  • Meeting: Five commissioners were present, a quorum, with Chris Meyer chairing; the minutes of the August 24 and September 14 meetings were adopted. The city website was down during the meeting, and staff shared the application materials by email.
  • Consent agenda: Four public hearing items were on the agenda. Items 5, 6 and 7 stayed on consent and were adopted on a voice vote, along with staff findings: a site plan review at 3200 Ko Avenue Southeast (as captioned), 800 Fifth Street Southeast and 700 Xerxes Avenue North. Only the first drew testimony.
  • Bus facility site plan (3200 Ko Avenue Southeast): The application expands an existing bus maintenance and storage facility operated by Transdev, moving outdoor storage into a vacated warehouse and adding a fueling station and landscaping. The University of Minnesota's director of campus planning supported approval but asked that the proposed snow storage area in the southwest corner be redesigned as a stormwater treatment area, citing past flooding and spill risk from the fueling station. Staff said the site is about 95 percent impervious, that staff recommend landscaping that roughly 10,000 square foot low corner, and that the zoning code does not require a stormwater practice there. Staff said public works review and an update to the site's industrial stormwater permit would likely address most of the concerns. The commission adopted the staff findings and encouraged the applicant to work with the university.
  • 3561 44th Street West and 4409 Chowen Avenue South: The commission adopted the staff findings, 5-0 on a roll call, for site plan review and a rezoning to add a split zoning overlay for a four-story mixed-use building with 18 two-bedroom units, about 2,000 square feet of ground-floor commercial space and an 18-space garage. Two administrative floor area ratio premiums were also part of the project. The item had been continued from August 24 so the building could be reduced to fit a transformer outside a shared private driveway easement. The developer said it kept parking near one space per unit. In response to a question about former gas-station soil contamination, the developer said a 1990s cleanup received a satisfaction letter and monitoring continues; staff said contamination is not regulated by the zoning code at this stage.
  • Neighbor concerns on 44th Street West: An owner of a five-unit building on the same block and a co-owner of another property using the easement said they did not oppose the project but argued the pad-mounted transformer was unsafe and obstructed the easement, that bollards could not fit, and that stormwater drainage toward the shared driveway would worsen existing ponding. They asked for added conditions and suggested a pole-mounted transformer. Staff said transformer placement, driveway drainage and easement rights are not zoning or site plan review standards and are resolvable through grading and utility review, and noted the grading plan lacked positive drainage at the southeast corner and had been flagged for public works. A condition requiring transformer screening and a lighting plan was already in the staff recommendation.
  • Looking ahead: The October 13 commission meeting will take up the data center zoning amendment, with the captioner asked to stay until 8:30 p.m. because of expected turnout; the moratorium timeline means it cannot be continued. The committee of the whole on Thursday will discuss a proposed six-story, 185-unit building near 2825 Cedar Avenue and a zoning code text amendment.

Issues Discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:08Welcome everyone to the regular meeting

00:09for the Minneapolis Planning Commission

00:10for September 28th, 2026. My name is

00:13Chris Meyer and I'm chair of the

00:14commission. At this time, I will ask the

00:16clerk to call the role.

00:19>> Commissioner Baxley is absent. Tori.

00:28[laughter]

00:29Yes,

00:29>> I heard Toby.

00:31>> Chowry, sorry. [laughter]

00:33>> I was like, I don't know. Present.

00:37>> Connley

00:38>> present.

00:39>> Garcia is absent. Gordon is absent.

00:43Jones is absent. Shepy is absent.

00:48Shepard

00:49>> here.

00:50>> Vice President Wagner

00:51>> here.

00:52>> And chair, I'm sorry, President Meyer

00:55>> here.

00:55>> There are five members present.

00:57>> We have a quorum. First, we'll go to the

00:59minutes. We have two of them. I would

01:01like someone like to move the adoption

01:02of the minutes for August 24th and

01:04September 14th.

01:05>> So, move.

01:06>> Second.

01:06>> Is there any discussion?

01:08>> All in favor say I. I. Opposed.

01:10Abstensions. The minutes are adopted.

01:13Next, we're going to organize our

01:14agenda. We have four public hearing

01:16items. Staff are recommending that all

01:18four of them be put on our consent

01:19agenda. I'm going to read through each

01:21one of them. If you came to speak

01:24against the staff recommendation for one

01:25of the items, raise your hand when I

01:27call on it. If you wanted to speak in

01:29support or make neutral comments, you'll

01:31have a chance to do that in just a

01:32minute. But we want to look now for just

01:34people who are against the staff

01:36recommendation. Uh so first item four,

01:39356144th

01:40Street West and 4409 Chowan Avenue

01:43South. Was anyone here to speak against

01:45that? Okay. So we will discuss that one.

