- Called to order with an invocation and pledge; the agenda and the consent agenda (including uncollectible water and sewer account write-offs, described as consistent with past years) were approved without opposition. The Onslow Water and Sewer Authority is a separate body from the City; its meeting is posted on the City's channel.
- Camp Davis wastewater force main expansion and emergency connection: the board approved an amended project ordinance and authorized the CEO to sign two construction contracts with the apparent low bidder, Busco Contractors, Inc.: $9,988,100 for about 55,237 linear feet of 12 to 20 inch force main (capacity about 1.8 MGD, with an emergency connection to the Holly Ridge plant) and $7,881,500 for two new pump stations. Also covered were $1,689,600 for design-engineer construction administration and about $75,000 for easements. There were 21 bidders (13 on the pipeline, 8 on the pump stations) and the bids ran about $2 million under estimate on wastewater. A director who came from the contracting world said the low bid looked too cheap and voted yes anyway; staff said the engineers vetted it closely and the contractor is bonded. See Camp Davis Wastewater Force Main Expansion.
- A federal-advocacy firm presented its services (earmark requests, Army Corps environmental infrastructure funding, defense-authorization funding for communities near Camp Lejeune, and WIFIA financing, which North Carolina does not yet fully access). The board approved a one-year agreement, subject to attorney review, funded from the administrative budget; a director said the cost was in the range of $72,000 a year. A member disclosed that their town signed with the same firm earlier that day. See ONWASA Federal Advocacy Agreement.
- Surplus property on Viking Place, next to a former wastewater treatment plant where only a pump station operates: the board declared it surplus and authorized the upset bid process on an offer of $5,000 from the adjacent owner, with survey costs covered. The acreage was stated inconsistently in the captions.
- Interlocal agreement with Onslow County for fleet repair and maintenance of about 50 diesel vehicles and 100 pieces of heavy equipment, approved. Costs are close to the current vendor (examples: $380 versus $560 for a service-truck service, $360 versus $480 for a backhoe), the main benefit is faster turnaround, either party can cancel on 30 days' notice, it is not exclusive and no employees are displaced. See ONWASA Fleet Maintenance Interlocal Agreement.
- Four project ordinances approved, all in the capital improvement plan: Irving Town wastewater pump station upgrade (continuing design), initial study for a Northeast wastewater treatment plant on the Parkertown property serving the Swansboro and Highway 24 corridor, a study to relocate North Topsail pump station 49 (its current site is environmentally unsound and unsafe for crews, and the pipe hangs from the bridge), and a wastewater system master plan with a hydraulic model the authority will own. See ONWASA Wastewater Project Ordinances.
- No public comment; the planned closed session did not materialize and moves to October.
- CEO report: signatures are being gathered on a letter to the base ahead of a regional planning group meeting; an EDA grant for a Holly Ridge water tower was not awarded and staff will seek feedback; a state abandoned-landfill review near Camp Davis is not expected to affect authority wells; new drought areas appeared in the county; the authority is coordinating with the City of Jacksonville on utility service for areas leaving the City's extraterritorial jurisdiction; staff described cybersecurity controls and said customers would be notified of any water-quality issue; crews fixed about 30 leaks in a week with about 50 on the list.
- Next meeting is October 22, to consider debt placement for capital projects ahead of Local Government Commission review in November.
Agenda
Agenda not yet posted.
Sources
- City calendar: https://www.jacksonvillenc.gov/Calendar.aspx?view=list&month=9&year=2026
- Video: https://www.youtube.com/watch?v=doKjBNqLD5U (City of Jacksonville YouTube channel)
Video
Transcript
*These are auto-generated captions; names and numbers may be misheard.
Transcript
00:24director's meeting for Thursday,
00:26September 17 to order. And I'm going to
00:30ask everyone to stand as Pastor Brian
00:33Young, uh, pastor of Love, Grace, and
00:35Mercy Church, provides the imitation and
00:38remain standing for the pledge, pledge
00:40of allegiance.
00:44Amen. Father, we just thank you tonight,
00:46Lord God. We are eternally grateful for
00:48your grace and your mercy, Lord, upon
00:50us, God. We thank you God tonight that
00:52you God your spirit is here God lead
00:55these men God and these women Lord in
00:57making the right decisions God for this
00:59community. Thank you oh Lord for a
01:01spirit of cooperation father God that we
01:04will come to the best decisions God to
01:07God just further God Anwasa's goals and
01:10their vision Lord God to be what they
01:13need to be in this community father we
01:15thank you for leading and guiding us
01:17tonight in Jesus name. Amen.
01:19>> Amen. Amen.
01:22>> Face the flag. I pledge allegiance to
01:25the flag of the United States of America
01:28and to the republic for which it stands,
01:31one nation under God, indivisible, with
01:34liberty and justice for all.
01:37>> Thank you.
01:42We ask all those present to turn their
01:45cell phones off or to vibrate.
01:49Individuals making presentations, public
01:52comments are asked to adjust the
01:53microphones as necessary and speak
01:55directly into the microphone.
01:58This meeting is being recorded.
02:01All right. I need a motion to approve
02:04the agenda.
02:05>> So moved.
02:06>> Second.
02:07>> I have a motion and a second. All in
02:09favor say I.
02:10>> I.
02:11>> Any opposed? By the same sign.
02:14The agenda is approved and then we'll
02:17consider adoption of the consent agenda.
02:23>> I have a motion and a second. Anybody
02:25need anything removed?
02:28Royce, not the remove, but could I ask
02:29one question about one item just real
02:31quick for clarification in regards to
02:33the uncollectible water and sewer
02:34account write offs? I was just wondering
02:36if the number there was in line with
02:38historical averages or if that was
02:40higher or lower from what we've seen in
02:42past years. It is consistent.
02:45>> Thank Thank you. That's the only thing I
02:47was wondering how much.
02:49>> Yeah, I think what I remember seeing in
02:52the past, we're
02:54in pretty good shape there.
02:57>> Um, all right. So, we have a motion and
02:59a second. Can we approve the consent
03:01agenda? All in favor say I.
03:04>> Any opposed?
03:06All right. The consent agenda is passed
03:09and we move into
03:11business and the Camp Davis Wastewater
03:14Force main expansion and emergency
03:17connection. Mr. Lore,
03:24>> good evening directors.
03:28This item consists of two single prime
03:31construction contracts for the Camp
03:33Davis wastewater force main expansion
03:36and emergency connection project along
03:39with construction administration and
03:41observation services and funding for
03:44necessary easement acquisition.
03:48The project includes the following major
03:51components for contract one. It's the
03:54wastewater force main transmission lines
03:57construction, testing and startup
04:01of the wastewater force main
04:02transmission lines from the Camp Davis
04:04Industrial Park. [clears throat]
04:07South on Highway 50, north on Highway
04:1117, then east on Highway 172 to 210, and
04:16then to the Southeast Regional
04:19Wastewater Treatment Facility.
04:22This project also includes an emergency
04:24pipeline connection from the new force
04:26man that'll be constructed on 17 to the
04:30existing Holly Ridge wastewater
04:32treatment plant.
04:34This project includes the installation
04:36of approximately 55,237
04:40linear feet of 12 to 20 in C900
04:46PVC and ductal iron pipe [clears throat]
04:49and associated pertinances via open cut
04:53and directional drill.
04:55The ultimate average daily flow capacity
04:58of this expansion is approximately 1.8 8
05:01MGD.
05:03The apparent low bidder was uh Busco
05:07Contractors, Inc. at $9,988,100.
05:16The next item is contract two, which is
05:18the wastewater pump stations for this
05:21project.
05:23Uh construction, testing, and startup of
05:25two new wastewater pump stations. one
05:28located in the Camp Davis Industrial
05:30Park in the town of Holly Ridge and the
05:33second pump station located off Highway
05:36172 in the Oyster Landing subdivision
05:39area. Again, the apparent low bidder was
05:43Busco Contractors, Inc. at 7,881,500.
05:52Uh this item also includes construction
05:54administration and observation services
05:57by the design engineer of record which
05:59is high infrastructure engineering at
06:031,689,600
06:07and necessary easement acquisition costs
06:10of approximately $75,000.
06:14Uh I will make note that we had a
06:16tremendous uh bid activity for these pro
06:20for this project. We had uh 21 total
06:22biders. Wow.
06:23>> For the pipeline work, we had 13.
06:27And for the pump stations, eight. So
06:29that's that's a pretty good turnout. And
06:32the cost of the pump stations was much
06:35less than what our estimate was.
06:39>> I'm sure you've vetted them, but have
06:41you ever done any business with this
06:42company?
06:43>> No.
06:44>> So we really just hadn't done anything.
06:47What were they out of? Um,
06:51Angier,
06:55>> do do we have any
06:56>> the city?
06:57>> I'm sorry.
06:58>> I was just gonna say, do we have any
06:59concerns at all based on I mean, looking
07:00at the numbers, you guys sent them over
07:01to us and we looked at them and they
07:03were significantly lower on wastewater
07:05by about 2 million and about a million
07:06on the water. So,
07:07>> right,
07:08>> no real concerns. I mean, you're saying
07:10they were vetted by the vetted by the
07:12engineers, but I mean there that's a lot
07:15of competition. That's a
07:17>> it is a lot of competition. Uh if you
07:19look at the range of bids,
07:23it was it's quite a range from the low
07:25bid to the high bid. Um I will say that
07:30uh they were vetted pretty closely. Uh I
07:33had that conversation with uh the
07:36engineer before they started their
07:39review since we had not worked with them
07:42uh here at ona.
