2026-09-22 - City Council Study Session (2)
Summary
Based on auto-generated captions that end about 46 minutes in, partway through the first agenda item; the other four items (the 2027-2028 biennial financial forecast, the 2027-2032 capital investment program review, the Housing and Human Services Action Plan and council talk time) are not covered. Names and numbers may be misheard.
- Opening: The Council President called the study session to order at 7:00 p.m. with all members present, one joining online; the mayor was absent. Five items were on the agenda.
- Municipal operations center update: Chris Stenger (interim public works director) and parks director Loreen Hamilton reported that the validation phase of the progressive design-build process is complete and the project is moving into phase one design and preconstruction, with Jason Lynch online for permitting questions. Substantial completion is now expected by May 2030, about six months earlier than previously planned. The campus would centralize public works, parks, fleet and fire fleet maintenance on the newly purchased site, with a two-story mass timber office building, a one-story shops and warehouse building, and a fleet maintenance building with two heavy-duty and eight medium-duty bays. The office building targets LEED v5 Gold; equivalent certifications are being studied for the maintenance buildings. The target budget is $268.5 million, which includes about $18.5 million to cover the new site; it removes the dispersed operations need and the parking garage. Council approval of the guaranteed maximum price is expected in the first half of 2028, with the phase two contract in the second quarter of 2028. See Municipal Operations Center Project.
- Old site stays in part: The decant facility cannot move to the new site for lack of space, and the fuel island, mineral bins and salt storage are under study. Moving everything would need an underground stormwater vault and a parking garage costing roughly $40 to 50 million, so it was not pursued. Menka Soni, Sayna Parsi and others said they had understood the old property would be surplused after the purchase and asked that the change be documented; staff committed to more transparency, said no sale proceeds are counted in the capital budget, and said the two sites are very close, so travel impact is low. See also Pacer Propane Property Surplus Sale (Resolution 1632) for another surplus sale.
- Sustainability: Staff said advanced battery and storage technology was kept as an aspiration rather than a baseline promise because it is improving and getting cheaper; a council member urged using the redevelopment to advance emission reduction goals.
Issues discussed
Agenda
Study session/special meeting; see agenda.
Sources
- Video: https://youtube.com/watch?v=kS5Fq3svElU
- Agenda: https://redmond.legistar.com/MeetingDetail.aspx?LEGID=3280&GID=652&G=4D25B8F6-2EB3-4784-A3AB-F30F60990FBD
Video
Transcript
These are auto-generated captions; names and numbers may be misheard.
Transcript
00:28Good evening. I am calling this meeting
00:29to order. This is a Redmond City Council
00:31study session held on Tuesday, September
00:3422nd, 2026, commencing at 700 p.m. All
00:38council members are in attendance.
00:40Council member Procria is online. Mayor
00:42Bernie will not be in attendance
00:44tonight. There are five items on the
00:47agenda. The um municipal operations
00:50center project update validation summary
00:52and recommendation
00:542027 2028 bianial forecast financial
00:58forecast the 2027 2032 capital
01:02investment program review the
01:04continuation of that conversation from
01:07our last study session the housing and
01:10human services action plan and council
01:12talk time. So the first item is the
01:15municipal operations center project
01:16update and Chris Stanger, interim public
01:18works director, will kick us off. Thank
01:20you, Chris.
01:22>> Thank you, council president, and good
01:23evening, council members. Uh, as
01:26introduced Chris Stinger, public works
01:28side, uh, joining me tonight is the
01:31parks director Loren Hamilton,
01:34project manager Amy Kim from Capital
01:37Projects team. We're also joined by our
01:39progressive design build team from Lee
01:41Crutcher Lewis and Miller Hall, Duncan
01:44Howard from the Lewis side and Claire
01:45Renick from the Miller Hall side. And
01:48then online, if there's any permitting
01:51type of questions, we have the acting
01:53development service director, Jason
01:55Lynch. So joined by a a cast uh tonight
01:59to present um the validation maintenance
02:03and operations center or campus
02:05redevelopment project. And tonight's
02:08presentation follows the completion of
02:10the validation phase and provides an
02:13overview of where we are headed as the
02:16project transitions into phase one
02:18design. Next slide, please.