01:50Uh second is 3200 KO Avenue Southeast.

01:53Was anyone here to speak against the

01:55staff recommendation for item number

01:57five?

02:00All right, we'll keep that on consent.

02:03Third, we have 800 Fifth Street

02:04Southeast. Was anyone here to speak

02:06against the staff recommendation for

02:08item number six?

02:12All right, we'll keep that on consent.

02:15And last, we have 700 Xerxes Avenue

02:17North. Was anyone here to speak against

02:20the staff recommendation for that one?

02:24All right. So to review, we will discuss

02:26item four and we'll have items five,

02:29six, and seven on our consent agenda. Uh

02:34so I will open up the hearing for our

02:36consent items. If you wanted to speak to

02:38any of them to items five, six, or

02:40seven, you can do so now. Did anyone

02:41want to speak? Go ahead.

02:46Welcome. Introduce yourself and you have

02:48two minutes.

02:51>> Thank you, Chair Meer. My name is

02:52Monnique McKenzie. I'm the director of

02:53campus planning at the University of

02:54Minnesota. Um I'm just here to speak yes

02:57in favor of the uh staff recommendations

02:59for item 5, which is the property at

03:013200 KO Avenue Southeast. But I am here

03:04also and I believe you're in receipt of

03:06our letter to recommend some additional

03:08consideration for that site plan review

03:10in particular. And this specifically

03:11relates to the topic of storm water

03:13management. Um this property that you're

03:16considering is a 10acre site. It's

03:17immediately adjacent to the University

03:18of Minnesota's land where we have a lot

03:20of our operations. As noted in your

03:22staff report, um we have really three uh

03:25requests for you to consider under your

03:26site plan review findings that your

03:28staff have prepared. We have worked with

03:30this land owner actually since the early

03:322000s, but in 2017 with the current land

03:34owner on how to manage for storm water

03:36runoff conditions, which are not good on

03:38the site you are considering. Um and

03:40that property owner has been very um

03:43engaged with us about how to remedy the

03:45situation. Unfortunately, the treatment

03:47at the southwest corner of this site

03:48does not do that. It is a landscape

03:50feature as noted in your staff report,

03:52but it does not address the grading nor

03:54any of the engineering you would expect

03:55to see. So, we can actually see storm

03:57water managed at that site. You may have

03:59seen in our letter that we enclosed some

04:01pictures uh on the last page of that. Um

04:04the conditions are better today because

04:05the university made some decisions to

04:07manage for storm water. That connection

04:09was permitted by the city. Um we

04:11specifically dedicated land and

04:12resources so we would not be wiped out

04:14by the flooding conditions that were

04:16occurring there. So, our three requests

04:19for you at the city um in terms of your

04:21site plan review as the final versions

04:23of these advance is to redesign that

04:25snow storage area in the southwest

04:26quadrant of the site as a storm water

04:28BMP. That is to avoid the risks we have

04:31already experienced in terms of damages

04:33and to prelude future risk. Uh there may

04:36be some considerations about putting a

04:37fueling station at that site,

04:39particularly if the storm water is not

04:40addressed, whether an incidental spill

04:42or a flooding caused spill will cause

04:45sheet drainage across to our property

04:47and eventually overwhelm the city's

04:48infrastructure at that location.

04:51That's really what I wanted to say.

04:52Commissioners, I'm happy to answer more

04:54questions. Uh we are dedicated to work

04:55with this land owner and of course

04:57within the city, we both hold MS4

04:58permits. We both have responsibilities

05:00to the state of Minnesota to uphold the

05:03storm water management and we ask the

05:05city I'm sorry the commission to um

05:07consider these reasonable and preventive

05:09measures in the site plan review

05:10component of this project application.

05:13Thank you.

05:14>> Thank you. Would anyone else like to

05:16testify to our consent items?

05:21>> All right. Uh not seeing anyone else. Um

05:25can we have so so I'll close the

05:27hearing. Um, can we have Aspen

05:30just speak to the testimony we just

05:32heard? And,

05:34um, I'm wondering if we can incorporate

05:36any of of the recommendations from the

05:38university or if you would recommend

05:39that.

06:03Thank you, Chair Meyer. Um, good

06:05afternoon, commissioners. My name is

06:06Aspen Flands, city planner on the land

06:09use design and preservation team. The

06:12application um before you at 3200 KOMO

06:15Avenue Southeast is an expansion of an

06:18existing bus maintenance and storage

06:20facility that's currently operated by

06:23Transdev. That applicant um has

06:27contracts with the University of

06:29Minnesota as well as the city of

06:32Plymouth um to and metrotransit to

06:36provide bus services in our city. They

06:40have been on the site since 2007. The

06:42request now is simply to take outdoor

06:47storage and put it within the existing

06:48warehouse building now that that

06:50adjacent tenants has vacated the site

06:53which was a pallet management company

06:54called 4840.

