2026-11-05 - Municipal Building Committee

Summary

Built from the posted agenda only; votes taken are not recorded because minutes are not yet posted.

  • Project: Malden River Works salt shed and boathouse (see Roosevelt Park Funds Repurposed to Malden River Works).
  • designLAB gave construction-drawing updates.
  • Vote to hire an owner's project manager (OPM) firm, conditional on reference vetting and price negotiation.
  • Approval of designLAB Invoice 26-02.0926 for $38,430.00 (Construction Documents moving from 75% to 100%).

Agenda

  • Construction-drawing updates from designLAB
  • OPM selection: vote to hire a firm (conditional on reference vetting and price negotiation)
  • Approve designLAB Invoice 26-02.0926, $38,430.00 (Construction Documents 75% to 100%)