07:44And uh I'm comfortable with their
07:46recommendation to award the contracts to
07:50Busco.
07:51>> Maybe they're hungrier than everybody
07:53else.
07:54>> Well, that amount of
07:55>> Well, given the overall bid numbers, I
07:58think uh several people are
08:00>> getting hungrier than they than they
08:02were.
08:06Uh the action requested uh is to
08:08consider a motion to approve the amended
08:10project ordinance and authorize the
08:14chief executive officer to execute the
08:16construction contracts
08:18and any additional documents as required
08:20in connection with this action.
08:22>> Motion second.
08:25>> I have a motion and a second. Is there
08:27any other
08:27>> Yeah, I have uh as y'all know I came
08:31from the contracting world. I have a
08:33concern. I mean, I'm I'm not going to
08:35vote against it, but uh they're too
08:37cheap. They've got a problem. They don't
08:39realize it. It's hard to find your own
08:41problem when you when you bid these
08:42things. Uh I would have preferred to
08:45seen them perhaps drop out. Uh just
08:49because they've got a $2 million
08:52problem. That number for the pipeline
08:55looks to be in line somewhere in the 12
08:57to 13 range. They're they're down there,
09:00you know, 11 to to 12 range. They're
09:03down in close to 10. So I I think
09:06they've [clears throat] got a problem,
09:06but they just don't realize it. But u I
09:09don't know that we can do much. I mean,
09:10they are responsive. They've told
09:12they've told Highfield that, hey, we
09:14we've gone back through our our our
09:16work, and we don't see a problem. So,
09:19but uh I'm still going to vote for it. I
09:21just I just have a concern and I just
09:24didn't want to go without
09:25[clears throat] saying that we that I
09:26had a concern. Sir,
09:28>> do we uh do we investigate their
09:31financial position so that we know if
09:35they fail to perform that we have some
09:38>> recourse?
09:39>> We check references.
09:41>> They're bonded.
09:43>> They're bonded too, right?
09:45[clears throat]
09:45>> The bonding company actually does the
09:47the due diligence on their fi company's
09:50finances. So,
09:53>> but there is one little thing that they
09:54don't do. Um, you know, it takes money
09:57to to to mobilize and you know,
10:01sometimes when we did core of engineer
10:03projects, we had to show a balance uh
10:06statement that we had money in the bank
10:07that we could we could go the first
10:09month of of construction. We could
10:11[clears throat] mobilize the first month
10:13before we ever started getting paid for
10:15our work because you got to put the work
10:17in before you get start getting paid.
10:19So, uh, but hey.
10:22>> Okay.
10:22>> Anyway, I've said my my my two cents.
10:26[laughter]
10:26>> Good concern.
10:27>> Yeah. Yeah.
10:28>> Absolutely. If I may, Bob, I mean, those
10:30are the same questions I sent Frankie
10:31last Friday when I first read over the
10:33agenda, thinking the same thing about
10:34past performance and responsiveness and
10:36understanding the true requirement that
10:38that we're asking them to fulfill. Uh,
10:41and so forth. Uh the the trouble is when
10:44you when you when you get notified that
10:46uh by your the engineering company or
10:48architect that you're low, you you can
10:50go back and through your your bid as
10:52best you can, but but if you've got a
10:54blind spot going in, that blind spot's
10:57generally unless there's a major mistake
11:00that just jumps out of a math mistake,
11:02you're not going to find it. So, but
11:04hey, we'll we'll cross our fingers and
11:06and and hope hope for the best. So,
11:09>> I agree.
11:11>> All right. Any other discussion?
11:14Seeing none, all in favor say I.
11:16>> I.
11:16>> Any opposed?
11:18All right.
11:22Motion pack carries. And uh you're
11:25all right. Miss And
11:28senior associate at the Ferguson Group
11:31has a presentation for us. Welcome.
11:33>> Hello. I'm Andrean. Thanks for um having
11:37me here tonight um to speak. I know um
11:41I've met Chairman Bennett before and
11:43worked with uh Mayor Grant um and many
11:48of you I'm just now meeting but I'm very
11:51happy to be here. Um
12:00I am with uh the Ferguson Group. Um we
12:03do federal advocacy for local
12:07governments, municipalities,
12:09um special districts, authorities, all
12:12of those sorts of things. Um and have
12:14been doing so for 40 years. um
12:18specializing in getting appropriations,
12:22finding funding, implementing that
12:24funding, keeping
12:26uh keeping fees and things or things
12:31problems from popping up u that could
12:33cost you money. I say that uh my job is
12:37twofold. It's to find you money and to
12:39save you money. And I'll show you uh
12:43some specific examples of those things.
12:47uh here in a minute. Uh but I'll keep
12:50this pretty short so that you can ask
12:52questions and we can have a discussion
12:55if you would like on these specifics. Um
12:59I work with um Jeremiah who is also
13:04specializes in the uh water issues and
13:08infrastructure funding, military um
13:13funding which you are uniquely
13:15positioned to based on your position
13:17next to camp lune.
13:20Um we do kind of a fivestep
13:24uh process for identifying. So the first
13:27is what is what are your problems? What
13:30do you need? What are your needs? What
13:32are you worried about? Um and then look
13:35for opportunities. Um trying to find fit
13:40the puzzle pieces together of how we can
13:44make that work at the federal level
13:45because it's not as government's not
13:48always so easy and straightforward. Uh,
13:51and there's if it was then everybody
13:54would go, well, we'll just go to the
13:56water money pot. Well, there's several
13:58different water money pots at the
14:00federal level and they're spread out in
14:02different areas and you're eligible
14:04based on a lot of different criteria.
14:07So, it's finding uh finding those
14:10opportunities
14:12uh and then strategically uh planning
14:16your projects and putting it on the
14:18radar of your uh federal elected
14:21officials. Um working to submit projects
14:27for earmark appropriations.
14:29um working to get authorizations in
14:32bills like WERA to be able to fund
14:35projects a couple years out. Uh and then
14:38organizing that support with the
14:40delegation uh and making sure that uh
14:43your federal elected officials are
14:46listening um listening to you
14:50specifically.
14:52uh our expertise and my personal
14:55expertise aligns with uh working with
14:59water in North Carolina. I work uh this
15:01is all publicly available information uh
15:04with Capefir public utilities, Fateville
15:06Public Works uh and have had some really
15:09great success um with with those
15:12organizations finding funding for those.
15:15So, uh, those don't you're in a
15:18different area. That's not they are not
15:20in competition with you for those money
15:22because we're not going to the same
15:23places. We're not going to the same
15:25representatives for that. Uh, but it
15:27does give me a lot of experience with
15:29these issues because those issues are
15:32the same across the board. Fyville
15:34Public Works is located next to Fort
15:36Bragg, uh, similar to your proximity to
15:40Camp Leune. So, I have a lot of work
15:43with being able to talk with uh the
15:47Pentagon and the military bases and
15:50commanders and have a good working
15:53relationship and establish good working
15:55relationships
15:57um with those because that's you provide
16:00a very good service here and your
16:03proximity to Camp Lune is uh they the
16:08military wants to help and they want to
16:10make things easy for you. Um it's just
16:14explaining how those how your priorities
16:16and their priorities align, how you can
16:18make their lives easier um doing what
16:21you do. We work with policy development.
16:24So if you have an issue, um we will
16:28create a policy and try to work and get
16:30that policy passed. Um environmental
16:34infrastructure through the core. I'll
16:35give you a specific example of this in
16:38just a second. Um, but that's a really
16:42good opportunity for uh getting core
16:45money, core funding for projects. I have
16:48one pending right now with uh Capefar um
16:52for some of their uh long-term projects.