06:56Um, and I'm showing here the proposed

06:59site plan. So, it's a fully developed

07:0295% imperous site. Um, and with the site

07:06plan review that's required for our

07:09vehicle fleet oriented services uses,

07:11you can see that some additional

07:13landscaping is being proposed as well as

07:15a fuel station that doesn't currently

07:17exist on the site. Um, where this orange

07:23boxes and that is the side of the

07:25property that shares a property line

07:26with the University of Minnesota's um,

07:28property that you just heard about. In

07:31the southwest corner, there's a snow

07:33storage site proposed that staff is

07:35recommending be landscaped um just to

07:38add additional pvious surface. Their

07:41impervious their landscaping requirement

07:44for a site of this size is over 66,000

07:47square ft. They currently have around

07:5028,000. They are proposing 35,000.

07:54staff is recommending that that 10,000

07:56square foot corner um because it is the

07:59lowest grade on the site and it does um

08:03all drain to adjacent properties that

08:04that also be landscaped to retain some

08:06of that storm water. As you heard from

08:09the testimony um they do have an

08:12industrial storm water permit that's

08:13active with the addition of this fueling

08:16site. public works because this has

08:18already gone through the first round of

08:19PDR has indicated that an update to the

08:22site's industrial storm water permit is

08:24likely needed given that addition of the

08:26fuel site. So most of the concerns that

08:30you just heard would hopefully be taken

08:34care of by that permitting process.

08:37Additionally, if half of an acre is

08:39disturbed, our public works um storm

08:42water chapter requires a storm water

08:44management plan. And so if the applicant

08:47does exceed more than half an acre of

08:48disturbance with their proposed upgrades

08:50to the site, there are approvals that

08:53they will go through with public works

08:55rather than our planning department to

08:58make sure that that's taken care of.

09:00>> Great.

09:02Thank you. Uh commissioners, are there

09:04any questions or discussion about our

09:06consent agenda?

09:08>> Commissioner Shepard,

09:09>> just want to thank you for that

09:10presentation. Is this just landscape or

09:12is this a BMP that we're looking at in

09:14that corner?

09:16>> Thank you for the question. Um staff's

09:18recommendation is just to landscape that

09:20corner. I am not sure if if this

09:23proposal does trigger a storm water

09:25management plan or those updates to the

09:27industrial storm water permit, how if

09:30this area could also be used as a BMP,

09:33but in terms of the zoning code, we

09:35don't have specifics to require that.

09:38>> And I think it's section 54, I think.

09:40>> Yes. Yeah. Okay. Thank you.

09:45>> All right. Um, so if any commissioner

09:48wants to take, you know, an item off

09:50consent, we can do that. But we weren't

09:54we weren't, you know, explicitly asked

09:55to do that. So I would suggest just

09:56moving to adopt this and encourage um

09:59the applicant to work with the

10:00university and hopefully have those

10:02resolved when the peritting process goes

10:03through. Is there a motion uh to adopt

10:05staff findings for our consent items?

10:09>> Motion. All right. Is there a second?

10:12>> All right. Any discussion? All in favor

10:15of adopting our consent items, say I. I.

10:17Opposed. Absentions.

10:19>> All right. Those are adopted. If you

10:20were here for items five, six, or seven,

10:22uh, those are passed. Good luck with

10:24your projects.

10:26All right. Now, we'll move uh to item

10:29number four. And staff is Andrew Fence.

