Summary

Based on auto-generated captions that end about 46 minutes in, partway through the first agenda item; the other four items (the 2027-2028 biennial financial forecast, the 2027-2032 capital investment program review, the Housing and Human Services Action Plan and council talk time) are not covered. Names and numbers may be misheard.

  • Opening: The Council President called the study session to order at 7:00 p.m. with all members present, one joining online; the mayor was absent. Five items were on the agenda.
  • Municipal operations center update: Chris Stenger (interim public works director) and parks director Loreen Hamilton reported that the validation phase of the progressive design-build process is complete and the project is moving into phase one design and preconstruction, with Jason Lynch online for permitting questions. Substantial completion is now expected by May 2030, about six months earlier than previously planned. The campus would centralize public works, parks, fleet and fire fleet maintenance on the newly purchased site, with a two-story mass timber office building, a one-story shops and warehouse building, and a fleet maintenance building with two heavy-duty and eight medium-duty bays. The office building targets LEED v5 Gold; equivalent certifications are being studied for the maintenance buildings. The target budget is $268.5 million, which includes about $18.5 million to cover the new site; it removes the dispersed operations need and the parking garage. Council approval of the guaranteed maximum price is expected in the first half of 2028, with the phase two contract in the second quarter of 2028. See Municipal Operations Center Project.
  • Old site stays in part: The decant facility cannot move to the new site for lack of space, and the fuel island, mineral bins and salt storage are under study. Moving everything would need an underground stormwater vault and a parking garage costing roughly $40 to 50 million, so it was not pursued. Menka Soni, Sayna Parsi and others said they had understood the old property would be surplused after the purchase and asked that the change be documented; staff committed to more transparency, said no sale proceeds are counted in the capital budget, and said the two sites are very close, so travel impact is low. See also Pacer Propane Property Surplus Sale (Resolution 1632) for another surplus sale.
  • Sustainability: Staff said advanced battery and storage technology was kept as an aspiration rather than a baseline promise because it is improving and getting cheaper; a council member urged using the redevelopment to advance emission reduction goals.

Issues discussed

Agenda

Study session/special meeting; see agenda.

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

00:28Good evening. I am calling this meeting

00:29to order. This is a Redmond City Council

00:31study session held on Tuesday, September

00:3422nd, 2026, commencing at 700 p.m. All

00:38council members are in attendance.

00:40Council member Procria is online. Mayor

00:42Bernie will not be in attendance

00:44tonight. There are five items on the

00:47agenda. The um municipal operations

00:50center project update validation summary

00:52and recommendation

00:542027 2028 bianial forecast financial

00:58forecast the 2027 2032 capital

01:02investment program review the

01:04continuation of that conversation from

01:07our last study session the housing and

01:10human services action plan and council

01:12talk time. So the first item is the

01:15municipal operations center project

01:16update and Chris Stanger, interim public

01:18works director, will kick us off. Thank

01:20you, Chris.

01:22>> Thank you, council president, and good

01:23evening, council members. Uh, as

01:26introduced Chris Stinger, public works

01:28side, uh, joining me tonight is the

01:31parks director Loren Hamilton,

01:34project manager Amy Kim from Capital

01:37Projects team. We're also joined by our

01:39progressive design build team from Lee

01:41Crutcher Lewis and Miller Hall, Duncan

01:44Howard from the Lewis side and Claire

01:45Renick from the Miller Hall side. And

01:48then online, if there's any permitting

01:51type of questions, we have the acting

01:53development service director, Jason

01:55Lynch. So joined by a a cast uh tonight

01:59to present um the validation maintenance

02:03and operations center or campus

02:05redevelopment project. And tonight's

02:08presentation follows the completion of

02:10the validation phase and provides an

02:13overview of where we are headed as the

02:16project transitions into phase one

02:18design. Next slide, please.

02:22The purpose of tonight's presentation is

02:24to provide a summary of the validation

02:26phase, share the outcomes of that work,

02:28and outline the path forward as the

02:30project moves into design. The

02:32validation phase provided an opportunity

02:35for the city and progressive design

02:37build team to further define the project

02:39requirements, confirm the project

02:41approach, and make sure we remain

02:43aligned with the project goals, budget,

02:45and overall schedule. Tonight is also an

02:48opportunity to provide council with

02:50visibility into where we are in the

02:52process and upcoming decision points as

02:55the project advances. Next slide,

02:58please. So these are the primary goals

03:01that are guiding the MOC project.