02:22The purpose of tonight's presentation is
02:24to provide a summary of the validation
02:26phase, share the outcomes of that work,
02:28and outline the path forward as the
02:30project moves into design. The
02:32validation phase provided an opportunity
02:35for the city and progressive design
02:37build team to further define the project
02:39requirements, confirm the project
02:41approach, and make sure we remain
02:43aligned with the project goals, budget,
02:45and overall schedule. Tonight is also an
02:48opportunity to provide council with
02:50visibility into where we are in the
02:52process and upcoming decision points as
02:55the project advances. Next slide,
02:58please. So these are the primary goals
03:01that are guiding the MOC project.
03:04One slide back. Thank you. Uh first, we
03:07want to create a multi-gener
03:09generational facility for our current
03:11and future public servants. That means a
03:14facility that is durable, adaptable,
03:17easy to maintain, and designed to evolve
03:19as the city's needs change. Second, we
03:23want to create a sustainable and
03:25functional workplace that supports staff
03:27well-being, collaboration, and changing
03:29workflows.
03:31The MOC will bring a uh multiple
03:33divisions together. So, the layout and
03:36adjacencies are important. We want to
03:38reduce physical and operational barriers
03:40between the teams and create
03:42opportunities for staff to work together
03:44more efficiently and ultimately serve
03:46the public more effectively.
03:49Then finally, we're looking at the
03:51project through a long-term lens in the
03:53context of Redmond 2050. The goal is to
03:56create a forward-looking campus that
03:58maximizes sustainability, capac
04:01capacity, and infrastructure readiness
04:03and provides a facility that can serve
04:05the gener uh city for generations. These
04:08goals have guided the validation phase
04:10and will continue to guide the design as
04:12we move forward. And finally, uh slide
04:16four for me.
04:18Slide here shows the overall project
04:20schedule and where we are today. So as
04:23stated we have completed the validation
04:25phase which is the initial phase of the
04:27progressive design build process. So
04:30during the validation the city and the
04:32design build team work together to
04:34confirm the project requirements, scope,
04:37schedule, risk and cost assumptions
04:39before advancing into the next phase. So
04:42now we are transitioning into phase one
04:45design and preconstruction.
04:47As part of phase one, the design build
04:49team will advance the design, continue
04:52to refine the project scope and cost,
04:54coordinate permitting, and develop the
04:56work necessary to prepare for
04:58construction.
05:00You'll see phase one NTP on the
05:02schedule. NTP stands for notice to
05:05proceed. This is an authorization for
05:07the design build team to begin the work
05:10associated with phase one. project will
05:13then move through permitting and early
05:15works while the design and construction
05:17approach continue to be developed.
05:20You'll also see GMP which stands for
05:23guaranteed maximum price. This is a
05:26major milestone associated with
05:27establishing the construction price
05:29before moving into primary construction
05:31phase. Following that that the project
05:34moves into phase two construction
05:35followed by project closeout. So the
05:38current schedule anticipates substantial
05:41completion by May 2030 right around the
05:44corner. So at a high level validation is
05:46complete. We are bringing uh beginning
05:48phase one design and pre-construction
05:50and focus now is advancing the design
05:53refining the scope and cost completing
05:56permitting and early work and preparing
05:58for construction. And with that I'm
06:01handing it over to Director Hamilton.
06:04>> Thank you Chris. Uh so I'm going to
06:06start talking a little bit about scope.
06:08As we talked about earlier today in
06:10committee, um validation does three
06:12things for us in the progressive design
06:14build process. It uh validates our
06:17scope, our schedule, and our budget. So
06:18Chris just talked about our schedule. Uh
06:21as you'll notice that that timeline did
06:23move up from previous touch points um by
06:28how long we we were previously in 2031.
06:32Correct. Yeah, we
06:34>> six months. So, we we um were able to
06:37move the completion up approximately six
06:39months as we went through the
06:40validation. And this is simply because
06:42information becomes more clear. It helps
06:43us understand the project a little bit
06:45better. The next piece that we're going
06:47to talk about is scope. And that's going
06:48to be over the next four slides or so.
06:50And so, the new MOC is really looking to
06:52replace our outdated facilities with the
06:54resilient and future flexible campus.
06:56Our current campus has been peacemeal
06:59over the decades. Um, and if you have
07:01toured it uh recently at all, you will
07:04notice that there are um teams that are
07:06in buildings that were never meant to be
07:08permanent. Uh, and so we are really
07:10looking forward to replacing these
07:11facilities uh in a way that is designed
07:14for long-term operational excellence.