10:53Good afternoon, Chair Meyer and

10:54commissioners. Uh before you today is an

10:56application for a reasonzoning and site

10:58plan review to allow the construction of

11:00a new four-story mixeduse building with

11:0218 dwelling units and approximately

11:042,000 square ft of commercial space at

11:073561

11:0844th Street West and 4409 Chowan Avenue

11:11South. The subject property consists of

11:14two parcels at the southeast corner of

11:1644th in Chowan. Um 356144th

11:20Street West is currently developed with

11:22a singlestory auto repair use and 4409

11:25Chowan is currently developed uh with a

11:27duplex. The property includes a narrow

11:29strip of land that extends out to 44th

11:32Street. That's what's uh that that uh

11:34sort of narrow flag in in red on the

11:36right there. Um

11:39uh and that's that constitutes one half

11:41of a shared driveway that's used by

11:43seven properties on this block. Uh the

11:45shared driveway functions much like a

11:47public alley but it is not public right

11:49ofway um and is instead uh private

11:52property um and the shared driveways

11:54established by private easements. Um the

11:57applicant is proposing to demolish both

11:59of the existing buildings and to

12:00construct a new four-story mixeduse

12:02building with 18 dwelling units and

12:04about 2,000 ft of commercial space. All

12:06of the proposed units would be two bed,

12:08two bath units. Um the commercial space

12:11would be oriented um towards 44th Street

12:14while the residential entrance would

12:15face Chowin. Um

12:19uh there would be an 18 space uh parking

12:22garage on the first floor accessed by a

12:24single curb cut on Chowan. Um there'd be

12:26a total of 24 long-term bikes bike bike

12:29parking spaces um and four short-term

12:31spaces um in the Chowan Avenue right

12:34away. Um the building has been designed

12:36to have a zero lot line uh urban street

12:38wall adjacent to 44th Street. Um and

12:40then on the Chowan frontage to

12:42transition between that um kind of

12:44commercial context and built form to the

12:46residential context of the neighborhood

12:48interior to the south with a series of

12:50steps uh back as as you move south along

12:53Chowan. Um the building would be clad

12:55primarily in brick um adjacent uh to um

13:00to the street where it presents a

13:02traditional street wall. Um and then on

13:04the interior elevations, it would be uh

13:06primarily burnished block at the first

13:08floor. Um and then uh stucco on the on

13:12the upper floors. Um in addition to the

13:16uh site plan review application and

13:18resoning that are before you today, the

13:20project also requires two administrative

13:23F premiums. Um the project as proposed

13:25is meeting the F premiums uh for

13:28mixeduse residential and commercial um

13:30as well as for enclosed parking.

13:34the uh 35 um 61 uh 44th Street parcel is

13:39located in the corridor 2 mixeduse

13:41district. That's a commercial zoning

13:43district. Um while the 4409 Showan

13:46parcel is in the UN3 urban neighborhood

13:48district both of these parcels are in

13:50the corridor 4 built form overlay

13:52district. Because these properties are

13:54in different primary zoning districts,

13:56in order to allow their combination and

13:59their development together as one

14:01project, um the SZ split zoning overlay

14:05district needs to be added uh to the

14:07properties to allow that. Um the SZ uh

14:10district defines the conditions under

14:12which properties with different zoning

14:14designations can be developed together.

14:16Um and lays out how um uh conflicting uh

14:22zoning regulations between those primary

14:24districts are are dealt with. Um so in

14:26this case they are proposing that

14:27resoning to add the split zoning

14:29overlay. Um and by adding the split

14:31zoning overlay here, they're allowing

14:32the properties to be developed together

14:35um while maintaining uh the existing

14:38boundaries between the commercial zoning

14:40and the residential zoning on the site

14:41and in the neighborhood. Um these

14:43applications were previously continued

14:46from uh the October 24th meeting. Um I'm

14:49sorry, the August 24th meeting. Um the

14:52purpose of that continuence was to allow

14:53for the applicant to make some changes

14:56uh to accommodate the building's

14:57transformer uh while complying with both

15:00um the uh driveway easement that's in

15:02place as well as the required yards. Um

15:05the proposed building footprint has been

15:07reduced slightly from what was first

15:09before you um to accommodate that

15:11proposed transformer near the northeast

15:13corner of the site. Um there have been

15:15several sets of public comments that

15:16have been received regarding this

15:18project. Those are all included um in

15:20your packet. Um and I'm happy to go into

15:23detail on any of the required findings,

15:25alternative compliance um or conditions

15:27of approval, but staff is recommending

15:29approval subject to the conditions lift

15:31listed in the staff report. Um and I'm

15:33happy to address any questions. Thank

15:34you.

15:36>> Thank you. Uh first I want to note that

15:37the website is down for us. Um

15:40Commissioner Shepard was smart enough to

15:41download everything beforehand. So if

15:43commissioners want to take a peek at his

15:45laptop, they can. But I believe Kimberly

15:46is going to try to I'm almost certain

15:49this email is not going to go through to

15:50you. Um I'm going to try, but if you're

15:53logged in with your city email

15:54addresses, I may be able to give it to

15:57you through SharePoint. Um I'll be

16:00working on that.

16:01>> Okay.

16:02>> Uh in the meantime, I'm hitting send

16:03right now, but it's 32 megabytes and I

16:05don't expect you to receive it.

16:07>> Okay. Um, so I I do have a question and

16:11it might be for the applicant as well,

16:13but so this was a gas station at a time

16:16when leaded gasoline was used. So I just

16:19want to understand, you know, is there a

16:22lot of pollution in the soil there? And

16:24if if so, what is being done to mitigate

16:26that so that it's, you know, lead gets

16:29in the soil and um I'm just concerned

16:31that during construction could get into

16:33the houses nearby and what what's being

16:34done to mitigate that?