03:04One slide back. Thank you. Uh first, we

03:07want to create a multi-gener

03:09generational facility for our current

03:11and future public servants. That means a

03:14facility that is durable, adaptable,

03:17easy to maintain, and designed to evolve

03:19as the city's needs change. Second, we

03:23want to create a sustainable and

03:25functional workplace that supports staff

03:27well-being, collaboration, and changing

03:29workflows.

03:31The MOC will bring a uh multiple

03:33divisions together. So, the layout and

03:36adjacencies are important. We want to

03:38reduce physical and operational barriers

03:40between the teams and create

03:42opportunities for staff to work together

03:44more efficiently and ultimately serve

03:46the public more effectively.

03:49Then finally, we're looking at the

03:51project through a long-term lens in the

03:53context of Redmond 2050. The goal is to

03:56create a forward-looking campus that

03:58maximizes sustainability, capac

04:01capacity, and infrastructure readiness

04:03and provides a facility that can serve

04:05the gener uh city for generations. These

04:08goals have guided the validation phase

04:10and will continue to guide the design as

04:12we move forward. And finally, uh slide

04:16four for me.

04:18Slide here shows the overall project

04:20schedule and where we are today. So as

04:23stated we have completed the validation

04:25phase which is the initial phase of the

04:27progressive design build process. So

04:30during the validation the city and the

04:32design build team work together to

04:34confirm the project requirements, scope,

04:37schedule, risk and cost assumptions

04:39before advancing into the next phase. So

04:42now we are transitioning into phase one

04:45design and preconstruction.

04:47As part of phase one, the design build

04:49team will advance the design, continue

04:52to refine the project scope and cost,

04:54coordinate permitting, and develop the

04:56work necessary to prepare for

04:58construction.

05:00You'll see phase one NTP on the

05:02schedule. NTP stands for notice to

05:05proceed. This is an authorization for

05:07the design build team to begin the work

05:10associated with phase one. project will

05:13then move through permitting and early

05:15works while the design and construction

05:17approach continue to be developed.

05:20You'll also see GMP which stands for

05:23guaranteed maximum price. This is a

05:26major milestone associated with

05:27establishing the construction price

05:29before moving into primary construction

05:31phase. Following that that the project

05:34moves into phase two construction

05:35followed by project closeout. So the

05:38current schedule anticipates substantial

05:41completion by May 2030 right around the

05:44corner. So at a high level validation is

05:46complete. We are bringing uh beginning

05:48phase one design and pre-construction

05:50and focus now is advancing the design

05:53refining the scope and cost completing

05:56permitting and early work and preparing

05:58for construction. And with that I'm

06:01handing it over to Director Hamilton.

06:04>> Thank you Chris. Uh so I'm going to

06:06start talking a little bit about scope.

06:08As we talked about earlier today in

06:10committee, um validation does three

06:12things for us in the progressive design

06:14build process. It uh validates our

06:17scope, our schedule, and our budget. So

06:18Chris just talked about our schedule. Uh

06:21as you'll notice that that timeline did

06:23move up from previous touch points um by

06:28how long we we were previously in 2031.

06:32Correct. Yeah, we

06:34>> six months. So, we we um were able to

06:37move the completion up approximately six

06:39months as we went through the

06:40validation. And this is simply because

06:42information becomes more clear. It helps

06:43us understand the project a little bit

06:45better. The next piece that we're going

06:47to talk about is scope. And that's going

06:48to be over the next four slides or so.

06:50And so, the new MOC is really looking to

06:52replace our outdated facilities with the

06:54resilient and future flexible campus.

06:56Our current campus has been peacemeal

06:59over the decades. Um, and if you have

07:01toured it uh recently at all, you will

07:04notice that there are um teams that are

07:06in buildings that were never meant to be

07:08permanent. Uh, and so we are really

07:10looking forward to replacing these

07:11facilities uh in a way that is designed

07:14for long-term operational excellence.

