2026-10-08 - Planning Commission

Summary

Built from YouTube captions (manual); the agenda and minutes were not read. Part 1 of the video covers the briefing session before the 2:30 PM public hearing and ends at adjournment for the hearing; the resumed preview is on Part 2. Names and figures are as captioned and may be misspelled.

  • Format: the Commission met in a retreat-style session, taking staff briefings so items could be initiated in two weeks, then a high-level preview of the afternoon hearing agenda.
  • Zoning ordinance cleanup: staff requested initiation of an eight-item technical cleanup for November 2026 covering articles 2 to 5. Items included changing Architectural Review Board determinations from "decides" to "recommends," sending undersized lots in the multifamily neighborhood school district to a conditional use permit instead of a variance, marina use-table updates, re-adding retail goods in pedestrian commercial overlays, a conditional use permit for vacation rentals of up to nine units, aligning the accessible-parking list with definitions, raising the short-term rental sign allowance from 2 to 4 square feet, and correcting corner side-yard fencing in historic and cultural districts. No vote; initiation was planned for October 22. See Zoning Ordinance Technical Corrections and Clerical Fixes.
  • Resilience quotient, phase two: staff proposed turning the resilience quotient from a mandatory checklist into an optional incentive program. Single-family requirements would keep elevation and water capture and tree planting but drop the generator and solar pigtail. Non-residential projects would earn incentives such as faster review, height, setbacks and parking reductions for larger resiliency investments. Staff also proposed removing the coastal resilience overlay's extra foot of mechanical and electrical elevation and the pervious-parking requirement. Commissioners raised concerns about trading housing for flood protection, asked for broader advocacy-group input, and requested estimates of affected projects and developer uptake; staff said the development community's top priority is review speed. See Resilience Quotient Zoning Amendment.
  • Faith-based housing amendment: staff reviewed the text amendment implementing the state law, which takes effect January 1, 2027 and sunsets January 1, 2031, with four eligibility requirements and simplified development standards. No vote. See Faith-Based and Nonprofit Housing Zoning.
  • Data center amendment: staff summarized revised definitions for small-scale (under 30,000 square feet and 25 MW) and large-scale data centers, permitted and conditional districts, and three performance standards (state-code assessment, noise compliance and equipment shielding). Commissioners asked about cooling-water runoff and closed-loop systems. No vote. See Data Center Zoning Standards.
  • Marijuana business amendment: staff walked through a roughly 50-page red-line covering dispensing, testing, retail, cultivation, processing, manufacturing, microbusinesses and transporters, all by conditional use permit with indoor-operation and security requirements and 1,000-foot buffers for dispensing. No vote. See Marijuana Business Zoning Categories.
  • Hearing preview: staff briefed the afternoon consent and permit items, including the airport terminal design review, Dockside Social, Boss Queens Soul Cafe, Martin's Soulfood, the juice bar banquet hall and the Dutch Bros continuance to October 22 over a deed-restriction issue with the awning. See 2026-10-08 - Planning Commission Public Hearing and Dutch Bros Drive-Through at 1501 East Little Creek Road.
  • Barraud Park dugouts: two new baseball dugouts matching the park's new pavilions, which the Architectural Review Board recommended 7-0. See Barraud Park Dugouts Design Review.
  • Slover Library permit: staff presented a conditional use permit for a banquet hall with live entertainment and on-premises alcohol consumption at 235 East Plum Street, a city-owned facility whose rentals have expanded. Alcohol is provided by caterers or renters with banquet licenses, not sold by the library. Hours 8 AM to 11 PM, room-by-room occupancy caps (300 in the largest rooms, fewer with a dance floor), and a security guard and staff required for each event. See Restaurant, Alcohol and Entertainment Conditional Use Permits.

Related: Zoning Ordinance Technical Corrections and Clerical Fixes, Resilience Quotient Zoning Amendment, Faith-Based and Nonprofit Housing Zoning, Data Center Zoning Standards, Marijuana Business Zoning Categories, Barraud Park Dugouts Design Review, Restaurant, Alcohol and Entertainment Conditional Use Permits

Agenda

Agenda not yet read.

Sources

Video

Watch the video

Transcript

These are manual (human-made) captions; names and numbers may still be misheard.

Transcript

00:06Um, our first presentation,

00:10I don't think Boston's

00:12Um, we can flip it.

00:14Let's flip.

00:16And just to provide, um, some

00:19try to figure out how we're

00:21quickly and efficiently

00:23We're going to do our

00:25Austin's here.

00:27Um, we're going to work through

00:29so that we can get you briefed

00:31working on, and we can get

00:35After that, we'll do the public

00:37hearing preview for for our 230.

00:41Rob will walk you

00:42We won't go as quickly as we

00:45it's been a little while.

00:46So I'll have them walk through

00:50then we'll go into the more

00:53for two weeks from now.

00:55If we come up against time, we

00:59we'll head upstairs to the

01:01pick back up the briefing after

01:03the public hearing

01:06Okay. All right.

01:08I think that the printer issue

01:14please pass it around.

01:17It looks like somebody loaded

01:19the wrong paper

01:21So it's very thick.

01:23It's still really

01:24Very nice.

01:28So as Bobby mentioned

01:33this is a request to initiate

01:37Another zoning

01:39I know you guys.

01:40You guys tolerate the cool new

01:44everything exciting to.

01:45I know this is what you really

01:48able to be here again,

01:51Uh,

01:53as, as always, this is a

01:56inconsistencies and Season.

01:57Omissions that we come up, that

02:01of about a year, six

02:03Although as we go, it's getting

02:07there are eight, this time

02:10four, and five of

02:12And again, to reiterate

02:16discussed here.

02:17This is all just errors or

02:20over the past eight years.

02:21Now

02:23we find less and less of the

02:25But believe it or not, there

02:28just haven't, you know, had

02:30really look at in the

02:33So I'll just go through

02:35And as always, please just feel

02:37over any of these

02:40So first, the zoning ordinance

02:43Review Board decides

02:46appropriateness when they are

02:49to the zoning administrator.

02:50It is technically a zoning

02:54And the word decide is a little

02:56misleading and

02:58It's also misleading for how

03:03in a case like that.

03:04So we just wanted to make

03:06little bit.

03:07Um, and for those of you

03:09determination of architectural

03:12simplest way to describe it is

03:16COA if you don't need a

03:18But we feel that it would

03:21architectural or the

03:25If something is architecturally

03:27for that.

03:29And it's baked into a few

03:30ordinance, but there's never

03:32really cause for

03:34So you may not know.

03:35Um, secondly, currently

03:40multifamily neighborhood school

03:44to develop an undersized lot

03:48This was a little bit of a, it

03:51came with that text amendment.

03:53I believe it was a year and a

03:56variance process to the CIP.

03:57So we're just coming back

04:01undersized lots and mfns go to

04:05single family home like they

04:09family districts, because at

04:11only be able to build a single

04:13Only undersized single family.

