2026-09-28 - School Building Committee 13
Summary
Based on auto-generated captions; names and figures may be misheard.
- Met remotely with 12 members present. Approved the minutes of the August 17 meeting by roll call after correcting the date on the agenda.
- Schematic design schedule: the feasibility phase is wrapping up with a Massachusetts School Building Authority (MSBA) facilities assessment meeting on Wednesday, September 30, and board approval of the preferred schematic report at the MSBA's October 28 meeting. Schematic design is about a six-month phase ending in February 2027: the pricing set goes to the cost estimator January 12, estimates are due February 5 and reconciled around February 10, the committee and School Committee vote on the budget, and the submission to the MSBA is due February 24 for review at its April board meeting.
- Meeting dates: to avoid school vacation week and a holiday, the committee moved its final vote meeting from February 15 to Thursday, February 11, and shifted other meetings to Tuesday, January 5 and Tuesday, February 2. Monthly agendas run from facade and site design in November through interior images, building systems and the mobility study to the pricing set review in February. The next meeting is November 2.
- Energy modeling: the design team will begin energy-code modeling next month. A member asked whether this rules out a passive house approach; the team said it is not ruled out and the committee will discuss the findings before deciding.
- Mass timber: the team is studying mass timber, meeting with city staff and construction managers and collecting regional cost and risk data on first cost, carbon, and operation and maintenance, before bringing a recommendation back.
- Traffic and community engagement: a transportation scoping memo has been reviewed by the city's mobility team, traffic counts begin within the week, and an impact study covering pedestrians, bicycles and transit goes to the mobility team in February. The team has attended the back-to-school fair, Civic Day and the Ward 4 neighborhood meeting, with Wards 5, 3 and 6 coming and a community forum planned for early November. Feedback repeats earlier themes (storage for community programs, community access to outdoor play and shared spaces, field seating) plus a splash pad, organic paths and storage for community bikes and toys. Children again voted the tall climbing structure their favorite play structure. Meetings with teachers, abutters and first responders are planned.
- Reduced parking garage option: a garage under the building cut to 50 spaces would still carry most of the cost of the larger one (extra elevator stop, two stairways, ventilation areaways), with deep excavation along Sycamore Street and the neighboring church property line, possible ledge, and drainage pumping. The cost estimators put it at $320 per square foot for about 26,000 square feet, roughly $8.3 million, or about $166,400 per space. The earlier larger garage, of nearly 100 spaces, was priced at about $15.5 million, and the site's excavation risk has since grown. Members said the decision should come soon because costs are most flexible now; one disliked the double 90-degree turn at the Medford Street entrance, which the team agreed is a challenge. A member asked the city to approach the Archdiocese about an easement or a piece of land along the property line, including for a transformer; the city representative agreed to reach out.
- Trees: after a site walk with the city's urban forestry and DPW arborist team, four large trees on Medford Street and four at a corner of the site will be protected during construction, and the city also wants two more on the north side of Evergreen saved, which the team is not sure it can do because of deep excavation. A planting plan is due to the tree team at the end of October.
- Design update: the plans are largely unchanged. Rearranging classrooms in the south wing shortened it and saved about 3,000 square feet. The MSBA requires showing 10 percent expansion potential, about five classrooms stacked above the lowest level out of roughly 47; the team said it is not proposing an addition. The design includes a usable rooftop green space over the lower kindergarten level. Two physical massing models of the building and neighborhood are being built. The educators had not yet seen the design in focus groups.
- No public comment. The committee adjourned by roll call.
Issues discussed
Sources
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:08Thank you.
00:10Um Sean, no I did I'm not aware that you
00:13missed anyone.
00:15>> Uh so we have 12 members present.
00:17>> Excellent.
00:19Um good evening. I hope all staying dry.
00:23I'm glad this is virtual. Um, our first
00:28item on our agenda tonight, uh, or I
00:30guess I should say our second is a vote
00:33to approve the meeting minutes of the
00:35August 3rd, 2026 SBC meeting.
00:42I'd be happy to entertain a motion to
00:44vote or we could discuss.
00:46>> Move to approve as presented.
00:48>> Thank you, Rich.
00:49>> Second.
00:50>> Thank you, Courtney.
00:53Uh is there any discussion on the topic?
00:59Okay. Uh I move to well I will
01:04move forward to call the vote. Uh Sean,
01:06could you help me with the roll call for
01:07that?
01:09>> Yes. Um so all for the meeting minutes
01:12from 8:17. Emily
01:14>> from 83.
01:16>> Is it 83?
01:20The date wrong. I might get another one.
01:24At least that's
01:25>> August 17th.
01:27>> Is it August 17th?
01:29>> Yeah.
01:30>> Then we have it incorrect on the agenda.
01:34>> Unless it's both, but I don't think so.
01:38>> The agenda I'm looking at says August
01:3917th.
01:40>> Okay. My apologies that I'm looking at.
01:43>> I could have an old one.
01:45>> Yeah. No, no, no. That's fine. Um, so
01:47I'm Let's go through this procedurally
01:48because I don't want to get dinged by
01:50open open meeting. Um, may I entertain a
01:54motion to uh take to approve the meeting
01:58minutes from August 17th, 2026.
02:07>> Rich. Yes.
02:08>> Yes.
02:10>> Seconded.
02:11>> Excellent. Thank you so much. Okay. Any
02:13discussion on
02:15>> the 17th? August 17th.
02:18>> Okay. Hearing none. Sean, could you help
02:20me uh with roll call for the vote for
02:22the August 17th meeting minutes?
02:26>> Yes. Uh Emily,
02:28>> yes.
02:29>> Rich R.
02:30>> Yes.
02:32>> Ruen.
02:36>> Yes.
02:37>> Uh Cy Gossson.
02:40>> Yes.
02:42>> Ed.
02:44>> Yes. Chris,
02:46>> yes.
02:48>> Eric,
02:50>> yes.
02:52>> Kathleen,
02:53>> yes.
02:54>> Jesse,
02:55>> yes.
02:56>> Siraj,
02:58>> yes.
02:59>> Courtney K,
03:01>> yes.
03:03>> And Rich H.
03:04>> Yes.
03:06>> All right. All four.
03:09>> Okay. Um,
03:11motion passes. and I have the correct uh
03:14agenda up. So, thank you for bearing
03:16with me. It is certainly a Monday. Uh
03:18the next item is to review schematic
03:20design schedule and work plan. And Lisa,
03:23I'm going to pass it off to you.
