Data Center Water Connections

At a glance

Based on auto-generated captions; names and details may be misheard.

  • What: residents and advocacy groups are asking the city to deny water utility extension agreements to new data centers in Durham County, starting with a proposed facility called "Project Lloyd", and to stop accepting data center applications filed as light industrial.
  • Where it stands: raised in public comment on 2026-10-08; the council did not respond or take action.
  • Next: none scheduled in this record.

Public comment

  • Speakers described Project Lloyd as roughly 88,000 square feet and 50 megawatts with a substation and 20 natural gas generators (another speaker called it a 72,000 square foot expansion). Figures are the speakers'.
  • Reasons given: drought conditions, a 12 percent water rate increase tied to emergency supply and PFAS treatment, power demand driving new fossil plants, and a county moratorium that exempts data centers up to 100,000 square feet.
  • Requests: deny city water connections; keep data centers from being classed as light industrial; work with residents and experts on long-term protections without loopholes.

Sources

Discussion time

About 11 minutes across 1 meeting (from transcript timestamps; approximate).