestrians, cyclists,

2:31:15faster bikes, and uh cars all at once.

2:31:18The risk of collision rises

2:31:20significantly.

2:31:21>> Thank you. That concludes your time.

2:31:25>> And uh to the chair, I just wanted to

2:31:27check in with you. We are at the halfway

2:31:28point of public comments. That's

2:31:29>> fine. We'll just finish.

2:31:30>> Okay. Our next speaker is Arthur L,

2:31:32followed by Richard Y.

2:31:39Good evening, Commissioners. I would

2:31:41like to speak on behalf of people who

2:31:44are not here, children who are biking to

2:31:47school. I think many of the people who

2:31:50live in Midtown, I live in Baron Park,

2:31:52so I think I'm going to be answering

2:31:53some of the questions that you posed

2:31:55initially, Carrie. Um, Mr. Samson. Um,

2:32:01at one of the community meetings, at the

2:32:03first community meeting, I think many of

2:32:05you people live in Midtown understand

2:32:08that a good part of the Ali High School

2:32:11district lives south of Oregon

2:32:14Expressway.

2:32:17At one of the at one of the community

2:32:20meetings, a parent came up to me. This

2:32:22was a community meeting at the the

2:32:27Mitchell Park Community Center when when

2:32:29the ideas were first being expressed for

2:32:32having a location. He said that a child

2:32:36a tunnel would make his child going to

2:32:39school much safer. Right now he's very

2:32:42uncomfortable having his child having to

2:32:44bike across Oregon Expressway. If a

2:32:47child is able to able to bike or walk

2:32:51through the tunnel to get onto Park

2:32:53Avenue, Park Avenue is a very low

2:32:56district, low traffic street. It's going

2:32:58to be a bicycle boulevard, I believe.

2:33:02Hopefully,

2:33:03that would be an easier way for someone

2:33:05to get to school.

2:33:09Secondly, if there are housing that's

2:33:11built in the Fry area, the North Ventur

2:33:15community area, a child would now have

2:33:18to go to Baron Park Schooling crossing

2:33:21El Camino.

2:33:23Whereas, if the tunnel were built, the

2:33:25child would be able to go to El Camello,

2:33:28much closer.

2:33:30So I think that in both those cases I'm

2:33:33speaking on behalf of kids and as Bruce

2:33:36Arthur said I think we needed a um a

2:33:41tunnel in this area for a long time.

2:33:43Thank you.

2:33:44>> Our next speaker is Richard Y followed

2:33:46by Robert N.

2:33:51>> I'll try to be brief. Uh my first point

2:33:53is uh Elorado Avenue is a very very

2:33:56narrow street. So I welcome all the

2:33:58commissioners to take a drive yourself

2:34:01and see uh you know how challenging it

2:34:03is if you try to turn from Elmo Ensville

2:34:06bad it's very rare that you don't have

2:34:08to negotiate with the cars coming uh

2:34:10towards you to figure out the right way

2:34:13to pass each other uh and if we consider

2:34:15adding more traffic and the pedest more

2:34:18vehicle and pedestrian traffic uh to the

2:34:20same street where the traffic light is

2:34:22going to be it's going to be even worse.

2:34:23Second point is um uh with Elorado so

2:34:26close to K Avenue uh it's hard to

2:34:29believe that it is the most optimal

2:34:31location to add a second crossing

2:34:33especially if it's meant to serve the

2:34:35entire South Palatoto. Uh that you know

2:34:39um uh we're we're talking about about

2:34:42two miles from Oregon Expressway to San

2:34:44Antonio and and this is spot that we

2:34:46found to be the most optimal location

2:34:48that doesn't seem to be very convincing.

2:34:50The third point is um looking at the

2:34:52price tag that we're planning for this

2:34:53item, right? We plan to spend 70 plus

2:34:56million dollars on this project. Uh we

2:34:58should spend it wisely and we shouldn't,

2:35:00you know, settle for something that is

2:35:02just convenient, right? It has to it has

2:35:04to make the most sense. So I urge

2:35:06commissioners to uh seriously consider

2:35:08the hyper hyper plan. Thank you.

2:35:12>> Our next speaker is Robert N followed by

2:35:13Ryan G.

2:35:17>> Thank you and good evening.

2:35:19I'm really glad to see this project

2:35:21coming to PTC this week. The vision of

2:35:23an additional bicycle pedestrian

2:35:25crossing at California on across the

2:35:28Calra Alma corridor in the visit

2:35:30vicinity of Elorado on Lum or Lomover

2:35:33has been on Palo Alto's active

2:35:35transportation plan

2:35:38for at least 20 years and this project

2:35:39will be the f is the first to take a

2:35:41serious look at how to implement that. I

2:35:44think this will benefit active

2:35:46transportation trips across the corridor

2:35:48from Midtown to El Camino Royale and the

2:35:50research park and also from Baron Park

2:35:52and Ventura to the Midtown shopping,

2:35:54Midtown parks and athletic fields.

2:35:57A couple of inputs. First, the

2:35:59California Avenue Tunnel is really

2:36:02substandard. If we want to talk about

2:36:05another place to spend $70 million, it

2:36:07would be on rebuilding the California

2:36:09Avenue tunnel to to regular standards.

2:36:12So depending on that is not a great idea

2:36:14and actually the process of getting

2:36:15across Oregon is not a great thing

2:36:17either if there's a much more direct way

2:36:18to get across. The second is that the

2:36:22proposed hybrid to um LMA does add

2:36:25significant distance. I'm glad the city

2:36:27staff city report mentioned that many

2:36:30track trips will be a half mile longer

2:36:33be by having to go divert all the way

2:36:35over to Lomo Verde and then perhaps go

2:36:37back over towards El Camaro El Dorado to

2:36:39get finish their trip.

2:36:42So I think the grade at grade crossing

2:36:45at Elorado is one of the two original

2:36:47options that's worth bringing to the 15%

2:36:49design and there fact and uh other I

2:36:53think you should give staff flexibility

2:36:54to consider other things for example uh

2:36:57signalized pedestrian and bicycle only

2:36:59crossing somewhere between El Dorado and

2:37:02El Carmelo avenues with widened

2:37:03sidewalks on both to connect to both El

2:37:07Dorado and Car El Carmelo so that the

2:37:10additional crossings single would have

2:37:11little impact on traditional on

2:37:13vehicular traffic in the neighborhood

2:37:16and or waiting to find someone willing

2:37:18to sell a house near Loie. Thanks.

2:37:22>> Our next speaker is Ryan G followed by

2:37:24Lori G.

2:37:28Evening Chair Chang and commissioners.

2:37:30My name is Ryan and I'm speaking as the

2:37:32chair of the Midtown Residents

2:37:34Association. Uh we live across from

2:37:35Hoover Park. I have two kids, one who

2:37:37bikes to JLS and one who bikes to Pali.

2:37:40So Midtown supports the goal of creating

2:37:43a safe bicycle and pedestrian crossing.

2:37:45However, we do not support either El

2:37:47Dorado alternative A1 or A2.

2:37:51So more than 300 neighbors have signed a

2:37:53posit a petition opposing these

2:37:55proposals and me many residents

2:37:57participated in Sunday's meeting. Now

2:38:00that kind of response reflects the deep

2:38:02concern in the community about this

2:38:04project. El Dorado is, as we've heard,

2:38:06an unusually narrow road, 27 ft, with

2:38:10some segments so constrained that a

2:38:12single parked car or trash cans left out

2:38:15and turn it into a one lane road.

2:38:18Now, both proposals would significantly

2:38:20affect traffic circulation, parking,

2:38:23driveway access, and potentially

2:38:25emergency access.

2:38:27We believe there is a better approach to

2:38:30Midtown supports further consideration

2:38:32of the hybrid plan that's been discussed

2:38:33tonight which could provide the needed

2:38:35connection while avoiding many of these

2:38:37impacts.

2:38:38We urge the commission not to advance A1

2:38:42or A2 and instead further evaluate the

2:38:45hybrid plan and other alternatives.

2:38:47Thank you.

2:38:49>> Our next speaker is Lori G followed by

2:38:51Paul G.

2:38:54>> Said what I wanted to say. Our next

2:38:57speaker is Paul G.

2:39:06>> My name is Paul Goldstein. I am a former

2:39:09member of uh Payback. I just want to um

2:39:14several of the previous speakers have

2:39:17said much of what I wanted to say. This

2:39:19plan has uh this crossing has been on

2:39:22the plan. It's been desired for at least

2:39:2520 years. So the entire time I was on

2:39:28payback, it was the South PaloAlto

2:39:30bicycle crossing. Everybody

2:39:34wanted it. It was high priority for the

2:39:35people in the south. And when uh the

2:39:38alternatives were presented to council,

2:39:40this alternative on El Dorado was the

2:39:43clear winner. Um is it perfect? It is

2:39:47not perfect, but it is lower cost than

2:39:50any of the other and it is most likely

2:39:52to be built sooner than any of the other

2:39:55plants. I want to emphasize that speed

2:39:57is important in this situation because

2:40:00the crossings at Meadow and at um at at

2:40:06Churchill and at Charleston are likely

2:40:08to be closed for extended periods of

2:40:11time while we navigate the road

2:40:15crossing, the railroad crossing that has

2:40:18only been going on for maybe 15 years um

2:40:22and probably has another 15 years to go.

2:40:25The concern about a traffic light at El

2:40:27Dorado I certainly get. But as staff

2:40:30mentioned, the configuration of that

2:40:33light is totally undecided. It could be

2:40:35a pedestrian bike light only, which

2:40:38would not drive uh vehicular traffic to

2:40:42it. Um so the cons and as far as

2:40:46narrowness of streets, one of our nice

2:40:48bicycle boulevards is Castileo Street

2:40:51right opposite Alley High. That is a

2:40:54very narrow street. I don't know if it's

2:40:5627 feet wide, but it is certainly no

2:40:59wider than 3030. And it is a totally

2:41:02adequate bicycle boulevard.

2:41:06Thank you.

2:41:09>> Our final speaker is on Zoom. Uh Euan,

2:41:12uh you may now speak.

2:41:18>> I won't be speaking tonight. Thank you.

2:41:23Uh then through the chair uh that

2:41:24concludes public comment on this item.

2:41:26>> Okay. Thank you everybody for coming out

2:41:30tonight and thank you so much for your

2:41:32public comments. We really appreciate

2:41:33them. We're going to take a 7 minute

2:41:36break right now and then resume

2:41:38discussion.

2:54:01Welcome back everyone.

2:54:06>> All right, welcome back everyone. We're

2:54:07going to get started again here.

2:54:15>> Okay, so I thought here um so just so

2:54:17that everybody is aware once we're

2:54:20finished with public comment. So, we're

2:54:21closing public comment now and the

2:54:23discussion is going to come back to the

2:54:24commission. Uh, we're going to start

2:54:26with commissioner questions so that

2:54:29because I'm sure a lot of us have them.

2:54:31So, light it up, please.

2:54:37Commissioner Tumbleton.

2:54:39>> Hello. Thank you. Um, thank you very

2:54:43much to everybody in the community who

2:54:44came out and it was really good to hear

2:54:46our biking activists and our

2:54:48neighborhood community organizers.

2:54:50Um,

2:54:52one of the questions that I have that

2:54:54I'd like to start with, um, is a

2:54:56question of staff. And, um, this is just

2:55:00reflecting off the comments we heard in

2:55:02the public comment. Um, what is

2:55:07what is the reason that the California

2:55:10Avenue underpass, which is everybody

2:55:14seems to agree is subpar, is not been

2:55:18repaired or brought up to to code.

2:55:25Um, it has not been put on the the

2:55:28capital budget yet. um it is in our list

2:55:32of things that we are trying to push

2:55:34through the pipeline to add it at some

2:55:37point in the future when when that gets

2:55:39um added to the budget.

2:55:40>> And is that something that the $80

2:55:43million that is being discussed here

2:55:45could be used to do instead?

2:55:48>> That would be a different project. Um so

2:55:52just in terms of potential funding

2:55:54sources um uh a pedestrian bicycle

2:55:59crossing underneath the tracks um south

2:56:03of Oregon is something that has been

2:56:06listed in the ballot measure for measure

2:56:08B um the you know VTA's measure B. So,

2:56:11so that source would not be suitable for

2:56:15something north of Oregon, but it could

2:56:18be, you know, there are other sources

2:56:20that we would also be seeking for any uh

2:56:23project that moves forward.

2:56:26Okay. So, these are separate things, but

2:56:29um how when's the last time council has

2:56:31been asked to fund

2:56:34improving the crossing that already

2:56:36exists

2:56:38that is subpar such that many people

2:56:40avoid it? Um so as part of the bicycle

2:56:43pedestrian transportation plan that was

2:56:46identified as a project on on the rather

2:56:49long list that we have of um of projects

2:56:52throughout the city and also we did

2:56:55raise it during the last capital budget

2:56:57go round um for an outside year. So

2:57:01>> an outside year

2:57:02>> it means it's not it hasn't been

2:57:04approved for this year but we we raised

2:57:07it as something that we would like to uh

2:57:09consider in a future year. So, we're not

2:57:11thinking 5 years ahead. We want to have

2:57:13it in the pipeline for the future.

2:57:15>> Cool. And so, for the scope of today's

2:57:18meeting, um we're focusing on um I'm

2:57:23asking for validation here. We're

2:57:24focusing on a South Paling. That is not

2:57:27it. And that also hasn't been funded,

2:57:30but could we include it in our motion to

2:57:33encourage council to fund that somehow

2:57:38or

2:57:38>> We welcome your comments if that's one

2:57:40of them.

2:57:41>> Well, I'm I'm specifically asking if

2:57:43it's disallowed. So, it sounds like not

2:57:46disallowed. So, that's great. Um, okay.

2:57:49And then the other thing um that came up

2:57:52um we had some really good comments by

2:57:54people who have been studying um biking

2:57:57and pedestrians uh uh movements here in

2:57:59PaloAlto and I really appreciate that.

2:58:01One of the things that came up um is

2:58:05crossing Oregon is hard and dangerous

2:58:08and scary. Um,

2:58:11is that something that is also on the

2:58:14the payback plan

2:58:17to make it easier for people to access

2:58:19the existing tunnel?

2:58:27Does staff agree that it's hard to cross

2:58:30Oregon

2:58:32>> from Midtown? I think we're consulting

2:58:34to see whether we it was part of the

2:58:37existing bike ahead plan. So as as part

2:58:41of the um the safety action plan um

2:58:45Oregon was identified as part of our

2:58:47high injury network. So it's something

2:58:49that we could consider as like a an

2:58:51intersection improvement

2:58:54>> but but it's not it's a county facility.

2:58:57So we would be we would need to work

2:58:59with a county. Oh,

2:59:01>> it's a C. That's great. That means

2:59:04contacting your supervisor

2:59:07will help uh in addition to contacting

2:59:10council. That's good to know. Thank you

2:59:11for clarifying that. Um Supervisor

2:59:14Margaret Abika. Um okay. So then um did

2:59:20staff consider at all closing the

2:59:24intersection from El Dorado to Alma so

2:59:28that bikes and pedestrians could go and

2:59:31cars could not go as part of this whole

2:59:34thing.

2:59:37I didn't see it on the plans those it

2:59:39wasn't A or B or A1 and A2.

2:59:44>> Yeah. So just to make sure you said

2:59:45Elorado closing Elorado, is that right?

2:59:48>> That intersection with all my

2:59:49>> intersection. Yeah. So one of the

2:59:51variants looked at a culde-sac option

2:59:53>> um on El Dorado and that would close it

2:59:56for um uh that was a variation of

2:59:59alternative A2.

3:00:00>> Okay.

3:00:01>> And uh would close to vehicles but allow

3:00:03um uh cyclists and pedestrians to access

3:00:06the tunnel and go underneath Elma and

3:00:08the uh Cal Train tracks.

3:00:09>> And was that one you guys wanted us to

3:00:11consider? It wasn't presented. So, I'm

3:00:14guessing no, and if not, why?

3:00:15>> Uh, it's mentioned in the staff report,

3:00:17and you're welcome to uh putage it. Um,

3:00:21>> I mean,

3:00:23I I I am trying to ask you to just speak

3:00:26it out loud, but if you want me to read,

3:00:27I'd like to know where.

3:00:29>> Um, if I recall correctly, I think that

3:00:31this was one that the fire department

3:00:33was didn't want. That's exactly the

3:00:35answer I was looking for. Thank you. Um,

3:00:38okay. So, and then um

3:00:44the last question is the bike path along

3:00:48Alma that was proposed by the community.

3:00:51Is that one that needs that is first of

3:00:55all, is that feasible? It sounds like

3:00:57possibly yes. We'll have to investigate

3:00:59more. Is that correct?

3:01:02>> That's correct assessment.

3:01:03>> And could it go all the way down? Like

3:01:06does it have to stop at Lomma Verde or

3:01:08is that something we could and is that a

3:01:10cow train project or a city project?

3:01:14>> So do you mean what do you mean go all

3:01:16the way down?

3:01:17>> So right now I believe biking is not

3:01:21encouraged on Alma, right? But if we

3:01:25wanted to provide a facility adjacent to

3:01:28the tracks for bikes, could it go from

3:01:32Oregon all the way down to Charleston?

3:01:35Is there any reason it has to stop at

3:01:36Lomma Verde? Like if we were to get

3:01:39excited about this or to discuss it or

3:01:41recommend it, do we have a constraint

3:01:43that it has to stop somewhere?

3:01:45>> That I think that that's a possibility.

3:01:47And um just to refer back to the bicycle

3:01:49pedestrian transportation plan um as

3:01:52part of that plan, there was um a

3:01:56facility along Alma near San Antonio

3:01:58station.

3:02:00So, if you want to go even further, it

3:02:02would may connect to something in the

3:02:04future.

3:02:05>> I love that suggestion. Uh, okay, that's

3:02:07all my questions for now. Thank you.

3:02:12>> Uh, I'm not seeing other lights, so I'm

3:02:13going to go. Um,

3:02:16okay. So, was there So, sounds like

3:02:21council had had, you know, had asked

3:02:24staff to look at a light at Elorado and

3:02:27then a tunnel in the vicinity. Um, was

3:02:31El Carmelo ever considered or Matadero

3:02:35Creek and could you speak to those a

3:02:37little bit more?