03:25>> Great. Thank you.
03:38All right.
03:40Good afternoon, everyone. It's been a
03:42little while since we've got together.
03:45So, um, yeah. So, the full agenda
03:47tonight is to, uh, review the schematic
03:49design work plan. We're going to, uh,
03:51provide a community engagement update,
03:53present the res, uh, the reduced, uh,
03:56parking garage option, as well as, um,
03:59look at the existing, uh, tree review
04:02uh, that we had with the, uh, with the
04:04city. And then we'll do a quick design
04:07update.
04:10Uh, So the past year was focused on
04:13feasibility study. Uh the final stages
04:15of this phase uh includes the meeting
04:18with the MSBA facilities assessment
04:21committee which is on Wednesday and then
04:23the approval of the PSR at the MSBA's
04:27October board meeting. Um however we've
04:30uh started to work on the next phase uh
04:32which is schematic design. This is about
04:35a six-month process um that will be
04:37completed in February of 2027.
04:43So, uh this is our schematic design work
04:45plan. Um and I'm just going to start at
04:48the top uh with the um community
04:50meetings. So, we've already attended a
04:52few community events over the past
04:54month. Uh at this time, we're scheduled
04:56to be at the upcoming uh neighborhood uh
04:59ward meetings. Um, and then we're uh
05:02planning a community forum sometime in
05:04early November. Um, and then we'll um
05:08more events I'm sure will follow as we
05:10progress through uh schematic design.
05:14We're going to uh continue our uh
05:16monthly meetings with the school
05:18building committee. Uh my next slide
05:20will um propose a few dates and agenda
05:23uh for these meetings and then we can um
05:26vote on that or discuss that at the end.
05:29see if it all works. Um we are working
05:33with the city's mobility team to develop
05:35solutions for circulation and parking.
05:38We have um completed the transportation
05:41scoping memo um which has been reviewed
05:44by the mobility team. Uh and our uh
05:47traffic consultants will uh begin
05:50existing condition uh traffic studies
05:52within the upcoming week. Sorry. Uh once
05:56the data is collected, then we'll work
05:59with the city's mobility team to develop
06:01a comprehensive impact study. Uh this
06:04will include uh pedestrians, bicycles,
06:07and uh transit. Um the study will uh be
06:11formally submitted to the mobility team
06:15in um February of next year.
06:19So uh a long process um but a lot of a
06:22lot of things to look at and consider.
06:26All right. Um, so during uh schematic
06:28design, we'll be meeting with the
06:30teachers to discuss educational needs
06:32inside the classrooms and also in other
06:35uh specialty spaces throughout the
06:37schools. So those are going to kick off
06:38soon. Uh when we met with the planning
06:41board, they asked us to hold some
06:43neighborhood uh meetings with the
06:45abutters to keep the neighbors uh
06:48informed throughout the process. Uh so
06:50we'll be setting those up.
06:53Um and uh we'll also um have more
06:55meetings with the city's uh first
06:57responders uh during this phase of work.
07:01So um down here at design, the uh
07:05schematic design focuses on the design
07:07of the exterior interior of the
07:08building. Uh our consultant team will be
07:11heavily engaged in developing drawings
07:13and system narratives for the robust
07:16schematic design pricing set that will
07:19be submitted to the MSBA.
07:22We'll begin with um we'll begin Teddy
07:24modeling next month to confirm the
07:26compliance with the energy code and
07:28develop um or begin to develop the most
07:31energy efficient approach for the new
07:33school. Um then we'll be looking at uh
07:36exterior and interior materials so we
07:38can develop our outline specifications
07:40for pricing.
07:43We'll need to continue our work on
07:45environmental and uh geotechnical site
07:48assessment to confirm the scope of the
07:52um subsurface conditions. Whoops. Sorry,
07:54I advanced too much too quickly. Um
08:00all right, lost my place. Um so, uh and
08:03then uh after that the um all this
08:06information is going to be packaged
08:08together. The schematic design pricing
08:10set will be uh submitted to the cost
08:12estimator in January on January 12th.
08:15The estimates are due on February 5th.
08:18Uh we'll reconcile the estimates around
08:21February 10th and then present the
08:23budget to the um to the SBC and the
08:25school committee on February 15th uh for
08:29a vote to submit the project to the
08:31MSBA. Uh so the submission to the MSBA
08:34would be due on February 24th uh for
08:38review and approval at that April board
08:40meeting. So that pretty much maps out
08:43the um the next few months. Any
08:47questions before I move on?
08:56>> You do you do have a hand up.
08:58>> Yep. Do you want to start with I think I
08:59see Courtney's hand up.
09:02Yeah, just question on um the note about
09:05Teddy modeling. Did that mean you've
09:07determined you're going the Teddy
09:09approach and not passive house?
09:11>> Um well, it's our first start to see if
09:14the if we're able to um make the um meet
09:20the requirements of the Teddy model. Uh
09:22but it's not 100% determined that we
09:25that we won't take a passive house
09:26approach. Um Dan, I don't know if you
09:29want to add to that. [snorts]
09:31I think that that's true. Um,
09:35>> is that something we'll be disc I'm
09:37curious to um have an opportunity to
09:40hear more about that as you're getting
09:42getting there? I have seen studies local
09:45studies done that passive house approach
09:47gets to better outcomes even if they're
09:50both acceptable models um to use for
09:55high performing building modeling. So
09:59you might have different D I see you
10:02might have a different take on it. Um
10:04and I could share with you what I
10:06learned last year.
10:07>> Yeah, I mean I think a conversation
10:08about it would be good. So we'll get
10:11we'll we'll note that we will um start
10:15that modeling and we'll have a
10:16discussion about what we find before we
10:20make any final decisions.
10:24>> By doing the Teddy modeling, are you
10:25then
10:27is it a
10:29Are you including it by not doing the
10:32wolfy model for passive [clears throat]
10:33house also?
10:34>> No. No.
10:36>> Okay.
10:39>> Okay.
10:40>> Very good.
10:41>> Lisa, you may have already said it and I
10:43I didn't hear it. I apologize. You are
10:45on the FAS agenda for this week.
10:48>> Yep. Uh it's um on Wednesday the 30th
10:51and I think it's like a 9:25 meeting. Do
10:53I have that right, Sean?
