Our Island Home Replacement Project

At a glance

  • What: The Town Manager's update on the New Our Island Home project.
  • Where it stands: Update is on the November 4, 2026 Select Board agenda.

Sources

Log

2026-11-04 - Select Board

First official update from the owner's project manager: the northern long-eared bat (an endangered species flagged by US Fish and Wildlife during stormwater permit review) pushed the start of tree clearing to December 1, about six weeks after the MOU sign-off; this will affect any town site clearing more than one acre. Submittals and shop drawings continue. The town applied this week for a federal rural health transformation grant focused on the housing components, potentially a six-figure sum. Next update the first meeting of December. Craig Piper of SMRT was also on the call.