07:17One thing that's important to note is

07:19that there are a handful of functions

07:20that at this time will be remaining at

07:22the existing site. Those three items are

07:25decant, fuel island, mineral bins, and

07:28salt storage. Uh and so in the red um on

07:32this diagram you'll see those red

07:34outlines. Those are the ones that will

07:36be maintained. The ones that are

07:38outlined in blue have the ability or the

07:41would not be too difficult to decouple

07:44and to um demolish and or surplus. And

07:47so uh the design build team is still

07:49working on squeezing this down. The

07:53biggest item that will remain on site is

07:55the decant facility. uh the decamp

07:57facility does not have the potential to

07:59move on to the new uh site that we have

08:03brought on at H Highleberg. Uh there is

08:06not space at that site for that program

08:08and so it will maintain there. The two

08:10others which are the fuel tank and the

08:13mineral bins are under further study uh

08:15and we'll be able to bring more

08:17information. there are going to be the

08:19potentials for um reducing out those

08:23other facilities uh as we continue on

08:26through the project as well

08:31at the new MOC. It's our Am I on the

08:34right side? Did I skip?

08:40Oh, got it. Okay. Sorry. We were we're

08:43making sure we're on the same slides

08:45here. Uh at the new MOC, the prior prior

08:48priority is going to be to centralize

08:50all public works, parks, fleet

08:51maintenance, and fire fleet maintenance

08:53staff at the MOC. Um the consolidation

08:57of this high use program at the new MOC

08:59will include workspaces, training

09:01spaces, fleet maintenance shops, labs,

09:03and frequent frequently accessed fleet.

09:10The new site which we have purchased and

09:12are designing the new MOC on will be a

09:14full redevelopment of the site and

09:16operation structures. It will have storm

09:18water infrastructure, vehicle wash

09:20facilities, vehicle and maintenance and

09:22equipment storage and other ancillary

09:24structures that will support the

09:25operational requirements of our crews.

09:28EV charging and surface parking is also

09:30included. The operations building which

09:33you see on the bottom in blue is going

09:35to be a new two-story mass timber

09:37building and it will house the people

09:39really. These are going to be our office

09:41building. This is going to be our office

09:43building that includes conference rooms,

09:45training rooms, kitchenetses, touchdown

09:47spaces, offices, etc.

09:51and our lockers. Sorry, that's an

09:52important one. Uh the operations

09:54building which you see in orange is a

09:56new one-story building. It will have

09:57shared use shops, labs, warehouse space,

10:00and storage functions. And so the design

10:01build team is working hard with the

10:03crews and the teams out at the MOC to

10:05ensure that adjacencies in these spaces

10:07are appropriate and working to the

10:10greatest um ability. The last is the

10:12operations building, which you'll see in

10:14pink. This is a new one-story building

10:16with um high high bay fleet maintenance

10:21areas, two pullthrough heavy duty bays,

10:23and eight tandem pullthrough medium duty

10:25bays. So this is where all of our fleet

10:27maintenance will happen and this will be

10:29both um citywide fleet as well as fire

10:32fleet is going to uh consolidate on this

10:34site in the future.

10:38Sustainability is a topic of continued

10:40conversation. Uh an important thing to

10:43note is that lead which is the

10:46certification that we discuss most often

10:48in this room is really targeted for

10:51people focused facilities. office

10:53buildings in particular. And so right

10:56now we are targeting the administrative

10:58building as lead gold. Uh it says lead

11:01v5 gold. They just updated their

11:03certifications. And so we are targeting

11:05lead v5 gold. Lead is not

11:09easily applied to maintenance and

11:11operations facilities or things that are

11:13more similar to infrastructure and

11:15public works types uses. And so the team

11:18is actively studying different

11:20certification methods uh to be able to

11:23meet our gold goal of lead gold or

11:26equivalent. And so we want to be really

11:28clear that we are not diminishing or

11:31overlooking our sustainability goals

11:33here, but we are going to have to be

11:35looking at different ways to um attain

11:38them. uh the sustainability manager

11:40Jenny Liebeck and Laida Harris who's our

11:42facilities and park sustainability

11:44program manager are working very closely

11:46with the team to understand what are the

11:48ways that we're wanting to have these

11:50green standards built into the MOC. Uh

11:53and so we are looking at different

11:54things such as Envision which is uh what

11:57Sound Transit uses for a lot of their

11:58projects uh and different zerocarbon um

12:02certifications as well. So this is still

12:04under study. Um but we are shooting for

12:08lead V5 gold on the people building and

12:12then looking at equivalent

12:13certifications for the other facilities

12:15and the site as a whole.