04:15Yep. Only undersized,

04:17Which is very common in Mfns.

04:19There's a lot of

04:22And a lot of a lot of those

04:26long time ago.

04:27They were all platted on 25,

04:29undersized lot in

04:31Um, third they use tables

04:35performance for the Marina

04:37So we came back with a, a,

04:42included a few things, but

04:45for marinas.

04:46Um, it would be easy to blame

04:49people didn't review it and

04:51update the tables.

04:52So it was a group effort there.

04:55So we're just going to go back

04:56correct that.

04:58Fourth. This is one of the true

05:01Retail goods establishment is

05:04in the pedestrian commercial

05:07That's clearly a mistake.

05:08Those are designed to be

05:11for a human being walking on

05:13their own two feet

05:15There is not a more friendly

05:19So that was clearly a mistake

05:22over from the 92 ordinance.

05:23So just going back to fix that.

05:24Yeah. In 2017 and 2018 when

05:27So this was a true mistake

05:30because of course, retail is

05:31allowed in pedestrian

05:36Uh, fifth, the zoning

05:39And this is another

05:40The zoning ordinance does not

05:43with up to nine dwelling units

05:47rental in the G one

05:50Now, G one to kind of give

05:52That's the Monticello district.

05:54So I don't know exactly where

05:57about the Frank Spicer building.

05:59And then the northern boundary,

06:03about the railroad just in

06:06between that

06:09Uh, and in most zoning

06:14vacation allowed for

06:16allowed for multifamily, any,

06:19any number of dwelling units

06:23I actually forget the, it's

06:25conditional use permit in any

06:28require conditional use permit.

06:30There's a few others.

06:31There's a list G one

06:33So we just want to make

06:35So it's treated the same as

06:38Uh next, the zoning ordinance

06:42that are considered

06:44under the Ada and the

06:45requirement for

06:47Uh, it is worth noting, we do

06:50section correctly, but not in

06:53So we're just going to

06:54Make sure that section

06:57Um, and you know, Ada, uh,

07:02for short term rentals conflict

07:05permitted for residential

07:07So currently in your

07:10you're only allowed

07:11This isn't always compatible

07:15signage that we have to put up.

07:16So the contact info that goes

07:20you know, posted near the front

07:23fence or a mailbox or

07:25Um, so we're just going to

07:282ft to 4ft to make sure

07:31allowance in order to

07:34Um, and then finally, the, this

07:38ordinance that we just

07:41The corner side yard fencing

07:43and cultural conservation

07:46Um, it currently says you can

07:49on the property line, which is

07:52And it was not that way in 92.

07:54Um, it's just it's

07:56We haven't really seen this

07:59seen has either not been right

08:02districts, or it's been

08:05So any time, you know, it's an

08:08like for like, we haven't

08:10to look at that

08:12Um, and that's the list with

08:15that, I stand by

08:16Are there any questions

08:20All right.

08:21Thank you.

08:28And I'm laying odds on whether

08:30goes up.

08:31Because usually it's now that

08:32we find 3 or 4 more

08:37So good afternoon commissioners.

08:39Um, I want to walk you

08:42development standards

08:45phase two.

08:46In the past, we've talked about

08:50I think at this point we're

08:52be done.

08:53And so I just want to talk to

08:56next with this.

08:58Specifically regarding the

09:00where we're really

09:02So just to refresh your memory,

09:06you about some deficiencies we

09:12of the development standards

09:14zoning ordinance, specifically

09:16dealing with some

09:20That's where we resulted in

09:24additions that were never quite

09:26spelled out as

09:28So that was what we had talked

09:30some unnecessary and some

09:32We also talked to you about the

09:35quotient and some thoughts that

09:39So to date, we have

09:42So in October I'm sorry.

09:43On August 25th of this year,

09:48set of amendments, and that's

09:51It's reflected online.

09:53Um, all those things we did

09:57of amendments.

09:58Um, so the next set is needed

10:01quotient, uh, and fix some

10:04things that we

10:06But we'll just, we won't talk

10:08Um,

10:10so just to, again, when we talk

10:13standards, it sort of

10:15Um, development standards

10:21that are highlighted in yellow.

10:22Those are the key changes we

10:23did in phase one

10:28We took those um or not

10:32We took those out and put them

10:34in better places

10:36So we now have a

10:38We can use for something later.

10:39And then 5.1 used to be what we

10:42We took a lot of those

10:45them to a more appropriate

10:47we replaced it with a new

10:49additions and site improvements.

10:51So now the next is to look

10:56So today the resilience

11:00is required of all new

11:02development substantial

11:05Um it is so so new single

11:11building, new commercial

11:15um, substantially

11:18All of these things require to

11:21one form or another.

11:23For single family development,

11:25elements that we apply to

11:30above grade.

11:31There are several areas of

11:33If you're in a flood zone,

11:35If you're in the traditional

11:36be higher.

11:38Um, but at a minimum, anywhere

11:41um, You have to capture

11:43That's the old rain barrel,

11:48modified this a few years ago,

11:51number of trees.

11:52Um,

11:54and then third, provide a

11:58solar, um, what they call

12:02Um,

12:04that's for single family, for

12:07to elevate to 16in.

12:09And there's provisions for

12:12that, but you have to elevate

12:16have to capture the first inch

12:21table of improvements and for

12:25you need.

12:26Um, or you can achieve lead

12:30certification or adaptively

12:33which we do see a lot of those.

12:34The adaptive reuse is they

12:37resilience question.

12:39Um, that's the way

12:45So

12:47Bobby's going to fill in here

12:50So the resilience quotient.

12:52Sure.

12:54So the select improvements

12:56The whole point was to let that

13:00were going to capture water

13:03development requirements, which

13:07different items include

13:09flood resilience, stormwater

13:10resiliency, energy

13:14Risk reduction.

13:15Risk reduction.

13:16So, um, and so that is

13:20the goal was to say there's

13:23there's a, there's another way,

13:25your money in either way

13:29For context, we were given

13:32Housing Commission and

13:34members of City Council and

13:38look again at the resilience

13:41it and also, um,

13:45turn it from being a

13:50bonus program.

13:52So where the

13:53So the reason why is because

13:56changes that were done to state

14:00resilience in the building

14:03resilience and, um, with the

14:05changes to the state

14:07So we didn't want to feel like

14:10stacking on extra requirements

14:13new requirements added recently.

14:15And so we were told to either

14:19make it where it could

14:21And so we're working to try

14:24bonus with this.

14:25So so to do that,

14:29And this is again

14:31And we can we're still

14:34Um so for single family

14:39keep the water capture,

14:41Those are very beneficial.

14:42We don't want to

14:45Um, but we do want to remove

14:49generator hookup that the

14:52it's been problematic, um,

14:57Uh, there's, there have been

14:59with the changes in code, it's

15:02Um,

15:04yes, ma'am.