16:56We uh literally TFG wrote the WIFIA
17:00program. Our CEO, Roger Gwyn, wrote uh
17:04the Water Infrastructure Financing and
17:06Innovation Act, uh which pro provides
17:09long-term financing. Currently, North
17:12Carolina is the only state that does not
17:15have the same access to WIFIA as other
17:18states. However, we are actively working
17:21right now with the state to change uh to
17:25change that and remove those limitations
17:27because you are currently at a
17:29disadvantage not being able to take
17:31advantage of WIFIA which is um low fi
17:36low interest rate financing for
17:38long-term really big projects uh really
17:42big money projects um you know hundred
17:44million dollar uh type of projects uh
17:48creative engagement with the NDAA,
17:51National Defense Authorization Act. Um,
17:54that is something a lot of people don't
17:57a lot of other groups like you do not
17:58have access to um because they're not
18:02next to a military base. The uh NDAA has
18:05to be passed every year and uh Jeremiah
18:08specifically right now uh is working
18:10with a transit organization um in
18:14Virginia
18:15um and getting actually getting funding
18:18through the NDAA um for projects uh next
18:23to military bases. Uh we have really
18:26good agency and committee relationships
18:30uh in Washington DC. um so that when
18:34problems arise we can get people on the
18:36phone. Um we can get you in the room and
18:40have meetings. Um I can call I have
18:45happy hours and dinners all the time
18:47with the staff of um the your delegation
18:52and the committees to one hear about
18:55what's going on on the ground and then
18:57also be able to tell them your position
19:02influence policy and tell them what
19:05we're our concerns are because what our
19:08concerns are are also your congressmen
19:10and senators concerns. concerns too
19:12because you are voting constituents. Uh
19:16they really do care. I promise. Uh and
19:19then through annual appropriations. This
19:21is the really big one. Uh and this is
19:24where uh you can get a lot of projects
19:28funding if you are just submitting these
19:30projects. Uh I work every year to submit
19:33a pile of earmark requests um to a v to
19:38everybody but in your state here to
19:40senators and to u mur congressman Murphy
19:43in this district here. Um
19:46appropriations got a bad rep pork barrel
19:49spending way back in the day and that's
19:51why in 2012 they stopped doing earmarks
19:54um and for good reasons. They brought
19:56them back in 2023, but with a whole
19:59different set of restrictions,
20:02requirements. Uh there's no more just
20:05sending some money through and or
20:08sending an idea through and just getting
20:09the money there. Each earmark request is
20:12about a 75page packet uh that I fill
20:15out. Um it's not exceptionally
20:18complicated to do. It's just a very
20:20tedious process. You're gathering
20:22letters. They have a lot of follow-up
20:24requests. uh and so getting the
20:27knowledge of how to submit and get those
20:30projects funding behind the scenes. I
20:32work with uh the congressional offices
20:36ahead of time. So when they're getting
20:38that appropriation request,
20:39[clears throat] that's not a surprise. I
20:41work to long-term plan out with them how
20:45we can get these funded and what they're
20:47looking for each year. Um, Congressman
20:50Murphy
20:53from year to year changes, you know,
20:54what types of projects they're looking
20:56to fund. So, we then pick uh based off
20:59your priorities and your funding needs,
21:01what is going to align that year and
21:03then knowing in the next year they might
21:05be looking at a different focus. And so,
21:08it's strategizing with those offices
21:11uh to make it work for them, make their
21:14lives easier, and get your projects uh
21:17funded.
21:19I have two examples. Like I said, I work
21:22with Fagville Public Works uh and Kate
21:25Fear. Uh Kate Fear I have just worked
21:27with in the past year. Um but right now
21:31uh if they ever pass the
21:34uh appropriate budget bills this year.
21:36They have just voted to ex a continuing
21:39resolution to December. So these are on
21:41hold. This is business as usual uh in DC
21:45these days. Eventually, it gets done,
21:47but uh not ever on time. Um but they
21:51have a $1.83 million uh request right
21:54now uh for um some of their projects.
21:58This is one where we went uh a few years
22:02before and got the authorization in
22:04WERA. Um WERA is Water Resources
22:07Development Act. It is a two-year
22:10authorization. And in fact, the House um
22:12just voted on this version today, this
22:16morning, last night. Um and it's getting
22:20that wording in the bill to be able to
22:22then go after that money in
22:24environmental infrastructure
22:26[clears throat] appropriation bills
22:27later. Uh Fagetville Public Works, uh we
22:31have done a lot of work with I've worked
22:33with them for a couple years now. uh and
22:35they're right now currently uh drawing
22:37down the a $4.5 million request uh that
22:42they received from uh Senator Tillis. Uh
22:46and that was the work I did to uh get
22:50that request submitted and then lobby
22:53and advocate get that request approved.
22:56Um those it's really easy. I never worry
23:01about when people ask me, you know,
23:046,000 a month or 10, that's a lot of
23:06money. That is a lot. But I never worry
23:08about uh ever proving a return on
23:10investment. I've never had that issue.
23:15Um in my work pays for itself tfold
23:20oftentimes. I have many of my clients
23:23have a 30 to1 return on investment. uh
23:25it takes a little while to build that
23:28up, but you know, you can see that
23:30compounds on itself over time because
23:33the longer I'm advocating and working,
23:36the more chance you have of getting that
23:39money. Um the other thing, uh I
23:42actually, it's not water related, but I
23:45work with Holden Beach. the saving you
23:48money part is harder to quantify because
23:51it's easy to go look and see 4.5 million
23:55uh for an infrastructure project that
23:57you get and that's great but the saving
24:00money is where you it's hard to put a
24:03number sometimes on that but uh Holden
24:06Beach uh this past week we resolved an
24:09issue uh with they have a dred they were
24:12dredging they're doing a dredge they use
24:14the core army corps of engineers uh
24:17disposal site for this. Uh out of
24:20nowhere, they had been paying about $5 a
24:23cubic yard for disposal. Out of nowhere,
24:26the core tells them, "Yes, you can use
24:28the site as usual. That'll be $26 a
24:31cubic yard." Uh that was not budgeted
24:34for. [snorts] Uh Holden Beach
24:36[clears throat] is happy to pay, but a
24:38little planning in advance. Uh, I've
24:41spent the last three months with the
24:44Wilmington district, then followed by
24:47Core HQ, uh, dealing with this and
24:50arguing about that one, their
24:53calculation was wrong. Uh, it was just
24:56wrong. There was no way, uh, that that
24:58was true. Um, and it went back and
25:02forth, back and forth. We got an answer
25:04Thursday. Uh, that number is $10. So
25:08that's a savings of $16
25:11uh dollars air ins with 30,000 cubic
25:14yards of material. Uh that's $470,000
25:20saved. Uh just because we have the
25:23knowhow and the relationships with the
25:25Pentagon and Wilmington uh to be able to
25:28say no, that calculation is incorrect.
25:32Um, but that's not necessarily money
25:33back in their pocket, but that was money
25:35they were going to have to pay because
25:36they were going to have to do the
25:37dredge. Um, not specifically water
25:40authority related, but those are the
25:42types of things uh that I do to save
25:45money and keep you from having to spend
25:48money you didn't want to or didn't plan
25:49for. Um,
25:55general overview of how we work with
25:57communications. We have a lot of special
26:00reports of like for example Wera um we
26:05do a special report and tailor it to
26:07you. So how does WRA affect you? Uh and
26:11we send those reports out. We have
26:13meetings with
26:15um anybody you need us to have meetings
26:18with within and we establish how often
26:20you want those. I have some that are
26:22people are like ah every month is fine,
26:25every two weeks uh is fine. Uh some of
26:28my clients, it's no official meetings.
26:30They call me
26:32when they have issues and I keep them
26:34updated when I see things. Uh it's just
26:37how you want that to to work. Uh and
26:40then
26:42um giving you those reports. I think the
26:44day I met Frankie, I was actually
26:46editing a data center um memo report. I
26:51gave them the unedited. I hope there
26:53weren't typos in that. Uh [laughter]
26:55but [snorts] uh we do those and say, you
26:58know, how does that affect you? Um
27:00they're working right now on a lot of
27:03data center, energy, water types of
27:06things in DC right now. Uh nobody's in
27:08agreement. That's a very wishy-washy
27:10area right now where nobody really knows
27:13yet their position. Uh, and that's a
27:16really good area to be able to make uh,
27:20you know, help shape their opinion uh,
27:22and tell them how it would affect you.
27:26Those are really, really good
27:27opportunities.
27:30Uh, these are examples of our uh, like
27:33weekly reports. We send out the
27:35legislative update tells you what's
27:38going on, any bills that are reg uh
27:40would affect you or if interest you as
27:42well as grants funding which is all of
27:45the different grants uh that come out
27:47every week that you might be eligible
27:50for. I kind of call it a shopping list
27:53um to go after
27:57special reports. For example, we've got
27:59a midterm election coming up that it
28:01doesn't matter if the makeup of the
28:04House stays the same, majority stay the
28:06same. The dynamics in every Congress are
28:09different. Um, and so we look at all of
28:12those factors and then tell you what
28:14that is go what to look for. The
28:17priorities change with every
28:19administration. Uh and so we want to
28:22make sure that we're pushing the
28:24priorities that we have that are going
28:27to get the attention in that specific
28:29Congress and in that administration.
28:33That was a pretty quick overview. I
28:36wanted to keep it a little bit short to
28:38uh answer any questions you may have.
28:43>> Yes, sir.
28:44>> Ju just full disclosure, I actually
28:46signed a contract with that firm today
28:48for the town. Um, and it was
28:50[clears throat] because the work that
28:51she did with Topsil Island Shoreline
28:53Protection Group in the interaction that
28:55we had with an um that I mean full
28:58disclosure I pushed um because I felt
29:01that particularly in DC and probably in
29:04the state although the county is working
29:06on that now is we really don't have
29:09anybody looking out for our stuff and
29:11you know not that we think you're cheap
29:14but this is short money to be able to do
29:16that particularly the way the contract
29:17is structured. Um, but also Anna talked
29:20about earmarks coming back and financing
29:23and and a lot of this stuff is knowing
29:24what's out there. So, I just wanted full
29:26disclosure. We've already I literally
29:28signed the contract this morning. So, we
29:30had approved last board meeting. Um, so
29:33full disclosure.
29:35>> Yes, sir.
29:36>> How big a company are you? I mean, how
29:38many how much staff do you have? Because
29:40you got a lot of things going. It's
29:41obvious.