07:17One thing that's important to note is
07:19that there are a handful of functions
07:20that at this time will be remaining at
07:22the existing site. Those three items are
07:25decant, fuel island, mineral bins, and
07:28salt storage. Uh and so in the red um on
07:32this diagram you'll see those red
07:34outlines. Those are the ones that will
07:36be maintained. The ones that are
07:38outlined in blue have the ability or the
07:41would not be too difficult to decouple
07:44and to um demolish and or surplus. And
07:47so uh the design build team is still
07:49working on squeezing this down. The
07:53biggest item that will remain on site is
07:55the decant facility. uh the decamp
07:57facility does not have the potential to
07:59move on to the new uh site that we have
08:03brought on at H Highleberg. Uh there is
08:06not space at that site for that program
08:08and so it will maintain there. The two
08:10others which are the fuel tank and the
08:13mineral bins are under further study uh
08:15and we'll be able to bring more
08:17information. there are going to be the
08:19potentials for um reducing out those
08:23other facilities uh as we continue on
08:26through the project as well
08:31at the new MOC. It's our Am I on the
08:34right side? Did I skip?
08:40Oh, got it. Okay. Sorry. We were we're
08:43making sure we're on the same slides
08:45here. Uh at the new MOC, the prior prior
08:48priority is going to be to centralize
08:50all public works, parks, fleet
08:51maintenance, and fire fleet maintenance
08:53staff at the MOC. Um the consolidation
08:57of this high use program at the new MOC
08:59will include workspaces, training
09:01spaces, fleet maintenance shops, labs,
09:03and frequent frequently accessed fleet.
09:10The new site which we have purchased and
09:12are designing the new MOC on will be a
09:14full redevelopment of the site and
09:16operation structures. It will have storm
09:18water infrastructure, vehicle wash
09:20facilities, vehicle and maintenance and
09:22equipment storage and other ancillary
09:24structures that will support the
09:25operational requirements of our crews.
09:28EV charging and surface parking is also
09:30included. The operations building which
09:33you see on the bottom in blue is going
09:35to be a new two-story mass timber
09:37building and it will house the people
09:39really. These are going to be our office
09:41building. This is going to be our office
09:43building that includes conference rooms,
09:45training rooms, kitchenetses, touchdown
09:47spaces, offices, etc.
09:51and our lockers. Sorry, that's an
09:52important one. Uh the operations
09:54building which you see in orange is a
09:56new one-story building. It will have
09:57shared use shops, labs, warehouse space,
10:00and storage functions. And so the design
10:01build team is working hard with the
10:03crews and the teams out at the MOC to
10:05ensure that adjacencies in these spaces
10:07are appropriate and working to the
10:10greatest um ability. The last is the
10:12operations building, which you'll see in
10:14pink. This is a new one-story building
10:16with um high high bay fleet maintenance
10:21areas, two pullthrough heavy duty bays,
10:23and eight tandem pullthrough medium duty
10:25bays. So this is where all of our fleet
10:27maintenance will happen and this will be
10:29both um citywide fleet as well as fire
10:32fleet is going to uh consolidate on this
10:34site in the future.
10:38Sustainability is a topic of continued
10:40conversation. Uh an important thing to
10:43note is that lead which is the
10:46certification that we discuss most often
10:48in this room is really targeted for
10:51people focused facilities. office
10:53buildings in particular. And so right
10:56now we are targeting the administrative
10:58building as lead gold. Uh it says lead
11:01v5 gold. They just updated their
11:03certifications. And so we are targeting
11:05lead v5 gold. Lead is not
11:09easily applied to maintenance and
11:11operations facilities or things that are
11:13more similar to infrastructure and
11:15public works types uses. And so the team
11:18is actively studying different
11:20certification methods uh to be able to
11:23meet our gold goal of lead gold or
11:26equivalent. And so we want to be really
11:28clear that we are not diminishing or
11:31overlooking our sustainability goals
11:33here, but we are going to have to be
11:35looking at different ways to um attain
11:38them. uh the sustainability manager
11:40Jenny Liebeck and Laida Harris who's our
11:42facilities and park sustainability
11:44program manager are working very closely
11:46with the team to understand what are the
11:48ways that we're wanting to have these
11:50green standards built into the MOC. Uh
11:53and so we are looking at different
11:54things such as Envision which is uh what
11:57Sound Transit uses for a lot of their
11:58projects uh and different zerocarbon um
12:02certifications as well. So this is still
12:04under study. Um but we are shooting for
12:08lead V5 gold on the people building and
12:12then looking at equivalent
12:13certifications for the other facilities
12:15and the site as a whole.