16:36>> Sure. Uh thanks for the question, Chair

16:37Meyer. Um uh dealing with um existing

16:41contamination on a site is not something

16:43that's regulated by the zoning code or

16:45something that we uh require

16:47documentation of at at this stage in the

16:49process. Um there are um standards for

16:52environmental investigation that include

16:54soil testing and vapor monitoring um

16:57that are out there. Um and then uh you

16:59know if there are issues there's you

17:02know mitigation that can be required. Um

17:04in some situations uh the environmental

17:07health group in uh at the city you know

17:09conducts review of that and and monitors

17:11it it during construction. Um at this

17:13point you know maybe the the applicant

17:15may have information to share about what

17:17they know about the soil conditions on

17:18the site but um that's not something

17:20that uh the zoning code regulates or

17:23that we we require information on at

17:25this point.

17:25>> Okay.

17:27Commissioners, do we have questions

17:28before for staff before we move to the

17:30public hearing? Commissioner Shepard,

17:32>> just a few. Thank you, Chair Meer. Um,

17:33thank you. The presentation that the

17:35documents say that the transformer

17:37location shown is not properly screened

17:39on the submitted diagram. So, is that

17:41something which has been rectified?

17:44>> Uh, uh, Commissioner Shepard, no, it

17:46hasn't. That's a recommended condition

17:48of approval. Um, so that is um,

17:53>> it's on page 14.

17:54>> Condition. Yeah. Uh, condition number 10

17:56on site plan review is is requiring that

17:58they add appropriate screening

18:00>> as well as a lighting plan and I believe

18:02we had us to move some short-term

18:04bicycle parking and those are still

18:06conditions.

18:06>> Yes, those are all recommended

18:07conditions of approval.

18:08>> Thank you.

18:09>> Y

18:11and the email did go through. So, check

18:12your inboxes if you need to to access uh

18:15the the application.

18:18>> All right. Any other questions before we

18:20proceed to the public hearing? All

18:22right. Thank you.

18:24So I will open the public hearing. Do we

18:26have the applicant with us?

18:29>> Question.

18:29>> Are you the applicant?

18:31>> No.

18:31>> Okay.

18:33>> Go ahead. Welcome. If you'd like to

18:35present your project, you can have 10

18:38minutes.

18:40>> Okay.

18:44>> Hi. Good afternoon. Uh Evan Williams, uh

18:46one of the owners of Elliot Capital

18:48Group, the developer. Um as uh Mr.

18:52friends already presented. Uh this is a

18:54project we've been working on for almost

18:562 years now uh with the seller. Um and

18:59so you know pleased to present this

19:01today. Our four-story mixeduse building

19:04with 18 units, 18 uh enclosed uh garage

19:07parking spaces, 2,000 square ft of

19:10retail commercial space on 44th. Um and

19:15um yeah, so just excited to uh to be

19:18able to present this to you. We think

19:20it's uh you know um this particular area

19:23in Lynen Hills, I know it's been

19:25wellreceived the additional retail space

19:27that's there. It's a very hightraic

19:28area. There's lots of other great um

19:31small businesses there, you know, coffee

19:33shops, restaurants, um other retail

19:36stores, and so we think this will be a

19:38very positive benefit. Um the building

19:40itself is uh you know, I would call it

19:42kind of a medium density building. It's

19:45um you know, we could have added more

19:46units, but we wanted to be respectful of

19:49trying to keep uh a parking ratio as

19:51close to possible with the with uh the

19:53number of units that we're uh building.

19:56So, it's a 1:1 ratio to provide uh

19:59people with um ability to park uh

20:01vehicles off the street. And we've also

20:04added um uh as uh Andrew mentioned 26 um

20:10parking or bike stall bike uh stall

20:14spacing. Uh so that's um over and above

20:17what we were required to to include in

20:19the bu in the building. Um

20:23and um yeah uh you know it's a

20:26four-story building. We think the mix of

20:28materials that we're using also

20:30corresponds well with the general area.

20:32It's a lot of brick that we're using.

20:34Um, everyone has outdoor patio space,

20:37um, which we think is great. Lots of

20:39natural light, um, you know, large

20:41windows, and so we think it's a, you

20:43know, it'll be a a great addition to

20:46this particular area in Lynen Hills.

20:49>> Thank you.

20:50>> Thank you. Any questions?

20:52>> Yes. So, are you familiar with this

20:55status of the soil on the site? Are

20:56there any lead issues with it? We have

20:59done a um I think we've I believe we've

21:03done a phase one. There was a soil

21:07contamination back in the 90s. Uh, which

21:10I do still I have all the paperwork from

21:11the seller on that that um I cannot

21:15remember the government agency that

21:17comes out and handles that cleanup, but

21:19they they send a satisfaction letter

21:21that everything was uh corrected and you

21:24know really it's just kind of a

21:25continuation of like monitoring um it.