10:55>> 9:30. They just want us to log in at
10:579:25 for technical issues, but the
11:00meeting starts at 9:30.
11:02>> Thank you.
11:03>> If anyone has any issues registering for
11:05the meeting through the MSBA, um if you
11:07if you're registering, you you will have
11:09already known that you are to be at the
11:11meeting, uh just let me know and I can
11:12help you through that process. You
11:13should have got an email from Claire
11:14last week.
11:19>> Very good. Um any other questions that
11:20I'm not able to see or
11:23No. Great. I will move on to the next
11:26thing. Um so
11:30these are the suggested meeting dates uh
11:32for the upcoming uh school committee
11:35meetings. Um the agendas uh just
11:38starting with uh November uh we'll
11:41review preliminary facade design and
11:44exterior some uh preliminary exterior
11:46materials. Uh we'll look at the
11:48development of the site design. Then in
11:51December, we're going to review the user
11:53meetings uh user meeting input. Um we'll
11:57have some updated uh floor plans and
11:59some inter uh preliminary interior
12:02materials to look at. Uh we'll also um
12:05look at building systems and uh present
12:08uh some interior images of the
12:10classrooms and breakout spaces. In
12:13January, we'll share schematic design
12:16progress and give an update on uh the
12:19mobility study. Um then present images
12:21of the uh lobby and cafeteria at this
12:24meeting. In February, we'll be um while
12:28we're waiting for cost estimates, um
12:31we'll be uh doing a review of the
12:33schematic design pricing set um that was
12:36submitted for pricing. We'll look at the
12:38room data sheets um that we put together
12:40based on the user meetings
12:43um and then we'll uh present some images
12:46of the uh media center and the teacher
12:49spaces and and then that last meeting
12:52hopefully on February 15th which I think
12:55actually might be the start of school
12:57vacation week. So that's why wanted to
13:00kind of address this early. Um, but we
13:02were hoping to be able to get uh a vote
13:04in so that we can um get everything
13:07ready for that February 24th uh
13:10submission to um the MSBA.
13:15So, I don't know if we want to come back
13:17to this at the end or if we want to stop
13:19and discuss now.
13:27So I think just to underscore this a bit
13:30um it's important for all of us to um or
13:33at least eight of us uh have February
13:3615th on our calendar um because we do
13:38not want to miss the deadline for the uh
13:40February 24th submission. So it is
13:43important for us and there there will be
13:45some obviously more meetings leading up
13:47to this but I would say of um the
13:50committee it's really critical that um
13:53you prioritize the February 1st and
13:56February 15th um meetings. Looking at my
14:00calendar, February 15th is President's
14:02Day
14:06>> would a Tuesday meeting.
14:08>> My calendar might be wrong, but
14:11>> uh and your concern is that uh the city
14:13is closed that day.
14:15>> Yeah.
14:16>> Yes. I work for a private institution
14:18and we don't get that as a [laughter]
14:20holiday. So I'm trying to figure out how
14:22to politely say that.
14:24>> I've got I've got openings, Emily. I've
14:26got openings. [laughter]
14:28It's also uh school vacation week, is it
14:30not?
14:31>> Yeah, that's what I was that's what I
14:32was concerned about it as well. Um I
14:35think what we working backwards from
14:37that February 24th date, I think we want
14:39to give ourselves a little time to
14:42collect signatures and and things like
14:44that. Um, so if there's a a good date
14:48sometime um maybe between the February
14:5211th or 12th and
14:55I don't know, maybe um February 20th
14:59um that we can that we can find. That
15:01would be great.
15:03>> Well, actually, can we can we pause for
15:04a moment? Lisa, if you could take the
15:06screen down. Let me just pull pull the
15:08crowd.
15:09>> Um you know, in terms of sort of like
15:12thumbs up, thumbs down. Um, how do you
15:14feel about having a meeting during
15:16school vacation week? Would you like us
15:17to avoid that and go a little earlier?
15:20>> Yeah, I'm seeing some nodded nodding
15:22heads. So, I want to respect people's
15:24vacation because it's few and far
15:27between. So, um, would we feel
15:30comfortable with a date that's perhaps
15:32off schedule, but let's say uh the
15:37Thursday the 11th
15:39um, to avoid the Friday. with that that
15:42that feels better. Okay. So, Lisa, I
15:45think let's let's plan for the 11th.
15:48>> Okay.
15:48>> So, we still make the target. Um it's
15:50just going to be a tighter turnaround
15:52with you for cost estimate and getting
15:54pulling stuff together, but I think that
15:57>> that's going to go a long way to make
15:59sure that we respect people's vacation
16:01time and and of course um Rich's
16:03observation of the holiday. Um,
16:05>> and for some of us, January 4th is also
16:08school vacation week still. I think it's
16:11professional development day. So, if
16:12that one could be moved up day to the
16:15fifth, that would be
16:17>> Yeah, sounds good. Superintendent
16:18Carmola
16:20>> um through the chair. So, February 1st
16:22is we have a meeting on the first. Is
16:24that is that what I heard?
16:26>> That's proposed. Yes.
16:28>> Because we we have a leadership meeting
16:30there uh that is usually from 3:30 to
16:325:30. And so Chris, so uh both
16:35principles will be tied up with me on
16:37that meeting. So um
16:40I just need to know um if that's the
16:43only day for everyone, then I have to
16:44make some arrangements.
16:47>> I think we can be flexible. Um unless
16:49I'm hearing other people um would
16:52Tuesday work better
16:57that Tuesday, February 2nd.
17:01>> That works best. Yeah.
17:03Okay. Um, others,
17:06would that work if Tuesday? Yep. Thumbs
17:07up. Okay, great.
17:10>> And then the fourth was also an issue
17:12right on in January.
17:14>> January 4th. Yes.
17:21Correct. There is no school that day.
17:25I think pull the crowd. Would do we want
17:28to move the January 4th as well?
17:32Seeing one one head nod. Yeah. Okay. Is
17:36less enthusiastic than February, but
17:38still important. Um, can we move to uh I
17:41know this is going to be a busy day for
17:42everyone. Uh, Tuesday, January 5th.
17:47Looks good. Okay.
17:51See, we we did this.
17:52>> Nice.
17:53>> Okay.
17:55>> Teamwork. All right.
17:57>> Excellent. Good. Let me steal the screen
17:58again.
17:59>> Yes. Thank you so much, Lisa, for
18:01pausing for that.
