ONWASA Wastewater Project Ordinances

At a glance

  • What: Four capital project ordinances funding studies and design for wastewater facilities.
  • Where it stands: All four approved September 17.
  • Next: Studies and design proceed; contracts return to the board later.

Details

  • Irving Town pump station upgrade (continuing design in the Richlands area).
  • Northeast wastewater treatment plant initial study on the Parkertown property.
  • Relocation study for North Topsail pump station 49.
  • Wastewater system master plan and hydraulic model, owned by the authority.
  • Staff said the financial consultant sees some of these as strong candidates for outside funding.

Sources

Log

2026-09-17 - ONWASA Board of Directors

  • The board adopted the four project ordinances in turn, each already in the capital improvement plan.