15:05I just wanted to clarify,

15:07You said it was posing.

15:09What problems?

15:10The generator.

15:10Solar hookups.

15:11So the generator

15:13We've had a couple of

15:15development community.

15:16One of them being, um, people

15:19the generator.

15:20They tend to go on the panel in

15:21the garage or just

15:23And those who don't necessarily

15:26generator, oftentimes I'll put

15:29which is bad.

15:30Um, things like that.

15:31They oftentimes are on that

15:33side yard where

15:35There's not room

15:37So you put it over there.

15:38Now you're overhanging

15:40We've had some issues

15:42There's also been discussion

15:46necessarily the best solution

15:48in an area that's

15:50And so a lot of this is a

15:52That's for everything.

15:54If you're, if your house is

15:58to the outlets and you generate

16:01You've electrified the

16:03So there's definitely been

16:07I mean, obviously, I think the

16:09about the, the, the

16:11Um, but as we worked with

16:15necessary, it has been a very

16:16successful requirement

16:19And perhaps there's some

16:21there without that.

16:22What about the solar.

16:24It's all the same technology.

16:26And so this wouldn't prevent

16:29house to solar.

16:30This would it's the same

16:32hookup essentially that you

16:36into the same connection.

16:37So there's no reason that you

16:41don't want to make

16:46I probably have more

16:49Okay.

16:50Um.

16:51Going back when you

16:54Yes. Are you specific

16:57There are specific requirements.

16:59There's a number of trees that

17:02maintain as per

17:05And I don't have it memorized,

17:08it is specific size.

17:09It is there's a, there's a

17:11large trees.

17:13And how many you have to have

17:14you do.

17:16And so we, we added that a few

17:20the rain barrel provision just,

17:24tend to grow legs and

17:27They also tend to not be

17:29maintained by the

17:30And so once the rain barrel is

17:34you if you don't drain it.

17:35And so instead, let's get

17:39Let's incentivize them.

17:40Let's incentivize the

17:43That's our priority number one,

17:45incentivize the planting of

17:48us than a rain barrel.

17:50We have the capacity to

17:54That's working out.

17:55On a regular basis.

17:57Um, I don't know if that, if

18:00we check it at the CEO to make

18:03certificate of occupancy.

18:05So.

18:06Um, I've had experience with

18:08house because we were within

18:14you know, there was

18:17And in fact, the trees did die.

18:21I just was curious about that

18:22because I would

18:24It is a.

18:25I recognize it's difficult to

18:31it's troublesome to me that

18:35don't make sure that

18:38that's being followed through.

18:40Yeah.

18:41It is something we are we are

18:44requiring and following up

18:47And we do now do that fairly

18:51removed on commercial

18:52plan process and

18:55I know the cbpa situation.

18:57They do.

18:57They they are taking

19:00Are we enforcing it on the

19:01individual single family houses?

19:03I think unless we

19:04If something.

19:06If one went away five minutes

19:10We would probably catch that.

19:11But yeah, it's it's definitely

19:14enforcement challenge.

19:17But I'll point out that has

19:19couple of years.

19:21Um, and then so for all

19:25indicated, the, the plan would

19:29quotient from a strict

19:31program, and the options would

19:34be, again, a selection

19:37Very similar to what's

19:40So some, some some significant

19:44like you to make to the

19:47resilient in general.

19:48And, um, I don't necessarily

19:51things that we're looking at,

19:54would make a property more

19:57Um, in exchange for that,

20:01you can choose from a set of

20:05reduced review time.

20:07Um, so particularly the site

20:09review process.

20:11Um, that is something that the

20:13us they think would be

20:16Um, comes down to your bottom

20:19increased height, reduced

20:21setbacks, reduced

20:23We've talked about a number

20:26we're still kind of testing

20:29But the idea being that in

20:33beneficial, that we would give

20:39making your project a little

20:43and anything you wanted to add.

20:46Yeah.

20:47What we also did is we set

20:50little bit easier to apply,

20:54noticeable differences, as

20:57could see and would be able

20:59So we've added things like if

21:04now, if you paid less and you

21:08would normally do, you could

21:12on reducing your setbacks.

21:13If you restored the Chesapeake

21:16buffer to a certain percentage,

21:20will shift your development

21:22to to reduce setback

21:24So we're trying to be very a

21:27it's more tangible.

21:28Um, that way we can see it and

21:30we have and the

21:33in the full development.

21:35It was hard.

21:36Some of the things in the

21:38were already requirements of

21:42the building code was updated.

21:43So people were just checking

21:46they weren't actually

21:47I was like, oh, I have to

21:51and do that already.

21:52I have to put install energy

21:54efficient specific

21:56Well, I have to do that already.

21:58And they were just checking off

22:01earning, but they were already

22:03required it.

22:04And so we were trying to

22:06So a lot of this is more, um,

22:10to keep track of when they do

22:13we can watch and have

22:15So yeah, we did an analysis on

22:18what we're getting out of the

22:20commercial scale properties

22:24are already things that they

22:27simply, if they're doing a

22:30the stormwater pond slightly

22:33more water.

22:34And so it's just the, the

22:36as, as much as we would have

22:37liked to have gotten

22:40Now as part of that, we're also

22:42the easy thing.

22:44There's nothing, I think after

22:46There's nothing wrong with

22:48water, then you can qualify to

22:52else because you're

22:53So that's still on the book as

22:56that gets you the most points.

22:58We want you to capture more

23:01handle it.

23:02And then a couple other things

23:06things like that to a certain

23:08similar to what

23:10So again, we're trying to right

23:13more tangible that someone

23:15And hopefully the developer

23:19And then we can in turn, see

23:22little bit more.

23:26Uh, two more slides, just

23:28And then.

23:29Okay.

23:30Then I'll hold.

23:31Okay. Additionally, there's two

23:34want to address that are

23:38this, but not directly in

23:40Um, one we right now we have a

23:45foot of elevation for

23:47electrical and

23:49Um, and so if you're required

23:52building a single family house,

23:54feet above the finished floor

23:57above the flood elevation.

23:59The coastal resilience overlay

24:03that mechanical or

24:05Um we're proposing to

24:07It adds a level of complexity

24:13Um and also in the coastal

24:18requirement for

24:21And the challenge with that is

24:26to flood, pervious parking

24:28spaces are not what

24:30They end up actually causing

24:33And that's what the

24:36Our stormwater team

24:38And we.

24:39So consequently we don't.

24:40We oftentimes just waive that

24:43good intervention if you're

24:46prone area.

24:47You'd rather just sheet flow

24:50stormwater system.

24:52Um, and then just, um, other

24:57a few things with the

24:59So we're going to fix those

25:02A lot of references to

25:04So we have found references

25:07clean them up.

25:08So that is the idea initially

25:12phases and kind of that

25:15Um, what we don't

25:16We can do it all at once.