21:29>> Good. I'm glad that's being monitored

21:31and and addressed. And then did you say

21:35like if if you built less parking that

21:38you could build more units?

21:42>> Um no, we we we could have added

21:44additional density, but we wanted to um

21:48we wanted to provide as much uh we

21:51wanted to keep the parking as close to a

21:531:1 ratio as possible. So 18 uh

21:57residential units and 18 parking spaces.

21:59So, but if you had chosen to build fewer

22:01parking spots, you could have built more

22:03units. Is that right?

22:04>> Yes. Or we could have just uh uh chosen

22:08to make smaller units.

22:09>> Okay.

22:10>> Mhm.

22:10>> All right. Those are my questions. Other

22:12commissioners.

22:15>> All right. Thank you.

22:15>> Okay. Thank you.

22:18>> All right. Anyone else would like to

22:20speak?

22:21Come on up. You have two minutes. And

22:24introduce yourself.

22:26Can I have the remainder of Evans 10

22:28minutes?

22:30>> Uh, no. We give the applicant extra time

22:32to explain their projects, but each

22:33subsequent speaker gets two minutes.

22:35>> Okay. All right. Um, I'm Chris Murphy. I

22:37am an owner of a five-unit building on

22:39the same city block that uh the

22:42development is proposed on. Um, I am not

22:46I provided a lot of input. I've

22:48corresponded with Andrew a great deal.

22:50I'll just assume that everybody's read

22:51that in detail. Um, but I would like to

22:55lend some further credibility to it

22:56hopefully by way of some added comments.

22:59Just focusing in on a few things. Before

23:01I do that, I want to say that um I don't

23:04object to the development. I'm fine with

23:06the development per se. I'm pro density.

23:09I hope that it is ultimately a success.

23:11But by virtue of experience that I have

23:14had with that five-unit building on the

23:17same city block and immediately adjacent

23:19construction, I've spent the better part

23:21of 3 to 5 years of my life cleaning up

23:23after that, including damage, including

23:26uh variance applications for

23:27transformers. All of my input has been

23:30in the vein. I hope to avoid that this

23:33time. I'm trying to help. In fact, um,

23:35this was supposed to initially have been

23:37heard, I believe, on August 14th

23:40thereabouts, and it would have come

23:42before you, and it would have said that

23:44the planning department approves it. And

23:46that approval would have occurred

23:47without any knowledge whatsoever of the

23:50private alley easement that exists on

23:53that property and several adjacent

23:55properties that that use that alley

23:57space. And I brought that to everybody's

23:59attention, to Evan's attention, to Ad's

24:01attention. I think I'm doing merely the

24:03same thing here with a a raft of

24:05questions. If you've read it, you've

24:07seen them that have to do with property

24:09rights, storm water uh handling, and in

24:12particular the the current placement of

24:14the transformer, which I don't think is

24:16viable. So, let me just kind of read

24:18through my notes as quickly as I can.

24:21Um, I think the pad transformer has has

24:24issues. I don't know if I can place

24:26things here, but you would have seen the

24:27input in in some of the written

24:29comments. Excel can't stand in a pool of

24:32water and hot stick a pad transformer.

24:34Furthermore, it's it's a a public safety

24:36issue because traffic drives a foot away

24:39from that transformer. In fact, pulls

24:41out towards it. I don't know that that

24:43has been addressed. If Excel mandates

24:45there need to be ballards to protect

24:47that transformer. There is no place to

24:49put them because it sits today that the

24:52transformer sits squarely on the private

24:55alley easement. There's no room to put

24:57ballers in front of them. I've got more

24:58to say, but I'll stop in respect of the

25:00time that I'm

25:00>> I have a question. So, you that'll give

25:03you some time. Um, so I I thought that

25:06after the continuence and after the

25:08changes that were made to that that that

25:09was addressing the concerns that you

25:11brought up and thank you for for

25:13bringing those up, but are are you

25:14saying that your

25:16concerns are even with the condition

25:18that's been added?

25:20>> That's correct. the the plan that would

25:22have come before you on the 14th of

25:24August had the pad transformer sitting

25:28in a private alley easement. encroached

25:31upon that space and again I'm not trying

25:34to find find fault I'm trying to help so

25:36that there is a better outcome than the

25:38other experience that I've had and I

25:40said hey there's a private alleyman I

25:41had to go on to prove that doing my own

25:43research on recordies to show that it

25:45exists providing my own title to the

25:47five unit building that I've mentioned

25:49the result of that was indeed to move it

25:51out of the private alley easement uh in

25:54my opinion Evan unfortunately lost some

25:56space in so doing I don't think that the

25:59current position is still supportable. I

26:02don't think that the property rights

26:04support it. I'm not sure that the public

26:05safety concerns support it. I'm pretty

26:08sure Excel won't support it when they

26:09see the actual picture that you will

26:11have seen which shows a virtual lake

26:15well within the 10-ft space required by

26:18Excel to do maintenance on a on a pad

26:21transformer.