3:02:41>> So, uh, connections to Madera Creek and

3:02:44El Cornelo were considered. Um, the and

3:02:47that was part of an A2 variation. So,

3:02:49the A2 variation is full grade

3:02:51separation under Elma and Cal Train

3:02:53tracks. the the real challenge there

3:02:55with the connection to Lom Verde and and

3:02:58the Manadero Creek are the uh driveways

3:03:01on um the east side of Alma Street.

3:03:05There are several and many of them

3:03:07connect to multif family housing. So um

3:03:10when you cut off access to a driveway,

3:03:12you're essentially essentially uh

3:03:14preventing any vehicular access to that

3:03:17residential complex. So those options

3:03:20were ruled out and were in advance since

3:03:21part of our evaluation. Okay. And then

3:03:24was there ever one that looked maybe as

3:03:26at using Matadero Creek

3:03:31um not necessarily coming up at Elma but

3:03:34just making the entirety of Matadero

3:03:37Creek a bike path.

3:03:42So, uh, that was so part of the Matador

3:03:45Creek idea is part of a 2016, um,

3:03:49Midtown,

3:03:51uh, connector study. I'm not quite

3:03:53getting that name right. Um, and so

3:03:57that's sort of where that idea

3:03:59originally was explored. Uh, the

3:04:02challenge there is what do you do once

3:04:03you get to Alma Street and the Cal Train

3:04:06tracks? How do you get across? um when

3:04:09you're looking at I don't know if

3:04:10there's a visual we can potentially pull

3:04:12up to look at that and if if that's

3:04:13helpful I'm happy to kind of do that.

3:04:15>> Yeah, I think that would be helpful.

3:04:16>> I think it's actually

3:04:18>> Yeah.

3:04:20>> Yeah. there at the very the very last

3:04:22slide. Um, I just threw in a aerial map,

3:04:30slide 81.

3:04:38So, it's somewhat difficult to see here

3:04:39when it comes up, but you'll see that

3:04:41along the Madera tree creek canal on the

3:04:43north side, um, there's space until you

3:04:47get to right at Elma Street. And this

3:04:49maybe isn't the best photo, but um right

3:04:52at that point where you see there's a

3:04:54residential unit just to the north on

3:04:57that corner where Manad meets Alma

3:05:00Street. That's a 4-unit residential

3:05:02property. And just south of that in the

3:05:04meta in the in the canal is a um an

3:05:07access route for maintenance vehicles,

3:05:09valley water maintenance vehicles. And

3:05:11so what that basically, you know, what

3:05:14that says is that if we were to try to

3:05:16make some kind of a connection from

3:05:17Manadero Creek to Alma and and somehow

3:05:20across the railroad tracks in this area,

3:05:22you would need to acquire that 4unit um

3:05:25residential property at that location.

3:05:29>> Okay. So, just to be clear, this

3:05:31wouldn't talk about tunneling under Elma

3:05:33Street alongside the creek or in order

3:05:37to tunnel, you need to acquire that

3:05:39property. Is that what you're saying?

3:05:41No, this is just at grid just to get to

3:05:44Alma Street and then from there we're

3:05:46Yeah, even once we got to that point it

3:05:49we sort of ruled that out as an option.

3:05:51>> Is there ever an option looked at that

3:05:53would put a tunnel at Matadero

3:05:57like at the creek

3:06:00>> underneath Elma and the road tracks.

3:06:02>> So I think similar type of concerns

3:06:06would arise as part of that. So you're

3:06:07needing to start to tunnel down

3:06:09somewhere along the Medadel Creek and

3:06:11now we're within valley water water

3:06:13right of way that becomes very

3:06:15challenging. Um I would invite uh Jaggy

3:06:18from BKF on the line if he wants to kind

3:06:20of expand on this. He's been part of uh

3:06:23other rail crossing projects has been

3:06:24involved in this so he's he's got the

3:06:26engineering background and can probably

3:06:28speak to this better than I can.

3:06:35>> Hello. Good evening. Um, just to, you

3:06:37know, expand on, uh, Charlie's

3:06:39commentary, uh, we did look at trying to

3:06:42squeeze in an, uh, an alignment at the

3:06:44Matador Creek crossing. Uh, we found it

3:06:47to be geometrically infeasible. Um,

3:06:50there are several constraints on the

3:06:52west side of the Cal Train corridor. Um,

3:06:55there's a small sliver between Matadero

3:06:57Creek and where the the railroad tracks

3:06:59are located. uh but it's just not wide

3:07:02enough in order to uh build the tunnel,

3:07:05you know, uh underneath the crossing. Um

3:07:07based on the methodology that we're

3:07:10assuming with the bor and jack, there's

3:07:11just not enough room to get those uh

3:07:14areas in there to squeeze a tunnel box

3:07:16underneath both and then come back up to

3:07:19grade. Um on the east side there are

3:07:22similar challenges because uh Valley

3:07:24Water has a maintenance pathway that

3:07:27runs from Alma down to Madera Creek for

3:07:30their maintenance purposes. We would be

3:07:32completely eliminating that access um in

3:07:36order to squeeze something in there as

3:07:38well as complicating some of their uh

3:07:40maintenance operations further to the

3:07:42east where um it runs parallel to the

3:07:46the canal. So, we eliminated any grade

3:07:49separation alternatives at this location

3:07:51for those reasons.

3:07:53>> Thank you. Okay. And then I had a

3:07:57question about um

3:08:00whether the utility impacts are the

3:08:02same.

3:08:05So, there's the tunnel option, A2

3:08:07option, there's some significant utility

3:08:10impacts. Are those the same anywhere

3:08:14along the tracks or is it specific to

3:08:16the Elorado location? In other words, if

3:08:18it were at Lamarie, would there be the

3:08:21same concerns?

3:08:25>> So, again, I'll I'll tee up joggy to um

3:08:28to expand or correct me if I'm wrong,

3:08:31but uh when we're looking at the

3:08:33city-owned utilities um on Alma Street,

3:08:36they're located along the entire stretch

3:08:38of Alma Street. So it would be the same

3:08:40concern for all of the alternatives that

3:08:42we looked at.

3:08:43>> Okay. Then the follow-up question to

3:08:45that is that back when we were looking

3:08:47at eight options, there was a hypothesis

3:08:49that

3:08:51um construction at Lom Verde would be

3:08:53more expensive than at Elorado.

3:08:58Is

3:09:00is that still the case given what we

3:09:02know now with the additional cost

3:09:04implications?

3:09:05Um,

3:09:08and if so, do you have a sense of what

3:09:10that order of magnitude is? Is it like,

3:09:12oh, we would now be 120 million over at

3:09:15Lovery?

3:09:18>> So, it depends on which um it depends on

3:09:21which alternative you're

3:09:22>> so comparing say tunnel to tunnel,

3:09:25>> right? Yeah.

3:09:26>> Yeah. So, there's there were two options

3:09:27for lom verde uh B and C. B at B I

3:09:32believe was the full grade separation

3:09:35with a connection down the middle of LMA

3:09:38verde and then a signal at um at Alma

3:09:42would be alternative C. I think the

3:09:44alternative C option would be relatively

3:09:48comparable to what we're looking at for

3:09:50alternative A1. uh it's a tunnel with a

3:09:54signal, but it's we're still, you know,

3:09:57there's a lot of assumptions built into

3:09:59these calculations at at these point and

3:10:01these uh cost estimates that been

3:10:03prepared for A1 and A2, but relative

3:10:06order of magnitude, they'd be similar

3:10:08because they're basic design concepts

3:10:10are similar. Having said that, there are

3:10:12many challenges that we might might

3:10:14encounter when we actually go down and

3:10:16explore, you know, what's actually

3:10:18underground. What type of soil is there?

3:10:20And I'm sure again Jogie could speak to

3:10:22this much more clearly if that's

3:10:23something you're interested in.

3:10:25>> Do we want to hear

3:10:29we're interested in hearing? Yeah, I

3:10:30mean I I I like Mono Verde like the

3:10:33first time around from this uh just

3:10:35because of the connectivity and because

3:10:37the we've heard a lot about sort of

3:10:39suite. Um and so I guess I would like to

3:10:42kind of know a little bit more about

3:10:43like are there problems with the

3:10:45landing, you know, location

3:10:48if you did a lama verde tunnel or even

3:10:53a light crossing and then a tunnel under

3:10:55the the railroad.

3:10:58So it might be helpful um to pull up

3:11:01slide 47 and then we can toggle between

3:11:0447 and 48. So these are the original

3:11:08concepts at LMovery Avenue uh that were

3:11:10presented to you last time. Um and with

3:11:13that, Jogie, I'm not sure if if uh you

3:11:16wanted to kind of expand on some of the

3:11:17cost considerations that were put into

3:11:19the original estimates for B and C.

3:11:22That'd be helpful.

3:11:23>> Yeah, absolutely, Charlie. Um I I think

3:11:25you captured it pretty correctly. The

3:11:27rough order of magnitude for both

3:11:30options are pretty comparable to what we

3:11:33came up with at um El Dorado. So um you

3:11:38know what's shown on the screen right

3:11:39now considered grade separating the Cal

3:11:42Train corridor and Alma Street with a

3:11:46ramp that would come up in between uh

3:11:49Loma Lomma Verde Avenue. Um this cost

3:11:52would be very comparable to what you see

3:11:54in A2.

3:11:56um because we're great separating both

3:11:58um the Cal Train Corridor and Alma

3:12:00Street. I I think the the added

3:12:03difference here is on the west side

3:12:04where we need to build a structure in

3:12:07order to ramp up from the tunnel um in

3:12:10order to connect up to Park Boulevard

3:12:13and then the rightway impacts come into

3:12:15play on the west side with full

3:12:16acquisitions versus the partials that

3:12:19are considered um at the Elorado

3:12:22location.

3:12:23And then conversely, you know, if you

3:12:26look at um alternative C, which was at

3:12:30the Loma Verde um location, that cost

3:12:34would be comparable to what you're

3:12:37seeing with alternative A1. Um we're

3:12:40essentially just great separating the

3:12:42Cal Train corridor here. Um, so you

3:12:47avoid all the complexities with having

3:12:49to go underneath Alma and those utility

3:12:51impacts, you know, that were previously

3:12:53described, but you're coming back up to

3:12:55grade in that uh landscaping area

3:12:58between the Cal Train Corridor and Alma

3:13:00Street. So, you'll need um similar types

3:13:03of structures at that location. Um and

3:13:06then you know again on the west side you

3:13:08have um a couple more complications

3:13:11given the rightway impacts and

3:13:12additional structures to get back to

3:13:14grade up here. But I think if you wanted

3:13:16to make you know a rough comparison to

3:13:20El Dorado, you can compare them back to

3:13:23the A1 and A2 alternatives respectively.

3:13:27And do you have a sense of what parcel

3:13:30impacts would be on the east side if it

3:13:33were at Lmer Verde? Maybe can't speak to

3:13:38that without fully designing it out.

3:13:42>> Well, we did look at it

3:13:43>> for the tunnel. For the tunnel. Yeah.

3:13:45>> Yeah, we we did look at it um you know,

3:13:48at a high level. I I think with

3:13:50alternative C that you see here, the

3:13:52east side doesn't have any of the

3:13:54property impacts. um we're staying

3:13:56within the public rightway um in order

3:13:58to get back up to grade. Um alternative

3:14:02B assumed utilizing the public right

3:14:05away with the ramp coming up in in the

3:14:08middle of the roadway and then having

3:14:10the two-way traffic go around it. So um

3:14:14there there weren't any, you know,

3:14:17property impacts on that side in order

3:14:19to conform. Granted, the configuration

3:14:21of Lomma Verde and how it operates would

3:14:24be altered in that, you know, a lot of

3:14:26the properties would have right in right

3:14:28out driveway access um around the ramp

3:14:31that's coming up to Great.

3:14:34>> Thank you. Very helpful. I'm going to

3:14:36stop with my questions and let Vice

3:14:37Chair G ahead.

3:14:40>> Thank you. Um, since we're on the slide,

3:14:42do you have a sense of how many parcel

3:14:45impacts would be on the west side here

3:14:48on alter alternative B?

3:14:52>> Uh, we assume two.

3:14:54>> Two. Two. So, the um and it would be too

3:14:56full compared to A2 which is two

3:14:59partial.

3:15:01>> Yeah. And maybe I can just kind of jump

3:15:03in here and expand. So, we you know, at

3:15:06the conceptual level, we're showing two,

3:15:08but it could be more. And so that's why

3:15:10we show the partial impacts and then we

3:15:11have the potential partial impacts

3:15:13recognizing that this is a very

3:15:15constrained space at the Lom Verde

3:15:18location between Park Boulevard and the

3:15:20railroad tracks compared to other

3:15:21locations on the corridor. They're very

3:15:23close together and the parcels

3:15:25themselves are smaller comparatively to

3:15:27other parcels along the corridor. Um and

3:15:30again these are conceptual. There are

3:15:32still many unknowns and it may require a

3:15:34bigger footprint when we actually look

3:15:35at constructibility. And that was part

3:15:37of the conversation that we had uh with

3:15:40council last year.

3:15:42>> Okay. Thank you. And then I had a

3:15:44follow-up question about the the mad

3:15:47creek. If you could pull that back up.

3:15:56So, just to kind of tee off the

3:15:59conversation here, are you saying that

3:16:02any tunnel underneath

3:16:04the Cal Train or Elmo at the tunnel at

3:16:08the creek would be very difficult or is

3:16:09it mostly the coming back up to grade

3:16:11portion that would be difficult?

3:16:15Or both?

3:16:18>> Charlie, I'll I'll jump in and take

3:16:19this. Um, I'm saying both. it it's it's

3:16:22extremely challenging to

3:16:25uh get an alignment in there and

3:16:27furthermore to construct it especially

3:16:29given the constraints on the west side

3:16:31with the creek configuration and where

3:16:34the tracks are located

3:16:37>> because I'm just kind of I'm not nearly

3:16:40studied this as much as you but I think

3:16:42there if the coming up to grade is the

3:16:45main problem at the creek I think there

3:16:47could be some potential

3:16:49experimental ideas that I just have out

3:16:51there, which is for example, we could

3:16:53just follow the creek further up and

3:16:55kind of wrap around to go into park. We

3:16:56could maybe leverage some of the land at

3:16:59the power plant if that's an issue on

3:17:01the west side. And on the east side, I

3:17:03know that you've mentioned that the

3:17:04there's a valley water accessible ramp

3:17:06for their maintenance, but maybe a crazy

3:17:10idea could be to extend the bike path

3:17:12along the creek to Bryant or something.

3:17:14So, I know that you mentioned that like

3:17:17the actual crossing at the train tracks

3:17:20in Elma is like a big consideration, but

3:17:24if there are issues to coming at grade,

3:17:26I think that there may be other creative

3:17:28solutions. I was just curious if you'd

3:17:30looked into any of those.

3:17:33>> Yeah, I can um maybe provide a little

3:17:35bit of clarification on a couple of the

3:17:37ideas you just raised. You know, one

3:17:39concern here is that we've heard from uh

3:17:41Cal Train that there's the desire to

3:17:43have the fourtrack configuration. Um I

3:17:45believe it's from uh Churchill to

3:17:48Meadow, so right in our study area. Uh

3:17:51and so in the future, Cal Train would be

3:17:54uh running four tracks through this

3:17:56area, which essentially means we need to

3:17:58be really careful not to propose

3:18:01anything that's within their right of

3:18:03way, at least at this early stage. um

3:18:06because we we suspect that that's going

3:18:08to be a very difficult conversation

3:18:10considering that kind of being in their

3:18:11future plans and what they've

3:18:12communicated to us so far. We haven't

3:18:14had any of those um uh potential

3:18:17right-of-way use con uh conversations

3:18:19with them specifically, but at this

3:18:22early stage we're we're starting with

3:18:23can we do something within the own

3:18:25within the city's right of way first and

3:18:27see what's potentially possible. Um the

3:18:30other thing you mentioned too is use of

3:18:32the substation and that um just to the

3:18:35the um right adjacent to Park Boulevard.

3:18:39Um uh this was something that was

3:18:40mentioned as part of that Midtown

3:18:42connector feasibility study that 2016

3:18:44study that I was mentioning earlier and

3:18:47uh providing the connection along the

3:18:49creek and then uh they showed three

3:18:51different options for what you could do

3:18:53uh to connect all the way to Park

3:18:55Boulevard. Two of those connection

3:18:56options use portion of the substation.

3:18:58And we have uh since then have had

3:19:00conversations with the utilities

3:19:01department uh who owns this. This is a a

3:19:04city-owned facility and had strongly

3:19:07advised that we do not um uh propose to

3:19:10build anything within this uh within

3:19:12this property and the land there. Um

3:19:14there's many reasons and I'm happy to go

3:19:16into that and I even have a backup slide

3:19:17if you're interested in learning more.

3:19:19Uh but it's all very uh yeah electrical

3:19:22technical type jargon stuff.

3:19:24>> We want the backup slide.

3:19:26Yes,

3:19:26>> you can open up slide 79.

3:19:32>> He's got it already. So, uh the key kind

3:19:34of feedback was that the the rightway

3:19:36should be avoided. This is and there

3:19:37were seven reasons uh to support that

3:19:40kind of conclusion. First is that this

3:19:42is a critical city facility and any kind

3:19:45of work within uh the substation would

3:19:48require um u turning off the power plant

3:19:52and this power plant uh provides

3:19:54electricity to half of the city is what

3:19:56I'm what I'm told. Um there is many

3:19:59equip there's much equipment within uh

3:20:01the property including underground

3:20:03facilities that are not visible and were

3:20:05not apparent as part of this early 2016

3:20:08study and it would be very difficult to

3:20:10move and consolidate any of that

3:20:11equipment. Um another kind of

3:20:14perspective that they brought that uh we

3:20:16hadn't considered was that space must be

3:20:17retained for maintenance and potential

3:20:20future growth. Uh electricity and

3:20:22building out the electrical grid in Palo

3:20:23Alto is a is another priority. Um and uh

3:20:26so they kind of uh recommended that

3:20:28being another reason why we don't use

3:20:30some of that space that from an aerial

3:20:32looks to be available. Uh and and then

3:20:34they sort of uh suggested that this is

3:20:36not an appropriate setting for bicycle

3:20:38and pedestrian activity uh considering

3:20:41there's lots of high-owered electricity

3:20:44in this area and there are certain

3:20:46safety standards that uh you need to

3:20:47keep uh buffers. I don't know the

3:20:49specifics of what those buffers are um

3:20:52but that was also part of the

3:20:53conversation.

