  • Board members present: Chair Ng, Vice Chair Leiserson, Keesler, Hidalgo and alternate Cecil.
  • Case 273148, 47 Granite Street: no one appeared; the board voted 5-0 to extend the expiration of an earlier approval to March 30, 2027, on the owners' written request.
  • Case 1225403, 127 Mount Auburn Street (hotel and residential project at 17 Story Street): the applicant's attorney said the revised plan moves the building toward the street edges (about 5.6 feet from Mount Auburn Street and near zero on Story Street) to give abutters on the Hilliard Street side a rear setback of about 13 feet 8 inches and to save trees. Several abutting households supported the setback, a Harriet Jacobs Legacy Committee representative supported the hotel and public access to the Harriet Jacobs House, and the Harvard Square Advisory Committee recommended approval if talks with abutters continue. A Harvard Square Neighborhood Association representative opposed it, citing scale, loss of existing businesses, flooding from deep excavation and tight delivery access on Story Street. The Planning Board supported shifting the building but worried about the narrow Story Street sidewalk. The board asked for a clearer exhibit and guidance from the city solicitor on mixed-use height and the new variance standard. The attorney then said his client would rather withdraw than continue, and members urged against that. The board continued the case 5-0 to October 15, 2026, with the usual conditions on a new posting sign, a sign waiver and new filings by 5 p.m. the Monday before.
  • 86 Sharappa Street (case number unclear in the captions): special permit to replace a nonconforming side landing and stair. One abutter wrote in support and no one spoke against; granted 5-0.
  • 200 Auburn Street (case number unclear in the captions): variance to keep an existing front setback of 6 feet where 10 feet is required, after the city treated replacement of rotted framing in an otherwise by-right renovation as new construction. A letter from the Cambridge Zen Center supported it. Granted 5-0, conditioned on the submitted drawings dated August 15, 2026.
  • Case 121885, 1 Myrtle Avenue: special permit to build a three-unit, four-story building on a corner lot in the Mid Cambridge Conservation District without the required upper-floor setbacks, replacing an as-of-right two-unit design. The applicant's attorney and architect said it was otherwise compliant and added a unit. Neighbors and an opposition letter alleged lost sunlight and open space and a building out of scale with a small two-story street. Leiserson recused herself after the petitioner's counsel said they believed she could not be objective. The motion to grant failed 2-2 (Keesler and Hidalgo in favor; Ng and Cecil opposed), so the permit was denied, on the grounds that the ordinance requirements could be met given the lot's size and shape and that it would affect the neighborhood's sunlight and open space. The reasons for denial were approved 4-0.

Issues discussed

Sources

Video

Watch the video

Transcript

These are auto-generated captions; names and numbers may be misheard.

Transcript

02:09All right. Good evening everyone. Uh,

02:11welcome to the September 24th, 2026

02:14meeting of the Cambridge Board of Zoning

02:16Appeal. My name is Stephen Ing and I am

02:19the chair. Pursuant to chapter two of

02:21the acts of 2023 adopted by

02:24Massachusetts General Court and approved

02:26by the governor, the city is authorized

02:28to use remote participation at meetings

02:31of the Cambridge Board of Zoning Appeal.

02:34This meeting is being video and audio

02:37recorded and is broadcast on cable

02:40television channel 22 within Cambridge.

02:43There will also be a transcript of the

02:45proceedings. All board members,

02:47applicants, and members of the public

02:49will state their name before speaking.

02:51All votes will be taken by roll call.

02:54Members of the public will be kept on

02:56mute until it is time for public

02:58comment. I will give instructions for

03:00public comment at that time and you can

03:02also find instructions on the city's web

03:05page for remote BA meetings. Generally,

03:08you will have up to three minutes to

03:11speak.

03:13I'll I'll start by asking staff to take

03:16board members attendance for our 6 pm

03:18continuences agenda item and verify that

03:21all members are audible.

03:23Virginia Keysler.

03:26>> Virginia Keysler, present.

03:28>> Daniel Legado.

03:29>> Daniel Galgo, present.

03:31>> Miranda Cecil.

03:34>> Miranda Cecil present.

03:36>> Wendy Lyserson.

03:37>> Wendy Lyserson, present.

03:39>> Uh, Stephen

03:40>> and Stephvening present. Thank you,

03:43Olivia. Uh, first order of business, um,

03:46on continued cases agenda, case number

03:49BZA 273148.

03:53uh 47

03:55Granite Street. Uh owners Luke and Judy

03:59Mitchell seeking a six-month extension

04:01request uh with based on an original

04:05hearing date of 7:25 2024 and decision

04:09filed September 30th, 2024.

04:15Luke and Judy, you on on the call?

04:20No.

04:21Okay. Um, so

04:25let's

04:32in the file we received an email from

04:35um,

04:37uh, Paula Kikis

04:40uh,

04:42to Olivia regarding or Maria regarding

04:44the request. Um

04:50and just seeking um scope currently

04:54being proposed.

05:01So they're in the process of trying to

05:03get through uh the building permit

05:05process. Correct. And um I think they're

05:08just nearing that expiration time. Um,

05:12so I don't know if the board has any

05:14questions regarding uh pro uh pro

05:17providing an extension.

05:21Hearing none, um, I'll just make a

05:24motion. Uh I move to extend the

05:28expiration date of

05:30September 30th, 2024

05:34uh of the decision for approval to and

05:37it's what 6 months

05:39to

05:43March 30th, 2027.

05:48And a voice vote by the board members,

05:51please. Uh Wendy Lysen. Wendy Lyserson

05:54in favor.

05:55>> Thank you. Virginia Keiesler.

05:57>> Virginia Keiesler in favor.

06:00>> Thank you. Uh Daniel Hidalago.

06:05>> Could you repeat that again? Daniel.

06:07>> Sorry. Daniel in favor.

06:08>> Thanks. Uh Miranda Cecil.

06:12>> Miranda Cecil in favor.

06:14>> Thank you. And Stephening in favor. So

06:17the motion to extend passes. And uh

06:20we'll you'll Olivia you'll notify the

06:22the app appellant. All right. Um I

06:26believe the agenda was just six o'clock

06:28for the next item. So next item up on

06:32our

06:33uh continued cases. Uh it was um a un

06:40the presentation was not heard at the

06:43last uh meeting and it's continued to

06:46this evening which is uh 127 Mount

06:50Auburn

06:52Street

06:54um petitioner 17tory LLC in care of

06:58Patrick W. Barrett III uh and

07:02description. Uh the propo project 127

07:05Mount Auburn, 17 story street has

07:08received a certificate of

07:10appropriateness from CHC. However, we

07:12are proposed to reduce the front setback

07:16um to 4 feet on Mount Auburn and Story

07:19Street, which would allow us to increase

07:21the sideyard setback and move building

07:23away from the residential neighborhood.

07:25Uh they also proposed to increase the

07:27commercial side setback on the first,

07:29second, third floor of the building to

07:32normalize the footprint of the allowed

07:34hotel use in the building increasing

07:37building efficiency and adding

07:39additional residential square footage

07:42seeking um uh citing article 5.0

07:465.31 table of dimensional requirements

07:48and also uh section 10.30

07:52uh seeking of variance. Mr. Barrett, are

07:56you of online?

07:59>> Mr. Chair, I am here. Um, uh, a couple

08:02things of note. We are seeking a

08:05variance to move the building.

08:11Button just popped up here and I can't

08:17participant has requested captions to be

08:19enabled for this webinar.

08:23>> Olivia can

08:25Can it It's not asking me. It's just on

08:28your screen.

08:29>> Yeah, I don't know

08:31>> how to get rid of that.

08:33>> I will. It is next door. I will get it.

08:37>> Appreciate it. But um Can you hear me?

08:39>> Yeah, we can hear you and see you.

08:41>> Okay, I'll I'll continue with this

08:43little screen. Um

08:46we um we're coming to you um with a

08:49project that we have been spending a

08:51great deal of time on and um we are

08:54asking for the um the variance to move

08:58the building into the residential

09:00setback and we're trying to get sort of

09:01a maximum

09:04um uh result in terms of I think right

09:07now we're showing about 5.6 feet from

09:10Mount Auburn Street and we're getting

09:11close to 0.2 two or zero on Story

09:13Street. Um with the intent of moving the

09:16entire building further away from the

09:19residential neighborhood. Um

09:22the um we're also looking to normal what

09:26I refer to as normalizing the commercial

09:28setback because it is the H+ L um

09:33formulaic setback that would have

09:35required um in preliminary

09:39design review a very significant cantal

09:42lever over residential floors. So our

09:44solution was to build the residential

09:47around the commercial setback. Um which

09:50thank you whoever did that. Um

09:54but um which we spent uh a few months

09:58with the Cambridge Historical

10:00Commission. We did get a certificate of

10:01appropriateness

10:03and in those meetings um which there

10:05were several with neighbors as well as

10:07uh you know stakeholders um there was

10:11concern about the fact that the multif

10:15family housing zoning allowed for a

10:16five- foot setback from the residential

10:19piece. Now, this lot is a five-sided

10:22corner lot. Um, and

10:25um, it has a lot going on with it. It's

10:28a C2 zone. Um, it also has a very small

10:32sliver of C1 in the back, which our

10:34property is not touching. Um, our our

10:37development plan is not touching. Um and

10:42we're trying to create sort of a vi

10:44viable project on the site. Um it does

10:47allow for hotel use um which is unusual

10:51um because it's more than 50% within the

10:54Harvard Square overlay.

10:56all those things put together, we came

10:58up with this plan and um as part of our

11:01approval process, I did know promise the

11:04neighbors as well as Charlie Sullivan

11:06that I would work with CDD to try to

11:08come up with a solution to increase the

11:10setback in back um and to try to

11:13alleviate some of the pressure of the

11:14building because it is a tall building.

11:16Um, and you know, we're sort of being

11:19squished on the lot because we have a

11:21Harriet Jacobs house. Um, and that we

11:24have to preserve and to is currently in

11:27the process of being landmark. And

11:29again, we're trying to create this

11:30viable project behind it and connect it

11:32and restore this corner. Um,

11:36up until the middle of July, I had no

11:38real solution for this. I've been

11:40talking with CDD and I I have another

11:42corner lot case this evening that also

11:44deals with some similar issues. But

11:46corner lots do not get the benefit of

11:47the contextual setback. A C2 zone is

11:50also not a zone where the multif family

11:53housing zoning was truly implemented in

11:56terms of contemplating mixed use which

11:58is why we have two different setbacks

11:59for uh two different use categories.

12:02Um but then as you guys well know um the

12:06state legislature changed the um what it

12:10means to get a variance. Um I provided a

12:12memo to the board sort of outlining what

12:14I thought were some of the more

12:15pertinent issues. I think in the old

12:18standard I would have brought uh maybe a

12:20furlong the zoning board of appeals of

12:22Salem type case citing uh site safety

12:25features. Um, I think that

12:28there's a couple of, um,

12:31larger issues that are being addressed

12:33by moving the building forward, not just

12:34to the benefit of the neighbors. There

12:36are several honeyloust trees that are

12:38about 50 to 60 feet in height behind the

12:41lot. There's also a two inexplicably

12:45tall 80 foot pine trees behind the lot

12:48as well that in the previous design, the

12:50one that's been granted a certificate of

12:52appropriateness, we'd be about 5 feet to

12:54six feet away from 8 feet away in the

12:56worst case scenario. A lot of the cases

12:58that are being, you know, sort of

13:00causing some aida amongst the neighbors

13:02and residents in Cambridge dealing with

13:05um very tight setbacks is because of

13:08this five- foot uh requirement. We are

13:11think a little bit uh in a different

13:13scenario where we have the opportunity

13:15to move the building further away,

13:17alleviating the pressure on the trees,

13:19alleviating

13:20um the pressure on the neighborhood. Um

13:23and I do believe that we do meet I I

13:26would actually make the argument we met

13:27the old standard, but I think we meet I

13:29certainly think we meet the balancing

13:30test of the new practical difficulty

13:32standard. And the practical difficulty

13:34sort of uh the practical difficulty

13:37being in

13:39we are a corner lot five-sided. We have

13:42uh the Harry Jacobs house that we have

13:44to preserve and to maintain and restore.

13:47Um which is really pushing the property

13:49further into the lot area. Had the Harry

13:51Jacobs house not been present on this

13:52lot, we would certainly not be in the

13:54position that we are. And further, we do

13:56have um the reason why I actually

13:59brought up furlong is because we have we

14:00do have a plan that we are zoning

14:03compliant. And what we're trying to do

14:05is to move the building um in a way that

14:08I think that the legislature intended

14:11for this new variant standard to work to

14:13allow the BCA to balance the needs of

14:16the neighbors, the public realm. I also

14:18included in um uh I sent it to Maria

14:21Lake because we took a long time to run

14:22to them some shots of u story street uh

14:27which I can bring up on my screen to

14:28show to show folks if uh if it's

14:30necessary because there was some concern

14:31raised about public realm. Um but we

14:34actually think that this is a a much

14:35better result not only for the neighbors

14:38but um for the public realm that is

14:41facing in the back of the area and as

14:43well as in the front. Story Street is a

14:45narrow width street. It has a narrow

14:47sidewalk about five feet. Mount Auburn

14:50is a little bit more blessed, but it is

14:52also somewhat tight and the existing

14:54structures go to about zero right now.

14:57Um 127 Mount Auburn has a stairwell that

14:59touches the sidewalk. Uh very similar to

15:01how we imagine the Harry Jacobs will

15:03look uh when it's moved to that lot site

15:06further down. Um the um Story Street

15:11residence has a sort of a strange

15:14underground vestibule that touches the

15:17street. There's a stairwell going down,

15:19but it's a nice big sort of hole at at

15:21the at the street corner. And our plan

15:24is to move the building

15:26on the story street side to as close to

15:29zero as we can to increase the setback

15:31um on the Hilliard Street line to about

15:3313 feet. eight inches. Um and on the

15:38Mount Auburn Street, we are still

15:40constrained by the Harry Jacobs house,

15:42but um we're working with historic right

15:44now to see how we can adjust the Harry

15:47Jacobs building to maybe inch a little

15:48bit uh further away uh closer actually

15:51and um and working with them to

15:56adjust some ADA compliancy regulation

15:58issues. And the reason why we're here

15:59and I do apologize this is somewhat

16:01unusual. um we have been through some

16:04significant process um and we still have

16:07a ways to go but I can't fully design

16:10the building without knowing whether or

16:11not we can building into the setback. Um

16:14without that piece of the puzzle it

16:16really becomes

16:18um next to impossible to design the

16:20building. Um, and I do believe that

16:23um, for the reasons I've already stated

16:26that we do meet the standard and I'm

16:29happy to um, pop up on the screen if

16:32that's helps visually to sort of get an

16:34idea of what we're talking about on the

16:36story street side in Mount Auburn. Um, I

16:39wasn't sure how much the materials the

16:40board has already gone through. was

16:42quite a bit and I didn't want to extend

16:44the meeting, you know, into extra days

16:46because we have I think it's a 60page

16:49presentation for the historical piece

16:51alone. Um, but I think

16:55that in a nutshell encapsulates what

16:58we're trying to do. Um, I'm happy to

17:01answer questions about it, but I think

17:03the most important sheet that I provided

17:05you was sort of the propo the the

17:07approved setback and the proposed

17:09setback. And there's there's, you know,

17:13a host of reasoning why. Um, thank you,

17:15Olivia.

17:18[clears throat] Um, that shows you u

17:20that's a new rendering that's part of

17:21our uh trying to address the um the

17:25needs of

17:27uh the planning requirements of the

17:30planning board have looked at this and

17:31they were asking for some shots on uh

17:34Story Street. This is how we imagined

17:35the building would set. Um, and this

17:38sort of gives you a um better uh sort of

17:43vantage point. Olivia, do you have the

17:44one that's the um

17:47Yes. Uh the one Yeah. That gives you an

17:50existing and shows you what the street

17:51currently looks like um and how we

17:54imagine the building sitting on Story

17:55Street, which sort of the biggest

17:56concern raised by um the planning board

18:00in our discussion with them the other

18:02day. It also shows the building across

18:04the street, which is also at a zero lot

18:05line. D Street really is at zero. Um,

18:09and while that is a tight condition, um,

18:12I do believe that as you go further

18:14down, um, into our development, it does

18:17break. And not only does this movement

18:22allow us to, if you move the building

18:24further away from the residences, it

18:26also allows us to lower the height of

18:28the proposed hotel. We were at six

18:29stories before, now we're at three.

18:31We're fully behind the Harry Jacobs

18:33building. We're not adding any more keys

18:35to the hotel. We don't get more hotel

18:36square footage. We're actually

18:37constrained by F, but we do get

18:40efficiency in the building that didn't

18:42exist before. So, that allows for the

18:45expansion of u more residential uses.

18:48This will be one of the first new

18:50residential buildings built in Harvard

18:51Square that comes with that actually

18:53will have inclusionary units. It may be

18:55the first inclusionary project in

18:56Harvard Square. Um, and I think that

18:59should carry a little bit of weight in

19:01terms of when we're talking about the

19:02public good. Um, not to mention the

19:04Harry Jacobs House, but we really are,

19:07this this whole plan really came about

19:10towards the end of the summer. Um, and

19:13my client was sort of gracious enough to

19:14allow me to attempt this because I

19:16thought with the new standard, it seemed

19:19much more clear to me how we could meet

19:21that standard. Um, I do think in the old

19:24standard we still do meet the standard,

19:26but again, um, I think it would be a

19:29little bit more of a difficult climb

19:31with a zoning compliant project. Um,

19:37I can pull up Olivia, do you have that?

19:39I'm not sure how this is is working, but

19:40do you want me to pull up my slide for

19:42the presentation and I can show the

19:44setback or is that

19:47not not sure?

19:49>> Yeah, this is Olivia. Yeah, you could do

19:51that.

19:57>> All right, I'm not going to go through

19:59my entire presentation because I think

20:00we would all fall asleep. Um, but I will

20:05get to the sort of the the meat and

20:07potatoes of what we're asking. Um,

20:21Okay.

20:23So, this is the existing

20:25setbacks as approved and zoning

20:27compliant. Um, and this is the position

20:32of the building um with the variance

20:34that we're

20:36to get an idea of what we're talking

20:38about. Um,

20:40the uh Can you see my cursor?

20:44>> Yes. Um, so the trees that I'm talking

20:46about are here, here, here, and here.

20:51Um, in the previous condition were, you

20:53know, pretty tight against that side. We

20:55also had some balconies

20:58um for the residential piece of this,

21:00but by allowing us to go up with the

21:02commercial on the first three floors, we

21:04eliminate all balconies on that side.

