  • What: a new heavy industrial zoning district in the Unified Development Ordinance amendments of May 2026 (ORD-2026-053), created so uses that do not fit the light industrial district, such as a detention center, have a clear process that comes before Council.
  • Where it stands: at the May 28, 2026 hearing, Amendments 1 and 2 were approved 4-0 and Amendment 3 was withdrawn. The minutes do not label which amendment covered this district, so its outcome is not stated.
  • Next: staff said more heavy industrial uses could be defined as the data center moratorium work and Environmental Advisory Board recommendations proceed (Data Center Moratorium and Rules).

Discussion

  • Mu asked whether a detention jail counts as a heavy industrial use; Mayor Pro Tem Mahaffey said yes. He explained Apex has no heavy industrial district today and no classification for a detention center, so a developer could argue a light industrial warehouse use without coming to Council.
  • Mu said it did not seem to benefit Apex. Zegerman suggested later adding uses such as battery manufacturing or data centers. Venable said holding cells in a police station would be an accessory use (under 20% of the principal use).
  • No one signed up to speak at the public hearing.

Sources

Log

2026-05-28 - Town Council Meeting

Discussed during the hearing on the May 2026 UDO amendments. See also Food Truck Court Rules.