29:42>> Yes. Uh we have uh I think it's in and
29:4730 I believe
29:48>> how many
29:49>> 30 uh I think it's kind of a a small a
29:53small but very impactful firm. Our uh CE
29:56or our president Mark Limba uh was a
30:00secretary in the Bush administration
30:02worked for the interior. Um, and it's
30:06one of those we are small, but the
30:08connections and relationships we have go
30:12a really long way. And something else I
30:16was sitting here thinking, u, you know,
30:18there's only so much money in the pots
30:20and in this region, we're all competing
30:24for the same amount of money. How do
30:25y'all handle that part of it?
30:28>> So, I actually did a lot looking at
30:32where you are. Uh there are act like
30:35there are laws that would prohibit me
30:38from uh actually you know conflict of
30:40interest wise um and I wouldn't take
30:44somebody who I was going to be in
30:46conflict with any of my other clients.
30:48So my concern was that I worked with
30:49Capefir and Fagatville, but that money
30:52uh and they have different in fact
30:54Fagatville uh Congressman Hudson does
30:56not earmark. They are at a disadvantage.
30:59So we have to go differently.
31:01Fortunately, um Congressman Dr. Murphy
31:05does earmark. Um and so we're not
31:07chasing the same the same money there.
31:11The uh congressmen get each year 15.
31:15they pick of all their projects that
31:17they get 15 and then they submit those
31:19to the committee. Um, and so you're kind
31:22of competing against other interests in
31:24your area.
31:25>> Well, my town's been fortunate with
31:27Congressman Murphy to get some money
31:28already.
31:30>> But, uh, that was just I was just
31:32curious about that because, you know,
31:34when there's only so much money there,
31:36everybody wants it
31:38>> and uh,
31:38>> yes. And it's a shame, you know, you
31:41can't the Congress, we have to have
31:43somebody advocate for us because
31:45congressman won't just do specifically
31:47for us. I mean, I, you know,
31:49>> uh,
31:51you one fortunate, um, Senator Bud has
31:55not previously earmarked. He would only
31:57do military defense related earmarks.
32:00That is changing. I actually helped his
32:02office this past year uh, set up how
32:04they do the portal uh, based on my work
32:07with the other offices.
32:09um telling them which offices had good
32:11ways of doing it versus really
32:13cumbersome ways. Uh but Congress or
32:16Senator Bud
32:18pays even he will do more than just the
32:21defense has works really well and does a
32:24lot uh with the defense communities. Uh
32:27and so you're very uniquely positioned
32:29with Senator Bud. Additionally, uh
32:33Senator Tillis earmarked. He's he
32:35obviously will not be there. Um but we
32:39my conversation so far with the part uh
32:43both potential new senators is that they
32:46do intend on earmarking and so actually
32:49you're growing your chances of being
32:51able to get money uh with this new
32:54Congress no matter how it shakes out.
32:57>> Director Herbert may have two questions.
32:59One, where are you physically located
33:01then? Just thinking for accessibility
33:02and so forth.
33:04>> So uh our firm is in DC. Okay.
33:07>> Uh we are on Pennsylvania Avenue. Um I
33:10am have just actually relocated to this
33:13area. Uh I kind I was in I'm from
33:16Georgia. I lived in Mobile, Alabama. Um
33:19I spend the bulk of like the first half
33:21the year in DC every week. Uh but have
33:25worked just out of how it shook out the
33:28clients I have in this area in North
33:30Carolina. Just very much liked uh and
33:33had I said, "Well, I like it here. Why
33:35don't I just live here? I'm here also
33:38>> and it's a closer uh to DC. So
33:41>> my my other question is c can you
33:43quantify then what your I guess for lack
33:45of better word your success rate is with
33:47water water authority projects i.e.
33:50annually you're submitting 12 projects
33:52for some type of support uh and eight
33:55are approved nine are approved or
33:57something along those lines.
33:59So that
34:00>> and when I say approve that could be any
34:02level of support not the you know the if
34:04they're asking for x amount of dollars
34:05or getting a portion of that or
34:06something along those lines.
34:08I wouldn't know how to do that. I could
34:11give you a list of, you know, this year
34:14each earmark that I received uh and the
34:17year before and that would span across,
34:19you know, from water authorities and to
34:21towns, municipalities. Um
34:25the I wouldn't just condense it down to
34:28just the appropriations request. Those
34:29are kind of the big flashy ones and
34:32those are the ones everybody's going
34:34after [clears throat] more competitive.
34:36However, there are other harder kind of
34:40to not as easy accessible money pots
34:44like the uh environmental in
34:46infrastructure uh pot of money with the
34:48core of engineers. Um that's there's
34:52that extra step and so it's not just
34:54easy for everybody to go. So, we want to
34:56think long term um of being able to set
35:00up projects to go after those pots or
35:04going with the funding you can get out
35:07of things like the NDAA
35:09um for, you know, defense communities.
35:13Um, and so spreading out where you're
35:16asking the money, looking at your
35:18project strategically from a one year,
35:20three year, 5year plan of what you want
35:24and then going after gradually uh, and
35:27spreading out where we're looking for
35:29that money and creating opportunities,
35:32too. For example, WIFIA, that would be
35:34an example of we built all of our water
35:38and sewer way back in the 40s, 30s. I've
35:41heard towns with older and it's really
35:43frightening. But around the time in 2014
35:46where this was created, the towns were
35:50going bankrupt with uh having to
35:53overhaul uh their water infrastructure.
35:56And that was an example of where we
35:59advocated the need to Congress uh and to
36:03DC to actually create WIFIA, to make
36:07that law, to create that pot of money uh
36:10to be able to help towns uh and local
36:13governments fund those those massive uh
36:16projects that were all coming due at the
36:18same time.
36:20>> If I can just two context things real
36:23quick. when we were we've been trying to
36:25the town's been trying to do this Cobra
36:27stuff for 25 years and [clears throat]
36:29when I did some research on it I found
36:32out that the the bills that are
36:34introduced in Congress it's about a 4%
36:36chance of it even getting to a vote
36:38[snorts] but the other reason and to
36:40follow up on your point which is a good
36:41point is we don't even know what's out
36:43there that that's what we faced is what
36:46pots are to your point what pots are out
36:48there what do we even ask for you know I
36:50couldn't go to Murphy today and say can
36:52you ask us you know can we get money in
36:53this pot or what's and that's why we
36:56decided, you know, because the work you
36:57did with TISPC, it's like you we had a
37:00discussion about we ought to spend some
37:02money in the front end to find out if
37:03there's value in doing other things. And
37:05so it was kind of a a test run and you
37:07would you were doing this stuff for
37:08TISPC, but you will be committing your
37:10time to on WASA, correct?
37:13>> Yes.
37:13>> Okay. Sorry.
37:15Um,
37:17I don't even know how to really phrase
37:19the question really, but so when you
37:21identify things when you we retain your
37:23guys services. So, do you look at our
37:25current CIP list and kind of go from
37:28there and see where the money would go
37:29or do or do you also do we get maybe
37:34lent staff that would look at our our
37:35organization holistically and say,
37:37"Well, you guys aren't really there's
37:39other places that you could spend money
37:40that you don't have um identified on
37:42your CIP and we could perhaps go that
37:45direction."
37:45>> Yes. So, uh, when I was drafting the
37:48proposal, [clears throat] I, uh, met
37:50with Frankie, uh, and this was, I would
37:52say, a more broad strokes of just
37:54understanding
37:56what your needs, priorities, issues were
37:59right now, uh, which is what I put, you
38:02know, specifically in the proposal. Um,
38:04looking at with EPA permitting, I job is
38:08to go make EPA get an answer back to
38:11Frankie. Um, and I go into the offices
38:15uh to do that. Uh, but it's looking at
38:19you. You would tell me how you would
38:21want, but looking overall at your CIP
38:24and then I can sit and say, "All right,
38:26here's easy. Here's where we want to
38:28focus this part." Um, how do you eat an
38:32elephant? A bite at a time. There's not
38:34going to be $500 million sitting
38:36somewhere so that you can do everything.
38:39But it's strategically looking at for
38:41like Cape Fear. They're $250 million
38:45project [clears throat] we paired down
38:48to all right this year we can go after
38:50phase one. And so you're gradually doing
38:53that uh and picking the projects.
38:56There's going to be some that are going
38:58to be easier to go find with military.
39:02There's going to be some that are easier
39:03to earmark. There's going to be some
39:05that are easier to go after grants.
39:07Hopefully, uh, we're getting close and
39:09getting North Carolina to change their
39:10mind on WIFFIA. Um, it's fine in that.
39:14And I always say it's easier sometime
39:17sometimes, you know, your easiest thing
39:19to fund is not what there's just federal
39:21money sitting there for. Uh, which is a
39:23challenge. So, it's finding what you
39:26have that you need that there is easy
39:29money for. So then you you can get that
39:32funded and have that money left over in
39:34a budget to fund the thing that's harder
39:36to find federal dollars for.