21:06There is no there is no further

21:07encroachment until you get to the fourth

21:08floor. Um, and you got the full 13.8 8

21:13at that back location. You also get oops

21:17um an additional

21:19uh increased setback on the Mount Auburn

21:21side which would allow for us now to

21:24locate our transformer on this side of

21:26the building and create a significant

21:28amount of green space all behind here

21:30which will add privacy for both the

21:32residences and the hotel. Um the hotel

21:35the lower floors does not have operable

21:36windows. Um it's a completely different

21:39scenario and I think uh in terms of

21:42programming the building a much better

21:44program for the neighbors and for um the

21:47my my client um and also point out that

21:50the treatment of the Harry Jacobs house

21:52itself um gets considerably better when

21:54we move the building this way. Right now

21:56we are extremely tight. There's a um

22:00there's ramping systems that we have to

22:02use to get to the appropriate grade. We

22:05moved the building more like sliding

22:07around the lot and now we have a

22:09normalized courtyard. The Harry Chico's

22:12house is a little bit closer to the

22:13curb. We have a nice space here to

22:15program with greenery and for um for

22:20outdoor seating perhaps, but um I think

22:24this is a much better program that the

22:27zoning just doesn't allow for at this

22:29moment. And I'd also point out that as

22:31of two days ago with the multif family

22:33housing zoning discussion, this is

22:35exactly what they're contemplating as

22:37part of the larger group of changes um

22:39to at least allow for you know a sum of

22:43approach that would get us to um what

22:46we're talking about here without having

22:47to go through a a relief process. Um,

22:51we're coming before you right now

22:52because I just need I need to understand

22:54what we have to work with because this

22:56affects everything uh in terms of how

22:58the building is designed including

23:00zoning and green factor um uh and other

23:04elements of the build other elements of

23:06the design that we'd otherwise have an

23:07answer for. But for this issue,

23:11um, I think I'm going to leave it there

23:12because I think I don't want to make it

23:14unnecessarily complicated what our ask

23:16is, but I do I am happy to get into the

23:19new standard. I'm happy to explain

23:22really anything about the history of

23:23this project and um, I'll leave it at

23:26that.

23:30>> Thank you, Mr. Barrett. Um, any

23:32questions from fellow board members?

23:40This is Daniel Yolgo. Can I can I just

23:42ask um I I know it sounds like not

23:44everything is settled. So So that's

23:46fine, but I just curious because some

23:48some of the numbers were different in

23:49different parts of the application just

23:50in terms of like the number of housing

23:52units and uh contemplated for for this

23:55project.

23:56>> So a number of housing units um in a

23:59original presentation to the historical

24:01commission who doesn't really their

24:03jurisdiction is not inside the building.

24:05We showed about 50 units. Um, this new

24:08configuration would allow us to get to

24:10about 60.

24:11>> Okay, great. Thank you.

24:15>> Uh, this is Miranda Cecil. I was

24:17wondering, you mentioned at some point

24:19that, and I I'm not entirely sure how

24:23how relevant this will end up being to

24:25what we're evaluating here today, but I

24:26wanted to ask anyway. Um, you mentioned

24:29that the residential space would not be

24:32coming above the hotel. Is that

24:35accurate? It looked like some of the

24:36renderings might have it be taller.

24:40>> The residential space is above the

24:41hotel.

24:43>> So what I'm saying

24:44>> so the the we want to put the hotel on

24:48the first three floors um within be

24:51considered the footprint of the building

24:53which includes the residential setback

24:55and we want to build so the hotel the

24:57hotel will be three floors. The

24:58residential floors will be 4 through

25:00eight.

25:03Okay.

25:05So, per perhaps there's a disconnect.

25:07So, is the

25:11um is the historic home shorter than the

25:15>> the building?

25:18>> Okay.

25:20>> So, the residential Okay. The Harry

25:22Jacobs house itself is not going to be a

25:24residential use. Part of

25:27>> um the charge of the historical

25:30commission. This is an old older

25:31rendering by the way. This is the

25:32approved historic piece. Um, part of the

25:36charge in the historical commission was

25:37to make the Harry Jacobs a public use.

25:40Um, there are not many options with

25:42that. So, we thought that the Harry

25:44Jacobs as the entry point to the hotel

25:47might be the best solution.

25:48>> We're putting hotel rooms within the

25:50Harry Jacobs House, but that also

25:52creates a difficulty for us, which is

25:53why I mentioned furlong. Uh, simply

25:55because we have a woodframe building

25:57next to a steel building. I got to keep

25:5910 feet away from it in order to have

26:01any window penetrations around it. So,

26:04um, the Harry J I can't close up the

26:07windows of the Harry Jacobs house. That

26:08would be wildly inappropriate. Um, and

26:10we also don't want to have building that

26:12on the third floor or fourth floor

26:14registers as just being a flat wall. Um,

26:17so our solution was our solution

26:20requires to keep that distance between

26:22the two. Um, but the Harry Jacobs House

26:24will be rooms on the second and uh third

26:26floor uh connecting to the back of the

26:28hotel for ADA compliance.

26:31>> I see. Okay. I think I just

26:34misunderstood something that you were

26:35saying here because that that completely

26:37makes sense. Um, thank you.

26:39>> Welcome.

26:41>> So, how many how many uh keys

26:45are being proposed in this project for

26:48the hotel?

26:49>> The original was 67. I think we're down

26:51to 65 now.

26:5365 hotel and then 60

26:57residential units.

26:58>> Yes sir.

27:00>> And are the residential and hotels

27:03combined

27:06in terms of access and so on? I mean do

27:08you have floor plans to show us?

27:11>> We have

27:14something like a floor plan. Um we have

27:16our um know based on the original design

27:19we did contemplate a separate entry

27:21point for the residences and for the

27:23hotel. The Harry Jacobs house because of

27:25the grade that it's at is going to

27:26require ramping. Um we are looking at an

27:29entry point at this location for the

27:32residences and at this point for the

27:35hotel. Um that will not be much altered

27:39or new design. They will be separated in

27:40terms of entry points. Um but with the

27:44movement of the building to the new loca

27:46to the new location that does change a

27:48little bit in terms of how we'll ex

27:50exactly address that. Um it does get a

27:53little bit um

27:57>> see you're showing quite a few different

28:00configurations here. I I'm very confused

28:03and I'm not gonna approve anything

28:06without knowing we've got something

28:09locked in that we're we know is what

28:12you're proposing. So if there's any

28:14ambiguity that's going to cause problems

28:18at least for myself.

28:20>> Okay.

28:22So if you have common entrance for the

28:26hotel and the residence, so they both

28:28come in, they access the elevator

28:31together, guests and and permanent

28:33residents. Is it condos or rental?

28:36>> Uh condos.

28:37>> So okay. So it sounds like it's kind of

28:40a standard uh luxury hotel setup where

28:43you've got uh condominiums. they get

28:45served by the hotel operator and uh and

28:49then guests can come and stay in the

28:51hotel section. Correct.

28:54>> Right.

28:56>> Okay. So, it's common shared. Um

29:00I guess some of my questions were also

29:03regarding the site plan um for a

29:06commercial hospitality

29:09project this size. I I just don't see

29:12any

29:14service or place for a dumpster. I

29:16thought maybe that alley onto off of

29:19Mount Auburn was where you're But you

29:21have a transformer coming in on that

29:23side.

29:24>> So loading and trash are served on Story

29:27Street.

29:33>> Is there like a I I'm look trying to

29:36find a floor plan here.

29:42This is Wendy Lyserson. Can you show us

29:43which tell us which document to look at?

29:47>> Um, we have the four plans that were

29:49presented as part of the historical

29:52presentation. Um, that include um

29:58um on slide

30:00on the slide that I'm showing now

30:02location for loading and for trash.

30:06>> Ah, okay. I see that.

30:19So if we're combining

30:23it, it's essentially kind of a the

30:27residences and the hotels are combined

30:29and being served by the hotel operator.

30:33Can you are you classifying the

30:35residential above as as

30:39residential units or is that basically

30:41should be considered commercial?

30:44>> No, they're they will be residential

30:46units. They will have no uh connection

30:48with the hotel other than the fact that

30:50they're in the same building. They won't

30:51be operated by the same operator. It

30:53won't be managed by the same company. Um

30:55they'll be for individual ownership.

30:57They will not be part of the hotel

30:59programming at all.

31:02The intent is to have them be standalone

31:04to sell the condos and uh to have a

31:07hotel operator, preferably a local one,

31:09to operate the small sort of boutique

31:12hotel operation.

31:17>> Okay. Um Okay. Thank you.

31:20>> You're welcome.

31:25>> This is Wendy Lys. I had a couple

31:27questions and um again it goes back to

31:30like the confusion of which plan and the

31:33detail level of the plan um here. So in

31:37looking at the um what was presented

31:42uh over a year ago now to the Cambridge

31:44Historical Commission.

31:46>> Yeah. Um, so in that

31:50project narrative, it says that the

31:53Harriet Jacobs House will serve as the

31:55hotel lobby. Is that correct?

31:57>> That's correct.

31:58>> Okay. And that's going to connect to a

32:00small cafe.

32:02>> Correct.

32:03>> And then will that house uh be connected

32:07to the first three stories of the new

32:10building?

32:12>> Correct. Yes.

32:13>> Okay. And so, um, I assume that even

32:18though you are providing a separate

32:20entrance to the residences,

32:23they could conceivably walk in off of

32:25Mount Auburn through the hotel and up to

32:27their residences. Correct.

32:30>> They could walk in the hotel through the

32:32lobby. Um, they'd have to go through the

32:34courtyard to go through a separate door

32:36to get to their elevator to go to the

32:38residences. So they can't if you're on

32:41the third floor of the hotel, you can't

32:42access the residences. Is that what

32:44you're saying?

32:44>> Right. Correct.

32:46>> Okay. So, um then

32:49I also wanted to get some clarification

32:52on the dimensions

32:55>> um because um

32:59I'm not sure how we grant a variance

33:01when we're uncertain what dimensional

33:03standards apply. And so, um, I'd like to

33:07get some have some discussion on that if

33:10you don't mind.

33:11>> Sure. Um,

33:12>> yeah.

33:14Part of the part of the issue that I'm

33:16that we're having with that, we

33:17presented the

33:20um the historical commission with a

33:23diagram that showed um the dimensional

33:26elements which is part of our submission

33:28um for the hotel as built um which

33:33because it's a five-sided lot, the H+ 5

33:36H+ L+ 5 dimensional requirements tucks

33:39the building in varying varying

33:41directions and varying feet on the Mount

33:43Auburn side, which would be this this

33:46side. It was about 34 feet.

33:48>> I'm sorry, which side? Um

33:51>> I call I'm calling it the Mount Auburn

33:52side, but it's the side that abuts Mount

33:54Auburn. Um

33:58um this side would have been about 34

33:59feet. This the Hillyard Street would

34:02have been about uh 24 to 26 feet.

34:05>> Hold on just one second. Sorry if I know

34:07you know this by heart probably, but I

34:09just want to make sure

34:10>> myself and the members of the public are

34:12following. So you're saying that on the

34:14Mount Auburn side you're saying it's 34

34:16feet

34:18>> correct

34:19for the commercial setback.

34:21>> When you say commercial setback can you

34:24please explain what you mean by

34:26commercial setback because that's not

34:27defined in the ordinance.

34:30>> Yeah. Well, unfortunately, when the

34:33multif family housing zoning was passed,

34:35they altered the residential setbacks

34:37for all residential zones, but they did

34:39not do the same for residential zones

34:42that also allowed for commercial uses.

34:44>> So, the commercial the commercial

34:45setback remains the formulaic setback

34:47while the residential setback was pushed

34:49to 5T.

34:52>> Well, so which side of the building is

34:56the commercial setback? the the um one

34:59to the left of the hotel facing Mount

35:01Auburn Street. Is that what you're

35:02saying?

35:03>> Correct. This is where it gets a little

35:04bit on the confusing side. So, I'll show

35:06the hotel as originally designed.

35:09The Mount Auburn Street give us a 34 set

35:12foot setback from this point to this

35:14point.

35:16The Hillier Street requirement given

35:18that the height of the hotel was at six

35:20stories and

35:22um

35:24slightly changed in width was about 26

35:28ft from this location to this location.

35:32On the um story street elevation, the

35:35setback was required to be about another

35:39uh 26 to 28 ft depending on how we how

35:43we looked at the floors. But the idea

35:45was that this this red zone represented

35:49where the commercial setback required

35:51the hotel to be built if it was to be

35:53built standalone.

35:56The remaining portions of the building

35:58which are residential

36:01are allowed to go to this 5 foot 5ft

36:04setback and 10 ft on on the corner in

36:06the front.

36:08We increased the back step back on the

36:10Hillyard side by three feet during our

36:12presentation to the historical

36:14commission as sort of a

36:17nod to the neighbors on Hillyard Street

36:19who had a real issue with this building

36:21being built. Um, and we're trying to

36:23give them some more space and sort of an

36:25indicator that in the future we would

36:27try to look for solutions to give them

36:29more space.

36:32So, I do appreciate that you're trying

36:33to accommodate the neighbors that um is

36:36part of the new and old standard. Um

36:40but, uh I wanted to ask you about how

36:43you're getting to that setback

36:46dimension.

36:47Um putting aside for a second what

36:49you're calling commercial versus

36:51non-commercial uh setbacks. um because

36:55there was some question in the file

36:57about what the permissible height is for

37:00this building.

37:01>> So the the question about the

37:03permissible height um came from a

37:05neighbor on the Hillyard Street side and

37:08because there's two height differentials

37:10for the Harvard Square overlay. There's

37:13a 60ft height limitation per commercial

37:15which is why the hotel we showed it

37:17being six floors and there's a there was

37:20an 80 foot height limitation for

37:22residential that got changed in 2025 to

37:2685 ft which is what the allowable C2

37:28zone is the it's now the greater of um

37:32so the residential height is 85 ft the

37:34commercial height is 60 feet um what

37:37we're showing in our new plan is the

37:40hotel being on the first three floors

37:42and the residential going up the

37:43remainder of the height. Um the height

37:46in in the harvest square overlay can be

37:48augmented by special permit. Um but it

37:51only allows for the commercial to go to

37:5380 ft and then there's the differential

37:55and we we had no intention of doing that

37:57because we are also constrained by F on

38:00the commercial side to 1.75.

38:03>> So I'm going to stop you for just one

38:05second. So um so the Harvard Square

38:08overlay

38:10>> in section or article 20 section 54.2 to

38:15discusses building height limitations in

38:17Harvard Square overlay and it says that

38:20the the maximum height is 60 but then

38:24there's of course additional language to

38:26discuss um and it says um you know that

38:32if the base zoning district has a more

38:36restrictive height limitation

38:38for non-residential uses the more

38:41restrictive shall apply.

38:43Right.

38:44>> Where the base zoning district

38:46establishes a more permissive height

38:47limitation for residences,

38:50then the more permissive shall apply. So

38:52I think what you're saying is that

38:54because there's residential use in this

38:57building, you're saying the more

38:58permissive

39:00of the base zoning district should apply

39:02to the height. Is that what you're

39:04saying?

39:04>> What I'm saying is that there are two

39:06applications of height in this building.

39:08that the commercial portion of the

39:09building is limited to 60 feet and that

39:13the residential portion is limited to 85

39:15feet and that if we were to build a

39:17mixeduse building, we would take the

39:20residential height or the residential

39:22piece as the limitation and the

39:24commercial height as the limitation for

39:26the commercial piece.

39:27>> But if it's a mixeduse building, then it

39:30would be subject to the commercial

39:32height restrict limitations in a base

39:36zoning district. Correct.

39:39I believe the Harvard Square overlay

39:41overrides that.

39:43>> No. Um, so what Harvard Square Overlay

39:46is saying, as I read it, anyway, I'm

39:49open to, you know, discussion here. As I

39:52read it, is that the Harvard Square

39:55Overlay District sets the height limit,

39:57the maximum height limit of buildings in

39:59the Harvard Square Overlay District is

40:01governed by section 20542.

40:06Section 20542

40:08number one says as of right height

40:10limitations the maximum height of any

40:12building shall be 60 feet. Now if you go

40:15back to the first paragraph of that

40:18article it then goes on to say where you

40:22have a nonresidential use.

40:25If the base zoning district establishes

40:28a more restrictive height limitation

40:31that applies. So, if the base zoning

40:34district establishes a more restrictive

40:36height limitation for non-residential

40:39uses, which means that it would be less

40:41than 60 ft to be more restrictive, then

40:44that would apply. Where the base zoning

40:46district establishes a more permissive

40:48height limitation for residences as

40:51listed in section 4.31 A throughJ, the

40:55more permissive shall apply. However,

40:58when you have a mixeduse building, it is

41:02subject to the non-residential use

41:05height limitation.

41:07So, you do not qualify for a more

41:09permissive height limitation.

41:13So, that means that the height

41:15limitation in Harvard Square overlay

41:16district is 60 ft

41:19unless you go to the planning board for

41:21a special permit under sub paragraph two

41:23of that section.

41:31I had been over this with ISD several

41:34times um as well as with the city of

41:36Cambridge. It was my understanding that

41:38we can go to 85 ft for the residential

41:41piece and we were limited on the

41:42commercial piece. If what you're saying

41:44is that we are now subject to a 60oot

41:47height limitation, then we don't need a

41:49variance to move the building at all. We

41:51can eliminate the hotel use be all

41:53residential building and go to 85 ft.

41:55Well,

41:57>> um I can't speculate on what's not

41:59before me right now, but I would say

42:01that the reading of the other the

42:04alternative reading that you suggest

42:06would make the sub paragraph 2 be um

42:12>> you know,

42:14so if you're looking at article 20

42:17>> y

42:18>> 54.2 two, building height limitations in

42:22the Harvard Square Overlay district.

42:25You'll see that there are two

42:26paragraphs, one numbered one and one

42:28numbered two. The second paragraph says

42:31there there's a special permit for

42:33additional height. Says if you want to

42:36increase the height to 80 ft, you need a

42:38special permit from the planning board.

42:40I don't know how you can make sense of

42:42that paragraph in this section if you're

42:45saying as of right you get to go beyond

42:4860 ft. That doesn't

42:50>> the first paragraph

42:52>> the first paragraph states that where

42:54the Bay zoning district establish the

42:56more permissive height residences listed

42:58A through J the more permissive shall

43:00apply

43:00>> but you have a mixeduse building you

43:02don't have a residential building

43:04>> when you provide a dim form for the city

43:06of Kim you provide the base height for

43:07the residential and the base height for

43:09the commercial is treated as two

43:10different things

43:11>> historically historically it's always

43:14been measured for that

43:16>> um set back equation that I gave you

43:19that they never look at the full height

43:21of the building. They use the

43:22residential port the commercial portion

43:24of the building to determine that

43:25formula setback. So, I don't know how

43:28you can reconcile what you're saying

43:31that because this building now has mixed

43:33use, which I don't see.

43:36I just don't I don't see that. They're

43:38saying now because of that mixed use,

43:41that that different use in that building

43:42that now the building can't achieve the

43:45the height for the residential piece of

43:46the building, which it clearly says it

43:47can.

43:50Well, I think perhaps we'll put this on

43:53the table. If we need to refer this to

43:55the city's law department for review, we

43:57can do that. But I would call your

43:59attention also to article 523.3

44:03sub paragraph C in terms of how mixeduse

44:07buildings and height uh calculations are

44:10done. But I think I'm going to table

44:12that now because um this may need the

44:16city solicitor weigh in.

