Sewer Asset Inventory and Assessment Grant
At a glance
- What: a $400,000 state AIA grant funded a Withers Ravenel study of the city sewer system.
- Where it stands: presented at the September 14, 2026 briefing for information.
- Next: the consultant recommended about $500,000 a year for mains and $250,000 for manholes, annual GIS and cost updates, coordination with NCDOT paving, and active pursuit of grants and low-interest loans.
Scope of the study
- GIS update, condition and risk analysis, and an asset management plan.
- A ten-year capital improvement plan: five rehabilitation projects from CCTV data, CCTV inspection phases, 50 poor-condition manholes, plus pump station and plant items.
Findings (from the auto-captions)
- About 228 miles of gravity main, 125,000 ft of force main, about 4,900 manholes and 27 pump stations.
- About 40 percent of mains and manholes are in high or very high likelihood-of-failure categories, mostly by age in the older central city.
Recommendations
- About $500,000 a year for mains and $250,000 for manholes.
- Annual GIS and cost updates.
- Coordination with NCDOT paving.
- Active pursuit of grants and low-interest loans.
Discussion time
About 23 minutes across 2 meetings (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-09-14 - Council Briefing | 21 |
| 2026-09-09 - Public Services Committee | 2 |
Log
- 2026-09-14 - Council Briefing - Withers Ravenel presented AIA results, ten-year capital plan and life cycle funding recommendations.
- 2026-09-09 - Public Services Committee - Resolution accepting Withers Ravenel's findings and confirming the $400,000 grant was spent correctly moved to briefing with presentation and action; staff to circulate the large asset management plan.