12:19Now that we've talked about schedule and

12:21scope, we're going to talk a little bit

12:23about budget. The new MOC, thank you

12:26Amy, uh is currently targeted at a

12:29budget of 268.5

12:31million. This has eliminated our

12:34dispersed operations need. It has

12:36eliminated the parking garage need and

12:38we have been able to fully incorporate

12:40fire fleet. This number does look

12:43different than what we have talked about

12:45and one of the reasons for that is

12:46because of the purchase of the new of

12:48the new site. Um there were dollars that

12:51were already built into the budget for

12:53dispersed operations and that was helped

12:56cover a portion of it. Um, but finance

12:58has worked with us to ensure that we can

13:00cover that additional $18.5 million in

13:03the project budget so that we can move

13:05on to that new site and fully outfit the

13:07site for the future of the maintenance

13:09and operations center.

13:15To date, we have engaged with city

13:17council um as follows. Uh, we did the

13:21validation contract approval with you

13:23all in Q4 of 2025. We've been doing

13:26quarterly updates. We were with you in

13:28Q1 uh of 2026. In Q2, we did the phase

13:31one approval for the contract. Um and

13:34then we were with you just recently in

13:37Q3 doing a study session update as well.

13:40Looking forward, there's going to be

13:42some decision points for city council

13:44and we want to make sure that it's

13:46understood. Um this graphic is busy and

13:48really small. My apologies, but you'll

13:51continue getting updates on a quarterly

13:53basis through the CIP update. Uh, in Q1

13:56to Q2 of 2028 will be the GMP approval,

14:00which is the Oh, it went away.

14:04There we go. Thank you, council

14:06president. Get the guaranteed maximum

14:07price for this project. And so that will

14:10need to come to council for approval.

14:12And then in Q2 of 2028 will be the phase

14:152 contract which will allow the design

14:16build team to continue their work.

14:22At that this point that is all of the

14:25information that we have to share. We're

14:26happy to answer questions. We also have

14:28Claire and Duncan here who are ready and

14:29willing to answer questions um as they

14:32have are really the experts on the

14:34design build side.

14:37>> Thank you so much team. Uh council who

14:39would like to kick us off? Council

14:40member Sony.

14:44>> Thank you so much. Uh I have a question

14:46specifically with the old site because

14:49it's still going to have our fuel island

14:52tick facility and material salt mineral

14:55bins. Now once everything has moved to

14:58to the new facility

15:00and and when we did took a tour for the

15:03old sai it's still big. So the cost of

15:05maintaining that site with just these

15:07limited um uh you know limited

15:10facilities isn't that going to be large

15:13or is there a plan that eventually these

15:16will also moved to the new MOC site you

15:19know any costing or anything associated

15:21with that?

15:21>> Yeah that's a great question. Thank you

15:23council member. So there are two items

15:25that we're hoping to either be able to

15:27move onto the new site or consolidate in

15:29a different way on the current site and

15:30that's the mineral and salt bins and the

15:32fuel island. And so that's something

15:34that the design build team is actively

15:36exploring is how do we reduce our

15:38footprint on the current site. Decant is

15:40a tricky one. It's a newer um piece of

15:43infrastructure for us. It's in really

15:45good working condition and there is not

15:47space on the new site for that to move

15:50over to that site. Um and so we will

15:54need to maintain it on the current site

15:56or it will be need to be moved to a

15:58different site if we ever wanted to

16:00fully vacate that site. Um the hope is

16:03though to minimize our impact on that

16:06site so that we can surplus some of that

16:08land and sell it so that we're not

16:10maintaining that full parcel. Uh what

16:12that looks like is still to be

16:14determined. Those things are still under

16:16study, but that is the um long-term goal

16:19is to minimize our use of that site and

16:21be able to um surplus that that space if

16:25that is what council chooses.

16:29Did you have a follow-up, Council Member

16:30Sony?

16:32>> So, now assuming there will be a staff

16:34travel time between both of these sites,

16:36I hope that has been taken into

16:38consideration into the budget.

16:39>> These two sites are extremely close

16:41geographically and we worked really

16:43closely with the the staff to understand

16:45what the impact would be of those two

16:47things being separated. This is from

16:51staff's perspective extremely low

16:53impact.