12:19Now that we've talked about schedule and
12:21scope, we're going to talk a little bit
12:23about budget. The new MOC, thank you
12:26Amy, uh is currently targeted at a
12:29budget of 268.5
12:31million. This has eliminated our
12:34dispersed operations need. It has
12:36eliminated the parking garage need and
12:38we have been able to fully incorporate
12:40fire fleet. This number does look
12:43different than what we have talked about
12:45and one of the reasons for that is
12:46because of the purchase of the new of
12:48the new site. Um there were dollars that
12:51were already built into the budget for
12:53dispersed operations and that was helped
12:56cover a portion of it. Um, but finance
12:58has worked with us to ensure that we can
13:00cover that additional $18.5 million in
13:03the project budget so that we can move
13:05on to that new site and fully outfit the
13:07site for the future of the maintenance
13:09and operations center.
13:15To date, we have engaged with city
13:17council um as follows. Uh, we did the
13:21validation contract approval with you
13:23all in Q4 of 2025. We've been doing
13:26quarterly updates. We were with you in
13:28Q1 uh of 2026. In Q2, we did the phase
13:31one approval for the contract. Um and
13:34then we were with you just recently in
13:37Q3 doing a study session update as well.
13:40Looking forward, there's going to be
13:42some decision points for city council
13:44and we want to make sure that it's
13:46understood. Um this graphic is busy and
13:48really small. My apologies, but you'll
13:51continue getting updates on a quarterly
13:53basis through the CIP update. Uh, in Q1
13:56to Q2 of 2028 will be the GMP approval,
14:00which is the Oh, it went away.
14:04There we go. Thank you, council
14:06president. Get the guaranteed maximum
14:07price for this project. And so that will
14:10need to come to council for approval.
14:12And then in Q2 of 2028 will be the phase
14:152 contract which will allow the design
14:16build team to continue their work.
14:22At that this point that is all of the
14:25information that we have to share. We're
14:26happy to answer questions. We also have
14:28Claire and Duncan here who are ready and
14:29willing to answer questions um as they
14:32have are really the experts on the
14:34design build side.
14:37>> Thank you so much team. Uh council who
14:39would like to kick us off? Council
14:40member Sony.
14:44>> Thank you so much. Uh I have a question
14:46specifically with the old site because
14:49it's still going to have our fuel island
14:52tick facility and material salt mineral
14:55bins. Now once everything has moved to
14:58to the new facility
15:00and and when we did took a tour for the
15:03old sai it's still big. So the cost of
15:05maintaining that site with just these
15:07limited um uh you know limited
15:10facilities isn't that going to be large
15:13or is there a plan that eventually these
15:16will also moved to the new MOC site you
15:19know any costing or anything associated
15:21with that?
15:21>> Yeah that's a great question. Thank you
15:23council member. So there are two items
15:25that we're hoping to either be able to
15:27move onto the new site or consolidate in
15:29a different way on the current site and
15:30that's the mineral and salt bins and the
15:32fuel island. And so that's something
15:34that the design build team is actively
15:36exploring is how do we reduce our
15:38footprint on the current site. Decant is
15:40a tricky one. It's a newer um piece of
15:43infrastructure for us. It's in really
15:45good working condition and there is not
15:47space on the new site for that to move
15:50over to that site. Um and so we will
15:54need to maintain it on the current site
15:56or it will be need to be moved to a
15:58different site if we ever wanted to
16:00fully vacate that site. Um the hope is
16:03though to minimize our impact on that
16:06site so that we can surplus some of that
16:08land and sell it so that we're not
16:10maintaining that full parcel. Uh what
16:12that looks like is still to be
16:14determined. Those things are still under
16:16study, but that is the um long-term goal
16:19is to minimize our use of that site and
16:21be able to um surplus that that space if
16:25that is what council chooses.
16:29Did you have a follow-up, Council Member
16:30Sony?
16:32>> So, now assuming there will be a staff
16:34travel time between both of these sites,
16:36I hope that has been taken into
16:38consideration into the budget.
16:39>> These two sites are extremely close
16:41geographically and we worked really
16:43closely with the the staff to understand
16:45what the impact would be of those two
16:47things being separated. This is from
16:51staff's perspective extremely low
16:53impact.