39:43>> Yeah. So I don't know in my recollection
39:47I don't know that we've ever had an
39:48advocate in in DC for Anasa. I had an
39:53opportunity to to talk to an uh
39:58before and um
40:01you know she she already has has
40:04introduced us to money sources talking
40:08about we wifia
40:11um that we didn't know about to start
40:14with and um I don't know it just seems
40:18like it uh the the I'd be happy to go to
40:22DC and hang out and do this for on, but
40:25it cost you a whole lot more than
40:26$72,000 a year. Um, so anyway, uh, if
40:31if, uh, if we need more discussion, if
40:33if somebody wants to make a motion to,
40:36uh, to approve the proposal from
40:39Ferguson Group for one-year term subject
40:41to renew
40:43the renewal and approval of the
40:45agreement by the authority attorney and
40:48authorizes CEO to execute the agreement.
40:51Somebody want to make that motion?
40:53>> Moved.
40:54>> We have a motion.
40:55>> Second.
40:55>> Second.
40:56>> And we have a second.
40:57>> Do we have any more discussion? Anybody?
40:59>> Brett, do I need to recuse myself or
41:01not?
41:02[snorts]
41:03>> Any other concerns, discussions? I mean,
41:06it's not like we're uh not like we're
41:09committing ourselves to a huge uh
41:12long-term
41:14commitment.
41:15Um,
41:17you know, we look at it again months, a
41:20year from now and and if we see the uh
41:25um see the benefits, we continue. We
41:29don't and [sighs and gasps] we wave
41:32goodbye.
41:33>> That's
41:34>> um
41:35>> easy. [laughter]
41:36>> Well, is she going to work hard the
41:37first year, huh?
41:38>> That's right. when she she said
41:4210% that's that's only $770,000.
41:45That's true. She can bring us
41:47>> 10 10 to one. Yeah, she'll be all right.
41:50>> I got a question, Eric. Where where does
41:53this money come from that we're going to
41:54pay for this?
41:55>> It was included in our administrative
41:58budget.
41:59>> Okay.
42:01>> All right. Any other discussion?
42:04All in favor say I.
42:06>> Any opposed? All right. Motion carries.
42:10Thank you, Ann.
42:10>> Thanks,
42:11>> very much. Very excited to work with
42:12you.
42:13>> Look forward to to getting you working
42:15with you and the staff and and
42:18determining what those priorities and
42:20opportunities are for Anasa.
42:22>> Very excited. Uh Frankie has my contact.
42:25I know I passed out my business cards,
42:26but please, if you have any questions or
42:28want to talk in detail about anything,
42:30I'm always available.
42:32>> Thank you very much.
42:33>> Thank you.
42:34>> Thank you.
42:34>> How does the county use to lobby at
42:36state level? You got everybody or no?
42:39[snorts] Yeah, we did. Um, all right.
42:42Let's see. Item C, uh, authorization of
42:46upset bid process for surplus property
42:48on Viking Place. And that is, um, who's
42:53presenting that? Frankie,
42:55>> that's me. I got you [laughter] got me.
42:57I appreciate everybody's attention this
42:59matter. We've got I think we spoke about
43:00this um prior meeting, but we've finally
43:03got everything sort of in order to be
43:04able to present to the board. So, we
43:06just want to go um out for upset bid on
43:09this particular piece of surplus
43:11property. This uh sits adjacent to um a
43:15facility that we we took over in this
43:17community. It's old wastewater treatment
43:19plant. This individual has a piece of uh
43:23I think a storage unit on this property.
43:25So, we felt the easiest thing to do is
43:28mark it as surplus. It doesn't do us any
43:30good as far as valuable to that. All we
43:32operate there now is a pump station um
43:34and send that flow to another site. Um
43:37so worked with the individual that's
43:40adjacent there who has the property and
43:42he submitted an offer of 5,000 to
43:45purchase approximately 2 acres and that
43:48area has been surveyed out that is
43:50included in the cost of this transaction
43:52as well. Just so there's no cost to
43:54Anasa. So, what we're doing is
43:56requesting that the board consider a
43:57motion to adopt a resolution declaring
43:59the 0.2 acres um as surplus property and
44:03authorizing the upset bid process.
44:06>> I move second.
44:07>> All right. I have a motion and a second.
44:09Is there any discussion?
44:12All in favor say I.
44:14>> Any opposed?
44:16>> Motion carries. And the interlocal
44:19agreement for fleet maintenance, Mr.
44:21Adams.
44:22>> Yes, sir. Thank you, Mr. Chairman. Good
44:23evening directors. First item this
44:25evening is the interlocal agreement
44:27[clears throat] between Enslow County
44:29and Anasa to provide for Enslow County
44:32to provide Anwasa with fleet repair
44:35maintenance services for specifically
44:37our diesel vehicles and equipment
44:40approximately 50 vehicles and 100 um
44:44heavy equipment. [cough]
44:46[clears throat] Our staff had an
44:47opportunity some time back to visit the
44:50the maintenance facility the county
44:52operates. uh and feel very very
44:54comfortable with their expertise and
44:56ability to perform these services. Um
45:01enter into some negotiations discussing
45:03and it's very coste effective um and
45:07very similar to what we're currently um
45:10receiving from our current vendor. So we
45:14feel that this is a very beneficial
45:15agreement for both parties and and a
45:18cost-effective one going forward. So
45:20this evening we're considering asking
45:23you to consider a motion to adopt or
45:26approve the interlocal agreement and
45:27authorize the CEO to execute any
45:30contracts required with this action.
45:32>> So move
45:33>> second. I have a motion and a second
45:36>> question.
45:36>> Yes.
45:38>> What was your guess on savings? What
45:40what did you what did you guess?
45:43>> So savings are not going to be as
45:45significant as as we had might have
45:47hoped. Um, but I do think that the the
45:51benefits come from the access to them
45:53and and utilizing their um systems for
45:58identifying issues and their uh queuing
46:02system for lack of a better term is how
46:04how they enter enter those projects in
46:07the costs were very very close with what
46:10we currently have with our current
46:11vendor. Um,
46:12>> what about timing? what about,
46:14[clears throat] you know, returning
46:15returning an equipment or vehicle back?
46:17>> And and that's where I think the real
46:18benefit is is is their their promises in
46:22the agreement their their
46:23[clears throat] agreement to um perform
46:26the necessary repairs and maintenance in
46:28a timely manner.
46:30>> That was that was a question I was going
46:32to ask is would we be put on the back
46:34burner because the county has a lot of
46:36vehicles they have to maintain.
46:38>> They have a really good system that
46:39they've employed that that keeps their
46:42their
46:43they're uh them flowing. They are very
46:47upfront that emergency services do take
46:50a priority. So we know that you know
46:52going in um this doesn't
46:56you know disallow us from using any
46:57outside vendor if it became an issue
46:59where we had a piece of equipment that
47:01we needed
47:04you know serviced immediately and they
47:06were unable to provide it. Um, but they
47:09they do have a very good process. It it
47:13does seem and how they present it is how
47:15they
47:16>> enter and and keep things moving.
47:18>> Well, I think the uh you know the
47:20naturally the cost savings, but if the
47:22cost savings wasn't significant to to
47:24amount for the time we'd have to have
47:26our vehicle down, I think that would be
47:28considered too. So,
47:29>> right.
47:30>> Thank you.
47:31>> What was the uh what's what's the uh how
47:33long is this agreement for?
47:37Anybody can
47:38>> anybody can cancel at any time if that's
47:40>> a 30-day notice or something.
47:42>> Yeah, we we have in here that anybody
47:44>> All right. So So we have a we have a
47:47self check selfchecking me mechanism. If
47:49we if we don't get the service we feel
47:51we deserve, we have a we have an out.
47:53Okay.
47:54>> Correct.
47:54>> 30 no exclusivity. So you don't get
47:57locked in if you've got to go someplace
47:59else. Right.
48:00>> Right.
48:01>> Worth a shot. [clears throat]
48:02Al also I would say the reason they are
48:05efficient because they schedule
48:07everything
48:07>> right
48:08>> and
48:08>> and I can tell you I started that
48:11>> and it makes a big difference
48:13>> and if you can keep people on time to do
48:16their part can more
48:20over more then do their part. So uh I'm
48:24glad this worked out.
48:25>> I think it's a great thing. And I think
48:27it's a way we can all down the road save
48:30money in government and uh not just
48:33savings on dollar amount but turnaround
48:36time is very important when it comes to
48:39projects.
48:40>> Their scheduling Bob well.
48:42[clears throat]
48:43>> Yes sir. Their their scheduling was was
48:45uh excellent. They also use the uh
48:48similar fleet maintenance software that
48:50we have recently employed um for
48:53tracking. So,
48:55>> are we will we have any employees
48:57displaced?
48:59>> No.
48:59>> Because of this move.
49:00>> No, sir.
49:01>> It was a contract. It's a prior
49:02contract. We had a
49:04>> service provider.
49:05>> That's correct.
49:06>> Also, just real quick to follow up on
49:08Tony's comment, anytime we can do a
49:10partnership with the different agencies
49:12and stuff, to me, you know, it's
49:17>> I think it's mutually beneficial.
49:18>> Yeah. I I just think the more you can do
49:20like that, the better the part more
49:22partnerships, Tony, you can make between
49:24between [clears throat] the groups makes
49:25a lot of sense to me.
49:26>> You have something?
49:28>> Yeah, just for what it's worth, I did a
49:29little bit of research on base and we
49:30have a very similar IGSA with the base
49:33and the county for very similar
49:35equipment sets for the last three years.