26:22>> And what is the remedy you're seeking?

26:24the remedy I'm seeing I'm sorry I don't

26:26know if I know how to use this correctly

26:27but I have a photo here of a pole

26:31transformer that was put in place about

26:34now I've lost track but about 2 three

26:36years ago as a result of having to

26:39appeal a variance application on an

26:42after the fact request for a variance

26:44for a pad transformer that Excel put on

26:46the ground um this is a brand new

26:49three-phase pole transformer um by way

26:53of the research that I'm capable of

26:54doing. I'm not an Excel employee. I'm

26:57not an engineer, but it seems that this

26:59doesn't have the capacity to support the

27:01new uh property that is adjacent to me,

27:05but can be upgraded a and in and the new

27:09property that's being proposed as well,

27:10but can be upgraded to do so. That

27:13photo, and I'm sorry if I'm not using

27:14this right, but that photo shows the

27:17pole transformer about

27:204 ft north of where the pad transformer

27:23is being proposed. Okay, thank you.

27:27All right. Are there any other speakers?

27:33Welcome. Come on up. Introduce yourself

27:36and you have two minutes. Y Thank you.

27:42Hello, I'm Martina Sagai. I'm a co-owner

27:45of the uh property in question that

27:48utilizes the easemen. Um, and I

27:51previously lived in one of the apartment

27:52units for 15 years. Uh, I echo the prior

27:57comments regarding the concerns

27:59surrounding the easement and what I

28:01believe is a reasonable request that the

28:05commission place conditions on the

28:07approval conditions that uh are beyond

28:10uh that uh expressed by staff.

28:14Um, similarly, I have no objections to

28:17the proposed development, but merely

28:18requests that parameters be put in place

28:21to ensure the construction does not

28:23impinge on the existing rights of the

28:25alley easement users. The private

28:28easement was created a 100 years ago for

28:30vehicular access. A proposed pad

28:33transformer should not constrain that

28:35access in any way, nor put alley users

28:38at risk. Similarly, the potential for

28:41added storm water runoff in an alley

28:44that already has significant drainage

28:45issues suggests that the planning

28:48process does not fully weight the

28:50development's impact on the current uses

28:53of the alley. Both the pad transformer

28:56and storm water concerns appear

28:58remediable.

28:59I'd like to understand if the developer

29:01has taken any steps to engage Excel on

29:04pole transformer discussions and whether

29:06the developer has plans to address or

29:09participate in resolving the alley

29:10drainage issues.

29:14You know the concerns do not center

29:15around the usual you know height of the

29:18building or uh you know sunlight is you

29:21know impacting the or the character of

29:24the you know building is not suitable to

29:25the neighborhood. This actually is about

29:29private uh it it impacts private

29:32property. So while I understand it is

29:35not the commission's perview to assess

29:37or interpret private easements, any

29:40action taken by the commission with

29:42knowledge that it may impact existing

29:45private rights can only be construed as

29:47a conscious decision by the commission

29:49to favor a new development over the

29:52rights of existing property owners and

29:54renters. At a minimum, the commission

29:57should place appropriate conditions

29:58should it vote to proceed with approval

30:00of the development.

30:02>> I do have a question for you. So, you're

30:04saying appropriate conditions. Do you

30:05have a specific condition that you would

30:06like us to consider?

30:07>> Um, I would refer the commission to the

30:11uh written input provided by the prize

30:14speaker.

30:15Um, uh he laid out uh in a specific

30:19section the recommended suggestions uh

30:22uh recommended conditions for approval.

30:23I'm happy to reiterate it. Um, but it is

30:26in written form.

30:29It was submitted to staff.

30:30>> Okay. Thank you.

30:32>> Are there any other questions?

30:34>> I don't see any hands raised. Thank you.

30:37>> Thank you.

30:38>> Next speaker, if there is one.

30:43All right. Um, not seeing any. I'm I'm

30:47going to leave the hearing open just in

30:48case we have questions. Um um Andrew,

30:52can you um come up and tell us um

30:56your thoughts on the testimony that we

30:59heard and if there's a condition that

31:01might satisfy them?