16:55Thank you, Council Vice President. Thank
16:58you, Chair. Um, director, thank you for
17:00that clarification and and, uh,
17:02expanding out on that. And thank you to
17:04my colleague, Council Member Sony for
17:06bringing up the question because as we
17:07were talking, I was uh uh trying to find
17:11in my notes because I was under the
17:13understanding that by purchasing the H
17:16Highleberg property that then we would
17:19be able to have the the current property
17:23go to surplus um and with the
17:26understanding that the TAMP facility is
17:27a phenomenal asset that we have and
17:29understand that we would we would need
17:31to move it over there. So, this is the
17:33first that I'm seeming to be hearing.
17:35So, I was trying to find it in my notes
17:37to to be able to go back to, but I'm
17:40kind of caught off guard because this is
17:42the first that I'm hearing that no,
17:44we're going to hang on to both
17:45properties and decant's going to stay
17:46there. Understandably, but again, the
17:49first that we're hearing it. Yes, I
17:51understand that this um may be a shift
17:55from what some of your previous
17:57understandings were. I was able to meet
17:58with a handful of you prior to today to
18:01kind of preview this because um it did
18:04become clear to me that that was not
18:05something that was fully understood by
18:07council. I can't necessarily fully
18:10account for why that is um as I was not
18:13um in some of those conversations that
18:15were had with you all previously, but
18:17what I can tell you is that we are doing
18:19all that we can to minimize the impact
18:21and to surplus as much of that property
18:23as we can. The only way we could
18:25reasonably move all of everything off of
18:28our current site and onto the new site
18:30is Can you go back to the map that shows
18:32the storm water, please?
18:36Or one of them. I know there's a few.
18:37Yeah, that's a great one. So, the only
18:39way that that is even potentially
18:41feasible is that um is a storm water
18:44detention vault up in the top left. That
18:47would need to be undergrounded into a
18:48large underground vault. And then we
18:50would need to put a parking garage on
18:52this site to be able to maximize that
18:54space. Um, according to our design build
18:57team, um, and if you have more
18:59questions, you can press on Claire a
19:01little bit, Claire and Duncan on this is
19:02that that would be in the range of $40
19:04to $50 million to accomplish those two
19:06things. And so, um, that was not the
19:10direction that was taken, but that is
19:12the only way that that would be
19:14attainable at this point.
19:16>> Thank you. Thank you. Lots of hands. I
19:19saw council member Sony and then council
19:20member for
19:22excuse me council member parsy my
19:24apologies. So um following up on the
19:27questions that my colleagues asked I
19:29think um I also am going to say from my
19:32memory not from my notes I do remember
19:35that um and my memory can be mistaken so
19:39please correct me um I remember that one
19:42of the premise of um the decision to
19:45move to H Highleberg was that we would
19:47be able to surplus this current property
19:51but what I'm hearing now is that decan
19:54not only So I don't have a problem with
19:56keeping decan because of um the it's um
20:00it has further life to live. Um, but I
20:03think we had the understanding and
20:06information that council received that
20:09the decant could be moved to H
20:11Highleberg, but from what I'm hearing,
20:13DECANT actually cannot move to H
20:15Highleberg because of uh the current um
20:19um location of H Highleberg and for
20:21environmental reasons, we can't support
20:23DECAN in H Highleberg as it is. Um so it
20:27would be really helpful to bridge that
20:29gap between um this because I think um
20:32that was part of the understanding as we
20:34purchased the property. So I want to
20:36make sure if it was incorrect
20:38information or how we can bridge that g
20:41bridge that gap it would be really
20:42helpful. And also um
20:46I do recall and correct me if I'm wrong
20:50um that in part of the financial
20:52decisions that we made in purchasing the
20:55land was um the assumption that we would
20:58completely sell this property. So if
21:01that's a change from that plan, I would
21:03really want to make sure that we
21:05document it. And I understand that um
21:07Director Hamilton, you weren't in the
21:09room, but I think there are others who
21:11were in the room and I would love to
21:13make sure that this is a big purchase
21:15and this is a big financial decision. Um
21:17I want to make sure that we have proper
21:19continuity and I understand that
21:21director we lost a previous director but
21:23the mayor was available in the room with
21:25us um at previous times and I do think
21:28it's important to make sure that we have
21:29continuity.