49:37And to the points a lot of people have
49:38made, we we have seen cost savings on
49:40base and more importantly, we've seen a
49:42very quick turnaround time. uh where
49:44before with the company we were using on
49:46base it was weeks now it's days. Uh so
49:49that is something that we can quantify
49:50to [clears throat] our benefit. And also
49:51some feedback we got from the county was
49:53that it was it was keeping their team
49:55busy and active and working on equipment
49:57repetitively and some new equipment that
49:59they hadn't had experience on and
50:00they've gotten that experience which is
50:01a good thing.
50:02>> And I I I did that too not trying to
50:06take anything because it was a team
50:08effort.
50:10But by doing these projects, just to to
50:13Bob, Bob, you make a great point is that
50:17we're able to buy the up-to-date
50:19equipment to go with the piece of
50:21equipment you bring on help diagnostics
50:25tool
50:26>> and that tool means a lot. That's why
50:28the base I'm so [clears throat] happy we
50:30were able to get the cat machine to to
50:33work to feed in and we can use it not
50:36just for them but for Oslo County as
50:38well as you know
50:40>> anyone else. It's
50:42>> great great facility that the camp
50:43>> Oh yes it is.
50:45>> But thank you. That's all I got to say.
50:47Chairman, I'll pull up.
50:49>> I would I would just commend the uh our
50:52staff and the county and and thank them
50:55all for the work because this has been
50:57in the process for uh many months now
51:01>> negotiating the deal and and trying to
51:03make sure it's good for all parties
51:06involved and I think it'll be good.
51:08It'll be good for us. Did Did we get a
51:10motion?
51:11>> Yeah, we did.
51:12>> We did. Okay. Thank you. You want to say
51:14something? Oh, I just found the uh
51:15quotes that Danny had provided us just
51:17to show us some examples, real life
51:19examples. So, like on a 4500 pickup
51:22truck, service truck, um what we were
51:24paying now was like $560 for a typical
51:26service and their estimated cost would
51:28be $380 for that same service. And then
51:30on a backhoe, it was $480 versus 360.
51:34So, just ballpark kind of idea of what
51:36we would be saving.
51:37>> That's because we're buying bolt.
51:40>> Okay,
51:40>> that's true. All right. If there's no
51:42more discussion, all in favor say I. I.
51:44>> Any opposed.
51:47All right. Motion carries. And then Mr.
51:50Adams, you got the next one.
51:52>> All right. Thank you. Um, next is um
51:56requesting approval for a project
51:58ordinance for the Irving Town Wastewater
52:00Pump Station. So, our staff currently
52:03has an design agreement in place that to
52:07work on an upgrade for the Irving Town
52:09Pump Station, which is located in the
52:10Northwest service area in the Richlands
52:13area. Um, it's been identified as
52:15needing an upgrade for future
52:17development and to meet current needs.
52:19So, this project ordinance would
52:20establish uh the project for the funding
52:24for the next couple years to continue
52:25that design work. At the end of that
52:27work, we would um bring forth a contract
52:30and construction costs to amend the
52:33project ordinance.
52:35Uh this project was included in our CIP,
52:38so has been considered in the 10-year
52:40plan and in the recent rate model.
52:45>> Make a motion we we we adopt the budget
52:48ordinance.
52:49>> Second.
52:50>> We have a motion in a second. Any
52:52discussion?
52:55All in favor say I.
52:56>> I.
52:57>> Any opposed?
52:58>> All right, moving on. Mr. Adams.
53:00>> Yes, sir. Um, next, similarly, a project
53:03ordinance for the Northeast Wastewater
53:05Treatment Plant. Um, this also is
53:08included in our CIP in the five six to
53:1110 year range for a wastewater treatment
53:14plant to serve the Swansboro and Highway
53:1624 corridor. This would be the uh
53:19initial study and analysis for a future
53:23plant to be located potentially at the
53:25Parkertown property that is owned and
53:28operated by Anasa currently.
53:30[clears throat]
53:32Um again, this was included in our CIP
53:35uh and and in a in a future date, we
53:38would come back with a uh
53:42contract or additional design work for
53:45to complete. So move.
53:48>> Got a motion. I have a second.
53:50>> Second.
53:51>> Do we have any discussion about that?
53:54>> This is property that on was owned for
53:56many years. I haven't really used it to
54:00uh to the extent possible hopefully and
54:04this uh study will help us know if if
54:06there's more potential use for that
54:08property. Um so all in favor say I.
54:12>> I.
54:12>> Any opposed?
54:14>> Right. Moving on to item G. Um, Mr.
54:17Adams, you're up again.
54:19>> Yes, sir. Next is a project ordinance
54:21for uh the study to relocate an existing
54:24pump station at North Topsel Wastewater
54:27uh for the North Topsel Wastewater pump
54:29station. It's pump station number 49. If
54:31you're familiar with the area, that's
54:32the pump station just when you uh cross
54:34the bridge on the right. Um its current
54:38location is is not environmentally sound
54:41or safe for staff to maintenance. So,
54:44this ordinance would establish funds to
54:47begin um the process of relocating uh
54:51determining a suitable site to relocate
54:54uh in the in the future. Again, this is
54:56[clears throat] included in our CIP and
54:59these funds would cover that initial
55:01work.
55:04>> Motion to approve.
55:05>> All right. So, we got a motion.
55:07>> Second.
55:08>> Second. Um
55:12does does the study include in uh whe
55:15there's a need to um upgrade that pump
55:18station? It needs to move if you know
55:20where it is. Oh yeah,
55:21>> it definitely needs to move, but is with
55:25the growth in on the on the island, does
55:28it need to be expanded or
55:32will we find out that with this study?
55:35>> Yeah, I'm certain that that would be a
55:37part of that. Um, I'm sure Mr. Lure may
55:40could speak more specifically to those.
55:42>> Yeah. Um, [clears throat]
55:46we might be able to salvage some of what
55:48the pump state what's there now, but I
55:50think we're basically looking at a new
55:52pump station.
55:53>> I gotcha.
55:54>> A new location
55:56>> and then we would demolish the existing
55:59one.
55:59>> I think that's your best bet.
56:01>> Yes, sir. I think what Royce is asking
56:03too is it would it wouldn't need to be
56:05larger, right? Or bigger for for future
56:07growth.
56:08>> We would take that absolutely. The
56:09design would take that into
56:10consideration.
56:11>> Okay.
56:12>> All right. Rick Rick said he had some
56:14room in his yard. [laughter] I'm
56:17>> telling you, if you've ever if you've
56:18ever seen them servicing this thing.
56:20>> It's they got traffic block.
56:22[clears throat] This is just [snorts]
56:24>> you can never figure out why they put it
56:25there. It's it's definitely an unusual
56:27location for anything.
56:29>> We wouldn't know where we're going to
56:30move. Yep. today
56:32>> has not been
56:32>> because we might possibly have to buy
56:33more land or something.
56:35>> Yeah, we've made some inquiries. We've
56:36looked at some alternatives possibly
56:38even different routes off the island.
56:40You know, right now that that pipe is
56:41suspended on the bridge and that's
56:43another concern, right, from the
56:46environmentally standpoint. So, we'd
56:47have to look at the hydraulics of
56:48putting it under the
56:50>> inter coastal waterway.
56:54>> All right, we need a Let's see. All in
56:56favor say I. I.
56:58>> Any opposed? All right.
57:00Motion carries. And then we got Mr.
57:03Adams. Finally, your last one.
57:06>> Final project ordinance for the evening.
57:08Uh for the wastewater system master
57:10plan. Um again, this has been included
57:13in our CIP. Um it would be to create a
57:17wastewater hydraulic model similar to
57:18the work that's been completed on our
57:20water model. um obviously help us ident
57:24to help better help us to identify um
57:27needs issues um throughout the system as
57:30we continue to expand develop but also
57:35be able to identify for um improvements
57:38of aging infrastructure.
57:41[clears throat]
57:42>> Will this model uh be owned by us and
57:46not not a consultant?
57:48>> Be owned by us. Mhm. [clears throat]
57:49>> It will be owned by us
57:51>> and we'll be able to run it on our own.
57:54Okay.
57:56>> To Bob's point though, would we be
57:58hiring in a consultant to develop this
58:01>> the plan and so forth?
58:02>> Yes, we already have this consultant on
58:05board. They've already done begun the
58:07initial work. We're actually I think we
58:10have we're up to about 25
58:1226.
58:14Um we're
58:17have meters and
58:20>> [clears throat]
58:20>> to start to gather the data that's
58:22needed over a period of time
58:26that that'll get built into the model
58:28and then we'll ultimately be using the
58:30model to master plan and develop future
58:33improvements as uh Eric said.
58:36>> Thanks Jeff.
58:39>> We have a motion
58:40>> move and a second.
58:42>> Second.
58:44>> Have any other discussion?
58:46This is definitely uh with the
58:49tremendous growth of Enzo County. Um
58:54planning is what it's all about, right?
58:57>> Crazy.
58:57>> And planning for INI every year. Your
59:00your your infrastructure slowly degrades
59:02and uh and causes you problems. So you
59:05got to
59:06>> got to plan for it.
59:07>> Well, we got these people from like
59:10Mobile and those places moving up here,
59:12too. And so they're adding. It's
59:14terrible.