18:03>> There we go. All right. I even plugged
18:06it in while we were talking, so
18:08>> amazing.
18:09>> So, all good. Great. All right. So,
18:11that's great. Um,
18:14all right. Let's move on to our
18:16community engagement update. So, since
18:18our last meeting, we've had a we've
18:21attended a few community events. Uh,
18:24starting with the back to school fair. I
18:25think that was in late August. Um then
18:28we went to civic day and then last week
18:30we attended the ward 4 uh neighborhood
18:33week meeting. Um this week we have uh
18:37the ward 5 neighborhood meeting and then
18:39that's followed by uh ward three and
18:42ward six. Uh I believe that's later in
18:45the month. Um and then we are trying to
18:48set up a um community forum in November
18:52uh to give a project update as well as
18:56um sustain um have our sustainability
18:59and lead uh meeting on that time as
19:01well. So um so that meeting uh we're
19:04still working on a a date for that with
19:06the uh communications team. So hopefully
19:09we'll have that soon.
19:13All right. So, at uh back to school
19:15night event um where there was actually
19:18a number of community members that
19:20stopped by to get an update on the new
19:22school project. Um some people provided
19:25uh comments. Um many of the things were
19:28things that we've heard in in the past
19:30um such as um storage for community
19:34programs, um community access to the um
19:38uh to the outside play spaces and um and
19:42any shared space in the building, um
19:44seating at the multi-purpose fields. Um,
19:48a few of the new items included um
19:50discussions about uh possible splash
19:52pad, organic paths, and um designated
19:56storage for community bikes and toys. Um
20:00so we can keep looking at that um as we
20:03develop the design. We also had the kids
20:05vote again on their um their favorite
20:07play structures and the once again the
20:10tall climbing structure uh received the
20:12most votes. So that's kind of been a
20:14consistent consistent win amongst the
20:17Somerville uh kids. So they like to
20:20climb. Um civic day was also uh a
20:25successful but um very windy event. As
20:28you can see, we have bricks holding down
20:30the boards. Um even had to tape the
20:33boards to the uh to the tables. Um but
20:36uh but it was nice. A lot of people uh
20:38were at this event as well. um few of
20:41which stopped by to um you know to hear
20:43about the progress on the on the new
20:46school project. So, and then we've been
20:49tracking all of the feedback that um
20:52that we've been getting at each one of
20:53these events. Um so, it's uh nice to see
20:57there's a lot of consistencies and some
21:00few new thoughts along the way as well.
21:04All right. Um, anyone have any questions
21:07about the community events before I move
21:09on?
21:12Great. All right. Um, so we were asked
21:16to look at a reduced uh parking garage
21:19option um a few months ago. So um so
21:23here's uh here's a study that we did. Um
21:27we uh we took a look at how we could
21:29reduce the parking garage down to 50
21:32spaces. Um, so the smaller GR garage
21:36below the building um actually would
21:38still incur a lot of the a lot of the
21:41costs that we still had on the larger
21:43garage will end up with the additional
21:45stop for the elevator uh the two
21:48stairways um areaways to uh ventilate
21:52the garage.
21:53Um, in order to get the 50 spaces uh
21:57below the building, we still had a a lot
22:00of areas along uh Sycamore Street where
22:03we have very deep um excavations uh
22:06right along the property line um of of
22:10St. An's Parish as well uh which is
22:12right here. Um this is this structure is
22:15right in the property line. So, uh,
22:17we'll have to keep an eye on that and,
22:20um, what's going to be required to, um,
22:23underpin or or put in sheeting and stuff
22:26along that property line. The the deeper
22:28we go, the the tougher it is. Um, we'll
22:31also incur in incur some cost with um,
22:34pumping uh, the underlab drainage um,
22:36especially at this lower end of the site
22:38when we uh, pitch the the garage down
22:42um, uh, well below grade here. Um, so,
22:46uh, based on the review from our cost
22:48estimators, they gave us a number of
22:50$320 a square foot. So, um, this area
22:54here is, uh, 200, um, 26, uh,,000 square
22:59ft, uh, which was given us a budget of,
23:02um, 8.3 million. Um, there's still some
23:06unknowns with the, uh, the ledge removal
23:09that we're, um, going to continue to
23:12study. Um and then um obviously some
23:16other incurred cost with um with
23:18foundations and waterproofing. So we
23:21took that number and we just divided it
23:23by 50 spaces just to kind of understand
23:25the cost of what each parking space
23:27would would cost the city. Um which came
23:30up to $166,400
23:34per space. So, um,
23:40any questions on the diagram?
23:44Oh, I see, uh, Jesse has his hand up.
23:47>> Yeah, thank you, Lisa. Um, really just a
23:49question to Rich. I know I saw you at
23:51the Ward 4 event and we discussed um I
23:55know we've approached the the um arch
23:57dascese before about selling the
23:59building. I know that that doesn't sound
24:01like it's very likely, but I was curious
24:04um if if you've if you guys have talked
24:07to Rich at all about even just some sort
24:10of easement or or some sort of uh a
24:13piece of the property
24:16uh on that edge where it really comes up
24:19close to their property line. Um
24:22especially where you had mentioned that
24:24you know we're in need of a spot for a
24:26um
24:28um what do you call it? Junction box or
24:30whatever uh
24:32>> transformer.
24:33>> Transformer. Yeah. Yeah. Transformer. Um
24:35is that something that Rich can bring
24:37back to the administration to try to
24:39approach them? And would that money have
24:42to come out like would it have to be
24:44rolled rolled into this or would there
24:46could there be a
24:48like a purchase
24:50separate from this the budget for this
24:52or does it have to be included if it's
24:54going towards the project?
24:58>> Uh
25:00so uh I haven't reached out to um the
25:03arch dasis about this. I can. Um, and in
25:07terms of the the funding and financing,
25:09you know, there's any number of ways we
25:11could do it. Um, so once we understand a
25:15their willingness and b their price, um,
25:18we can then talk about how to finance
25:20it. But I I can reach out to the parks
25:22dasis and see what smaller options we
25:25have available to us.
25:26>> Yeah. I mean, I just wanted to advocate
25:28for that in in the case that the the
25:32design team wanted, you know, thought
25:34that that would be um something that we
25:38really should do um to make this, you
25:40know, project work a little better. So,
25:42I just wanted to put that out there.
25:43Thank you.