21:32>> Thank you, Council Member Sony. Uh yeah,
21:34can I address to because there were two
21:37pieces to what she um just shared. So um
21:40I agree with you on the budget and the
21:42continuation of that information. Um I
21:46don't like surprising folks. That's not
21:48something I I don't love coming into
21:50council chambers and surprising this
21:52table of um people. Uh I respect the
21:55work that we do together and I hope that
21:56as we move through this project, we can
21:59pre prevent that. And so that's what I
22:01can commit to you and what what Chris
22:02can commit to you as we move forward is
22:04that we can really try to make sure that
22:06we're being transparent and clear. Um
22:09from a decant perspective, uh my
22:12understanding is that the main driving
22:13factor that we are not moving decamp
22:15over is because of space. Um Claire and
22:19Duncan, I don't know if there's
22:20environmental factors that have come
22:22into play and if you could speak to
22:23those uh because I'm not.
42:40propped on to if we can provide it as
42:42part of the project we would love to do
42:44so we're going to balance that with the
42:45other priorities we hear um the other
42:48thing I'd point out is that for anything
42:50battery storage and advanced
42:51technologies the reality is that
42:53technology is advancing so quickly that
42:55if we buy something today it's likely
42:57not the best use of your money. Uh that
42:59technology is getting less expensive. It
43:01is beginning to perform better. It is
43:03getting smaller. There are all sorts of
43:05things that are happening in that space.
43:07That meant that when we had to evaluate
43:09what's the right thing to guarantee as a
43:12validation baseline, scope, schedule,
43:14budget versus what's something that's
43:15aspirational, that's a piece that we are
43:18still holding very very dearly and
43:20really tracking diligently, but didn't
43:22make sense as a as a baseline promise.
43:25Thank you. Thank you. I appreciate that
43:28commentary and the chance to come back
43:29uh and just keep an eye on the subject,
43:31especially since I I do believe our
43:34community's nearest and dearest values
43:35live and breathe at the MOC. Um and
43:38there is uh such a great opportunity to
43:41advance our um emission reduction goals
43:44through the redevelopment of this
43:45campus. So that's for my part. Okay, for
43:47round two, the first hand I saw was
43:49council vice president Nova Kamina.
43:51>> Thank you. um
43:54appreciate the conversation and how we
43:55advanced and we're we're looking
43:56forward. So I I feeling a little some
44:00sort of way about taking us back for a
44:02second because I had a follow-up on uh
44:04the decant and uh maintaining the
44:07existing site with a very scaled down
44:09operation and that was just to get clear
44:12on what are we estimating the remaining
44:15life on our decant. So then we're
44:16thinking about how long would we be
44:18hanging on to at least a portion of of
44:21that property. Um so we can already
44:24start somewhat thinking about or maybe
44:26holding in our back pocket the the idea
44:29of um when when it comes time to surplus
44:32was this cost taken into consideration
44:35while coming up with the budget. Um uh
44:39so if we are not you know if you're not
44:41planning to sell then does it impact our
44:43budget like you know where's this gap
44:45going to be filled?
44:46>> That's a great question. Um we don't
44:48have a current idea of the full value of
44:50the site. We haven't done any studying
44:52on that. Um as far as I know and I'll
44:55look we have not taken into account the
44:57sale of that property into any budget
44:59whether it bec or otherwise. So per code
45:03that the sale of that property goes back
45:05into the CIP budget. we have not
45:07accounted for that sale in the CIP
45:09budget as we see it. So there's no hole
45:11to fill and so it'll be under further
45:13study of you know how do we parcel it
45:16out? What's the total sale and and how
45:18is that money used?
45:20Yeah, I apolog
45:26uh for you know for the pond in case if
45:29you want to move the decan facility
45:31there and then the reason why I was
45:33asking this cost is like if it makes
45:36more sense to have uh you know
45:39everything there together based on like
45:41the cost of this thing if it's like
45:43selling and then building up there as
45:45one one property versus this
45:48>> and um uh for this property. There was a
45:51second uh concern was because of the
45:54underground contamination.
45:56So, you know, I may want to hear more
45:59about that if that has been taken into
46:01considerations and what has been and any
46:03update on that part.
46:05>> Uh we can have further conversations and
46:07share more information with council. uh
46:10as we went through validation and
46:12understood the cost and the impact of
46:15undergrounding that storm water and not
46:18just as CLA was sharing not just on our
46:20budget but also on our environmental
46:22goals and um the embodied carbon that
46:25that puts into the site. Uh we did not
46:28explore a whole lot more past that
46:30because the determination was that that
46:32was going to be a really impact.