31:15>> Uh yes, Chair Meer and commissioners. um

31:18you know when it comes to

31:21transformers and and their placement um

31:24you know the the city we do our best to

31:27work with XL and we reach out to Excel

31:30to um try to get ahead of of issues um

31:34and you know I'm very appreciative of uh

31:38of Chris bringing information uh to our

31:41attention in August um you know related

31:44to the the shared driveway here um and

31:47us, you know, having the development

31:49team make changes to the building

31:51footprint to accommodate the transformer

31:53outside of the easement. um at that

31:56time. Um the the concerns that um have

32:01been raised about the transformer

32:04potentially being hit by vehicles um

32:07that are exiting the easement and and

32:10going onto the private property or about

32:12Excel having concerns about um the the

32:17the

32:19drainage in the in the shared driveway.

32:22Those are concerns that I think um a are

32:26are not things that are regulated by the

32:29zoning code or the site plan review

32:31standards um and and b are resolvable

32:35through

32:37um through through grading and through

32:40work with Excel that and very likely

32:42would not require changes to the

32:44building footprint. Um when it comes to

32:47the the drainage concerns,

32:50um uh final grading and drainage is

32:54reviewed primarily by public works

32:56surface water and sewers. They do that

32:58as part of the PDR process. Um Chris uh

33:01very I think I think accurately and I

33:04also appreciate this uh you know

33:05identified um that their proposed

33:08grading plan um does not have uh

33:11positive drainage the entire way around

33:12the building. there is an area um at the

33:15southeast corner of the property um that

33:18does not drain, you know, as as shown on

33:20their on their grading plan does not

33:22drain to the alley easement or sorry, a

33:26shared driveway um and then out to 44th

33:29Street. It would drain onto the adjacent

33:30property to the south. Now, that's a

33:32parking lot that, you know, very likely

33:33goes across, but um that was that was

33:35helpful feedback and I I flagged that uh

33:38for the PDR reviewer from Surface Waters

33:40and Sewers. But ultimately, you know,

33:42the the review of the final grading here

33:46is in is in the purview of public works

33:49surface water and sewers. It's not a

33:52site plan review standard.

33:53>> Okay. Thank you,

33:56commissioners. Are there any questions

33:57for staff or anyone or anyone else

33:58before I close the hearing?

34:01>> All right. Thank you. I'll close the

34:04hearing. Um

34:08I I'll give some general thoughts.

34:09First, first I think this is a a a great

34:11project. It looks good and want to point

34:14out that it's right next to the Eline.

34:16Um so I think it'd be nice if you chose

34:20to put in fewer parking spots and more

34:22units, but um

34:26you still like the project and I think

34:30um you know the zoning and the um

34:35the other things on it are are pretty

34:36straightforward. Um, I'm inclined to go

34:39with the staff recommendation. Um, you

34:41know, I think they're they're valid

34:42concerns that people have brought up. It

34:44just doesn't seem like it's in our uh

34:47purview today, but those are things that

34:49would come up with um with the grading

34:51with with Excel. Um, so my position

34:55would be to adopt staff findings today.

34:58Um, any other thoughts from

35:00commissioners?

35:04Would anyone like to make a motion?

35:10Um, I'm happy to move staff findings as

35:12it relates to uh item number four.

35:15>> All right. Is there a second?

35:18>> We have a motion to second. Is there any

35:20other discussion?

35:24All right. Not seeing any. So, I'll ask

35:26staff to please take the role.

35:29>> Commissioner Chowry.

35:30>> I.

35:32>> Connley.

35:33>> I.

35:34Sheepard. I

35:36>> Vice President Wagner

35:37>> I

35:38>> and President Meyer

35:40>> I

35:40>> there are five eyes.

35:42>> That is adopted. Thank you everyone for

35:44coming. So that concludes our business

35:45for the day. Um our next uh planning

35:48commission will be October 13th. It's a

35:51big one. We're going to have the

35:53discussion on data centers. So bring

35:56snacks and diapers and anything else you

35:57need.

36:00We have asked for the captioner to stay

36:02until 8:30 that night. Um, we are

36:05expecting a very [laughter] large public

36:07turnout. Um, so do plan accordingly. Um,

36:13with the timeline with the moratorum, we

36:15cannot continue that item at planning

36:17commission. We need to get that through

36:19the commission on the 13th.

36:21>> Great. And then we do also have

36:23committee the whole this Thursday.

36:25All right. Any other updates from staff

36:27or commissioners? Could I just ask

36:30what's what are the topics covered at

36:32committee of the whole on Thursday?

36:35>> Yes, the two items we have one project

36:37discussion and one zoning code text

36:39amendment. So the project discussion is

36:42for a proposed six-story 185 unit

36:44building at 2825 Cedar 185128th Street

36:48and 185528th Street East. And then we

36:52have the 1 to3 amendment which had been

36:55previously scheduled for a committee of

36:56the whole meeting and then was

36:58rescheduled. Um

36:59>> good.

37:00>> So you'll be seeing that as well.

37:03>> Great. All right. Not seeing anyone

37:06else. So we are adjourned. Thank you

37:07everyone.