59:16She just moved here.
59:18>> I didn't [laughter] think you had enough
59:19room down there to build much more.
59:21>> You know, you know what's funny is off
59:23the subject,
59:24>> the next phase is the is the tear down,
59:26build out. They're going to buy that 800
59:28ft house on the beach, tear it down.
59:30It'll be a 12 bedroomedroom, 14 bath
59:32monstrosity like we see near the serve
59:34city line that they're building motel.
59:40>> All right. Um, all in favor?
59:42>> I.
59:43>> Any oppose? say no. All right. And we
59:47move on to Thank you, Mr. Adams.
59:49>> Thanks.
59:50>> Um All right. We have a whole line of
59:52folks for public comment.
59:55>> Nobody. [laughter]
59:56>> Man, [snorts]
59:59nobody. Okay. Um we don't need a closed
1:00:02session. Is that right? So, we're gonna
1:00:07[laughter]
1:00:07>> I know everybody wants to have a clos
1:00:10wants to get home.
1:00:12Um [snorts]
1:00:14I think the item for close session
1:00:16didn't uh isn't hasn't materialized. So
1:00:19um we'll have to do that in October.
1:00:22>> Um so do we have to do anything for
1:00:25that? We just bypass it.
1:00:27>> All right, Mr. Howard, your comments.
1:00:30>> Yes, sir. Thank you. Just a couple items
1:00:32um before we wrap up. Just uh letting
1:00:35the board know we've been successful in
1:00:37getting signatures on the letter to the
1:00:38base. Uh Royce has went around to
1:00:40different meetings and in fact um I
1:00:43think we got one of our signatures this
1:00:44evening from the city of Jacksonville. I
1:00:46think we'll be getting one from the
1:00:48county and Swansboro here later in the
1:00:50week. Um Royce and I will be
1:00:52participating in the CPG meeting uh
1:00:54later this month to maybe hand deliver
1:00:56that letter to the to the general
1:00:58himself uh or his representative that'll
1:01:01be at that meeting. So I know at that
1:01:03meeting they'll be hearing from the
1:01:04group that's conducting the uh
1:01:06resiliency study and we have several
1:01:08items that have been identified in the
1:01:09resiliency study that impact anasa and
1:01:11the base. Uh so and some of those are
1:01:14partly uh identified in that letter as
1:01:16well. Um just wanted to also let the
1:01:19[clears throat] board know that earlier
1:01:20today we received notice from the EDA
1:01:22and I shared that with you all via
1:01:23email. Um in case you hadn't seen that
1:01:26we we did not get the grant for the
1:01:29water tower in Holly Ridge
1:01:31unfortunately. But now that we have some
1:01:33advocacy uh contract work, we might can
1:01:35find another avenue of funding or maybe
1:01:37try again with EDA. Um they told us
1:01:40nicely [clears throat] in the response
1:01:41there that they had quite a few
1:01:43inquiries for funding this year and they
1:01:47had better applicants basically. So
1:01:49>> we don't have a dedicated uh uh grant
1:01:51writer, do we on staff? We we don't and
1:01:54we've used consultants for various um
1:01:57would part of part of uh part of the
1:01:59Ferguson group be be partially doing
1:02:02some grant writing also in addition to
1:02:04finding the uh
1:02:05>> I think they'll definitely help us find
1:02:06the sources. I'm not sure about the
1:02:08actual writing of the grants but
1:02:10>> yes so in the proposal or in the
1:02:12contract it's not we have a the grant
1:02:16division is separate um but with your
1:02:20contract we do already included grant
1:02:23review so if you do write the grant
1:02:24yourself um we will have a grant writer
1:02:27or somebody an expert with it review
1:02:30your grant and get back to you also um I
1:02:34would be getting you letters of support
1:02:37from your delegation to include in your
1:02:38grant packet. Uh as well, did EDA get
1:02:42[cough] debrief?
1:02:43>> We did get offered that and we will
1:02:45reach we reached out and of course
1:02:47thanked them for the the notice and um
1:02:50we're going to reach out again to to get
1:02:51some feedback because I promised at Holl
1:02:54Ridge that we would figure out, you
1:02:55know, where we could maybe make that
1:02:57applicant application better for future
1:03:00submitt. But we will we will definitely
1:03:03follow up with that. We used um Hazen I
1:03:06think was our group that helped us write
1:03:07that particular grant. They had some
1:03:09capacity to help us. They were doing our
1:03:10water model and it was part of that uh
1:03:12water models. We identified these two
1:03:14projects. So, but we've also used
1:03:16others. We've got our firm Rafelis that
1:03:18does our financial models. They have a
1:03:20grant writing group. We've engaged with
1:03:21them to kind of see uh how they can help
1:03:24us. Um and they've identified some areas
1:03:26like some of these projects you approved
1:03:28tonight. these ordinances like the pump
1:03:29station for example is one that they
1:03:31feel like is a prime project for certain
1:03:34funding that's out there that we might
1:03:35seek. So
1:03:39and other than that we uh I just point
1:03:40out I saw a map earlier too. I think
1:03:42it's today Thursday the drought map
1:03:43comes out. So we picked up some areas in
1:03:46the county that's back into the drought.
1:03:48We had kind of come out of the drought
1:03:49and now we're getting some dry areas. So
1:03:52for us hopefully it's not as big a deal
1:03:53because we're on the downward slope of
1:03:55our demand, our peak demand. you know,
1:03:57it's July and August, so we're starting
1:03:58to see that come down, but we still have
1:04:00to pay attention to the drought and that
1:04:02may folks may pick up using water again
1:04:04and try to keep that grass as green as
1:04:06possible to the end this the season.
1:04:09[clears throat]
1:04:10Um, other than that, it was mentioned
1:04:11that we'll meet in October. We
1:04:12appreciate the board's flexibility to
1:04:14have that meeting date. I think we
1:04:16settled on the 22nd. That'll be to
1:04:18consider uh some debt placement for our
1:04:21CIP projects this fiscal year. So Doug
1:04:24Carter and the folks from Rap Tails will
1:04:26be here to talk to us about approving
1:04:28[snorts] items that'll [clears throat]
1:04:29go to the LGC in November
1:04:32for review
1:04:33and that is all I have. So I appreciate
1:04:35staff of course for working on items for
1:04:37this evening. And uh thank you to the
1:04:39board.
1:04:41>> I got I ask Frank a question
1:04:42[clears throat] please.
1:04:43>> Sure. I know that the state was doing
1:04:46that study on the government property
1:04:47down there. Uh
1:04:49>> yes.
1:04:49>> Uh did they finalize that or was that
1:04:52just a preliminary thing?
1:04:54They said that they would let us know if
1:04:55they found anything. We have reached out
1:04:57to our contact through public water
1:04:59supply to see if they were familiar with
1:05:01what was going on there. Um, but just so
1:05:03the board's aware of what's happening,
1:05:04we got notice uh in the town of Holly
1:05:06Ridge did as well because they have
1:05:07property next to uh this subject
1:05:09property that was being reviewed by the
1:05:11state uh department of um
1:05:16whatever that's the state that reviews
1:05:17the uh abandoned landfills. uh they had
1:05:20a consultant doing some studies for the
1:05:22abandoned landfill of Camp Davis that's
1:05:24on the Ottawa property I believe and so
1:05:26we have property north of that the
1:05:27Wakovia track and the town has property
1:05:29adjacent to it in the industrial park
1:05:31and they wanted to identify any public
1:05:33water supply wells within a certain
1:05:35search ring around that
1:05:37>> of course we have wells D10 and 11 that
1:05:39are on the Wovia track so we identified
1:05:42those for this firm uh and we have not
1:05:45heard back so but for what we hear from
1:05:47our consultants we're outside of any
1:05:49concern area that they're aware of, you
1:05:51know, by current state requirements. So
1:05:55now, if they find something through this
1:05:57review or study, then we'll we'll adjust
1:05:59accordingly.
1:06:03>> Uh, Mr. Howard, I have a question, too.
1:06:05Have you have you had a an opportunity
1:06:07to talk to anybody at this uh with the
1:06:09city of Jacksonville about the
1:06:11properties that have left their ETJ
1:06:14that uh are being serviced by the city
1:06:18utilities? I don't know. I' I've assured
1:06:21people that they're not not going to
1:06:23turn off their water, but uh you know,
1:06:26the question then is who's going to
1:06:28service their their water and sewer?
1:06:31>> Yeah. And I think it just comes down to
1:06:34what they've negotiated with that
1:06:36developer, I guess, in these areas for
1:06:39future volunteer annexation because I
1:06:41think they're still allowed to do that
1:06:42in certain areas of the ETJ. Um, and
1:06:44they're working on figuring out what
1:06:45happened with this whole south of 24
1:06:47area. So, if they're, you know,
1:06:49petitioning to voluntary annex and the
1:06:50city has infrastructure there, it
1:06:53naturally fits that they'll be the
1:06:54service provider. In a lot of cases,
1:06:56what we found is, or in some cases, we
1:06:58might have the water there and the
1:06:59city's got sewer. to work out a deal
1:07:01where we'll be the sewer provider and
1:07:04they might be the sewer provider.
1:07:06>> So, we haven't really gone to a lot of
1:07:07detail, but I do meet regularly. Matter
1:07:09of fact, we met Monday with the city
1:07:11manager and so we'll continue.