25:49>> Any other comments,
25:53>> Lisa? As we move towards pricing, um
25:55what is your intended expectation for
26:00like will this be an alternate that gets
26:02priced?
26:05>> Um
26:06from a structural
26:09design uh standpoint uh and schematic.
26:13Um I don't know, Dan, do you think we
26:15could do this continue this on as an
26:17alternate? I'm just trying to think of
26:19what challenges I might not be
26:22thinking of at this point.
26:23>> Well, it sounds like you've already
26:24priced it in order to get the per
26:25parking space cost to it. I'm just
26:29curious.
26:30>> No, and I'm wondering like as we
26:32progress through schematic design, um I
26:34mean I I
26:35>> I've got I've got to say I think this is
26:37one that has sort of systemic impacts
26:40throughout the building. it it's the
26:44site, it's the structure, it's there's a
26:46whole lot of things. So, um you know, if
26:50if we need to do more to come to a
26:54decision, we should do that. Um
26:59you know, we should have we should have
27:01a discussion about that. Um but you know
27:05I is this enough to understand like the
27:08order of magnitude
27:10costs um to then dive a little bit more
27:14into all of the implications feasibility
27:16and and the like um or does this say oh
27:19yeah this is easy let's do this or boy
27:22this is you know not how we want to be
27:24spending our our money. I think that the
27:27rough order of magnitude is
27:30you know it's rough but but it
27:34[clears throat] might be enough to
27:38understand if this is like in the
27:39ballpark or out of the ballpark and we
27:41do need to kind of uh you know provide
27:45any more information that's needed etc.
27:48I think sooner rather than later because
27:51[snorts] the this is one that the longer
27:53we
27:54carry it on um the less time we have for
27:59other things that really are important
28:01to try to understand and resolve so that
28:05that estimate for SD is as accurate as
28:08we can make it.
28:10>> Yes, I I think that makes sense. I'm
28:12going to um have comments and then I'll
28:14follow up with my own personal comment
28:16afterwards. Um Rich H Highleberg and
28:18then uh Eric, go ahead.
28:22>> Um thanks. Um I completely agree with
28:25Dan that um the first thing you do when
28:27you build a building is you dig a hole
28:29and we really need to know how big it
28:30needs to get dug, right? Because it has
28:32all sorts of implications for everything
28:33else. Um, so in order for us to make
28:36this decision, is there a number for the
28:38larger garage per total and per space
28:41and other impacts it would have on the
28:43structure so that we can just look at
28:44that and kind of figure out what we're
28:47what we're picking here?
28:50>> Yeah, I mean we we did have those um
28:53those earlier estimates uh as um at
28:57alternates when we did the uh the PSR uh
29:00pricing. Do
29:00>> you know do you know those numbers off
29:02the top of your head? I don't remember
29:03them.
29:05Um, I do not. Um, Sean, do you happen to
29:10have it in your
29:11>> I'm I'm looking for it now. I'll pull
29:13them open as we as we talk here. Um,
29:17>> I mean, there's there's obviously
29:18numbers that would speak uh to that
29:21would make it not really a decision. And
29:22then there are numbers where it would be
29:24a decision, right? Um,
29:27[clears throat]
29:29okay. Um, did someone else had their
29:32hand up while we're
29:34>> Eric, did you want to say something?
29:36>> No, I'm also next.
29:37>> Okay. Um,
29:40just just two things. Um, one of the
29:43best Well, how do I say this? Um,
29:46there's a graph that that I've used in
29:48presentations often. you know, when we
29:50think about costs, one of the best times
29:53to start um making changes or exploring
29:56ideas or also making critical decisions
30:00to to Dan's point, um you can have the
30:03the greatest cost impact at this moment
30:06in schematic design, right? As we move
30:08forward with the design, as we go into
30:10design, development and construction
30:13documents, the order of magnitude for
30:15saving money um becomes uh more
30:18challenging, right? because systems have
30:20been decided and decisions have been
30:21made. So I think as we're move for
30:23moving forward with this, I want to make
30:26sure that we're um that we're quite
30:29clear um and have these difficult
30:32discussions uh regarding these decisions
30:35now rather than um putting them off or
30:38saying that we can do them uh in the
30:40future. So, I think that's, you know,
30:42I'm not saying that we need to make this
30:43decision now, but I think this is
30:45something that I want to challenge the
30:47committee to to really lean in on and
30:50say what we need to say uh so we can get
30:53to where we are. Um, and this is a much
30:55finer point, which is I don't love the
30:58entrance of Medford Street, and I don't
31:02love that sort of 90° turn that you have
31:06to take twice um to come in or out. Um,
31:10so I don't, you know, that's just from a
31:12design standpoint. Um, I totally
31:14understand why it's there. Um, but but I
31:17think, you know, it's it's just a it's
31:20challenging and I'll just leave it at
31:22that.
31:26>> Any other comments? Go ahead.
31:28>> Just to say we don't we don't dispute
31:30that. Um, we're trying to get under
31:32under the building from as low a point
31:35as as we can. So, uh, we agree with you,
31:38Emily. Yeah, it will definitely have to
31:41be a 5 mph uh drive ramp with um
31:45probably a patience thing of one car in,
31:47one car out. Um but assuming that
31:51everyone's coming in at the at the same
31:53time and leaving at the same time. Uh
31:55the other thing that um is challenging
31:57as well with the um with the
31:59kindergarten uh prek play space down
32:03here is um that connection over to the
32:07uh um to the side of the site where um
32:10some of the um
32:13spaces we have egressing out to this
32:15little side area uh we get gets
32:18interrupted by by the ramp.
32:21Um, so
32:25I don't know if we can get it lower
32:26enough, but
32:27>> and I think while while we were talking,
32:29uh, Rich put uh the price for the
32:32previous parking in at what 15.5. Rich,
32:38is that what you put in?
32:40>> Sean,
32:41>> Sean,
32:41>> I put at 15.5. Yes.
32:43>> And I just conf uh confused the two of
32:46you, so I apologize for that. But yes,
32:47the number was 15.5.
32:49I'm just looking to see if I can find
32:51how many parking lot counts.
32:53>> Come on.
32:54>> I think we were close to 100. Um,
32:57>> okay,
32:57>> Sean. Yeah, like 98 or 97 or something.
33:01>> And that may not have full
33:06um
33:07refinement in terms of the cost of
33:10spaces to the south versus the north.