3:20:56Thank you. Um, I actually had a question

3:21:00about another thing that you said, but

3:21:01if any of the other commissioners had a

3:21:03question about the utility,

3:21:05you can jump on here or I'm going to

3:21:07move on to another thing that Charlie

3:21:08had said.

3:21:11Okay. I think your faces are really

3:21:13small, so I'm just going to move to my

3:21:15other question.

3:21:16>> Go ahead. Go ahead. which is so one

3:21:20thing that really stuck out from what

3:21:22you just said Charlie is that Cal Train

3:21:25wants to put the four track uh

3:21:28potentially put four tracks in our

3:21:29section. Wouldn't that really impact the

3:21:34proposal from the neighbors about the

3:21:37hybrid plan? Because if you were to want

3:21:42to put four tracks, there would be no

3:21:43longer any space for a bike path along

3:21:47the Cal Train alignment, right?

3:21:51>> So all of the designs that we had

3:21:53proposed uh that use that uh planted

3:21:56median strip between the railroad tracks

3:21:58and Alma Street is from uh from what we

3:22:01understand within the city's property.

3:22:04So we are we are working outside of

3:22:06Calr's right of way. So that would not

3:22:08be um that would not be a concern.

3:22:11>> No, no, my question is for the one that

3:22:12the neighbors have proposed the like

3:22:15hybrid plan. So that would also be

3:22:17outside of the Cal Train right away.

3:22:20>> That's correct.

3:22:22>> Okay. So that's really helpful because I

3:22:24was a little bit worried about that.

3:22:26Okay. Um those are the ends of my my

3:22:27questions for this round and I'll let

3:22:29the commission continue.

3:22:31>> Commissioner Aken.

3:22:34>> Thank you, Chair. Um,

3:22:37if you travel west through the Homer

3:22:40tunnel from downtown, one of the first

3:22:43structures you see after you've gone

3:22:44under the tracks is a standalone

3:22:47elevator unit

3:22:49and it's about well by 15 ft. You could

3:22:54probably fit two people and two bikes in

3:22:56there. Um, so in looking at some of the

3:23:01concerns with A2,

3:23:04um, I began to wonder if a somewhat

3:23:07larger elevator unit, uh, that could fit

3:23:10in the, um, in the space along Alma near

3:23:16El Dorado,

3:23:18uh, would be viable as a way to get

3:23:21people down to and up from a tunnel.

3:23:26Um the reason this is interesting uh is

3:23:29that it eliminates the need for parcel

3:23:33acquisitions. Um it eliminates the

3:23:35emergency emergency access concerns. It

3:23:39eliminates the driveway u diversions.

3:23:43Um and it eliminates the need for a

3:23:45signal on Alma.

3:23:48So the question I have for you is, is it

3:23:51worthwhile pursuing

3:23:54um mechanical systems as an alternative

3:23:57to ramps to get people up and down?

3:24:00>> Um maybe I can respond to that. So um in

3:24:05terms of some of the parking work that

3:24:07the city does, we have elevators in

3:24:09places that don't have many people in

3:24:11them at nighttime. We get a lot of

3:24:13damage to those. So, as staff, I don't

3:24:16think that we would be recommending

3:24:18an elevator like a mechanical system in

3:24:21a place that has not got a lot of eyes

3:24:24on it 24 hours a day. Um, yeah, it's

3:24:28they become quite unpleasant sometimes

3:24:30as well.

3:24:32>> Okay. Yeah, the security concerns

3:24:34bothered me uh as well because you have

3:24:37to come up with a way to have adequate

3:24:39visibility uh particularly at the tunnel

3:24:42level. Um but

3:24:46it given the advantages it might be

3:24:48worth seeing if there is some solution

3:24:51that's u active rather than passive.

3:25:00>> Commissioner Templeton.

3:25:02>> Thank you. Um, yeah, there's no no

3:25:04reason to limit that to to working with

3:25:06the tunnel as well. If you're if you

3:25:10think about the cost comparison to going

3:25:12up three stories in an elevator versus

3:25:14building a tunnel, you could do Cher

3:25:17Chang's idea of going over as well. So,

3:25:20if if an elevator were to be considered,

3:25:22it sounds like there may be some reasons

3:25:24not to do it. Um, the cow train. Uh,

3:25:31just going to throw this out there cuz I

3:25:32I know you're working on this, but we're

3:25:37very constrained with space in PaloAlto

3:25:39and they have lots of space by Central

3:25:41Expressway, one city south. That perhaps

3:25:45would be a better location for the

3:25:49four-way passing lanes. However, um here

3:25:52in PaloAlto,

3:25:54um the wrinkle, I don't remember who

3:25:57just brought it up. Um Commissioner G,

3:25:58maybe. Um the the wrinkle here in Palo

3:26:02Alto is that that any construction we

3:26:04might do may have to interfere with that

3:26:07space. Um, we've looked at, I think it's

3:26:11called the Shoefly,

3:26:13uh, tracks would be going not only into

3:26:16that, um, PaloAlto owned area, but even

3:26:19partially into Alma. Um, so, you know,

3:26:23that that really does, um, constrain us.

3:26:27Um, and then the the thing that I really

3:26:30think we should talk about, u maybe, uh,

3:26:33and I'm gonna try coming at this from a

3:26:35slightly different angle because we've

3:26:37sort of beat Matadero Creek to death.

3:26:39Are there other creeks that PaloAlto has

3:26:41that go under the trains?

3:26:46>> Don't worry, the answer is yes.

3:26:49>> Yes.

3:26:51I'm wondering if we could look at those

3:26:53and consider those because um when I

3:26:56first moved here in um in 2006, I I had

3:27:00to go under the 101

3:27:02uh in the only half a year available

3:27:05bike lanes to the shoreline office park.

3:27:08Um and um you know there was a creek and

3:27:13it was a channelized creek like many of

3:27:14our creeks here in PaloAlto but also it

3:27:17had a bike lane um beside it and it went

3:27:20all the way under um I mean I don't know

3:27:24how wide it is there eight 8 to 10 lanes

3:27:26of of 101. Um and so like it's possible

3:27:31to do these things. Um the the question

3:27:34is um of course could we keep it open

3:27:38all year? Probably not. Certainly the

3:27:40one under 101 we couldn't because it was

3:27:42flooding constantly uh once rainy season

3:27:45started. Um and I do remember um many

3:27:49times in rainy season here watching the

3:27:52the creek levels and it does get up

3:27:54pretty high. So it would not be um a

3:27:57perfect solution, but um it does offer

3:28:03us the chance to imagine

3:28:07if we've already channelized these

3:28:09creeks, what additional engineering

3:28:12could we do

3:28:14that would make this usable in other

3:28:17ways besides flood prevention, which is

3:28:19the primary goal right now to find if

3:28:22there's any transportation options

3:28:23there. I don't pretend to know and I

3:28:25know you guys haven't studied

3:28:27everything, but just to throw that out

3:28:28there because what what I anticipate

3:28:31based on the comments tonight, which you

3:28:33might hear from us, is we don't think

3:28:36that that the identified options are are

3:28:39really going to work for the city. And

3:28:42we want to be able to say, what if you

3:28:44check this out and check this out so

3:28:45that you when you go back to council,

3:28:47you have something um actionable. So,

3:28:50that's sort of what we're trying to

3:28:51figure out. How do we um give you good

3:28:54useful feedback? So, if if there were um

3:28:58other channelized creeks that we should

3:29:00look at or mention, feel free to bring

3:29:03it up. I assume they don't all assume

3:29:05the others don't have power stations on

3:29:08top of them. Um so, that would be

3:29:10something else to investigate. Um and

3:29:13feel free to let us know if you learn

3:29:14any of that during tonight's meeting.

3:29:16Thank you.

3:29:18>> Okay. I did have a few more questions.

3:29:20So, um, some public comments brought up

3:29:22the me mentioned a toxic plume and my

3:29:26quick internet research suggested that

3:29:28that extended possibly 15 to 30 ft deep.

3:29:30Is that something that would increase

3:29:32the costs um or make infeasible a

3:29:35tunnel? Um, and one of the diagrams I

3:29:39saw like there's a pretty big toxic

3:29:41plume right at the end of El Carmelo,

3:29:43but it actually extends

3:29:45all the way possibly to Lumaver. And if

3:29:48you guys don't know the answer, that's

3:29:49just fine. But I just wanted to ask if

3:29:51you what you knew about it.

3:29:53>> If you wouldn't mind opening slide 74,

3:29:55please. Um, so we are aware of uh the

3:29:59the underground plume. Um, so it's a

3:30:02groundwater and coil vapor contamination

3:30:04from historic industrial uses. I believe

3:30:07it was HP or some other computer

3:30:10manufacturing um company. It's common

3:30:13multiple. Yeah, it's uh it's common not

3:30:16just it's it's uh common in I wouldn't

3:30:19say common but they are around in

3:30:21Silicon Valley. Um and uh so we've been

3:30:25coordinating with the planning

3:30:27department uh public works and the Santa

3:30:29Clara County Public Health Department.

3:30:31Um and if this alternative were to

3:30:32advance uh this is uh something that

3:30:34would need to be coordinated with the

3:30:36San Francisco regional water quality

3:30:38board and Kosha to understand the level

3:30:41of contamination and requirements. uh

3:30:43for the project. Um a tunnel can be

3:30:46built uh in or near the plume uh plume

3:30:49area, but it requires additional

3:30:51environmental investigation, engineering

3:30:54controls and and oversight uh during

3:30:56construction. There's a there's a

3:30:57process for this. Um and it's something

3:30:59that the city has done and and other

3:31:01nearby cities have done as well. Uh not

3:31:03for tunnels. Maybe I'm sure there has

3:31:05maybe there has been a tunnel, but um

3:31:07there

3:31:08>> there's been studies and you can you can

3:31:10build on on top of uh the plume and and

3:31:12and there's a process for that.

3:31:14>> And this contamination presumably

3:31:16predates Oregon Expressway. So, it's

3:31:18been done.

3:31:20>> Yeah. Uh and I think to to answer uh

3:31:23your question is is it may uh affect

3:31:26project cost and schedule. It all

3:31:28depends on where the contamination is

3:31:31actually located, it's its levels and

3:31:34and where the project would would be

3:31:37built and what construction methods are

3:31:38used. So um a lot of unknowns at this

3:31:41point uh but it's nothing that causes

3:31:43concern to stop the project.

3:31:46>> Okay, two final questions. one um were

3:31:49there any parking studies done in terms

3:31:51of the parking utilization for the first

3:31:54couple blocks of Elorado, El Carmelo,

3:31:57Lverie coming from um Alma to the

3:32:02east?

3:32:04And then the second question so that you

3:32:06can answer them at the same time um was

3:32:10were there any studies done regarding

3:32:12the impacts of adding a light on to Elma

3:32:16with respect to how far the backup would

3:32:19extend um you know would like as far as

3:32:22Oregon potentially in the loop-de-loop

3:32:25there or any information about that that

3:32:30>> I I can answer the it's basically the

3:32:32same response for both of those

3:32:33questions. Uh the answer is no. We

3:32:35haven't done that yet. Uh we anticipate

3:32:37that being something that would come at

3:32:38a later phase uh to understand the you

3:32:41know uh some of these unintended

3:32:43consequences and and ways to address

3:32:45them um and validate a lot of the

3:32:47concerns that we're hearing from the

3:32:48community.

3:32:50>> Thank you. Okay. So I think that I don't

3:32:52see other light. So I think that's it

3:32:53for my questions and all of our

3:32:54questions. So now on to our comments.

3:32:59Commissioner Hugman.

3:33:04Yeah, thank you. So, I u didn't have any

3:33:07questions of my own, but but I I thought

3:33:09there were a lot of really great

3:33:10questions that have um pulled out a lot

3:33:13of uh good additional information. uh

3:33:15and I want to stay uh thank staff and

3:33:19really their predecessors and ancestors

3:33:23for all the work that brought us to this

3:33:24day because this concept is as reflected

3:33:28in the reports. It it it's been worked

3:33:32on for you know decades and um and and I

3:33:37also want to thank uh uh all the

3:33:39neighbors who galvanized

3:33:42uh on this issue. I've been on the

3:33:44planning commission six and a half years

3:33:46and and this was um I think easily the

3:33:50the the most neighborhood public

3:33:53participants and not only is it your

3:33:57numbers but but you know I I we all I'm

3:34:00sure read all the letters and and they

3:34:02weren't just a form uh there were a lot

3:34:04of different ideas expressed and so we

3:34:07really appreciate that and staff really

3:34:11um uh took notice of that. You can tell

3:34:14because it was very unusual when a

3:34:17neighborhood comes up with an idea sort

3:34:20of late later in uh in the process for

3:34:23staff actually to fold it into their

3:34:26report um their presentation. And so I

3:34:29want to acknowledge that staff did that

3:34:31and let you know that doesn't always

3:34:33happen, but it's a reflection of of that

3:34:35they they listened um and that they're,

3:34:38you know, trying to give some initial

3:34:40feedback on those plans. So, so you

3:34:44know, sort of stepping back, the the

3:34:45purpose of this project is is to provide

3:34:50uh a a safe way to get from one side of

3:34:55Elma and the train track to the other

3:34:58that is south of California. That's the

3:35:01that's the goal. And that's an a really

3:35:04important goal that that people in this

3:35:06city have been working on for decades.

3:35:09the the

3:35:11issue arises that it is impossible

3:35:16to meet that goal without impacting

3:35:19somebody. It's impossible.

3:35:22Some if it's ever going to happen, some

3:35:25neighborhood

3:35:27I is going to take one for the larger

3:35:29community.

3:35:31That's just that's just the reality of

3:35:34changing

3:35:36public improvements to accommodate

3:35:38things that don't exist today.

3:35:41And in in the imminent domain work I do,

3:35:45there's there's a finding that's

3:35:48required of government that really is a

3:35:50good test even where no eminent domain

3:35:52is involved, which hopefully this

3:35:55project when it reaches its fruition

3:35:57won't involve eminent domain. But that

3:35:59test is, is the project designed to

3:36:02achieve the greatest public good with

3:36:05the least private injury?

3:36:08The greatest public good with the least

3:36:10private injury. And that's really the

3:36:12exercise that this city has been engaged

3:36:15in

3:36:16in in analyzing these uh various uh

3:36:21alternatives in winnowing down and then

3:36:24focusing more on the ones that seemed

3:36:28most likely to meet that test. Greatest

3:36:32public good, least private injury. Um

3:36:36and as we know uh at the council level

3:36:41uh their last action they seem to be

3:36:43focusing on these two elderorado

3:36:47as sort of meeting that criteria but uh

3:36:52as staff pointed out in response to our

3:36:54chair's questions

3:36:57staff went away and dug into these two

3:37:00and has a lot of information that the

3:37:02council has not yet seen including u not

3:37:05the least of which is the the potential

3:37:07cost of 72 million 87 million um and the

3:37:12impacts I think um that that weren't

3:37:15fully known when the council directed

3:37:18them to u go take a look at this. So is

3:37:22the um El Dorado solution A1 or A2

3:37:28provide the greatest good with the least

3:37:30private entry?

3:37:32Maybe it may be, but it it also may be

3:37:36true that it's not. And I'm feeling like

3:37:39we're not far enough along

3:37:42yet. We can use more information

3:37:46before taking a next step forward. Um

3:37:51Kurt Vonagget once wrote that

3:37:54um a step backwards after a wrong turn

3:37:57is a step in the right direction.

3:38:00And I don't I don't think the city has

3:38:02taken any wrong turn yet. I think we had

3:38:05to get to here to really start to

3:38:08understand the impacts of these two. But

3:38:10the question is what we go what are we

3:38:13going to do going forward? What is the

3:38:14council going to do going forward? And

3:38:16is that going to be a wrong turn?

3:38:19Um

3:38:22I think we're not ready to pick an

3:38:24alternative or maybe two tonight to

3:38:27recommend to council. I don't feel like

3:38:29I am. I don't understand, you know, um I

3:38:32heard in the staff uh presentation

3:38:33tonight that, you know, one of the

3:38:35things that council didn't like about

3:38:37Lomma Verde alternatives that turned

3:38:39them toward El Dorado was they weren't

3:38:42wanting to accept property impacts,

3:38:44meaning takings. But now it turns out

3:38:46we've got a number of takings in A2 and

3:38:51and so I don't know if council

3:38:55once they were aware of that would have

3:38:57the same same feeling. Does that mean

3:38:59they're only interested in A1? I I I

3:39:01don't know. Um uh I think the the hybrid

3:39:06idea is

3:39:08um it it it has some uh first of all as

3:39:12I said I appreciate staff doing this

3:39:14sort of initial uh review of it and

3:39:18clearly

3:39:20there may be a little less um

3:39:25public good if it's more ciruitous and

3:39:28gets um less use, but

3:39:34maybe that's a fair tradeoff for a lot

3:39:36less private injury. And I think we need

3:39:39more information on that. So, I think

3:39:41it's worth recommending to the council

3:39:43to look at that. And then finally,

3:39:46um I'm I'm interested in the overpass

3:39:49idea. Um um it's it it wasn't, you know,

3:39:53referenced in this staff report and and

3:39:55I appreciate uh staff's uh telling us

3:39:57that it was the a concept that was

3:40:00considered in the original 25. Um but

3:40:04didn't make like the cut to eight. Um

3:40:07and actually I went back and looked at

3:40:09this was in front of the planning

3:40:10commission twice last year. I went back

3:40:11and looked at those staff reports to see

3:40:14if I could get some information about

3:40:15like where maybe it didn't make the cut.

3:40:18I I couldn't find it. Now, I didn't

3:40:20rewatch the videos. I didn't read the

3:40:22attachments, so maybe it's in there

3:40:23somewhere. But but I do know that that

3:40:26um San Mato considered this um uh an

3:40:30overcrossing

3:40:32>> um

3:40:34in light of the the greater difficulties

3:40:36with the electrification of the lines

3:40:38and and um the need to go higher. And

3:40:42they found my understanding is they

3:40:44found they could physically do it but

3:40:46the co the price tag was 20 to 25

3:40:48million and to solve whatever problem

3:40:50they were dealing with they had a lower

3:40:52cost solution so they turn toward that.