44:23Did you have any other questions, Wendy?

44:26>> Um, I'd like to hear from any of the

44:28other board members before I

44:35>> any other questions.

44:36>> I just

44:37>> Yep.

44:39We don't have any additional questions,

44:41but I agree with Wendy's interpretation,

44:43and I think if we have a question about

44:44this, it might make sense to continue

44:47um until the board can get more

44:50information from the city solicitor's

44:51office.

44:54>> I do have other questions about the

44:56variance standard, but I don't know if

44:57you want me to hold that if we're going

44:59to continue it.

45:02I defer to the chair on this matter.

45:07Do you want to take a reading of the

45:08board's position?

45:11>> Uh yeah, we can check with the board

45:14here. Um

45:17what's uh the favor of the group? Do we

45:20want to just continue with the

45:22discussion and then uh essentially I

45:25think we would require a continuous

45:28continuence to seek out uh guidance from

45:31uh city council but

45:35We could also hear from any members of

45:37the public here so that we would know

45:38how to weigh the benefits as required.

45:49Uh I think I've already made my position

45:51clear, but I think it might make sense

45:53to

45:56hear from members of the public, but

45:57then also continue the hearing as it

45:59relates to our questions subject to

46:01getting city solicitors input.

46:05Um, this I mean this is Daniel Dalgo.

46:08I'm I mean I'm fine continuing, but I'm

46:11a little puzzled that why like I I would

46:13assume this would have been flagged

46:14earlier by ISD or or someone. Um, so

46:17that's just I'm interested in that. Um,

46:20one question I is I mean we can hear the

46:22public so if the

46:24>> Can I can I please just weigh in on this

46:26on the side issue really quickly because

46:28a lot because you you threw 5.2 23.3 at

46:32me and I've already gone through this

46:34issue in the memo to Olivia as well as

46:37to CD uh 5.23.C.

46:41Um you know you'll paraphrase some of it

46:45but you know in a mixeduse building

46:46containing both residential

46:48uh and non-residential uses blah blah

46:51blah portions of the building devoted to

46:53residential uses may exceed the

46:54non-residential height limitation

46:57so but not exceed the the residential

46:59height limit. So in a mixeduse building,

47:02the residential height is allowed to go

47:04above the commercial height. That is

47:07what a mixeduse building is. So it is

47:10not constrained by the Harvard Square

47:12overlay cap is 60 ft for commercial

47:14uses. The building doesn't become

47:15magically commercial. The commercial

47:18section of the building is commercial

47:19and the residential section of the

47:21building is dealt with the residential

47:22height limitation which is 85 ft.

47:25We'll have to agree to disagree pending

47:28input from the city solicitor for now.

47:30I'm prepared to be wrong, but I want the

47:32city solicitor to be the decider.

47:42>> Okay. Um I think Go ahead.

47:45>> I was going to say this is Virginia. I

47:46think Wendy, if you do have any other

47:48questions, it seems like we should get

47:50all our questions out now so that

47:52there's not like another threshold

47:54question that comes up in the next

47:56meeting and we're continuing it again.

47:58Uh, so

48:01>> yeah,

48:02>> sure. Um, I did have a question. Um,

48:06because this is now we now have the

48:08benefit of having three submissions from

48:12different

48:14well-known attorneys in the local area

48:16about how to construe the new variant

48:19standard and they're not all the same.

48:23Um, so I would like to make sure that or

48:28to hear feedback about how we're

48:30applying this new variant standard.

48:34The way I read your memo, which I thank

48:36you for. Um

48:39on your second page of your submission

48:43that's um the header says from your law

48:47office says 70 17 story street variance

48:50practical difficulty memorandum and it

48:52should be in the public files for anyone

48:54who would like to look.

48:57But on the second page you've cited the

49:00new 40A section 10. And then you go on

49:03to say below that

49:05um structurally

49:08um the rewritten statute imposes one

49:11mandatory finding a practical difficulty

49:14and one mandatory balancing test and you

49:18cite the language from the section and

49:20then you talk about the four enumerated

49:23factors that are optional.

49:26But my question to you is um because

49:29this is your argument about how to

49:32interpret the new standard differs from

49:34both of the other attorneys argument.

49:37And in the language of section 10, the

49:39new language, it says in making its

49:43determination, the determination of what

49:45would result in a practical difficulty,

49:48the permit granting authority engages in

49:51this weighing

49:53um balancing test that you've interrupt

50:07Um, and I think this is this is not new

50:11laws often have different reads. This is

50:14why they usually end up in court cases

50:16for us to be told how to read them. So,

50:20it's uh no reflection on you know um how

50:25you've tried to help us to understand

50:27this. But um I think that

50:32the practical difficulty cannot be

50:35defined by the impact of applying the

50:39strict the the zoning law or the

50:42building code or the ADA laws or the

50:46fire codes. The practical difficulty

50:49based on the language in the statute

50:52says that is to be determined through

50:55this process of weighing the benefits to

50:58the applicant and the benefits to the

51:01public interest

51:02including the interest in supporting the

51:04production of housing against the

51:06detriment to the public health safety

51:08and welfare of the neighborhood.

51:11And as part of this, I'm thinking we may

51:14also consider these four additional

51:16questions that are enumerated in there.

51:18So, I'd like to get your feedback on

51:20that because um as I said, all three

51:23very well-qualified attorneys have

51:25presented a slightly different

51:28read of the standard.

51:31So, do you have any comments to help us

51:33navigate that?

51:36So this is why I mentioned um furlong at

51:40the onset of my um presentation.

51:44Um I do believe that where the balancing

51:48test lies is in the public interest and

51:51sa safety is also included as part of

51:53that. Um

51:56the um the production of housing is

52:00clearly something that we're we're we're

52:02trying to achieve in this project.

52:05But the the balancing test, I see this

52:10standard as being something very similar

52:11to what the

52:14BCA has been doing for a very long time.

52:16It has now just simply been codified. Um

52:19the public health safety and welfare um

52:22has always been the the language of a

52:24special permit as well as a variance. Um

52:27but it gives you the ability and in

52:29great wide latitude to look at the net

52:32benefits of what the variance will grant

52:35me as the appalance or my client as well

52:38as what benefits given to the

52:40neighborhood that I cite uh fire code um

52:44that I cite um I think fire code was the

52:47big one as well as some efficiencies

52:49granted in the building looking to

52:51connect those issues of fire safety as

52:54being certainly something in that's of

52:56interest to the public welfare. Um that

53:00um the difficulty of designing a

53:02building that has mixed uses on every

53:04floor versus mixed uses on stacking

53:07floors, which is just a practical and

53:09more practical and better way to build a

53:12building. That the Harriet Jacobs House

53:14itself presents a challenge on this lot

53:17that doesn't exist on any other lot. um

53:20in that it needs to be preserved which

53:22is traditionally historical properties

53:23have not been something you can lever a

53:26a variance or uh a variance on at least

53:29um but you know certainly we we we've

53:32tried I think the the standard as I see

53:36it um

53:40looks at these things holistically um so

53:44I included um you know the fire code

53:48which you don't normally consider

53:49considered to be part of your calculus

53:51in determining a variance because there

53:55actually is case law that looks at

53:57safety in particular as being to the

54:01benefit of the public welfare. Um you

54:04know again I go back to furlong but you

54:07know this is where you had a 25-sided

54:10lot and the variance allowed for a

54:13better condition for the public. The

54:15better condition for the public I'm

54:16citing as well is the movement away from

54:18very large deeply rooted trees. The more

54:21we can preserve those root structures,

54:23the better off the neighborhood's going

54:25to be and the public realm is going to

54:26be. So my understanding of the standard

54:30as I I did get the um the training that

54:33you all received in terms of what the

54:35solicitor gave everyone um that that

54:39balancing test can look at those kinds

54:40of issues and that you're able to to

54:44weigh whether or not this is a better

54:46development scheme with the variance

54:48than it would be without. Um, you know,

54:50part of the complexity of this

54:52particular project is we have a project

54:54that we can build. Well, you know,

54:58we can disagree on the implications of

55:015.23.3C,

55:04but we have a building we can build that

55:06that's extremely close to the lot line

55:08of the neighbors that I don't believe is

55:10in anyone's best interest that we build

55:12it this way. And for all the reasons I

55:15cited in my memo, I think that that

55:17gives you at least a roadmap to seeing

55:20how we do meet the standard. I don't

55:22think it's the

55:24um is cut and dry and I don't know what

55:26those other attorneys drafted for you,

55:28but I do think that how we've presented

55:30this, we do meet the standard. It's not

55:33just the fire code as it relates to us.

55:35It's the fire codes relates to all those

55:37around us. It's not just the proxy. It's

55:39not just the tree root system itself.

55:41It's how we are able to design the

55:43building in a way that's safer for those

55:45abutters as well as um preserving trees

55:48for the public realm. So I don't I just

55:51I I see these things all being

55:53interconnected. I don't think that

55:54you're procluded from looking at any of

55:56these things based on how the standard

55:58is written.

55:59>> Thank you for that. Um I I do understand

56:01what you're saying. I think I think what

56:03I'm should have pointed out I think is

56:06that um in your memo you start by decid

56:11determining what is the practical

56:13difficulty and then going into the

56:15balancing test and I think my my

56:18understanding or what I saw in some

56:21other variations of how we should

56:24interpret this is that you engage in the

56:27balancing test. So in other words, first

56:29identify what's the benefit to you. The

56:31benefit to you, you said, you know, you

56:33gave us a number of things. And then you

56:35identify the benefit to the public

56:37interest. Again, you've identified a

56:39number of things. And you also identify

56:42the detriment to the public health

56:45welfare and safety of the neighborhood,

56:47however that neighborhood is defined.

56:49And then at the end of that, you may

56:52also ask these four additional

56:54questions.

56:56And by going through that analytic

56:59process, that's how you make the

57:01determination of what is a practical

57:03difficulty. You don't start by saying

57:05there's a practical difficulty. That's

57:07that's what I'm asking. U you know um or

57:11that's what I'm seeing. Yeah.

57:13>> The word may is is operable there. So I

57:15don't think the you have to consider any

57:17of those things.

57:18>> That's correct. I agree with you on

57:19that. Yes. But I'm just saying that if

57:22you want to consider those things, then

57:23it would be

57:24>> part of this um determination of what's

57:27a practical difficulty. Is that how you

57:29read it?

57:30>> Yes.

57:30>> Okay. Thank you.

57:36Any other questions?

57:39>> You all said, Wendy,

57:40>> for now.

57:41>> For [laughter] now. Okay. Thank you. Um,

57:44if there's no other comments or

57:46questions from fellow board members,

57:48I'll move to uh public comment. And I

57:52think and I propose um that after we

57:55hear back from the public, we'll also

57:57summarize uh any written correspondence

58:00that uh we I'll make a motion to

58:03continue uh so that we seek out uh

58:06guidance and interpretation from uh t

58:09city council. So, we'll hold off on um

58:13board deliberation

58:14>> city solicitor. Sorry, just

58:17>> Okay.

58:18>> Sorry.

58:20Uh so, uh checking um opening up for

58:24public comments. Any members of the

58:26public who wish to speak should now

58:28click the icon at the bottom of your

58:30Zoom screen that says raise hand. If

58:33you're calling in by phone, you can

58:35raise your hand by pressing star9 and

58:37unmute or mute by pressing star six.

58:40I'll now ask staff to unmute the

58:42speakers one at a time. You should begin

58:45by saying your name and address and

58:47staff will confirm that we can hear you.

58:50After that, we will have up you'll have

58:52to up to three minutes to speak before I

58:55ask you to wrap up.

58:58>> Suzanne Blair.

59:03Thank you very much. Um, I live at

59:05[clears throat] Five Fuller Place, which

59:07is near um it's it's right right in this

59:11neighborhood right off of Hillyard. And

59:14I'm also president of the Harvard Square

59:15Neighborhood Association and by

59:17profession an art and architectural

59:20historian who also does writing on

59:22cities. Um, the Harvard Square

59:25Neighborhood Association has decided to

59:28oppose the current plan for a number of

59:30reasons and I want to address it here.

59:32I've been at many of these meetings.

59:34Originally, this was presented to us as

59:36a luxury hotel. Some somewhat we were

59:40hoping like the Veritus Hotel. Um, from

59:43the outset, it was known through the

59:46historical commission and other ways

59:47that the Harriet Jacobs House really

59:49must be preserved. And we've got great

59:52examples of this kind of thing whether

59:55it's Frost Terrace or in other uh manner

59:59just the moving of a house like this

1:00:00would be a great expense and they knew

1:00:02this going into it. Um the other thing

1:00:06that I think that we need to address in

1:00:08terms of public good etc is that between

1:00:12this house and 127 Mount Auburn we will

1:00:17be losing in let's say 127 Mount Auburn

1:00:20about 35 rooms that are now local

1:00:23businesses um but they could also have

1:00:26been any historically were residences.

1:00:29Um, we could think about the same thing

1:00:31with the Harriet Jacobs House, which

1:00:32historically was residences and now, um,

1:00:35most recently local businesses. There

1:00:37were three on the the sort of basement

1:00:40area as you enter through Mount Auburn

1:00:42Street. Um, I and others have also been

1:00:46concerned about the very different

1:00:47configurations that that have been put

1:00:50forward. One issue that that I hadn't

1:00:52heard here, but I came in late to the

1:00:54meeting is that there's a trough um that

1:00:57runs down the back of Mount Alurn Street

1:01:00or the homes behind Mount Auburn Street

1:01:02for flooding. And what is going to be

1:01:04the impact of a deep cement well uh or

1:01:09wall rather on the flooding that that

1:01:12may cause to these areas both to the

1:01:14trees and to other concerns. The other

1:01:17issue with this and I I would you know I

1:01:20I support hotels. I support local

1:01:22businesses. I support residential. I'm a

1:01:25strong proponent of of bold great new

1:01:28design and historic preservation. But

1:01:31another major concern of mine is and and

1:01:34you alluded to this. This is a massive

1:01:36structure with a lot of residences and

1:01:38hotel rooms and it's supposedly

1:01:40separate, but we have one place for the

1:01:44um interior for the delivery and the the

1:01:47taking out of trash, etc., etc. on Story

1:01:50Street. That's a very narrow street and

1:01:52it's a critical street for all of the

1:01:54businesses in Harvard Square and anybody

1:01:56getting into our neighborhood because

1:01:58people it's a oneway going down off

1:02:00Brattle and if we've got large trucks

1:02:03trying to back into that area and trying

1:02:06to get out it's going to be it's a very

1:02:09tight space and and there doesn't seem

1:02:11to be room in that for a separate space

1:02:13for both the residences on the one hand

1:02:16and the hotel on the other. So I'm

1:02:19delighted that you are asking for a

1:02:22continuence and I hope that the among

1:02:25the other considerations including

1:02:27height will be the question of the loss

1:02:31of these other residences potentially

1:02:34and local businesses because we really

1:02:36need more affordable not only housing

1:02:40but also more affordable places for

1:02:42people to carry out their business in

1:02:44Harvard Square. Thank you so much.

1:02:46>> Thank you Miss Blair.

1:02:49Anita Patterson.

1:02:54>> Yeah, this is Anita Patterson, but I'm

1:02:56my husband, Orlando Patterson, is here,

1:02:58too.

1:02:59>> Yeah, I'm Orlando Patterson. We are at

1:03:0214 Hillad Street.

1:03:03>> We're Butters.

1:03:04>> Um, we're Abutters, one of the five

1:03:06Abutters.

1:03:08And um let me say first that um we've

1:03:12been in long discussions um uh with the

1:03:16developers of this project and um um

1:03:22we voice our support for the granting of

1:03:26um these variances tonight and this

1:03:28comes at the end of um long discussions.

1:03:32Let me just say first of all, you I'm a

1:03:35strong believer in the um position that

1:03:40the we should not make the perfect the

1:03:43enemy of the good. Um I think um we've

1:03:49the the five of us who are the mutters

1:03:54have um faced what we think is a

1:03:57nightmare of having a building only five

1:04:00feet from us.

1:04:02Um the developers have um come up with

1:04:06an alternative proposal which brings it

1:04:09all the way down to over almost 14 ft

1:04:13and for that reason we um we strongly

1:04:16support um granting of these variances.

1:04:21Um, we should also note that this

1:04:23version of the project receives support

1:04:25from the Cambridge Historical

1:04:27Commission, from Charlie Sullivan, and

1:04:30from the Harvard Square Advisory

1:04:32Council. It's not perfect by any means,

1:04:35but we think it's the best possible uh

1:04:38compromise. Uh, and it certainly will

1:04:41make life um a lot better um for us if

1:04:46this building is to be built at all.

1:04:52Mr. and Mrs. Patterson, thank you very

1:04:54much.

1:04:55>> Thank you.

1:04:57>> Christopher Macken.

1:05:02>> Uh, this is Christopher Macken. I am

1:05:05resident of 48 JFK Street in Cambridge

1:05:09and a tenant um at 17 Story Street since

1:05:132011. I'm also the vice president of the

1:05:16Harry Jacobs Legacy Committee, a 501c3

1:05:20nonprofit that hopes to be able to tell

1:05:22the story of the escape slave and author

1:05:27Harriet Jacobs when this building is

1:05:29built. Uh the project, as I understand

1:05:32it, has obtained a certificate of

1:05:35appropriateness from the city. That

1:05:37means it's going to proceed. The

1:05:39question is whether a plan can give

1:05:42greater relief to the abutters. Um and

1:05:45this variance which I believe is how

1:05:48this conversation is is contained or

1:05:51this meeting is about the variance. This

1:05:53not about the project in general but

1:05:55about the variance. This variance uh

1:05:57gives that relief to the abutters and

1:06:00also saves trees that are beautiful

1:06:04trees on this on this site. The Harriet

1:06:07Jacobs Legacy Committee um advocates for

1:06:10a project that includes public access to

1:06:13these buildings in order to be able to

1:06:15bring people in to tell the Harriet

1:06:17Jacobs story. A hotel use allows for

1:06:22public access. Uh if this was just a

1:06:25residential project, that would be much

1:06:28much more limited. Um the amended plan

1:06:32not only the variance before you not

1:06:34only helps the neighbors it strengthens

1:06:37the case for a hotel uh component. It

1:06:41appears if I am heard the discussion

1:06:44correctly that there's some perhaps

1:06:47difference of opinion that hopefully

1:06:48could be ironed out about a mixeduse

1:06:51project versus a commercial project. Uh

1:06:55this to me sounds like a mixeduse

1:06:58project and a mixeduse project is

1:07:00exactly what is needed. Uh this it would

1:07:03be wonderful to have more housing in

1:07:05Harvard Square, to have affordable

1:07:06housing in Harvard Square and to have

1:07:09access to a public building where people

1:07:11can learn this story. Thank you.

1:07:16>> Thank you, Mr. Min.

1:07:18>> Donar.

1:07:24Thank you. Can you hear?

1:07:26>> Yes, sir.