33:13which is to say that the north the gray
33:16area has uh excavation requirements that
33:20are
33:21greater than those at the south.
33:24>> Yeah, we might hit more ledge um based
33:27on some of the based on some of the
33:29information we have now. We might hit
33:31more ledge up here um
33:35from the from the borings, but obviously
33:37we could still
33:39>> the the full lot would be more expensive
33:41than we initially had it at because we
33:43have more information about the site at
33:44this point.
33:45>> There's there's uh greater risk there in
33:48terms of the site excavation cost. Yes.
33:52>> Great.
33:54Um anything else about parking garage
33:56option, Lisa, or do you want to move on
33:57to the sidewalk? Uh if there's um no
34:01additional questions, I can move on to
34:03our sitewalk.
34:06Okay, great.
34:10All right, my slides advancing. There we
34:12go. Okay, so um early in the month, we
34:16walked the site with the tree amigos. Uh
34:18we talked about what trees uh we would
34:22be able to save during construction. We
34:25identified the uh I identified the four
34:28large trees on Medford Street uh to be
34:32protected uh during construction. Um and
34:35we'll put a plan together uh when the
34:38project um goes out to bid uh to ensure
34:42protection and um as well as reviews by
34:46uh arborists uh probably like monthly
34:48reviews so that we can make sure those
34:50trees uh stay healthy um through the
34:53construction phase. We also identified
34:57uh four other trees at the corner of
34:59Evergreen and Thirsten Street um that
35:02would be saved uh protected and saved
35:04during construction. Um and then there
35:07were two more trees uh further up on
35:09Evergreen on the north side of the site
35:12um that the um the city would like for
35:15us to try to save. Um, I think we have
35:17to do a little bit more work to to
35:19understand um these trees because a lot
35:23of our deep excavation um occurs uh
35:27right along this property line for the
35:29for the cafeteria and for the um uh
35:32rooftop play space. So, um, so we'll
35:35look at it a little a little further,
35:37um, to see what can be done, but, um,
35:39we're not 100% confident that we can we
35:43can save these two, uh, trees, um,
35:45during construction.
35:47However, um, new trees will be planted.
35:51Um, our, uh, landscape architect will be
35:53developing a planting plan, um, in which
35:56we're going to share, uh, with the, uh,
35:58the tree amigos. Um I think we said we'd
36:01submit it at the end of October for them
36:03to review and comment on. I know um uh
36:07caliber size of the trees as well as uh
36:10which trees have better canopies and and
36:12things like that. They like variety as
36:14well uh will be an important part of the
36:16review. So um so trying to keep them
36:19involved uh throughout the process so
36:21that um we can uh uh meet all the
36:25requirements and expectations that the
36:29um that the city's looking for.
36:31>> Lisa, have you had any initial
36:33conversations with urban forestry?
36:35>> Yes, that's that would be the um that's
36:38the tree amigos, right? Rich right? They
36:40are twothirds of the tree amigos.
36:42>> Two3s of Okay.
36:43>> Okay. I wasn't sure if Tree Amigos was
36:46the consultant that you were using or
36:48[laughter] if it was a it was a familiar
36:50name for urban forestry.
36:53>> It's it's the combination of urban
36:55forestry and uh the arborist who sits in
36:58DPW. So they they are the tree team
37:04affectionately known as the tree amigos.
37:06>> Thank you for clarifying. Somerville
37:09just got cooler. Okay.
37:11>> As though that were possible. I was told
37:14everybody knew them by that name. So, um
37:17>> I do not. I know them as [laughter]
37:18urban forestry
37:19>> and I believe I believe they
37:21>> not cool.
37:24>> I believe they told me all three of them
37:25are actually arborist as well. So, um
37:28but uh yeah. So, great. Um any questions
37:31about our assessment?
37:36Great.
37:39All right. I'm gonna hand it over to Bob
37:42to give a uh a brief update on the
37:45plans.
37:47>> Sure. Thanks, Lisa. Um, not a lot has
37:50changed. Um, these plans are arranged a
37:53little bit different than what you're
37:54used to. It's a very difficult geometry
37:56to to kind of um, you know, increase the
38:00size of, but uh, the lowest level is on
38:02the far right. Um, and that's our prek
38:06kindergarten. that pretty much remains
38:07the same surrounded by green space. Um
38:11the hillside going up sycamore as well
38:13as on the church property um does uh
38:16rapidly increase. So some of what you
38:19have on the site right now with um uh I
38:23don't want to call them areaways, but um
38:26you know kind of daylight pockets uh to
38:29to make sure we there are windows and
38:32and some daylight getting to those rooms
38:34is something that's going to continue.
38:35although we're studying making it
38:37significantly wider. Um in the middle
38:42plan level one um it's pretty much the
38:46same. So this is where the rooftop over
38:49the calf and kitchen is green space. Um
38:53the gymnasium and the calf um have this
38:55uh we'll call it level one but basically
38:58you can access the building from the uh
39:01multi-purpose field side. That hasn't
39:03changed. um that can be a decision on
39:07whether that's an arrival point or if
39:08it's just um reserved for coming and
39:12going outside from the calf and gym and
39:14maybe on special events. So that that's
39:16something that can be managed. The um
39:19here we also have uh shared spaces in
39:21the middle, music, theater, health,
39:24classrooms, everything you see in green,
39:26those haven't really changed. The purple
39:28rooms are special education and we've
39:32deliberately dispersed them, but on
39:34occasion you'll see two in a row, which
39:36I'm guessing when we have our FAS
39:38meeting, the dees will will prompt us to
39:41try to try to spread those out and not
39:43have two next to each other. Um, but we
39:45are also trying to stick with the
39:47geometry of having uh two classrooms
39:50with shared uh pull out or small group
39:53space between. So there are increments
39:55of the program that we're working with
39:57here um that make that a challenge. So
40:00on the far left, this is now the main
40:04floor level. Um the corner of um
40:08Sycamore and Evergreen really is the
40:09high point of the site and that's the
40:11the entry level here. Um if you come in
40:14the main entry, you can look down and
40:16visually connect to the cafeteria and
40:18the gymnasium. Um and that's intended to
40:21have really good outdoor views and
40:22connections. So it'll feel like a a nice
40:25arrival. And you know, the plan here is
40:28to make it very understandable. When you
40:30walk in this main entry door, you can
40:31see down to community spaces. You can
40:33see in the other direction down the
40:36academic corridor. So relatively simple.
