Griffin Road Waterline Extension

At a glance

  • What: the Griffin Road waterline extension, approved previously, but the Route 20 portion needs a MassDOT permit.
  • Where it stands: blocked on the MassDOT permit as of October 7, 2026.
  • Next: escalated to MassDOT and unresolved; work off Route 20 can proceed but the contractor should not dig the Route 20 section.

The blockage

  • Vinnie, Andrew Golas, and Nick Peele all lacked permissions to submit through the MassDOT portal.
  • Escalated to MassDOT and unresolved as of October 7.

Discussion time

About 6 minutes across 2 meetings (from transcript timestamps; approximate).

Meeting Minutes
2026-10-07 - Water and Sewer Commission Meeting 1
2026-08-05 - Water and Sewer Commission Meeting 5