25:18That's already pretty much

25:20finish up the

25:21So that's the intent is to

25:24So from a next step standpoint,

25:29on the 22nd.

25:31Again that's just um approval

25:34we've already been doing and to

25:36would be to advertise

25:39Um, we do need to finish

25:42We have been doing coordination

25:45We have spoken with several um

25:49this on a daily basis and

25:53from them.

25:54We need to, we need to keep

25:56We've also talked about this

25:59Building Industry Association,

26:03And we have a meeting with

26:05weeks, and we want to go back

26:08Um, we think that that

26:11outreach that we need to do on

26:14those who are using it on a

26:17that it is doing what

26:21And with that, I'm

26:25Okay. Go ahead, Mr. Baker.

26:28Oh you don't.

26:29Okay, I do.

26:31Um,

26:33I am not a civil

26:38I can appreciate what the

26:41especially as we, you know,

26:44seem to be still in

26:46Um, but what I don't want to do

26:48is trade housing and

26:54just to put it simply, um, we

26:58edge of resilience and I'd

27:02Um, and so I can appreciate

27:07Um, but I was wondering, what

27:11Um, and also, um, and civil

27:16we've included our

27:21other advocacy groups, folks

27:25water for good or

27:28And I wonder if there's, um,

27:33voices into this conversation.

27:36I think I know what I want to

27:37see, but I'm not

27:40So, um, is, is will there be

27:45other folks for maybe a.

27:49We can, if that's the direction

27:51push this to December and

27:55where we're working towards

27:59council members that have have

28:02administration, but, um,

28:07As for the first the first part

28:11the, our analysis shows that

28:15It's not providing any.

28:17It's not providing any or very

28:21change in code, as

28:23One of the main things they

28:26the 110 mile per hour wind load.

28:29In most buildings.

28:30Now it's 130 mile per hour.

28:31Wind load is the minimum

28:33so easy check off for them.

28:36They've already got their

28:38we're getting nothing out of it.

28:39And so the hope is that by

28:43making it something that is

28:47them and get some really

28:51Because even those that are

28:54just check off, they are tend

28:57things that don't

29:00And we're not getting the big

29:03what we wanted to get in 2018.

29:04When we wrote this, we

29:07interventions that

29:08So we're by removing all the

29:11the big ones subject of an

29:15real incentives.

29:17And the.

29:18And the discussion that we've

29:21that we have here may

29:23I mean, one of the things we've

29:26not something we can do with

29:28can do as a city administration

29:32that would incentivize someone

29:34to do, make some of

29:35So the idea is to really

29:40eliminating the the

29:42That is all they're

29:45And I'm a huge

29:47I think I've said it several

29:49years is that when we work

29:52a decision, people get

29:57as well.

29:58Um, was concerned, still

30:03solar hookups.

30:04Um, I think as we're right in

30:09as well, that giving people the

30:14lowering the barriers to

30:18Um, I would hate for

30:21Um, anyway, from a first

30:25questions and I'm not an expert.

30:27I think I know enough to

30:30So if maybe inviting other

30:33And I think we can look at some

30:37because on the single family

30:39some options that might

30:41multifamily might incentivize

30:43the placement of those

30:46I think the challenge has

30:49proven to be problematic,

30:51incentivize that or

30:54Um, something we can absolutely.

30:55We've, we've talked

30:57So something we can

31:01I hope that makes sense to me.

31:03Uh, commissioners,

31:07I'm having trouble equating

31:11same level.

31:12One is using

31:15sustainable energy, one

31:19So the hookup is

31:23You know, when you're talking

31:24about space requirements

31:27I just I was just puzzled why

31:29generators were

31:33I mean, it's nice for people to

31:35sure where it ends.

31:37So the concept of resilience

31:39hurricane and power was out for

31:42resilient thing that everybody,

31:44available to them.

31:45That was the idea

31:47they would have even better.

31:49Yes, yes.

31:52Just a quick question, because

31:55You know, for our short term

31:58require the Hvac to be up so

32:02requirement, does

32:04It will slightly.

32:06Um, uh, There were some that

32:10were built after 2018, but

32:15added to add an additional foot.

32:18And so someone had a pretty new

32:20to elevate their Hvac unit.

32:22So that's, that's where

32:24But we would still require them

32:27feet above the base flood

32:30But it'd be the same as

32:33As a regular.

32:36Increase. Correct.

32:38Okay. Thank you.

32:40And I think one other thing I'd

32:45the changes that are proposing,

32:49affect and I'd like obviously

32:53likelihood that

32:56choose the option of being more

32:58resilient over just

33:00And, and that's part of the

33:03with the civil engineers to see

33:07be comfortable with what would

33:08actually move the

33:10What incentives could we give

33:13make these improvements?

33:14And that was exactly that was

33:17the the group of engineers that

33:21you what, what what do you want?

33:22What do you think your clients

33:25these things into

33:27And the number one thing we

33:32will speed things up.

33:33I would add that cost is a.

33:37Can you tell me.

33:40That this cost versus putting

33:45higher cost, you know,

33:48you're going to lean towards.

33:50That was definitely

33:51Cost was definitely

33:52But surprisingly, actually, um,

33:55that we heard from everybody

33:58things up

34:01because there is a

34:04In X Pay this

34:06You're okay.

34:076 to 12 months.

34:08You pay this amount?

34:09Well, I mean, there is a cost

34:11factor involved in that as well.

34:12Carrying costs on the loan and

34:16gets things moving.

34:17So I was thinking about maybe

34:21larger developers

34:24you know, those cost cutting

34:27what, I don't have to do

34:29We'll just do it

34:31And that doesn't

34:34I'm afraid that it could

34:37more housing, but then

34:40Yeah. I mean, part of our

34:44the things that we required in

34:48building code or in stormwater

34:51So a lot of the things that

34:54this are already there in code,

34:56so they're required

34:59without the resilience quotient

35:02when we wrote this.

35:03And that includes flood

35:05That includes resilience

35:07So that's part of the part of

35:10they're already required to do

35:12And so do we require them to do

35:15even more above and beyond that?

35:17Or do we flip it to make it

35:19find, find ways to get

35:22That's the conversation

35:24I think maybe broadening more

35:28would be helpful.

35:28And then maybe just,

35:32estimated impact that it could

35:35me to know to make

35:37Okay.

35:56All right.

35:56Good afternoon.

35:58Commission. I'm going to go

36:00but also give you the

36:02this is our preview for

36:05The items that we presented to

36:10in the middle of September.

36:11So just going over all of them

36:13little more in depth than I

36:15the updates.

36:17Um, the Norview airport, the

36:19going through several changes

36:24century and functionality.

36:26And those went to the design

36:29you for final approval.

36:30These are the consent agenda

36:33Uh, Vaso Wine Social is doing

36:36alcohol sales and off premise

36:40They own vino culture at 130.