3:40:55Um we built our uh last uh highway 101

3:41:00San Antonio area um uh bike uh crossing

3:41:05for I think 23 million. So, so those

3:41:08figures um make sense. Um and

3:41:14now we know that the alternatives were

3:41:16looking at um with A1 and A2 are three

3:41:20three times that and then some. And so

3:41:25um

3:41:26maybe it's worth now that we know what

3:41:29these price tags are, maybe it's worth

3:41:31looking at this again. I understand that

3:41:33there are uh design challenges um and

3:41:37you know you need a lot of ramp up to at

3:41:407% to to get three stories up. Um but

3:41:45again it's it's you know San Mateo

3:41:47looked at this and found it feasible and

3:41:50maybe now that we know that the

3:41:51alternatives are three times as much as

3:41:5525 million um it's worth looking at

3:41:58again um at least to get to you know a

3:42:025% review. So so you know those are my

3:42:06thoughts. I appreciate that slowing this

3:42:10train is inconsistent with the timing

3:42:14that the council seems to want, but my

3:42:16thought is, you know, this is a facility

3:42:18that's going to serve us for a century

3:42:21and then be replaced with the another

3:42:24kind of the same thing. It's it's like a

3:42:27permanent thing for the future of our

3:42:29city. And so if it if it takes, you

3:42:33know, a few more years to get it done

3:42:35right with the greatest public good and

3:42:37least private injury, then that's the

3:42:39path we should take.

3:42:45>> Commissioner Aken, Ben Templeton,

3:42:49>> that's a hard act to follow.

3:42:53Um,

3:42:55I wanted to start by uh revisiting um

3:43:00why Elorado seemed attractive to me the

3:43:02last time this came before us at PTC,

3:43:05which was almost exactly a year ago.

3:43:08Uh so the state is forcing us to grow in

3:43:12population but it's not funding new

3:43:16transportation infrastructure

3:43:18at the same level not to match.

3:43:23We have to prepare for that or we're

3:43:26going to start seeing cutth through

3:43:27traffic increase everywhere

3:43:31whether we build this uh crossing or

3:43:34not.

3:43:36Um,

3:43:38one thing that we discussed the last

3:43:39time this came before us is that one

3:43:44thing we can do to deal with this

3:43:45reality is we can look for ways to shift

3:43:48short trips away from cars and

3:43:51particularly toward bikes.

3:43:55So where are the great opportunities to

3:43:58do that?

3:44:00Well, near Midtown, the largest number

3:44:03of short trips across the tracks is on

3:44:05Oregon Expressway.

3:44:07So, that suggests

3:44:10that what we want is something that's

3:44:13relatively close to Oregon Expressway,

3:44:16but on the south side so that people

3:44:19don't have to cross.

3:44:22And

3:44:24that's largely what drove me

3:44:29um

3:44:31except that a crossing at El Dorado was

3:44:34the most appropriate place

3:44:37and the circulation studies that were

3:44:39presented to us at the time suggested

3:44:41that we would get better utilization of

3:44:45a crossing at El Dorado than we would at

3:44:47Lomma Verde um or a number of other uh

3:44:51options in between

3:44:54and finally of course it had the

3:44:57advantage that we wouldn't require

3:45:00property takings on the west side of the

3:45:02tracks.

3:45:04Okay, so all that said

3:45:07um

3:45:11A2 is just not going to fly.

3:45:16you know, there's there really is no

3:45:18point in pursuing the design without

3:45:21some

3:45:23drastic change in the way that uh that

3:45:26that's organized, which is largely why I

3:45:29suggested elevators. Something that

3:45:32drastic is what you're going to need to

3:45:34make A2 workable.

3:45:37A1 looks viable to me,

3:45:40provided we have the network

3:45:42enhancements that you've already alluded

3:45:44to.

3:45:46And

3:45:48given what I've seen elsewhere, I

3:45:51believe that's possible.

3:45:53We simply haven't reached that point

3:45:55yet. So that you can make a convincing

3:45:58argument for people who are less

3:46:00familiar with how that works.

3:46:02Um,

3:46:04so where that leaves me is

3:46:07I would be inclined to recommend that uh

3:46:11A1 proceed

3:46:15And if we're going to make a

3:46:17recommendation,

3:46:19then another option

3:46:23would be good.

3:46:25Uh right now, the one we have before us

3:46:28is the hybrid option. If you wanted to

3:46:31take more time to try and uh redevelop

3:46:35something at Lomma Verde, for example,

3:46:38um then that probably would be

3:46:40worthwhile despite the delay that that

3:46:44that would cause in the in the project.

3:46:48But um so if you ask me uh if you ask me

3:46:51today to make a recommendation, a one

3:46:54goes through and I would like to see

3:46:56something else in addition.

3:46:59So that's

3:47:00>> Could I ask a clarifying question? So um

3:47:02just then you mentioned um something at

3:47:05Lom Verde. Do you mean a hybrid at Lom

3:47:08Verde or do you mean the uh what was the

3:47:10BC? Was it were those the numbers

3:47:13>> given given that uh we're looking at um

3:47:17costs that are similar B and C probably

3:47:20should be reconsidered.

3:47:25Uh yes, the property acquisition on the

3:47:28park side is a problem, but compared to

3:47:33the property acquisitions uh that A2 is

3:47:36demanding of us along Elorado,

3:47:40that's a wash.

3:47:42Uh council needs to understand that.

3:47:46>> Commissioner Temple,

3:47:49>> thank you. What interesting commentary

3:47:51I'm so excited what a good discussion.

3:47:53Um, I would say, um, I you you've got me

3:47:57thinking, Commissioner Hecman. Um, wow.

3:48:00Onethird of the cost to do an overpass

3:48:04is very exciting and worth

3:48:06consideration, and I hope that staff

3:48:08will somehow

3:48:10bring that information

3:48:12uh to council. Um but more interestingly

3:48:17what what that brings to us is

3:48:20tremendous opportunity to deal with the

3:48:22problems that were just raised. Um when

3:48:26I'm thinking about the when you first

3:48:29mentioned the reasons not to do an

3:48:30overpass

3:48:32um I think staff said something like uh

3:48:35the ramps would be really long and

3:48:37inconvenient.

3:48:39But could that be an opportunity for us

3:48:42to have one of the ramps start at Cal A,

3:48:47go over and come down on the other side

3:48:52of Oregon, solving a lot of problems at

3:48:56once and making the California Avenue uh

3:48:59crossing compliant, improving it, also

3:49:02connecting both sides of Oregon

3:49:03Expressway. Who knows? I don't know. I'm

3:49:07spitballing here, but I what I'm trying

3:49:09to say is if you do look up and discover

3:49:14that what Commissioner Hecman mentioned

3:49:16is true, that you can do one-third of

3:49:19the cost um and perhaps solve two

3:49:24problems at once, that might be

3:49:26something to consider. Um that said, um

3:49:32I would not want to recommend

3:49:35alternatives A1 or A2 to council. I

3:49:39think what we have um achieved and how

3:49:43staff may choose to present this is the

3:49:46investigation that council authorized

3:49:48has proven that these are not viable to

3:49:51the community. And I think that means

3:49:55that the money is well spent, the effort

3:49:57was well spent, and we learned something

3:49:59actionable going forward, which is we

3:50:01need to find a different alternative.

3:50:03So, um I I know it's I see the grimaces,

3:50:06but it is what it is and that is

3:50:10sometimes how it goes and why we do the

3:50:12different percent investigations before

3:50:14going all the way through with anything

3:50:17um that we learn along the way isn't

3:50:20going to work. So, um I do also uh wish

3:50:24that we could consider um

3:50:29um

3:50:30the

3:50:32LMA verde

3:50:34options including the hybrid uh a little

3:50:36bit more deeply and I don't know if you

3:50:38need to go back to council to get

3:50:39authorization to do that. Are you can

3:50:41staff tell me if that is that one of the

3:50:43things that would have to happen that

3:50:46>> Yes, we would need to get authorization

3:50:48to go back to those options. Great. Um,

3:50:51and if

3:50:53I'm just trying to think of forming the

3:50:55motion um, as we go forward, do we also

3:50:59Commissioner G has his hand up for going

3:51:00next? Um the do we need to specify

3:51:05whether it's El Dorado or Alma Verde or

3:51:09use the the lettering nomenclature that

3:51:11you had already for you to look into if

3:51:15we did an overpass where would it come

3:51:18down on either side? Like we don't know.

3:51:22That would be a question for you guys to

3:51:23figure out. Do we need to specify it

3:51:25with those letters or can we just say

3:51:27something like

3:51:29um that to see if council wanted to fund

3:51:32an exploration of that?

3:51:36>> Um I wouldn't want to limit you in in

3:51:39how you give a recommendation. So any

3:51:40kind of feedback you give and we can

3:51:42just make sure that we un try to

3:51:44understand what what it is you're you're

3:51:45the recommendation you're making and if

3:51:47there's some clarifications we think

3:51:48might be helpful to make that clear for

3:51:50everybody, we can we can certainly help

3:51:51with that.

3:51:52>> Okay. Um, so I'm going to leave it at

3:51:54that because I want to hear from

3:51:55Commissioner G and then maybe we can and

3:51:57there's others who are in line. So,

3:51:59thank you,

3:52:00>> Commissioner James and then Vice Chair

3:52:02G.

3:52:05>> So, there we go. Um, I guess if this was

3:52:09easy,

3:52:11>> um, I'm not going to quote Vonagget, but

3:52:13my dad used to say measured twice and

3:52:15cut once, you know, and I think it's

3:52:17kind of along those those lines. So I

3:52:20appreciate um your observations and you

3:52:24know I don't see you know a clear winner

3:52:29uh in my mind. Um I always like Palo

3:52:32Verde. Um uh I do feel like El Dorado is

3:52:36too narrow for a ramp. Um um I was

3:52:40intrigued by some of the the uh

3:52:42residents comments um about uh crossings

3:52:47that were limited to bikes and

3:52:49pedestrians. And I feel like there's

3:52:52something there that's sort of

3:52:54interesting to me in terms of not sort

3:52:56of solving like cut through traffic and

3:52:58and so forth. I don't think I have a

3:53:00clear idea where the best place for that

3:53:02would be, but I think that is um it

3:53:05sounds virtuous, let's say, uh in in the

3:53:08absence of evidence to the contrary. Um

3:53:11so I'm left, you know, I I I maybe I

3:53:14have had a hard time moving off of my

3:53:16first first choice being Lum Verde. Um I

3:53:19guess I would love to see that explored

3:53:22uh more fully. I think there um may be

3:53:27some some virtue to the resident's uh uh

3:53:31suggestion um of a hybrid. Um so I guess

3:53:34I'm sort of left uh

3:53:38in a very similar kind of state of mind

3:53:40with Mr. Hecman uh Commissioner Hecman.

3:53:42Um that I I wish um I wish I had uh

3:53:47evidence that would lead me to you know

3:53:51a great conclusion. Um it is a lot of

3:53:54money. I think we do need to make sure

3:53:56we get it right. Um you know um nobody

3:54:00wants to kick it down the road like

3:54:01another decade. Um but I really do wish

3:54:05we had you know two clear uh viable

3:54:09alternatives and I have a hard time sort

3:54:11of seeing those.

3:54:15>> Vice Chair G.

3:54:17>> Thank you and for the great discussion

3:54:19with my fellow commissioners.

3:54:22I think that where I come down on these

3:54:25lines is very similar to Commissioner

3:54:27Hecman in that this is the kind of

3:54:31project that will last for a very long

3:54:33time and we need to make sure we do this

3:54:35right

3:54:37and the trade-offs that we have to make

3:54:38are between the public benefit and the

3:54:40potential injury cure.

3:54:43And something that really concerns me is

3:54:46spending quite a large amount of money

3:54:48to build something that ends up being

3:54:51not very used. So for example, if we say

3:54:56something like the hybrid plan has the

3:54:58least amount of potential parcel

3:55:00impacts,

3:55:01but the S shape and the additional half

3:55:05a mile potentially that people are

3:55:06traveling reduces the amount of trips

3:55:09taken. Are we actually getting that much

3:55:11public benefit out of the project? Could

3:55:14could the money be better spent

3:55:15elsewhere?

3:55:18And I want to comment also on what

3:55:20Commissioner Akin had mentioned about

3:55:21how the transportation study in the last

3:55:24time we saw this indicated that more

3:55:26trips came through on the Oregon side.

3:55:29And I wonder if that's a little bit of a

3:55:31chicken and egg problem, right? in that

3:55:33we see more trips coming through Oregon

3:55:35because the people who live there

3:55:38see that as an easier route to get

3:55:40through to the other side via Calav,

3:55:42right? More bike and ped trips may

3:55:44inherently already occur because there

3:55:46is a way to get there, right? It's

3:55:49really unclear that that demonstrates

3:55:52that having a tunnel further south, for

3:55:54example, at LMA Verde wouldn't create as

3:55:56many trips. And I also want to tie this

3:56:00together with some of the new housing

3:56:02that we've seen along El Camino. For

3:56:03example, 366 El Camino, which will be at

3:56:06Madero and which is kind of right across

3:56:09from where Lomma Verde would come out

3:56:13to, as well as other projects like the

3:56:14fish market, NVCAP, and others. And kind

3:56:18of tying this back to what Commissioner

3:56:19Templeton had mentioned at the very top

3:56:21of our discussion.

3:56:23It's hard for me to see what benefits

3:56:26the Elorado tunnel is providing that the

3:56:27Calv tunnel is not already providing.

3:56:32And in kind of some across all these

3:56:35different options,

3:56:37I'm not left with very

3:56:40many good options. I'm pretty

3:56:42unhappy with recommending either A1 or

3:56:45A2. I also want to think about the

3:56:47potential implications of the light. As

3:56:49Chair Chang had mentioned, we haven't

3:56:52seen a transportation study with uh a

3:56:55traffic light on Alma, and I think that

3:56:56would pretty dramatically change the

3:56:58potential traffic patterns that may

3:57:00occur there.

3:57:02In addition, I also am curious about the

3:57:06potential behavior impact that we create

3:57:09by putting a light there that comes out

3:57:10to a bike tunnel. So, for example, I

3:57:13actually end up seeing quite a lot of

3:57:14people biking on Alma, like in the

3:57:17street in downtown near Homer. And why

3:57:20is that? Well, it's because the Homer

3:57:22tunnel comes out onto Alma and then, oh

3:57:26well, I'm just going to bike on Alma

3:57:28because I'm already here, right? And I

3:57:30feel like that's significantly more

3:57:31dangerous and we shouldn't be

3:57:32encouraging this kind of behavior.

3:57:36In terms of potential next steps,

3:57:39I think that one issue that I had with

3:57:41Lomover Verde in the previous version

3:57:44when it came to us was the costs. But

3:57:46now that staff has mentioned that the

3:57:48costs are pretty similar, I'm pretty

3:57:51interested in option B, the LM Verde

3:57:54with um with the full tunnel without the

3:57:56traffic light. And so if I were to be

3:57:59asked to recommend something to council,

3:58:03I would probably recommend continued

3:58:05exploration of option B. And as

3:58:08Commissioner Templan said, I think this

3:58:10is money greatly spent. As we've

3:58:12previously discussed as a commission,

3:58:14some of these like pilot projects, the

3:58:17whole point is to iterate quickly and

3:58:18get feedback. And that doesn't mean that

3:58:21just because we've continued with a 5%

3:58:24means that we should go all the way to

3:58:25100%. Right? Sometimes the best way to

3:58:28look at it is we've spent a small amount

3:58:31of money to test to iterate quickly and

3:58:33determine that neither of these options

3:58:35are ones that we'd recommend.

3:58:37And if we if I had to recommend a second

3:58:39option, I would probably recommend the

3:58:41hybrid option just for a comparison

3:58:44against the tunnel at Luma Verde. Thank

3:58:46you.

3:58:50>> All right, I will opine now. Um my my

3:58:53thoughts are very aligned I think with

3:58:56Commissioner Beckman and Templeton and

3:59:00Vice Chair G and um Commissioner James.

3:59:04So I do have one quick question of

3:59:06staff. Was city council aware that

3:59:09Elorado is the smallest street between

3:59:12Cal A and San Antonio when they made the

3:59:17decision?

3:59:20I I don't think we on the commission

3:59:22were aware of that at the time we were

3:59:25advanc we were choosing options from the

3:59:27eight options.

3:59:29>> It did come up as part of the

3:59:30conversation. Okay. Yes.

3:59:32>> All right. Well, what I would say is

3:59:34that for me, Elorado as a non-starter,

3:59:37as a bike path, um it's just too narrow

3:59:40for a bike path. And if we're really

3:59:42anticipating that number of trips and

3:59:44we're expecting all this growth in our

3:59:46city, um, and you've got, you know,

3:59:49several multiund unit developments going

3:59:53on in the El Camino Rail Focus area and

3:59:56Ventura and then

3:59:59potentially a lot of development going

4:00:01on in South Palto.

4:00:03I don't think that we pick we should be

4:00:06picking the narrowest street uh for

4:00:08that. And I understand I've heard from

4:00:11people who say that okay well lumberie

4:00:14is busier. It is busier. It is a little

4:00:17bit busier. None of the streets in that

4:00:19area are extremely busy. What we've got

4:00:21right now is

4:00:24safe routes to school down Charleston

4:00:26down Meadow. Those are busy. And so I

4:00:28think there's a lot of room between tiny

4:00:32little Elorado and massive streets like

4:00:34Charleston and East Meadow um that that

4:00:38accommodate

4:00:40a bike lane and some cars because we

4:00:44have all these residents living in these

4:00:46areas that need to get in and out. And

4:00:48so I think that Elorado just doesn't

4:00:50make sense because it's too narrow

4:00:51because of the culdeacs.

4:00:53Um secondly with respect to a light I'm

4:00:57very and we would have to do the

4:00:59additional studies to see it but because

4:01:02I drive down Elma

4:01:05almost every single day and then I see

4:01:08how the traffic backs up um as you know

4:01:13things are very congested at Page Mill

4:01:15and El Camino and so cars back up all

4:01:18the way on the clover and then and then

4:01:22onto Elma. Uh, and that's only going to

4:01:24get worse as we increase our population

4:01:27and increase the development. Um,

4:01:30particularly with the amount of

4:01:31development that's being slated for

4:01:32South Palto. So, I'm very concerned

4:01:35about a light that is that close to the

4:01:39to Oregon. Um,

4:01:43and furthermore, there's this really

4:01:46unique point where I understand that

4:01:48cast, you know, uh, somebody had

4:01:49mentioned that Castile is a very narrow

4:01:51street and it works great as a bike

4:01:52lane. There's a fundamental difference

4:01:54here where

4:01:57Elorado represents critical parking for

4:02:01the

4:02:02naturally affordable housing on Elma.