40:40Um we've talked about it before, but
40:41when we get into the academic
40:43neighborhoods, there's a little bit of a
40:44spllay to the plan. Um and that's to
40:47create a little bit more space. We plan
40:49on using that. There'll be many design
40:50studies that determine how do we create
40:53um flexible use space there but maybe
40:56also visually connect between floors
40:58because we want the grade clusters of um
41:02prek through three to feel a bit
41:04connected um and that they share kind of
41:06a zone within the school as well as the
41:09um four to six and then and then the 7
41:11to 8. Um, the one thing that's changed
41:14in the plan is on the south wing, you
41:17wouldn't know what's changed, but where
41:19you see the grade one or grade two
41:21classrooms, we actually shuffled the
41:23rooms around a little bit. We moved a
41:25specialed room to the opposite side of
41:28the corridor, and we were able to
41:30shorten the wing slightly uh while still
41:34having this generous play area. It saved
41:36about 3,000 square ft. So, that's
41:38something we're always looking to do to
41:40try to tighten up the plan where we can
41:42make sure it still meets all the
41:45educational objectives. But, um, that's
41:47really the only change to the plan. We
41:49can go up one more level. And
41:51>> actually, um, Bob, before we move on, I
41:53just want to point out where you've got
41:55the future edition where you were able
41:57to pull back. That's a remnant of the
41:59MSBA because they always want to know
42:03like you to think ahead to the next
42:05moment. If you did have to do kind of a
42:08a late game edition or future edition,
42:12where would that go? Um, I'm assuming
42:14that's not what you're proposing, but
42:16you do have to show that for MSBA
42:18because it's one of their fun facts that
42:20they make you do.
42:21>> Yeah, I'm actually really glad you that
42:23was on my mental list to describe. No.
42:27And no, but I totally forgot to. So, um,
42:29we're not proposing a future edition.
42:31The MSBA requires a 10% expansion
42:34potential. Um, and so, we have here, I
42:39forget the exact number, 47 or so
42:40classrooms. So, um, this would represent
42:43five classrooms that that would stack on
42:45top of each other. It just means that
42:46we're going to design the structure, um,
42:48at that lowest kindergarten level to be
42:51able to translate up in the future and
42:53allow this addition to happen. um your
42:56spaces like music, theater, they
42:58actually all have scheduling capacity.
43:00So, we don't need an additional room
43:01there. We know your cafeteria is
43:04designed for um three lunch seings when
43:07the reality is it's likely to be four or
43:10planned to be four. So, that gives you
43:11capacity and the gym also has scheduling
43:14capacity. So, you know, basically we're
43:16planning for the long longterm future,
43:18not knowing um how the school may need
43:22to evolve and
43:25>> keep going.
43:26>> Oh, it could be expansion not for
43:28enrollment but just for special needs
43:31programs or maybe more innovation um
43:33offerings. You It could be for a number
43:35of reasons.
43:36>> Yeah, because there has been uh examples
43:37in the past where um a school district
43:40uh builds a building and then
43:41immediately they realize that they need
43:42more. Um, so the MSBA just wants to make
43:45sure that communities are responsible
43:48with taxpayer money. Uh, Courtney, you
43:50have a comment.
43:51>> I just had a question. What the where it
43:54says rooftop in the middle
43:57>> um will that be usable rooftop space or
44:01just condensers and
44:03>> Yeah. Our plan is you won't know that
44:05it's rooftop. It'll feel like a
44:08combination of uh playground, green
44:11space, um basketball court. It will feel
44:14very much what it feels like now. Um
44:18we've we've buried the cap.
44:20>> This is future that's future expansion
44:22or that is
44:23>> No, I think she's talking about the one
44:25on the south above um the [snorts]
44:27outdoor uh classroom space that we have
44:29off of uh the first grade.
44:32>> Oh, yeah.
44:33>> Yeah. So the kindergarten level is um a
44:36larger footprint than when we get into
44:38the first, second grade and every floor
44:40above. So that gives us a usable rooftop
44:43that we think faces south as well. So
44:46it's a great opportunity for could be a
44:48continuation of academic outdoor
44:51learning and gardens. it would not be
44:53readily uh accessible to the community,
44:56not easily accessible to the community,
44:58but we um have so much of the other
45:01green space. Uh the majority of all
45:03green space and outdoor space is
45:04accessible to the community. This would
45:06be the maybe one exception. Maybe
45:08there's
45:09>> But it is actually in the plan, not the
45:11future expansion.
45:12>> It is.
45:13>> Yeah. So, Courtney, when if you look at
45:15the um the level one versus lower level,
45:18do you see the alignment of the um
45:20stairwells?
45:22>> Right. You can sort of see how the
45:23kindergarten one has some pink
45:25underneath it, right? So, that footprint
45:27extends out and obviously you have to
45:30put a roof on that. So, um it it it
45:32affords some interesting rooftop space
45:35closer to Medford than was previously
45:38done at the school.
45:39>> Yeah, that's great. I hadn't seen that
45:41detail before that there'd be that
45:43little green space. Wasn't sure. It
45:45sounds like it'll be used as a
45:48amenity, not just condensers.
45:51That's nice.
45:52>> What's funny is I had dotted lines that
45:54allowed you to visually see how this
45:56stacks across the plan and the MSBA made
45:59me take them off. I don't know why.
46:01>> Yeah, graphic clarity. Give me a break.
46:04Okay.
46:06MSBA wise. Awesome. Thank you.
46:08>> Where's the wetland delineation?
46:11>> The wetland delineation.
46:13>> Was that a joke?
46:15[laughter]
46:16>> I hope so. No. Yes, it is.
46:19wrong project.
46:21>> Um, the floors above, uh, I'm calling
46:24them level three, four, and five, but I
46:25think we've actually renumbered them so
46:27it starts from one. So, this would be
46:29four, five, and six. But, um, again,
46:32nothing's really changed here. We've
46:34just tightened up that south wing that
46:36has third grade, 7th grade, and eighth
46:37grade. Um, and, you know, not
46:41compromising some of the design
46:42objectives. So when you're in that
46:43shared corridor space or you're looking
46:45down the corridor, you're going to see
46:47outside, you're going to see treetops.
46:49Um, so very much visually connected to
46:51the landscape.
46:54>> Okay, any questions?