1:07:28>> Good. Uh, my name is Donald Wear. Uh, my

1:07:30wife Susan and I live at 16 Hillyard

1:07:33Street. So, we too are abutters of the

1:07:35proposed development. We moved here in

1:07:381980 and never left. And so, as you can

1:07:40see, we're very committed to the

1:07:42neighborhood. Um,

1:07:45the members raised some technical

1:07:48questions about whether the height limit

1:07:50should be 85 feet or 60 feet. I'll just

1:07:53say as a neighbor living in a

1:07:55three-story building um who under

1:08:00whatever height it is, we're going to

1:08:01lose a lot of sun. And so we've been

1:08:04very focused, very focused

1:08:06[clears throat] on the setback because

1:08:09uh even if we could persuade you that

1:08:11the limit was 60 feet, it's still very

1:08:14very tall. And so the setback is very

1:08:16important to us. And our understanding

1:08:19is that what's really before the BCA

1:08:21tonight is the setbacks and particularly

1:08:23the setback uh the Story Street setback

1:08:26because only by granting that variance

1:08:28can you allow the developer to then move

1:08:31the building further away from us. Um I

1:08:34just like to add a couple of of um I'd

1:08:36like to quote a couple of things u

1:08:39reports to give you some historical

1:08:41context on Story Street. I just thought

1:08:43this would be helpful. The Cambridge

1:08:45Historical Commission studied this in

1:08:471980 and wrote that quote, "Story Street

1:08:50is a transition point from the mixeduse

1:08:52character of Harvard Square to the

1:08:54primarily residential nature of the

1:08:56half-crowned conservation district which

1:08:59is Hillyard Street. I also want to note

1:09:01that 17tory street is is in the overlay

1:09:04district as as the members are aware.

1:09:06When the city adopted the overlay, it

1:09:08described in section 20.52 of the

1:09:11ordinance that one of the purposes was

1:09:13the need to mitigate the functional

1:09:15impacts of new development on

1:09:18residential neighborhoods. Putting these

1:09:20together, um, it makes good sense to

1:09:23grant a variance that allows the

1:09:25developer to push the hotel up against

1:09:28Story Street because by doing so, she

1:09:30can increase the setback from our

1:09:32Hillyard Street houses and allow for

1:09:34that transition from Harvard Square to

1:09:37the neighborhood that the city intended.

1:09:39So, we support the petition that is

1:09:42before the BCA tonight, which is to

1:09:46permit the uh variance to um uh uh to to

1:09:51zero out the um the setback on on Story

1:09:55Street and we suggest that doing so will

1:09:57carry out help carry out the twin

1:09:59objectives of the Cambridge Historical

1:10:01Commission and the overlay. Thank you.

1:10:05>> Thank you, Mr. Wear. Nicole Bryant.

1:10:11>> Good evening. My name is Nicole Bryant

1:10:14and I too am in a butter this time at 18

1:10:17Hillyard Street and I join in my

1:10:19neighbors um to support um the granting

1:10:23of this variance as regards this setback

1:10:26of this project. As you can imagine,

1:10:29many of us have been on a journey over

1:10:31these past couple of years since

1:10:33learning um about this project. And um I

1:10:36think it is fair to say that we have

1:10:37come a long way to be offering our

1:10:39support of this variance. Um tonight uh

1:10:45I have spent a lot of time thinking

1:10:47about what it would be like um looking

1:10:49at this building from my kitchen from my

1:10:51daughter's bedroom. Um but I will also

1:10:53offer another perspective because almost

1:10:55every morning you can find me at the

1:10:58corner of Mount Auburn and Story Street

1:10:59waiting for a Cambridge school bus with

1:11:02my family. And so I see this corner um

1:11:05in my blurry uh morning moments and I

1:11:08would like to just offer that the

1:11:10setback that is being proposed by moving

1:11:12the building closer to Story Street is

1:11:14pretty much identical to the one on the

1:11:16other side of the street at the post

1:11:18office where I'm standing every morning.

1:11:20It would seem then completely in keeping

1:11:22with the rest of the street to have this

1:11:25building um closer that way and

1:11:27obviously offer a lot of great relief um

1:11:30on the backside as well as green space

1:11:32and preservation of these trees which

1:11:34are so so important to all of us in

1:11:37preserving the residential aspect of

1:11:39this neighborhood. So I am here to offer

1:11:42my support. It would be wonderful to

1:11:44have um this public space with the

1:11:47hotel, the public space with the cafe

1:11:49that is planned and selfishly at 7:15 in

1:11:52the morning. I would love to have a

1:11:53latte as I'm out there waiting for the

1:11:55yellow school bus every morning. Thank

1:11:57you very much.

1:11:58>> Thank you, Miss Bryant.

1:12:02>> Noah Nathan.

1:12:07>> Hello. Um this is Noah Nathan. I live at

1:12:0912 Hillyard Street, also directly behind

1:12:11um this site. Can you hear me?

1:12:13>> Yes, sir.

1:12:14>> Great. So, I just wanted to echo what my

1:12:16neighbor uh Don Wear recently said,

1:12:18which is I think as I understand that

1:12:19the main issue before you tonight is not

1:12:21the question of height, but it's about

1:12:22the setbacks. And so, I want to focus my

1:12:25comments on the setbacks. And so, you

1:12:26know, contrary to the statement of the

1:12:28Harvard Square Neighborhood Association,

1:12:29I want to be clear that the abuters who

1:12:31live directly next to this property

1:12:33support the variance that's being

1:12:34requested tonight um because we think

1:12:37this meaningfully improves conditions

1:12:38for the neighborhood. And I also want to

1:12:40echo my neighbor Nicole Brian's comments

1:12:42just now that as someone who walks past

1:12:44um the site almost every day, I just

1:12:47want to stress that a zero foot setback

1:12:48on Story Street really doesn't seem like

1:12:50a problem in terms of public use. Many

1:12:52of the surrounding buildings on Story

1:12:53Street already have these same

1:12:55non-conforming zero feet setbacks. The

1:12:58post office building directly across the

1:12:59street from the site has a zero foot

1:13:01setback and a bus stop for the 71 and 73

1:13:03bus that gathers a lot of people on that

1:13:05sidewalk every day. And in my

1:13:06experience, it doesn't pose any issue

1:13:08for walking by that stretch of sidewalk.

1:13:10So, I think this is something that's not

1:13:12going to really impose a cost on the

1:13:13public to pull this building forward,

1:13:15but is going to meaningfully improve uh

1:13:17conditions for the people who have to

1:13:18live next to this building. And for that

1:13:20reason, we really hope that you're able

1:13:21to support um this variance petition.

1:13:23Thank you so much.

1:13:24>> Thank you, Mr. Nathan.

1:13:27>> Marley Mayer.

1:13:32>> Hi, Maril Meer. 10 Dana Street. Um, I am

1:13:35a member of the Harvard Square

1:13:37Neighborhood Association and also the

1:13:39Harriet Jacobs Legacy uh committee. Um,

1:13:44but I'm speaking for myself um tonight I

1:13:47have um just a couple of questions and

1:13:50I'm sure that if I stray off the

1:13:52reservation as not being um uh pertinent

1:13:56um I you will tell me. So I had a a

1:13:59couple of uh um questions. what was

1:14:03floated about the height even though

1:14:05even though we're talking about setback

1:14:07um I would like to know whether the

1:14:09height is 80 80 feet or 85 feet because

1:14:13both had float floated around in the

1:14:15discussion of what a residential

1:14:19um uh portion would be and number two um

1:14:24if a if a hotel is is commercial and the

1:14:28residential is uh a a separate a

1:14:32separate um

1:14:34uh

1:14:36um rules or whatever um and they they

1:14:40don't match. But if you put them

1:14:41together, one on top of the other, um

1:14:44that's where I get confused because um

1:14:47what has priority um and it says um

1:14:52technically the residential

1:14:55the the the greater the greater uh

1:14:58height u would prevail, but um and I'm

1:15:02glad you're you're having um um law

1:15:06department look into that. And um just a

1:15:09um a smaller design question even though

1:15:12um that again it may not be your purview

1:15:15is pulling pulling this um whole mass

1:15:18forward to Mount Auburn and um Story

1:15:22Street. Uh Patrick, what does that do to

1:15:24your cafe? I mean before you had, you

1:15:28know, a a plaza out front and all that

1:15:31kind of stuff. Um, and so you're just

1:15:35you're just pulling it um forward as a

1:15:37um commercial business, small business.

1:15:41Um, and I still have an issue with the

1:15:43way the windows are. Um, just they don't

1:15:46they don't fit with the rest of the um

1:15:50things. But anyway, that's not your

1:15:51perview either. Um, I really appreciate

1:15:54the fact that um you're you're giving

1:15:56the neighbors more space behind and I

1:15:59think that would uh that's going to

1:16:00really work well and also uh pulling the

1:16:04Harriet Jacobs house forward also give

1:16:07it more more prominence on that corner

1:16:10so um it can be more visible from

1:16:13various different um streetscapes. So

1:16:16thank you.

1:16:19>> Thank you Miss Meyer.

1:16:25Um the chair, this is Wendy Lyserson.

1:16:27The chair was just uh asking me just to

1:16:30quickly comment on those questions, all

1:16:32of which I think are good and which I

1:16:33share. Um the reason for the difference

1:16:37in the 80t versus 85 ft number though uh

1:16:41comes from one refers the 85- ft number

1:16:44refers to the base zoning district if it

1:16:47was not covered by the Harvard square

1:16:49overlay and the 80 foot uh figure comes

1:16:53from the section in the zoning ordinance

1:16:56regarding the Harvard square overlay and

1:16:59again if you want to look at that that

1:17:01is article 20.54

1:17:034.2 and then you'll see that there are

1:17:06two enumerated paragraphs in that

1:17:08section and the second paragraph um

1:17:12talks about getting a special permit for

1:17:14additional height up to 80 ft. Um and

1:17:18then I also just wanted to clarify that

1:17:21um height is a variable that is used to

1:17:25calculate the appropriate setback. And

1:17:28so that is why height is relevant to a

1:17:31variance for setbacks because you have

1:17:34to know the height in order to come up

1:17:36to what is the var setback that you're

1:17:40being asked to uh get zoning relief

1:17:43from. And I also uh just while I have

1:17:46the floor, I guess would say that my

1:17:49questions are meant to have clarity on

1:17:53the law and on what we as a board can

1:17:56decide. It's not a comment on whether I

1:17:59believe um the ideas proposed are good

1:18:04or bad. That is not what this is about.

1:18:07Thank you.

1:18:08>> Thank you, Wendy.

1:18:11Ronald Hifitz.

1:18:17>> Hi.

1:18:17>> Hi.

1:18:17>> Can you hear me?

1:18:26>> Um, my wife Katherine and I live at 20

1:18:29Hillyard Street and uh

1:18:32uh thank you very much for all of this

1:18:35conversation. Um, we agree with our

1:18:38we're one of the we're the fifth of the

1:18:40butters. Uh and we uh we agree with what

1:18:44all of our neighbors have said that this

1:18:46is right now um the the best of uh of

1:18:50what the options appear to be. Um, we

1:18:53have been told that uh if if the um

1:18:59uh if the uh

1:19:03um if the

1:19:07uh building is not approved at this

1:19:09height that they would simply turn it

1:19:12into a fully residential property in

1:19:15order to be able to keep it at this

1:19:16height. I don't um and assuming that

1:19:19that's the case uh I think it would be

1:19:23very upsetting if uh if the the decision

1:19:27of this board forced them to convert

1:19:30this

1:19:31mixeduse building to a fully residential

1:19:33building so that they could then um

1:19:36build a 85 ft building with a 5-ft set

1:19:38by without needing any variances at all.

1:19:42That would be the, you know, uh, uh, a

1:19:45worst case than the current situation in

1:19:48which we still have an 85 foot building.

1:19:50It isn't clear that the trees will

1:19:52survive even if the roots aren't damaged

1:19:55with the minimum of sunlight that it's

1:19:57going to be reached. But nevertheless,

1:19:59it increases the odds and it makes it

1:20:02much more livable for there to be green

1:20:04space, 13 and a half, 13 almost 14 feet

1:20:07of green space in back of us instead of

1:20:09five feet. So, you know, if if this

1:20:12board is going to make decisions that

1:20:14are going to push the developer to build

1:20:17a fully residential 85 ft tower 5T from

1:20:20us, that would be uh a pretty terrible

1:20:23outcome. Um, thank you very much.

1:20:26>> Thank you, Mr. Hest.

1:20:31>> Okay. hearing. Uh I think we've allowed

1:20:35all public speaking um to have uh their

1:20:40turn. Um, so running through uh

1:20:44correspondence.

1:20:45Um, we have an email from

1:20:49Miss Jill Jillson uh at the Harvard

1:20:53Square uh business association. um

1:20:58in favor of sharing a letter of support

1:21:01for the var variance petition um citing

1:21:05uh the restoration of the Harriet Jacobs

1:21:08House um

1:21:11and uh the added vibrancy of having a

1:21:14hotel in another hotel in Harvard Square

1:21:18as well as uh the addition of new

1:21:20housing. Um and

1:21:24uh project has

1:21:26The applicant has conducted extensive

1:21:28community outreach including meetings

1:21:30with neighbors and abutters and has

1:21:32worked to incorporate their feedback.

1:21:34The project has already received a

1:21:36certificate of appropriateness from the

1:21:38Cambridge Historical Commission

1:21:40confirming that its design is

1:21:41appropriate for its historic setting. Uh

1:21:44for these reasons, uh Jill Denise uh

1:21:48requests the board to grant uh the

1:21:50variance and uh thanks for our

1:21:53consideration. also received um

1:21:57uh a le a letter or email from Nicola

1:22:00Williams um attaching a memo from the

1:22:05Harriet Jacobs Legacy um as cited by uh

1:22:13uh just going through my notes here.

1:22:23Um from Mr. Jamaican. Um the memo cites

1:22:26uh

1:22:28support for uh the application

1:22:31um and uh from the board of directors uh

1:22:35of the Harriet Jacobs Legacy Committee.

1:22:37Um

1:22:39they believe that this is this plan

1:22:41responds both to the important concerns

1:22:43expressed by abuing neighbors as well as

1:22:45to the public interest. We therefore

1:22:47believe the request should be granted.

1:22:50Um and so that was thank you for sending

1:22:52that in. Uh a memo from the uh planning

1:22:56board to the board of zoning appeals. Um

1:23:00it was issued uh September 23rd. Uh they

1:23:03were citing uh they the planning board

1:23:06has discussed the proposal and voted to

1:23:09forward the following comments. Um as

1:23:12explained in the CDD memo uh the project

1:23:15will be subject to planning board review

1:23:18uh more as a advisory consultation uh

1:23:22where board members can make uh

1:23:24non-binding comments of the design. Um

1:23:27it has not conducted its full review at

1:23:29this time but I'm sure that'll get

1:23:31scheduled in the near future. Um,

1:23:34planning board members generally

1:23:35recognize the benefit of granting

1:23:37setback relief to move the building

1:23:39envelope further away from adjacent

1:23:41residential properties and mature trees.

1:23:44Uh, particularly on Mount Auburn Street,

1:23:47this shift towards the edge street edge

1:23:49is a favorable tradeoff for the overall

1:23:52site planning. Um, board members felt

1:23:55that a closer street wall was

1:23:57appropriate for activating the hotel

1:23:59frontage along an already wide public

1:24:02sidewalk that is approximately 10 to 12

1:24:04feet. Um, they did concern express some

1:24:07concerns of the proposed proximity of

1:24:11the project to Story Street given the

1:24:13narrow 5-ft existing sidewalk.

1:24:17Um but they since their review is not is

1:24:20has not really been completed they have

1:24:22not provided a specific recommendation

1:24:25but advises the BCA to ensure this

1:24:28condition is thoughtfully considered.

1:24:33Um, we also received a memo from C uh C,

1:24:38no, that's uh part of the planning board

1:24:41letter. Um, Harvard Square Advisory

1:24:44Committee dated September 16th. Uh, uh,

1:24:48the the Harvard Square Advisory

1:24:50Committee uh voted in support of the

1:24:52current application. Um,

1:24:59let's see.

1:25:02Uh

1:25:11just trying to summarize here. Um they

1:25:15recommend approval of the requested

1:25:17variance uh for 127 Mount Auburn Street

1:25:21uh 17 Story Street conditioned on

1:25:23continued dialogue with the Butters for

1:25:25improved design outcomes.

1:25:28Um and the vote was passed uh four to

1:25:32one vote um four in favor one abstain

1:25:36abstension vote of among voting

1:25:39committee members. Um jumping ahead

1:25:46and we did receive uh a letter from the

1:25:49Harvard Square Neighborhood Association

1:25:51September 16, 2026.

1:25:54Um key takeaways uh they they commented

1:25:58current approval record is not

1:26:00sufficiently clear. Um they would like

1:26:04uh kind of a synopsis or history of of

1:26:09the project development over time. Um

1:26:12preser second preservation and

1:26:14relocation of the Harriet Jacob house

1:26:16was a known project requirement not an

1:26:19unexpected hardship. Um, number three,

1:26:24Story Street is narrow and one way. Uh,

1:26:27the proposed 250 foot loading area

1:26:30should be tested uh for trucks making

1:26:3390° turns uh and 100% interior loading.

1:26:38Um and uh item four uh regarding the

1:26:43C1C2 boundary uh questioning um height

1:26:47calculations uh that need to be resolved

1:26:51uh citing the Harvard Square overlay may

1:26:54allow up to 80 ft by planning board

1:26:56special permit. The applicant should

1:26:58show how the boundary eight level

1:27:01mixeduse plan and grade calculations

1:27:03apply. Uh five, item five, proposal must

1:27:08distinguish permanent housing from hotel

1:27:10and transient use. Um and they are

1:27:15asking for uh additional information on

1:27:18condominium rental model um

1:27:24regarding the housing.

1:27:26And um that's pretty much um their

1:27:32concerns listed.

1:27:34Um, and I believe that was it for um

1:27:38written correspondence.

1:27:42So, um, Mr. Barrett, uh, we we I'll make

1:27:46a motion for continuence. Um, and I

1:27:50guess Olivia, do you have available

1:27:53dates for us?

1:27:54>> Excuse me, Mr. Chair. May I just ask

1:27:57something if we are going to continue

1:27:59this because I I do hear loud and clear

1:28:01the neighborhood uh the members of the

1:28:03public here who are desirous of uh some

1:28:07change to the setbacks but I also heard

1:28:10or read in the file some request for

1:28:14clarity of the plans to be reviewed by

1:28:16the public. So I do wonder um the other

1:28:19variable that is needed to calculate

1:28:22height is the length of the building.

1:28:26And um when I was reviewing the plans

1:28:29that had been submitted, it was unclear

1:28:33uh which side of the you know where that

1:28:37length was derived from. So I just

1:28:39wonder if the petitioner could do

1:28:41something simple. I'm not asking for

1:28:44stamped drawings or anything, but simple

1:28:46where they um submit something as part

1:28:50of the continued package that clearly

1:28:53marks what they're referring to as the

1:28:55commercial setback, the lengths of the

1:28:58building sides that are relative to the

1:29:01setback calculation,

1:29:04the number of residential units that

1:29:07will be um separate from the hotel rooms

1:29:11because we also saw that in the file.