4:02:05And that is a situation that just simply

4:02:07doesn't exist in many certainly on

4:02:11Castilea, but we have all these multif

4:02:14family units um or like duplexes

4:02:17uh and there simply isn't parking on

4:02:20Elma. There's just no option. And so as

4:02:23we as the current situation stands, we

4:02:25have people who have to hike like more

4:02:28than a block. And so

4:02:32while I understand that for bike

4:02:33infrastructure we may need to remove

4:02:35parking. My thought is that for a wider

4:02:37street like Lumie maybe we can preserve

4:02:40more parking there or at least some

4:02:42because uh even I was driving around and

4:02:45the utilization is actually quite high

4:02:47uh even in the middle of the day for um

4:02:51for for all the streets along Elma. So,

4:02:55it's just a there's a practical

4:02:56implication here. And much as we would

4:02:59like everybody to get out of their cars,

4:03:01there just needs to be parking.

4:03:04Uh, and there just really is no other

4:03:05option uh for a lot of these homes. So,

4:03:09I don't think that I would want to

4:03:11advance either Elorado option as

4:03:13currently stands. I think the hybrid is

4:03:15worth investigating. I'm also very

4:03:17concerned about creating an option,

4:03:19however, that doesn't get a lot of use.

4:03:22I was always in more in favor of low

4:03:24mortarity. I know that there's these

4:03:25negative impacts of parcel impacts, but

4:03:29something on a street that's already,

4:03:33you know, has a good bike lane, uh, just

4:03:36seems to make a lot more sense to me. I

4:03:38love the idea of the other options like

4:03:40a bridge, but I don't know how feasible

4:03:42that is realistically. Um, so I would be

4:03:45interested in looking at both B and C at

4:03:47Lum Verde, uh, as well as the hybrid.

4:03:53That's it for me.

4:03:59>> Oh, Commissioner Hecman and Templeton.

4:04:04>> Thanks. So, a question of staff and then

4:04:06a comment. Um, after council gave you

4:04:10direction to focus on A1 and A2, I I

4:04:15think what you you went away and did was

4:04:18I think you called it like a 5% design.

4:04:21I want to kind of use the the right

4:04:24terminology. Is that Did I hear that?

4:04:30>> It's all we usually just refer to it as

4:04:32conceptual design.

4:04:33>> Concept. Okay. All right. So, so after

4:04:37the last time, last time you were at the

4:04:39council, you had eight potential

4:04:42uh uh concepts and they sent you away to

4:04:47work on two conceptual designs. Okay.

4:04:53All right. Um thank you. I'm asking that

4:04:56because it might be useful in framing a

4:04:59motion later. Um the other thing I want

4:05:01to do is just clarify. I am not

4:05:03suggesting I don't want to be

4:05:05misunderstood to suggest that we could

4:05:08do an overpass solution for 25 million.

4:05:11I I have no idea how much it would cost.

4:05:14That figure I heard from San Mato. I

4:05:16think that's the correct figure um um

4:05:19for the one we did over 101, but those

4:05:21are different circumstances. This could

4:05:24cost um you know twice that. I don't

4:05:26know. It may be geometrically impossible

4:05:30without taking multiple parcels. I I I

4:05:32don't know that. But I do know that if

4:05:35it I mean the reason I'm attracted to

4:05:37looking at it is because

4:05:40if it can be done it it provides no at

4:05:45grade crossing, so it's the safest. It

4:05:48provides no dark nighttime tunnel, so

4:05:51it's the the safest in that regard. It

4:05:54provides no utility interface problems

4:05:59like a tunnel. and it you're not going

4:06:02to run into a plume. And so so there are

4:06:06some potential benefits that and and you

4:06:10know um some of those aren't measured in

4:06:12dollars, but some are. And so that's why

4:06:14I'm I'm interested in in

4:06:18having staff look at a conceptual design

4:06:22for an overcrossing at whatever location

4:06:25between Colorado and Charleston staff

4:06:28determines might involve the greatest

4:06:31public good and least private injury.

4:06:35>> Commissioner Templeton,

4:06:36>> thank you. I just want to add one more

4:06:38benefit that you didn't list.

4:06:40um we can choose where the ramp starts

4:06:43and where it ends which gives us a lot

4:06:46more flexibility to work with the

4:06:49available parcels with the that would

4:06:51reduce potential takings even more. So,

4:06:55if your motion is going to be uh bring

4:06:58Lomma Verde options B and C to

4:07:01conceptual stage and um scope out a

4:07:06potential overpass

4:07:08uh in terms of pricing and location

4:07:11options, I think I would be very excited

4:07:14about that. I hope that we will be able

4:07:16to include that. If it can't be done,

4:07:19staff will tell us. But why not ask for

4:07:21it? Because it could be the most

4:07:24economically feasible and the fewest

4:07:26takings.

4:07:30>> Do you want to make a motion? Do you

4:07:31want to make a motion?

4:07:34>> Are there any more comments?

4:07:35>> No.

4:07:36>> Do you mind if I make

4:07:38>> Yes, vice chair G.

4:07:40>> So, I want to jump on this. If we ha

4:07:44choose an overpass, we can kind of

4:07:46choose the beginning and end. Having

4:07:48recently um been to I was recently in a

4:07:52place that had a lot of these

4:07:53overpasses.

4:07:54And one thing that I saw that really

4:07:57reduced the amount of parcel impacts is

4:08:00by starting and ending a lot of these

4:08:02overpasses in parks.

4:08:05and some parks we there's not as many

4:08:08parks along Elma or the Cal Train per se

4:08:10in this area, but if we need to achieve

4:08:13the 7% at grade, this is one potential

4:08:16way to extend it, right? So, we could

4:08:18say, oh, like we want to we can use the

4:08:20the public land that we already have

4:08:22that would minimize a parcel impact and

4:08:24then have the long ramp from a park

4:08:26going into somewhere else. I also wonder

4:08:28if this potential strategy could be

4:08:31interesting if we decide to also connect

4:08:35somewhere to Calav, right? Because on

4:08:37the east side of the Calav tunnel, we

4:08:40end up in a park, right? And as

4:08:41Commissioner Akin had mentioned, it is

4:08:44potentially pretty difficult to get

4:08:46across Oregon. And so that could be

4:08:47another area where we could kind of

4:08:49interconnect, where we could say, hey,

4:08:51uh, we can make another easy way for

4:08:54folks in Midtown to get across Oregon.

4:08:56So these are just some different ideas

4:08:58that I was kind of bouncing around based

4:09:00on the most recent discussion.

4:09:02>> I love it.

4:09:12>> I will try a motion and get some

4:09:14feedback on it.

4:09:16So, I move that

4:09:20the PTC recommend to council that they

4:09:26hold current alternatives A1

4:09:30and A2 in obeyance

4:09:33until the completion of uh concept

4:09:37conceptual designs equivalent to what's

4:09:40been done for A1 and A2 or or possible

4:09:45other alternatives,

4:09:48uh, LMA Verde option B and LMA Verde

4:09:52option C.

4:09:55uh the hybrid that um has been

4:09:58referenced in much of the Elorado

4:10:00neighborhood correspondence and was part

4:10:03of our staff report and uh an

4:10:07overcrossing

4:10:09at the location that uh staff feels

4:10:13provides the greatest benefit and least

4:10:15injury.

4:10:17>> Second.

4:10:21>> Any additional discussion?

4:10:25Is there any interest in adding

4:10:27something along the lines of

4:10:31focusing on uh h or like having

4:10:34discussed criteria such as parcel

4:10:36impacts, cost and others that kind of

4:10:40help us guide us to this decision.

4:10:45>> I I I don't think we need to do that

4:10:47because I think it's baked into the

4:10:49conceptual design process. you know,

4:10:52that that shaded bar graph that um staff

4:10:56did, I thought was super helpful. And

4:10:58you know, I can envision a a new version

4:11:02of that if council so chooses that would

4:11:04have all six and and sort of categorize

4:11:07them along this uh gray spectrum. So, I

4:11:10think staff understands that as part of

4:11:12the conceptual design process.

4:11:15>> Okay. Yeah. The reason I the only reason

4:11:16I mentioned that is that I want to help

4:11:18council understand why we kind of

4:11:20decided not to move like why we don't

4:11:23believe A1 and A2 are good rationale but

4:11:26I also do agree with you that staff has

4:11:28done a pretty good job with the bar

4:11:29graph. So I just am throwing that out as

4:11:31an option but I'm happy either way.

4:11:37>> Okay then I think we're ready for our

4:11:39vote.

4:11:41Um, Commissioner Hecman,

4:11:43>> before we vote, just want to check to

4:11:45see if there's clarification needed.

4:11:48>> It was uh more of just um just make sure

4:11:50we have the terminology correct. So, um

4:11:54LMA verde option previously referred to

4:11:58as alternatives B and C. Those

4:12:01conceptual designs have already been

4:12:02completed. So, those are those are at

4:12:05the conceptual design level and we've

4:12:06done an evaluation of tradeoffs. Um, so

4:12:10I just wanted to clarify that because I

4:12:11thought that I heard something

4:12:12different. I thought you said Lovery A

4:12:14and B, but I just wanted to make sure

4:12:15we're speaking the same language.

4:12:16>> I did say B and C, but this gets back to

4:12:18my question of what do you call what you

4:12:20did to A1 and A2? Because you brought A1

4:12:23and A2 to us with price tags. And as far

4:12:26as I know, B and C don't have price

4:12:28tags. So whatever you did for LMA verde

4:12:32B and C is not the equivalent. And the

4:12:34purpose of trying to get the right name

4:12:38is I I would like uh that my motion is

4:12:41for you to do with these four other

4:12:43alternatives

4:12:44the level of study you did for A1 and A2

4:12:47Elor Dorado.

4:12:49Thanks for clarifying. Okay.

4:12:54>> Okay. Uh Vice Chair G, is that a ghost

4:12:57hand or a

4:13:00>> ghost hand?

4:13:01>> Okay. I think we're ready for a vote

4:13:04then.

4:13:05>> Uh, Commissioner Hecman,

4:13:07>> yes.

4:13:08>> Uh, Commissioner Aken,

4:13:10>> yes. Uh, Commissioner James,

4:13:12>> yes.

4:13:12>> Commissioner Templeton,

4:13:14>> yes.

4:13:14>> Vice Chair G,

4:13:16>> yes.

4:13:17>> Uh, Chair Chang,

4:13:18>> yes.

4:13:18>> Motion carry 6.

4:13:21>> All right. Thank you everyone.

4:13:24>> We're going to go on to the next item,

4:13:26which is more transportation.

4:13:33Um, so the

4:13:37last action item tonight is Bryant

4:13:40Street Boulevard and Lincoln Avenue

4:13:42trafficcoming project initial design

4:13:45concepts. Could we start with the staff

4:13:48report, please?

4:13:53We'll just take a moment to get staff

4:13:57swapped out here uh to get this. Also

4:14:00giving the audience time to clear

4:14:03chambers so we have quiet for

4:14:05discussion.

4:14:50So, I would just like to note that

4:14:52Commissioner Aken needs to leave at

4:14:5310:45.

4:15:02>> All right, go for it, Mr. Ray.

4:15:05>> Thank you, Chair Chang. Hello,

4:15:07commissioners again. Uh my name is

4:15:08Aussie Arcles, senior transportation

4:15:10planner uh with the office of

4:15:12transportation. Tonight I'm presenting

4:15:14updated design concepts for the Bryant

4:15:16Street and Lincoln Avenue traffic

4:15:17calming project. Uh the effort advances

4:15:21a near-term project from the 2026

4:15:23bicycle and pedestrian transportation

4:15:25plan, also known as the BPTP, and also

4:15:29addresses specific resident concerns

4:15:31regarding vehicle volumes and speeds

4:15:32along the Spike Boulevard and school

4:15:34commute corridor. Next slide, please.

4:15:37Our purpose tonight is to present a

4:15:39suite of ideas and suggestions for

4:15:40traffic calming in this area and most

4:15:43importantly to gather your feedback on

4:15:45the updated concept plans. I will

4:15:47present some existing conditions data,

4:15:49best practice thresholds, and the

4:15:50suggested improvements. This is about a

4:15:5310-minute presentation.

4:15:55The recommended action tonight is to

4:15:57review the update next slide, please. to

4:15:58review the updated concept plans for

4:16:00portions of Bryant Street and Lincoln

4:16:02Avenue and recommend council direct

4:16:04staff to advance the elements listed on

4:16:08the slide also in your staff report.

4:16:12Next slide, please. The Bryant Lincoln

4:16:14traffic calming project merges two

4:16:16initiatives. the 2024 neighborhood

4:16:19traffic calming petition the city

4:16:20received from residents in the area. And

4:16:23like I mentioned earlier, it advances a

4:16:25near-term project from the 2026 BPTP,

4:16:28also known as the Bryant Street Bike

4:16:30Boulevard downtown access project. This

4:16:34allows the city to effectively deliver

4:16:35on both goals simultaneously.

4:16:38Separate yet related and important note

4:16:40is that the city is interested in

4:16:42revamping its traffic calming policy

4:16:44from 2001 and using this project as a

4:16:48pilot test case to understand how to

4:16:50better deliver traffic calming

4:16:52improvements in accordance with best

4:16:54practice. This includes understanding

4:16:56how to better balance the lived

4:16:58experience of residents with current

4:17:00safety standards to to advance traffic

4:17:02calming projects from design all the way

4:17:05through to construction.

4:17:07Next slide, please. Our primary goal is

4:17:10to enhance the boulevard as it

4:17:12approaches downtown, creating a

4:17:14worldclass low-speed all ages and

4:17:16ability street, which is a goal of the

4:17:182026 BPTP.

4:17:21We also want to optimize the street for

4:17:23bicyclists actively discourage cut

4:17:25through vehicle traffic as described in

4:17:27the neighborhood traffic calming

4:17:29petition received. According to the

4:17:31National Association of City

4:17:33Transportation Officials or NACTO, a

4:17:35successful bike boulevard relies on two

4:17:38things. Low vehicle volumes and low

4:17:41speeds. So, just really quick on these

4:17:43best p best practice guidelines from

4:17:45NATO. Uh it targets fewer than a,000

4:17:48daily vehicles. Uh ideally between 500

4:17:51and a,000 for bike boulevards. Um and

4:17:54during peak hours that drop to just 50

4:17:56to 100 vehicles. Regarding speeds, the

4:18:00goal is for the 85th percentile of

4:18:03drivers to travel at 15 to 20 mph. And

4:18:07just for additional project area

4:18:09boundaries, this is between Bryant

4:18:11Street uh between Embaradero Road and

4:18:14Homer Avenue and Lincoln Avenue between

4:18:17Waverly and Emerson.

4:18:21Next slide. So, how do we measure up to

4:18:23those targets today? Next slide. Uh in

4:18:27May 2026, our project team collected new

4:18:30volume and speed data. Uh the short

4:18:33answer is both volumes and speeds are

4:18:36too high when compared to best practice

4:18:38thresholds. And I'll direct your eyes to

4:18:40the table on the top right. Looking at

4:18:42the numbers, daily vehicle volumes have

4:18:44jumped by about 35% since 2015, going

4:18:47from just over,500 to nearly 2100

4:18:50vehicles today. That's more than double

4:18:53the nacto ideal target for a bike

4:18:55boulevard. Speeds have also crept up.

4:18:58The 85th percentile speed is now 28 mph.

4:19:01When you consider a typical bicyclist

4:19:03travels roughly 13 mph, that creates an

4:19:06uncomfortable and unsafe speed

4:19:08differential.

4:19:11Uh this might lead to why it's no

4:19:13surprise that our peak hour bicycle

4:19:15counts are sitting at 55, well below the

4:19:17target of 100 to 200 for a bike

4:19:20boulevard. Next slide, please. The daily

4:19:22volume suggests that commuters are

4:19:24frequently using Bryant Street to travel

4:19:26north towards downtown. So, this using

4:19:29and using Lincoln Avenue to bypass

4:19:31heavier traffic on University Avenue and

4:19:33Embaradero Road. This cutth through

4:19:36behavior impacts safely and we have a

4:19:39significant concentrations of collisions

4:19:41between uh where Bryant Street meets

4:19:43Lincoln Avenue as well as multiple

4:19:45collisions further up on Channing

4:19:47Avenue. As you can see from this map,

4:19:50between 2016 and 2024, there were 10

4:19:53reported collisions on Bryant Street.

4:19:5530% of the collisions involved the

4:19:57bicyclists and at least 50% involved of

4:20:00the collisions were broadside.

4:20:03An important note here is that the city

4:20:04has also received several 311 inquiries

4:20:07in recent years from resident expressing

4:20:10safety concerns in the project area with

4:20:12a concentration of 311 tickets submitted

4:20:15at the Bryant Lincoln at the Bryant and

4:20:17Barkadero road intersections.

4:20:20And anecdotally, residents tell us of

4:20:22frequent collisions that are not

4:20:24reported. So we know the actual activity

4:20:26on the street is higher than what's in

4:20:28the record.

4:20:30Next slide, please. So how are we

4:20:32proposing to tackle these issues? Next

4:20:35slide.

4:20:36Uh to reverse these trends, our strategy

4:20:39relies on three pillars. Reducing

4:20:41vehicle speeds, reducing traffic

4:20:44volumes, and improving the streets

4:20:46legibility. So everyone knows it's a

4:20:48bicycle priority zone. So I'll walk

4:20:50through these three strategies in the

4:20:52next few slides quickly. So let's talk

4:20:55about reducing speeds. Drivers tend to

4:20:57speed up when they see a long

4:20:59uninterrupted clear path. To disrupt

4:21:02that visual roadway, we are suggesting a

4:21:04new traffic circle at Kingsley Avenue, a

4:21:07new traffic circle at Bryant and

4:21:08Lincoln, and suggest upgrading the

4:21:10existing circle at Addison to include

4:21:12crosswalks, splitter islands, and a

4:21:14mountable truck apron.