36:43Um, they do off premise

36:46and they want to do some type

36:50at this second location

36:52So they're linked, they have

36:54they're just doing

36:57Now.

36:58Akella LLC is a duplex at

37:02With multifamily structures, we

37:05structures to be available

37:09tenant's primary address.

37:12So you can't get a multifamily

37:14occupy both units

37:16Um, so both units are going

37:19rentals, vacation rentals.

37:22And then 3624 day street is a

37:25four bedroom single family home.

37:26That is the applicant's

37:28They are looking to do a

37:31this location,

37:33which was continued from the

37:38September now, October 8th, um,

37:42owner's request to talk to the

37:45of the business to try to get

37:48figure out a way to mitigate

37:50Again, upstairs

37:52There's an art studio and a

37:55require a little more,

37:59Um, the applicant has agreed to

38:04no earlier than 7 p.m..

38:06Um, as well as eliminate the

38:11Um so both of those

38:13There are also two other

38:15between the tenant and the,

38:19the property owner that we

38:22realistically enforce or are

38:26which include lowering the

38:28the facility to four

38:31I don't know what height

38:33speakers are kind of close to

38:36sound up and make

38:38Um, and also interior sound

38:41levels, keeping it

38:43Um, we can't enforce that.

38:45Um, you know, from our

38:47going in there with decibel

38:50level they're at, but that's

38:52can, can work with the property

38:55Um, the other tenants are happy

38:58proposed, but they're not sorry.

39:00The other businesses are happy

39:02be proposed and included, but

39:04they still feel

39:06The operation of the Wrekin

39:09their business and possibly

39:13I have letters that were

39:14included as part

39:18so they should they will be on

39:20to the public.

39:22If you have any questions

39:23I believe the at least 1 or 1

39:27to attend the public hearing

39:31and if there's others.

39:34Uh, boss Queen Soul Cafe

39:38Sorry, I should have

39:39Recommending approval of

39:42The reason I'm mentioning it

39:44were recommending a

39:46Um, given the applicant's

39:50conditional use permit for the

39:53three years, um, as well as the

39:58closing by 11:00.

39:59So previously they were

40:01Issue and she wanted to have

40:04required her to be classified

40:05as a nightclub by

40:07She didn't want

40:09So she's closing at 11:00 now.

40:11But again, with this change,

40:15entertainment options and

40:18you get to run for everything.

40:19Even if she hadn't

40:21But both those factors combined

40:24staff's recommendation

40:27Uh, Martin Soulfood is going

40:29where the former

40:32Um,

40:34they're doing a restaurant

40:36entertainment and

40:39You recall possibly during

40:45reason that Uno's formally, uh,

40:48requested a change in

40:51denied by council was

40:54I'm going to say tailgating,

40:57events because the Uno's

41:00So people were pulling up in

41:02alcohol and drinking in

41:05adjacent property parking lot.

41:07Um, and Uno's didn't think that

41:12So this application, uh,

41:17conditional use permit, uh,

41:21information, the same

41:24operators, two owners of that

41:27and another owner has joined

41:29one of the other

41:31Um, so that's really the only

41:34approved last time by council.

41:36Martin soul Food and what

41:40Um, they are all aware of the

41:42they are aware of

41:43We've said it multiple times

41:45parking lot, make sure that

41:47parking lot because of their

41:50We've explained that

41:55Dockside social.

41:57This is the former Max barge.

41:58They're doing restaurant

42:00entertainment and

42:02You recall I think it was 2025.

42:05We had an applicant come in to

42:10new ownership.

42:11The gentleman who owns

42:13supposed to go in there.

42:15He never did.

42:16Um, we don't know

42:17Uh, but we have a new

42:21Um, they were the former

42:24the East Beach in East Beach.

42:26Um.

42:29They have been working with the

42:32sure that the impact of their

42:35minimal as far as it can go.

42:37Um, the Highland Park Civic

42:40support for this application.

42:42Um, assuming the conditions

42:46report are upheld, um the

42:50uh, Closing the outdoor dining

42:53and 10:00 Friday and Saturday.

42:55Not having outdoor live

42:59garage door closed at all times.

43:00There is live entertainment.

43:01Again, we have an area where

43:04that goes directly to

43:07And um, Max barge did sorry,

43:13those conditions and updated

43:15And so we do have that letter

43:16of support from

43:18I do believe there will be a

43:20water coming to speak at the

43:27because of his experience with

43:31saying that it was too loud

43:33even if there wasn't

43:35Um, I encouraged him to come

43:38for the new applicant, um, you

43:41any issues or any specific

43:44might be outside

43:45They can talk about that

43:48between them.

43:49Um, I don't think he's

43:50business being there, but he

43:52enjoy the peace and quiet of

43:57BJ Juice Bar is a banquet hall

44:02on premise.

44:03They don't function

44:04They function primarily as

44:07small space that in times where

44:10juice, they want to be able to

44:13They rented it out a small.

44:15I think the applicant said 20

44:19they previously came through

44:22None of them had alcohol, and

44:26at the ABC records.

44:27There was no alcohol

44:29So he's still been renting it

44:31flexibility to have alcohol if

44:35banquet hall style

44:39operation. But we haven't had

44:40any issues with him

44:42And, um, it's been a small

44:46that they've been rented out.

44:49Last but not least,

44:51Coffee? Sorry.

44:52Dutch Bros.

44:53Coffee. They are being

44:56public hearing.

44:57That is because they

44:59diligence, a restriction in the

45:01put anything within 30ft

45:05While the building was

45:07They wanted to put an awning

45:09that 30 foot encroachment.

45:11And I guess they've determined

45:14the awning from

45:16So they're trying to rework

45:19they're not sure if it's going

45:20back a couple feet or if it's

45:24the whole site.

45:25I think they're working

45:26I hope to have it in in

45:30But they're being

45:32And then we have initiation for

45:34for the faith based housing

45:36presentation on at the

45:40Any questions?

45:52Commissioner will go into the

45:56public hearing.

46:02Good afternoon.

46:03We have one design review

46:07Um, back in December 2024,

46:10reviewed for larger

46:13construction at the park.

46:14So this is adding just the

46:17baseball dugouts

46:20here, the existing

46:24and baseball field.

46:26And then here's one of the new

46:28pavilions that has

46:29The goal is to construct the

46:32same materials that's been

46:38Um, here's the demo plans.

46:43And then here's the

46:47So the two existing dugouts,

46:50benches, will be demolished,

46:53steel column framing and a

46:56metal roofing.

47:00And A or B voted to recommend

47:07Any questions?

47:25Good afternoon commissioners.

47:27This is the Faith and Housing

47:30presented to you at the

47:33Um,

47:35as a reminder, the law becomes

47:40Sunsets January 1st of 2031 and

47:45mixed use and residential

47:48nonprofit and religious

47:51You have a copy

47:54It reads.