1:29:15Um, and clearly marking which parts of

1:29:19both the old the historic building and

1:29:23which parts of the new building will be

1:29:25hotel versus residential?

1:29:28Um, and was there anything else that you

1:29:31heard from members of the public that

1:29:33would help them to review the

1:29:35>> No, I think in the in uh the

1:29:36correspondence there was some requests

1:29:38for just uh

1:29:41more committed information for us to

1:29:43review for the record. And I I think Mr.

1:29:45Barrett, that's that's a fair request

1:29:47because when we make a motion, I have to

1:29:51cite a set of documents that we're going

1:29:53to base, you know, the approval off of.

1:29:56And of course it will have the setbacks,

1:29:58but it I think having a configuration

1:30:00for the building and something that's

1:30:02officially set uh for us to approve is

1:30:07going to help go a long way for that.

1:30:11>> Thank you.

1:30:18>> Yeah.

1:30:18>> Would you like me to weigh in on any of

1:30:20that or should I?

1:30:21>> Yeah. Um just I think that request uh

1:30:24will help us with the motion and so on.

1:30:26>> Yeah, I understand everything that

1:30:28you're looking for and I've been here

1:30:29before. I do understand the requirements

1:30:31of a variance and what you guys are

1:30:33typically used to seeing and I do

1:30:34apologize that this project is in flux,

1:30:37but there's no other legal mechanism to

1:30:40address the setback. What I'm confused

1:30:43by and I and I think we're leaning

1:30:45towards not continuing um is on the

1:30:48issue of height and we've established

1:30:50that with ISD multiple times. I've

1:30:52written several memos on the subject. Um

1:30:55we're not going to be uh subject to

1:30:58further discussion on that in terms of

1:31:01going through a law review. Um and that

1:31:05also causes further delay. We have a

1:31:07project that we can move forward on that

1:31:08doesn't require us to be here. We did

1:31:11this primarily as a gesture to move the

1:31:14building to address concerns of the

1:31:16neighbors and this is the only legal

1:31:18mechanism I have. Um so I'm not asking

1:31:21you guys to

1:31:23I think I understand the complication

1:31:25and frustration that people are having

1:31:27with this. Um and to be frank I don't

1:31:29know what I was expecting for this

1:31:31evening for this project because I know

1:31:32we're not fully baked in knowing counts

1:31:35and hotel room counts. They'll be

1:31:37forthcoming. Um, but the level of

1:31:39commitment for a project this size to do

1:31:41all those things, once we're once we've

1:31:43done that, the site is we're cited.

1:31:46We're not going to move the building.

1:31:48Um, so I've consulted with my client and

1:31:52I think um

1:31:56uh the best course of action for my

1:31:58client is not to continue. Um, we'll

1:32:00withdraw and um we'll just continue on

1:32:03with the Bite residential project um and

1:32:06move on from there. But thank you.

1:32:12>> Excuse me. This is Wendy Lyserson. I

1:32:14just wanted to say for the record, I

1:32:16don't think that when a legal decision

1:32:19is being asked to be made that it is

1:32:22unusual to ask for the record to show

1:32:25what the actual criteria and figures

1:32:28are. I'm sorry that your client feels

1:32:31that way because I think you are

1:32:32disappointing

1:32:34um most of the neighbors and you've

1:32:36already put this much effort into it and

1:32:38it would be sad to see you withdraw this

1:32:41way.

1:32:42>> We're not we're not talking about the

1:32:43setback and the height. We're not we're

1:32:45not talking about the calculations of

1:32:46the setbacks. Those are actually largely

1:32:48irrelevant. Um because if you're talking

1:32:51about the height and width of the

1:32:52building to determine the setbacks,

1:32:54we're asking to be able to use the

1:32:56residential setbacks. So whatever

1:32:58calculation we come up with, whatever

1:33:00we're asking for in terms of relief, we

1:33:02can provide I'm happy to provide that

1:33:03calculation to show you what it would

1:33:05have been at the new configuration.

1:33:07We've already showed the city what it

1:33:09has been, what it would be with our

1:33:11current configuration. Our current

1:33:13>> it needs to be a matter of the record

1:33:14that we're reviewing and it is not as

1:33:16you've conceded. So thank you.

1:33:19>> Oh, thank you. Okay.

1:33:40All right. So, um the proponent has

1:33:44appellent has uh requested to withdraw

1:33:46the application. Um I believe that it's

1:33:49a discussion for the board to um decide

1:33:54whether to make that motion and make it

1:33:56happen. I guess our other option would

1:33:58be to

1:34:01deliberate on what we have or you know

1:34:04depending on the board's favor uh to

1:34:06make a decision or uh approve the

1:34:09withdrawal. Right. So any comments from

1:34:12fellow board members?

1:34:16>> This is Daniel Dogo. Well, I you know, I

1:34:18understand the legal complexities here,

1:34:20but I I guess I'm willing to trust ISD,

1:34:24etc. Um, you know, uh, consider all

1:34:28these issues. And so, I I'm actually

1:34:30perfectly fine moving forward on a vote

1:34:32and I I would support this, uh, given

1:34:35what we heard from the neighbors and and

1:34:37the complexity of this project. But, um,

1:34:38but but I understand that's not the what

1:34:42what the rest of the board would be

1:34:43interested in.

1:34:47This is Wendy Lerson. I'm also trying to

1:34:50think about is there any remedy here?

1:34:53And my question is, is the petitioner

1:34:57able to state clearly for the record

1:35:00what the dimensions are that you are

1:35:03seeking? And then we can amongst

1:35:06ourselves decide whether we believe that

1:35:09those dimensions

1:35:11are

1:35:13do satisfy the legal question.

1:35:16Which actually I do want to call

1:35:18attention to the fact that the

1:35:19petitioner himself raised the fact that

1:35:22mixeduse development was not

1:35:24specifically contemplated in this new um

1:35:28zoning and therefore this is what's

1:35:30partly causing the problem.

1:35:33>> And and I I cited that because we're we

1:35:36have an issue where we have two setback

1:35:39configurations. Um we have a residential

1:35:42setback and a commercial setback. So um

1:35:45what we're asking for

1:35:48is dimensionally is very clear on the

1:35:50table on the the chart that we gave you

1:35:53um that shows the existing uh conforming

1:35:55approved side setbacks but um but not

1:35:59the

1:36:00um well the side setbacks I guess that's

1:36:03all we're talking about front and side

1:36:05and what we can what we want to move the

1:36:06building to which is the 510 on Mount

1:36:09Auburn the 10 foot6 at the in between

1:36:12the two buildings of Mount Auburn

1:36:1413.8 behind Hilliard, 5T next to 15th

1:36:18story. Um, and

1:36:21we're at zero um on on that stretch of

1:36:24story street uh for the first half of

1:36:26the building. Um, those are the

1:36:29dimensions that we're asking for. Um,

1:36:34I'm not sure I can be any more clear. I

1:36:36think what I think, and please correct

1:36:38me if I'm wrong, is I'm not trying to be

1:36:40combative. What you're I think what you

1:36:42were asking for before was what would

1:36:44the dimensions be if we had to conform

1:36:47to the commercial setback for the hotel.

1:36:50Is that correct?

1:36:52>> No. Um my question was simply because

1:36:55you are invoking two different setback

1:36:58um formulas here or rules you know for

1:37:02calculating the dimensional standards.

1:37:05All I'm asking for is a clear statement

1:37:09that's legally supported. Um, and

1:37:12unfortunately because of the mixed use

1:37:14issue, it's which you reference, it is a

1:37:18matter that has not been well

1:37:21written, shall we say. Um, so I'm simply

1:37:25asking for that data, that evidence to

1:37:30be on the record of this decision

1:37:32because recall also that you are not the

1:37:36whether I like your proposal or not,

1:37:38whether the neighbors like your proposal

1:37:39or not, there's also a precedent here

1:37:41that we're setting and I want to make

1:37:42sure that we in today's local

1:37:46environment are using the right

1:37:48dimensions and the right calculations.

1:37:50So, um,

1:37:52>> we're asking for the dimensions shown on

1:37:55>> and there was some confusion about that

1:37:57and from some of the people who looked.

1:37:59Yes, you may talk. Sorry.

1:38:01>> We we're asking for the dimensions that

1:38:03we show on the table that shows the

1:38:04before and after of the setback.

1:38:06>> Um, I just cited what those numbers are.

1:38:10That's what we're asking for. And as far

1:38:11as precedent goes, um, the city is

1:38:14already looking to fix this issue. We're

1:38:16ahead of the curve on that this um the I

1:38:20actually have another case this evening,

1:38:21so you're going to see me again. I'm

1:38:22sorry. Um that's another corner lot. Um

1:38:26dealing with a much smaller site, but

1:38:28similar issues. Um this

1:38:32um comports very well with urban design

1:38:35guidelines and everything else that

1:38:36we're told we should be looking at in

1:38:39terms of how we develop a site. But from

1:38:41a a numerical standard, what we're

1:38:43asking for is 10 foot six

1:38:46on the side, 5 foot 10 on the Mount

1:38:48Auburn side, zero on the Story Street

1:38:50side, 5T on the abuing uh 15 story

1:38:55street property line, and 13.8

1:38:58for the Hillyard line. Those are that's

1:39:00what we're asking for for the building.

1:39:02So, uh, I'm sorry, uh, attorney, uh,

1:39:05Barrett, to interrupt you, but

1:39:13here's the thing. I would love to,

1:39:15please, the neighbors. I would love to

1:39:17not continue this case. And, um, I'm

1:39:20feeling, frankly, a little bullied by

1:39:22the fact that you're saying we're going

1:39:23to withdraw it and just do what we want

1:39:25to do when you've already come to an

1:39:27agreement that pleases the neighbors.

1:39:30We'll will make a nice development

1:39:32project in Harvard Square simply because

1:39:35I'm asking for clarity on the law

1:39:37>> and that doesn't seem right to me and um

1:39:41>> and and I [clears throat] understand

1:39:42that you just told me your numbers, but

1:39:45I recall now that the issue is were

1:39:48those numbers properly calculated and

1:39:50that's what I'm asking for clarity from

1:39:51from the legal department. We're willing

1:39:53to put you on the calendar as soon as

1:39:55possible. You've had this property for a

1:39:58long time

1:39:58>> calculation to be done. Well,

1:40:01>> I'm sorry.

1:40:02>> There's no

1:40:02>> there's no calculation that's required.

1:40:04We are we are asking to use the

1:40:06residential setbacks as as they are to

1:40:10have the commercial setback mirror the

1:40:12residential setback. There is no

1:40:14calculation. So that's where I'm

1:40:16confused.

1:40:17>> I'm not trying I'm not trying to bully

1:40:19you, but we

1:40:20>> I know I understand you're frustrated. I

1:40:22do.

1:40:23>> This option came to us at a very sort of

1:40:25last minute. We had no no intention of

1:40:27even doing this because there's no legal

1:40:29way to do it. Um, but you're telling me

1:40:31you want the calculations for the

1:40:33setbacks when I'm confused because there

1:40:35is no calculation. The required setback

1:40:38on this lot for residential use would be

1:40:4010 feet on the and five feet on the

1:40:42sides.

1:40:43>> Like you, I have also consulted ISD

1:40:45staff. So, I'm not just bringing this

1:40:47out of the blue either. And so, I

1:40:49wouldn't I trust the ISD staff as well.

1:40:52And if there's any confusion, then

1:40:55that's where we have to go to law. Mr.

1:40:57Stop talking. I think I think if board

1:41:00members need additional clarification,

1:41:03it's not an indication, I don't think,

1:41:05of you know, denial or not in favor, but

1:41:08we I think we have to do our due

1:41:10diligence to make sure that uh we feel

1:41:14it's we're doing all the right things to

1:41:17get to a decision for you and your and

1:41:19your your uh client. So, if we're trying

1:41:24to get um and I appreciate all the work

1:41:27and I see the the public support and

1:41:30especially the abutters. So, you know, I

1:41:32think it's better to allow this board to

1:41:36do the our job to make sure we've got

1:41:40the right info and and just kind of, you

1:41:43know, take it to that next step.

1:41:49>> Okay, Mr. Chair, you win.

1:41:52Thank you, sir. Um, and is

1:41:57so I'm gonna make and we we'll catch up

1:42:00with you on the the uh next application

1:42:02coming up. But um yeah, so let me make a

1:42:07motion to continue

1:42:09uh to continue the matter of BZA case

1:42:131225403

1:42:16uh for 127 Mount Auburn Street to the

1:42:19what's our next

1:42:21>> next one is October 15th

1:42:23>> October 15th uh hearing. Is that work

1:42:25for you, Mr. Barrett?

1:42:27>> I'm sorry. The date is October 15th.

1:42:29>> Yes.

1:42:31>> Perfect. Thank you.

1:42:32>> All right. uh to the October 15, 2026

1:42:35hearing on the condition that the

1:42:37petitioner change the posting sign to

1:42:38reflect the new date and the new new

1:42:41time of 6 pm. Also that the petitioner

1:42:44sign a waiver to the statutory

1:42:46requirements of the hearing. This waiver

1:42:48can be obtained from Maria Pacheo or

1:42:51Olivia Retay at the inspectional

1:42:53services department. I ask that the

1:42:55petitioner sign the waiver and return it

1:42:58to the inspectional services department

1:43:00by a week before this coming Monday.

1:43:02Failure to do so will de facto cause

1:43:05this board to give an adverse ruling on

1:43:07the case. Uh also if there are any new

1:43:10submitts, changes to the drawings,

1:43:11dimensional forms, or any supporting

1:43:14statements that those be in the file by

1:43:165:00 p.m. on the Monday prior to the

1:43:19continued meeting date. on the motion to

1:43:22continue.

1:43:25>> Oh. Um, can uh before I close the

1:43:28motion, can uh other members uh make the

1:43:31October 15th hearing?

1:43:35>> Yes, Virginia.

1:43:37>> Thank you, Virginia.

1:43:41>> Yes, Miranda Cecil.

1:43:45>> And thank you, Dan and Miranda. So,

1:43:47>> and Wendy. Yes.

1:43:48>> Thanks, Wendy. Uh on the motion to

1:43:50continue this matter until October 15th.

1:43:54Uh Wendy Lyserson, voice vote, please.

1:43:58>> In favor. Thank you.

1:44:00>> Uh Dan Hidalgo

1:44:03in favor.

1:44:04>> Virginia Keiesler.

1:44:05>> Virginia Keysler in favor.

1:44:07>> And Miranda Cecil.

1:44:11>> Miranda Cecil in favor.

1:44:12>> And Stephvening in favor. Okay. Thank

1:44:14you very much. Thank you.

1:44:21All right. Our next

1:44:24our next case for uh 615 was 86 Sharappa

1:44:29Street.

1:44:31Um

1:44:33uh Arez Yoli, uh seeking a special

1:44:36permit to replace an existing

1:44:38nonconforming side landing and stair

1:44:41that increases length of structure but

1:44:44maintains existing width that sits in

1:44:47the side setback uh citing articles 5.31

1:44:52table of dimensional requirements uh

1:44:56article 8.22.2d

1:44:582.D non-conforming structure and article

1:45:02uh 10 section.40

1:45:05special permit. Um Mr. Yoi Yo Ellie, are

1:45:10you available?

1:45:12>> Yes. Hi.

1:45:14>> Hello.

1:45:16>> Thanks for hearing the case.

1:45:21>> Okay. Tell us about uh your special

1:45:24permit request.

1:45:26>> Sure. Let me cave you up by saying I'm

1:45:29just a homeowner who doesn't have much

1:45:32experience doing this.

1:45:34>> Okay.

1:45:34>> Um I'm not developing any hotels. Um I

1:45:39own a very small house in East

1:45:41Cambridge. Uh the entire house sits on a

1:45:4320 foot by 30 foot lot. Um it was

1:45:47probably the carriage house to one of

1:45:48the houses around the corner 150 years

1:45:51ago. Um and was carved out. The uh house

1:45:55sits on most of the lot. The house has

1:46:00three points of egress. The front door,

1:46:03uh door from the basement, which is not

1:46:05um a compliant uh form of egress, and

1:46:08the rear um door from the kitchen, which

1:46:13is the um

1:46:16uh point of egress that we're discussing

1:46:18today. It has a landing that was uh

1:46:20probably built in 2013.

1:46:23Uh it's falling apart. It has been

1:46:26falling apart for months. I've been

1:46:27trying to get this permit for months so

1:46:28that I could fix it and make it safe. Um

1:46:31and uh I am asking to change the

1:46:35dimensions of this a little bit. Um I

1:46:38would like to extend the landing itself

1:46:40so that it clears the window that is

1:46:42underneath it. You can't see that window

1:46:44from the photos that you are looking at

1:46:46right now, but there is a window like it

1:46:49uh which is the one that you see uh

1:46:51behind the stairs. There's a second one.

1:46:54>> Um, if you want, I'll get up and show it

1:46:56to you because I'm sitting in the

1:46:57basement, which is where it's at. Um,

1:46:59and that window is blocked by the

1:47:02landing. And so, if we extend the

1:47:04landing by a few inches, um, and

1:47:09adjust the height of it and so that we

1:47:11don't have to extend the full run of

1:47:13stairs. We can actually cut a stair um,

1:47:15and stay with all very close to the

1:47:17existing dimensions. Then I can put in a

1:47:20glass floor over that window and uh get

1:47:23it some light. Um so the project sort of

1:47:26designed to make the minimal changes to

1:47:28the existing structure but allow for

1:47:30that. Uh and that's what I'm asking for

1:47:32uh permission to do. What what can I

1:47:35answer that would be helpful to you guys

1:47:36since I I don't actually know if

1:47:37anything I said was helpful. Well, I

1:47:39think I think you now I now understand

1:47:42the glass uh det material product info

1:47:46you gave in in your application. So I I

1:47:49can see why you could get daylight down

1:47:51into um that particular window. So that

1:47:55helps me quite a bit. Um thank you for

1:47:59the presentation. Um uh any questions

1:48:02from fellow board members?

1:48:04>> This is Wendy Lyserson. I have no

1:48:07questions. you'll be glad to hear.

1:48:11[clears throat]

1:48:18>> Uh any any other board members,

1:48:20comments, questions?

1:48:29Hearing none, um I'll uh move to public

1:48:34comment. Um, in the file we have one

1:48:38email uh from Abigail Lewis Bowen. Uh,

1:48:43and she writes, "We are writing today in

1:48:45support of the petition by Arez Yoli,

1:48:51uh, at 86 Jerappa Street. Uh, we live at

1:48:5380 Thornike Street and our backyard

1:48:55directly abuts the rear of the property.

1:48:58Concerned. We have no concerns regarding

1:49:00this petition and support the

1:49:02petitioner's request for the special

1:49:05permit which makes the side landing and

1:49:08stair more usable while having

1:49:10negligible impact on any surrounding

1:49:12properties. Kind regards uh the al uh

1:49:16Abigail and Alistister Lewis Bowen.