4:21:19These small traffic circles are similar

4:21:21to those you see already on univers uh

4:21:23north of University Avenue. For example,

4:21:25at Hawthorne and Kalper shown on the

4:21:27image, Everett and Webster and Everett

4:21:30and Emerson. So, this is something the

4:21:32city has implemented in the past and

4:21:34currently is on our city streets.

4:21:37Um updated traffic circles serve a dual

4:21:41purpose for this corridor. From a

4:21:42neighborhood traffic calming

4:21:43perspective, they address residents

4:21:45concerns around uh physically forcing

4:21:48vehicles to slow down at key

4:21:49intersections. And from a BPTP

4:21:51perspective, traffic circles preserve

4:21:53continuous low stress momentum for

4:21:56cyclists. Uh just a quick note here that

4:21:59traffic circles in Palo Alto do include

4:22:02either two-way or four-way stop control,

4:22:05unlike a roundabout that traditionally

4:22:08has all yields at intersections, no stop

4:22:10signs. So that's an important

4:22:12distinction that we wanted to make.

4:22:15Continuing with reducing speeds. Uh next

4:22:17slide please. We are proposing curb

4:22:20extensions at Homer Avenue and Channing

4:22:22Avenue intersections. Uh this is similar

4:22:25to what you see entering Carfree Cal A.

4:22:28Now I won't go into too much detail

4:22:30about these but really the point here is

4:22:32curb extensions are identified by the

4:22:34Federal Highway Administration as a

4:22:36safety countermeasure. physically

4:22:38tightening the roadway at intersections

4:22:40and visually narrowing the roadway to

4:22:42slow turning vehicles. And this um is an

4:22:46intentional safety design. Uh by

4:22:49narrowing the throat, drivers are forced

4:22:51to slow down so to bicycle speeds,

4:22:54creating a single file and highly

4:22:56predictable intersection for all users.

4:23:00And regarding volumes, to address high

4:23:03uh next slide, please high traffic

4:23:05volumes, we need to deter cutroughs.

4:23:07This is something that the residents uh

4:23:09spoke about a lot. Uh currently about

4:23:11half of the vehicle tra vehicle traffic

4:23:14on Bryant Street enters via the

4:23:16eastbound left turn from Embaradero

4:23:18coming from Town and Country. So staff

4:23:21suggests a pilot to restrict the left

4:23:23turn from eastbound Embarcadero to

4:23:25northbound. And we can do this in a

4:23:28short term with paint and plastic

4:23:29delineators to understand the outcomes

4:23:32and impacts of that turn restriction. So

4:23:34proposing that as a pilot first

4:23:37and finally legibility uh back a bike

4:23:40boulevard should be instantly

4:23:42recognizable. We are proposing to add

4:23:44highly visible bike boulevard pavement

4:23:46legends directly on the road of each

4:23:48block.

4:23:50Uh and just lastly a point here about uh

4:23:53managing additional vehicle volumes on

4:23:55Waverly. So recognizing that restricting

4:23:58that left turn at Embaradero might move

4:24:00some of that traffic to the next

4:24:02signalized intersection at Waverly

4:24:04Street at Embaradero. So to proactively

4:24:06manage this and prevent Waverly from

4:24:08becoming a new cut through, we suggest

4:24:10installing a new additional traffic

4:24:12circle at the Lincoln and Waverly

4:24:14intersection.

4:24:17So to summarize uh based on data and

4:24:20recent community feedback, staff

4:24:22recommends advancing the package of

4:24:25improvements shown on the slide. Sorry,

4:24:27next slide please. Uh to directly

4:24:30address uh the resident concerns and

4:24:34again uh move forward with a priority

4:24:36project from the BPTP. And couple slides

4:24:39over just to close out with some next

4:24:41steps. There is an online survey open

4:24:44now through October 9th for the public

4:24:46to provide feedback on the concept

4:24:48plans. And tonight, we're asking the

4:24:50commission to recommend that the city

4:24:52council direct staff to advance these

4:24:54updated elements. And again, following

4:24:56tonight's meeting, we will present these

4:24:58plans to the city council on November

4:25:009th to get their uh authorization to

4:25:03advance the project to either 65 or 100%

4:25:07design. And that concludes my

4:25:09presentation. Thank you. I'm available

4:25:11to answer any questions.

4:25:13>> Okay. So, we've still got quite a few

4:25:15people in chambers for 10:10 p.m. And

4:25:17so, just wanting to remind everybody to

4:25:19get your speaker cards in um because

4:25:22usually we cut off uh notification of

4:25:26public comments 5 minutes after the

4:25:28staff presentation. Um

4:25:31commissioners, any clarifying questions?

4:25:35>> Commissioner Templeton, Ben James.

4:25:39>> Thank you. Uh thank you for a great

4:25:41presentation. I love the diagrams that

4:25:43you provided so much useful information

4:25:45to help us prepare. So thank you very

4:25:46much. Um I I wanted to ask you said you

4:25:50had gotten some community feedback. How

4:25:52how is that like volumetrically? Do you

4:25:56feel like some significant portion of

4:25:58the community has weighed in on this or

4:26:01are we going to be surprised like

4:26:05sometimes happens. So,

4:26:08>> uh, we hosted a, uh, neighborhood

4:26:11meeting with, uh, residents from the

4:26:14immediate adjacent area. There were

4:26:16about two dozen attendees. Um,

4:26:19>> two dozen

4:26:20>> two.

4:26:21>> Okay.

4:26:21>> Two dozen about 24

4:26:23>> Yeah. folks showed up and um

4:26:27overwhelmingly in support of the project

4:26:30and if anything asked us to uh move as

4:26:33fast as we can towards implementation.

4:26:36There was um some debate around whether

4:26:40there should be a traffic circle or a

4:26:42diverter at the Bryant and Lincoln

4:26:44intersection and I went a little bit

4:26:46more into that in detail in the staff

4:26:47report and I'm happy to elaborate. Um

4:26:49but overall we feel relatively confident

4:26:52about the initial engagement that we

4:26:54did. We passed out about a hundred uh

4:26:56paper flyers to the neighborhood

4:26:58announcing the meeting and we have met

4:27:01with additional residents from the area

4:27:03on a one-on-one basis after the meeting.

4:27:06Um and I looked today and there's about

4:27:0850 survey responses.

4:27:11>> And you're feeling generally there's

4:27:12still positive support. Looks like you

4:27:14have a comment as well.

4:27:16Um so I would like to add that the

4:27:19petition came from neighbors you know

4:27:22across both both streets Bryant and

4:27:24Lincoln. Um at the neighborhood meeting

4:27:27we had um passed out the flyers also on

4:27:30Waverly right um but they were not well

4:27:34represented at I don't there might have

4:27:36been one person who's actually other

4:27:38dest from from Waverly um

4:27:41>> thank God for you

4:27:43>> so yeah so staff noticed that that

4:27:45>> okay

4:27:45>> that street even though we' noticed them

4:27:49it was not well represented at the at

4:27:51the neighborhood meeting

4:27:52>> it can happen right so it's it's good to

4:27:54talk about it and you still have it

4:27:55Sounds like it's still open for public

4:27:57comment. So,

4:27:58>> yes, that's good.

4:27:59>> And I think that also in terms of um the

4:28:02community feedback,

4:28:05we had initially proposed a diagonal

4:28:07diverter at Lincoln and Addison and um

4:28:12Lincoln and Bryant, sorry. Um and the

4:28:16feedback from the immediate neighbors

4:28:18was uh

4:28:20maybe not. And um I would expect that as

4:28:23you go further away it would be get more

4:28:25negative. And so that was part of our

4:28:27thinking as we shifted to the circle in

4:28:29that location that

4:28:30>> that's really good context. Yeah. Thank

4:28:32you for that. Um I have one more

4:28:34communityoriented question to find out

4:28:37if it plays at all. Um, in my

4:28:40conversations with people in this area,

4:28:43like I'm I've definitely heard um all

4:28:45the same stuff about Lincoln, but I I

4:28:48heard Emerson is giving people fits and

4:28:52has been for decades. Is that some place

4:28:55that still needs attention? I say I see

4:28:58Miss Starlac over there may have heard

4:29:00the same kind of comments. I don't know.

4:29:03Um, is is this going to improve the

4:29:06situation at Emerson and Barkadero or is

4:29:08it going to make it worse?

4:29:09>> Um, my understanding of the situation at

4:29:12um Emerson is to do with kind of the

4:29:15concept of a clover leaf. So, as you're

4:29:18coming off Alma turning to the and you

4:29:20want to go onto Embaradero heading

4:29:23towards Stanford. So, people are turning

4:29:26to the right on Lincoln and then right

4:29:27on Emerson then right on Oh, no. That

4:29:30doesn't make sense, does it?

4:29:32>> Yeah. I'm thinking I'm thinking about

4:29:34bites though. It it's used as a clover

4:29:36leaf to get to somewhere. Um

4:29:39>> Embaradero.

4:29:40>> Yeah, you're not wrong. That's right.

4:29:41Yeah. Yeah, it's fine. It doesn't go

4:29:43through. Um and so

4:29:46>> but so I don't bikes though. It's not

4:29:48the cars that's the problem there. The

4:29:50bikes in that specific area. There's

4:29:53people who live there and are like

4:29:55constantly like nashing their teeth

4:29:58about the dangerous bike situation. I

4:30:00don't know if that is going to be made

4:30:03worse or better. It sounds like better

4:30:05because

4:30:05>> so over the summer we completed a

4:30:07project at that exact location.

4:30:10>> So that's better now.

4:30:11>> It's much better.

4:30:12>> That's all I need to know cuz I I that's

4:30:15what I was I was concerned. I was like

4:30:16if this is going to make that worse then

4:30:18no. But already you've got improvements

4:30:20there. So we're good. So this is the

4:30:22next step.

4:30:24>> It's just it just Yeah. In addition to

4:30:27that project, just another effort. The

4:30:29Emerson Street improvements were done

4:30:30right before the start of the school

4:30:32year.

4:30:32>> Great. I haven't been down there. I'll

4:30:34have to go look. That's great. Okay.

4:30:36Well, that's all I need to know. Thank

4:30:37you,

4:30:39>> Mr. James.

4:30:41>> Um, well, as luck would have it, um, I

4:30:44lived at Brian and Lincoln, uh, and was

4:30:46on the one of the people that signed the

4:30:48petition. Um and actually Miss Low uh

4:30:52right after she um came to work in

4:30:55PaloAlto um went out and knocked on

4:30:58doors in the in the area. So and was um

4:31:01including mine and uh so I was very kind

4:31:03of impressed from from the start at how

4:31:06you uh

4:31:09uh wanted to talk to neighbors. I think

4:31:11maybe at that point maybe they were

4:31:13painting 21 foot red stripes and and and

4:31:16there needed to be some uh some

4:31:18conversation. So, but I I have uh picked

4:31:20up bikers out of my front yard and and I

4:31:23have uh lots of pictures on my phone of

4:31:26crashes that so even though we're sort

4:31:29of you know primarily like bike safety

4:31:31is driving this, it's going to be sort

4:31:32of have some great benefits for uh fewer

4:31:36fewer uh t-bone collisions right there.

4:31:40Um, so I I wanted to ask about the um

4:31:42the circle at uh at Addison. You said

4:31:46that would be sort of upgraded. Um, and

4:31:48I think that you referred to these as

4:31:50small circles and I actually live very

4:31:53near the one Hawthorne and in Kapper

4:31:55now. Um, so I'm I'm familiar with that.

4:31:57Is that does that one that one always

4:32:00seemed like it kind of pushed cars

4:32:03pretty close to the crosswalks to me?

4:32:07Um, and I think if I read the the

4:32:10drawings correctly, um, the design for

4:32:14these actually there's, you know, pushes

4:32:16the crosswalk back a little bit from the

4:32:18corner. Is that right? I guess if I just

4:32:21get you to kind of comment a little bit

4:32:24is are you are the new circles going to

4:32:27be the same size as Addison? Are they

4:32:28smaller? You mentioned the trunk apron.

4:32:31I mean, that's just kind of the one that

4:32:33I have a kind of comparison to there. It

4:32:36does feel a little I think the ones over

4:32:38near Hawthorne are are smaller.

4:32:42Um so just kind of wondering if you can

4:32:45talk a little bit about the design of

4:32:47those and am I reading it correctly that

4:32:50you know there sort of bulb outs to get

4:32:52more sort of visibility of pedestrians

4:32:55and and artwalks sort of moving back

4:32:58from the corners a little bit to create

4:33:00space. Can you just talk about that a

4:33:01little bit?

4:33:05I would say it's a it's design

4:33:07consideration at this point. Uh we

4:33:10haven't at 15% concept designs. We

4:33:13haven't drilled down to that level. What

4:33:15I will say is that they will be more

4:33:18fitting to the specific intersection.

4:33:21>> Uh will they all have the same

4:33:23dimensions? Probably maybe not

4:33:26considering, you know, these

4:33:27intersections might look slightly

4:33:28different. The feedback that we've

4:33:29received from the Addison traffic circle

4:33:32is around the curb that it currently

4:33:36has. And uh also

4:33:38>> the curb on the

4:33:39>> on the traffic circle itself

4:33:41>> uh rather than it being flush or this

4:33:43truck apron that we're referring to um

4:33:46in addition to the comment that you

4:33:48mentioned around uh it has a feeling

4:33:51that the cars move into the pedestrian

4:33:54space. So we would need to look at the

4:33:57entire design of the Addison traffic

4:33:58circle again to ensure that uh it's more

4:34:02form fitting to that intersection. Um

4:34:06there uh we do have uh uh uh Hugh from

4:34:12uh Faren Piers the consultant on the

4:34:15call if they want to elaborate a bit

4:34:18more on the traffic circle dimensions.

4:34:21Um, another point I want to make is I

4:34:24don't want to confuse the traffic circle

4:34:26proposals or recommendations to the curb

4:34:29extensions and those can happen in

4:34:32different intersections and the curb

4:34:33extensions do uh bulb out bring out the

4:34:37the walkway to shorten to tighten the

4:34:40the intersection. Um, again, all for

4:34:42traffic calming purposes, but you might

4:34:44not see those at the same intersection

4:34:46simply for space purposes.

4:34:50>> Thank you.

4:34:51Um, so I don't see other lights. Let's

4:34:54go to public comment.

4:34:56How many do we have?

4:34:57>> Uh, chair, we have six requests to

4:34:59speak.

4:35:00>> All right. Um, let's do three minutes

4:35:03and hopefully you don't need it.

4:35:05>> Okay. Uh, our first speaker is Rob S,

4:35:07followed by Jack T.

4:35:16>> Good evening, uh, Madame Chair, uh,

4:35:19commissioners. My name is Rob Steinberg.

4:35:21I'm an architect. I've lived uh on the

4:35:24bicycle boulevard for the last 45 years.

4:35:27I have been working with the city on the

4:35:30safety of that for the last 20 years.

4:35:33I have been one of uh two members that

4:35:37have um brought in 40 signatures of our

4:35:41neighbors and I think I speak for many

4:35:43of them tonight when I say we are 100%

4:35:48in favor of staff recommendation

4:35:53100%. Number two, the transportation

4:35:58department. These four people sitting

4:36:00here deserve an attab boy. They have

4:36:05done a phenomenal job of It took us a

4:36:09while. It took us a long time to get

4:36:12their ear, but when we got it, they have

4:36:14listened to us. They have responded.

4:36:18They have been flexible. They have

4:36:20adjusted to what the community wanted.

4:36:22And it's really they should be commended

4:36:27for the process that they've gone

4:36:28through to get us to this point. And my

4:36:32third point is

4:36:34I have an ask from you. We have been

4:36:38discussing this for years. It is a

4:36:41safety concern for all of our neighbors.

4:36:44We saw how quickly the city was able to

4:36:48construct the intersection of Emerson

4:36:51and Embaradero. When the city made up

4:36:54their mind to do it, they did it

4:36:56quickly. And we're asking for your help

4:36:59tonight. Please send a message to the

4:37:03council. We want this done. We've been

4:37:06talking about this for years and years.

4:37:09It's time to move forward. We're all in

4:37:12agreement. Please make this happen

4:37:15quickly before we have a tragedy. Thank

4:37:18you.

4:37:19>> Thank you.

4:37:20>> Our next speaker is Jack T followed by

4:37:22Monica White.

4:37:32>> Uh good evening. Uh my name is Jack

4:37:35Turner. Um I want to thank everybody for

4:37:39all their hard work and for helping move

4:37:41this project forward. Um, I am now

4:37:45raising my children in the house that I

4:37:47grew up in

4:37:49on Brian Street and uh things that maybe

4:37:53I didn't notice as a kid uh have become

4:37:55very apparent to me as a parent and uh I

4:37:58worry about my kids, their safety

4:38:01crossing the street. I don't think a day

4:38:03goes by that I don't hear a screech of

4:38:06brakes at that intersection. Um, and

4:38:09occasionally we get we do hear uh a

4:38:12crash. Um, we've got pictures of cars in

4:38:16u your guys' yard. Um, and uh so I was

4:38:22the one who uh one of the one of the

4:38:24people who participated and sort of

4:38:26brought that um petition I think back in

4:38:292024. And so, uh, I think everything Rob

4:38:32said, um, is is on point with, I think,

4:38:37how I feel and I think all the neighbors

4:38:39feel. So, we would love for it to move

4:38:40forward as quickly as possible. Thank

4:38:42you.

4:38:44Next speaker is Monica Y followed by

4:38:46Adrien A.

4:38:58Good evening, commission commissioners.

4:39:01Um, I'm Monica Young Arma and I live on

4:39:051052 Brian Street, right at the corner,

4:39:09north

4:39:10west corner of Brian and Lincoln for

4:39:14more than 30 years. So I have observed a

4:39:18lot of activities there because I have

4:39:20my home office at home in the front. I

4:39:23would say we average probably about once

4:39:28a week at least one accident per week

4:39:33that is not noticed by other people

4:39:36because if there is no injury is never

4:39:39reported to the police. So it's not in

4:39:41any of your records that you can see.

4:39:44But by my observations and maybe perhaps

4:39:47other people's observation they can tell

4:39:50you that this happened very frequently.

