Jesse Commons PUD Amendment

At a glance

Based on auto-generated captions; names and numbers may be misheard.

  • What: rezoning case 26CZ02 (the agenda printed 26CZ01) to amend the 2006 Jesse Commons planned unit development: about 60,000 more square feet of light industrial in two pods and a 48-foot height limit, on 64 acres east of NC 55. Applicant: Strategic Real Estate Partners; a grocery-anchored retail center is planned on the NC 55 frontage.
  • Where it stands: the Planning Board recommended approval on Oct 12 (voice vote) with a full-movement signalized intersection at NC 55 and Jesse Drive, instead of the reduced-conflict (super street) design staff wanted.
  • Next: Town Council consideration; the applicant is to share its correspondence with the affected property owners with staff and settle wording of the starred conditions first.

The intersection dispute

  • Staff: the transportation plan calls for NC 55 to become a six-lane super street; building a full-movement intersection now makes the later conversion harder and costlier. A 2017 federal study found about 15 percent fewer crashes at such intersections.
  • Applicant: the required U-turn bulb would remove access to two businesses on the west side of NC 55 whose owners declined to sell, and it cannot require or deliver off-site right of way. It says its design converts later without more right of way, at the state's cost, and that cumulative delay is lower with the full-movement option for now.
  • Neither side expects a date for the NC 55 conversion; it is not in the state's funded program.

Other conditions

  • Concrete pads for future bus stops; fee in lieu if off-site right of way cannot be acquired.
  • An added southbound through lane on NC 55 (applicant says off-site).
  • No left turns out of one Jesse Drive driveway, because the state will not take over the road otherwise; the applicant says this hurts retail circulation.
  • The project builds most of the Jesse Drive link, leaving about 1,200 feet.

From the video (October 27, 2026)

Public hearing on case 26 CZ2: 64.37 acres, office space up from 180,000 to 240,000 sq ft, 48 ft height. The applicant cited a $70 million investment and $5.5 million of road work and asked for a full-movement signalized intersection at NC 55; staff recommended a restricted-movement intersection (dual U-turn) with a fee-in-lieu if right-of-way cannot be acquired. The Planning Board had recommended approval with conditions. The Council continued the case to December 17, 2026 to study the fee-in-lieu and right-of-way effects. See 2026-10-27 - Town Council Meeting.

Sources

Discussion time

About 82 minutes across 1 meeting (from transcript timestamps; approximate).

Meeting Minutes
2026-10-12 - Planning Board Meeting 82

Log

  • 2026-10-12 - Planning Board Meeting — Public hearing; motion approved, reconsidered, then recommended approval with the full-movement option plus conditions to share owner correspondence and agree starred-condition wording with staff.