1:49:18Thank you uh for that. Um, and I'll also

1:49:23uh check uh any members of the public

1:49:26who wish to speak should now click the

1:49:28icon at the bottom of your Zoom screen

1:49:30that says raise hand. If you're calling

1:49:33in by phone, you can raise your hand by

1:49:34pressing star9 and unmute or mute by

1:49:37pressing star six. I'll now ask staff to

1:49:40unmute the speakers one at a time. You

1:49:42should begin by saying your name and

1:49:44address and staff will confirm that we

1:49:46can hear you. After that, you will have

1:49:48up to two minutes to speak before I ask

1:49:51you to wrap up.

1:49:56Nope. So, there's no one um online for

1:49:59public speaking. So, um

1:50:02closing public comment, moving to uh

1:50:05deliberations. Um if are there any

1:50:08comments from the board or are you ready

1:50:10to entertain a motion?

1:50:15>> Ready for a motion.

1:50:17Thank you. So, uh, the chair makes a

1:50:19motion to grant a special permit from

1:50:21the requirements of the ordinance under

1:50:23sections, uh, 5.31,

1:50:27uh, sections 8.22.2.D,

1:50:30a non-conforming structure, and sections

1:50:3210.40 for a special permit. uh respon uh

1:50:37reviewing responses uh for supporting

1:50:40statement for a special permit that a it

1:50:43appears the requirements of this

1:50:44ordinance cannot or will not be met. Um

1:50:47the proposed replacement extended

1:50:49landing does not create any new

1:50:51dimensional nonconformity.

1:50:54Um a proposed structure has identical

1:50:57footprint height and location to the

1:50:59existing pre-existing non-conforming

1:51:01structure at the northeast corner of the

1:51:03lot. Uh item B, traffic generated or

1:51:06patterns of access of egress could cause

1:51:09congestion hazard or substantial change.

1:51:11Uh the pro proposed replacement landing

1:51:14is a private residential access and will

1:51:17not um generate uh traffic or alter

1:51:22patterns or of access or egress to or

1:51:25from the public way. Um item C, the

1:51:28continued operation of or the

1:51:30development of the adjacent uses as

1:51:33permitted in the zoning ordinance would

1:51:35be adversely affected. Um and the

1:51:38replacing the instru existing structure

1:51:41uh in in kind same location, footprint

1:51:44and height will not impact um

1:51:49or create an adverse uh condition. Uh

1:51:52item D, nuisance or hazard would be

1:51:54created to detriment of health, safety

1:51:57or welfare of the occupant and it will

1:52:00not and for other reasons the proposed

1:52:02use would impair the integrity of the

1:52:04district or adjoining districts and uh

1:52:07we find that it will not. So based on

1:52:10that finding they meet uh the criteria

1:52:13in the section 10.40 40 for a special

1:52:15permit and further that we incorporate

1:52:18supporting statements and dimensional

1:52:20forms submitted as part of the

1:52:21application on a voice vote please.

1:52:24Board members Wendy Lyserson.

1:52:26>> Wendy Lyserson in favor.

1:52:28>> Thank you. Virginia Keiesler.

1:52:31>> Virginia Keiesler in favor.

1:52:33>> Thank you. Virginia Daniel Halgo.

1:52:35>> Daniel.

1:52:37>> Thank you. Miranda Cecil.

1:52:40>> Miranda Cecil in favor.

1:52:42>> Thank you. And Stephvening in favor. So

1:52:44vote is 50 in favor. And the special

1:52:48permit is granted.

1:52:52>> Thanks guys. Have a good night. Thank

1:52:54you. You too.

1:52:55>> You too.

1:52:57Next up is uh case number uh BZA1225403

1:53:05um 200 Auburn Street uh care of Adam

1:53:08Dash uh seeking a variance for new

1:53:11construction of a residential structure

1:53:14pre-existing non-conforming minimal

1:53:16front yard setback uh requiring relief

1:53:19are citing our section articles 5.31

1:53:24table of dimensional requirements ments

1:53:27uh section 8.22.3

1:53:29non-conforming structure and section

1:53:3210.3 for variance. Um

1:53:37>> Mr. Dash,

1:53:39>> Mr. Chair, [clears throat] good evening.

1:53:41>> Good evening.

1:53:41>> Attorney Adam Dash, 48 Grove Street in

1:53:43Somerville, representing the petitioner,

1:53:46200 Auburn Street LLC. Uh with us is

1:53:49Jeremy Henry of the petitioner, uh Clay

1:53:52Bero, uh the builder, and Tatiana, the

1:53:55architect, should we need them.

1:53:57Hopefully, we will not. Um petitioner

1:53:59seeks a variance for non-conforming

1:54:01minimum front yard setback as you stated

1:54:03in the resident C1 zoning district. This

1:54:06is a very odd situation because we are

1:54:08seeking a variance to keep the building

1:54:11as it is with regard to that front yard

1:54:13setback for which we are seeking a

1:54:14variance. I had not seen this happen

1:54:17much in the past,

1:54:18>> but allow me to tell a little bit of a

1:54:20story here. I apologize if it may go on

1:54:21a little bit, but

1:54:23>> the need for this relief um comes out of

1:54:25an unforeseen issue which arose during

1:54:27construction of this project which was

1:54:29approved by Wright. The petitioner

1:54:31obtained a byite building permit to

1:54:33alter the existing 4-unit residential

1:54:35structure. During construction, it was

1:54:38found that the existing framing was

1:54:40rotted. So, it was removed and replaced

1:54:42in the same location to remediate a

1:54:44dangerous situation. And you have a

1:54:46letter from Anderson Pacheo of Alpha

1:54:48Carpentry, uh, who was doing that work

1:54:51and cooperates this. The city then said

1:54:53that since the framing had been

1:54:55replaced, even though it was in the

1:54:57exact same place, that the project now

1:54:59constitutes new construction and the

1:55:02previously grandfathered pre-existing

1:55:04front yard setback now requires a

1:55:06variance even though it's staying

1:55:08exactly the same place. So, keep in mind

1:55:11the front yard setback's not changing.

1:55:14It's pre-existing. It's only because the

1:55:16existing framing was found to be rotted

1:55:18and not feasible to retain that the need

1:55:20for the front yard variance arose.

1:55:23There's practical difficulty to the

1:55:24petitioner related to the layout and

1:55:26location of this pre-existing structure.

1:55:28Had the structure not been in a

1:55:31situation with the pre-existing front

1:55:32yard setback nonconformity, then

1:55:35replacing the rotted framing would not

1:55:36have triggered any need for variance

1:55:38whatsoever. Um strict enforcement would

1:55:41require the petitioner to demolish

1:55:43and/or move the struct the building from

1:55:46its pre-existing location which would be

1:55:48a substantial hardship and impractically

1:55:51difficult especially with work under the

1:55:54byite per building permit being partly

1:55:56done.

1:55:57There's no other way to achieve the

1:55:59result here without this variance

1:56:00because the rotted framing had to be

1:56:02replaced for safety reasons and that

1:56:04would create the need for this variance.

1:56:06Uh the petitioner is only seeking to

1:56:08keep that existing front yard setback

1:56:10the same as it's always been and the

1:56:12same as it was for the byite building

1:56:14permit. The variance will allow the

1:56:16existing streetscape to be retained. Uh

1:56:18there's no new residential units being

1:56:20proposed. The relief sought is for the

1:56:23six-foot pre-existing front setback

1:56:25where 10 ft is required. However, as you

1:56:28can see in the plans we filed, the

1:56:30average front setback of the houses on

1:56:31either side is only 6' 10 in. So the

1:56:35relief sought would keep things

1:56:37basically the same kind of a context and

1:56:40keep everything contextually

1:56:41appropriate. The practical difficulty

1:56:44was not self-created. A petitioner had

1:56:46no idea the framing was rotted and and

1:56:49we and would end up stuck in the same

1:56:51situation whether they'd actually

1:56:52replace that framing or come to you

1:56:54first. It really doesn't matter. The

1:56:56situation would have been the same. Um

1:56:59there was no feasible alternative and

1:57:01petitioner you know as I said would be

1:57:03here anyway and I I hope that they don't

1:57:05end up penalized for remediating an

1:57:07unsafe situation. Um you have a letter

1:57:10of support from the Cambridge Zen Center

1:57:12directly across the street from and

1:57:13adjacent to the property at issue.

1:57:16>> Um please note that the original

1:57:17dimensional table just for the record

1:57:19that was filed with this petition was

1:57:21later revised but the revision had

1:57:23nothing to do with the front yard

1:57:24setback. It was had to do with issues

1:57:27that came out of the Mass Architectural

1:57:28Access Board for other other things why

1:57:31we had to file an amendment. But the

1:57:32front yard setback issue we're here

1:57:34tonight is not related to that. So the

1:57:37petitioner requests that the board grant

1:57:39the variance for the minimum front yard

1:57:41setback even though the front yard

1:57:42setback is not changing from what it

1:57:44was. So there is the odd situation I

1:57:47have for you this evening. Thank you.

1:57:48>> Thank you so much. Um I think it's

1:57:51pretty straightforward uh uh situation

1:57:54here. Um any questions from fellow board

1:57:58members?

1:58:01>> This is Wendy Lyserson. I also don't

1:58:04have questions. Just seeking

1:58:05confirmation of the analysis that under

1:58:07the new variants. So the benefits to the

1:58:09petitioner is to allow the existing

1:58:11structure to stay exactly the same

1:58:13without costly and frankly uh seemingly

1:58:16impossible alternatives. Uh the benefits

1:58:19to the public interest is to maintain

1:58:21the neighborhood streetscape as is and

1:58:23not disrupt it.

1:58:25there uh seems to have been no detriment

1:58:28articulated

1:58:29um to the public health, safety and

1:58:31welfare um of the neighborhood. And I

1:58:36have not found one, but perhaps others

1:58:38will chime in on this. And then the four

1:58:43additional factors that we may consider

1:58:46per the new law are, as attorney Dash

1:58:50just articulated, so I won't repeat

1:58:53them. And having

1:58:57gone through that analysis, I agree that

1:59:00um there's a practical difficulty here

1:59:04that um supports a variance in this

1:59:06case.

1:59:07>> All right. Thank you, Wendy. Um any

1:59:09other comments from fellow board

1:59:11members?

1:59:14Uh we'll move to uh public comment. Um

1:59:18we did as mentioned uh by Mr. dash uh an

1:59:22email from the Cambridge Zen Center in

1:59:24support and um so that was it there and

1:59:30so we'll check for any public comment

1:59:33online. Any members of the public who

1:59:35wish to speak should now click on the

1:59:37icon at the bottom of your Zoom screen

1:59:39that says raise hand. If you're calling

1:59:41in by phone, you can raise your hand by

1:59:44pressing star9 and unmute or mute by

1:59:46pressing star six. I'll now ask staff to

1:59:49unmute the speakers one at a time. You

1:59:52should begin by saying your name and

1:59:53address and staff will confirm that we

1:59:55can hear you. After that, you will have

1:59:58up to two minutes to speak before I ask

2:00:00you to wrap up.

2:00:03Anyone online?

2:00:06>> All right. Seeing no one uh needing to

2:00:10speak, uh we'll close public comment and

2:00:12move to deliberations.

2:00:15Um any comments,

2:00:19questions from fellow board members? Um

2:00:24I will move into uh a motion. Um

2:00:29the chair makes a motion to grant relief

2:00:31from the requirements of the ordinance

2:00:33under sections 5.31 table of dimensional

2:00:36requirements, sections 8.22.3 22.3

2:00:40non-conforming structure and section

2:00:4210.3

2:00:43uh for variance. Uh

2:00:48reviewing um standards uh for granting

2:00:52of variance uh permanent authority

2:00:54specifically finds that a strict

2:00:56enforcement of the ordinance or bylaw

2:00:58would result in a practical difficulty

2:01:00in making the determination. The permit

2:01:04granting authority shall weigh the

2:01:06benefits to the appellant or petitioner

2:01:10and to the public interest including the

2:01:12interest in supporting the production of

2:01:14housing against the detriment to the

2:01:17public health, safety and welfare of the

2:01:20neighborhoods and may also consider one

2:01:23whether the practical difficulty relates

2:01:26to soil condition, shapes or topography

2:01:28of such land or structures. Um

2:01:36the layout and location of the existing

2:01:38structure within the front setback

2:01:40creates the practical difficulty had the

2:01:42existing structure had not been

2:01:44pre-existing nonconforming front yard

2:01:48setback then replacing the framing would

2:01:50not have created the need for variance.

2:01:52Uh item two, whether the strict

2:01:55enforcement would impose a financial

2:01:57hardship on the appellant or peti

2:01:59petitioner. Uh project was approved by

2:02:02Wright and given a building permit to

2:02:04alter existing structure. Uh during

2:02:06construction, it was found the existing

2:02:08framing was rotted. Uh so it was removed

2:02:12and replaced in same location. um to

2:02:17repair that damage. Uh the city required

2:02:20uh since the framing was replaced even

2:02:23though it was in the same place, the

2:02:24framing constituted new construction. As

2:02:27such, the pre-existing non-conforming

2:02:29minimum front yard setback now required

2:02:32a variance even though the building was

2:02:34going to be in the same place as before.

2:02:37uh having to tear down move the building

2:02:39from where it had been for a very long

2:02:41time only to do only due to the

2:02:44replacement of rotted framing would be a

2:02:48substantial hardship to the applicant.

2:02:50Uh item three uh whether the benefit

2:02:53sought by the appellant or petitioner

2:02:55can be achieved by some other method

2:02:57feasible uh for the appellant or

2:02:59petitioner to achieve. Um

2:03:04the replaced uh replacing the stair uh

2:03:07due to rotted framing was what triggered

2:03:09the variance. Um trying to shift the

2:03:14building uh would

2:03:22would be an uh would not be the best uh

2:03:25method feasible uh to meet this. Uh and

2:03:28item four, whether the practical

2:03:30difficulty was self-created [snorts]

2:03:32and it was it was not it was a

2:03:35pre-existing condition for the existing

2:03:38stair uh and um

2:03:41applicant should not be penalized for

2:03:43remediating the dangerous situation. Uh

2:03:47so based on that finding uh the

2:03:50applicant meets the criteria under 10.34

2:03:53variance on the condition that the work

2:03:56proposed conform to the drawings uh to

2:03:59the drawing set

2:04:01um

2:04:04entitled 200 Auburn Street house

2:04:06renovation by TC Studio dated August 15,

2:04:102026. and further that we incorporate

2:04:12the supporting statements and

2:04:14dimensional forms submitted as part of

2:04:17the application on a voice vote please.

2:04:19Board members Wendy Lyserson

2:04:21>> Wendy Lyserson in favor.

2:04:23>> Thank you Virginia.

2:04:25>> Virginia Keiesler in favor.

2:04:27>> Thank you Virginia. Daniel Halago.

2:04:29>> Daniel Halago in favor.

2:04:30>> Thank you Daniel Miranda Cecil.

2:04:34>> Miranda Cecil in favor.

2:04:36>> Thank you. And Stephvening in favor.

2:04:38Vote is 50 in favor and the variance is

2:04:41granted. Uh thank you

2:04:44Mr. Dash.

2:04:47>> Uh thank you Mr. chair, members of the

2:04:49board, have a good evening.

2:04:50>> All right. Good night.

2:04:51>> Good night.

2:04:55>> All right. Uh, final

2:04:58application. Oh, this is 86. I'm sorry.

2:05:05And final application for this evening

2:05:08is case number BZA 121885.

2:05:15Uh, one Myrtle A. uh owners Fan Wang and

2:05:19Mark Wagner in care of uh Patrick W.

2:05:22Barrett III uh seeking a special permit

2:05:25for pre-existing non-conforming two

2:05:28family on a three street facing corner

2:05:31lot adding one additional floor

2:05:34following the footprint of the lot to

2:05:36add one additional unit of housing um

2:05:40citing uh section 5.31 table of

2:05:43dimensional requirements section

2:05:458.22.2.6

2:05:46C non-conforming structure and section

2:05:5010.4

2:05:51uh for a special permit. Uh Mr. Barrett.

2:06:03Hello again.

2:06:04>> Hello.

2:06:05>> Um so [clears throat]

2:06:07I'm I'm coming before you with a another

2:06:09corner lot and a special permit request.

2:06:11Um

2:06:13this project has had sort of a winding

2:06:15history. Um it came to me um a few

2:06:19months ago. It had already been through

2:06:21it is it is in the Mid Cambridge

2:06:23Conservation District. It had gone

2:06:24through an advisory review. Um the owner

2:06:28had proceeded on several building

2:06:30permits and the project had stalled

2:06:32somewhat. We included some photos of the

2:06:34existing site. You can see that it is

2:06:37uh in a state of mid construction.

2:06:40[clears throat] Um this case comes

2:06:42before you um as a special permit, not a

2:06:45variance. Um and cannot meet uh the the

2:06:51requirements of the ordinance and

2:06:53primarily because of the inability of

2:06:56corner lots to use uh the contextual

2:06:59setback. um in what the issue is and I

2:07:03think it's better illustrated um I'm

2:07:05going to share my screen again in terms

2:07:06of

2:07:08um what I'm talking about uh

2:07:18the here's here's the lot as it sits the

2:07:22none of this is changing the um setbacks

2:07:26everything remains the same but it is a

2:07:28three-facing lot uh three street facing

2:07:31lot and it does present itself with um

2:07:34you know natural difficulties um in in

2:07:37terms of its construction. This is how

2:07:38the building currently is in in play. It

2:07:42does have a building permit. It is

2:07:43proceeding on that building permit. Um,

2:07:46but the developer and owner who's with

2:07:48me tonight felt as though that the

2:07:50design itself is really being driven by

2:07:52zoning and not by what we would consider

2:07:55to be practical building design and

2:07:57urban planning uh methodology. Um, and

2:08:00the reason that we're here for you

2:08:03tonight is because here before you

2:08:04tonight is because the project as

2:08:07designed would be required to set back

2:08:09on the upper floors um to conform with

2:08:12the setback requirements where the

2:08:13existing structure would not. That

2:08:15really only exists at the uh for corner

2:08:19lots. This is exactly like 351 Cardinal

2:08:22Manderos which I brought to you I think

2:08:24almost exact same time last year. Um

2:08:28well, corner lots are fall is for corner

2:08:30lots. Um but um that is sort of what

2:08:37we're looking at in terms of the same

2:08:41same difficulty, same um

2:08:45uh

2:08:47practical abuing of the uh the

2:08:49ordinance. And I think, you know, the

2:08:50production of housing being paramount in

2:08:52the city of Cambridge, this allows for

2:08:54us to get to a more uniform looking

2:08:57building that conforms better with what

2:08:59surrounds it. Um, this is a side by side

2:09:02that I had the architect put together to

2:09:04show you sort of where we were, the

2:09:07existing house, what's been approved,

2:09:09and what we're currently building and

2:09:11what we'd like to build. And I think

2:09:12this is the best way I can illustrate

2:09:14the

2:09:17um maybe the imperfections of some of

2:09:20the results in the multif family housing

2:09:22zoning which um as I stated an hour and

2:09:25a half ago um you know in about maybe

2:09:27six or seven months this might actually

2:09:29be a mood issue anyway.