16:55Thank you, Council Vice President. Thank

16:58you, Chair. Um, director, thank you for

17:00that clarification and and, uh,

17:02expanding out on that. And thank you to

17:04my colleague, Council Member Sony for

17:06bringing up the question because as we

17:07were talking, I was uh uh trying to find

17:11in my notes because I was under the

17:13understanding that by purchasing the H

17:16Highleberg property that then we would

17:19be able to have the the current property

17:23go to surplus um and with the

17:26understanding that the TAMP facility is

17:27a phenomenal asset that we have and

17:29understand that we would we would need

17:31to move it over there. So, this is the

17:33first that I'm seeming to be hearing.

17:35So, I was trying to find it in my notes

17:37to to be able to go back to, but I'm

17:40kind of caught off guard because this is

17:42the first that I'm hearing that no,

17:44we're going to hang on to both

17:45properties and decant's going to stay

17:46there. Understandably, but again, the

17:49first that we're hearing it. Yes, I

17:51understand that this um may be a shift

17:55from what some of your previous

17:57understandings were. I was able to meet

17:58with a handful of you prior to today to

18:01kind of preview this because um it did

18:04become clear to me that that was not

18:05something that was fully understood by

18:07council. I can't necessarily fully

18:10account for why that is um as I was not

18:13um in some of those conversations that

18:15were had with you all previously, but

18:17what I can tell you is that we are doing

18:19all that we can to minimize the impact

18:21and to surplus as much of that property

18:23as we can. The only way we could

18:25reasonably move all of everything off of

18:28our current site and onto the new site

18:30is Can you go back to the map that shows

18:32the storm water, please?

18:36Or one of them. I know there's a few.

18:37Yeah, that's a great one. So, the only

18:39way that that is even potentially

18:41feasible is that um is a storm water

18:44detention vault up in the top left. That

18:47would need to be undergrounded into a

18:48large underground vault. And then we

18:50would need to put a parking garage on

18:52this site to be able to maximize that

18:54space. Um, according to our design build

18:57team, um, and if you have more

18:59questions, you can press on Claire a

19:01little bit, Claire and Duncan on this is

19:02that that would be in the range of $40

19:04to $50 million to accomplish those two

19:06things. And so, um, that was not the

19:10direction that was taken, but that is

19:12the only way that that would be

19:14attainable at this point.

19:16>> Thank you. Thank you. Lots of hands. I

19:19saw council member Sony and then council

19:20member for

19:22excuse me council member parsy my

19:24apologies. So um following up on the

19:27questions that my colleagues asked I

19:29think um I also am going to say from my

19:32memory not from my notes I do remember

19:35that um and my memory can be mistaken so

19:39please correct me um I remember that one

19:42of the premise of um the decision to

19:45move to H Highleberg was that we would

19:47be able to surplus this current property

19:51but what I'm hearing now is that decan

19:54not only So I don't have a problem with

19:56keeping decan because of um the it's um

20:00it has further life to live. Um, but I

20:03think we had the understanding and

20:06information that council received that

20:09the decant could be moved to H

20:11Highleberg, but from what I'm hearing,

20:13DECANT actually cannot move to H

20:15Highleberg because of uh the current um

20:19um location of H Highleberg and for

20:21environmental reasons, we can't support

20:23DECAN in H Highleberg as it is. Um so it

20:27would be really helpful to bridge that

20:29gap between um this because I think um

20:32that was part of the understanding as we

20:34purchased the property. So I want to

20:36make sure if it was incorrect

20:38information or how we can bridge that g

20:41bridge that gap it would be really

20:42helpful. And also um

20:46I do recall and correct me if I'm wrong

20:50um that in part of the financial

20:52decisions that we made in purchasing the

20:55land was um the assumption that we would

20:58completely sell this property. So if

21:01that's a change from that plan, I would

21:03really want to make sure that we

21:05document it. And I understand that um

21:07Director Hamilton, you weren't in the

21:09room, but I think there are others who

21:11were in the room and I would love to

21:13make sure that this is a big purchase

21:15and this is a big financial decision. Um

21:17I want to make sure that we have proper

21:19continuity and I understand that

21:21director we lost a previous director but

21:23the mayor was available in the room with

21:25us um at previous times and I do think

21:28it's important to make sure that we have

21:29continuity.