46:59>> I'm curious any comments from the
47:01educators. Um, I know that you're in
47:03user group meetings right now. I think
47:06things that you're looking for or any
47:08reactions to these designs.
47:20>> Okay, I think we can keep moving.
47:23>> Yeah, we're just in the phases of the
47:25the focus group. So, uh we we haven't
47:29brought that discussion to
47:31>> uh the teams yet. So um I think very
47:33soon we'll be engaging with faculty.
47:36>> Amazing. I look forward to to hearing
47:38some of the reactions because I think
47:39anytime you bring it in front of a
47:42larger group, you always discover new
47:44things.
47:47>> Very good.
47:51>> So um we brought just some images of
47:54what we've also been working on in the
47:56background. We actually are developing
47:58two different scaled models. So you can
48:00see these are a few uh visual
48:04perspectives of uh a model we have right
48:07now where the building is only masked
48:08out. It doesn't show any articulation of
48:11materials or windows or anything. Um and
48:15it shows the surrounding neighborhood,
48:17the church um to help give a sense of
48:20the size and scale and mass. Um
48:24and then uh and so this is something
48:27that we'll continue to develop. This is
48:29done with 3D printers. The cork is uh
48:32the base is made out of cork. Um so as
48:34the design develops, we'll be swapping
48:36out pieces. Um and kind of playing with
48:40how we can make it, you know, better fit
48:42nest into the neighborhood. Um but it
48:45gives everybody a sense of of the scale.
48:49>> I'm always waiting for neighbors to ask
48:51if they can have a copy of their house
48:53as as things go by. But um this is these
48:56are always great conversation topics
48:58especially to those who are um you know
49:00in different different levels of
49:02understanding architecture.
49:05Okay.
49:07>> And then uh okay, we have a larger scale
49:10model we're also working on as well to
49:12get a little bit more detail and we've
49:14had design uh sharets within our office
49:17even in pulling in design talent from
49:19across the nation to talk about ways to
49:23um really make that lower kindergarten
49:24pre-K level. Fantastic.
49:29>> Okay.
49:31Um, and we we also want to just give you
49:34an update uh regarding mass, not timer,
49:37but timber. Uh,
49:38>> oops.
49:39>> Oops. That's all right.
49:42>> Uh, keeps it light. Um,
49:44>> this is why education matters. Okay,
49:46keep moving. [laughter]
49:49>> Uh, anyhow, uh, you always see something
49:52when it goes up on the screen, I think.
49:54Anyhow, um, we we're looking at at mass
49:57timber. we know we need to give you, you
50:00know, a fullthroated explanation of the
50:03the pros and the cons. Uh what will the
50:06impacts of implementing it be? Um and so
50:09we're working with that. Uh most
50:11recently
50:13uh we've met with some select folks from
50:16uh the city uh together with some uh
50:20construction manager friends as we're uh
50:22collecting some data um about recent uh
50:26local regional projects
50:30uh in terms of uh cost but also in terms
50:34of sort of overall risks and benefits.
50:37Um and those conversations will um will
50:41be continuing with uh more people being
50:44pulled in and pulled and discussed so
50:47that we have a full uh sort of idea
50:50about everything from first cost, carbon
50:54impacts, uh operation and maintenance
50:56impacts if if any. Um, and so we'll be
51:00able to come back to you then soon. Um,
51:04so that we can update you on uh the
51:08breadth of the information we pulled
51:09together and and come to a decision
51:12about is this a good choice for this
51:16project for you.
51:22>> Any questions?
51:27Okay. Okay.
51:30All right. That brings us to next steps.
51:33Um, so we actually already completed our
51:37next step of setting our meeting dates
51:39for schematic design. Uh, and um, we
51:43talked a little bit about getting
51:44direction on the parking garage. So, uh,
51:47looks like um, that'll kind of be
51:50discussed over the next week or two, I'm
51:53assuming. Um and then our um MSBA FAS uh
51:58meetings upcoming as well as the um
52:01October uh board meeting approval which
52:04isn't that far away either. I believe
52:06that is that the 28th? Do I have that
52:08date right Sean? I think it's October
52:1028th
52:12>> of the MSBA.
52:13>> Yeah, for the board meeting.
52:16>> I'll look it up. I don't know off the
52:17top of my head. That sounds right.
52:19>> Something like that.
52:20>> Yeah. So, um, and then, um, that's all
52:26we have for today.
52:30>> October 28th. Yep.
52:40>> Any additional questions?
52:46>> I don't see any on the comments. I don't
52:49see any hands up. Okay. Um, with that,
52:53uh, I will open it up for public
52:55comment. I know that we have two
52:56attendees. If you are in, actually, it's
52:59one. Um, Ed, you're in there twice. Um,
53:02if you are interested in speaking, let
53:04us know. Uh, indicating by, um, see, I
53:10think you can raise hand or chat.
53:21Okay. Uh, not hearing any public
53:23comment. Uh, I move to Well, I don't
53:28move. Uh, I look forward to a motion to
53:32adjourn the meeting.
53:37>> Motion to adjurnn.
53:38>> Thank you, Courtney. Second.
53:40>> Thank you, Rich. Uh, Sean Burke, can you
53:43help me out with the roll call on this
53:44one? Sure. Um, Emily,
53:48>> yes.
53:50>> Rich Ra,
53:51>> yes.
53:52>> Reven,
53:54>> yes.
53:55>> Courtney Roslin,
53:56>> yes.
53:58>> Ed,
53:59>> yes.
54:01>> Chris,
54:05>> yes.
54:06>> Kathleen,
54:07>> yes.
54:09>> Jesse,
54:10>> yes.
54:11>> Sash,
54:12>> yes.
54:14Gordon Cole.
54:15>> Yes.
54:16>> And Rich H.
54:24>> Is Rich still on?
54:26>> He's on, but he's muted.
54:32>> Uh, do we have enough for a quorum vote?
54:35>> You do. Yes.
54:36>> Okay, great. Oh, Rich, you're back. Do
54:39you vote to adjourn the meeting?
54:41>> Sorry about that. that I was picking up
54:42John at Brown. Um yes, [laughter]
54:465:30.
54:47>> All right.
54:48>> Amazing.
54:50>> Amazing. Um the motion passes. We are
54:53adjourned. I will see you all on
54:55November 2nd. Thank you so much.
54:58>> Thanks all. Take care.
55:00>> Thank you.