2:09:30>> Um but here but here we are. Um, and I

2:09:34think the developer who, you know, I

2:09:36think you have a few letters in

2:09:38opposition tonight and I we recognize

2:09:40that we also will have to go back before

2:09:42the Mid Cambridge Conservation District

2:09:45uh next month for uh some final review.

2:09:48Um, I think there's been agitation in

2:09:51terms of what we're building, how long

2:09:53it's taken to build. Um, you saw the

2:09:55condition of the site and I think I, you

2:09:56know, can sympathize with neighbors

2:09:58understanding why that might be

2:10:00problematic. But, you know, we're here

2:10:01tonight to try to get this project on

2:10:04the right track. Since my involvement,

2:10:06the building permits have been reduced

2:10:08from five to one. Um, and we are getting

2:10:11it sort of properly aligned in a

2:10:14regulatory fashion to um to proceed on

2:10:18on some development. I think what the

2:10:20developer owner is saying is that I

2:10:22think that in general it makes much more

2:10:24sense to design the building in a much

2:10:27more conforming knowledesque

2:10:30style than the um you pardon the

2:10:33expression layered wedding cake design

2:10:36that you see before you. Um here's some

2:10:40different angles of what we're talking

2:10:42about in terms of elevations uh approved

2:10:45and what we would uh like to build. This

2:10:48is the approved building. This is um the

2:10:52u the building we'd like to build. And I

2:10:55want to highlight that we are in the Mid

2:10:56Cambridge Conservation District. And

2:10:58while typically we would be under their

2:11:01jurisdiction for the advisory um

2:11:04building, we are approve we are we don't

2:11:06need approval to build this [music] for

2:11:08the Mid Cambridge Conservation District.

2:11:10We can proceed with design. Um, I think

2:11:13that's important because I think in

2:11:14general what our my client is trying to

2:11:17do is is a much better result in terms

2:11:19of uniformity with what's in the

2:11:21neighborhood. Um, here's another sort of

2:11:25example of that uh wedding cake setup.

2:11:29And um

2:11:32we could go through other elements of

2:11:34the plan, but I think at the heart of

2:11:35this case in particular is it's really a

2:11:37mirror image of what we looked at at 3

2:11:40uh 51 Carlas is trying to address this

2:11:43corner lot issue in a way that makes a

2:11:46little bit of design and development

2:11:47sense. It's certainly much more

2:11:48difficult to build a building this way.

2:11:50It doesn't this middle design doesn't

2:11:52really conform to anything that's in the

2:11:54neighborhood. and the, you know, the

2:11:57fourstory building does add an

2:11:59additional unit and does look a lot more

2:12:01like a building you you'd expect to see

2:12:03in this neighborhood. Um, you know,

2:12:05height is an issue. This was the same

2:12:07issue that came up in the Carlo Madero's

2:12:09case, but that's also a reflection of

2:12:12the the the new world we live in in

2:12:14terms of the multif family housing zone.

2:12:16We're four stories by right. It does

2:12:18require a little more involvement moving

2:12:20in terms of meetings, but but for the

2:12:23fact that this is in the Mid Cambridge

2:12:25Conservation District, you know, there

2:12:26wouldn't really be much more any more

2:12:28layers of review, but we will be going

2:12:30back to them. We have some requirements

2:12:32from them in terms of

2:12:34uh they wanted to see where the BCA

2:12:36stood on this um and uh some exterior uh

2:12:43details, etc. that they they normally

2:12:45take a look at. Um, we did provide some

2:12:52of the study. I think I think that's the

2:12:54end of that u presentation from the

2:12:56architect. The architect is with me

2:12:57tonight um Alpa um from Pesco Architects

2:13:01if there are questions of an

2:13:02architectural nature. I think um we did

2:13:05try to show what it looks like in in the

2:13:07in the natural setting as best we could.

2:13:10um which is a city which is a street

2:13:12line by triple deckers as well as two

2:13:15families along Magnolia that are you

2:13:17know 25 to 30 ft tall. Um that is in a

2:13:21nutshell what this case is. Um and I'm

2:13:24happy to take questions.

2:13:28Thank you Mr. Barrett. Um any questions

2:13:32from fellow board members?

2:13:41I think my only comment, Mr. Barrett, is

2:13:44if you could because the plans I have in

2:13:47the file don't really show that fourth

2:13:50floor plan. Um,

2:13:54or

2:13:57because it's it's a four unit structure,

2:14:02correct?

2:14:03>> It'll be a three-unit structure.

2:14:04>> Three units. Okay. So yeah and then uh

2:14:08the third to fourth floor is that third

2:14:11unit kind of two floors. Okay then we do

2:14:14we got the right drawings then

2:14:16>> um

2:14:22all right um any other comments from

2:14:25board members?

2:14:33>> Mr. Chair, you can just notate the

2:14:35supporting statement to correct the

2:14:37number of units. Is that correct?

2:14:39>> Yeah, that's I was a little

2:14:42So

2:14:42>> the supporting statement says four

2:14:44units,

2:14:54three units. Okay. Yep, we got that.

2:14:57Thanks. Uh

2:15:01since uh no comments for um questions

2:15:04from fellow board members, we'll move to

2:15:08um public comment. So we'll Oh, do we

2:15:10have some folks online? Okay, so we'll

2:15:12go to that first. Uh any members of the

2:15:15public who wish to speak should now

2:15:18click the icon at the bottom of your

2:15:19Zoom screen that says raise hand. If

2:15:22you're calling in by phone, you can

2:15:23raise your hand by pressing star9 and

2:15:26unmute or mute by pressing star six.

2:15:28I'll now ask staff to unmute the

2:15:30speakers one at a time. You should uh

2:15:34begin by saying your name and address

2:15:35and staff will confirm that we can hear

2:15:37you. After that, you will have up to

2:15:40three minutes to speak before I ask you

2:15:42to wrap up.

2:15:44>> Tia Chapman.

2:15:50>> Hello. U Mr. Chair and board members, I

2:15:53didn't hear about the three minute time

2:15:55limit with the other uh items on the

2:15:57agenda. Was that also the case and I

2:15:59just didn't hear it?

2:16:01>> Yes, we we try to keep it to three

2:16:03minutes. Um I think a few of the

2:16:05speakers on an earlier application spoke

2:16:08they went over a little bit, but uh you

2:16:11know, we

2:16:12>> okay,

2:16:12>> pretty flexible.

2:16:13>> I know uh from prior experience that

2:16:15attorney Barrett keeps track of time, so

2:16:18I'm already nervous.

2:16:20home.

2:16:21>> So, um we I think had some confusion

2:16:26first of all um in our neighborhood

2:16:29because just two weeks ago we all had a

2:16:32hearing on September 9th. Um, and so I

2:16:36think some people were feeling like they

2:16:38had already voiced their opposition then

2:16:42at that meeting which I think was before

2:16:43the historical commission and um we

2:16:47aren't represented by we don't have an

2:16:50attorney Barrett and um

2:16:53we I think we're feeling uh confused and

2:16:57then also at that same historical

2:16:59commission hearing uh attorney Barrett

2:17:02said that if we didn't uh if I

2:17:04understood correctly if we didn't go

2:17:06along with the historic proposition that

2:17:08this new proposal that was made on

2:17:10September 9th different from this that

2:17:13he already they already had by right to

2:17:15make this thing he described as the

2:17:17wedding cake. So we would get the

2:17:19wedding cake if we didn't go with this

2:17:22new his new proposal which I is I guess

2:17:26are now at the historic commission which

2:17:28is a different one which I'm confused. I

2:17:30don't know if that's I don't know what I

2:17:33think we're all feeling pretty confused.

2:17:36And so this is the wedding cake. And I

2:17:39don't I I don't I think what we lack, if

2:17:43you look at the yellow map with the

2:17:45yellow uh buildings in yellow, you can

2:17:48see how dense we are. We lack open

2:17:50spaces and our back windows. We already

2:17:53look out on Clabard. Um and we've been

2:17:55able to live with that. We stand cheek

2:17:57to gel with line street and on the other

2:18:00this uh is a corner on two streets. I

2:18:02heard attorney Barrett say three

2:18:03streets. It's just two streets and our

2:18:05one open space is at this corner where

2:18:08we see the sky things open up. We're a

2:18:10small street with only twotory. He keeps

2:18:13showing Magnolia, but you can see on

2:18:15Myrtle, we're very small twotory, very

2:18:19tiny one-way street. And

2:18:23uh this is uh the way I'm in favor of

2:18:26the wedding cake, and I know a lot of my

2:18:28neighbors are. It lets in the sun. This

2:18:30is going to block the open space. We

2:18:32already this property, one myrtle is

2:18:35takes up all the land virtually on its

2:18:38lot. It's already taking up all the

2:18:39land, but above it you have open space.

2:18:42Um, so that's been really important for

2:18:45this whole neighborhood that we have

2:18:46that area where things finally open up

2:18:49and the setbacks are a vital way to

2:18:51preserve what little open space we have.

2:18:53You can see how dense our corner of the

2:18:55city is. If you look at those yellow

2:18:57buildings on line and on Myrtle and on

2:19:00Roberts. Um, and so on a small site like

2:19:04this, which as I said takes up its

2:19:06entire uh, lot almost like the gentleman

2:19:09who was talking about extending his

2:19:11stairs, it takes up already all of its

2:19:14lot. And on a small site like this, even

2:19:16a few feet make a huge difference. Which

2:19:18is why even though it had a preservation

2:19:20award, I'm in favor of the wedding cake

2:19:22because it gives us our neighborhood. It

2:19:24gives us light. It's more in scale. Even

2:19:27if it's a wedding cake, it's more in

2:19:28scale with our small buildings on one

2:19:30Myrtle, I mean on Myrtle A. Um, and

2:19:33granting this permit would also damage

2:19:35our climate resiliency because despite

2:19:38the drawings because it sits and takes

2:19:40up its whole lot, there's very little

2:19:42space for landscaping. And if you've got

2:19:44these three units, well, these residents

2:19:46are going to need space for their if you

2:19:48could finish up.

2:19:49>> Recycling. I'm finishing up. Thanks. The

2:19:51the recycling bins and things. Where are

2:19:53those in the drawings? They have to have

2:19:55recycling, trash, compost. Three sets of

2:19:57those are going to barely fit. And I how

2:19:59are you going to be able to have the uh

2:20:01landscaping there? Um and then the

2:20:06um I feel as though uh we hear this word

2:20:08normalizing. He's going to normalize the

2:20:10building. Well, the original option

2:20:12they've already dug out the basement was

2:20:14to have this dormers and keep the roof

2:20:17line and still be able to increase to

2:20:19three units. Why have a fourth floor?

2:20:22The three units. They've got the

2:20:23basement. You can add dormers to the

2:20:25third floor. I I guess I I really

2:20:28strongly oppose something like this

2:20:30because

2:20:31four minutes profit and I think it's our

2:20:34job to think about what's good for the

2:20:36city, not what's just good for profit.

2:20:39>> Sorry for going over Thank you, Miss

2:20:42Chapman.

2:20:43>> Thank you for your time.

2:20:46>> Alberto Paratti.

2:20:51>> Yes. Hi. Thank you. Um uh thank you for

2:20:54thank you for giving us the opportunity

2:20:56to speak about this project. Um Alberto

2:20:59I live at six Myrtle Avenue so right

2:21:01across from right across from the

2:21:03property. Um I um actually to follow up

2:21:07it's a good segue on what Miss Chapman

2:21:09was just saying. There was a previous a

2:21:12previous project that didn't that didn't

2:21:14show up in the comparison that Barrett

2:21:17was u was showing. I don't know if you

2:21:19could scroll to page 24, 23, 24, and 25

2:21:25of um what you have right now.

2:21:29I guess maybe you have a different set

2:21:31of drawings than the ones that were

2:21:33posted in the city. It's the drawings

2:21:36that the original drawings from ABC

2:21:39design. So A21, A22, A23,

2:21:43which is exactly what Miss Chapman was

2:21:45talking about the the house that the

2:21:48propo the original proposal that was

2:21:52much more much more in um in keeping

2:21:55with with what Merl Avenue looks like um

2:21:59which is not the three decaries um that

2:22:03are on that are on Magnolia.

2:22:06Yeah, thank you. It's pages 23 24 25.

2:22:16>> This is Olivia T. Can I get the um the

2:22:19document page numbers again?

2:22:22>> 23, 24, and 25.

2:22:24>> They're drawings 821, 822.

2:22:27>> Okay.

2:22:28>> This is from the version that I

2:22:30downloaded from the the version

2:22:32availability from the city's website.

2:22:38Oh, way in the back.

2:22:41>> There you go.

2:22:42>> I got it.

2:22:42>> Yeah.

2:22:44>> All right. So, this was the original

2:22:45project u for this uh for this site uh

2:22:49way back I don't even remember at this

2:22:51point. Um back when the story was we're

2:22:54a family, we're moving in. We want to be

2:22:56part of this neighborhood. Um we're

2:22:58going to do this this work. And I think

2:23:00that this did not pass historical.

2:23:03Historical had a saying in projects back

2:23:06then. Didn't pass historical I believe

2:23:08was because of the raising of the roof

2:23:11line. Um and then when the and I believe

2:23:15that in coincidence with the with the

2:23:17zoning changes then that this became the

2:23:20wedding cake and now it's becoming the

2:23:22highrise that's uh that's being proposed

2:23:25right now. Right. So we are all in

2:23:27Cambridge. We're all uh for uh for more

2:23:31more housing, more affordable housing uh

2:23:33despite the fact that we're what the

2:23:35fourth or fifth densest uh city in

2:23:38America. But we also would love to to

2:23:42keep Cambridge what it is. Keep uh keep

2:23:46the keep it as a as a city that I would

2:23:50like my kids to come back when they're

2:23:53when they're adults when they're working

2:23:55or studying somewhere and feel that they

2:23:57belong and that they recognize their

2:23:58hometown as as the place the place where

2:24:01we grew up. We brought our kids home

2:24:03from Ker Hospital. They grew up playing

2:24:06at that intersection, every intersection

2:24:09in front of of one metro with all the

2:24:11other kids on my Avenue with the kids on

2:24:14Magnolia because this is a it's a family

2:24:16neighborhood. It's people who want to be

2:24:20who want to be Mr. Cambridge.

2:24:23>> I will. It's not a one we don't want

2:24:25Cambridge to become a one or two years

2:24:28residence while I'm working my tech job

2:24:32um and then I move away. So I oppose the

2:24:36project. I would like it to go back to

2:24:38the original project which was much more

2:24:41uh much more in keeping with what the

2:24:43street looks like.

2:24:44>> Thank you Mr. F.

2:24:45>> The wedding cake the wedding cake at

2:24:47least give us lets us keep some light.

2:24:50>> Thank you. Thank you for your time.

2:24:55>> That was it. Okay. Uh that was it for

2:24:57public comment online. Uh just running

2:25:00through the ledger here. uh

2:25:02correspondence, an email or letter from

2:25:07uh well quite a letter uh Mr. Oie Porat

2:25:12uh 24 Myrtle Avenue. Um

2:25:16he is against the application um citing

2:25:21uh establish one project, one unit count

2:25:24and a documented lawful baseline. Um

2:25:28just citing documentation

2:25:31um require corrected uh current survey

2:25:35and corrected dimensional information.

2:25:38Um

2:25:39also citing uh der determine actual

2:25:42total height and legal treatment of the

2:25:44head house. uh followed by uh comments

2:25:48regarding supply bicycle parking and rec

2:25:51reconcile the automobile site plans

2:25:55resolving basement flood resilience

2:25:57issues. uh demonstrate lawful open space

2:26:00accounting and coordinate building facil

2:26:03feasibility require dimension site

2:26:05accommodation exhibit. Uh and um

2:26:12I think uh a little more uh criticism of

2:26:16uh documentation

2:26:18uh and

2:26:21that um another um well Tia Miss Chapman

2:26:25uh wrote uh an email but we've heard her

2:26:28public comment today. um

2:26:32uh several uh emails from Miss Chapman

2:26:36and um uh including several photographs

2:26:39of kids uh playing in the neighborhood.

2:26:41Uh I believe that was it for uh

2:26:45correspondence. So we'll close uh public

2:26:49comment and uh move into deliberation.

2:26:52Uh any comments or thoughts from fellow

2:26:55board members?

2:27:00This is Wendy Lyserson.

2:27:04Um,

2:27:06I am profoundly disappointed um by what

2:27:09I've heard here tonight. I'm just going

2:27:12to say that um to hear that the

2:27:15neighbors in good faith

2:27:18evaluated a plan set as recently as

2:27:21September 9th that they're not seeing

2:27:23here and that though

2:27:27this is hearsay um but they have

2:27:30represented that they feel bullied as

2:27:33well as um to have been threatened by

2:27:36the developer that if you don't like

2:27:38what I want to push through the zoning

2:27:40forward. I will construct something that

2:27:43I think is not visually appealing that I

2:27:47will call a wedding cake.

2:27:49I think that if this is the pattern

2:27:53with which developers in the city are

2:27:55going to engage in what is supposed to

2:27:57be a good faith public discussion with

2:28:01the neighbors,

2:28:03I would not be surprised to see if the

2:28:05city council or voters

2:28:07decide that they don't want to continue

2:28:10to be development friendly in this way.

2:28:13Um I would like you to think about as

2:28:17the earlier case

2:28:19you also said take it or leave it

2:28:21basically to this board and I would be

2:28:26very disappointed to hear of future

2:28:28instances of that same pattern of a lack

2:28:30of good faith engagement with the

2:28:32neighbors.

2:28:34And I would encourage developers of all

2:28:36sorts to think about their legacy in the

2:28:39architecture that they are building. And

2:28:42that if they're going to say take it or

2:28:44leave it, I'll build something ugly if

2:28:45you don't like what I want so that I can

2:28:47get more profit. That's not a very good

2:28:49legacy to leave behind in this world in

2:28:52my opinion.

2:28:54Um, with regard to the legal criteria,

2:28:58I think that the neighbors have clearly

2:29:00said that this uh, special permit

2:29:03request would fail the second criteria

2:29:07that there would be an adverse impact

2:29:10on the neighborhood.

2:29:13Thank you.

2:29:15Or actually, I guess it would be the

2:29:17third criteria. Thank you.

2:29:21Any

2:29:24other comments, thoughts from fellow

2:29:26board members?

2:29:34A little participation would be good.

2:29:37Hello.

2:29:40Uh I am very familiar with this street

2:29:44and um just as a a person who lives in

2:29:48Cambridge. Um and

2:29:52I tend to agree with the abutters that

2:29:55while maybe triple deckers are common in

2:29:58this neighborhood, I don't think um

2:30:02necessarily triple deckers of this scale

2:30:05are. Um,

2:30:08and I think the

2:30:12the wedding cake, uh, for what it's

2:30:14worth, doesn't seem

2:30:16that unattractive to me. Um, but I do

2:30:20also recognize attorney Barrett's note

2:30:22that the city has made housing a

2:30:24priority. And if this is truly the way

2:30:26that

2:30:28um, we can make sure that there are

2:30:30three units versus two, then that's

2:30:33worth uh, worth considering as well. So,

2:30:37I think that gives us a lot to think

2:30:39about.

