Sewer Capacity and Allocation
At a glance
Details come from auto-captions.
- What: city sewer capacity is constrained in several sewer sheds.
- Where it stands: as of August 4, 2026 an engineer projected about 90 days for a Pilot-area capacity analysis.
- Next: then roughly 60 days of preliminary drawings and 30 days of construction drawings, so 7 to 9 months before financing could be sought. Realistic timelines for the main projects are 3 to 10 years.
Capacity by area
- The Pilot area is over-allocated with no new flow approved.
- East Davidson has approved 22 projects with three on hold for not meeting the allocation policy.
- Raines Road is being monitored (under a month of data) but looks able to serve all requests so far, mainly single-family.
Plant and system limits
- Morgan Huffman, Director of Public Utilities, said both the water and wastewater plants are rated 6 MGD but run about 2.25 to 2.5 MGD (water) and 2.1 to 2.25 MGD (wastewater).
- The water plant is about 100 years old and landlocked.
- The key limits are force mains at the Pilot, East Davidson and North Side pump stations.
Funding and advice
- Funding has historically been the clean water state revolving fund.
- The rate study (Willdan Financial Services) is done every five years and was said to be due this year.
- Staff advice to council was to lobby the state for far more water and sewer funding.
- Out-of-city rate structures may be limited by new legislation.
- See also Sewer Asset Inventory and Assessment Grant.
Discussion time
About 17 minutes across 1 meeting (from transcript timestamps; approximate).
| Meeting | Minutes |
|---|---|
| 2026-08-04 - Public Services Committee | 17 |
Log
- 2026-08-04 - Public Services Committee - Morgan Huffman answered five written questions: capacity, bottlenecks, timeline (3 to 10 years), funding and recommended actions.