4:39:53The reason for that is Lincoln is a

4:39:55street carry the traffic all the way

4:39:58from university crescent park community

4:40:01center area middlefield to Elma. A lot

4:40:06of people have high school students to

4:40:08bring their kids to Pali, but they don't

4:40:11use Embado because the traffic is pretty

4:40:15bad. So I think people that are local,

4:40:18they are they are very aware of that. So

4:40:21something need to be done to that

4:40:22because Brian Street is a bike lane and

4:40:25it doesn't have any stop sign. So as

4:40:28soon as the people start on embado they

4:40:31will speed all the way down without

4:40:34consider anything in a hurry to get to

4:40:37their destination. So I think that for

4:40:39that anything that you do with uh

4:40:43slowing the traffic will be helpful. Uh,

4:40:46like the gentleman said, one accident of

4:40:50the one that I mentioned, we were not

4:40:52home,

4:40:54but the car ran into my yard right at

4:40:56the corner. I have a metal fence, metal

4:41:00post, but the metal post actually fell

4:41:03down. So, you could imagine how much

4:41:06impact that is. And that's not good. And

4:41:12I saw the report that says in 1912 a

4:41:15study was done on stops four-way stop

4:41:18sign but it wasn't um implement because

4:41:21it was not recommended. So I would say

4:41:24that anything that you do whether it's

4:41:26stop sign or circle will slow down the

4:41:29traffic will be helpful. Um another

4:41:31thing that I didn't mention that I

4:41:33wanted to mention today is the traffic.

4:41:36You go on Brian Street in the morning

4:41:38and in the afternoon, there is the fine

4:41:41spot. When the sun rise and the run

4:41:43sunset, when you look ahead of you, you

4:41:46can't really see very far distance. So,

4:41:48it's actually very dangerous for people

4:41:50that are driving very fast. And uh

4:41:54lastly, one more point, not related to

4:41:56the subject. This is um going on for a

4:42:00long time, street cleaning signs. And I

4:42:04asked for that for many many times but

4:42:07it's just never have any response.

4:42:09Transportation would say public work,

4:42:12public work would say street cleaning.

4:42:14So we need to coordinate to get that

4:42:17done so that you don't have to nail a

4:42:20nail on the streets.

4:42:23>> Thank you.

4:42:24>> Our next speaker is Adrian A followed by

4:42:26Paul G.

4:42:30Uh good evening and thank you for the

4:42:32opportunity to speak to you. Um I do

4:42:35want to affirm the uh the good work that

4:42:38the staff has been doing on this. It's

4:42:40been really really wonderful to work

4:42:42with them on it. So kudos to them. Um my

4:42:46main comment regarding the uh proposals

4:42:49is first of all that there there is

4:42:52virtually 100% support in the

4:42:54neighborhood for this. Uh we've talked

4:42:56to other neighbors that weren't at the

4:42:58meeting and they all agreed that

4:43:01something needs to be done and this is a

4:43:03pretty good approach to it. Um my one

4:43:06thought was which I expressed to staff

4:43:08and they have incorporated it in their

4:43:10revised proposal is to do it in phases.

4:43:13you can start soon. Um, and the the

4:43:17first thing you can do is close off the

4:43:19access to Embaradero at Bryant. Um,

4:43:22which is easy to do and actually was

4:43:24done um a couple months ago for the

4:43:27because of the construction

4:43:29and u because I live at Lincoln and

4:43:31Bryant I would expect that to be pretty

4:43:33inconvenient but actually it wasn't.

4:43:36It's a very very minor inconvenience to

4:43:38have it closed and there's really no

4:43:39reason to have it open when there's a

4:43:41full intersection at Waverly and

4:43:43Embaradero. So that's something you can

4:43:46do. And then the next priority would be

4:43:48the traffic circle at Brian and Lincoln,

4:43:51which is the the major um problem area.

4:43:55Um but I don't think you need to do the

4:43:57whole project at once. You could

4:43:59implement that and then see if that's

4:44:02enough. And I I kind of doubt whether

4:44:06you need a traffic circle at Kingsley

4:44:08and Bryant because Kingsley is a dead

4:44:11end street and under the proposal Bryant

4:44:13become a dead end street at Embaradero.

4:44:16Um and there's a dip there. So there's

4:44:18signs that say 15 miles an hour dip. So

4:44:21I'm not sure you would need it and maybe

4:44:23if you implement the circle at Brian and

4:44:24Lincoln that would be enough and you

4:44:26would not need it to spend the money on

4:44:28that. So I urge kind of a step by step

4:44:31maybe phase by phase process um and then

4:44:34we can stop when it's good enough. Thank

4:44:38you very much.

4:44:40>> Our next speaker is Paul G.

4:44:48>> Thank you. My name is uh Paul Goldstein.

4:44:50I live at 1024 Emerson Street. Um,

4:44:54and I strongly support doing something

4:44:58on Bryant. I am a bicyclist. I was on

4:45:02the payback for many years. Um, Bryant

4:45:06Street is the premier bicycle facility

4:45:09and the oldest bicycle boulevard in the

4:45:12country. it. Um

4:45:15I've lived in my house for over 50 years

4:45:19and it has just gotten much busier

4:45:23especially in the last maybe 5 years. Uh

4:45:27traffic volumes have to be cut down and

4:45:30I strongly support having no left turn

4:45:34off um embaradero. I agree with the

4:45:37previous speaker. I think we can do this

4:45:38in phases and uh we can pilot the no

4:45:42left turn, see if that cuts down the

4:45:44traffic. I've not found the speeds to be

4:45:46quite so high, but I trust the speed

4:45:49study. As a pedestrian in the area, I do

4:45:53not like the Addison Circle. I live

4:45:57about a block and a half from it. I walk

4:46:00through it about every day, maybe

4:46:03sometimes twice. cars do not slow down

4:46:07as much as they should, maybe with

4:46:09better signage or something or maybe

4:46:12even street decorations or something.

4:46:16Um, but because the circle is large, the

4:46:20cars swerve out into into the pedestrian

4:46:23crosswalks. Maybe having marked

4:46:26crosswalks would work, but as a

4:46:28pedestrian, I do not like them. As a

4:46:31bicyclist, I have no trouble slowing uh

4:46:34as I say, slowing down traffic isn't as

4:46:37much of a concern as just reducing the

4:46:39number of cars. And I would hope that

4:46:41the left turn um restriction would help

4:46:44that. The improvements on Emerson

4:46:46Street, which is the street I live in,

4:46:49have been I I would like to congratulate

4:46:52uh transportation on that. They were

4:46:54done quickly. Um and I feel that they

4:46:57work they work well at the moment. There

4:47:00is there is some um driver malfunction

4:47:06with them but I can I can handle that

4:47:08with transportation staff. That's all I

4:47:10have to say. Thank you very much.

4:47:13>> Uh our final speaker is Bruce A.

4:47:16>> Uh thank you very much. I agree with

4:47:18what everyone said. Let's do this. Let's

4:47:19do it quickly. I would only add if it's

4:47:21not enough, I'd like to add a modal

4:47:24filter on Bryant. Also, there's a lot of

4:47:26people who get directions from south of

4:47:29here and the directions of downtown will

4:47:31take them down Embarcadero and down

4:47:33Bryant Street. And if we could add a

4:47:35modal filter like we have the other ones

4:47:37on Bryant that work so well in that same

4:47:39neighborhood, that would be a

4:47:40spectacular improvement if the circles

4:47:42and the ballouts prove insufficient.

4:47:45Let's do it fast. Thank you.

4:47:48>> All right, the chair. I have no other

4:47:50requests to speak.

4:47:51>> Thank you. Um, so I just want to make

4:47:53sure that we get uh, Commissioner Aken's

4:47:57comments in before he needs to leave

4:47:59because he lives in this neighborhood,

4:48:00too.

4:48:03>> Thank you, Chair. Yeah, apologies to

4:48:05everyone. I have a family obligation I

4:48:07can't um, omit. Um, everyone has been

4:48:12thoughtful and extremely responsive on

4:48:15this project. It's been very well

4:48:18managed and uh I think the uh I think

4:48:22the outcome is excellent. Uh so along

4:48:25with uh my neighbors I uh hope that it's

4:48:28uh that it proceeds to implementation

4:48:31fairly quickly. Um the only comments I

4:48:36have are fairly technical.

4:48:38Um it'll be interesting to see the

4:48:40physical design standards for the new

4:48:42traffic circles. um

4:48:46what sizes of particularly trucks are

4:48:50going to be able to make it through

4:48:52them. Um

4:48:55whether the straight through bicycle

4:48:58paths encourage additional stop sign

4:49:00running uh beyond what we already have.

4:49:04Uh and whether there are uh ballouts on

4:49:08the curbs which have been sources of

4:49:10complaint uh in other areas.

4:49:14Uh so if someone uh demands that you

4:49:19uh compare and contrast these traffic

4:49:23circles with Ross Road, you should be

4:49:25prepared.

4:49:28Um

4:49:30I think the last comment I want to make

4:49:33is um

4:49:36about traffic on Waverly.

4:49:39So the as you see from the data that you

4:49:41provided uh weekday average is around

4:49:443,700 vehicles a day now.

4:49:48Uh so that's up from the years that I

4:49:51was doing traffic measurement. Um and if

4:49:55you actually succeed in taking a

4:49:57thousand vehicles off Bryant, you don't

4:49:59want those adding to the 3,700 that are

4:50:02already on Waverly. Um, the last time I

4:50:05measured traffic on Lincoln, um, it was

4:50:08just shy of 2500 vehicles a day. You

4:50:12don't have a direct equivalent to that

4:50:13in the measurements you've taken for

4:50:15this, but just be aware that there's a

4:50:19lot of load at that intersection.

4:50:22So, you may need to uh

4:50:25uh at least

4:50:27uh take some measurements once the

4:50:29implementation is done and figure out

4:50:31what's really going on. uh as a result

4:50:34of these changes.

4:50:36But that in no way uh means that uh I'm

4:50:40recommending against the changes.

4:50:46I think those are all the essentials.

4:50:48Thank you very much for uh your work on

4:50:50this project.

4:50:53Thank you. All right. I don't see other

4:50:55lights. Are there other people who would

4:50:57like to speak? Commissioner Hecman

4:51:00and then Vice Chair G.

4:51:04uh a few

4:51:07I guess that's a combination of

4:51:08questions and comments. Um the uh 10

4:51:12collisions uh along Bryant um in the

4:51:1910y year 8year period those aren't um

4:51:24those aren't necessarily involving

4:51:26bicyclists. Those could be card uh two

4:51:28automobiles.

4:51:30>> Correct. Okay. All right. Um I I do

4:51:33think uh it's not acceptable. I I I

4:51:38don't know if we've got another fourb

4:51:40block nonarterial

4:51:43with with 10 crashes in eight years, but

4:51:46to have it on our famous bike boulevard

4:51:50is a bad look. So, um I'm really glad

4:51:54staff is uh tackling this uh project and

4:51:58um I like the street furniture concepts

4:52:02that you've come up with. Um

4:52:05I noticed in uh on packet page 2011, the

4:52:10project goals include restoration of

4:52:13some on street parking. And when I look

4:52:16through the six actions, I could see

4:52:19that the curb extensions may actually

4:52:22reduce a couple of on street parking

4:52:25spaces, but I couldn't tell whether any

4:52:28of the other five added on street

4:52:30parking. And so maybe you could clarify

4:52:33that. Um yes. So as part of so the

4:52:36original request that staff received as

4:52:39I understand was for a fourway stop sign

4:52:42and um it didn't make warrant in terms

4:52:45of the manual for uniform traffic

4:52:47control devices. Um but a secondary

4:52:50analysis that happened as part of that

4:52:52was um sight triangles based on the

4:52:56highway design manual. And so we

4:52:58actually have some red curve out there

4:52:59that is quite long and that would be

4:53:02reconsidered as part of this process of

4:53:04introducing these new treatments and

4:53:06also um

4:53:09I'm not sure how the timing will work

4:53:11out but we we're also planning on doing

4:53:13speed surveys to potentially reduce

4:53:15speeds and that would also reduce those

4:53:16triangles.

4:53:17>> Okay. So my suggestion is as this moves

4:53:20to council just

4:53:23you don't want to take up their time

4:53:25asking the same question I just asked.

4:53:26How are we going to add parking? So

4:53:28maybe just add a sentence somewhere

4:53:31because I I did read somewhere else in

4:53:32the staff report that this there was a

4:53:35tempor there there was a reduction of

4:53:37parking and so I figured okay I think I

4:53:40think we're putting that back but I

4:53:42wasn't sure. So anyway, I think you can

4:53:43clear that up. And then the other

4:53:45question I have is kind of technical.

4:53:46I'm curious about the um uh the no left

4:53:51turn from Embaradero on to Bryant. And

4:53:53so u I was just trying to understand the

4:53:57traffic volumes that will be reduced by

4:54:00that. And so I'm looking at packet page

4:54:04uh 218

4:54:06and I want to find out am I reading this

4:54:09right that that

4:54:11in the AM peak by having this

4:54:15restriction we will basically

4:54:18stop what's typically 48 cars from

4:54:22making that movement

4:54:26then on 218

4:54:31Uh, I believe you're correct, but I will

4:54:33ask Hugh to jump in here. Uh,

4:54:37Hugh, I don't know if you have page

4:54:38packet 218 open.

4:54:41I think you're mute. You're you might be

4:54:43muted, Hugh.

4:54:44>> Sorry. Hi, Huge from Fran Pierce. I I

4:54:46don't actually Sorry, I need a minute to

4:54:48grab that, but yes, that sounds correct.

4:54:50>> Okay. And then in the PM it's 126 it

4:54:56looks like

4:55:00that's on 221,

4:55:04>> right? That sounds correct as well.

4:55:06Yeah. And to be fair, those are peak

4:55:08hour numbers, not all day numbers.

4:55:10>> Yeah. Yeah. Peak AM and PM. And then is

4:55:13there some place in these tables that

4:55:15tells me what the the total daily is?

4:55:19No, we just have the peak. I think we

4:55:22have might have peak two hours. So, we

4:55:23might have about four hours out of the

4:55:25whole day. And we could give a rough

4:55:27estimate of what that is given general

4:55:29shares, but um but not an exact number.

4:55:33>> Okay. So, um yeah, I'd be I'd be

4:55:35interested in that kind of rough

4:55:36estimate just because I think the one of

4:55:38the slides shown was that we've got like

4:55:41twice the traffic on that road than the

4:55:44desirable metrics would provide for. And

4:55:47so so you know it looks like just during

4:55:48the peak we're cutting almost 200. I

4:55:51would hope maybe you know maybe twice

4:55:52that over the course of a day which

4:55:54would be great. Yeah. All right. Uh

4:55:57thank you. So I'm I am supportive of

4:56:00staff recommendation on this.

4:56:02>> Vice Chair G.

4:56:04>> Yeah. Thank you. Uh I have two

4:56:06questions. One is Mr. Arce you said you

4:56:09could elaborate further about the

4:56:11diagonal diverter. Could you talk about

4:56:13why that was no longer recommended?

4:56:19Yeah. So, as uh the director mentioned,

4:56:22uh we received feedback from the

4:56:25residents and it was split about the

4:56:27diverter or the traffic circle at Bryant

4:56:30Lincoln. And um in this in the spirit of

4:56:34implementing quickly and and not

4:56:37necessarily needed to head in a

4:56:38direction where we would potentially be

4:56:40asked rightfully so to do additional

4:56:43analysis and data collection on uh

4:56:46modeling what that diverter would look

4:56:48like in either direction. Um, and as as

4:56:52the director noted that if we feel like

4:56:54as we're doing additional community

4:56:56engagement, as the project advances and

4:56:58more people from the neighborhood find

4:56:59out, it it might not necessarily get

4:57:02more popular. And so under the context

4:57:06of again moving fast and this idea of

4:57:08residents and neighborhood support, uh,

4:57:11we shifted to the traffic circle.

4:57:14>> Okay. And I see listed in the staff

4:57:16report that item on packet page 203 that

4:57:19items 1 through five were supported. But

4:57:21I see that you've still included the

4:57:24short-term parking

4:57:26for the uh item

4:57:29uh the short-term parking zone. I think

4:57:32was that let me just double check.

4:57:35>> Yeah, I see that that wasn't one of the

4:57:37items that the community had been

4:57:40supportive of, but yet you're still

4:57:42choosing to advance that as a staff

4:57:43recommendation. Can you explain that?

4:57:45>> Um, yeah, I can respond to that. So,

4:57:47this was something that was not strongly

4:57:50supported at the community meeting, but

4:57:52it was also not strongly opposed. Um, it

4:57:54is something that is, um, requested by

4:57:57our fire department. Um, as someone who

4:58:01rides along this street every day, the

4:58:03fire department is at this location more

4:58:07than once a day. And so it would be nice

4:58:09for them to have a spot that they could

4:58:11stand in and that doesn't cause the

4:58:13students to have to ride on the wrong

4:58:15side of the street as they're getting

4:58:16past the the fire truck.

4:58:19>> Okay. Awesome. Thank you. That that

4:58:20context is helpful and I'd recommend

4:58:22putting that information in the report

4:58:24that goes to council. I'm generally

4:58:26supportive of this project as a whole.

4:58:29I'm very excited. Um but two main

4:58:32comments I want to provide. one is that

4:58:35I'm when looking at the data that

4:58:39Commissioner Hecman had mentioned which

4:58:40is about kind of the traffic at Brian

4:58:44and Lincoln and Brian and Barkadero like

4:58:47so for example on packet page 212 I'm

4:58:49looking at Brian and Lincoln during peak

4:58:51hours it looks like there's just a sheer

4:58:55volume issue we have a volume issue at

4:58:57this intersection and in south Paul Alto

4:59:00Bryant has significant modal filtering

4:59:02and on Park Boulevard, which I bike

4:59:04often as well, there's a lot of modal

4:59:06filtering. And so for me, I think that

4:59:10the most obvious solution to be reducing

4:59:14demand is to just prevent the cars from

4:59:17driving there. In fact, uh sometimes

4:59:20after commission meetings, I drop off

4:59:22Commissioner Akin at his house, which

4:59:23is, as we've noted, in the zone. And

4:59:25what does Google tell me to do? Tells me

4:59:27to drive down Lincoln, right? And so and

4:59:31then also potentially sometimes turn on

4:59:33Bryant to go down in Barkadero, right?