1:07:13>> I got one more thing, too.
1:07:15>> Okay.
1:07:15>> Just come to thought, a lady
1:07:17[clears throat] called me the other day
1:07:18and she was really concerned about all
1:07:20these hacks and all this stuff that's
1:07:22going on all over the country with the
1:07:25systems and she was really concerned
1:07:27about it happening here. And I know we
1:07:30had a problem one time before, but uh
1:07:33basically she just want to know how
1:07:35would the public be notified if this
1:07:38happened and would it affect our water
1:07:40system at all?
1:07:41>> Yeah, I mean we we've certainly put
1:07:44things in place to be prepared and to
1:07:46shield ourselves as best we can from
1:07:48these types of attacks. Um in fact,
1:07:51we've gone through some exercises where
1:07:52we make sure certain controls are not
1:07:55connected to outside uh sources. So, and
1:07:58in fact, if if a consultant needs to get
1:08:00in, they're having to directly
1:08:02communicate that with us to do any kind
1:08:04of changes to that system. So, I feel
1:08:06like we're we're we're doing everything
1:08:07possible now. We're participating in
1:08:10statewide communications when when they
1:08:12see things that are happening. Um, we
1:08:15are uniquely position, you know, close
1:08:17with the base, you know, so it's a good
1:08:19thing for a lot of these things we've
1:08:21talked about, but it actually puts a
1:08:22target on us for certain things as well.
1:08:23So, I feel like we've done the best we
1:08:26can. you know, we things, you know, are
1:08:29happening every minute, you know, to try
1:08:31to attack these things.
1:08:32>> Basically, I told her the same after
1:08:33that first time we, you know, we made a
1:08:36lot of changes. Her biggest concern was
1:08:38was how is the public going to know if
1:08:41something happens?
1:08:42>> Yeah. I mean, we would definitely um
1:08:44with with every means of possible, we
1:08:46would communicate like we do now to the
1:08:49customers if there is a concern about
1:08:50water quality. You know, what they
1:08:53they're trying to do is get in there and
1:08:54control the system. Um, fortunately we
1:08:57don't we don't have a lot of systems
1:08:58controls that would impact directly to
1:09:01the customer that I feel like, you know,
1:09:03as far as the way the operations are.
1:09:05Um, but we would definitely communicate
1:09:06out to the customers if there was a if
1:09:09there was something to communicate
1:09:10related to water quality.
1:09:14>> Frank, I got a random question, too. Um,
1:09:18water leaks and stuff like that. When
1:09:19there's a leak near DOT road that's
1:09:22going to potentially affect the road, do
1:09:24we have to get in line to get like
1:09:25permits with them to fix said leaks or
1:09:29do we have a does it depend on how bad
1:09:31the leak is?
1:09:32>> I think it really just depends on how
1:09:33bad um Matthew still here. Yes,
1:09:36>> encroachment.
1:09:37>> We do have a blanket encroachment which
1:09:38would allow us to get into certain
1:09:40areas. They do have restrictions in
1:09:42parts of the um county that we can only
1:09:46work during certain hours, right? if
1:09:48it's a planned event, but I think during
1:09:50emergencies, it's one of those you just
1:09:51got to get it done.
1:09:52>> The only reason I'm and I've been seeing
1:09:54water run down the road and obviously a
1:09:55leak has been identified and I was just
1:09:57kind of looking at it the past couple
1:09:58days and again it's not massive. It's
1:10:00not like it's shooting up in like it was
1:10:01in Steve's Fair or whatever.
1:10:03>> Easy easy.
1:10:04>> Hey you guys, when you guys do it, you
1:10:05do it. Um but no, I was just looking at
1:10:08it. I'm like, well, it's either a
1:10:09scheduling issue on our part or we're
1:10:10waiting on DOT to say we can dig up the
1:10:12road right here. So, I'm glad you asked
1:10:14because I think I answered his question
1:10:15earlier too, but I didn't put it in the
1:10:16all uh email back. So, in in
1:10:18[clears throat] Matthew's report to to
1:10:20the leadership team this week, his
1:10:22distribution department identified how
1:10:24many leaks they've been working on
1:10:25weekly. So, this past week, I think they
1:10:27fixed 30 leaks and they have 50 leaks on
1:10:30the list to be completed. Like, so
1:10:32they're working down a list, you know,
1:10:34but when I got here, it was taps we were
1:10:35trying to deal with and get caught up on
1:10:36taps and now it seems like it's leaks.
1:10:38>> Well, that were
1:10:39>> I just want to make sure. Um, that's
1:10:41just I was just wondering like I said if
1:10:43if it was a thing with DOT cuz we've
1:10:45been dealing with them on something
1:10:46privately, you know what I mean? Just
1:10:47kind of getting in the queue and going
1:10:48through the process and
1:10:50>> man, what a process that can be and I
1:10:52just didn't know if we had a problem if
1:10:53we could figure out how to
1:10:55>> Well, we when we do, you know, I have
1:10:57communicated concerns with DOT to like
1:10:59Senator Lazaro when we have we've been
1:11:00waiting on encroachment approvals or um
1:11:04and that is frustrating because it's
1:11:05take it's taken months sometimes to get
1:11:07those. But for leaks though, we we put
1:11:09them in the queue. We go out and
1:11:10identify them. In fact, we've put some
1:11:11signage out and I think some folks have
1:11:13seen the signage where we once has
1:11:15identified the leak so we don't continue
1:11:16to get multiple calls and that works in
1:11:18some cases but I know it frustrates
1:11:20folks when they see a leak and we
1:11:22haven't jumped right on it. Now there is
1:11:23a time that we do have to wait for
1:11:25[clears throat] um location like
1:11:27locating utilities around there so we
1:11:29can dig
1:11:30>> and I never blame the people. I always
1:11:31blame the bureaucracy that you know that
1:11:33we've been able to create around certain
1:11:35things. So again that was no slight on
1:11:37DOT by any means. Oh, no, no, no, no.
1:11:38It's just a process. It's just a
1:11:40process, right?
1:11:43>> All right. Thank you. Thank you. Um,
1:11:48Mr. Herbert,
1:11:50>> I just want to quickly say thanks to the
1:11:51uh the organization in totality,
1:11:53[clears throat] up and down the org.
1:11:54Appreciate everything you do on a daily
1:11:55basis, especially to our crews out
1:11:57there. You know, I mean, I I travel back
1:12:00uh daily from Swansboro to Jacksonville.
1:12:02my duties on base take me off in the New
1:12:04River out in town and you see our crews
1:12:07consistently almost daily for me at
1:12:09least and they're the face of the
1:12:11organization. They're the they're
1:12:12interacting with the uh the community
1:12:14and so forth and we just want to say
1:12:16thank them for everything they do. We
1:12:17appreciate it.
1:12:20>> Mr. Padet
1:12:20>> couldn't said it better. Thank you so
1:12:22much,
1:12:24>> Mr. Hind.
1:12:25>> Well, I'm just tickled to death to be
1:12:27here. Uh and also my usual say hello to
1:12:30Miss Janette. I got to say that. But uh
1:12:33yeah uh y'all said enough about it. I
1:12:36mean that's we do have I've always said
1:12:38we've got the best crowd out there.
1:12:40>> Absolutely.
1:12:42>> All right, Mr.
1:12:43>> I'll throw some kudos to the uh the
1:12:45staff. Uh this is some of the best
1:12:47planning that I've seen in the in the
1:12:49relatively short time I've been on WASA
1:12:51on Wasa. I can see an improvement. Uh so
1:12:54so thank you all for for what you're
1:12:56doing.
1:12:58>> Took the words right out of my mouth.
1:13:00Great job. Thank you. Thank you.
1:13:02>> Thank you, Mr. Bitner. [clears throat]
1:13:04Um,
1:13:05>> thank you everybody. And Frankie, if you
1:13:07hadn't fixed the geyser soon, we're
1:13:08going to use it as a marketing tool to
1:13:09bring people onto the beach because that
1:13:11I could see that sucker from my house.
1:13:13[snorts] Unbelievable. Everybody got a
1:13:16copy of that. You got the video on that,
1:13:17didn't you?
1:13:18>> Yeah. Yeah, I saw something else. You
1:13:20could have made a splash pad out of it
1:13:21while
1:13:21>> That's what I was thinking. Ain't that a
1:13:23splash pad? I mean,
1:13:25>> behind the booster station.
1:13:26>> But thank thank you and your team.
1:13:28[laughter]
1:13:29>> Uh, Mr. Vice Chairman,
1:13:31>> thank you guys as always. Thank you very
1:13:33much.
1:13:34>> All right. All right. And I'd say the
1:13:36same thing. You guys, you got a lot got
1:13:39a lot done for this meeting tonight. We
1:13:41really appreciate it. And and um yeah,
1:13:45being out there in the middle of the
1:13:46night working on these uh these systems,
1:13:50and I I know I'm glad I'm not out there.
1:13:52You do a great job. [clears throat]
1:13:54All right. So, do we have a motion to
1:13:56adjurnn?
1:13:57>> And we got a motion in a second. And
1:13:59we're ajourned. [snorts] They're like
1:14:01the Coast Guard. They go out.
```*