47:55The zoning administrator shall

47:58certificate to development

48:01owned by tax exempt religious

48:06property tax exempt nonprofit

48:09code requirements specifically

48:13parking, height, density and

48:18certain standards, including

48:22floodplain and the Chesapeake

48:26not apply to land zoned

48:31So as a reminder, the four

48:36that the property has to have

48:39organization for five years

48:41application, and at least 60%

48:4580% or less of the am I for

48:50sale units and three.

48:52The land is served or planned

48:55meets all applicable

48:57archeological, transportation,

49:01And lastly, all housing built

49:04property taxation following

49:08approved under this bill is

49:11in accordance with NF k 2050.

49:16So the development standards

49:19simplified than they were at

49:24just to make it a

49:26Um, so the building height

49:30building within 500ft.

49:31And this does not include

49:34additional height via special

49:37of 20 units per acre or the

49:41project within 500ft of the

49:45setbacks or the smallest

49:48existing property within

49:51And at least 70% of the

49:55residential, and the remaining

49:58gross floor area may include

50:02nonresidential facilities and

50:05one parking space

50:11Lastly, the limitations

50:13The by right rule does not

50:16adjacent to industrial zone.

50:17So for us, that's IIGIW,

50:21I'd w, b, c o and BCI and

50:28and projects already in

50:30this year and

50:35And that's all I have for you.

50:37Any questions?

50:55All right.

50:55Good afternoon.

50:56Commission. Um, there's been

50:58original language for data

51:01about at the last month.

51:04Um, as a recap, we're going to

51:07center small scale facilities,

51:09scale facilities.

51:10Um, the small scale facilities

51:13surrounding area and

51:16We kind of start to see the

51:18noise and strain

51:21Uh, we also wanted to designate

51:24they're allowed and then create

51:29So the definition for data

51:32facility that specializes in

51:34or related equipment used to

51:37digital data.

51:38The key thing with here it's

51:41area and requires less than

51:45given time.

51:46Originally, the power

51:49That was way too high.

51:50We realized we needed to turn

51:53aligns with the governor's

51:56approval for anything over 25.

51:58I signed into law yet, but

52:01Um, and then the third one,

52:04perceptible noise, odors,

52:06interference at any given time.

52:09Uh, very similar definition

52:12Um, except this is anything

52:16than 25MW of electrical

52:20Uh, the perceptible noise

52:22this definition.

52:25All right.

52:26For the permitted

52:27Uh, small scale data centers

52:31business, Commerce.

52:32Office. Business.

52:33Commerce. Park.

52:34Industrial Industrial Light

52:37institutional campus.

52:39And then the large scale data

52:42industrial general, industrial

52:46business, Commerce Park,

52:48commerce Park office.

52:51We do have three performance

52:52standards that

52:54The first one is an assessment

52:56administrator that's in

53:00Virginia, and that will

53:03residential units and schools,

53:06impacts, agricultural resource

53:10and then forest land.

53:11This is required by state code.

53:13As I mentioned, this is only

53:14for 100 megawatt

53:17We thought this should

53:21All right.

53:21For noise.

53:22Any noise shall comply with

53:25ordinance, the city code.

53:27We do have three exceptions.

53:28One is temporary construction

53:32of associated structure

53:33generator testing

53:35and 4 p.m., unless required.

53:37Outside of those hours by the

53:38DQ or during a natural disaster.

53:41Any unforeseen event where

53:43generator usage

53:46and we change that from

53:49100ft noise ordinance or 100ft

53:52noise. It was cleaner, a

53:56The last performance standard.

53:57In addition to mechanical

53:59equipment necessary for

54:01structures shall be shielded

54:03from public view and

54:07And the last one,

54:09These are the districts where

54:12right to large scale and small

54:15would be permitted.

54:16So any questions?

54:18We were able to find

54:21Yes. I will update the

54:24Correct.

54:25Do you mind going back one more?

54:26Yes.

54:28This one.

54:30I think it was this one.

54:33Tell me about generator testing.

54:35Uh, they do have the test

54:38That should only be done

54:40required by the DEQ Department

54:46And the large scale could

54:51Um,

54:53do we have any restrictions

54:56proximity to like a school?

54:59Not proximity.

55:06And all that information will

55:08use permit for for

55:11All that can be part of the

55:12consideration during

55:14We won't know that until they

55:16So that's part of

55:17Gotcha.

55:19Okay.

55:21Anything else.

55:22Um with all of this recently

55:27other cities where they're

55:31data centers.

55:32Uh, by no means am I an expert

55:36was one of the biggest

55:40scale data centers is

55:45Uh, and so they have an

55:47excessive amount

55:49And there are companies now

55:53centers to incorporate green

55:58a benefit for the

56:03be able to address the water.

56:05The cooling water runoff,

56:08retention pond or going into

56:13the ground that it it provides

56:17So it's a way of I'm not sure

56:20would have that issue, but

56:23were to have that.

56:24I really think we should have

56:28the Water

56:29retention. Water

56:33abatement or whatever that is.

56:36Some of the things that we've

56:39switching over to a closed loop

56:42as much water anymore.

56:44Um, where there are issues

56:47So if there's a groundwater,

56:49groundwater, that initial

56:52Um, but most of them, most that

56:57even those that have, that are

57:00and other in the northern

57:04most of them are switching to

57:06into that.

57:07Um, Mr. Bateman, just to see

57:09anything we need to

57:11Yeah.

57:13And um what's the risk of

57:18here and not catching something.

57:21Yeah. So, um, the

57:27already exist, and they provide

57:33we use on a regular basis.

57:34That and they have no you

57:38they're there.

57:38That's the important thing.

57:40So the two that we know

57:42websites, um, they are within

57:48it's just, it's just

57:49It's like a, as we would

57:53It's just a really

57:55Um, some of them also are on

58:00don't have to disclose.

58:02Um, Centera probably has a

58:03number of them on

58:04We don't want to capture any of

58:08to do their on site processing

58:10and for their

58:12So, um, we think that 30,000

58:16for, um, redevelopment that we,

58:20for approval and

58:21It's a clean number that we use

58:27And 30,000 probably won't

58:3125MW is a little larger than

58:33governor's framework.

58:34And I thought that

58:38Yeah. Thank you.

58:39Thank you.

58:54Marijuana. Once again, I have

58:57the full red line

58:59It's 50 pages.

59:00I didn't want to kill more

59:03If you want to take a look at

59:06and the images for the use

59:09Um, otherwise it's very similar

59:13included in the memo, but I'm

59:15really quickly here.

59:17Um, essentially this is the

59:20deleted this number of

59:25So the main change that is

59:28red line version is that all

59:31being shifted around to,

59:33the zoning ordinance

59:35performance standards.

59:36So instead of 4.2.3

59:41dot FG66G,

59:44you know, there was a use

59:46classification and that gets

59:49where we put it in.