4:59:35And so I feel like for me personally,

4:59:39modal filtering would be the best

4:59:42solution

4:59:44to the problem at hand. And I admit that

4:59:47um from staff's I agree with staff that

4:59:50we don't want to spend that much time

4:59:51potentially at this point investigating

4:59:53further into that. But I think that the

4:59:55the cor the quote unquote correct

4:59:57solution to be resolving this issue is

4:59:59to add modal filtering here on Bryant

5:00:01instead. And then the other thing that I

5:00:05want to say is that I'm not as

5:00:08supportive of the permanent curb

5:00:11extensions. So I've biked on several

5:00:13streets where we do have the curve

5:00:16extensions come out and I do agree that

5:00:17it is great for pedestrians because it

5:00:19does shorten the distance that the

5:00:21crosswalk needs to have. But what I find

5:00:23that happens to me as a biker is that

5:00:24pushes me into the lane with the car and

5:00:27I really don't see the car slowing down

5:00:30because as noted in the diagram on

5:00:33packet page 205,

5:00:35you'll see that the curb out really just

5:00:38comes to kind of where the a little bit

5:00:40further than where the parking is. And

5:00:42so the cars don't really have that much

5:00:45of a narrowing that occurs because

5:00:48they're already avoiding the the parked

5:00:49cars that are already there. and but

5:00:51instead as a biker that usually ends up

5:00:53what happens is that forces me into the

5:00:55road where I'm competing with cars and

5:00:58so that's one that I'm not as

5:01:00enthusiastic about but otherwise I'm

5:01:02generally supportive of this project as

5:01:04is

5:01:07>> commissioner and for the record

5:01:09commissioner Aken has left

5:01:11>> thank you

5:01:13>> u thank you before I make my comment um

5:01:16does staff want to respond I mean I

5:01:18assume this is best practice ice, but

5:01:21could you respond to vice chair G's

5:01:25>> um in terms of the bulb out the

5:01:27>> Yeah, he said it's it's bad for him as a

5:01:29biker. So, what do you say to that?

5:01:31>> So, the um curve ball belts are included

5:01:34by the Pedro Highway Administration as a

5:01:38um proven safety counter measure and

5:01:39they do reduce speeds. So it it can be a

5:01:43little counterintuitive because it is

5:01:45coming into the roadway, but I think

5:01:47psychologically motorists respond to it

5:01:50by driving at a slower speed. And so and

5:01:52also for bike boulevards um we do expect

5:01:57the cyclist to ride in the lane to take

5:02:00the lane um and there is parking so they

5:02:03will already be taking the lane. Um,

5:02:05when we do uh safe routes to school, we

5:02:07encourage the students not to swerve

5:02:09back and forth between the parking lane

5:02:12and the the travel lane when they're

5:02:14riding along a street because that can

5:02:15make them unpredictable and so staying

5:02:18in a straight line is is what we

5:02:20recommend anyway.

5:02:22>> Thank you. Um so my um question is um

5:02:26for the pilot of of removing the left

5:02:29turn capability um

5:02:33what are the success criteria and what's

5:02:35the timeline?

5:02:37So how do we in other words is this a

5:02:39reversible pilot? We've been burned by

5:02:42that one before. So um like how do we

5:02:45know when it's done and is there the

5:02:48option to roll it back?

5:02:54Sorry,

5:02:55I didn't mean to catch off guard with

5:02:57that.

5:02:57>> Yeah, those are that's a great question.

5:02:58I you know, I don't know if we've we've

5:03:00given it as much thought as um as maybe

5:03:04at this point uh simply I think because

5:03:07of this more more recent pivot to to

5:03:10turn it into a pilot, okay, as the

5:03:12initial phase. Um

5:03:15I think the bottom line though is that

5:03:17we want to learn and understand from the

5:03:20pilot program. So there will be a data

5:03:23collection effort and observations done

5:03:25once implemented.

5:03:27Um but I would think um that maybe we

5:03:30give that a little bit more thought as

5:03:32we go to council.

5:03:33>> I love that suggestion.

5:03:35>> Yeah. So I think the key criteria that

5:03:37we'd be looking at are speed and volume.

5:03:39And so we would look at the speed and

5:03:42volume before and after

5:03:44>> and anything like reduction in collision

5:03:47rates or anything like that

5:03:49>> and collisions. Yes.

5:03:50>> So um I is the next step for this to go

5:03:52to council.

5:03:54Right. Okay. So if that's the next step,

5:03:56my recommendation to you guys would be

5:03:58to come up with success criteria and a

5:04:01timeline. So, for example, people if a

5:04:06person were to get frustrated that

5:04:07wasn't part of the feedback community

5:04:09you've already reached, they would be

5:04:11able to say, "Okay, I'm willing to give

5:04:13it six months and see how this works or

5:04:15I'd be willing to give it three months,

5:04:16whatever it is." Um, but also for you

5:04:19guys to as a department to measure um

5:04:22and start start thinking about it in

5:04:24terms of objective criteria that you can

5:04:27provide to council for the next step to

5:04:29finalize something because that would be

5:04:31super valuable to them. I think. Okay.

5:04:33Thank you guys. I'm I'm supportive of

5:04:35the staff motion.

5:04:38>> All right. Um I just wanted to

5:04:40understand something that I've heard.

5:04:42It's not partially related to this

5:04:45project. Um so can you explain

5:04:49the regulation of stop signs by the

5:04:51California Manual for Uniform Traffic

5:04:54Control Devices because I know that

5:04:56that's something that's been requested

5:04:58in many neighborhoods. Um, and we find

5:05:02ourselves needing to put a circle

5:05:03instead of stop signs. And I just I

5:05:07think it's be good for us all to

5:05:09understand that process.

5:05:11>> Um, so I don't have the numbers off the

5:05:13top of my head. Um, but stop signs are

5:05:17um

5:05:19essentially treated as something to

5:05:21control the the flow like where it's

5:05:23essential to deal with travel flow um of

5:05:26of vehicles. And so there's a specific

5:05:28volume that is required under the MUTCD.

5:05:32Um and particular like I think the

5:05:36collision number of collisions is

5:05:37another one. Um I'm not sure what the

5:05:40other criteria off my head. Um but a lot

5:05:44of locations don't meet those

5:05:46thresholds.

5:05:48>> So today we heard from somebody who said

5:05:51that there's Go ahead.

5:05:52>> It it looks like maybe our consultant

5:05:55would like to say something. Yeah, great

5:05:57>> if I can. just a lot of it's about the

5:05:59balance of the flows, right, from

5:06:00different directions. So if you have one

5:06:03direction that's your primary direction

5:06:04and another that has a a more light

5:06:07volume, right? That typically is one

5:06:09where they aren't uh incur they're

5:06:12discouraged, right? Because you're

5:06:14creating a situation where people will

5:06:16not they will learn to not stop um

5:06:19despite there being a stop sign and then

5:06:20that actually makes it feel or become

5:06:22often less safe for folks. So that

5:06:24that's that's the rationale behind it,

5:06:27right? Is you have stop signs that are

5:06:29not followed because they're not

5:06:30actually representing a condition that

5:06:33that would be a normal stopping

5:06:34condition. You know, it's trying to sort

5:06:36of match human behavior as best you can.

5:06:39>> Okay, that's a helpful explanation. And

5:06:41at the same time, we know, I mean, we've

5:06:44got public commenters who've said that

5:06:48there's weekly accidents here. And so,

5:06:50and I've heard the same thing from other

5:06:52neighborhoods, right, where there's lots

5:06:55of unreported accidents and then as a

5:06:58result, we can't get stop signs. So,

5:07:01I'm sure you guys are very familiar with

5:07:04this challenge. Um, and and yet like a

5:07:08circle is probably not the right

5:07:09solution in each of those places. So,

5:07:11it's just as I've been talking to

5:07:13neighbors, every single school has one

5:07:16of these near it and some of them have

5:07:18had serious accidents actually. So,

5:07:21particularly with the safe routes to

5:07:22school, I just don't I'm asking, you

5:07:24know, it's not particularly it's not

5:07:25specifically related to this project,

5:07:28but what can we do to get our safe

5:07:31routes much more protected? Um, since we

5:07:35don't seem to be allowed to to to get

5:07:38stop signs. Um, okay. Uh, then also not

5:07:43directly related to this, but I was just

5:07:45visiting the improvements that you guys

5:07:48made at Emerson. Yay. Those were

5:07:50fantastic. Um, but then the uh the car

5:07:55misbehavior that was uh mentioned

5:07:58earlier. Um, I think that there's a

5:08:01solution that's been in discussion with

5:08:03you guys about some delimiters and

5:08:04stuff. Do we know what the time frame is

5:08:06for for that improvement? So um yes we

5:08:11um so what was implemented was phase one

5:08:14of the Emerson

5:08:16actually inbucket road improvements um

5:08:19and phase two will be in the coming

5:08:22year. So our plan is to incorporate some

5:08:25potential tweaks to phase one as part of

5:08:28the phase 2 design. So it's like on a

5:08:30proper stamped plan and then um

5:08:33implement those when phase 2 happens on

5:08:35the south side.

5:08:37>> Okay. I guess there's a lot of people

5:08:39are saying faster please, but okay. Um,

5:08:44I'm supportive of the changes here. I I

5:08:47did want to

5:08:49comment that there were a couple public

5:08:51commenters had said that perhaps we

5:08:54could get some of this done more quickly

5:08:56and then kind of add to the project as

5:09:00like you know with if if Bryant and

5:09:02Lincoln is the epicenter there. um along

5:09:06with the traffic reduction with the no

5:09:08left turn. Um but then

5:09:12uh what I'm particularly sensitive to is

5:09:15the bulbout

5:09:17because they were so controversial with

5:09:20Ross Road. And so

5:09:22um I just wouldn't want people to start

5:09:26hating this because it's so needed. Um

5:09:29and so if there is any sort of phasing

5:09:31and prioritization of like uh the the

5:09:36starting at the epicenter and then

5:09:37moving out that maybe that's a good idea

5:09:41uh in terms of getting buy in.

5:09:46>> Thanks. So, Vice Chair G.

5:09:50>> Oh, yeah. Actually, I was going to ask

5:09:52if staff had any thoughts about the uh

5:09:55phasing

5:09:56that the public comment has mentioned.

5:10:05Uh, I think staff supports the idea of

5:10:08phasing. I think we'll give that a

5:10:11little bit more thought as we head into

5:10:13council and maybe we have some of uh we

5:10:18have additional improvements that we can

5:10:19implement via a pilot. But I do

5:10:22appreciate the strategy and thinking

5:10:24about prior efforts and how we can maybe

5:10:26not repeat some of those same mistakes.

5:10:28So appreciate that strategy.

5:10:33Okay, then I think uh vice chair G is

5:10:35that just a ghost hand now.

5:10:37>> Oh, I guess I was just going to move

5:10:39towards a motion. I don't know if anyone

5:10:40else had

5:10:41>> Please. No, wait. Sorry. Sorry. Sorry.

5:10:44There's one light here.

5:10:45>> Yeah, I I want to make sure other people

5:10:46go first.

5:10:47>> Commissioner He

5:10:49>> Thanks. Just on the on the bulb outs, I

5:10:53I um what vice chair uh G said kind of

5:10:58resonates with me because when I get um

5:11:00to those bulb outs, I I also get

5:11:02uncomfortable pulling toward the middle

5:11:05if there's a you know, car I can hear a

5:11:07car coming up behind me and you know, so

5:11:09do I have to turn and look to make sure

5:11:12as I pull in, you know, to avoid hitting

5:11:16the curb, I'm not going to run into it

5:11:18and and Maybe it's just because I grew

5:11:21up before there were bike lanes where I

5:11:23was supposed to ride down the middle of

5:11:24the road, but that that to me that just

5:11:27feels wrong. I should kind of stay out

5:11:29of the way of the cars until and so and

5:11:31I don't know that I'm going to learn

5:11:32that new trick. Um but I might try. But

5:11:35what I was going to say was um uh on

5:11:38Ross Road just just south of Richardson

5:11:41Court there are a couple of these

5:11:43bullouts and the it's it's an island

5:11:46really because there's a gap between

5:11:49this curb structure that extends into

5:11:51the road and the the rolled curb where

5:11:55the sidewalk is. And so um often I'm

5:11:58more comfortable riding between the

5:12:02island and the sidewalk. um you know

5:12:05it's it's it's only you know two or

5:12:07three feet and and is there any reason

5:12:13it's hard you know these diagrams don't

5:12:14really show the design but is that the

5:12:17typical design that there is that gap or

5:12:19do you more normally run it all the way

5:12:21to the curb so a biker couldn't stay out

5:12:24of the middle if they wanted to

5:12:26>> um so I think the design that you're

5:12:28referring to is actually the goal of it

5:12:31is more to do with drainage but that's

5:12:33also something that we could potentially

5:12:35consider. Some people are not

5:12:36comfortable in the size of that. Like

5:12:38>> it is a little narrow. I could

5:12:40understand that, but

5:12:41>> it's not necessarily designed for a

5:12:43cyclist, but maybe it has a secondary

5:12:45effect for people who are not

5:12:47comfortable.

5:12:47>> Yeah. And I think it could be wider,

5:12:50right? I mean, really, it's it's that

5:12:52furniture in the middle of the street. I

5:12:53mean, you don't want to make it so wide

5:12:54that a car thinks, "Oh, I could use that

5:12:56as a turn lane, right?" But but I think,

5:12:59you know, 3, four feet. Um, anyway,

5:13:02something to think about. Thanks for the

5:13:03clarification. So, normally though, the

5:13:05bulb belts you were envisioning run all

5:13:08the way to the sidewalk. So, there's no

5:13:10gap.

5:13:11>> Uh, yes.

5:13:12>> Okay.

5:13:14>> All right. That's it for lights here.

5:13:16Vice Chair G, if you'd like to make a

5:13:17motion.

5:13:18>> So, what's actually really funny is I

5:13:20was going to mention the same thing as

5:13:21Commissioner Hecman because there is

5:13:23another island over on Margarita on Park

5:13:25that I also use the little drainage

5:13:27ditch for. Um, so,

5:13:31um, actually originally I was going to

5:13:33say that I wasn't going to be supportive

5:13:35of the the curb extensions and they

5:13:38separate those out of separate motions,

5:13:40but if there's interest from the

5:13:42commission, I would be willing to

5:13:44incorporate that as a potential part for

5:13:47um, council council to look into. So,

5:13:49I'd make something like, I support the

5:13:51staff recommendation of the six items

5:13:54listed in the staff report on packet

5:13:57page 197 with potentially looking into

5:14:02one uh having a little path or drainage

5:14:06ditch in between the the bulbout portion

5:14:09and the sidewalk that potentially could

5:14:11have bikers. and two to look into having

5:14:14a phased approach focusing on the

5:14:18epicenter at Brian and Lincoln and the

5:14:21pilot left turn at Embaradero and

5:14:24Bryant.

5:14:33>> I kind of lost thread of it.

5:14:36>> So we lost the thread of it over here.

5:14:39Could you please hurt?

5:14:40>> Oh,

5:14:41>> yeah. So, so, okay. So, I I would move

5:14:44the staff recommendation for the six

5:14:46items listed on packet page 21 197, the

5:14:49traffic circle at Brian and Lincoln,

5:14:50etc. The curb extensions at Bryant

5:14:53Channing, Bryant Homer,

5:14:56the the high visibility crosswalk, the

5:14:58Bryant pavement, Bryant Boulevard

5:15:00pavement, the short-term parking zone,

5:15:02and the pilot left turn restriction. So,

5:15:04that's kind of like the staff

5:15:05recommendation. And then in addition to

5:15:07that, I'd like to explore having a like

5:15:12drainage ditch or little gap between the

5:15:16bulbout portion and the sidewalk. And

5:15:18then also I would like to uh have staff

5:15:22look into a phased approach focusing on

5:15:25the epicenter at Bryant and uh Lincoln

5:15:30and then also the left turn and phasing

5:15:32outwards.

5:15:37Yeah. Um, yeah, sure. I will second

5:15:39that.

5:15:41>> Okay, great. Any further discussion?

5:15:46>> Staff clear on the motion.

5:15:49>> Yes. Thank you.

5:15:50>> All right, let's vote.

5:15:53>> Commissioner Templeton,

5:15:55>> yes.

5:15:55>> Uh, Commissioner James,

5:15:57>> yes.

5:15:57>> Commissioner Hecman,

5:15:59>> yes.

5:16:00>> Vice Chair G,

5:16:01>> yes.

5:16:02>> Chair Chang,

5:16:03>> yes. Motion carries 5-0.

5:16:05>> Thank you. All right.

5:16:09>> Yeah, very exciting. So many safety

5:16:11improvements.

5:16:13>> Oh, 501. Not Commissioner Absent.

5:16:17>> Thank you, Commissioner Huckman. All

5:16:18right. So, now we're on to commissioner

5:16:21questions, comments, announcements, or

5:16:23future meetings and agendas. And there's

5:16:26one thing that I'd like to quickly talk

5:16:27about, which is that Commissioner Aken

5:16:29had asked for a backup. Uh, so I think

5:16:32let's just address that right now.

5:16:36Um,

5:16:38>> want to say thank you to the people who

5:16:39stuck it out this long before they head

5:16:41out.

5:16:41>> Yes. Thank you all. We're very excited

5:16:44for your neighborhood, too.

5:16:48Um,

5:16:50so

5:16:51>> I'm I'm wondering if this would be

5:16:53better

5:16:55um handled online where everybody can

5:16:58look at their calendars and and perhaps

5:17:01uh tell Ms. Arner, you know, what what

5:17:06um Mondays in October we'd be available.

5:17:13>> Okay, let's look at our calendars.

5:17:15That's the suggestion. And let's do

5:17:16that.

5:17:18>> Great. Anything else?

5:17:20Commissioner comments, questions. Uh,

5:17:23yeah.

5:17:25Announcements, future meetings.

5:17:28All right. Now, now it's time for

5:17:31virtual public comment on items that are

5:17:34not on the agenda. Mr. Trava, do we have

5:17:36any raised hands?

5:17:38>> Uh, to the chair, there are no raised

5:17:39hands. If there's any members of the

5:17:40public that like to speak, uh, you may

5:17:42raise your hand.

5:17:44>> I see none. Fantastic. So this meeting

5:17:47is adjourned.