21:32>> Thank you, Council Member Sony. Uh yeah,

21:34can I address to because there were two

21:37pieces to what she um just shared. So um

21:40I agree with you on the budget and the

21:42continuation of that information. Um I

21:46don't like surprising folks. That's not

21:48something I I don't love coming into

21:50council chambers and surprising this

21:52table of um people. Uh I respect the

21:55work that we do together and I hope that

21:56as we move through this project, we can

21:59pre prevent that. And so that's what I

22:01can commit to you and what what Chris

22:02can commit to you as we move forward is

22:04that we can really try to make sure that

22:06we're being transparent and clear. Um

22:09from a decant perspective, uh my

22:12understanding is that the main driving

22:13factor that we are not moving decamp

22:15over is because of space. Um Claire and

22:19Duncan, I don't know if there's

22:20environmental factors that have come

22:22into play and if you could speak to

22:23those uh because I'm not.

42:40propped on to if we can provide it as

42:42part of the project we would love to do

42:44so we're going to balance that with the

42:45other priorities we hear um the other

42:48thing I'd point out is that for anything

42:50battery storage and advanced

42:51technologies the reality is that

42:53technology is advancing so quickly that

42:55if we buy something today it's likely

42:57not the best use of your money. Uh that

42:59technology is getting less expensive. It

43:01is beginning to perform better. It is

43:03getting smaller. There are all sorts of

43:05things that are happening in that space.

43:07That meant that when we had to evaluate

43:09what's the right thing to guarantee as a

43:12validation baseline, scope, schedule,

43:14budget versus what's something that's

43:15aspirational, that's a piece that we are

43:18still holding very very dearly and

43:20really tracking diligently, but didn't

43:22make sense as a as a baseline promise.

43:25Thank you. Thank you. I appreciate that

43:28commentary and the chance to come back

43:29uh and just keep an eye on the subject,

43:31especially since I I do believe our

43:34community's nearest and dearest values

43:35live and breathe at the MOC. Um and

43:38there is uh such a great opportunity to

43:41advance our um emission reduction goals

43:44through the redevelopment of this

43:45campus. So that's for my part. Okay, for

43:47round two, the first hand I saw was

43:49council vice president Nova Kamina.

43:51>> Thank you. um

43:54appreciate the conversation and how we

43:55advanced and we're we're looking

43:56forward. So I I feeling a little some

44:00sort of way about taking us back for a

44:02second because I had a follow-up on uh

44:04the decant and uh maintaining the

44:07existing site with a very scaled down

44:09operation and that was just to get clear

44:12on what are we estimating the remaining

44:15life on our decant. So then we're

44:16thinking about how long would we be

44:18hanging on to at least a portion of of

44:21that property. Um so we can already

44:24start somewhat thinking about or maybe

44:26holding in our back pocket the the idea

44:29of um when when it comes time to surplus

44:32was this cost taken into consideration

44:35while coming up with the budget. Um uh

44:39so if we are not you know if you're not

44:41planning to sell then does it impact our

44:43budget like you know where's this gap

44:45going to be filled?

44:46>> That's a great question. Um we don't

44:48have a current idea of the full value of

44:50the site. We haven't done any studying

44:52on that. Um as far as I know and I'll

44:55look we have not taken into account the

44:57sale of that property into any budget

44:59whether it bec or otherwise. So per code

45:03that the sale of that property goes back

45:05into the CIP budget. we have not

45:07accounted for that sale in the CIP

45:09budget as we see it. So there's no hole

45:11to fill and so it'll be under further

45:13study of you know how do we parcel it

45:16out? What's the total sale and and how

45:18is that money used?

45:20Yeah, I apolog

45:26uh for you know for the pond in case if

45:29you want to move the decan facility

45:31there and then the reason why I was

45:33asking this cost is like if it makes

45:36more sense to have uh you know

45:39everything there together based on like

45:41the cost of this thing if it's like

45:43selling and then building up there as

45:45one one property versus this

45:48>> and um uh for this property. There was a

45:51second uh concern was because of the

45:54underground contamination.

45:56So, you know, I may want to hear more

45:59about that if that has been taken into

46:01considerations and what has been and any

46:03update on that part.

46:05>> Uh we can have further conversations and

46:07share more information with council. uh

46:10as we went through validation and

46:12understood the cost and the impact of

46:15undergrounding that storm water and not

46:18just as CLA was sharing not just on our

46:20budget but also on our environmental

46:22goals and um the embodied carbon that

46:25that puts into the site. Uh we did not

46:28explore a whole lot more past that

46:30because the determination was that that

46:32was going to be a really impact.