59:50So I did include all the

59:52think it helps the those of

59:55ordinance, organize it, our

59:59reflected in the

1:00:01Um, so cannabis

1:00:03This is a facility that will

1:00:06recreational sales

1:00:10I like to think they stole our

1:00:13definition from our

1:00:15Um, but I can't confirm that

1:00:17we're saying a licensed

1:00:20all times.

1:00:21The facility is open to the

1:00:22state's language, saying that

1:00:27site unless there's

1:00:29Um, we're mirroring our, our

1:00:33the Virginia ABC stores,

1:00:36to 10 p.m.

1:00:37Monday through Saturday,

1:00:38to 6 p.m.

1:00:39on Sunday.

1:00:40No cannabis dispensing

1:00:42within 1000ft of any hospital,

1:00:45school or institution of higher

1:00:48retail, marijuana store, or

1:00:49another cannabis

1:00:52And that I'm not going

1:00:55That is prevalent for, uh,

1:00:58retail sales.

1:00:59So there's two other uses that

1:01:00sales, including retail

1:01:02Microbusiness that standard

1:01:03will be included in all of them.

1:01:05Um, and all signage shall

1:01:08provisions of the zoning

1:01:10Uh, the state, the state did

1:01:11update their

1:01:13Basically says you can't put

1:01:16your businesses.

1:01:18And there's certain other

1:01:21says the signs can't be within

1:01:24If you're doing outdoor

1:01:27Marijuana testing facility.

1:01:29It tests the the quality of

1:01:33whether that's the the plants

1:01:36edibles, you bring it to the

1:01:40quality, and then you're good

1:01:43rest of that batch, for

1:01:46We imagine this setting to

1:01:48laboratory, which is why we've

1:01:52use in all of the districts

1:01:56So it's IGILCCCROBCO

1:01:59and BCI, and I apologize, all

1:02:02permits and cannabis dispensing

1:02:06the districts that

1:02:10Cannabis testing facility to

1:02:15retail marijuana store.

1:02:16This is the one you're probably

1:02:20which is just anyone goes in,

1:02:23their marijuana, and walk out.

1:02:25Um, again, it's the same

1:02:27cannabis dispensing facility,

1:02:30have a pharmacist on site.

1:02:32Um, and it's the same districts

1:02:35permit only.

1:02:38These are the areas we

1:02:42Um, I don't think this

1:02:44But these are the potential

1:02:47So that teal color the KR and

1:02:51is the same buffer language

1:02:53state code.

1:02:54We just put it in our zoning

1:02:56Um, those teal areas are the

1:03:01for this use.

1:03:04And again, we already have one

1:03:07It's in Ward's corner

1:03:09and they're going to be looking

1:03:13into the cannabis

1:03:20Transition or correlation.

1:03:21With the great.

1:03:24Purge is are we restricting the

1:03:29the same location?

1:03:31No. So you can't.

1:03:33The state code specifically

1:03:35alcohol or tobacco tobacco

1:03:36products anywhere

1:03:39Um, so you can't do both.

1:03:41You can't turn into a vape shop

1:03:43and just have a little

1:03:45It can't be an accessory use.

1:03:46It's, it's all or nothing to

1:03:48at this time.

1:03:49We did have a number of

1:03:51about in 2021, a lot of people

1:03:54smoke and vape shop, I can just

1:03:55sell marijuana when

1:03:57And Susan and I quickly just

1:04:00works at all.

1:04:01Um, and people stopped coming

1:04:05no, no, no, no.

1:04:07Um,

1:04:09and the a, b, C is also being

1:04:12tobacco products.

1:04:13And they now have an approved

1:04:14list of products

1:04:16You have to get a tobacco

1:04:18tobacco products.

1:04:20And if you're selling products

1:04:22it's, um, it's a fine and you

1:04:27don't shape up, for

1:04:33So now we're into the

1:04:36cultivation, processing

1:04:39So we expect all of these uses.

1:04:41Um it's in the state code.

1:04:43They're three separate uses

1:04:44cultivation, processing

1:04:46We group them all into one

1:04:49going to all have the same

1:04:51facility that where they make

1:04:55facilities are the big ones.

1:04:56Their lights are going 24 over

1:05:00warehouse styles with multiple

1:05:03the height of the plants.

1:05:04Um, so our performance

1:05:07reflect that.

1:05:08You shall not generate

1:05:11electrical interference or

1:05:137 a.m.

1:05:13to 10 p.m..

1:05:15Um, we do.

1:05:16In our previous version of this

1:05:18use, we did have

1:05:21all cultivation and processing

1:05:23and manufacturing

1:05:25Um, we think that might have

1:05:28code language.

1:05:29So we might change to say all

1:05:32explicitly, explicitly

1:05:35conditional use permit, that

1:05:38the marijuana microbusiness,

1:05:41one, marijuana microbusiness

1:05:44potentially just

1:05:47Um, and the reason for that

1:05:50essentially we allow it in the

1:05:51I L district by

1:05:53That's a proposal at least, and

1:05:56residential areas.

1:05:58So we want to make sure it's

1:06:01space here on your site, plan

1:06:04it's not going to impact the

1:06:07going to be indoors.

1:06:08Um, and we do have a

1:06:12secured according to the state

1:06:14of that security plan as part

1:06:19And like I was saying,

1:06:21do all of these uses.

1:06:22So it's all the performance

1:06:23cannabis dispensing facility,

1:06:26pharmacist on site, and then

1:06:29standard for the cultivation,

1:06:33We're recommending

1:06:37This is the one.

1:06:38We're not entirely sure what

1:06:40to look like, just because they

1:06:42could do a number

1:06:45Um, so we're not concerned, but

1:06:50district and the proximity

1:06:52But again, by conditional use

1:06:54application on its own.

1:06:58So these are the potential

1:07:00locations based on the

1:07:03Um those areas are

1:07:05This is a brand new map.

1:07:06Um.

1:07:10I'll give everyone a second

1:07:12The blue is the micro.

1:07:14Yeah. Those are areas in the

1:07:18And if it's not blocked out by

1:07:201000ft of

1:07:23that long list of things.

1:07:30And obviously this is a rolling

1:07:33or close, hospitals, whatever.

1:07:34Open and close daycare

1:07:36Um, this is not the

1:07:39This is not the map that will

1:07:42of 2027 when, um, or February

1:07:47accept applications at the

1:07:50But I want to at least provide

1:07:53locations might be.

1:07:56And it doesn't necessarily mean

1:07:59will be.

1:08:00They can do any number of

1:08:02smaller scale site.

1:08:04So they can have cultivation in

1:08:07have retail sales in the front,

1:08:09production, any number

1:08:19And the last one is marijuana

1:08:22This is someone who takes the

1:08:25and usually the cultivation

1:08:29the retail sales, where the

1:08:32distribute it from there.