2:30:44>> Thank you, Miranda.

2:30:47Yeah, this is Daniel Delgo. Yeah, I'm

2:30:49torn on this one. Um I Yeah, I want

2:30:53better engagement with the neighbors. On

2:30:54the other hand, um yeah, I I see the

2:30:57need for housing, special permit. I

2:30:59don't see I know the neighborhood very

2:31:03uh pretty well. And uh

2:31:06I don't I don't see the proposed plan so

2:31:08out of keeping um with what's around

2:31:11there.

2:31:13But yeah, I I I I

2:31:16guess I I'm I'm kind of a little bit

2:31:18troubled about the the timeline, but

2:31:22but I'm otherwise disposed to it.

2:31:26>> Uh this is Virginia. Um, I

2:31:30would say I hold a similar view to

2:31:32Daniel where I'm not as opposed to the

2:31:36design or how it fits within the context

2:31:39of the neighborhood per se, but agreed

2:31:42regarding engagement with the neighbors

2:31:44and um wanting there to be a

2:31:49good and thoughtful process.

2:31:56>> Okay. Thank you, Virginia.

2:32:01Um, yeah. And I I also I I think and I

2:32:04know the zoning changes in in Cambridge

2:32:06have have really changed a lot of uh

2:32:10what you're seeing in neighborhoods

2:32:12getting built these days, but uh

2:32:15um I

2:32:21I think in terms of this particular corn

2:32:24a lot, it's something we should um

2:32:27you know

2:32:30see what works. uh for the neighbors

2:32:33while you're trying to uh maximize and

2:32:36and meet those needs uh that are listed

2:32:40by the city. Um

2:32:46>> Mr. Chair, this is Wendy Lyserson again.

2:32:48Um if we just simply adhere to the

2:32:50special permit criteria

2:32:53um first of all um

2:32:57whether the requirements of the

2:32:58ordinance cannot be met due to the size

2:33:00and shape of the lot. What would your

2:33:03your opinion be on that please fellow

2:33:05board members? We'll just go through the

2:33:07criteria.

2:33:11H

2:33:14>> I think that the requirements of the

2:33:16ordinance could be met um based on the

2:33:19size and shape of the lot because we've

2:33:21seen several proposals in which they

2:33:23were met.

2:33:28>> Okay. Um criteria. The second criteria

2:33:32is whether traffic generated or patterns

2:33:34of access or egress

2:33:37would not cause congestion or

2:33:38substantial change and established

2:33:40neighborhood character.

2:33:42Any comments from the board?

2:33:48I mean I I for me personally I I I don't

2:33:50I'm not um a problem. You know this is a

2:33:53dense neighborhood. is,

2:33:56you know, it's I'm sure a lot of people

2:33:57are taking public transit, biking, etc.

2:34:00as well. So, I don't know. I just don't

2:34:02see that as a as as an issue here

2:34:03personally.

2:34:05>> Anyone else?

2:34:07>> And I don't think that there's a the is

2:34:11an issue on that point.

2:34:14>> Okay. And I would just uh remind the

2:34:16board as we're looking at the supporting

2:34:18statement that both the original design

2:34:22which was more acceptable to the

2:34:24neighbors was three units and this uh

2:34:28new proposal is also three units. So

2:34:30there's no change in the housing stock

2:34:32from this proposal. um criteria. The

2:34:35third criteria, the continued operation

2:34:37of or the development of adjacent uses

2:34:40as permitted in the zoning ordinance

2:34:42would not be adversely affected by the

2:34:45nature of the proposed use for the

2:34:46following reasons. We've in my opinion

2:34:49heard from the public saying that the

2:34:52continued operation of adjacent uses

2:34:54would be adversely affected due to the

2:34:57lack of sunlight and other green space

2:35:00issues and circulation that was cited.

2:35:03Other members of the board, do you have

2:35:04an opinion?

2:35:12>> I tend to agree with what you've said

2:35:14there, Wendy. I think we've heard that

2:35:16um

2:35:18that there would be an adverse impact.

2:35:22Anyone else?

2:35:25>> I'd agree with that.

2:35:28The fourth criteria, nuisance or hazard

2:35:31would not be created to the detriment of

2:35:32the health, safety, and or welfare of

2:35:34the occupant of the proposed use or the

2:35:36citizens of the city. Does anyone have a

2:35:38comment on that one?

2:35:45>> I don't think that this would create a

2:35:47nuisance or a hazard based on what we've

2:35:48heard.

2:35:51>> Okay. The final criteria u for other

2:35:54reasons the proposed use would not

2:35:56impair the integrity of the district or

2:35:58adjoining district or otherwise dergate

2:36:00from the intent or purpose of this

2:36:01ordinance.

2:36:04Um so my opinion is um the paragraph

2:36:07here is talking about um housing. I know

2:36:12that Cambridge is encouraging increase

2:36:14in housing stock meaning the number of

2:36:17dwelling units available. This will not

2:36:18change the number of dwelling units

2:36:20available.

2:36:22And because two out of the five criteria

2:36:25that we are supposed to um evaluate um

2:36:29have not been met, I would deny the

2:36:31special permit. That's my opinion. Any

2:36:34members of the board want to comment on

2:36:36that final criteria and where they're

2:36:38leaning.

2:36:42>> So your side

2:36:43>> I also am leaning in favor.

2:36:46>> It's what? I'm sorry. I think

2:36:49I am also leaning I that was confusing

2:36:52language to use. I'm leaning towards

2:36:54denial um because this doesn't change

2:36:58the number of housing units. So, while I

2:37:00think that that is a compelling um idea,

2:37:03typically in a special permit scenario,

2:37:05if we're not getting any additional

2:37:07units and the neighbors are also

2:37:10um opposed to this configuration,

2:37:14whereas they wouldn't be opposed to a

2:37:15different configuration,

2:37:17I don't find it compelling that the city

2:37:19has prioritized housing.

2:37:27>> All right. So you're we're citing um

2:37:30section A and C

2:37:33um

2:37:36not meeting the criteria.

2:37:39>> That's my understanding, Mr. Chair.

2:37:41>> Okay.

2:37:44So um

2:37:48I I'd like to add we are actually

2:37:51increasing one unit. It is currently a

2:37:53two unit house and we are increasing it

2:37:57to three unit

2:38:00>> and the original proposal also created

2:38:03three units. Correct.

2:38:05>> No, the original proposal was a two

2:38:08unit. The approved building permit is a

2:38:11two unit only.

2:38:13>> And the wedding cake, will that be two

2:38:15or three units?

2:38:17>> Two units.

2:38:19Well, I still don't think that you've

2:38:20gotten over the fact that the neighbors

2:38:22are adversely affected. So, if you fail

2:38:25one criteria, that's enough.

2:38:27>> Completely object to this entire

2:38:29proceeding. The the approach from Miss

2:38:32Commissioner Lester has been nothing but

2:38:34insulting throughout my first process

2:38:36and now this. You've taken the word from

2:38:39neighbors at face value and you've

2:38:40thrown it back at us as if we've

2:38:42actually done something wrong. We

2:38:44haven't threatened anybody. We have a

2:38:46building permit. We're trying to make

2:38:48the condition better on the site. We

2:38:50have a two-unit project that has a

2:38:52building permit that's as of right.

2:38:55We're trying to add a third unit and and

2:38:57we're presenting a project that would

2:38:59otherwise be zoning compliant but for a

2:39:01setback. And I'm astounded by the

2:39:05approach of this board and their

2:39:08approach of me talking about legacy of

2:39:10developers.

2:39:11Is is is the intent of this board to

2:39:13make every case that comes before you

2:39:15rip for appeal?

2:39:17>> I'm asking with all due respect to you,

2:39:19Mr. Barrett,

2:39:22>> I'm I'm Please, you've asked you you've

2:39:24made your comment. I'd like to respond

2:39:26to you. I have nothing personal against

2:39:28you or this developer, but your um

2:39:32behavior with regarding the first case

2:39:35um made me frankly

2:39:38find it plausible to believe the

2:39:40experience of the neighbors

2:39:42uh who testified in this case. Now, I

2:39:45also said that it was hearsay, meaning I

2:39:47don't know whether it was true or not,

2:39:50but in every case of the zoning board,

2:39:53we listen to the neighbors and we weigh

2:39:55what the neighbors say. we don't go

2:39:57independently factf finding.

2:39:59Several neighbors said that they were

2:40:01adversely affected and I will seed the

2:40:03floor to the chair. Thank you Wendy. Um

2:40:06and Mr. Barrett the public comment is

2:40:10how we communicate with the neighbors in

2:40:14wherever an application is similar to

2:40:16the earlier application. Um and those

2:40:20were very compelling statements. So I

2:40:22mean in every case it depends on how the

2:40:26board sees uh other you know our fellow

2:40:29Cambridge well fellow residents uh and

2:40:34their opinions about it and we do filter

2:40:37that through. So I think when when our

2:40:39board uh feels uh they see um the issues

2:40:45that are being brought brought to light

2:40:47I that that is the purview of our review

2:40:50of this application. I

2:40:52>> I'm I'm well aware of how that process

2:40:54works and I've been doing this for a

2:40:55very long time. I know that interaction

2:40:57with the neighbors is paramount. I know

2:40:58that their opinions matter deeply. I

2:41:01also know that this process is always

2:41:03somewhat contentious. You just had a

2:41:04case with me about an hour ago where

2:41:06people on Hillard Street unanimously

2:41:09approve what we were doing. It shows we

2:41:10know how to do outreach. At least I know

2:41:12how to do it. In terms of this

2:41:13particular project, you've had two

2:41:15people speak against it. You've had, I

2:41:16think, one letter from one other person

2:41:18uh who's also a developer around the

2:41:20corner who just developed a project very

2:41:21similar to this one. Um at 351 Carlo

2:41:25Maderos, you had one person in in

2:41:26opposition. You approved that case. What

2:41:29I heard tonight though was not about

2:41:30this property was about me personally.

2:41:33Um, I heard I heard I heard something

2:41:36about legacy, which I'm not sure legacy

2:41:37of developers, legacy of MI, what that

2:41:39really means. I've heard that before.

2:41:40Um, and we have not brought something

2:41:42that is deeply contentious. This is a

2:41:44four story fourtory project and a

2:41:47predominantly threetory district. The

2:41:49zoning itself is in the in the project

2:41:51is going to be four stories no matter

2:41:52what we do. Now, we could introduce

2:41:54front decks to the building to maybe set

2:41:56it back a little bit if that's more

2:41:57palatable to the neighbors. I'm happy to

2:41:59take a look at a redesign of that. but

2:42:01to flatly deny a special permit simply

2:42:03because two neighbors showed up and said

2:42:04we're blocking their sunlight. This

2:42:06isn't uh uh Manchester by the Bay where

2:42:09we expect to have a view of the ocean.

2:42:11>> Mr. Barrett, you have the right to

2:42:13continue if you would like to.

2:42:14>> Please.

2:42:15>> Yeah, I I'm I'm just I'm trying to

2:42:17figure out and and Miss Lyster, I I have

2:42:20to say I I I'm probably going to file a

2:42:24complaint, [music] but I don't

2:42:26understand the personal issue. Um, but

2:42:28what I do understand is in the previous

2:42:30case, uh, there was a misstatement of

2:42:32law and we'll bring that up later down

2:42:35the road, but we had also vetted this

2:42:37process through ISD multiple times. So,

2:42:39either there's an a miscommunication

2:42:41between this board and ISD and what's

2:42:43zoning compliant or we have to figure

2:42:45out what that is. For this particular

2:42:47case, we are zoning compliant but for

2:42:49the setback issue and we are willing to

2:42:53work with the neighbors. we're willing

2:42:55to make changes if we if necessary, but

2:42:59a flatout denial of a special permit

2:43:01based on what we heard tonight is in my

2:43:04opinion, I've never I've never I've

2:43:05never seen the board do that. Um, and I

2:43:07I understand that, you know, some

2:43:09neighbors are upset, but to say that

2:43:11we're blocking out the sun, to say that

2:43:13we're creating an unsafe condition and

2:43:16and to accept those things without

2:43:18having seen any real valid proof, I'm

2:43:20kind of I'm curious as to why the

2:43:21board's so willing to accept that that

2:43:24testimony and not look at our design,

2:43:27our our shadow study, and look at the

2:43:30project as a whole and say largely that

2:43:32we're adding housing, which is something

2:43:34that is a goal. We are doing it in a way

2:43:36that is largely conforming with the

2:43:37neighborhood and we have open space on

2:43:40the site that's been brought up, but you

2:43:42can clearly see our open space plan. We

2:43:44have a very tiny lot. So, I'm not

2:43:46hearing that this is a bad project

2:43:48necessarily. I'm hearing that there's

2:43:49maybe some other issue and I I think

2:43:51that that's what I have an issue with.

2:43:56>> So, what I think and miss Mr. Barrett,

2:44:00please understand we're we're giving

2:44:02you, you know, the opportunity to

2:44:05deliberate with us in this case, you

2:44:07know, and um but I think that's the way

2:44:10our board it we we're going to make our

2:44:14decision. I mean, I'll make a motion

2:44:16that is in the affirmative

2:44:18and um that's up to board members to

2:44:22make a vote on what they believe is the

2:44:25right thing to do.

2:44:27>> Understood. I appreciate you allowing me

2:44:30a voice.

2:44:30>> Yeah. No, and I I mean I don't want to

2:44:32Yeah. No, it's not my intent to exclude

2:44:35people in the conversation. So, you

2:44:37know, I think uh I think um I mean

2:44:41that's what our next steps will be. So,

2:44:43um the chair

2:44:46uh will make a motion uh to grant a

2:44:49special permit from the requirements of

2:44:51the ordinance under sections uh 5.31,

2:44:558.22.2.

2:44:57C and 10.40

2:45:00special permit and um reviewing um

2:45:04responses uh for the supporting

2:45:08statement for the special permit that um

2:45:11a it appears the requirements of this

2:45:14ordinance cannot or will not be met. Um

2:45:20the requirements of the ordinance uh

2:45:23cannot be met due to the size and shape

2:45:25of the lot. Uh item B uh traffic

2:45:28generated or patterns of access or

2:45:31egress should it cause congestion,

2:45:33hazard or substantial change. Uh

2:45:35existing use is a two family home in a

2:45:38predominantly multif family district

2:45:40where cost composition is larger three

2:45:43units. Uh proposed uh use and increase

2:45:47to three unit uh well it's um

2:45:49maintaining three units and will not

2:45:52pose a substantial change to the

2:45:54existing built environment. It's an

2:45:56increase to three units.

2:45:58>> It's what? I'm sorry. Increase

2:45:59>> an increase. Increase to three units.

2:46:03>> Two three units. Okay. Increase to three

2:46:05units will not pose a substantial change

2:46:07to the existing built environment. Um

2:46:10item C, the continued operation of or

2:46:13the development of the adjacent uses as

2:46:15permitted in the zoning ordinance would

2:46:17be adversely affected. Uh the adjacent

2:46:20uses are the same use category as

2:46:22proposed and would be uniform and

2:46:24harmonious. uh dn nuisance or hazard

2:46:27would be created to the detriment of the

2:46:29health, safety or welfare of the

2:46:32occupant. Uh the proposed addition and

2:46:34renovation of the existing structure

2:46:37will bring the entire site up to

2:46:38Cambridge's rigorous code standards and

2:46:41clean up a site that has been run down

2:46:44through passage of time, creating a

2:46:45vibrant point to an otherwise awkward

2:46:48lot configuration. and e uh for other

2:46:51reasons. Uh the proposed use would

2:46:56impair the integrity of the district or

2:46:58adjoining districts. Uh Cambridge has

2:47:00committed itself to a building and

2:47:02housing and the rules rule changes that

2:47:05permit the expansion of existing two

2:47:07family structures are proof. This is

2:47:10exactly the type of development

2:47:11anticipated by the city of Cambridge and

2:47:14encouraged which is most recently cited

2:47:17in neighborhood and long-term planning

2:47:19presentations given on June 25th. Um and

2:47:23so by that finding they meet the

2:47:25criteria under sections 10.40 for

2:47:28special permit and further we

2:47:30incorporate the supporting statements

2:47:32and dimensional forms submitted as part

2:47:35of the application. And so on a voice

2:47:38vote, please, board members, uh, Wendy

2:47:41Lyserson.

2:47:42>> Mr. Chair, I think it's appropriate for

2:47:44me to recuse myself from this vote, uh,

2:47:48because, uh, the petitioners council

2:47:51believes that I cannot be objective. So,

2:47:54I will do that and allow my fellow board

2:47:55members.

2:47:55>> Understood. Thank you, Miss Lysen. Um,

2:47:58Virginia Keiesler.

2:48:01>> Virginia Keiesler in favor.

2:48:03Daniel Hadaga.

2:48:15>> Sorry about that. Daniel in favor.

2:48:17>> Uh, Miranda Cecil.

2:48:22>> Miranda Cecil opposed.

2:48:27>> And Stephen Ing uh opposed.

2:48:31So that's uh two opposed and two in

2:48:35favor, two opposed. Uh so is that the

2:48:39right count for

2:48:43>> Okay. the special permit is denied and

2:48:47um so I'll also move that

2:48:51um I have to cite the reasons right for

2:48:56um

2:48:59uh so the denial is based upon um item A

2:49:05that uh the requirements of this

2:49:09ordinance

2:49:11could be met uh due to size and shape of

2:49:16the lot

2:49:20as well as

2:49:22uh section C the continued operation of

2:49:31right development of the adjacent uses

2:49:34as permitted in the zoning ordinance

2:49:35would be adversely affected. Um and

2:49:43We would be ad this project would

2:49:45adversely affect uh the neighborhood um

2:49:48in through a variety of environmental

2:49:51condition impacts such as sunlight and

2:49:58an open space.

2:50:01So and then I just asked for the board

2:50:05to approve that. Right.

2:50:07>> Okay. So based on those criteria, uh I

2:50:11asked the board to uh approve

2:50:16uh

2:50:19those reasons for denial. So by a voice

2:50:22vote uh with Wendy Lyserson uh recusing

2:50:25herself uh Virginia Keysler.

2:50:30>> Uh I'm sorry. So So although I voted in

2:50:32favor, I'm just voting now on approving

2:50:35our the

2:50:36>> the reasons. Yeah.

2:50:37>> Okay. Um, uh, yes, in in favor.

2:50:41>> Thank you. Uh, Daniel Hago.

2:50:43>> Daniel Halgo in favor.

2:50:45>> Thank you. Uh, Miranda Cecil.

2:50:49>> Miranda Cecil in favor.

2:50:51>> And Stephen Ing in favor. So

2:50:58that closes our

2:51:00uh agenda for this evening.

2:51:03>> Thank you.

2:51:04>> Thank you, Mr. Chair.