1:08:33Um, the only performance

1:08:36have a security plan and submit

1:08:39Um, but again, all these uses

1:08:41So if a site needs a specific

1:08:45part of the CIP process rather

1:08:48We do imagine these

1:08:51So we do.

1:08:52We are recommending a C, P

1:08:55This one.

1:08:59What.

1:09:02I'll be honest, I did not read

1:09:03through how you

1:09:05I don't know if they have the

1:09:06security standards

1:09:08Um, it could be a Brinks

1:09:14And just generally speaking, as

1:09:19to all these users because we

1:09:21this is going to be established.

1:09:23We don't know exactly how many

1:09:26going to get, how many

1:09:28to be available for people who

1:09:31processors, for the areas who

1:09:33cultivation facilities.

1:09:35Um, we don't know how

1:09:37businesses are going to be.

1:09:38We don't know exactly how the

1:09:40going to look and operate, how

1:09:43going to be.

1:09:44So we're going to do it by

1:09:46we can reevaluate expanding to

1:09:50uh, potentially some by

1:09:53If the time if.

1:09:57Depending on how, how it

1:09:58develops, how the

1:10:01So.

1:10:05Is this going to be controlled

1:10:09they're covering cannabis.

1:10:10Cannabis control authority.

1:10:12Okay. So they'll

1:10:16very much track everything

1:10:19and all that.

1:10:20So it is a seed to

1:10:22So the authority is supposed to

1:10:25in the ground to when

1:10:28Yeah.

1:10:37Thanks, Ron.

1:10:39I don't know what time we

1:10:42stopping to head upstairs.

1:10:44I can keep going for now.

1:10:47Okay.

1:10:51Okay. Not a problem.

1:10:53So the application that you

1:10:56haven't seen in a long time.

1:10:57This is the Slover

1:10:59235 East Plum Street on the

1:11:01Street and Atlantic Street.

1:11:03It's been operating as the

1:11:05now, and they're proposing to

1:11:10entertainment instead

1:11:13Again, this is a city owned

1:11:18has rentals have

1:11:20We felt it was appropriate for

1:11:23permit to formally authorize

1:11:26them into the same standards

1:11:28places that

1:11:30have events in alcohol.

1:11:33They are not

1:11:36They have catering companies

1:11:39the individual ABC

1:11:41The individual

1:11:44renter of the facility will get

1:11:45a banquet license

1:11:47So Slover is not selling

1:11:50But when the alcohol is on

1:11:54being consumed, we consider it

1:11:56though the use is sale of.

1:11:58It's just for the on premise

1:11:59consumption part

1:12:01This is just a slower.

1:12:02It's not like the corner

1:12:05It's not going to sell beer.

1:12:06Right? No.

1:12:07Well, there was an ABC issue

1:12:11only have one ABC license

1:12:14downstairs or connected to

1:12:18So yeah.

1:12:19I think the waffle shop closed.

1:12:22Okay, so maybe that's

1:12:24just get their own license.

1:12:25If that's the case.

1:12:27The use is consistent with

1:12:31activity center where

1:12:34Downtown business center.

1:12:35It's also within the downtown

1:12:37coastal resilience overlay.

1:12:38In this district, you need a

1:12:40banquet hall, to have live

1:12:43alcohol on premises

1:12:46Most of us are probably pretty

1:12:48It's very it looks very nice.

1:12:49There's a lot of

1:12:52So there are seven rooms

1:12:56the facility.

1:12:59Four of them only have a

1:13:02I did not include those floor

1:13:06I wanted to give you an

1:13:08entertainment, the

1:13:10I did one floor plan where

1:13:12layout, which is going to be

1:13:15one layout where they

1:13:17There is another layout for

1:13:20but those will all be

1:13:22But just in terms of not

1:13:28only took the ones I think

1:13:30discussion of them

1:13:34So this is the forum room.

1:13:36You can see the dance floor

1:13:38This is on the third floor,

1:13:42ones people are

1:13:43If you've been to

1:13:47Is it strictly in the

1:13:51It's not in the old wing where

1:13:54That's where these.

1:13:56This one is, I believe.

1:13:57I think some of the other rooms

1:14:00floor plans for are probably

1:14:03So it would be encompassing

1:14:05It would just be used for.

1:14:07Yeah, it covers the whole site.

1:14:09Um.

1:14:10That's a very classic old

1:14:11movies in the

1:14:15This is another banquet layout.

1:14:17This is the one without

1:14:20This is the 235 commons.

1:14:22Uh, this is the ground

1:14:25Um, again, we have a platform

1:14:30for cocktail area and those

1:14:32There's no real seats

1:14:35And then this is the theater.

1:14:37The more theater layout where

1:14:39like a public speaking

1:14:41like that.

1:14:43And then this is the, what they

1:14:45call the community

1:14:47Um, this one is upstairs.

1:14:49I don't remember the exact

1:14:50floor number off

1:14:52Six

1:14:55um, you see the dance floor

1:14:56there on the bottom

1:14:58Um, we do have requirements

1:15:01prohibited from having smoking.

1:15:03Um that's already a library

1:15:06including as a condition

1:15:09And then this is

1:15:12So we've had a couple

1:15:15have had this, this style where

1:15:18venues that can be rented out.

1:15:20Um, so this is the conditional

1:15:23Slover as a banquet facility.

1:15:25Um not the library hours.

1:15:28Um, so 8 a.m.

1:15:29to 11 p.m., seven days a week

1:15:30events, um, in the conditions.

1:15:35Uh, we have a maximum

1:15:39Um, we are considering right

1:15:42allow them to have

1:15:45Um, and I don't necessarily

1:15:48about having one big room

1:15:51but if they have two events

1:15:56biggest spaces that could lead

1:15:59aware that the security

1:16:02each event, that they have a

1:16:04and a number of staff

1:16:07I know that was something

1:16:09between us and them.

1:16:12The maximum capacity for all

1:16:16Again, the floor plan with

1:16:18dance floor.

1:16:19Most likely the theater layout.

1:16:20By building code, they're

1:16:23form room in the

1:16:26It's also 300 if they don't

1:16:28with the dance floor, the

1:16:31the terrace room

1:16:32This is just what they call

1:16:35And I think what they're

1:16:3849, 49 and 49, respectively.

1:16:40Those layouts don't

1:16:42Those are the ones I

1:16:44And then the community

1:16:46last one I showed with no dance

1:16:49which is that theater layout.

1:16:50And with the dance floor is 153

1:16:52people at that room

1:16:55They were requesting live band,

1:16:56DJ poetry, reading and

1:17:06I think I took all five minutes.

1:17:13Now

1:17:15and then,

1:17:17and then immediately after the

1:17:21rest of the

1:17:23preview. Is that right?

1:17:24That's correct.

1:17:26Yes. At the same time.

1:17:38I similarly can

1:17:41I think we can do it by then.

1:17:43Otherwise I got to go.

1:17:44Understood.

1:17:49Okay. But with that,